exw-p006-0000-gs-shc-mt-00003 method statement for surveying and setting out rev.1

Upload: syed-umair-hashmi

Post on 02-Jun-2018

287 views

Category:

Documents


4 download

TRANSCRIPT

  • 8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1

    1/39

    ~ o o ~ ~ ~ ~ ~ m ~ 4 ~ ~ ~ ~ ~ ~ ~ ; , & ~

    SINOHYDRO GROUP LIMITED

    Doha Expressway (Package 6

    East Industrial Road Interchanges at Intersection with Street

    10

    and Street

    23

    Contact No. C2011/085

    Document No. EXW POOS 0000 GSSHC MT-00003

    Method Statement

    for

    Surveying and Setting

    Out

    1 13-May-12 Comply the comments from Parsons dated 14-Apr-12

    0

    4-Mar-12 Submittal

    Revision Date Reason

    for

    Issue

    Contractor Check l s t

    Reviewed y

    Checked y Approved

    by

    Luo, Tao Mukattash, Mahran

    Sun, Jinhui

    Consultant Comments

    o Approved o Approved with Comments o

    Approved

    Engineer s Representative

    Date

    Doha - Stateof Qa tar

    Tel 97 4-44126471

    Fax

    974-44 126471 wwwsmohydrocom

  • 8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1

    2/39

    SINOHYDRO GROUP LIMITED

    Doha ExpresswayPackage 6

    East Industrial Road Interchanges at Intersection with Street 10 and Street 23Contact No. C2011/085

    Doha State of Qatar Tel: +974-44126471Fax: +974-44126471 www.sinohydro.com

    Submittal Information

    1. Document NumberEXW-P006-0000-GS-SHC-MT-00003

    2. DescriptionMethod Statement for Surveying and Setting Out

    3. Pages39

    4. RevisionRev.1

    5. Reference NumberNil

    6. Country of OriginQatar

    7. BOQ Ref.1.05

    8. Specification Ref.QCS 2010, Section 1, Part 13 & 15

  • 8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1

    3/39

    SINOHYDRO GROUP LIMITED

    Doha ExpresswayPackage 6

    East Industrial Road Interchanges at Intersection with Street 10 and Street 23Contact No. C2011/085

    Doha State of Qatar Tel: +974-44126471Fax: +974-44126471 www.sinohydro.com

    Index

    1. General Description of Package 6 Project

    2. Purpose and Scope of Work

    3. Specification and Standard

    4. Abbreviations

    5. Utilization of Existing Information

    6. Manpower

    7. Equipment

    8. General Surveying Method

    9. Process of Survey Works

    10. Quality Assurance Procedure

    11. Safety and Health Plan for survey works

    12. Inspection & Testing

    13. Appendix

    Appendix 1. List of Survey Equipment (Used on P6 Site)

    Appendix 2.Inspection for formation level/base slab/roof slab/backfilling surface of sheet

    Appendix 3. Inspection for formation level/base slab/roof slab/backfilling surface drawing

    Appendix 4. Setting Out for excavation sheet

  • 8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1

    4/39

    SINOHYDRO GROUP LIMITED

    Doha ExpresswayPackage 6

    East Industrial Road Interchanges at Intersection with Street 10 and Street 23Contact No. C2011/085

    Doha State of Qatar Tel: +974-44126471Fax: +974-44126471 www.sinohydro.com

    Appendix 5. Manhole/chamber inspection for base slab level sheet

    Appendix 6. Inspection for level of the installed pipeline sheet

    Appendix 7. Formwork checking for kerb blinding

    Appendix 8 Survey data for compacted ground/sub-grade/sub-base

    Appendix9Inspection for kerb stone sheet

    Appendix10Inspection deviation drawing for kerb stone

  • 8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1

    5/39

    Sinohydro Group LimitedDoha Expressway Package 6 Method Statement for Surveying and Setting Out

    EXW-P006-0000-GS-SHC-MT-00003 Rev.1 12 May 2012 Page 1 of 35

    1 General Descr ipt ion of Package 6 Project

    Package 6 of the Doha Expressway mainly covers the existing East Industrial Road

    Alignment. The section of the road included in this contract, starts almost 850 m south of

    the Industrial Roundabout up to its junction with the extension of Al Muntazah Street 33

    with a total length of about 3.5 km.

    The scope of work includes the upgrading of the existing East Industrial Road to provide a

    three lane in each direction for the mainline traffic. The local traffic will be served through a

    continuous service roads network providing safe and efficient movement between the

    main line traffic to the adjacent existing facilities along the route. scope of works include:

    a) Roads

    b) Junctions and interchanges

    c) Hard and soft landscape

    d) Potable Water supply and reticulation systems

    e) Irrigation supply and distribution systems

    f) Wastewater system

    g) Surface and ground water drainage system.

    h) Electrical supply and distribution networks including 66/11 kV

    i) Telecommunications and ELV duct network

    j) Road and amenity lighting

    k) Traffic control and street signs

    2 Purpose and Scope of Works

    2.1 Purpose

    This plan provides the survey methodology and inspection scope adopted by Sinohydro

    for Survey Works.

    2.2 Scope of Works

    1) Benchmarks

    2) Earthworks

    3) Concrete Works

    4) Manhole and Chamber

  • 8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1

    6/39

    Sinohydro Group LimitedDoha Expressway Package 6 Method Statement for Surveying and Setting Out

    EXW-P006-0000-GS-SHC-MT-00003 Rev.1 12 May 2012 Page 2 of 35

    5) Pipeline Works

    6) Road Works

    3 Specification and Standard

    Unless otherwise provided or required by the Engineer, following standards and

    specifications shall be used in performing survey works:

    a) Basic survey data source: Qatar National Grid (QNG) and Qatar National Height

    Datum (QNHD)

    b) Qatar Construction Specification 2010

    c) Qatar Survey Manual

    d) Project General Specification

    e) Other Survey Specification

    f) Information and document of Engineer

    4 Abbreviations

    The following abbreviations are used in this Plan.

    GPS Global Position System

    GIS Geographic information system

    QNG Qatar National Grid

    QNHD Qatar National Height Datum

    TGO Trimble Geomatics Office

    TBC Trimble Business Center

    LGO LEICA Geo Office

    RTK Real Time Kinematic

    RFI Request for Inspection

  • 8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1

    7/39

    Sinohydro Group LimitedDoha Expressway Package 6 Method Statement for Surveying and Setting Out

    EXW-P006-0000-GS-SHC-MT-00003 Rev.1 12 May 2012 Page 3 of 35

    5 Utilization of Existing Information

    Qatar National Benchmarks will be the basis for survey works, Benchmarks provided by

    center for GIS. Details please see Table 1 and Appendix 11

    Table 1

    Point No.Horizontal Coordinates (QNG95) Vertical (QNHD95)

    Easting Northing Used Elevation

    570001 224096.741 382207.121 19.481

    560046 223366.897 383367.888 20.618

    560080 223109.127 383197.218 22.054

    560047 222681.230 383860.419 ---------

    560048 222940.056 384007.725 ---------

    560061 222591.112 384553.745 ---------

    560062 222327.402 384396.843 ---------

    Before starting survey works,every Qatar national benchmark will be checked. Accroding

    checked result some benchmark not ues for this survey works.Benchmark of the above

    table is the first class control point for the construction. Some new benchmark will be

    established base on the condition of site survey during construction.

    6 Manpower

    Total 5 personnel are involved in this work. According to the site actual situation, It

    increase suitably with the reduction surveyor. Details please see Table 2.

    6.1 List of Personnel

    Table 2S/N Name Age

    WorkExperience

    Position

    1 Wang Shaolin 49 30 Survey Manager

    2 Zhang jisheng 43 20 Site Survey Chief

    3 Bao Yanjie 31 8 Office Survey Chief

    4 Qi Wanyi 25 2 Land Surveyor

    5 Shen Jianchao 25 2 Land Surveyor

  • 8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1

    8/39

    Sinohydro Group LimitedDoha Expressway Package 6 Method Statement for Surveying and Setting Out

    EXW-P006-0000-GS-SHC-MT-00003 Rev.1 12 May 2012 Page 4 of 35

    6.2 Organization Chart

    7 Equipment

    7.1 Survey Instrument

    The following survey instrument should be involved in the site survey works.

    a) GPS Receiver 2 unit

    b) Total Station 1 unit

    c) Electronic Level 1 unit

    d) Automatic Level 1 unit

    According to the actual site situation, It increase suitably with the reduction survey

    instrument. Survey instrument should be regular get of calibration certificate.

    7.2 Survey Software

    The following software should be involved in the survey works.

    a) Trimble Geomatics Office (TGO)

    b) Trimble Business Center (TBC)

    c) LEICA Geo Office (LGO)

    d) AutoCAD

    e) Nikon Data Transfer

    Survey ManagerWang ShaoLin

    Site SurveyChief

    Zhang JiSheng

    Office SurveyChief

    Bao YanJie

    Site Survey Team

    Shen JianChao,Qi WanYi

    Office Surveyor

    Shen JianChao,Qi WanYi

  • 8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1

    9/39

    Sinohydro Group LimitedDoha Expressway Package 6 Method Statement for Surveying and Setting Out

    EXW-P006-0000-GS-SHC-MT-00003 Rev.1 12 May 2012 Page 5 of 35

    7.3 Other Equipment

    According to work requirement, Computer and site vehicle will be involved in the survey

    works. Details equipment info please see appendix 1. List of Survey Equipment (Used on

    P6 Site).

    8 General Surveying Method

    8.1 Surveying Method for GPS

    8.1.1 Static Survey

    GPS static measurements, is the use of measurement-based GPS receivers to locate a

    measurement. Mainly used to create various kinds of control net. Static GPS

    measurements carried out that the GPS receiver antenna in the location of the observation

    process is static, in data processing, it will be the location of the antenna as a receiver

    does not change over time, the amount of change, through the received satellite data to

    seek a change in the coordinates of points to be determined. In the measurement, GPS

    static measurements of the specific observation model is more than one receiver at

    different stations on the static synchronous observation time from 20 minutes to 10 hours

    range.Relevant Technical Index

    No.s of observation session1.8

    Length of observation session: 25 minutes

    Valid observation satellite:4 pcs

    Geometry pattern strength PDOP6

    Satellite height angle: 15

    Data collection interval 15s

    8.1.2 RTK Survey

    Set up GPS base station on a benchmark. The tripod is erected on the benchmark and

    strictly centered. Antenna installed, Input point numbers and coordinates. And at least two

    benchmarks shall be surveyed for checking purpose. The two control-benchmarks will be

    surveyed at least 5 sec.

  • 8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1

    10/39

    Sinohydro Group LimitedDoha Expressway Package 6 Method Statement for Surveying and Setting Out

    EXW-P006-0000-GS-SHC-MT-00003 Rev.1 12 May 2012 Page 6 of 35

    8.2 Surveying Method for Total Station

    8.2.1 Fixed Station

    Set up total station on a know benchmark. The tripod is erected on the benchmark and

    strictly centered. Input station and backsight point number and coordinates, and input

    instrument height. Observation backsight point and measurement coordinates record, and

    checking other benchmarks. If checking point coordinates exceed 10mm shall be re-set up

    station.

    The fixed station relevant Technical Index, please as following Figure1:Sketch of Fixed

    Station.

    Distance of survey point Distance of BS.point

    Accuracy of Check point 10 mm

    Figure1: Sketch of Fixed Station

    8.2.2 Free Station

    Set up total station on anywhere and strictly leveling. At least input two backsight point

    number and coordinates. Observation backsight point and measurement coordinates

    record,and checking other benchmarks. If checking point coordinates exceed 10mm shall

    be re-set up station.

    The free station relevant Technical Index, please as following Figure2:Sketch of Free

  • 8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1

    11/39

    Sinohydro Group LimitedDoha Expressway Package 6 Method Statement for Surveying and Setting Out

    EXW-P006-0000-GS-SHC-MT-00003 Rev.1 12 May 2012 Page 7 of 35

    Station.

    Angle r is 30~ 150

    Distance to a and b700 m

    Distance of survey point Distance of BS.point

    Accuracy of Check point 10 mm between 90~ 190from BS. Point

    Points surveyed from a free station shall be placed in site or here the polygon

    between the known points used for determine the free station point.

    Figure2: Sketch of Free Station

    8.3 Surveying Method for Leveling

    8.3.1 Closed Leveling

    From the known elevation point of the beginning, and finally closed in fact point to the

    standard route. Single survey and middle thread reading method was adopted for the

    leveling survey, the sequence of reading is back-front-front-back. The reading is saved to

    the five places of decimal.

    8.3.2 Annexed leveling

    From the known elevation point of beginning and end another known elevation point of

    standard route. Single survey and middle thread reading method was adopted for the

    leveling survey, the sequence of reading is back-front-front-back. The reading is saved to

    the five places of decimal.

  • 8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1

    12/39

    Sinohydro Group LimitedDoha Expressway Package 6 Method Statement for Surveying and Setting Out

    EXW-P006-0000-GS-SHC-MT-00003 Rev.1 12 May 2012 Page 8 of 35

    8.4 The Detailed Survey Procedure

    If the control / check survey shows that the result does not comply with the tolerance, the

    responsible engineer in the construction or QA/QC group shall be informed immediately.

    The result shall be submitted for the Engineer accept as soon as it have been completed.

    RFI from QA/QCDepartment

    Setting-Out orInspection

    Uesing GPS,Total

    Station or Leveling for

    Setting-out/Inspection

    Transfer DesignCoordinates to

    GPS/Total Station

    Approved ShopDrawings

    Download GPS,Totalstation or Leveling

    survey raw data

    Prepare data to sheet andautocad drawing (please see

    appendix)

    Hand over hard copyand soft copy to

    QA/QC

    Not OK

    Hand over hard copy andsoft copy to Engineer

    acceptance

    Not OK

    Engineer ApprovedAnd return to QA/QC

  • 8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1

    13/39

    Sinohydro Group LimitedDoha Expressway Package 6 Method Statement for Surveying and Setting Out

    EXW-P006-0000-GS-SHC-MT-00003 Rev.1 12 May 2012 Page 9 of 35

    9 Process of Survey Works

    9.1 Benchmarks

    9.1.1 Temporary Benchmarks

    a) Survey used instruments

    GPS and total station should be adopted for horizontal coordinates. Total station and level

    instrument should be adopted for vertical.

    b) Survey Method

    Horizontal control should be established by GPS static survey, opening and closing

    traverses, resection, intersection, free-station etc.

    Vertical control should be established by closed and annexed leveling line, total stationtriangulation etc.

    c) Tolerance

    Horizontal : Points position 10mm, relative total length closing error of traverse 1/35000.

    Vertical : 4 L mm (where L is the distance leveled in kilometers).

    d) Results Submit

    A RFI should be submitted for engineer acceptance, RFI including temporary benchmarks

    results, calculation processing for Horizontal and vertical.

    9.1.2 Maintenance and Monitoring for Benchmarks

    Site surveyors should be regular maintenance and monitoring the site benchmarks,

    Maintenance including point name, safety fence etc. Monitoring including horizontal and

    vertical coordinates checked.

    a) Monitoring Time

    Horizontal monitoring frequency: should be carried out every six months

    Vertical monitoring frequency: should be carried out every three months.

    b) Used Instrument

    Horizontal check should be used RTK-GPS

    Vertical check should be used level instrument.

    c) Checking Method

    Horizontal coordinates checking method: Set up GPS base station on a national

    benchmark560046provided by center for GIS. The tripod is erected on the benchmark

    and strictly centered. Antenna installed. Input point numbers for each point .Two groups of

  • 8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1

    14/39

    Sinohydro Group LimitedDoha Expressway Package 6 Method Statement for Surveying and Setting Out

    EXW-P006-0000-GS-SHC-MT-00003 Rev.1 12 May 2012 Page 10 of 35

    data were measured on each points. With min. 20 minute interval or counter check. The

    observation section were not less than 5 second and data were recorded .

    Vertical elevation checking method: One closed leveling line origins and terminates on the

    national benchmark 560046, elevation is based leveling 570001 and 560046. Single

    survey and middle thread reading method was adopted for the leveling survey, the

    sequence of reading is back-front-front-back. The reading is saved to the five places of

    decimal. Relevant specifications were followed in the progress of survey.

    d) Tolerance

    Horizontal : Points position 20mm+1ppm

    Vertical : 4 L mm (where L is the distance leveled in kilometers).

    e) Results Submit shall be submitted for engineer

    acceptance.

    9.2 Earthworks

    9.2.1 Setting-Out for Excavation

    a) Used Instrument

    Horizontal setting-out should be used RTK-GPS or Total Station.

    b) Setting-out Method

    The excavation coordinates for center line, boundary line and key points from the

    approved shop drawing, are transfer into the GPS data collector or total station. The

    setting out points shall be show at intervals of not more than 25m along the setting out line.

    But also every key point must be staked out.

    c) Tolerance

    Setting-out points horizontal tolerance 50mm.d) Results Submit

    A RFI should be submitted for engineer acceptance, RFI including deviation drawing,

    survey data and soft copy.

    9.2.2 Final Survey for Formation Level

    a) Used Instrument

    Horizontal checked should be used RTK-GPS or Total Station

    Vertical checked should be used RTK-GPS, Total Station or Level Insrument.b) Checking Methods

  • 8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1

    15/39

    Sinohydro Group LimitedDoha Expressway Package 6 Method Statement for Surveying and Setting Out

    EXW-P006-0000-GS-SHC-MT-00003 Rev.1 12 May 2012 Page 11 of 35

    Formation level checked for pipeline: A point surveyed / checked every 10 m along the

    centerlines.

    Formation level checked for concrete works

    Building: Max grid of 10m x 10m,and every key point must be checked.

    c) Tolerance

    Horizontal : 50mm, Vertical : - 150mm / +10mm.

    d) Results Submit

    A RFI should be submitted for engineer acceptance, RFI including deviation drawing,

    survey data and soft copy.

    9.3 Concrete Works

    9.3.1 Blinding

    Setting-out for Blinding

    a) Used Instrument

    RTK-GPS (RTK-GPS only horizontal and vertical ues level instrument) or Total Station

    should be adopted for this works.

    b) Setting-out Method

    Setting-out coordinates for centerline, boundary lines and key points for blinding, screed,base slab, wall and roof slab from the approved shop drawing (please see appendix). are

    transfer into the GPS data collector or total station. In each section min. 6 point shall be

    marked / staked out. But also every key point must be staked out.

    c) Tolerance

    Horizontal : 20mm, Vertical : 10mm.

    9.3.2 Base Slab

    Setting-out for Base Slab

    a) Used Instrument

    Total station should be adopted for this works.

    b) Setting-out Method

    Setting-out base slab method is the same as the blinding method.

    c) Tolerance

    Horizontal : 10mm, Vertical : 10mm.

    d) Results SubmitA RFI should be submitted for engineer acceptance, RFI including deviation drawing,

  • 8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1

    16/39

    Sinohydro Group LimitedDoha Expressway Package 6 Method Statement for Surveying and Setting Out

    EXW-P006-0000-GS-SHC-MT-00003 Rev.1 12 May 2012 Page 12 of 35

    survey data and soft copy.

    9.3.3 Wall and Column

    Setting-out for Wall and Columna) Used Instrument

    Total station and level instrument should be adopted for this works.

    b) Setting-out Method

    Setting-out wall and column method is the same as the blinding method.

    c) Tolerance

    Horizontal : 10mm, Vertical : 10mm.

    d) Results Submit

    A RFI should be submitted for engineer acceptance, RFI including deviation drawing,

    survey data and soft copy.

    9.3.4 Roof Slab

    Setting-out for Floor and Roof Slab

    a) Used Instrument

    Total station and level instrument should be adopted for this works.

    b) Setting-out Method

    Setting-out roof slab method same to as blinding method.

    c) Tolerance

    Horizontal : 10mm, Vertical : 10mm.

    Random check can be done any time by SST.

    9.3.5 Inspection after formworks completed

    a) Used Instrument

    Total station and level instrument should be adopted for this works.b) Inspection Method

    After formworks completed, survey actual horizontal coordinates and level for boundary

    lines and key point. Comparison between the checked Survey Results and the design

    Results. Where the difference between checked Survey Results and design Results

    not exceed the tolerance the formworks is ok, if exceed the tolerance the formworks shall

    be adjusted.

    c) Tolerance

    Horizontal : 10mm Vertical : 10mm.

  • 8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1

    17/39

    Sinohydro Group LimitedDoha Expressway Package 6 Method Statement for Surveying and Setting Out

    EXW-P006-0000-GS-SHC-MT-00003 Rev.1 12 May 2012 Page 13 of 35

    Random check can be done any time by SST.

    d) Results Submit

    Deviation drawings, survey data should be submitted for engineer acceptance

    9.3.6 Elevation Checking for Roof Slab (final surface)

    a) Used Instrument

    Total station and level instrument should be adopted for this works.

    b) Checking Method

    Elevation check for roof slab method same to as elevation check for screed method.

    c) Tolerance

    Vertical : 10mm.

    d) Results Submit

    A RFI should be submitted for engineer acceptance, RFI including deviation drawing,

    survey data and soft copy.

    9.4 Manhole and Chamber

    9.4.1 Blinding

    Setting-out for Blinding

    a) Used Instrument

    RTK-GPS or Total Station should be adopted for this works.

    b) Setting-out Method

    Setting-out coordinates for centerline, boundary lines and key points from the approved

    shop drawing, are transfered into GPS data collector or total station. But also every key

    point must be staked out.

    c) Tolerance

    Horizontal : 20mm, Vertical : 10mm.

    9.4.2 Base Slab

    9.4.2.1 Setting-out for manhole and chamber position

    a) Used Instrument

    Total Station should be adopted for this works.

    b) Setting-out MethodSetting-out coordinates for manhole and chamber from the approved shop drawing, are

  • 8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1

    18/39

    Sinohydro Group LimitedDoha Expressway Package 6 Method Statement for Surveying and Setting Out

    EXW-P006-0000-GS-SHC-MT-00003 Rev.1 12 May 2012 Page 14 of 35

    transfered into total station, Site surveyor shall be setting-out manhole and chamber.

    c) Tolerance

    Horizontal : 20mm.

    d) Results Submit

    A RFI should be submitted for engineer acceptance, RFI including deviation drawing,

    survey data and soft copy.

    9.4.2.2 Elevation Check for Base Slab

    a) Used Instrument

    Total station and level instrument should be adopted for this works.

    b) Checking Method

    Every manhole and chamber center points and boundary points are checked.

    c) Tolerance

    Storm Water Vertical : - 30mm / +10mm

    Sewer Water Vertical : 10mm.

    d) Results Submit

    A RFI should be submitted for engineer acceptance, RFI including checked drawing,

    survey data and soft copy.

    9.4.3 Manhole and Chamber Cover

    Cover level checked after manhole and chamber completed.

    a) Used Instrument

    Total station and level instrument should be adopted for this works.

    b) Checking Method

    Every manhole and chamber cover center points shall be checking.

    c) Tolerance

    Vertical : 10mm.

    d) Results Submit

    A RFI should be submitted for engineer acceptance, RFI including checked drawing,

    survey data and soft copy.

    9.5 Pipeline Works

    9.5.1 Setting out for pipeline

  • 8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1

    19/39

    Sinohydro Group LimitedDoha Expressway Package 6 Method Statement for Surveying and Setting Out

    EXW-P006-0000-GS-SHC-MT-00003 Rev.1 12 May 2012 Page 15 of 35

    a) Used Instrument

    RTK-GPS and Total station should be adopted for this works.

    b) Setting out method

    Setting out method for pipeline work is to set out a point every 10m along the centerlines.

    and key point must be staked out.

    c) Tolerance

    Wastewater pipeline: Horizontal tolerance: Pipe diameter 800mm: 20mm, 800mm:

    30mm.

    Storm pipeline: Horizontal tolerance : Pipe diameter 800mm: 20mm, 800mm:

    30mm.

    Irrigation pipeline: Horizontal tolerance : 100mm.

    Potable Water pipeline: Horizontal tolerance : 100mm.

    9.5.2 Wastewater Pipeline

    Sewer pipeline elevation check after installation.

    a) Used Instrument

    Total station and level instrument should be adopted for this works.

    b) Checking Method

    Pipeline between two manhole or chamber is checked, Distance between point surveyed

    shall not exceed 10 m along the centerlines.

    c) Tolerance

    Pipe diameter 800mm, Horizontal : 20mm, Vertical : 10mm.

    Pipe diameter 800mm, Horizontal : 30mm, Vertical : 10mm.

    d) Results Submit

    A RFI should be submitted for engineer acceptance, RFI including deviation drawing,

    survey data and soft copy.

    9.5.3 Storm Pipeline

    Storm pipeline elevation check after installation.

    a) Used Instrument

    Total station and level instrument should be adopted for this works.

    b) Checking Method

    Checking method for storm pipelines is the same as checking method Sewer Pipelines.c) Tolerance

  • 8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1

    20/39

    Sinohydro Group LimitedDoha Expressway Package 6 Method Statement for Surveying and Setting Out

    EXW-P006-0000-GS-SHC-MT-00003 Rev.1 12 May 2012 Page 16 of 35

    Pipe diameter 800mm, Horizontal : 20mm, Vertical : 10mm.

    Pipe diameter 800mm, Horizontal : 30mm, Vertical : 10mm.

    d) Results Submit

    A RFI should be submitted for engineer acceptance, RFI including deviation drawing,

    survey data and soft copy.

    9.5.4 Irrigation Pipeline

    Irrigation pipeline elevation check after installation.

    a) Used Instrument

    RTK-GPS and Total station should be adopted for this works.

    b) Checking MethodChecking method for irrigation pipelines is to survey a point every 10m-20m along the

    centerlines. Key point must be checked.

    c) Tolerance

    Horizontal : 100mm, Vertical : 25mm.

    d) Results Submit

    A RFI should be submitted for engineer acceptance, RFI including deviation drawing,

    survey data and soft copy.

    9.5.5 Potable Water Pipeline

    Potable Water pipeline elevation check after installation.

    a) Used Instrument

    RTK-GPS and Total station should be adopted for this works.

    b) Checking Method

    Checking method for potable water is the same as the checking method for irrigation pipe.

    c) Tolerance

    Horizontal : 100mm, Vertical : 25mm.

    d) Results Submit

    A RFI should be submitted for engineer acceptance, RFI including deviation drawing,

    survey data and soft copy.

    9.6 Road Works

    9.6.1 Setting out and OGL survey of Road works

  • 8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1

    21/39

    Sinohydro Group LimitedDoha Expressway Package 6 Method Statement for Surveying and Setting Out

    EXW-P006-0000-GS-SHC-MT-00003 Rev.1 12 May 2012 Page 17 of 35

    a) Used Instrument

    RTK-GPS should be adopted for this works.

    b) Survey Method

    Setting-out Method: Coordinates for centerline, boundary lines and key points from the

    approved shop drawing, are transfered into GPS data collector. Center line and both

    boundary lines shall be show at intervals of not more than 25m, and every key point must

    be staked out.

    OGL Survey Method: Each cross section not more than 25 m and every cross section for 5

    point shall be survey. Every cross section survey width exceed road design width.

    c) Tolerance

    Setting-Out Horizontal : 20mm.d) Results Submit

    A RFI should be submitted for engineer acceptance, RFI including deviation drawing,

    survey data and soft copy.

    9.6.2 Survey inspection of compacted grounda) Used Instrument

    RTK-GPS should be adopted for this works.

    b) Inspection Method

    Each cross section not more than 25 m and every cross section for 4~6 points shall be

    survey. Every cross section survey width exceed road design width. Details please see

    appendix.10.

    c) Tolerance

    Horizontal : 20mm, Vertical : 30mm.

    d) Results Submit

    A RFI should be submitted for engineer acceptance, RFI including survey data and

    deviation.

    9.6.3 Survey inspection for formation level (final layer of sub-grade)a) Used Instrument

    Leveling Instrument and Total Station should be adopted for this works.

    b) Inspection Method

    Each cross section not more than 25 m, every cross section for 4~6 points shall be survey.

    Construction guy first marking every checked point, the points are fix offset from

    kerb-stone. Site surveyor used leveling instrument or total station survey every marked

  • 8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1

    22/39

    Sinohydro Group LimitedDoha Expressway Package 6 Method Statement for Surveying and Setting Out

    EXW-P006-0000-GS-SHC-MT-00003 Rev.1 12 May 2012 Page 18 of 35

    points, and calculation deviation..

    c) Tolerance

    Vertical:-20mm/+15mm

    d) Results Submit

    A RFI should be submitted for engineer acceptance, RFI including survey data and

    deviation.

    9.6.4 Setting out of kerb-stone

    a) Used Instrument

    Total Station and Leveling Instrument should be adopted for this works.

    b) Setting-out Method

    Setting out method for kerb stone work is to set out a point every interval of 20 meters for

    straight as well as every 5 meters for curved. And key point must be staked out.

    c) Tolerance

    Horizontal : 10mm, Vertical : 10mm.

    d) Results Submit

    A RFI should be submitted for engineer acceptance, RFI including deviation drawing,

    survey data and soft copy.

    9.6.5 Survey Inspection for Kerb-stonea) Used Instrument

    Total Station and Leveling Instrument should be adopted for this works.

    b) Inspection Method

    Inspection method for kerb stone work is to checked point every interval of 20 meters for

    straight as well as every 5 meters for curved. And key point must be checked.

    c) Tolerance

    Horizontal : 10mm, Vertical : 5mm.d) Results Submit

    A RFI should be submitted for engineer acceptance, RFI including deviation drawing,

    survey data and soft copy.

  • 8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1

    23/39

    Sinohydro Group LimitedDoha Expressway Package 6 Method Statement for Surveying and Setting Out

    EXW-P006-0000-GS-SHC-MT-00003 Rev.1 12 May 2012 Page 19 of 35

    10 Quality Assurance Procedure

    10.1 Management and Responsibi lities

    10.1.1 Purpose

    The purpose of this procedure is to carry through a whole course control the whole

    process of the survey works so that a satisfactory survey result can be achieved in

    accordance with contract.

    10.1.2 Responsibi lit ies

    Survey Manager shall fully take charge of survey work of the project, and implement the

    regulations in quality assurance plan in the survey work and achieve survey resultconforming to the requirement of Project Specification.

    Chief surveyor shall participate in the planning of survey technical design, and take

    charge of on-site survey, calibration of survey instruments and checking of survey results.

    Site surveyor team shall be responsible for conducting on-site survey works.

    Office surveyor shall be responsible for the post-processing of data and preparation of

    drawings.

    10.2 Quality Assurance Process

    The quality assurance process includes survey planning, survey preparation, on-site

    survey, post-processing data and acceptance checking.

    10.2.1 Survey Planning

    As per contract requirement, survey manager and chief surveyor shall participate in

    planning works, includes the following:

    General description and scope of work

    Technical and quality requirement

    Determination of program and completion time

    Work method

    Survey preparation includes: joint checking of drawings, method, quality control index,

    instrument maintenance, and personnel training.

    10.2.2 On-site Survey

    Every procedure of survey works (horizontal control, elevation control) shall be carried out

  • 8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1

    24/39

    Sinohydro Group LimitedDoha Expressway Package 6 Method Statement for Surveying and Setting Out

    EXW-P006-0000-GS-SHC-MT-00003 Rev.1 12 May 2012 Page 20 of 35

    as per relevant specifications.

    Effective measures should be taken for the protection of the instrument in storage and

    delivery. Special attention should be paid to maintain accuracy and sensitivity of the

    instruments.

    Survey records should be made in a uniform form and includes all necessary information.

    For topography survey refer to plan In-survey.

    10.2.3 Post-processing

    Chief survey shall make further arrangements for data and documents review and check

    relevant site record and calculation data. Drawer shall cooperate with each other and

    make self-assessment. Survey team leader shall make final checking.Survey superintendent shall be responsible for preparation of technical report, checking

    of relevant survey record and data calculation.

    10.2.4 Acceptance Checking

    Team leader shall make final acceptance checking after self-checking of on-site survey

    team.

    Checking content: content of works fulfils specification requirements, survey method

    should be suitable for the work, result drawing conform to requirement of construction

    works, survey data and document be complete and correct.

    The survey result shall be self-checked by surveyor, reviewed by checker, verified by

    survey superintendent and approved by survey manager finally.

    Final acceptance and submittal: All survey products together with relevant records shall be

    submitted to QC department of the project for approval. And survey team shall print out the

    survey product and submit it to Engineers for approval.

    10.3 Resources Management

    10.3.1 Personnel Training

    a) Training programs will be prepared. Such program shall be established taking into

    account any impact resulting from changes in technology and other survey

    processes.

    b) Training shall be provided to ensure that personnel are aware of the importance

    and relevance of their activities. Records of the training are maintained.

  • 8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1

    25/39

    Sinohydro Group LimitedDoha Expressway Package 6 Method Statement for Surveying and Setting Out

    EXW-P006-0000-GS-SHC-MT-00003 Rev.1 12 May 2012 Page 21 of 35

    10.3.2 Instrument Control

    a) All survey instruments shall be selected and controlled with consideration to range,

    accuracy and tolerance to accomplish the required results

    b) Survey instrument shall as a minimum be calibrated as stated on the valid

    calibration certificate , and record of calibration should be filed. If it is indicated the

    an instrument is out of calibration, it will immediately be handed over to the

    responsible chief surveyor so a re-calibration can be carried out.

    c) All survey instruments shall be calibrated, adjusted and maintained at prescribed

    intervals or prior to use against internationally or certified nationally recognized

    standards. Where no such standards the basis and method for calibration shall be

    documented

    10.4 Control of Document

    Relevant survey document will be controlled as per document control procedures. The

    document management system will cover control over approval, publishing,

    communication, change, maintenance of relevant supporting document to assure validity,

    integrity and applicability of document. Special attention should be paid to laws,

    specifications and standards concerning survey works.

    Change and revision of documents: Any change and revision of documents shall be

    implemented by approval department. And revised documents shall be identified clearly.

    Document controller will be assigned to manage the relevant survey documents and will

    be in charge of management, handling, collection, catalog, maintenance of relevant

    documents.

    10.5 Quality Record

    Relevant quality record shall be prepared and shall be provided to engineer as per their

    requirement. And a quality controller shall be assigned for the arrangement, catalog, filing

    and maintenance of quality record. Information of relevant points should be maintained.

  • 8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1

    26/39

    Sinohydro Group LimitedDoha Expressway Package 6 Method Statement for Surveying and Setting Out

    EXW-P006-0000-GS-SHC-MT-00003 Rev.1 12 May 2012 Page 22 of 35

    11 Safety and Health Plan for survey works

    11.1 Risk Assessment

    Risk Potential Danger Control Measures Reference

    Inadequateknowledge of

    Projectrequirements

    Personal injuryInjury to othersIgnorant to site

    regulations

    Attend Sinohydro Safety Induction forNew Employees

    Moving vehicles/ Machinery

    Road accident,Personal injury, loss of

    life, property andequipment damages

    Attend driver training conducted bySinohydro Safety Department

    Not familiar withwork execution

    Personal injuryInjury to Others

    Struck by machinery

    Attend the daily program conducted bysupervisor / foreman

    Personnel onground

    Hit by moving vehicleHit by moving truck

    Wear proper high visibility vestProvide shed / covering

    Vehicles fallingfrom the edge ofthe excavation

    Back Injury, Fractures,Cuts, Bruises, Death

    Rigid safety barriers shall be erectedaround all excavations to preventvehicles falling into them. Vehicles

    shall be kept away from excavationswherever possible. Where vehicles

    have to tip materials into excavations,stop blocks to prevent them fromover-running shall be used and abanksman shall be present before

    discharging the load.Fallen material

    from highPersons injured

    Equipment damaged

    Wear Safety helmet ;Keep away from dangerous place.

    Falls fromHeight

    Back Injury, Fractures,

    Cuts, Bruises, Death

    Suitable signs will be positioned andrigid edge protection will be erected atplaces where the falls of more than 2m

    could occur. Personal suspensionequipment will be used by operatives

    working at or near the edge.Training, toolbox talks and

    instructions shall be provided to all

    operatives and supervisory staffinvolved in the use of suspension

    equipment such as lines andharnesses, and how to inspect andassess PPE of this type before use.

    11.2 Protective & Safety Equipment

    All workers involved shall be equipped with adequate PPE as follows:

    Safety helmet

    Safety boots

  • 8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1

    27/39

    Sinohydro Group LimitedDoha Expressway Package 6 Method Statement for Surveying and Setting Out

    EXW-P006-0000-GS-SHC-MT-00003 Rev.1 12 May 2012 Page 23 of 35

    Safety vest

    11.3 Contractual Requirements

    Safety induction for New Employees

    PPE requirements

    Inspection of Machinery

    Emergency Procedures

    Welfare facilities

    First aid requirements

    Defensive driving training

    Water tank for drinkingCommunications (walktalking, mobile telephone)

    11.4 Emergency Procedures

    In the event of an accident, the following shall be activated:

    The area supervisors shall act as the Rescue Team Leader and attend to the accident

    He shall inform the emergency controller of the accident

    In the absence of the Project Manager, the Construction Manager shall act as the

    Emergency Controller

    The emergency controller shall alert the emergency response team, comprising of first

    aiders to attend the accident when required.

    The emergency controller shall alert the fire fighting team should there be a fire.

    The rescue team leader shall alert the emergency controller for additional assistance from

    other rescue team leaders

    The emergency controller shall arrange for transportation to send the injured person to the

    clinic or hospital if required

    The accident area shall be barricaded and nothing shall be removed from the area.

    A watchman shall be engaged to protect the area from unauthorized entry

    The emergency controller shall call for a post mortem meeting after the emergency with

    the people involved in the emergency.

    The S&H representative shall organize the safety committee to perform a full accident

    investigation

    All information leading to the accident including information, description, photos, time,

    location, sources, witness statements, police and medical reports shall be prepared a

  • 8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1

    28/39

    Sinohydro Group LimitedDoha Expressway Package 6 Method Statement for Surveying and Setting Out

    EXW-P006-0000-GS-SHC-MT-00003 Rev.1 12 May 2012 Page 24 of 35

    submitted by the Project Manager.

    Defensive driver permit

    12 Inspection & testing

    Inspections and testing will be performed by Sinohydro; the procedure should be

    subjected to Document EXW-P006-0000-GS-SHC-IT-00001.

    13 Appendix

    Appendix.1 List of Survey Equipment (Used on P6 Site)

    Appendix 2.Inspection for formation level /base slab/roof slab/backfilling surface of sheet

    Appendix 3.Inspection for formation level /base slab/roof slab/backfilling surface drawing

    Appendix 4.Setting out for excavation sheet

    Appendix 5. Manhole/chamber inspection for base slab level sheet

    Appendix 6 . Inspection for level of the installed pipeline sheet

    Appendix 7.Formwork checking for kerb blinding

    Appendix 8. Survey data for compacted ground/sub-grade/sub-base

    Appendix 9. Inspection for kerb stone sheet

    Appendix 10Inspection deviation drawing for kerb stone

  • 8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1

    29/39

    Sinohydro Group LimitedDoha Expressway Package 6 Method Statement for Surveying and Setting Out

    EXW-P006-0000-GS-SHC-MT-00003 Rev.1 12 May 2012 Page 25 of 35

    Appendix.1 L is t of Survey Equipment (Used on P6 Site)

    Item Type Model ManufacturerManufactures

    Serial No

    Calibration

    DateExpireDate Remarks

    Survey

    Instrument

    Automatic

    Level

    FOIF

    NAL-124FOIF T97212

    19-Mar-20

    1218-Sept-2012

    GPS

    ReceiverR6 Trimble 4822153875

    24-Dec-20

    1123-Dec-2012

    GPS

    ReceiverR6 Trimble 4822153857

    24-Dec-20

    1123-Dec-2012

    Total Station DTM532 Nikon 03275313-Mar-20

    1212-Sept-2012

    Electronic

    LevelDINI12 Trimble 703163A

    20-Feb-20

    1219-Aug-2012

    Survey

    Software

    TBC 2.4 Trimble

    TGO 1.63 Trimble

    AutoCAD 2006/2010 Autodesk

    LGO LEICA

    Nikon Data

    TransferNikon

    Computer unit 1

  • 8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1

    30/39

    Sinohydro Group LimitedDoha Expressway Package 6 Method Statement for Surveying and Setting Out

    EXW-P006-0000-GS-SHC-MT-00003 Rev.1 12 May 2012 Page 26 of 35

    Appendix 2.Inspect ion for formation level /base slab/roof slab/backfi ll ing sur face ofsheet

    Location.____ Inspection for formation level/screed/base slab/roof slab/backfi lling surface

    CHAINAGE ELEVATION CHECKED POINTS DESIGNELEVATIONDEVIATIONP.N EAST NORTH ELEVATION

    SURVEY INSTRUMENT: GPS / TOTAL STATION / LEVELING

    DESCRIPTI P.N EAST NORTH ELEVATIONSTATION

    BS

    CHECK .BS

    Surveyor:_________ Date:_________

  • 8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1

    31/39

    Sinohydro Group LimitedDoha Expressway Package 6 Method Statement for Surveying and Setting Out

    EXW-P006-0000-GS-SHC-MT-00003 Rev.1 12 May 2012 Page 27 of 35

    Appendix 3.Inspection for formation level /base slab/roof slab/backfi ll ing surfacedrawing

    N

    3300.00

    1400.0

    0

    3850.00 3850.00

    480

    0.0

    3

    4799.97

    Surveyor:_________ Date:_________

  • 8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1

    32/39

    Sinohydro Group LimitedDoha Expressway Package 6 Method Statement for Surveying and Setting Out

    EXW-P006-0000-GS-SHC-MT-00003 Rev.1 12 May 2012 Page 28 of 35

    Appendix 4.Setting out for excavat ion sheet

    Location.______ Setting out for excavation

    CHAINAGESETTING OUT POINTS

    P.N EAST NORTH ELEVATION

    SURVEY INSTRUMENT: GPS / TOTAL STATION / LEVELING

    DESCRIPTION P.N EAST NORTH ELEVATIONSTATION

    BS

    CHECK .BS

    Surveyor:_________ Date:_________

  • 8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1

    33/39

    Sinohydro Group LimitedDoha Expressway Package 6 Method Statement for Surveying and Setting Out

    EXW-P006-0000-GS-SHC-MT-00003 Rev.1 12 May 2012 Page 29 of 35

    Appendix 5. Manhole/chamber inspection for base slab level sheet

    MANHOLE/CHAMBER NO. INSPECTION FOR BASE SLAB LEVEL (STORM / SEWER / IRRIGATION / POTABLE)

    Manhole/CHAMBER P/NCHECK POINTS COORDINATE DESIGN COORDINATE DEVIATION(mm)

    EAST NORTH ELEVATION EAST NORTH ELEVATION EAST NORTH ELEVATION

    SURVEY INSTRUMENT GPS/TOTAL STATION/LEVELINGN.O. EAST NORTH ELEVATION

    STATION

    BS

    CHECK

    POINTS

    REFERENCE DRAWING:

    Surveyor:_________ Date:_________

  • 8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1

    34/39

    Sinohydro Group LimitedDoha Expressway Package 6 Method Statement for Surveying and Setting Out

    EXW-P006-0000-GS-SHC-MT-00003 Rev.1 12 May 2012 Page 30 of 35

    Appendix 6 . Inspection for level of the instal led pipel ine sheet

    SURVEY INSTRUMENT:GPS / TOTAL STATION / LEVELING

    N.O. EAST NORTH ELEVATION

    STATION

    B.S.

    CHECK POINTS

    REFERENCE DRAWING :

    Surveyor:_________ Date:_________

    CH.______ INSPECTION FOR LEVEL OF THE INSTALLED PIPELINE(STORM/SEWER/IRRIGATION/POTABLE)

    CHAINAGE P/NCHECK POINT COORDINATE DESIGN DEVIATION(mm)

    EAST NORTH ELEVATION ELEVATION ELEVATION

  • 8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1

    35/39

    Sinohydro Group LimitedDoha Expressway Package 6 M

    EXW-P006-0000-GS-SHC-MT-00003 Rev.1 12 May 2012

    Appendix 7.formwork chencking for kerb blinding

    FORMWORK CHECKING FOR KERB BLINDING ( CH. __________)

    CHAINAGEKERBLEVEL

    OFFSET FROM KERB LINE CHECKED COORDINATES

    L R POINT NO. E N ELEVATION

    Surveyor: Date:

  • 8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1

    36/39

    Sinohydro Group LimitedDoha Expressway Package 6 Method Statement for Surveying and Setting Out

    EXW-P006-0000-GS-SHC-MT-00003 Rev.1 12 May 2012 Page 32 of 35

    Appendix 8. Survey data for compacted ground/sub-grade/sub-base.

    CHAINAGE NO.

    SURVEY COORDINATEAND LEVEL

    FINISHEDROADLEVEL

    SUB-GRADELEVEL(TOP)

    DIVATIONLEVEL(mm)

    EAST NORTH LEVEL

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    18

    19

    20

    21

    22

    23

    24

    25

    26

    27

    28

    SURVEYOR: DATE:

  • 8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1

    37/39

    Sinohydro Group LimitedDoha Expressway Package 6 Method Statement for Surveying and Setting Out

    EXW-P006-0000-GS-SHC-MT-00003 Rev.1 12 May 2012 Page 33 of 35

    Appendix 9.Inspect ion for kerb stone sheet

    NO.CHECK POINT COORDINATE DESIGN

    ELEVATIONDEVIATION

    ELEVATION(mm)EAST NORTH ELEVATION

    1

    23

    4

    NO. EAST WEST ELEVATION

    STATION FREE

    BS

    CHECK BS

    LEVELING BS

    SURVEY INSTRUMENT:TOTAL STATION AND AUTO-LEVEL

    SURVEYOR: DATE:

  • 8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1

    38/39

    Sinohydro Group LimitedDoha Expressway Package 6 Method Statement for Surveying and Setting Out

    EXW-P006-0000-GS-SHC-MT-00003 Rev.1 12 May 2012 Page 34 of 35

    Appendix 10inspection deviation drawing for kerb stone.

    Surveyor:__________ Date:____________

  • 8/10/2019 EXW-P006-0000-GS-SHC-MT-00003 Method Statement for Surveying and Setting Out Rev.1

    39/39

    Sinohydro Group LimitedDoha Expressway Package 6 Method Statement for Surveying and Setting Out

    Appendix 11inspection deviation drawing for kerb stone.