expression of interest for anhydrous ammonia …
TRANSCRIPT
EXPRESSION OF INTEREST FOR
ANHYDROUS AMMONIA CHARGING FACILITY
1. Introduction
2. General requirements
3. Typical Schematic of facility
4. Evacuation System
5. Evacuation and charging system
6. Baking Chamber
7. Cryostat with cooling pads
8. Residual Gas Analyzer
9. Sensors and Instrumentation
10. PLC based Data Acquisition and Control Systems (DACS)
11. Safety and protection
12. Wiring
13. Environment
14. Utilities available with ISAC/ISRO
15. Installation, Commissioning and Testing
16. Preliminary Design Review
17. Deliverable Documents
1. Introduction
ISRO Satellite Centre (ISAC), Bangalore is a lead centre of Indian Space
Research Organization (ISRO) for design, fabrication, assembly and testing of satellites
in India. Thermal Systems Group (TSG) of ISAC/ISRO is responsible for providing a
suitable thermal control system for all its satellites. As a part of thermal control system,
efficient heat conductor / distributers, namely, heat pipes are used.
Heat pipe is a hermetically sealed two-phase heat transport device. It is made ofa
hollow aluminum tube having two independent channels, each channel contain a small
quantity of fluid like ammonia, ethane, acetone etc. The inner diameter of each channel
may vary from 2mm to 15mm, length can vary from 100mm to 3000mm and weight
from 30g to 500g per meter length.
In our application, fluid is ultra-high purity ≥ 99.999% with water vapor content <
0.5ppm. It is transferred in gaseous form from ammonia cylinder through a manifold
after thorough out gassing of tube using heating and evacuation equipments. No added
contaminants in to the tube and into the gas including water vapors are allowed during
transfer of the gas from cylinder in to tube.
The major functions of the proposed anhydrous ammonia charging equipment are:
• Evacuation / baking of the tubes, up to 250oC.
• Gaseous ammonia transfer into both channels of tube by local cooling of tube
• Baking the tube at the selected temperature and finally flushing out, one by one
from each channel of the tube, one at time.
• Gaseous Ammonia charging into one channel of the tube and measuring ammonia
leak through second channel of tube by gas analyzer.
The facility shall be used to charge ammonia into maximum of twelve number of heat
transport tubes simultaneously.
On behalf of ISRO, ISAC invites the proposal from reputed and experienced vendors
for “ammonia charging facility” as per the following requirements / specifications
provided in the subsequent section of this RFP.
2. General requirements
2.1 Scope of work
� The vendor shall fabricate, demonstrate, and install anhydrous ammonia
charging facility at ISRO Satellite Centre, Vimanapura, Bangalore -17,
Karnataka, India or any other location in Bangalore specified by ISAC/ISRO.
2.2 Experience / Expertise
� Vendor shall have experience / expertise in manufacturing and installation of
vacuum systems, heating/cooling systems, handling of highly corrosive
gases, etc.
� Vendor shall submit, along with offer, brief overview of vendor’s
infrastructure, technical capabilities and purchase order copies of similar
facilities developed and installed for other organizations/industries.
� Vendor shall hold full responsibility of execution of this system completely
in all aspects.
� Vendor/s shall be asked to make detailed presentations on their offer to the
expert committee of ISAC/ISRO at ISAC/ISRO as a part of vendor
evaluation process. Vendor shall provide confirmation for this detailed
technical presentation in the technical offer / quotation.
� Offers without the above information or offers with incomplete / inaccurate /
false information will be rejected.
3 Typical Schematic of facility
The heat transport tube assembly to be loaded into the ammonia charging facility is
shown in figure 1.The facility shall have a baking chamber with horizontal supporting
platforms made of SS 304L at the center onto which the heat transport tubes shall be
loaded as shown in figure 2.
Fig.1. Schematic of heat transport tube
The valves on either side of the heat transport tube shall be connected to flexible bellows
to suit specified lengths and shapes of heat transport tubes. These flexible bellows in
turn shall be connected to high vacuum evacuation system and anhydrous ammonia
cylinder through vacuum compatible, high pressure resistant & corrosive grade
manifolds with different types of valves in the charging line. The evacuation system and
ammonia cylinder shall exist on either side of the platforms, as shown in Figure-3.
4 Evacuation System
It consists of two separate sets of ultra-high vacuum evacuation systems as shown
in Figures-3A, 3B, and 3C. The evacuation systems are based on rotary cum turbo
molecular pumps with vacuum level better than 10-6 mbar inside the channels of heat
transport tube.The evacuation system and its accessories shall be compatible with
anhydrous ammonia (corrosive grade). No parts/ components including oil, if any used
in pump, shall contaminate the connected vacuum manifold etc. It shall have nitrogen
gas purging port with suitable interface (I/F) for connecting the gas cylinder. All joints
shall have leak rate less than 1x 10-9Standard cm3/s (SCC/s).
Double stage rotary vane pump shall be used as backing pump with pump
speed≥15m3/hrat for the turbo molecular pump of suitable capacity. Safety valve shall
Two channels
Needle valve
be used to separate the pump from the high vacuum side during shut-down and Gas
ballast valve to avoid contamination in the lubricant oil. Lubricant selected (Fomblin oil
or equivalent) shall not contaminate the flow lines and compatible with ammonia. Other
accessories such as cables, connectors, etc.required for effective and safe operation of
turbo molecular pump (if any) shall be included in the quote.
The detailed specifications of the turbo molecular pump and the rotary pump are
given in section1 and 2.
Fig. 2: Schematic of baking chamber
Chamber Wall
Base compartment
Tube holding trays Sliding fixtures
Front View
Cut-outs for flexible
hoses/bellows Sliding doors
Section View from side
Section-1:Compact turbo molecular pump system specifications
I. Pumping Speed (Nitrogen)
Handling fluid : anhydrous ammonia
400 litre/sec. or better
II. Ultimate vacuum at pump inlet Better than 5 E-10 mbar
III. Inlet Flange ISO-CF 160 mm or suitable
IV. Fore line Flange KF 25 mm or suitable
V. Bearing compatible with ammonia gas
VI. Liquid Trap Zeolite dry trap shall be
provided at the fore line of the
turbo pump
VII. Installation Orientation Any
VIII. Cooling Air cooled ( preferred)
IX. Venting Flange 10 KF or suitable
X. Purge Gas Flange 10 KF or suitable
XI. Pressure gauge Suitable cold cathode gauge at the
inlet of turbo pump
XII. Compatible Drive-unit/controller shall be supplied.
XIII. Display screen: Liquid Crystal Display (LCD).
Accessories such as
Power supplies for powering pump series with integrated drive electronics
Venting valves
Heating jackets
Specifications for the gate valve
XIV. Body material Stainless steel or aluminium (compatible
with anhydrous NH3)
XV. Actuator Pneumatic actuator , double acting with
position indicator with solenoid
XVI. Flange DN 160 CF-F or suitable
XVII. Sealing material (for gate and bonnet) Compatible with ammonia gas
XVIII. Feed through Bellows (SS) sealed mechanism without
lubricant
XIX. Leak rate ~1x10-9 mbar l/sec
XX. Pressure range ~1x10-10 to ~1.5 bar
XXI. Mounting position Vertical
XXII. Supply voltage for solenoid 24 VDC
Section-2: Specifications for the rotary pump
a) Pumping speed ≥15m3/hr
b) Inlet flange DN 25 ISO KF or suitable
c) Exhaust flange DN 25 ISO KF or suitable
d) Ultimate Pressure i) With gas ballast
ii) Without gas ballast
~5x10-2 mbar &
~5x10-3 mbar
e) Compact full range Vacuum gauge 1000 to 5x10-9 mbar
f) Vacuum gauge display and control unit RS 232C/GPIB Interface or equivalent
g) O-rings / Seals Compatible with Ammonia
Pump shall have a anti suckback provision
h) Gate Valve Electro-pneumatically activated
i) Compressed air requirement 4 to 6 bar
j) Pumping oil Compatible with ammonia
k) In-line valve type Manually operated valve
l) Mobility for turbo-pumping system A trolley with caster wheels and proper
locking system capable of bearing the
weight of the turbo-pump, backing pump
and the related accessories
m) • Oil mist separator and condensate separator shall be provided
• Adsorption filter shall be provided.
• The system must be supplied with reputed make pumping systems from Agilent, Leybold,
and Pfeiffer.
v a c u u m h e a d e r p ip e
R o ta ry p u m p
T u rb o - m o lec u la r p u m p
R G A
T o a m m o n ia e x h a u st
A m m o n ia c y l in d e r
A m m o n ia h e a d e r p ip e
E le c tro -p n e u m a t ic v a lv e s
C o n tr o l p a n e l
E le c tro -p n e u m a tic v a lv es
B a k in g c h a m b e r
v a c u u m h e a d e r p ip e
R o ta ry p u m p
T u r b o -m o le c u la r p u m p
R G A
T o a m m o n ia e x h a u s t A m m o n ia c y lin d e r
A m m o n ia h e a d e r p ip e
n e e d le v a lv e s
a ll d im e n sio n s a r e in m m a n d a re a p p ro x im a te
N o te : L v a r ie s fr o m 0 .3 m to 3 m
E le c tro -p n e u m a tic v a lv e sH T T -1H T T -2
H T T -3H T T -4
H T T = H e a t T r a n sp o r t T u b e
D A C S
E v a c u a tio n & c h a rg in g sy s te m E v a c u a tio n & c h a r g in g sy s te m
A m m o n ia e x h a u st
w a te r ta n k
T ra y h o ld in g su p p o rt
v er tic a lly s l id a b le tu b e h o ld in g tra y s
Fig.3A: Typical sketch of anhydrous ammonia charging facility
Rotary pump
Turbo-molecular pump
To ammonia exhaust
Ammonia cylinder
flexible bellow of ~1.5m length
vacuum header pipe
RGA Ammonia header pipe
TRAY
all dimensions are in mm and are approximate
solenoid valves
Rotary pump
Turbo- molecular pump
To ammonia exhaust
Ammonia cylinder
vacuum header pipe
RGA Ammonia header pipe
solenoid valves
20mm dia.tube
20mm dia.tube
6.35mm dia.tube12.7mm dia.tube
TOP VIEW OF BAKING CHAMBER
TUBE HOLDING TRAY-1
solenoid valves
Control panel
DACS
Evacuation & charging system Evacuation & charging systemTray holding support
Fig. 3B: Schematic of top view of the ammonia charging system showing one flow line from vacuum header on either side.
Fig.3C: Typical sketch of side view of the ammonia charging system showing one flow line
5 Evacuation and charging system : Evacuation and charging system is a separate manifold system connecting the heat
transport tube with anhydrous ammonia cylinder and evacuation system. Two such
systems shall be installed on either side of the baking chamber to cater to the needs of
two channels of heat transport tubes.
Single channel heat transport tubesshall have connection with evacuation / charging
line on any one side of the climatic chamber. Each channel of the dual-channel heat
transport tube shall be connected to separate evacuation / charging line, generally
located on opposite sides.
Various types of valves, washers, flexible bellows / hoses, etc. shall be used as a part
of evacuation and charging system. Requirementsand brief descriptions of these
components aregiven below:
5.1 Valves Solenoid operated valves shall be used in evacuation and charging lines as shown in
Figure-4. The requirements for these valves are given in section 3.The valves in vacuum
line help in isolating the ammonia line from the vacuum pumpsduring ammonia
charging / evacuation. The valves in charging line need to be operated for a specified
duration to fill anhydrous ammonia into heat transport tubes. The valves shall be
selected such that ammonia charge control shall be in the order of ±0.1g.
Fig.4: Typical sketch showing location of valves in evacuation / charging lines
Section-3: Typical requirements for electro-pneumatic valves ( corrosive grade application)
Differential Pressure rating during operation Up to 12 bar
Operating temperature limits
� Lower limit
� Upper limit
~ 0oC
~ +45oC
Input power supply Suitable power supply unit shall be provided to
operate the valve within the above pressure
range
Solenoid Supply Voltage ~ 24 V DC
Actuator Double acting with solenoid valve & position
indicator
Differential pressure on gate valve 1 bar or better in either direction
Material of body Aluminium or SS - suitable grade (to be
compatible with anhydrous ammonia)
Flange connection& Centering ring Suitable (to connect to the charging system)
Leak tightness ~1 X 10-9 mbar liters/sec or better
End connections Size : 3/4” , Type : integral male
Vacuum range ~ 1x 10-10 mbar.
5.2 Flexible bellows / hoses:
Flexible bellows / hoses are required in order to accommodate heat transport tubes of
different lengths and shapes in the baking chamber. These bellows shallconnectthe needle
valves of heat transport tubes with the evacuation / charge lines. Lengths of the bellows
shall be designed to accommodate any specified lengths& shapes of heat transport tube in
the baking chamber with sufficient margins. Typical requirements for the bellows are
given in section 4.
Section 4: Typical requirements for flexible bellows / hoses
Working pressure ~ 10-9 mbar to ~ 45bar
Temperature range -50°C to +250°C
Material SS 316L
Hose dia. ( OD) 1/2”
Nominal length of hose ~ 1.5m
End connections Size : ½”
Type: integral male
Braided type Double braided
All tubing shall be seamless tube and made of SS-316L tube with electro polished for
handling ultra-high purity ammonia gas.
6 Baking chamber
Evacuation / degassing is to be done at high temperature in order to remove adsorbed air
molecules and moisture from the inside surface of heat transport tubes, manifolds and
valves. The baking chamber is a closed enclosurewith required door / opening / exhaust,
which houses a vertical support and horizontal platforms on the inside, onto which heat
transport tubes are loaded. The baking chamber and the horizontal platforms shall be
seated on a base compartment at a height suitable for working, as shown with a conceptual
sketch in Figure-2 with requirements as given in section 5.
The following shall be considered while designing the baking chamber:
• Heating system shall be designed with sufficient power margin, accommodating heat
leak / loss from heat source.
• Heaters shall be baffled from test space to prevent direct radiation on heat transport
tube.
• Materials compatible with ammonia shall be selected for all parts / components used in
heating system.
• The doors, located on front and back sides, shall be of sliding type and large enough to
load / unload maximum size heat transport tubes. The sliding doors shall have
provision to move up and down vertically and shall be operated both manually and
through PLC based motor control. Provision shall exist to lock the sliding doors when
in OPEN position, as a safety feature.
• Appropriate provision shall exist to have access to inside of the baking chamber for
connecting / disconnecting manifolds & valves, fixing / removing temperature sensors,
servicing / maintenance operations, etc. The system shall be custom built to meet all
the specified requirements.
• There shall have exhaust system with fansat the top side in order to purge out ammonia
vapour if any gets accumulated inside the chamber.
• Provision shall exist to treat and dispose ammonia collected in the exhaust system to
meet statutory and regulatory requirements for hazardous gases.
• The baking chamber shall have good structural rigidity to withstand the load of tubes
and its loading system. Also, the chamber shall be designed to withstand movement of
a person, weighing about 100kgs.
• The vendor shall design, fabricate, demonstrate, and supply a suitable mechanism for
safe loading and unloading of tubes into the facility. It shall be a light weight rigid
structure with suitable frame and made of SS 304L materials. This mechanism shall be
of manual pull-push type for tubes loading/unloading. The vendor shall submit the
proposed mechanism of the tubes loading system in the offer.
• The space between interior and exterior shall be insulated using multi layered,
environmental friendly, low thermal conductive, non-hygroscopic material.
• The base platform for the charging facility shall be of appropriate height (~ 1m) for
easy loading by a person in standing position.
• Thickness of the insulation shall ensure chamber outside temperature less than50oC
when chamber is maintained at its extreme temperature for 24 hrs or more.
• The chamber exterior shall be made of formed stainless steel-SS304L sheet or
equivalent. Also it shall be designed with sufficient reinforcement to withstand the
various loads.
• The chamber shall be a light weight rigid structure with suitable frame and made of SS
304L materials. All materials used inside the baking chamber must be compatible with
anhydrous ammonia.
Section-5: Typical requirements for baking chamber
Clear working volume (L x B x H) ~4m x ~3.5m x ~2.5m
Operating Temperature ambient to +250oC, adjustable
Temperature stability Within ±1oC of set value
Heatsource Electric resistance heaters
Temperature sensor/s for control Six or more PRTs inside enclosure on the tube
Temperature control By Programmable Logic Controller (PLC) based
data acquisition & control system (DACS)
operable through PC.
Average heating rate at atmospheric
pressure
~1.5°C/min. or better
Exterior wall temperature < 50oC
Duty cycle Continuous heating up to 7 days or more without
degrading its specification
Material i) Double walled chamber
ii) Inner / outer walls made of SS 304 and
powder coated outer surface
Thickness ~ 300mm
Other mandates:
(i) Provision for air ventilations
(ii) Air circulating fan.
(iii) Variable microprocessor based digital temperature controller with digital display and
thermometer.
(iv) Dampers shall be provided at the bottom and top of the baking chamber
7 Residual Gas Analyzer
Residual Gas Analyzer (RGA) shall be installed in the evacuation / charging lines to
measure channel-to-channel leak rate of ammonia in heat transport tubes. One channel
shall be filled with a small amount of ammonia gas and RGA connected in the line of
other channel shall measure ammonia leak rate and vice-versa. The specifications of the
RGA shall be as given in section 7.
Section-7: Typical specifications of the RGA
Detection range of Atomic Mass Unit
(AMU)
1 to 100 AMU
Partial pressure measurement range 10–5Torr to5 × 10–11Torr.
Resolution ≤ 1AMU
Programming software Lab view or any suitable software
Interfacing with PC Through RS-232 and Ethernet cable
8 Cryostat with cooling pads
An approx. length of about 300mm to 500mm at the non-filling end of heat transport tubes
shall be cooled and maintained at a temperature of -20ºC, using individual cooling pads,
during the process of transferring anhydrous ammonia vapour. The cooling system shall
have the requirements as given in section 6 of Table-1.
Section-6: Typical requirements for Cryostat
Circulating Fluid temperature Adjustable from ~ -35oC to ~ +40oC
Cooling capacity ~150W at -20oC
flow rate ~ 15 litre/min
Pump flow pressure Variable
Type of temperature sensor PRT
Temperature accuracy ± 1oC of set value
Setting/ display resolution 0.1oC
Digital interface RS 232 or equivalent
Temperature control By Programmable Logic Controller (PLC) based data
acquisition & control system (DACS) operable
through PC
Connecting Tubes Flexible. About 2m length each for inlet and outlet connections of about 12.5mm diameter with suitable thermal insulation
9 Sensors & Instrumentation
9.1 Facility sensors: Vendor shall supply and incorporate the necessary sensors for measuring the pressure,
temperature, fluid flow and leaks at appropriate locations in the charging equipment.
9.2 User sensors: The vendor shall incorporate the temperature sensors for measuring the temperature at
various locations on the heat transport tubes in the equipment.
Vendor shall provide adequate numbers of suitable types of temperature sensors
required for operation and control of the entire system. The total number of sensors
shall be approximately60 Nos.
These sensors shall be easily mountable and detachable using connectors to /from
tubes. They shall have both male-female connectors for easy routing / removal inside
the baking chamber.
Sensors shall be cadmium free inside the chamber.
9.3 Run time meter
Run time counter shall be provided for recording process running time and total
cumulative running time of the chamber.
9.4 Digital panel meters
Individual digital panel meters shall be provided to display the following parameters
of the baking chamber:
i) Chamber temperature
ii) Chamber pressure
iii) Humidity level
9.5 Mimic panel: The vendor shall provide a circuit diagram of ammonia charging facility with LED
indicators to show the status of each unit/equipment/valves/pumps/heaters/cryostat /etc.
Separate status display for turbo molecular pump controllers, gauge controllers, heaters,
controllers, etc. shall be provided.
10 PLC based Data Acquisition & Control System (DACS)
Programmable Logic Controller (PLC) based Data Acquisition and Control System
(DACS) is required for acquiring, controlling, logging, storing, displaying and analyzing
the on-line and off-line parameters such as vacuum data, temperature data, and electrical
parameters (voltage, current etc.). Necessary ON/OFF switchers, timers, display monitors,
etc. shall be provided in a control panel in addition to front end interface with personal
computers. The DACS shall have the following specifications:
• The scan period for monitoring shall be 10 seconds or less and selectable for overall
acquisition and control functions.
• The Data storage shall be at least once in 30 seconds and time selectable.
• The system shall be modular and scalable.
• The hardware shall be rack mountable.
• Supervisory Control and Data Acquisition (SCADA) and PLC based GUI software
shall be used for control function.
• The PLC units, input/output modules and digital input/output modules shall be
connected through a common back plane and data and communication bus. Total
number of monitoring/ controlling channels shall be achieved by interconnecting many
modules.
• The control unit and input/output system shall be complete with control and recording
environment capable of continuous analog, logic and sequential control combined with
secure data recording.
PLC (Programmable Logic controller)
• PLCs shall have redundancy.
• Latest version of processor with suitable processing speed and functional capabilities
shall be provided. The PLC processor shall also have spare capacity of its memory to
take care of future up gradation of data acquisition and control logic programme.
• It shall have other features such as software protection with password, Ethernet
communication between peer systems, serial port, and operator panel with touch
screen display for programming and visualizing all the control functions and variables
for running the facility in standalone mode.
• Three phase power protection:-
Single phasing protection
Reverse phase protection (Phase sequence protection)
Noise level of the chamber shall be less than 70dB (A) (typically at 1 m distance from
chamber)
11 Safety and protection
• Vendor shall provide false tolerance and fail safe features in case of mains power
failure.
• Safety over temperature protection independent of equipment shall be employed to
switch off / trip the main contactor when the chamber temperature exceeds the
maximum set limit.
12 Wiring
All the wires shall be suitably numbered for easy identifications and documentation,
Strapped/bundled, and shall be routed in the ducts.
i. All electrical circuits shall have reliable safety devices like fuse or circuit breaker.
ii. Power connection terminal block and ground lugs shall be provided for easy utility
connections.
Complete wiring of the facility shall meet International and National Standard Code.
13 Environment:
The whole equipment must be operational continuously under the ambient condition ranging from +100C to +500C and relative humidity 20% to 90% RH.
14 Utilities available with ISRO/ISAC
• Cooling water pressure: ~ 3.0 bar
• Pneumatic air supply pressure: 5 bar to 6 bar
• Electricity : Voltage: 230 V single phase ac / 415V 3 phase ac± 10%, & Frequency :
50Hz
15 Installation, Commissioning and Testing
a. Installation, testing and commissioning shall be carried out by the VENDOR at
ISITE / ISAC / ISRO, Bangalore.
b. Vendor is responsible for unloading, unpacking, erection, installation and
commissioning of total facility at ISAC / ISRO, Bangalore.
c. Final acceptance of the facility is subjected to the successful demonstration of the
ammonia charging conducted at the time of commissioning at ISAC. The
acceptance test matrix shall be mutually agreed between vendor and ISRO.
d. No logistic / tool support, in any form, until unless specified in the final contract,
will be provided by ISAC / ISRO. Vendor shall consider only the normal working
hours of 08:30AM to 05:00PM from Monday to Friday (excluding holidays
declared by ISAC / ISRO).
16 Prelim
inary Design Review
Preliminary Design Review (PDR) will be conducted for all vendors, approximately
within a month after the due date for Expression of Interest. Prior to this, the vendor
shall submit a detailed design review document containing detailed description
ofdesign of baking chamber, high vacuum evacuation system, heating&cooling
systems, data acquisition & control system, etc. along with realization plan, test
/validation plan, detailed schedules and other relevant data.
17 Deliverable Documents
Hard/and soft copy of the following documents/information, but not limited to, are
required to be submitted by the vendor, along with the proposal:
Brief overview of vendor’s infrastructure, technical capabilities and purchase order
copies of similar facilities developed & installed for other organizations/industries.
Technical compliance statement mentioning compliance details against each
Note:
The technical compliance statement should be given point-wise for all of the
specifications. Mere writing “complied” against each of the specification points is not
sufficient. Instead the exact numerical values are to be mentioned, wherever required.
Any deviation in specification leading to better performance shall be clearly
highlighted with merits. Otherwise the offer will not be considered.
specification with description / numeric values / etc. wherever required.
Preliminary design review document(including details of proposed plan, design
concepts, work flow charts, schedules& delivery period, conceptual
drawings,tentative facility layout plan, proposed software for automation, subsystem
details / data sheets /manuals, etc.)