exploring strategy translation in projects

229
EXPLORING STRATEGY TRANSLATION IN PROJECTS A thesis submitted to The University of Manchester for the degree of Doctor of Philosophy in the Faculty of Engineering and Physical Sciences 2016 Mazen Mohammed Ali Melebari School of Mechanical, Aerospace, Civil Engineering, The University of Manchester

Upload: others

Post on 11-Feb-2022

2 views

Category:

Documents


0 download

TRANSCRIPT

EXPLORING STRATEGY TRANSLATION IN

PROJECTS

A thesis submitted to The University of Manchester

for the degree of Doctor of Philosophy

in the Faculty of Engineering and Physical Sciences

2016

Mazen Mohammed Ali Melebari

School of Mechanical, Aerospace, Civil Engineering,

The University of Manchester

2

Table of Contents

TABLE OF CONTENTS ............................................................................................ 2TABLE OF FIGURES ................................................................................................. 6LIST OF PHOTOGRAPHS ......................................................................................... 7LIST OF TABLES ....................................................................................................... 8LIST OF THE ABBREVIATIONS ............................................................................. 9ABSTRACT .............................................................................................................. 11DECLARATION ....................................................................................................... 12COPYRIGHT STATEMENT .................................................................................... 13ACKNOWLEDGMENT ........................................................................................... 14DEDICATION ........................................................................................................... 15LIST OF PUBLICATIONS ....................................................................................... 16

CHAPTER ONE..................................................................................................................17

INTRODUCTION...............................................................................................................171.1 RESEARCH OVERVIEW ............................................................................... 171.2 RESEARCH PROBLEM AND FOCUS OF THE STUDY ............................ 191.3 RESEARCH AIM AND OBJECTIVES .......................................................... 191.4 RESEARCH QUESTIONS .............................................................................. 201.5 RESEARCH PROPOSITION .......................................................................... 201.6 RESEARCH FRAMEWORK .......................................................................... 211.7 PROPOSED METHODOLOGY ..................................................................... 221.8 THESIS STRUCTURE .................................................................................... 22

CHAPTER TWO.................................................................................................................24

LITERATURE REVIEW PART I: STRATEGY FROM A CAPABILITIES

PROSPECTIVE...................................................................................................................242.1 OVERVIEW ..................................................................................................... 242.2 CAPABILITIES PERSPECTIVE .................................................................... 242.3 STRATEGIC MANAGEMENT TOOLS - VISION AND MISSION ............ 252.4 STRATEGY DEFINITION AND STRATEGIC PLANS ............................... 282.5 STRATEGY THEORIES AND PERSPECTIVES .......................................... 312.6 DEVELOPMENT AND PLANNING PROCESSES OF STRATEGY .......... 332.7 STRATEGY IMPLEMENTATION ................................................................ 35

3

2.8 PERFORMANCE MEASUREMENT AND THE BALANCED SCORECARD

........................................................................................................................ 382.9 PROJECT MANAGEMENT ........................................................................... 442.10 PROGRAMME AND MULTIPLE PROJECTS MANAGEMENT .............. 492.11 PORTFOLIO, AND PROJECT PORTFOLIO MANAGEMENT (PPM) ..... 502.12 STRATEGY IMPLEMENTATION OBSTACLES, CHALLENGES, ISSUES

AND PROBLEMS .................................................................................................... 542.13 ISSUES OF PROJECTS, MULTIPLE PROJECTS, PROGRAMME, AND

PPM ........................................................................................................................ 582.14 ORGANISATIONAL BEHAVIOR ASPECTS ............................................. 662.15 CRITICAL SUCCESS FACTORS FOR IMPLEMENTATION ................... 682.16 CLOSING THOUGHTS ................................................................................ 69

CHAPTER THREE............................................................................................................72

LITERATURE REVIEW PART II: STRATEGY FROM A PRACTICE

PROSPECTIVE...................................................................................................................723.1 OVERVIEW ..................................................................................................... 723.2 PRACTICE PERSPECTIVE ............................................................................ 723.3 TRANSLATION THEORY AND THE STRATEGY .................................... 773.4 VEHICLE AND MODEL OF THE TRANSLATION .................................... 803.5 TRANSALTION AS COMMUNICATION TOOLS ...................................... 833.6 STRATEGY AS PRACTICE (SAP) ................................................................ 853.7 CLOSING THOUGHTS .................................................................................. 90

CHAPTER FOUR...............................................................................................................93

RESEARCH DESIGN AND METHODS......................................................................934.1 OVERVIEW ..................................................................................................... 934.2 RESEARCH AIM AND OBJECTIVES .......................................................... 934.3 RESEARCH PHILOSOPHIES ........................................................................ 944.4 RESEARCH PARADIGMS ............................................................................ 954.5 RESEARCH METHODOLOGY ..................................................................... 984.6 RESEARCH APPROACH: INDUCTIVE ..................................................... 1014.6.1 DATA COLLECTION TECHNIQUES: INTERVIEWS AND

DOCUMENTS ........................................................................................................ 1034.6.2 SECURING ACCESS .................................................................................. 1034.6.3 INTERVIEW METHODS ........................................................................... 105

4

4.6.4 OPEN-ENDED QUESTIONS ..................................................................... 1074.6.5 OBSERVATION .......................................................................................... 1094.6.6 DOCUMENTS ............................................................................................. 1094.7 RESEARCH STRATEGY: MULTIPLE CASE STUDY .............................. 1104.8 UNIT OF ANALYSIS ................................................................................... 1124.9 DATA PREPRATION ................................................................................... 1134.9.1 CODING AND TEMPLATE ANALYSES ................................................. 1134.10 CROSS REFERENCES AND TRUTH VALUE ......................................... 1154.11 ETHICAL CONDUCT ................................................................................ 1164.12 SUMMARY ................................................................................................. 116

CHAPTER FIVE...............................................................................................................118

PHASE ONE INTERVIEWS..........................................................................................1185.1 OVERVIEW ................................................................................................... 1185.2 INTRODUCTION .......................................................................................... 1185.3 PLANNING AND DESIGNING OF THE PHASE-ONE INTERVIEWS ... 1195.3.1 SECURING DATA ACCESS ........................................................................ 1195.3.2 INTERVIEWED ORGANISATIONS ........................................................... 1195.3.3 PARTICIPANTS’ PROFILES ....................................................................... 1205.4 DATA PREPARATION ................................................................................ 1245.5 ANALYSIS AND DISCUSSION .................................................................. 1245.6 SUMMARY OF PHASE ONE ...................................................................... 131

CHAPTER SIX..................................................................................................................133

PHASE TWO INTERVIEWS........................................................................................1336.1 OVERVIEW ................................................................................................... 1336.2 INTRODUCTION .......................................................................................... 1336.3 PLANNING AND DESIGNING THE PHASE TWO INTERVIEWS ......... 1356.3.1 SECURING DATA ACCESS ........................................................................ 1356.3.2 INTERVIEWED ORGANISATIONS ........................................................... 1356.3.3 PARTICIPANTs’ profiles .............................................................................. 1366.4 DATA PREPARATION ................................................................................ 1386.5 DATA ANALYSIS ........................................................................................ 1396.6 DISCUSSION ................................................................................................ 1706.7 SUMMARY OF PHASE TWO ..................................................................... 172

CHAPTER SEVEN...........................................................................................................173

5

CASE STUDIES.................................................................................................................1737.1 OVERVIEW ................................................................................................... 1737.2 CASE STUDY: IT PROJECTS ..................................................................... 1747.3 SUMMARY OF CASE STUDY: IT PROJECTS .......................................... 1787.4 CASE STUDY: CONSTRUCTION PROJECTS .......................................... 1807.5 SUMMARY OF CASE STUDY: CONSTRUCTION PROJECTS .............. 183

CHAPTER EIGHT...........................................................................................................186

DISCUSSIONS...................................................................................................................1868.1 DISCUSSTION .............................................................................................. 1868.2 TRANSLATION CHALLENGES IN PROJECTS ....................................... 1898.2.1 CHANGE ........................................................................................................ 1908.2.2 INDIVIDUAL INFLUENCES ....................................................................... 1928.2.3 THE ROLE OF THE OBJECTS .................................................................... 1948.3 IMPROVING THE TRANSLATION OF THE PRACTICE ............................ 197

CHAPTER NINE...............................................................................................................200

CONCLUSIONS AND FUTURE RESEARCH..........................................................2009.1 CONCLUSIONS ............................................................................................ 2009.2 REFLECTIONS ON THE GENERAL PRPOSITIONS AND THE

CONCEPTUAL FRAMEWORK ............................................................................ 203• 9.2.1IMPLICATIONSFORTHESTRATEGYMAKER....................................................................205• 9.2.2IMPLICATIONSFORPROJECTMANAGEMENTPRACTITIONERS..............................206• 9.2.3IMPLICATIONSFORTHEORYOFTRANSLATION.............................................................207

9.3 LIMITATIONS .............................................................................................. 2079.4 RECOMMENDATIONS FOR FURTHER RESEARCH ............................. 208APPENDICES ......................................................................................................... 217APPENDIX A - INFORMED CONSENT FORM .................................................. 218APPENDIX B - INSURANCE ASSESSMENT FORM ......................................... 220APPENDIX C - PARTICIPANT INFORMATION SHEET .................................. 222APPENDIX E - ETA STRATEGY II GUIDELINES - DOCUMENT ANALYSIS

AND SITE VISIT .................................................................................................... 224

6

Table of Figures

Figure1.1:ResearchFrameworktoFulfiltheGapinKnowledge.....................................21Figure2.1:Conceptualframeworkforstrategytheoriesandperspectives..................37Figure2.1:OriginalStructureofBalancedScorecard(R.Kaplan,2008:1254)............40Figure2.2:Translatingmission,values,andvisionintoDesiredOutcomes(Kaplan

andNorton,2008:73).......................................................................................................................41Figure2.3:OutcomesofStrategyDevelopmentProcesses.................................................42Figure2.4:ProblemsofStrategyImplementation(PellegrinelliandBowman,

1994:126).............................................................................................................................................45Figure2.5:ProjectManagementApproachforStrategyImplementation

(PellegrinelliandBowman,1994:127)......................................................................................46Figure2.6:ProjectLifecycleProcess(GrayandLarson,2008).........................................47Figure3.1:TranslationconceptualframeworksCzarniawska(2002)...........................80Figure3.1:TheoriesRelatedtotheFieldofSAP(Jarzabkowskietal.,2007)...............87Figure3.2:ConceptualFrameworktoAnalyseSAP(P.Jarzabkowskietal.,2007:11)

.................................................................................................................................................................88Figure4.1:FourfoldResearchParadigms(Saundersetal.2012:141)...........................96Figure4.2:TheResearchDesignProcess..................................................................................99Figure8.1:ChallengesofStrategyTranslation....................................................................189Figure9.1:ReflectionsonConceptualFrameworkforSAP.............................................205

7

List of Photographs

Photograph1:SignboardofVocationalInstituteProjectinEta....................................229

8

List of Tables

Table2.1:Referencetableofarticlesforstrategyimplementationchallenges..........55

Table2.2:ObstaclestoStrategyExecution(Hrebiniak,2008)..........................................55

Table2.3:ChallengesofimplementingformulatedStrategy(Hrebiniak,2008;

Sterling,2003;Heideetal.,2002)...............................................................................................57

Table2.4:Referencetableofprojectimplementationchallenges...................................59

Table2.5:majorchallengesofprogrammemanagementpractice(Shehuand

Akintoye,2010).................................................................................................................................59

Table2.6:ProblemAreasofmulti-projectenvironments(ElonenandArtto,2003)61

Table2.7:Implementationchallengesforpracticingproject/programme/portfolio

management(ShehuandAkintoye,2010;ElonenandArtto,2003;Cooperetal.,

1999;Cooperetal.,1998)..............................................................................................................63

Table3.1:summaryofstrategyperspectivesbothcapabilitiesandpractice..............92

Table4.1:TwoPhasesinterviewscomparision...................................................................100

Table4.2Mappinginterviewquestionswithresearchobjectives................................108

Table5.1:ParticipatingOrganisationsinPhaseOne.........................................................120

Table5.2:PhaseOneInterviewees’Profiles.........................................................................121

Table5.3:PhaseOneFindingsExperiencedbytheCaseStudyOrganisations..........131

Table6.1:CaseStudyOrganisationsinPhaseTwo.............................................................136

Table6.2:ProfileofPhaseTwoInterviewees......................................................................137

Table7.1:summaryoftranslationprocessinITProjects................................................179

Table7.2:summaryoftranslationanalysisinConstructionProjects.........................185

9

List of the Abbreviations

MVV Mission, Vision and Values

BSC Balanced Scorecard

HBR Harvard Business Review

ROI Return on Investment

IRR Internal Rate of Return

PPM Project Portfolio Management

PMBOK Project Management Body of Knowledge

PMI Project Management Institute

APM Association of Project Management

ANT Active Network Theory

SAP Strategy as Practice

STS Science and Technology Studies

SCE Saudi Council of Engineering

SABIC Saudi Arabia Basic Industries Corporation

PMO Project Management Offices

PgMO Programme Management Offices

PMP Project Management Professional

PgMP Programme Management Professional

HE Higher Education

MENAFN Middle East North Africa Networks

IBS Individual Banking Sector

EMC Executive Management Committee

SGA Stage Gate Approach

BCM Business Case Model

CA Coupling Approach

SWOT Strength, Weaknesses, Opportunities, and Threats

IT Information Technology

EPM Enterprise Project Management

CAPS Centre for Advanced Projects Support

VPP Vice President for Projects

10

BTG Business Transformation Group

VP Vice President

11

Abstract

Strategy Translation in Projects

Mazen Mohammed Ali Melebari, University of Manchester, PhD

Many management studies report poor implementation of organisational strategy into practice (Yukl and Lepsinger, 2007; Li et al., 2008) and the absence within the literature of the question of how to translate strategy into effective practice provides the encouragement for this study. There are suggestions that by adopting a project management approach, organisations can better implement their overall strategies, meaning that what they do is properly and totally aligned with their goals (Pellegrinelli and Bowman, 1994). However, recent studies have concluded that project management makes little contribution to the achievement of organisational objectives, and possibly causes failure in this respect (Young and Grant, 2014). That said, Young and Grant (2014) have not provided any detailed information on the reason for such failure. At the same time, some management studies have revealed a number of challenges that confront organisations when approaching strategy implementation. Given these observations, this study aims to explore how organisations in Saudi Arabia are practising project management. It does so by adopting a qualitative method, involving thirty (30) face-to-face semi-structured and unstructured interviews undertaken in two phases with five organisations from the banking, property development, and higher education sectors. Two exploratory case studies (IT and Construction) were used to investigate the translation challenges in respect of strategy and project management implementation. From these, the study has identified a number of challenges confronting the participating organisations, and shows these challenges to be inter-related. Furthermore, it arrives at an understanding of why these challenges arise by investigating how the practice has been translated in these organisations. The tools and materials which resulted as objects from the translation are used to establish common knowledge, but are insufficient to create a clear view of the strategy within the participating organisations. Three main challengers related directly to the translation of project management practice emerged, namely: change, individual influences, and the role of the objects. The study makes several recommendations to improve the translation concept so that strategy implementation and overall project management practice can be enhanced. Additionally, it makes recommendations for further research to continue the efforts in this field of enquiry.

12

Declaration

No portion of the work referred to in the thesis has been submitted in support of an application for another degree or qualification of this or any other university or other institute of learning.

13

Copyright Statement

The following four notes on copyright and the ownership of intellectual property rights must be included as written below: i. The author of this thesis (including any appendices and/or schedules to this thesis) owns certain copyright or related rights in it (the “Copyright”) and s/he has given The University of Manchester certain rights to use such Copyright, including for administrative purposes.

ii. Copies of this thesis, either in full or in extracts and whether in hard or electronic copy, may be made only in accordance with the Copyright, Designs and Patents Act 1988 (as amended) and regulations issued under it or, where appropriate, in accordance with licensing agreements which the University has from time to time. This page must form part of any such copies made.

iii. The ownership of certain Copyright, patents, designs, trade marks and other intellectual property (the “Intellectual Property”) and any reproductions of copyright works in the thesis, for example graphs and tables (“Reproductions”), which may be described in this thesis, may not be owned by the author and may be owned by third parties. Such Intellectual Property and Reproductions cannot and must not be made available for use without the prior written permission of the owner(s) of the relevant Intellectual Property and/or Reproductions.

iv. Further information on the conditions under which disclosure, publication and commercialisation of this thesis, the Copyright and any Intellectual Property and/or Reproductions described in it may take place is available in the University IP Policy (see http://documents.manchester.ac.uk/DocuInfo.aspx?DocID=487), in any relevant Thesis restriction declarations deposited in the University Library, The University Library’s regulations (see http://www.manchester.ac.uk/library/aboutus/regulations) and in The University’s policy on Presentation of Theses

14

Acknowledgment

First and the foremost, all thanks to Allah Almighty for helping me, providing me with faith, and for giving me the patience to complete this study. I would like also to thank my country for sponsoring me during my study. Special thanks go to the King Abdullah Scholarship Programme, for sincere and generous support during my PhD Journey. Indeed, this has been a long journey that seemed sometimes to be never ending. Looking back, I remember there were moments when I almost surrendered but then Allah gave me the strength to carry on; and also sent many people to me to offer support so that I could overcome that difficult time. There are many people to whom I would like to express my deepest gratitude for their encouragement and support. Firstly, I would like to thank my supervisor Dr Paul W Chan, for his continuous guidance and advices, which has been fundamental in shaping the thesis. I would also like to acknowledge the help of Faculty administration member, Ms Beverly Knight. Secondly, I am very thankful to those organisations, managers, and individuals who participated in the study during the data collection phase. Special thanks are due to the University Vice President for Projects, and all presidency staff members, for their support in facilitating data collection and enabling the fieldwork. Thirdly, I would like to express my deepest appreciation to my friends and colleagues. Special thanks to Dr Syed Waqar, and Dr Abdullah Al-Shehri, for their encouragement and emotional support during the hard time I experienced in completing this thesis. Finally, I thank my family members for their sincere prayers and encouragements. Last but not least, I would like to express my profound thanks to my lovely wife Najla Jan and my beloved children for their patience and support during my study.

15

Dedication

To my father’s soul.

To my mother’s soul, who passed away last year before witnessing my

graduation.

To my lovely wife Najla.

To my beloved son Mohammed and my sweetie daughters Maya, Sara, and

Leen.

16

List of Publications

a) Conference Papers

1. Melebari, Mazen “Projects Execution Challenges in Private Sector Organizations in Saudi Arabia”. The 5th Saudi International Conference (SIC2011). Published in SIC2011, The University of Warwick, Coventry, 23th – 26th Jun 2011.

b) Posters

1. Melebari, Mazen “Challenges Facing Projects Execution in Private Sector Organizations in Saudi Arabia”. The 5th Saudi International Conference (SIC2011). Published in SIC2011, The University of Warwick, Coventry, 23th – 26th Jun 2011.

2. Melebari, M., Chan, P. “The Contribution of the Performance Management of Multiple Projects in Achieving Organisation Strategy ”. Post Graduate Research Conference, School of MACE, The University of Manchester, 11th June 2009.

17

CHAPTER ONE

INTRODUCTION

1.1 RESEARCH OVERVIEW

It has been argued that the adoption of a project management approach would

help in realising organisational strategies (Pellegrinelli and Bowman, 1994).

Since that claim, project management has become increasingly important as

more work is continually organised through projects and programmes (Winter et

al., 2006). Accordingly, many frameworks, models, and concepts based on the

project management approach have been developed and practised that aim to

offer better connectivity between projects and organisation strategies (Dietrich

and Lehtonen, 2005). The project management approach provides a process by

which organisational strategies can be translated into goals and objectives; that

said, the implementation is not necessarily straightforward as many challenges

are encountered in practice (Shehu and Akintoye, 2010; Elonen and Artto,

2003).

Recent research has concluded that project management contributes little or less

than expected in realising organisational strategy. The research conducted in the

public sector by Young et al. (2012), and replicated by Young and Grant (2014)

in the private sector, which examined the effectiveness of project management

frameworks, referred to systematic deficiencies of these frameworks as vehicles

for achieving organisational strategy, but did not provide much explanation of

the reasons for these shortcomings. Additionally, Winter et al. (2006) observed

that project management research attracts criticism for its lack of relevance to

practice.

Given the dynamic, and complex nature of strategy implementation, more

attention is being accorded to the way in which strategy is translated into reality,

18

and various researchers have made an effort to understand this process from the

practice perspective. These efforts need to be linked directly with the strategy as

practice (SAP), and theory of translation. Jarzabkowski (2004) emphasises that

the SAP concept embodies the idea of strategy as something that organisations

and people do rather than possess. And the concept of translation is a vehicle to

describe how the idea of SAP moved around the globe, according to

Czarniawska and Sevon (2005). No practice or institution can travel unless it is

simplified and materialised, and hence this must occur for it to be capable of

moving from one place and time to another (Czarniawska and Sevon, 2005;

Czarniawska, 2002). Using the theory of translation and the concept of SAP,

this study aims to explore the process of project management to understand how

the practice has been simplified and materialised. The study has taken the work

of Parmigiani and Howard-Grenville conducted in 2011, which views strategy

from capabilities and practice perspectives, the former being focused on routines

as whole ‘entities’, and the latter focused on the ‘parts’ of routines.

To summarise, it can be seen firstly, that there is lack of research in the area of

strategy implementation, as the organisational management literature

concentrates more on identifying issues and challenges related to strategy

formulation. Secondly, there is a need for project management research to relate

to practice, since it mostly reports the capabilities perspective, based on linear,

analytic, and rational approaches intent upon planning, scheduling, and

controlling parts of the project, whereas in the real world projects are

undertaken through the efforts of humans and objects within a social context,

thereby being implemented in a dynamic and frequently-changing environment.

Clearly, therefore, there is a requirement for a better appreciation of the

challenges associated with strategy implementation, and there is a strong

rationale for a study like this one that goes beyond the exploration of the usual

obstacles and challenges to include the practice perspective, which has a

significant influence in furthering our understanding of real project

environments.

19

1.2 RESEARCH PROBLEM AND FOCUS OF THE STUDY

From what has been said so far, it can be seen that recent research findings

support the notion that project management contributes little to the eventual

realisation of organisational strategy, and that project management frameworks

seem to suffer from systematic deficiencies, the reasons for which are not

described (Young et al., 2012; Young and Grant, 2014). Furthermore, Winter et

al. (2006) have observed that project management research attracts criticism for

its lack of relevance to practice.

Hence, it is apparent that the research problem is double-sided. On one side,

strategy is not a fully-formed entity that exists for straightforward

implementation but is rather mediated through individual actors and objects or

artefacts that in themselves have resulted from the strategy translation process.

The capabilities perspective acknowledges that individuals are involved in the

processes but neglects the influences of both individual actors and objects. On

the other side, in the specific case of project management, criticism is made

because of its lack of relevance to practice; essentially it is viewed as a ‘black

box’ mainly interested in what routines accomplish in the effort to achieve

organisational goals. Consequently, this study concerns itself with the theory of

translation, and an exploration of how the approach is being translated in the

real project world, thereby emphasising what happens inside the ‘black box’ and

how practice and routines are enacted on a day-to-day basis.

1.3 RESEARCH AIM AND OBJECTIVES

The study aims to explore how project management is practised in a real project

environment, and to understand the influences of the translation model on the

implementation. It takes Saudi Arabian organisations that use project

management as the vehicle for implementing their organisational strategy, as the

data collection sites. In order to achieve this aim, the following objectives are

identified:

a) To review the relevant theoretical perspectives on strategy and project

management, with particular emphasis on implementation.

20

b) To evaluate the usefulness of the project management approach in

achieving organisational strategy in Saudi Arabia.

c) To investigate the challenges confronting project management

implementation through practice and translation theory.

d) To explore the models used in translating both strategy and the project

management approach in practice.

e) To examine the roles and implications of objects in strategy

communications.

1.4 RESEARCH QUESTIONS

In order to accomplish the above objectives, several questions which emerge

after a comprehensive review of the literature related to strategy implementation

and project management (in particular the translation of the practice) are

formulated as research questions, these being:

1 Why does the project management approach make only a small

contribution, if any, to the achievement of organisational strategy?

2 How is organisational strategy being translated?

3 What is the translation model used for translating organisational strategy

and project management?

4 Who is involved in the translation of strategy and project management

practice?

5 What are the translation challenges?

6 What objects are produced for communicating organisational strategy?

7 How do these objects connect to the individual daily activities within the

entire organisation?

1.5 RESEARCH PROPOSITION

The propositions made in this study are driven from the review of the literature

(Chapters Two and Three). In this respect, there are two propositions to be

explored, these being: firstly, successful strategy implementation can be

achieved through a project approach; and secondly, in project-oriented

21

organisations, the project management approach would be implemented

differently.

1.6 RESEARCH FRAMEWORK

The study draws on the work of Parmigiani and Howard-Grenville (2011), as

seen in Figure 1.1. This figure depicts the gap in knowledge associated with

strategy as viewed from the capabilities and practice perspectives, and indicates

how this study intends to bridge that gap through a consideration of the strategy

as practice (SAP) and the theory of translation.

Figure 1.1: Research Framework to Bridge the Gap in Knowledge

Gap Neglects the influences of individual actors and objects

Fails to uncover what inside the ‘black box’

• Understanding the role of individual actors and objects • Exploring what is being travelled? Is it the actual practice

of project management or only the name of the practice? • Using the theory of translation for better understanding of

practice challenges

Capabilities Perspective

Deliberate approach Strategy delivered as

intended Focus on routine as

'Black Box'

Practice Perspective

Emergent approach Response to market

changes Focus on what inside

the 'Black Box'

SAP and the Theory of Translation

22

1.7 PROPOSED METHODOLOGY

In order to answer the research questions posed in Section 1.4, and consequently

to achieve the aim and objectives presented in Section 1.3, a qualitative

approach is proposed, in which both secondary and primary data are obtained.

Secondary data come from an in-depth literature survey, while primary data are

gathered from an empirical exercise with two case studies of organisations in

Saudi Arabia. These organisations serve as the context for exploring strategy

and project management implementation, and the methodology involves 30

interviews with individuals, documentary analysis, and non-participant

observation.

1.8 THESIS STRUCTURE

The thesis is presented in nine chapters and a brief indication of the content of

each is now given.

Chapter One: this presents an overview of the research work, the aim,

objectives, and the research questions that study seeks to answer.

Chapter Two: this conducts a review of relevant management literature on

strategy from capabilities perspective.

Chapter Three: this provides a review of relevant literature review on the

strategy from practice perspective with emphasis on the theory of translation.

Chapter Four: this discusses in detail, the qualitative research methodology

adopted in the study to achieve the research objectives.

Chapter Five: this presents an analysis of the initial findings of the exploratory

interviews that constitute Phase One of the empirical work. Additionally, it

explains the process of data gathering, data analysis and the techniques used.

23

Chapter Six: validates the findings of the Phase One interviews and provides the

results gained from the in-depth analysis of the interviews conducted in Phase

Two of the empirical work.

Chapter Seven: presents two case studies undertaken in five organisations in

Saudi Arabia namely: IT projects, and construction projects.

Chapter Eight: offers a general discussion of the challenges related to the

translation of the practice that results from case studies.

Chapter Nine: this draws a conclusion, and makes recommendations

Several appendices, which are pertinent to the thesis are attached at the end.

24

CHAPTER TWO

LITERATURE REVIEW PART I: STRATEGY

FROM A CAPABILITIES PROSPECTIVE

2.1 OVERVIEW

This chapter reviews the literature pertaining to strategy from capabilities lens.

It introduces the concept of strategy, and the processes of strategy development,

and implementation. Various management tools are available for translating the

strategy into routine activities through performance measurement, balanced

scorecards and project management approaches that presented and discussed,

and as part of this discussion different concepts associated with project

management, such as projects, programmes and portfolios, are elaborated upon.

2.2 CAPABILITIES PERSPECTIVE

Capabilities are one of common terms that associated with strategy and

management topics. However the meaning can be translated depending on the

use of the word (McCabe, 2010). This study takes the benefit of work of

Parmigiani and Howard-Grenville conducted in (2011), which viewing strategy

from capabilities and practice perspectives, where capabilities perspective

focused on routines as whole “entities” and the practice perspective focused on

the “parts” of routines. Number of pervious studies has reviewed to establish

common understanding with related terms. Parmigiani and Howard-Grenville

(2011) define capabilities as range of processes, actions, and skills a firm do at

any time to manage targeted performance. Capabilities sometimes used

interchangeably with routines that seen as performance targets, which providing

mechanisms for control and bases for replication.

25

Organizational economists tend to treat routines as a “black box,” mainly

interested in the purpose or motivation for routines and their impact on firm

performance (Parmigiani and Howard-Grenville, 2011). Routines viewed as

building blocks of the capabilities with repetitive and context-dependent

characteristics. Repetitive activities in combinations with other resources

constitute the organizational capabilities (Parmigiani and Howard-Grenville,

2011). Organizational capabilities defied as social complex routine that

determine the performance by transforming the inputs into significant outputs.

There are two types of capabilities, ordinary that related to typical operations,

and dynamic, which involve creation and change (Winter, 2003; Helfat et al.,

2007). Zollo and Winter (2002: 348) define dynamic capabilities as “systematic

patterns of organizational activity aimed at the generation and adaptation of

operating routines”. Dynamic capability focuses on the effectiveness of

performed activities involves a well-managed cluster of activities what some

call a ‘people strategy’. For that reason says Feiler and Teece (2014), it have to

be developed ‘in-house’ through a set of activities and cognitive processes

focused on the organization’s own routines. Dynamic capability is important

concept in the strategy literature, which defined as a meta-process that

coordinates a number of processes, best practices or competencies to manage

comprehensively and systemically, something that is strategically vital to

organisation, including strategy development ‘formulation’ and execution

(Feiler and Teece, 2014). The next sections discuss in details processes and best

practices for strategy development and execution from capabilities lens.

2.3 STRATEGIC MANAGEMENT TOOLS - VISION AND MISSION

The importance of mission, vision and strategy has been acknowledged in many

organisations around the globe. Mission expresses the reason why the

organisation exists; vision is describing in words the futuristic image of an

organisation, and strategy defines the way the organisation believes it can reach

that state. These tools are considered to be essential in guiding the whole

organisation down the appropriate pathway to the desired goals (Naaranoja et

26

al., 2007). McCabe (2010) belief that mission is broad in term of intention and

wording that sets directions but does not provide particular targets. Thus,

mission needs to be connected with particular objectives, which can provide

managers with something allows them to translate broad vision into tangible

result McCabe(2010). For more than three decades, scholars have argued that

vision is important to leadership and strategy implementation. Some scholars

point out that vision building is intended to create a fundamental, ambitious

sense of purpose, which to be pursued over the years (Kantabutra and Avery,

2010). Various management literature highlight clearly the importance of the

vision, however, the process of vision development is not defined in a generally

agreed-upon manner (Kantabutra and Avery, 2002). This is a critical problem

because the way in which vision is defined influences the way it is adopted by

practising managers and studied by scholars (Kantabutra and Avery, 2010).

The definition of ‘vision’ varies in management and leadership literatures, but

essentially it is conceived of as “an idealised future goal state, as a plan for

future goal attainment, and as an image of the future that articulates the values,

purposes, and identity of followers” (Strange and Mumford, 2005:122). It is the

emphasis placed on the construction of a distinct image for a group’s or an

organisation’s future that binds these different definitions together (Strange and

Mumford, 2005). And this observation has led to the argument that vision

involves a set of beliefs about how people should act, and interact, to make

manifest some idealised future state (Strange and Mumford, 2005). As vision is

a common terms associated with capabilities, capabilities perspective paying

relatively less attention to individual agency in routines (Parmigiani and

Howard-Grenville, 2011). Zollo and Winter (2002) argued that capabilities must

developed ‘in-house’ through a set of activities and knowledge processes

focused on the organization’s own routines (Zollo and Winter, 2002). Scholars

of capabilities perspective acknowledge that individuals are involved in this

complex processes with generally assumption that routines operate as intended.

However, capabilities perspective omits the influences of individual agency that

complex in nature (Parmigiani and Howard-Grenville, 2011).

27

Usually, vision statements are presented in one or two sentences that define the

mid- to long-term goals of the organisation. According to Kaplan and Norton

(2008), such statements should be market-oriented and expressed in futuristic

terms. Feiler and Teece (2014) stated that dynamic capabilities do not just

emerge and are more than something that firms do well. In the same perspective,

vision does not just emerge and are more than things that organization does well

(Feiler and Teece, 2014).

Vision is comprised of an ambitious goal that challenges all employees and that

simultaneously requires an organisation to possess strong leadership that can

move it from the status quo to the future target place. It provides a high-level

description of how an organisation intends to create value in the future (Kaplan

and Norton, 2008). There is no doubt that vision is crucial for many

organisations. However, these organisations need to ask themselves how

effective their vision is (Kantabutra and Avery, 2010). According to many

leadership scholars, senior managers need to distinguish between ‘strong’ and

‘weak’ vision to ensure effectiveness. This is particularly important in

organisations where people down the managerial line must share the same

vision as senior managers and executives (Kantabutra and Avery, 2010).

In the same context, Professor Stephen R. Covey considered a shared vision as a

main ingredient of organisational success, highlighting that the root reason of

organisations fail is that its members do not share a common vision (Covey,

2004). As emphasised above, capabilities perspective acknowledged that

individuals are involved in the processes but omits the influences of individual

agency. Moreover, capabilities perspective assumes that routines operate as

intended; however, practice perspective does not share the same assumption.

The presence of a clear vision is the starting point in the development of strategy

that drives effective implementation. Powerful visions indicate the long-term

prospect for the business, and the future environment in which it functions. In a

28

business situation, the vision must be one that offers a view of a better future,

otherwise it will not possess any power to inspire staff members or attract their

commitment (Kantabutra and Avery, 2010). Visions that can be considered as

powerful, through their ability to make a significant impact on customer and

employee satisfaction, have certain characteristics including: conciseness,

clarity, abstractness, challenge, future orientation, stability, and desirability or

the ability to inspire (Kantabutra and Avery, 2010). Hence, it can be understood

that vision is a vital when establishing any organisation. As Kantabutra and

Avery (2010:37) stated: “we know that vision is the starting point of any

organisational transformation process, and should underpin business strategy”.

This brings the discussion to the issue of strategy, since that in itself, must be

understood in all its facets. Consequently, the concept of strategy, and questions

concerning how it is created, who is involved in it, to whom it created, how it

functions and why, are elaborated upon in the following sections.

2.4 STRATEGY DEFINITION AND STRATEGIC PLANS

“Understanding what is strategy has been complicated by the proliferation of the number of schools of strategic thought and by undisciplined, even the reckless use of the term” (Porter, 1996:61).

There is a general agreement among strategy scholars about the nuances

differences of the strategy based on the personal interpretation “translation” of

the definition McCabe (2010). Taking this in consideration, the above quotation

expressing the dilemma of strategy definition, as it appears not to be a

straightforward. Thus, we need to look at what managers actually doing when

they are involved in strategy in order to define strategy precisely. The classical

view of the strategy rooted back to the early days of writing about war

(Patanakul and Shenhar, 2012). The word of strategy used in military as means

to organise soldiers in best way to win the battle McCabe (2010). Whilst, in

business the definition of strategy is used in the same way where resources are

organised to compete effectively McCabe (2010).

29

In business, Daft (1998:53) defined strategy as “a plan for interacting with a

competitive environment to achieve organizational goals”. Strategy defined here

as design or plan constructed to achieve a company’s goals and objectives. It

embodies the way in which those goals and objectives will be realised, what

operational units will be used, what resources will be needed, and how those

resources will be acquired. It is obvious that resources are the centrals to the

design of all strategy, since a strategy by itself cannot achieve anything at all.

Strategy formulation is important, and due to it importance, there is belief the

tasks of strategy development can be done only by senior managers McCabe

(2010). However, implementing strategy is responsibility of lesser seniority

managers. The belief that strategy can be developed by senior managers and

based on rigid application, rational decision of top-down approach has become

dominate says McCabe (2010). So, senior managers at the top-level of an

organisation developing strategy that directs managers at lower level of same

organisation.

Successful strategy is about exploiting opportunities that offered potential

market. This required a full dedication from those concerned managers who

should not hampered by the daily operational issues. This thought supported by

management scholars who believes managers in particular at executive levels

were expected to be dedicated for the to the pursuit of efficiency and

effectiveness. Thus, once senior managers of an organisation have taken

strategically decision the remaining managers are responsible to implement

theme (McCabe, 2010).

The main purpose of developing the strategy is to clarify how the vision can be

achieved (Kaplan and Norton, 2008). To simplify, an organisation might set

goals that it wants to achieve, so the strategies define the way to achieve these

goals, and hence, are called strategic plans. The strategic plan is defined as “a

document that articulates a set of goals in various aspects of an organization,

specifies action plans or items, and proposes in some case a set of measures to

30

track progress towards those specified goals in given period of time” (Hwang

and Suarez, 2005:73). From practice perspective, this set of documents portrays

an organisation as an actor with clear targets and with the capacity to achieve

them (Hwang and Suarez, 2005). The strategic plan is formal to the extent that

its goals and objectives are specified and that it provides indicators for gauging

the progress (Hwang and Suarez, 2005). So, plans and documents are a new

form, ‘objects’, or ‘artefacts’ that representing a strategy. However, the formal

nature of the strategic plan does not mean there is uniformity among such plans.

Indeed, strategic plans vary according to the number of organisational

dimensions or aspects to which they apply. Further, in the business world,

strategic plans vary widely with regard to both formality and scope (Hwang and

Suarez, 2005). Likewise, strategic goals also vary, but it is true to say that they

mostly fall into two categories, these being ‘promotion’ and ‘aspiration’ (Hwang

and Suarez, 2005). Promotion aims to promote and strengthen an organisation’s

internal capacity by making technological improvements and implementing

effective human resource management, for example, while aspiration aims to

move the organisation forward into its desired position or to solidify its position

in the industry.

From the project perspective, there are various definitions in the literature

relating to strategy. The optimal definition of project strategy, is one provided

by Artto et al. (2008:8), who state that such strategy is: “[d]irection in a project

that contributes to success of the project in its environment”. This definition

encompasses all types of project strategy, and the important in that it includes

four particular elements, these being: direction, contribution, success, and

environment (Artto et al. 2008).

At this point, two questions become immediately apparent, which are:

o Is strategy existing as real thing that ready for implementation, or not?

o If not, why do organisation strategies fail to achieve the intended goals?

31

Answers to these questions have been provided by Czarniawska (2007:353) who

said:

“When I was starting my career as a researcher in organisation studies in the 1970s, the word I heard most often was ‘structure’. Structures were this and structures were that; they had to be built or they had to be changed; they were too rigid or too flexible, but they were always at the centre of attention. Soon, however, they began to give way to ‘strategies’. Then, in the 1980s, ‘strategies’ were shelved and replaced by ‘cultures’”(Czarniawska, 2007:353).

In modern organisation every action, plans, and decision called a ‘strategy’

(Patanakul and Shenhar, 2012) or capabilities that organisation do

systematically at any time to manage targeted performance (Parmigiani and

Howard-Grenville, 2011). Taking in consideration that “strategy is a process,

not a destination” (Pugh and Bourgeois III, 2011), it is a linear analytical

process, the main outcomes of strategy formulation and planning being

descriptive documents that are used in developing a direction that differentiates

a company’s position (Kaplan and Norton, 2008). Thus, strategy is not done

deal thing that exist for straightforward implementation. Consequently, it is

necessary to ask why strategy objects ‘descriptive documents’ do not succeed in

being achieved, and why many organisations still continue to formulate strategy.

In the following section, explore the theories of strategy and prospective for

better understanding of how strategy is developed and what function it serves.

2.5 STRATEGY THEORIES AND PERSPECTIVES

In major strategy texts, there is general agreement that there are only two

theoretical approaches for strategy, namely: deliberate and emergent (McCabe,

2010). Both strategy approaches described in the following:

Deliberate strategy assumes that there can be a logical and structure approach

to the planning and delivery of intended outcomes. According to Lynch, there

are four area ‘theories’ for deliberate strategy: Industry and environment based

theories, resource based theories, game based theory, and cooperation and

network based theories. However, this approach is challenged and criticised due

to its rational and logical assumption.

32

Emergent strategy uses of experiment and learning from experience as

alternative approach for deliberate. In emergent approach strategy is usually

developed in response to changes that may occurs to the market or environment.

The final objective of this approach is fuzzy and can be always changed to suite

the market situation. According to Lynch there are four areas ‘theories’

associated with emergent approach: survival based theories, uncertainty based

theories, human resource based theories, and innovation and knowledge based

theories.

Consequently, there are four perspectives for strategy approaches, namely:

classical, evolutionary, processual, and systematic.

Classical uses deliberate approach and belief that strategy is predetermined

process and planned based on desire to maximise the outcomes. Thus

maximizing profit is the key motive for achieving objectives.

Systematic uses deliberate approach that rejects profit is main motive for the

outcomes. In this perspective, culture and power influenced by social systems

that organization operates and relevant market they serves. In this prospective,

multiplicity outcomes ‘pluralism’ is the object.

Evolutionary uses emergent approach based on belief that organisations

survival and prosperity are depending on their ability to response quickly to

market situation. They also seek to maximize the outcomes using process that

developed or ‘emerge’ during the practice.

Processual uses emergent approach and proponent of classical perspective that

beliefs market, people, and organisations as being far from perfect entities. This

perspective “accepts that strategy is a matter of accommodation of multiplicity

of outcomes needed to satisfy both those involved in and the opportunities that

present themselves in the market”.

Regardless of chosen strategy approach or perspectives, successful strategy is

about exploiting opportunities that offered a potential market. This required a

full dedication from those concerned managers who should not hampered by the

33

daily operational issues. Management scholars believe managers in particular at

executive levels were expected to be dedicated for the pursuit of efficiency and

effectiveness. Thus, once senior managers of an organisation have taken

strategic decisions, the remaining managers are responsible to implement theme

McCabe (2010). Developing strategy is important, and due to that, there is a

belief this task can be done only by senior managers McCabe (2010). However,

implementing strategy is responsibility of lesser seniority managers. So, senior

managers at the top-level of an organisation developing strategy that directs

managers at lower level of same organisation.

In the following section, explore the development process as a means of

promoting an understanding of how strategy is developed and what function it

serves.

2.6 DEVELOPMENT AND PLANNING PROCESSES OF STRATEGY

Over the past three decades numerous frameworks have been introduced to ‘do

strategy’, to help organisations to clarify their visions and make them

implementable (Pugh and Bourgeois III, 2011). Essentially, these frameworks

embrace the notion that the connection between the vision and the strategy is

vital if the organisation is to realise that vision at some point in the future. But

what dose Pugh and Bourgeois means by saying ‘do strategy’? Is this means to

develop a plan or actually doing strategy ‘makes it work’? Thus, as mentioned

earlier, we need to consider what managers actually doing when they are

involved in strategy in order to define strategy precisely.

There are many different frameworks and methodologies for strategic planning

and management. However, they tend to follow a similar pattern and to have

common attributes. In general, the strategy development process is divided into

two parts: strategy formulation and strategic planning (Kaplan and Norton,

2008).

• Strategic Formulation uses either deliberate or emergent approach

that consists of strategic analysis activities for both external and

34

internal environments. The task of developing strategy can be done by

senior managers only McCabe (2010). Strategy formulation divided

into two main analysis activities, both external and internal.

§ External analysis. Assesses the macro-economic elements such

as economic growth, interest rates, currency, regulation, etc. The

five forces of Michael Porter, and PESTEL, are examples of

well-known models and frameworks used to conduct external

analysis.

§ Internal analysis. Examines an organisation’s own performance

and capabilities and identifies the sequence of the process

required to deliver products or services to the customer. Value

chain analysis and Activity Based Cost (ABC) are examples of

the tools and frameworks.

Once the internal and external analyses have been performed, the

strategy team conducts a SWOT (Strengths, Weakness,

Opportunities, and Threats) analysis to understand the key issues that

the organisation must address when formulating the strategy.

• Strategic Planning focuses on ‘strategy implementation’ by

translating the formulated strategy into policies and procedures for

achieving the grand decision. Once senior managers have taken

strategic decisions the remaining managers are responsible to

implement theme McCabe (2010). Implementation involves all levels

of management in moving the organisation toward its vision. The

process seeks to create a fit between the organisation’s formulated

goal and its on-going activities. Because implementation involves all

levels of the organisation, it results in the integration of all aspects of

the firm’s functioning.

As mentioned earlier, it should be borne in mind that “strategy is a process, not

a destination” (Pugh and Bourgeois III, 2011). It is a linear analytical process,

35

the main outcomes of strategy formulation and planning being descriptive

documents that are used to develop a direction that differentiates a company’s

position (Kaplan and Norton, 2008). Thus, strategy is not ‘done deal’ thing that

exist for straightforward implementation. Feiler and Teece (2014) supported this

by saying capabilities do not just emerge and are more than something that firms

do well. Focusing on the effectiveness of performed processes, implementation

is complex process that involve people across all organisation levels and results

in creating new objects or ‘artefacts’, however, capabilities have relatively less

attention to individual agency and artefacts influences (Feiler and Teece, 2014).

The below section discusses the aspects related to the strategy implementation.

2.7 STRATEGY IMPLEMENTATION

It is important to remember that developing and implementing strategy is a

closed-loop process and interdependent in which each part of the system

influencing every other part (McCabe, 2010; Kaplan and Norton, 2008).

Implementing strategy is the responsibility of lesser seniority managers that uses

deliberate ‘perspective’ approach that assumes deliberate predetermined choices

with intention to create particular actions McCabe (2010:7).

When talking about strategy implementation it is crucial to know whether we

are ‘execute’ or ‘implement’ a strategy? Is ‘getting things done’ what we mean

by implementation or execution? Ken Favaro (2015) has asked these questions

at the beginning of his article published recently in Harvard Business Review

(HBR). It is important to have a clear understating about the differences

between both words before going further with study topic. The distinction

between strategy implementation and execution has very less attention by

business leaders (Favaro, 2015), as there is no specific articles could be fond

that highlighted the differences. Favaro (2015) stated “there are meaningful

distinctions between strategy, implementation, and execution that are helpful to

running a company or business in the real world. Ignoring, blurring, or getting

them wrong creates sloppy thinking, deciding, and doing at all levels of an

organization”.

36

Favaro (2015) summarise the differences by saying, if organisation has the

capabilities, enterprise advantage, and business portfolio it wants, its strategy is

implemented, then all decisions and activities required for turning strategic

choices into reality defined as strategy implementation. On the other hand,

strategy execution consisting all decisions and activities organisation undertakes

in order to turn implemented strategy into commercial success.

Of course, a strategy can never be fully implemented as planned because

everything that organisation necessarily assumed when formulating it as in a

constant state of flux. However, there will always be a gap between organization

current situation and what their strategies call for. Closing that gap is

“implementation.” Says Favaro (2015). Consequently, through this study, we

decided to use ‘implementation’ as word that refers to ‘getting strategy done’.

Strategy implementation requires an organisation to translate the inspirational

language and tone of vision or strategy into a form of words that allow for

implementation. Unfortunately, many organisations fail to become what they

want because they cannot translate their formulated strategy into an

implementation strategy that will actually bring them tangible results (Cascella,

2001; Hrebiniak, 2006). And this is purely because managers are trained to

formulate strategy, they receive no instruction on how to implement it

(Hrebiniak 2008).

The critical point that should be highlighted first is that ‘implementation’ is a

process, which results in a series of decisions or actions over a certain period.

Successful implementation requires the effective management that adopt

changes and that must focus on the wider picture. It is not easy to execute

decisions but the execution of decisions is indeed critical for strategic success.

That said, implementation is often poorly managed by organisations (Hrebiniak,

2008), and the reason, apart from a lack of managerial training already

mentioned, is that as noted by Warnock (2000), strategy is itself characterised

by multiple options, multiple paths, and multiple outcomes, and hence,

37

implementation is much more complex than would be the case if there were a

linear solution.

Figure 2.1 represent the conceptual framework that summarise the theories of

strategy formulation and implementation along those typically charged with

responsibility.

Strategy Formulation Strategy Implementation Strategy

Outcomes

App

roac

h

Deliberate Approach

• Industrial Based Theory

• Resource Based Theory

• Game Based Theory

• Corporate Based Theory

Emergent Approach

• Survival Based Theory

• Uncertainty Based Theory

• HR Based Theory

• Innovation Based Theory

Peop

le C

harg

ed Top-level management

Senior managers

CEO, Strategy team

Middle- to- low level management

Lesser-seniority managers

Function manager,

Front-level staff

Executives Seniority-level Front-line

Figure 2.1: Conceptual Framework for Strategy Theories and Perspectives

General management studies acknowledged that strategy implementation has

affected by people, thus the assumption of rationality is suspected says McCabe

(2010:7). Furthermore, implementation process evolving people across

organisation levels and results in creating new form or object, however,

Translation

Stra

tegi

c O

bjec

tives

& G

oals

38

capabilities has relatively less attention to individual agency and artefacts

influences. Focusing on the effectiveness of performed processes this involves a

well-managed cluster of activities that sometimes called a ‘people strategy’

(Feiler and Teece, 2014). Implementation, which is the common way of

describing the process of translating strategy into tangible results and

maintaining efficient, reliable operations, is regarded as one of the essential

challenges for leaders in today’s business environment (Yukl and Lepsinger,

2007).

Strategy implementation is complex for the reasons just outlined, and

consequently the field requires attention from researchers who can ultimately

provide guidance. Indeed, in order to develop the ability to implement strategy

successfully, managers need direction in the form of a logical, theoretical model,

which they can adopt. As noted by Hrebiniak (2008:23),“without guidelines,

execution becomes a helter-skelter affair”.

Having identified these as useful tools practiced by those organisations under

the investigation, this study discusses the three indicated below in details:

• Performance Measurement Systems and Balance Scorecards

• Project and Programme Management

• Project Portfolio Management

To understand the role of these tools mentioned above, and how the tools

themselves help in translating the strategy, their nature and function is

elaborated upon in the following sections.

2.8 PERFORMANCE MEASUREMENT AND THE BALANCED

SCORECARD

In today’s volatile markets many organisations in many industries are

confronted by huge challenges to their survival, and as noted, in order to

overcome these, they are adopting newer management systems to clarify their

vision and strategy and translate them into action (Fernandes et al., 2006). One

such management system is Performance Measurement and this is currently

39

attracting a great deal of interest among both industrialists and academics alike.

Among the different models of Performance Measurement, the Balanced

Scorecard (BSC) is one approach that is popular and is cited by the Harvard

Business Review (HBR) as one of the most important management tools to

emerge over the last 75 years (Fernandes et al., 2006; Bourne and Neely, 2003).

There are, however, numerous balanced performance measurement frameworks

and management processes for the design of performance measurement systems

(Bourne et al., 2002).

Generally, performance measurement is introduced as an approach that controls

business; implements strategy effectively, measures success continuously, and

encourages feedback on the strategy. In a study by Haapasalo et al. (2006) it was

found that all organisations that had a BSC system in place were satisfied with

the system, and that what problems did exist were related to the creation of the

strategy or vision, the applicability of those, or the ineffective use of the

company’s own activities.

Of the many models and applications of performance measurement that are

available, the BSC is the most dominant, hence it is important to learn more

about this and to find out why it enjoys this prominent position. Within the

literature there is some ambiguity surrounding the BSC (Speckbacher et al.,

2003), but for the purposes of this study, the definition proposed by the

originators of the concept, Robert Kaplan and David Norton, two Harvard

professors who introduced the idea in 1992, is used. According to Kaplan and

Norton, the starting point for the development of the BSC concept was the idea

that traditional performance measurement systems were adequate in the

industrial age, but not in today’s information age (Kaplan, 2008; Kaplan and

Norton, 2006). Traditional performance measurement uses an accounting model

of the firm based purely on financial measures and a linear additive framework,

but this does not capture intangible assets that have no financial value. Customer

loyalty and staff knowledge are examples of such intangible assets that are

40

usually associated with products or services delivered by an organisation, and

that are measured by units rather than currency (Speckbacher et al., 2003).

Kaplan and Norton (2008) viewed corporate strategy as a specific way of

linking tangible and intangible assets. In this, they stress that value does not

ordinarily reside in any specific intangible asset, but rather, is created by a

strategy that unites a set of both tangible and intangible assets in a specific way

(Speckbacher et al., 2003; Kaplan, 2008). This is can be done by formulating

strategic objectives with respect to four perspectives, these being: ‘financial’,

‘customer’, ‘internal business process’, and ‘learning and growth’. These four

perspectives are shown in Figure 2.1 that depicts the structure of the BSC.

Figure 2.1: Original Structure of Balanced Scorecard (R. Kaplan, 2008:1254)

From this it can be seen that the BSC retains financial metrics as the ultimate

outcome measures for company success, but supplements these with metrics

from three additional perspectives (customer, internal process, and learning and

growth) that are proposed as the drivers for generating long-term shareholder

value (Kaplan, 2008).

The BSC was not the first model to advocate the use of non-financial measures

to motivate, measure, and evaluate company performance as the means of

translating vision and strategy. Indeed in a study conducted in 2003 by

Speckbacher et al., three types of BSC were identified as follows:

41

• Type I BSC: a specific strategic performance measurement system

containing financial and non-financial measures and objectives.

• Type II BSC: a system that describes the company’s strategy using a

sequential cause-and-effect logic to link tangible and intangible assets.

• Type III BSC: a system that implements the organisation’s strategy

through action plans and/or ‘target setting’ and links it with the reward

system.

However, all three types share the common objective of aiming to implement

the strategy by defining the objectives, creating action plans, and monitoring

results (Speckbacher et al., 2003). It is true to say that many organisations have

implemented the approach and learned how to use these performance

measurement system tools within their overall management systems to drive the

implementation of their corporate strategy (Kaplan, 2008).

Figure 2.2: Translating Mission, Values, and Vision into Desired Outcomes

(Kaplan and Norton, 2008:73)

The process of translating the mission, vision, and strategy into strategic

initiatives and objectives, is envisioned in Figure 2.2, from which it can be seen

that the process start with the creation of the mission, the core values, and the

42

vision (MVV). These things are then translated into strategy, which in turn, is

translated through the BSC into measurable initiatives and objectives.

It has been mentioned already that Pugh and Bourgeois III (2011) make the

point that strategy is a process and not a destination, and this is appreciated

through Figure 2.3, which depicts the outcomes of the development process via

the BSC. This begins with translating the MVV statements into tangible

outcomes, and moves to translate the strategy into plans, objectives, initiatives,

and measures. All of these stages in the process are documented in detailed

plans, which should be communicated throughout the organisation in various

styles such that all members are aware of the organisational vision and can

connect with it. As mentioned earlier, these plan and documents resulted form

translation processes are a new form or ‘object’ that aim to clarify and

communicate strategy. The question is, dose artefacts including various types of

documents and plans helped in creating a shared vision across the whole

organisation? Dose this translated outcomes helped in communicating strategy

effectively?

Figure 2.3: Outcomes of Strategy Development Processes

Kaplan and Norton (2008) mention that the literature on strategy formulation

and development can be overwhelming with its many approaches and schools of

thought, but as noted by Yukl and Lepsinger (2007:3), “a brilliant strategy is of

little value unless it can be implemented effectively”. Moreover, as noted by

Mission, Values,

Vision (MVV)

Statement

Strategic Plans Balanced

Scorecards

Statement

1-2 sentences

Objectives

Measures

Full Plans Many Pages

Game Plans

SWOT

Few Pages

43

Sterling (2003:27) “effective implementation of an average strategy, beats

mediocre implementation of a great strategy every time”.

There is no doubt that formulating strategy is difficult. However, “[m]aking

strategy work, executing or implementing it throughout the organisation is even

more difficult” (L. G. Hrebiniak, 2006:12). Without effective implementation,

no business strategy can succeed. And since most managers know far more

about formulating strategy than they do about implementing it, finding ways to

improve implementation is an important task for today’s leaders (Yukl and

Lepsinger, 2007; Hrebiniak, 2006).

The benefits to be obtained from the use of a BSC approach depend upon what

it is used for, how well it is designed, and how it is applied. Actually, there are

many organisations using the BSC in many different formats, but there are two

distinctly different applications, these being operational control on the one hand,

and strategic management on the other. However, even with the increased

adoption of a strategy implementation system based on the BSC, a gap still

exists between the formulation of high level strategic plans and their effective

implementation by frontline departments, process teams and employees (Kaplan

and Norton, 2008).

This knowledge gap is recognised in some recent studies that have revealed a

number of problems and difficulties confronted in the implementation of

performance measurement systems, which are just beginning to be recognised,

and as pointed out by Bourne and Neely (2003), there are big differences

between the published approaches to designing performance measurement

systems, and the implementation of those systems, and this applies in particular

to the implementation of the BSC. In all approaches, little reference is made to

the softer aspects of change that challenge the implementation of a performance

measurement system. Furthermore, Kaplan and Norton identified four barriers

to the implementation of performance measurement systems, each of which is

centred on the strategy, as follows (Kaplan and Norton, 2008):

44

• Vision and strategy are not actionable

• Strategy is not linked to departments, teams, and individual teams

• Strategy in not linked to resource allocation

• Feedback is tactical and not strategic

Furthermore, Hacker and Brotherton (1998) highlighted some traditional

challenges found in the management of change literature concerning

implementation of the BSC such as lack of leadership and resistance to change

(Hacker and Brotherton, 1998).

As a performance measurement tool, the BSC originally offers an effective way

to implement strategy, yet recent studies have revealed a number of issues

facing the adoption of the BSC. Essentially what occurs is that the organisation

may shift its focus from implementing its strategy, placing all its efforts into

implementing the BSC.

To sum-up, the problems mentioned above about the BSC and in particular,

implementation, bring the discussion back to the crux of the study, which is

concerned with the challenges to strategy implementation. And in this

connection, an important question can be raised, that being, why when there are

many management theories and models, do organisations still fail when trying to

implement strategy. In the next section, the author will attempt to find an answer

to this thought-provoking question by discussing another promising tool for

translating strategy. This tool is basically, the concept of project management.

2.9 PROJECT MANAGEMENT

Project management approach serve as primary capabilities for an organisation

respond to change that maintain its competitive edge (Dietrich and Lehtonen,

2005). Many organisations today operate almost entirely on a project platform,

in which the use of efficient, tactical and operative control tools ensures that

projects are run in accordance with the business visions and intended goals of

45

the organisation (Raisanen and Linde, 2004). From capabilities perspective,

projects as individual stand-alone entities, or as a part of a wider group of

projects, are used to support the overall organisation position in the future, by

changing obsolete and inefficient structures.

Poor organisation performance has been studied to understand the causes of the

result. The failure in the conventional approach to strategy implementation is

due to senior management’s use of the existing organisation structure and

system as depicted in the below Figure 2.4.

Figure 2.4: Problems of Strategy Implementation (Pellegrinelli and Bowman,

1994:126)

The great success of the project concept in managing construction and

information technology (IT) activities, has caught the attention of management

researchers. Consequently, a study conducted by Pellegrinelli and Bowman

(1994) recommended that by adopting the project and programme approach,

organisations can ensure greater success. The project approach offered here acts

as a translation vehicle to achieve most organisational strategies by implanting

new behaviour that helps organisational members to perform outside the the

exisiting organisational bureaucracy, process, and culture.

46

Figure 2.5: Project Management Approach for Strategy Implementation

(Pellegrinelli and Bowman, 1994:127)

Figure 2.5 demonstrates the project approach by translating strategy into action

in a process which is far superior to traditional management approaches. The

new behaviour is embedded in two key project roles, these being those of the

client and the project manager. This aproach is assumed to help senior

management to implement the strategy perfectly (Pellegrinelli and Bowman,

1994). Nevertheless, when implementing strategy using the project approach it

is important to take into consideration, two associated difficulties, namely: the

interdependences of project activities and the continual learning associated with

them (Pellegrinelli and Bowman, 1994). From capabilities perspective, project

management approach acknowledged that individuals are involved in the

processes but omits the influences of individual agency. Moreover, it assumes

from the beginning that routines operate as intended; however, practice

perspective does not share the same assumption.

Having a clear understanding of the meaning of strategy from the project

perspective is fundamental to the establishment of a strong basis before going

further with different aspects of the research. From the capabilities viewpoint,

strategy is defined as “a plan for interacting with a competitive environment to

achieve organizational goals” (Daft, 1998:53). To simplify, an organisation

might set goals that intends to achieve, so the strategies define the way to

47

achieve these goals. From project perspective, however, there are many

definitions of project strategy. That said, the definition provided by Artto et al.

(2008:8) already indicated as “direction in a project that contributes to the

success of the project in its environment” is useful since it is designed to

include various types of project strategies that may vary from one project to

another. The importance of this definition lies in the four elements - direction,

contribution, success, and environment (Artto et al. 2008), which are described

as follows:

Direction interprets one or several explicit elements including: goals, plans,

guidelines, methods, tools and other controlling devices.

Contribution refers to the assumption that the chosen direction has an effect.

Success refers to how well the project is able to accomplish its goals.

Environment refers to the boundaries outside, between, and within the project.

Considering the strategy as a project, the intended strategy could be

implemented though the processes of the project management or through the

project life cycle, which is itself another approach to describe the unique

characteristics of a project. Basically, a project can be conceived of as being

implemented in four sequential phases as depicted in below Figure 2.6 by Gray

and Larson (2008).

Figure 2.6: Project Lifecycle Process (Gray and Larson, 2008)

Gray and Larson (2008), explain these phases as follows:

• Defining: in this stage the project specification, objectives and team

members are defined.

• Planning: in this stage project objectives are scheduled into activities.

Based on this it is determined as to when the project activities will have

Defining Planing Execution Delivery

48

the deliverables ready, the expected benefits of the project and the

requirement for budget and manpower.

• Execution: this is the core stage of the project lifecycle, where the

project output or delivery actually takes place. During the execution

process, project activities are assessed against the initial plan to assure

that they are on the right track in terms of time, budget and quality.

• Delivery/Closing: this is the last stage where the project goal is

achieved and the end product delivered to the customer.

Furthermore, the fifth edition of PMBOK® published in (2013), identified three

types of project role for the project management office (PMO) that determines

the degree of control provided as follows:

• Supportive: Serves as a repository for the project by providing a

template, training, best practice, and lessons learned from previous

projects. The degree of the control provided by this type of PMO is low.

• Controlling: Provides support and the required compliance by adopting

a project management framework using various methodologies and

tools. The degree of control provided by this type of PMO is moderate.

• Directive: Manages the project directly and has the authority to act as

the key decision-maker through the life cycle of the project. The degree

of control provided by this type of PMO is high.

This study exploring whether the organisations under the investigation have

decided in ahead the role of the PMO they would like to translate/implement in

their organisation or not?

Furthermore, Payne (1995) argued that books on project management have

written with assumption that the projects are managed as single project.

However, in business world, an organisation runs in multiple projects and

portfolio environment rather than as a single project. The following sections

49

explain various terms used within project management and consider concepts

such as ‘programme’ and ‘project portfolio management’ that are usually used

in the project environment. The issues and challenges associated with each

approach are discussed too.

2.10 PROGRAMME AND MULTIPLE PROJECTS MANAGEMENT

Often, ‘project’ and ‘programme’ terms are used interchangeably in the practical

world, thereby sometimes leading to confusion. Both projects and programmes

have similar attributes like objectives, plans and resources, which are used to

achieve project goals. The only real difference is in their scope and timeframe

(Gray and Larson, 2008), since programmes can be on-going over many years

and projects have usually reached their conclusion within such timescales.

The term ‘programme management’ and ‘multi-project management’ are,

however, closely related (Archer and Ghasemzadeh, 1999). Indeed, there are

similarities between many definitions of programme management, and portfolio

management (Archer and Ghasemzadeh, 1999). Turner (1999:347), for example,

emphasises that “in a programme, projects form a coherent group of projects

that are managed in a co-ordinated way, for added benefit”. He adds that

programme management includes the management of interfaces between

projects and resources as well as balancing the responsibilities aligned with

corporate objectives.

Gray and Larson (2008:6-7) define a programme as “a series of co-ordinated,

related, multi-projects that continue over extended time and are intended to

achieve a goal”, and programmes management is conceived as “the process of

managing multi, on-going, interdependent projects” (Rajegopal et al., 2007:14).

Programme management is also a powerful way of co-ordinating projects that

have a shared business aim, and is an important method of ensuring that the

organisation gains the maximum benefit from integrating its project

management activities (Morris, 2004).

50

2.11 PORTFOLIO, AND PROJECT PORTFOLIO MANAGEMENT

(PPM)

Portfolio is a financial term used usually in the investment and stock industry.

The idea behind using this term within project management is concerned with

the desire to deal with projects precisely as investments. From a financial

perspective, portfolio managers are always looking at the performance of their

portfolio of investments, i.e. this may be calculated by common financial

techniques such as Return on Investment (ROI), Internal Rate of Return (IRR),

and the pay-back period.

Whether dealing with a single project or a group of projects, it is necessary for

the manager(s) to align time, scope and cost in order to support the overall

organisational position in the future. The idea of strategy is implicit in this style

of working since underpinning all the approaches is the idea that the projects are

linked with the organisation’s long-term strategy because in themselves they are

‘the right projects’ for the organisation (Elonen and Artto, 2003). Various

literatures discuss the concept of project portfolio management, project portfolio

being defined by them all as a group of projects that compete for scarce

resources and are conducted under the sponsorship or management of a

particular organisation. Cooper and colleagues (1998) stated three main

objectives of portfolio management, namely: the maximisation of the value of

the portfolio, linking the portfolio to the strategy, and balancing the portfolio

(Cooper et al. 1998).

From product research and development perspectives, Cooper et al. (1999:333)

views portfolio management as “making strategic choice, in other words, which

market, product and technology business will invest in”. It helps to determine

which product or development project that has to be chosen from all proposed

projects, taking into consideration the need to achieve the right balance between

numbers of projects and the available resources (Cooper et al., 1999). Moreover,

portfolio management focuses on three main goals as follows (Cooper et al.

1998):

51

• Maximising value. Ensuring that only the high value project goes into

the portfolio.

• Balance. Ensuring that the entire portfolio has the right mix of the

projects to develop a balanced portfolio.

• Strategic direction. Ensuring that all the projects within the portfolio

are strategically aligned.

Archer and Ghasemzadeh (1999) define a portfolio as a group of projects

sponsored by a particular management of the organisation. These projects are

carried out with limited resources from the sponsor to meet the organisation’s

requirements such as the need for profitability. However, profits should be

achieved properly without exceeding the allocated resources be they people,

budget, time, etc. (Archer and Ghasemzadeh, 1999).

Sometimes the terms ‘project portfolio management’ (PPM) and ‘programme

management’ are substituted for each other in practical situations. Indeed, both

portfolio management and programme management focus on prioritising

resources and optimising the business benefit. However, they are fundamentally

different, since whilst it is true that programme and project management are

about executing projects in the right way, PPM is concerned with selecting and

undertaking the right project by considering projects as an investment portfolio.

So it is the nature of the project that is important inside PPM and not just how it

is implemented. Furthermore, programme management is more involved with

day-to-day management, whereas portfolio management is more periodic and

strongly analytical (Morris, 2004; Oltmann, 2008).

According to Rajegopal et al. (2007:10), PPM is a “paradigm shift in thinking”.

It empowers and helps the business by establishing a clear line of sight from the

top-level view right down to the individual project layer. In other words, PPM is

management of the collection of projects and programmes in which an

organisation invests to implement its strategy. Accordingly, PPM is presented as

a set box of programmes and projects (Rajegopal et al., 2007).

52

Gray and Larson (2008:520) defined PPM as “the centralized management of

projects to ensure that the allocation of resources to projects is directed toward

projects that contribute the greatest value to organization goals”. The

collection of programmes and projects within an organisation is recognised as a

‘portfolio’. This portfolio embodies the entire image of an organisation’s

direction that is responsible for delivering the organisation’s strategic objectives.

Levine (2005) views PPM as more than an extended application of project

management, defining it as a set of business practice that connects projects with

strategies, resources and executive oversight of the enterprise. Without this

connectivity, project efforts are directed towards ‘doing the project right’ even if

the on-going project is not actually the ‘right project’ for the organisation. In

addition, “The PPM process will move us closer to zero failed projects. The

objective is to reduce the terminated projects to zero” and provide structure and

process for project governance (Levine, 2005:3). In particular, PPM brings

about changes for the better in the organisational culture especially in terms of

communication and decision-making (Levine, 2005).

The primary objective of PPM is to identify, select, finance, monitor, and

maintain the portfolio balance, by ensuring an appropriate mix of projects to

achieve organisational goals and objectives. It involves the aggregation of costs,

risk and the returns of all projects within the portfolio. Based on the provided

information, a portfolio management approach helps organisations to make the

optimal decisions concerning whether to fund a new project or continue

financing on-going projects. It is able to do this because in terms of benefits and

cost, portfolio theory can clearly assess the exchange among competing

investment opportunities and risks (Hutchings, 2009).

From a quality perspective, PPM is perceived as a continuous decision process

that strategically supervises the allocation of resources in respect of the many

different projects comprising the portfolio. Clearly, the quality of project output

53

is always affected by the quality level of the resources at the disposal of the

project, which means that when assigned resources to project activities are

inadequate, project outcomes will be influenced negatively. The PPM process

aims to maximise the portfolio value by improving resource utilisation via

effective resource allocation such that sufficient resources are continually

directed towards the most beneficial projects (Hunt and Killen, 2008).

Project managers use the PPM process within organisations to describe methods

for analysing and managing groups of current or proposed projects. The main

concerns of PPM are focused on two fundamental points (Hayes, 2003), as

follows:

• Effectiveness: which revolves around maximising the benefits by

choosing the right projects or terminating less valuable projects, and

eliminating those that are redundant.

• Efficiency: which requires executives to provide support and direction

by allocating the necessary funds and resources for the selected projects,

and to promptly respond to performance issues to prevent any

unnecessary project delays.

The literatures on the implementation of corporate strategy via portfolios,

programmes, and projects are varied, patchy, and incomplete. Furthermore,

there is little on the basic practical details of implementation. Both PMBOK and

APM lack in the details provided in this respect. Frome capabilities perspective,

PPM described here viewed as a “black box” that mainly interested in what

routines accomplish toward organizational goals (Parmigiani and Howard-

Grenville, 2011). And whilst the literature on portfolio management is quite

thorough, the treatment is primarily from an analytic viewpoint (Morris, 2004),

which assuming process and routines operate as intended (Winter,2003).

However, practice perspective, does not share this assumption. Scholars from

capabilities perspective sometimes acknowledge that actors are involved and

that the processes are complex (Parmigiani and Howard-Grenville, 2011).

Consequently, there is a need for practice perspective to investigate how project,

54

programme, and PPM is being implemented in the real project world, with

emphasizes inside the “black box” by focuses on how routines are enacted in the

day-to-day. Particularly, how it helps those organisations in managing and

aligning projects with business strategy. Moreover, there is a need to explore

whether these organisations choose to establish single or multiple portfolios for

managing their projects, and what the implications are of the chosen approach.

As mentioned earlier that implementation is not necessarily straightforward and

not done deal thing; and many challenges are encountered the approach in real

projects and businesses world. Thus, it is useful to discuss the challenges

encountered practitioners in practice. The following two sections discuss in

details these challenges encountered implementation of strategy and project

management approaches in practice.

2.12 STRATEGY IMPLEMENTATION OBSTACLES, CHALLENGES,

ISSUES AND PROBLEMS

“The real reasons why strategies fail are varied. Fortunately, the causes can often be anticipated and the pitfalls can be avoided” (Sterling, 2003:27).

Strategy itself is frequently an umbrella that permits a range of options rather

than a clearly and tightly defined set of goals (Morris, 2004). Thus, as the

intended ‘deliberate’ strategy moves to the implementation the desired

objectives might be dissipated, changed, or even demonstrate their inability to

be achieved, long before the expected benefits are due to be realised

(Pellegrinelli and Bowman, 1994). In fact, there are many reasons why strategy

is not implemented properly, all of which stem from the numerous challenges to

the implementation. In this matter, below Table 2.1 summarises the articles

carried during the literature reviews, which discussed the challenges

encountered strategy implementation ordered by article date.

55

TABLE 2.1: REFERENCE TABLE OF ARTICLES FOR STRATEGY

IMPLEMENTATION CHALLENGES Article /Year Year Author(s) No. of

challenges

Obstacles to Strategy Execution 2008 Hrebiniak (2008) 12

Translating strategy into effective implementation: dispelling the myths and highlighting what works

2003 Sterling (2003) 6

Exploring barriers to the successful implementation of a formulated strategy

2002 Morten Heide, Kjell Gronhaug, and Simen Johannessen

7

Commenting on two surveys conducted by Wharton-Gartner, and Wharton-

Executive Education respectively, Hrebiniak (2008) notes that twelve challenges

to strategy implementation were revealed, eight of which were ranked as the top

five in both surveys. Hrebiniak (2008) summarises the results in Table 2.2.

TABLE 2.2: OBSTACLES TO STRATEGY EXECUTION (HREBINIAK,

2008) No. Strategy Execution Obstacles

‘Challenges’

Wharton-

Gartner

Survey

N=243

Wharton-

Executive

Education

N=200

Top 5

Ranking

Either

Survey

1. Inability to manage the change or

the resistance to change

1 1 √

2. Trying to execute strategy that

conflict with current organization

hierarchy or power of structure

2 5 √

3. Poor information management

between individual or business unit

handling the strategy execution.

2 4 √

4. Unclear communication of

responsibility or accountability

4 5 √

5. Poor or vague strategy 5 2 √

6. Lack of ownership of strategy 5 8 √

7. Lack of guidelines or models for

guiding the strategy

7 2 √

56

8. Lack of awareness of

organizational structure in the

execution structure

9 5 √

9. Lack to generate buy-in on critical

execution steps or actions.

7 10

10. Poor intensives to support

execution objectives.

9 8

11. Insufficient financial resources 11 12

12. Lack of upper management support

of strategy execution.

12 11

In article published in 2003, Sterling identified below six challenges for strategy

implementation as reasons for failure:

1. Unanticipated market change

2. Lack of management support (lack of support from the CEO)

3. Lack of individual commitment – the phenomenon of the “Emperor’s

new clothes”

4. Lack of focus or lack of alignment between strategy and projects

5. Poor strategy or lack distinctiveness

6. Insufficient financial resources

Furthermore, Morten Heide et al. (2002) has identified below seven barriers as

challenges for strategy implementation ordered by frequency, namely (Heide et

al., 2002):

1. Communication

2. Organisational structure

3. Learning and knowledge

4. Personnel

5. Cultural

6. Political

7. Resources

57

Based on what have been said, below Table 2.3 lists all challenges facing

strategy implementation that discussed by three articles and will be used during

the experimental phases of this study. Nonetheless, all these challenges or

failure are anticipated as Sterling (2003:27) did also criticise these reasons for

failure, stating, “most common cited causes of failure are either myth or excuses

that gained their creditability from being repeated”.

And it is the case that there is much research offering advice to implementers

wishing to remove these failure factors (Sterling, 2003). Also Kaplan and

Norton (2008) stressed that strategy implementation needs an architecture that

can link the strategy with the operation. In this respect, they state: “Strategy

execution requires an architecture that integrates the strategies and operations

of diverse units scattered throughout an enterprise” (Kaplan and Norton,

2008:45) .

TABLE 2.3: CHALLENGES OF IMPLEMENTING FORMULATED

STRATEGY (HREBINIAK, 2008; STERLING, 2003; HEIDE ET AL., 2002)

Implementation challenges confronts

formulated strategy

Hrebiniak

Sterling Morten Heide

& colleagues

1. Inability to manage/anticipate the

change or the resistance to change

√ √

2. Trying to execute strategy that

conflict with current organization

hierarchy or power of structure

√ √

3. Poor information management

between individual or business unit

handling the strategy execution

√ √

4. Unclear responsibility or

accountability

√ √ √

5. Poor or vague strategy √ √

6. Lack of ownership of strategy √

7. Lack of guidelines or models for

guiding the strategy

8. Lack of awareness of organizational √

58

structure in the execution structure

9. Lack to generate buy-in on critical

execution steps or actions

√ √

10. Poor intensives to support execution

objectives

√ √ √

11. Insufficient financial resources √ √ √

12. Lack of upper management support

of strategy execution.

√ √

13. Communication √

14. Organizational culture √

As this study is focusing on understanding the implementation challenges of

project management approaches in practice, following section discuses

challenges encounter the implementation of multiple-projects, programme, and

project portfolio management.

2.13 ISSUES OF PROJECTS, MULTIPLE PROJECTS,

PROGRAMME, AND PPM

The adoption of the project and programme approach was recommended in the

mid-1990s as a new approach to strategy implementation, and one which would

result in greater organisational performance (Pellegrinelli and Bowman, 1994).

Undoubtedly, attention was turned to the new approach since survival in today’s

business environment requires quick decision-making, better allocation of

resources, and a clear focus. Without this last feature, problems can be

magnified. Indeed, this is supported by first rule of the fifth disciplines, who

according to Senge (1990:57) believe that “today’s problems come from

yesterday’s solutions”. In fact, there are many studies have listed a numerous

challenges (obstacles/barriers/issues/problems) to the implementation of

project/programme/portfolio management approach; however, as mentioned

earlier most of these challenges are anticipated. In this matter, below Table 2.4

summaries the number of highlighted challenges listed in each article by date.

59

TABLE 2.4: REFERENCE TABLE OF PROJECT IMPLEMENTATION

CHALLENGES Article /Year Year Author(s) No. of

challenges

Major challenges to the successful

implmentation and pracice of

programme management in constuction

enviroment

2010 Zayyana Shehu, and

Akintola Akintoye

28

Problems in managing internal

development projects in

multi-project environments

2003 Elonen and Artto 22

Portfolio Management For New

Products

1999&

1998

Cooper, Robert G

Edgett, Scott J

Klein schmidt, Elko J

7

Management of multiple simultaneous

projects: a state-of-the-art review

1995 Payne 5

Project and programme management like other management approaches

confronts with many challenges in implementation and practice. Shehu and

Akintoye conducted research on UK construction industry in (2010) and they

fond 29 challenges that confronts the practice of programme management. In

order to reduce the list into more manageable number, factor analysis of Kaiser-

Meyer-Olkin (KMO) test has conducted and reduced the list into six factors that

confronts programme management practice. These factors being: strategy focus,

human and communication, financial, leadership and commitment, strategy

awareness, and benefits understanding. Below Table 2.5 is rotated factor matrix

that contains these major challenges (Shehu and Akintoye, 2010).

TABLE 2.5: MAJOR CHALLENGES OF PROGRAMME

MANAGEMENT PRACTICE (SHEHU AND AKINTOYE, 2010) Factor Challenges

Strategy focus Lack of cross-functional working

Lack of alignment of project to strategy

Lack of coordination between projects

Conflicting project objectives

60

Defining clear mission for the programme

Lack of programme delivery infrastructure

Lack of relevant training

Human and communication Perception among PM that programme serves as an obstacle to

accomplish project on time

Resistance to organisational change

People constraint

Lack of knowledge of portfolio management techniques

Lack of human/finance to analyse project data

Financial Initial funding and on-going operational costs

Lack of financial skills of projects

Financial constraints

Lack of clear company strategy

Lack of appropriate way to measure project benefits

Leadership and

commitment

Lack of knowledge to evaluate risks

Frequent changes of projects scope

Lack of business leaders commitment

Late delivery of projects

Lack of cross-functional communication

Strategy awareness factors Too many unrelated projects

Disappointment with final programme benefit

Presenting a detailed description of intended role of PMO

Lack of understanding of value proposition

Benefits awareness factors Lack of understanding of programme management

Lack of awareness of associated benefits

Whilst there have been a few studies that have addressed the general problems

of a multiple project approach to implementation, such studies are rate in the

specific case of internal development projects. Indeed, Elonen and Artto (2003)

were unable to find any studies that directly focused on the issues and problems

associated with the management of internal projects. However, some studies

have identified certain common problems encountered by companies developing

new products through project selection and portfolio management. The

researchers involved are specifically: Cooper et al. (1999) and Cooper et al.

(1998), and the seven persistent challenges are noted as being:

61

1. No link between strategy and project selection.

2. Poor-quality portfolio; this occurs when too many new product projects

are weak, or when the selection criteria are not in place in respect of

mature projects.

3. Reluctance to kill projects, such that project remain until the end of the

development work, even if their implementation is no longer justified.

4. Scarce resources. This obviously happens when numbers of on-going

projects are inappropriately mapped to the available resources.

5. Choosing easy and quick projects. This is a result of traditional bottom-

up approaches, as companies have a tendency to implement the short-

term, easy, and cheap projects.

6. Information overflow and the amount of available information for

making a decision may be confusing, irrelevant or inaccurate.

7. Decision-making based on power when there are in fact, many

interdependencies that require committee decisions.

Based on cause-effect analysis, Elonen and Artto (2003) used these above

problems as the starting point to understand the causes for their research, which

aimed to investigate causes associated with problems within the management of

internal development projects in the context of multiple projects. In his study,

six problem areas emerged as indicated in below Table 2.6:

TABLE 2.6: PROBLEM AREAS OF MULTI-PROJECT

ENVIRONMENTS (ELONEN AND ARTTO, 2003) Problem areas Challenges

Inadequate project level

activities

Improper implementation of the pre-project phase

Infrequent monitoring of project progress

Too long projects that are difficult to plan realistically

Lacking resources,

competencies and methods There are no adequate methods or guidance for portfolio

evaluation and project planning and management

Continuous shortage of resources, lacking commitment to the

project work

Inadequate competencies to manage a project

62

Lacking commitment, unclear

roles and responsibilities. The roles and the responsibilities between the portfolio

decision makers and the other parts of the organisation are not

clear

Management does not seem to support project work

Roles are not clear between the steering committee, the project

team and the project managers

Inadequate portfolio level

activities Projects were overlapping both within one portfolio and

between portfolios

Projects were not integrated into each other

The roles and the responsibilities of the portfolio manager is

not clear

No feedback given to the project level

Reluctance to kill undesired projects

In adequate information

management Lack of transparency in project information and its quality

Information does not flow fluently

Personnel is not clearly informed about when information

should be delivered

No common database for the projects

Inadequate management of project-oriented business

Project work is often given a second priority and not rewarded

equally to the other tasks

Strategy owner for the portfolio is not defined Rapid and recurring changes in roles, responsibilities or

organizational structure

Organisational levels and bodies are entitled to set up projects

In the same context, in multiple and concurrent projects environments the

number of projects are multiple; however, the teams are much smaller, and

project members actually remain in their function according to Payne (1995).

They have to consider a number of interface dealings with their project team, on

an individual basis, and not through their department head. And some team

members may work on several different projects, so they have to work with

multiple interfaces Payne (1995).

Different groups of individuals placed in one environment can create slightly

different cultures. This can cause culture problems for senior management if the

possibility of sub- and conflicting workplace cultures is not considered in the

63

early stage of a project (Payne, 1995). Consequently, Payne (1995) brought his

wide experiences in the field of project management and classified the

challenges to multiple projects within five categories, known as the ‘five Cs’,

being: capacity, complexity, conflict, commitment, and context. The common

elements between the five categories stated above are based on the intra-

organisational relations within the projects. In other words, they are all

underpinned by relationships between people and the organisation within which

they work. However, Payne have not provides much details of issues associated

with each of categories mentioned above; as he was more interested in

understanding the complexity. Thus, these categories will not be considered in

this study.

Based on what have been said, below Table 2.7 summaries the challenges facing

strategy implementation through the practice of project, programme, and PPM

approach, which will be used during the experimental phases of this study. As

this study are focusing on the practice of project management approaches, below

Table 2.7 used as the basis for the conducted interviews when exploring the

challenges facing organisations in Saudi Arabia during projects implementation.

This framework helps to define and code the problems when conducting these

interviews, which intend to find answers to the following two research

questions:

• What are the challenges and issues facing projects in practice?

• What is the source of these challenges?

TABLE 2.7: IMPLEMENTATION CHALLENGES FOR PRACTICING

PROJECT/PROGRAMME/PORTFOLIO MANAGEMENT (SHEHU AND

AKINTOYE, 2010; ELONEN AND ARTTO, 2003; COOPER ET AL., 1999;

COOPER ET AL., 1998) Challenges of Project

Implementation

Shehu and

Akintoye

Elonen

and Artto

Cooper &

Colleagues

1. Insufficient human resources or

lack of competent professionals

√ √ √

64

2. Project selection and decisions

based on power of hierarchy

√ √ √

3. No clear links between the

strategy and the project

√ √ √

4. Lack of the strategy

communication and awareness

√ √

5. Lack of communications

between the upper management

and lower staff

6. Lack of centralised IT software

to handle and share project

information

√ √

7. Inadequate capacity planning or

lack of resources allocation

8. Changes in project scope √ √

9. Project/programme management

responsibilities and roles are

overlapping

√ √

10. Lack of process or incorrect

practice of the

project/programme/PPM

management

√ √ √

11. Conflict between the

organisation structure and the

project execution

√ √

12. Changes in strategy √

13. Lack of the upper management

support for project management

roles

√ √

14. Insufficient financial resources √

15. Internal conflicts and lack of

team spirit

16. People resistance to change √

17. Project complexity √ √

18. Lack of cross-functional

working

√ √

19. Lack of programme delivery

infrastructure

65

20. Lack of relevant training √

21. Lack of knowledge of portfolio

management techniques

√ √ √

22. Lack of appropriate way to

measure project benefits

√ √

23. Lack of knowledge to evaluate

risks

24. Presenting a detailed description

of intended role of PMO

25. Late delivery of projects √

26. Disappointment with final

programme benefit

As mentioned by Sterling (2003) who claimed that most of the challenges or

‘causes of failure’ to be simply excuses for poor performance that had gained

creditability as genuine challenges merely by the fact that they were repeatedly

encountered. In comparison, the number of the challenges confronts the

implementation of project approaches were more than strategy implantation, as

it represents issues at operational level. Moreover, the challenges listed in Table

2.7 that confronts the implementation of project management practice were

occurred during the strategy implementation and repeated previously in Table

2.3 except cultural differences. This is supported by Pellegrinelli and Bowman

(1994) that sugessted to use project and programme approach that would helps

organisational members to perform outside the the exisiting organisational

bureaucracy and culture.

Regardless to the number of challenges, this study is much interested in

exploring strategy translation through the practice of project management. Thus,

listing these challenges has less contribution to the knowledge as many of the

management studies have mentioned previously most of them. Nonetheless, this

study will use challenges list in Table 2.7 as the basis for the Phase Two

interviews that to be conducted when exploring the challenges facing projects

organisations in Saudi Arabia. This list would help in define and label the

problems when conducting these interviews.

66

2.14 ORGANISATIONAL BEHAVIOR ASPECTS

Bacharach and Lawler (1980) highlighted organisational life as being based on

exchange and dependency or ‘interdependent’ relationships. These

interdependencies, power, conflicts, and shared responsibilities are part of the

business life cycle in every organisation. In respect of organisational conflicts,

there are different types and sources of these, and it is very important to

appreciate the possibility of these arising and to diagnose them when they do.

Often the damaging relationships that emerge from conflict result from both

intra- and inter-organisational reasons.

The organisational culture is an important management instrument in terms of it

providing a means of negotiation, co-ordination, and integration (Lax and

Sebenius, 1986). As mentioned already, in those projects where teams are small,

staff members find themselves dealing with many other personnel, and human

behaviour often needs to be mediated.

Daft (1998) notes the importance of the human resource, noting that the main

sources of organisational conflict are scarce resources and unclear

responsibilities, and in respect of scare resources, he identifies money, supplies,

people, and even information. In the real world, most organisations encounter a

certain degree of resource scarcity and interdependences that leads to an

increase in conflicts (Herbs et al., 2008). Therefore, intra-organisational theory

plays a major role in resolving such issues of shortage in resources. It has many

objectives, one of the most important being how to deal with a shortage of

resources (Herbs et al., 2008).

Conflicts occur in every organisation, especially in a multi-project environment,

and as such they make for unstable relationships among individuals. Payne

(1993) observes the different types and sources of organisational conflict,

making the point that it is important for managers to understand the potential for

these and be aware of how to diagnose them. Despite the variety in the character

of conflicts, however, all types of conflict lead to unwanted results which in

67

themselves work to the detriment of efforts to align strategy with

implementation (Payne, 1993).

In considering this intra-organisational conflict, it can be seen that this occurs

between parties within an organisation, and can concern the structure of the

organisation, the location of formal authority, and the way jobs are designed.

There are four types of intra-organisational conflict: vertical conflict, horizontal

conflict, line-staff conflict, and role conflict (Hellriegel et al., 1989). Each of

these is now described:

• Vertical conflict. This occurs between parties at different hierarchical

levels within the organisation, for instance between an employee and a

manager who is trying to maintain overall authority. The employee may

think that by reducing his/her powers through micro-management, the

manager is infringing the employee’s right to control some aspects of

his/her work.

• Horizontal conflict. This happens between employees or units within

the same hierarchical level. There are many potential causes of conflict,

such as disagreement of ideas or decisions being taken with which the

whole unit or units on the same level do not agree.

• Line-staff conflict. This occurs between support staff and other staff

within the same department. For instance, conflict in the perception of

staff and line managers when staff members take decisions without

considering their line managers’ opinions. In such circumstances, line

managers may feel threatened, believing that employees are trying to

reduce their (line managers’) authority over the project concerned.

• Role conflict. This arises when there is an expectation that at least two

different tasks will be performed within the same timeframe.

All conflict levels are inter-related and can trigger each other. For example,

intra-personal conflict may lead to inter-personal conflict if individuals act

aggressively or with hostility towards others (Hellriegel et al.,1989). Current

68

study, also explores the implications of these characteristics on chosen

organisations for this study in Saudi Arabia.

2.15 CRITICAL SUCCESS FACTORS FOR IMPLEMENTATION

As mentioned earlier, there is a wealth of research that offers advice concerning

the means by which to overcome failure factors in respect of implementation,

and one checklist which has been proposed as a summary of critical success

factors (CSFs) in this respect, is that produced by Sterling (2003). Sterling’s

(2003) critical success factors for translating strategy into effective

implementation emerge as a set of recommendations as follows:

1. Align organisational design and capabilities with the strategy.

2. Consider potential competitor reactions to the strategy.

3. Involve managers in the strategy development process.

4. Engage in consistent and persistent communication.

5. Action planning and budgeting.

6. Monitoring and accountabilities.

7. Symbolic actions or encouragement.

8. Alignment of information resources with the strategy.

Hrebiniak (2008) has approached the issues from the viewpoint of what

managers should be engaged in when trying to rise to the challenges posted by

implementation of strategy. In this respect, he argues that they should be:

1. Developing a model to guide the execution.

2. Understanding how the creation of the strategy affects the execution of

the strategy.

3. Managing change and culture effectively.

4. Understanding the power of influence and using it for execution success.

5. Fostering information sharing and co-ordination through the

development of the organisational structure.

6. Establishing effective controls and feedback systems.

7. Knowing how to create an execution-supportive culture.

69

8. Exercising execution-biased leadership.

Above CSFs’ or ‘advices’ can been seen as recipes for success that would be

helpful for those are involved in the implementation process. There are much

studies offering advices to implementers wishing to remove these failure factors

(Sterling, 2003). However, these advices considered as temporay solutions for

curing todays problems as this supported by first rule of the fifth disciplines, and

according to Senge (1990:57) who believe that “today’s problems come from

yesterday’s solutions”. Therefore, above recipes for success have less

contribution as they were repeated in many of organisation and management

studies, more importantly is how these recipes have been translated in practice

for better strategy implementation. As Kaplan and Norton (2008) stressed that

strategy implementation needs an architecture that can link the strategy with the

operations. The next Chapter will discusses strategy from practice perspectives

and aspects related to translation theory, in order to explore how strategy and

project approach translated in practice.

2.16 CLOSING THOUGHTS

This chapter has conducted a review on published works relating to organisation

and management studies on strategy from capabilities perspective. Regardless of

the dilemma of strategy definition, strategy from the researcher’s viewpoint can

be perceived as a road map designed by senior managers in order to express

their organisations’ vision. Considering vision as futuristic image inscribed in

the mind of senior managers i.e. ‘CEO’ of an organisation, strategy guides

organisation members in understanding how the final image will be drawn or

achieved. If the futuristic image was blurry, so too will be the strategy;

therefore, the vision and mission of an organisation must be clear to all

organisation members.

There is general agreement that there are only two theoretical approaches for

strategy, deliberate and emergent. Deliberate approach assumes that there can be

a logical and structure approach to the planning, and outcomes delivery to be as

70

intended. Emergent approach developed usually in response to changes that may

occurs to the market or business environments. Once the senior managers have

taken the required strategically decisions the remaining managers at less

seniority levels are responsible to implement theme. The belief that senior

managers can manage strategy has become dominant, and based on rigid

application and rational decision of top-down approach. Capabilities perspective

acknowledged that individuals are involved in the processes but omits the

influences of individual agency. Moreover, capabilities perspective assumes that

routines operate and deliver as intended. However, various studies revealed a

number of challenges associated with the implementation, which contradicts

with the capabilities assumptions and this supported by practice perspective.

Bearing in mind that strategy is a process and not a destination, it’s become

clearer that strategy is not a done deal thing, and as capabilities do not just

emerge, and are more than something those firms do well. Focusing on the

effectiveness of performed processes, implementation is complex process that

involves people across organisation. As a part of the process, translation of

strategy or project management practice that usually results in producing new

form, documents ‘objects’ or artefacts. However, capabilities perspective dose

not discussed the influences and the effectiveness of these objects or ‘artefacts’.

It has been argued that by adopting a project management approach,

organisations can ensure greater success for strategy implementation. The

literatures on the implementation of projects, programmes, and projects

portfolio management are incomplete and lacks to the basic practical details of

approach implementation. Frome capabilities perspective, these approaches

viewed as a ‘black box’ that mainly interested in what routines accomplish

toward organizational goals. Consequently, there is a needs for practice lens to

explore how these approaches are being implemented in the real project world,

with emphasizes inside the ‘black box’ on how routines are enacted in the day-

to-day.

71

Despite of the revealed challenges that facing project, programme, and projects

portfolio management in practice, some studies offered advices to overcome

these challenges during the implementation as recipes for success. However,

these challenges and advices have less contribution as they were repeated in

organisation and management studies; more importantly is how these recipes

have been translated and communicated in practice.

Thus, this research needs for practice lens to get insight the aspects associated

with strategy in particular: individual agency, artefact, and the ‘black box’ of the

approaches. The next chapter will elaborate on the strategy from practice

perspective.

72

CHAPTER THREE

LITERATURE REVIEW PART II: STRATEGY

FROM A PRACTICE PROSPECTIVE

3.1 OVERVIEW

This chapter presents the second part of the literature review carried-out during

the study, which focuses on strategy from practice perspective. It presents the

theoretical and the fundamental concept of the strategy from practice lens, the

theory of translation and models. Additionally, it offered theoretical

perspectives that relate to the practice through strategy as practice (SAP).

3.2 PRACTICE PERSPECTIVE

The practice perspective in the organizational and management literature rose

from the gap between the theories of what ‘people say they do’ and ‘what

people actually do’ (Whittington, 1996). In this study, the needs for exploring

strategy form the practice lens rose from the limitation of the capabilities

perspective to discover the influences of individual actors, artefacts, ‘black box’

of the organisational routines that associated strategy. This gap supported by the

study of Paul Feiler and David Teece (2014) that summarises the differences

between the capabilities and practice that lays on their fundamental assumption.

Capabilities perspective pay attention particularly to organisation routine and

how they build to form capabilities, how create value, and the transferability

within and between an organisations. On the other hand, practice perspective

focus on individual actors and artefacts influences on routines performance, how

routine is been created and the role of the artefacts on routine stability and

change. Capabilities perspective acknowledged the change with more interest in

stability. In contrast, the practice perspective view both change and stability is

possible (Feiler and Teece, 2014).

73

The practice perspective on organizational is grounded in the work of Feldman

and Orlikowski (2011) that study “the everyday activity of organizing”

(Feldman and Orlikowski, 2011: 1), which based on works of social theorists

mainly Bourdieu and Giddens (Bourdieu, 1977, 1990; Giddens, 1984), who

describes how everyday practices are accomplished, reinforced, or changed .The

emphasis of a practice perspective on routines is on the internal workings of

specific routines in specific organizational contexts. It is concerned more about

the effectiveness of strategist than the organisation, and is built heavily on the

insight process but from a managerial level (Whittington, 1996). Feldman and

Pentland (2003) argues that this focus on internal workings open the ‘black box’

of organisational routines and conceptualize them as being made of interacting

parts.

The main question asked within practice perspective is ‘what does it take to be

an effective strategy practitioner?’ Clearly, this concern with how strategy

practitioners behave and interact actually in the business world. Strategy

practitioners including organisation individual actors from multiple levels as

well powerful external actors like consultants and regulators (Jarzabkowski and

Whittington, 2008). Obviously, strategy is not a fully formed thing that ready

for implementation but it mediated through individual actors who involved in

the translation and through objects or artefacts that resulted from the translation

process. Both individuals and objects are useful stuff for communicating

strategy and have influences on how things translated and communicated. Thus,

strategy practitioner ‘ individual actors’ at all organisation levels and strategy

documents ‘objects’ will be used as unit of the analyses for investigation in this

study.

Empirical studies conducted in (2011) from the practice perspective, to capture

situated action and develop an understanding of how routines came to life in

particular organizations (Parmigiani and Howard-Grenville, 2011). In each

study the authors make an effort to generalise the theory, and beginning to build

a coherent body of understanding around three main areas. First, several studies

74

have built theory on the role of individual actors and agency in shaping routines.

Second, a few studies have investigated the role of artefacts in routines. Finally,

a few studies have focused on the embeddedness of organizational routines in

other sides of organizational life. These three areas are discussed in details in the

following.

• Individual actors and agency

There are two assumptions to be considered underlying practice theory and

their implications for work on routines. First assumption, practice

approaches highlight human actors and agency, seeing people’s everyday

actions as consequential in “producing the structural contours of social life”

(Feldman & Orlikowski, 2011: 2). Scholars working in this tradition seek to

access specific actions of people’s behaviour placed in specific places and

times, and based on generalized principles of how action might unfold in

other settings. The second assumption emphasis on, to what extent the

patterns remain stable versus change over time. The core assumption is that

“phenomena always exist in relation to each other, produced through a

process of mutual constitution” (Feldman & Orlikowski, 2011: 3). Mutual

constitution suggests that structures including routines, institutions, and

other social orders are the product of human action, however, human action

is controlled and enabled by these actual structures (Giddens, 1984).

The practice perspective on routines portrays them as both emergent and

generative; emergent that comes only through being performed by actors and

generative or ‘ reproductive’ that maintain their own continuity or change

((Feldman, 2000); Feldman & Pentland, (2003)). Some studies suggest that

routines provide stability while the surrounding organizational structures and

practices facilitate adaptation (Karim& Mitchell, 2000). On other hand some

scholars views routines as a basis for organizational change through learning

and demonstrate how routines can affect firm boundary decisions. This view

supported by works of Karim and Mitchell (2000), Mitchell and Shaver

75

(2003), and Zollo and colleagues (2002). In the next, we turn into empirical

studies on artefacts from the practice perspective.

• Artefacts or ‘Objects”

Few empirical studies have investigated the role of artefacts in routines

performance (Parmigiani and Howard-Grenville, 2011). Artefacts referred

by some as non-human actors, either as representations or material entities;

representations including documents like policy, plans and standard

operating procedures, while material entities like computer software and

physical spaces (Parmigiani and Howard-Grenville, 2011). Artefacts could

signal routines performances and enable their replication. However, earlier

empirical work around artefacts demonstrating that artefacts do not

necessarily act as expected in encoding or indicating routines (Parmigiani

and Howard-Grenville, 2011). These empirical works suffer from the same

challenges that found artefacts either matter a great deal, or not at all, for

specific routines.

Based on these few studies, and insights from others, artefacts appear to

have an important, but somewhat ambiguous role, in routines (Howard-

Grenville [2005]). Sometimes they matter a great deal; at other times, they

only minimally encode a routine and do even less to influence its on-going

use. The role of artefacts in routines continues to be an exciting area of study

in work done from the practice perspective. Some scholars are using actor

network theory (ANT) to theorize the interactions between human and non-

human actors (D’Adderio, 2008; Pentland & Feldman, 2008a). In the next,

we turn into empirical studies on embeddedness from the practice

perspective.

• Embeddedness

First empirical paper conducted by Feldman in 2003, notes the importance

of the organizational context to the performance of routines, arguing that

performances within and outside the routine itself shape the dynamics of the

76

routine. The context in which routines are embedded shapes their use.

However, change in organizational routines may be difficult to accomplish

when the change is inconsistent with people’s understandings of how the

organization works (Feldman, 2003).

Routines are embedded in cultures, technologies, and coordinative structures

within an organization are become more resistant to change over time. From

a form of planning ‘road-mapping’ routine, actors’ intentions, their

background and artefacts influence situated routine performances and may

provide stability or produce change over time (Howard-Grenville, 2005).

The implication is that routines have internal dynamic or ‘drives’ for their

reproduction that rely neither on mindless, habitual performance as a source

of stability nor on external shocks as a source of change (Gersick and

Hackman, 1990; Meyer, 1982). Even seemingly stable routines that do not

change over time are regarded as the effortful accomplishments of actors

(Pentland and Rueter, 1994: 488). Mutual constitution also implies that

“stability and change are different outcomes of the same dynamic, rather

than different dynamics” (Feldman and Orlikowski, 2011:6).

Overall, above reviewed empirical studies on practice perspectives provide

important descriptions and details on how routines operate and change. These

studies confirm that everyday actions are significant for performance, and

change or stability of routines. Moreover, these studies shows that who performs

a routine is very important to how that routine is enacted (Parmigiani and

Howard-Grenville, 2011). However, as commented by Parmigiani and Howard-

Grenville (2011: 440) “A second common element, also consistent with practice

theory, is that authors further uncover the internal dynamics of routine

reproduction”. Following sections attempts to uncover the black box of internal

dynamic of routines through further theoretical concepts including translation

theory and strategy as practice (SAP).

77

3.3 TRANSLATION THEORY AND THE STRATEGY

In linguistic debates concerning the status of translation, arguments are

presented as to whether translation is an art or science. From a scientific point of

view, translation is perceived as seeking to create some kind of objective

description of phenomena (Bell, 1991). It is the expression in another language

of what has been expressed in a different, source language, described by Bell

(1991:6) as “the replacement representation of a text in one language by a

representation of an equivalent text in a second language”. However, as noted

by Bell (1991), the replacement does not necessarily mean a literal translation

since it can be the case that different linguistic structures and vocabulary prevent

this.

The emergence of translation theory used in social sciences, was borrowed from

Michel Serres, who introduced it in his series of Hermes books (Serres and

Brown, 2002). In his conception, Serres views translation as “a generalized

operation, not merely linguistic, and it takes many different forms. It may

involve displacing something, or the act of substitution; it always involves

transformation. Consequently, that which is involved in translation be it

knowledge, people or thing – has uncertain identity. Each act of translation

changes the translation and what is translated” (Czarniawska and Sevon,

2005:8). This idea adopted by both Michel Callon and Bruno Latour,

sociologists in the areas of science and technology. Callon used this notion

primarily in Actor Network Theory (ANT), and emphasised its homologising

effects, stating: “[translation] postulates the existence of a single field of

significations, concerns and interests, the expression of a shared desire to arrive

at the same result. …Translation involves creating convergences and

homologies by relating things that were previously different” (Callon, 1980:

211).

In this sense, we can consider organisational vision as a ‘shared desire’ – a

situation that an organisation aims to achieve in the future and pursues by

translating the ‘desire’ (vision) into strategic goals/objectives. This is an

78

identical view to that put forward by translation theory. However, by comparing

what organisations want, that is to say their ‘shared desire’, and what they

actually achieve, the ‘outcome’ of the daily activities, it becomes obvious that

the desire and outcome are different. Czarniawska and Sevon (2005:8)

substantiated this by saying “the desire to become similar might be at its

origins”. Considering, individual actors as factors involved within the process

of translating the strategy, it becomes clear that the practice angle is an

important one to the research.

Latour (1986) was not certain about the results of the translation. Indeed, he said

that “the spread of time and space of anything - claims, orders, artifacts, goods-

is in the hand of people; each of these people may act in many different ways,

letting the token drop, or modifying it, or deflecting it, or betraying it or adding

to it, or appropriating it.”(Latour, 1986:267). But actually, Latour’s idea about

translation explains precisely what happens to an organisation’s vision and

strategy in the process of translating these into strategic plans. Clearly, at the

start of the process, all participants will have had the same desire, but the result

of personal inputs may well render the ‘translated strategy’ as somewhat remote

from the original desire. The best way to understand this point is to treat

translation as a form of communication, or a message passing between points.

Contemporary rhetoric around communication holds the term as an unalloyed

either good communication or miscommunication, where good communication

is good and miscommunication is an error or a disaster (Serres and Brown,

2002).

In 1996, Czarniawska and Sevon adopted Latour’s approach to understanding

translation in an attempt to comprehend the continuous circulation of

management ideas and practice. In reporting their observations they said:

“With our contributors, we watched how management ideas translated into objectives (models, books, and transparencies), sent to other places, translated into new kind of objectives, and sometimes in actions, which, if repeated, might have stabilized into institutions. […] We have noticed that the

79

concept of translation is a good way to describe the emergence and construct of various types of connections around the globe exactly because it is polysemous: albeit usually associated with language, it also means transformation and transference”(Czarniawska and Sevon, 2005:8).

They continued by saying that the main point was that when things moved from

one place to another, they are subject to change. This change is due to the

transformation of the idea into new type of objects or the movement into new

place. Moreover, Czarniawska and Sevon (2005) believed that translation is

associating directly with symbolic or ‘material’.

“Thus, translation is a concept that immediately evokes symbolic associations, while at same time being stubbornly material: only a thing can be moved from one place to another and from one time to another. Ideas must materialize, at least in somebody’s head; symbols must be inscribed, otherwise, it is bound to be ephemeral” (Czarniawska and Sevon, 2005:9).

Consequently, organisation strategy must be understood, remain in people’s

minds, and connected with their daily activities through the concept of idea

materialization; otherwise the strategy would be ephemeral.

“A practice or institution cannot travel. It must be simplified and abstracted into an idea, or at least approximated in a narrative permitting a vicarious experience, and therefore converted into words or images. Neither can words nor images travel until they have materialised, until they are embodied, inscribed or objectified, as only bodies or things can move in time and space” (Czarniawska, 2002:7).

The notion of materialising an idea by converting it into words and images in

order to enable its transfer across time and space is a critical part of the strategy

translation. Below Figure 3.1 presents the translation concept of practice that

proposed initially by Czarniawska (2002) is based on two fundamental steps:

simplification and materialisation. However the frequent application of the

translation concept could change the original practice or could be viewed

differently at different levels of the organisation.

80

Figure 3.1: Translation Conceptual Frameworks (Czarniawska, 2002)

3.4 VEHICLE AND MODEL OF THE TRANSLATION

Czarniawska and Sevon, (2005) asked the question of what puts the vehicle of

translation in motion, to which Callon (1980) responded by saying it was the

shared desire that served as the motivator. Behind the translation there is

imitation, a fundamental learning mechanism used by all people since childhood

(Czarniawska and Sevon, 2005). However, how does any person know what to

imitate? In other words, what to translate and what not to translate?

At the same time, the more imitated something is, the less attractive it becomes

with time. However, there is always a room ‘for new fashion’ for subsequent

translation according to Czarniawska and Sevon (2005). The circular ‘spiral’

process produces massive variety of different results. It is easy to say that an

idea must be materialised in order to travel across time and space, and it is not

very surprising to see that this can happen by turning the idea into an object

such as a documents, forms, plans and picture. However, the question being

asked once the idea has been materialised, what is spreading the idea? And is it

the form and documents, or the content of the idea that is being disseminated, in

the case of organising practice. One thing that travels easily and with great

speed is a name.

The empirical study conducted by Czarniawska and Sevon (2005) on Sweden’s

state administration, shows how the idea and the experience of the UK economy

Practice

Simplification

Materialisation

81

arrived in Scandinavia that faithfully follows the UK example but has never

used the name. On the other hand, organisations and people do different things

and call it the same name. The best example for that is the state of Victoria in

Australia which imitated the best value reform from UK but did it in its own

way (Czarniawska and Sevon, 2005). In the same sense, an organisation

borrows one of the many management concepts or models for strategy

implementation, depending on its particular needs. In this connection, various

project management models have been used by many organisations as vehicles

for implementing strategy, as has already been indicated. Thus, the study will

also investigate what has travelled in the case study organisations, asking the

question of whether it has simply been the name or the whole practice ‘concept’.

As well as names and forms, practice also travel when incorporated in human

bodies or prescribed in detail. The provoking question here is what is actually

translated in the case of, for example, strategic plans and websites? Is what

appears in such documentation a written description of action (practices) or is it

merely an artefact, a symbol purely for show. This question posed by

Czarniawska and Sevon (2005) before they indicate that the next question is

concerned with who is doing the translation – ‘the travel agent’ as it were. And

clearly, the answer can vary from an external consultant working for a given

organisation, to organisational members themselves (i.e. the people who are

responsible for the practices to emerge from the strategy) (Czarniawska and

Sevon, 2005). Consequently, another aim of the present study is to explore who

is playing the role of the travel agent in organisations under the investigation,

and the implications of that.

It must be borne in mind that the theory of translation accepts that the translation

activity is a normal part of human daily life, enacted unconsciously by people to

understand their environment. This supported by Senge (1990:3) said that

“[f]rom a very early age, we are taught to break apart problems, to fragment

the world. This apparently makes complex tasks and subjects more

manageable”. Usually, people break down any complex or unclear idea into

82

smaller ideas in order to make them more comprehensible. This is what most

organisations do in order to make their strategy more understandable by

individuals within the organisation and more manageable for those in charge of

delivery. In this effort, organisations make use of many management tools and

models that are available to help translate their strategies into actions, but they

often do so without considering the consequences, and there are implications of

such an approach. In this matter, Senge (1990:3) argues that “we pay a hidden,

enormous price […] we lose our intrinsic sense of connection to a larger whole.

When we then try to ‘see the big picture, we try to re-assemble the fragments in

our minds, to list and organize all the pieces’”. He continues by quoting the

physicist David Bohm, saying, “the task is futile - similar to trying to

reassemble the fragments of a broken mirror to see a true reflection” (Senge,

1990). The outcome of the frustration experienced in this matter means that after

a while we give up trying to see the whole altogether.

One thing is clear, that strategy does not exist as done deal thing that can be

achieved as one whole piece. Therefore, strategy cannot travel from the status of

an idea or plans into that of implementation without some form of simplification

(Czarniawska and Sevon, 2005). The ‘travel agent’ can be considered as the

implementation model, as this agent purports to help organisations by breaking

down, or translating, the shared vision into objectives and actions, and this

applies whether the ‘agent’ is selected from within the organisation, or

outsourced through external individual/agency coming to the issue on a

consultancy basis. In this respect, Gray and Larson (2008) defined two

approaches in particularly to outsourcing, these being, the traditional one and

the partnering one. The traditional approach is similar to the master-slave

relationship that exists between the owner and the provider; whereas, the

partnering approach involves all parties working together as partners and

sharing the ultimate goals of success. This study investigates the process of

translating the strategy, whose in charge for the strategy translation, and

explores what organisations do to communicate and keep themselves connected

with the big picture.

83

3.5 TRANSALTION AS COMMUNICATION TOOLS

In this respect, strategy implementation is a multi-level process involving people

at different levels throughout the organisation, but as confirmed in a recent

survey conducted by Harvard University, it occurs through a top-down

approach. This observation supported by Cunha et al. (2011:491) who noted that

“strategy still comes from the top, and hierarchy can hurt execution”. They also

argue that members operating at the base and the frontline of an organisation are

very important. Thus ignoring this segment at organisation level has a cost or

‘hidden cost’ on the execution (Cunha et al., 2011). The centrality of hierarchy

in the strategy implementation debate is clear. Unsurprisingly, the disconnection

between the formulation and the implementation of the strategy is also obvious.

In this respect, Cunha et al. (2011:492) argue that “strategists still formulate,

the rest still execute, and there is no conjuncture between formulating and

executing”. The problem with this approach is that the principle of scientific

management is time dependent, and the emergence of new organisational forms

is knowledge-intensive rather than work-intensive. Furthermore, the hierarchy

or traditional top-down approach affects the implementation and limits the

usefulness and applicability of the strategy implementation (Cunha et al., 2011).

Therefore, it is necessary to seek alternatives to the traditional approach and to

show how these are able to bridge the formulation and implementation gap.

From what have been said, the top-down strategy approach is dominant in most

of organisational and management studies; in which senior managers initiate the

ideas and sets direction for the organisation. However, the implementation of

the strategy is with those managers and staff who are lesser-seniority in the

organisation, and the separation between activity of strategy development and

the implementation stands as the main challenge to the effectiveness of the

overall process. Hrebiniak (2008:7) confirmed this structural fact, by saying

“[e]very organization, of course, has some separation of planning and doing, of

formulation and execution. However, when such separation becomes

dysfunctional - when planners see themselves as smart people and treat the

doers as ‘grunts’- there clearly will be execution problems”.

84

In this matter, the most crucial dimension to be improved is the communication

flow between the senior managers ‘strategy-makers’ at the top-level of an

organisation and the less-seniority ‘strategy-implementers’. Porter (1996)

emphasises the need for clear communication and constant discipline if strategy

is to be properly implemented, and Hussey (1996:11) says that “[i]t is the task

of ensuring that others in the organization understand, support and eventually

share the vision. The vision cannot be understood unless it communicated, and

cannot be communicated unless it is defined in a coherent way”. It is very

important that all employees, whatever their level, feel passion, and inspired by

their organisation strategy.

In order to shift employees’ thinking from doing without understanding into

strategic visioning, Hussey (1996) proposed the ‘envisioning’ idea that proposed

as a method for improving the translation concept. Hussey (1996:10) defined

envisioning as a “process of developing a coherent view of the future in order to

form an overarching objective for the organisation. […] Vision is an

appropriate first step for implementation at various levels in the organisation,

and will be as critical for the leader of a business unit, or the head of a

section”. On the other hand, proposing the concept of envisioning in the

translation concept, the translation would represent a coherent view of the

practice or strategy. Additionally, it would help in improving the visualisation of

the ‘shared vision’ by encouraging the imagination of employees across the

entire organisation. “Imagination is about improving the ability to see and

understand the situation in new ways” (Morgan, 1997:2).

Carroll (2000:183) argued that imagination plays a major role in leadership,

saying “[n]ew things must first be imagined. Likewise, imaginative failure

entails certain consequences”. The importance of the imagination in improving

employees’ understanding is emphasised by Gillen (2000:146) who stated that

“[l]eaders of learning must encourage the employees’ implementing strategies

to see and understand situations in new ways. This is the ability to allow

employees to change the old practices of bureaucratic organizations and

85

produce new self-organizing systems”. Furthermore, the importance of the

imagination is based on offering pragmatic insights that help to resolve many

dilemmas associated with strategy implementation (Carroll, 2000).

3.6 STRATEGY AS PRACTICE (SAP)

As mentioned earlier, the ‘practice’ approach in the management literature rose

from the gap between the theories of what people say they do and what people

actually do. This practice perspective is concerned more about the effectiveness

of the strategist than the organisation, and is built heavily on the insight process

school but from a managerial level (Whittington, 1996). Jarzabkowski

(2004:529) emphasises the importance of practice by saying “we should

examine strategy not as something a firm has, but something a firm does”.

Practice theory is used to explain people’s behaviour by putting the practice as

the first object of research. Meaning is formed by doing and that is not an

independent state of mind. Bourdieu proposes a theory of practice that is to

“transcend the objectifying standpoint of the other two sorts of knowledge by

constructing the ‘generative principle’ of practice, by situating itself within the

very movement of accomplishment” (Acciaioli, 1981:26). Similarly, strategy as

practice (SAP) focuses on the strategy-maker from social lens. Strategy-makers

or ‘strategists’ use their practical daily skills for formulating a strategy;

however, little is known about how they do this, or indeed about how they

acquired the skills to do it. This appreciation of the reality opened a new

direction of thought from the practice perspective that was concerned more

about the effectiveness of the strategist than the organisation (Whittington,

1996). SAP considers strategy as something that organisations are involved with

developing and implementing everyday (Whittington, 2006). This view does

require, however, that the social context must taken into account since at the

micro-level of strategy the actors are not acting in isolation. Indeed, in the real

world “actors are not acting in isolation but are drawing upon the regular,

socially defined modes of acting that arise from the plural social institutions to

which they belong” (Jarzabkowski et al., 2007: 6).

86

According to Jarzabkowski and Whittington (2008), studies on SAP are not

intended as a prescriptive for improving practice by providing explanations of

activity and consequences. Rather, they are concerned with explanatory theory,

which benefits from familiarity and reliability, attempting to reflect accurately,

what happens in actual practice (Jarzabkowski and Whittington, 2008). Whilst

people formulate and implement strategy, strategy theory is populated with

multivariate analysis of industry-level effects upon firm performance. However,

the absence of human/individual actors and their actions in most strategy

theories has increased the dissatisfaction of conventional strategy research

(Jarzabkowski and Spee, 2009).

“[m]uch of the social infrastructure, such as tools, technologies and discourses, through which micro-actions are constructed has macro, institutionalized properties that enable its transmission within and between contexts, whilst being adopted and adapted differently within micro-contexts” (Jarzabkowski et al., 2007: 6).

In SAP, tools and technologies enables transmission between micro-actions and

macro across the contexts. Consequently, two questions arise here, what are the

theories behind SAP? Does it require any further theory from the sociological

disciplines? Jarzabkowski et al. (2007) argue that SAP as a field is characterised

less by what theory is adopted than by what problem is explained. As such,

many problems posed in existing strategy research, such as those concerned

with dynamic capabilities, the resource-based view, the knowledge-based view,

and strategy process theory might be illuminated by a practice-based approach

to their study (Jarzabkowski et al., 2007). Therefore, the field does not requires

a new theories, but build upon a range of existing theories to explore the

strategy problems and to develop novel methods and research designs for their

study (Balogun et al., 2003).

87

Figure 3.1: Theories Related to The Field of SAP (Jarzabkowski et al., 2007)

Moreover, additional advance explanations of how strategy is accomplished

using these different levels and units of analysis are required. The empirical

research into SAP has drawn upon the diverse theoretical resources available in

areas such as practice, sense-making, cognition, culture, power, narrative and

discourse theory as depicted in Figure 3.1 (Jarzabkowski et al., 2007).

From the theory of practice, Whittington (2006) proposes three elements that

may be isolated: praxis, practice, and practitioners; each one comprises a

different analytic choice and entry into the field of SAP (Jarzabkowski et al.,

2007). Many practice theorists have identified one or more of these elements in

their studies as discrete but inter-related social phenomena. There has been

impressive empirical progress given the promising state of SAP fields.

However, the ongoing challenges of SAP remain in those contributions of this

field that may yet be developed by further exploring the issues raised by the key

research questions and grounding these within the integrative framework that

involves three parameters praxis, practices and practitioners and their

relationships. As Jarzabkowski (2004) suggested, further empirical research is

required, and this study has been explicitly framed and designed to address the

SAP research agenda. Figure 3.2 briefly depicts this overview of praxis,

practices and practitioners, which provides a conceptual framework, and which

simultaneously be used to link some of the key questions within a SAP research

SAPRelatedTheories

Practice

Power

Naritive

DiscoursesCulture

Cognition

Sense-Makaing

88

agenda.

Figure 3.2: Conceptual Framework to Analyse SAP (P. Jarzabkowski et al.,

2007:11)

Each of parameter in the framework is defined below.

Praxis: This is an emphatic term that describes the flow of human action in

which strategy accomplished within an institution. “Praxis comprises the

interconnection between the actions of different, dispersed individuals and

groups and those socially, politically, and economically embedded institutions

within which individuals act and to which they contribute” (P. Jarzabkowski et

al., 2007:9). This definition is very important and plays a major role in building

the understanding of the human actions and interactions that constitute the

framework of SAP. It indicates that praxis is both an embedded concept that

may occur at different levels from the institutional to the micro, and also

dynamic, shifting fluidly through the interactions between levels (Jarzabkowski

et al., 2007). It takes into consideration the fact that human actions and activities

are not singular but reflective of the pluralistic nature of society.

Practice: The social, material and tools that strategy work done through.

Reckwitz (2002) describes practice as type of routine behaviour that consist of

89

interconnected elements. Reckwitz (2002:249) defines practice as “routinized

types of behaviour that consist of several elements, interconnected to one

another: forms of bodily activities, forms of mental activities, ‘things’ and their

use, a background knowledge in the form of understanding, know-how, states of

emotion and motivational knowledge”.

Practitioners: These are the individual actors who act upon practice.

“Practitioners are thus interrelated with practices and praxis. They derive

agency through their use of the practices ways of behaving, thinking, emoting,

knowing and acting prevalent within their society, combining, coordinating and

adapting them to their needs in order to act within and influence that society”

(Reckwitz, 2002:249).

Strategizing occurs between praxis, practice, and practitioners and referred for

doing strategy. Therefore, in order to develop a richer understanding of these

three elements, it is vital to explore the correlation between them. Moreover, it

is important to examine strategy not only at the organisational level but also to

analyse the social dynamics between the elements at the institutional, and,

particularly, the sub-organisational levels of activity, which are still weakly

operationalised in much strategy research (Jarzabkowski et al., 2007). As a

practice-based approach, SAP constitutes an attempt to get close to practitioners

and their activities in order to gain a deeper understanding of what actually

happens when people engage in practices. The approach seeks to bridge the gap

between the strategy and the practice by engaging deeply in the empirical details

of organisational life in reality (Whittington et al., 2003; Jarzabkowski and

Spee, 2009;Whittington, 1996). However, recent research by Splitter and Seidl

(2011:99) draws on the theory of Bourdieu, and criticises the practice-based

approach by saying, “it is unclear to what extent and under what conditions

practice-based research would prove relevant to practitioners”. In the same

context, scholars argue that most practice-based strategists are unaware of their

inevitably ‘scholastic view’ which is the cause of the gap between strategy

research and praxis (Splitter and Seidl, 2011).

90

From the project perspective, SAP represents the efficiency of daily activity of

actors and how these activities are linked with the organisation. By focusing on

project management as approach for strategy implementation, this study

explores how practitioners translate the practice, how interconnected with each

other, what social infrastructural material/tools/procedures they use to do this,

determining whether they help in connecting employees’ daily activities with

organisational goals.

Tools are not necessarily applied instrumentally, their use being shaped both by

social and political dynamics between actors and by the particular characteristics

of the tool itself. Strategy tools are defined as “numerous techniques, tools,

methods, models, frameworks, approaches and methodologies, which are

available to support decision making within strategic management” (Clark,

1997: 417). Within these tools are frameworks such as Porter’s five forces, core

competences and various other matrices and models (Spee and Jarzabkowski,

2009). In deed, powerful actors may use tools specifically to constrain the array

of strategic choices (Spee and Jarzabkowski, 2009). In the same sense, strategy

tools are employed differently in order to provide a common language for

organisational conversation. Thus, it is important to understand how translation

outcome or ‘objects’ is communicated? And how this understood by different

management levels within the organisation. Existing research confirms that

strategy tools are indeed used in practice, but such studies offer only limited

clues about how they are used.

3.7 CLOSING THOUGHTS

This chapter has presented the second part of the literature review, which

explores strategy from practice perspective. It has covered various aspects

related to practice perspective including (i.e individual actor, artefacts, and

embeddedness), which missed in capabilities perspective. The tension between

the strategy formulation and implementation viewed through theory of

91

translation and SAP, thereby weakening the connectivity between the daily

activities of individual actors and organisation vision or the ‘big picture’.

It was confirmed in this chapter as in the previous one, that strategy defines as a

road map drawn by strategists to enable them to achieve the organisational

vision. As the vision being the big picture of organisation in the minds of senior

managers relating to where the organisation should be heading. The strategic

plans are artefacts that drawn up by strategists to portray the objectives, which

must then be translated into a set of manageable action plans. In this

‘translation’ exercise, the theory of translation has been shown to be useful, and

specifically, the process is seen to unpack the inter process of practice and how

it been translated and who is in charge for the translation.

The outcomes of translation process including documents, procedures and

strategic plans, are representing artefacts for communicating strategy and

connecting individual actors with an organisation big picture. When the various

organisational actors are presented with a big picture only, the task they face in

implementation is seen to be very difficult. So too, when they are confronted

with many detailed plans, because in this case they are faced with the task of

reassembling all the fragments into the big picture. This whole process can

result in the organisational actors forgetting or losing the connections with the

original vision, and ending up with a blurred picture of what is necessary.

Bearing both literature chapters that summarised in Table 3.1, it become clearer

that strategy are not a fully formed things ready for implementation but it

mediated through individual actors and objects that involved in the translation

process. Both individuals and objects are useful stuff for communicating

strategy and have influences on how things translated and communicated.

Strategy practitioner as ‘individual actors’ at all organisation levels and strategy

documents as ‘objects’ will be used as unit of the analyses for investigation in

this study.

92

TABLE 3.1: SUMMARY OF STRATEGY PERSPECTIVES BOTH

CAPABILITIES AND PRACTICE

Strategy Capabilities Perspective Practice Perspective

Approach Deliberate Emergent

Assumption • Strategy delivered as intended • Acknowledged the role of

individual actors/agency

• Response to market and environment changes

• Acknowledged the influences of individual actors and objects

Focus on Routine as whole ‘black box’ What inside ‘black box’

Challenge Not flexible to changes of markets or business environments

Unclear about the role of individual actors and objects in strategy communication

Gap Neglects the influences of individual actors and objects

Fails to uncovering what inside the routine ‘black box’

Bearing all the literature in mind, the next chapter discusses in detail how this

study achieves its objectives, by adopting a particular research design and

method.

93

CHAPTER FOUR

RESEARCH DESIGN AND METHODS

4.1 OVERVIEW

This chapter introduces the research methods that were used in the study. It

provides a general overview of the research design together with the

researchers’ reasoning in respect of his choice of case study organisations, the

methods used for data collection, and the data analysis. It also presents research

methodology used in this study by giving an overview of the empirical work. In

doing this, it discusses the design of the research, the strategy followed, and how

the fieldwork was actually conducted, from the start to the finish.

4.2 RESEARCH AIM AND OBJECTIVES

It is important to briefly reflect on the research aims and objectives presented in

Chapter One before elaborating on the research design and methodology. In this

respect, it was stated in Chapter One, that this study aims to explore how project

management approach being implemented in real project environment, and

understand what are the influences of the translation model on the

implementation.

By focusing on the implementation, this study explores various approaches and

models used in translating strategy within projects environment. Additionally,

understanding how the practice of the project management has been translated,

it explores the problems associated with the approach in each industry. Given

the need for a better understanding of the challenges associated with strategy

implementation, this research applying the translation lens on strategy and

practice implementation in a real projects-oriented environment in such a way as

to include the practice perspective. The next sections present information

94

relating to the research philosophy, methodology, and techniques that have been

adopted in order to suit the context and aims of this study.

4.3 RESEARCH PHILOSOPHIES

Saunders et al. (2007) stated that a research philosophy embodies important

assumptions about the way the researcher using it to view the world (Saunders

et al., 2007). This assumptions or positions will underpin the research strategy

and methods that will have significant impact on how we understand what we

are investigating (Saunders et al., 2012). In this matter, we are exploring two

major ways of thinking underpin philosophical issues that related to this study,

these being: epistemology and ontology, which discussed briefly in below:

• Epistemology concerns what constitutes acceptable knowledge in the field

of study; in another words, how do we know what we know? In this matter,

below are four assumptions or stances of what could constitute knowledge in

brief:

o Positivism relates to the philosophical stance of the natural scientist.

This entails working with an observable reality and the end product

can be law-like generalisations similar to those in the physical and

natural sciences. This means reality represents by ‘objects’ or facts

that exist external to the social entities (Saunders et al., 2007;

Saunders et al., 2012).

o Realism is the essence of what the senses show us is reality, where

objects have an existence independent of the human mind. Focus on

explaining within a contexts (Saunders et al., 2007; Saunders et al.,

2012).

o Interpretivism is necessary for the researcher to understand the

differences between humans in our role as social actors. Concerns

about feeling and impression motivating the actions (Saunders et al.,

2007; Saunders et al., 2012).

95

o Pragmatism integrating different perspectives to interpret the data,

this view focused on practical applied research (Saunders et al.,

2012).

• Ontology is about the research views of the reality or nature of the reality. It

concerned with the nature of social phenomena as entities. In this matter,

below are four assumptions or stances of what could constitute knowledge in

brief:

o Objectivism is the ontological position, which holds that social

entities exist in reality external to social actors (Saunders et al.,

2007).

o Subjectivist represent that social phenomena are created from the

perceptions and consequent actions of social actors. The meaningful

attached to those phenomena by social actors within the organisation

and that need to be understood (Saunders et al., 2007).

o Pragmatism holds that the most important determinant of the

research philosophy adopted is the research question (Saunders et al.,

2007).

o Realism is objective exist independently from human though and

beliefs, but interpreted by social conditioning (Saunders et al., 2012).

4.4 RESEARCH PARADIGMS

Saunders et al. (2012) extended their views of research philosophy to explore

the concept of research paradigm, which defined as the way of examining the

social phenomena to gain particular understanding and explanation that can be

attempted (Saunders et al., 2012:141). Below Figure 4.1 a fourfold

categorisation offered by Burrell and Morgan (1982) for research paradigms

namely: interpretive, radical humanist, functionalist, and radical structuralist.

Saunders et al. (2012) emphasised that research paradigms developed by Burrell

and Morgan (1982) are helpful in summarising and clarifying the epistemologies

and ontologies, which represents the belief systems of management and business

96

researchers based on two dimensions: ontology of research and nature of

society.

Figure 4.1: Fourfold Research Paradigms (Saunders et al. 2012:141)

The first conceptual dimension represents the ontology of research including

objectivist and subjectivist perspectives. Objectivist assumes that social entities

exist in reality external to social actors, whereas is subjectivist assumes that

social phenomena are constructed from the perceptions and consequent actions

of social actors. The meaningful attached to those phenomena by social actors

within the organisation and that need to be understood (Saunders et al., 2007).

The second conceptual dimension of research paradigms represents the nature of

society including radical change and regulation perspectives. Radical change is

relates to judgement about the technique organisational affairs should be

conducted and provide suggestions to make major changes to normal order of

things. Whereas, regulation perspective is less judgmental and seeks to explain

the situation in which the organisational affairs regulated and provide

suggestions to improve things within existent framework.

Figure 4.1 developed by Burrell and Morgan (1982) have offered fourfold

categorisation of research paradigms namely: interpretive, radical humanist,

functionalist, and radical structuralist that discussed in below.

Radical Change

Regulation

Subj

ectiv

ist

Obj

ectiv

ist

Radical

Humanist

Radical

Structuralist

Interpretive

Functionalist

97

• Radical structuralist paradigm is located on the objectivist and radical

changes dimensions, which concerned with objective entities and

involved in understanding the existent structure patterns of organisation

such as hierarchies and reporting correlations to which this may create

conflicts.

• Functionalist paradigm is located on the objectivist and regulation

dimensions in which most of the management and business research

operates. The key assumptions would be making here that organisations

are rational entities, in which rational explanation propose solution to

rational problems.

• Interpretive paradigm located in subjectivist and regulation dimensions

and clearly refers to philosophical position of interpretivism. Far for the

rational thinking, interpretive paradigm attempts to understanding the

fundamental meanings attached to organisational life by involving in

organisations daily activities in order to explain what is going on, rather

than changing things.

• Radical humanist paradigm located in subjectivist and radical changes

dimensions that attempt to understand the meanings of social phenomena

from subjectivist perspectives of practicing social actors. Researchers in

this paradigm are would be concerned with changing the status quo.

Turning strategy implementation into understanding the ways in which the

intended strategic objectives of management derailed for unseen reasons, even

though these reasons may not be apparent to those involved with the strategy.

This study attempting to understand the organisation life concerning the

meanings constructed with the practice of project management in chosen

organisations. Therefore paradigms located in subjectivist dimensions as

ontological perspectives are more appropriate. Interpretive and radical humanist

paradigms are concerned with the meaningful attached to those phenomena by

98

social actors within the organisation and that need to be understood. However

radical humanist concerned with changing the status quo and this study are not.

Thus, this study adopts the interpretive paradigm to understand and explain what

is going on and how is strategy and project been translated, in order to generate

fresh insights into real-life through daily involvement in organisation’s

activities.

4.5 RESEARCH METHODOLOGY

The term ‘methodology’ refers to “the way in which we approach problems and

seek answers” (Taylor and Bogdan, 1998:3). From a social science perspective

this term applies to the way in which the research is conducted when

assumptions, interests, and the purpose of the research have been debated

(Taylor and Bogdan, 1998).

In practice, a research design describes a flexible set of guidelines that connect

the theoretical paradigm to strategies of enquiry and/or techniques of collecting

the empirical material for the study. It refers to how the researcher addresses the

two critical issues of the representation and legitimation of the study (Denzin

and Lincoln, 1998). Additionally, it incorporates the rationale for conducting

the research and presents the sequence of activities involved within it, giving

reasons for that particular order.

As exploratory study, the design based on qualitative method in which the

research is divided into two phases as shown in below Figure 4.2.

99

Figure 4.2: The Research Design Process

As mentioned earlier in this section, the research divided into two phases that

summarised in Below Table 4.1. Through semi-structured interviews, Phase One

designed to establish a basis for the views of practitioners concerning the

challenges and issues facing strategy implementation in the real world. The data

of Phase One analysed as soon as it been collected using template that

developed during the literature review of Chapter Two. Phase Two designed to

Literature Review

Form Research

Questions?

Yes

Research Design & Template Creation

1st Phase Interviews: Initial Exploration of Strategy

Practice and Examination of Project Management

Further Research

Needed?

Yes

Redefine Research Design & Template

No

2nd Phase Interviews: In-depth Exploration of Practice

Translation and Building Case Study

No

No

Write

Conclusions?

Investigating Strategy Implementation

Through Projects

Initial Findings

Findings and Recommendations

100

validate the initial findings of the previous phase and to establish further in-

depth understanding of translation process of both the strategy and project

management practice, through both semi-structured and unstructured interviews.

TABLE 4.1: TWO PHASES INTERVIEWS COMPARISION Interview Phase Interview One Interview Two

Purpose Exploring the effectiveness

project management

approach in chosen

organisations

Conduct in-depth interviews to

validate Phase One findings and

explore the practice of project

management approach

Interview

methods Semi-structured

Semi-structured and

un-structured interview

Site visit

Documents

No. of

organisations 5 5

Organisations

industry

Banking (2)

Property Development (1)

Oil (1)

Petrochemical (1)

Banking (2)

Property Development (2)

University (1)

No f the

interviewees 5 25

Theory SAP Translation

The data of Phase Two analysed using the redefined template that developed

during the literature review of Chapter Two and Three.

Phase One explores the gap between the theory and practice of strategy

implementation in the context of project management. The interviews in Phase

One conducted on five organisations that belong to four industries namely:

property development, banking, oil, and petrochemicals. All chosen

organisations are familiarised with international project management approaches

of PMI, and they ‘practicing’ the project management approach for

implementing their organisation strategy. However projects type, size, and the

way of doing project are not the same. The data of Phase One has been analysed

101

as soon it been collected and the findings from this phase together with the

findings from the on-going literature reviews constitute the bases for Phase Two

of the study. As mentioned, the second phase of this study is designed to

establish further in-depth understanding the process of strategy and translation

of project management practice, and by considering the human dimensions of

these challenges from a practice perspective.

Thus, the two interviewed organisations within Phase One are replaced by two

new organisations in Phase Two in order to accomplish the research objectives

outlined in Chapter One. This replaces organisations from oil and petrochemical

by property development and Higher Education (HE). In the case of the HE, the

university selected are involved in a big expansion project that includes

construction projects for building a new university from scratch in order to

achieve strategy objectives of the Ministry of Higher Education in Saudi Arabia.

The case study organisations are selected to explore strategy implementation

through a project management approach. However, the continuity between

Phase One and Phase Two ensured through the study.

4.6 RESEARCH APPROACH: INDUCTIVE

In inductive approach researchers collect data then explore themes or issues then

follow-up works and seeks to build up theory that is adequately grounded in

collected data (Saunders et al., 2012). The logic behind inductive conclusion,

that known premises are used to generate untested conclusion. Saunders et al

stated “data collection is used to explore phenomena, identify themes and

patterns and create a conceptual framework” (Saunders et al., 2012:144).

The inductive approach is well known and associated with qualitative research,

which has in itself, the main goal of obtaining a better understanding of the

nature of the problem being studied. This better understanding can be realized

by exploring the attributes and meanings that individuals or groups associate

with a particular social or human problem (Creswell, 2009). Inductive approach

applied in this study is concerned with collecting and analysing data, and as a

102

result of analysing that data, developing some element of theory. There are

many reasons for adopt the qualitative approach Creswell (2009), however we

listed only six of them that related to this study:

1. The research question tends to be open-ended questions, which mostly

starts with a how or why and aims to find a description of what is going

on.

2. The topic needs to be explored because the variables to explain

participants’ behaviour are not apparent, and therefore, theory needs to

be developed.

3. A holistic picture of the topic does not exist or is unavailable, so a

detailed view of the topic needs to be obtained.

4. Individuals need to be studied in their natural settings.

5. There is an interest by the writer in participating him/herself in the study

and in producing literature about the phenomenon.

6. There is a need to spend extensive time and resources on the data

collection.

Thus, the qualitative research approach has a naturalistic nature, being adopted

in the real world, and it is chosen because of these characteristics. In the same

sense, data collected by using several methods taking in consideration the

human aspect of the study’s participants. Qualitative research is emergent in

nature, which means that it uses inductive logic or reasoning to move from a

particular to a more general statement, and then to theory. Furthermore,

qualitative research design is flexible allowing modification during the research

process as shown in above Figure 4.2, which response to the emerging findings.

Since the aim of this study is to explore the strategy implementation in project-

oriented environments by gaining an in-depth understanding of the reasons of

challenges in various industries, the researcher will act as an explorer, seeking to

appreciate the experiences shared by people who are actually involved in these

situations. In such circumstances the qualitative approach is appropriate and

essential for this study, as this type of research is fundamentally interpretive

103

which means that it focuses on descriptive analysis and interpretation.

However, it is important to acknowledge that qualitative research is not an easy

option to take when considering whether to adopt a qualitative or quantitative

approach. Qualitative research requires the researcher to study the problem in

depth, which is both time and resource-demanding (Creswell, 1998). The

following sections elaborate more on the qualitative research methods and

techniques used in this study.

4.6.1 DATA COLLECTION TECHNIQUES: INTERVIEWS AND

DOCUMENTS

This section introduces the various research techniques used during this study for

data gathering.

4.6.2 SECURING ACCESS

According to Stake (1995:57), “almost always, data gathering is done on

somebody’s ‘home grounds’. Most educational case data gathering involves at

least a small invasion of personal privacy”. At the beginning of this research,

the author has attempted to get access for one of UK bank through the support

of the supervisor; however these tries were not go through. There is no doubt

that getting access to UK organisations, and in particular banks, is very difficult

and time-consuming. Consequently, the researcher has chosen to conduct this

research in Saudi Arabia where securing access to targeted organisations are

faster and more easier than UK. Considering the global implication, this study

decided to chose only organisation that familiarised with international project

management approaches such PMI and prince2. As well, adopting project

management approach as means for implementing their organisation strategy.

Two main criteria were used for targeted organisations, these organisations were

strategy-driven, and project-oriented.

A brief description of the characteristics of each are provided below:

104

• Strategy-driven: well-established organization with clear vision,

mission and long-term strategies, and which is involved in the strategy

implementation process.

• Project-oriented: organisation that familiar with project management

approaches, which uses project management as an approach to

implement their organisation strategies.

Once the access to organisation secured, it was difficult to acquire

organisational data. This means it is important to secure access to the study

subject as the first step in data gathering, and it should be borne in mind that this

could be a long process. In this study, access was secured through the following

two channels:

• Individual efforts

Direct communication for the part of the research happened by approaching

people or departments through the researcher own personal networks.

• Enlisting the efforts of the Professional Association

The Saudi Council of Engineering or (SCE) is organised professional body

intended to promote the engineering profession, develop and upgrade its

standards, and the standards of practitioners. It operates under the

supervision of the Ministry of Commerce, has its headquarters in Riyadh,

and has other branches in the Kingdom’s main cities.

Both these channels were used to secure a group of interviewees, in order to gain

the maximum possible response. At the beginning of the research, access was

obtained through individual efforts, and the required data was collected partially

from targeted companies. The researcher also approached the SCE to gain

access to the engineering organisations in Saudi Arabia, but the process was

extremely long and drawn out, and the responses were slow. Consequently, this

study continued by the researcher using his own personal networks.

105

4.6.3 INTERVIEW METHODS

A great deal of qualitative material comes from talking to people whether it is

through formal interviews or casual conversations. There are three types of

interview, namely: structured, semi-structured, and unstructured. The three types

are discussed in detail as follows:

• Structured Interviews

The aim of structured interviews is to gain a quantitative result from the

participants. Structured interviews or ‘quantitative research interviews’

are used to collect quantifiable or ‘statistical’ data. In this type of

interview, the researcher usually uses a questionnaire with the

interviewees, thereby asking each person an identical set of prepared,

piloted, and refined questions. The interviewer asks each interviewee the

questions exactly as they appear on the questionnaire, so each participant

is asked the same questions, in the same tone, and in the same order.

This means that the interviewer does not show any bias in asking the

questions (Cauvery et al., 2003). Structured interviews are suitable for

identifying general patterns in descriptive studies and can also could be

used in a statistical sense to understand the relationships existing in an

explanatory study (Saunders et al., 2007).

The simplest way to conduct this type of interview is to ask the interviewee

questions that require only short pre-coded answers (a simple yes or no, or an

indication on a scale of responses) so that the researcher merely has to tick a box

on a standardised template (Easterby-Smith et al., 2008; Saunders et al., 2007).

After the data analysis, the researcher can present the results in a statistical

format such as through percentages or numbers. From these results, the

researcher can generalise, provided that large numbers of such interviews are

undertaken (Easterby-Smith et al., 2008).

• Semi-Structured Interviews

In semi-structured interviews, the researcher conducts the interview with

a list of prepared questions, but those questions can vary from one

106

interview to another. This means that the researcher can delete or add

questions, and may also change the sequence of the questions depending

on the interview. Usually, the interviewer records the interview by

making an audio recording or by taking notes. Therefore, semi-

structured interviews could be used in relation both to an exploratory

study and to an explanatory study in order to understand the relationship

between variables that result from a descriptive study (Saunders et al.,

2007).

• Unstructured Interviews

Unstructured interview are informal, which represent the opportunity for

the researcher to investigate in-depth a general area of interest.

Sometime it refers to in-depth interviews that allow the interviewee the

talk freely about events or opinions related to research topic. This would

open up new dimensions of a problem and uncover clues that are based

on personal experience (Saunders et al., 2007; Cauvery et al., 2003).

Researchers use unstructured interviews in relation to an exploratory

study to determine what is happening and to seek new insights (Robson,

2002). These interviews are used in research where the researcher has a

clear idea about the aspects s/he wants to explore but does not have

either a prepared list of questions s/he wants to ask or a definite order in

which s/he wants to gain information. In this situation, the interviewee is

free to talk about events, behaviour and beliefs, which are related to the

research topic (Saunders et al., 2007), and may even introduce ideas that

are outside the research topic but which the interviewer feels may lead to

some other fruitful outcome.

This research was performed using semi-structured interviews for Phase One of

the study, and both semi-structured and unstructured interviews by speaking to

both senior managers and project managers. And during Phase Two of the study,

where a more in-depth understanding of the implementation challenges was

sought, more people were interviewed including people from senior management

107

to front-line staff. In conducting the interviews, the researcher established a

good rapport with the interviewees to win their confidence, and efforts were

made not to be obtrusive in any way during the interview encounter in order that

the researcher did not impose his ideas upon the interviewees.

4.6.4 OPEN-ENDED QUESTIONS

A question that does not provide a set of fixed options for the answer, is called an

open-ended question, and this type of question was chosen for the study. Open-

ended questions give a respondent the freedom to answer the question in the way

s/he likes, and have the advantage that the respondent is allowed to express

his/her thoughts and feelings without being forced to follow specific or pre-

defined answers. The question structure allows for flexibility so the respondent

may give as much detail as s/he wishes (Cauvery et al., 2003). This requires of

course, that all answers should be fully recorded since essentially the interviewee

is engaged in story-telling. In this respect, the researcher believed that a better

understanding could be gained by using open-ended questions, as they would

allow for people who were actually involved in the situations of interest to him,

to say as much as they wished about their experiences.

Open-ended questions are powerful methods of exploration and are particularly

useful to ask before research objectives are defined. They can also be used when

the research issues are complex or the related dimensions are hazy, or when the

researcher is engaged in a pilot survey. The main disadvantage of this type of

question is the difficulty of analysing the data, since the more data that is

available, the harder it is to perform the analysis, and this implies that the

researcher should design a coding frame to classify all the answers in order to

have better clarity (Cauvery et al., 2003).

As exploratory studies considered as valuable ways to ask open-ended questions

to discover what is happening and gaining insights about a topic of interest. It is

useful to clarify the understanding of the problem especially if unsure of precise

nature of problem. Exploratory studies can be conducted through number of

108

was including literature reviews, interviews, focus group interviews. Interviews

approaches are likely to be unstructured and rely on the quality of contribution

of the participants that help guiding the next stage of the research. The

advantage of exploratory research is it fixable and adaptable to change Saunders

et al. (2012).

Below Table 4.2 list the main questions asked during Phase One interviews that

links each question with relevant research objective:

TABLE 4.2 MAPPING INTERVIEW QUESTIONS WITH RESEARCH

OBJECTIVES Asked Questions Related Research Objectives

• What are the methods of project

management do you implemented in

your company?

a) To review the relevant theoretical

perspectives on strategy and

project management, with

particular emphasis on

implementation.

• If you have your own way, what the

things you do to make life better in

terms of “project management”?

• If there is a different strength of

projects, how projects are connected?

b) To evaluate the usefulness of

project management approach in

achieving the organisational

strategy in Saudi Arabia.

• What are the issues and the challenges

you are currently facing in your

company? Can you give me some

examples?

c) To investigate the challenges

confronting project management

implementation through practice

and translation theory.

• How project initiation process is started?

• What are the types of the projects your

do?

• Are all these types of projects executed

by your company or by contractors?

• How projects are connected?

d) To explore the models used in

translating both strategy and

project management approach in

practice.

• What do you do? What is your role in

the projects?

• What is your nature involvement in the

projects?

e) To examine the roles and

implications of objects on strategy

communications.

109

4.6.5 OBSERVATION

The first knowledge of the universe begins with observation as oldest method

used a scientific investigation (Cauvery et al., 2003). The observation technique

is suitable for research that focuses on people’s behaviour. It involves the

systematic observation, recording, description, analysis and interpretation of

what people actually do.

As a research technique, observation is classified into five types based on the

methods used and the type of control, these being: participant observation, non-

participant observation, non-controlled observation, controlled observation, and

organisation observation (Cauvery et al., 2003). However, this study employed

organisation observation that known as field observation. When deciding to

conduct a study based on field observation, a researcher must be aware of

whether or not the organisation under investigation will allow observation by an

outsider. This kind of observation is bounded by time, place, and people that to

be observed by the researcher. The researcher (or ‘field worker’) must be very

cautious about all the factors present once the observation begins, especially

when observing complex phenomena (Cauvery et al., 2003).

In the present study, field observation is used as a secondary source of data

collection and is conducted at the interview site where possible, in order to

understand the influence of team distribution and the workplace environment on

the project performance and communications.

4.6.6 DOCUMENTS

Documents are perceived as sources of ready data, which can be easily accessed

by the imaginative and resourceful investigator (Merriam, 1998). Secondary

data from websites, and when available from within organisations, were

gathered and used in the data analysis process. The documents were mainly

about the organisational structures, missions, visions, strategies, goals, and

plans. However, there is an inherent problem with the use of documentation

110

when investigating multiple case study organisations, and that is quite simply

that owing to different organisational structures and reporting mechanisms, there

is often no uniformity in the types of documents available, and this means that

the opportunity to compare and contrast may be lost. Moreover, documents may

be produced but available in one organisation and not in another due to

confidentiality rules. These obstacles were indeed met in this study because in

some organisations documents were available, in others they were not in

existence, and in yet others there were confidentiality issues and documents

were not released. Hence the comparison of situations between the case study

organisations was impeded.

4.7 RESEARCH STRATEGY: MULTIPLE CASE STUDY

There are many different approaches that are undertaken in qualitative research,

which in itself is used mainly in the field of social, behavioural, and health

sciences. Creswell (1998:27) highlights five traditions that reflect the types of

qualitative research approach frequently used, namely, “a biography, a

phenomenology, a grounded theory, an ethnography and a case study”.

The need for case study arises from the desire to understand complex social

phenomena as the method allows the investigator to retain the holistic and

meaningful characteristics of real-life events, such as individual life,

organisational and managerial processes, neighbourhood change, international

relations, and maturation of industries (Yin, 1993).

In defining case study, Merriam (1998:2) stated it to be: “a basic design that

can accommodate a variety of disciplinary perspectives as well as philosophical

perspectives on the nature of research itself. A case study can test a theory or

build a theory, incorporate random or purposive sampling, include quantitative

and qualitative data”.

Sometimes case study is referred to as fieldwork, field research, or ethnography.

Case studies examine complex phenomena through in-depth analysis of a

111

limited number of details and inter-relationships. Additionally, case study is an

intensive description and analysis of a phenomenon or social unit such as an

individual, group, institution, community, or organisation that is bounded by

time and place. The case study is characterised by the unit of analysis rather

than by the topic of the investigation, and because of this, the approach is

sometimes combined with other types of qualitative methods (Creswell, 1998).

The case study provides a systematic way of looking at events, collecting data,

analysing information, and reporting results. It focuses on researching details in

the situation being investigated in order to gain sufficient information to explain

the unique characteristic of each case study (Ghauri et al., 2005). Case studies

focus on process, context, and discovery rather than outcomes, a specific

variable, or a confirmation. They may be carried out on multi-sites or within one

site; collective case studies examine more than one case (Creswell 1998). When

conducted with organisations rather than individuals, case studies consider the

organisation as a social unit that is bounded by time and place, and which can be

examined in depth by exploring the behavior of organisational members. Case

study should be suitable to the nature of research question and objectives, in

particularly should provide answers to why questions’.

Yin (2009) distinguished between four approaches of the case studies based on

the two distinct dimensions:

• Single case versus multiple cases

• Holistic case versus embedded case

Considering the first dimension, single strategy used to present critical and

unique case study. Whereas, multiple case studies (between two and three) are

likely to produce more evidence and are chosen because of its capacity to

demonstrate one or both forms of replications Saunders et al. (2012). Yin’s

second dimension, holistic verses embedded, which refers to the unit of analysis.

Holistic case study, the research treating the organisation as whole, equally if

the research examining a number of the logical sub-units within chosen

112

organisation then the case predictably involve more than one unite of analysis

which called embedded case study. Unit of analyse will discussed in details in

the next section.

This research uses multiple case study approach as a research strategy to explore

the strategy implementation in the project management context, with focus on

translation theory within three different industries in Saudi Arabia that results

from both interviews Phases (1 & 2).

Through multiple case studies, the researcher is able to obtain an understanding

of the phenomena of strategy translation, and to recognise and reveal the

specific and novel features of strategy translation within each organisation in the

different industries that are included in this study. By this, the researcher

ensured the continuity between both phases interviews and case studies.

Case studies can vary in nature, but the type adopted for this research is the

exploratory (comparative) case study. The aim of conducting comparative case

studies was to offer more compelling evidence of convergent and/or divergent

responses in respect of strategy and practice translation. Two case studies were

undertaken based on project types, these being: IT, and Construction. The unit

of analysis and the criteria for choosing these organisations are explained in the

following sections.

4.8 UNIT OF ANALYSIS

As mentioned, Yin’s second dimension refers to the unit of analysis. Holistic

verses embedded, in holistic case study the research treating the organisation as

whole; equally if the research examining a number of the logical sub-units

within chosen organisation then the case predictably involve more than one

unite of analysis which called embedded case study.

Identifying the unit of analysis in any research project is extremely important, as

noted by Yin (1993:10) who stated that: “No issue is more important than

defining the unit of analysis. […] for time periods of undetermined duration -

113

you must clearly define the unit of analysis at the outset of your study. […] Thus

the entire design of the case study as well as its potential theoretical

significance is heavily dominated by the way the unit of analysis is defined”.

In order to answer the research questions, five different organisations from the

population of Saudi Arabian industries were chosen in total. Bear in mind, two

main criteria were used in choosing the case study organisations, these

organisations were strategy-driven, and project-oriented. Utilizing the idea for

theory of translation to uncover what inside the practice or ‘Black Box’. The

unit of analysis are based on the findings of practice perspective presented at the

end of Chapter Three, there are two sub-unites of analyse concerned this study

and needs to be examined inside the logical entity of chosen organisations.

These units of analyses are:

• The role Individuals

• The role of objects associated with translation

4.9 DATA PREPRATION

The analysis of data involves organising data, developing themes, interpreting

the data, and finally, writing the results. In total, for this study, the data for

analysis emerged from 30 interview transcripts, site visits, non-participant

observations, and the review of documents and information from the

organisations’ websites including organisations’ vision, mission, and strategic

plans. This information was used to establish an understanding of how strategy

had been translated into projects, and also to generate the emerging themes.

Thus, a template was developed to organise the data thematically for the

purpose of analysis and interpretation.

4.9.1 CODING AND TEMPLATE ANALYSES

“A code is a label attached to a section of text to index it as relating to a them or issue in the data which the researcher

114

has identified as important to his or her interpretation” (King, 1998:119).

Categories or label can be developed in advance by consulting the literature

review and this known as concept-driven category, or from collected data that

called data-driven category or can be used both. Identifying categories is the

first activity for analysing the data that allows rearranges the original data into

analytical categories in which each category given name that referred as code or

label (Saunders et al., 2012).

Template analysis is widely used approach associated with qualitative research

methods, which known as ‘codebook analyses’ or ‘thematic code’(King, 1998).

Template analysis does not describe a single, clearly delineated method, but

rather refers to a varied and related group of techniques for thematically

organising and analysing textual data. The analysis starts by producing a list of

codes or a ‘template’ by the researcher, so that the data can be organized in a

way that represents themes identified in the textual structure, and that in

themselves represents the relationships between those themes as defined by the

researcher (King, 2004). The spirit of this approach, researcher produces a list of

codes or template that representing themes identified in their textual data. Some

of theses code identified prior, but researchers will update the list as reads and

interprets the data (King, 1998).

The rationale for using the template analysis technique is that it is a flexible set

of techniques in terms of data collection with less specified procedures. It helps

in developing conceptual themes and clustering them into broader groupings,

and enabling cross-case analysis to produce a master theme. It is also suited for

research that aims to compare (in a simple and easy way) different types of

sector/industry and companies applying the project approach (King, 2004).

The main disadvantage of the approach is the lack of supportive literature for

the technique in comparison to the other available methods of analysis, such as

grounded theory and discourse analysis. This might cause the researcher to be

115

uncertain about the analytical decision that should be made, or it could lead to

the generation of very simple or complex templates. Consequently, this could

lead to the loss of the individual voice in the analysis of aggregated themes

(King, 2004).

The planning of the analysis of the data began at early stage through the

formulation of interview questions in a way that helped in categorising the data

collected during the interviews. After the pilot stage interview, the number of

the questions was limited to eight and these were revised to form more general

categories. From what said, Table 2.7 that placed in Chapter Two is representing

the templates for analysing the data were developed according to the literature

review, initial research questions, and the transcripts of the Phase One and Two

interviews. Moreover, new themes emerged during the fieldwork and the

transcripts of the 2nd Phase interviews are based on practice and the idea

translation placed through Chapter Three.

4.10 CROSS REFERENCES AND TRUTH VALUE

To enhance the truth-value and reliability of this study, the researcher developed

the following measures:

1. The question types used in this study are based on the open-ended

question in order to allow the interviewee to tell the story from his or her

own perspective. The importance of the stories in organisational studies

has recently been recognised. Stories are powerful research instruments

that open valuable windows into the emotional and symbolic lives of an

organisation (Gabriel and Griffiths, 2004).

2. The researcher used the quotes from the interviewees’ answers in the

analysis in order to capture the interest of the reader and present the

actual comments.

3. As this study using a case study strategy, using multiple sources of data

is required such as interviews, site visits, documentation, and

information from the organisations’ websites in which is called

116

triangulation (Saunders et al., 2012). The use of multiple data sources

collected at different points at time helps to ensure that the researcher

has not studied only a small part of the research problem, as well to cross

reference different perspectives of the issue under investigation.

4.11 ETHICAL CONDUCT

Within each organisation a request to gain access to conduct the interviews with

members of staff was made. Approval was granted from all the organisations in

various ways, i.e. by email, letter, or verbally, and it was believed that the nature

of the questions which did not request any sensitive information, encouraged the

co-operation of organisations in this respect (Please see Appendices D and E).

Additionally, confidentiality in terms of the name of the organisation and those

who agreed to be interviewed was also guaranteed at the beginning of the

process.

Another ethical issue to be considered is the individual’s right to choose whether

or not to answer any questions during the interview process. All interviewees

were informed that they had the right not to answer any of the questions at any

time during the interview. Prior to the actual interview, the exact purpose of the

interview was explained, interviewees were clearly advised about the average

time required to answer the questions, and consent to record the interview was

requested. In all cases, this was granted (Please see Appendix A and Appendix

C). Furthermore, complete anonymity was guaranteed to all interviewees in an

effort to encourage their honesty.

4.12 SUMMARY

This chapter has discussed the research design of this study and all the aspects

related to the research methods, methodology, and the use of case studies as a

research strategy. The methods used to collect data were confirmed as being

interviews, site visit, and documents. Additionally, the chapter indicated that

the process of analysing and categorising the large volume of data secured by

117

these methods, and ‘templates’. Finally, issues of validity and reliability in

respect of the collected data were considered, and assured through the two

measures of the cross-reference, and ethical conduct.

118

CHAPTER FIVE

PHASE ONE INTERVIEWS

5.1 OVERVIEW

This chapter provides the analysis and initial findings of the Phase One

interviews conducted during the study between July and September 2010. Since

the approach of project management promised to deliver organisational strategic

objectives, the first phase interviews were carried out to explore the challenges

facing this approach. Semi-structured interviews were conducted with senior

management and project managers in the private and semi-private sector in

Saudi Arabia. The interviews began after the researcher had undertaken the

literature review and generated the research questions, and it was believed that

at this point they would enable the researcher to explore the challenges and

problems related to each organisation. Within this chapter there is also a

discussion of the data gathering, and data analysis process and techniques.

5.2 INTRODUCTION

The convenience and purposive sampling strategy, discussed in the previous

chapter in Section 4.5, was adopted for the semi-structured interviews in Phase

One. Convenience sampling was used in recognition of time and logistical

constraints, but this decision did not result in any compromise on the quality of

the interviewees or the procedure. The interview guide was prepared with the

research questions in mind, and the researcher aimed for clarity in the questions

in order to obtain a meaningful response and to ensure that the duration of the

interviews was not excessive. The schedules of those involved in projects are

usually very busy with various activities and tasks, and hence, the interview

guide was designed to restrict the duration of the interview to a maximum of one

and a half hours. Additionally, it was formulated and revised in consultation

with the researcher’s supervisor and associate research students. Initial

interviews were conducted with the associate students to verify the clarity of

119

questions and assess the time required for the interview, and to become familiar

with the process. Initially, the interview guide consisted of six questions but a

further two questions were later added, taking into account the flow of the

interviews.

5.3 PLANNING AND DESIGNING OF THE PHASE-ONE INTERVIEWS

Since Phase One of the study aims to explore the challenges facing the strategy

execution through the project approach, it was decided to interview individuals

from organisations familiar with implementing project management approaches.

In the following sub-sections, the planning and design of Phase One of the study

including securing access to information, organisations and participants

information, data preparation, analysis, and discussion, are presented in detail.

5.3.1 SECURING DATA ACCESS

Initially, it was very challenging for the researcher to secure access to

organisational data through the interview process, as it was actually difficult to

arrange the interviews. It was necessary to take a variety of factors into

consideration in this respect, such as the managerial levels of the participants,

and the organisations’ standing in term of project size, types, and numbers of

on-going projects in their portfolios. The total number of interviews in Phase

One were five, however, seem reasonable given the exploratory nature of the

exercise, and through these people the researcher also obtained the assurance

that they would participate in Phase Two of the study to ensure the continuity

between the both interviews phases.

5.3.2 INTERVIEWED ORGANISATIONS

After access was secured, confidentiality of the data was the main concern of all

interviewed managers and directors. In this respect, the researcher assured

everyone involved that the data obtained from interviewees would be

completely confidential and used only for the research purpose. The names of

120

the companies and the personnel interviewed were consequently classified as

confidential in accordance with good research ethics. Table 5.1 presents the

alias for the participating companies in Phase One, indicating also the industry,

project type, and the project management team members. The alias given to

each company is used throughout the entire thesis.

TABLE 5.1: PARTICIPATING ORGANISATIONS IN PHASE ONE Given Company

Name

Industry/Sector Project Type Project Team

Size

Alpha Banking IT 15

Beta Banking IT 5

Gamma Property Development Construction 10

Delta Oil IT and Construction 100+

Epsilon Petrochemicals Construction --

The number of the project managers in both the banking and property

development sectors are between 5 and 15, and in the oil sector 100+. The

project management role in the petrochemicals industry is outsourced to

consultants, and therefore, the number of project managers is not known. The

project types are varied; in the banking sectors the majority of projects are

internal development projects and mainly related to IT. However, in the

property development and petrochemicals sectors the project type is external

and mainly construction-related. Finally, the oil sector has a mix of both types –

IT (telecommunications) and construction projects.

5.3.3 PARTICIPANTS’ PROFILES

Table 5.2 indicates the profiles of interviewees. The interviewees’ industries

were selected in consultation with the supervisor, keeping in view the broad

spectrum of the research topic. As Phase One investigating the project

121

management approach in practice, people with extensive industrial experiences

was required, senior personnel were interviewed.

TABLE 5.2: PHASE ONE INTERVIEWEES’ PROFILES Company Participant Role Experiences On-going

Projects Industrial Projects

Alpha Manager - Project Portfolio

Management (PPM)

15 10 100+

Beta Head - Project

Management Office (PMO)

25 20 50+

Gamma Manager – PMO 22 15 100+

Delta Senior Project Manager 20 15 100 +

Epsilon General Manager 30 25 --

The range of industrial experience amongst the interviewees was from 15 to 30

years, and their project experience was between 10 and 25 years. The on-going

projects for selected organisations ranging from 50 to over 100. The industrial

includes Banking, Property Development, Oil, and Petrochemicals. The

organisations were chosen based on their familiarity with the project

management concept, as the main objective of Phase One is to explore the

challenges faced by organisations implementing a project management

approach.

The same interview questions were asked of all the interviewees; however, the

way the questions were asked was refined as the interviews progressed. Most of

the interviewees gave the permission to voice record their sessions in order to

assist in the transcription and post-interview analysis.

The first part of the interview covered biographical data, qualifications,

company information, and job experience. An exploration of the project types

and the roles within those projects was made via the next two questions.

Thereafter, the connectivity of multiple projects within each interviewee’s

overall organisation portfolio was investigated. The fifth question explored the

122

challenges and the issues associated with the projects, and additional questions

were then asked according to the responses given, for elaboration. The final

question asked interviewees for their opinions regarding potential improvement

areas, and any recommendations they wished to make to resolve any of the

issues they had identified.

Initially, eleven interview requests were sent to senior managers from various

Saudi industries in both the private and semi-private sectors, including banking,

construction, property development, water utilities, oil and petrochemicals.

However, only six managers expressed their willingness to participate in the

research, and in the final event, only five were actually interviewed. These came

from four industries: banking, property development, oil, and petrochemicals. A

brief personal profile of each of the interviewees in Phase One is provided as

follows:

• Project Portfolio Manager at Alpha Alpha is one of the oldest and well-established banks in Saudi Arabia. The

participant was appointed as manager for PPM in Alpha Bank in 2009. His

role within the project was throughout (i.e. from the initial ideas to project

closure), and involved daily communications with wide range of

stakeholders across the bank including sector and division heads. The

participant has more than fifteen years’ experiences in various levels of

project management. He holds a BSc degree in Electrical Engineering and

many professional certificates.

• Head of Project and Programme Management Office at

Beta Beta is another well-established bank in Saudi Arabia. The interviewee had

recently joined Beta bank, having been employed mainly in London by

project management consultancy organisations, like Compaq, HP, Accenture

and Deloitte. This interviewee has more than twenty years’ experience at

various managerial levels of project management. His role within the project

123

was from initiation until closure, and required daily communications with a

wide range of stakeholders across the bank including sector and division

heads. His background is in computer science and holds an MBA degree

from the University of London.

• Project Management Office Manager at Gamma Gamma is a newly established property development organisation. The

interviewee from Gamma has more than twenty years’ experience at various

managerial levels of project management, and in different industries. He is a

certified Project Management Professional (PMP) and has a Programme

Management Professional (PgMP) from the PMI. His involvement in the

project is from initiation to closure. The interviewee’s role requires

extensive communications with a wide range of stakeholders across the

company and with third parties. He obtained an MSc degree in Industrial

Engineering in 2009.

• Senior Project Manager at Delta Delta is one of the famous oil companies in the region. The interviewee

from Delta is involved in many telecommunications projects that are

complex in nature. He has also been involved in two mega projects over the

last fifteen years of his work experience with Delta. His role requires

extensive communication and co-ordination with various stakeholders

within and outside of the company. He has a BSc degree in Electrical

Engineering obtained in the USA and is also certified in PMP terms.

• General Manager (GM) at Epsilon Epsilon is one of the petrochemicals companies working under the umbrella

of the Saudi Arabia Basic Industries Corporation (SABIC). The interviewee

from Epsilon works as the General Manager, and he has an important

managerial role at different levels within the organisation. He was also

involved in the process of establishing two petrochemical manufacturing

124

sites over the last fifteen years of his work experience with Epsilon. His role

requires extensive communication and co-ordination with various

stakeholders within and outside of the company. He has a BSc degree in

Engineering from the KFUPM in Saudi Arabia.

5.4 DATA PREPARATION

Before beginning the analysis, the collected data was prepared in a suitable

format. In the preparation of data gathered through exploratory interviews of the

kind generating much qualitative information, the two main steps are

transcribing and coding. Each Phase interview was transcribed to aid the

analysis, and then the entire text was reviewed and then coded according to the

theme of the answer. The codes were listed based on previous studies about

project challenges and problems that were discussed in Chapter Two. Table 2.7

were used to help convert the interviews into meaningful information.

5.5 ANALYSIS AND DISCUSSION

The analysis of the Phase One interviews was carried out when all available

audio data files had been transcribed, and coded such that the results were

meaningful. In conducting this analysis, the information provided in existing

studies concerning the challenges and problems related to strategy and project

implementation, presented in section 2.12 and in sub-sections of Chapter Two,

was used as a theoretical support. Table 2.7 were used to code all interviews into

meaningful information based on the theme of the answers provided by the

participants in this phase.

Regardless of the organisations and the industries to which they belonged, all

participants acknowledged the project management approach as a good

approach that used to implement their strategy. Most of these organisations

tended to implement the project management method and were aware of

international best practice such as PMI. Indeed, they had dedicated departments

called Project /Programme Management Offices (PMO) to deliver the strategy

125

objectives through the successful implementation of projects. This confirmed by

the following quotations:

“Once the project is approved in term of budget and capacity, then we move to the second process initiate the project through the PMI PLC. (Initiation, planning, execution, control)” Beta, Head of PMO

“The SCO are responsible to create organization strategy and the board are in charge to translate this strategy to projects ' project initiation' .PMO is part of the board to follow up the project with the dedicated project manager. […] My role is (PMO) manager (PMO: program management office). So we over seen the whole projects and programme; we make sure that project delivered on time and on budget and within scope.” Gamma, PMO Manager

Moreover, organisations from banking and property development were familiar

with the concept of Project Portfolio Management (PPM). However, this

familiarity did not mean they implementing the concept in the same way.

Recently, Alpha had adopted PPM to overcome the traditional challenges of the

project management approach that the organisation had encountered in the past.

The concept was customised in a way that fitted the organisation structure by

creating one portfolio for each sector. This confirmed by the following

quotations from the interviewees concerned:

“Alpha is structured on sectors, therefore we have a single portfolio for each sector. So we have multiple portfolios, one for each sector. Also we have a portfolio especially for the departments that do not belong to any sector. .” Alpha, PPM Manager

In Gamma, the project management was implemented through programme

management approach. However they call it ‘portfolio’ to connect set of projects

together.

“In Gamma we implement programme management methods. However, we used the term ‘portfolio’ to refer to set of projects related together.” Gamma, PMO Manager

Nevertheless, having the project management approaches in place did not mean

these organisations have challenge free implementation for their strategic

126

objectives. Phase One interview have revealed a number of traditional

challenges that confronts these project-oriented organisations. These challenges

discussed in the following paragraphs.

In Alpha, Beta, Gamma, Epsilon insufficient human resources or lack of

competent resources for the project were the greatest challenges occurring in

these organisations. Also the lack of sufficient capacity planning was relevant

indirectly to the lack of human resources issue. This supported by the following

quotations:

“There are no professional mechanism for capacity planning and resources allocation per project and initiative. IT recourses / man-days planning is not professional enough to avoid problem during the execution to make them go smoothly.” Alpha, PPM Manager “Lack of resources. For example I have system that developed and ready but the qualified people to test this system are not in the bank. So we have to recruit a qualified staff to do the job and that takes 3-4 months. Thus results in delay in delivering the project.” Beta, Head of PMO “[…] we have lack of the expertise, this is the first time we build city from the scratch and therefore we need expertise in every aspect not only construction. […] and lack of resources in term of people we have only '200' staff.” Gamma, PMO Manager

“The nature of the our project requires expertise in petrochemical that mostly not available in local market. So, we look abroad for hiring experts and if we managed to get the competent person, the hiring process is long.“ Epsilon, GM

In the same sense, the insufficient financial resources were highlighted clearly in

petrochemical and property development industries due to size and type of

projects they involved in. Gamma confirmed this challenge as below:

“[…] the company is PLC and has no income from this project because the city not operating yet. Therefore the challenge is to generate revenue before finishing the capital budget. So they have to build the city gradually and to

127

generate revenue at the same level to pay the shareholder. The infrastructure project cost huge money ' billions'. Therefore, they get a loan from the government to resolve project finance issue.” Gamma, PMO Manager

Alpha and Gamma highlighted the changes in strategy or project scope as major

challenge that overwhelming the organization, even though the change was for

the best. This confirmed by following quotations:

“Changing of the scope is main issue facing this approach, which affects the whole project it’s like killing the project.” Alpha, PPM Manager “[…]at the beginning and this is was very big strategic mistake; they start to build residential building. So they start the design for residential towers, resorts, recreation, and they start selling it to the people. After while 'two years' they fond that this was very big strategic mistake based on several facts.[…] Therefore, they change their strategy after the facts.” Gamma, PMO Manager

Regardless to the project management approach that being adopted in these

organisations, this phase revealed number of challenges was related directly to

the practice of project management approaches. For instance, lack of the top

management support to the project management, inadequate project activities,

reluctance to stop low value project, and no clear accountability for a single

project. Theses challenges supported by the following quotation:

“Another bigger issue with portfolio is about the reporting line, our portfolio managers are not reporting to the portfolio office in the bank. What ever I explained to you before about the role of project portfolio management, that what should be done and that what presented by the core team when they brought the portfolio management as an idea to be implemented in the bank. However what is going on is not that at all. […] The involvement in the initiative from itself is not part of the portfolio management.” Alpha, PMO Manager

“[…] the alignment with strategy is one of the issue I facing right now. We have people who are execute but they don’t know where they are from their strategy.” Beta, Head of PMO “[…] in order to make PMO functioning effectively it should

128

be focus of strategic rather than the tactics […]. The point I would like emphasis here that for a single project we have a lot of accountable persons, so the accountability is not strong enough. There is no clear accountability for a single project, which is a real problem. The responsibilities are overlapping.” Gamma, PMO Manager

Furthermore, most of mentioned above challenges are inter-related and lead to

each other. For example the absence of management support for the project

activities could lead to hierarchy power that influences the decision on project

selection, which could affect badly on the allocated resources. This supported by

the following quotations:

“Every division head try to use his power to influence the sector head to get the approval of his project not as per to strategy not to the process of the portfolio management.[…] when the projects going on, some of the senior mangers decide to add/remove services or options for running project. This decision will cause again change in the scope of the project and capacity issue.” Alpha, PMO Manager

Consequently, the lack of centralised project software to handle and share

project information was obvious in banking and property development

organisations. Indeed, the importance of management software as a supportive

tool for the entire project management approach was neglected in these

organisations. This challenge is not critical as highlighted in the below

quotations, but it does directly affect the ability to get accurate information for

monitoring the project activities, and it does therefore, indirectly cause poor

project management practice. This issue confirmed by the following quotations:

“Introduce software tools that manage the idea from the initiation till it translation to the execution and to project post implementation process, which we don’t have and it’s really very important to have.” Alpha, PPM Manager “[…] in very professional and matured environment or ‘organization’ you will find what is called ‘PM tools’ i.e. MS Project and other. In my environment, people are scared of new tools because they have their own operations and daily activities, and when you impose new tools on them you have to report and stuff like that. […] In term of tools I use MS. Office

129

(Excel, PowerPoint and SharePoint). I do have the software as tool of project management but I don’t use it because people are resisting using it. I would like to keep things simple.” Beta, Head of PMO “[…] we use mainly PowerPoint and excel sheet to report our project status in weekly basis as we get information from the project managers. […] we don't have tools which is a problem. Also all generated report is out-dated.” Gamma, PMO Manager

Even though the entire interviewed organisations in Phase One were

familiarised with various approaches related to project management in particular

PMI, this familiarity with project management approaches or PPM did not mean

correct translation of the approach or the practice. For instance, the PMO in

Alpha and Gamma was established originally to support both organisations to

deliver strategic projects. However, in practice the function of the PMO in

Alpha was far away from what it originally created for. This is confirmed

explicitly by the quotation:

“[…] Whatever I explained to you before about the role of project portfolio management, that’s what should be done, and that is what presented by the core team when they brought the project portfolio management as an idea to be implemented in the bank. However, what is going on? is not that at all.” Alpha, PPM Manager

In the same sense, the role of the PMO in Gamma limited to reporting function

about the project progress. Somehow, this limitation reduces the value of PMO

function within the organisation. Regardless of the approach, without fully

committing to all processes within the project management approach, the

organisation will not realise the benefits of the practice. The following quotation

highlights the issue:

“In order to make PMO function effectively it should be the focus of strategic rather than the tactics. It should have a valuable output and not only a report. No one will understand the value of PMO if they are just seeing PMO as a reporting unit. There is no doubt how important it is to have a report and dashboard; however, it will be a problem if this is the only output of the PMO unit.” Gamma, PMO Manager

130

Based on what been said, the majority of the challenges revealed during the

Phase One interviews were related directly to the practice of the project

management approach. Alpha and Gamma have very notably quotations in

regards to translation of the practice on the following:

“[…] Whatever I explained to you before about the role of project portfolio management, that’s what should be done, and that is what presented by the core team when they brought the project portfolio management as an idea to be implemented in the bank. However, what is going on? is not that at all.” Alpha, PPM Manager “There is no doubt how important it is to have a report and dashboard; however, it will be a problem if this is the only output of the PMO unit.” Gamma, PMO Manager

Eventually, this leads to a project management approach that is not based on

good practice, and that does not help the organisation to obtain the benefits it is

hoping for. Recalling the idea of translation presented in Chapter Three, only the

practice name of project management is being translated and travelled to those

organisations. This is supported by Czarniawska and Sevon (2005) by saying

organisations and people do different things and call it the same name

(Czarniawska and Sevon, 2005).

131

5.6 SUMMARY OF PHASE ONE

Phase One of this study revealed 15 challenges encountered the participated

organisations in Saudi Arabia that outlined in below Table 5.3.

TABLE 5.3: PHASE ONE FINDINGS FOR ORGANISATIONS FROM

SAUDI ARABIA

Phase-One Collective Challenges/Problems

Insufficient human

resources or lack of

competent resources

for the project

Inadequate activities

of project

management/ project

portfolio management

(PPM)

Conflict between

the organisation

structure and the

project execution

Lack of centralised

project software to

handle and share

project information

Lack of senior

management support

for the project

management roles

Inadequate capacity

for planning and lack

of resources

allocation

No clear

accountability for a

single project

Project selection

process based on

hierarchy power and

not based on

strategy

Insufficient financial

resources

No clear links

between the strategy

and the project

Lack of strategy

communication or

awareness

Changes in project

scope

Changes in strategy Reluctance to stop or kill low value projects or non-strategic projects

Internal conflict and lack of team spirit

Challenges outlined above in Table 5.3, represents the themes of empirical data

related exclusively to participants working in Saudi Arabia organisations.

Considering the geographical location of the participants, there are particular

extant cultural issues and therefore the findings cannot be generalised.

Moreover, above listed challenges revealed nothing new, as most of the

challenges listed above similar to those mentioned in previous studies. It is

notable that Sterling (2003) claimed these challenges or ‘causes of failure’ to be

simply excuses for poor performance that had gained creditability as genuine

challenges merely by the fact that they were repeatedly encountered.

132

Nonetheless, the initial result of this research confirming both studies of Young

et al. (2012) and Young and Grant (2014), which indicates a defects in project

management approach. Most importantly, listed above challenges revealed from

the project-oriented organisation are directly related to the translation process of

the practice of project management rather than the project management itself.

Accordingly, the researcher continue another set of interviews by applying the

translation concept to gain in-depth understanding of two particular translation

processes firstly, the simplification, and secondly, the materialisation that

associated with the practice translation inside these organisations.

133

CHAPTER SIX

PHASE TWO INTERVIEWS

6.1 OVERVIEW

This chapter provides an analysis of the data gathered from the Phase Two

interviews conducted between July and September 2011, and June and

September 2012. The purpose of these interviews was to validate the initial

findings of the Phase One interviews and explore in depth, the issues associated

with the practice of translating the organisational strategy via the project

management approach. In Phase Two, Twenty-five (25) semi-structured and

unstructured interviews were conducted with five organisations from three

industries namely: Banking, Property Development, and Higher Education

(HE).

Being informed by the outcomes of the Phase One interviews, the second phase

interviews focused on obtaining in-depth understanding of two things through

the practice lens and the idea of translation presented in Chapter Three: firstly,

the strategy translation process, and secondly, the project management approach

in facilitating the translation concept in these organisations.

6.2 INTRODUCTION

The decision to proceed to the Phase Two interviews was made after

considering the results of Phase One of the study, which it became clear that the

oil and petrochemicals industries were not suitable for the research, and for that

representatives from other industries were required. The problem with the oil

and petrochemicals interviews related to the heavy work schedules of the

desired interviewees as these individuals had very busy work diaries that

involved frequent abroad trips, thus making them relatively inaccessible.

Moreover, the geographical location of the sites involved the researcher himself

134

in a great deal of time travelling. Consequently, the oil and petrochemicals

industries were dropped from the Phase Two interviews, and the property

development and higher education were included instead, as both selected

organisations within these industries are project-oriented. In this respect, the

researcher added a giant property developer, and university from Saudi

Arabia’s. The property development organisation was chosen because it had

extensive experience of executing government mega-projects and managing

various construction projects. In respect of the university selected, this case

organisation had witnessed huge expansion projects, thereby being of direct

relevance to the research. The banking and property development organisations

from Phase One continued through into Phase Two. During this later phase,

supervisors were consulted to ensure that those interviewed represented a wide

range of employee levels, and industrial background, and that they had a good

theoretical knowledge of project management.

Based on the researcher experience of conducting the Phase One interviews,

certain questions were modified and/or omitted to retain their focus and

relevance, and to improve on the clarity. The interview guide was accordingly

prepared, bearing in mind the need to obtain a meaningful response, and to

restrict the duration of the interviews to a period that would be acceptable to

those participating. Also, it was found in Phase One that people involved in

projects were usually busy and having a variety of activities and tasks to

complete in given time-frames, so the interview guide was designed to ensure

that the interview would not exceed one and a half hours. The interview guide

was designed and revised in consultation with the supervisor (See Appendix C).

The purpose of the Phase Two interviews was to validate the challenges and

problems revealed in the Phase One interviews, and to investigate the practice of

project management approach in these selected organisations. By this, the

researcher ensured the continuity between both interviews phases.

135

6.3 PLANNING AND DESIGNING THE PHASE TWO INTERVIEWS

Given the intention of the Phase Two interviews to confirm the implementation

issues that emerged in Phase One, this second round of interviews included a

wide range of individuals who were able to provide detailed information about

the processes. Included were employees ranging from executive general

managers to junior staff from the banking, property development, and higher

education industries, all of whom were believed to help the researcher in

investigating strategy translation issues through the various applied management

approaches. The following sub-sections describe in detail the planning and

design of Phase Two (i.e. securing the access to information, the selection of

organisations and participants, and data preparation) of the study.

6.3.1 SECURING DATA ACCESS

Securing access to organisational data continued to present a substantial

challenge during Phase Two of the study, a feature that was particularly difficult

given that two of the industrial sectors had been replaced, and the researcher

essentially had to start from the beginning with two organisations that newly

entered. Nonetheless, the researcher worked to build a rapport with the

managers of each participating organisation, and to obtain from them, an

assurance that the further fieldwork planned for Phase Two would be facilitated.

By this, the researcher ensured the continuity between both interviews phases.

In total, there were (25) interviews conducted during Phase Two. Most of the

interviews conducted within the premises of concerned organisations. In

addition, the researcher reviewed documents during one site visit as a means of

gaining an in-depth understanding of the research problems. It is believed that

the interviews, documents reviewed, and the one site visit enabled a data

saturation level that met the study’s requirements.

6.3.2 INTERVIEWED ORGANISATIONS

Confidentiality of the data was the main concern of all those interviewed. In this

respect, an invitation letter was sent to participants and the interviews were

136

arranged via email (See Appendix D). The interview protocol was explained at

the beginning of the interview (See Appendix C), and some of interviewee

signed an informed consent form (See Appendix A). The researcher gave an

assurance that all interview data would remain confidential and to be used only

for the purpose of this particular research study. Consequently, the names of the

participating companies and the individual interviewees were classified as part

of the agreement concluded between both parties and in according with research

ethics. Table 6.1 presents basic information about the case study organisations

in Phase Two of the study, using pseudonyms to protect the anonymity of the

companies. As can be seen from Table 6.1, the number of projects on an annual

basis ranged from 50 to 100+ in the participating organisations.

TABLE 6.1: CASE STUDY ORGANISATIONS IN PHASE TWO Given Company

Name

Industry Project Type On-going

Projects

Alpha Banking IT 100+

Beta Banking IT 50+

Gamma Property Development Construction 100+

Zeta Property Development Construction 100+

Eta Higher Education Construction 60+

6.3.3 PARTICIPANTS’ PROFILES

Below Table 6.2 presents the roles, background, and industrial sector of the

interviewees in Phase Two. The group of interviewees was comprised of a wide

range of employees in order to obtain varied views on the process. Indeed,

interviewees ranged from executive general managers to junior staff in each of

the four sectors represented (banking, property development, and higher

education).

TABLE 6.2: PROFILE OF PHASE TWO INTERVIEWEES

Alias Industry Participant’s Role Background

Alp

ha

Ban

king

Vice President, IBS - Strategy Office Engineering

Manager - Project Portfolio Management

(PPM) - Project Management Office (PMO)

IT and Business

Manager - Project Management Office

(PMO)

Engineering

Project Manager - PMO Engineering

Bet

a

Ban

king

Head - Project Management Office (PMO) Computer Science,

MBA

Project Manager 1- PMO Accountant

Project Manager 2- PMO Engineering

Project Manager 3- PMO Engineering

Gam

ma

Prop

erty

Dev

elop

men

t Executive General Manager Engineering

Manager -Project Management Office (PMO) Engineering

Senior Architect Architect

Development Director Engineering

Development Deputy Engineering

Zeta

Prop

erty

Dev

elop

men

t

Director, Centre for Advanced Projects

Support (CAPS)

Engineering, PhD

Senior Project Manager - CAPS Engineering

Projects Manager 1- CAPS Engineering

Projects Manager 2 - CAPS Engineering

Quality Engineer - CAPS Engineering

Eta

Hig

her E

duca

tion

Vice President for Project (VPP) Engineering, PhD

General Director-University Projects Engineering, PhD

Department Manager of Projects Engineering

Strategy Implementation Supervisor- VPP

Office

Engineering, PhD

Project Manager, Branch 1 Development Engineering

Project Manager, Branch 2 Development Engineering

Project Manager of Strategy Implementation Engineering

Site Manager for Campus Projects -

Consultant office

Engineering

Construction Engineer - Consultant office Engineering Engineer-Consultant office Engineering

138

It can be seen from above Table 6.2 that the background of the interviewees in

the banking sector was varied, including engineering, IT, and business, whereas

in the other two organisations industries, the interviewees mainly came from

engineering backgrounds. All respondents were asked to choose from the

projects that had worked on in the past or were working on at the time of the

interview. Being able to choose their own project for discussion presented

interviewees with a degree of freedom that enabled them to talk spontaneously

and allowed the researcher to gain an in-depth understanding of the project

management processes in place, and the associated challenges.

6.4 DATA PREPARATION

Before beginning the analysis, the collected data was prepared in a format

suitable for the procedure. Whilst some data were collected through

documentary review and the site visit, the data in Phase Two mainly originated

from the interviews. The interview is a common technique in exploratory

research, and the analysis of data obtained usually follows a particular pattern.

Firstly, it is necessary to transcribe an interview and then to code the data

obtained. The processes of transcription and coding data are the two main steps

within the data preparation stage. So, the interviews in Phase Two were

transcribed by listening to the audio files, and then the entire text of each was

reviewed and subsequently coded according to the themes discussed within the

interviews.

The codes were based on Table 2.7 that collected from previous studies

investigating project challenges and problems placed in Chapter Two. The

process of coding represents a useful way to convert the outcomes of interviews

data into meaningful information. Furthermore, the documentary review (from

websites) and observations made during the site visit helped in clarifying and

understanding the organisational situation. In terms of documentary review,

there was no set pattern for each organisation. Rather the researcher read what

was available in terms of strategy documentation and related information

published on the organisations’ websites and/or printed in booklets and reports.

139

One site visit for the Eta organisation was conducted during Phase Two. To

complete the process of data preparation, the three interviews that were

conducted in Arabic were translated into English, and the comments made

during the site visit were also produced in a text format.

6.5 DATA ANALYSIS

Data obtained from this phase interviews was then analysed to establish the

types and natural of project each organisation was engaged in, the way in which

the organisations developed strategy, the approach used to translate strategy, the

involved staff, whether any techniques were used in the translation of strategy

and practice, and at what level in the organisation the project head was placed.

The in-depth analysis of data conducted based on two factors:

• Strategy translation

• Practice translation of project management

The analysis presented below in alphabetic order based on the given name for

each organisation.

140

• Alpha Alpha is belongs to bank industry that adopting project management aimed at

realised the organisational strategy. Alpha strategy is to increase its

attractiveness to such organisations, and hence generate more revenue for itself.

This strategy is translated into various projects and initiatives to make itself

attractive to private and semi-private organisations seeking financial support.

Most of Alpha’s projects are internal development projects, designed either to

enhance existing services or to provide new products.

• Strategy translation

Alpha has deliberate strategy approach operated on a top-down basis determined

by the structure of the bank, with top management views predominating. The

Executive Management Committee (EMC) conducts a periodic meeting to

review strategy and decides the direction to be taken and the required initiatives

to facilitate the required resources. This EMC and Strategy Forum plays a major

role in translating the strategy and deciding the direction and the initiatives

adopted. This was elaborated on by the interviewee as being the first step in the

translation of the strategy. Four strategy heads from each sector meet with the

Planning and Finance Office to review the strategy and cascade it down the

organisation. The EMC and Strategy Forum are representing the translation

processes that are used to establish the discussion and to share information

within Alpha so that the translation of the strategy can occur.

“The EMC conducts a periodic meeting to decide the initiatives and the directions of the bank based on market research and economic reports. The main objectives of these initiatives are either to generate revenues or to cut the cost. Based on this, the direction will be decided; and these initiatives translated to project whether IT or business project. […]We have now what we call it strategy forum. In the strategy forum, every strategy heads from different sectors meet with the planning and finance office to cascade down the strategy or build a review”(Alpha, IBS-Strategy Office, Vice President).

141

Alpha employees are involved directly in strategy development and

implementation. However, the management recognise that there is variance

between formulation and implementation, and the senior manager interviewed

believed that this gap between the development of the strategy and its

implementation represented the main problem. Given the concern about the

variance between the formulation and the implementation in Alpha, the bank

management proposed several new approaches to try to resolve issues that arose

during the implementation. The first of these approaches was called the Stage

Gate Approach (SGA), which aimed directly to resolve the implementation gap

through the use of a Business Case Model (BCM). The output of the SGA and

the BCM are examples of objects resulted from the translation that are brought

into play to establish shared goal within the organisation and allow different

groups to collaborate on a common task to achieve the organisation’s target. The

interviewee considered these approaches would help in resolving the gap, as

indicated in the following comment:

“In our bank, we develop strategy then jump to implementation, and this is the problem. […]Recently, the bank introduced a new approach called the Stage Gate Approach (SGA), which aims to fill the gap between strategy formulation and implementation. […]After identifying the objectives, the initiative will be created through the Stage Gate Approach, which is a process to validate the generated idea through a Business Case (BC) model. This BC goes through a number of validation checks before it goes to the implementation”(Alpha, IBS-Strategy Office, Vice President).

The concern of strategy translation was the fact that there were changes

introduced to the initiatives during the actual implementation, which affected

the plans.

“Usually the bank vision is not changed from one year to another, our vision is constant. The strategy of the bank lasts for three years. However, the strategic goals and initiatives could be changed, which is been cascaded.[…] Strategy is on-going exercise and change over the time based on the market. The direction is known but the initiatives changed as you go” (Alpha, IBS- Strategy Office, Vice President).

142

The Coupling Approach (CA) is the second approach that aims to overcome the

issue of change being introduced to the initiatives. This approach links the

approved initiative with the annual operating plan by obtaining the required

budget. It represents a second layer of translation process to validate the

initiative pre-implementation, and the interviewee believed it served as a

reservoir for all the initiatives generated.

“Every department has an annual operating plan (AOP) that is linked with the fiscal year. To resolve the change issue, the AOP is linked with the strategy as a couple; but not a tight couple. The main purpose of coupling the strategy with the AOP is to get the initiative ready for the implementation. By this, not every initiative will get budget in the AOL, only the one that passes the business case process in SGA. Furthermore, it will keep as reserve for the all initiatives that may be generated”(Alpha, IBS-Strategy Office, Vice President).

The third approach was called Business Architecture, and the interviewee

emphasised the features of this approach, which maps the initiatives using five

elements that ensure better success for the implementation. These mapping

elements are: the financial situation, capability, readiness, internal enablers, and

external providers. In fact, the Business Architecture approach proposed here is

based on the Balanced Scorecard BSC concept. However, the practice is used

but the name is not used.

“This idea is driven from the Construction and Civil engineering when constructing a building. It has been used in the IT, which uses a blueprint concept. Similarly, we will use a business architecture and blueprint concept in the bank. If I have a set of initiatives, before I move to the implementation, I should do a mapping. The mapping will be against four elements within the bank including the finance situation. These four elements of mapping are: Capability, Readiness, Internal Enablers, and External Providers”(Alpha, IBS-Strategy Office, Vice President).

The communication team in Alpha utilises various channels to communicate the

strategy and directions including discussion, meetings, internal newsletters and

the portal. The results of the meeting with the CEO are communicated directly

143

through the senior managers to their colleagues. The used material used here are

example of the objects resulted from the translation.

“There is a communication team working with the management on communicating our strategy and direction. They utilise the events, town-hall, periodical news, discussion, and portal; they also utilise all media available to communicate the direction, vision, and mission. Also, there is a quarterly review meeting between senior managers and the CEO. In this meeting he discusses the 'status quo' of the bank and the senior managers are conveying the messages to their fellows. Senior managers should cascade the vision, mission and the strategic goals. However, each business area is already involved in the initiatives” (Alpha, IBS-Strategy Office, Vice President).

• Practice translation of project management

In Alpha, the lack of success of the previous PMO model was replaced with a

new model called the Enterprise Project Management Office (EPMO), which

aimed to resolve the issues associated with its predecessor by having a number

of dedicated project managers responsible for centralising the projects and

strategically directing them. However, it was considered that the number of

these project managers was still insufficient.

“Before one and a half year, the bank started a new exercise called Enterprise Project Management Office (EPMO), and this is a centralised project management system. EPMO have a number of project managers who can be seconded to do projects. The number of the project managers is not enough, thus some of the business managers are managing some of the projects. The big and strategic project goes to EPMO, and the remaining projects are left for sector portfolio”(Alpha, Project Manager). “We have strategic goals that are translated into strategic initiatives, which can carry a set of projects, or programme and projects, or programme. So, with programme and projects, we define the initiative, set of activities under the initiatives. As well the business case is carrying out exactly what we want doing includes budget, cost, goals, and requirement” (Alpha, IBS-Strategy Office, Vice President).

144

In addition to the EPMO, Project Portfolio Management (PPM) represents

another means of conducting sector projects. Recently Alpha adopted PPM to

overcome the challenges associated with the traditional project management

approach. The concept was customised to fit the organisational structure by

creating one portfolio for each sector. Consequently, the bank ended up with

multiple portfolios rather than a single portfolio that integrated projects within

the organisational strategy.

“The big and strategic project goes to EPMO, and the remaining project is left for the sector portfolio. […] Now we have a Project Portfolio Management (PPM). […] Across the bank there are portfolio managers in the PPM connected directly to the strategic office. Every sector in the bank has a portfolio. Bear in mind, all the projects in the portfolio are strategic projects. The projects reported through the PPM to the bank portfolio, which goes to EMC and bank IT committee”(Alpha, IBS-Strategy Office, Vice President).

“After conducting some studies on ideas, the portfolio manager gets initial approval to implement this idea as projects in order to get final approval from the division heads. After that all listed projects should be prioritised according to the sectors and then across the whole bank. The CEO should approve this list too, to get the final list of the projects. […] The bank structured based on sectors, therefore we have multiple portfolios, one per sector. Moreover, there is a portfolio especially for the departments that do not belong to any sector”(Alpha, PPM Manager).

Consequently, the customisation of PPM in Alpha ended up with multiple

portfolios rather than a single portfolio that integrated projects within the

organisational strategy. Therefore, the interviewee believed that the main idea of

the PPM approach and the way it had been translated in Alpha were totally

different, which did not help the organisation to achieve the benefits it was

hoping for.

“If you want me to extend this to the bigger issue, it is in the organisation itself, where the issue of role itself. […]Whatever I explained to you before about the role of project portfolio management, that what should be done and that what presented by the core team when they brought the portfolio

145

management as an idea to be implemented in the bank. However what is going on is not that at all”(Alpha, PPM Manager).

In Alpha, the middle management thought that the current efforts and approach

of project and portfolio management were insufficient to overcome the

challenges presented by the previous project approach. As well the top

management believed the main challenge to practice translation was the lack of

process and the leadership to guide the implementation. So, it is clear that the

process of PPM practice was not in place or was not travelled as part of the

translation, and only the name of the practice was travelled.

146

• Beta Beta is belongs to bank industry that adopting project management aimed at

realised the organisational strategy. In Beta, strategy development is top-down.

Senior managers formulate the strategy and cascade it throughout the

organisation for implementation by those in more junior positions. The Head of

the PMO had only recently joined the bank and when interviewed, indicated that

he thought the business cases were used as techniques to translate the bank’s

strategy. In Beta the selection process in respect of projects is based on the

strategy and the PMO team forms part of the committee.

• Strategy translation

In Beta the business cases are used as the first step for translating the strategy

and to establish the discussion and communication between various groups

within the organisation so that they can collaborate and together achieve the

bank’s strategy.

“The programme and project management are there to implement ‘execute’ the strategy. […]I filter the projects with something called project committee, to filter and approve projects that will go to the execution this year. […] I had been involved in the project from the beginning as business case. So we filter the business cases to know what is match with the strategy of the bank”(Beta, Head of PMO).

In Beta the development of the strategy and the implementation is part of the

bank’s role. The interviewee stressed the importance of considering the market

situation in order that a realistic strategy could be formulated. The linkage

between the bank strategy and the projects was seen as quite direct, since

projects were created in total alignment with the strategy.

“We evaluate the strategy based on many factor and report that to senior management and they are in charge to discuss it with the CEO and the board to take the required decision. […] The formulated strategy should be realistic based on the current market situation and achievable; not promising the

147

moon. First of all we confirm our strategy and then we create the required project to achieve these strategies”(Beta, Head of PMO).

“The bank in order to move to next level they have vision; we have consolidated list of projects at the top level at ‘strategy level’; this strategy office we called it transformation group who control all this projects”(Beta, PMO, Project Manager 1).

• Practice translation of project management

The project management process starts once the committee’s approved the

business case submitted by a project manager has been obtained. Project

selection and prioritisation are made based on the alignment of the project with

the organisational strategy. And once the committee’s approval has been given,

the financial resources and the capacity planning are allocated for the project.

Beta thereby applies a typical project management process borrowed from PMI.

The initiation of the business case is a collaborative effort between the project

manager and the business owner who requested the project. The business case

provides information concerning the business such as the current situation, the

needs, and the benefits accruing to the bank after implementation, thus

incorporating a justification for asking the bank for support. The document

resulted from business case considered as objects that allows collaboration

between people in Beta to work together on a common task.

“The first part of the process is project or portfolio of projects is to put framework; how to select them and then how prioritize, and that kind of things. Once the project is approved in term of budget and capacity, then we move to the second process initiate the project through the PMI PLC (Initiation, planning, execution, control)”(Beta, Head of PMO).

The head of the PMO elaborated on three project management models: support,

control, and execution. Currently Beta implements only the support model as

role but the new management hopes to implement all three models in the future

with the help of competent project managers. However, both interviewed project

managers thoughts they paly the execution role.

148

“There are three types of roles for project and programme management, depend on the model you chose to implement. We have three models: support, control, and execution. […]I take the office and there was only support. I'm trying to have support and control. So I'm setting the new governors to take up the methodology that every project manager in the bank should follow”(Beta, Head of PMO). “In the past between 2008 and 2009, PMO was only playing the role of supporting the project and we have project manager assigning in every business unit; the business owner is also the project manager ‘not experienced project manager’ but we assist them, […] but now we are doing execution also; as project manager we manage project from initiation to closure” (Beta, PMO, Project Manager 1). “Now we shifted to another approach where PMO will execute the project and business is only the stakeholders. […] We are going to somehow maturity process and I think we are more mature now than before; but still we don’t have a solid project management methodology”(Beta, PMO, Project Manager 3).

Moreover, Beta project managers themselves emphasised that these models

were not yet authorised, and that the outcome was variance in the practice of the

project management from one project manager to another.

“In initiation for example, we prepare a business case not all the project manager do that, but in my project I do that. […] Some time we are forgetting this however we are becoming more mature than the past. In the past we don’t have methodology, there is no process, or single process to follow when implements the project. Some project has a business cases and some don’t have, we just do it” (Beta, PMO, Project Manager 1).

“There is no approved process that says I should do that or this; we have only guidelines tell do this and that for example for initiating project. Up to my knowledge, there is no written approved process that everyone should follow and you could share it with your team in the bank. There is nothing like that till know […] we have methodology and process but not approved yet”(Beta, PMO, Project Manager 3).

149

In Beta, weekly meetings, memo, and project status reports are used to monitor

project progress and to keep the stakeholders updated. Hence, these meetings

and reports represent objects used for share project information. However, the

project manager considered the report to be only useful for updating top

management. Furthermore, there is no specific technique are used for translating

the practice of project management.

“In regards to the monitoring, we have a steering committee for the stakeholders and our chief operation officer (COO) attending this meeting and this happening every week. Also we have the project status report that sent to the whole stakeholder in particular the group heads and division managers. Because from my experience in the project, we met with the most of the stakeholders on daily bases and they are already updated on the project; so, we don’t need to update them” (Beta, Strategy Office, Project Manager 2).

150

• Gamma

Gamma is belongs to property development industry and the strategy

development and implementation was dominated by the structure of the

company and the owners’ intentions. The strategy reviewed through the

company’s website and prospectus (2011) described the strategy development

process in brief, from which it was established that the new management

thinking is for Gamma to align its direction with the government vision that

aims to accommodate more religious visitors in the old area of Makkah. To

achieve this, the original plan of the Gamma project was to operate as a land

converter, parcelling different pieces of land for sale to investors. However, that

plan has changed and now the company’s strategy is to become a property

developer.

• Strategy translation

Gamma has a deliberate strategy approach operated on a top-down basis

determined by the Chairmen. The 2011 Prospectus confirmed that two

consultants had been assigned to assist in the strategy development process,

which was undertaken by conducting a SWOT analysis. Furthermore, Gamma

team members were also involved in developing and translating the strategy, but

the goals and approaches were changed over time by senior managers and this

negatively affected the progress of the project. The information on Gamma

website and the Prospectus are example of the objects resulted from the strategy

translation and the role of these objects will be examined during this phase.

“We are also involved in strategizing and optimizing the resources that we have. For instance the basic cooling, we don’t have enough money for cooling and that clear, and rather than trying to do everything by ourselves, we ended-up to bring investors into the project. […] Our projects have had the chance of bringing investment with the investment and better chance of success”(Gamma, Development Director).

151

In Gamma, the top management uses weekly meetings as objects to

communicate and review strategy progress. These meetings and the discussion

used to create a common language for organisational conversation.

“Everybody, almost on daily basis or a weekly basis, we have to look into our strategy, what is going on? How it would be implemented? How we are going to move forward with it? […] I appointed as General Manager for this project from several months, and I’m aware about our strategy to a certain level” (Gamma, Executive General Manager). “We believe that we are part of the whole role. By doing a control on progressive business, having a forum or meetings to check on the status, the adjustment issues and to be able to provide clear direction at the right time, that is one of the key items that difficult for every business” (Gamma, Development Director).

• Practice translation of project management

The business owners has translated the strategy and agreed to begin executes the

project as one phase. Gamma signed contracts of project execution as one phase

with two local giant contractors over the 36 months between January 2008 and

January 2011. The interviewed project architect believed that proceeding project

execution as a one-phase was a major challenge from the financial and

management perspective, which was discovered by top management two years

after commencing the project, at which point the decision was made to divide

the project execution into a number of phases.

“Actually I believe this the main problem with this project from the beginning. From the architectural point of view, it’s of course divided into parts not one part; it’s not one part as one tower. From the construction point of view, it was handed from the beginning as one phase; I believe this was our main problem. This is a problem phasing the project. After two years of the project, they started now phasing the project. They understand this issue and admit that we cannot handle as one project from a financial point of view, from constructions, and from follow up. You need more than three or four project management firms to control such big projects as one phase. So now this project has been divided into phases” (Gamma, Senior Architect).

152

Later on, the management team introduced a new multi-phase strategy to

achieve the project’s goals. The Development Director thought that by breaking

down the project into phases and then into smaller projects, there would be a

better chance of success. Here, the practices of the programme and project

portfolio management have been translated through the idea of breaking down

the phases, but it was only the practice that travelled and not the name.

“[…] It became clear that the project of 2.2 Million Square Meters (SM) have been broken down into phases. And it became clear that the amount of money to be brought in, has to be within the appetite and capacity of the market. We have to bring around 15 billions in one go, and no banks will take such risk. But if we break it down into 4 billions and we do a multiple strategy, you will be able to have a better chance of success” (Gamma, Development Director).

The approach of breaking down the project into smaller projects was borrowed

from the interviewees’ experiences on a similar development project in

Malaysia in the belief that this would resolve the capabilities and resource issues

as a number of medium-sized contractors would be involved. It was also

believed to elevate the knowledge level and the experiences of these local

medium-sized companies that would be valuable in the projects in the next

phase. The Development Director elaborated on the practice of ‘split wealth’ as

example to simplify the practice to translate the approach and share the

knowledge. Split wealth is about breaking a big project into smaller projects that

can be executed by local medium-sized companies with supervision from

international expert company. Using such a translation technique of the practice,

the company would achieve the desired result and at the same time enable

knowledge transfer in the medium-sized companies. Furthermore, Gamma

would benefit from these medium-sized companies in the next phase projects.

However, only the Malaysian practice of breaking down the project into smaller

practices travelled, and the name of ‘split wealth’ not being used. “We come from practice back in Malaysia that we need to split the wealth. We need to bring in experts from many sites.

153

When we put these together for instance project like this worth about 6.5 or almost 7 billions, we have broken-down 7 billions for selling them into one thousand different companies, consultants, contractors and multiple people that were involved in the project. This enhances the capabilities of the local companies, because the size of the project is not so big; I mean the med-size companies, med-size consultant, and then med-size suppliers will be part of this. And with that we used such skills to enhance the capacity of the professionals of the country, so when will go for phase-two and phase three these same companies will do it. And that are how we have more wide distribution of wealth and more wide distribution of knowledge” (Gamma, Development Director).

“When we did the twin tower and we brought by the government, we just finished Canary works. Twenty people from the expert company putting as key managers then we put in with our team to do knowledge transfer. By the time ‘ the third year’ expect phasing out this people; then our management the locals staff coming in, remember that we learnt from them, we went to the same steam with them, so there is no gap in experience working and how to do work” (Gamma, Deputy of Development Director).

The responsibility for project management was held by different partners in

Gamma. At the beginning, the contractor ‘designer’ was involved as well as

undertaking his normal responsibilities, and then later another partner take the

control. Thus, the translation of the project management practice was done

through both partners. However, the interviewees believed that the project

management role was unclear and difficult to enact.

“From our side, the role was not clear as a project manager because we start the project as design developer and then they add project management to our role. So it’s difficult to be the project manager and also design reviewer, and design developer this is very different. I believe it’s not common and as a project manager you cannot involved in any other decision, you cannot involve in any other design development requires by client. […] But in our case we were both the project manager and also the design developer to achieve this kind of modification required to do this, and this is very difficult. Very difficult because at sometimes it takes you from the original scope to the other, and of course it will be our problem not anyone else.[…] sometimes we wearing two hats,

154

the hat of project manager and the hat of designer development” (Gamma Senior Architect).

“The time we left the project our role was as project management consultant, however now we are the builder. […] So we shift our role from being project management consultant to become part and parcel of the client” (Gamma, Development Director).

Gradually, Gamma has come to realise the importance of clarity in the project

management role, and top management has decided that in the case of a project

running for a limited time, hiring a consultant is the best option. Thus, it was

decided to assign the project management role to international consultancy

company. Using this approach, each partner has a specific role and the project

management is undertaken with the international consultant acting as the

translation agent. However, some interviewee considered this decision to have

been made purely for political and financial reasons.

“This project is a short period project. For example, you build, operate it, maybe we will be under them and later on as a facility management operation, but it is only one time, you are going to build it and that’s it; then you leave. There are no other new buildings. So, we don’t have to have the entire group of people and later on you tell them okay bye, bye. […] You cannot manage it your-self, you have to have a consultant and your-self to manage it with you. And most important thing, you must have a project manager to manage it. […] It can be the consultant or it could be as a project manager” (Gamma, Executive General Manager).

“You need professional project managers to be on the job because we cannot explain ourselves to bring anything, we cannot hire 200 people in Makkah, it’s difficult. But if we engage professional companies, we can do the investor role. And after completing the development of this project, we don’t have a headache on how to deal with these people and tell them to go home”(Gamma, Development Director).

“There were some political and financial issues, some banks recommended to hire international project manager for project finance, that’s why we replaced by Internationally Project Management Consultant Company and changed our role to be design developer again”(Gamma, Senior Architect).

155

The Development Director thought that the international consultants would

travel to the site with their own experts. Consequently, these experts play a key

role in translating the practice and in providing a common language for Gamma.

However, in fact the organisation did not gain the benefit from outsourcing the

role of project management for international company, since the international

experts did not travel to their site to offer expertise, and the relationships was

little, since the actual project manager assigned was a local individual. The

interviewee believes that the appointment of an international consultancy

organisation was not the best option as had been thought in the first place.

“What we saw when we bring the international project management consultant here? Our consultant is one of the largest project management consultancy services in the world not only here and in construction management may probably from top five. So, we thought that we brought the engineers of this International from American but fact was not that at all. […] By bring in this International consultant we were looking to bring in the experts. Unfortunately, it was only the name that came. Because the people brought into project were from around the same region as expected, and I will not say anything about these people. […] So, if you put another company name, you will not know the differences; because we have the name but we don’t have the people or the experts” (Gamma, Development Director).

It was clear that there was a disconnection between the project manager hired by

the international consultancy, and the actual headquarters of the consultancy in

the USA. The interviewee believed that the lack of expertise and competent

project managers was the main reason for the project delay. He considered that

the main issue with the project management consultant was the lack of

competent project managers who were definitely required for such a mega

development project.

“We been client and been ended up teaching team of the project management consultant how to manage project. However, at that stage cancelling the consultancy contract would not be a very good strategy, and the solution is not simple too. We tried to contact first the international management office of the consultant at the U.S. to see if we have other options. That explains why we did not want to

156

bring another new consultant. We preferred to maintain them, but what we are trying to do, is changing the people. Last year we went to Dubai and we interviewed few people and hired the good one” (Gamma, Deputy of Development Director). “We have lack of the expertise. […]. There is no knowledge share between the local company and the mother company. And lack of resources in term of people we have limited staff […] Also project never finished on time, projects always delayed which is an indication to weak project management skills or lack of competent project managers”(Gamma, PMO Manager).

• Zeta

Zeta is another example of organisation being contractor for over eight decades

and changed to be a property developer. Zeta undergone a huge transformational

strategy to change from family business contractor to be a property development

organisation deals with mega and fast track projects in Saudi Arabia. The

researcher consulted Zeta’s website hoping to review the organisation hierarchy,

vision, mission, and strategy, but unfortunately this type of information was not

published there. Consequently, organisation strategy was obtained through the

interviews, which took place in Zeta’s main office in Jeddah. Zeta changed its

strategy to become more proactive or emergent, which they making proposals to

government for projects that were aligned with the vision of the country’s

leaders.

• Strategy translation

Being a family business organisation, Zeta demonstrates emergent strategy

approach based on innovative theory in which the way forward is dictated by the

Chairman and the interests of the family members. The interviewee believed

that besides the traditional way of doing business, Zeta also sought potential

business based on the Chairman’s vision.

“The strategy is dominant by the chairman and it is part of the commitments for our networks. Well, of course we still go on bid, 92% of all our projects are office competition. And we bid and we had reached a point that we could capture the projects that we want, and here you get into this strategy and to the operational mix and you see how the chairman, for example if our strategy is to enter the Jordanian market and even if entering Jordanian market would end-up to loss five millions Jordanian Dinars. It is part of the strategy when we write-off the project, whenever we work a job and we do our work better and see how it does”(Zeta, CAPS Senior Projects Manager).

Recently, Zeta has undergone a transformational strategy to take the

organisation from a family-owned business in construction to a building

158

development organisation, which initiates, finances, and executes its own

projects.

“Now we believe that our identity has been transformed into building developer; we initiate our own projects, we finance our own projects we certainly build and we can do a lot of things that not a typical of contracting”(Zeta, Director of CAPS). “From few billion Riyals turn-over in year into tens of billions of Riyals turn-over; from simple highway projects and expressways into building the highest skyscraper in the world”(Zeta, CAPS Senior Projects Manager).

In considering how Zeta had managed its transformational strategy, the

interviewees identified four main components of the strategy that enabled the

identity change. The first component was concerned with leadership, it being

noted that Zeta aimed to be a leader in the sector. The second was to be

specialised in fast track mega. The third was the effort and will to transform

itself from contractor into builder developer. And the fourth was a desire to be

social responsible to the Saudi community. The interviewees stressed that the

reason behind this strategy was the desire to reconcile the family business and

show a strong commitment to social networking.

“I think I can define our strategy in four different areas. The first point I should have made about some time ago I want to be a leader in my sector. So many people says I want to be the leader, to be number one and this has always been controversial which is better to be number one or number two or number three. […] But I think the first component across strategies is to be the leader. The second one, we would focus only on mega fast track projects and that's very important later on we’ll explain as we talk about it. Third strategy is to transform from pure contracting to a builder developers. And the fourth component is a new commitment to Saudi community”(Zeta, Director of CAPS).

• Practice translation of the project management

Recently, the Chairman of Zeta had established a new department called the

Centre for Advanced Project Support (CAPS). The interviewees perceived the

159

CAPS as a vehicle for Research and Development, and as providing a strong

support for excellence within strategy development and implementation by

linking the strategy with the operations. Therefore, the translation of the practice

is happening through CAPS.

“What we do is soft work, and from here we don’t pour concrete, we don’t burn steel, we don’t procure hardware, we don’t do anything in the project, but I think I can say that what I'm doing in jobs really around technical and commercially type feasibility studies of questions or issues of projects that the organisation is interested in. This R&D hat and I'm wearing on behalf of R&D”(Zeta, CAPS Senior Projects Manager). “The emphasis we see it from the literature on CAPS, we are targeting the top and the bottom, we are supporting the development for this strategy, and then again we are focusing on the operational excellence at the operational level. But we are really trigger, support, coordinate, facilitate the improvement of project management direction”(Zeta, Director of CAPS).

It was also believed that being in its early stage of existence, the CAPS was

setting out to play the role of knowledge centre where all project stakeholders

both individuals and divisions, could share and exchange their project

experiences and knowledge. Thus, the CAPS is playing the role of translating

the practice that facilitates knowledge sharing within Zeta.

“We consider ourselves at early stage, we just started actually. Our ultimate goal is eventually as a partnership; we will have a portal in the company where all the project operational directors, project engineers and their assigned tasks of a project to be able to access the portal and download all the related plans, documents as our opponents companies are have; in other words we would not want out project managers to start from scratch. We wanted to capture all the experience internally and then once project is launched then we will get on the previous experience, because most of the projects are similar in nature“(Zeta, CAPS Projects Manager 1).

160

In Zeta, the CAPS Director thought the project management process to be very

simple. It begins as soon as the work for any particular project is formally

agreed, and one of the three major divisions is assigned to take the lead. The

division is appointed according to the project type, with projects being allocated

on the basis of division speciality. These three divisions are physically located

in one building, thereby allowing for better communication and collaboration

between their various members. The interviewee believed this made the

operational processes very straightforward. Once assigned a project, the project

manager begins to communicate with the Human Resource Department to start

the process of allocating the required resources for the project.

“The way we do things is very simple. Let’s say the project we want to do, or we can do, or we were contracted to do; we picked one of our three divisions and that division is allowed to collaborate with other groups. So at the end if one division is strong in electrical mechanical, it comes above the electrical mechanical section of the council. And from there the division has a collection of power plants and the company hierarchy is what you see here in this building and then there are three operating divisions that are located outside this building and the top man has an office in this building and co-ordinates. Then they divide their work into the projects, so you see at the division, what will the project manager in development projects like our department here help each other. Who deals with the soft issues of designing management packages of the projects from beginning to end”(Zeta, Director of CAPS). “They identify a project manager, and the project manager working with our recruitment department to bring people from anywhere around the world. So it becomes a typical project management process how do we get the resources, how do we plan the project, how do we allocate the resources, and how do we appoint the work and then how do we evaluate them and do all of this stuff, so that’s the way we do our work”(Zeta, CAPS Projects Manager 1).

Zeta has two approaches to execute mega projects successfully. These are

known as ‘zoning’ or ‘sub-zoning’, and vertical construction. Both approaches

are representing the process for translating the practice used in mega projects.

The zoning concept is about breaking down a project into zones, and assigning

161

independent project managers for each zone so that these smaller zones work as

separate projects that are being completed in parallel with each other. The

zoning and sub-zoning approach is comparable with the practice of

programme/multiple concurrent projects. Here the practice could be seen to

have travelled, although the name given to the practice was different.

Irrespective of differences in nomenclature, however, the virtual construction

used for the practice of zoning is considered as object.

“By zoning, we break up projects into zones, we make every zone a project, and we put a project manager and completely independent, we know that it is possible it is horizontally spread like housing project; I have 2000 villas, every 300 villas is a project, and it’s one of the things like that. […] 3000 villas is a lot, and we cannot do that in one go. […] We discovered that now there is virtual construction software that will allow us to build a bridge on the computer before we go to the site, and we see it, we found it, and we used it at Jmarat project”(Zeta, CAPS Senior Projects Manager). “With virtual construction you stimulate, you read the project within hour. Let’s say I want to build this steel and I want to put this item here and you managed to put it. Suddenly, you want to put the last steel and it does not fit because it doesn’t have a place to go, what I do about it? In the old days we discovered it when we were doing it. However, virtual construction is a very powerful tool; sub-zoning is a very powerful tool, I think we believe that a combination of decentralization of certain project measurement activities and centralization of certain project measurement activities are a must to make things happen; like procurement, you don’t go and sub divide a project into fifteen sub projects and tell everyone to go procure his stuff and things like that especially from design and wholesalers stuff. So I think the most exciting part of our work is that we are challenged with infeasible demands but we are aware of what we are talking about. And as we hit, as we try different approaches we know some of the workers might talk about it”(Zeta, CAPS Quality Engineer).

• Eta

Eta is Universities falling under the jurisdiction of the Ministry of Higher

Education. The university’s vision, mission, and other information were viewed

through the university website and used in this case study. Currently Eta is

undergoing a huge expansion projects including the construction of four new

universities.

• Strategy translation

The interviewees and the strategy document confirmed that Eta has deliberate

strategy approach operated on a top-down basis determined by the university

vision. Top management across the university were involved directly in the

development and translation process with participants from outside the

university boundaries for better views of the situation. The strategy development

was done using SWOT analysis techniques throughout three workshops and

Balance scorecards technique used for strategy translation that utilise meetings

and workshops to create a common language between different groups to

achieve the organisation goals. Strategy Document analysis place the Appendix

(E).

“In regards to the strategy development we conducted three workshops and spent between 3-6 months for developing our strategy. The first workshop was dedicated only to put the vision, values and mission, so includes the top management and stakeholders such executives. The junior engineers were not included in these workshops because we are putting the strategy for five years so we need to get the inputs from the executives. Moreover, this workshop was conducted offsite to take the participants out from the daily routine environments and to make sure that they come with fresh mind. Based on the MVV resulted from first workshop, in the second workshop we starts to put the strategic goals objectives and the SWOT Analysis. In order to get better views of the current organisation picture, the SWOT analysis includes participants from out of the university boundaries such as contractors, consultant and suppliers. In the third workshop, the SWOT outcomes used to identify the strategic dimensions, strategic objectives and goals, and then the execution plans. After that we starts to put specifics objectives that utilizing the strength points to take the advantage of the opportunity, and

163

empowering the weakest point and at the end uses this specific objective to avoid or confront the challenges. Then we start to put details for the execution plan”(Eta, Strategy Implementation Supervisor- VPP Office).

In Eta the management uses various objects for communicating the strategy of

the university and the presidency of the projects. This includes workshops,

sessions, monthly meeting, printed document and internal website. Moreover,

recently Eta launched new software called MARZ that developed to follow-up

the university strategies. The interviewee thoughts these approaches would help

in connecting their daily activities with the university strategy. Recurring

meeting, MARZ and strategy plans considered as objects produced as part of the

translation process ‘simplification’ that enables strategy communication and

knowledge sharing within the university members and constrain knowledge

sharing are beyond the university.

“In regards to the strategy development we conducted three workshops to put the mission, vision, goals and execution plans. […] We use several approaches such as sessions, letters, booklet, motivational meeting, and follow-up meeting. […] We do two things to connect our projects and daily activities with our vision through the organisation environment; first we framed our vision and mission statement in every corridors to make sure that every one is aware of it or at least read it once. Second thing all our strategy and objectives have printed in the strategy guideline document. For the strategy communication and monitoring, the university uses eight different approaches including booklet and documents, sessions and workshops, committee meetings, newsletter, MARZ, face-book, letters and annul report.[…] There is Executive Committee head by the VP for projects meets every month with the champions to follow-up the strategy implementation progress and to take the required decision on spot. Champion is like manager; if there is team of six people works on projects we appoint one of them as Champion. There are a number of champions and there is a leader for the champions or champion of champions”(Eta, Strategy Implementation Supervisor- VPP Office).

However, consultants and contractors members were excluded from this

communication approaches. The knowledge of strategy and cognition remains

within the boundaries of the university staff.

164

“The contractor does not cares about the strategic reflections of the project itself; the most important thing for him is the profit and to get his payments. I believed that the consultant should be aware of the strategy as he representing the owner to follow-up the projects strategically. However, the consultant perception of the university strategy is limited and missing the details”(Eta, Site Manager for Campus Projects - Consultant Office).

The top management thoughts above material or ‘object’ would help in

connecting their daily activities of staff at execution level with the university

strategy. However, at execution level, the interviewees are more focused on

project completion rather than understanding the strategic objectives of the

project and this increases the gap between the strategy and the implementation.

“The vision of the university is not clear, even though with this number of projects and measures we have. Sometimes in the committee meeting I shocked when I listen to our executives because there is a big variance between what they thoughts ‘mind picture’ and what we actually do”(Eta, Project Manager of Strategy Implementation). “For my level as engineer, I'm interested to complete the project, once the project completed I will inform them, so the top managers would know which part of the strategy was achieved, and this on our level. For me I deal with this project normally, so I do the similar follow-up as the rest of the projects I have”(Eta, Construction Engineer - Consultant office). • Practice translation project management

The importance of the project management role has been acknowledged from

the beginning of the establishment of the university, and the creation of the

Engineering Department. Eta uses the Balance scorecards for translating their

strategy into projects and initiatives. Strategy document II developed in Arabic

and contains the university strategic plans and list of projects that connected

directly to each strategic objective. The document has been translated into

English language and attached to the Appendix (E) of this study.

165

In Eta, the project management role splits between project management

department and the consultants. The interviewees thought the department of

project management roles are mainly coordination and administration. Due to

the expansion projects in the university and the loads of the projects works, the

number of consultants for project management has increased into three

consultants. The interviewees thought that consultants hired mostly in

government projects to the resolve the staff shortage issue. However, by

splitting the project management roles between the VPP and the consultant the

question raised here, whether the practice of project management was travelled

or only the name (Czarniawska and Sevon, 2005).

“Before we have only one consultant who has all the projects at the same time. So all the details, all the specs, everything is with this consultant. Whatever project we have, he will follow the same procedures, the same quality and the same material. Those days we have three consultants; from our side we are doing the coordination between the three consultants. So, whatever approved in the university as materials or sub-contractor we apply it on the three consultants; so we coordinate between the three. We have developed a form that will filled by the consultant in case of seeking to approve new material, or new supplier or something like that. For the materials that used here, all the three consultants follow university standard. In case we have a problem in the location of this campus for example we referred to the location project manager. So, we have only one manager per location who dealing with all the three consultants. So the coordination is happening with the university all the time”(Eta, Department Manager). “We are working understaffing, and this the case for the governmental project. The reason behind that the project extensions happened suddenly without creating vacancies. [..] To resolve the issue we used the outsourcing the project management that have higher level than the construction management. Project management are involved in the process tendering, payment, contractors selection, and the consultant; actually they represent the owners”(Eta, General Director University Projects). “Often, in the government projects there are no enough employees or qualified engineers to do the job. To compensate this shortage they hire a consultant to help them to manage the project and to deliver it in time, within cost, and the

166

quality. The university dealing with the administration issues which are related to the invoices and payments. This is what happened unusually because we don’t have enough staff, they hire a consultant with his staff and qualified engineers to make sure that the contractors will submit the project as per to specs on-time, on cost”(Eta, Project Manager, Branch 1 Development).

The consultant of project management is responsible for managing construction

works on-site and will play the role of the translator. If there is an issue occurred

during the project execution, for example between the contractors and the

subcontractors, the issue will be escalated to the project management

department for support. The department interferes to resolve any raised issues

by using two approaches namely black list and the payment guarantor. The

interviewee mentioned that they used successfully these two approaches several

time. Thus the role of the project management department is limited to

coordination and conflict resolution only. Whereas the actually project planning

and performance monitoring are left to the consultants.

“Sometimes the consultant stuck with the contractor or the sub-contractor in issue that they couldn’t resolve; so, the consultant refers the issue to us. A real example, onetime a sub-contractors who approved earlier by the university refuses to submit the project on time due to some problems. Thus, we have interfered to help the consultant; we brought the sub-contractor to discuss the issue. Usually we told him that we will put the company in our black list, and we will never deal with him in future projects. We used this approach many times and things get better. Sometimes we guarantee the sub-contractor money. This approach used if the contractor is not willing to pay to the sub-contractor. So we guarantee that they will get the money by deducting it from the invoice of the contractor. But we will guarantee this just on the time of the payment. Sometimes, the contractor himself is not moving forward due to other project outside the university. The consultant tries so many times to push the project and nothing happens. This time we interfere and we bring the contractor and we give them hard time just only to focus in our project and that takes our time actually, because this happens daily” (Eta, Department Manager).

167

The interviewee thoughts appointed projects consultants works as mediator

between the university and projects contractors. The consultant managing

construction works on-site and monitoring the contractors progress as per to the

plan. In case of issue, the consultant reports that to the project management

department who is interferes to resolve the issue. The interviewee believes they

are as one team; therefore both project management department and the

consultant are responsible for managing all the construction projects in the

university.

“All the departments of Vice President for university projects take into account during their work set of values of such as professional excellence, innovation, energy and environment conservation, all of this within the fame of loyalty and Allah's piety and the one teamwork spirit”(Eta, Vice President for Projects). “The consultant helps the university ‘owner’ to manage and deliver the project. The consultant is managing the whole projects and the construction works on-site. Whereas the owner role paying bills and dealing with the administration issues like internal conflicts, delays, and etc. Actually, we are more involved with the consultant in the university. So we are like one team; we are helping the consultant to do his job with the contractor”(Eta, Department Manager).

The interviewee stressed that changes happen sometimes as a desire of the

department ‘end-user’ to follows the technology market in order to align with

the university strategy. Furthermore, the department of the project management

are trying to do the project considering the country strategy that aims to increase

the university’s student capacity too. However, the changes and strategy

alignment has undesirable result in terms of cost and time of the project.

“We try to solve as much as we can because we want to serve the strategy of the university that they want to combine the building with the latest educational equipment. We want to be up to-date and therefore we have to do changes to align wit the strategy. For example, departments like the civil department, they have some equipment that used in teaching the students. If they don’t get the latest equipment, they will be behind and it’s not good. So, we have to do that to align with the strategy. […] Sometimes, because of the strategy of

168

the whole country, which aim to increase the number of students’ capacity in the university. We have taken this in our consideration, thus we try to follow this and increase the floors to increase the capacity of the building. So that’s why sometimes we have to take a decision that to increase during the construction. This is actual example of the change we suffer from which we don’t like to do much. But we do it only to serve the strategy of the education. We stay around this strategy and we try to do it without affecting the time but we cannot. If you have any change, the contractors will ask for additional time. Sometime even if you don’t have changes they ask for extra time. So imagine if you ask them to do something extra, they will ask for time extension”(Eta, Department Manager). “Sometimes departments come with new demand based on the market and so forth, so we adopt our system accordingly. For example if we are trying to build new collage according to our master plan and the university decided not to go with building this college and switch to another college; then we have to readjust our plan”(Eta, General Director - University Projects). “The university are focused on having the state-of-art technology in regards to educational building project. Therefore, we have weekly meeting with the department manager to proposing and suggesting a new idea that supporting the education”(Eta, Engineer, Consultant Office).

Even though Eta has a strategy and they trying to execute strategic projects as

much as possible. The interviewees highlighted that some projects change the

scope of VPP strategy that called as ‘rush project’. The rush projects are mainly

serve the university strategy that newly added and not part of the VPP projects.

The interviewee stressed that theses rush projects have special execution path in

term of the finance and monitoring, which known for both project consultant

and contractor. On the other hand, the project manager of strategy

implementation believed that the entire department projects should leads to

realize the objectives of university strategy. However, only 10 % of the projects

are representing the strategic projects of the university and the rest are rush

projects. Therefore strategy project manager thought VPP strategy was poorly

developed. Also, the department manager thought doing rush project is part of

the challenge that consumes the time of the department.

169

“We have 57 on-going projects that considered out of the scope of the second university strategy. If these projects are not considered as a strategic projects that mean we have something wrong; or it mean we are work on needs bases and not on strategically bases. On the other hand we only seven projects that serve the second university strategy. Comparing the numbers both strategic and non-strategic projects, I believed that the majority of our projects should serve the university strategy, unfortunately the case here are totally reverse. If we calculate this by percentage, this mean 10 % of our projects are severing university strategy and that means we have a defect in our strategic planning”(Eta, Project Manager of Strategy Implementation). “First of all, the project that serve the university strategy have different path than the none-strategic project. We do strategic project as ‘rush project’ and both the contractor and the consultant knew that from the beginning. The budgeting process of 'rush project' is faster, takes less time and the follow-up happened on daily bases. Also, the contractor will give the permission to work 24 by 7 if that is required”(Eta, Site Manager for Campus Projects - Consultant office). “We are not ready with our contractors here to do the rush projects. And this takes most of our time, because we wish that to do the project in certain time like six months. We tender the project by six months and do the required things but we are suffering from this. Because we are spends so much time on pushing the contractor to complete the project on time. So this takes most of our time”(Eta, Department Manager).

As part of the strategy translation, strategy documents, onsite signboard and

project plans are example of objects resulted from the translation process of

Balanced Scorecards. Regardless of the objects used to connect the daily

activities of university employees with the strategy or to make them thinking

strategically. However, these attempts fail because the employee at the down

levels of the organisation will see only plans and tasks; they cannot see the big

picture of the work they do. Therefore, staff at front levels of the organisation

‘execution level’ sees detailed plans and actions rather than the strategic

objectives. They are recalling measures and forms rather than university vision.

This asserted by Senge (1990) by saying that organisation uses many of

surrounding management tools and models that available to translate their

170

strategies into actions without considering the consequences. Thus, when we

then try to see the big picture, we lose our intrinsic sense of connection to a

larger whole.

“I have attended the MARZ awareness session and I knew that the university have strategies and objective but I can’t feel it. Furthermore, I cannot imagine how the university would be looks like after 5 or 10 years. The only thing I could think of that all the faculties will have enough capacity in terms of building. […] For my level as engineer, I'm interested to complete the project, once the project completed I will inform them, so the top managers would know which part of the strategy was achieved, and this on our level. For me I deal with this project normally, so I do the similar follow-up as the rest of the projects” Eta, Construction Engineer - Consultant Office. “University strategy plans is very broad and includes more than 11,000 transactions for the implementation and about 159 KPIs for monitoring.[…] we never looked back to check whether this plan will reach to our vision. […] We where focused on our strategic objectives, which comes from the SWOT” Eta, Strategy Implementation Supervisor - VPP office.

The discussion of Phase Two analysis presented in the below section.

6.6 DISCUSSION

Based on the analysis of the participated organisations that presented in this

chapter, there were consensuses in in using deliberate strategy approach in the

case study organisation except Zeta. Also SWOT analysis as techniques for

strategy development was adopted in three organisations. Alpha and Beta,

which belong to banking industries, execute internal development projects that

mainly related to Information Technology (IT). In these organisations, the

approach of strategy is deliberate. Strategy development is part of the top

management (located within the Strategy Office) role, and consequently, there is

a top-down approach in both Alpha and Beta. The belief that strategy can be

developed by senior managers and based on rigid application, rational decision

of top-down approach has become dominate says McCabe (2010).

171

Both organisations use a Business Case as model for translating their strategy.

However, no model been used for translating the practice even though they

follow the project management approach of PMI through the Project

Management Office (PMO). In both banks, PMO are responsible for the

translation of the project practice, including the process and role. Alpha uses

SWOT analysis, whereas Beta does not use a specific technique. Thus, the

project management activities are conducted through the team members of the

PMO.

On other hand, Gamma, Zeta, belong property development industries, and Eta

being higher education. Nonetheless, despite their varying industries, all three

organisations implements mega development projects that are related to

construction works. The strategy development is part of the top management’s

responsibility in Eta, and the responsibility of family members within Zeta,

whereas in Gamma, the strategy is developed through a consultant. SWOT

analysis techniques are used for the strategy development in both Gamma and

Eta. Irrespective of the differences in sources of strategy development, and the

techniques used, however, the approach is top-down in all three organisations,

as the approach has become dominate says McCabe (2010).

In Gamma and Eta the project management activities are undertaken through a

project management consultant, but Zeta has a dedicated project management

department called the Centre for Advanced Projects Support (CAPS). Thus,

practice translation of the projects activities in Zeta are done by the CAPS team

members.

Despite of the organisation industries, all the interviewed organisations use

project management as a vehicle for their strategy implementation, although the

responsibility in this regard varies, being with a dedicated department in one

organisation, and with a consultant in the other two. However, none of the case

study organisations has agreed on techniques or model that would guidelines the

translation of the practice. Clearly the effectiveness of translation of the practice

172

was based on the skills and knowledge of the individual represented by function

manager of PMO in these organisations.

6.7 SUMMARY OF PHASE TWO

Through this chapter, there were consensuses in using deliberate strategy

approach in participated organisations. Phase Two validated the initial findings

of the study obtained from Phase One. However, Phase Two interviews aiming

to have in-depth exploration on the challenges associated with the translation of

the strategy and the practice in participated organisations. To do so, an in-depth

analysis of the both interview phases is presented in Chapter Seven through the

two case studies built based on the project types the participated organisations

do.

173

CHAPTER SEVEN

CASE STUDIES

7.1 OVERVIEW

This chapter presents two case studies namely: IT Projects, and Construction

Projects, which reflect the type of projects undertaken in the participating

organisations. The case study presented in this chapter arises from information

gathered from both interview phases conducted in three industries within Saudi

Arabia (SA), there being: Banking, Property Development, and Higher

Education. The empirical study was performed using five organisations, and the

total number of interviewees for both case studies was twenty-eight (n= 28). The

names of the organisations and the interviewees are withheld for confidentiality

reasons. As the case study focuses on the project management approach adopted

by the participating organisations to achieve their strategic objectives, two units

of analysis which are associated with the theory of translation are incorporated

as follows:

• The role of individuals

• The role of objects

The details of the case studies are now presented.

174

7.2 CASE STUDY: IT PROJECTS

This case study considers projects related to IT. Alpha and Beta, which belong

to the banking industry, execute internal development projects that are mainly

concerned with IT. In these organisations, the strategic approach is deliberate

and the development of the strategy is the responsibility of the top management

(located within the Strategy Office) role. Consequently in both Alpha and Beta

there is a top-down approach. The development of strategy is via SWOT

analysis in Alpha whilst there is no specific technique used in Beta. The belief

that strategy can be developed by senior managers and rigidly applied, explains

why the top-down approach has become dominant, according to McCabe

(2010). The role of the individual and the role of the objects resulting from the

translation process are now discussed.

• The role of individuals

In Alpha and Beta, the strategy approach is deliberate and the development of

the strategy is a responsibility of top management assigned to the Strategy

Office, and hence a top-down approach is evident in both organisations.

Alpha uses various techniques for translating and simplifying the organization

strategy, this includes: Business Management Committee (EMC), Stage Gate

Approach (SGA), Business Case Models (BMC), Strategy Forum, Coupling

Approach, and Business Architectures that borrowed from the Balance

Scorecards. However, Beta uses Business Case Module as technique for strategy

translation. In banking organisations, strategy development and translation is

part of the top management role in particular the Strategy Office.

Considering the variance between the formulation and the implementation of the

strategy, Alpha management proposed several approaches to resolve issues that

arose during the implementation. These approaches were called the Stage Gate

Approach (SGA), which directly intended to resolve the implementation gap

through the use of a Business Case Model (BCM). The interviewee thought

175

these approaches were helpful in resolving the gap, as indicated in the following

quotation:

“Recently, the bank introduced a new approach called the Stage Gate Approach (SGA), which aims to fill the gap between strategy formulation and implementation. […] After identifying the objectives, the initiative will be created through the Stage Gate Approach, which is a process to validate the generated idea through a Business Case (BC) model. This BC goes through a number of validation before it goes to the implementation”(Alpha, IBS-Strategy Office, Vice President).

Furthermore, Alpha uses Business Architecture Technique for mapping the

initiatives to ensure better success for the implementation as emphasised earlier

by the interviewee. The Business Architecture Technique used by Alpha has

five elements, including: the financial situation, capability, readiness, internal

enablers, and external providers. In fact, the Business Architecture Technique

proposed here is similar to the Balanced Scorecard (BSC) mentioned earlier in

Chapter Six of this study. However, whilst that practice is evident, the actual

name is never used. Czarniawska and Sevon (2005) confirmed this by saying

that the idea and experience of the practice is present within the organisation

and faithfully implemented but it is not referred to by the words Balanced

Scorecard.

Like Alpha, Beta also uses the Business Case Model as a technique for

translating its strategy in the same way. However, this is not to imply that the

same methods are used within that overall technique.

In both banking organisations, the Project Management Office (PMO) is

responsible for the practice of translating the project management, including the

processes, templates, and definition of the role of the PMO. Thus, the project

management activities are conducted through PMO team members at the middle

management level in both organisations. As noted in the fifth edition of

PMBOK® published in 2013, there are three types of roles for the PMO:

supportive, controlling, and directive, and these roles determine the degree of

176

control provided. Both banking organisations acknowledged the differences

between the three types of PMO role, and regardless of their familiarisation with

the project management approach (in particular PMI), neither organisation had

any solid agreement about the actual content of the PMO role and how that

would be implemented across the organisation.

Alpha was seen to be trying to implement full control via the PMO role through

its use of the Coupling Approach (CA) to overcome the changes issue for

introduced initiatives. This approach links the approved initiative with the

annual operating plan by obtaining the required budget as stated by the Strategy

Vice President. However, the PPM manager had a different idea about the role

of the PMO or the PPM, believing this to be limited to one of reporting, or

supporting, as expressed in his comments below:

“To resolve the change issue, the AOP is linked with the strategy as a couple; but not a tight couple. The main purpose of coupling the strategy with the AOP is to get the initiative ready for the implementation”(Alpha, IBS-Strategy Office, Vice President). “[…] Whatever I explained to you before about the role of project portfolio management, that’s what should be done, and that is what presented by the core team when they brought the project portfolio management as an idea to be implemented in the bank. However, what is going on? Is not that at all” (Alpha, PPM Manager).

Similarly, Beta has no common agreement across the organisation about the

implementation of the PMO roles, even though the bank was familiar with the

various PMO roles articulated in the PMI PMBOK® published by the PMI. The

PMO head stated that the organisation currently implements the controlling role

for the PMO, but the project manager thought the organisation’s implementation

was actually of a executive or directive PMO. These beliefs were confirmed

explicitly in the following comments:

“There are three types of roles for project and programme management, depend on the model you chose to implement. We have three models: support, control, and execution. […]I

177

take the office and there was only support. I'm trying to have support and control” (Beta, Head of PMO).

“Now we shifted to another approach where PMO will execute the project and business is only the stakeholders. […] We are going to somehow maturity process and I think we are more mature now than before; but still we don’t have a solid project management methodology”(Beta, PMO, Project Manager 3).

• The role of objects

The various techniques mentioned as being used for the strategy translation

produce a number of objects resulting from the simplification that are used for

strategy communication. However, in Alpha the objects resulting from one

process could be used by other techniques or go through several validation

processes as confirmed by the Vice President of Strategy:

“[…]After identifying the objectives, the initiative will be created through the Stage Gate Approach, which is a process to validate the generated idea through a Business Case (BC) model. This BC goes through a number of validation checks before it goes to the implementation”(Alpha, IBS-Strategy Office, Vice President).

Both banking organisations use traditional communication materials or ‘objects’

for communicating their strategy or practice. These objects include various

types of printed document such as plans, forms, templates, and other pro-formas

published on the internal Internet ‘portal’. The communication team in Alpha

utilises various channels for communication of the organisational strategy

directions, as a result of the translation process. The outcomes of the meeting

with the CEO are communicated directly by the senior managers to their

colleagues as highlighted in the following comment:

“There is a communication team working with the management on communicating our strategy and direction. They utilise the events, town hall, periodical news, discussion, and portal; they also utilise all media available to communicate the direction, vision, and mission. Also, there is a quarterly review meeting between senior managers and the CEO. In this meeting he discusses the 'status quo' of the bank and the senior managers are conveying the messages to their

178

fellows. Senior managers should cascade the vision, mission and the strategic goals. However, each business area is already involved in the initiatives”(Alpha, IBS-Strategy Office, Vice President).

Alpha also evaluates the level of the strategy awareness across the organisation.

In this respect, the Senior Manager believed the current effort to be sufficient.

However, the feedback survey in operation relies on closed questions that lead

to biased answers. For example, survey questions like: Do you understand our

strategy? and Are you aware of the organisation’s direction? provide little

opportunity for any comments other than yes or no. The fact that the survey

questionnaire does not seek any in-depth response means that the outcome

cannot reflect the true understanding possessed by employees.

“We always need feedback to check the understanding; beside that there is a survey to check the satisfaction mainly pre-satisfaction survey. In this survey, some of the questions are related to the strategy understanding. i.e. do you know where is our direction? Is the bank strategy clear for you? The results of this survey will help the bank to assess their weak points related to the vision, and the mission. This survey conducted yearly by the HR with coordination with the whole bank sectors. And I think there is nothing more we can do”(Alpha, IBS- Strategy Office, Vice President).

7.3 SUMMARY OF CASE STUDY: IT PROJECTS

In both banking organisations - Alpha and Beta – there is a top-down approach

to strategy development that begins at the pinnacle of the organisation. The role

of the individual in strategy translation was obvious, as the top management

personnel were involved in the translation using various techniques. For

example the Business Case Model was used in both banking organisations, but

there was no agreement on the techniques used by them for translating the

project management practice. As the translation activities of the practice fall

under the full responsibility of the PMO head, the effectiveness of practice

translation is associated with the skills, experiences, and knowledge of the

practitioner or functional manager of the PMO in both banking organisations.

Having focused on the challenges associated with the translation of the strategy

179

and the practice in IT projects, this exploratory case study has identified that the

main challenges to IT projects are concerned with: change, and clarity of the

PMO role in the practice. Table 7.1 summarises the translation process of the

case study on IT projects.

TABLE 7.1: SUMMARY OF TRANSLATION PROCESS IN IT

PROJECTS

Organisation Name Alpha Beta

Strategy Approach Deliberate Deliberate

Strategy Translation

Technique

Executive Management

Committee (EMC), Strategy

Forum, Coupling Approach

(CA), Business Architectures,

Strategy Gate Approach (SGA),

Business Case Model (BCM),

Business Architecture (BA)

Business Case Model

(BCM)

Strategy

Translation Done by

Top management members from

Strategy Office

Top management

members from

Strategy Office

Material Resulted from

Strategy Translation

‘Object’

Plans, Memo, Form, Portal Plans, Memo, Form,

Portal

Challenges of Strategy

Translation Change of the initiative or scope Clarity of PMO roles

Practice Translation

Done by PMO Head PMO Head

180

7.4 CASE STUDY: CONSTRUCTION PROJECTS

This case study considers construction projects, as three organisations are

involved in this type of activity, these being: Gamma, Zeta, and Eta. Both

Gamma, and Zeta are within the Property Development industry, while Eta is

part of the Higher Education sector. Irrespective of the industry context,

however, all three organisations implement mega construction projects. The

strategy development is part of the top management responsibility in Eta, and

the responsibility of family members within Zeta, whereas in Gamma, the

strategy was developed through an external consultant. SWOT analysis

techniques are used for the strategy development in both Gamma and Eta. The

strategy approach tends to be deliberate in Eta and Gamma and emergent in

Zeta and under the responsibility of family members. SWOT analysis

techniques are used for the strategy development in both Gamma and Eta.

The role of the individual and objects within the translation process are now

discussed.

• The role Individuals

The strategy development is part of the top management responsibility in Eta,

and the responsibility of family members within Zeta, whereas in Gamma, the

strategy is developed through an external consultant. SWOT analysis techniques

used for the strategy development in both Gamma and Eta. Irrespective of the

differences in sources of strategy development, and the techniques used,

however, the approach is top-down in all three organisations. University team

members are engaged in strategy formulation and execution. Balanced

Scorecards (BSC) used in Eta as technique for translating the organisation

strategy goal and objectives. In Eta the translation process is facilitated through

forums and discussions with top and middle management members, and through

the use of the ‘Champion’ leadership model for translating the strategy.

“[…] We use several approaches such as sessions, letters, booklet, motivational meeting, and follow-up meeting. […] We do two things to connect our projects and daily activities with our vision through the organisation environment; first we

181

framed our vision and mission statement in every corridors to make sure that everyone is aware of it or at least read it once. Second thing all our strategy and objectives have printed in the strategy guideline document. […] Champion is like manager; if there is team of six people works on projects we appoint one of them as Champion. There are a number of champions and there is a leader for the champions or champion of champions“(Eta, Strategy Implementation Supervisor- VPP Office). “University strategy plans is very broad and includes more than 11,000 transactions for the implementation and about 159 KPIs for monitoring.[…] we never looked back to check whether this plan will reach to our vision. […] We were focused on our strategic objectives, which comes from the SWOT”(Eta, Strategy Implementation Supervisor - VPP office).

However, the project management activities are translated through a project

management consultant. Zeta on the other hand, has a dedicated project

management department called the Centre for Advanced Projects Support

(CAPS). Thus, in Zeta the translation of the project management approach is

undertaken by CAPS members. In Gamma, the multi-phases and split-wealth

was used as a model to translate the practice or ‘simplification’ of the

programme and project portfolio management through the phase breakdown

idea. However, only the practice has travelled – the name has not. In Zeta,

zoning and sub-zoning were used as the model to translate the practice

employed in executing ‘fast mega track projects’. The zoning concept breaks

down the project into zones which are then worked upon in parallel. Zoning and

sub-zoning approaches are compatible with the practice of programme/multiple

concurrent projects. Here the practice travelled, but again, the name did not.

The most difficult challenges were associated with changing the strategy and

project scope, and interviewees considered that the simplification of the

university strategy and the engagement of middle management would help to

make the strategy more understandable.

“We have 57 on-going projects that considered out of the scope of the second university strategy. If these projects are

182

not considered as a strategic projects that mean we have something wrong; or it mean we are work on needs bases and not on strategically bases. On the other hand we only seven projects that serve the second university strategy. Comparing the numbers both strategic and non-strategic projects, I believed that the majority of our projects should serve the university strategy, unfortunately the case here are totally reverse. If we calculate this by percentage, this mean 10 % of our projects are severing university strategy and that means we have a defect in our strategic planning”(Eta, Project Manager of Strategy Implementation). “First of all, the project that serve the university strategy have different path than the none-strategic project. We do strategic project as ‘rush project’ and both the contractor and the consultant knew that from the beginning”(Eta, Site Manager for Campus Projects - Consultant office).

• The role of objects

Both Gamma and Zeta use traditional materials for communicating the objects

resulting from the practice translation. These objects including various types of

printed document such as plans, forms, booklets or other pro-formas published

on the internal Internet ‘portal’. Additionally, Eta produces various types of

object resulting from the translation process including: strategy document

(Appendix E), plans, forms, measures, and annual reports. Moreover, the

university utilises the latest technology in communicating and following-up its

strategy through software developed in-house, called MARZ and PCM. This

includes the use of social media such as facebook and twitter.

“[…] there is Executive Committee head by the VP for projects meet every-month with the champions to follow-up the strategy implementation progress and to take the required decision on spot. […]Second thing all our strategy and objectives have printed in the strategy guideline document“(Eta, Strategy Implementation Supervisor- VPP Office).

However, these objects have contributed little in terms of strategy

communication as consultants and contractors members have been excluded

from these communication approaches, thereby leaving the knowledge of

strategy and cognition purely within the boundaries of the university staff.

183

“The contractor does not cares about the strategic reflections of the project itself; the most important thing for him is the profit and to get his payments. I believed that the consultant should be aware of the strategy as he representing the owner to follow-up the projects strategically. However, the consultant perception of the university strategy is limited and missing the details”(Eta, Site Manager for Campus Projects - Consultant Office).

Moreover, the employee at the execution levels of the organisation only sees

plans and tasks, and is not part of the bigger picture of how the work they

undertake fits in with everything else. This was echoed by one interviewee who

indicated being focused purely on project completion without paying attention

to the project’s strategic objectives. Clearly, this increases the gap between the

strategy development and the implementation.

“I have attended the MARZ awareness session and I knew that the university have strategies and objective but I can’t feel it. […] For my level as engineer, I'm interested to complete the project, once the project completed I will inform them, so the top managers would know which part of the strategy was achieved, and this on our level”(Eta, Construction Engineer - Consultant Office). “Sometimes in the committee meeting I shocked when I listen to our executives because there is a big variance between what they thoughts ‘mind picture’ and what we actually do”(Eta, Project Manager of Strategy Implementation).

Therefore, staff at the lower levels of the organisation (‘execution level’) are

involved with detailed plans and transactions rather than the strategic objectives.

This observation is confirmed by Czarniawska and Sevon (2005) who note that

when an idea has been simplified and materialised into a document, that

document has travelled over the content.

7.5 SUMMARY OF CASE STUDY: CONSTRUCTION PROJECTS

Irrespective of the industrial context of the three organisations, they all use

project management as a vehicle for implementing their strategy, although the

responsibility in this regard varies, being with a dedicated department member

184

in Zeta and Eta, although in Eta the responsibility for the project management is

shared with a consultant. In Gamma the entire responsibility is delegated to a

consultant. However, despite the use of project management as a strategy

implementation mechanism in all three organisations, there is no consensus

among them on the technique or model used for translating the practice. Clearly

the efficiency of practice translation is dependent upon the skills and knowledge

of the functional manager of the PMO in Zeta and Eta, and on the consultant in

Gamma.

In Gamma, the multi-phases and split-wealth was mentioned as a model for

simplifying the practice of the programme and project portfolio management

through the phase breakdown idea. However, only the practice travelled - the

name has not.

In Zeta, zoning and sub-zoning, were used as the model for translating the

practice associated with the execution of ‘fast mega track projects’. The zoning

concept breaks down the project into zones that are worked upon in parallel. The

zoning and sub-zoning approaches are compatible with the practice of

programme and multiple concurrent projects. Here the practice travelled, but the

name has not. As the exploratory case study focuses on exploring the challenges

associated with the translation of both strategy and project management

practice, it is seen that the main challenges associated with construction projects

are limited to: changes in the strategy and project scope, and the minimal

contribution of the produced objects.

Below Table 7.2 summarises the translation analysis of the case study for

construction projects.

185

TABLE 7.2: SUMMARY OF TRANSLATION ANALYSIS IN

CONSTRUCTION PROJECTS

Organisation Name Gamma Zeta Eta

Strategy Approach Deliberate Emergent Deliberate

Strategy Translation

Technique SWOT

Impose by

Owners

Balanced Scorecards,

Champion

Strategy

Translation Done by

Top- level

management

members

Family

Business

Owners

Top- level management

members

(Strategy Office)

Material Resulted from

Strategy Translation

‘Object’

Plans, Memo,

Form, Intranet

Plans, Memo,

Form, Intranet

Strategy Document II,

Plans, Memo, Form,

Intranet, MARZ

Challenges of Strategy

Translation

Changes in

strategy and

project scope

Changes in

strategy

Changes in strategy and

project scope, and the little

role of Objects

Practice Translation

Done by Consultant

CAPS Team

Members PMO & Consultant

Practice Translation

Model Split wealth

Zoning and

Sub-zoning -----

186

CHAPTER EIGHT

DISCUSSIONS

8.1 DISCUSSTION

Having explored how organisations in Saudi Arabia are practising the project

management approach to achieve their strategic objectives, and done so by

considering how the concept of translation influences that implementation, it is

now appropriate to present a general discussion of the overall research findings.

Hence, the research questions raised in Chapter One of the thesis are answered

through this chapter. For ease of reading, these questions are repeated below:

1 Why does the project management approach make only a small

contribution, if any, to the achievement of organisational strategy?

2 How is organisational strategy being translated?

3 What is the translation model used for translating organisational strategy

and project management?

4 Who is involved in the translation of strategy and project management

practice?

5 What are the translation challenges?

6 What objects are produced for communicating organisational strategy?

7 How do these objects connect to the individual daily activities within the

entire organisation?

To answer the above questions, two groups of interviews were conducted in five

separate organisations, two of which were from the banking industry, two from

the property development industry, and one was a university representing the

HE sector. The data was collected through two phases of face-to-face semi-

structured and unstructured interviews with participants ranging from executive

to junior frontline staff within each organisation. Two case studies presented in

Chapter Seven, namely of IT projects, and Construction projects, confirmed that

187

in the main, the approach to strategy is deliberate, using a top-down technique

for both development and implementation, in which either the top management

or owners of the organisations take control. This is evident regardless of the

organisation’s industry, structure, type or size of the projects in which it is

involved. The top-down approach mirrors the traditional method used in these

organisations, confirming that the project concept is not necessarily adopted as a

means for implementing the strategy. There is a fundamental belief that senior

managers can develop the organisational strategy and ensure its implementation

by the strict application of certain processes, and this coincides with the point

made by McCabe (2010) that it is perceived as a rational way forward that has

come to dominate the field.

The study aimed to obtain an in-depth understanding of the translation

challenges in the five organisations mentioned. An associated question posed by

Czarniawska and Sevon (2005), was whether strategy was developed for actual

practice or simply stood as artefact, existing purely for show, and this question

remained in the researcher’s mind throughout the various phases of the study.

Czarniawska and Sevon (2005) suggest that the status of strategy depended

upon who was developing it, that is to say, whether it was a consultant who

conducted the work on behalf of the organisation for agreed benefits, or the

organisation members themselves. However, Czarniawska and Sevon (2005)

were unable to be specific in this matter and indicate whether the employment

of a consultant was better for the organisation than the alternative, and

consequently, a certain amount of vagueness is left and the question remains

unanswered. Moreover, they contemplated the role of strategy objects,

wondering whether they merely stood as artefacts existing purely for show. This

study set out to find a more precise answer to these questions, as is shown in the

following paragraphs.

In this study, three organisations, Alpha, Beta, and Eta were found to be

involved directly in their strategy development and translation through

organisational activities, and in particular, there was direct involvement from the

188

top management. In Alpha strategy development was the main responsibility of

the Strategy Office, established entirely for this function, and SWOT techniques

(quantifying the strengths and weaknesses of the organisation) were adopted by

this Office to analyse the internal and external market variables. In Beta,

strategy development and translation was the responsibility of the Business

Transformation Group (BTG), also established purely for this purpose. The

BTG considered the internal and external market variables during their strategy

development process. In Eta, the strategy team was seen to use the SWOT

technique to analyse the organisation’s internal and external environment, and to

identify what opportunities could be exploited and which threats needed to be

avoided.

In contrast, the management of Gamma commissioned a consultant for

developing the organisation’s strategy, and this consultant used SWOT

techniques to address the internal and external environments. However, this

study found no evidence whatsoever that the use of an external consultant

brought valuable benefits to the organisation, since it was apparent that the lack

of internal expertise within Gamma was not compensated for by the external

consultant, and in fact Gamma encountered exactly the same challenges as the

other participating organisations. Clearly the advice from Hussey (1996:12-13)

that an “organization should not be too proud to supplement its implementation

skills from consultancy or other sources where it lacks experiences of what it is

about to do”, is given in the knowledge that hiring a consultant to work

alongside internal teams, brings the opportunity for better strategy formulation

and more successful implementation as the team and the consultant can learn

from each other, and engage in greater knowledge sharing. However, in this

case, there were no perceived benefits.

Regardless of who developed the organisational strategy, the approach was top-

down, being informed by top management or the owners, and this formula

accounted for the absence of any relationship between the formulation and

implementation of the strategy. This reflects the observation made by Cunha et

189

al. (2011:491) to the effect that “strategy still comes from the top, and hierarchy

can hurt execution”.

8.2 TRANSLATION CHALLENGES IN PROJECTS

As mentioned earlier, Latour (1986) expressed caution about the result of

translation efforts. Indeed, the point is made by (Czarniawska and Sevon, 2005)

that the translation might not adequately reflect the strategy, and this problem

encouraged deeper investigation of the issue to arrive at a better understanding

of the challenges involved in the activity. The Phase Two interviews were,

therefore, held to assist the researcher to gain more information about the

challenges and issues associated with the translation concept as evidenced

through the use of the project approach. Based on both case studies, the change

in project scope, and the individual inferences were the main translation

challenges for organisations dealing with IT projects; and the change of strategy

and the role of objects were the main translation challenges for organisations

working on construction projects. In total, three sources of challenge emerged in

the translation effort, these being: change, individual influences, and the role of

objects, as depicted in Figure 8.1.

Figure 8.1: Challenges of Strategy Translation

Change

Individual influences The role of objects

Translation

Challenges

190

These three challenges are discussed in more detail in the following sub-

sections, and specific instances of their presentation in the two case studies are

cited.

8.2.1 CHANGE

The majority of participating organisations adopted the deliberate strategy

approach, and hence it was not surprising to discover that change presented the

greatest challenge when translating the strategy into practice, because this

approach is insufficiently flexible to accommodate changes in the market or

business environments (McCabe, 2010). However, notwithstanding the fact that

change is anticipated as a challenge, many organisations do not accept that when

change is introduced part way through a process, it has a substantial impact

(Sterling, 2003). This study revealed that change, whether in strategy or project

scope, continues to represent one of the greatest challenges for strategy

translation, and subsequently promotes implementation difficulties.

In Alpha, changes to project scope were a concern of top management, and in

response to that, the Coupling Approach was introduced with the aim of

reducing such change as much as possible. Nonetheless, the change remained a

major challenge for middle managers, and again this was seen to be the fault of

senior managers exercising their power to change the project scope without

considering the consequences. Top management believed that a new process

entitled ‘Benefit Realisation’ was required, in which outcomes could be

compared with original objectives, to determine how much change had actually

occurred throughout the implementation process.

In Beta, change of the project scope functioned as a critical challenge

confronting the project management team. Project managers stressed that top

managers were able to use their power to change the project scope because of

the absence of any monitoring process.

191

In Gamma, the initial organisational strategy was to generate revenue by

functioning as a land developer and investor but the owners decided to change

the organisation’s mission such that it became a property developer. Moreover,

the original project execution changed from a one-phase approach into a multi-

phase approach. This particular decision had clear implications on the financial

resources of the organisation, which were stretched beyond their capacity, and

led to the need for further tactical change, such as for example, changing the

consultants and managers leading particular projects.

In Eta, one of the major challenges confronting projects was the change in

project scope or design. Change requests come from the end-users’ desires to

use the latest technology, thereby superseding their original specifications.

Furthermore, ‘rush projects’ contradicting the agreed strategic projects and

interfering with the natural and planned project management process, were

taken on. In this respect, the ‘strategy executors’ at the frontline become irritated

by the need to accelerate their planned activities. Of course, it must be taken into

account that change is sometimes inevitable due to external variables or to the

need to support the competitiveness of the organisation, and that indeed it is

sometimes for the better. Porter (1996) mentioned the role of change in this

respect, stating that new strategic positions mostly arise because of industry

changes. However, Saul (2000:213) observed that “[t]he problem is that some

drivers of change (like technology, cost restructuring, business re-engineering)

are associated in people’s minds with loss for employees, rank, status, overtime,

jobs and so on, and there appears to be a preference to avoid such loss,

notwithstanding the fact that the ultimate loss caused by failure to tackle such

issues could be much greater; i.e. total collapse of the business and loss of all

jobs”.

The problem of the change is twofold. Firstly, during the translation, the new

change is not always reflected in the original big picture, and consequently

organisations try to implement new ideas without appreciating that the big

picture must also be updated. And secondly, frequent changes to the project

192

scope cause those at the frontline to wonder whether the strategy was poorly

designed in the first place. Therefore, whenever changes occur, whether they are

good or bad ones, frontline employees become annoyed and discouraged, not

wanting to be part of that change, and in a sense they demonstrate what can be

interpreted as resistance to change. In the same sense, Porter (1996) notes that

the threats to strategy are usually seen to emanate from outside the organisation,

as for instance, advances in technology or alterations in the behaviour of

competitors. There is no doubt that external changes can be the problem, but the

greater threat to strategy often comes from within the organisation.

Considering that on one hand, strategy development is a long and complicated

process, and on the other hand, there is a fast rhythm of external factors, this

study proposes that strategy development should not only focus on the details of

strategic projects but should also leave room for emergent projects as a norm. It

also proposes that organisational leaders should encourage employees to accept

the emergent changes in both strategy and project scope in recognition of the

volatility in the market situation. In this respect, Porter (1996:61) argued

“companies must be flexible to respond quickly to changes. They must

benchmark continuously to achieve best practice”.

8.2.2 INDIVIDUAL INFLUENCES

Regardless of the organisation’s industry, structure, or size, all the case study

organisations use a top-down approach to strategy development in which top

management initiate the ideas and direction for the organisation. However, the

translation of the strategy is the responsible of those with less seniority in the

organisation, and the separation between the activity of strategy development

and the implementation of the strategy stands as the main challenge to the

effectiveness of the overall process. Hrebiniak (2008:7) confirmed this structural

fact, by saying “[e]very organization, of course, has some separation of

planning and doing, of formulation and execution. However, when such

separation becomes dysfunctional - when planners see themselves as smart

193

people and treat the doers as ‘grunts’- there clearly will be execution

problems”.

This research confirmed that strategy translation is effected by collaboration

between the top and middle-level management using various available

techniques and models. For instance, Balance Scorecards technique used in

Alpha and Eta, and Business Case Model used in Alpha, Beta. However, the

translations of project management practice in the organisations interviewed

were performed by the PMO manager with no specific techniques guiding these

translations, thereby indicating that the outcomes were influenced by the

individual skills, experiences, and knowledge of the practice possessed by the

manager.

Moreover, such outcomes are problematic since it is crucial for all employees,

whatever their level, to feel some ownership of the strategy implementation

plan, if there is to be any chance of success in the exercise, and in the case study

organisations, it emerged that this was not in evidence. In Alpha, those in

middle management were not part of the committee that made decisions about

the projects the company took on board, and they felt that the organisational

hierarchy wielded power that negatively affected the selection and prioritisation

process. They believed that individuals in top management used their power to

conceal problems associated with projects because they were afraid that if such

problems were to be recognised, this might reflect badly on them and eventually

reduce their authority. Gray and Larson (2008:41) comment on the use of power

in this way, and explain the reason for the lack of proper prioritisation

processes, by saying “[p]rioritizing can be an uncomfortable exercise for

managers. Prioritizing means discipline, accountability, constraints, reduced

flexibility, and loss of power”.

In Eta, even though the top management did not behave in such a way as to

suggest they believed they were above those lower down the organisation,

middle managers nonetheless believed that strategy development was beyond

their role, and was indeed the job of top management. Furthermore, junior

194

engineers with responsibility for implementing strategic projects perceived

themselves as ‘doers’ only, and frontline employees simply considered

themselves to be at the ‘execution level’. However, as argued by Cunha et al.

(2011), people operating at the frontline of an organisation are very important,

and the outcome of ignoring the needs of these workers is a ‘hidden cost’ at the

level of strategy execution. Unsurprisingly, the disconnection between the

formulation and the implementation of the strategy is also obvious. In this

respect, Cunha et al. (2011:492) argue that “strategists still formulate, the rest

still execute, and there is no conjuncture between formulating and executing”.

8.2.3 THE ROLE OF OBJECTS

This study demonstrated that strategy was developed and implemented via a

top-down approach, and whilst that in itself was not a problem, there are clear

implications for the communication of strategy across the whole organisation,

and there must be absolute clarity in this respect.

Unfortunately, it was seen that there was no organisation-wide view or

understanding of the strategy, and this was the result of ineffective

communication between the upper and lower management. Objects resulting

from the translation process are intended to establish clear communication, but

this can only be achieved if there is a good communication style that portrays a

definite and clear picture of the strategic objectives to be achieved, and that can

be shared and understood collectively by people at all organisational levels.

According to many leadership scholars, senior managers need to distinguish

between ‘strong’ and ‘weak’ vision to ensure effectiveness. This is particularly

important in organisations where it is necessary for individuals down the

managerial line to share the same vision as senior managers and executives

(Kantabutra and Avery, 2010). Hussey (1996) uses the word ‘activating’ to

represent the task of ensuring that others in the organisation understand and

support the common goal or ‘shared vision’. This common goal should be

195

defined in a consistent way to be understood, so that later in the implementation

process, common ground can be established between the key players.

In Alpha, the communication team was seen to utilise various objects to

communicate the direction of the organisational strategy and goals. These

objects include the outcome of discussion, meetings, internal events and

newsletters, and the organisation’s portal. Moreover, the main discussion points

and outcomes of the quarterly meetings with the CEO are communicated

directly through the senior managers or department heads. Additionally, Alpha

uses a feedback survey to assess the employees’ understanding of strategy and

the organisation’s direction. However, this feedback survey is conducted

infrequently and uses closed questions that introduce bias into the responses,

which do not adequately reflect the actual understanding possessed by

employees.

As a project-based organisation, Gamma aims to complete its projects on time

and to budget. Thus, top management uses weekly meetings to communicate

and review strategy through project progress review. These meetings and the

discussion within the team are used to create a common language for

organisational conversation. However, no efforts are made to assess the

understanding of strategy among employees, since the top management believe

the team is small enough to spread the message, which is clearly understood as

being ‘to complete the project’.

In Eta, various objects were used to communicate the organisation’s strategy.

These included power point slides of workshops and sessions, printed

documents, plans, forms, and published pages on the internal website.

Moreover, a new software package called ‘MARZ’ had been recently developed

to enable the effective follow-up of strategy implementation. Together, these

various objects were successful in creating an enormous number of objectives,

tasks, and measures. Nonetheless, these objects did fail to construct a clear and

common picture of Eta’s strategy and to clarify the ultimate goal, which would

196

have helped in connecting the daily activities of staff with the organisational

strategy. This answered the question posed in the literature concerning whether

objects (including various types of document and plan) were helpful in creating

a shared vision across the whole organisation.

In this respect, Gray and Larson (2008:29) state that “[t]he implementation gap

refers to the lack of understanding and consensus of organisation strategy

among top and middle-level managers”. In Eta, staff at lower levels of the

organisation, at the ‘execution level’, recognised the detailed plans and

transactions, rather than the strategic objectives. In these instances, they simply

recall measures and forms as opposed to envisioning the big picture or the ‘Eta

vision’.

To sum up, the participating organisations used various materials and tools to

communicate the direction of their translated strategy and practice. These

communication tools and approaches are considered as objects that attempt to

create common knowledge and understanding across all levels of the

organisation. However, although these objects are intended to play a major role

in sharing knowledge by facilitating collaboration and communication between

individual actors in diverse environments through drawings, specifications and

reports (Di Marco et al., 2012), the genuine sharing of strategic information

tends to occur through communicative episodes such as discussions and

workshops (Hodgkinson et al., 2006). This study showed most definitely that

these tools and approaches do not make any significant contribution to the

creation of a clear and common view or appreciation of the strategy across the

entire organisation. It may be that the reports and other documents that comprise

these tools may simply be filed away and not perceived as part of the overall

strategy implementation. In this sense, Spee and Jarzabkowski (2009:228)

stated, “strategy tools may be useful for facilitating social interactions between

strategy participants. However, the analyses performed in a specific interaction

may then simply be relegated to a report or document that has little relevance to

ongoing strategy activities”.

197

8.3 IMPROVING THE TRANSLATION OF THE PRACTICE

In regard to the project management approach, this study revealed that the role

of the PMO was not defined clearly at the beginning of the translation of project

management practice. This failing has had a major impact on the way that

project management has been undertaken in these organisations. The fifth

edition of PMBOK® published in 2013, identified three types of role for the

PMO, considering these as determinants of the degree of control provided, as

follows:

Supportive: Serves as a repository for the project by providing a template,

training, best practice, and lessons learned from previous projects. The degree of

control provided by this type of PMO is low.

Controlling: Provides support and the required compliance by adopting a

project management framework using various methodologies and tools. The

degree of control provided by this type of PMO is moderate.

Directive: Manages the project directly and has the authority to act as the key

decision-maker through the life cycle of the project. The degree of control

provided by this type of PMO is high.

Four of the case study organisations (Alpha, Beta, Zeta, and Eta) have

established a dedicated department with responsibility for all projects within

these organisations.

In Alpha, various types of project management approach were adopted by the

PMO. The top management thought the variety of project practices that were in

use within the organisation, such as PPM and EPMO, would help in fully

controlling the projects such that they followed the strategic direction of the

organisation. However, the frontline project managers believed the role of the

PMO was purely one of reporting, which confirms that the supporting type has

very low control over the projects. The variance in views between top

management and the project managers in regard to the PMO role was the main

198

issue that led to the lack of clarity in terms of the project management role in

Alpha.

In Beta, project management approaches were adopted through the PMO. The

top management was seen to have a clear view about the old role (Supportive)

and the new role (Controlling) that was being implemented, and despite the

project challenges that the organisation certainly faced, it is true to say that Beta

did have a clear understanding of the role it wanted to adopt across the

organisation. Furthermore, the PMO had better engagement in the process of

project selection and prioritisation.

In Zeta, project management approaches were executed through the CAPS that

had recently been established. The intention of the top management was that the

project management role aimed to be that of mediator, linking strategy and

operation. The project approach remains, however, at the early stage of its

implementation, and Zeta does not yet have a clear understanding of which role

will be adopted across the organisation.

In Eta, the project management role was split between the project management

department and project consultants. However, although the project department

within Eta believed it was sharing the role with three consultants who undertook

the project management role, the department’s role was limited to supporting the

consultants in cases where issues arose with the contractors during the project

execution. Eta management considered the project department and the

consultants to be working as one team.

On the other hand, Gamma decided to commission consultants to discharge the

full role of project management, that decision being made in an attempt to

overcome the lack of human resources with expertise in this area. Consultant

commissioning as seen in Gamma represents a type of outsourcing in which

project works are essentially sub-contracted to other companies. There are

advantages to be gained from this approach, including cost reduction, faster

project completion, the ability to use a high level of expertise, and resource

flexibility (Gray and Larson, 2008). Unsurprisingly, both organisations Gamma

199

and Eta are dealing with construction projects in which outsourcing is normal in

the construction industry. Gray and Larson (2008:389) note that “[c]ontracting

project work has long been the norm in the construction industry, where firms

hire general contractors who, in turn, hire and manage cadres of

subcontractors to create new buildings and structures”.

Furthermore, Gray and Larson (2008) defined two approaches to outsourcing,

these being, the traditional one and the partnering one. The traditional approach

is similar to the master-slave relationship that exists between the owner and the

provider; whereas, the partnering approach involves all parties working together

as partners and sharing the ultimate goals of success. Considering this

outsourcing approach, in Gamma the consultant relationships were considered

as subscribing to the traditional approach, whereas in Eta they were more

reflective of the partnering approach.

Whether the project management was performed through a dedicated

department within the organisation or by an external consultant, the translation

of the practice was weakened by the absence of technique or model that could

guide it.

200

CHAPTER NINE

CONCLUSIONS AND FUTURE RESEARCH

9.1 CONCLUSIONS

This study aimed to explore the practice of project management in Saudi

Arabian organisations, and to understand the influences of the translation model

on the implementation. During this exploration it was necessary to acquire an

appreciation of how strategy is translated and to investigate the problems

associated with that translation. By doing this, the research has gone beyond the

mere exploration of the implementation challenges, to include an examination of

how the theory of translation operates to create a framework whereby strategy

can become alive in a real project-orientated environment.

The exploratory data presented in this study has been collected from five

separate organisations in Saudi Arabia, two from the banking industry, two

engaged in property development, and one from the HE sector. That data was

collected via face-to-face semi-structured and unstructured interviews with

participants ranging from executives to junior frontline staff within each

organisation. The detailed analyses of the data presented in the previous

chapters has led to the following conclusions:

1. The project management approach makes little contribution in achieving

the strategic objectives of an organisation due to weaknesses in the

translation of the practice. This study has shown through the case study

organisations that the project management approach is implemented

differently, either using project and programme management, or project

portfolio management (PPM). Alpha adopted PPM to overcome the

problem of the old project management approach, but it emerged that the

outcomes and benefits of the newly-adopted technique were similar to

201

the old one. This was not because the approaches and methods chosen

were the same, but rather because the translation of the practice or

‘simplification’ was poorly performed, and thus ineffective.

2. The study revealed 15 challenges confronting Saudi organisations in

various industries during project implementation. The themes of these

challenges were mentioned in Chapter Two of the thesis when attention

was given to existing research. However, as the empirical study was

conducted with a research sample working in Saudi Arabian

organisations, the findings from it cannot be generalised, as there are

particular cultural factors that relate exclusively to the Saudi Arabian

context.

3. The Balanced Scorecards Technique was used in strategy translation in

Alpha, and Eta, although Alpha did not name the technique as such.

There was no consensus in respect of techniques used for translating the

strategy into achievable objectives in those organisations. That said, all

the participating organisations used the project management approach as

a tool to execute and monitor strategy implementation. Eta used the

Balanced Scorecard as an approach for translating the strategy into

specific objectives and projects, which can then be measured easily

through the project management approach.

4. The majority of participating organisations tend to use a deliberate

approach based on corporate theory. Only Zeta uses an emergent

approach that is founded on innovation theory. The study shows that top-

level management in four organisations were involved in the strategy

formulation. Only Gamma hired a consultant for this purpose.

5. Individuals from top and middle level management were in charge of the

translation of the strategy in these case study organisations. However,

the practice translation was performed by functional managers, in

particular the manager responsible for the PMO. Gamma hired a

consultant for the role of project manager, and Eta shared this role with a

consultant due to certain organisational aspects. Nonetheless, the study

revealed that even with the benefit of an external consultant, these

202

organisations still faced a number of challenges, thereby indicating that

the consultants themselves were unable to bring success in

implementation.

6. This study indicates that the objects make little contribution in respect of

connecting people with the organisational strategy or practice. Strategy

documents, plans, templates, measures, and procedures are examples of

objects resulting from the translation process or ‘materialisation’. The

practice perspective acknowledged the influence of objects but was

unclear about the role of the objects in strategy communication. In Eta,

special software had been developed in-house to track the

implementation of strategy objectives. All organisations participating in

the study were using objects in various formats to link the daily activities

of their staff with their organisations’ strategic objectives, which they

aimed to achieve. These objects resulted from the translation, in

particular from plans and documents that could easily be tracked,

measured, and associated with a responsible person. However, these

objects fail to connect staff daily activities with the organisation’s big

picture because the staff involved were seen to focusing on completing

the list of activities for which they were accountable, rather than

understanding the strategic contribution of their work.

7. Change in strategy and project scope is the main challenge to the

translation of the strategy through the project management approach, and

can often result in undesired outcomes. This is due to the deliberate

strategy approach adopted in most of the organisations. The gap between

the strategy development activity and the implementation of that strategy

arises because of changes that occur to the strategy or the scope of the

project during the implementation. Such changes lead to differences

between the original desire and the translated objectives. In Alpha the

change led to a result that was not aligned with the original objective,

and hence, the management expressed the needs for new process

‘Benefit Realisation’ to trace backward the result. In Gamma the change

resulted in the organisation being drained of financial resources at the

203

beginning of the project. And in Eta the change led to delay in project

completion.

8. In all participating organisations, the lack of communication was

revealed in relation to the strategy, which was not linked appropriately to

the employees’ daily activities, as mentioned earlier. These organisations

used traditional styles of communication based on text format, such as

written documents, plans, and strategy guideline. Furthermore, none of

the organisations, with the exception of Alpha, sought feedback to

evaluate employees’ understanding of these strategies.

9.2 REFLECTIONS ON THE GENERAL PRPOSITIONS AND THE

CONCEPTUAL FRAMEWORK

Reflecting on the general propositions of this study, it can be seen that two

assumptions were made, the first being that successful strategy implementation

could be achieved within Saudi organisations via the project management

approach, and the second that this approach would be implemented differently.

In respect of the first assumption, the exploratory case studies involved in the

Phase One interviews resulted in the identification of 15 challenges confronting

Saudi organisations in their attempts to implement their organisational

strategies. These challenges are similar to those encountered in the traditional

approach to strategy implementation. Some studies suggest a number of critical

success factors for successful implementation depending upon on the choice of

the project management approaches adopted. However, regardless of the name

of the particular approach selected, organisations still failed to obtain the

ultimate benefits of the said approach due to inadequate translation of the

project management practice.

In terms of the second assumption, the data gathered the five organisations

interviewed and reported in Chapter Six, revealed obvious differences in the

translation activity. The banking sector implemented its project management

through the team members from the PMO. In Alpha there was an attempt to

204

implement a directive role of the PMO through various approaches across the

organisation, but these were used in a supporting role only, whereas in Beta

both the supporting and controlling roles of the PMO were implemented. On the

other hand, Gamma and Eta dealing mainly with construction projects,

commissioned a consultant for their project management activities for

organisational and structural reasons. In Zeta, project management was

undertaken by the recently-established Centre for Advanced Projects Support

(CAPS), but it was clear that the project approach remains in its infancy, and

Zeta does not yet have a clear understanding of which role the PMO will adopt

with all parts of the organisation.

The second assumption was that in Saudi project-oriented organisations, the

project management approach would be implemented differently. The collected

data from five interviewed organisations that presented in Chapter Six showed

obvious differences in translating the project management approach. The

banking sector tended to implement the project management through the team

members from the Project Management Office (PMO). Alpha attempts to

implement directive role of PMO through variety of approaches were seen

across the organisation, but they were used in as supporting role only, whereas

in Beta there was an attempt to implement both supporting and controlling roles

of PMO. On the other hand, Gamma and Eta were dealing mainly construction

projects, and they commissioned a consultant for project management activities

for organisational and structural reasons. In Zeta, project management carried-

out through Centre for Advanced Projects Support (CAPS) that had recently

been established. The project approach is still, however, at the early stage of its

implementation, and Zeta does not yet have a clear understanding of which role

of PMO will be adopted across the organisation.

Recalling the SAP conceptual framework developed by Jarzabkowski et al.

(2007), and discussed in Chapter Three, we can appreciate the presence of three

elements: strategy makers, project management practitioners, and the theory of

translation as depicted in Figure 9.1.

205

Figure 9.1: Reflections on Conceptual Framework for SAP

The detail contained within Figure 9.1 is now discussed.

• 9.2.1 IMPLICATIONS FOR THE STRATEGY MAKER

This study confirmed that there are many challenges confronting the

participating Saudi Arabian organisations in using the project management

approach as a vehicle to achieve their organisational strategies. Without doubt,

they do all view strategy development as very important, but they do all fall

short in not devoting the same energy to the issue of how to implement what

they have conceptualised. Strategy development attracts the attention and

support of the top managers, who are not actually responsible for

implementation in an operational sense. Consequently, top management fails to

appreciate that a sound implementation plan is necessary for operational

personnel to follow, as it is they who produce the final outcome of all the

strategy development efforts. Nonetheless, despite the lack of senior

management attention to implementation, efforts by a range of other individuals

throughout the organisation to ensure implementation activities are in evidence.

Praxis

SimpliSicationand

Materialisation

Practitioners

Practices

Strategy Maker

Acknowledge the influences of individuals to improve the communication flow across organisation levels

Theory of Translation

Enhance objects’ roles through pictorial representation

Project Management

Defining the desired role of PMO at the beginning

206

That said, irrespective of such involvement, and all the efforts, approaches and

the use of management tools that purport to fill the gaps, the research findings

provide strong evidence of the gap between strategy development and

implementation. In this matter, the most crucial dimension to be improved is

the role of the objects created to facilitate the communication flow between the

upper management ‘strategy makers’ and the lower management ‘strategy

implementers’. Porter (1996) emphasises the need for clear communication and

constant discipline if strategy is to be properly implemented, and Hussey

(1996:11) says that “[i]t is the task of ensuring that others in the organization

understand, support and eventually share the vision. The vision cannot be

understood unless it communicated, and cannot be communicated unless it is

defined in coherent way”.

• 9.2.2 IMPLICATIONS FOR PROJECT MANAGEMENT

PRACTITIONERS

There are many studies proposing the effectiveness of the project management

approach in achieving organisational strategy, and others proposing a number of

critical success factors for improving implementation, but equally these also

demonstrate that many challenges confront the organisation during project

implementation. Taking into consideration the variations in practising the

project management approach from one organisation to another as revealed in

this study, it can be seen that the main problem is not in the project management

approach itself but rather in the way that the approach has been translated into

workable practice in these organisations. Thus, it is very important that these

organisations give a great amount of attention to the translation concept, so that

the project management approach to be implemented for organisational strategy

can be successful. Moreover, there must be complete agreement from the

beginning on the role of the PMO and whether this is fully in control or shares

control with other functions. Simultaneously, there must be a clear and strict

definition of the responsibilities of all involved in order to avoid the

207

implementation challenges and other organisational conflicts that may occur due

to misunderstandings between the project management stakeholders.

• 9.2.3 IMPLICATIONS FOR THEORY OF TRANSLATION

The theory of translation proposed by Czarniawska (2002) suggested that for an

idea to be transported it must first be simplified, and then materialised, so that it

may effectively travel over time and space. This study was conducted within

five organisations in order to explore the role of objects produced from the

translation process of strategy and the project practice adopted by these

organisations. As presented in Chapter Seven, all participating organisations did

indeed follow the theory in this respect, since they did simplify and materialise

their strategies and practice through objects including various document formats

such as strategy guidelines, plans, forms, reports, and templates, which were all

based on textual representation. Consequently, these objects failed to establish a

shared vision because of the lack of embodiment of the idea, and this was

obvious in the number of challenges that remained as revealed during the two

case studies, which demonstrated variance in their results. In order to develop a

consistent view, it is recommended by the researcher to use a pictorial

representation to enrich the textual objects and guide the translation of the

practice through visual representation. This would help in connecting

organisation members with the shared goal they wish to achieve.

9.3 LIMITATIONS

1. The research was conducted in five organisations in Saudi Arabia, and

the conclusions drawn from the data collected from these five particular

organisations are tightly related to these organisations’ particular

institutional and sector settings. Accordingly, the study did not aim to

generalise its results to other settings. Rather, it focused on helping these

precise organisations, and other like organisations, to have a better

understanding of how strategy can be translated through project working,

and how project management can be effectively implemented through

208

the translation concept. In particular, it aimed its findings at senior

managements, strategy-makers, and project management practitioners in

such organisations in Saudi Arabia and other countries where there is a

similar culture.

2. In aiming to explore the challenges associated with translation of

strategy into practice in organisations in Saudi Arabia, the first and

foremost limitations experienced by both the researcher and the

respondents were related to the constraints imposed by time and

distance. These constraints resulted in a relatively small number of

practitioners from the banking industry being available for interviews.

Additionally, the long bureaucratic process involved in gaining access to

participants in the petrochemicals and oil industries was a constraint.

Moreover, the researcher was operating to a specific timescale to meet

with academic regulations, and had particular financial constraints.

Consequently, there were the said limitations on the size of the research

sample.

3. This study has mainly depended on a qualitative approach to the

collection and analysis of data, and the highly intensive nature of the

qualitative design placed limitations on the amount of data that could

realistically be gathered. The findings could have been strengthened by

the additional of more data regarding the participating organisations

which would have generated a greater appreciation of the context in

which they operate, but this would have implied reducing the number of

participants to create a more in-depth focus on just one or two

organisations.

9.4 RECOMMENDATIONS FOR FURTHER RESEARCH

1. This study explored five Saudi Arabian organisations representing three

specific industries, namely: banking, property development, and higher

education. These five organisations all operated a project management

philosophy, some being involved with IT projects, and others with

Construction projects. Other industries are engaged in different types of

209

project, and consequently, investigations in such environments may well

reveal new findings. Hence, there is a suggestion to replicate the study in

different industries.

2. This study discovered that strategy and practice translation are facilitated

through discussions during meetings and other forums in which

communication can take place effectively, and hence, knowledge-

sharing is evident. Such opportunities for communication are considered

as boundary objects. Hence, it might be useful to consider other

theoretical perspectives, for instance ANT and boundary objects.

3. It would also be interesting to explore the same cases over several years

with a focus on one or two organisations only to acquire a set of

longitudinal data that would allow for the tracking of a newly-

implemented project management approach. It would also enable the

identification of the means of strategy translation through project

management practice from the beginning, and of the factors that affect

practice.

210

REFERENCES

(PMI), P.M.I. (2013). A GUIDE TO THE PROJECT MANAGEMENT BODY OF KNOWLEDGE-PMBOK Guide. 5th Ed. Pennsylvania: Project Management Institute. [online]. Available from: http://www.pmi.org/PMBOK-Guide-and-Standards.aspx.

Acciaioli, G.L. (1981). Knowing What You Are Doing a Review of Pierre Bourdieu’s Outline of a Theory of Practice. Canberra Anthropology, 4(1), pp.23–51.

Bacharach, S. and Lawler, E. (1980). Power and Politics in Organizations: the social psychology of conflict, coalitions, and bargaining. California: Jossey-Bass.

Balogun, J., Huff, A.S. and Johnson, P. (2003). Three Responses to the Methodological Challenges of Studying Strategizing *. Journal of Management Studies, 40(1), pp.197–224.

Bell, R.T. (1991). Translation and Translating: Theory and Practice. C. N. Candlin, ed. Longman.

Bourne, M. et al. (2002). The success and failure of performance measurement initiatives: Perceptions of participating managers. International Journal of Operations & Production Management, 22(11), pp.1288–1310.

Bourne, M. and Neely, A. (2003). Implementing performance measurement systems : a literature review John Mills and Ken Platts. , 5(1), pp.1–24.

Callon, M. (1980). Struggles and Negotiations to Define What is Problematic and What is Not: The Socio-logic of Translation. In K. D. Knorr, R. Krohn, & R. Whitley, eds. The Social Process of Scientific Investigation. London: D. Reidel Publication Company, pp. 197–221.

Carroll, C. (2000). The Primacy of Imagination. In P. Flood et al., eds. Managing Strategy Implmentation. Oxford: Blackwell Publishing Ltd., pp. 183–195.

Cascella, V. (2001). Three Keys for Translating Strategy into Action. Journal of Organizational Excellence, 21(1), pp.65–71.

Cauvery, R., Sudhanayak, U.K. and Meenakshi, R. (2003). Research Methodology for student in social science. S.Chand Group.

Chesley, J. and Wenger, M. (1999). Transforming an organization: Using models to foster a strategic conversation. California Management Review, 41(3), pp.54–73.

Clark, D. (1997). Strategic Management Tool Usage: A Comparative Study. Strategic Change, 6(7), pp.417–427.

Cooper, R.G. et al. (1999). New product portfolio management Practices and Performance.pdf. Journal of Product Innovation Management, 16(16), pp.333–

211

351.

Cooper, R.G., Edgett, S.J. and Kleinschmidt, E.J. (1998). Portfolio Management For New Products. First. PERSEUS BOOKS.

Covey, S.R. (2004). The 7 Habits of Highly effective People. FP Free Press.

Creswell, J.W. (2009). Research design: qualitative, quantitative, and mixed method approaches. 3rd ed. London: Sage Publications.

Cunha, M.P.E., Rego, A. and Clegg, S. (2011). Beyond addiction: Hierarchy and other ways of getting strategy done. European Management Journal, 29(6), pp.491–503.

Czarniawska, B. (2002). A Tale of Three Cities: or The Glocalization of City Management. Oxford: Oxford University Press.

Czarniawska, B. (2007). Reclaiming processes. Scandinavian Journal of Management, 23(3), pp.353–355.

Czarniawska, B. and Sevon, G. (2005). Translation is Vehicle, Imitation It’s Motor, and Fashion Sits at the Wheel. In B. Czarniawska & G. Sevon, eds. Globle Ideas: How Ideas, Objects and Practices Travel in the Globle Economy. Copenhagen Business School Press, pp. 7–12.

Daft, R.L. (1998). Organizational Theory and Design. 6th Ed. Ohio: South Western College Publishing.

Denzin, N.K. and Lincoln, Y.S. (1998). Collecting and Interpreting Qualitative Materials. Sage Publications.

Easterby-Smith, M., Thorpe, R. and Jackson, P. (Paul R.. (2008). Management Research. 3rd ed. London: SAGE.

Elonen, S. and Artto, K. (2003). Problems in managing internal development projects in multi-project environments. International Journal of Project Management, 21(6), pp.395–402.

Favaro, K. (2015). Defining Strategy , Implementation , and Execution.

Feiler, P. and Teece, D. (2014). Case study, dynamic capabilities and upstream strategy: Supermajor EXP. Energy Strategy Reviews, 3, pp.14–20. [online]. Available from: http://dx.doi.org/10.1016/j.esr.2014.05.003.

Feldman, M. and Orlikowski, W. (2011). Theorizing practice and practicing theory. Organization Science, 22, pp.1–14.

Feldman, M.S. (2003). Reconceptualizing organizational routines as a source of flexibility and change. Administrative Science Quarterly, 48(1), pp.94–118.

Fernandes, K.J., Raja, V. and Whalley, A. (2006). Lessons from implementing the balanced scorecard in a small and medium size manufacturing organization. Technovation, 26(5-6), pp.623–634.

Gabriel, Y. and Griffiths, D. (2004). Stories in organizational studies. In C.

212

Cassell & G. Symon, eds. Essential guide to qualitative methods in organizational research. London, pp. 114–126.

Gersick, C. and Hackman, R. (1990). Habitual routines in task-performing groups. Organizational Behavior and Human Decision Processes, 47, pp.65–97.

Ghauri, Pervez N., Grønhaug, K. (2005). Research methods in business studies: a practical guide. Financial Times Prentice Hall.

Gray, C.F. and Larson, E.W. (2008). Project Management, the Managerial Process. Fourth. McGraw-Hill Higher Education.

Haapasalo, H., Ingalsuo, K. and Lenkkeri, T. (2006). Linking strategy into operational management: A survey of BSC implementation in Finnish energy sector. Benchmarking: An International Journal, 13(6), pp.701–717.

Hacker, M. and Brotherton, P.A. (1998). Designing and installing effective performance measurement systems. IIIE Solutions, 30(8), pp.18–23.

Heide, M., Grønhaug, K. and Johannessen, S. (2002). Exploring barriers to the successful implementation of a formulated strategy. Scandinavian Journal of Management, 18(2), pp.217–231.

Helfat, C.E. et al. (2007). Dynamic capabilities: Understanding strategic change in organizations. Malden, MA: Blackwell.

Hellriegel, D., Slocum, J. and Woodman, R. (1989). Organizational Behavior. South-Western Publishing.

Hill, T. and Westbrook, R. (1997). SWOT analysis: It’s time for a product recall. Long Range Planning, 30(1), pp.46–52.

Hodgkinson, G.P. et al. (2006). The Role of Strategy Workshops in Strategy Development Processes: Formality, Communication, Co-ordination and Inclusion. Long Range Planning, 39(5), pp.479–496.

Howard-Grenville, J.A. (2005). The persistence of flexible organizational routines: The role of agency and organizational context. Organization Science, 16(6), pp.618–636.

Hrebiniak, L. (2008). Making Strategy Work, Leading effective execution and change. Wharton school publishing.

Hrebiniak, L. (2006). Obstacles to Effective Strategy Implementation. Organizational Dynamics, 35(1), pp.12–31.

Hussey, D. (1996). A Framework for Implementation. In D. Hussey, ed. The Implementation Challenge. West Sussex: John Wiley & Sons Ltd., pp. 1–14.

Hwang, H. and Suarez, D. (2005). Lost and Found in the Translation of Strategic Plans and Websites. In B. Czarniawska & G. Sevon, eds. Globle Ideas: How Ideas, Objects and Practices Travel in the Globle Economy. Copenhagen Business School Press, pp. 71–93.

Jarzabkowski, P. (2004). Strategy as Practice: Recursiveness, Adaptation, and

213

Practices-in-Use. Organization Studies, 25(4), pp.529–560.

Jarzabkowski, P., Balogun, J. and Seidl, D. (2007). Strategizing: The challenges of a practice perspective. Human Relations, 60(1), pp.5–27.

Jarzabkowski, P. and Paul Spee, A. (2009). Strategy-as-Practice: A review and future directions for the field. International Journal of Management Reviews, 11(1), pp.69–95.

Jarzabkowski, P. and Whittington, R. (2008). A Strategy-as-Practice Approach to Strategy Research and Education. Journal of Management Inquiry, 17(4), pp.282–286.

Kantabutra, S. and Avery, G.C. (2002). Proposed model for investigating relationships between vision components and business unit performance. Journal of Management and Organization, 8(2), pp.22–39.

Kantabutra, S. and Avery, G.C. (2010). The power of vision: statements that resonate. Journal of Business Strategy, 31(1), pp.37–45.

Kaplan, R.S. (2008). Conceptual Foundations of the Balanced Scorecard. In C. Chapman, A. Hopwod, & M. Shields, eds. Handbooks of Management Accounting Research. Amsterdam: Elsevier Ltd, pp. 1253–1269. [online]. Available from: http://www.sciencedirect.com/science/article/pii/S1751324307030039 [Accessed March 2, 2012].

Kaplan, R.S. and Norton, D.P. (2006). How to Implement a New Strategy Without Disrupting Your Organization. Harvard Business Review, 84(3), pp.100–109.

Kaplan, R.S. and Norton, D.P. (2008). The Execution Premium: Linking Strategy to Operations for Competitive Advantage. Boston: Harvard Business Press.

King, N. (1998). Template Analysis. In S. Gillian & C. Catherine, eds. Quilitative Methods and Analysis in Organizational Research: A Practical Guide. London: Sage Publications, pp. 118–1334.

King, N. (2004). Using templates in thematic analysis of text. In C. Cassell & G. Symon, eds. Essential guide to qualitative methods in organizational research. London: Sage.

Latour, B. (1986). The Power of Association. In J. Law, ed. Power, Action, And Belief: A new Sociology Of Knowledge. London: Routledge & Kegan Paul., pp. 264–280.

Li, Y., Guohui, S. and Eppler, M.J. (2008). Making Strategy Work : A Literature Review on the Factors influencing Strategy Implementation.

Di Marco, M.K., Alin, P. and Taylor, J.E. (2012). Exploring negotiation through boundary objects in global design project networks. Project Management Journal, 43(3), pp.24–39.

214

McCabe, S. (2010). Corporate Strategy in Construction:Understanding today’s theory and practice. First. WILEY-BLACKWELL.

Merriam, S.B. (1998). Qualitative research and case study applications in education. 2nd ed. San Francisco: Jossey-Bass Publishers.

Meyer, A.D. (1982). Adapting to environmental jolts. Administrative Science Quarterly, 27(4), pp.515–537.

Morgan, G. (1997). Imaginization: new mindset for seeing, organizing and managing. San Francisco: Sage Publications.

Morris, P.W.G. (2004). Moving from Corporate Strategy to Project Strategy : Leadership in Project Management. In PMI Research Conference 2004. Proceedings. London: PMI. [online]. Available from: http://marketplace.pmi.org/Pages/ProductDetail.aspx?GMProduct=00100811600&iss=1.

Naaranoja, M., Haapalainen, P. and Lonka, H. (2007). Strategic management tools in projects case construction project. International Journal of Project Management, 25(7), pp.659–665.

Oltmann, J.C.-U.S.A. (2008). Project Portfolio Management: How to Do the Right Projects at the Right Time. PMI Global Congress Proceeding, pp.1–8.

Parmigiani, A. and Howard-Grenville, J. (2011). Routines Revisited: Exploring the Capabilities and Practice Perspectives. The Academy of Management Annals, 5(1), pp.413–453.

Patanakul, P. and Shenhar, A.J. (2012). What project strategy really is: The Fundamental Building Bloack in Strategic Project Management. Project Management Journal, 43(1), pp.4–20.

Payne, J.H. (1993). Introducing formal project management into a traditional, functionally structured organisation. International Journal of Project Management, 11(4), pp.239–243.

Pellegrinelli, S. and Bowman, C. (1994). Implementing Strategy Through Projects. Long Range Planning, 27(4), pp.125–132.

Pentland, B.T. and Rueter, H.H. (1994). Organizational routines as grammars of action. Administrative Science Quarterly, 39(3), pp.484–510.

Porter, M.( H.B.S. (1996). What is strategy? Harvard Business Review, (Nov), pp.61–78.

Pugh, J. and Bourgeois III, L.J. (2011). ‘Doing’ strategy. Journal of Strategy and Management, 4(2), pp.172–179.

Raisanen, C. and Linde, A. (2004). Technologizing Discourse to Standardize Projects in Multi-Project Organizations: Hegemony by Consensus? Organization, 11(1), pp.101–121. [online]. Available from: http://org.sagepub.com/cgi/content/abstract/11/1/101 [Accessed March 17, 2013].

215

Reckwitz, A. (2002). Toward a Theory of Social Practices: A Development in Culturalist Theorizing. European Journal of Social Theory, 5(2), pp.243–263.

Saunders, M., Lewis, P. and Thornhill, A. (2007). Research methods for business students. 4th Ed. Harlow: Financial Times Prentice Hall.

Saunders, M., Lewis, P. and Thornhill, A. (2012). Research methods for business students. sixth. Pearson education.

Senge, P.M. (1990). The Fifth Discipline: The Art and Practice of the Learning Organization. New York, NY: Doubleday.

Serres, M. and Brown, S.D. (2002). Science, Translation and Logic of the Parasite. Theory, Culture & Society, 19(3), pp.1–27.

Shehu, Z. and Akintoye, A. (2010). Major challenges to the successful implementation and practice of programme management in the construction environment: A critical analysis. International Journal of Project Management, 28(1), pp.26–39. [online]. Available from: http://dx.doi.org/10.1016/j.ijproman.2009.02.004.

Speckbacher, G., Bischof, J. and Pfeiffer, T. (2003). A descriptive analysis on the implementation of Balanced Scorecards in German-speaking countries. Management Accounting Research, 14(4), pp.361–387.

Spee, a. P. and Jarzabkowski, P. (2009). Strategy tools as boundary objects. Strategic Organization, 7(2), pp.223–232.

Splitter, V. and Seidl, D. (2011). Does Practice-Based Research on Strategy Lead to Practically Relevant Knowledge? Implications of a Bourdieusian Perspective. The Journal of Applied Behavioral Science, 47(1), pp.98–120.

Stake, R. (1995). The Art of Case Study Research. Sage Publications.

Star, S.L. and Griesemer, J.R. (1989). Institutional Ecology, `Translations’ and Boundary Objects: Amateurs and Professionals in Berkeley's Museum of Vertebrate Zoology, 1907-39. Social Studies of Science, 19(3), pp.387–420.

Sterling, J. (2003). Translating strategy into effective implementation: dispelling the myths and highlighting what works. Strategy & Leadership, 31(3), pp.27–34.

Strange, J.M. and Mumford, M.D. (2005). The origins of vision: Effects of reflection, models, and analysis. The Leadership Quarterly, 16(1), pp.121–148.

Wenger, E. (1998). Communities of Practice: Learning, Meaning, and Identity. R. Pea, J. S. Brown, & J. Hawkins, eds. Cambridge: Cambridge University Press.

Whittington, R. (2006). Completing the Practice Turn in Strategy Research. Organization Studies, 27(5), pp.613–634.

Whittington, R. (1996). Strategy as Practice. Long Range Planning, 29(5), pp.731–735.

216

Whittington, R. et al. (2003). Taking Strategy Seriously: Responsibility and Reform for an Important Social Practice. Journal of Management Inquiry, 12(4), pp.396–409.

Winter, M. et al. (2006). Directions for future research in project management: The main findings of a UK government-funded research network. International Journal of Project Management, 24(8), pp.638–649.

Winter, S.G. (2003). Understanding dynamic capabilities. Strategic Management Journal, 24(10 SPEC ISS.), pp.991–995.

Yin, R.K. (1993). Applications of Case Study Research. 1st Ed. T. S. Mead, ed. London: Sage Publications.

Young, R. et al. (2012). Is strategy being implemented through projects? Contrary evidence from a leader in New Public Management. International Journal of Project Management, 30(8), pp.887–900. [online]. Available from: http://linkinghub.elsevier.com/retrieve/pii/S0263786312000452 [Accessed October 14, 2012].

Young, R. and Grant, J. (2014). Is strategy implemented by projects? Disturbing evidence in the State of NSW. International Journal of Project Management, 33(1), pp.15–28. [online]. Available from: http://dx.doi.org/10.1016/j.ijproman.2014.03.010.

Yukl, G. and Lepsinger, R. (2007). Getting it Done: Four Ways to translate Strategy into Results. Leadership in Action, 27(2), pp.3–7.

Zollo, M. and Winter, S.G. (2002). Deliberate learning and the evolution of dynamic capabilities. Organization Science, 13(3), pp.339–351.

217

APPENDICES

218

APPENDIX A - INFORMED CONSENT FORM

219

220

APPENDIX B - INSURANCE ASSESSMENT FORM

Revised 25 November 2011

Research Involving Human Subjects

Insurance Assessment Form

The University provides insurance cover in respect of research involving human subjects undertaken in the United Kingdom for:

• harm to participants, on a “no-fault” or “non-negligent harm” basis, and • financial loss by participants and participating organisations, on a legal liability basis.

The University also provides insurance cover in respect of research involving human subjects undertaken abroad that does not have a medical content, on a legal liability basis.

Special arrangements are normally required for research involving human subjects undertaken abroad that has a medical content.

For these purposes, medical content means: • treating or preventing disease • diagnosing disease or ascertaining the

existence, degree of, or extent of a physiological or psychological condition

• assisting with or altering in any way the process of conception or investigating or participating in methods of contraception

• inducing anaesthesia • otherwise preventing or interfering with the

normal operation of a physiological or psychological function in order to improve health or wellbeing

• testing medicinal products or devices, or • taking tissue or blood samples.

The insurance cover is available for research sponsored, managed, designed or conducted by, or on behalf of, the University (including research undertaken by students under supervision). For further details, visit http://www.campus.manchester.ac.uk/insurance/professional-activities/humansubjects.

If you answer “No” to all the questions below, you may assume that cover will be provided by the University, subject to approval of the research by an appropriate research ethics committee and approval of any contract terms by the University Contracts Office.

If you answer “Yes” to any of the questions the proposal will need to be considered by the Insurers as part of the review process by the Research Office. If the insurance cover is confirmed you will be provided with a copy of this form signed by the Insurance Office.

Title of Research: Strategy Translation in Projects

Principal investigator: Mazen Melebari

School: School of Mechanical, Aerospace and Civil Engineering

Question Yes/No

If any part of the research, or use of the protocol, is to be carried out abroad (including internet-based research that could include respondents from abroad), does it have a medical content?

No

Does the research involve “first into man” use of a medicinal product? No

Do the research subjects deliberately include: • pregnant women? No

• children under five years of age? No

• people with special needs? No

Does the research include medical intervention involving: • investigating a medical device? No

• contraception? No

Is the research to be carried out by other organisations where the University is required by contract to provide insurance cover for the research if it proceeds?

No

Signed (PI): Date: 15 Nov 2012

This form should accompany the proposal when it is submitted to the Research Office for review.

Insurance Office approval (not required if all answers above are ‘No’)

Signed: Date:

221

What happens to the data collected? The interviews will be audio-recorded for the purpose of analysis. The interviews will also be transcribed verbatim, and saved as encrypted files in the researcher computer/laptop based at the University of Manchester. How is confidentiality maintained? Data will not be disclosed to a third party under any circumstance, and all information will be treated with the strictest of confidence. Where data is used in academic publications, these will be anonymised. Direct quotations will also be selected based on how typical and general these can be gleaned from the transcripts. Participants will be invited to view and agree to a précis of any draft publication prior to submission. What happens if I do not want to take part or if I change my mind? It is up to you to decide whether or not to take part. If you do decide to take part you will be given this information sheet to keep and be asked to sign a consent form. If you decide to take part you are still free to withdraw at any time without giving a reason and without detriment to yourself. Will I be paid for participating in the research? There is no payment for participating in this research. What is the duration of the research? The interviews are planned to last between 30 and 120 minutes, although this is likely to be longer if you have more information to tell us. Where will the research be conducted? Interviews will be undertaken at a location that is convenient for you. This can be at your office, or in a public place of your choice. Will the outcomes of the research be published? It is intended that the analysis will be published in peer-reviewed conference and journals. Contact for further information Please contact me on email: [email protected], +966 (5) 6553776), or +44 (0) 7533493335 if you require any more information. Or contact my supervisor, Dr. Paul W Chan (email: [email protected], or +44 (0) 774 783 5506) if you require any more information. What if something goes wrong? If a participant wants to make a formal complaint about the conduct of the research they should contact the Head of the Research Office, Christie Building, University of Manchester, Oxford Road, Manchester, M13 9PL.

222

APPENDIX C - PARTICIPANT INFORMATION SHEET

223

APPENDIX D - INVITATION LETTER FOR PARTICIPATE IN THE

RESEARCH

224

APPENDIX E - ETA STRATEGY II GUIDELINES - DOCUMENT

ANALYSIS AND SITE VISIT

The document contains 64 pages of A5 (210 x 148 mm) that printed in Arabic

language, as the majority of the employees are Arabic Native speaker. The

guidelines document consists of 14 topics that related to the strategy

development and programme plans for the period between 2010 and 2014. The

language of the document was easy to understand, as Arabic is the first language

of the researcher. Moreover, the conducted interviews with the appointed

strategy implementation supervisor and VPP engineers helps in connecting the

document topics with their activities. Thus, the easiness of the document

language and the interviews helped in translating the document into English as

secondary source for the data.

The first three topics are presents brief introduction about the university and its

faculties, departments and the university achievements. Furthermore, highlights

the development of the department of the projects and its related function units.

An introduction of the strategy development of the vice presidency for projects

and its importance was described in details on the three stages of the strategy

development namely formulation, execution, and the evaluation. Followed by

strategic measurements and controls that help in achieving the long-term

strategic goals. The vision, mission, and stakeholders are highlighted too. The

internal and external environments analysed was conducted based on the SWOT

approach. The results of SWOT analysis was grouped in points as below:

- (S) Strength points: there were six points that considered as a

strength points, these as below:

o The familiarities with the international codes of the construction

o Strong relationships with university departments and with other

external parties

o Top management supports for the new innovative ideas

o Being part of the university top management council

o Having a wide knowledge and the variety of expertise

o The location of the presidency of the projects within the

university in Jeddah province.

225

- (W) Weakness points: there were seven points that considered as a

strength points, these as below:

o The lack of staff development plans

o The lack of second row leaders

o The lack of internal organisational structure for the presidency of

the projects and the unclear career path for the staff

o The spatial spacing between departments within the presidency

o The lack of the communications between the project management

department and the department of operation and maintenance

o There are no studies unit in place for research that related to the

construction and building

o Weakness system of performance monitoring

- (O) Opportunities: there were six points that considered as a

opportunities points, these as below

o Increased oil prices and economics boost

o The variety of funding and project financing

o Competences availability the and variety of the expertise

o The ability for the international companies to works in Saudi

Arabia

o The advanced development in the construction and building

technologies and the building safety tools

o The ability for using university lands and assets as local

investment

- (T) Threats: in the document considered as challenges, there were

eight points that considered as main challenges, these challenges as

below

o Unrealistic administrative and finical procedures

o The lack of vision clarity for some projects in the master plan

o Low financial budget for the department of the operation and

maintenance

226

o The limited job vacancies

o The current financial policy is limiting the department from

attracting new competent staff or keeping the existent staff.

o The geographical expansion of the university and the expanded

work loads

o Low performance of the local contractors and the consultant

o No integrated database in place for project information

After that, the document elaborate of the strategic dimensions, which is consist

of six keys for realizing the strategic plan namely:

- Administrations development

- Project management

- Operation and maintenance

- Security and safety

- Master plans

- Financial development

Based on the above six strategic dimensions and the SWOT analysis for both

internal and external environment, ten strategic goals were extracted as a focal

point for the strategy plan for VPP. These strategic goals as following:

o Attracts and trains the qualified staff

o Building stimulation environment for the performance and quality

o Provide a reference studies in construction and building domain

o Developing advanced procedures for the project management

o Increasing the financial support for the department of operation and

maintenance

o Reengineering the systems of operation and maintenance

o Develop scientific mechanism for completing the master plan

o Simplify the financial procedures

o Increasing the funds

o Developing a database for financial information

227

Based on the above strategic goals, a total of twenty programmes were

developed in which two programmes assigned as maximum for each goal. Six

tables developed per strategic dimension that connects the strategic dimension

with the related strategic goals, the specific objectives, and the executive

programme and the assigned principle. The total programmes and specifics

objectives were summaries per strategic dimension in one table.

To achieve these programme of the strategic plan, the specified objectives were

translated into project using balanced scorecards (BSC), which draws the

relationships between these objectives. BSC graph demonstrates the relationship

between the specific objectives, which grouped into (inputs, outputs, internal

process, and financial). The Inputs helps in building the university

‘infrastructure’, internal process that shows how to take the advantage from the

inputs, and the outputs helps in achieving the stakeholders’ requirements and the

internal process explains how to use the input to produce the output.

The stakeholders are specified: master plan, infrastructure projects, and

operation and maintenance systems. Based on the BSCs and the grouped

objectives, four performance measurements tables developed to achieve the

strategic goals. Based on that, follow-up forms developed to track the progress

of the programmes execution in details. This form compares the planned

progress with the actual progress per year for the whole strategy period (2010 -

2014).

The operating plans tables were placed in the appendices of the strategy

document. This table is similar to project plan, which contains detailed

programme activities by determining project tasks that required for delivering

the project. It contains the task description, principle person, start date, and the

end date.

Comments on VPP Strategy II guideline

After reviewing the strategy document of VPP, there are some comments have

been taken related to the research topic. These comments as below:

228

- Initially, the total strategic dimensions were six as listed in page 16,

however in page 23 and thereafter the strategic goal linked only with the

five dimensions. The fourth dimension (Safety and Security) was

eliminated without mentioning the reasons behind that.

- The total strategic goals were ten as highlighted in page 23. To simplify

the strategies and achieve the goals, twenty programmes were

developed, two programmes for each goal as maximum. However, the

details table of each strategic dimension to link the dimension with

goals, with the objectives, programme, and the business justification of

each dimension. The information presented in each table was repeated

and tends to be descriptive, therefore, the details makes the plan so

complicated and not easy to understand. The justification part looks

more descriptive and repeat the same information that present in the

same table and that make it useless in this position.

SITE VISIT

As part of the research approach the researcher conducts a site visit to explore

the process of the project management in the real world. Moreover, exploring

how is the strategy is been translated in Eta and how object are connecting

project with strategy objective. One project was visited in the university campus

and below Photograph 7.1 is the project signboard that contains basic project

information and considered as ‘object’. This includes project name, contract

value, contractor name, consultant agent, date of award, contract signature date,

date of the handover, and the completion date. Moreover, in case of the period

extension, the extension information will be inserted too; this includes extension

period, start and end date of the extension.

229

Photograph 1: Signboard of Vocational Institute Project in Eta

Even though this visited project was one of the strategic projects; no information

was displayed on the signboard about the strategy objective of this project or

even the project number as in the strategy guideline book that easily could link

with strategy. Displaying this information would have a significant reflection in

terms of connecting project stakeholders including contractors and consultant

with the strategy visually. Czarniawska and Sevon (2005:9) substantiated this by

saying “Ideas must materialize, at least in somebody’s head; symbols must be

inscribed.” otherwise, it is bound to be ephemeral”. Thus strategy should be

visualize rather than materialise in the project world to ensure better

connectivity.