extra exercises on network diagrams
DESCRIPTION
Network diagramming Exercise for PMPTRANSCRIPT
![Page 1: Extra Exercises on Network Diagrams](https://reader036.vdocuments.us/reader036/viewer/2022081721/55cf9ce7550346d033ab7bfd/html5/thumbnails/1.jpg)
RMC Project Management, Inc. Extra Exercises on Network Diagrams
Copyright © 2007 RMC Project Management, Inc. All rights reserved.500 East Travelers Trail, Suite 100 • Minneapolis, Minnesota [email protected] • www.rmcproject.com • (952) 846-4484The copyright owner hereby grants permission to make copies of this handout for personal, noncommercial use only.
![Page 2: Extra Exercises on Network Diagrams](https://reader036.vdocuments.us/reader036/viewer/2022081721/55cf9ce7550346d033ab7bfd/html5/thumbnails/2.jpg)
Copyright © 2007 RMC Project Management, Inc. All rights reserved.500 East Travelers Trail, Suite 100 • Minneapolis, Minnesota [email protected] • www.rmcproject.com • (952) 846-4484The copyright owner hereby grants permission to make copies of this handout for personal, noncommercial use only.
�
Exercise 1
[AON] Using the table below, draw the network diagram and answer the questions. When you have completed answering the questions, do a forward/backward pass.
�. How many paths are in the network, and what are they?
2. What is the critical path and its duration?
3. What is the float on activity U?
4. What is the impact to the project if activity B takes three weeks longer than planned?
Do a forward and backward pass using the original estimates.
Activity Predecessor Estimate in weeks
Start - 0
C Start 6B Start 4P Start 3A C, B, P 7U P 4T A 2R A 3N U 6
End T, R, N 0
![Page 3: Extra Exercises on Network Diagrams](https://reader036.vdocuments.us/reader036/viewer/2022081721/55cf9ce7550346d033ab7bfd/html5/thumbnails/3.jpg)
Copyright © 2007 RMC Project Management, Inc. All rights reserved.500 East Travelers Trail, Suite 100 • Minneapolis, Minnesota [email protected] • www.rmcproject.com • (952) 846-4484
The copyright owner hereby grants permission to make copies of this handout for personal, noncommercial use only.
2
Answer to Exercise 1
[AON] Using the table below, draw the network diagram and answer the questions. When you have completed answering the questions, do a forward/backward pass.
�. How many paths are in the network, and what are they?
Therearesevenpaths.Seethedetailsonthenextpage.
2. What is the critical path and its duration?
Start,C,A,R,End 16WEEKS
3. What is the float on activity U?
3weeks
4. What is the impact to the project if activity B takes three weeks longer than planned?
CriticalpathshiftstoStart,B,A,R,End. Itwilldelaytheprojectendbyoneweek.
Do a forward and backward pass using the original estimates.
Activity Predecessor Estimate in weeks
Start - 0
C Start 6B Start 4P Start 3A C, B, P 7U P 4T A 2R A 3N U 6
End T, R, N 0
Start
C A T
EndB R
P U N
![Page 4: Extra Exercises on Network Diagrams](https://reader036.vdocuments.us/reader036/viewer/2022081721/55cf9ce7550346d033ab7bfd/html5/thumbnails/4.jpg)
Copyright © 2007 RMC Project Management, Inc. All rights reserved.500 East Travelers Trail, Suite 100 • Minneapolis, Minnesota [email protected] • www.rmcproject.com • (952) 846-4484The copyright owner hereby grants permission to make copies of this handout for personal, noncommercial use only.
3
Legend
Answer to Exercise 1
Start, C, A, T, End �5Start, C, A, R, End �6Start, B, A, T, End �3Start, B, A, R, End �4Start, P, A, T, End �2Start, P, A, R, End �3Start, P, U, N, End �3
Start
C A T
EndB R
P U N
6 7 2
00
66
0 66
1313
0 1314
1516
1
4
02
46
2
3
1313
1616
0
3
03
36
3
4
36
710
3 710 3 13
16
ID
D
ESLS
EFLF
S
Note: Answers are based on using the zero method. See www.rmcproject.com/free/tips.htm for an explanation of the two methods.
![Page 5: Extra Exercises on Network Diagrams](https://reader036.vdocuments.us/reader036/viewer/2022081721/55cf9ce7550346d033ab7bfd/html5/thumbnails/5.jpg)
Copyright © 2007 RMC Project Management, Inc. All rights reserved.500 East Travelers Trail, Suite 100 • Minneapolis, Minnesota [email protected] • www.rmcproject.com • (952) 846-4484
The copyright owner hereby grants permission to make copies of this handout for personal, noncommercial use only.
4
Exercise 2 [AOA] Using the table below, draw the network diagram and answer the questions. When you have completed answering the questions, do a forward/backward pass.
�. How many paths are in the network, and what are they?
2. What is the critical path and its duration?
3. What is the float on activity A–C?
4. What is the impact to the project if activity F-End takes two weeks longer than planned?
Do a forward and backward pass using the original estimates.
Activity Estimate in weeks
Start–A 2Start–B 3
A–C 5A–D 4B–C 6B–F 2C–E 3C–F Dummy
D–End �E–End 3F–End 4
![Page 6: Extra Exercises on Network Diagrams](https://reader036.vdocuments.us/reader036/viewer/2022081721/55cf9ce7550346d033ab7bfd/html5/thumbnails/6.jpg)
Copyright © 2007 RMC Project Management, Inc. All rights reserved.500 East Travelers Trail, Suite 100 • Minneapolis, Minnesota [email protected] • www.rmcproject.com • (952) 846-4484The copyright owner hereby grants permission to make copies of this handout for personal, noncommercial use only.
5
Answer to Exercise 2
[AOA] Using the table below, draw the network diagram and answer the questions. When you have completed answering the questions, do a forward/backward pass.
�. How many paths are in the network, and what are they?
Therearesixpaths.Seethedetailsonthenextpage.
2. What is the critical path and its duration?
Start–B,B–C,C–E,E–Endanditwilltake15weeks.
3. What is the float on activity A-C?
Twoweeks
4. What is the impact to the project if activity F–End takes two weeks longer than planned?
Therearetwocriticalpaths.AnadditionaloneisStart–B,B–C,C–F,F–End.
Do a forward and backward pass using the original estimates.
Activity Estimate in weeks
Start–A 2Start–B 3
A–C 5A–D 4B–C 6B–F 2C–E 3C–F Dummy
D–End �E–End 3F–End 4
Start
A D
C E
B F
Start
![Page 7: Extra Exercises on Network Diagrams](https://reader036.vdocuments.us/reader036/viewer/2022081721/55cf9ce7550346d033ab7bfd/html5/thumbnails/7.jpg)
Copyright © 2007 RMC Project Management, Inc. All rights reserved.500 East Travelers Trail, Suite 100 • Minneapolis, Minnesota [email protected] • www.rmcproject.com • (952) 846-4484
The copyright owner hereby grants permission to make copies of this handout for personal, noncommercial use only.
6
Answer to Exercise 2
Start–A, A–D, D–End 7Start–A, A–C, C–E, E–End �3Start–A, A–C, C–F, F–End ��Start–B, B–C, C–E, E–End �5Start–B, B–C, C–F, F–End �3Start–B, B–F, F–End 9
Start
A D
C E
B F
End
0
22
2
24 4
29
25
7
102 4
86
146
14 18 7
151512 31512 0
13154
2911
5116
293
30
99
633
30
0
0
3
99
30 12
12
X YD
LS LFES EF
S
Legend
![Page 8: Extra Exercises on Network Diagrams](https://reader036.vdocuments.us/reader036/viewer/2022081721/55cf9ce7550346d033ab7bfd/html5/thumbnails/8.jpg)
Copyright © 2007 RMC Project Management, Inc. All rights reserved.500 East Travelers Trail, Suite 100 • Minneapolis, Minnesota [email protected] • www.rmcproject.com • (952) 846-4484The copyright owner hereby grants permission to make copies of this handout for personal, noncommercial use only.
7
Exercise 3[AOA] Using the table below, draw the network diagram and answer the questions. When you have completed answering the questions, do a forward/backward pass.
�. How many paths are in the network, and what are they?
2. What is the critical path and its duration?
3. What is the float on Activity F? Activity H?
4. What is the impact to the project if activity B takes three weeks longer than planned?
Do a forward and backward pass using the original estimates.
Activity Successor Estimate in weeks
Start A, B, C 0A D 2B E 4C F, G 5D H 3E I 4F I DummyG J 2H K II K 2J End 4K End 6
End - 0
![Page 9: Extra Exercises on Network Diagrams](https://reader036.vdocuments.us/reader036/viewer/2022081721/55cf9ce7550346d033ab7bfd/html5/thumbnails/9.jpg)
Copyright © 2007 RMC Project Management, Inc. All rights reserved.500 East Travelers Trail, Suite 100 • Minneapolis, Minnesota [email protected] • www.rmcproject.com • (952) 846-4484
The copyright owner hereby grants permission to make copies of this handout for personal, noncommercial use only.
�
Answer to Exercise 3
[AOA] Using the table below, draw the network diagram and answer the questions. When you have completed answering the questions, do a forward/backward pass.
�. How many paths are in the network, and what are they?
Therearefourpaths.Seethedetailsonthenextpage.
2. What is the critical path and its duration?
Start,B,E,I,K,Endanditwilltake16weeks.
3. What is the float on Activity F? Activity H?
BecauseactivityFisadummytaskthereisnofloat.ActivityHhasfloatof4weeks.
4. What is the impact to the project if activity B takes three weeks longer than planned?
Itwilldelaytheprojectby3weeksbecauseBisonthecriticalpath.
Do a forward and backward pass using the original estimates.
Activity Successor Estimate in weeks
Start A, B, C 0A D 2B E 4C F, G 5D H 3E I 4F I DummyG J 2H K II K 2J End 4K End 6
End - 0
EndStart
A
D H
K
J
G
C
B E
I
F
![Page 10: Extra Exercises on Network Diagrams](https://reader036.vdocuments.us/reader036/viewer/2022081721/55cf9ce7550346d033ab7bfd/html5/thumbnails/10.jpg)
Copyright © 2007 RMC Project Management, Inc. All rights reserved.500 East Travelers Trail, Suite 100 • Minneapolis, Minnesota [email protected] • www.rmcproject.com • (952) 846-4484The copyright owner hereby grants permission to make copies of this handout for personal, noncommercial use only.
9
Answer to Exercise 3
Start, A, D, H, K, End �2Start, B, E, I, K, End �6Start, C, F, I, K, End �3Start, C, G, J, End ��
EndStart
A,2
D,3 H,1
K,6
J,4
G,2
C,5
B,4 E,4
I,2
F
426
59
59
4 610 10
100
1616
1010
0
88
1116
5
7127
1255
10
58
3
03
00
0 44
014
4
26
44
0 88
ID,DLS LFES EFS
Legend
![Page 11: Extra Exercises on Network Diagrams](https://reader036.vdocuments.us/reader036/viewer/2022081721/55cf9ce7550346d033ab7bfd/html5/thumbnails/11.jpg)
Copyright © 2007 RMC Project Management, Inc. All rights reserved.500 East Travelers Trail, Suite 100 • Minneapolis, Minnesota [email protected] • www.rmcproject.com • (952) 846-4484
The copyright owner hereby grants permission to make copies of this handout for personal, noncommercial use only.
�0
Exercise 4[AON] Using the table below, draw the network diagram and answer the questions. When you have completed answering the questions, do a forward/backward pass.
�. How many paths are in the network, and what are they?
2. What is the critical path and its duration?
3. What is the float on activity E?
4. What is the impact to the project if activity C takes three weeks longer than planned?
Do a forward and backward pass using the original estimates.
Activity Predecessor Estimate in weeks
A - 5B A 7C A 3D B �E B, C 3F D, E 2
![Page 12: Extra Exercises on Network Diagrams](https://reader036.vdocuments.us/reader036/viewer/2022081721/55cf9ce7550346d033ab7bfd/html5/thumbnails/12.jpg)
Copyright © 2007 RMC Project Management, Inc. All rights reserved.500 East Travelers Trail, Suite 100 • Minneapolis, Minnesota [email protected] • www.rmcproject.com • (952) 846-4484The copyright owner hereby grants permission to make copies of this handout for personal, noncommercial use only.
��
Answer to Exercise 4[AON] Using the table below, draw the network diagram and answer the questions. When you have completed answering the questions, do a forward/backward pass.
�. How many paths are in the network, and what are they?
Therearethreepaths.Seethedetailsonthenextpage.
2. What is the critical path and its duration?
A,B,E,Fanditwilltake17weeks
3. What is the float on activity E?
Zero,itisonthecriticalpath.
4. What is the impact to the project if activity C takes three weeks longer than planned?
Therewillbenoimpacttothecriticalpathoritsduration.
Do a forward and backward pass using the original estimates.
Activity Predecessor Estimate in weeks
A - 5B A 7C A 3D B �E B, C 3F D, E 2
A
B D
F
C E
5
7 1
3 3
2
![Page 13: Extra Exercises on Network Diagrams](https://reader036.vdocuments.us/reader036/viewer/2022081721/55cf9ce7550346d033ab7bfd/html5/thumbnails/13.jpg)
Copyright © 2007 RMC Project Management, Inc. All rights reserved.500 East Travelers Trail, Suite 100 • Minneapolis, Minnesota [email protected] • www.rmcproject.com • (952) 846-4484
The copyright owner hereby grants permission to make copies of this handout for personal, noncommercial use only.
�2
Legend
Answer to Exercise 4
A, B, D, F 15A, B, E, F 17A, C, E, F 13
A
B D
F
C E
5
7 1
3 3
0 5
0 0 5
5 12 12 13
14 2 155 0 12
5 8
9 4 12
215 17
15 0 17
12 15
12 0 15
ID
DES
LS
EF
LFS