extension of time under jct (illustration)
DESCRIPTION
Delay and Extension of Time: Notifying Delay under JCT Intermediate Building Contract 2011TRANSCRIPT
-
DELAY AND EXTENSIONS OF TIMENOTIFYING DELAY UNDER JCT INTERMEDIATE BUILDING CONTRACT 2011
Contract & Construction Consultants Limited Tel: 0117 925 900165 Woodland Road, Clifton, Bristol, BS8 1UL www.contract-consultants.com
The Contractor's Works are DELAYEDor
LIKELY TO BE DELAYED
The Contractor must use his best endeavoursto prevent delay, and do anything reasonably
required by the Architect/ContractAdministrator to proceed with the Works
Each and every time the Works are delayed,or likely to be delayed, the Contractor MUSTgive a WRITTEN NOTICE of the delay to the
Architect/Contract Administrator
What should thenotice contain?
For each and everydelay, the notice should
state the CAUSE ofthat delay
The Architect/Contract Administrator should then assess:(1) if completion is delayed (or likely to be delayed) and
(2) whether the cause of the delay is a Relevant EventRelevant Events are listed at Clause 2.20
If there is a delay to completion caused by a Relevant Event, then the Architect/Contract Administratormust give a notice in writing setting out a fair and reasonable extension of time. The notice should
be given as soon as the Architect is able to estimate the length of the delay to the completion date
Under the Intermediate BuildingContract, if the Architect/ContractAdministrator does not considerthat completion is delayed or thatthe cause was a Relevant Event,
he does not have to give anotice stating this.
This is all the information theContractor is required to give,
under the Intermediate BuildingContract but the Contractor should
also aim to give the following:What the effect of the delay is
Whether the cause is a Relevant EventAn estimate of delay to completion.
Not least because the Architect/Contract Administrator will expect to
receive this information anyway!
The Contractor is not required to incurunreasonable costs in accelerating the
Works. Any loss suffered may beclaimable as loss and expense
The consequences of notgiving a notice on time
could include:The Contractor may not
be entitled to a fullextension of time or
extended preliminariesThe Contractor might beliable for delays whichhave been caused by itsfailure to notify a delay
to the Architect/Contract Administrator
The Contractor should also provide any further information required bythe Architect/Contract Administrator which is reasonably necessary forthe purposes of this clause 2.19 - that is, for notifying delay or assessing
an extension of time