explanatory memorandum - abode group
TRANSCRIPT
Application Reference: EN070001 June 2014
Explanatory Memorandum
The Yorkshire and Humber (CCS Cross CountryPipeline) Development Consent Order
Under Regulation 5(2)(c) of the Infrastructure Planning
(Applications: Prescribed Forms and Procedure)
Regulations 2009
DO
CU
ME
NT
Contents
Clause Name Page
1 Introduction to the Onshore and Offshore Schemes ........................................ 1
2 This Explanatory memorandum..................................................................... 3
3 Purpose of the order ................................................................................... 4
4 Ancillary matters ......................................................................................... 7
5 The draft Order......................................................................................... 11
6 Part II of the Order - Works Provisions ........................................................ 16
7 Part III of the Order - Acquisition and Possession of Land .............................. 31
8 Part IV of the Order - Miscellaneous and General .......................................... 46
9 Schedules ................................................................................................ 53
Appendix Name Page
Tracked change version of the Order against the DCO Model Provisions .......... 70
1
1 INTRODUCTION TO THE ONSHORE AND OFFSHORE SCHEMES
1.1 National Grid Carbon Limited (the “undertaker”) proposes
constructing and operating a carbon dioxide transportation and storage system to support the provision of carbon capture and storage (“CCS”) technology in the Yorkshire and Humber Region.
The project in its entirety, known as The Yorkshire and Humber CCS Transportation and Storage project (the “Project”), would comprise the construction of a Cross Country Pipeline and sub-sea pipeline for
transporting carbon dioxide captured from power projects in the region to a permanent geological storage site beneath the North Sea.
1.2 The Project includes both onshore and offshore elements which are subject to separate consenting regimes (the “Onshore Scheme” and the “Offshore Scheme”).
1.3 The onshore elements of the Project are collectively termed the Yorkshire and Humber Carbon Capture and Storage Cross Country Pipeline (shortened to the “Onshore Scheme”) and are proposed to
comprise the construction of a cross country pipeline and associated infrastructure including pipeline internal gauge (“PIG”) traps, a multi-junction, three block valves, a pumping station (collectively termed
“Above Ground Installations” or “AGIs”) and any necessary interconnecting local pipelines and associated works.
1.4 The Onshore Scheme requires a new buried high pressure cross
country pipeline of approximately 67km in length with an external diameter of up to 610mm for the transportation of carbon dioxide in liquid form to a location on the Holderness coast.
1.5 As the length of the proposed cross country pipeline comprised in the Onshore Scheme will exceed 16.093km it constitutes a nationally significant infrastructure project (“NSIP”) pursuant to the Planning
Act 2008. This requires an application to be made to the Secretary of State for a development consent order (“DCO”).
1.6 The cross country pipeline will have an external diameter of up to 610mm and will be sized to accommodate up to 17 million tonnes (mt) of carbon dioxide emissions per year. The multi-junction would
enable the connection of multiple pipelines from regional carbon dioxide emitters to the Onshore Scheme. At present one installation for the capture of carbon dioxide streams, the White Rose CCS
project adjacent to Drax Power Station at Selby, being promoted by Capture Power Limited, would require a pipeline connection into the cross country pipeline. An interconnecting pipeline between the White
Rose CCS project and the multi-junction will form part of the application for the Onshore Scheme.
2
1.7 PIG traps would be sited at the start and end of each pipeline to launch PIGs (these are required as part of the planned pipeline
inspection and maintenance programme). Following a site appraisal, a PIG trap site has been identified in the vicinity of the White Rose CCS project adjacent to the Drax Power Station, near Selby.
1.8 The multi junction will facilitate the connection of multiple pipelines from other regional carbon dioxide emitters to the Onshore Scheme in the future. A site options appraisal has identified a site on land to
the south of the A645, Camblesforth as the preferred site option for the multi-junction.
1.9 Block valves will be required at regular intervals along the length of the cross country pipeline to enable the isolation of sections of pipeline for maintenance and safety. Site appraisals have been
undertaken for all the block valves and preferred sites have been identified as land to the south of Skiff Lane, Tollingham; land to the south of Lund Wold Road, South Dalton; and land to the south of the
unnamed track to Copper Hall, Skerne.
1.10 A pumping station is required to re-pressurise the carbon dioxide before it is transported offshore. This is proposed to be constructed
near to the coast. A site appraisal has been undertaken and identified land to the south of Sands Road, Barmston as the preferred site.
1.11 The offshore elements of the Project are collectively termed the
Yorkshire and Humber CCS Sub-Sea Pipeline and Geological Storage Site (shortened to the “Offshore Scheme”) and are proposed to comprise the construction of a 90km subsea pipeline to a geological
storage site. This is subject to a separate consenting regime requiring authorisation by the Secretary of State for Energy and Climate Change in accordance with the Petroleum Act 1998 and the Energy
Act 2008 respectively.
1.12 The sub-sea pipeline will have an external diameter of up to
approximately 610mm and would be sized to accommodate up to 17mt of carbon dioxide emissions per year. The geological storage site presently proposed would comprise the permanent storage of
captured carbon dioxide in a saline aquifer located approximately 1000m below the seabed. The undertaker has been granted an agreement to lease area 5/42 in the southern North Sea for the
purpose of geological storage of carbon dioxide. The capacity of the storage site is subject to on-going investigations but it is expected to accommodate at least 200mt of captured carbon dioxide. It is
anticipated that once this site has reached capacity further storage sites would be identified and utilised.
3
1.13 The Onshore and Offshore Schemes would be joined at the Mean Low Water Mark using appropriate landfall techniques; this is also the
juncture of the onshore and offshore consenting regimes.
1.14 A more detailed explanation of the authorised development, as set out in Schedule 1 (authorised development) of the Order and on the
works plans (Document Reference 2.3) can be found in the Construction Report (Document Reference 7.6).
2 THIS EXPLANATORY MEMORANDUM
2.1 A draft DCO accompanies the application for the Onshore Scheme and is entitled The Yorkshire and Humber (Carbon Capture and
Storage Cross Country Pipeline) Order 201[●] (the "Order").
2.2 As required by Regulation 5(2)(c) of the Infrastructure Planning (Applications: Prescribed Forms and Procedure) Regulations 2009,
this explanatory memorandum also accompanies the application for the Onshore Scheme. It explains the purpose and effect of provisions in the draft Order.
2.3 The Planning Inspectorate’s Advice Note Thirteen as republished in April 2012 (“Advice Note 13”) clarifies its approach to the Infrastructure Planning (Model Provisions) (England and Wales)
Order 2009 (the “DCO Model Provisions”) as follows:
“‘Model provisions’
Model provisions were set out in the Infrastructure Planning (Model Provisions) (England and Wales) Order 2009 (SI 2009/2265). They included provisions which could be common to all NSIPs, others which relate to particular infrastructure development types, in particular railways and harbours, and model provisions in respect of requirements. The Localism Act 2011 removed the requirement for the decision-maker to have regard to the prescribed model provisions in deciding an application for development consent.
Model provisions were intended as a guide for developers in drafting orders, rather than a rigid structure, but aided consistency, and assisted developers to draft a comprehensive set of lawful provisions.
In the absence of relevant guidance published by DCLG, it would be helpful for the Planning Inspectorate to receive a track-change draft of the DCO showing any departures from the model provisions. The Planning Inspectorate would wish to receive such a track-change draft of the DCO both at the pre-
4
application stage and with the formal submission of the application for development consent.
Other provisions
Provisions used in ‘predecessor’ regimes such as for Transport and Works Act Orders or Harbour Empowerment Orders may be helpful in the drafting of a DCO. Developers should though satisfy themselves that the inclusion of particular wording is appropriate and relevant in all the circumstances of a given development. The relevant precedent and the rationale for including the particular wording of a provision will need to be set out and justified in the explanatory memorandum.”
2.4 This explanatory memorandum complies with the requirements of Advice Note 13.
2.5 The Order follows the DCO Model Provisions but, where appropriate for the circumstances of the Onshore Scheme, there are certain departures from these. Such departures, where material, are
explained in this explanatory memorandum.
2.6 Certain of these departures from the DCO Model Provisions reflect wording from the Transport and Works (Model Clauses for Railways
and Tramways) Order 2006 (the "TWA Model Provisions") and Orders made under the Transport and Works Act 1992 (“TWA Orders”). Where appropriate, this explanatory memorandum sets
out the rationale for including such wording in the context of the 2008 Act and the Onshore Scheme.
2.7 Where relevant, regard has also been had to the precedents set in
the development consent orders made by the Secretary of State under the 2008 Act; and references to such orders are made in this explanatory memorandum as appropriate.
2.8 A comparison version of the draft Order against the DCO Model Provisions is also provided at appendix 1 to this explanatory
memorandum, showing any departures from the DCO Model Provisions.
3 PURPOSE OF THE ORDER
Nationally significant infrastructure development
3.1 Under sections 14(1)(g) and 21 of the Planning Act 2008 (the “2008 Act”) the construction of a cross-country1 pipeline in England2 other
1 S.21(1)(a) of the 2008 Act
5
than by a gas transporter,3 which would otherwise require authorisation under section 1(1) of the Pipe-lines Act 1962 (the
“Pipe-lines Act”)4 (on account of the pipeline exceeding 16.093km in length),5 constitutes an NSIP. As stated at paragraph 1.4 above, the cross-country pipeline comprised in the Onshore Scheme is
approximately 67 km in length and will thus exceed 16.093 km in length.
3.2 Section 31 of the 2008 Act provides that a development consent
order is required to the extent that a development is or forms part of an NSIP.
3.3 Accordingly, the undertaker is making an application to the Secretary of State under section 37 of the 2008 Act in order to obtain development consent for the Onshore Scheme. The Order is part of
the application.
Associated development
3.4 Pursuant to section 115(1) of the 2008 Act and in accordance with
the principles set out in the document entitled “Planning Act 2008: Guidance on associated development applications for major infrastructure projects” published in April 2013 by the Department for
Communities and Local Government (the “CLG Guidance”), the Order also seeks consent for associated development set out in Schedule 1 (authorised development) of the Order. Examples of
items of associated development with their own Work Nos. in the Schedule include:
3.4.1 access roads;
3.4.2 temporary working areas;
3.4.3 temporary pipeline stores; and
3.4.4 office, welfare and security facilities.
3.5 A list of further associated development is included at the end of Schedule 1 (authorised development) for works associated with
multiple Work Nos. These include in summary:
2 S.21(2)(a) of the 2008 Act
3 S.14(1)(g) of the 2008 Act
4 S.21(1)(b) of the 2008 Act
5 S.1(1) and s.66(1) of the Pipe-lines Act
6
3.5.1 site preparation works and construction compounds for certain of the AGIs;
3.5.2 the installation of wires, cables, conductors, pipes and ducts;
3.5.3 pipeline construction works;
3.5.4 works to remove or alter the position of apparatus including mains,
sewers drains and cables, which will be required where these items need to be temporarily or permanently removed to allow the construction and operation of the authorised development. Examples
include the possible temporary diversion of a utility pipe or cable to provide working space to allow construction of permanent works;
3.5.5 locating aerial markers, cathodic protection test posts and field boundary markers;
3.5.6 landscaping, ecological mitigation works and other works to mitigate
any adverse effects of the construction, maintenance or operation of the authorised development;
3.5.7 works for the benefit or protection of land affected by the authorised
development, which might (where the undertaker considers it necessary) include works to reinstate land to its former condition including land drainage systems or providing fencing to replace that
temporarily removed or to provide a delineation between land ownership or usage;
3.5.8 works required for the strengthening, improvement, maintenance or
reconstruction of any streets, which may be required where existing tracks or streets are to carry increased heavy traffic or increased numbers of vehicles. Crossings of existing public and private
highways are required and reinstatement of excavated trenches will be necessary;
3.5.9 works to alter or remove road furniture;
3.5.10 ramps, means of access, footpaths and bridleways, which are required to access the facilities as a whole and to safely access
individual areas and buildings associated with the development;
3.5.11 the carrying out of street works pursuant to article 10 (street works), works to alter the layout of streets pursuant to article 11 (power to alter layout, etc., of streets) and the alteration or removal of road furniture;
3.5.12 works for the maintenance of the authorised development;
3.5.13 works for the decommissioning, restoration and aftercare of the authorised development;
7
3.5.14 installation of drainage, drainage attenuation and land drainage including outfalls; and
3.5.15 other works, including working sites, storage areas and works of demolition necessary for the construction or operation of the authorised development and which do not give rise to any materially
different effects from those assessed in the environmental statement.
3.6 The undertaker considers that all of the works described in Schedule 1 (authorised development) are either development for which
development consent is required or associated development for which development consent may be granted (in accordance with
sections 31 and 115 of the 2008 Act and CLG Guidance) and, accordingly, may lawfully form part of an application for an Order granting development consent under the 2008 Act.
4 ANCILLARY MATTERS
4.1 The Order also contains several matters ancillary to the development for which consent is sought.
4.2 Powers of compulsory acquisition
The main ancillary matter is that the Order seeks (1) powers of compulsory acquisition for land (and rights in or over land) that are
required for, facilitate or are incidental to the Onshore Scheme under sections 122 and 159 of the 2008 Act and (2) the power to override easements and other rights within the Order limits under sections
120(3) and (4) and paragraphs 2 and 3 of Schedule 5 of the 2008 Act. Justification for these powers is set out more particularly in the statement of reasons (Document Reference 4.1), which accompanies
the application.
4.3 Approach of book of reference and land plans
The book of reference
4.3.1 The application for the Onshore Scheme is accompanied by a “book of reference” as defined in Regulation 7 of the Infrastructure
Planning (Applications: Prescribed Forms and Procedure) Regulations 2009 (the “Regulations”). It should be read in conjunction with:
4.3.2 the Order (Document Reference 3.1); and
4.3.3 the twenty five “land plans” (Document Reference 2.1) with drawing nos. HUMBCC-2014-1-JH-SH1 to HUMBCC-2014-1-JH-SH25,
which also accompany the application.
4.3.4 The book of reference is split into five parts, listing (in summary):
8
(a) in Part 1, the plots of land over which powers of compulsory acquisition or temporary possession are sought for the
purposes of the authorised development. These plots together form the “Order land”, more particularly defined in article 2 of the Order;
(b) in Part 2, any persons who “would or might” be entitled to make a claim under section 10 of the Compulsory Purchase Act 1965 (the “1965 Act”) or Part 1 of the Land
Compensation Act 1973 (the “1973 Act”) as a result of the Order being implemented or as a result of the use of the land
once the Order has been implemented. The 1965 Act relates to claims that may be made by those persons who have no land taken but who have the benefit of a right over the Order
land and whose right is interfered with or breached by the construction or use of the authorised development in such a way as to depreciate the value of its own land. The 1973 Act
relates to claims by persons whose property is sufficiently close to be depreciated in value by execution of works for the authorised development;
(c) in Part 3, any persons who have rights over the Order land, which may be extinguished, suspended or interfered with due to the carrying out of the authorised development;
(d) in Part 4, any of the Order land in which the Crown has an interest; and
(e) in Part 5, any Order land which falls into a "special category",
i.e. forming part of a common, open space, National Trust land or fuel or field garden allotment.
4.3.5 The first page of each Part provides the statutory language
describing what it lists.
Types of land on the land plans
4.3.6 The land plans show three different types of land within the Order land:
(a) The land tinted dark grey is land which (if the Order is made)
may be subject to the exercise of compulsory acquisition powers (as further explained in paragraph 4.3.8 below). In addition to those compulsory acquisition powers, this land may
also be subject to the exercise of temporary possession powers for carrying out the authorised development generally and maintaining it (as further explained in paragraph 4.3.9
below), which includes in particular carrying out drainage works (as further explained in paragraph 4.3.10 below).
9
(b) The land tinted light grey is land which (if the Order is made) may be subject to the exercise of temporary possession
powers for carrying out the authorised development generally and maintaining it (as further explained in paragraph 4.3.9 below), which, again, includes in particular carrying out
drainage works (as further explained in paragraph 4.3.10 below). The differentiating feature of this type of land is that none of the land tinted light grey is land that may be subject
to the exercise of compulsory acquisition powers under the Order.
(c) The land shown cross-hatched may (if the Order is made) be subject to the exercise of temporary possession powers for drainage works (as further explained in paragraph 4.3.10
below). The differentiating feature of this type of land is that none of the cross-hatched land may be subject to the exercise of compulsory acquisition powers under the Order and the
purposes for which temporary possession powers may be exercised is narrower than that at paragraph 4.3.6(b) above.
4.3.7 In other words, the purpose of the differentiation above is to ensure
that the rights sought are proportionate to the requirements of constructing, operating and maintaining the authorised development on different parts of the Order land.
Compulsory acquisition powers and temporary possession
4.3.8 The compulsory acquisition powers to which the land tinted dark grey relate are conferred by articles 23-27 (inclusive) of the Order. These
are either:
(a) referred to in this book of reference as “Permanent Type 1” i.e. the acquisition of all interests and estates in the land;
and/or
(b) referred to in this book of reference as “Permanent Type 2”
i.e. the creation of the following permanent new rights in relation to the land in a 24.4 metres wide strip of land (within which a pipeline comprised in the authorised development (as
defined in article 2 of The Yorkshire and Humber (Carbon Capture and Storage Cross Country Pipeline) Order 201[●]) may be located):
(i) rights to construct lay inspect test maintain repair protect reconstruct replace dismantle remove or render unusable the authorised development in upon and over
the land;
10
(ii) rights to use the authorised development for the purposes for which it was designed;
(iii) rights to enter, pass and repass with or without vehicles over the said 24.4 metres wide strip of land for all purposes associated with these rights;
(iv) rights to prevent the planting or removal of any trees, bushes or other fauna within the said 24.4 metres wide strip of land which could damage or obstruct the
authorised development or obstruct the undertaker from exercising its rights and powers in relation to the
authorised development (and which for the avoidance of doubt shall not prevent the planting of conventional cereal crops);
(v) rights to prevent the construction of or remove any new building, structure or erection which is within the said 24.4 metres wide strip of land;
(vi) rights of continuous vertical and lateral support for the pipeline and ancillary apparatus (if any) within the said 24.4 metres wide strip of land;
(vii) rights to install, adjust, alter and remove cathodic protection test posts, aerial markers, field boundary markers transformer rectifier kiosks and electricity
cabinets.
4.3.9 Referred to in this book of reference as “Temporary - general”, the temporary possession powers to which the land tinted dark grey and
light grey relate are more particularly described in articles 28 and 29 and Schedule 9 of the Order and, in summary, authorise the temporary possession of the relevant land for the construction and
(for the duration of a five year maintenance period where the undertaker so chooses) the maintenance of the authorised
development on the terms set out in the those provisions.
4.3.10 Referred to in this book of reference as “Temporary - drainage”, the temporary possession powers for “drainage works” (defined in
article 2 of the Order) to which the land tinted dark grey and light grey and the land shown cross-hatched relate are more particularly described in articles 28 and 29 and Schedule 9 of the Order and, in
summary, authorise the temporary possession of the relevant land for the construction of the drainage works and (for the duration of a five year maintenance period where the undertaker so chooses) the
maintenance of the authorised development on the terms set out in the those provisions.
11
4.4 Statutory instrument
The Order seeks to apply and modify certain statutory provisions as
set out below in this explanatory memorandum, in particular in relation to compulsory acquisition, under section 120(5) of the 2008 Act. Accordingly, pursuant to section 117(4) of the 2008 Act, the
Order is set out in the form of a statutory instrument.
4.5 Other ancillary matters
Other ancillary matters include, for example, the maintenance and
operation of the Onshore Scheme, the improvement, alteration and temporary stopping up of lengths of existing highways necessary for
the Onshore Scheme, the creation of new private means of access, the interaction between leases of the Onshore Scheme and landlord and tenant law and provision for disputes and appeals under the
Order. These are more particularly described at paragraph 5 below.
5 THE DRAFT ORDER
The purpose and effect of the Order are summarised as follows:
5.1 Preamble to the Order
As with every statutory instrument, the Order is introduced by a preamble, which amongst other things, recites the powers under
which the instrument would be made.
5.2 Part I of the Order - Preliminary
Part I of the Order contains preliminary provisions.
Article 1 (citation and commencement) provides for the
commencement and citation of the Order.
Article 2 (interpretation) follows article 1 of the DCO Model Provisions and provides for the interpretation of words
and phrases used in the Order. The definitions in article 1 of the DCO Model Provisions have been amended and supplemented to reflect the particular
circumstances of the authorised development.
Amongst other things:
• “approved plans” means the plans listed in
Part 4 of Schedule 2 (plans) to the Order, with which the authorised development must be carried out in general accordance (unless
12
otherwise set out in the Requirements, for example where approval of detailed design is
to follow the making of the Order). The matter of approved plans is dealt with at Requirement 3 in Schedule 3 (requirements);
• The term “drainage works” is defined for the purposes of article 6(2), which clarifies that
these can be constructed within the Order limits;
• “Maintain” is defined as including “inspect,
examine, monitor, repair, set up, configure, clear, dismantle and/or reconstruct the authorised development and/or replace part
or a section of the authorised development with a part or section which materially serves the same purpose”. Save for “clear”,
“dismantle” “examine”, “monitor”, “set up” and “configure” all of these elements are derived from Article 1 of Schedule 2 to the
DCO Model Provisions. It is appropriate that maintenance should include the ability of the undertaker to inspect, examine and monitor
the authorised development to ascertain the extent of maintenance required. “Set up” and
“configure” relate to equipment and apparatus comprised in the authorised development. “Repair” and “dismantle”, by way of their plain
meaning, relate to development already constructed at the time of maintenance, rather than potential for the construction of
new development. It may be necessary to “clear” an area for the purposes of access for maintenance. “Reconstruct” is necessary,
particularly in the event that the authorised development, or part of it, were damaged such that reconstruction were required, and it
would not be appropriate in such circumstances for a nationally significant infrastructure project to require a new
development consent or planning permission, particularly when a plain English interpretation of “reconstruct” must relate to a
reconstruction of what had existed previously rather than unenvisaged development and, in
any event, article 5(a) (maintenance of authorised development) makes it clear that
13
the power to maintain is subject to the proviso that following reconstruction, the authorised
development may not, save in immaterial respects, vary from the description of it given in Schedule 1 (authorised development). “Replace”, again from the DCO Model Provisions, is qualified twofold: first by
clarification that replacement must be of part or a section of the authorised development with a part or section which materially serves
the same purpose (rather than by unenvisaged development, for example); secondly by way of the proviso at article 5(a)
that “maintenance” cannot vary from the description of the authorised development given in Schedule 1 (authorised development). The above amendments result in narrower wording than in the DCO Model Provisions and are permitted by section 120(5)(c) of the 2008
Act, as they give full effect to the power to maintain the authorised development under article 5 (maintenance of authorised development);
• the definition of “Order land” is brought in line
with section 159 of the 2008 Act, which clarifies that for the purposes of Part 7 of the 2008 Act, “land” includes any interest in or
right over land: it is appropriate that the same applies in this definition as the book of reference (Document Reference 4.3) provides
for the acquisition of both land and interests in and rights over land. Further, it is clarified that the land within the Order limits may also
be “used”, i.e. in accordance with temporary possession powers pursuant to articles 28 (temporary use of land for carrying out the authorised development) and 29 (temporary use of land for maintaining the authorised development).
• the definition of “relevant planning authority” has been amended to clarify that the relevant planning authority will be the district planning
authority for any area of land to which any particular provision relates; and for clarity on
the face of the draft Order, this article specifies who these bodies currently are;
14
• the definition of statutory undertaker removes references to sections 128 and 129 of the
2008 Act as these were repealed by the Growth and Infrastructure Act 2013.
• the definition of “watercourse” from article 2
of Schedule 1 of the DCO Model provisions relates only to article 19 (discharge of water), for which it was intended in the Model provisions, and has therefore been inserted at article 19(8)(b) for ease. The different
definition of watercourse provided here, however, relates to the means of laying the pipeline below the disused railway
embankment.
Paragraph (2) provides that apart from the definition of the “undertaker”, the definitions in paragraph (1) do
not apply to Schedule 10 (deemed marine licence under Part 4 of the Marine and Coastal Access Act 2009). This is because Schedule 10 has its own set of
definitions and, whilst the deemed marine licence is in law merely another schedule of the draft Order to be made by the Secretary of State, rather than the Marine
Management Organisation (“MMO”), in practice the licence is likely to be considered by contractors and
agents as a self-contained document. Significant cross-references to the draft Order would then be unduly complex. Moreover, if the licence is varied by the MMO
under section 72 (variation, suspension, revocation and transfer) of the Marine and Coastal Access Act 2009, the draft Order will become increasingly remote,
making cross-reference to it more burdensome.
Paragraph (3) specifies that the definition of “undertaker” in paragraph 1 does not apply to
Schedule 11 (protective provisions). This is because in Schedule 11, so as to avoid any confusion, National Grid Carbon is referred to as “the promoter” on the
basis that in protective provisions the term “undertaker” is commonly used to relate to the relevant statutory undertaker in whose favour the
protective provisions are made.
Further, it is clarified:
• at paragraph (4) that, as with recent DCOs,
including at article 1(2) of the Hinkley Point C
15
(Nuclear Generating Station) Order 2013, references to rights over land include rights in
relation to and under that land as well as above it;
• at paragraph (5) that all distances, directions
and lengths referred to in the Order, such as in the works plan, land plan and other
drawings, are approximate and distances between points on a work are to be taken to be measured along that work. In particular in
respect of scheduled linear works referred to in this Order all distances are measured along the indicative pipeline route as shown on the
works plans for that work. This is to ensure consistency between interpretation of the Order and the documents to which it refers;
• at paragraph (6) that all areas described in metres in the book of reference are approximate;
• at paragraph (7) that a reference in the Order to a work designated by a number, or by a combination of letters and numbers (for
example “Work No. 2”) is a reference to one of the works listed in Schedule 1 (authorised development);
• at paragraph (8) that a reference in the Order to a document or plan required to be
submitted for certification under article 49 (certification of plans etc.) is a reference to the version of that document or plan that has
been so certified;
• at paragraph (9) that a reference in the Order to legislation includes that legislation as
amended.
Article 3 (application, modification and disapplication of legislative provisions) has similar effect to article 6 of
Schedule 1 of the DCO Model provisions.
Paragraph (1) would provide for the application,
modification and exclusion of public general legislation set out in Part 1 of Schedule 12 (miscellaneous controls). This is only used as a drafting mechanism
for the purposes of SSSI consent, and for applying
16
certain regulations under the Pipeline Safety Regulations 1996 which would otherwise not apply to
the authorised development, as more particularly explained in respect of Schedule 12 below.
Paragraphs (2) to (4) would exclude byelaws and
statutory provisions of local application having effect, but only so far as these would be inconsistent with
powers exercised under the draft Order. Although the undertaker has made diligent efforts to search for relevant local legislation and byelaws, and sets out
certain known byelaws for specific exclusion at Part 2 of Schedule 12 (explained more particularly in respect of that Schedule below), such searches can never be
entirely definitive. Accordingly, paragraph (2) extends exclusion to any statutory provision of local application to avoid any unknown local legislation acting as an
impediment to the Onshore Scheme. For the avoidance of doubt, paragraph (3) further clarifies that certain key activities necessary for the construction,
operation and maintenance of the authorised development, which could otherwise be compromised by common provisions in local enactments or statutory
provisions of local application, are allowed under the Order.
As a safeguard, if the undertaker is notified that anything to be done under the Order would contravene a statutory provision of local application,
the undertaker has to respond within 14 days setting out whether it agrees that there would be a contravention and the grounds on which it believes the
article is excluded and the extent of that exclusion.
The provisions of this article may be made pursuant to section 120(5)(a) of the 2008 Act. That section
provides that an Order granting development consent may apply, modify or exclude a statutory provision which relates to any matter for which provision may be
made in the Order.
6 PART II OF THE ORDER - WORKS PROVISIONS
6.1 Principal powers
Articles 4 to 7 of the Order contain provisions for the principal powers needed for the authorised development.
17
Article 4 (development consent etc. granted by the Order) is based on Article 2 of Schedule 1 of the DCO Model
Provisions and grants development consent for the authorised development within the Order limits.
The authorised development means the development
under sections 14(1)(g) and 21 of the 2008 Act and associated development under section 115 of the 2008
Act. Schedule 1 (authorised development) describes the authorised development.
Development consent for the authorised development
is subject to the requirements set out in Schedule 3 (requirements).
Sub-paragraph (b) of the article provides for consent
to operate and use the authorised development for the purpose for which it is designed. Section 157(2) of the 2008 Act expressly allows the authorisation for use of
a “building” for the purpose for which it is designed. However, the authorised development includes key elements, such as the pipeline, which are not buildings
and therefore the clarification provided in sub-paragraph (b) is necessary. Such a paragraph may be included in the Order because such provision is
sensible and section 120(3) of the 2008 Act allows a draft Order to make provision relating to the
development for which consent is granted.
Article 5 (maintenance of authorised development) follows the wording of article 3 of Schedule 1 of the DCO Model
Provisions, providing for the maintenance of the authorised development, save that it clarifies for the avoidance of doubt that following maintenance
activities being completed the resulting works may not vary from the description of those works in Schedule 1 (authorised development).
Article 6 (limits of deviation) The works plans set out that the limits of deviation for where the pipeline is to be
located are narrower than the construction corridor, i.e. the Order limits, required for construction of the pipeline. Accordingly, in terms of lateral limits of
deviation, article 6 of Schedule 2 of the DCO Model Provisions has been tailored to clarify for the avoidance of doubt that whilst the ultimate location of
works themselves fall within the limits of deviation, the construction activities for those works may be carried
18
out anywhere within the Order limits. This does not apply to the drainage works: it is clarified in the article
that these may be located anywhere within the Order limits.
In terms of vertical limits of deviation:
• it should be noted that the Order does not use such limits in respect of development at above
ground installations as a proxy for the concept of a building envelope, where instead the conventional approach for defining built
development is adopted by way of Requirements 3 (approved details), 5 (Barmston Pumping Station) and 6
(Camblesforth Multi-junction design) and the approved plans listed in Part 4 of Schedule 2 (approved plans).
• paragraph (3) clarifies that aerial markers, cathodic protection test posts and field boundary markers may be up to 3 metres
high;
• paragraph (4) specifies that the authorised development may deviate vertically from
ground surface levels to any extent downwards as may be found to be necessary
or convenient. This wording is directly from article 6(b)(ii) of Schedule 2 of the DCO Model Provisions and article 5(b)(ii) of the TWA
Model Provisions. It is common in linear projects: see article 8(b)(ii) of the Network Rail (North Doncaster Chord) Order 2012 and
article 7(b)(ii) of the Network Rail (Ipswich Chord) Order 2012, for example. Although a minimum depth of cover, in terms of how
much ground must be kept above a pipeline, is relevant because of receptors above it, such as roads and rivers, for example (and such
depths of cover are secured by way of the description in relevant Work Nos. in Schedule 1 (authorised development)), the amount of
ground which is to lie beneath a pipeline does not need to be constrained. Indeed, an element of flexibility as to how deep a pipeline
is to be installed is necessary so that installation can be carried out in line with the
19
ground conditions ascertained during construction, and this is recognised in both
the DCO and TWA Model Provisions. In any event, there is no material prejudice to land ownership the deeper a pipeline is installed.
Article 7 (defence to proceedings in respect of statutory nuisance) follows article 7 of Schedule 1 of the DCO
Model Provisions and provides that no one can bring statutory nuisance proceedings under the Environmental Protection Act 1990 in respect of noise,
if:
• the noise relates to premises used by the undertaker for the purposes of or in
connection with the construction or maintenance of the authorised development and notice has been given under section 60 or
consent obtained under section 61 or 65 of the Control of Pollution Act 1974 or it is unavoidable; or
• the noise relates to premises used by the undertaker for the authorised development
and the authorised development is being used in accordance with a scheme for noise management approved by the relevant
planning authority as described in paragraph 15 of Schedule 3 (requirements) of the draft Order.
6.2 Benefit of Order
Articles 8 and 9 of the Order contain provisions relating to the benefit and transfer of the benefit of the Order.
Article 8 (benefit of Order) follows article 4 of Schedule 1 of
the DCO Model Provisions and would, subject to article 9 (transfer of benefit of Order) of the Order, grant only National Grid Carbon Limited the benefit of the Order
rather than allowing the benefit to run with ownership the land as envisaged by the 2008 Act.
Paragraph (2) excepts where works are carried out for
the benefit or protection of persons or land affected by the authorised development, so that it is clear that in these cases the benefit of the “planning permission”
20
equivalent of the Order, i.e. development consent, for those mitigation works is not personal to the
undertaker but also for the users of the relevant land.
Article 9 (transfer of benefit of Order) follows article 5 of
Schedule 1 of the DCO Model Provisions and would provide for the permanent or temporary transfer of the benefit of the Order, subject to the consent of the
Secretary of State and the transferee being subject to the same restrictions, liabilities and obligations placed upon National Grid Carbon under the Order.
6.3 Streets
Articles 10 to 18 of the Order contain provisions relating to streets.
Article 10 (street works) follows article 8 of Schedule 1 of the DCO Model Provisions and would confer, for the
purposes of the authorised development, authority on the undertaker to break open (including for the purposes of carrying out surveys); tunnel under; place
or change the position of apparatus or execute any works incidental to these works in or under certain streets, which are specified in Schedule 4 (streets subject to street works) and within the Order limits, for the purposes of the authorised development.
The authority given by this article is a statutory right
for the purposes of sections 48(3) (streets, street works and undertakers) and 51(1) (prohibition of unauthorised street works) of the New Roads and
Street Works Act 1991 (the “1991 Act”), which means that the Order replaces the need for a street works
licence under the 1991 Act.
Paragraph (3) confirms that the provisions of sections 54 to 106 of the 1991 Act apply to any street works
(as defined in that Act) carried out under this power apart from the following exceptions:
• an undertaker does not ordinarily need the
consent of the street authority for placing apparatus in a protected street if it has a street works licence (see section 61(2) of the
1991 Act). The equivalent of that licence is comprised in paragraph (1). Accordingly, sub-paragraph (3)(a) confirms that this means
21
that the undertaker does not need further consent from the highway authority for
placing apparatus in the course of the authorised development. This is necessary because the highway authority has identified
the A1034 and A1079 as “protected streets”, the pipeline will be crossing these and the
highway authority has in pre-application discussions not indicated any objection to that.
• sections 62(2) and 62(4) of the 1991 Act allow the Secretary of State following the designation of a protected street to require
removal or repositioning of apparatus already placed in the street, or if works are still in progress, to give directions in respect of
those. It is therefore sensible for sub-paragraphs (3)(b) and (c) to disapply these in relation to apparatus placed in the course of
the authorised development, in case streets in which the pipeline is placed are in future designated as protected streets, as the
pipeline is a nationally significant infrastructure project requiring certainty that it
will not have to be moved.
In this article, “apparatus” has the same meaning as in
Part 3 of the 1991 Act. However, for the purposes of the draft Order this has been expanded to include aerial markers, cathodic protection test posts and field
boundary markers as it will be necessary to place these along the pipeline route. Pipelines, transformer rectification kiosks and electricity cabinets are also
clarified as being included within the definition of “apparatus”.
Article 11
(power to alter layout, etc., of streets) is based on
article 6 of Schedule 2 of the TWA Model Provisions and would allow for the layout of the existing streets
specified in Schedule 5 (streets subject to alteration of layout) to be altered to ensure that these are appropriately configured to merge with the new roads
comprised in Work Nos. 4C, 3G, 6C, 8B, 9C, 11C, 12 and 14B which connect the AGIs to the existing highway network in Schedule 1 (authorised development) of the Order.
22
Paragraph (2) confers a broader power to alter the layout of any street within the Order limits for the
purposes of constructing and maintaining the authorised development. However, this broader power is limited by the consent of the street authority, not to
be unreasonably withheld or delayed.
This provision falls under item 15 of part 1 of Schedule
5 of the 2008 Act, namely the carrying out of civil engineering or other works, and is permitted to be included in the draft Order under Section 120(3) of the
2008 Act.
This provision is also necessary and expedient under Section 120(5)(c) of the 2008 Act to give full effect to
article 4 (development consent etc. granted by the Order) which authorises the new roads comprised in Work Nos. 3G, 4C, 6C, 8B, 9C, 11C, 12 and 14B in
Schedule 1 (authorised development) of the Order. Article 11 also has precedent in recent linear schemes authorised under the Transport and Works Act 1992
(e.g. at article 7 of the Network Rail Hitchin (Cambridge Junction Order) 2011) and the 2008 Act (e.g. article 10 of the Network Rail (North Doncaster
chord) Order 2012) and article 8 of The Lancashire County Council (Torrisholme to the M6 Link (A683
Completion of Heysham to M6 Link Road)) Order 2013.
Paragraph (4) is not from the DCO Model provisions but sets out a list of the types of works to streets
which may be carried out to the streets listed in Schedules 4 (streets subject to street works) and 5 (streets subject to alteration of layout). These include
the right to:
• demolish, remove, replace and relocate any bus shelter and associated bus stop
infrastructure;
• execute any works to provide or improve sight lines required by the highway authority;
• remove and replace kerbs and flume ditches for the purposes of creating permanent and temporary accesses;
• execute and maintain any works to provide hard and soft landscaping;
23
• carry out re-lining and placement of new temporary markings; and
• carry out works required that are incidental to those kinds of works.
These items are often added by promoters of
development consent orders into the list of works to be carried out pursuant to the power equivalent to a
street works licence under the 1991 Act, i.e. article 10 (street works) but such a licence relates to the placing of apparatus rather than works to streets of this kind
not necessarily related to the placing of apparatus; and for that reason these items are moved to this provision in respect of alterations of highway layout as the more
appropriate provision to which they relate. This element of the provision may be included in the Order because it provides for the carrying out of civil
engineering or other works related to the authorised development, as permitted by sections 120(3) and (4) together with item 15 of Part 1 of Schedule 5 of the
2008 Act. The provision is also necessary and expedient to give full effect to the power to carry out the authorised development under article 4 of the draft
Order (development consent etc. granted by the Order), as permitted under Section 120(5) of the 2008
Act.
Article 12 (construction and maintenance of new, altered or diverted streets) is based on article 10 of Schedule 2 of
the DCO Model Provisions and creates a mechanism whereby any new street constructed under the Order will, if notice has been served on the highway
authority, after a 12 month maintenance period, and provided that it is completed to the reasonable satisfaction of the highway authority be adopted for
maintenance at the public expense. The equivalent DCO Model Provision, article 10, has only been modified so that adoption is by notice rather than
automatic on the above criteria being met. This is because not all streets to be constructed under the
Order, such as the access roads to the AGIs, are to be adopted and the intention is for them to remain private, save for elements of junctions joining existing
highway to be determined following construction. Similar provision is made in paragraph (2) in the case of alterations and diversions, where it is expected that
24
the highway authority would require all such alterations or diversions to be adopted, so the DCO
Model Provisions are followed in this regard without reference to a notice system.
Paragraph (3) of this article provides that any street
constructed pursuant to the Order (which was not previously part of the public highway) will be deemed
as dedicated as public highway on prior notice being given to the highway authority (and if different the street authority). This is intended to make provision for
the dedication of new streets, or parts of streets, constructed under the Order. This mechanism for dedication is complementary to the mechanism from
the DCO Model Provisions at paragraphs (1) and (2), which instead relate to the terms on which:
• new streets (such as access roads to the
AGIs) are to be adopted as maintainable at the public expense by the local highway authority; or
• altered parts of streets (such as those which are altered or diverted in connecting AGI access roads to existing public highway) are to
be adopted as maintainable at the public expense by the local highway authority.
It is not proposed that any new streets constructed pursuant to the Order that will be private will also be left in the ownership of a third party land owner and
the book of reference (Document Reference 4.3) secures the relevant land.
Paragraph (4) of this article excludes from its scope
the structure of any bridge carrying a street as the responsibility for maintaining the structure of any bridge will remain with the owner of the relevant
bridge.
Following article 10 of Schedule 2 of the DCO Model Provisions, further incidental provision is made for the
undertaker to have a defence against claims for loss or damage resulting from failure to maintain any street under this article if he can prove that he took all care
reasonably necessary in the circumstances to ensure that the relevant part of the street was not dangerous to traffic. The article sets out factors which a court can
take into account in considering this defence. No
25
offence is created.
Article 13 (permanent stopping up of streets) follows article 9 of Schedule 1 of the DCO Model Provisions and would provide for the permanent stopping up of any street so
long as the prior approval of the local highway authority has been given.
In relation to such streets, the local highway authority
may require a substitute. There are other safeguards for where no substitute is to be provided for a street stopped up, including ensuring that the undertaker
either owns the land either side of the street being stopped up, there being no right of access hindered or there being another reasonably convenient access.
There is provision for compensation.
Where a section of street is stopped up, all rights of way over the street are extinguished and the
undertaker may use it for the purpose of the authorised development.
Article 14 (temporary stopping up of streets and public rights of way) follows article 11 of the DCO Model Provisions but has been expanded to deal also with public rights
of way because the DCO Model provisions contain no provision for the temporary stopping up of such rights of way but only for permanent extinguishment. This
would provide for either the temporary stopping up, alteration or diversion:
• of streets and rights of way (whether or not
within the Order limits) subject to the consent of the relevant local highway authority, which may attach reasonable conditions to that
consent but cannot unreasonably withhold or delay it;
• of those streets and rights of way listed in Schedule 6 (streets and rights of way etc. to be temporarily stopped up) to the Order,
following consultation with the relevant local highway authority.
The Order may make provision for the stopping up of
highways under sections 120(3) and 120(4) and item 17 of Part 2 of Schedule 5 of the 2008 Act. The rights of way to which this article refers are as much
highways for the purposes of item 17, being another
26
form of public highway, as the streets to which article 11 of the DCO Model Provisions refers and on which
this article is based.
Sub-paragraph (1)(a) of the article clarifies that both a class of traffic as well as traffic generally can be
diverted under this power and is included to reduce inconvenience to the public where possible.
This provision is necessary and expedient under section 120(5)(c) of the 2008 Act to give full effect to article 4 (development consent etc. granted by the Order) because the streets or rights of way listed at Schedule 6 (streets and public rights of way to be temporarily stopped up) need to be stopped up,
primarily to allow the laying of the cross-country pipeline across these.
Article 15 (apparatus and rights of statutory undertakers in permanently stopped up streets) is derived from article 32 of Schedule 1 of the DCO Model Provisions and would provide that the undertaker may, where a street
is permanently stopped up, require the statutory undertaker to relocate affected apparatus or provide
other apparatus in substitution for the existing apparatus. The statutory undertaker is to be reimbursed in such circumstances. Otherwise, a
statutory undertaker retains the same powers and rights in respect of its apparatus under permanently stopped up streets which it would have had if the
Order had not been made.
Article 16 (access to works) follows article 12 of Schedule 1 of the DCO Model Provisions and confers upon the
undertaker powers for the purposes of the authorised development to provide or improve access as specified
in Schedule 7 (access to works).
Similar powers are conferred in relation to any other locations within the Order limits reasonably required in
relation to the authorised development, provided that the relevant planning authority provides approval following consultation with the highway authority,
which is not to be unreasonably withheld or delayed.
Article 17 (traffic regulation) is not from the DCO Model Provisions, but is based on article 41 of Schedule 2 of
the TWA Model Provisions for tramways, i.e. for linear projects, and article 39 of the Network Rail (North
27
Doncaster Chord) Order 2012.
It would allow the undertaker to put in place
temporary and traffic regulation measures subject to the consent of the traffic authority should this be necessary for the purpose of the construction,
maintenance and operation of the authorised development, for example should the traffic authority
require traffic lights and/or a left turn sign only as a result of junction modifications comprised in the authorised development. It can be included in the
Order under sections 120(3) and 120(4) and item 20 of Part 2 of Schedule 5 of the 2008 Act.
Article 18 (agreements with street authorities) follows article 13
of Schedule 1 of the DCO Model Provisions and would allow the undertaker to enter into agreements with street authorities which could devolve the undertaker’s
powers under the Order to the authority in respect of the construction of new streets; the improvement of existing streets; the stopping up, alteration or
diversion of streets; and street works listed in the Order. Note that this power is a separate matter to
agreements under section 278 of the Highways Act 1980. Agreements under that section do not relate to powers under the Order but instead to a local highway
authority devolving its powers under that section to a developer, rather than the developer devolving its powers under the Order to a local highway authority,
which is the purpose of this article.
Sub-paragraph 1(b) departs from the DCO Model Provisions and clarifies that an agreement may relate
to strengthening, improving, repairing or reconstructing streets under the powers conferred by the Order. As permitted by section 120(5)(d) of the
2008 Act, this additional provision supplements the power in sub-paragraph 1(a) for an agreement to be entered into for the construction of a street as well as
article 5 of the Order (maintenance of authorised development), which would allow for such streets to
be repaired. It also has precedent in article 17 of the Nottingham Express Transit System Order 2009 and article 13 of the Network Rail (Hitchin (Cambridge
Junction)) Order 2011.
28
6.4 Supplemental powers
Articles 19 to 22 of the Order contain provisions relating to
supplemental powers.
Article 19 (discharge of water) follows article 14 of Schedule 1 of
the DCO Model Provisions and would enable the undertaker to discharge water into any watercourse, public sewer or drain in connection with the carrying
out and maintenance of the authorised development with the approval of the authority to which the
watercourse, public sewer or drain belongs and subject to certain other conditions.
For the purpose of this article, public sewers or drains
mean those which belong to the Environment Agency, an internal drainage board, joint planning board, local authority or a sewerage undertaker.
Paragraph (6) clarifies the wording from the equivalent paragraph of the DCO Model Provisions’ article 14 that nothing in this article requiring avoidance of releasing
impurities into public watercourses or drains requires the undertaker to maintain either these or private drains comprised in the authorised development:
whilst any private drains on land of which temporary possession is taken for the purposes of construction of the authorised development must be reinstated to the
satisfaction of the landowner pursuant to article 28(4), once the undertaker has vacated that land, the
responsibility for maintenance of any private drains on private land resides with the landowner, as it did prior to construction of the authorised development.
The definition of “watercourse” at article 2 of Schedule 1 of the DCO Model provisions is inserted at sub-paragraph 8(b) of this article for ease, rather than at
article 2 of this Order, as this meaning of watercourse is used only in this article.
Reference to section 85 of the Water Resources Act
1991, which appears in the DCO Model Provisions, has been deleted. This is because this section has been repealed by, inter alia, paragraph 8(a) of Schedule 26
of the Environmental Permitting (England and Wales) Regulations 2010 (the “Environmental Permitting Regulations”). Instead, paragraph (7) of the article is
updated to refer to the successor regime under the
29
Environmental Permitting Regulations. This approach was accepted by the Secretary of State in article 13(7)
of the Network Rail (Ipswich Chord) Order 2012 and at article 14(7) of the Rookery South (Resource Recovery Facility) Order 2011.
Article 20 (protective work to buildings) follows article 15 of Schedule 1 of the DCO Model Provisions and confers
on the undertaker the right at its own expense to carry out protective works to buildings within the Order limits before or during construction of the authorised
development, in the vicinity of the building and for up to five years after that part of the authorised development opens for use. Except in the case of
emergency, there are requirements for prior notice to be given to owners and occupiers.
Provision is also made for owners and occupiers to
serve counter-notices questioning the necessity of such protective works, with recourse to arbitration and provision for compensation.
Article 21 (authority to survey and investigate the land) follows article 16 of Schedule 1 of the DCO Model Provisions
and confers on the undertaker power to survey and investigate land, to make trial holes and remove soil samples, carry out ecological and archaeological
investigations, place on/leave on/remove apparatus for use in connection a survey, investigation or trial holes.
The power in the DCO Model Provisions is extended to
include the ability to take, and process, samples of water, air, soil or rock, flora, bodily excretions, non-human dead bodies, or any non-living thing present as
a result of human action found on, in or over the land. This wording is not contained in the DCO Model
Provisions. It reflects the wording of section 53(3A) of the 2008 Act which clarifies that the right to enter land for the purposes of surveying includes the power to
take and process certain types of samples. This may be included in a DCO under section 120(4) and item 12 of Part 1 of Schedule 5 of the 2008 Act, which makes
particular provision for the inclusion of powers for carrying out surveys or taking of soil samples.
The power to enter land and leave apparatus is subject
to a requirement on the undertaker to give at least 14 days’ notice to owners and occupiers of the land.
30
The undertaker may be asked to provide evidence of its authority to enter the land.
Trial holes cannot be made on public highway without the consent of the highway authority or on a private street without the consent of the street authority, not
to be unreasonably withheld or delayed. There is also provision for compensation payments.
Article 22 (removal of human remains) is based on DCO Model Provision article 17. It requires the undertaker, before it carries out any development or works which will or
may disturb any human remains in any land within the Order limits, to remove those remains. Before removing any human remains, the undertaker is
required to publish notice of its intention to do so. Notice is also required to be displayed near the site and, as soon as reasonably practicable, after its
publication a copy should be sent to the relevant planning authority.
Any relative or personal representative of any
deceased person whose remains are proposed to be removed from any land within the Order limits may
undertake the removal of the remains themselves and arrange for those remains to be re-interred or cremated, the undertaker being responsible for the
reasonable costs in doing so.
In the event that such relative or personal representative does not remove the remains, the
undertaker is required to comply with any reasonable request the relative or personal representative may make in relation to the removal and re-interment or
cremation of the remains.
Paragraph (12) clarifies that the removal of remains under this article must be carried out in accordance
with any directions which may be given by the Secretary of State.
Paragraphs (14) and (16) clarify that section 25 of the
Burial Act 1857 (bodies not to be removed from burial grounds save under faculty, without licence of
Secretary of State) and The Town and Country Planning (Churches, Places of Religious Worship and Burial Ground) Regulations 1950 (the “1950
Regulations”) are disapplied in relation to the
31
authorised development. This is because this legislation contains procedures for removing human
remains which conflict with or duplicate the procedures set out in the DCO Model provisions.
Paragraph (15) applies to this Order sections 238 and
239 of the 1990 Act, which ordinarily allow the use of consecrated land or burial grounds in accordance with
a planning permission notwithstanding ecclesiastical law, so that land acquired for the authorised development or temporarily used or in relation to
which rights are acquired, has the same benefit of those 1990 Act sections as it would have done if the Order had been a planning permission.
7 PART III OF THE ORDER - ACQUISITION AND POSSESSION OF LAND
7.1 Powers of acquisition
Articles 23 to 27 of the Order contain provisions for the compulsory acquisition of land and for the payment of compensation.
Article 23 (compulsory acquisition of land) follows article 18 of Schedule 1 of the DCO Model Provisions. It authorises
the compulsory acquisition of land shown on the land plan and described in the book of reference, so far as it is required for the authorised development, to
facilitate it or is incidental to it.
The article further makes provision for the discharge or suspension of rights, trusts and incidents to which the
land was previously subject so far as their continuance would be inconsistent with the exercise of the powers under this Order. “Suspension” is not included in the
relevant DCO Model Provision but is included here to allow the undertaker to minimise private rights
discharged where it is of the view that permanent discharge is not necessary. This is a more proportionate approach than article 18 of Schedule 1
of the DCO Model Provisions which would otherwise “cleanse” the title of even those rights which the undertaker considers consistent with the authorised
development.
Paragraph (3) of the article specifies that a person who suffers the loss of a private right of way under this
article is entitled to compensation, a paragraph which
32
is repeated in article 37 of the Order which specifically deals with the extinguishment of private rights of way.
These provisions both replicate articles 18(3) and 22(4) of Schedule 1 of the DCO Model Provisions. Specific reference to “private rights of way” only in this
article, duplicated in article 37, rather than to other private rights, mirrors articles 18(3) and 22(4) of
Schedule 1 of the DCO Model Provisions. The DCO Model Provisions in turn mirror section 236 of the 1990 Act (extinguishment of rights over land compulsorily
acquired), which states as follows:
(1) Subject to the provisions of this section, upon the completion of a compulsory acquisition of land under
section 226, 228 or 230—
(a) all private rights of way […] on, under or over the land shall be extinguished […]
(4) Any person who suffers loss by the extinguishment of a right […] shall be entitled to compensation from the acquiring authority.”
In other words, the equivalent articles 18 and 37 from the DCO Model Provisions imitate the elements of section 236 which extinguish private rights of way and
clarify that compensation in certain circumstances may be available for such extinguishment. It is not clear
why the DCO Model Provisions duplicate these elements in both articles 18 and 37 but the undertaker has no objection to following the tendentious approach
of the DCO Model Provisions in this regard. However, as per section 236, it is not necessary or appropriate to extend reference to compensation for other private
rights. Any person from whom an estate or interest in land is acquired compulsorily, i.e. who has a compensatable interest, has a right to a claim in
compensation. Nevertheless, it is an established principle of the compensation code that this right is not expressly stated in any statute, a large and
complex body of case law relates to it and seeking to set out such a general right in shorthand here would be unprecedented, unhelpful and inappropriate.
For clarity on the face of the Order, paragraphs 4, 5 and 6 reflect subsections 135(1) and (2) of the 2008 Act: no interest in Crown land may be acquired
pursuant to the Order unless the appropriate Crown
33
authority consents to the acquisition; moreover, the Order only applies to Crown land so far as the
appropriate Crown authority consents.
Article 24 (compulsory acquisition of rights) follows article 21 of
Schedule 1 of the DCO Model Provisions and would confer on the undertaker the power to acquire existing rights or create new rights in the Order land as
described in the book of reference.
Upon acquisition or vesting, land over which new rights are acquired is discharged from existing rights
insofar as the existing rights are inconsistent with the new rights.
A person who suffers the loss of a private right of way
under this article is entitled to compensation.
Paragraph (4) and Schedule 14 (modification of compensation and compulsory purchase enactments for creation of new rights) are not from the DCO Model Provisions but mirror the wording of article 27(3) and Schedule 11 of the Hinkley Point C (Nuclear Generating
Station) Order 2013. These impose modifications to the compulsory purchase and compensation provisions
under general legislation. They do not affect the entitlement to compensation, but generally ensure that the compensation procedure applies to the additional
categories of acquisition covered by the Order – the creation of new rights and the imposition of restrictive covenants in particular. This is a consequence of the
extension of land acquisition powers to these categories (done to allow lesser land interests to be acquired), and is commonplace in Transport and
Works Act orders and other compulsory purchase orders made by local authorities. For the purpose of section 126(2) of the Act, the relevant compensation
provisions are modified only to the extent necessary to ensure that they apply properly to the acquisition of rights, and not to affect the amount of compensation
to which landowners would be entitled.
Article 25 (acquisition of subsoil only) is based on article 24 of
Schedule 1 of the DCO Model Provisions and would authorise the undertaker to compulsorily acquire so much of, or such rights in, the subsoil of land referred
to in article 23(1) instead of acquiring the whole.
Further, the article confirms that in taking such a
34
subsoil interest, the undertaker would not be required to acquire an interest in any remaining part of that
land.
Article 26 (power to override easements and other rights) does
not derive from the DCO Model Provisions but closely mirrors section 237 of the Town and Country Planning Act 1990 (the “1990 Act”) in keeping with similar
approaches at article 25 of the Hinkley Point C (Nuclear Generating Station) Order 2013 and article 18 of the Rookery South (Resource Recovery Facility)
Order 2011.
This article addresses the fact that it is not clear whether the reference to discharging “rights, trusts
and incidents” in articles 23(2) (compulsory acquisition of land) and 24(2) (compulsory acquisition of rights) of the draft Order, taken from the DCO Model Provisions,
includes the discharge of items listed in section 237, namely easements, liberties, privileges, rights or advantages annexed to land and adversely affecting
any other land, including any natural right to support or restrictions as to the user of land resulting from a
contract. In particular, this resolves the doubt over the applicability of these provisions to restrictions on user.
This lack of clarity would not be a concern for a local planning authority promoting compulsory purchase powers to facilitate a development because under
section 237 it is entitled to carry out works on land which it has acquired or appropriated for planning purposes, notwithstanding any interference with the
items listed in that section. However, the undertaker in this draft Order is not a local planning authority, so it is necessary to apply section 237 in an amended form
appropriate to the proposed development.
Sections 120(3) and (4) and item 2 of part 1 of Schedule 5 of the 2008 Act confirm that the draft
Order may make provision, such as that in this article, relating to the compulsory suspension, extinguishment
or interference with interests in or rights over land. Moreover, this article is supplementary (under section 120(5)(d) of the 2008 Act) to articles 23 (compulsory acquisition of land) and 24 (compulsory acquisition of rights) of the draft Order and is necessary and expedient to give full effect to the development
35
consent in article 4 (development consent etc. granted by the Order) of the draft Order (as permitted by
section 230(5)(c) of the 2008 Act).
Sub-paragraphs 26(1)(a) and (b) mirror section 237(1).
The definition of “authorised activity” in this article is based on the list of activities in sections 237(1) and
237 (1A) of the 1990 Act but modified to be bespoke to the authorised development and the draft Order and its powers: sub-paragraphs 2(a) and 2(b) specify such
activities as being the erection, construction, carrying out, maintenance, or operation of any part of the authorised development or the exercise of any power
authorised by the Order. Sub-paragraph 2(c) clarifies that “use of any land” includes the “temporary use of land”. This gives full effect to the powers under articles
28 (temporary use of land for carrying out the authorised development) and 29 (temporary use of land for maintaining the authorised development) of
the Order, which ought to be capable of use without constraint by the interests etc, rights or restrictions described in paragraph (3) of this article.
Article 26(3) reflects section 237(2) of the 1990 Act but also applies to restrictions as to the user of land
arising by virtue of contract.
No drafting is included to reflect section 237(3), because it may be necessary to alter the apparatus of
statutory undertakers in accordance with the Order and the relationship between the undertaker and statutory undertakers is provided for in the protective
provisions included at Schedule 11 (protective provisions) of the Order.
Article 26(4) makes provision for compensation and is
based on section 237(4) of the 1990 Act and comments of the (now abolished) IPC in relation to the Rookery South (Resource Recovery Facility) Order
2011 in relation to removal of reference to the Land Clauses Consolidation Act 1845.
Section 237(6) of the 1990 Act is not reflected in the
article because the undertaker is not a local planning authority and, as the promoter of the authorised development itself, it will not have an indemnity
agreement from a promoter relating to compensation
36
liability.
Article 26(5) mirrors the wording of section 237(7) of
the 1990 Act.
Article 27 (application of the Compulsory Purchase (Vesting Declarations) Act 1981) follows article 23 of the DCO Model Provisions and would provide for the application, with modifications, of the Compulsory Purchase
(Vesting Declarations) Act 1981 (in this paragraph the “1981 Act”), which makes provision for vesting procedures for land subject to compulsory purchase.
Some wording has been added to this article to ensure that the 1981 Act is applied properly to the undertaker and the draft Order. This is because article 23(1) of
the DCO Model Provisions was drafted on the assumption that the undertaker is a public authority under section 1(2) of the 1981 Act. However, as the
undertaker is not a public authority, the additional wording has been included to clarify that it is to constitute a public authority for the purposes of the
1981 Act, so that its vesting procedures would apply to the Order.
It is noted that the draft Order does not contain an express provision incorporating Part I of the Compulsory Purchase Act 1965. This is because section
125 of the 2008 Act already applies that Part to a development consent order authorising the compulsory acquisition of land.
7.2 Temporary possession of land
Articles 28 to 29 of the Order contain provisions for the temporary possession of land for the purposes of or in connection with the
authorised development.
Article 28 (temporary use of land for carrying out the authorised development) follows article 28 of Schedule 1 of the DCO Model Provisions and confers upon the
undertaker a right to enter on and take possession of:
• land specified in Schedule 9 (land of which temporary possession may be taken) to carry
out those elements of the authorised development listed in that Schedule. This is
37
the land tinted light grey or shown cross-hatched on the land plans (Document
Reference 4.3);
• any other Order land where no notice of entry has been served and no general vesting
declaration made, i.e. where compulsory acquisition powers have not yet been
exercised. This is the land tinted dark grey on the land plans (Document Reference 4.3).
This approach means that the undertaker may use
temporary use powers to construct the authorised development in the particular Order land described in paragraph 28(1)(a)(ii) and, following construction,
once the exact location of the pipeline is known, the undertaker may compulsorily acquire the 24.4 metre wide easement strip required for the ongoing use,
access and maintenance of the pipeline.
This approach does not preclude the undertaker from instead both (i) exercising its compulsory acquisition
powers pursuant to article 24 (compulsory acquisition of rights) to acquire the 24.4 metre wide easement strip for carrying out the authorised development (i.e.
laying the pipeline) and at the same time (ii) pursuant to temporary use powers also taking possession of
land necessary for construction in the wider Order limits described in paragraph 28(1)(a)(ii) outside of that easement strip. In this way, the minimum width of
land possible will be burdened by the permanent rights comprised in the easement strip. This is because, once the pipeline has been located in that 24.4 metre wide
easement strip, the remaining land of which possession was taken only temporarily for construction will be returned to its owners in accordance with this
article without being subject to permanent rights.
The AGIs are likely to be subject to compulsory acquisition alone but circumstances may arise in which
it is sensible to make provision for temporary possession powers as well, so as not to burden any land with permanent rights where this can be avoided.
Both of the above alternatives allow flexibility for the undertaker; at the same time, for landowners they allow the compulsory acquisition of land or rights to
match the final location of the authorised
38
development, which in certain Work Nos., such as the pipeline, will not extend to the full width of the limits
of deviation, whilst allowing land necessary for carrying out the authorised development to be returned to its owners after only temporary use.
Separately, land listed in paragraph 28(1)(a)(i), by way of a Schedule in the Order, i.e. the land tinted light
grey or shown cross-hatched on the land plans (Document Reference 4.3), relates to areas where there are to be no permanent works remaining
following construction and temporary use is necessary for the duration of construction only, with no subsequent permanent rights or land to be taken
compulsorily (although protective works and surveys, it is clarified, can still be carried out on that land pursuant to articles 20 (protective work to buildings) and 21 (authority to survey and investigate the land).
Use of the two paragraphs 28(1)(a)(i) and (ii) is a slightly different drafting approach to the Model DCO
Provisions but has the same effect: it simply means that it is not necessary to schedule out in Schedule 9 (land of which temporary possession may be taken) all
plots set out in the book of reference but only those where no permanent rights or land are subsequently to
be taken. This approach also allows the under taker to provide clarity to the owners of paragraph 28(1)(a)(i) plots that the proposals affect their land only in terms
of temporary use and not the compulsory acquisition of rights over land or of land itself. Separately, the owners of paragraph 28(1)(a)(ii) plots know that the
easement strip could be located on their land but other than that 24.4m strip, possession rights for construction will be only temporary, pursuant to this
article. This approach has previously been adopted at article 23 of the Network Rail (Ipswich Chord) Order 2012, article 40 of the Able Marine Energy Park
Development Consent Order 2014 and article 23 of the Network Rail (Redditch Branch Enhancement) Order 2013.
Sub-paragraphs (1)(b), (c) and (d) further confer upon the undertaker the right to remove any building and vegetation, construct temporary works and buildings
and carry out any mitigation works specified in Schedule 9 (land of which temporary possession may be taken).
39
Prior notice to owners and occupiers is required and the article makes further provision for restoring land
after temporary use and compensation.
The article clarifies at paragraph (3) that the undertaker may not (unless the landowners agree)
remain in possession:
• in relation to the land specified in Schedule 9
(land of which temporary possession may be taken), i.e. where no permanent land or rights are to be taken, for longer than one year after
the authorised development has been completed; or
• in relation to other Order land, i.e. where
permanent land or rights might be taken, for longer than one year after the authorised development has been completed, unless the
undertaker exercises compulsory acquisition powers over it by serving a notice of entry or making a general vesting declaration.
Paragraph (3) amends the DCO Model Provision equivalent so that the year runs from when the undertaker has certified that the entire Onshore
Scheme is first capable of being brought into operational use for the purpose for which it was
designed rather than from when the works on that land in isolation are complete. This is a critical amendment for a linear scheme such as a cross-
country pipeline where construction on any given element is not complete, potentially requiring testing, back-checks and further works (as necessary)
depending on construction matters arising further down the line, until the entire linear scheme can be considered to be complete. The undertaker is best
placed to certify such completion and, in practice, the compensation provision at paragraph 5 means that there can be confidence that undue delay in issuing
appropriate certificates would be minimised.
Paragraph 11 also clarifies that nothing in this article prevents the taking of possession more than once in
relation to land specified in Schedule 9 (land of which temporary possession may be taken).
Sub-paragraph 4(b) and (c) extend the DCO Model
40
Provisions to clarify that in restoring land, the undertaker does not have to restore areas where
permanent mitigation works listed in Schedule 9 (land of which temporary possession may be taken) remain and also cannot be required to remove ground
strengthening works.
Sub-paragraphs (8)(a) and (b) expand the DCO Model
Provisions to clarify that even though land listed in paragraph (1) cannot be acquired, the undertaker can still carry out protective works and surveys under other
provisions of the Order.
The additions to this article may be included under section 120(3) of the 2008 Act as they make important
provision for the development for which consent is sought, namely in respect of rights required for its construction.
Article 29 (temporary use of land for maintaining the authorised development) follows article 29 of Schedule 1 of the DCO Model Provisions and provides that the
undertaker may take temporary possession of land within the Order limits reasonably required for the
purpose of maintaining the authorised development and constructing such temporary works and buildings on the land as may be reasonably necessary.
Sub-paragraph 1(b) of the article extends article 29 of the DCO Model Provisions to include a right to enter on any land within the Order limits for the purpose of
gaining access where this is reasonably required to maintain the authorised development. This supplemental provision clarifies that the undertaker
can secure appropriate access within the Order limits to those parts of the authorised development which need to be maintained, giving full effect to the
maintenance powers granted under sub-paragraph (1)(a).
This article is subject to safeguards:
• The above powers may only be exercised during the “maintenance period”. As per
article 29(12) of Schedule 1 of the DCO Model Provisions this is 5 years but this runs from the date on which the entire authorised
development is first brought into operational use for the purpose for which it was designed
41
rather than the completion of only a part of it. This amendment to the DCO Model Provision
equivalent is critical for a linear scheme such as a cross-country pipeline where the maintenance period cannot be allowed to run
in a “rolling” set of consecutive dates when the scheme must be treated as an interacting
whole, with issues (if any) in one location potentially requiring attention further down the line on sections completed earlier;
• Provision is made for notice, restoration and compensation;
• The undertaker must give 28 days’ notice
before entering on and taking temporary possession of land for the purposes of maintenance, except where there is an
identified potential risk to the safety of the authorised development, the public or the surrounding environment (in which case such
notice, if any, as is reasonably practicable should be given).
7.3 Compensation
Articles 30 to 32 of the Order contain provisions clarifying existing principles of compensation in relation to the compulsory acquisition
and temporary possession of land in connection with the authorised development.
Article 30 (disregard of certain interests and improvements) is not contained in the DCO Model Provisions but follows article 26 of Schedule 1 of the TWA Model Provisions.
It would provide for disregarding certain interests in and enhancements to the value of land for the
purposes of assessing compensation with respect to its compulsory acquisition, where the creation of the interest or the making of the enhancement was
designed with a view to obtaining compensation or increased compensation.
It complies with section 126 (Compensation for compulsory acquisition) of the 2008 Act as it does not have the effect of modifying or excluding the application of an existing provision relating to
42
compulsory purchase compensation.
The wording of this article mirrors section 4
(Assessment of compensation) of the Acquisition of Land Act 1981 (in this paragraph the “1981 Act”). It is necessary to specifically apply the effect of section 4
of the 1981 Act in the draft Order. This is because the 1981 Act only applies to a compulsory purchase to
which any other statutory instrument has applied its provisions section 1 (application of Act)) and neither the 2008 Act nor the DCO Model Provisions apply
section 1 of the 1981 Act to the draft Order.
Sections 120(3) and 120(5)(a) and item 36 of part 1 of Schedule 5 allow the application in an Order of
statutory provisions which relate to the payment of compensation.
Article 31 (set-off for enhancement in value of retained land) is not contained in the DCO Model Provisions but follows article 27 of Schedule 1 of the TWA Model Provisions.
It would provide that in assessing the compensation
payable to any person in respect of the acquisition of any land, the Lands Chamber of the Upper Tribunal
shall set off against the value of the acquired land any increase in value of any contiguous or adjacent land belonging to that person arising out of construction of
the authorised development.
These provisions comply with section 126(2) of the 2008 Act. This is because it does not have the effect of
modifying the application of an existing provision relating to compulsory purchase compensation. The principle in this article is established in section 7 of the
Land Compensation Act 1961 (effect of certain actual or prospective development of adjacent land in same ownership), which needs to be applied. Sections
120(3) and 5(a) and item 36 of part 1 of Schedule 5 allow the application in an Order of statutory provisions which relate to the payment of
compensation.
Article 32 (no double recovery) is not contained in the DCO
Model Provisions but predominantly follows article 44 of the TWA Model Provisions.
It provides that compensation is not payable both
under this Order and other compensation regimes for
43
the same loss or damage.
In addition, this article provides that there is to be no
double recovery under two or more different provisions of this Order, precedence for which can be found in numerous TWA Orders.
The principle of equivalence, namely that a claimant in a compulsory purchase matter shall be compensated
for no more and no less than his loss, is long established and no part of the compensation code conflicts with this principle.
Accordingly, this article complies with section 126(2) of the 1990 Act and is a supplementary provision under section 120(5)(d) of the 2008 Act as well as a
provision relating to the payment of compensation under sections 120(3) and (4) and item 36 of Part 1 of Schedule 5 of the 2008 Act.
7.4 Supplementary
Articles 33 to 40 of the Order contain supplementary provisions relating to the compulsory acquisition provisions in Part III of the
Order.
Article 33
(acquisition of part of certain properties) follows article 26 of Schedule 1 of the DCO Model Provisions, replaces section 8(1) of the Compulsory Purchase Act 1965 and
would enable the undertaker to acquire a part rather than the whole of properties subject to compulsory acquisition.
Further, it contains a procedure enabling the relevant
owner to require the whole to be taken, in certain circumstances, with disputes to be determined by the Lands Chamber of the Upper Tribunal.
Article 34
(statutory undertakers) is based on article 31 of Schedule 1 to the DCO Model Provisions. It authorises the undertaker
to (1) compulsorily acquire land belonging to statutory undertakers shown on the land plans, (2) remove or reposition any statutory undertakers’ apparatus, where it is
anywhere within the Order limits and (3) acquire compulsorily new rights over land belonging to statutory undertakers.
Sections 120(3) and (4) together with item 14 of part 1 of
44
Schedule 5 of the 2008 Act allow particular provision relating to the removal, disposal or re-siting of apparatus.
Article 35
(recovery of costs of new connections) follows article 33 of Schedule 1 of the DCO Model Provisions and would provide
for an owner or occupier of premises to recover from the undertaker the costs of reconnecting to public utilities/communications services if these are removed
pursuant to article 34 of the Order (statutory undertakers).
Article 36
(time limit for exercise of authority to acquire land compulsorily) follows article 20 of Schedule 1 of the DCO
Model Provisions and would impose a time limit of eight years from the Order coming into force for the exercise of the proposed powers of acquisition and temporary
possession. Sections 154(3) and (4) of the 2008 Act and regulation 3 of the Infrastructure Planning (Miscellaneous
Prescribed Provisions) Regulations 2010 allow the Order to prescribe a period longer than five years for exercise of such powers. Eight years is considered to be necessary in
respect of the Order for the reasons set out in the statement of reasons (Document Reference 4.1) which accompanies the application for the Onshore Scheme.
Article 37
(private rights of way) follows article 22 of Schedule 1 of the DCO Model Provisions and enables extinguishment of private rights of way over land subject to compulsory
acquisition under the Order.
Private rights of way over land of which the undertaker takes temporary possession are suspended and
unenforceable for as long as the undertaker remains in lawful possession of the land. There is no need to amend
this article from the DCO Model Provisions to refer to other types of private right as these are addressed in articles 23(2) and 24(2).
This provision can be disapplied by a notice from the undertaker or by agreement with the owner of the right of way.
It also makes provision for persons suffering loss as a result of the suspension or extinguishment of such private rights of way to be entitled to compensation.
Article 38
(rights under or over streets) follows article 27 of Schedule 1 of the DCO Model Provisions and provides that the undertaker may use the subsoil under and airspace over a
street required for the authorised development without
45
being required to acquire any part of the street or any easement or right in the street.
Provision is made for compensation.
Article
39
(incorporation of the mineral code) is derived from article
19 of the DCO Model Provisions. Part 2 of Schedule 2 of the Acquisition of Land Act 1981 (in this paragraph the “1981 Act”) would be incorporated into the Order to provide that
the undertaker would not be entitled to any mines of coal, ironstone, slate and other minerals under the land acquired under the draft Order unless they have been expressly
purchased, apart from minerals necessarily extracted or used in the construction of the authorised development. Part 3 of Schedule 2 of the 1981 Act regulates the
relationship between the owner of the mines which lie below the land taken for the authorised development and the undertaker.
Article 40
(open space) Under section 132 of the 2008 Act, an order granting development consent is subject to special
parliamentary procedure to the extent that it authorises the compulsory acquisition of a right over land, forming part of, amongst other things, open space, unless:
• the Secretary of State is satisfied that certain statutory criteria under that section apply; and
• his satisfaction and the relevant subsection are
recorded in the Order.
Land referencing commissioned in connection with the Onshore Application has identified that there are potentially
three plots listed in the book of reference (Document Reference 4.3) accompanying the application for the Onshore Scheme which constitute open space and in
respect of which the Order authorises the compulsory acquisition of rights. These are Plots 232, 233 and 268.
The letter from Berwin Leighton Paisner LLP on behalf of the undertaker dated June 2014 to the Secretary of State, care of the National Planning Casework Unit, contains an
application setting out the subsection of section 132 which the undertaker submits apply to these Plots, with supporting information for this view.
If the Secretary of State concurs with the undertaker’s submissions in that letter, he is invited pursuant to section 132 to record his satisfaction and the relevant subsection in
46
the form proposed in Schedule 8 (record of the satisfaction of the Secretary of State pursuant to section 132 of the 2008 Act) of the Order.
8 PART IV OF THE ORDER - MISCELLANEOUS AND GENERAL
Articles 41 to 53 of the Order contain a number of miscellaneous and general provisions.
Article 41 (application of landlord and tenant law) follows article 35 of Schedule 1 to the DCO Model Provisions and would override the application of landlord and tenant
law in so far as it may prejudice the operation of any agreement for leasing the whole or part of the authorised development or the right to operate the
same and any agreement for the construction, maintenance, use or operation of the authorised
development or any part of it entered into by the undertaker.
Article 42 (deemed consent under Part 4 (Marine Licensing) of the Marine and Coastal Access Act 2009) does not make reference to deemed consent under section 34 of the Coast Protection Act 1949 as per article 37 of
Schedule 1 of the DCO Model Provisions. This is because that provision has been repealed by the Marine and Coastal Access Act 2009 (the “2009 Act”).
Section 149A of the 2008 Act allows provision in a development consent order for a deemed marine licence under the 2009 Act.
Accordingly, this article would constitute deemed consent under section 65 of the 2009 Act, the
successor provision to section 34 of the Coast Protection Act 1949.
Schedule 10 (deemed Marine Licence under Part 4 (Marine Licensing) of the Marine and Coastal Access Act 2009) sets out the terms on which the deemed licence would be granted by the Secretary of State.
The Marine Management Organisation has reviewed the form of licence and discussions between it and the undertaker in respect of the application are ongoing.
The terms of the licence are explained more particularly below in this explanatory memorandum where Schedule 10 is explained.
47
For information, an overlay of the deemed marine licence coordinates over the relevant works plans with
drawing number 10-2574-GND-01-05-0056 Rev A accompanies the Onshore Scheme application (Document Reference 2.7).
Article 43 (operational land for the purposes of the 1990 Act) follows article 36 of Schedule 1 of the DCO Model
Provisions and provides that, for the purposes of section 264(3)(a) of the 1990 Act, the development consent granted by the Order is to be treated as
specific planning permission.
Article 44 (felling or lopping of trees or shrubs) follows article 39 of Schedule 1 of the DCO Model Provisions (save in
relation to hedgerows). It would enable the undertaker to fell or lop trees and shrubs for the purposes of
preventing obstruction or interference with the authorised development and danger to people constructing, maintaining, operating or using the
authorised development. In the case of unnecessary damage, provision is included for the payment of compensation for loss or damage.
Reference to “passengers” at sub-paragraph (1)(b) of the equivalent DCO Model Provision has been removed as this is not relevant to the authorised development.
This article departs from the DCO Model Provisions in that paragraphs (3) to (6) remove the need to obtain a hedgerow licence under the Hedgerow Regulations
1997. The removal of hedgerows shown on the hedgerow plans (Document Reference 2.5) is instead to be consented in this article or, should the removal
of any hedgerows other than those shown on the hedgerow plans be required (if any), consent from the
local planning authority will be needed. This is similar to the approach taken at article 15 of the Brechfa Forest West Wind Farm Order 2013. Section 120(5)(a)
of the 2008 Act enables a DCO to exclude a statutory provision which relates to any matter for which provision may be made in the Order. Sections 120(3)
and (4) together with item 15 of Part 1 of Schedule 5 of the 2008 Act allow a DCO to make a provision for carrying out civil engineering or other works. The
authorised development, a civil engineering work, will necessitate the removal of hedgerows, particularly for
48
the laying of the pipeline. Accordingly, the Hedgerow Regulations 1997 are excluded under the Order.
Article 45 (trees subject to tree preservation orders) departs from article 40 of Schedule 1 of the DCO Model
Provisions in that the undertaker has assessed the Order limits and determined that no trees subject to an existing tree preservation order will be adversely
affected by the carrying out of the authorised development. However, the undertaker considers that it would be prudent and sensible to include a provision
allowing it to fell or lop any tree, or cut back its roots, which has been made the subject of a tree preservation order since the date of its application for
development consent. This power will only be exercisable where the undertaker reasonably believes it to be necessary to prevent obstruction or
interference with the construction, maintenance or operation of the authorised development or to prevent a danger to people constructing, maintaining,
operating or using the authorised development.
The permission granted by the article would constitute
a deemed consent under a tree preservation order.
Article 46 (Resumption of land use following certain works) is derived from article 10 of the Hinkley Point C (Nuclear
Generating Station) Order 2013. It is intended for the protection of landowners so that after their land has been used under temporary possession powers for
office accommodation and pipe stores, for example, irrespective of the duration of that use, it will be clear that they do not need planning permission to resume a
use which predated the making of this Order. This is done by appropriately applying section 57(2) of the
Town and Country Planning Act 1990 - this clarifies that where planning permission is granted for a limited period, once it expires, permission is not needed for
the original use.
Article 47 (application of the Community Infrastructure Levy) provides that the Order is to be treated for the
purposes of the Community Infrastructure Levy Regulations 2010 as a planning permission granted for a temporary period. The community infrastructure levy
(CIL) is not chargeable on temporary planning permissions, so this would have the effect of excluding the authorised development from the CIL charging
49
provisions. Similar provision was made in article 11 of the Hinkley Point C (Nuclear Generating Station) Order
2013.
Article 48 (protective provisions) gives effect to Schedule 11
(protective provisions) which would contain specific safeguards for statutory undertakers within the Order limits.
Article 49 (certification of plans etc) follows article 41 of Schedule 1 of the DCO Model Provisions and would require the undertaker to submit copies of key
documents referred to in the Order to the Secretary of State for certification as true copies following the making of the Order.
Article 50 (service of notices) would make provision as to the manner in which notices or other documents required
or authorised to be served under the Order are to be served.
The article mirrors section 229 of the 2008 Act (which
applies only to notices under that Act rather than under an Order made under it) and its inclusion is permitted as an incidental provision under section
120(5)(d) of the 2008 Act.
Article 51 (arbitration) follows article 42 of Schedule 1 of the
DCO Model Provisions and would make provision for differences or disputes arising under any provision of the Order to be settled by arbitration.
Additional wording is included to exclude differences or disputes referred to the Lands Chamber of the Upper Tribunal (because that is the appropriate forum for
disputes relating to the compensation relating to the compulsory acquisition of land and rights etc.) and allows parties to agree to methods of dispute
resolution other than arbitration.
There is significant precedence for such additional wording in TWA Orders and has been accepted in
recent development consent orders, including at article 42 of The Lancashire County Council (Torrisholme to the M6 Link (A683 Completion of Heysham to M6 Link
Road)) Order 2013. Sections 120(3) and (4) together with item 37 of part 1 of Schedule 5 of the 2008 Act also permit the inclusion of provisions relating to the
submission of disputes to arbitration.
50
Further, the DCO Model Provision equivalent has been amended so that if the parties fail to agree on an
arbitrator, one will be appointed by the Secretary of State rather than the Institute of Civil Engineers. This approach was proposed by PINS and was followed at
article 34 of the National Grid (King’s Lynn B Power Station Connection) Order 2013.
Article 52 (requirements) introduces Schedule 3 (requirements) which contains requirements corresponding to conditions which, under section 120(2) of the 2008
Act, could have been imposed on the grant of planning permission for the authorised development had it not fallen within the 2008 Act planning regime.
Such requirements may be imposed in the Order under section 120(1) of the 2008 Act.
Paragraph (2) has been added to the article as part of
the mechanism within the Order of dividing the authorised development between those parts subject to the Requirements in Schedule 3 (requirements), with the local planning authorities as the appropriate approving bodies, and those parts subject to the
deemed marine licence conditions in Schedule 10 (deemed Marine Licence under Part 4 (Marine Licensing) of the Marine and Coastal Access Act 2009)
with the MMO as the appropriate approving body.
Paragraph (2) therefore clarifies that the Requirements at Schedule 3 (requirements) will not apply to parts of
the authorised development which fall within the UK marine area (apart from the listed exceptions, which should apply across all the Work Nos. irrespective of
whether they fall within the UK marine area or otherwise). This is because, for the most part, it is appropriate for areas submerged at mean high water
springs that the authorised development should be governed only by the licence conditions attached to the marine licence at Part 2 of Schedule 10 (deemed Marine Licence under Part 4 (Marine Licensing) of the Marine and Coastal Access Act 2009), so as to avoid
inconsistency with the Requirements.
Article 53 (procedure in relation to certain approvals etc.) gives effect to Schedule 15 (appeals relating to decisions made by certain authorities pursuant to this order) which is not derived from the DCO Model Provisions
51
but follows the wording of article 46 and Schedule 14 of the Hinkley Point C (Nuclear Generating Station)
Order 2013.
The Schedule sets out procedures for determinations made by the relevant discharging authority pursuant
to:
• the Requirements set out in Schedule 3
(requirements);
• the deemed marine licence conditions in Schedule 10 (deemed Marine Licence under Part 4 (Marine Licensing) of the Marine and Coastal Access Act 2009);
• consent from the relevant planning authority
in respect of the removal of hedges not set out on the hedgerow plan (if required) pursuant to article 44;
• provisions in the Order requiring the consent of the highway authority in respect of street works (including pursuant to consents under
the incorporated provisions of the 1991 Act), the alteration of layout of streets, the construction and maintenance of streets, the
temporary and permanent stopping up of streets, traffic regulation or where consent is
required for surveying land comprised of highway;
• the issuing of notices and consents under the
Control of Pollution Act 1974 (“COPA”).
Paragraph (1) sets out timescales for determinations. These mirror those in article 29(2)(b) (time periods for decision) of the Town and Country Planning (Development Management Procedure) (England) Order 2010, namely 8 weeks, other than in respect of
COPA applications, which mirror the 28 days in section 62 of COPA. Reasonable timescales for requests for information are also addressed.
Paragraph (2) sets out the fee to be paid in relation to the discharge of Requirements, as no provision is made in existing legislation – the fee follows the
equivalent charge for conditions attached to planning permissions in the Town and Country Planning (Fees
52
for Applications, Deemed Applications, Requests and Site Visits) (England) Regulations 2012. Scope is
provided for the fee to increase in line with amendments to those Regulations over time pursuant to sections 303 (fees for planning applications etc.)
and 333(2A) (regulations and orders) of the 1990 Act. Fees for other consents to which this Schedule relates
are provided for directly in existing legislation, unlike Requirements pursuant to a development consent order.
Paragraph (3) sets out an appeal procedure to the Secretary of State which may be exercised in circumstances which mirror the wording of sub-
sections 78(1) and (2) of the 1990 Act (right to appeal against planning decisions and failure to take such decisions), extended to:
• where the undertaker does not agree that requests for information are reasonable:
• deemed marine licence conditions (which are,
as described in this explanatory memorandum, simply terms of the Order in the same way as Requirements, are the only
difference being that the Secretary of State has designated a specialist discharging
authority different to the relevant planning authority, namely the MMO, because of its particular marine expertise); and
• if a notice further to section 60 of COPA is issued.
The process for appeals in sub-paragraph 3(2) is
broadly similar to the Town and Country Planning (Appeals) (Written Representations Procedure) (England) Regulations 2009, save that timescales are
shorter proportionate to the need for expedition for nationally significant infrastructure projects and to the fact that appeals would not relate to entire applications
for planning permission but to narrower consents.
The DCO Model Provisions provide for items required under requirements to be submitted to the former IPC
for approval. However, CLG Guidance for local authorities states that a draft Order can allow scheme promoters to appeal local authority decisions on a
subsequent approval as with previous regimes.
53
Indeed, it is now common practice for such an article to be included in Orders made under the 2008 Act: in
addition to the Hinkley Point C (Nuclear Generating Station) Order 2013, this approach was accepted in the Rookery South (Resource Recovery Facility) Order
2011, Network Rail (Ipswich Chord) Order 2012 and the Network Rail (North Doncaster Chord) Order 2012;
and Schedule 16 may be included in the draft Order as a supplementary provision under section 120(5)(d) of the 2008 Act.
9 SCHEDULES
Schedules 1 to 15 of the Order contain information referred to in the articles of the Order.
Schedule 1 (authorised development) lists out the particular Work
Nos. comprised in the authorised development for which development consent is sought and which are to be read alongside the works plans. See paragraphs
3.1 to 3.5.15 above for further explanation.
Schedule 2 (plans) lists the works plans, land plans, access plans, and other plans submitted for approval (including
plans where only certain parts are for approval).
Other indicative and illustrative plans will be provided as part of the application.
This approach to scheduling plans has precedence in Part 2 of Schedule 1 of the Hinkley Point C (Nuclear Generating Station) Order 2013.
Schedule 3 (requirements) contains requirements corresponding to conditions which, under section 120(2) of the 2008
Act, could have been imposed on the grant of planning permission for the authorised development had it not fallen within the 2008 Act regime. Such requirements
may be imposed in the Order under section 120(1) of the 2008 Act.
The Requirements in Schedule 3 are based on the
Requirements set out in Schedule 4 of the DCO Model Provisions, but these have been modified as appropriate for the Onshore Scheme and following
dialogue with the relevant planning, highways and marine authorities.
54
The undertaker has consulted North Yorkshire County Council, East Riding of Yorkshire Council, Selby District
Council and the Marine Management Organisation on the form and content of the Requirements and had regard to comments received: these bodies provided
consultation responses during non-statutory and statutory consultation; further, throughout the course
of planning performance agreement meetings the undertaker has provided opportunity to comment on draft Requirements and revisions of documents
produced to secure environmental mitigation.
Appropriate Requirements in this Schedule have been amended to make a further body (such as the
Environment Agency ("EA"), Natural England (“NE”) or the local highway authority) a consultee in the approval process set out in the relevant Requirement.
A number of DCO Model Provisions Requirements have not been included in Schedule 3 because the proposed development will not produce the kinds of effects
which those Requirements seek to control. For example, it was not necessary to include Requirement 31 (Control of insects) from the DCO Model Provisions
because the authorised development is not in a location, or of a nature, where there is a real risk of
infestation or emanation of insects. Similarly, Requirement 29 (Control of smoke emissions) from the DCO Model Provisions is not necessary because
construction of the authorised development will not result in smoke emissions. Other Model Provisions have been amended to make them applicable to the
nature of the authorised development (i.e. a cross-country linear construction project). Several have been combined.
An explanation of the Requirements in their current form can be found below. Reference to a Requirement in the DCO Model Provisions means the corresponding
paragraph at Schedule 4 of those provisions.
Requirement 1 (Interpretation) sets out the meaning of words and phrases used in this Schedule which are
in addition to the terms defined within the main body of the Order. Some definitions additional to those found in Requirement 1 of the DCO Model Provisions
are necessary to define elements particular to the
55
Project such as “AGIs”, “Area B” and “Construction Compounds”. It is also sensible to include a definition
of “commence”/”commencement” of the authorised development for clarity on the triggers of discharge, which is common in development consent orders made
by the Secretary of State, including, to give one example, paragraph 1(1) of Schedule 2 of the Hinkley
Point C (Nuclear Generating Station) Order 2012.
Requirement 2 (Time Limits) sets out a time limit within which the authorised development must be
begun within five years of the Order being made, the period provided in regulation 3 of the Infrastructure Planning (Miscellaneous Prescribed Provisions)
Regulations 2010, and follows Requirement 2 of the DCO Model Provisions. Justification for this period is further set out in section 5 of the Statement of
Reasons (Document Reference 4.1).
Requirement 3 (Approved Details) requires the authorised development to be carried out in general
accordance with the approved details shown on the drawings listed in Part 4 of Schedule 2 (approved plans). It follows Requirement 6 of the DCO Model
Provisions, save that given the standard approach in development consent orders, reflected in article 6
(limits of deviation) of this Order, for works to be carried out within limits of deviation (both vertical and lateral) it is appropriate for works to be in general accordance with the approved plans so long as they fall within the limits of deviation specified in the Order; and Requirement 3(2) clarifies that “general” is to be
interpreted in this manner for the purposes of this Requirement.
Requirement 4 (Stages of authorised development) sets out defined stages of the authorised development. This is because it is proposed that Requirements may be discharged separately for different elements of the
authorised development for the purposes of carrying out the authorised development expeditiously. This approach is envisaged in Requirement 3 of the DCO
Model Provisions and is common on linear schemes such as the authorised development.
Requirement 5 (Pumping Station) requires certain
details for the Barmston Pumping Station (including layout, scale, external appearance and planting) to be
56
approved by the relevant planning authority before its construction can commence, which must be carried out
in accordance with the approved details.
The design and scale of the Barmston Pumping Station will be within the parameters set in the relevant
parameter plan (Document Reference 2.14) and guiding principles established in Chapter 8 of the
Design and Access Statement. The parameter plan sets out the maximum envelope within which the buildings and infrastructure will be constructed. However, the
detailed design of the Barmston Pumping Station needs to take place on a flexible basis, for later approval, because precise equipment and its exact
location within the site will be known closer to the point of implementation. As such, by seeking outline consent at this time, the undertaker can ensure that
the detailed design of the Barmston Pumping Station reflects the appropriate equipment available at the time of construction.
Requirement 6 (Multi-Junction Design) requires certain details for the Area B of the Camblesforth Multi-Junction (including layout, scale, external
appearance and planting) to be approved by the relevant planning authority before its construction can
commence, which must be carried out in accordance with the approved details. This is because the proposed Camblesforth Multi-junction has been
designed to accommodate up to four incoming pipeline connections (4 PIG traps) and one outgoing connection (1 PIG trap) into the cross country pipeline. However,
general arrangement drawings, elevations and profiles comprised in the application for the Order show:
• design for two PIG traps to accommodate an
inlet PIG Trap for the pipeline connection from the White Rose CCS Project and an outlet PIG
Trap to the cross country pipeline comprised in the authorised development; and
• “Area B”. Area B cannot yet be designed in
detail as the capacity and rate at which the area is built out will depend on when third
party connectors come forward and the direction from which they enter the facility. Capacity has been provided for three PIG
Traps within this Area B and this Requirement
57
secures detailed design approval by the relevant authority when such details become
available.
Requirement 7 (European Protected Species) follows Requirement 34 of the DCO Model Provisions and
requires that prior to commencement of each stage of the authorised development, surveys need to be
carried out to ascertain whether there are any European protected species present on land affected by the authorised development. Where such species
are present, that stage of the authorised development cannot be carried out until, following consultation with Natural England, a scheme of protection and mitigation
has been approved by the relevant planning authority; and the scheme must be complied with.
Requirement 8 (Scheme of ecological mitigation and reinstatement) requires each pipeline stage of the authorised development to be carried out in accordance with a scheme of ecological mitigation and
reinstatement approved by the relevant planning authority. This has the same effect as Requirement 17 of the DCO Model Provisions, save that it relates
specifically to pipeline stages. In addition, similar to Requirement 8 of the DCO Model Provisions, it
provides for the replacement of any shrub, hedge or tree planted as part of the scheme that dies or becomes seriously damaged or diseased within five
years of completion of the authorised development.
Requirement 9 (Water) requires construction works for the authorised development must be carried out in
accordance with an approved construction water management plan and a pollution prevention and control plan. Further, crossing methods for the
authorised development in relation to watercourses must be undertaken in a manner which will not cause an increase in flood risk.
Requirement 10 (Removal of trees and hedgerows) is required because the laying of the pipeline is likely to require the removal of certain trees or hedges along
the pipeline route, which is provided for in the Order. This Requirement means that the relevant planning authority must approve details of those trees and
hedgerows to be removed during a particular stage of the authorised before work on that stage can
58
commence. The approach to tree planting following the installation of the pipeline is dealt with as part of
the landscaping works under Requirement 8 above, as is the reinstatement of hedgerows.
Requirement 11 (AGI hard landscaping and drainage) prohibits a stage of the development commencing until details of hard surfacing materials
and drainage methods for any AGIs in that stage have been submitted to and approved by the relevant planning authority. This Requirement does not apply to
the Pumping Station or Area B of the Multi Junction because, as explained above, detailed design for these is to follow and would address hard surfacing and
drainage so far as appropriate.
Requirement 12 (Archaeology) follows the approach in Requirement 16 of the DCO Model Provisions and
requires that each stage of the authorised development must be carried out in accordance with a written archaeological scheme approved by the
relevant planning authority. The archaeological scheme will identify areas where a programme of archaeological investigation is required, and measures
to protect, record or preserve any archaeological remains that are found. This is because construction
of an underground pipeline may reveal undiscovered archaeological artefacts. The undertaker has remained in regular dialogue with English heritage on the
progression of the Onshore Scheme.
Requirement 13 (Construction Hours) means that construction of the authorised development can only
take place during set hours, other than in relation to certain listed operations, in cases of emergency or if otherwise approved by the relevant planning authority.
The list of operations which may take place outside of the set time frames is included because either, due to the engineering nature of the activity, they require 24-
hour working or, in the case of temporary possession of railway infrastructure, construction hours will be determined by third parties (like Network Rail).
Requirement 14 (Code of Construction Practice) follows Requirement 18 of the DCO Model Provisions and requires that construction works are carried out in
accordance with the code of construction practice submitted with the application, unless otherwise
59
agreed by the relevant local planning authority. The code of construction practice contains a series of
measures and standards of work to be applied by the undertaker and its contractors during construction of the authorised development.
Requirement 15 (Noise) requires the authorised development to be constructed in accordance with
specified construction noise levels at stated times. Further, Barmston Pumping Station must be operated in accordance with a noise report approved by the
relevant planning authority, demonstrating that noise for permanent fixed plant / machinery at the nearest residential receptor will not exceed certain levels.
Requirement 16 (Land Drainage) requires that subject to any alternative approved in respect of AGIs pursuant to Requirement 11 above, the authorised
development must be constructed in accordance with the Drainage Strategy submitted with the application. The authorised development is a long linear scheme
excavating a trench for much of the pipeline. As such, some existing drains may be severed. The purpose of this Requirement is to secure compliance with that
Drainage Strategy. This approach to land drainage, and the resultant likely effects on the Order limits as a
result of drainage design, were detailed as part of the Stage 2 statutory consultation.
Requirement 17 (Contaminated Land and Groundwater) has the same effect as Requirement 15 of the DCO Model Provisions and requires that if previously unidentified contamination is found whilst
carrying out the authorised development, it must be immediately reported to the relevant planning authority. It also requires that an investigation and
risk assessment is completed in accordance with an approved scheme. Any necessary remediation must be carried out in accordance with an approved
scheme, and following completion of the remediation, a verification report must be produced, and approved by the relevant planning authority. The purpose of this
Requirement is to ensure that potentially significant effects of previously unidentified contamination (if any) along the pipeline route are dealt with in a responsible
and satisfactory manner.
Requirement 18 (Traffic Management Plan) requires
60
that the authorised development be carried out in accordance with a Traffic Management Plan to be
submitted to and approved by the relevant planning authority in consultation with the highway authority. This would need to addresses the management of
construction traffic, which includes deliveries of pipe, construction plant and materials as well as
construction workers travelling to and from the temporary construction compounds and the construction working areas.
Requirement 19 (Restoration of land used temporarily for construction) follows Requirement 35 of the DCO Model Provisions and requires that any
land used temporarily for construction must be reinstated to a condition fit for its former use within 12 months of completion of the authorised development.
Though the DCO Model Provision Requirement requires reinstatement of land to its “former condition”, Requirement 18 provides for reinstatement to “a
condition fit for its former use”. This is to account for immaterial changes resulting from the installation of the pipeline which do not affect the landowner or
occupier continuing with the former use of the land used for construction.
Requirement 20 (Requirement for written approval) follows Requirement 36 of the DCO Model Provisions and requires that any approvals by the relevant
planning authority must be provided in writing.
Requirement 21 (Amendments to approved details) clarifies that where the relevant planning authority
approves details with which the undertaker must comply, and later agrees compliance with amended details, the originally approved details are to be
considered in light of the amendments which have been subsequently approved but only so far as those amendments may lawfully be made by the relevant
planning authority. This follows Requirement 37 of the DCO Model Provisions with additional wording to make clear that it will only apply to approvals that the
planning authority can lawfully make.
Requirement 22 (Decommissioning) provides a framework for the relevant planning authority
approving the approach to the authorised development at the end of its operational life. Accordingly, this
61
Requirement sets out that at least six months before the operations of the authorised development come to
a permanent end, a scheme of decommissioning, restoration and aftercare must be submitted for approval by the relevant planning authority. Following
the end of operations, that scheme must then be implemented as approved.
Requirement 23 (Driffield Construction Compound) provides control over the extent of the buildings to be demolished, or not as the case may be, in accordance
with the assumptions made in the course of the environmental impact assessment.
Requirement 24 (Venting for AGI maintenance)
provides control over the planned maintenance venting of AGIs. It controls the frequency, duration and noise emission level of that activity.
Requirement 25 (AGI venting for pipeline inspections) provides control over the planned internal inspection of pipelines using PIGs and venting of PIG
traps at AGIs for the purposes of the internal inspection of pipelines. It controls the frequency, duration and noise emission levels of that activity.
Schedule 4 (streets subject to street works) sets out those streets referred to in article 10 (street works) subject to street
works.
Schedule 5 (streets subject to alteration of layout) sets out those streets referred to in article 11 (power to alter layout, etc., of streets) subject to alteration of layout.
Schedule 6 (streets and rights of way to be temporarily stopped up) sets out those streets and rights of way referred to in article 14 (temporary stopping up of streets and rights of way) to be temporarily stopped up.
Schedule 7 (access to works) sets out the new accesses referred to in article 16 (access to works) to be constructed as part of the authorised development.
Schedule 8 (record of the satisfaction of the Secretary of State pursuant to section 132 of the 2008 Act) records
further to article 40 that the Secretary of State (if he is so minded) is satisfied that a subsection of section 132 of the 2008 Act applies to Plots 232, 233 and 268 of
the book of reference (Document Reference 4.3).
62
Schedule 9 (land of which temporary possession may be taken) sets out the land referred to in article 28 (temporary use of land for carrying out the authorised development) of which temporary possession may be taken.
Schedule 10
(deemed marine licence under Part 4 (Marine Licensing) of the Marine and Coastal Access Act 2009) sets out the marine licence referred to in article 42, which would be deemed to be granted for works comprised in the authorised development below mean
high water spring tide and the conditions to which the licence would be subject. There has been pre-submission dialogue with the Marine Management
Organisation (the “MMO”). It has reviewed the form of licence and discussions between it and the undertaker are ongoing.
Background to deemed marine licences
In terms of background, the MMO was established pursuant to the Marine and Coastal Access Act 2009
(“2009 Act”). The 2009 Act requires a Marine Licence to be obtained to carry out specified “licensable marine
activities” in the area submerged at mean high water spring tide (“MHWS”) and the waters of rivers so far as the tide flows at MHWS. The MMO would ordinarily,
i.e. outside of the Planning Act 2008 (“2008 Act”), be the decision-maker responsible for determining whether to grant a Marine Licence under the 2009 Act.
However, this is not the case for nationally significant infrastructure projects falling under the 2008 Act, such as the Onshore Scheme. Should the Secretary of State
accept the Onshore Scheme for Examination, and that it is therefore subject to the 2008 Act, he will be the decision-maker responsible for determining whether to
grant development consent in the form of the DCO for the Onshore Scheme, which will include the area within the Order limits of the DCO submerged at
MHWS down to mean low water spring tide (“MLWS”). This would include the areas within the
Order limits seaward of MHWS at Barmston Sands and the tidal reach of the River Ouse, which are shown for information only on the Deemed Marine Licence Co-
ordinates drawing with reference 0-2574-GND-01-05-0056 (Document Reference 2.7). Section 149A of the
63
2008 Act allows a DCO made by the Secretary of State to deem that a Marine Licence has been granted
pursuant to the 2009 Act. The draft DCO sought by the undertaker deems such a licence to have been issued in article 42 and sets out in this Schedule the terms of
that deemed Marine Licence.
In other words, the Secretary of State, rather than the
MMO, is the decision-maker for the Marine Licence, deemed to be granted by the DCO and contained within it. There is therefore no “crossover” of
jurisdictions and no separate Marine Licence is required from the MMO. However, the MMO plays the following important roles under the 2008 Act regime:
(A) The MMO is a consultee on the deemed Marine Licence, whose representations, amongst other things, may inform what
conditions are to be attached to the deemed marine licence by the Secretary of State;
(B) The Secretary of State may specify in the
deemed Marine Licence that the MMO is the responsible discharging body for conditions attached to that deemed Marine Licence. This
is the case in the deemed Marine Licence contained in the DCO;
(C) The MMO is responsible for enforcing breaches of the conditions attached to the deemed Marine Licence, with a choice of
enforcement procedures under the 2008 and 2009 Acts.
Terms of the deemed marine licence
The terms of the marine licence can be summarised as follows:
PART 1: INTERPRETATION
Paragraph 1 (interpretation) sets out the interpretation of certain words and phrases used in the licence and contact details for the MMO and other
relevant organisations including, inter alia, the Environment Agency, Natural England and English Heritage.
Paragraph 2 (details of licensed marine activities)
64
authorises the construction of those elements of the authorised development which fall within the English
inshore region, i.e. the area submerged at MHWS for which marine licences are ordinarily required, and constitute licensable activities for the purposes of the
2009 Act. This includes the following: the deposit of specified substances at sea; the construction,
inspection and maintenance of works in, under or over the intertidal area and the River Ouse; and sampling or investigative works required in connection with these.
The paragraph also specifies the parameters of the licensed area within which the licensed activities are permitted.
PART 2: LICENCE CONDITIONS
Paragraph 1 (application of licence conditions) provides that the licence conditions will not apply to
areas of the authorised development which fall outside the English inshore region, i.e. the landward side of MHWS and for which the relevant local planning
authority would be the appropriate discharging and enforcing body pursuant to the Requirements in Schedule 3. This has been agreed with the MMO.
Paragraph 2 (licensed location) specifies the area within which the licensed activities may be carried out.
Paragraph 3 (notifications and inspections) sets out the persons who must be given a copy of the Schedule, and where it will be available for inspection,
as well as certain notification and publication requirements.
The paragraph provides that only persons and vessels
notified to the MMO are permitted to carry out the licensed activities, and each of these persons must be provided with a copy of the Schedule. The undertaker
must also appoint suitably qualified liaison officers (Fisheries Liaison Officer(s) and Environmental Liaison Officer(s)) and their identities and responsibilities must
be notified to the MMO. Prior to commencement of licensed activities, the undertaker must give notice to the MMO and mariners (mariners’ notices must be
updated at least once a week) and a notice must be published in the Kingfisher Fortnightly Bulletin. This is to ensure that other vessels in the vicinity can safely
plan and conduct their passage. In addition, the
65
undertaker must comply with notice requirements regarding completion.
The undertaker must also provide access to the MMO to carry out any inspection of the works.
Paragraph 4 (chemicals, drilling and debris) restricts
the use of chemicals, drilling fluids, coatings and treatments. It provides that all chemicals used in the
construction of the licensed works must be selected from an approved list and the undertaker must ensure that any coatings and treatments are suitable for use
in the marine environment and are used in accordance with specified Environment Agency and Health and Safety Executive guidelines. This is to ensure that
hazardous chemicals that may be toxic, persistent or bioaccumulative are not released into the marine environment and are used appropriately.
In addition, the undertaker is required to ensure that the storage, handling, transport and use of fuels, lubricants, chemicals etc. is carried out in a way so as
to prevent releases into the marine environment. This is to prevent marine pollution incidents by adopting best practice techniques.
The undertaker is also required to report any accidental spillages of coatings or treatments to the
MMO within 6 hours. This is to ensure that any spills are appropriately recorded and managed to minimise the impact to sensitive receptors and the general
marine environment.
For any drilling works other than those using water-based mud, the MMO’s approval is required in relation
to the proposed disposal of any arisings from the drilling works.
Further, any waste, debris, equipment and temporary
works must be removed within 4 weeks of completion. This is to prevent the accumulation of unlicensed material/debris and the potential environmental
damage, safety and navigational issues associated with such material/debris.
Paragraph 5 (force majeure) provides for the
notification to the MMO of deposits made outside of the licensed location in the event of force majeure. This notification must be made within 48 hours, and
66
the deposits must be removed on approval by the MMO. This is to manage the associated safety and
navigation issues as the deposits (if any) could cause an obstruction or hazard to other sea or sea-bed users.
Paragraph 6 (pre-construction plans and documentation) requires the undertaker to submit for the approval of the MMO, four months before
commencement of licensed activities the following documents: a construction and monitoring programme; a construction method statement; a
project environmental management plan; and a written scheme of archaeological investigation. Each of these documents must contain certain specified
information. No licensed activity can commence until the relevant programme/plan has been approved by the MMO and all licensed activities must be carried out
in accordance with the approved programmes/plans.
Paragraph 7 (reporting of engaged agents, contractors and vessels) requires the undertaker to
provide details to the MMO of agents, contractors and vessels that will be carrying out the licensed activities.
Paragraph 8 (equipment and operation of vessels engaged in licensed activities) requires the undertaker to ensure all vessels being used to carry out the
licensed activities meet specified technical requirements and are constructed and equipped to enable compliance with the licence conditions.
Paragraph 9 (pre-construction baseline) requires the undertaker to submit a pre-construction baseline report to the MMO for approval prior to
commencement of licensed activities. The form and content of the pre-construction baseline report must be agreed with the MMO in advance and must include
certain specified information.
Paragraph 10 (construction monitoring) requires the undertaker to submit environmental monitoring reports
to the MMO during construction (in accordance with paragraph 6). The monitoring reports must include certain specified information.
Paragraph 11 (post construction) requires the undertaker to submit environmental monitoring reports to the MMO following construction of the licensed
works (in accordance with paragraph 6).
67
Paragraph 12 (amendments to approved details) makes provision for any amendments lawfully
approved by the MMO to be included in the approved details for the purposes of carrying out the licensed activities in accordance with the details provided.
Schedule 11
(protective provisions) sets out protective provisions for specified statutory undertakers who have been
identified as having apparatus within the Order limits. The provisions have been based on those contained in several recent TWA Orders and Orders under the 2008
Act.
Schedule 12
(miscellaneous controls) part 1 of this Schedule applies, modifies and excludes specified general
statutory provisions which relate to matters for which provision may be made in the Order:
Paragraph 2 provides the consents necessary under the Wildlife and Countryside Act 1981 for the proposed non-intrusive installation of the pipeline beneath Kelk
Beck, part of the River Hull Headwaters SSSI, and a bridge to allow access for construction traffic over it. The consents are subject to the provisions of the
Order, particularly the requirements in Schedule 3 (requirements). This application of and modification to the Wildlife and Countryside Act 1981 may be made
pursuant to section 120(5)(a) of the 2008 Act and the Planning Inspectorate have confirmed that this is an appropriate approach.
The context of paragraph 3 is as follows:
• The Pipeline Safety Regulations 1996 (the “1996 Regulations”) (which are Regulations
made under the Health and Safety at Work etc Act 1974) apply to the authorised
development in general terms.
• However, the authorised development is not a “major accident hazard pipeline”, as defined
under the 1996 Regulations, and therefore certain additional duties imposed on major accident hazard pipelines do not apply to the
authorised development.
• The specific Regulations under the 1996 Regulations that have been applied by this
68
Order relate to the requirement to notify the relevant authorities prior to construction and
prior to use, the need to have a major accident prevention document and to have in place certain emergency procedures. In other
words, the undertaker, therefore, has adopted a precautionary approach and has elected to
operate the proposed pipelines as if Carbon Dioxide were classed as a “dangerous fluid” under Part III of the Pipeline Safety
Regulations 1996, even though this is not presently the case.
• The provisions that have not been applied
relate primarily to the incorporation of emergency shut-down valves into the design and the need to have an emergency plan
approved by the relevant authority. These provisions are unnecessary given that the undertaker is voluntarily assuming certain
duties that otherwise would not apply. The emergency shut-down valves are only relevant to offshore pipelines. In addition, the criminal
provisions of the Health and Safety at Work etc. Act 1974 need to be disapplied because
these duties are by virtue of incorporation into the draft Order “terms of a development consent order”, breach of which is already a
criminal offence pursuant to the section 161 (breach of terms of order granting development consent).
Part 2 of this Schedule applies, modifies and excludes specified local legislation which relates to matters for which provision may be made in the Order. The
approach in relation to the byelaws listed is as follows:
• byelaws which do not conflict with the carrying out of the authorised development
are not excluded;
• byelaws which prohibit an activity required for the carrying out of the authorised
development but which refer to scope for obtaining the consent of the relevant independent drainage board (“IDB”) or
Environment Agency are not excluded and, it has been agreed with these bodies, such
69
consents will be sought following the making of the Order; and
• byelaws which conflict with activities required for the carrying out of the authorised development but which do not provide scope
for consent under the terms of those byelaws are listed in this Schedule as being excluded.
It is understood that The Beverley and North Holderness Internal Drainage Board Byelaws have not yet been confirmed by the Secretary of State, so no
date is given in the Schedule. It is understood that confirmation is likely to have taken place prior to the making of the Order (if made) and the relevant date
can be inserted at that time.
Schedule 13
(modification of compensation and compulsory purchase enactments for creation of new rights) as
explained above in relation to article 24(4) (compulsory acquisition of rights), mirrors the wording of Schedule 11 of the Hinkley Point C (Nuclear
Generating Station) Order 2013 and imposes modifications to the compulsory purchase and
compensation provisions under general legislation which do not affect the entitlement to compensation, but generally ensure that the compensation procedure
applies to the additional categories of acquisition covered by the Order – namely, the creation of new rights and the imposition of restrictive covenants in
particular.
Schedule 14
(procedure in relation to certain approvals etc.) sets out a procedure in respect of certain approvals to be
determined pursuant to the Order, which is more particularly explained in this explanatory memorandum
at article 53 above.
Berwin Leighton Paisner LLP
June 2014
32330277.13
70
Appendix Tracked change version of the Order against the DCO Model Provisions
Page 28 of 99PART 1
PRELIMINARY
1. Citation and Commencement
12. Interpretation
2 Incorporation of the Railway Clauses Acts3 . Application and, modification and disapplication of legislative provisions
PART 2
WORKS PROVISIONS
Principal Ppowers
4 . Development consent etc. granted by the Order
5 . Maintenance of authorised projectdevelopment
6 . Limits of Ddeviation
7 Benefit of Order. Defence to proceedings in respect of statutory nuisance
Benefit of order
8. Benefit of Order
8 Consent to transfer9. Transfer of benefit of Order
Streets
9 10. Street works
10 1. Power to alter layout, etc., of streets
12. Construction and maintenance of new or, altered or diverted streets
11 Stopping up of streets12 Application of the 1991 Act
13 Public rights of way. Permanent stopping up of streets
14 . Temporary stopping up of streets and public rights of way
15 . Apparatus and rights of statutory undertakers in permanently stopped up streets
16. Access to works
16 7. Traffic regulation
18. Agreements with street authorities
17 Construction of bridges and tunnels
2 2
S T A T U T O R Y I N S T R U M E N T
201[●] No. [●]
INFRASTRUCTURE PLANNING
The [Draft] Yorkshire and Humber (Carbon Capture and Storage
Cross Country Pipeline) Order 201[●]
Made - - - - [●] 201[●]
Coming into force - - [●] 201[●]
CONTENTS
Preliminary
Page 29 of 99
34 Rights under or over streets35 28. Temporary use of land for carrying out the authorised projectdevelopment
36 29. Temporary use of land for maintaining the authorised projectdevelopment
Compensation
37 Special category land0. Disregard of certain interests and improvements
31. Set-off for enhancement in value of retained land
38 Statutory undertakers2. No double recovery
Supplementary
33. Acquisition of part of certain properties
34. Statutory undertakers
39 Apparatus and rights of statutory undertakers in stopped up streets5. Recovery of
costs of new connections
36. Time limit for exercise of authority to acquire land compulsorily
37. Private rights of way
38. Rights under or over streets
39. Incorporation of the mineral code
40 Recovery of costs of new connections
Operations. Open space
PART 4
MISCELLANEOUS AND GENERAL
41 Operation and use of railways. Application of landlord and tenant law
42 F a r es 43 . Deemed consent under section 34 of the Coast Protection Act 194Part 4
(marine licensing) of the Marine and Coastal Access Act 2009
3 3
18 Level Crossings19 Railway and navigation undertakings
Supplemental Ppowers
20 19. Discharge of water
210. Protective work to buildings
22 1. Authority to survey and investigate the land
23 2. Removal of human remains
PART 3
ACQUISITION AND POSSESSION OF LAND
Powers of Aacquisition
23. Compulsory acquisition of land
24 . Compulsory acquisition of landrights
25 Compulsory acquisition of land--incorporation of the mineral code.Acquisition of subsoil only
26 Time limit for exercise of authority to acquire land compulsorily.Power to override easements and other rights
27 Compulsory acquisition of rights
28 Private rights of way29 . Application of the Compulsory Purchase (Vesting
Declarations) Act 1981
30 Acquisition of subsoil only31Acquisition of land limited to subsoil lying more than 9 metres beneath surfaceTemporary
possession of land
32 Acquisition of part of certain properties33 Application of the Land Compensation Act 1973
Page 30 of 9953. Procedure in relation to certain approvals etc.
SCHEDULES
SCHEDULE 1 — AUTHORISED DEVELOPMENT
4 4
44 Deemed licence under Part 2 of the Food and Environment Protection Act 19853.Operational land for purposes of the 1990 Act
445 . Felling or lopping of trees or shrubs
46 5. Trees subject to tree preservation orders
Miscellaneous and General
46. Resumption of land use following certain works
47 . Application of landlord and tenant lawthe Community Infrastructure Levy
48 Operational land for purposes of the 1990 Act49 Defence to proceedings in respect of statutory nuisance50 Protections of Interests. Protective provisions
5149. Certification of plans etc.
52 Arbitration0. Service of notices
Schedule A--Authorised Project
Part 1--Authorised Development Part 2--Ancillary Works
Schedule B--Streets Subject to Street Works Schedule C--Streets to be Stopped Up
Part 1--Streets for which a Substitute is to be Provided Part 2--Streets for which No Substitute is to be Provided
Schedule D--Streets to be Temporarily Stopped UpSchedule E--Access to WorksSchedule F--Land of which Only Subsoil More than 9 Metres Beneath Surface may beAcquiredSchedule G--Land of which Temporary Possession may be TakenSchedule H--Deemed Consent Under Coast Protection Act 1949
51. Arbitration
Schedule I--Deemed Licence Under the Food and Environment Protection Act 198552.Requirements
Schedule J--Trees Subject to Tree Preservation OrdersSchedule K--Level CrossingsSchedule L--Protective Provisions
Preliminary
SCHEDULE 2 — PLANS
PART 1 — WORKS PLANS
PART 2 — LAND PLANS
PART 3 — ACCESS, RIGHTS OF WAY AND TEMPORARY STOPPING UP
PLANS
PART 4 — APPROVED PLANS
SCHEDULE 3 — REQUIREMENTS
SCHEDULE 4 — STREETS SUBJECT TO STREET WORKS
SCHEDULE 5 — STREETS SUBJECT TO ALTERATION OF LAYOUT
PART 1 — STREETS SUBJECT TO TEMPORARY ALTERATION OF
LAYOUT
PART 2 — STREETS SUBJECT TO PERMANENT ALTERATION OF
LAYOUT
SCHEDULE 6 — STREETS AND PUBLIC RIGHTS OF WAY TO BE
TEMPORARILY STOPPED UP
PART 1 — STREETS
PART 2 — RIGHTS OF WAY
SCHEDULE 7 — ACCESS TO WORKS
PART 1 — TEMPORARY ACCESS
PART 2 — PERMANENT ACCESS
SCHEDULE 8 — RECORD OF THE SATISFACTION OF THE SECRETARY OF
STATE PURSUANT TO SECTION 132 OF THE 2008 ACT
SCHEDULE 9 — LAND OF WHICH TEMPORARY POSSESSION MAY BE
TAKEN
SCHEDULE 10 — DEEMED MARINE LICENCE UNDER PART 4 (MARINE
LICENSING) OF THE MARINE AND COASTAL ACCESS ACT
2009
PART 1 — INTERPRETATION
PART 2 — LICENCE CONDITIONS
SCHEDULE 11 — PROTECTIVE PROVISIONS
PART 1 — FOR THE PROTECTION OF ELECTRICITY, GAS, WATER AND
SEWERAGE UNDERTAKERS
PART 2 — FOR THE PROTECTION OF OPERATORS OF ELECTRONIC
COMMUNICATIONS CODE NETWORKS
SCHEDULE 12 — MISCELLANEOUS CONTROLS
PART 1 — PUBLIC GENERAL LEGISLATION
PART 2 — LOCAL LEGISLATION
SCHEDULE 13 — MODIFICATION OF COMPENSATION AND COMPULSORY
PURCHASE ENACTMENTS FOR CREATION OF NEW RIGHTS
SCHEDULE 14 — PROCEDURE IN RELATION TO CERTAIN APPROVALS ETC.
EXPLANATORY NOTE
An application was made to the Secretary of State in accordance with section 37 of the Planning Act
2008(a) for an order under sections 37, 114, 115, 120 and 122 of that Act.
The Examining authority(b) appointed by the Secretary of State examined the application in accordance
with Chapter 4 of Part 6 of that Act(c) and made a recommendation under section 74 of that Act(d) that
the application should be granted.
5 5
(a) 2008 c.29; section 37 is amended by the Localism Act 2011 (c. 20) s.137 and Sch. 13, para.5(2), (3).
(b) See section 86 of the Planning Act 2008 as amended by the Localism Act 2011, Sch. 13 para.37.
(c) The provisions of that Part are amended by the Localism Act 2011.
(d) Section 74 is amended by the Localism Act 2011, Sch.13 para.29(3) and Sch. 25 para.1.
The Secretary of State, having the function of deciding the application(e), in exercise of the powers
conferred by sections 103, 114, 115, 120 and 122 of that Act, makes the following Order—
PART 1
PRELIMINARY
Citation and Commencement
This Order may be cited as the Yorkshire and Humber (Carbon Capture and Storage Cross 1.
Country Pipeline) Order 201[●] and comes into force on [●] 201[●].
Interpretation 1
(1) —a) In this Order--, unless the context requires otherwise—2.
"“the 1961 Act"” means the Land Compensation Act 1961(f);
"“the 1965 Act"” means the Compulsory Purchase Act 1965(g);
"“the 1980 Act"” means the Highways Act 1980(h);
“the 1984 Act” means the Road Traffic Regulation Act 1984(i);
"“the 1990 Act"” means the Town and Country Planning Act 1990(j);
"“the 1991 Act"” means the New Roads and Street Works Act 1991(k);
"“the 2008 Act"” means the Planning Act 2008; 2008;
"ancillary works" means the ancillary works described in Part 2 of Schedule A (authorised project) [and any other works authorised by the Order] and which are not development within the meaning of section 32 of the 2008 Act;
“access, rights of way and temporary stopping up plans” means the plans certified as the access,
rights of way and temporary stopping up plans by the Secretary of State for the purposes of this
Order and listed in Part 3 of Schedule 2 (plans);
“approved plans” means the plans listed in part 4 of Schedule 2 (plans) and such revised or
supplemental plans as may be approved pursuant to Schedule 3 (requirements);
"“authorised development"” means the development and associated development described in Part 1
of Schedule A1 (authorised projectdevelopment) [and any other development authorised by this
Order], which is development within the meaning of section 32 of the 2008 Act;
"the authorised project" means the authorised development and the ancillary works authorised by this Order;
"“the book of reference"” means the book of reference certified by the decision-makerSecretary of
State as the book of reference for the purposes of this Order;
"“building"” includes any structure or erection or any part of a building, structure or erection;
"“carriageway"” has the same meaning as in the 1980 Act;
"“compulsory acquisition notice"” means a notice served in accordance with section 134 of the 2008
Act; "the decision-maker"
“drainage works” means that part of the authorised development comprised in paragraph (n) in
Schedule 1 (authorised development) and such other further associated development in connection
6 6
(e) See section 103 of the Planning Act 2008 as amended by the Localism Act 2011 Schs. 13, 25.
(f) 1961 c.33.
(g) 1965 c.56.
(h) 1980 c.66.
(i) 1984 c. 27.
(j) 1990 c.8.
(k) 1991 c.22.
(l) 1981 c.67; the definition of “owner” is amended by the Planning and Compensation Act 1991 (c. 34), Sch.15(I) para.9.
(m) Section 48 is amended by the Local Transport Act 2008 (c. 26), Pt 7 s.124(2).
Page 31 of 99
facility, in which case it means the county planning authority;
(ii) a National Park Authority;
(iii) the Broads Authority; and
(iv) the Greater London Authority if the land to which the provisions of this Order or requirements apply is situated in Greater London;
"rights plan" means the plan certified as the rights plan by the decision-maker for the purposes of this Order;
"the sections" means the sections shown on the plan certified as the section drawings plan by the decision-maker for the purposes of this Order;
"“statutory undertaker"” means any person falling within section 127(8), 128(5) or 129(2) of the
2008 Act;
"“street"” means a street within the meaning of section 48 of the 1991 Act(m), together with land on
the verge of a street or between two carriageways, and includes part of a street;
"“street authority"”, in relation to a street, has the same meaning as in Part 3 of the 1991 Act; "tree
preservation order" has the meaning given in section 198 of the 1990 Act; "
7 7
with that paragraph as is listed at paragraphs (e), (g), (h), (i), (j), (k), (l), (m) and (o) of that
Schedule;
“highway” has the same meaning as in section 103 of the 2001980 Act; "highway" and
"highway authority" have the same meaning as in the 1980 Act;
“highway authority” means North Yorkshire County Council or East Riding of Yorkshire Council as
the case may be including their successor and where the relevant matter is located in the
administrative areas of both then it means both;
"“the land plans"” means the plans certified as the land plans by the decision-makerSecretary of
State for the purposes of this Order;"limits of deviation" means the limits of deviation referred to in
article 6; and listed in Part 2 of Schedule 2 (plans);
"“maintain" and any of its derivatives include to” includes inspect, examine, monitor, repair, adjust,
alter, remove,set up, configure, clear, dismantle and/or reconstruct the authorised development
and/or replace the authorised project and any derivative of "maintain" shallpart or a section of the
authorised development with a part or section which materially serves the same purpose; and
“maintaining” and “maintenance” must be construed accordingly;“National Grid Carbon” means
National Grid Carbon Limited (company number 03932833) whose registered office is at 1 - 3
Strand, London, WC2N 5EH;
"“Order land"” means the land shown on the land plans which is within the limits of land, and
interests in or rights over land, to be acquired and/or used and described in the book of reference;
"“the Order limits"” means the limits shown on the works plans within which the authorised
projectdevelopment may be carried out;
"“owner"”, in relation to land, has the same meaning as in section 7 of the Acquisition of Land Act
1981(l); "
“PIG” means a pipeline inspection gauge or pipeline internal gauge;
“relevant planning authority" means--” means Selby District Council or East Riding of Yorkshire
Council as the case may be including their successor and where the relevant matter is located in the
administrative areas of both then it means both;
(i) the district planning authority for the area in which the land to which the provisions of this Order apply is situated unless the provisions relate to the construction or alteration of a hazardous waste
(n) 2009 c.23.
Page 32 of 99
section 77 (presumption that minerals excepted from acquisition of land);
sections 78 to 83, 85 to 85E and Schedules 1 to 3 (minerals under railways), as respectively substituted and inserted by section 15 of the Mines (Working Facilities and Support) Act 1923; and
8 8
“the tribunal"” means the Lands Chamber of the Upper Tribunal;
“UK marine area” has the same meaning as in section 42 of the Marine and Coastal Access Act
2009(n);
"“undertaker"” means the person who has the benefit of this Order in accordance with section 156 of
the 2008 ActArticles 8 and 9 of this Order;
"watercourse" includes all rivers, streams, ditches, drains, canals, cuts, culverts, dykes, sluices,
sewers and passages through which water flows except a public sewer or drain; and“watercourse” in
Schedule 1 (authorised development) means a flowing surface watercourse such as a river, stream,
open drain, canal or dyke but does not mean a land drain, culvert or sewer; and
"“the works plans"” means the plans certified as the works plans by the decision-makerSecretary of
State for the purposes of this Order and listed in part 1 of Schedule 2 (plans).
Save for the definition of the “undertaker”, the definitions in paragraph (1) do not apply to Schedule (1)
10 (deemed marine licence under Part 4 (marine licensing) of the Marine and Coastal Access Act
2009).
The definition of the “undertaker” in paragraph (1) does not apply to Schedule 11 (protective (2)
provisions).
(2) References in this Order to rights over land include references to rights to do, or to place and(3)
maintain, anything in, on or under land or in the air-space above its surface.
(3) All distances, directions and lengths referred to in this Order are approximate and distances (4)
between points on a work comprised in the authorised project shall be taken to be measured along that
work.and any document referred to in this Order are approximate and distances between points on a work
comprised in the authorised development are taken to be measured along that work (and in particular in
respect of scheduled linear works referred to in this Order all distances are measured along the indicative
pipeline route as shown on the works plans for that work).Incorporation of the Railway
Clauses Acts 2
(1) The following provisions of the Railways Clauses Consolidation Act 1845 shall be incorporated in this Order--
section 46 (crossing of roads--level crossings), subject to paragraph (4) and article 18 (level
crossings);
section 58 (company to repair roads used by them), except for the words from "and if any question" to the end;section 61 (company to make sufficient approaches and fences to highways crossing on the
level); section 68 (accommodation works by company);
section 71 (additional accommodation works by owners), except for the words "or directed by such justices to be made by the company" and "or, in case of difference, as shall be authorised by two justices";
sections 72 and 73 (supplementary provisions relating to accommodation works);
section 105 (carriage of dangerous goods on railway), except for the words from "and if any person" to "for every such offence".
(2) The following provisions of the Railways Clauses Act 1863 shall be incorporated in this
Order-- sections 5 and 7 (level crossings); and
section 12 (signals, watchmen etc).
(3) In those provisions, as incorporated in this Order--
"the company" means the undertaker;
"goods" includes any thing conveyed on the railway authorised to be constructed by this
Order; "lease" includes an agreement for a lease;
"prescribed", in relation to any such provision, means prescribed by this Order for the purposes of that provision;
"the railway" means any railway authorised to be constructed by this Order and any other authorised development; and
"the special Act" means this Order
All areas described in square metres in the book of reference are approximate.(5)
A reference in this Order to a work designated by a number, or by a combination of letters and (6)
numbers (for example, “Work No. 2”), is a reference to the work so designated in Schedule 1 (authorised
development).
A reference in this Order to a document or plan required to be submitted for certification under (7)
article 49 (certification of plans etc.) is a reference to the version of that document or plan that has been
certified under article 49.
(4) In section 46 of the Railways Clauses Consolidation Act 1845, as incorporated in this Order, for (8)
the proviso there shall be substituted "Provided always that, with the consent of the highway authority and
subject to such conditions as the authority may reasonably impose, the railway may be carried across a
highway on the level.".References in this Order to any statute, order, regulation or similar instrument are
to be construed as a reference to the statute, order, regulation or instrument as amended by any subsequent
statute, order, regulation or instrument or as contained in any subsequent re-enactment.
Application and, modification and disapplication of legislative provisions
3
(1) Subject to the modifications set out in paragraph (2) [the following provisions of] the [insert short title of the relevant Act] shall be incorporated in this Order--
—a) Part 1 of Schedule 12 (miscellaneous controls) to this Order, which makes provision 3.
applying, modifying and excluding statutory provisions which relate to matters for which provision
may be made by this Order, has effect.
The byelaws specified in Part 2 of Schedule 12 (miscellaneous controls) and any other statutory (1)
provision of local application—
have effect subject to the provisions of this Order, and(a)
are excluded and do not apply to the extent that they would be inconsistent with a provision of, (b)
or the exercise of a power conferred by, this Order.
In particular, a power conferred by this Order may be exercised despite, and without having regard (2)
to, a provision made by or by virtue of a specified enactment, or any other provision of local application,
that—
requires or permits a specified road, path, passage, bridge, parapet, fence or other place or (a)
structure to be kept open or maintained generally or in a specified manner;
9 9
requires or permits the provision and maintenance of lights or other apparatus or structures (b)
generally or in a specified manner;
prohibits or restricts (or imposes conditions or penalties on or in relation to) the obstruction or (c)
removal of, or the causing of damage to, a specified place or structure (or class of places or
structures);
prohibits or restricts (or imposes conditions on or in relation to) the erection of structures, or the (d)
undertaking of other works, in a specified place or structure (or class of places or structures);
permits or requires a specified place or structure to be closed;(e)
makes provision about the conduct of persons using a specified walkway or other place or (f)
structure (or class of places or structures) whether by prohibiting or restricting movement (of
persons, vehicles or animals) or otherwise;
specifies a minimum or maximum depth for, or otherwise restricts or imposes conditions in (g)
relation to, the laying of pipes or the carrying out of any other works;
prohibits the laying of pipes or the carrying out of any other works generally or without the (h)
consent of a specified person;
makes provision about the construction or maintenance of, or any other matter relating to, pipes, (i)
drains or other means of connecting with sewers;
prohibits or restricts interference with the banks or bed of, or traffic on, the River Ouse, River (j)
Foulness, Market Weighton Canal, River Hull, Driffield Canal, Nafferton Highland Stream,
White Dike and Kelk Beck; or
in any other way would or might apply in relation to anything done, or omitted to be done, in the (k)
exercise of a power conferred by this Order.
For the purposes of paragraph (2) a provision is inconsistent with the exercise of a power conferred (3)
by this Order if and insofar as (in particular)—
it would make it an offence to take action, or not to take action, in pursuance of a power (a)
conferred by this Order;
action taken in pursuance of a power conferred by this Order would cause the provision to (b)
apply so as to enable a person to require the taking of remedial or other action or so as to enable
remedial or other action to be taken;
action taken in pursuance of a power or duty under the provision would or might interfere with (c)
the exercise of any work authorised by this Order.
Where any person notifies the undertaker in writing that anything done or proposed to be done by the (4)
undertaker or by virtue of this Order would amount to a contravention of a statutory provision of local
application, the undertaker must as soon as reasonably practicable, and at any rate within 14 days of
receipt of the notice, respond in writing setting out—
section X [specify relevant section(s)]; andwhether the undertaker agrees that the action (a)
taken or proposed does or would contravene the provision of local application;
section X [specify relevant section(s)].if the undertaker does agree, the grounds (if any) on (b)
which the undertaker believes that the provision is excluded by this Article; and
(4) The provisions of the [insert relevant Act] Act [date] as incorporated in this Order shall be modified as follows [insert relevant modifications].
(5) In construing the [insert relevant Act] Act [date] as incorporated the following expressions shall have the following meanings [insert relevant expressions and definitions.
the extent of that exclusion.(c)
10 10
(o) 1990 c.43; section 82 is amended by section 5 of the Noise and Statutory Nuisance Act 1993 (c.40), Schedule 17 to the Environment Act 1995 (c.25) and section 103 of the Clean Neighbourhoods and Environment Act 2005 (c.16).
Page 33 of 99
development consent for the authorised development to be carried out within the Order limits;(a)
and
consent to operate and use the authorised development for the purposes for which it is designed.(b)
(b) consent for the ancillary works, to be carried out within the Order limits. Maintenance of
authorised projectdevelopment
5
The undertaker may at any time maintain the authorised development—5.
provided that, following such maintenance, the authorised development may not, save in (a)
immaterial respects, vary from the description of it given in Schedule 1 (authorised
development);
The undertaker may at any time maintain the authorised project, except to the extent that this(b)
Order, or an agreement made under this Order, provides otherwise.
Limits of Ddeviation
6
In carrying out linear works—a) Save in relation to the drainage works (in which case paragraph 6.
(2) applies), the undertaker may--—
in respect of the location of any work comprised in the authorised development deviate laterally(a)
from the lines or situations of the authorised development shown on the works plans to the
extent of the limits of deviation for that work shown on that those plans; and
deviate vertically from the levelscarry out construction activities for the purposes of the(b)
authorised development shown onanywhere within the sections--Order limits.
The undertaker may construct the drainage works anywhere within the Order limits.(1)
(i) Aerial markers, cathodic protection test posts, field boundary markers, transformer rectifier kiosks (2)
and electricity cabinets comprised in the authorised development may deviate vertically from ground
surface levels to any extent not exceeding [insert number]3 metres upwards; or.
(ii) The authorised development may deviate vertically from ground surface levels to any extent(3)
downwards as may be found to be necessary or convenient.
Defence to proceedings in respect of statutory nuisance
—a) Where proceedings are brought under section 82(1) of the Environmental Protection Act 7.
1990(o) (summary proceedings by person aggrieved by statutory nuisance) in relation to a nuisance
falling within paragraph (g) of section 79(1) of that Act (noise emitted from premises so as to be
prejudicial to health or a nuisance) no order may be made, and no fine may be imposed, under
section 82(2) of that Act if—
11 11
PART 2
WORKS PROVISIONS
Principal Ppowers
Development consent etc. granted by the Order
4
Subject to the provisions of this Order and to the requirements in the Schedule 3 (requirements)4.
attached to this Order the undertaker is granted--—
the defendant shows that the nuisance—(a)
relates to premises used by the undertaker for the purposes of or in connection with the (i)
construction or maintenance of the authorised development and that the nuisance is
attributable to the carrying out of the authorised development in accordance with a notice
served under section 60 (control of noise on construction site), or a consent given under
section 61 (prior consent for work on construction site) or 65 (noise exceeding registered
level), of the Control of Pollution Act 1974(p); or
is a consequence of the construction or maintenance of the authorised development and (ii)
that it cannot reasonably be avoided; or
the defendant shows that the nuisance— (b)
relates to premises used by the undertaker for the purposes of or in connection with the (i)
use of the authorised development and that the nuisance is attributable to the use of the
authorised development which is being used in accordance with paragraph 15 of Schedule
3 (requirements); or
is a consequence of the use of the authorised development and that it cannot reasonably (ii)
be avoided.
Section 61(9) (consent for work on construction site to include statement that it does not of itself (1)
constitute a defence to proceedings under section 82 of the Environmental Protection Act 1990) of the
Control of Pollution Act 1974 and section 65(8) of that Act (corresponding provision in relation to
consent for registered noise level to be exceeded), does not apply where the consent relates to the use of
premises by the undertaker for the purposes of or in connection with the construction or maintenance of the
authorised development.
Benefit of order
Benefit of Order
7
—a) Subject to article 8 9 (consent to transfer of benefit of Order) and paragraph (2) of this 8.
article, the provisions of articles [ ] and [ ] [specify relevant articles] shallthis Order have effect
solely for the benefit of [specify person, body or class of person]National Grid Carbon.
[NOTE: This article is required where provisions of the Order are specific to a named undertaker or class of undertaker (see section 156(2) of the 2008 Act).]
Consent to transfer
Paragraph (1) does not apply to the benefit of the consent granted by this Order for works carried out (1)
by the undertaker for the benefit or protection of land or persons (including statutory undertakers) affected
by the authorised development.
Transfer of benefit of Order
8
(1)—a) The undertaker may, with the consent of the [specify person or body] --Secretary of 9.
State—
transfer to another person (“the transferee”) any or all of the benefit of the provisions of this (a)
Order and such related rights as may be agreed between the undertaker and the transferee; or
grant to another person ("“the lessee"”) for a period agreed between the undertaker and the(b)
lessee any or all of the benefit of the provisions of this Order and such related statutory rights
as may be so agreed.
(2) Where an agreement has been made in accordance with paragraph (1) references in this Order to(1)
the undertaker, except in paragraph (3), shall include references to the transferee or the lessee.
12 12
(p) 1974 c.40; sections 61 and 65 are amended by section 133 of the Building Act 1984 (c.55), Schedule 24 to the Environment Act 1995 (c.25) and section 162 of, and Schedule 15 to, the Environmental Protection Act 1990 (c.43); there are other amendments
not relevant to this Order.
(q) Section 48 is amended by the Local Transport Act 2008 (c. 26) s.124(2); section 51 is amended by Schedule 1 to the Traffic Management Act 2004 (c.18).
Page 34 of 99
Street works
9
(1)—a) The undertaker may, for the purposes of the authorised projectdevelopment, enter on so10.
much of any of the streets specified in Schedule B4 (streets subject to street works) as is within the
Order limits and may--—
break up or open the street, or any sewer, drain or tunnel under it (including for the purposes of (a)
carrying out surveys to ascertain the location of apparatus);
tunnel or bore under the street;(b)
place apparatus in the street;(c)
maintain apparatus in the street or change its position; and(d)
execute any works required for or incidental to any works referred to in sub-paragraphs (a), (b), (e)
(c) and to (d) above.
(2) The authority given by paragraph (1) is a statutory right for the purposes of sections 48(3)(1)
(streets, street works and undertakers) and 51(1) (prohibition of unauthorised street works) of the 1991
Act(q).
(3) The provisions of sections 54 to 106 of the 1991 Act apply to any street works carried out under(2)
paragraph (1). save that—
(4) In this article "apparatus" has the same meaning as in Part 3 of the 1991 Act.
[NOTE: This article should not be used for the purposes of authorising street works that affect a trunk road (as defined in the 1980 Act); no trunk roads should be specified in Schedule B (streets subject to street works). For any street works affecting a trunk road the undertaker should make an application for a licence under section 50 of the 1991 Act.]
section 61(1) of the 1991 Act (under which the consent of the street authority is required for the (a)
placing of apparatus in a protected street) does not apply to the placing of apparatus in the
course of the authorised development;
section 62(2) of the 1991 Act (power following the designation of a protected street to require (b)
removal or repositioning of apparatus already placed in the street) does not, unless otherwise
agreed with the undertaker, apply in relation to apparatus placed in the course of the authorised
development;
section 62(4) of the 1991 Act (power when a designation as a protected street commences or (c)
ceases to give directions with respect to works in progress) does not, unless otherwise agreed
with the undertaker, apply in relation to the authorised development.
In this article “apparatus” and “street works” have the same meanings as in Part 3 of the 1991 Act (3)
save that “apparatus” further includes pipelines (and parts of them), aerial markers, cathodic protection
test posts, field boundary markers, transformer rectifier kiosks and electricity cabinets.
Power to alter layout, etc., of streets
—a) The undertaker may alter the layout of a street specified in column (2) of Schedule 5 11.
(streets subject to alteration of layout) in the manner specified in relation to that street in column (3).
Without prejudice to the specific powers conferred by article 4 (development consent etc. granted (1)
by the Order) or paragraph (4) but subject to paragraph (3), the undertaker may, for the purposes of
constructing and maintaining the authorised development, alter the layout of any street within the Order
13 13
(3) The exercise by a person of any benefits or rights conferred in accordance with any transfer or(2)
grant under paragraph (1) shall beis subject to the same restrictions, liabilities and obligations as would
apply under this Order if those benefits or rights were exercised by the undertakerNational Grid Carbon.
Streets
limits and the layout of any street having a junction with such a street; and, without limiting the scope of
this paragraph, the undertaker may—
increase the width of the carriageway of the street by reducing the width of any kerb, footpath, (a)
footway, cycle track, verge or central reservation within the street;
alter the level or increase the width of any such kerb, footpath, footway, cycle track, verge or (b)
central reservation;
reduce the width of the carriageway of the street;(c)
make crossovers and passing places;(d)
carry out works for the provision or alteration of parking places, loading bays and cycle tracks; (e)
and
execute any works required for or incidental to any works referred to in sub-paragraphs (a) to (f)
(e) above.
The powers conferred by paragraph (2) must not be exercised without the consent of the street (2)
authority but such consent must not be unreasonably withheld or delayed.
The undertaker may, for the purposes of the authorised development, enter on so much of any of the (3)
streets specified in Schedule 4 (streets subject to street works) and Schedule 5 (streets subject to
alteration of layout) as is within the Order limits and may—
demolish, remove, replace and relocate any bus shelter and associated bus stop infrastructure;(a)
execute any works to provide or improve sight lines required by the highway authority;(b)
remove and replace kerbs and flume ditches for the purposes of creating permanent and (c)
temporary accesses;
execute and maintain any works to provide hard and soft landscaping;(d)
carry out re-lining and placement of new temporary markings; and(e)
execute any works required for or incidental to any works referred to in sub-paragraphs (a) to (f)
(e) above.
Construction and maintenance of new or, altered or diverted streets
10
(1) —a) Any street (other than [insert relevant private streets]) to be constructed under this12.
Order shallin respect of which the undertaker has given the highway authority notice that this
paragraph applies must be completed to the reasonable satisfaction of the highway authority and,
unless otherwise agreed with the highway authority, shallmust be maintained by and at the expense of
the undertaker for a period of [12 months] from its completion and at the expiry of that period by and
at the expense of the highway authority.
Where a street is altered or diverted under this Order, the altered or diverted part of the street(1)
shallmust, when completed to the reasonable satisfaction of the street authority, unless otherwise agreed
with the street authority, be maintained by and at the expense of the undertaker for a period of [12 months]
from its completion and at the expiry of that period by and at the expense of the street authority.
Where any street not previously part of the public highway is constructed pursuant to this Order it (2)
will on the undertaker giving notice to the highway authority (and street authority if different) that this
paragraph applies be deemed to be dedicated for public use as highway on the completion of that street.
(3) Paragraphs (1) and (2to (3) do not apply in relation to the structure of any bridge or tunnel (3)
carrying a street over or under any railway of the undertaker.
(4) In any action against the undertaker in respect of loss or damage resulting from any failure by it(4)
to maintain a street under this article, it shallwill be a defence (without prejudice to any other defence or
the application of the law relating to contributory negligence) to prove that the undertaker had taken such
care as in all the circumstances was reasonably required to secure that the part of the street to which the
action relates was not dangerous to traffic.
(5) For the purposes of a defence under paragraph (45), the court shallmust in particular have regard(5)
to the following matters--—
the character of the street and the traffic which was reasonably to be expected to use it;(a)
the standard of maintenance appropriate for a street of that character and used by such traffic;(b)
14 14
the state of repair in which a reasonable person would have expected to find the street;(c)
Page 35 of 99
whether the undertaker knew, or could reasonably have been expected to know, that the(d)
condition of the part of the street to which the action relates was likely to cause danger to users
of the street;
where the undertaker could not reasonably have been expected to repair that part of the street(e)
before the cause of action arose, what warning notices of its condition had been displayed,
but for the purposes of such a defence it is not relevant to prove that the undertaker had arranged for a
competent person to carry out or supervise the maintenance of the part of the street to which the action
relates unless it is also proved that the undertaker had given the competent person proper instructions
with regard to the maintenance of the street and that the competent person had carried out those
instructions.
(6) Nothing in this article shall--— (6)
prejudices the operation of section 87 of the 1991 Act (prospectively maintainable highways);(a)
and the undertaker shallis not by reason of any duty under that article to maintain a street be
taken to be a street authority in relating to that street for the purposes of Part 3 of that Act; or
haves effect in relation to the street works with regard to which the provisions of Part 3 of the(b)
1991 Act apply.
StoppingPermanent stopping up of streets 11
(1)—a) Subject to the provisions of this article, the undertaker may, in connection with the13.
carrying out of the authorised project, stop up each of the streets specified in columns (1) and (2)
of Parts 1 and 2 of Schedule C (streets to be stopped up) to the extent specified, by reference to
the letters and numbers shown on the works plan, in column (3) of those Parts of that
Scheduledevelopment stop up any street with the consent of the highway authority, which must not be
unreasonably withheld or delayed but the highway authority may attach reasonable conditions to any
such consent.
(2) No street specified in columns (1) and (2) of Part 1 of Schedule C (being a street to be stopped up(1)
pursuant to sub-paragraph 13 for which the highway authority acting reasonably requires a substitute is to
be provided) shall may be wholly or partly stopped up under this article unless--—
the new street to be substituted for it, which is specified in column (4) of that Part of that (a)
Schedule, has been completed to the reasonable satisfaction of the street authority and is open
for use; or
a temporary alternative route for the passage of such traffic as could have used the street to be(b)
stopped up is first provided and subsequently maintained by the undertaker, to the reasonable
satisfaction of the street authority, between the commencement and termination points for the
stopping up of the street until the completion and opening of the new street in accordance with
sub-paragraph (a).
(3) No street specified in columns (1) and (2) of Part 2 of Schedule C (being a street to be stopped up (2)
pursuant to this article for which no substitute is to be provided) shall may be wholly or partly stopped up
under this article unless the condition specified in paragraph (4) is satisfied in relation to all the land which
abuts on either side of the street to be stopped up.
(4) The condition referred to in paragraph (3) is that--—(3)
the undertaker is in possession of the land; or(a)
there is no right of access to the land from the street concerned; or(b)
there is reasonably convenient access to the land otherwise than from the street concerned; or(c)
the owners and occupiers of the land have agreed to the stopping up.(d)
(5) Where a street has been stopped up under this article--—(4)
all rights of way over or along the street so stopped up shall beare extinguished; and(a)
the undertaker may appropriate and use for the purposes of the authorised projectdevelopment(b)
so much of the site of the street as is bounded on both sides by land owned by the undertaker or
as is otherwise provided in this Order.
15 15
Page 36 of 99
Page 37 of 99
16 16
Any person who suffers loss by the suspension or extinguishment of any private right of way under(5)
this article shall beis entitled to compensation to be determined, in case of dispute, under Part 1 of the
1961 Act.
This article is subject to article 39 15 (apparatus etcand rights of statutory undertakers in stopped (6)
up streets). Application of the 1991 Act
12
Works carried out under this Order in relation to a highway which consists of or includes a carriageway shall be treated for the purposes of Part 3 of the 1991 Act (street works) as major transport works if--
(a)they are of a description mentioned in any of paragraphs (a), (c) to (e), (g) and (h) of section 86(3) of that Act (which defines what highway authority works are major highway works); or
(b)they are works which, had they been carried out by the highway authority, might have been carried out in exercise of the powers conferred by section 64 of the 1980 Act (dual carriageways and roundabouts).
Public rights of way
13
(1) With effect from the [date of publication of this Order] [the date of certification by the local highway authority that the agreed alternative right of way has been created to the standard defined in the implementation plan], [the section of] the public right of way (being a [insert one of: footpath/bridleway/byway open to all traffic/restricted byway]) shown marked in [red] between the points [A] and [B] on the rights plan is extinguished.
(2) With effect from [that same date] [insert later date] an alternative section of [insert description of right of way of that same type] as marked in [green] between the points [C] and [D] on the rights plan is created.
(3) In this article--
"implementation plan" means the written plan agreed between the undertaker and the local highway authority for creation of the agreed alternative right of way to the defined standard; and
"local highway authority" has the same meaning as in section 329(1) of the 1980 Act. Temporary
stopping up of streets and public rights of way
14
(1)—a) The undertaker, during and for the purposes of carrying out the authorised14.
projectdevelopment, may temporarily stop up, alter or divert any street or any public right of way and
may for any reasonable time--—
divert the traffic or a class of traffic from the street or public right of way; and(a)
subject to paragraph (2), prevent all persons from passing along the street or public right of (b)
way.
(2) The undertaker shallmust provide reasonable access for pedestrians going to or from premises(1)
abutting a street or public right of way affected by the temporary stopping up, alteration or diversion of a
street or public right of way under this article if there would otherwise be no such access.
(3) Without prejudice to the generality of paragraph (1), the undertaker may temporarily stop up,(2)
alter or divert the streets or public rights of way specified in columns (1) and (2) of Parts 1 and 2 of
Schedule D6 (streets and public rights of way to be temporarily stopped up) to the extent specified, by
reference to the letters and numbers shown on the works planaccess, rights of way and temporary stopping
up plans, in column (3) of Parts 1 and 2 of that Schedule.
(4) The undertaker shallmay not temporarily stop up, alter or divert--—(3)
any street or public right of way specified as mentioned in paragraph (3) without first(a)
consulting the streethighway authority; and
any other street or public right of way without the consent of the streethighway authority which, (b)
which must not be unreasonably withheld or delayed but the highway authority may attach
reasonable conditions to any such consent.
(5) Any person who suffers loss by the suspension of any private right of way under this article shall (4)
beis entitled to compensation to be determined, in case of dispute, under Part 1 of the 1961 Act.
Apparatus and rights of statutory undertakers in permanently stopped up streets
—a) Where a street is stopped up under article 13 (permanent stopping up of streets), any 15.
statutory utility whose apparatus is under, in, on, along or across the street has the same powers and
rights in respect of that apparatus, subject to the provisions of this article, as if this Order had not
been made.
Where a street is stopped up under article 13 (permanent stopping up of streets), any statutory (1)
utility whose apparatus is under, in, on, over, along or across the street may, and if reasonably requested to
do so by the undertaker must—
remove the apparatus and place it or other apparatus provided in substitution for it in such other (a)
position as the utility may reasonably determine and have power to place it; or
provide other apparatus in substitution for the existing apparatus and place it in such position as (b)
described in sub-paragraph (a).
Subject to the following provisions of this article, the undertaker must pay to any statutory utility an (2)
amount equal to the cost reasonably incurred by the utility in or in connection with—
the execution of the relocation works required in consequence of the stopping up of the street; (a)
and
the doing of any other work or thing rendered necessary by the execution of the relocation (b)
works.
If in the course of the execution of relocation works under paragraph (2)—(3)
apparatus of a better type, of greater capacity or of greater dimensions is placed in substitution (a)
for existing apparatus; or
apparatus (whether existing apparatus or apparatus substituted for existing apparatus) is placed (b)
at a depth greater than the depth at which the existing apparatus was,
and the placing of apparatus of that type or capacity or of those dimensions or the placing of apparatus at
that depth, as the case may be, is not agreed by the undertaker, or, in default of agreement, is not
determined by arbitration to be necessary, then, if it involves cost in the execution of the relocation
works exceeding that which would have been involved if the apparatus placed had been of the existing
type, capacity or dimensions, or at the existing depth, as the case may be, the amount which, apart from
this paragraph, would be payable to the statutory utility by virtue of paragraph (3) must be reduced by
the amount of that excess.
For the purposes of paragraph (4)—(4)
an extension of apparatus to a length greater than the length of existing apparatus is not to be (a)
treated as a placing of apparatus of greater dimensions than those of the existing apparatus; and
where the provision of a joint in a cable is agreed, or is determined to be necessary, the (b)
consequential provision of a jointing chamber or of a manhole is to be treated as if it also had
been agreed or had been so determined.
An amount which, apart from this paragraph, would be payable to a statutory utility in respect of (5)
works by virtue of paragraph (3) (and having regard, where relevant, to paragraph (4)) must, if the works
include the placing of apparatus provided in substitution for apparatus placed more than 7 years and 6
months earlier so as to confer on the utility any financial benefit by deferment of the time for renewal of
the apparatus in the ordinary course, be reduced by the amount which represents that benefit.
Paragraphs (3) to (6) do not apply where the authorised development constitutes major highway (6)
works, major bridge works or major transport works for the purposes of Part 3 of the 1991 Act, but
instead—
17 17
the allowable costs of the relocation works must be determined in accordance with section 85 of (a)
that Act (sharing of cost of necessary measures) and any regulations for the time being having
effect under that section; and
the allowable costs must be borne by the undertaker and the statutory utility in such proportions (b)
as may be prescribed by any such regulations.
In this article—(7)
“apparatus” has the same meaning as in Part 3 of the 1991 Act;
“relocation works” means work executed, or apparatus provided, under paragraph (2); and
“statutory utility” means a statutory undertaker for the purposes of the 1980 Act or a public
communications provider as defined in section 151(1) of the Communications Act 2003(r).
Access to works
15
The undertaker may, for the purposes of the construction and/or the maintenance of the 16.
authorised project--development—
form and lay out means of access, or improve existing means of access, in the locationas(a)
specified in columns (1) and (2) of Parts 1 and 2 of Schedule E7 (access to works); and
with the approval of the relevant planning authority, which is not to be unreasonably withheld (b)
or delayed, after consultation with the highway authority, form and lay out such other means of
access or improve existing means of access, at such locations within the Order limits as the
undertaker reasonably requires for the purposes of the authorised projectdevelopment.
Traffic regulation
—a) Subject to the provisions of this article and the consent of the traffic authority in whose 17.
area the road concerned is situated, which consent must not be unreasonably withheld or delayed, the
undertaker may, in so far as may be expedient or necessary for the purposes of or in connection with
construction, operation, or maintenance of the authorised development—
revoke, amend or suspend in whole or in part any order made, or having effect as if made, under (a)
the 1984 Act;
permit, prohibit or restrict the stopping, parking, waiting, loading or unloading of vehicles on (b)
any road;
authorise the use as a parking place of any road;(c)
make provision as to the direction or priority of vehicular traffic on any road; and(d)
permit or prohibit vehicular access to any road;(e)
either at all times or at times, on days or during such periods as may be specified by the undertaker.
The undertaker may not exercise the powers in paragraph (1) unless it has—(1)
given not less than 4 weeks’ notice in writing of its intention so to do to the chief officer of (a)
police and to the traffic authority in whose area the road is situated; and
advertised its intention in such manner as the traffic authority may specify in writing within 7 (b)
days of its receipt of notice of the undertaker’s intention under sub-paragraph (a).
Any prohibition, restriction or other provision made by the undertaker under paragraph (1)—(2)
has effect as if duly made by, as the case may be—(a)
the traffic authority in whose area the road is situated as a traffic regulation order under (i)
the 1984 Act; or
the local authority in whose area the road is situated as an order under section 32 of the (ii)
1984 Act; and
is deemed to be a traffic order for the purposes of Schedule 7 to the Traffic Management Act (b)
2004(s) (road traffic contraventions subject to civil enforcement).
18 18
(r) 2003 c.21.
(b) 2004 c.18.
Page 38 of 99
(2)The undertaker may in constructing any new level crossing alter the level of any highway specified in Schedule K.
(3)The highway authority and the undertaker may enter into agreements with respect to the construction and maintenance of any new level crossing; and such an agreement may contain such terms as to payment or otherwise as the parties consider appropriate.
(4)In this article--
"new level crossing" means the place at which the railway is authorised by this article to cross a highway on the level; and"the railway" means the railway authorised to be constructed by
this Order. Railway and navigation undertakings
19 19
Any prohibition, restriction or other provision made under this article may be suspended, varied or (3)
revoked by the undertaker from time to time by subsequent exercise of the powers conferred by paragraph
(1) at any time.
Before complying with the provisions of paragraph (2) the undertaker must consult the chief officer (4)
of police and the traffic authority in whose area the road is situated.
Expressions used in this article and in the 1984 Act have the same meaning in this article as in that (5)
Act.
Agreements with street authorities
16
(1)—a) A street authority and the undertaker may enter into agreements with respect to--—18.
the construction of any new street, including any structure carrying the street over or under a (a)
railwayany part of the authorised by this Orderdevelopment;
the maintenance of the structurestrengthening, improvement, repair or reconstruction of any(b)
bridge or tunnel carrying a street over or under a railway;the powers conferred by this Order;
any stopping up, alteration or diversion of a street authorised by this Order; or(c)
the carrying out in the street of any of the works referred to in article 9 10(1) (street works).(d)
(2) Such an agreement may, without prejudice to the generality of paragraph (1)--—(1)
make provision for the street authority to carry out any function under this Order which relates(a)
to the street in question;
include an agreement between the undertaker and street authority specifying a reasonable time(b)
for the completion of the works; and
contain such terms as to payment and otherwise as the parties consider appropriate. (c)
Construction of bridges and tunnels
17
Any bridge or tunnel to be constructed under this Order for carrying a highway over or under a railway shall be constructed in accordance with the plans and specifications approved by the relevant planning authority after consultation with the highway authority.
Level Crossings
18
(1) The undertaker may construct the railway so as to carry it on the level across the highways specified in Schedule K.
(t) 1991 c.56; section 106 is amended by sections 36(2) and 99 of the Water Act 2003 (c.37); there are other amendments to this section which are not relevant to this Order.
Page 39 of 99
(4) The undertaker shallmust not make any opening into any public sewer or drain except--—(3)
in accordance with plans approved by the person to whom the sewer or drain belongs, but such(a)
approval shallmust not be unreasonably withheld or delayed; and
where that person has been given the opportunity to supervise the making of the opening.(b)
(5) The undertaker shallmust not, in carrying out or maintaining works pursuant to this article,(4)
damage or interfere with the bed or banks of any watercourse forming part of a main river.
(6) The undertaker shallmust take such steps as are reasonably practicable to secure that any water(5)
discharged into a watercourse or public sewer or drain pursuant to this article is as free as may be
practicable from gravel, soil or other solid substance, oil or matter in suspension.; but nothing in this Order
requires the undertaker to maintain a watercourse or public sewer or drain or the drainage works.
(7) This article does not authorise the discharge or entry into controlledinland fresh waters or coastal(6)
waters of any matter whose entry or discharge into controlledthose waters is prohibited by section 85(1),
20 20
19
(1) Subject to the following provisions of this article, the undertaker may not under article 9 (street works) break up or open a street where the street, not being a highway maintainable at public expense (within the meaning of the 1980 Act)--
(a)is under the control or management of, or is maintainable by, railway or tramway undertakers or a navigation authority; or
(b)forms part of a level crossing belonging to any such undertakers or to such an authority or to any other person,
except with the consent of the undertakers or authority or, as the case may be, of the person to whom the level crossing belongs.
(2) Paragraph (1) shall not apply to the carrying out under this Order of emergency works, within the meaning of Part 3 of the 1991 Act.
(3) A consent given for the purpose of paragraph (1) may be made subject to such reasonable conditions as may be specified by the person giving it but shall not be unreasonably withheld.
(4) In this paragraph "navigation authority" means any person who has a duty or power under any enactment to work, maintain, conserve, improve or control any canal or other inland navigation, navigable river, estuary or harbour.
Supplemental Ppowers
Discharge of water
20
(1) —a) The undertaker may use any watercourse or any public sewer or drain for the drainage19.
of water in connection with the carrying out or maintenance of the authorised projectdevelopment and
for that purpose may lay down, take up and alter pipes and may, on any land within the Order limits,
make openings into, and connections with, the watercourse, public sewer or drain.
Any dispute arising from the making of connections to or the use of a public sewer or drain by the(1)
undertaker pursuant to paragraph (1) shallis to be determined as if it were a dispute under section 106 of
the Water Industry Act 1991(t) (right to communicate with public sewers).
The undertaker shallmust not discharge any water into any watercourse, public sewer or drain except(2)
with the consent of the person to whom it belongs; and such consent may be given subject to such terms
and conditions as that person may reasonably impose, but shallmust not be unreasonably withheld or
delayed.
(u) S.I. 2010/675.
(v) 1991 c.57.
Page 40 of 99
a right under sub-paragraph (4)(a) to enter a building and land within its curtilage; or(c)
a right under sub-paragraph (4)(b) to enter land,(d)
the undertaker shallmust, except in the case of emergency, serve on the owners and occupiers of the
building or land not less than 14 days'’ notice of its intention to exercise that right and, in a case falling
within subparagraph sub-paragraph (a) or (c), specifying the protective works proposed to be carried
out.
(6) Where a notice is served under sub-paragraph (5)(a), (5)(c) or (5)(d), the owner or occupier of(5)
the building or land concerned may, by serving a counter-notice within the period of 10 days beginning
with the day on which the notice was served, require the question whether it is necessary or expedient to
carry out the protective works or to enter the building or land to be referred to arbitration under article 521
(arbitration).
(7) The undertaker shallmust compensate the owners and occupiers of any building or land in(6)
relation to which rights under this article have been exercised for any loss or damage arising to them by
reason of the exercise of those rights.
21 21
(2) or (3) of the Water Resources Act 1991 (offences of polluting waterregulation 38 of the Environmental
Permitting (England and Wales) Regulations 2010(u).
(8) In this article--— (7)
"“public sewer or drain"” means a sewer or drain which belongs to the Homes and (a)
Communities Agency, the Environment Agency, a harbour authority within the meaning of
section 57 of the Harbours Act 1964, an internal drainage board, a joint planning board, a local
authority, a National Park Authority, or a sewerage undertaker or an urban development
corporation;
“watercourse” includes all rivers, streams, ditches, drains, canals, cuts, culverts, dykes, sluices, (b)
sewers and passages through which water flows except a public sewer or drain; and
(b) other expressions, excluding watercourse, used both in this article and in the Water(c)
Resources Act 1991(v) have the same meaning as in that Act.
Protective work to buildings 21
(1)—a) Subject to the following provisions of this article, the undertaker may at its own expense20.
carry out such protective works to any building lying within the Order limits as the undertaker
considers necessary or expedient.
(2) Protective works may be carried out--—(1)
at any time before or during the carrying out in the vicinity of the building of any part of the(a)
authorised projectdevelopment; or
after the completion of that part of the authorised projectdevelopment in the vicinity of the(b)
building at any time up to the end of the period of 5 years beginning with the day on which that
part of the authorised project is first opened for usedevelopment is first brought into operational
use for the purpose for which it was designed.
(3) For the purpose of determining how the functions under this article are to be exercised the(2)
undertaker may enter and survey any building falling within paragraph (1) and any land within its
curtilage.
(4) For the purpose of carrying out protective works under this article to a building the undertaker(3)
may (subject to paragraphs (5) and (6))--—
enter the building and any land within its curtilage; and(a)
where the works cannot be carried out reasonably conveniently without entering land which is(b)
adjacent to the building but outside its curtilage, enter the adjacent land (but not any building
erected on it).
(5) Before exercising--—(4)
a right under paragraph (1) to carry out protective works to a building;(a)
a right under paragraph (3) to enter a building and land within its curtilage;(b)
Page 41 of 99
The power conferred by sub-paragraph (1)(c) includes without prejudice to the generality of that (1)
sub-paragraph the power to take, and process, samples of or from any of the following found on, in or over
the land—
water;(a)
air;(b)
soil or rock;(c)
its flora;(d)
bodily excretions, or dead bodies, of non-human creatures; or(e)
any non-living thing present as a result of human action.(f)
(2) No land may be entered or equipment placed or left on or removed from the land under paragraph(2)
(1) unless at least 14 days’ notice has been served on every owner and occupier of the land.
(3) Any person entering land under this article on behalf of the undertaker--—(3)
shallmust, if so required entering the land, produce written evidence of their authority to do so;(a)
and
may take with them such vehicles and equipment as are necessary to carry out the survey or,(b)
investigation, monitoring, or to make the trial holes.
(4) No trial holes shallmay be made under this article--—(4)
in land located within the highway boundary without the consent of the highway authority; or(a)
22 22
(8) Where--—(7)
protective works are carried out under this article to a building; and(a)
within the period of 5 years (beginning with the day on which the part of the authorised(b)
projectdevelopment carried out in the vicinity of the building is first opened for usebrought
into operational use for the purpose for which it was designed) it appears that the protective
works are inadequate to protect the building against damage caused by the carrying out or use
of that part of the authorised projectdevelopment,
the undertaker shallmust compensate the owners and occupiers of the building for any loss or damage
sustained by them.
(9) Nothing in this article shall relieverelieves the undertaker from any liability to pay(8)
compensation under section 10(2) of the 1965 Act (compensation for injurious affection).
(10) Any compensation payable under paragraph (7) or (8) shallmust be determined, in case of(9)
dispute, under Part 1 of the 1961 Act ((determination of questions of disputed compensation).
(11) In this article "“protective works"” in relation to a building means--—(10)
underpinning, strengthening and any other works the purpose of which is to prevent damage(a)
which may be caused to the building by the carrying out, maintenance or use of the authorised
projectdevelopment; and
any works the purpose of which is to remedy any damage which has been caused to the building(b)
by the carrying out, maintenance or use of the authorised projectdevelopment.
Authority to survey and investigate the land 22
(1)—a) The undertaker may for the purposes of this Order enter on any land shown within the21.
Order limits or which may be affected by the authorised projectdevelopment and--—
survey and/or investigate the land;(a)
without prejudice to the generality of sub-paragraph (a), make trial holes in such positions on(b)
the land as the undertaker thinks fit to investigate the nature of the surface layer and/or subsoil
and/or to remove soil samples;
without prejudice to the generality of sub-paragraph (a), carry out ecological and/or(c)
archaeological investigations on suchthe land; and/or
place on, leave on and remove from the land apparatus for use in connection with the survey(d)
and/or investigation of land and, the making of trial holes.
Page 42 of 99 representative or relative as that person claims to be, or that the remains in question can
be identified, the question shallmust be determined on the application of either party in a summary
manner by the county court, and the court may make an order specifying who shallmust remove the
remains and as to the payment of the costs of the application.
(8) The undertaker shallmust pay the reasonable expenses of removing and re-interring or(7)
cremating the remains of any deceased person under this article.
(9) If--—(8)
within the period of 56 days referred to in paragraph (5) no notice under that paragraph has(a)
been given to the undertaker in respect of any remains in the specified land; or
such notice is given and no application is made under paragraph (7) within 56 days after the(b)
giving of the notice but the person who gave the notice fails to remove the remains within a
further period of 56 days; or
within 56 days after any order is made by the county court under paragraph (7) any person,(c)
other than the undertaker, specified in the order fails to remove the remains; or
it is determined that the remains to which any such notice relates cannot be identified,(d)
subject to paragraph (10) the undertaker shallmust remove the remains and cause them to be
reinterredre-interred in such burial ground or cemetery in which burials may legally take place as the
23 23
in a private street without the consent of the street authority, but such consent shall not be (b)
unreasonably withheld.
but such consent must not be unreasonably withheld or delayed.
(5) The undertaker shallmust compensate the owners and occupiers of the land for any loss or(5)
damage arising by reason of the exercise of the authority conferred by this article, such compensation to be
determined, in case of dispute, under Part 1 of the 1961 Act (determination of questions of disputed
compensation) of the 1961 Act.
Removal of human remains 23
(1) —a) In this article "“the specified land"” means [insert description of the land]any land 22.
within the Order limits.
(2) Before the undertaker carries out any development or works which will or may disturb any(1)
human remains in the specified land it shallmust remove those human remains from the specified land,
or cause them to be removed, in accordance with the following provisions of this article.
(3) Before any such remains are removed from the specified land the undertaker shallmust give(2)
notice of the intended removal, describing the specified land and stating the general effect of the
following provisions of this article, by--—
publishing a notice once in each of two successive weeks in a newspaper circulating in the area(a)
of the authorised projectdevelopment; and
displaying a notice in a conspicuous place on or near to the specified land.(b)
(4) As soon as reasonably practicable after the first publication of a notice under paragraph (3)(3)
the undertaker shallmust send a copy of the notice to [insertthe relevant localplanning authority].
(5) At any time within 56 days after the first publication of a notice under paragraph (3) any(4)
person who is a personal representative or relative of any deceased person whose remains are interred
in the specified land may give notice in writing to the undertaker of that person'’s intention to
undertake the removal of the remains.
(6) Where a person has given notice under paragraph (5), and the remains in question can be(5)
identified, that person may cause such remains to be--—
removed and re-interred in any burial ground or cemetery in which burials may legally take(a)
place; or
removed to, and cremated in, any crematorium,(b)
and that person shallmust, as soon as reasonably practicable after such re-interment or cremation,
provide to the undertaker a certificate for the purpose of enabling compliance with paragraph (11).
(7) If the undertaker is not satisfied that any person giving notice under paragraph (5) is(6)
the personal
undertaker thinks suitable for the purpose; and, so far as possible, remains from individual graves
shallmust be reinterredre-interred in individual containers which shallmust be identifiable by a record
prepared with reference to the original position of burial of the remains that they contain.
(10) If the undertaker is satisfied that any person giving notice under paragraph (5) is the(9)
personal representative or relative as that person claims to be and that the remains in question can be
identified, but that person does not remove the remains, the undertaker shallmust comply with any
reasonable request that person may make in relation to the removal and re-interment or cremation of
the remains.
(11) On the re-interment or cremation of any remains under this article--—(10)
a certificate of re-interment or cremation shallmust be sent by the undertaker to the Registrar(a)
General by the undertaker giving the date of re-interment or cremation and identifying the place
from which the remains were removed and the place in which they were reinterredre-interred or
cremated; and
a copy of the certificate of re-interment or cremation and the record mentioned in paragraph (9)(b)
shallmust be sent by the undertaker to [insertthe relevant localplanning authority] mentioned in
paragraph (4).
(12) The removal of the remains of any deceased person under this article shallmust be carried(11)
out in accordance with any directions which may be given by the Secretary of State.
(13) Any jurisdiction or function conferred on the county court by this article may be exercised(12)
by the district judge of the court.
(14) Section 25 of the Burial Act 1857(w) (bodies not to be removed from burial grounds, save(13)
under faculty, without licence of Secretary of State) shalldoes not apply to a removal carried out in
accordance with this article.
Sections 238 and 239 of the 1990 Act (use and development of consecrated land and burial (14)
grounds) apply—
in relation to land, other than a right over land, acquired for the purposes of the authorised (a)
development (whether or not by agreement), so as to permit use by the undertaker in accordance
with the provisions of this Order; and
in relation to a right over land so acquired (whether or not by agreement), or the temporary use (b)
of land pursuant to articles 28 (temporary use of land for carrying out the authorised
development) and 29 (temporary use of land for maintaining the authorised development), so
as to permit the exercise of that right or the temporary use by the undertaker in accordance with
the provisions of this Order, without prejudice to the status of the land over which the right is
exercised as consecrated land,
and in section 238(1)(b) of the 1990 Act reference to a “planning permission” includes this Order, in
section 240(1) of the 1990 Act reference to “regulations made for the purposes of sections 238(3) and
(4) and 239(2)” means, so far as applicable to land or a right over land acquired under this Order,
paragraphs (2) to (13) of this article and in section 240(3) of the 1990 Act reference to a “statutory
undertaker” includes the undertaker and reference to “any other enactment” includes this Order.
The Town and Country Planning (Churches, Places of Religious Worship and Burial Ground) (15)
Regulations 1950(x) do not apply to the authorised development.
PART 3
ACQUISITION AND POSSESSION OF LAND
Powers of AcquisitionCompulsory acquisition
Compulsory acquisition of land 24
(1) —a) The undertaker may acquire compulsorily so much of the Order land as is required for23.
the authorised project [development or to facilitate it, or is incidental, to it][or is required as
replacement land].
24 24
(w) 1857 c.81; section 25 is amended by the Criminal Justice Act 1982 (c.48.) s.46.
(x) S.I. 1950/792.
Page 43 of 99
As from the date on which a compulsory acquisition notice under section 134(3) (notice of (1)
authorisation of compulsory acquisition) of the 2008 Act is served or the date on which the Order land, or
any part of it, is vested in the undertaker, whichever is the later, all rights, trusts and incidents to which
that land or that part of it which is vested (as the case may be) shall be discharged from all rights, trusts
and incidents to which it was previously subject are discharged or suspended, so far as their continuance
would be inconsistent with the exercise of the powers under this Order.
Any person who suffers loss by the extinguishment or suspension of any private right of way under(2)
this article shall beis entitled to compensation to be determined, in case of dispute, under Part 1 of the
1961 Act.
This article is subject to article 31 (acquisition of land limited to subsoil lying more than 9 metres (3)
beneath surface) and article 35 (temporary use of land for carrying out the authorised project).No interest
in Crown land may be acquired pursuant to this Order unless the appropriate Crown authority consents to
such acquisition.
Compulsory acquisition of land--incorporation of the mineral code
25
[Part(s)] 2 [and 3] of Schedule 2 to the Acquisition of Land Act 1981(minerals) [is/are] incorporated in this Order subject to the modifications that--
(a)paragraph 8(3) is not incorporated;
(b)for "the acquiring authority" substitute "the undertaker";
(c)[insert additional modifications].
Time limit for exercise of authority to acquire land compulsorily
26
(1) After the end of the period of [5 years] beginning on the day on which the Order is made--
(a)no notice to treat shall be served under Part 1 of the 1965 Act; and
(b)no declaration shall be executed under section 4 of the Compulsory Purchase (Vesting Declarations) Act 1981 as applied by article 29 (application of the Compulsory Purchase (Vesting Declarations) Act 1981).
(2) The authority conferred by article 35 (temporary use of land for carrying out the authorised project) shall cease at the end of the period referred to in paragraph (1), save that nothing in this paragraph shall prevent the undertaker remaining in possession of land after the end of that period, if the land was entered and possession was taken before the end of that period.
This Order applies to Crown land only to the extent that the appropriate Crown authority consents to (4)
such application.
In this article, “Crown land” and “the appropriate Crown authority” have the same meaning as that (5)
given in section 227 (“Crown land” and “the appropriate Crown authority”) of the 2008 Act.
This article is subject to article 25 (acquisition of subsoil only) and article 28 (temporary use of (6)
land for carrying out the development).
Compulsory acquisition of rights
27
25 25
(2)As from the date on which a compulsory acquisition notice under section 134(3) of the 2008
Act is
Page 44 of 99
28
(1) Subject to the provisions of this article, all private rights of way over land subject to compulsory acquisition under this Order shall be extinguished--
Acquisition of subsoil only
—a) The undertaker may acquire compulsorily so much of, or such rights in, the subsoil of the 25.
land referred to in paragraph 23(1) of article 23 (compulsory acquisition of land) as may be required
for any purpose for which that land may be acquired under that provision instead of acquiring the
whole of the land.
Where the undertaker acquires any part of, or rights in, the subsoil of land under paragraph (1), the (1)
undertaker is not required to acquire an interest in any other part of the land.
Paragraph (2) does not prevent article 33 (acquisition of part of certain properties) from applying (2)
where the undertaker acquires a cellar, vault, arch or other construction forming part of a house, building
or manufactory.
Power to override easements and other rights
—a) Any authorised activity which takes place on land within the Order limits (whether the 26.
activity is undertaken by the undertaker or by any person deriving title from the undertaker or by any
servants or agents of the undertaker) is authorised by this Order if it is done in accordance with the
terms of this Order, notwithstanding that it involves—
an interference with an interest or right to which this article applies; or(a)
a breach of a restriction as to the user of land arising by virtue of a contract.(b)
In this article “authorised activity” means—(1)
as from the date of acquisition of the land by the undertaker, whether compulsorily or by (a)
agreement; orthe erection, construction or carrying out, operation or maintenance of any part of
the authorised development;
on the date of entry on the land by the undertaker under section 11(1) of the 1965 Act (power of (b)
entry),the exercise of any power authorised by this Order; or
26 26
(1) —a) The undertaker may acquire compulsorily the existing rights and create and acquire24.
compulsorily the new rights described in the book of reference and shown on the land plan [rights
plan]plans.
As from the date on which a compulsory acquisition notice is served or the date on which any new(1)
right is vested in the undertaker, whichever is the later, the land over which any new rights is acquired
shall beis discharged from all rights, trusts and incidents to which it was previously subject so far as their
continuance would be inconsistent with the exercise of that new right.
Subject to section 8 of the 1965 Act, as substituted by article 323 (acquisition of part of certain(2)
properties), where the undertaker acquires an existing right over land under paragraph (1), the undertaker
shallis not be required to acquire a greater interest in that land.
Schedule 13 (modification of compensation and compulsory purchase enactments for creation of (3)
new rights) has effect for the purpose of modifying the enactments relating to compensation and the
provisions of the 1965 Act in their application in relation to the compulsory acquisition under this article
of a right over land by the creation of a new right or the imposition of a restrictive covenant.
(4) Any person who suffers loss as a result of the extinguishment or suspension of any private right(4)
of way under this article shall beis entitled to compensation to be determined, in case of dispute, under Part
1 of the 1961 Act.
Private rights of way
whichever is the earliest.
(2) Subject to the provisions of this article, all private rights of way over land owned by the undertaker which, being within the limits of land which may be acquired shown on the land plan, is required for the purposes of this Order shall be extinguished on the appropriation of the land by the undertaker for any of those purposes.
(3) Subject to the provisions of this article, all private rights of way over land of which the undertaker takes temporary possession under this Order shall be suspended and unenforceable for as long as the undertaker remains in lawful possession of the land.
(4) Any person who suffers loss by the extinguishment or suspension of any private right of way under this article shall be entitled to compensation to be determined, in case of dispute, under Part 1 of the 1961 Act.
(5) This article does not apply in relation to any right of way to which section 138 of the 2008 Act (extinguishment of rights, and removal of apparatus, of statutory undertakers etc) or article 38 (statutory undertakers) applies.
(6) Paragraphs (1) to (3) shall have effect subject to--
(a) any notice given by the undertaker before--
(i)the completion of the acquisition of the land;
(ii)the undertaker's appropriation of it;
(iii)the undertaker's entry onto it; or
(iv)the undertaker's taking temporary possession of it,
that any or all of those paragraphs shall not apply to any right of way specified in the notice;
and
(b) any agreement made at any time between the undertaker and the person in or to whom the right of way in question is vested or belongs.
(7) If any such agreement as is referred to in
the use of any land (including the temporary use of land).(c)
The interests and rights to which this article applies include any easement, liberty, privilege, right or (2)
advantage annexed to land and adversely affecting other land, including any natural right to support and
include restrictions as to the user of land arising by virtue of a contract.
Where an interest, right or restriction is overridden by paragraph (6)(b)-- (1), compensation— (3)
is made with a person in or to whom the right of way is vested or belongs; andis payable (a)
under section 7 or 10 of the 1965 Act(y); and
is expressed to have effect also for the benefit of those deriving title from or under that (b)
person,must be assessed in the same manner and subject to the same rules as in the case of
other compensation under those sections where—
it shall be effective in respect of the persons so deriving title, whether the title was derived before or after the making of the agreement
the compensation is to be estimated in connection with a purchase under that Act; or(i)
the injury arises from the execution of works on or use of land acquired under that Act.(ii)
Nothing in this article may be construed as authorising any act or omission on the part of any person (4)
which is actionable at the suit of any person on any grounds other than such an interference or breach as is
mentioned in paragraph (1) of this article.
27 27
(y) There are amendments that are not relevant to this Order.
(z) 1981 c.66.
Page 45 of 99 compulsory purchase order and as if the undertaker were a public authority under
section 1(2) of that Act.
(2) The Compulsory Purchase (Vesting Declarations) Act 1981, as so applied, shall havehas effect(1)
with the following modifications.
(3) In section 3 (preliminary notices), for subsection (1) there shall beis substituted--—(2)
"“(1) Before making a declaration under section 4 with respect to any land which is subject to a
compulsory purchase order, the acquiring authority shallmust include the particulars specified in
subsection (3) in a notice which is--—
(a) (a) given to every person with a relevant interest in the land with respect to which the
declaration is to be made (other than a mortgagee who is not in possession); and
(b) (b) published in a local newspaper circulating in the area in which the land is situated."”.
(4) In that section, in subsection (2), for "“(1)(b)"” there shall beis substituted "“(1)"” and after(3)
"“given"” thereshall be is inserted "“and published"”.
(5) In that section, for subsections (5) and (6) there shall beis substituted--—(4)
"“(5) For the purposes of this section, a person has a relevant interest in land if--—
(a) (a) that person is for the time being entitled to dispose of the fee simple of the land,
whether in possession or in reversion; or
(b) (b) that person holds, or is entitled to the rents and profits of, the land under a lease or
agreement, the unexpired term of which exceeds one month."”.
(6) In section 5 (earliest date for execution of declaration)--—(5)
in subsection (1), after "“publication"” there shall beis inserted "“in a local newspaper(a)
circulating in the area in which the land is situated"”; and
subsection (2) shall beis omitted.(b)
(7) In section 7 (constructive notice to treat), in subsection (1)(a), the words "“(as modified by(6)
section 4 of the Acquisition of Land Act 1981)" shall be” are omitted.
(8) References to the 1965 Act in the Compulsory Purchase (Vesting Declarations) Act 1981shall (7)
are to be construed as references to that Act as applied by section 125 of the 2008 Act to the compulsory
acquisition of land under this Order.Acquisition of
subsoil only 30
(1)The undertaker may acquire compulsorily so much of, or such rights in, the subsoil of the land referred to in article 24(1) (compulsory acquisition of land) as may be required for any purpose for which that land may be acquired under that provision instead of acquiring the whole of the land.
Temporary possession of land
Temporary use of land for carrying out the authorised development
—a) The undertaker may, in connection with the carrying out of the authorised development—28.
enter on and take temporary possession of— (a)
the land specified in columns (1) and (2) of Schedule 9 (land of which temporary (i)
possession may be taken) for the purpose specified in relation to that land in column (3) of
that Schedule relating to the part of the authorised development specified in column (4) of
that Schedule;
28 28
Application of the Compulsory Purchase (Vesting Declarations) Act 1981
29
(1)—a) The Compulsory Purchase (Vesting Declarations) Act 1981 shall apply(z) applies as if27.
this Order were a
Page 46 of 99
31
(1)This article applies to the land specified in Schedule F (land of which only subsoil more than 9 metres beneath surface may be acquired).
in the case of land specified in paragraph (1)(a)(i) after the end of the period of one year (a)
beginning with the date of completion the authorised development; or
in the case of land referred to in paragraph (1)(a)(ii), after the end of the period of one year (b)
beginning with the date of completion of the authorised development unless the undertaker has,
before the end of that period, served a notice of entry under section 11 of the 1965 Act or made
a declaration under section 4 of the Compulsory Purchase (Vesting Declaration) Act 1981,
and in this paragraph the date on which the authorised development is completed means the date
on which the undertaker has certified that it is first capable of being brought into operational
use for the purpose for which it was designed.
Before giving up possession of land of which temporary possession has been taken under this article, (3)
unless otherwise agreed by the owners of the land, the undertaker must remove all temporary works and
restore the land to the reasonable satisfaction of the owners of the land; but the undertaker is not required
to—
replace a building removed under this article;(a)
restore the land on which any permanent works have been constructed under sub-paragraph (b)
(1)(d); or
remove any ground-strengthening works which have been placed in that land to facilitate (c)
construction of the authorised development.
The undertaker must pay compensation to the owners and occupiers of land of which temporary (4)
possession is taken under this article for any loss or damage arising from the exercise in relation to the
land of the provisions of any power conferred by this article.
Any dispute as to a person’s entitlement to compensation under paragraph (5), or as to the amount of (5)
the compensation, must be determined under Part 1 of the 1961 Act.
Nothing in this article affects any liability to pay compensation under section 10(2) of the 1965 Act (6)
(further provisions as to compensation for injurious affection) or under any other enactment in respect of
29 29
any Order land in respect of which no notice of entry has been served under section 11 of (ii)
the 1965 Act (powers of entry) (other than in connection with the requisition of rights
only) and no declaration has been made under section 4 of the Compulsory Purchase
(Vesting Declarations) Act 1981 (execution of declaration) for the purposes of
constructing and carrying out the authorised development;
remove any buildings and vegetation from the land referred to in paragraphs (1) (a)(i) and (b)
(a)(ii);
construct temporary works (including the provision of means of access) and buildings on the (c)
land referred to in paragraphs (1) (a)(i) and (a)(ii); and
construct and carry out any mitigation works on the land referred to in paragraphs (a)(i) and (d)
(a)(ii).
Where the undertaker acquires any part of, or rights in, the subsoil of land under paragraph (1), the (1)
undertaker shall not be required to acquire an interest in any other part of the land.Not less than 14 days
before entering on and taking temporary possession of land under this article the undertaker must serve
notice of the intended entry on the owners and occupiers of the land.
Paragraph (2) shall not prevent article 32 (acquisition of part of certain properties) from applying (2)
where the undertaker acquires a cellar, vault, arch or other construction forming part of a house, building
or manufactory.The undertaker may not, without the agreement of the owners of the land, remain in
possession of any land under this article—
Acquisition of land limited to subsoil lying more than 9 metres beneath surface
loss or damage arising from the carrying out of the authorised development, other than loss or damage for
which compensation is payable under paragraph (5).
The undertaker may not compulsorily acquire under this Order the land referred to in paragraph (7)
(1)(a)(i), or acquire new rights over any part of that land under article 24 (compulsory acquisition of
rights), or acquire any part of the subsoil (or rights in the subsoil) of that land under article 25 (acquisition
of subsoil only), except that the undertaker is not be precluded from—
carrying out protective works on that land under article 20 (protective work to buildings); or(a)
carrying out a survey on that land under article 21 (authority to survey and investigate the (b)
land).
Where the undertaker takes possession of land under this article, the undertaker is not required to (8)
acquire the land or any interest in it.
Section 13 of the 1965 Act(aa) (refusal to give possession to acquiring authority) applies to the (9)
temporary use of land pursuant to this article to the same extent as it applies to the compulsory acquisition
of land under this Order by virtue of section 125 of the 2008 Act (application of compulsory acquisition
provisions).
Subject to paragraph (3), nothing in this article prevents the taking of temporary possession (10)
pursuant to it more than once in relation to any land specified in paragraph (1).
Temporary use of land for maintaining the authorised development
—a) Subject to paragraph (2) the undertaker may during the maintenance period—29.
enter on and take temporary possession of any land within the Order limits if such possession is (a)
reasonably required for the purpose of maintaining the authorised development;
enter on any land within the Order limits for the purpose of gaining access as is reasonably (b)
required for the purpose of maintaining the authorised development; and
construct such temporary works (including the provision of means of access) and buildings on (c)
the land as may be reasonably necessary for that purpose.
In the case of land to which this article applies, the undertaker may only acquire compulsorily under (1)
article 24 (compulsory acquisition of land) so much of, or such rights in, the subsoil of the land as may be
required for the purposes of the authorised project.Paragraph (1) does not authorise the undertaker to take
temporary possession of—
any house or garden belonging to a house; or(a)
any building (other than a house) if it is for the time being occupied.(b)
Where the undertaker acquires any part of, or rights in, the subsoil of the land to which this article (2)
applies, the undertaker shall not be required to acquire a greater interest in the land or an interest in any
other part of it.Not less than 28 days before entering on and taking temporary possession of land under this
article the undertaker must serve notice of the intended entry on the owners and occupiers of the land,
except as provided in paragraph (12).
References in this article to the subsoil of land are references to the subsoil lying more than 9 metres (3)
beneath the level of the surface of the land; and for this purpose "level of the surface of the land"
means--The undertaker may only remain in possession of land under this article for so long as may be
reasonably necessary to carry out the maintenance of the part of the authorised development for which
possession of the land was taken.
Before giving up possession of land of which temporary possession has been taken under this article, (4)
the undertaker must remove all temporary works and restore the land to the reasonable satisfaction of the
owners of the land.
The undertaker must pay compensation to the owners and occupiers of land of which temporary (5)
possession is taken under this article for any loss or damage arising from the exercise in relation to the
land of the provisions of this article.
Any dispute as to a person’s entitlement to compensation under paragraph (6), or as to the amount of (6)
the compensation, must be determined under Part 1 of the 1961 Act.
Nothing in this article affects any liability to pay compensation under section 10(2) of the 1965 Act (7)
(further provisions as to compensation for injurious affection) or under any other enactment in respect of
30 30
(aa) Section 13 is amended by section 139 of the Tribunals, Courts and Enforcement Act 2007 (c.15).
loss or damage arising from the maintenance of the authorised development, other than loss or damage for
which compensation is payable under paragraph (6).
Where the undertaker takes possession of land under this article, the undertaker is not required to (8)
acquire the land or any interest in it.
Section 13 of the 1965 Act (refusal to give possession to acquiring authority) applies to the (9)
temporary use of land pursuant to this article to the same extent as it applies to the compulsory acquisition
of land under this Order by virtue of section 125 of the 2008 Act (application of compulsory acquisition
provisions).
Where the undertaker has identified a potential risk to the safety of—(10)
the authorised development or any part of it; or(a)
the public; or(b)
the surrounding environment,(c)
the requirement to serve not less than 28 days’ notice under paragraph (3) does not apply and the
undertaker may enter the land pursuant to paragraph (1) subject to giving such period of notice (if any)
as is reasonably practicable in all the circumstances.
In this article the “maintenance period” means in relation to any part of the authorised development (11)
the period of 5 years beginning with the date on which the authorised development is first brought into
operational use for the purpose for which it was designed.
Compensation
Disregard of certain interests and improvements
—a) In assessing the compensation payable to any person on the acquisition from that person of 30.
any land or right over any land under this Order, the tribunal must not take into account—
any interest in land; or(a)
any enhancement of the value of any interest in land by reason of any building erected, works (b)
executed or improvement or alteration made on relevant land,
if the tribunal is satisfied that the creation of the interest, the erection of the building, the execution of
the works or the making of the improvement or alteration as part of the authorised development was not
reasonably necessary and was undertaken with a view to obtaining compensation or increased
compensation.
In paragraph (1) “relevant land” means the land acquired from the person concerned or any other (1)
land with which that person is, or was at the time when the building was erected, the works executed or the
improvement or alteration made as part of the authorised development, directly or indirectly concerned.
Set-off for enhancement in value of retained land
—a) In assessing the compensation payable to any person in respect of the acquisition from that 31.
person under this Order of any land (including the subsoil) the tribunal must set off against the value
of the land so acquired any increase in value of any contiguous or adjacent land belonging to that
person in the same capacity which will accrue to that person by reason of the construction of the
authorised development.
In assessing the compensation payable to any person in respect of the acquisition from that person of (1)
any new rights over land (including the subsoil), under article 24 (compulsory acquisition of rights), the
tribunal must set off against the value of the rights so acquired—
in the case of any land on which a building is erected, the level of the surface of the ground (a)
adjoining the building;any increase in the value of the land over which the new rights are
required; and
in the case of a watercourse or other water area, the level of the surface of the ground nearest to (b)
it which is at all times above water level; orany increase in value of any contiguous or adjacent
land belonging to that person in the same capacity,
which will accrue to that person by reason of the construction of the authorised development.
The 1961 Act has effect, subject to paragraphs (1) and (2), as if this Order were a local enactment (2)
for the purposes of that Act.
31 31
Page 47 of 99
without material detriment to the remainder of the land subject to the counter-notice; or(a)
where the land subject to the notice to treat consists of a house with a park or garden, without(b)
material detriment to the remainder of the land subject to the counter-notice and without
seriously affecting the amenity and convenience of the house,
the notice to treat shall beis deemed to be a notice to treat for that part.
(7) If on such a reference the tribunal determines that--—(6)
the land subject to the notice to treat cannot be taken without material detriment to the(a)
remainder of the land subject to the counter-notice; but
the material detriment is confined to a part of the land subject to the counter-notice,(b)
the notice to treat shall beis deemed to be a notice to treat for the land to which the material detriment is
confined in addition to the land already subject to the notice, whether or not the additional land is land
which the undertaker is authorised to acquire compulsorily under this Order.
(8) If the undertaker agrees to take the land subject to the counter-notice, or if the tribunal(7)
determines that--—
none of the land subject to the notice to treat can be taken without material detriment to the(a)
remainder of the land subject to the counter-notice or, as the case may be, without material
32 32
No double recovery
Compensation is not payable in respect of the same matter both under this Order and under any 32.
other enactment, any contract or any rule of law, or under two or more different provisions under this
Order.
Supplementary
(c) in any other case, ground surface level. Acquisition of part of certain properties
32
(1)—a) This article shall applyapplies instead of section 8(1) of the 1965 Act (other provisions33.
as divided land) (as applied by section 125 of the 2008 Act) where--—
a notice to treat is served on a person ("“the owner"”) under the 1965 Act (as so applied) in(a)
respect of land forming only part of a house, building or manufactory or of land consisting of a
house with a park or garden ("“the land subject to the notice to treat"”); and
a copy of this article is served on the owner with the notice to treat.(b)
(2) In such a case, the owner may, within the period of 21 days beginning with the day on which the(1)
notice was served, serve on the undertaker a counter-notice objecting to the sale of the land subject to the
notice to treat which states that the owner is willing and able to sell the whole ("“the land subject to the
counter-notice"”).
(3) If no such counter-notice is served within that period, the owner shall beis required to sell the(2)
land subject to the notice to treat.
(4) If such a counter-notice is served within that period, the question whether the owner shall beis(3)
required to sell only the land subject to the notice to treat shallmust, unless the undertaker agrees to take
the land subject to the counter-notice, be referred to the tribunal.
(5) If on such a reference the tribunal determines that the land subject to the notice to treat can be(4)
taken--—
without material detriment to the remainder of the land subject to the counter-notice; or(a)
where the land subject to the notice to treat consists of a house with a park or garden, without(b)
material detriment to the remainder of the land subject to the counter-notice and without
seriously affecting the amenity and convenience of the house,
the owner shall be required tomust sell the land subject to the notice to treat.
(6) If on such a reference the tribunal determines that only part of the land subject to the notice to(5)
treat can be taken--—
Page 48 of 99
within the Order limits as may be required for the purposes of the authorised project and may use the subsoil or air-space for those purposes or any other purpose ancillary to the authorised project.
(2) Subject to paragraph (3), the undertaker may exercise any power conferred by paragraph (1) in relation to a street without being required to acquire any part of the street or any easement or right in the street.
(3) Paragraph (2) shall not apply in relation to--
(a)any subway or underground building; or
(b)any cellar, vault, arch or other construction in, on or under a street which forms part of a building fronting onto the street.
(4) Subject to paragraph (5), any person who is an owner or occupier of land appropriated under paragraph (1) without the undertaker acquiring any part of that person's interest in the land, and who suffers loss as a result, shall be entitled to compensation to be determined, in case of dispute, under Part 1 of the 1961 Act.
33 33
detriment to the remainder of the land subject to the counter-notice and without seriously
affecting the amenity and convenience of the house; and
the material detriment is not confined to a part of the land subject to the counter-notice,(b)
the notice to treat shall beis deemed to be a notice to treat for the land subject to the counter-notice
whether or not the whole of that land is land which the undertaker is authorised to acquire compulsorily
under this Order.
(9) Where, by reason of a determination by the tribunal under this article, a notice to treat is deemed(8)
to be a notice to treat for less land or more land than that specified in the notice, the undertaker may,
within the period of 6 weeks beginning with the day on which the determination is made, withdraw the
notice to treat; and, in that event, shallmust pay the owner compensation for any loss or expense
occasioned to the owner by the giving and withdrawal of the notice, to be determined in case of dispute by
the tribunal.
(10) Where the owner is required under this article to sell only part of a house, building or(9)
manufactory or of land consisting of a house with a park or garden, the undertaker shallmust pay the
owner compensation for any loss sustained by the owner due to the severance of that part in addition to the
value of the interest acquired.
Application of the Land Compensation Act 1973
33
(1)Any regulations made by the Secretary of State under section 20 (sound proofing of buildings affected by public works) and 20A (power to make payments in respect of caravans and other structures affected by noise of public works) of the Land Compensation Act 1973 which apply to a railway provided or used in the exercise of statutory powers shall apply to the railway comprised in the authorised project as if that railway was provided or used in the exercise of statutory powers.
(2)Section 28 (power to pay expenses) of the Land Compensation Act 1973 shall have effect as if any works comprised in the authorised project were public works for the purposes of that section.
Rights under or over streets
34
(1) The undertaker may enter on and appropriate so much of the subsoil of, or air-space over,
any street
Page 49 of 99
except that the undertaker shall not be precluded from--
(a)acquiring new rights over any part of that land under article 27 (compulsory acquisition of rights); or
(b)acquiring any part of the subsoil (or rights in the subsoil) of that land under article 30 (acquisition of subsoil only) or in accordance with article 31 (acquisition of land limited to subsoil lying more than 9 metres beneath surface).
34 34
(5) Compensation shall not be payable under paragraph (4) to any person who is an undertaker to whom section 85 of the 1991 Act (sharing cost of necessary measures) applies in respect of measures of which the allowable costs are to be borne in accordance with that section.Temporary use of land for carrying out the
authorised project 35
(1) The undertaker may, in connection with the carrying out of the authorised project--
(a)enter on and take temporary possession of the land specified in columns (1) and (2) of Schedule G (land of which temporary possession may be taken) for the purpose specified in relation to that land in column (3) of that Schedule relating to the part of the authorised project specified in column (4) of that Schedule;
(b)remove any buildings and vegetation from that land; and
(c)construct temporary works (including the provision of means of access) and buildings on that
land.
(2) Not less than 14 days before entering on and taking temporary possession of land under this article the undertaker shall serve notice of the intended entry on the owners and occupiers of the land.
(3) The undertaker may not, without the agreement of the owners of the land, remain in possession of any land under this article after the end of the period of one year beginning with the date of completion of the part of the authorised project specified in relation to that land in column (4) of Schedule G.
(4) Before giving up possession of land of which temporary possession has been taken under this article, the undertaker shall remove all temporary works and restore the land to the reasonable satisfaction of the owners of the land; but the undertaker shall not be required to replace a building removed under this article.
(5) The undertaker shall pay compensation to the owners and occupiers of land of which temporary possession is taken under this article for any loss or damage arising from the exercise in relation to the land of the provisions of this article.
(6) Any dispute as to a person's entitlement to compensation under paragraph (5), or as to the amount of the compensation, shall be determined under Part 1 of the 1961 Act.
(7) Nothing in this article shall affect any liability to pay compensation under section 10(2) of the
1965Act (further provisions as to compensation for injurious affection) or under any other enactment in respect of loss or damage arising from the carrying out of the authorised project, other than loss or damage for which compensation is payable under paragraph (5).
(8) The undertaker may not compulsorily acquire under this Order the land referred to in
paragraph (1)
Page 50 of 99
temporary use of land pursuant to this article to the same extent as it applies to the compulsory acquisition of land under this Order by virtue of section 125 of the 2008 Act (application of compulsory acquisition provisions).
35 35
(9)Where the undertaker takes possession of land under this article, the undertaker shall not be required to acquire the land or any interest in it.
(10)Section 13 of the 1965 Act (refusal to give possession to acquiring authority) shall apply to the temporary use of land pursuant to this article to the same extent as it applies to the compulsory acquisition of land under this Order by virtue of section 125 of the 2008 Act (application of compulsory acquisition provisions).Temporary use of land for maintaining
authorised project 36
(1) Subject to paragraph (2), at any time during the maintenance period relating to any part of the authorised project, the undertaker may--
(a)enter on and take temporary possession of any land within the Order limits if such possession is reasonably required for the purpose of maintaining the authorised project; and
(b)construct such temporary works (including the provision of means of access) and buildings on the land as may be reasonably necessary for that purpose.
(2) Paragraph (1) shall not authorise the undertaker to take temporary possession of--
(a)any house or garden belonging to a house; or
(b)any building (other than a house) if it is for the time being occupied.
(3) Not less than 28 days before entering on and taking temporary possession of land under this article the undertaker shall serve notice of the intended entry on the owners and occupiers of the land.
(4) The undertaker may only remain in possession of land under this article for so long as may be reasonably necessary to carry out the maintenance of the part of the authorised project for which possession of the land was taken.
(5) Before giving up possession of land of which temporary possession has been taken under this article, the undertaker shall remove all temporary works and restore the land to the reasonable satisfaction of the owners of the land.
(6) The undertaker shall pay compensation to the owners and occupiers of land of which temporary possession is taken under this article for any loss or damage arising from the exercise in relation to the land of the provisions of this article.
(7) Any dispute as to a person's entitlement to compensation under paragraph (6), or as to the amount of the compensation, shall be determined under Part 1 of the 1961 Act.
(8) Nothing in this article shall affect any liability to pay compensation under section 10(2) of the 1965Act (further provisions as to compensation for injurious affection) or under any other enactment in respect of loss or damage arising from the maintenance of the authorised project, other than loss or damage for which compensation is payable under paragraph (6).
(9) Where the undertaker takes possession of land under this article, the undertaker shall not be required to acquire the land or any interest in it.
(10) Section 13 of the 1965 Act (refusal to give possession to acquiring authority) shall apply to
the
Page 51 of 99
36 36
(11) In this article "the maintenance period", in relation to any part of the authorised project, means theperiod of 5 years beginning with the date on which that part of the authorised project is first opened for use.
Special category land
37
(1)The special category land shall not vest in the undertaker until the undertaker has acquired the replacement land and [insert name of relevant body] has certified that a scheme for the provision of the replacement land as [common/open space/fuel or field garden allotment] has been implemented to its satisfaction.
(2)On the requirements of paragraph (1) being satisfied, the replacement land shall vest in [insert name of relevant body] subject to the same rights, trusts and incidents as attached to the special category land; and the special category land shall be discharged from all rights, trusts and incidents to which it was previously subject.
(3)In this article--
"the special category land" means the land identified as forming part of a common, open space, or fuel or field garden allotment in the book of reference and on the plan entitled "Special Category Land Plan" attached to the land plan, which may be acquired compulsorily under this Order and for which replacement land is to be provided; and
"the replacement land" means the land identified in the book of reference and on the plan entitled "Replacement Land Plan" attached to the land plan.
Statutory undertakers
38
—a) The undertaker may--—34.
acquire compulsorily the land belonging to statutory undertakers shown on the land plans within(a)
the limits of the land to be acquired and described in the book of reference;
extinguish the rights of, remove or reposition the apparatus belonging to statutory undertakers(b)
shown on the [insert name] plan and described in the book of reference; andwhere such
apparatus is anywhere within the Order limits; and
acquire compulsorily the new rights over land belonging to statutory undertakers shown on the (c)
[insert name] plan and described in the book of reference and shown on the land plans.
Apparatus and rights of statutory undertakers in stopped up streets
39
(1)Where a street is stopped up under article 11 (stopping up of streets) any statutory utility whose apparatus is under, in, on, along or across the street shall have the same powers and rights in respect of that apparatus, subject to the provisions of this article, as if this Order had not been made.
Where a street is stopped up under article 11 any statutory utility whose apparatus is under, in, on, (1)
over, along or across the street may, and if reasonably requested to do so by the undertaker shall--Parts 1
and 2 of Schedule 11 (protective provisions) apply to the power in sub-paragraph (1)(b).
(a)remove the apparatus and place it or other apparatus provided in substitution for it in such other position as the utility may reasonably determine and have power to place it; or
(b)provide other apparatus in substitution for the existing apparatus and place it in such position as described in sub-paragraph (a).
(3) Subject to the following provisions of this article, the undertaker shall pay to any statutory utility anamount equal to the cost reasonably incurred by the utility in or in connection with--
(a)the execution of the relocation works required in consequence of the stopping up of the
street; and
(b)the doing of any other work or thing rendered necessary by the execution of the relocation
works.
(4) If in the course of the execution of relocation works under paragraph (2)--
(a)apparatus of a better type, of greater capacity or of greater dimensions is placed in substitution for existing apparatus; or
(b)apparatus (whether existing apparatus or apparatus substituted for existing apparatus) is placed at a depth greater than the depth at which the existing apparatus was,
and the placing of apparatus of that type or capacity or of those dimensions or the placing of apparatus at that depth, as the case may be, is not agreed by the undertaker, or, in default of agreement, is not determined by arbitration to be necessary, then, if it involves cost in the execution of the relocation works exceeding that which would have been involved if the apparatus placed had been of the existing type, capacity or dimensions, or at the existing depth, as the case may be, the amount which, apart from this paragraph, would be payable to the statutory utility by virtue of paragraph (3) shall be reduced by the amount of that excess.
(5) For the purposes of paragraph (4)--
(a)an extension of apparatus to a length greater than the length of existing apparatus shall not be treated as a placing of apparatus of greater dimensions than those of the existing apparatus; and
(b)where the provision of a joint in a cable is agreed, or is determined to be necessary, the consequential provision of a jointing chamber or of a manhole shall be treated as if it also had been agreed or had been so determined.
(6) An amount which, apart from this paragraph, would be payable to a statutory utility in respect of works by virtue of paragraph (3) (and having regard, where relevant, to paragraph (4)) shall, if the works include the placing of apparatus provided in substitution for apparatus placed more than 7 years and 6 months earlier so as to confer on the utility any financial benefit by deferment of the time for renewal of the apparatus in the ordinary course, be reduced by the amount which represents that benefit.
(7) Paragraphs (3) to (6) shall not apply where the authorised project constitutes major highway works, major bridge works or major transport works for the purposes of Part 3 of the 1991 Act, but instead--
(a)the allowable costs of the relocation works shall be determined in accordance with section 85 of that Act (sharing of cost of necessary measures) and any regulations for the time being having effect under that section; and
(b)the allowable costs shall be borne by the undertaker and the statutory utility in such proportions as may be prescribed by any such regulations.
(8) In this article--In the provisions of the 1990 Act as applied by paragraph (1), references to the (2)
appropriate Minister are references to the Secretary of State.
"apparatus" has the same meaning as in Part 3 of the 1991 Act;
"relocation works" means work executed, or apparatus provided, under paragraph (2); and
37 37
(bb) 2003 c.21; there are amendments to section 151 that are not relevant to this Order.
(cc) 1981 c.66.
Page 52 of 99 under article 384 (statutory undertakers) any person who is the owner or occupier of
premises to which a supply was given from that apparatus shall beis entitled to recover from the
undertaker compensation in respect of expenditure reasonably incurred by that person, in consequence of
the removal, for the purpose of effecting a connection between the premises and any other apparatus
from which a supply is given.
(2) Paragraph (1) shalldoes not apply in the case of the removal of a public sewer but where such a(1)
sewer is removed under article 38,4 any person who is--—
the owner or occupier of premises the drains of which communicated with that sewer; or(a)
the owner of a private sewer which communicated with that sewer,(b)
shall beis entitled to recover from the undertaker compensation in respect of expenditure reasonably
incurred by that person, in consequence of the removal, for the purpose of making the drain or sewer
belonging to that person communicate with any other public sewer or with a private sewerage disposal
plant.
(3) This article shalldoes not have effect in relation to apparatus to which article 39 (apparatus and (2)
rights of statutory undertakers in stopped-up streets) or Part 3 of the 1991 Act applies.
(4) In this paragraph--—(3)
"“public communications provider"” has the same meaning as in section 151(1) of the
Communications Act 2003(bb); and
"“public utility undertaker"” has the same meaning as in the 1980 Act.
Operations
Operation and use of railways
41
(1)The undertaker may operate and use the railway and any other elements of the authorised project as a system, or part of a system, of transport for the carriage of passengers and goods.
Time limit for exercise of authority to acquire land compulsorily
—a) After the end of the period of 8 years beginning on the day on which this Order is made—36.
no notice to treat is to be served under Part 1 of the 1965 Act; and(a)
no declaration is to be executed under section 4 of the Compulsory Purchase (Vesting (b)
Declarations) Act 1981(cc) as applied by article 27 (application of the Compulsory Purchase
(Vesting Declarations) Act 1981).
The authority conferred by article 28 (temporary use of land for carrying out the authorised (1)
development) ceases at the end of the period referred to in paragraph (1), save that nothing in this
paragraph prevents the undertaker remaining in possession of land after the end of that period, if the land
was entered and possession was taken before the end of that period.
38 38
"statutory utility" means a statutory undertaker for the purposes of the 1980 Act or a public communications provider as defined in section 151(1) of the Communications Act 2003.
Recovery of costs of new connections 40
(1)—a) Where any apparatus of a public utility undertaker or of a public communications35.
provider is removed
(dd) Section 11 is amended by Schedule 4 to the Acquisition of Land Act 1981 (c.67), Schedule 1 to the Housing (Consequential Provisions) Act 1985 (c.71), the Church of England (Miscellaneous Provisions) Measure 2006 No. 1 Sch.5 para.12(1) and
the Transfer of Tribunal Functions (Lands Tribunal and Miscellaneous Amendments) Order 2009 (S.I. 2009/1307).
Page 53 of 99
Felling or lopping of trees
45
(1) The undertaker may fell or lop any tree or shrub near any part of the authorised project, or cut back its roots, if it reasonably believes it to be necessary to do so to prevent the tree or shrub--
Subject to the provisions of this article, all private rights of way over land of which the undertaker (2)
takes temporary possession under this Order are suspended and unenforceable for as long as the undertaker
remains in lawful possession of the land.
Any person who suffers loss by the extinguishment or suspension of any private right of way under (3)
this article is entitled to compensation to be determined, in case of dispute, under Part 1 of the 1961 Act.
39 39
Private rights of way
—a) Subject to the provisions of this article, all private rights of way over land subject to 37.
compulsory acquisition under this Order are extinguished—
as from the date of acquisition of the land by the undertaker, whether compulsorily or by (a)
agreement; or
on the date of entry on the land by the undertaker under section 11(1) of the 1965 Act(dd) (b)
(power of entry),
whichever is the earlier.
Nothing in this Order, or in any enactment incorporated with or applied by this Order, shall prejudice (1)
or affect the operation of Part 1 of the Railways Act 1993 (the provision of railway services).Subject to
the provisions of this article, all private rights of way over land owned by the undertaker which, being
within the limits of land which may be acquired shown on the land plans, is required for the purposes of
this Order are extinguished on the appropriation of the land by the undertaker for any of those purposes.
Fares
42
The undertaker may demand, take and recover or waive such charges for carrying passengers or goods on the railway comprised in the authorised project, or for any other services or facilities provided in connection with the operation of that railway, as it thinks fit.
Deemed consent under section 34 of the Coast Protection Act 1949
43
The undertaker is granted deemed consent under section 34 of the Coast Protection Act 1949 to carry out the works described in Schedule H, subject to the requirements set out in that Schedule.
Deemed licence under Part 2 of the Food and Environment Protection Act 1985
44
The undertaker is granted a deemed licence under Part 2 of the Food and Environment Protection Act 1985 to carry out the works described in Schedule I, subject to the requirements set out in that Schedule.
This article does not apply in relation to any right of way to which section 138 of the 2008 Act (4)
(extinguishment of rights, and removal of apparatus, of statutory undertakers etc.) or article 34
(statutory undertakers) applies.
Paragraphs (1) to (3) have effect subject to—(5)
any notice given by the undertaker before—(a)
the completion of the acquisition of the land,(i)
the undertaker’s appropriation of it,(ii)
the undertaker’s entry onto it, or(iii)
the undertaker’s taking temporary possession of it,(iv)
that any or all of those paragraphs do not apply to any right of way specified in the notice; and
any agreement made at any time between the undertaker and the person in or to whom the right (b)
of way in question is vested or belongs.
If any such agreement as is referred to in sub-paragraph (6)(b)—(6)
from obstructing or interfering with the construction, maintenance or operation of the authorised (a)
project or any apparatus used in connection with the authorised project; oris made with a person
in or to whom the right of way is vested or belongs; and
from constituting a danger to passengers or other persons using the authorised project.is (b)
expressed to have effect also for the benefit of those deriving title from or under that person,
(2) In carrying out any activity authorised by paragraph (1), the undertaker shall do no unnecessary damage to any tree or shrub and shall pay compensation to any person for any loss or damage arising from such activity.
(3) Any dispute as to a person's entitlement to compensation under paragraph (2), or as to the amount of compensation, shall be determined under Part 1 of the 1961 Act.
Trees subject to tree preservation orders
46
(1) The undertaker may fell or lop any tree described in Schedule J and identified on the [insert name] plan, or cut back its roots if it reasonably believes it to be necessary in order to do so to prevent the tree or shrub--
it is effective in respect of the persons so deriving title, whether the title was derived before or after the
making of the agreement.
Rights under or over streets
—a) The undertaker may enter on and appropriate so much of the subsoil of, or air-space over, 38.
any street within the Order limits as may be required for the purposes of the development and may
use the subsoil or air-space for those purposes or any other purpose ancillary to the authorised
development.
Subject to paragraph (3), the undertaker may exercise any power conferred by paragraph (1) in (1)
relation to a street without being required to acquire any part of the street or any easement or right in the
street.
Paragraph (2) does not apply in relation to—(2)
from obstructing or interfering with the construction, maintenance or operation of the authorised (a)
project or any apparatus used in connection with the authorised project; orany subway or
underground building; or
from constituting a danger to passengers or other persons using the authorised project.any (b)
cellar, vault, arch or other construction in, on or under a street which forms part of a building
fronting onto the street.
(2) In carrying out any activity authorised by paragraph (1)--
40 40
(ee) 1981 c.67.
Page 54 of 99 granted by or under that agreement is to be provided for that person'’s use.
No enactment or rule of law regulating the rights and obligations of landlords and tenants shall (1)
prejudiceprejudices the operation of any agreement to which this article applies.
Accordingly, no such enactment or rule of law shall applyapplies in relation to the rights and(2)
obligations of the parties to any lease granted by or under any such agreement so as to--—
exclude or in any respect modify any of the rights and obligations of those parties under the(a)
terms of the lease, whether with respect to the termination of the tenancy or any other matter;
41 41
Subject to paragraph (5), any person who is an owner or occupier of land appropriated under (3)
paragraph (1) without the undertaker acquiring any part of that person’s interest in the land, and who
suffers loss as a result, is entitled to compensation to be determined, in case of dispute, under Part 1 of the
1961 Act.
Compensation is not payable under paragraph (4) to any person who is an undertaker to whom (4)
section 85 of the 1991 Act (sharing cost of necessary measures) applies in respect of measures of which
the allowable costs are to be borne in accordance with that section.
Incorporation of the mineral code
Parts 2 and 3 of Schedule 2 to the Acquisition of Land Act 1981(ee) (minerals) are 39.
incorporated in this Order subject to the modifications that—
the undertaker shall do no unnecessary damage to any tree or shrub and shall pay compensation (a)
to any person for any loss or damage arising from such activity; andfor “the acquiring
authority” substitute “the undertaker”;
the duty contained in section 206(1) of the 1990 Act (replacement of trees) shall not (b)
apply.for “undertaking” substitute “authorised development”; and
(3) The authority given by paragraph (1) shall constitute a deemed consent under the relevant tree preservation order.
(4) Any dispute as to a person's entitlement to compensation under paragraph (2), or as to the amount of compensation, shall be determined under Part 1 of the 1961 Act
for compulsory purchase order” substitute “this Order”. (c)
Open space
Schedule 8 (record of the satisfaction of the Secretary of State pursuant to section 132 of the 40.
2008 Act) to this Order has effect.
Miscellaneous and General
PART 4
MISCELLANEOUS AND GENERAL
Application of landlord and tenant law
47
(1) —a) This article applies to--—41.
any agreement for leasing to any person the whole or any part of the authorised(a)
projectdevelopment or the right to operate the same; and
any agreement entered into by the undertaker with any person for the construction,(b)
maintenance, use or operation of the authorised projectdevelopment, or any part of it,
so far as any such agreement relates to the terms on which any land which is the subject of a lease
confer or impose on any such party any right or obligation arising out of or connected with(b)
anything done or omitted on or in relation to land which is the subject of the lease, in addition to
any such right or obligation provided for by the terms of the lease; or
restrict the enforcement (whether by action for damages or otherwise) by any party to the lease(c)
of any obligation of any other party under the lease.
Deemed consent under Part 4 (marine licensing) of the Marine and Coastal Access Act 2009
—a) A marine licence is deemed to have been issued to the undertaker under Part 4 (marine 42.
licensing) of the Marine and Coastal Access Act 2009(ff).
The marine licence deemed to have been issued under this article is set out at Schedule 10 (deemed (1)
marine licence under Part 4 (marine licensing) of the Marine and Coastal Access Act 2009).
Operational land for purposes of the 1990 Act
48
Development consent granted by this Order shallis to be treated as specific planning permission43.
for the purposes of section 264(3)(a) of the 1990 Act (cases in which land is to be treated as not
being operational land for the purposes of that Act).
Defence to proceedings in respect of statutory nuisance
49
(1) Where proceedings are brought under section 82(1) of the Environmental Protection Act 1990 (summary proceedings by person aggrieved by statutory nuisance) in relation to a nuisance falling within paragraph (g) of section 79(1) of that Act (noise emitted from premises so as to be prejudicial to health or a nuisance) no order shall be made, and no fine may be imposed, under section 82(2) of that Act if--
(a) the defendant shows that the nuisance--
(i)relates to premises used by the undertaker for the purposes of or in connection with the construction or maintenance of the authorised project and that the nuisance is attributable to the carrying out of the authorised project in accordance with a notice served under section 60 (control of noise on construction site), or a consent given under section 61 (prior consent for work on construction site) or 65 (noise exceeding registered level), of the Control of Pollution Act 1974; or
(ii)is a consequence of the construction or maintenance of the authorised project and that it cannot reasonably be avoided; or
(b) the defendant shows that the nuisance--
Felling or lopping of trees or shrubs
—a) The undertaker may fell or lop any tree or shrub near any part of the authorised 44.
development, or cut back its roots, if it reasonably believes it to be necessary to do so to prevent the
tree or shrub—
from obstructing or interfering with the construction, maintenance or operation of the authorised (a)
development or any apparatus used in connection with the authorised development; or
from constituting a danger to persons constructing, maintaining, operating or using the (b)
authorised development.
In carrying out any activity authorised by paragraph (1), the undertaker must not cause unnecessary (1)
damage to any tree or shrub and must pay compensation to any person for any loss or damage arising from
such activity.
The undertaker may remove— (2)
42 42
(ff) 2009 c.23; there are amendments that are not relevant to this Order.
(gg) S.I. 1997/1160, to which there are amendments not relevant to this Order.
Page 55 of 99
Protections of Interests
50
the “hedgerow plans” mean the drawings with drawing numbers 10-2574-GND-01-05-0140 (b)
rev A to 10-2574-GND-01-05-0156 rev A and certified as the hedgerow plans by the Secretary
of State for the purposes of this Order.
Any dispute as to a person’s entitlement to compensation under paragraph (2), or as to the amount of (6)
compensation, is to be determined under Part 1 of the 1961 Act.
Trees subject to tree preservation orders
—a) The undertaker may fell or lop any tree in respect of which a tree preservation order has 45.
been made on or after 10 June 2014, or cut back its roots if it reasonably believes it to be necessary
in order to do so to prevent the tree or shrub—
from obstructing or interfering with the construction, maintenance or operation of the authorised (a)
development or any apparatus used in connection with the authorised development; or
from constituting a danger to persons constructing, maintaining, operating or using the (b)
authorised development.
In carrying out any activity authorised by paragraph (1)—(1)
the undertaker must not do unnecessary damage to any tree or shrub and must pay compensation (a)
to any person for any loss or damage arising from such activity; and
the duty contained in section 206(1) of the 1990 Act (replacement of trees) does not apply.(b)
43 43
hedgerows shown on the hedgerow plans; (a)
with the approval of the relevant planning authority, which is not to be unreasonably withheld (b)
or delayed, any other hedgerow within the Order limits if the undertaker reasonably believes it
to be necessary to do so for the purposes of the construction and/or carrying out of the
authorised development.
The undertaker is not required to obtain any consent to remove a hedgerow referred to in paragraph (3)
(3) under the Hedgerows Regulations 1997(gg).
Reference to “planning permission” in regulation 6 (permitted work) of the Hedgerows Regulations (4)
1997 includes this Order.
In this article—(5)
“hedgerow” includes—(a)
relates to premises used by the undertaker for the purposes of or in connection with the (i)
use of the authorised project and that the nuisance is attributable to the use of the
authorised project which is being used in accordance with a scheme of monitoring and
attenuation of noise agreed with the Commission as described in requirement 25;
orhedgerows to which the Hedgerows Regulations 1997 apply; and
is a consequence of the use of the authorised project and that it cannot reasonably be (ii)
avoided.any part of a hedgerow; and
(2) Section 61(9) (consent for work on construction site to include statement that it does not of itself constitute a defence to proceedings under section 82 of the Environmental Protection Act 1990) of the Control of Pollution Act 1974 and section 65(8) of that Act (corresponding provision in relation to consent for registered noise level to be exceeded), shall not apply where the consent relates to the use of premises by the undertaker for the purposes of or in connection with the construction or maintenance of the authorised project.
The authority given by paragraph (1) constitutes a deemed consent under the relevant tree (2)
preservation order.
Any dispute as to a person’s entitlement to compensation under paragraph (2), or as to the amount (3)
of compensation, is to be determined under Part 1 of the 1961 Act.
In this article “tree preservation order” means an order made or having effect as if made under (4)
section 198 of the Town and Country Planning Act 1990.
Resumption of land use following certain works
—a) This article applies to the resumption of the use of land used for the specified works for the 46.
use for which that land had normally been used before this Order was made.
Where this article applies, section 57(2) of the 1990 Act (planning permission required for (1)
development) applies as if the development consent granted by this Order were planning permission to
develop land granted for a limited period.
In this article “specified works” means Work Nos. 2A, 7, 12, 14A(a) and paragraph (b) (further (2)
associated development) of Schedule 1 (authorised development).
Application of the Community Infrastructure Levy
The Community Infrastructure Levy Regulations 2010(hh) apply to the authorised development 47.
as if this Order were a planning permission (for the purposes of regulation 5(1) of those Regulations)
which (for the purposes of regulation 5(2) of those Regulations) had been granted for a limited
period.
Protective provisions
Schedule L11 (protective provisions) to this Order has effect.48.
Certification of plans etc.
51
(1)—a) The undertaker shallmust, as soon as practicable after the making of this Order, submit49.
to the decision-makerSecretary of State copies of--—
the access, rights of way and temporary stopping up plans;(a)
the approved plans;(b)
(a) the book of reference;(c)
(b) the land plan;environmental statement;(d)
(c) the rightsland plans;(e)
(d) the works plan;plans; and(f)
(e)the sections; and
any other plans or documents referred to in this Order,(g)
(f) any other plans or documents referred to in this Order, for certification that they are true
copies of the plans or documents referred to in this Order.
(2) A plan or document so certified shall beis admissible in any proceedings as evidence of the(1)
contents of the document of which it is a copy.
Service of notices
—(1) A notice or other document required or authorised to be served, given or supplied under 50.
this Order may be served, given or supplied in any of these ways—
by delivering it to the person on whom it is to be served or to whom it is to be given or supplied;(a)
by leaving it at the usual or last known place of abode of that person or, in a case where an (b)
address for service has been given by that person, at that address;
44 44
(hh) S.I. 2010/948.
by sending it by post, addressed to that person at that person’s usual or last known place of (c)
abode or, in a case where an address for service has been given by that person, at that address;
by sending it in a prepaid registered letter, or by the recorded delivery service, addressed to that (d)
person at that person’s usual or last known place of abode or, in a case where an address for
service has been given by that person, at that address;
in a case where an address for service using electronic communications has been given by that (e)
person, by sending it using electronic communications, in accordance with the condition set out
in paragraph (2), to that person at that address;
in the case of an incorporated company or body—(f)
by delivering it to the secretary or clerk of the company or body at their registered or (i)
principal office;
by sending it by post, addressed to the secretary or clerk of the company or body at that (ii)
office; or
by sending it in a prepaid registered letter or, or by the recorded delivery service, (iii)
addressed to the secretary or clerk of the company or body at that office.
The condition mentioned in sub-paragraph (e) is that the notice or other document must be -(1)
capable of being accessed by the person mentioned in that provision;(a)
legible in all material respects; and(b)
in a form sufficiently permanent to be used for subsequent reference.(c)
For the purposes of paragraph (2), “legible in all material respects” means that the information (2)
contained in the notice or document is available to that person to no lesser extent than it would be if
served, given or supplied by means of a notice or document in printed form.
Arbitration
52
Any difference or dispute under any provision of this Order (other than a difference or dispute 51.
which falls to be determined by the tribunal) must, unless otherwise provided for in this Order or
unless otherwise agreed between the parties, shall be referred to and settled by a single arbitrator to
be agreed between the parties or, failing agreement, to be appointed on the application of either party
(after giving notice in writing to the other) by the [insert appropriate body]Secretary of State.
Requirements
—a) Schedule 3 (requirements) of this Order has effect.52.
Save for paragraphs 2 (time limits), 3 (approved details), 4 (stages of authorised development), 7 (1)
(European protected species), 8 (scheme of ecological mitigation and reinstatement), 9 (water
management), 10 (removal of trees and hedgerows), 12 (archaeology), 13 (construction hours), 14
(code of construction practice), 15 (noise), 18 (construction traffic plan), 19 (restoration of land used
temporarily for construction), 20 (requirement for written approval), 21 (amendments to approved
details), and 22 (decommissioning) of Schedule 3 (requirements) and the definitions in paragraph 1
(interpretation) of Schedule 3 (requirements) which relate to those paragraphs, Schedule 3
(requirements) does not apply to Work Nos. 5C and 15B of Schedule 1 (authorised development) so far
as these fall within the UK marine area.
Procedure in relation to certain approvals etc.
Schedule 14 (appeals relating to decisions made by certain authorities pursuant to this 53.
Order) to this Order has effect.
Signed by authority of the Secretary of State
[Name of Secretary of State]
[●] [●] 201[●] Department of [●]
45 45
SCHEDULES
SCHEDULE 1 Article 4
AUTHORISED DEVELOPMENT
Schedule AA nationally significant infrastructure project as defined in sections 14 and 21 of the 2008
Act and associated development within the meaning of section 115 of the 2008 Act comprising the works
described below.Authorised Project
Part 1Authorised Development
[NOTE: This Part should describe as fully as possible the elements of the proposed project (including any associated development), which are development for the purposes of section 32 of the 2008 Act, for which development consent is sought. It should not include any elements of development which would be authorised by specific provisions in the Order.]
Part 2Ancillary Works
[NOTE: This Part should describe as fully as possible the ancillary works for which consent is sought and which are not development within the meaning of section 32 of the 2008 Act and which are not be the subject of a separate provision [article] in this Order.]
Schedule B
In the District of Selby in the County of North Yorkshire and in the East Riding of Yorkshire—
Work No. 1A – A carbon dioxide pipeline inspection facility at Drax, to be known as the Drax PIG
Trap, including the following works and structures—
(a) construction and/or installation of above and below ground piping, piping bridles and bypasses,
insulation joints, valves, actuators, vents, analysers, meters and filtration;
(b) construction and/or installation of a PIG trap reception and insertion area including associated
hard standing, pipe supports, instrument building and associated photo voltaic cells and turbine, hard
standing for temporary generator, backfilled pits and chambers, gated security fence and cameras,
pedestrian access, satellite dish, troughs, trays, ducting, drainage and drainage attenuation, internal
vehicular access routes, turning areas, pedestrian areas, post and rail fencing and landscape screening;
(c) electrical and instrumentation construction and/or installation including instrumentation,
electrical cables, earthing protection, electricity and communications kiosks, satellite dish, control and
telecommunications cables, utilities and utility metering, intruder detection systems and closed circuit
television;
(d) works, including pipes, to enable a tie in to the White Rose carbon capture and storage project
adjacent to Drax power station, Selby; and
(e) extensions of those parts of the carbon dioxide pipeline comprised in Work No. 3A, the cathodic
protection facility comprised in Work No. 1B and an access road which link to elements within this
Work No. 1A.
46 46
Work No. 1B – A cathodic protection facility including a transformer rectifier kiosk with control
cabinet and junction box surrounded by a post and rail fence; anode canisters, electrical and cathodic
protection cables, utility meter and cabling; and cathodic protection test posts and aerial markers.
Work No. 2A – A temporary pipeline store and office area including temporary–
(a) office, welfare and security facilities;
(b) power supplies and temporary lighting;
(c) enclosures;
(d) pipe, equipment and fittings storage;
(e) plant storage;
(f) fabrication area;
(g) waste storage areas;
(h) spoil storage areas;
(i) internal haul roads;
(j) access parking; and
(k) water management areas.
Work No. 3A – A carbon dioxide pipeline from Drax PIG Trap (Work No. 1A) to Pear Tree Avenue
(Work No. 3B), approximate chainage 1592 metres, laid in trench, in sleeves or by trenchless methods;
such pipeline to be not less than 1.2 metres below ground surface (or not less than 1.7 metres below the
true clean bottom of rivers, streams, open drains, canals or dykes, but excluding land drains, culverts or
sewers and not less than 2 metres below public highways where applicable) save where the pipeline rises
to interface with the Drax PIG Trap (Work No. 1A).
Work No. 3B – A carbon dioxide pipeline from and beneath Pear Tree Avenue, approximate chainage
1592 metres, to Carr Lane (Work No. 3C), approximate chainage 2313 metres, laid in trench, in sleeves
or by trenchless methods; such pipeline to be not less than 1.2 metres below ground surface (or not less
than 1.7 metres below the true clean bottom of rivers, streams, open drains, canals or dykes, but
excluding land drains, culverts or sewers and not less than 2 metres below public highways where
applicable).
Work No. 3C – A carbon dioxide pipeline from and beneath Carr Lane, approximate chainage 2313
metres, to Main Road (Work No. 3D), approximate chainage 2972 metres, laid in trench, in sleeves or
by trenchless methods (save beneath watercourses adjacent to the disused railway embankment at
approximate chainage 2478 metres where it must be laid by trenchless methods); such pipeline to be not
less than 1.2 metres below ground surface (or not less than 1.7 metres below the true clean bottom of
rivers, streams, open drains, canals or dykes, but excluding land drains, culverts or sewers and not less
than 2 metres below public highways where applicable).
Work No. 3D – A carbon dioxide pipeline from and beneath Main Road, approximate chainage 2972
metres, to Church Dike Lane (Work No. 3E), approximate chainage 3933 metres, laid in trench, in
sleeves or by trenchless methods; such pipeline to be not less than 1.2 metres below ground surface (or
1.7 metres below the true clean bottom of rivers, streams, open drains, canals or dykes, but excluding
land drains, culverts or sewers and not less than 2 metres below public highways where applicable).
Work No. 3E - A carbon dioxide pipeline from and beneath Church Dike Lane, approximate chainage
3933 metres, to Brickhill Lane (Work No. 3F), approximate chainage 4713 metres, laid in trench, in
sleeves or by trenchless methods; such pipeline to be not less than 1.2 metres below ground surface (or
1.7 metres below the true clean bottom of rivers, streams, open drains, canals or dykes, but excluding
land drains, culverts or sewers and not less than 2 metres below public highways where applicable).
Work No 3F – A carbon dioxide pipeline from and beneath Brickhill Lane, from approximate chainage
4713 metres to A645 (Work No. 3E), approximate chainage 5298 metres, laid in trench, in sleeves or by
trenchless methods; such pipeline to be not less than 1.2 metres below ground surface (or not less than
1.7 metres below the true clean bottom of rivers, streams, open drains, canals or dykes, but excluding
land drains, culverts or sewers and not less than 2 metres below public highways where applicable).
47 47
Work No. 3G – A carbon dioxide pipeline from and beneath A645, approximate chainage 5298 metres,
to Camblesforth Multi-Junction (Work No. 4A), approximate chainage 5630 metres, laid in trench, in
sleeves or by trenchless methods; such pipeline to be not less than 1.2 metres below ground surface (or
not less than 1.7 metres below the true clean bottom of rivers, streams, open drains, canals or dykes, but
excluding land drains, culverts or sewers and not less than 2 metres below public highways where
applicable) save where the pipeline rises to interface with the Camblesforth Multi Junction (Work No.
4A).
Work No. 4A – A carbon dioxide pipeline multiple inspection facility at Camblesforth, to be known as
the Camblesforth Multi-junction, including the following works and structures—
(a) construction and/or installation of above and below ground piping, piping bridles and bypasses,
insulation joints, valves, actuators and vents;
(b) construction and/or installation of up to 5 PIG trap reception and insertion areas including
associated hard standing, pipe supports, instrument building and associated photo voltaic cells and
turbine, hard standing for temporary generator, backfilled pits and chambers, gated security fence,
pedestrian access, satellite dish, troughs, trays, ducting, drainage and drainage attenuation, internal
vehicular access routes, turning areas, pedestrian areas, post and rail fencing and landscape screening;
(c) electrical and instrumentation construction and/or installation including instrumentation,
electrical cables, earthing protection, electricity and communications kiosks, satellite dish, control and
telecommunications cables, utilities and utility metering, intruder detection systems and closed circuit
television; and
(d) extensions of those parts of the carbon dioxide pipeline comprised in Work No. 3G and Work
No.5A, the cathodic protection facility comprised in Work No. 4B and the road comprised in Work No.
4C which link to elements within this Work No. 4A.
Work No. 4B – A cathodic protection facility including a transformer rectifier kiosk with control
cabinet and junction box surrounded by a post and rail fence; anode canisters, electrical and cathodic
protection cables, utility meter and cabling; and cathodic protection test posts and aerial markers.
Work No. 4C – A road from A645 / Wade House Lane junction up to and including the carbon dioxide
facility at Camblesforth Multi-junction (Work No. 4A) including any splays, gates, fencing, drainage,
drainage attenuation and interceptors, piped culverts, utilities, associated ducting and landscape works.
Work No. 4D – A temporary pipeline store and office area including temporary–
(a) office, welfare and security facilities;
(b) power supplies and temporary lighting;
(c) enclosures;
(d) pipe, equipment and fittings storage;
(e) plant storage;
(f) fabrication area;
(g) waste storage areas;
(h) spoil storage areas;
(i) internal haul roads;
(j) access parking; and
(k) water management areas.
CAMBLESFORTH TO TOLLINGHAM
Work No. 5A – A carbon dioxide pipeline from Camblesforth Multi-junction (Work No. 4A) to the
A645, approximate chainage 5984 metres, laid in trench, in sleeves or by trenchless methods; such
pipeline to be not less than 1.2 metres below ground surface (or not less than 1.7 metres below the true
clean bottom of rivers, streams, open drains, canals or dykes, but excluding land drains, culverts or
48 48
sewers and not less than 2 metres below public highways where applicable) save where the pipeline rises
to interface with the Camblesforth Multi-junction (Work No. 4A).
Work No. 5B – A carbon dioxide pipeline from and beneath the A645, approximate chainage 5984
metres to Church Dike Lane (Work No. 5C), approximate chainage 7458 metres, laid in trench, in
sleeves or by trenchless methods; such pipeline to be not less than 1.2 metres below ground surface (or
not less than 1.7 metres below the true clean bottom of rivers, streams, open drains, canals or dykes, but
excluding land drains, culverts or sewers and not less than 2 metres below public highways where
applicable).
Work No. 5C – A carbon dioxide pipeline from and beneath Church Dike Lane, approximate chainage
7458 metres, to Barmby Road (Work No. 5D), approximate chainage 11,089 metres, laid in trench, in
sleeves or by trenchless methods (save beneath the true clean bottom of the River Ouse where it must be
laid by trenchless methods); such pipeline to be not less than 1.2 metres below ground surface (or not
less than 1.7 metres below the true clean bottom of rivers, streams, open drains, canals or dykes, but
excluding land drains, culverts or sewers and not less than 2 metres below public highways and the true
clean bottom of the River Ouse where applicable).
Work No. 5D – A carbon dioxide pipeline from and beneath Barmby Road, approximate chainage
11,089 metres, to the A63, Hull Road (Work No. 5E), approximate chainage 12,969 metres, laid in
trench, in sleeves or by trenchless methods; such pipeline to be not less than 1.2 metres below ground
surface (or not less than 1.7 metres below the true clean bottom of rivers, streams, open drains, canals or
dykes, but excluding land drains, culverts or sewers and not less than 2 metres below public highways
where applicable).
Work No. 5E – A carbon dioxide pipeline from and beneath the A63, Hull Road, approximate chainage
129,69 metres, to Brind Lane (Work No. 5F), approximate 15,252 metres, laid in trench, in sleeves or
by trenchless methods (save beneath the Howden to Wressle railway line where it must be laid by
trenchless methods); such pipeline to be not less than 1.2 metres below ground surface (or not less than
1.7 metres below the true clean bottom of rivers, streams, open drains, canals or dykes, but excluding
land drains, culverts or sewers, not less than 2 metres below public highways or not less than 4 metres
below the underside of the railway sleepers comprised in the Howden to Wressle railway line where
applicable).
Work No. 5F – A carbon dioxide pipeline from and beneath Brind Lane, approximate chainage 15,252
metres, to the B1228, Wood Lane (Work No. 5G), approximate chainage 16,603 metres, laid in trench,
in sleeves or by trenchless methods; such pipeline to be not less than 1.2 metres below ground surface
(or not less than 1.7 metres below the true clean bottom of rivers, streams, open drains, canals or dykes,
but excluding land drains, culverts or sewers and not less than 2 metres below public highways where
applicable).
Work No. 5G – A carbon dioxide pipeline from and beneath the B1228, Wood Lane, approximate
chainage 16,603 metres, to the A614, Holme Road (Work No. 5H), approximate chainage 20,737
metres, laid in trench, in sleeves or by trenchless methods; such pipeline to be not less than 1.2 metres
below ground surface (or not less than 1.7 metres below the true clean bottom of rivers, streams, open
drains, canals or dykes, but excluding land drains, culverts or sewers and not less than 2 metres below
public highways where applicable).
Work No. 5H – A carbon dioxide pipeline from and beneath the A614, Holme Road, approximate
chainage 20,737 metres, to Bursea Lane (Work No. 5I), approximate chainage 23,217 metres, laid in
trench, in sleeves or by trenchless methods (save beneath the bed of the River Foulness where it must be
laid by trenchless methods); such pipeline to be not less than 1.2 metres below ground surface (or not
less than 1.7 metres below the true clean bottom of rivers, streams, open drains, canals or dykes, but
excluding land drains, culverts or sewers and not less than 2 metres below public highways and the true
clean bottom of the River Foulness where applicable).
Work No. 5I – A carbon dioxide pipeline from and beneath Bursea Lane, approximate chainage 23,217
metres, to Drain Lane (Work No. 5J), approximate chainage 24,757 metres, laid in trench, in sleeves or
by trenchless methods; such pipeline to be not less than 1.2 metres below ground surface (or not less
than 1.7 metres below the true clean bottom of rivers, streams, open drains, canals or dykes, but
excluding land drains, culverts or sewers and not less than 2 metres below public highways where
applicable).
49 49
Work No. 5J – A carbon dioxide pipeline from and beneath Drain Lane, approximate chainage 24,757
metres, to Tollingham Block Valve (Work No. 6A), laid in trench, in sleeves or by trenchless methods;
such pipeline to be not less than 1.2 metres below ground surface (or not less than 1.7 metres below the
true clean bottom of rivers, streams, open drains, canals or dykes, but excluding land drains, culverts or
sewers and not less than 2 metres below public highways where applicable) save where the pipeline rises
to interface with Tollingham Block Valve (Work No 6A).
Work No. 6A – A carbon dioxide pipeline isolation facility at Tollingham, to be known as the
Tollingham Block Valve, including the following works and structures—
(a) construction and/or installation including above and below ground piping, piping bridles and
bypasses, insulation joints, valves, actuators and vents;
(b) construction and/or installation including pipe supports, instrument building and associated
photo voltaic cells and turbine, hard standing for temporary generator, backfilled pits and chambers,
gated security fence and cameras, pedestrian access, satellite dish, troughs, trays, ducting, drainage and
drainage attenuation, internal vehicular access routes, turning areas, pedestrian areas, post and rail
fencing and landscape screening;
(c) electrical and instrumentation construction and/or installation including instrumentation,
electrical cables, earthing protection, satellite dish, control and telecommunications cables, utility
metering, intruder detection systems and closed circuit television; and
(d) extensions of those parts of the carbon dioxide pipeline comprised in Work No. 5J and Work
No.8A, the cathodic protection facility comprised in Work No. 6B and the road comprised in Work No.
6C which link to elements within this Work No. 6A.
Work No. 6B – A cathodic protection facility including a transformer rectifier kiosk with control
cabinet and junction box surrounded by a post and rail fence; anode canisters, electrical and cathodic
protection cables, utility meter and cabling; and cathodic protection test posts and aerial markers.
Work No. 6C - A road from Skiff Lane up to and including the carbon dioxide facility at Tollingham
Block Valve (Work No. 6A) including any splays, gates, fencing, drainage, drainage attenuation and
interceptors, piped culverts, electricity kiosk, utilities, associated ducting and landscape works.
Work No. 6D – A temporary pipeline store and office area including temporary—
(a) office, welfare and security facilities;
(b) power supplies and temporary lighting;
(c) enclosures;
(d) pipe, equipment and fittings storage;
(e) plant storage;
(f) fabrication area;
(g) waste storage areas;
(h) spoil storage areas;
(i) internal haul roads;
(j) access parking; and
(k) water management areas.
Work No. 7 – A temporary pipeline store and office area to be known as Tollingham Construction
Compound including temporary—
(a) office, welfare and security facilities;
(b) power supplies and temporary lighting;
(c) enclosures;
(d) pipe, equipment and fittings storage;
50 50
(e) plant storage;
(f) fabrication area;
(g) waste storage areas;
(h) spoil storage areas;
(i) internal haul roads;
(j) access parking;
(k) vehicle maintenance area including washing facilities; and
(l) water management areas.
TOLLINGHAM TO DALTON
Work No. 8A – A carbon dioxide pipeline from Tollingham Block Valve (Work No. 6A) to Skiff Lane,
approximate chainage 26,010 metres, laid in trench, in sleeves or by trenchless methods; such pipeline to
be not less than 1.2 metres below ground surface (or not less than 1.7 metres below the true clean bottom
of rivers, streams, open drains, canals or dykes, but excluding land drains, culverts or sewers and not
less than 2 metres below public highways where applicable) save where the pipeline rises to interface
with the Tollingham Block Valve (Work No. 6A).
Work No. 8B – A carbon dioxide pipeline from and beneath Skiff Lane, approximate chainage 26,010
metres, to Lock Lane (Work No. 8C), approximate chainage 27,238 metres, laid in trench, in sleeves or
by trenchless methods; such pipeline to be not less than 1.2 metres below ground surface (or not less
than 1.7 metres below the true clean bottom of rivers, streams, open drains, canals or dykes, but
excluding land drains, culverts or sewers and not less than 2 metres below public highways where
applicable).
Work No. 8C – A carbon dioxide pipeline from and beneath Lock Lane, approximate chainage 27,238
metres, to Sands Lane (Work No. 8D), approximate chainage 29,025 metres, laid in trench, in sleeves or
by trenchless methods (save beneath the bed of the disused Market Weighton Canal where it must be
laid by trenchless methods); such pipeline to be not less than 1.2 metres below ground surface (or not
less than 1.7 metres below the true clean bottom of rivers, streams, open drains, canals or dykes, but
excluding land drains, culverts or sewers and not less than 2 metres below public highways or the
beneath the true clean bottom of the disused Market Weighton Canal where applicable).
Work No. 8D – A carbon dioxide pipeline from and beneath Sands Lane, approximate chainage 29,025
metres, to Cliffe Road (Work No. 8E), approximate chainage 32,750 metres, laid in trench, in sleeves or
by trenchless methods; such pipeline to be not less than 1.2 metres below ground surface (or not less
than 1.7 metres below the true clean bottom of rivers, streams, open drains, canals or dykes, but
excluding land drains, culverts or sewers and not less than 2 metres below public highways where
applicable).
Work No. 8E – A carbon dioxide pipeline from and beneath Cliffe Road, approximate chainage 32,750
metres, to the A1034 Sancton Road (Work No. 8F), approximate chainage 34,547 metres, laid in trench,
in sleeves or by trenchless methods; such pipeline to be not less than 1.2 metres below ground surface
(or not less than 1.7 metres below the true clean bottom of rivers, streams, open drains, canals or dykes,
but excluding land drains, culverts or sewers and not less than 2 metres below public highways where
applicable).
Work No. 8F – A carbon dioxide pipeline from and beneath the A1034 Sancton Road, approximate
chainage 34,547 metres, to the A1079 Arras Hill (Work No. 8G), approximate chainage 36,283 metres,
laid in trench, in sleeves or by trenchless methods; such pipeline to be not less than 1.2 metres below
ground surface (or 1.7 metres below the true clean bottom of rivers, streams, open drains, canals or
dykes, but excluding land drains, culverts or sewers and not less than 2 metres below public highways
where applicable).
Work No. 8G – A carbon dioxide pipeline from and beneath the A1079 Arras Hill, approximate
chainage 36,283 metres, to Kiplingcotes Lane (Work No. 8H), approximate chainage 39,393 metres,
laid in trench, in sleeves or by trenchless methods; such pipeline to be not less than 1.2 metres below
ground surface (or 1.7 metres below the true clean bottom of rivers, streams, open drains, canals or
51 51
dykes, but excluding land drains, culverts or sewers and not less than 2 metres below public highways
where applicable).
Work No. 8H – A carbon dioxide pipeline from and beneath Kiplingcotes Lane, approximate chainage
39,393 metres, to Kiplingcotes Road (Work No. 8I), approximate chainage 40,231 metres, laid in
trench, in sleeves or by trenchless methods; such pipeline to be not less than 1.2 metres below ground
surface (or 1.7 metres below the true clean bottom of rivers, streams, open drains, canals or dykes, but
excluding land drains, culverts or sewers and not less than 2 metres below public highways where
applicable).
Work No. 8I – A carbon dioxide pipeline from and beneath Kiplingcotes Road, approximate chainage
40,231 metres, to Kiplingcotes Race Course Road (Work No. 8J), approximate chainage 40,600 metres,
laid in trench, in sleeves or by trenchless methods; such pipeline to be not less than 1.2 metres below
ground surface (or 1.7 metres below the true clean bottom of rivers, streams, open drains, canals or
dykes, but excluding land drains, culverts or sewers and not less than 2 metres below public highways
where applicable).
Work No. 8J – A carbon dioxide pipeline from and beneath Kiplingcotes Race Course Road,
approximate chainage 40,600 metres to Park Road (Work No. 8K), approximate chainage 41,370
metres, laid in trench, in sleeves or by trenchless methods; such pipeline to be not less than 1.2 metres
below ground surface (or 1.7 metres below the true clean bottom of rivers, streams, open drains, canals
or dykes, but excluding land drains, culverts or sewers and not less than 2 metres below public highways
where applicable).
Work No. 8K – A carbon dioxide pipeline from and beneath Park Road, approximate chainage 41,370
metres, to Holme Wold Road (Work No. 8L), approximate chainage 43,264 metres, laid in trench, in
sleeves or by trenchless methods; such pipeline to be not less than 1.2 metres below ground surface (or
1.7 metres below the true clean bottom of rivers, streams, open drains, canals or dykes, but excluding
land drains, culverts or sewers and not less than 2 metres below public highways where applicable).
Work No. 8L – A carbon dioxide pipeline from and beneath Holme Wold Road, approximate chainage
43,264 metres to Dalton Block Valve (Work No. 9A), laid in trench, in sleeves or by trenchless
methods; all to be not less than 1.2 metres below ground surface (or 1.7 metres below the true clean
bottom of rivers, streams, open drains, canals or dykes, but excluding land drains, culverts or sewers and
not less than 2 metres below public highways where applicable) save where the pipeline rises to
interface with Dalton Block Valve (Work No. 9A).
Work No. 9A – A carbon dioxide pipeline isolation facility at Dalton to be known as the Dalton Block
Valve including the following works and structures—
(a) construction and/or installation including above and below ground piping, piping bridles and
bypasses, insulation joints, valves, actuators and vents;
(b) construction and/or installation including pipe supports, instrument building and associated
photo voltaic cells and turbine, hard standing for temporary generator, backfilled pits and chambers,
gated security fence and cameras, pedestrian access, satellite dish, troughs, trays, ducting, drainage and
drainage attenuation, internal vehicular access routes, turning areas, pedestrian areas, post and rail
fencing and landscape screening;
(c) electrical and instrumentation construction and/or installation including instrumentation,
electrical cables, earthing protection, satellite dish, control and telecommunications cables, utility
metering, intruder detection systems and closed circuit television; and
(d) extensions of those parts of the carbon dioxide pipeline comprised in Work No. 8L and Work
No.10A, the cathodic protection facility comprised in Work No. 9B and the road comprised in Work No.
9C which link to elements within this Work No. 9A.
Work No. 9B – A cathodic protection facility including a transformer rectifier kiosk with control
cabinet and junction box surrounded by a post and rail fence; anode canisters, electrical and cathodic
protection cables, utility meter and cabling; and cathodic protection test posts and aerial markers.
Work No. 9C – A road from Lund Wold Road up to and including the carbon dioxide facility at Dalton
Block Valve (Work No. 9A) including any splays, gates, fencing, drainage, drainage attenuation and
interceptors, piped culverts, electricity kiosk, utilities, associated ducting and landscape works.
Work No. 9D – A temporary pipeline store and office area including temporary–
52 52
(a) office, welfare and security facilities;
(b) power supplies and temporary lighting;
(c) enclosures;
(d) pipe, equipment and fittings storage;
(e) plant storage;
(f) fabrication area;
(g) waste storage areas;
(h) spoil storage areas;
(i) internal haul roads;
(j) access parking; and
(k) water management areas.
DALTON TO SKERNE
Work No. 10A – A carbon dioxide pipeline from Dalton Block Valve (Work No. 9A) to Lund Wold
Road (Work No. 10B), approximate chainage 45,909 metres, laid in trench, in sleeves or by trenchless
methods; such pipeline to be not less than 1.2 metres below ground surface (or 1.7 metres below the true
clean bottom of rivers, streams, open drains, canals or dykes, but excluding land drains, culverts or
sewers and not less than 2 metres below public highways where applicable) save where the pipeline rises
to interface with the Dalton Block Valve (Work No. 9A).
Work No. 10B – A carbon dioxide pipeline from and beneath Lund Wold Road, approximate chainage
45,909 metres, to Middleton Road (Work No. 10C), approximate chainage 46,874 metres, laid in trench,
in sleeves or by trenchless methods; such pipeline to be not less than 1.2 metres below ground surface
(or 1.7 metres below the true clean bottom of rivers, streams, open drains, canals or dykes, but excluding
land drains, culverts or sewers and not less than 2 metres below public highways where applicable).
Work No. 10C – A carbon dioxide pipeline from and beneath Middleton Road, approximate chainage
46,874 metres, to the B1248 Lund Road (Work No. 10D), approximate chainage 47,913 metres, laid in
trench, in sleeves or by trenchless methods; such pipeline to be not less than 1.2 metres below ground
surface (or 1.7 metres below the true clean bottom of rivers, streams, open drains, canals or dykes, but
excluding land drains, culverts or sewers and not less than 2 metres below public highways where
applicable).
Work No. 10D – A carbon dioxide pipeline from and beneath the B1248 Lund Road, approximate
chainage 47,913 metres, to Middleton Road (Work No. 10E), approximate chainage 48,823 metres, laid
in trench, in sleeves or by trenchless methods; such pipeline to be not less than 1.2 metres below ground
surface (or 1.7 metres below the true clean bottom of rivers, streams, open drains, canals or dykes, but
excluding land drains, culverts or sewers and not less than 2 metres below public highways where
applicable).
Work No. 10E - A carbon dioxide pipeline from and beneath Middleton Road, approximate chainage
48,823 metres to unnamed road from Bracken Lane to Burnbutts Lane (Work No. 10F), approximate
chainage 50,921 metres, laid in trench, in sleeves or by trenchless methods; such pipeline to be not less
than 1.2 metres below ground surface (or not less than 1.7 metres below the true clean bottom of rivers,
streams, open drains, canals or dykes, but excluding land drains, culverts or sewers and not less than 2
metres below public highways where applicable).
Work No. 10F – A carbon dioxide pipeline from and beneath unnamed road from Bracken Lane to
Burnbutts Lane, approximate chainage 50,921 metres, to Burnbutts Lane (Work No. 10G), approximate
chainage 51,349 metres, laid in trench, in sleeves or by trenchless methods; such pipeline to be not less
than 1.2 metres below ground surface (or not less than 1.7 metres below the true clean bottom of rivers,
streams, open drains, canals or dykes, but excluding land drains, culverts or sewers and not less than 2
metres below public highways where applicable).
Work No. 10G – A carbon dioxide pipeline from and beneath Burnbutts Lane, approximate chainage
51,349 metres, to Southburn Road (Work No. 10H), approximate chainage 54,681 metres, laid in
53 53
trench, in sleeves or by trenchless methods; such pipeline to be not less than 1.2 metres below ground
surface (or not less than 1.7 metres below the true clean bottom of rivers, streams, open drains, canals or
dykes, but excluding land drains, culverts or sewers and not less than 2 metres below public highways
where applicable).
Work No. 10H – A carbon dioxide pipeline from and beneath Southburn Road, approximate chainage
54,681 metres, to the A164, Beverley Road (Work No. 10I), approximate chainage 54,964 metres, laid
in trench, in sleeves or by trenchless methods; such pipeline to be not less than 1.2 metres below ground
surface (or not less than 1.7 metres below the true clean bottom of rivers, streams, open drains, canals or
dykes, but excluding land drains, culverts or sewers and not less than 2 metres below public highways
where applicable).
Work No. 10I – A carbon dioxide pipeline from and beneath the A164, Beverley Road, approximate
chainage 54,964 metres, to Jenkinson Lane (Work No. 10J), approximate chainage 55,172 metres, laid
in trench, in sleeves or by trenchless methods; such pipeline to be not less than 1.2 metres below ground
surface (or not less than 1.7 metres below the true clean bottom of rivers, streams, open drains, canals or
dykes, but excluding land drains, culverts or sewers and not less than 2 metres below public highways
where applicable).
Work No. 10J – A carbon dioxide pipeline from and beneath Jenkinson Lane, approximate chainage
55,172 metres, to Ricklepits (Work No. 10K), approximate chainage 57,185 metres, laid in trench, in
sleeves or by trenchless methods (save beneath the Driffield to Hutton Cranswick railway line where it
must be laid by trenchless methods); such pipeline to be not less than 1.2 metres below ground surface
(or not less than 1.7 metres below the true clean bottom of rivers, streams, open drains, canals or dykes,
but excluding land drains, culverts or sewers, not less than 2 metres below public highways or not less
than 4 metres below the underside of the railway sleepers comprised in the Driffield to Hutton
Cranswick railway line where applicable).
Work No. 10K – A carbon dioxide pipeline from and beneath Ricklepits, approximate chainage
57,185metres, to Skerne Block Valve (Work No. 11A), laid in trench, in sleeves or by trenchless
methods; such pipeline to be not less than 1.2 metres below ground surface (or not less than 1.7 metres
below the true clean bottom of rivers, streams, open drains, canals or dykes, but excluding land drains,
culverts or sewers and not less than 2 metres below public highways where applicable) save where the
pipeline rises to interface with Skerne Block Valve (Work No. 11A).
Work No. 11A – A carbon dioxide pipeline isolation facility at Skerne, to be known as the Skerne
Block Valve, including the following works and structures—
(a) construction and/or installation of above and below ground piping, piping bridles and bypasses,
insulation joints, valves, actuators and vents;
(b) construction and/or installation of pipe supports, instrument building and associated photo
voltaic cells and turbine, hard standing for temporary generator, backfilled pits and chambers, gated
security fence and cameras, pedestrian access, satellite dish, troughs, trays, ducting, drainage and
drainage attenuation, internal vehicular access routes, turning areas, pedestrian areas, post and rail
fencing and landscape screening;
(c) electrical and instrumentation construction and/or installation including instrumentation,
electrical cables, earthing protection, satellite dish, control and telecommunications cables, utility
metering, intruder detection systems and closed circuit television; and
(d) extensions of those parts of the carbon dioxide pipeline comprised in Work No. 10K and Work
No.13A, the cathodic protection facility comprised in Work No. 11B and the road comprised in Work
No. 11C which link to elements within this Work No. 11A.
Work No. 11B – A cathodic protection facility including a transformer rectifier kiosk with control
cabinet and junction box surrounded by a post and rail fence; anode canisters, electrical and cathodic
protection cables, utility meter and cabling; and cathodic protection test post and aerial markers.
Work No. 11C – A road from Main Street up to and including the carbon dioxide facility at Skerne
Block Valve (Work No. 11A) including any splays, gates, fencing, drainage, drainage attenuation and
interceptors, piped culverts, electricity kiosk, utilities, associated ducting and landscape works.
Work No. 11D – A temporary pipeline store and office area including temporary—
(a) office, welfare and security facilities;
54 54
(b) power supplies and temporary lighting;
(c) enclosures;
(d) pipe, equipment and fittings storage;
(e) plant storage;
(f) fabrication area;
(g) waste storage areas;
(h) spoil storage areas;
(i) internal haul roads;
(j) access parking; and
(k) water management areas.
Work No. 12 – A temporary pipeline store and office area, to be known as the Driffield Construction
Compound, including temporary–
(a) office, welfare and security facilities;
(b) power supplies and temporary lighting;
(c) enclosures;
(d) pipe, equipment and fittings storage;
(e) plant storage;
(f) fabrication area;
(g) waste storage areas;
(h) spoil storage areas;
(i) internal haul roads;
(j) access parking;
(k) vehicle maintenance area including washing facilities; and
(l) water management areas.
SKERNE TO PUMPING STATION
Work No. 13A - A carbon dioxide pipeline from Skerne Block Valve (Work No. 11A) to the B1249,
Frodingham Road (Work No. 13B), approximate chainage 60,990 metres, laid in trench, in sleeves or by
trenchless methods (save beneath the beds of the River Hull and the Driffield Canal where it must be
laid by trenchless methods); such pipeline to be not less than 1.2 metres below ground surface (or not
less than 1.7 metres below the true clean bottom of rivers, streams, open drains, canals or dykes, but
excluding land drains, culverts or sewers and not less than 2 metres below public highways or the true
clean bottom of the River Hull and the Driffield Canal where applicable) save where the pipeline rises to
interface with the Skerne Block Valve (Work No. 11A).
Work No. 13B – A carbon dioxide pipeline from and beneath the B1249, Frodingham Road,
approximate chainage 60,990 metres, to Main Street (Work No. 13C), approximate chainage 64,982
metres, laid in trench, in sleeves or by trenchless methods (save beneath the beds of the Nafferton
Highland Spring Drain, White Dike and Kelk Beck where it must be laid by trenchless methods); such
pipeline to be not less than 1.2 metres below ground surface (or not less than 1.7 metres below the true
clean bottom of rivers, streams, open drains, canals or dykes, but excluding land drains, culverts or
sewers and not less than 2 metres below public highways and the true clean bottom of the Nafferton
Highland Spring Drain, White Dike and Kelk Beck where applicable).
Work No. 13C – A carbon dioxide pipeline from and beneath Main Street, approximate chainage
64,982 metres, to Gransmoor Road (Work No. 13D), approximate chainage 68,618 metres, laid in
55 55
trench, in sleeves or by trenchless methods; such pipeline to be not less than 1.2 metres below ground
surface (or not less than 1.7 metres below the true clean bottom of rivers, streams, open drains, canals or
dykes, but excluding land drains, culverts or sewers and not less than 2 metres below public highways
where applicable).
Work No. 13D – A carbon dioxide pipeline from and beneath Gransmoor Road, approximate chainage
68,618 metres, to the A165, Bridlington Road (Work No. 13E), approximate chainage 71,453 metres,
laid in trench, in sleeves or by trenchless methods; such pipeline to be not less than 1.2 metres below
ground surface (or not less than 1.7 metres below the true clean bottom of rivers, streams, open drains,
canals or dykes, but excluding land drains, culverts or sewers and not less than 2 metres below public
highways where applicable).
Work No 13E – A carbon dioxide pipeline from and beneath the A165, Bridlington Road, approximate
chainage 71,453 metres, to Barmston Pumping Station (Work No. 14A), laid in trench, in sleeves or by
trenchless methods; such pipeline to be not less than 1.2 metres below ground surface (or not less than
1.7 metres below the true clean bottom of rivers, streams, open drains, canals or dykes, but excluding
land drains, culverts or sewers and not less than 2 metres below public highways where applicable) save
where the pipeline rises to interface with Barmston Pumping Station (Work No. 14A).
PUMPING STATION
Work No. 14A – A carbon dioxide pumping facility at Barmston, to be known as the Barmston
Pumping Station, including the following works and structures—
(a) temporary working area for constructing the Barmston Pumping Station including temporary—
(i) office, welfare and security facilities;
(ii) power supplies and temporary lighting;
(iii) enclosures;
(iv) pipe, equipment and fittings storage;
(v) plant storage
(vi) fabrication area;
(vii) waste storage areas;
(viii) spoil handling and storage areas;
(ix) internal haul roads;
(x) access and parking; and
(xi) water management areas;
(b) water supply works, foul drainage provision, surface water management system and culverting;
(c) construction and/or installation of two PIG trap reception and insertion areas including above
and below ground piping, piping bridles and bypasses, filtration, meters, analysers, pumping facility
bypass, insulation joints, actuators, vents and vent stacks, valves (including non return valves,
emergency shutdown valves and recycle valves), coolers, chillers, monoethylene glycol (MEG) tank and
water tank;
(d) construction and/or installation of pipe supports, local and remote instrument building and
associated photo voltaic cells and turbine, control and domestic building, stores areas, workshops, pump
houses, air and nitrogen building, substation, switchroom, variable speed drive containers, metering
buildings, analyser building, associated bottle store and hard standing hard standing for temporary
generator, backfilled pits and chambers, gated security fence and cameras, pedestrian access, lighting
columns, satellite dish, weather station, troughs, trays, ducting, internal vehicular access routes, turning
areas, pedestrian areas, pond, post and rail fencing and landscape screening, planting and earthworks;
(e) construction and/or installation of instrumentation, electrical cables, earthing protection,
satellite dish, control and telecommunications cables, utility metering, intruder detection systems and
closed circuit television, electrical cables, cathodic protection facility including a transformer rectifier
kiosk, anode canisters, electrical and cathodic protection cables, utility supplies, meters and cabling,
56 56
earthing protection, backfilled pits and chambers, electricity and communications kiosks, control and
telecommunications cables, troughs, trays, ducting, drainage and drainage attenuation; and
(f) extensions of those parts of the carbon dioxide pipeline comprised in Work No. 13E and Work
No. 15A and the road comprised in Work No 14B which link to elements within this Work No.
Work No. 14B – A cathodic protection facility including a transformer rectifier kiosk with control
cabinet and junction box surrounded by a post and rail fence; anode canisters, electrical and cathodic
protection cables, utility meter and cabling; and cathodic protection test posts and aerial markers.
Work No. 14C – Modifications to Sands Road between A165, Bridlington Road and Sands Road track;
modification of junction between Sands Road tarmac road and Sands Road track; upgrading Sands Road
track between junction with Sands Road tarmac road and access to Barmston Pumping Station; and a
road from Sands Road track up to and including the Barmston Pumping Station (Work No. 14A)
including any splays, gates, fencing, drainage, drainage attenuation and interceptors, piped culverts,
utilities, associated ducting and landscape screening.
Work No. 14D – A temporary pipeline store and office areas including temporary—
(a) office, welfare and security facilities;
(b) power supplies and temporary lighting;
(c) enclosures;
(d) pipe, equipment and fittings storage;
(e) plant storage;
(f) fabrication area;
(g) waste storage areas;
(h) spoil storage areas;
(i) internal haul roads;
(j) access parking;
(k) vehicle maintenance area including washing facilities; and
(l) water management areas.
LANDFALL
Work No. 15A – A carbon dioxide pipeline from Barmston Pumping Station (Work No. 14A) to a
landfall drive shaft (Work No. 15B), approximate chainage 73,094 metres, laid in trench, in sleeves or
by trenchless methods; such pipeline to be not less than 1.2 metres below ground surface save where the
pipeline rises to interface with the Barmston Pumping Station (Work No. 14A).
Work No. 15B A carbon dioxide pipeline from a landfall drive shaft comprised in this Work No. 15B to
mean low water spring tide (which has the same meaning as that given in Schedule 10 (deemed marine
licence under Part 4 (marine licensing) of the Marine and Coastal Access Act 2009), approximate
chainage 73,568 metres, laid by trench in sleeves or by trenchless methods (save beneath the cliffs
where it must be laid by trenchless methods); such pipeline to be not less than 1.2 metres below ground
surface; and which may include the following works and structures -
(a) temporary working areas including temporary—
(i) office, welfare and security facilities;
(ii) power supplies and temporary lighting;
(iii) workshops and stores;
(iv) materials and pipe, equipment and fittings storage;
(v) water tanks;
(vi) control cabin;
57 57
(vii) waste storage areas;
(viii) spoil handling and storage areas, spoil separators and settlement lagoons;
(xiii) de-watering systems and water management areas;
(ix) generators and switchgear;
(x) air receivers and compressors;
(xi) oil store;
(xii) drive shaft, slip trench;
(xiii) drilling rig, anchor blocks, slip trench;
(xiv) crane working areas;
(xv) reception pit / tie-in pit;
(xvi) access to the drive shaft/ drilling rig and reception area/ beach and parking;
(b) construction and installation of the pipeline under the cliffs by trenchless methods which may include
the installation of a concrete sleeve drive shaft and tunnel; backfilling of permanent structures not less
than 1.2 metres below ground surface; and temporary works including tunnel boring/pipeline drilling,
reception pit, hydraulic rams, rollers and brackets and winch;
(c) construction and installation of pipeline within the inter tidal zone which may include cofferdams and
temporary works including crane working areas, raised causeway, channel dredging, shallow bottomed
barge, winch, reception/tie-in pit and spoil storage.
FURTHER ASSOCIATED DEVELOPMENT
In connection with the above Work Nos. further associated development within the Order limits
consisting of—
(a) in relation to Work Nos. 1A, 4A, 6A, 9A, 11A and 14A site preparation works, site clearance
(including fencing, vegetation removal and creation of new footpaths), earthworks (including soil
stripping and storage) and site levelling;
(b) in relation to Work Nos. 1A, 4A, 6A, 9A and 11A establishment of site construction
compounds, storage areas, temporary vehicle parking, construction fencing (including perimeter
enclosure and security fencing), construction related buildings, welfare facilities, construction lighting,
haulage roads, fabrication areas, waste storage areas, spoil storage area, access, parking and water
management areas;
(c) installation of wires, cables, conductors, pipes and ducts;
(d) in relation to Work Nos. 3A, 3B, 3C, 3D, 3E, 3F, 3G, 5A, 5B, 5C, 5D, 5E, 5F, 5G, 5H, 5I, 5J,
8A, 8B, 8C, 8D, 8E, 8F, 8G, 8H, 8I, 8J, 8K, 8L, 10A, 10B, 10C, 10D, 10E, 10F, 10G, 10H, 10I, 10J,
10K, 13A, 13B, 13C, 13D, 13E, 15A and 15B pipeline construction works including—
(i) surveying and setting-out;
(ii) breaking-through, site clearance (including vegetation removal) and establishment of temporary
working area;
(iii) installation of demarcation fencing/stockproof fencing/heras fencing or similar;
(iv) pre-construction drainage;
(v) topsoil stripping;
(vi) levelling and benching;
(vii) archaeological surveys and watching brief;
(viii) pipe stringing, pipe bending, end preparation, front end welding, back end welding, fabrication
welding, pipeline coating, pipeline trench excavation, disruption or fragmentation of rock (including by
mechanical means), dewatering activities, trenchless crossings, lower and lay, sand padding, backfilling,
58 58
pipeline tie-ins, re-grading of soil, post construction drainage, cross-ripping and reinstatement of
top-soil, internally swab and gauge pipeline test sections;
(ix) filling, testing and dewatering test sections;
(x) reinstating test locations;
(xi) removing demarcation fencing;
(xii) reinstating boundary walls, hedges, and fencing;
(xiii) final gauge plate and calliper surveys;
(xiv) drying and commissioning pipelines;
(xv) demobilisation from site; and
(xvi) works to enable power supplies;
(e) works to remove or alter the position of apparatus including mains, sewers, drains and cables;
(f) in relation to Work Nos. 1A, 3A, 3B, 3C, 3D, 3E, 3F, 3G, 4A, 5A, 5B, 5C, 5D, 5E, 5F, 5G,
5H, 5I, 5J, 6A, 8A, 8B, 8C, 8D, 8E, 8F, 8G, 8H, 8I, 8J, 8K, 8L, 9A, 10A, 10B, 10C, 10D, 10E, 10F,
10G, 10H, 10I, 10J, 10K, 11A, 13A, 13B, 13C, 13D, 13E, 14A, 15A, 15B the location of aerial
markers, cathodic protection test posts and field boundary markers;
(g) landscaping and other works to mitigate any adverse effects of the construction, maintenance or
operation of the authorised development;
(h) works for the benefit or protection of land affected by the authorised development;
(i) works required for the strengthening, improvement, maintenance or reconstruction of any
streets;
(j) the carrying out of street works pursuant to article 10 (street works), works to alter the layout of
streets pursuant to article 11 (power to alter layout, etc., of streets) and the alteration or removal of road
furniture;
(k) ramps, means of access, provision of footpaths, bridleways, cycleways and footpath linkages;
(l) works for the maintenance of the authorised development;
(m) works for the decommissioning (including removal and demolition), restoration and aftercare of
the authorised development which fall within the scheme approved pursuant to paragraph 22
(decommissioning) of Schedule 3 (requirements);
(n) installation of drainage, drainage attenuation and land drainage including outfalls; and
(o) such other works, including working sites, storage areas and works of demolition, as may be
necessary for the purposes of or in connection with the construction or operation of the authorised
development and which do not give rise to any materially different effects from those assessed in the
environmental statement.
59 59
60
Page 56 of 99SCHEDULE 2
Streets Subject to Street Works
(1) (2)
Area Street subject to street works
Schedule CStreets to be Stopped Up
Part 1Streets for which a Substitute is to be Provided
(1) (2) (3) (4)
Area Street to be stopped up Extent of stopping up New street to be
substituted
Part 2Streets for which No Substitute is to be Provided
(1) (2) (3)
Area Street to be stopped up Extent of stopping up
Schedule DStreets to be Temporarily Stopped Up
(1) (2) (3)
Area Street to be temporarily stopped Extent of temporary stopping up
up
Schedule EAccess to Works
(1) (2)
Area Description of access
61
Page 57 of 99
Schedule FLand of which Only Subsoil More than 9 Metres Beneath Surface may be Acquired
(1) (2)
Area Number of land shown on land plan
Schedule GLand of which Temporary Possession may be Taken
(1) (2) (3) (4)
Area Number of land shown Purpose for which Relevant part of the
on land plan temporary possession
Authorised project may be taken
Schedule HDeemed Consent Under Coast Protection Act 1949
[Insert details of deemed consent]
Schedule IDeemed Licence Under the Food and Environment Protection Act 1985
[Insert details of deemed licence]
Schedule JTrees Subject to Tree Preservation Orders
(1) (2) (3)
Type of tree Number[reference] of tree shown Work to be carried outon land plan
Schedul
Sheet 1 of 25 10-2574-GND-01-05-0031
Sheet Number Drawing Number
e K Level Crossings
[Insert details of level crossings]
Schedule LProtective Provisions
Page 58 of 99
[Insert details of
protective provisions]
NOTES
Initial Commencement
Specified date
Specified date: 1 October 2009: see art 1.
UK Parliament SIs 2000-2009/2009/2251-2300/Infrastructure Planning (Model Provisions) (England and Wales) Order 2009 (SI 2009/2265)/SCHEDULE 3 Model Provisions for Harbours
SCHEDULE 3
MODEL PROVISIONS FOR HARBOURS
Article 2
CONTENTS
Preliminary
PLANS
PART 1 Article 2
WORKS PLANS
62
Drawing title
Works plans
Sheet 2 of 25
Sheet 3 of 25
Sheet 4 of 25
Sheet 5 of 25
Sheet 6 of 25
Sheet 7 of 25
Sheet 8 of 25
Sheet 9 of 25
Sheet 10 of 25
Sheet 11 of 25
Sheet 12 of 25
Sheet 13 of 25
Sheet 14 of 25
Sheet 15 of 25
Sheet 16 of 25
Sheet 17 of 25
Sheet 18 of 25
Sheet 19 of 25
Sheet 20 of 25
Sheet 21 of 25
Sheet 22 of 25
Sheet 23 of 25
Sheet 24 of 25
Sheet 25 of 25
10-2574-GND-01-05-0032
10-2574-GND-01-05-0033
10-2574-GND-01-05-0034
10-2574-GND-01-05-0035
10-2574-GND-01-05-0036
10-2574-GND-01-05-0037
10-2574-GND-01-05-0038
10-2574-GND-01-05-0039
10-2574-GND-01-05-0040
10-2574-GND-01-05-0041
10-2574-GND-01-05-0042
10-2574-GND-01-05-0043
10-2574-GND-01-05-0044
10-2574-GND-01-05-0045
10-2574-GND-01-05-0046
10-2574-GND-01-05-0047
10-2574-GND-01-05-0048
10-2574-GND-01-05-0049
10-2574-GND-01-05-0050
10-2574-GND-01-05-0051
10-2574-GND-01-05-0052
10-2574-GND-01-05-0053
10-2574-GND-01-05-0054
10-2574-GND-01-05-0055
Drawing NumberDrawing title
63
Sheet Number
Location Plan HUMBCC-2014-1-LP-JH-OV
Sheet Number Drawing Number
Land plans
Sheet 1 of 25
Sheet 2 of 25
Sheet 3 of 25
Sheet 4 of 25
Sheet 5 of 25
Sheet 6 of 25
Sheet 7 of 25
Sheet 8 of 25
Sheet 9 of 25
Sheet 10 of 25
Sheet 11 of 25
Sheet 12 of 25
Sheet 13 of 25
Sheet 14 of 25
Sheet 15 of 25
Sheet 16 of 25
Sheet 17 of 25
Sheet 18 of 25
Sheet 19 of 25
Sheet 20 of 25
Sheet 21 of 25
Sheet 22 of 25
Sheet 23 of 25
Sheet 24 of 25
Sheet 25 of 25
HUMBCC-2014-1-LP-JH-S1
HUMBCC-2014-1-LP-JH-S2
HUMBCC-2014-1-LP-JH-S3
HUMBCC-2014-1-LP-JH-S4
HUMBCC-2014-1-LP-JH-S5
HUMBCC-2014-1-LP-JH-S6
HUMBCC-2014-1-LP-JH-S7
HUMBCC-2014-1-LP-JH-S8
HUMBCC-2014-1-LP-JH-S9
HUMBCC-2014-1-LP-JH-S10
HUMBCC-2014-1-LP-JH-S11
HUMBCC-2014-1-LP-JH-S12
HUMBCC-2014-1-LP-JH-S13
HUMBCC-2014-1-LP-JH-S14
HUMBCC-2014-1-LP-JH-S15
HUMBCC-2014-1-LP-JH-S16
HUMBCC-2014-1-LP-JH-S17
HUMBCC-2014-1-LP-JH-S18
HUMBCC-2014-1-LP-JH-S19
HUMBCC-2014-1-LP-JH-S20
HUMBCC-2014-1-LP-JH-S21
HUMBCC-2014-1-LP-JH-S22
HUMBCC-2014-1-LP-JH-S23
HUMBCC-2014-1-LP-JH-S24
HUMBCC-2014-1-LP-JH-S25
PART 2 Article 2
LAND PLANS
Drawing title
64
Land plans – Location Plan
Sheet Number Drawing Number
Access, rights of way and
temporary stopping up plans
Sheet 1 of 25 10-2574-GND-01-05-0061
PART 3 Articles 2
ACCESS, RIGHTS OF WAY AND TEMPORARY STOPPING UP PLANS
Drawing title
Sheet 2 of 25
Sheet 3 of 25
Sheet 4 of 25
Sheet 5 of 25
Sheet 6 of 25
Sheet 7 of 25
Sheet 8 of 25
Sheet 9 of 25
Sheet 10 of 25
Sheet 11 of 25
Sheet 12 of 25
Sheet 13 of 25
Sheet 14 of 25
Sheet 15 of 25
Sheet 16 of 25
Sheet 17 of 25
Sheet 18 of 25
Sheet 19 of 25
Sheet 20 of 25
Sheet 21 of 25
Sheet 22 of 25
Sheet 23 of 25
Sheet 24 of 25
Sheet 25 of 25
10-2574-GND-01-05-0062
10-2574-GND-01-05-0063
10-2574-GND-01-05-0064
10-2574-GND-01-05-0065
10-2574-GND-01-05-0066
10-2574-GND-01-05-0067
10-2574-GND-01-05-0068
10-2574-GND-01-05-0069
10-2574-GND-01-05-0070
10-2574-GND-01-05-0071
10-2574-GND-01-05-0072
10-2574-GND-01-05-0073
10-2574-GND-01-05-0074
10-2574-GND-01-05-0075
10-2574-GND-01-05-0076
10-2574-GND-01-05-0077
10-2574-GND-01-05-0078
10-2574-GND-01-05-0079
10-2574-GND-01-05-0080
10-2574-GND-01-05-0081
10-2574-GND-01-05-0082
10-2574-GND-01-05-0083
10-2574-GND-01-05-0084
10-2574-GND-01-05-0085
65
A
Camblesforth Multi-junction Planting
Drawing
10-2574-PLN-01-0328 A
A
Drawing Number
Tollingham Block Valve Location Plan 10-2574-PLN-01-0304 A
Drax Pig Trap Elevations (Operational
Site
10-2574-PLN-01-0303
Tollingham Block Valve Planning
Arrangement
10-2574-GA-01-0319 A
A
Revision
Tollingham Block Valve Elevations (N
& E)
10-2574-GA-01-0320 A
Drax Pig Trap Planning Arrangement
Drax Pig Trap Planting Drawing
Tollingham Block Valve Elevations (S
& W)
10-2574-GA-01-0321 A
10-2574-PLN-01-0327 A
Tollingham Block Valve Elevations
(Operational Site)
10-2574-PLN-01-0323 A
10-2574-GA-01-0306 A
Tollingham Block Valve Planting
Drawing
10-2574-PLN-01-0329 A
Camblesforth Multi-junction Location
Plan
10-2574-PLN-01-0326
Dalton Block Valve Location Plan 10-2574-PLN-01-0308 A
A
PART 4 Article 2
APPROVED PLANS
Dalton Block Valve Planning
Arrangement
10-2574-GA-01-0322 A
Drawing title
Camblesforth Multi-junction Planning
Arrangement
Dalton Block Valve Elevations (N &
E)
10-2574-GA-01-0323 A
10-2574-GA-01-0316 A
Dalton Block Valve Elevations (S &
W)
10-2574-GA-01-0324 A
Drax Pig Trap Elevations (N & E) 10-2574-GA-01-0307
Dalton Block Valve Elevations
(Operational Site)
10-2574-PLN-01-0324 A
Camblesforth Multi-junction
Elevations (N & E)
10-2574-GA-01-0317
Dalton Block Valve Planting Drawing 10-2574-PLN-01-0331 A
A
A
Skerne Block Valve Location Plan 10-2574-PLN-01-0310 A
Drax Pig Trap Location Plan A
Camblesforth Multi-junction
Elevations (S & W)
Skerne Block Valve Planning
Arrangement
10-2574-GA-01-0325 A
10-2574-GA-01-0305 A
Skerne Block Valve Elevations (N &
E)
10-2574-GA-01-0326 A
10-2574-PLN-01-0302
Drax Pig Trap Elevations (S & W)
Skerne Block Valve Elevations (S & 10-2574-GA-01-0327 A
Camblesforth Multi-junction
Elevations (Operational Site)
10-2574-PLN-01-0325 A
66
10-2574-GA-01-0308
10-2574-PLN-01-1050 A
A
Skerne Block Valve Elevations
(Operational Site)
Widening of Sands Road Between
A165 Junction and Site Access
10-2574-PLN-01-1051 A
10-2574-PLN-01-0322
Camblesforth Multi-junction
Permanent Vehicular Access (A645)
Tollingham Construction Compound
Temporary Vehicular Access (Skiff
Lane)
10-2574-PLN-01-1052 A
10-2574-PLN-01-1045 A
Driffield Construction Compound
Temporary Vehicular Access (A614)
10-2574-PLN-01-1053 A
A
Revision
Drax Pig Trap Permanent Vehicular
Access (New Road) Swept Path
Analysis
10-2574-PLN-01-1054 A
Tollingham Block Valve Permanent
Vehicular Access (Skiff Lane)
10-2574-PLN-01-1046
Camblesforth Multi-junction
Permanent Vehicular Access (A645)
Swept Path Analysis
10-2574-PLN-01-1055 A
A
Drawing title
Tollingham Block Valve Permanent
Vehicular Access (Skiff Lane) Swept
Path Analysis
10-2574-PLN-01-1056 A
Skerne Block Valve Planting Drawing
Dalton Block Valve Permanent
Vehicular Access (Lund Wold Road)
Dalton Block Valve Permanent
Vehicular Access (Lund Wold Road)
Swept Path Analysis
10-2574-PLN-01-1057 A
10-2574-PLN-01-1047 A
Skerne Block Valve Permanent
Vehicular Access (Main Street,
Skerne) Swept Path Analysis
10-2574-PLN-01-1058 A
10-2574-PLN-01-0330 A
Barmston Pumping Station Permanent
Vehicular Access (Sands Road) Swept
Path Analysis
10-2574-PLN-01-1059 A
Skerne Block Valve Permanent
Vehicular Access (Main Street,
Skerne)
10-2574-PLN-01-1048
Tollingham Construction Compound
Temporary Vehicular Access (Skiff
Lane) Swept Path Analysis
10-2574-PLN-01-1060 A
A
Drawing Number
Driffield Construction Compound
Temporary Vehicular Access (A614)
Swept Path Analysis
10-2574-PLN-01-1061 A
W)
Barmston Pumping Station Permanent
Vehicular Access (Sands Road)
Typical Temporary Access From
Highway Flumed Ditch Crossing
10-2574-STD-01-1014 A
10-2574-PLN-01-1049 A
Typical Temporary Access From
Highway No Flumed Ditch Crossing
10-2574-STD-01-1015 A
Drax Pig Trap Temporary Construction
Vehicular Access (New Road)
10-2574-PLN-01-1044
67
Barmston Pumping Station Permanent
Vehicular Access (Sands Road)
(ii) S.I. 2010/490.
68
SCHEDULE 3 Article 52
REQUIREMENTS
1 InterpretationInterpretation
2 Incorporation of the Harbours, Docks and Piers Clauses Act 1847
Principal Powers
3 Development consent etc granted by the Order4 Period for completion of work5 Limits of harbour6 Maintenance of authorised project7 Subsidiary works8 Benefit of Order9 Consent to transfer benefit of Order
Streets
In this Schedule—1.
“the 2010 Regulations” means the Conservation of Habitats and Species Regulations 2010(ii);
“AGIs” means Above Ground Installations, namely those parts of the authorised development that
are the Drax PIG trap, Camblesforth Multi-junction, Tollingham, Skerne and Dalton Block Valves
and Barmston Pumping Station;
“Area B” means the area identified as “Area B” on drawing no.10-2574-GA-01-0316 rev A
(Camblesforth MJ Planning Arrangement) listed in Part 4 of Schedule 2 (plans) as the southern
area of the Camblesforth Multi-junction site to accommodate apparatus including up to 3 PIG traps;
“Barmston Pumping Station” means that part of the authorised development described in Work No.
14A of Schedule 1 (authorised development);
“Camblesforth Multi-junction” means that part of the authorised development described in Work
No. 4A of Schedule 1 (authorised development);
“code of construction practice” means the document(s) certified as the code of construction practice
by the Secretary of State for the purposes of this Order;
“commence” means for the purposes of this Schedule beginning to carry out any material operation
(as defined in section 155 of the 2008 Act) other than operations consisting of site clearance,
demolition work, archaeological investigations and removal works, investigations for the purpose of
assessing ground and geological conditions, remedial work in respect of any contamination or other
adverse ground conditions, diversion and laying of services, delivery and storage of equipment and
materials to construction compounds, temporary site accommodation, de-vegetation, necessary
pre-commencement environmental mitigation, erection of any temporary means of enclosure, the
temporary display of site notices or advertisements and “commencement” and “commenced” are to
be construed accordingly;
“construction compounds” means the temporary compounds needed to store equipment, materials
and site accommodation during the construction of the authorised development;
“construction work” means works to construct the authorised development, or relevant part of it,
excluding mobilisation of plant and equipment into, out of or within the Order limits;
69
“environmental statement” means the document(s) certified as the environmental statement by the
Secretary of State for the purposes of this Order together with any supplemental or additional
environmental statement submitted for the purposes of complying with and/or discharging these
requirements;
“European protected species” has the same meaning as in regulation 40 of the 2010 Regulations;
“European site” has the same meaning as it has in regulation 8(1) of the 2010 Regulations;
“Requirement” means the appropriate numbered paragraph or paragraphs in this Schedule to which
reference is made, for example “Requirement 6” or “these Requirements”;
“reinstatement” means the restoration of land within the Order limits for future use after
construction of the authorised development;
“relevant highway authority” means North Yorkshire County Council or East Riding of Yorkshire
Council as the case may be including their successor and where the relevant matter is located in the
administrative areas of both then it means both;
“relevant planning authority” means Selby District Council or East Riding of Yorkshire Council as
the case may be including their successor and where the relevant matter is located in the
administrative areas of both then it means both; and
“stage” means part of the authorised development as described in Requirement 4.
Time limits
The authorised development must be commenced within five years of the date of this Order.2.
Approved details
—a) The authorised development referred to in Schedule 1 must take place in general accordance 3.
with the approved details; and in this Requirement the “approved details” means the drawings listed
in Part 4 of Schedule 2 (approved plans).
For the purposes of Requirement (1), in determining “general accordance” the authorised (1)
development must be constructed within the lateral and vertical limits of deviation set out in article 6
(limits of deviation), subject to Requirements 5 and 6.
Stages of the authorised development
The stages of the authorised development for the purposes of these Requirements are (in no 4.
order of construction phasing)—
the “Drax to Camblesforth stage”, namely Work Nos. 3A to 3G;(a)
the “Camblesforth to Tollingham stage”, namely Work Nos. 5A to 5J;(b)
the “Tollingham to Dalton stage”, namely Work Nos. 8A to 8L;(c)
the “Dalton to Skerne stage”, namely Work Nos. 10A to 10K;(d)
the “Skerne to Barmston stage”, namely Work Nos. 13A to 13E;(e)
the “Barmston stage”, namely Work Nos. 14A to 14D;(f)
the “Drax PIG Trap stage”, namely Work Nos. 1A to 2A;(g)
the “Camblesforth Multi-junction stage”, namely Work Nos. 4A to 4D;(h)
the “Tollingham Block Valve stage” namely Work Nos. 6A to 6 D;(i)
the “Dalton Block Valve stage” namely Work Nos. 9A to 9D;(j)
the “Skerne Block Valve stage” namely Work Nos. 11A to 11D;(k)
the “Tollingham Construction Compound stage” namely Work No. 7;(l)
the “Driffield Construction Compound stage” namely Work No. 12;(m)
the “Landfall stage” namely Work Nos. 15A to 15B,(n)
and in each case such further associated development in connection with those Work Nos. as is listed at
paragraphs (a) to (o) of Schedule 1 (authorised development) inclusive insofar as it is relevant to that
stage.
70
Barmston Pumping Station
—a) Construction of the Barmston Pumping Station (Work Nos.14A and 14B) must not 5.
commence until details of the layout, scale, external appearance and landscaping of the Barmston
Pumping Station have been submitted to and approved by the relevant planning authority.
The details referred to in paragraph (1) must be in accordance with the Barmston Pumping Station (1)
parameter plan and the principles of chapter 8 of the design and access statement; and in this
Requirement—
the “design and access statement” means the document(s) certified as the design and access (a)
statement by the Secretary of State for the purposes of this Order; and
the “Barmston Pumping Station parameter plan” means the drawing given drawing number (b)
10-2574-PLN-01-0346 and document reference 2.14 and certified as the Barmston Pumping
Station parameter plan by the Secretary of State for the purposes of this Order.
The construction of the Barmston Pumping Station must be carried out in accordance with the (2)
approved details.
Camblesforth Multi-junction design
—a) No works to Area B of the Camblesforth Multi-junction (Work No. 4A) are to commence 6.
until details of the layout, scale and external appearance of those works have been submitted to and
approved by the relevant planning authority.
The details referred to in paragraph (1) must be in accordance with the Camblesforth Multi-junction (1)
parameter plan; and in this Requirement the “Camblesforth Multi-junction parameter plan” means the
drawing given drawing number 10-2574-GA-01-0316 and document reference 2.25 and certified as the
Camblesforth Multi-junction parameter plan by the Secretary of State for the purposes of this Order.
The construction of Area B of the Camblesforth Multi-junction must be carried out in accordance (2)
with the approved details.
European protected species
—a) No stage of the authorised development may commence until, for that stage, further survey 7.
work has been carried out to establish whether a European protected species is present—
on any land which may be affected by that stage of the authorised development; (a)
in any of the trees to be lopped or felled, in hedgerows removed or in buildings to be (b)
demolished during that stage of the authorised development,
and the results of the survey must be provided to Natural England.
Where a European protected species is shown to be present by the further survey work referred to in (1)
Requirement 7(1), the stage of the authorised development to which that survey work relates must not
commence until a scheme of protection and mitigation measures has been submitted to and approved by the
relevant planning authority, following consultation with Natural England; and that stage of the authorised
development must be carried out in accordance with the approved scheme.
Scheme of ecological mitigation and reinstatement
—a) No pipeline stage of the authorised development may commence until a scheme of 8.
ecological mitigation and reinstatement for that pipeline stage has been submitted—
in draft form for consultation with the relevant planning authority; and (a)
in final form for approval by the relevant planning authority and has been approved. (b)
The scheme must contain, insofar as it is relevant for that pipeline stage—(1)
the survey results and ecological mitigation measures for species and habitats that are not (a)
subject to the need for a licence pursuant to the 2010 Regulations (and which are included in
the environmental statement); and
a strategy for the reinstatement, re-planting and restoration of hedgerows and trees that are (b)
removed in the course of the carrying out of the authorised development.
71
The scheme must include an implementation timetable applicable to that pipeline stage of the (2)
authorised development.
Any pipeline stages of the authorised development must be carried out in accordance with the (3)
approved scheme for that stage.
Any tree, shrub or hedge planted as part of a scheme of ecological mitigation and reinstatement (4)
which dies or becomes within a period of 5 years after completion of the authorised development, in the
opinion of the relevant planning authority, seriously damaged or diseased, must be replaced in the first
available planting season (provided that it is within the 5 year period referred to in this Requirement 8(5))
with a specimen of the same species and size as that originally planted, unless otherwise approved by the
relevant planning authority.
In this Requirement, “pipeline stage” means any part of a stage insofar as it includes the (5)
cross-country pipeline comprised in the authorised development.
Water
—a) No stage of the authorised development shall commence until, for that stage, both a 9.
construction water management plan and pollution prevention and control plan have been submitted
to and approved by the relevant planning authority, in consultation with the Environment Agency.
The construction water management plan must include the following— (1)
details of measures to ensure discharge from dewatering is non-polluting and will not (a)
exacerbate flood risk;
details of areas at risk of water pollution from surface water run-off, and any special control (b)
measures required in those areas;
details of measures to minimise suspension of and pollution due to sediment;(c)
a commitment that works in the channel will be carried out in a bunded, dry working space with (d)
any water entering the space being pumped out for treatment prior to discharge back to the
watercourse;
a commitment that no discharges or abstractions will take place to or from ponds; (e)
where it is considered necessary to store material in the flood plain, the requirements for (f)
mitigation will be agreed with the Environment Agency before construction commences;
details of hydrostatic testing requirements, including water sources and discharge points, and (g)
water quality monitoring of test water discharged;
a commitment that water will be returned to the catchment it was abstracted from or if a (h)
groundwater source is used that groundwater is discharged to a surface water location identified
in consultation with the Environment Agency; and
all necessary licenses and consents will be obtained. (i)
The pollution prevention and control plan must include the following—(2)
details of a pollution incident response plan; (a)
details of storage and management of fuel and any other potentially polluting chemicals;(b)
details of pollution control measures;(c)
details regarding the control of mud at site accesses using road sweepers;(d)
details of the design and management of vehicle wash areas within the main Temporary (e)
Construction Compounds.
The construction works for each stage of the authorised development must be carried out in (3)
accordance with the approved construction water management plan and pollution prevention and control
plan, unless otherwise agreed with the relevant planning authority.
The method of crossing main rivers and ordinary watercourses (including land drains) shall be (4)
undertaken in a manner which will not cause an increase in flood risk to any area upstream, downstream or
surrounding the crossing.
72
Removal of trees and hedgerows
—a) No stage of the authorised development may commence until, for that stage, details 10.
identifying the trees, groups of trees and hedgerows to be removed during that stage have been
submitted to and approved by the relevant planning authority.
Each stage of the authorised development must be carried out in accordance with the approved (1)
details (if any) for that stage.
AGI hard landscaping and drainage
—a) No stage of the authorised development may commence until, for that stage, details of hard 11.
surfacing materials (if any) and drainage methods for all AGIs (with the exception of Area B of the
Camblesforth Multi-junction and the Barmston Pumping Station), have been submitted to and approved
by the relevant planning authority.
The authorised development must be carried out in accordance with the approved details.(1)
Archaeology
—a) No stage of the authorised development may commence until a written scheme of 12.
archaeological investigation for that stage has been submitted to and approved by the relevant
planning authority.
The written scheme must identify areas where a programme of archaeological investigation is (1)
required and the measures to be taken to protect, record or preserve any significant archaeological remains
that may be found.
Any archaeological works or watching brief for a stage of the authorised development must be (2)
carried out in accordance with the approved written scheme for that stage.
Construction Hours
—a) Subject to Requirements 13(3) and 13(4), construction work must only take place between 13.
the hours of 07:00 and 19:00 from Monday to Saturday and between 07:00 and 17:00 on Sundays
and Bank Holidays except in the event of an emergency, or unless otherwise agreed in writing by the
relevant planning authority.
In the event of an emergency, notification of that emergency must be given to the relevant planning (1)
authority as soon as practicable.
The following operations may take place outside the working hours referred to in Requirement (2)
13(1)—
microtunnelling;(a)
horizontal directional drilling;(b)
filling, testing, dewatering and drying locations (c)
works within the landfall, namely Work Nod.15A and 15B;(d)
dewatering activities;(e)
temporary possession of railway infrastructure;(f)
commissioning. (g)
Nothing in Requirement 13(1) above precludes—(3)
a reasonable start-up period and a reasonable shut-down period on Mondays to Saturdays (a)
(inclusive); and
maintenance at any time of plant and machinery engaged in the construction of the authorised (b)
development.
In this Requirement “emergency” means a situation where, if the relevant action is not taken, there (4)
will be adverse health, safety, security or environmental consequences that in the reasonable opinion of the
undertaker would outweigh the adverse effects to the public (whether individuals, classes or generally as
the case may be) of taking that action.
Effect Assessment Period
Day of Week
Monday – Saturdays 19.00 – 23.00 65
Time of Day SPL, dB LAeq,T
Sundays and Bank Holidays07.00 – 19.00
19:00 – 23:00
65
60
Construction Noise Threshold (at
the nearest façade)
Code of construction practice
Construction work must be carried out in accordance with the code of construction practice, 14.
unless otherwise approved in writing by the relevant planning authority.
Noise
—a) The construction of the authorised development must take place in accordance with, and 15.
not exceed, the following construction noise levels at the stated times, unless otherwise agreed with
the relevant planning authority—
Each Day 23.00 – 07.00 55
Monday – Fridays
Saturday
The operation of Barmston Pumping Station (Work Nos. 14A and 14B) must not commence until a (1)
noise report is submitted to and approved by the relevant planning authority for the Pumping Station.
The noise report must be based on the methodology as defined in British Standard 4142:1997 and (2)
demonstrate that the rating noise level for permanent fixed plant / machinery at the nearest existing
residential receptor (namely Rose Cottage) does not exceed the existing background noise level for when
the plant / machinery will operate (recorded as 24.4 LA90,T dB in July 2013).
The authorised development must be carried out in accordance with any— (3)
noise limits; and (a)
specifications for— (b)
site design and material;(i)
plant and machinery specifications;(ii)
operation and maintenance,(iii)
specified in the approved noise report, unless otherwise approved by the relevant planning
authority.
Land drainage
Subject to Requirement 11 (AGI hard landscaping and drainage), the authorised development 16.
must take place in accordance with the drainage strategy, unless otherwise agreed in writing by the
relevant planning authority; and in this Requirement “drainage strategy” means the document(s)
certified as the drainage strategy by the Secretary of State for the purposes of this Order.
Contaminated land and groundwater
—a) In the event that contamination is found at any time when carrying out the authorised 17.
development that has not been previously identified it must be reported in writing immediately to the
relevant planning authority.
07.00 – 19.00
07.00 – 19.00
73
70
70
74
An investigation and risk assessment must be completed in accordance with a scheme to assess the (1)
nature and extent of any contamination on the part of the Order limits within which works are being
carried out, whether or not that contamination originates on that part of the Order limits; and—
the contents of that scheme are subject to the approval in writing of the relevant planning (a)
authority; and
that investigation and risk assessment must be undertaken by competent persons and a written (b)
report of the findings must be produced.
Where remediation is required a detailed remediation scheme to bring a part of the Order limits (2)
within which works are being carried out to a condition suitable for the intended use must be prepared and
submitted for the written approval of the relevant planning authority; and—
the approved remediation scheme must be carried out in accordance with its terms unless (a)
otherwise approved in writing by the relevant planning authority; and
following completion of measures identified in the approved remediation scheme, a verification (b)
report that demonstrates the effectiveness of the remediation carried out must be produced and
approved in writing by the relevant planning authority.
Construction traffic plan
—a) No stage of the authorised development may commence until a traffic management plan 18.
for that stage has been submitted to and, following consultation with the highway authority, been
approved by the relevant planning authority; and each stage of the authorised development must be
carried out in accordance with the traffic management plan for that stage, unless otherwise agreed in
writing by the relevant planning authority.
Restoration of land used temporarily for construction
Subject to article 28(4) (temporary use of land for carrying out the authorised development), 19.
any land within the Order limits which is used temporarily for construction must be reinstated to a
condition fit for its former use, or such other condition as the relevant planning authority may
approve, within 12 months of completion of the authorised development.
Requirement for written approval
Where under any of the Requirements the approval or agreement of the relevant planning 20.
authority or another person is required, that approval or agreement must be given in writing.
Amendments to approved details
With respect to any Requirement which requires the authorised development to be carried out in 21.
accordance or general accordance with details approved by the relevant planning authority, the
approved details include any amendments that may subsequently be approved in writing by the
relevant planning authority to the extent that the authority may lawfully do so.
Decommissioning
—a) At least six months prior to the permanent cessation of operation of the authorised 22.
development, a scheme of decommissioning, restoration and aftercare of the authorised development
must be submitted for approval by the relevant planning authority.
The scheme must include proposals for—(1)
future uses of the above ground installations following permanent cessation of such installations (a)
or (if none) the means of decommissioning such installations;
future uses of the pipelines comprised in the authorised development or (if none) the means of (b)
decommissioning of such pipelines;
what above-ground structures, buildings and other parts of the authorised development are to be (c)
demolished or retained and the means of any demolition;
the phasing of any decommissioning, demolition and/or removal proposed in Requirements (d)
22(2)(a) to (c);
75
the means of removal of decommissioning materials and demolition waste arising from the (e)
activities listed in Requirements 22(2)(a) to (c);
works for the restoration of land within the Order limits on which the authorised development is (f)
located and the phasing of such restoration works;
aftercare of the authorised development, having regard to any future uses of elements of the (g)
authorised development, including the long term retention and maintenance of cathodic
protection;
a risk management plan setting out measures to be taken in appropriate circumstances to (h)
minimise risk in respect of the authorised development following permanent cessation of
operation of the authorised development; and
a timetable for implementation of the scheme.(i)
The scheme must be implemented as approved following the permanent cessation of the operation of (2)
the authorised development.
In this Requirement—(3)
“aftercare” means monitoring, maintenance and management of land within the Order limits (a)
following its reinstatement and restoration;
“decommissioning” means the decommissioning of the authorised development on the later of (b)
(a) the date on which it is no longer required for operational use or (b) the permanent cessation
of operation of the authorised development, as the case may be;
“operational use” or “operation of the authorised development” means use of the authorised (c)
development for the purposes for which it is authorised; and
“permanent cessation” means the cessation of operation of the authorised development, or (d)
relevant part of it, where there is a demonstrable intention to cease permanently those
operations.
Driffield Construction Compound
In the Driffield Construction Compound comprised in Work No. 12 no buildings may be 23.
demolished in the area shown coloured blue, cross-hatched orange and labelled “no buildings to be
demolished as part of the Onshore Scheme” on the drawing entitled “Environmental Commitments
Map 8 of 10” provided in the code of construction practice.
Venting for AGI Maintenance
For planned maintenance of each of the AGIs, the internal inventory of carbon dioxide may 24.
only be vented twice a year;
10 Street works) At a rate whereby noise emissions at each site do not exceed a maximum of
70dB LAeq, 1hr at the nearest existing noise sensitive receptor;
11 Stopping up of streets12 Temporary stopping up of streets13 Access to works14 Agreements with street authorities15 Public rights of way
2) Where the duration of a vent activity does not exceed one hour; and
3) Between the hours of 07:00 and 19:00 Monday to Friday.
AGI Venting for Pipeline Inspections
The initial frequency of planned internal inspection of pipelines using PIGs will be set at once 25.
every five years. Over time the frequency will be adjusted following examination of previous
inspection data. That is, the inspection intervals could be extended or reduced to meet the needs of
maintaining a safe operating pipeline.
76
Venting of the internal inventory of carbon dioxide at PIG traps at AGIs, for the purposes of internal
inspection of pipelines, may only occur;
At a rate whereby noise emissions at each site do not exceed a maximum of 70dB LAeq, 1hr at the (1)
nearest existing noise sensitive receptor;
Over a venting duration of no more than one hour for each site, which may be repeated on multiple (2)
days over a period which does not exceed 14 days at each AGI;
Between the hours of 07:00 and 19:00 Monday to Friday.(3)
For the purposes of Work No. 3A, unnamed private tarmac track to Drax
pump house and River Ouse (for information indicated as TX 0/4 on access,
rights of way and temporary stopping up plans drawing number
10-2574-GND-01-05-0061 sheet 1 of 25) where crossed by the authorised
development within the Order Limits.
Works plans drawing number 10-2574-GND-01-05-0031(sheet 1 of 25)
For the purposes of Work No. 3A, Long Drax Footpath 35.47/6/1 (for
information indicated on access, rights of way and temporary stopping up
plans drawing number 10-2574-GND-01-05-0061 sheet 1 of 25) where
crossed by the authorised development within the Order Limits.
Works plans drawing number 10-2574-GND-01-05-0031 (sheet 1 of 25)
(1)
Area
North Yorkshire
County Council, Selby
District Council
For the purposes of Work No. 3B, Pear Tree Avenue, Long Drax (for
information tarmac road indicated as RDX 1/A and B on access, rights of way
and temporary stopping up plans drawing number 10-2574-GND-01-05-0061
sheet 1 of 25) where crossed by the authorised development within the Order
Limits.
Works plans drawing number 10-2574-GND-01-05-0031(sheet 1 of 25)
North Yorkshire
County Council, Selby
District Council
North Yorkshire
County Council, Selby
District Council
North Yorkshire
County Council, Selby
District Council
For the purposes of Work No. 3B, Long Drax Footpath No. 35.47/1/1
(for information indicated on access, rights of way and temporary stopping up
plans drawing number 10-2574-GND-01-05-0061 sheet 1 of 25) where
crossed by the authorised development within the Order Limits.
Works plans drawing number 10-2574-GND-01-05-0031(sheet 1 of 25)
For the purposes of Work No. 3A, unnamed private farm track north of
Augustinian Priory (for information indicated as TX 0/2 on access, rights of
way and temporary stopping up plans drawing number
10-2574-GND-01-05-0061 sheet 1 of 25) where crossed by the authorised
development within the Order Limits.
Works plans drawing number 10-2574-GND-01-05-0031 (sheet 1 of 25)
For the purposes of Work No. 3A, unnamed private farm track to Foreman’s
Cottage (for information indicated as TX 0/1 on access, rights of way and
temporary stopping up plans (drawing number 10-2574-GND-01-05-0061;
sheet 1 of 25) where crossed by the authorised development within the Order
Limits.
Works plans drawing number 10-2574-GND-01-05-0031(sheet 1 of 25)
North Yorkshire
County Council, Selby
District Council
For the purposes of Work No. 3B, Long Drax Footpath No. 35.47/8/1
(for information indicated on access, rights of way and temporary stopping up
plans drawing number 10-2574-GND-01-05-0061 sheet 1 of 25) where
crossed by the authorised development within the Order Limits.
Works plans drawing number 10-2574-GND-01-05-0031(sheet 1 of 25)
(2)
Street subject to street works
North Yorkshire
County Council, Selby
District Council
North Yorkshire
County Council, Selby
District Council
For the purposes of Work No. 3B, Unnamed private track north east of New
Close Plantation (for information indicated as TX 1/1 on access, rights of way
and temporary stopping up plans drawing number 10-2574-GND-01-05-0061
sheet 1 of 25) where crossed by the authorised development within the Order
Limits.
For the purposes of Work No. 3A, unnamed private farm track east of Lendall
Drain (for information indicated as TX 0/3 on access, rights of way and
temporary stopping up plans drawing number 10-2574-GND-01-05-0061
sheet 1 of 25) where crossed by the authorised development within the Order
Limits.
Works plans drawing number 10-2574-GND-01-05-0031(sheet 1 of 25)
SCHEDULE 4 Article 10
STREETS SUBJECT TO STREET WORKS
North Yorkshire
County Council, Selby
District Council
77
North Yorkshire
County Council, Selby
District Council
North Yorkshire
County Council, Selby
District Council
For the purposes of Work No. 3E, Church Dike Lane, Drax (for information
tarmac road indicated as RDX 4/A and B on access, rights of way and
temporary stopping up plans drawing number 10-2574-GND-01-05-0062
sheet 2 of 25) where crossed by the authorised development within the Order
Limits.
Works plans drawing number 10-2574-GND-01-05-0032 (sheet 2 of 25)
North Yorkshire
County Council, Selby
District Council
North Yorkshire
County Council, Selby
District Council
North Yorkshire
County Council, Selby
District Council
For the purposes of Work No. 3E, Hales Lane unmade private track (for
information indicated as TX 4/1 on access, rights of way and temporary
stopping up plans drawing number 10-2574-GND-01-05-0062 sheet 2 of 25)
where crossed by the authorised development within the Order Limits.
Works plans drawing number 10-2574-GND-01-05-0032 (sheet 2 of 25)
For the purposes of Work No. 3D, Main Road, Long Drax (for information
tarmac road indicated as RDX 3/A and B on access, rights of way and
temporary stopping up plans drawing number 10-2574-GND-01-05-0061
sheet 1 of 25) where crossed by the authorised development within the Order
Limits.
Works plans drawing number 10-2574-GND-01-05-0031(sheet 1 of 25)
For the purposes of Work No. 3C, Carr Lane, Long Drax (for information
tarmac road indicated as RDX 2/A and B on access, rights of way and
temporary stopping up plans drawing number 10-2574-GND-01-05-0061
sheet 1 of 25) where crossed by the authorised development within the Order
Limits.
Works plans drawing number 10-2574-GND-01-05-0031(sheet 1 of 25)
North Yorkshire
County Council, Selby
District Council
For the purposes of Work No. 3F, Brickhill Lane, Drax (for information
tarmac road indicated as RDX 5/A and B on access, rights of way and
temporary stopping up plans drawing number 10-2574-GND-01-05-0062
sheet 2 of 25) where crossed by the authorised development within the Order
Limits.
Works plans drawing number 10-2574-GND-01-05-0032 (sheet 2 of 25)
Works plans drawing number 10-2574-GND-01-05-0031(sheet 1 of 25)
North Yorkshire
County Council, Selby
District Council
North Yorkshire
County Council, Selby
District Council
For the purposes of Work No. 3G and 5B, A645, Drax (for information
tarmac road indicated as RDX 6 + 7/A and B on access, rights of way and
temporary stopping up plans drawing number 10-2574-GND-01-05-0062
sheet 2 of 25) where crossed by the authorised development within the Order
Limits.
Works plans drawing number 10-2574-GND-01-05-0032 (sheet 2 of 25)
For the purposes of Work No. 3D, Drax Footpath No. 35.47/5/1 (for
information indicated on access, rights of way and temporary stopping up
plans drawing number 10-2574-GND-01-05-0061 sheet 1 of 25) where
crossed by the authorised development within the Order Limits.
Works plans drawing number 10-2574-GND-01-05-0031(sheet 1 of 25)
(2)
Street subject to street works
North Yorkshire
County Council, Selby
District Council
For the purposes of Work No. 3G and 5A, unnamed private concrete/ tarmac
track to fishing lake (for information indicated as TX 6/1 and TX 6/4 on
access, rights of way and temporary stopping up plans drawing number
10-2574-GND-01-05-0062 sheet 2 of 25) where crossed by the authorised
development within the Order Limits.
Works plans drawing number 10-2574-GND-01-05-0032 (sheet 2 of 25)
North Yorkshire
County Council, Selby
District Council
North Yorkshire
County Council, Selby
District Council
North Yorkshire For the purposes of Work No. 3G and 5A, unnamed private unmade farm
For the purposes of Work No. 3D, Drax Footpath 35.26/7/1
(for information indicated on access, rights of way and temporary stopping up
plans drawing number 10-2574-GND-01-05-0062 sheet 2 of 25) where
crossed by the authorised development within the Order Limits.
Works plans drawing number 10-2574-GND-01-05-0032 (sheet 2 of 25)
For the purposes of Work No. 3C, Long Drax Footpath No. 35.47/4/1
(for information indicated on access, rights of way and temporary stopping up
plans drawing number 10-2574-GND-01-05-0061 sheet 1 of 25) where
crossed by the authorised development within the Order Limits.
Works plans drawing number 10-2574-GND-01-05-0031(sheet 1 of 25)
78
(1)
Area
For the purposes of Work No. 5C, unmade path Scurff Cottages, Drax
Footpath No. 35.26/13/1 / Newland Footpath No. 35.49/1/2 (for information
indicated on access, rights of way and temporary stopping up plans drawing
number 10-2574-GND-01-05-0062 sheet 2 of 25) where crossed by the
authorised development within the Order Limits.
Works plans drawing number 10-2574-GND-01-05-0033 (sheet 3 of 25)
North Yorkshire
County Council, Selby
District Council
For the purposes of Work No. 5B, (Brickhill Lane track) Drax Footpath No.
35.26/9/1 (for information indicated on access, rights of way and temporary
stopping up plans drawing number 10-2574-GND-01-05-0062 sheet 2 of 25)
where crossed by the authorised development within the Order Limits.
Works plans drawing number 10-2574-GND-01-05-0032 (sheet 2 of 25)
North Yorkshire
County Council, Selby
District Council
For the purposes of Work No. 5C, unmade path Scurff Cottages, Newland
Footpath No.35.49/2/2 (for information indicated on access, rights of way and
temporary stopping up plans drawing number 10-2574-GND-01-05-0062
sheet 2 of 25) where crossed by the authorised development within the Order
Limits.
Works plans drawing number 10-2574-GND-01-05-0033 (sheet 3 of 25)
(1)
Area
(2)
Street subject to street works
East Riding of
Yorkshire Council
For the purposes of Work No. 5C, Barmby-on-the-Marsh Footpath No 3,
north of River Ouse (for information indicated on access, rights of way and
temporary stopping up plans drawing number 10-2574-GND-01-05-0063
sheet 3 of 25) where crossed by the authorised development within the Order
Limits.
Works plans drawing number 10-2574-GND-01-05-0033 (sheet 3 of 25)
North Yorkshire
County Council, Selby
District Council
For the purposes of Work No. 5B, Hales Lane unmade private track (for
information indicated as TX 7/2 on access, rights of way and temporary
stopping up plans drawing number 10-2574-GND-01-05-0062 sheet 2 of 25)
where crossed by the authorised development within the Order Limits.
Works plans drawing number 10-2574-GND-01-05-0032 (sheet 2 of 25)
East Riding of
Yorkshire Council
For the purposes of Work No. 5C, Bankfield Lane private stone surfaced
track (for information indicated as TX 8/1 on access, rights of way and
temporary stopping up plans drawing number 10-2574-GND-01-05-0063
sheet 3 of 25) where crossed by the authorised development within the Order
Limits.
Works plans drawing number 10-2574-GND-01-05-0033 (sheet 3 of 25)
North Yorkshire
County Council, Selby
District Council
For the purposes of Work No. 5B, Brickhill Lane, tarmac track (for
information indicated as TX 7/1 on access, rights of way and temporary
stopping up plans drawing number 10-2574-GND-01-05-0062 sheet 2 of 25)
where crossed by the authorised development within the Order Limits.
Works plans drawing number 10-2574-GND-01-05-0032 (sheet 2 of 25)
East Riding of
Yorkshire Council
For the purposes of Work No. 5C, Gateland Field Lane unmade private farm
track (for information indicated as TX 8/2 on access, rights of way and
temporary stopping up plans drawing number 10-2574-GND-01-05-0063
sheet 3 of 25) where crossed by the authorised development within the Order
Limits.
Works plans drawing number 10-2574-GND-01-05-0033 (sheet 3 of 25)
North Yorkshire
County Council, Selby
District Council
For the purposes of Work No. 5C, Church Dike Lane, Drax (for information
tarmac road indicated as RDX 8/A and B on access, rights of way and
temporary stopping up plans drawing number 10-2574-GND-01-05-0062
sheet 2 of 25) where crossed by the authorised development within the Order
Limits.
Works plans drawing number 10-2574-GND-01-05-0032 (sheet 2 of 25)
East Riding of
Yorkshire Council
For the purposes of Work No. 5C, unnamed private unmade track prior to
Fields Drain (for information indicated as TX 8/3on access, rights of way and
County Council, Selby
District Council
track (continuation of Wade House Lane) (for information indicated as TX
6/2 and TX 6/3 on access, rights of way and temporary stopping up plans
drawing number 10-2574-GND-01-05-0062 sheet 2 of 25) where crossed by
the authorised development within the Order Limits.
Works plans drawing number 10-2574-GND-01-05-0032 (sheet 2 of 25)
79
North Yorkshire
County Council, Selby
District Council
For the purposes of Work No. 5C, unnamed private unmade track to RDX9,
Barmby Road (for information indicated as TX 8/5 on access, rights of way
and temporary stopping up plans drawing number 10-2574-GND-01-05-0063
sheet 3 of 25) where crossed by the authorised development within the Order
Limits.
Works plans drawing number 10-2574-GND-01-05-0033 (sheet 3 of 25)
(1)
Area
East Riding of
Yorkshire Council
For the purposes of Work No. 5D, Asselby Footpath No.2 Side of Marsh
Lane track (for information indicated on access, rights of way and temporary
stopping up plans drawing number 10-2574-GND-01-05-0064 sheet 4 of 25)
where crossed by the authorised development within the Order Limits.
Works plans drawing number 10-2574-GND-01-05-0034 (sheet 4 of 25)
East Riding of
Yorkshire Council
East Riding of
Yorkshire Council
East Riding of
Yorkshire Council
For the purposes of Work No. 5D, Asselby Footpath No.1 to Old Derwent
Drain (for information indicated on access, rights of way and temporary
stopping up plans drawing number 10-2574-GND-01-05-0064 sheet 4 of 25)
where crossed by the authorised development within the Order Limits.
Works plans drawing number 10-2574-GND-01-05-0034 (sheet 4 of 25)
For the purposes of Work No. 5D, Barmby Road, Asselby (for information
tarmac road indicated as RDX 9/A and B on access, rights of way and
temporary stopping up plans drawing number 10-2574-GND-01-05-0063
sheet 3 of 25) where crossed by the authorised development within the Order
Limits.
Works plans drawing number 10-2574-GND-01-05-0033 (sheet 3 of 25)
For the purposes of Work No. 5C, unnamed private unmade track from Fair
Field Farm (for information indicated as TX 8/4 on access, rights of way and
temporary stopping up plans drawing number 10-2574-GND-01-05-0063
sheet 3 of 25) where crossed by the authorised development within the Order
Limits.
Works plans drawing number 10-2574-GND-01-05-0033 (sheet 3 of 25)
East Riding of
Yorkshire Council
For the purposes of Work No. 5D, unnamed private unmade track at the side
of New Drain (for information indicated as TX 9/3 on access, rights of way
and temporary stopping up plans drawing number 10-2574-GND-01-05-0064
sheet 4 of 25) where crossed by the authorised development within the Order
Limits.
Works plans drawing number 10-2574-GND-01-05-0034 (sheet 4 of 25)
temporary stopping up plans drawing number 10-2574-GND-01-05-0063
sheet 3 of 25) where crossed by the authorised development within the Order
Limits.
Works plans drawing number 10-2574-GND-01-05-0033 (sheet 3 of 25)
East Riding of
Yorkshire Council
East Riding of
Yorkshire Council
For the purposes of Work No. 5E, A63 Hull Road, Newsholme (for
information tarmac road indicated as RDX 10/A and B on access, rights of
way and temporary stopping up plans drawing number
10-2574-GND-01-05-0064 sheet 4 of 25) where crossed by the authorised
development within the Order Limits.
Works plans drawing number 10-2574-GND-01-05-0034 (sheet 4 of 25)
For the purposes of Work No. 5D, unnamed private unmade farm track north
east of Mount Pleasant bungalow (for information indicated as TX 9/1 on
access, rights of way and temporary stopping up plans drawing number
10-2574-GND-01-05-0064 sheet 4 of 25) where crossed by the authorised
development within the Order Limits.
Works plans drawing number 10-2574-GND-01-05-0034 (sheet 4 of 25)
(2)
Street subject to street works
East Riding of
Yorkshire Council
For the purposes of Work No. 5E, Wressle Footpath No.10 to Park Farm
(for information indicated on access, rights of way and temporary stopping up
plans drawing number 10-2574-GND-01-05-0064 sheet 4 of 25) where
East Riding of
Yorkshire Council
East Riding of
Yorkshire Council
80
For the purposes of Work No. 5D, Marsh Lane private track (for information
indicated as TX 9/2 on access, rights of way and temporary stopping up plans
drawing number 10-2574-GND-01-05-0064 sheet 4 of 25) where crossed by
the authorised development within the Order Limits.
Works plans drawing number 10-2574-GND-01-05-0034 (sheet 4 of 25)
For the purposes of Work No. 5E, Wressle Footpath No 8 (for information
indicated on access, rights of way and temporary stopping up plans drawing
number 10-2574-GND-01-05-0065 sheet 5 of 25) where crossed by the
authorised development within the Order Limits.
Works plans drawing number 10-2574-GND-01-05-0035 (sheet 5 of 25)
(1)
Area
East Riding of
Yorkshire Council
For the purposes of Work No. 5G, Eastrington Bridleway No. 17 (western
end of Featherbed Lane) (for information indicated on access, rights of way
and temporary stopping up plans drawing number 10-2574-GND-01-05-0066
sheet 6 of 25) where crossed by the authorised development within the Order
Limits.
Works plans drawing number 10-2574-GND-01-05-0036 (sheet 6 of 25)
East Riding of
Yorkshire Council
East Riding of
Yorkshire Council
East Riding of
Yorkshire Council
For the purposes of Work No. 5G, Featherbed Lane unmade private track
(western end of Featherbed Lane) (for information indicated as TX 12/1on
access, rights of way and temporary stopping up plans drawing number
10-2574-GND-01-05-0066 sheet 6 of 25) where crossed by the authorised
development within the Order Limits.
Works plans drawing number 10-2574-GND-01-05-0036 (sheet 6 of 25)
For the purposes of Work No. 5E, Wressle Footpath No 7 (for information
indicated on access, rights of way and temporary stopping up plans drawing
number 10-2574-GND-01-05-0065 sheet 5 of 25) where crossed by the
authorised development within the Order Limits.
Works plans drawing number 10-2574-GND-01-05-0035 (sheet 5 of 25)
For the purposes of Work No. 5E, Wressle Footpath No 6 (for information
indicated on access, rights of way and temporary stopping up plans drawing
number 10-2574-GND-01-05-0065 sheet 5 of 25) where crossed by the
authorised development within the Order Limits.
Works plans drawing number 10-2574-GND-01-05-0035 (sheet 5 of 25)
East Riding of
Yorkshire Council
For the purposes of Work No. 5G, Featherbed Lane unmade private track
(eastern end of Featherbed Lane) (for information indicated as TX 12/2
on access, rights of way and temporary stopping up plans drawing number
10-2574-GND-01-05-0066 sheet 6 of 25) where crossed by the authorised
development within the Order Limits.
Works plans drawing number 10-2574-GND-01-05-0036 (sheet 6 of 25)
crossed by the authorised development within the Order Limits.
Works plans drawing number 10-2574-GND-01-05-0034 (sheet 4 of 25)
East Riding of
Yorkshire Council
East Riding of
Yorkshire Council
For the purposes of Work No. 5G, Eastrington Bridleway No. 17 (eastern end
of Featherbed Lane) (for information indicated on access, rights of way and
temporary stopping up plans drawing number 10-2574-GND-01-05-0066
sheet 6 of 25) where crossed by the authorised development within the Order
Limits.
Works plans drawing number 10-2574-GND-01-05-0036 (sheet 6 of 25)
For the purposes of Work No. 5F, Brind Lane, Brind (for information tarmac
road indicated as RDX 11/A and B on access, rights of way and temporary
stopping up plans drawing number 10-2574-GND-01-05-0065 sheet 5 of 25)
where crossed by the authorised development within the Order Limits.
Works plans drawing number 10-2574-GND-01-05-0035 (sheet 5 of 25)
(2)
Street subject to street works
East Riding of
Yorkshire Council
For the purposes of Work No. 5H, A614 Holme Road, Spaldington (for
information tarmac road indicated as RDX 13/A and B on access, rights of
way and temporary stopping up plans drawing number
10-2574-GND-01-05-0067 sheet 7 of 25) where crossed by the authorised
development within the Order Limits.
Works plans drawing number 10-2574-GND-01-05-0037 (sheet 7 of 25)
East Riding of
Yorkshire Council
East Riding of
Yorkshire Council
81
For the purposes of Work No. 5G, B1228 Wood Lane, Brind (for information
tarmac road indicated as RDX 12/A and B on access, rights of way and
temporary stopping up plans drawing number 10-2574-GND-01-05-0065
sheet 5 of 25) where crossed by the authorised development within the Order
Limits.
Works plans drawing number 10-2574-GND-01-05-0035 (sheet 5 of 25)
For the purposes of Work No. 5H, unnamed private unmade farm track to
Chestnut farm (for information indicated as TX 13/1 on access, rights of way
and temporary stopping up plans drawing number 10-2574-GND-01-05-0067
sheet 7 of 25) where crossed by the authorised development within the Order
Limits.
Works plans drawing number 10-2574-GND-01-05-0037 (sheet 7 of 25)
East Riding of
Yorkshire Council
For the purposes of Work No. 5I, Bursea Lane, Holme Upon Spalding Moor
(for information tarmac road indicated as RDX 14/A and B on access, rights
of way and temporary stopping up plans drawing number
10-2574-GND-01-05-0068 sheet 8 of 25) where crossed by the authorised
development within the Order Limits.
Works plans drawing number 10-2574-GND-01-05-0038 (sheet 8 of 25)
East Riding of
Yorkshire Council
For the purposes of Work No. 5H, Spaldington Footpath No.12 - Combined
with TX 13/2 (for information indicated on access, rights of way and
temporary stopping up plans drawing number 10-2574-GND-01-05-0067
sheet 7 of 25) where crossed by the authorised development within the Order
Limits.
Works plans drawing number 10-2574-GND-01-05-0037 (sheet 7 of 25)
East Riding of
Yorkshire Council
For the purposes of Work No. 5J, Drain Lane, Holme Upon Spalding Moor
(for information tarmac road indicated as RDX 15/A and B on access, rights
of way and temporary stopping up plans drawing number
10-2574-GND-01-05-0068 sheet 8 of 25) where crossed by the authorised
development within the Order Limits.
Works plans drawing number 10-2574-GND-01-05-0038 (sheet 8 of 25)
(1)
Area
(2)
Street subject to street works
East Riding of
Yorkshire Council
For the purposes of Work No. 8B, Skiff Lane, Holme Upon Spalding Moor
(for information tarmac road indicated as RDX 16/A and B on access, rights
of way and temporary stopping up plans drawing number
10-2574-GND-01-05-0069 sheet 9 of 25) where crossed by the authorised
development within the Order Limits.
Works plans drawing number 10-2574-GND-01-05-0039 (sheet 9 of 25)
East Riding of
Yorkshire Council
For the purposes of Work No. 5H, unnamed private unmade track to Sikes
Farm (for information indicated as TX 13/3 on access, rights of way and
temporary stopping up plans drawing number 10-2574-GND-01-05-0067
sheet 7 of 25) where crossed by the authorised development within the Order
Limits.
Works plans drawing number 10-2574-GND-01-05-0037 (sheet 7 of 25)
East Riding of
Yorkshire Council
For the purposes of Work No. 8C, Lock Lane, Holme Upon Spalding Moor
(for information tarmac road indicated as RDX 17/A and B on access, rights
of way and temporary stopping up plans drawing number
10-2574-GND-01-05-0069 sheet 9 of 25) where crossed by the authorised
development within the Order Limits.
Works plans drawing number 10-2574-GND-01-05-0039 (sheet 9 of 25)
East Riding of
Yorkshire Council
For the purposes of Work No. 5H, unnamed private unmade track to Taynton
Lodge (for information indicated as TX 13/2 on access, rights of way and
temporary stopping up plans drawing number 10-2574-GND-01-05-0067
sheet 7 of 25) where crossed by the authorised development within the Order
Limits.
Works plans drawing number 10-2574-GND-01-05-0037 (sheet 7 of 25)
East Riding of
Yorkshire Council
For the purposes of Work No. 8C, unnamed private unmade track to the side
of Market Weighton Canal (for information indicated as TX 17/1 on access,
rights of way and temporary stopping up plans drawing number
East Riding of
Yorkshire Council
For the purposes of Work No. 5H, unnamed private unmade track to Welham
Bridge Farm (for information indicated as TX 13/4 on access, rights of way
and temporary stopping up plans drawing number 10-2574-GND-01-05-0067
sheet 7 of 25) where crossed by the authorised development within the Order
Limits.
Works plans drawing number 10-2574-GND-01-05-0037 (sheet 7 of 25)
82
East Riding of
Yorkshire Council
For the purposes of Work No. 8D, unnamed private unmade farm track to Top
Cottages (for information indicated as TX 18/1 on access, rights of way and
temporary stopping up plans drawing number 10-2574-GND-01-05-0070
sheet 10 of 25) where crossed by the authorised development within the Order
Limits.
Works plans drawing number 10-2574-GND-01-05-0040 (sheet 10 of 25)
(1)
Area
East Riding of
Yorkshire Council
For the purposes of Work No. 8E, unnamed private unmade farm track from
Cliffe Road by the side of the reservoir (for information indicated as TX 19/1
on access, rights of way and temporary stopping up plans drawing number
10-2574-GND-01-05-0071 sheet 11 of 25) where crossed by the authorised
development within the Order Limits.
Works plans drawing number 10-2574-GND-01-05-0041 (sheet 11 of 25)
East Riding of
Yorkshire Council
East Riding of
Yorkshire Council
East Riding of
Yorkshire Council
For the purposes of Work No. 8F, A1034 Sancton Road, Market Weighton
(for information tarmac road indicated as RDX 20/A and B on access, rights
of way and temporary stopping up plans drawing number
10-2574-GND-01-05-0072 sheet 12 of 25) where crossed by the authorised
development within the Order Limits.
Works plans drawing number 10-2574-GND-01-05-0042 (sheet 12 of 25)
For the purposes of Work No. 8D, Unnamed private unmade track from Long
Lane to Bellsbeck Farm (for information indicated as TX 18/2 on access,
rights of way and temporary stopping up plans drawing number
10-2574-GND-01-05-0070 sheet 10 of 25) where crossed by the authorised
development within the Order Limits.
Works plans drawing number 10-2574-GND-01-05-0040 (sheet 10 of 25)
For the purposes of Work No. 8D, Sand Lane, North Cliffe (for information
tarmac road indicated as RDX 18/A and B on access, rights of way and
temporary stopping up plans drawing number 10-2574-GND-01-05-0070
sheet 10 of 25) where crossed by the authorised development within the Order
Limits.
Works plans drawing number 10-2574-GND-01-05-0040 (sheet 10 of 25)
East Riding of
Yorkshire Council
For the purposes of Work No. 8F, unnamed private unmade farm track to
Weighton Wold House (for information indicated as TX 20/1 on access, rights
of way and temporary stopping up plans drawing number
10-2574-GND-01-05-0072 sheet 12 of 25) where crossed by the authorised
development within the Order Limits.
Works plans drawing number 10-2574-GND-01-05-0042 (sheet 12 of 25)
10-2574-GND-01-05-0069 sheet 9 of 25) where crossed by the authorised
development within the Order Limits.
Works plans drawing number 10-2574-GND-01-05-0039 (sheet 9 of 25)
East Riding of
Yorkshire Council
East Riding of
Yorkshire Council
For the purposes of Work No. 8G, A1079 Arras Hill, Market Weighton (for
information tarmac road indicated as RDX 21/A and B on access, rights of
way and temporary stopping up plans drawing number
10-2574-GND-01-05-0072 sheet 12 of 25) where crossed by the authorised
development within the Order Limits.
Works plans drawing number 10-2574-GND-01-05-0042 (sheet 12 of 25)
For the purposes of Work No. 8E, Cliffe Road, Market Weighton (for
information tarmac road indicated as RDX 19/A and B on access, rights of
way and temporary stopping up plans drawing number
10-2574-GND-01-05-0071 sheet 11 of 25) where crossed by the authorised
development within the Order Limits.
Works plans drawing number 10-2574-GND-01-05-0041 (sheet 11 of 25)
(2)
Street subject to street works
East Riding of For the purposes of Work No. 8G, unnamed private unmade farm track to
East Riding of
Yorkshire Council
East Riding of
Yorkshire Council
83
For the purposes of Work No. 8E, Market Weighton Footpath No 11, between
Market Weighton Canal and Back Delfin Drain (for information indicated on
access, rights of way and temporary stopping up plans drawing number
10-2574-GND-01-05-0071 sheet 11 of 25) where crossed by the authorised
development within the Order Limits.
Works plans drawing number 10-2574-GND-01-05-0041 (sheet 11 of 25)
For the purposes of Work No. 8J, Kiplingcotes Racecourse Road, Etton (for
information tarmac road indicated as RDX 24/A and B on access, rights of
way and temporary stopping up plans drawing number
10-2574-GND-01-05-0074 sheet 14 of 25) where crossed by the authorised
development within the Order Limits.
Works plans drawing number 10-2574-GND-01-05-0044 (sheet 14 of 25)
East Riding of
Yorkshire Council
For the purposes of Work No. 8H, Kiplingcotes Lane, Market Weighton (for
information tarmac road indicated as RDX 22/A and B on access, rights of
way and temporary stopping up plans drawing number
10-2574-GND-01-05-0073 sheet 13 of 25) where crossed by the authorised
development within the Order Limits.
Works plans drawing number 10-2574-GND-01-05-0043 (sheet 13 of 25)
East Riding of
Yorkshire Council
For the purposes of Work No. 8K, Park Road, South Dalton (for information
tarmac road indicated as RDX 25/A and B on access, rights of way and
temporary stopping up plans drawing number 10-2574-GND-01-05-0074
sheet 14 of 25) where crossed by the authorised development within the Order
Limits.
Works plans drawing number 10-2574-GND-01-05-0044 (sheet 14 of 25)
(1)
Area
(2)
Street subject to street works
East Riding of
Yorkshire Council
For the purposes of Work No. 8K, unnamed private unmade farm track (for
information indicated as TX 25/1 on access, rights of way and temporary
stopping up plans drawing number 10-2574-GND-01-05-0075 sheet 15 of 25)
where crossed by the authorised development within the Order Limits.
Works plans drawing number 10-2574-GND-01-05-0045 (sheet 15 of 25)
East Riding of
Yorkshire Council
For the purposes of Work No. 8H, Etton Bridleway No. 5 Hudson Way (for
information indicated on access, rights of way and temporary stopping up
plans drawing number 10-2574-GND-01-05-0073 sheet 13 of 25) where
crossed by the authorised development within the Order Limits.
Works plans drawing number 10-2574-GND-01-05-0043 (sheet 13 of 25)
East Riding of
Yorkshire Council
For the purposes of Work No. 8L, Holme Wold Road, Holme on the Wolds
(for information tarmac road indicated as RDX 26/A and B on access, rights
of way and temporary stopping up plans drawing number
10-2574-GND-01-05-0075 sheet 15 of 25) where crossed by the authorised
development within the Order Limits.
Works plans drawing number 10-2574-GND-01-05-0045 (sheet 15 of 25)
East Riding of
Yorkshire Council
For the purposes of Work No. 8G, Goodmanham Footpath No. 6 (for
information indicated on access, rights of way and temporary stopping up
plans drawing number 10-2574-GND-01-05-0072 sheet 12 of 25) where
crossed by the authorised development within the Order Limits.
Works plans drawing number 10-2574-GND-01-05-0042 (sheet 12 of 25)
East Riding of
Yorkshire Council
For the purposes of Work No. 10A, Lund Footpath No. 2 path from Lund
Wold Road to Bulmer’s Triangle (for information indicated on access, rights
of way and temporary stopping up plans drawing number
10-2574-GND-01-05-0075 sheet 15 of 25) where crossed by the authorised
development within the Order Limits.
Works plans drawing number 10-2574-GND-01-05-0045 (sheet 15 of 25)
East Riding of
Yorkshire Council
For the purposes of Work No. 8I, Kiplingcotes Road, Etton (for information
tarmac road indicated as RDX 23/A and B on access, rights of way and
temporary stopping up plans drawing number 10-2574-GND-01-05-0074
sheet 14 of 25) where crossed by the authorised development within the Order
Limits.
Works plans drawing number 10-2574-GND-01-05-0044 (sheet 14 of 25)
East Riding of For the purposes of Work No. 10B, Lund Wold Road, Lund (for information
Yorkshire Council Wold House Farm (for information indicated as TX 21/1 on access, rights of
way and temporary stopping up plans drawing number
10-2574-GND-01-05-0072 sheet 12 of 25) where crossed by the authorised
development within the Order Limits.
Works plans drawing number 10-2574-GND-01-05-0042 (sheet 12 of 25)
84
East Riding of
Yorkshire Council
For the purposes of Work No. 10E, unnamed private unmade track
(for information indicated as TX 30/1 on access, rights of way and temporary
stopping up plans drawing number 10-2574-GND-01-05-0077 sheet 17 of 25)
where crossed by the authorised development within the Order Limits.
Works plans drawing number 10-2574-GND-01-05-0047 (sheet 17 of 25)
East Riding of
Yorkshire Council
For the purposes of Work No. 10D, B1248 Lund Road, Middleton on the
Wolds (for information tarmac road indicated as RDX 29/A and B on access,
rights of way and temporary stopping up plans drawing number
10-2574-GND-01-05-0076 sheet 16 of 25) where crossed by the authorised
development within the Order Limits.
Works plans drawing number 10-2574-GND-01-05-0046 (sheet 16 of 25)
East Riding of
Yorkshire Council
For the purposes of Work No. 10E, Walton Footpath No 20 (for information
indicated on access, rights of way and temporary stopping up plans drawing
number 10-2574-GND-01-05-0077 sheet 17 of 25) where crossed by the
authorised development within the Order Limits.
Works plans drawing number 10-2574-GND-01-05-0047 (sheet 17 of 25)
(1)
Area
(2)
Street subject to street works
East Riding of
Yorkshire Council
For the purposes of Work No. 10F, unnamed Road from Bracken Lane to
Burnbutts Lane, Watton (for information tarmac road indicated as RDX 31/A
and B on access, rights of way and temporary stopping up plans drawing
number 10-2574-GND-01-05-0077 sheet 17 of 25) where crossed by the
authorised development within the Order Limits.
Works plans drawing number 10-2574-GND-01-05-0047 (sheet 17 of 25)
East Riding of
Yorkshire Council
For the purposes of Work No. 10E, Middleton Road, Kilnwick (for
information tarmac road indicated as RDX 30/A and B on access, rights of
way and temporary stopping up plans drawing number
10-2574-GND-01-05-0077 sheet 17 of 25) where crossed by the authorised
development within the Order Limits.
Works plans drawing number 10-2574-GND-01-05-0047 (sheet 17 of 25)
East Riding of
Yorkshire Council
For the purposes of Work No. 10G, Burnbutts Lane, Hutton Cranswick (for
information tarmac road indicated as RDX 32/A and B on access, rights of
way and temporary stopping up plans drawing number
10-2574-GND-01-05-0077 sheet 17 of 25) where crossed by the authorised
development within the Order Limits.
Works plans drawing number 10-2574-GND-01-05-0047 (sheet 17 of 25)
East Riding of
Yorkshire Council
For the purposes of Work No. 10C, Middleton Road, Lund (for information
tarmac road indicated as RDX 28/A and B on access, rights of way and
temporary stopping up plans drawing number 10-2574-GND-01-05-0076
sheet 16 of 25) where crossed by the authorised development within the Order
Limits.
Works plans drawing number 10-2574-GND-01-05-0046 (sheet 16 of 25)
East Riding of
Yorkshire Council
For the purposes of Work No. 10G, Hutton Cranswick Footpath No. 12 to
Bustardnest Fox Covert (for information indicated on access, rights of way
and temporary stopping up plans drawing number 10-2574-GND-01-05-0078
sheet 18 of 25) where crossed by the authorised development within the Order
Limits.
Works plans drawing number 10-2574-GND-01-05-0048 (sheet 18 of 25)
East Riding of
Yorkshire Council
For the purposes of Work No. 10E, Walton Footpath No 2 (for information
indicated on access, rights of way and temporary stopping up plans drawing
number 10-2574-GND-01-05-0077 sheet 17 of 25) where crossed by the
authorised development within the Order Limits.
Works plans drawing number 10-2574-GND-01-05-0047 (sheet 17 of 25)
East Riding of
Yorkshire Council
For the purposes of Work No. 10G, Hutton Cranswick Footpath No. 11 to
Bustardnest Fox Covert (for information indicated on access, rights of way
Yorkshire Council tarmac road indicated as RDX 27/A and B on access, rights of way and
temporary stopping up plans drawing number 10-2574-GND-01-05-0076
sheet 16 of 25) where crossed by the authorised development within the Order
Limits.
Works plans drawing number 10-2574-GND-01-05-0046 (sheet 16 of 25)
85
East Riding of
Yorkshire Council
For the purposes of Work No. 10I, A164 Beverley Road, Hutton Cranswick
(for information tarmac road indicated as RDX 34/A and B on access, rights
of way and temporary stopping up plans drawing number
10-2574-GND-01-05-0079 sheet 19 of 25) where crossed by the authorised
development within the Order Limits.
Works plans drawing number 10-2574-GND-01-05-0049 (sheet 19 of 25)
(1)
Area
East Riding of
Yorkshire Council
For the purposes of Work No. 10K, unnamed private unmade farm track to
Church Farm (for information indicated as TX 36/1 on access, rights of way
and temporary stopping up plans drawing number 10-2574-GND-01-05-0080
sheet 20 of 25) where crossed by the authorised development within the Order
Limits.
Works plans drawing number 10-2574-GND-01-05-0050 (sheet 20 of 25)
East Riding of
Yorkshire Council
East Riding of
Yorkshire Council
East Riding of
Yorkshire Council
For the purposes of Work No. 13A, unnamed private unmade farm track to
Cooper Hall (for information indicated as TX 36/2 on access, rights of way
and temporary stopping up plans drawing number 10-2574-GND-01-05-0080
sheet 20 of 25) where crossed by the authorised development within the Order
Limits.
Works plans drawing number 10-2574-GND-01-05-0050 (sheet 20 of 25)
For the purposes of Work No. 10J, Jenkinson Lane, Hutton (for information
tarmac road indicated as RDX 35/A and B on access, rights of way and
temporary stopping up plans drawing number 10-2574-GND-01-05-0079
sheet 19 of 25) where crossed by the authorised development within the Order
Limits.
Works plans drawing number 10-2574-GND-01-05-0049 (sheet 19 of 25)
For the purposes of Work No. 10H, Southburn Road, Hutton Cranswick (for
information tarmac road indicated as RDX 33/A and B on access, rights of
way and temporary stopping up plans drawing number
10-2574-GND-01-05-0079 sheet 19 of 25) where crossed by the authorised
development within the Order Limits.
Works plans drawing number 10-2574-GND-01-05-0049 (sheet 19 of 25)
East Riding of
Yorkshire Council
For the purposes of Work No. 13A, Skerne and Wansford Bridleway No. 7 to
Cooper Hall (for information indicated on access, rights of way and temporary
stopping up plans drawing number 10-2574-GND-01-05-0080 sheet 20 of 25)
where crossed by the authorised development within the Order Limits.
Works plans drawing number 10-2574-GND-01-05-0050 (sheet 20 of 25)
and temporary stopping up plans drawing number 10-2574-GND-01-05-0078
sheet 18 of 25) where crossed by the authorised development within the Order
Limits.
Works plans drawing number 10-2574-GND-01-05-0048 (sheet 18 of 25)
East Riding of
Yorkshire Council
East Riding of
Yorkshire Council
For the purposes of Work No. 13A, Skerne and Wansford Bridleway and
Footpath No. 9 south of River Hull (for information indicated on access, rights
of way and temporary stopping up plans drawing number
10-2574-GND-01-05-0081 sheet 21 of 25) where crossed by the authorised
development within the Order Limits.
Works plans drawing number 10-2574-GND-01-05-0051 (sheet 21 of 25)
For the purposes of Work No. 10J, Hutton Cranswick Footpath No.18 at the
side of Northfield Beck (for information indicated on access, rights of way
and temporary stopping up plans drawing number 10-2574-GND-01-05-0079
sheet 19 of 25) where crossed by the authorised development within the Order
Limits.
Works plans drawing number 10-2574-GND-01-05-0049 (sheet 19 of 25)
(2)
Street subject to street works
East Riding of For the purposes of Work No. 13B, B1249 Frodingham Road, Wansford (for
East Riding of
Yorkshire Council
East Riding of
Yorkshire Council
86
For the purposes of Work No. 10K, Ricklepits, Skerne (for information
tarmac road indicated as RDX 36/A and B on access, rights of way and
temporary stopping up plans drawing number 10-2574-GND-01-05-0079
sheet 19 of 25) where crossed by the authorised development within the Order
Limits.
Works plans drawing number 10-2574-GND-01-05-0049 (sheet 19 of 25)
information tarmac road indicated as RDX 37/A and B on access, rights of
way and temporary stopping up plans drawing number
10-2574-GND-01-05-0081 sheet 21 of 25) where crossed by the authorised
development within the Order Limits.
Works plans drawing number 10-2574-GND-01-05-0051 (sheet 21 of 25)
East Riding of
Yorkshire Council
For the purposes of Work No. 13C, Foston on the Wolds Footpath No.11 (for
information indicated on access, rights of way and temporary stopping up
plans drawing number 10-2574-GND-01-05-0082 sheet 22 of 25) where
crossed by the authorised development within the Order Limits.
Works plans drawing number 10-2574-GND-01-05-0052 (sheet 22 of 25)
East Riding of
Yorkshire Council
For the purposes of Work No. 13B, unnamed private track to South
Cattleholmes (for information indicated as TX 37/2 on access, rights of way
and temporary stopping up plans drawing number 10-2574-GND-01-05-0081
sheet 21 of 25) where crossed by the authorised development within the Order
Limits.
Works plans drawing number 10-2574-GND-01-05-0051 (sheet 21 of 25)
East Riding of
Yorkshire Council
For the purposes of Work No. 13C, unnamed private unmade track to
Gransmoor Quarry (for information indicated as TX 38/1 on access, rights of
way and temporary stopping up plans drawing number
10-2574-GND-01-05-0082 sheet 22 of 25) where crossed by the authorised
development within the Order Limits.
Works plans drawing number 10-2574-GND-01-05-0052 (sheet 22 of 25)
(1)
Area
(2)
Street subject to street works
East Riding of
Yorkshire Council
For the purposes of Work No. 13C, unnamed private unmade track to Manor
Farm (for information indicated as TX 38/2 on access, rights of way and
temporary stopping up plans drawing number 10-2574-GND-01-05-0083
sheet 23 of 25) where crossed by the authorised development within the Order
Limits.
Works plans drawing number 10-2574-GND-01-05-0053 (sheet 23 of 25)
East Riding of
Yorkshire Council
For the purposes of Work No. 13B, unnamed private track South of Markham
Dale (for information indicated as TX 37/3 on access, rights of way and
temporary stopping up plans drawing number 10-2574-GND-01-05-0082
sheet 22 of 25) where crossed by the authorised development within the Order
Limits.
Works plans drawing number 10-2574-GND-01-05-0052 (sheet 22 of 25)
East Riding of
Yorkshire Council
For the purposes of Work No. 13D, Gransmoor Road, Gransmoor (for
information tarmac road indicated as RDX 39/A and B on access, rights of
way and temporary stopping up plans drawing number
10-2574-GND-01-05-0083 sheet 23 of 25) where crossed by the authorised
development within the Order Limits.
Works plans drawing number 10-2574-GND-01-05-0053 (sheet 23 of 25)
East Riding of
Yorkshire Council
For the purposes of Work No. 13B, unnamed private unmade track west of
White Dike (for information indicated as TX 37/1 on access, rights of way
and temporary stopping up plans drawing number 10-2574-GND-01-05-0081
sheet 21 of 25) where crossed by the authorised development within the Order
Limits.
Works plans drawing number 10-2574-GND-01-05-0051 (sheet 21 of 25)
East Riding of
Yorkshire Council
For the purposes of Work No. 13D, unnamed private unmade track to fishing
pond (for information indicated as TX 39/1 on access, rights of way and
temporary stopping up plans drawing number 10-2574-GND-01-05-0085
sheet 25 of 25) where crossed by the authorised development within the Order
Limits.
Works plans drawing number 10-2574-GND-01-05-0055 (sheet 25 of 25)
East Riding of
Yorkshire Council
For the purposes of Work No. 13C, Main Street, Great Kelk (for information
tarmac road indicated as RDX 38/A and B on access, rights of way and
temporary stopping up plans drawing number 10-2574-GND-01-05-0082
sheet 22 of 25) where crossed by the authorised development within the Order
Limits.
Works plans drawing number 10-2574-GND-01-05-0052 (sheet 22 of 25)
87
Yorkshire Council
For the purposes of Work No. 13E, A165 Bridlington Road, Barmston (for
information tarmac road indicated as RDX 40/A and B on access, rights of
way and temporary stopping up plans drawing number
10-2574-GND-01-05-0085 sheet 25 of 25) where crossed by the authorised
development within the Order Limits.
Works plans drawing number 10-2574-GND-01-05-0055 (sheet 25 of 25)
East Riding of
Yorkshire Council
For the purposes of Work No. 13E, Barmston Footpath No.3 (for information
indicated on access, rights of way and temporary stopping up plans drawing
number 10-2574-GND-01-05-0085 sheet 25 of 25) where crossed by the
authorised development within the Order Limits.
Works plans drawing number 10-2574-GND-01-05-0055 (sheet 25 of 25)
(1)
Area
(2)
Street subject to street works
East Riding of
Yorkshire Council
For the purposes of Work No. 15A, Barmston Footpath No.4 (for information
indicated on access, rights of way and temporary stopping up plans drawing
number 10-2574-GND-01-05-0085 sheet 25 of 25) where crossed by the
authorised development within the Order Limits.
Works plans drawing number 10-2574-GND-01-05-0055 (sheet 25 of 25)
East Riding of
Yorkshire Council
For the purposes of Work No. 13E, Barmston Footpath No.2 (for information
indicated on access, rights of way and temporary stopping up plans drawing
number 10-2574-GND-01-05-0085 sheet 25 of 25) where crossed by the
authorised development within the Order Limits.
Works plans drawing number 10-2574-GND-01-05-0055 (sheet 25 of 25)
88
East Riding of
Yorkshire Council
SCHEDULE 5 Article 11
STREETS SUBJECT TO ALTERATION OF LAYOUT
PART 1
STREETS SUBJECT TO TEMPORARY ALTERATION OF LAYOUT
(1)
Area
North Yorkshire County
Council
Selby District Council
Carr Lane, Long
DraxTemporary construction accessAt RDX 2/A and B shown on access, rights of way
and temporary stopping up plan drawing number
10-2574-GND-01-05-0061 (Sheet 1 of 25) the
creation of a temporary bellmouth access on each
side of the road, with sufficient size to accommodate
a low loader comprising a temporary alteration of the
roadside verge and the temporary fluming of the
ditch on each side of the road.
North Yorkshire County
Council
Selby District Council
New Road, Long
Drax
North Yorkshire County
Council
Selby District Council
Main Road, Long
DraxTemporary construction accessAt RDX 3/A and B shown on access, rights of way
and temporary stopping up plan drawing number
10-2574-GND-01-05-0061 (Sheet 1 of 25) the
creation of a temporary bellmouth access on each
side of the road, with sufficient size to accommodate
a low loader comprising a temporary alteration of the
roadside verge on each side of the road and the
temporary fluming of the ditch on the western side of
the road (RDX3A).
Temporary construction accessAt RDX 0/A shown on access, rights of way and
temporary stopping up plan drawing number
10-2574-GND-01-05-0061 (Sheet 1 of 25) the
widening of an existing bellmouth access to create a
temporary access with sufficient size to
accommodate large articulated vehicle (15.4m
length) comprising an alteration of the splay,
hedgeline and verge on the north western side and
reinforcement of verge on south eastern side of New
Road approximately 150 metres from the junction
with Pear Tree Avenue. As depicted in drawing no.
10-2574-PLN-01-1044 and 10-2574-PLN-01-1054.
(2)
Street subject to
alteration of layout
North Yorkshire County
Council
Selby District Council
Church Dike Lane,
Drax Temporary construction accessAt RDX 4/A and B shown on access, rights of way
and temporary stopping up plan drawing number
(3)
Description of alteration
North Yorkshire County
Council
Selby District Council
Pear Tree Avenue,
Long Drax
89
Temporary construction accessAt RDX 1/A and B shown on access, rights of way
and temporary stopping up plan drawing number
10-2574-GND-01-05-0061 (Sheet 1 of 25) the
creation of a temporary bellmouth access on each
side of the road, with sufficient size to accommodate
a low loader comprising a temporary alteration of the
roadside verge on each side of the road.
(3)
Description of alteration
North Yorkshire County
Council
Selby District Council
Church Dike Lane,
Drax Temporary construction accessAt RDX 8/A and B shown on access, rights of way
and temporary stopping up plan drawing number
10-2574-GND-01-05-0062 (Sheet 2 of 25) the
creation of a temporary bellmouth access on each
side of the road, with sufficient size to accommodate
a low loader comprising a temporary alteration of the
roadside verge on each side of the road and the
temporary fluming of the ditch on the northern side of
the road (RDX 8/B).
North Yorkshire County
Council
Selby District Council
Brickhill Lane, Drax
East Riding of
Yorkshire Council
Barmby Road,
AsselbyTemporary construction accessAt RDX 9/A and B shown on access, rights of way
and temporary stopping up plan drawing number
10-2574-GND-01-05-0063 (Sheet 3 of 25) the
creation of a temporary bellmouth access on each
side of the road, with sufficient size to accommodate
a low loader omprising a temporary alteration of the
roadside verge on each side of the road.
Temporary construction accessAt RDX 5/A and B shown on access, rights of way
and temporary stopping up plan drawing number
10-2574-GND-01-05-0062 (Sheet 2 of 25) the
creation of a temporary bellmouth access on each
side of the road, with sufficient size to accommodate
a low loader comprising a temporary alteration of the
roadside verge on each side of the road and the
temporary fluming of the ditch on the eastern side of
the road (RDX 5/A).
(1)
Area
East Riding of
Yorkshire Council
A63 Hull Road,
NewsholmeTemporary construction accessAt RDX 10/A and B shown on access, rights of way
and temporary stopping up plan drawing number
10-2574-GND-01-05-0064 (Sheet 4 of 25) the
creation of a temporary bellmouth access on each
side of the road, with sufficient size to accommodate
a low loader comprising a temporary alteration of the
kerb line and roadside verge on each side of the road.
10-2574-GND-01-05-0062 (Sheet 2 of 25) the
creation of a temporary bellmouth access on each
side of the road, with sufficient size to accommodate
a low loader comprising a temporary alteration of the
roadside verge on each side of the road and the
temporary fluming of the ditch on the northern side of
the road (RDX4/A).
North Yorkshire County
Council
Selby District Council
East Riding of
Yorkshire Council
Brind Lane, Brind Temporary construction accessAt RDX 11/A and B shown on access, rights of way
and temporary stopping up plan drawing number
10-2574-GND-01-05-0065 (Sheet 5 of 25) the
creation of a temporary bellmouth access on each
side of the road, with sufficient size to accommodate
a low loader comprising a temporary alteration of the
A645, Drax Temporary construction accessAt RDX 6+7/A and B shown on access, rights of
way and temporary stopping up plan drawing number
10-2574-GND-01-05-0062 (Sheet 2 of 25) the
creation of a temporary bellmouth access on each
side of the road, with sufficient size to accommodate
a low loader comprising a temporary alteration of the
kerb line and roadside verge on each side of the road.
90
(2)
Street subject to
alteration of layout
(3)
Description of alteration
East Riding of
Yorkshire Council
Bursea Lane, Holme
Upon Spalding MoorTemporary construction accessAt RDX 14/A and B shown on access, rights of way
and temporary stopping up plan drawing number
10-2574-GND-01-05-0068 (Sheet 8 of 25) the
creation of a temporary bellmouth access on each
side of the road, with sufficient size to accommodate
a low loader comprising a temporary alteration of the
roadside verge on each side of the road and the
temporary fluming the ditch on the north-eastern side
of the road (RDX 14/B).
East Riding of
Yorkshire Council
B1228 Wood Lane,
Brind
East Riding of
Yorkshire Council
Drain Lane, Holme
Upon Spalding MoorTemporary construction accessAt RDX 15/A and B shown on access, rights of way
and temporary stopping up plan drawing number
10-2574-GND-01-05-0068 (Sheet 8 of 25) the
creation of a temporary bellmouth access on each
side of the road, with sufficient size to accommodate
a low loader comprising a temporary alteration of the
roadside verge on each side of the road and the
temporary fluming the ditch on the north-eastern side
of the road (RDX 15/B).
Temporary construction accessAt RDX 12/A and B shown on access, rights of way
and temporary stopping up plan drawing number
10-2574-GND-01-05-0065 (Sheet 5 of 25) the
creation of a temporary bellmouth access on each
side of the road, with sufficient size to accommodate
a low loader comprising a temporary alteration of the
roadside verge on each side of the road and the
temporary fluming of the ditch on the western side of
the road (RDX 12/A).
(1)
Area
East Riding of
Yorkshire Council
Skiff Lane, Holme
Upon Spalding MoorTemporary construction accessAt RDX 16/A and B shown on access, rights of way
and temporary stopping up plan drawing number
10-2574-GND-01-05-0069 (Sheet 9 of 25) the
creation of a temporary bellmouth access on each
side of the road, with sufficient size to accommodate
a low loader comprising a temporary alteration of the
roadside verge on each side of the road.
roadside verge and the temporary fluming of the
ditch on each side of the road.
East Riding of
Yorkshire Council
East Riding of
Yorkshire Council
Lock Lane, Holme
Upon Spalding Moor Temporary construction accessAt RDX 17/A and B shown on access, rights of way
and temporary stopping up plan drawing number
10-2574-GND-01-05-0069 (Sheet 9 of 25) the
creation of a temporary bellmouth access on each
side of the road, with sufficient size to accommodate
a low loader comprising a temporary alteration of the
roadside verge on each side of the road and the
temporary fluming the ditch on the southern side of
A614 Holme Road,
SpaldingtonTemporary construction accessAt RDX 13/A and B shown on access, rights of way
and temporary stopping up plan drawing number
10-2574-GND-01-05-0067 (Sheet 7 of 25) the
creation of a temporary bellmouth access on each
side of the road, with sufficient size to accommodate
a low loader comprising a temporary alteration of the
roadside verge and the temporary fluming the ditch
on each side of the road.
91
(2)
Street subject to
alteration of layout
A1034 Sancton
Road, Market
Weighton
Temporary construction accessAt RDX 20/A and B shown on access, rights of way
and temporary stopping up plan drawing number
10-2574-GND-01-05-0072 (Sheet 12 of 25) the
creation of a temporary bellmouth access on each
side of the road, with sufficient size to accommodate
a low loader comprising a temporary alteration of the
roadside verge on each side of the road, and the
tarmac pavement on the north-eastern side of the
road (RDX 20/B).
East Riding of
Yorkshire Council
Sand Lane, North
Cliffe
East Riding of
Yorkshire Council
A1079 Arras Hill,
Market WeightonTemporary construction accessAt RDX 21/A and B shown on access, rights of way
and temporary stopping up plan drawing number
10-2574-GND-01-05-0072 (Sheet 12 of 25) the
creation of a temporary bellmouth access on each
side of the road, with sufficient size to accommodate
a low loader comprising a temporary alteration of the
kerb line and roadside verge on each side of the road.
Temporary construction accessAt RDX 18/A and B shown on access, rights of way
and temporary stopping up plan drawing number
10-2574-GND-01-05-0070 (Sheet 10 of 25) the
creation of a temporary bellmouth access on each
side of the road, with sufficient size to accommodate
a low loader comprising a temporary alteration of the
roadside verge on each side of the road.
(1)
Area
East Riding of
Yorkshire Council
Kiplingcotes Lane,
Market WeightonTemporary construction accessAt RDX 22/A and B shown on access, rights of way
and temporary stopping up plan drawing number
10-2574-GND-01-05-0073 (Sheet 13 of 25) the
creation of a temporary bellmouth access on each
side of the road, with sufficient size to accommodate
a low loader comprising a temporary alteration of the
roadside verge on each side of the road.
the road (RDX 17/A).
East Riding of
Yorkshire Council
East Riding of
Yorkshire Council
Kiplingcotes Road,
Etton Temporary construction accessAt RDX 23/A and B shown on access, rights of way
and temporary stopping up plan drawing number
10-2574-GND-01-05-0074 (Sheet 14 of 25) the
creation of a temporary bellmouth access on each
side of the road, with sufficient size to accommodate
a low loader comprising a temporary alteration of the
roadside verge on each side of the road.
Cliffe Road, Market
Weighton Temporary construction accessAt RDX 19/A and B shown on Access, Rights of
Way and Temporary Stopping Up Plan drawing
number 10-2574-GND-01-05-0071 (Sheet 11 of 25)
the creation of a temporary bellmouth access on each
side of the road, with sufficient size to accommodate
a low loader comprising a temporary alteration of the
roadside verge on each side of the road and the
temporary fluming the ditch on the eastern side of the
road (RDX 19/B).
East Riding of
Yorkshire Council
Kiplingcotes
Racecourse Road,
Etton
Temporary construction accessAt RDX 24/A and B shown on access, rights of way
and temporary stopping up plan drawing number
10-2574-GND-01-05-0074 (Sheet 14 of 25) the
creation of a temporary bellmouth access on each
(2)
Street subject to
alteration of layout
(3)
Description of alteration
92
East Riding of
Yorkshire Council
Lund Wold Road,
Lund Temporary construction accessAt RDX 27/A and B shown on access, rights of way
and temporary stopping up plan drawing number
10-2574-GND-01-05-0076 (Sheet 16 of 25) the
creation of a temporary bellmouth access on each
side of the road, with sufficient size to accommodate
a low loader comprising a temporary alteration of the
roadside verge on each side of the road.
East Riding of
Yorkshire Council
Park Road, South
Dalton
East Riding of
Yorkshire Council
Middleton Road,
Lund Temporary construction accessAt RDX 28/A and B shown on access, rights of way
and temporary stopping up plan drawing number
10-2574-GND-01-05-0076 (Sheet 16 of 25) the
creation of a temporary bellmouth access on each
side of the road, with sufficient size to accommodate
a low loader comprising a temporary alteration of the
roadside verge on each side of the road.
Temporary construction accessAt RDX 25/A and B shown on access, rights of way
and temporary stopping up plan drawing number
10-2574-GND-01-05-0074 (Sheet 14 of 25) the
creation of a temporary bellmouth access on each
side of the road, with sufficient size to accommodate
a low loader comprising a temporary alteration of the
roadside verge on each side of the road.
(1)
Area
East Riding of
Yorkshire Council
B1248 Lund Road,
Middleton on the
Wolds
Temporary construction accessAt RDX 29/A and B shown on access, rights of way
and temporary stopping up plan drawing number
10-2574-GND-01-05-0076 (Sheet 16 of 25) the
creation of a temporary bellmouth access on each
side of the road, with sufficient size to accommodate
a low loader comprising a temporary alteration of the
roadside verge on each side of the road.
side of the road, with sufficient size to accommodate
a low loader comprising a temporary alteration of the
roadside verge on each side of the road.
East Riding of
Yorkshire Council
East Riding of
Yorkshire Council
Middleton Road,
KilnwickTemporary construction accessAt RDX 30/A and B shown on access, rights of way
and temporary stopping up plan drawing number
10-2574-GND-01-05-0077 (Sheet 17 of 25) the
creation of a temporary bellmouth access on each
side of the road, with sufficient size to accommodate
a low loader comprising a temporary alteration of the
roadside verge on each side of the road.
Holme Wold Road,
Holme on the WoldsTemporary construction accessAt RDX 26/A and B shown on access, rights of way
and temporary stopping up plan drawing number
10-2574-GND-01-05-0075 (Sheet 15 of 25) the
creation of a temporary bellmouth access on each
side of the road, with sufficient size to accommodate
a low loader comprising a temporary alteration of the
roadside verge on each side of the road.
East Riding of
Yorkshire Council
Unnamed Road from
Bracken Lane to
Burnbutts Lane,
Watton
Temporary construction accessAt RDX 31/A and B shown on access, rights of way
and temporary stopping up plan drawing number
10-2574-GND-01-05-0077 (Sheet 17 of 25) the
creation of a temporary bellmouth access on each
side of the road, with sufficient size to accommodate
a low loader comprising a temporary alteration of the
(2)
Street subject to
alteration of layout
(3)
Description of alteration
93
East Riding of
Yorkshire Council
A164 Beverley
Road, Hutton
Cranswick
Temporary construction accessAt RDX 34/A and B shown on access, rights of way
and temporary stopping up plan drawing number
10-2574-GND-01-05-0079 (Sheet 19 of 25) the
creation of a temporary bellmouth access on each
side of the road, with sufficient size to accommodate
a low loader comprising a temporary alteration of the
kerb line and roadside verge and the temporary
fluming of the ditch on each side of the road.
East Riding of
Yorkshire Council
Burnbutts Lane,
Hutton Cranswick
East Riding of
Yorkshire Council
Jenkinson Lane,
Hutton Temporary construction accessAt RDX 35/A and B shown on access, rights of way
and temporary stopping up plan drawing number
10-2574-GND-01-05-0079 (Sheet 19 of 25) the
creation of a temporary bellmouth access on each
side of the road, with sufficient size to accommodate
a low loader comprising a temporary alteration of the
roadside verge on each side of the road and the
temporary fluming of the ditch on the southern side
of the road (RDX 35/A).
Temporary construction accessAt RDX 32/A and B shown on access, rights of way
and temporary stopping up plan drawing number
10-2574-GND-01-05-0077 (Sheet 17 of 25) the
creation of a temporary bellmouth access on each
side of the road, with sufficient size to accommodate
a low loader comprising a temporary alteration of the
roadside verge on each side of the road.
(1)
Area
East Riding of
Yorkshire Council
Ricklepits, Skerne Temporary construction accessAt RDX 36/A and B shown on access, rights of way
and temporary stopping up plan drawing number
10-2574-GND-01-05-0079 (Sheet 19 of 25) the
creation of a temporary bellmouth access on each
side of the road, with sufficient size to accommodate
a low loader comprising a temporary alteration of the
roadside verge on each side of the road and the
temporary fluming of the ditch on the western side of
the road (RDX 36/A).
roadside verge on each side of the road.
East Riding of
Yorkshire Council
East Riding of
Yorkshire Council
Road to Skerne
(Main Street),
Wansford
Temporary construction accessAt RDX 37/B shown on access, rights of way and
temporary stopping up plan drawing number
10-2574-GND-01-05-0081 (Sheet 21 of 25) the
creation of a temporary bellmouth access on the
south-eastern side of the road between the canal
bridge and River Hull, with sufficient size to
accommodate a low loader comprising a temporary
alteration of the roadside verge, fencing and gate.
Southburn Road,
Hutton Cranswick Temporary construction accessAt RDX 33/A and B shown on access, rights of way
and temporary stopping up plan drawing number
10-2574-GND-01-05-0079 (Sheet 19 of 25) the
creation of a temporary bellmouth access on each
side of the road, with sufficient size to accommodate
a low loader comprising a temporary alteration of the
roadside verge and the temporary fluming of the
ditch on each side of the road.
East Riding of
Yorkshire Council
B1249 Frodingham
Road, Wansford Temporary construction accessAt RDX 37/A shown on access, rights of way and
(2)
Street subject to
alteration of layout
(3)
Description of alteration
94
East Riding of
Yorkshire Council
Main Street, Great
Kelk Temporary construction accessAt RDX 38/A and B shown on access, rights of way
and temporary stopping up plan drawing number
10-2574-GND-01-05-0082 (Sheet 22 of 25) the
creation of a temporary bellmouth access on each
side of the road, with sufficient size to accommodate
a low loader comprising a temporary alteration of the
roadside verge on each side of the road.
temporary stopping up plan drawing number
10-2574-GND-01-05-0081 (Sheet 21 of 25) the
creation of a temporary bellmouth access on the
north-eastern side of the road, with sufficient size to
accommodate a low loader comprising a temporary
alteration of the roadside verge and the temporary
fluming of the ditch on the north-eastern side of the
road.
(1)
Area
East Riding of
Yorkshire Council
Gransmoor Road,
GransmoorTemporary construction accessAt RDX 39/A and B shown on access, rights of way
and temporary stopping up plan drawing number
10-2574-GND-01-05-0083 (Sheet 23 of 25) the
creation of a temporary bellmouth access on each
side of the road, with sufficient size to accommodate
a low loader comprising a temporary alteration of the
roadside verge on each side of the road.
(2)
Street subject to
alteration of layout
East Riding of
Yorkshire Council
East Riding of
Yorkshire Council
A165 Bridlington
Road, Barmston Temporary construction accessAt RDX 40/A and B shown on access, rights of way
and temporary stopping up plan drawing number
10-2574-GND-01-05-0085 (Sheet 25 of 25) the
creation of a temporary bellmouth access on each
side of the road, with sufficient size to accommodate
a low loader comprising a temporary alteration of the
roadside verge on each side of the road.
B1249 Frodingham
Road, Wansford Temporary construction accessAt RDX 37/C shown on access, rights of way and
temporary stopping up plan drawing number
10-2574-GND-01-05-0081 (Sheet 21 of 25) the
temporary widening of an existing bellmouth access
on the south-western side of the road, with sufficient
size to accommodate a low loader comprising a
temporary alteration of the roadside verge on the
western side of the road.
East Riding of
Yorkshire Council
A614, Driffield Access to Driffield Construction Compound,
Former Alamein Barracks, opposite Mallard
House
The creation of a temporary access onto the A614
comprised in Work No. 12 (works plans drawing
number 10-2574-GND-01-05-0049; inset on sheet
19 of 25) and as shown on access, rights of way and
temporary stopping up plan drawing number
10-2574-GND-01-05-0079 (inset on Sheet 19 of
25), namely increase in width of existing bellmouth
access on the northern side of the road with sufficient
size to accommodate a maximum legal length
articulated vehicle (16.5m length) comprising a
temporary alteration of the pavement, roadside verge,
kerb line and carriageway on the northern side of the
(3)
Description of alteration
95
East Riding of
Yorkshire Council
road as depicted in drawing
no.10-2574-PLN-01-1053 and
10-2574-PLN-01-1061. Provision of new gate.
(2)
Street subject to
alteration of layout
(3)
Description of alteration
96
(1)
Area
(3)
Description of alteration
North Yorkshire County
Council
Wade House Lane/
A645, DraxAccess to Camblesforth Multi-junction
Alteration of the existing junction between
Wade House Lane (South) and the A645 to
accommodate the creation of a permanent access
onto the A645 from Wade House Lane
comprised in Work No. 4C on Works Plans
(drawing number 10-2574-GND-01-05-0032;
sheet 2 of 25) and RDX6+7/C as depicted on the
access, rights of way and temporary stopping up
plans (drawing number
10-2574-GND-01-05-0062; sheet 2 of 25),
namely the upgrading of an existing bellmouth
access on the southern side of the A645, with
sufficient size to accommodate junction radii to
enable turning movements of a large articulated
vehicle (15.4m length) comprising an increase to
the width and alteration of the alignment of
existing adopted road junction, alteration of the
splay, kerb line, carriageway and adjoining
road-side verge and embankment on the southern
side of the A645 and upgrading of Wade House
Lane road surface as depicted in drawing no.
10-2574-PLN-01-1045 and
10-2574-PLN-01-1055 cutting back of
vegetation in highway verge to enable visibility
splay.
PART 2
STREETS SUBJECT TO PERMANENT ALTERATION OF LAYOUT
(1)
Area
East Riding of Yorkshire
Council
Skiff Lane, Holme Upon
Spalding MoorAccess to Tollingham Block Valve
North Yorkshire County
Council
Wade House Lane,
DraxAccess to Camblesforth Multi-junction
The creation of a permanent access onto Wade
House Lane comprised in Work No. 4C on
Works Plans (drawing number
10-2574-GND-01-05-0032; sheet 2 of 25) and
RDX6+7/C as depicted on the access, rights of
way and temporary stopping up plans (drawing
number 10-2574-GND-01-05-0062; sheet 2 of
25), namely the creation of a permanent
bellmouth access on the eastern side of the road,
with sufficient size to accommodate junction
radii to enable turning movements of a large
articulated vehicle (15.4m length) comprising an
alteration of the existing adopted carriageway
and adjoining roadside verge and kerb line on
the eastern side of the road to create a junction
with a new access road as depicted in drawing
no. 10-2574-PLN-01-1045 and
10-2574-PLN-01-1055.
97
(2)
Street subject to
alteration of layout
East Riding of Yorkshire
Council
Lund Wold Road, Lund Access to Dalton Block Valve
The creation of a permanent access onto Lund
Wold Road for comprised in Work No. 9C on
Works Plans (drawing number
10-2574-GND-01-05-0045; sheet 15 of 25) and
RDX27/C as depicted on the access, rights of
way and temporary stopping up plans (drawing
number 10-2574-GND-01-05-0075; sheet 15 of
25), namely the creation of a new permanent
bellmouth access on the southern side of the road
comprising an alteration of the existing adopted
carriageway and adjoining hedgeline and
roadside verge to accommodate a junction with a
new access road with sufficient size to
accommodate junction radii to enable turning
movements of a large articulated vehicle (15.4m
length), in and out of Lund Wold Road, as
depicted in drawing no. 10-2574-PLN-01-1047
and 10-2574-PLN-01-1057.
(3)
Description of alteration
East Riding of Yorkshire
Council
Main Street, Skerne Access to Skerne Block Valve
Modification of existing junction of Church
Farm access road with Main Street, Skerne to
accommodate permanent access comprised in
Work No. 11C on Works Plans (drawing
number 10-2574-GND-01-05-0050; sheet 20 of
25) and RDX36/C as depicted on the access,
rights of way and temporary stopping up plans
(drawing number 10-2574-GND-01-05-0080;
sheet 20 of 25), namely the upgrading of an
existing bellmouth access on the southern side of
Main Street Skerne with sufficient size to
accommodate junction radii to enable turning
movements of a large articulated vehicle (15.4m
length) comprising an increase to the width and
alteration of the alignment of existing adopted
road junction, an alteration of the splay,
The creation of a permanent access onto Skiff
Lane comprised in Work No. 6C on Works
Plans (drawing number
10-2574-GND-01-05-0039; sheet 9 of 25) and
RDX16/C as depicted on the access, rights of
way and temporary stopping up plans (drawing
number 10-2574-GND-01-05-0069; sheet 9 of
25), namely the creation of a new permanent
bellmouth access on the southern side of the road
comprising an alteration of the existing adopted
carriageway and adjoining hedgeline and verge
to accommodate a junction with a new access
road with sufficient size to accommodate
junction radii to enable turning movements of a
large articulated vehicle (15.4m length), in and
out of Skiff Lane as depicted in drawing no.
10-2574-PLN-01-1046 and
10-2574-PLN-01-1056.
(1)
Area
98
(2)
Street subject to
alteration of layout
(3)
Description of alteration
East Riding of Yorkshire
Council
Sands Road, Barmston Access to Barmston Pumping Station.
Permanent access from A165 Bridlington
Road/Sands Road, Barmston comprising—
the creation of two permanent accesses (a)
onto Sands Road (track), comprising
new permanent bellmouth accesses as
depicted in drawing no.
10-2574-PLN-01-1049, and an
increase to the width of the existing
adopted track with sufficient size to
accommodate junction radii to enable
turning movements of a large
articulated vehicle (15.4m length) as
depicted in drawing no.
10-2574-PLN-01-1059; and alteration
of the carriageway/ upgrading of the
road surface for approximately 100m.
modification of existing junction where (b)
Sands Road (track) meets the tarmac
road, an increase to the width of the
carriageway and alteration of the
adjoining roadside verge on the eastern
side of the existing bend. Provision of
new gate. As depicted in drawing
no.10-2574-PLN-01-1050.
an increase to the width of the (c)
carriageway and alteration of the
adjoining roadside verge for 630m
between the junction with Sands Road
(track) and A165. As depicted in
drawing no.10-2574-PLN-01-1051;
all comprised in Work No. 14C on Works Plans
(drawing number 10-2574-GND-01-05-0055;
sheet 25 of 25) and RDX40/C as depicted on the
access, rights of way and temporary stopping up
plans (drawing number
10-2574-GND-01-05-0085; sheet 25 of 25)
(1)
Area
hedgeline and roadside verge, kerb line and
carriageway as depicted in drawing no.
10-2574-PLN-01-1048 and
10-2574-PLN-01-1058
99
(2)
Street subject to
alteration of layout
East Riding of
Yorkshire Council
Kiplingcotes Racecourse Road,
Etton
Between point ST7 and ST8 as depicted
on the access, rights of way and temporary
stopping up plans (drawing number
10-2574-GND-01-05-0074; sheet 14 of
25)
Between point ST1 and ST2 as depicted
on the access, rights of way and temporary
stopping up plans (drawing number
10-2574-GND-01-05-0061; sheet 1 of 25)
(2)
Street subject to temporary
stopping up
East Riding of
Yorkshire Council
Park Road, South Dalton Between point ST9 and ST10 as depicted
on the access, rights of way and temporary
stopping up plans (drawing number
10-2574-GND-01-05-0074; sheet 14 of
25)
(3)
Extent of temporary stopping up
North Yorkshire
County Council
Selby District
Council
East Riding of
Yorkshire Council
Holme Wold Road, Holme on the
Wolds
Between point ST11 and ST12 as depicted
on the access, rights of way and temporary
stopping up plans (drawing number
10-2574-GND-01-05-0075; sheet 15 of
25)
Brickhill Lane, Drax Between point ST3 and ST4 as depicted
on the access, rights of way and temporary
stopping up plans (drawing number
10-2574-GND-01-05-0062; sheet 2 of 25)
East Riding of
Yorkshire Council
Unnamed Road from Bracken Lane
to Burnbutts Lane, Watton
Between point ST13 and ST14 as depicted
on the access, rights of way and temporary
stopping up plans (drawing number
10-2574-GND-01-05-0077; sheet 17 of
25)
SCHEDULE 6 Article 14
STREETS AND PUBLIC RIGHTS OF WAY TO BE TEMPORARILY
STOPPED UP
PART 1
STREETS
(1)
Area
East Riding of
Yorkshire Council
Burnbutts Lane, Hutton Cranswick Between point ST15 and ST16 as depicted
on the access, rights of way and temporary
stopping up plans (drawing number
10-2574-GND-01-05-0077; sheet 17 of
25)
East Riding of
Yorkshire Council
Kiplingcotes Lane, Market
Weighton
East Riding of
Yorkshire Council
Sands Road, Barmston Between point ST17 and ST18 as depicted
on the access, rights of way and temporary
stopping up plans (drawing number
10-2574-GND-01-05-0085; sheet 25 of
25)
Between point ST5 and ST6 as depicted
on the access, rights of way and temporary
stopping up plans (drawing number
10-2574-GND-01-05-0073; sheet 13 of
25)
North Yorkshire
County Council
Selby District
Council
100
Pear Tree Avenue, Long Drax
Between point FP5 and FP6, as
depicted on the access, rights of
way and temporary stopping up
plans (drawing number
10-2574-GND-01-05-0061;
sheet 1 of 25)
North Yorkshire County Council,
Selby District Council
Long Drax Footpath no.
35.47/6/1 (as diverted), running
along outside of western and
southern boundaries of Drax
Priory Scheduled Ancient
Monument, at Drax Abbey Farm
North Yorkshire County Council,
Selby District Council
Drax Footpath No. 35.26/7/1,
running east from Drax Main
Road along track at southern
edge of Read School Playing
Field and thence east and then
north-east through agricultural
land
Between point FP7 and FP8, and
between point FP8A and FP8B
as depicted on the access, rights
of way and temporary stopping
up plans (drawing number
10-2574-GND-01-05-0062;
sheet 2 of 25)
Between point FP1 and FP2, as
depicted on the access, rights of
way and temporary stopping up
plans (drawing number
10-2574-GND-01-05-0061;
sheet 1 of 25)
(2)
Footpath to be temporarily
stopped up
North Yorkshire County Council,
Selby District Council
Drax Footpath No. 35.26/13/2,
running through agricultural land
east of Read School Playing
Field, and north-west of Scurff
Hall
Between point FP8B and FP9, as
depicted on the access, rights of
way and temporary stopping up
plans (drawing number
10-2574-GND-01-05-0062;
sheet 2 of 25
(3)
Extent of temporary stopping up
North Yorkshire County Council,
Selby District Council
North Yorkshire County Council,
Selby District Council
Drax Footpath 35.26/13/1,
running through agricultural land
north-west of Scurff Hall
Between point FP8B and FP10,
as depicted on the access, rights
of way and temporary stopping
up plans (drawing number
10-2574-GND-01-05-0062;
sheet 2 of 25)
Long Drax Footpath No.
35.47/1/1 (as diverted), running
along southern side of Pear Tree
Avenue, around perimeter of
adjacent agricultural field
Between point FP3 and FP4, as
depicted on the access, rights of
way and temporary stopping up
plans (drawing number
10-2574-GND-01-05-0061;
sheet 1 of 25)
North Yorkshire County Council,
Selby District Council
Newland Footpath No. 35.49/1/2,
running through agricultural land
north-west of Scurff Hall
Between point FP10 and FP11,
as depicted on the access, rights
of way and temporary stopping
up plans (drawing number
10-2574-GND-01-05-0062;
PART 2
RIGHTS OF WAY
(1)
Area
North Yorkshire County Council,
Selby District Council
101
Long Drax Footpath No.
35.47/8/1, running south-west
from Pear Tree Avenue, across
agricultural land
North Yorkshire County Council,
Selby District Council
Newland Footpath No. 35.49/2/2,
running through agricultural land
north of Scurff Hall
North Yorkshire County Council,
Selby District Council
Drax Footpath No. 35.26/9/1,
known as Brickhill Lane
Between point FP16 and FP17,
as depicted on the access, rights
of way and temporary stopping
up plans (drawing number
10-2574-GND-01-05-0062;
sheet 2 of 25)
Between point FP12 and FP13,
as depicted on the access, rights
of way and temporary stopping
up plans (drawing number
10-2574-GND-01-05-0062 and
0063; sheet 2 and 3 of 25)
(1)
Area
East Riding of Yorkshire Council Asselby Footpath No. 2, known
as Marsh Lane (Track), running
through agricultural land
Between point FP18 and FP19,
as depicted on the access, rights
of way and temporary stopping
up plans (drawing number
10-2574-GND-01-05-0064;
sheet 4 of 25)
sheet 2 of 25)
North Yorkshire County Council,
Selby District Council
East Riding of Yorkshire Council Asselby Footpath No. 1, running
north from Asselby village,
across agricultural land
Between point FP20 and FP21,
as depicted on the access, rights
of way and temporary stopping
up plans (drawing number
10-2574-GND-01-05-0064;
sheet 4 of 25)
Newland Footpath No. 35.49/3/1,
running through agricultural land
to north-west of Scurff Hall
Between point FP13 and FP14,
as depicted on the access, rights
of way and temporary stopping
up plans (drawing number
10-2574-GND-01-05-0063;
sheet 3 of 25)
East Riding of Yorkshire Council Wressle Footpath No. 10,
running across agricultural land
north of Newsholme Parks
Between point FP22 and FP23,
as depicted on the access, rights
of way and temporary stopping
up plans (drawing number
10-2574-GND-01-05-0064;
sheet 4 of 25)
(2)
Footpath to be temporarily
stopped up
(3)
Extent of temporary stopping up
East Riding of Yorkshire Council Wressle Footpath No. 6, running
across agricultural land north of
Newsholme Parks and south-west
of Brind
Between point FP24 and FP25,
as depicted on the access, rights
of way and temporary stopping
up plans (drawing number
10-2574-GND-01-05-0065;
North Yorkshire County Council,
Selby District Council
Newland Footpath No. 35.49/2/1,
running through agricultural land
north of Scurff Hall
102
Between point FP13 and FP15,
as depicted on the access, rights
of way and temporary stopping
up plans (drawing number
10-2574-GND-01-05-0063;
sheet 3 of 25)
East Riding of Yorkshire Council Wressle Footpath No. 8, running
across agricultural land north of
Newsholme Parks and south-west
of Brind
East Riding of Yorkshire Council Market Weighton Footpath No.
11, running across agricultural
land at Crossfields Farm
Between point FP34 and FP35,
as depicted on the access, rights
of way and temporary stopping
up plans (drawing number
10-2574-GND-01-05-0071;
sheet 11 of 25)
Between point FP26 and FP27,
as depicted on the access, rights
of way and temporary stopping
up plans (drawing number
10-2574-GND-01-05-0065;
sheet 5 of 25)
(1)
Area
East Riding of Yorkshire Council Goodmanham Footpath No. 6,
running east from Rifle Butts
quarry, across agricultural land
Between point FP36 and FP37,
as depicted on the access, rights
of way and temporary stopping
up plans (drawing number
10-2574-GND-01-05-0072;
sheet 12 of 25)
sheets 5 of 25)
East Riding of Yorkshire Council
East Riding of Yorkshire Council Lund Footpath No. 2, running
south from Lund Wold Road,
along the edge of an agricultural
field, to Bulmers Triangle
plantation
Between point FP38 and FP39,
as depicted on the access, rights
of way and temporary stopping
up plans (drawing number
10-2574-GND-01-05-0075;
sheet 15 of 25)
Eastrington Bridleway No. 17,
known as Featherbed Lane
(Track). This is crossed twice,
toward the Lane’s western and
eastern ends
Between point FP28 and FP29,
and from FP30 to FP31, as
depicted on the access, rights of
way and temporary stopping up
plans (drawing number
10-2574-GND-01-05-0066;
sheet 6 of 25)
East Riding of Yorkshire Council Watton Footpath No. 2, running
across agricultural land north of
Bracken village
Between point FP40 and FP41,
as depicted on the access, rights
of way and temporary stopping
up plans (drawing number
10-2574-GND-01-05-0077;
sheet 17 of 25)
(2)
Footpath to be temporarily
stopped up
(3)
Extent of temporary stopping up
East Riding of Yorkshire Council Watton Footpath No. 20,
following track running north
from Bracken village through
agricultural land
Between point FP42 and FP43,
as depicted on the access, rights
of way and temporary stopping
up plans (drawing number
East Riding of Yorkshire Council Spaldington Footpath No. 12,
along a track running south-east
from the A614 to Featherbed
Drain, across agricultural land
south of Sikes Farm
103
Between point FP32 and FP33,
as depicted on the access, rights
of way and temporary stopping
up plans (drawing number
10-2574-GND-01-05-0067;
sheet 7 of 25)
East Riding of Yorkshire Council Hutton Cranswick Footpath No.
12, running north of and adjacent
to Bustard Nest Farm, across
agricultural land
East Riding of Yorkshire Council Skerne and Wansford Bridleway
No. 7, running along a track from
Church Farm to Cleaves Farm,
through agricultural land
south-east of Skerne village
Between point FP50 and FP51,
as depicted on the access, rights
of way and temporary stopping
up plans (drawing number
10-2574-GND-01-05-0080’
sheet 20 of 25)
Between point FP44 and FP45,
as depicted on the access, rights
of way and temporary stopping
up plans (drawing number
10-2574-GND-01-05-0078;
sheet 18 of 25)
(1)
Area
East Riding of Yorkshire Council Skerne and Wansford Bridleway
No. 8, running along a track
south-west of Copper Hall,
through agricultural land
south-east of Skerne village
Between point FP52 and FP53,
as depicted on the access, rights
of way and temporary stopping
up plans (drawing number
10-2574-GND-01-05-0080;
sheet 20 of 25)
10-2574-GND-01-05-0077;
sheet 17 of 25)
East Riding of Yorkshire Council
East Riding of Yorkshire Council Foston on the Wolds Footpath
No. 11, running through
agricultural land from Great Kelk
south to Gembling
Between point FP54 and FP55,
as depicted on the access, rights
of way and temporary stopping
up plans (drawing number
10-2574-GND-01-05-0082;
sheet 22 of 25)
Hutton Cranswick Footpath No.
11, running north of Bustard Nest
Farm, across agricultural land
Between point FP46 and FP47,
as depicted on the access, rights
of way and temporary stopping
up plans (drawing number
10-2574-GND-01-05-0078;
sheet 18 of 25)
East Riding of Yorkshire Council Barmston Footpath No. 2,
running across agricultural land
from Bridlington Road at
Stonehills to its junction with
Barmston Footpath No. 3, west
of Hamilton Hill
Between point FP56 and FP57,
as depicted on the access, rights
of way and temporary stopping
up plans (drawing number
10-2574-GND-01-05-0084;
sheet 24 of 25)
(2)
Footpath to be temporarily
stopped up
(3)
Extent of temporary stopping up
East Riding of Yorkshire Council Barmston Footpath No. 3,
running north from Barmston
village, to west of Hamilton Hill,
through agricultural land
Between point FP58 and FP59,
as depicted on the access, rights
of way and temporary stopping
up plans (drawing number
East Riding of Yorkshire Council Hutton Cranswick Footpath No.
18, running across agricultural
land north of Hutton village
104
Between point FP48 and FP49,
as depicted on the access, rights
of way and temporary stopping
up plans (drawing number
10-2574-GND-01-05-0079;
sheet 19 of 25)
(3)
Extent of temporary stopping up
East Riding of Yorkshire Council Barmston Footpath No. 4,
running north from Barmston
village, to east of Hamilton Hill,
through agricultural land
Between point FP60 and FP61,
as depicted on the access, rights
of way and temporary stopping
up plans (drawing number
10-2574-GND-01-05-0085;
sheet 25 of 25)
(1)
Area
10-2574-GND-01-05-0085;
sheet 25 of 25)
105
(2)
Footpath to be temporarily
stopped up
http://www.lexisnexis.com/uk/legal/delivery/PrintDoc.do?jobHandle=2826%3A2917... 20/06/2011
Temporary access from any point within the order limits on Brickhill
Lane, RDX5/A and RDX5/B as indicatively shown on the access,
rights of way and temporary stopping up plans (drawing number
10-2574-GND-01-05-0062; sheet 2 of 25)
North Yorkshire County Council,
Selby District Council
North Yorkshire County Council,
Selby District Council
North Yorkshire County Council,
Selby District Council
Temporary access from any point within the order limits on the A645,
RDX6&7/A and RDX6&7/B as indicatively shown on the access,
rights of way and temporary stopping up plans (drawing number
10-2574-GND-01-05-0062; sheet 2 of 25)
Temporary access from any point within the order limits on Carr Lane,
RDX2/A and RDX2/B as indicatively shown on the access, rights of
way and temporary stopping up plans (drawing number
10-2574-GND-01-05-0061; sheet 1 of 25)
Temporary access from any point within the order limits on New
Road, RDX0/A as indicatively shown on the access, rights of way and
temporary stopping up plans (drawing number
10-2574-GND-01-05-0061; sheet 1 of 25)
North Yorkshire County Council,
Selby District Council
Temporary access from any point within the order limits on Church
Dike Lane, RDX8/A and RDX8/B as indicatively shown on the
access, rights of way and temporary stopping up plans (drawing
number 10-2574-GND-01-05-0062; sheet 2 of 25)
(2)
Access details
North Yorkshire County Council,
Selby District Council
East Riding of Yorkshire Council Temporary access from any point within the order limits on Barmby
Road, Asselby, RDX9/A and RDX9/B as indicatively shown on the
access, rights of way and temporary stopping up plans (drawing
number 10-2574-GND-01-05-0063; sheet 3 of 25)
Temporary access from any point within the order limits on Main
Road, RDX3/A and RDX3/B as indicatively shown on the access,
rights of way and temporary stopping up plans drawing number
10-2574-GND-01-05-0061; sheet 1 of 25)
Supplemental Powers SCHEDULE 7 Article 16
ACCESS TO WORKS
PART 1
TEMPORARY ACCESS
East Riding of Yorkshire Council Temporary access from any point within the order limits on Barmby
Road, Asselby, RDX9/C as indicatively shown on the access, rights of
way and temporary stopping up plans (drawing number
10-2574-GND-01-05-0063; sheet 3 of 25)
North Yorkshire County Council,
Selby District Council
North Yorkshire County Council,
Selby District Council
East Riding of Yorkshire Council Temporary access from any point within the order limits on A63 Hull
Road, RDX10/A and RDX10/B as indicatively shown on the access,
tights of way and temporary stopping up plans (drawing number
Temporary access from any point within the order limits on Church
Dike Lane, RDX4/A and RDX4/B as indicatively shown on the
access, rights of way and temporary stopping up plans (drawing
number 10-2574-GND-01-05-0062; sheet 2 of 25)
Temporary access from any point within the order limits on Pear Tree
Avenue, (RDX1/A and RDX1/B indicatively shown on the access,
rights of way and temporary stopping up plans (drawing number
10-2574-GND-01-05-0061; sheet 1 of 25)
(1)
Area
106
North Yorkshire County Council,
Selby District Council
Temporary access from any point within the order limits on the A614
Holme Road, RDX13/A and RDX13/B as indicatively shown on the
access, rights of way and temporary stopping up plans (drawing
number 10-2574-GND-01-05-0067; sheet 7 of 25)
Temporary access from any point within the order limits on Brind
Lane, Brind, RDX11/A and RDX11/B as indicatively shown on the
access, rights of way and temporary stopping up plans (drawing
number 10-2574-GND-01-05-0065; sheet 5 of 25)
East Riding of Yorkshire Council Temporary access from any point within the order limits on Lock
Lane, RDX17/A and RDX17/B as indicatively shown on the access,
rights of way and temporary stopping up plans (drawing number
10-2574-GND-01-05-0069; sheet 9 of 25)
10-2574-GND-01-05-0064; sheet 4 of 25)
East Riding of Yorkshire Council
East Riding of Yorkshire Council Temporary access from any point within the order limits on Sand
Lane, RDX18/A and RDX18/B as indicatively shown on the access,
rights of way and temporary stopping up plans (drawing number
10-2574-GND-01-05-0070; sheet 10 of 25)
Temporary access from any point within the order limits on Bursea
Lane, RDX14/A and RDX14/B as indicatively shown on the access,
rights of way and temporary stopping up plans (drawing number
10-2574-GND-01-05-0068; sheet 8 of 25)
(2)
Access details
East Riding of Yorkshire Council Temporary access from any point within the order limits on Cliffe
Road, RDX19/A and RDX19/B as indicatively shown on the access,
rights of way and temporary stopping up plans (drawing number
10-2574-GND-01-05-0071; sheet 11 of 25)
East Riding of Yorkshire Council
East Riding of Yorkshire Council
East Riding of Yorkshire Council Temporary access from any point within the order limits on the
A1034, Sancton Road, Market Weighton, RDX20/A and RDX20/B
as indicatively shown on the access, rights of way and temporary
stopping up plans (drawing number 10-2574-GND-01-05-0072; sheet
12 of 25)
Temporary access from any point within the order limits on Drain
Lane, RDX15/A and RDX15/B as indicatively shown on the access,
rights of way and temporary stopping up plans (drawing number
10-2574-GND-01-05-0068; sheet 8 of 25)
Temporary access from any point within the order limits on Wood
Lane, Brind, RDX12/A and RDX12/B as indicatively shown on the
access, rights of way and temporary stopping up plans (drawing
number 10-2574-GND-01-05-0065; sheet 5 of 25)
East Riding of Yorkshire Council Temporary access from any point within the order limits on the A1079
Arras Hill, Market Weighton, RDX21/A and RDX21/B as
indicatively shown on the access, tights of way and temporary
stopping up plans (drawing number 10-2574-GND-01-05-0072; sheet
12 of 25)
(1)
Area
East Riding of Yorkshire Council
East Riding of Yorkshire Council Temporary access from any point within the order limits on
Kiplingcoates Lane, Market Weighton, RDX22/A and RDX22/B as
indicatively shown on the access, rights of way and temporary
stopping up plans (drawing number 10-2574-GND-01-05-0073; sheet
13 of 25)
Temporary access from any point within the order limits on Skiff
Lane, RDX16/A and RDX16/B as indicatively shown on the access,
rights of way and temporary stopping up plans (drawing number
10-2574-GND-01-05-0069; sheet 9 of 25)
East Riding of Yorkshire Council
East Riding of Yorkshire Council Temporary access from any point within the order limits on
Kiplingcoates Road, Market Weighton, RDX23/A and RDX23/B as
indicatively shown on the access, rights of way and temporary
stopping up plans (drawing number 10-2574-GND-01-05-0074; sheet
East Riding of Yorkshire Council
East Riding of Yorkshire Council
107
Temporary access from Skiff Lane, RDX16/D as depicted on the
access, rights of way and temporary stopping up plans (drawing
number 10-2574-GND-01-05-0069; sheet 9 of 25)
Temporary access from any point within the order limits on Holme
Wold Road, South Dalton, RDX26/A and RDX26/B as indicatively
shown on access, rights of way and temporary stopping up plans
(drawing number 10-2574-GND-01-05-0075; sheet 15 of 25)
Temporary access from any point within the order limits on
Kiplingcoates Racecourse Road, Etton, RDX24/A and RDX24/B as
indicatively shown on the access, rights of way and temporary
stopping up plans; (drawing number 10-2574-GND-01-05-0074;
sheet 14 of 25)
East Riding of Yorkshire Council Temporary access from any point within the order limits on Road
between Bracken Lane and Burnbutts Lane, Watton, RDX31/A and
RDX31/B as indicatively shown on the access, rights of way and
temporary stopping up plans (drawing number
10-2574-GND-01-05-0077; sheet 17 of 25)
14 of 25)
East Riding of Yorkshire Council
East Riding of Yorkshire Council Temporary access from any point within the order limits on Burnbutts
Lane, Hutton Cranswick, RDX32/A and RDX32/B as indicatively
shown on the access, rights of way and Temporary Stopping Up Plan
drawing number 10-2574-GND-01-05-0077; sheet 17 of 25)
Temporary access from any point within the order limits on Lund
Wold Road, South Dalton, RDX27/A and RDX27/B as indicatively
shown on the access, rights of way and temporary stopping up plans
(drawing number 10-2574-GND-01-05-0076; sheet 16 of 25)
(2)
Access details
East Riding of Yorkshire Council Temporary access from any point within the order limits on Southburn
Road, Hutton Cranswick, RDX33/A and RDX33/B as indicatively
shown on the access, rights of way and temporary stopping up plans
(drawing number 10-2574-GND-01-05-0079; sheet 19 of 25)
East Riding of Yorkshire
Council
East Riding of Yorkshire Council
East Riding of Yorkshire Council Temporary access from any point within the order limits on the A164
Beverley Road, Hutton Cranswick, RDX34/A and RDX34/B as
indicatively shown on the access, rights of way and temporary
stopping up plans (drawing number 10-2574-GND-01-05-0079; sheet
19 of 25)
Temporary access from any point within the order limits on Middleton
Road, Lund, RDX28/A and RDX28/B as indicatively shown on the
access, tights of way and temporary stopping up plans (drawing
number 10-2574-GND-01-05-0076; sheet 16 of 25)
Temporary access from any point within the order limits on Park
Road, South Dalton, RDX25/A and RDX25/B as indicatively shown
on the access, rights of way and temporary stopping up plans (drawing
number 10-2574-GND-01-05-0074; sheet 14 of 25)
East Riding of Yorkshire Council Temporary access from any point within the order limits on Jenkinson
Lane, Hutton Cranswick, RDX35/A and RDX35/B as indicatively
shown on the access, rights of way and temporary stopping up plans
(drawing number 10-2574-GND-01-05-0079; sheet 19 of 25)
(1)
Area
East Riding of Yorkshire
Council
East Riding of Yorkshire Council Temporary access from any point within the order limits on Ricklepits,
Skerne, RDX36/A and RDX36/B as indicatively shown on the
access, rights of way and temporary stopping up plans (drawing
number 10-2574-GND-01-05-0079; sheet 19 of 25)
Temporary access from any point within the order limits on the
B1248, Lund Road, Middleton on the Wolds, RDX29/A and
RDX29/B as indicatively shown on the access, rights of way and
temporary stopping up plans (drawing number
10-2574-GND-01-05-0076; sheet 16 of 25)
East Riding of Yorkshire Council
East Riding of Yorkshire Council Temporary access from any point within the order limits on the B1249
, Frodingham Road RDX37/A as indicatively shown on the access,
East Riding of Yorkshire Council
East Riding of Yorkshire Council
108
Temporary access from any point within the order limits on Middleton
Road, Kilnwick, RDX30/A and RDX30/B as indicatively shown on
the access, rights of way and temporary stopping up plans (drawing
number 10-2574-GND-01-05-0077; sheet 17 of 25)
East Riding of Yorkshire Council
PART 2
PERMANENT ACCESS
Refer to access rights of way and temporary stopping up plan, drawing number
10-2574-GND-01-05-0061 to 0085
East Riding of Yorkshire Council
(1)
Area
(2)
Access details
Temporary access from any point within the order limits on Main
Street, Great Kelk RDX38/A and RDX38/B as indicatively shown on
the access, rights of way and temporary stopping up plans (drawing
number 10-2574-GND-01-05-0082; sheet 22 of 25)
Temporary access from Road to Skerne (Main Street), RDX37/B as
indicatively shown on access, rights of way and temporary stopping up
plans drawing number 10-2574-GND-01-05-0081; sheet 21 of 25)
North Yorkshire County Council,
Selby District Council
Permanent access from the A645 / Wade House Lane, RDX6&7/C as
depicted on the access, rights of way and temporary stopping up plans
(drawing number 10-2574-GND-01-05-0062; sheet 2 of 25)
rights of way and temporary stopping up plans (drawing number
10-2574-GND-01-05-0081; sheet 21 of 25)
East Riding of Yorkshire Council
East Riding of Yorkshire Council Permanent access from Skiff Lane, RDX16/C as depicted on the
access rights of way and temporary stopping up plans (drawing
number 10-2574-GND-01-05-0069; sheet 9 of 25)
Temporary access from any point within the order limits on
Gransmoor Road, Gransmoor, RDX39/A and RDX39/B as
indicatively shown on the access, rights of way and temporary
stopping up plans (drawing number 10-2574-GND-01-05-0083; sheet
23 of 25)
(2)
Access details
East Riding of Yorkshire Council Permanent access from Lund Wold Road, South Dalton, RDX27/C as
depicted on the access, rights of way and temporary stopping up plans
(drawing number 10-2574-GND-01-05-0075; sheet 15 of 25)
East Riding of Yorkshire Council
East Riding of Yorkshire Council
East Riding of Yorkshire Council Permanent access from Main Street, Skerne, RDX36/C as depicted
on the access, rights of way and temporary stopping up plans (drawing
number 10-2574-GND-01-05-0080; sheet 20 of 25)
Temporary access from any point within the order limits on the A165,
Bridlington Road, Barmston, RDX40/A and RDX40/B as indicatively
shown on the access, rights of way and temporary stopping up plans
(drawing number 10-2574-GND-01-05-0084; sheet 24 of 25)
Temporary access from B1249, Frodingham Road RDX37/C as
indicatively shown on access, rights of way and temporary stopping up
plans (drawing number 10-2574-GND-01-05-0081; sheet 21 of 25)
East Riding of Yorkshire Council Permanent access from A165 Bridlington Road / Sands Road,
Barmston RDX40/C as depicted on the access, rights of way and
temporary stopping up plans (drawing number
10-2574-GND-01-05-0085; sheet 25 of 25)
(1)
Area
East Riding of Yorkshire Council
109
Temporary access from the A614, Driffield as indicatively shown on
the access, rights of way and temporary stopping up plans (drawing
number 10-2574-GND-01-05-0079; sheet 19 of 25)
(1)
Plot
number
Plot 1102
Plot 1277 3397.66 square metres or thereabouts of land forming part of the beach known as
Barmston Sands, Barmston shown on sheet 25 of the land plans
1712.78 square metres or thereabouts of agricultural land situated to the West of the
River Hull at Wansford shown on sheets 20 and 21of the land plans
(2)
Description of plot
Plot 1280 23,649 square metres or thereabouts of land forming part of the beach known as
Barmston Sands, Barmston shown on sheet 25 of the land plans
SCHEDULE 8 Article 40
RECORD OF THE SATISFACTION OF THE SECRETARY OF STATE
PURSUANT TO SECTION 132 OF THE 2008 ACT
The Secretary of State in exercise of his powers under subsection 132(2) of the 2008 Act hereby records
that he is satisfied that subsections 132(3) and 132(4B) of that Act apply to the open space land
described in this Schedule (by reference to the corresponding plot numbers in the book of reference)
because either—
(a) that land, when burdened with the rights authorised to be compulsorily acquired under this Order,
will be no less advantageous than it was before to the persons in whom it is vested, other persons, if any,
entitled to rights of common or other rights, and the public; or
(b) that land forms part of an open space, none of it is of any of the other descriptions in subsection
132(1) and order rights are being acquired for a temporary (although possibly long-lived) purpose.
Plot 1106
110
1429.88 square metres or thereabouts of land forming part of the riverbed and banks of
the River Hull at Wansford shown on sheets 20 and 21of the land plans
Work No. 2A
Work No. 3A
Work No. 3B
Work No. 3C
Work No. 3D
Work No. 3E
Work No. 3F
Work No. 3G
Work No. 4C
Work No. 4D
Work No. 5A
Work No. 5B
Work No. 5C
(2)
Plot number of land shown
on land plans
(3)
Purpose for which
temporary possession may
be taken
North
Yorkshire
County
Council; Selby
District Council
Plot 4
Plot 76
Temporary construction
compounds, stores and
office areas for the
construction and carrying
out of the authorised
development
Work No. 2A
Work No. 4D
(4)
Relevant part of the
authorised
development
SCHEDULE 9 Article 28
LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKEN
North
Yorkshire
County
Council; Selby
District Council
Plot 7 Plot 73 Plot 135
Plot 9 Plot 74 Plot 137
Plot 16 Plot 77 Plot 139
Plot 19 Plot 81 Plot 142
Plot 20 Plot 82 Plot 146
Plot 25 Plot 97 Plot 147
Plot 26 Plot 99 Plot 156
Plot 27 Plot 103Plot 160
Plot 29 Plot 107Plot 162
Plot 36 Plot 110Plot 168
Plot 37 Plot 111Plot 169
Plot 40 Plot 112Plot 171
Construction and carrying
out of the drainage works
The drainage works
(which has the meaning
given in article 2
(interpretation)
(1)
Area
North
Yorkshire
County
Council; Selby
District Council
Plot 1 Plot 60 Plot 124
Plot 2 Plot 61 Plot 125
Plot 4 Plot 62 Plot 128
Plot 5 Plot 63 Plot 129
Plot 8 Plot 64 Plot 132
Plot 10 Plot 65 Plot 133
Plot 11 Plot 70 Plot 136
Plot 12 Plot 72 Plot 140
Plot 13 Plot 76 Plot 141
Plot 14 Plot 79 Plot 144
Plot 17 Plot 80 Plot 145
Plot 22 Plot 83 Plot 148
Plot 23 Plot 88 Plot 150
Plot 24 Plot 89 Plot 151
Plot 30 Plot 90 Plot 153
Plot 31 Plot 92 Plot 155
Plot 33 Plot 94 Plot 157
Plot 34 Plot 96 Plot 159
Plot 35 Plot 100Plot 163
Plot 39 Plot 101Plot 164
Plot 42 Plot 102Plot 167
Plot 45 Plot 105Plot 170
Plot 46 Plot 106Plot 173
Plot 49 Plot 109Plot 174
Plot 50 Plot 114Plot 179
Plot 52 Plot 117Plot 180
Plot 53 Plot 120Plot 184
Plot 56 Plot 121Plot 185
Plot 57 Plot 187
Plot 58 Plot 188
111
Construction and carrying
out of the authorised
development
East Riding of
Yorkshire
Council
Plot 190Plot 580Plot 904
Plot 191Plot 582Plot 908
Plot 192Plot 584Plot 912
Plot 194Plot 585Plot 913
Plot 196Plot 587Plot 914
Plot 197Plot 588Plot 915
Plot 199Plot 589Plot 916
Plot 201Plot 592Plot 921
Plot 203Plot 593Plot 925
Plot 205Plot 597Plot 930
Plot 207Plot 598Plot 931
Plot 209Plot 599Plot 932
Plot 211Plot 602Plot 935
Plot 213Plot 603Plot 936
Plot 214Plot 605Plot 938
Plot 217Plot 610Plot 939
Plot 219Plot 611Plot 943
Plot 220Plot 612Plot 944
Plot 221Plot 613Plot 948
Plot 222Plot 616Plot 949
Plot 223Plot 617Plot 953
Plot 224Plot 619Plot 954
Plot 225Plot 620Plot 955
Plot 227Plot 622Plot 959
Plot 228Plot 623Plot 960
Plot 231Plot 624Plot 961
Plot 234Plot 629Plot 964
Plot 237Plot 633Plot 965
Plot 238Plot 634Plot 966
Plot 241Plot 636Plot 970
Plot 242Plot 638Plot 971
Plot 244Plot 639Plot 972
Plot 247Plot 641Plot 973
Plot 249Plot 642Plot 977
Plot 253Plot 644Plot 980
Construction and carrying
out of the authorised
development
Work No. 5C
Work No. 5D
Work No. 5E
Work No. 5F
Work No. 5G
Work No. 5H
Work No. 5I
Work No. 5J
Work No. 6C
Work No. 6D
Work No. 7
Work No. 8A
Work No. 8B
Work No. 8C
Work No. 8D
Work No. 8E
Work No. 8F
Work No. 8G
Work No. 8H
Work No. 8I
Work No. 8J
Work No. 8K
Work No. 8L
Work No. 9A
Work No. 9B
Work No. 9C
Work No. 9D
Work No. 10A
Work No. 10B
Work No. 10C
Work No. 10D
Work No. 10E
Work No. 10F
Work No. 10G
Work No. 10H
Plot 41 Plot 115Plot 175
Plot 43 Plot 116Plot 176
Plot 47 Plot 119Plot 177
Plot 55 Plot 123Plot 178
Plot 66 Plot 127Plot 183
Plot 68 Plot 131
Plot 69 Plot 134
(4)
Relevant part of the
authorised
development
East Riding of
Yorkshire
Council
Plot 254Plot 645Plot 983
Plot 257Plot 647Plot 984
Plot 261Plot 648Plot 986
Plot 262Plot 649Plot 988
Plot 264Plot 651Plot 989
Plot 266Plot 653Plot 992
Plot 269Plot 657Plot 993
Plot 270Plot 662Plot 995
Plot 663
Plot 275Plot 664Plot 996
Plot 276Plot 668Plot 999
Plot 280Plot 669Plot 1000
Plot 281Plot 675Plot 1002
Plot 284Plot 676Plot 1003
Work No. 10I
Work No. 10J
Work No. 10K
Work No. 11C
Work No. 11D
Work No. 12
Work No. 13A
Work No. 13B
Work No. 13C
Work No. 13D
Work No. 13E
Work No. 14B
Work No. 14C
Work No. 14D
(1)
Area
(2)
Plot number of land shown
on land plans
112
(3)
Purpose for which
temporary possession may
be taken
Work No. 15B
(1)
Area
(2)
Plot number of land shown
on land plans
East Riding of
Yorkshire
Council
Plot 381Plot 754Plot 1081
Plot 382Plot 755Plot 1082
Plot 385Plot 757Plot 1084
Plot 386Plot 759Plot 1085
Plot 390Plot 760Plot 1086
Plot 391Plot 762Plot 1088
Plot 396Plot 765Plot 1089
Plot 397Plot 769Plot 1091
Plot 405Plot 770Plot 1094
Plot 406Plot 772Plot 1095
Plot 409Plot 773Plot 1096
Plot 413Plot 776Plot 1098
(3)
Purpose for which
temporary possession may
be taken
Plot 285Plot 679Plot 1004
Plot 289Plot 682Plot 1005
Plot 290Plot 684Plot 1007
Plot 293Plot 688Plot 1008
Plot 295Plot 689Plot 1009
Plot 298Plot 692Plot 1010
Plot 302Plot 696Plot 1011
Plot 303Plot 700Plot 1016
Plot 308Plot 701Plot 1020
Plot 309Plot 702Plot 1021
Plot 310Plot 706Plot 1024
Plot 318Plot 707Plot 1026
Plot 321Plot 710Plot 1027
Plot 324Plot 712Plot 1030
Plot 325Plot 713Plot 1031
Plot 329Plot 714Plot 1032
Plot 332Plot 715Plot 1037
Plot 333Plot 716Plot 1038
Plot 334Plot 717Plot 1040
Plot 335Plot 718Plot 1041
Plot 338Plot 720Plot 1042
Plot 339Plot 721Plot 1043
Plot 341Plot 723Plot 1047
Plot 343Plot 724Plot 1048
Plot 345Plot 726Plot 1050
Plot 347Plot 727Plot 1051
Plot 348Plot 728Plot 1052
Plot 351Plot 729Plot 1055
Plot 353Plot 730Plot 1057
Plot 354Plot 732Plot 1058
Plot 357Plot 734Plot 1059
Plot 359Plot 736Plot 1060
Plot 360Plot 737Plot 1062
Plot 362Plot 738Plot 1063
Plot 363Plot 739Plot 1064
Plot 364Plot 742Plot 1067
Plot 365Plot 743Plot 1068
Plot 369Plot 744Plot 1069
Plot 370Plot 746Plot 1075
Plot 373Plot 747Plot 1076
Plot 374Plot 749Plot 1077
Plot 376Plot 750Plot 1078
Plot 378Plot 752Plot 1079
Plot 379Plot 753Plot 1080
113
(4)
Relevant part of the
authorised
development
(2)
Plot number of land shown
on land plans
(3)
Purpose for which
temporary possession may
be taken
East Riding of
Yorkshire
Council
Plot 506Plot 843Plot 1201
Plot 507Plot 846Plot 1202
Plot 509Plot 847Plot 1204
Plot 510Plot 848Plot 1205
Plot 511Plot 849Plot 1206
Plot 515Plot 851Plot 1213
Plot 516Plot 852Plot 1214
Plot 517Plot 854Plot 1219
Plot 518Plot 856Plot 1220
Plot 414Plot 777Plot 1100
Plot 418Plot 778Plot 1104
Plot 419Plot 779Plot 1108
Plot 422Plot 781Plot 1111
Plot 423Plot 782Plot 1112
Plot 426Plot 784Plot 1114
Plot 431Plot 785Plot 1117
Plot 433Plot 787Plot 1119
Plot 434Plot 788Plot 1122
Plot 436Plot 790Plot 1125
Plot 437Plot 791Plot 1128
Plot 439Plot 793Plot 1129
Plot 440Plot 794Plot 1132
Plot 443Plot 796Plot 1133
Plot 445Plot 797Plot 1134
Plot 448Plot 798Plot 1135
Plot 451Plot 799Plot 1139
Plot 452Plot 801Plot 1140
Plot 453Plot 802Plot 1141
Plot 455Plot 804Plot 1142
Plot 458Plot 805Plot 1146
Plot 459Plot 807Plot 1148
Plot 463Plot 808Plot 1150
Plot 464Plot 809Plot 1156
Plot 467Plot 811Plot 1157
Plot 469Plot 812Plot 1159
Plot 470Plot 814Plot 1160
Plot 472Plot 815Plot 1163
Plot 473Plot 816Plot 1164
Plot 476Plot 818Plot 1167
Plot 477Plot 819Plot 1168
Plot 478Plot 821Plot 1172
Plot 479Plot 822Plot 1173
Plot 481Plot 824Plot 1174
Plot 482Plot 825Plot 1176
Plot 484Plot 827Plot 1177
Plot 485Plot 828Plot 1180
Plot 487Plot 829Plot 1181
Plot 488Plot 830Plot 1183
Plot 490Plot 832Plot 1184
Plot 491Plot 833Plot 1185
Plot 494Plot 834Plot 1190
Plot 499Plot 836Plot 1191
Plot 500Plot 837Plot 1192
Plot 501Plot 839Plot 1196
Plot 503Plot 840Plot 1197
Plot 504Plot 842Plot 1200
(4)
Relevant part of the
authorised
development
114
(1)
Area
East Riding of
Yorkshire
Council
Plot 572
Plot 592
Plot 593
Plot 847
Plot 1059
Plot 1060
Plot 1068
Plot 1261
Plot 1262
Plot 1272
Temporary construction
compounds, stores and
office areas for the
construction and carrying
out of the authorised
development
Work No. 6D
Work No. 7
Work No. 9D
Work No. 11D
Work No. 12
Work No. 14D
Plot 519Plot 857Plot 1224
Plot 520Plot 859Plot 1225
Plot 524Plot 860Plot 1227
Plot 525Plot 862Plot 1228
Plot 526Plot 863Plot 1230
Plot 530Plot 865Plot 1231
Plot 531Plot 866Plot 1233
Plot 534Plot 867Plot 1234
Plot 535Plot 869Plot 1237
Plot 538Plot 870Plot 1238
Plot 539Plot 872Plot 1241
Plot 541Plot 873Plot 1244
Plot 542Plot 874Plot 1245
Plot 543Plot 875Plot 1248
Plot 546Plot 877Plot 1249
Plot 547Plot 879Plot 1250
Plot 550Plot 880Plot 1251
Plot 553Plot 882Plot 1252
Plot 554Plot 883Plot 1256
Plot 558Plot 885Plot 1257
Plot 559Plot 886Plot 1260
Plot 564Plot 888Plot 1261
Plot 565Plot 889Plot 1262
Plot 566Plot 891Plot 1264
Plot 568Plot 892Plot 1266
Plot 572Plot 893Plot 1267
Plot 573Plot 894Plot 1269
Plot 574Plot 896Plot 1272
Plot 575Plot 900Plot 1275
Plot 576Plot 901Plot 1278
Plot 578Plot 902Plot 1279
Plot 579Plot 903Plot 1281
Plot 1282
(4)
Relevant part of the
authorised
development
East Riding of
Yorkshire
Council
Plot 204Plot 493Plot 963
Plot 216Plot 495Plot 968
Plot 218Plot 496Plot 969
Plot 229Plot 498Plot 974
Plot 232Plot 505Plot 975
Plot 235Plot 512Plot 976
Plot 239Plot 514Plot 979
Plot 243Plot 521Plot 982
Plot 245Plot 523Plot 987
Plot 251Plot 527Plot 991
Plot 252Plot 529Plot 998
Plot 258Plot 532Plot 1006
Plot 260Plot 536Plot 1012
Construction and carrying
out of the drainage works
The drainage works
(which has the meaning
given in article 2
(interpretation)
(1)
Area
(2)
Plot number of land shown
on land plans
115
(3)
Purpose for which
temporary possession may
be taken
(2)
Plot number of land shown
on land plans
(3)
Purpose for which
temporary possession may
be taken
East Riding of
Yorkshire
Council
Plot 400Plot 687Plot 1186
Plot 401Plot 691Plot 1188
Plot 402Plot 693Plot 1189
Plot 404Plot 695Plot 1193
Plot 407Plot 697Plot 1195
Plot 408Plot 699Plot 1198
Plot 410Plot 703Plot 1207
Plot 412Plot 705Plot 1209
Plot 415Plot 709Plot 1210
Plot 417Plot 711Plot 1212
Plot 420Plot 850Plot 1215
Plot 265Plot 540Plot 1014
Plot 268Plot 544Plot 1015
Plot 271Plot 548Plot 1018
Plot 272Plot 549Plot 1019
Plot 274Plot 552Plot 1023
Plot 277Plot 555Plot 1029
Plot 279Plot 557Plot 1034
Plot 283Plot 560Plot 1035
Plot 286Plot 561Plot 1036
Plot 288Plot 563Plot 1044
Plot 292Plot 567Plot 1045
Plot 297Plot 590Plot 1053
Plot 299Plot 591Plot 1054
Plot 301Plot 595Plot 1065
Plot 304Plot 596Plot 1070
Plot 305Plot 601Plot 1092
Plot 307Plot 606Plot 1093
Plot 311Plot 607Plot 1099
Plot 312Plot 608Plot 1101
Plot 313Plot 609Plot 1103
Plot 314Plot 614Plot 1105
Plot 316Plot 625Plot 1107
Plot 317Plot 626Plot 1109
Plot 319Plot 628Plot 1116
Plot 323Plot 630Plot 1118
Plot 326Plot 631Plot 1121
Plot 327Plot 632Plot 1123
Plot 331Plot 635Plot 1126
Plot 336Plot 646Plot 1130
Plot 349Plot 652Plot 1136
Plot 350Plot 654Plot 1138
Plot 355Plot 656Plot 1143
Plot 356Plot 658Plot 1144
Plot 361Plot 659Plot 1145
Plot 366Plot 660Plot 1147
Plot 367Plot 661Plot 1149
Plot 372Plot 666Plot 1151
Plot 375Plot 667Plot 1152
Plot 383Plot 671Plot 1154
Plot 387Plot 672Plot 1155
Plot 389Plot 673Plot 1162
Plot 392Plot 674Plot 1166
Plot 393Plot 678Plot 1169
Plot 395Plot 680Plot 1170
Plot 398Plot 681Plot 1171
Plot 399Plot 685Plot 1178
(4)
Relevant part of the
authorised
development
116
(1)
Area
(4)
Relevant part of the
authorised
development
(1)
Area
(2)
Plot number of land shown
on land plans
(3)
Purpose for which
temporary possession may
be taken
117
Plot 905
Plot 424Plot 906Plot 1216
Plot 425Plot 910Plot 1217
Plot 427Plot 911Plot 1218
Plot 428Plot 917Plot 1221
Plot 429Plot 919Plot 1222
Plot 430Plot 920Plot 1232
Plot 441Plot 923Plot 1235
Plot 442Plot 924Plot 1236
Plot 444Plot 927Plot 1239
Plot 446Plot 928Plot 1240
Plot 447Plot 929Plot 1243
Plot 450Plot 934Plot 1246
Plot 457Plot 941Plot 1247
Plot 460Plot 942Plot 1253
Plot 462Plot 946Plot 1255
Plot 466Plot 947Plot 1259
Plot 474Plot 951Plot 1270
Plot 475Plot 952Plot 1273
Plot 492Plot 957Plot 1274
Plot 958 Plot 1276
Plot 1283
Plot 1284
Plot 1285
118
SCHEDULE 10 Article 42
DEEMED MARINE LICENCE UNDER PART 4 (MARINE LICENSING)
OF THE MARINE AND COASTAL ACCESS ACT 2009
PART 1
INTERPRETATION
—a) In this Schedule—1.
“the 2009 Act” means the Marine and Coastal Access Act 2009;
“authorised deposits” means the substances and articles specified in sub-paragraph 2(4) of Part I of
this Schedule;
“Cefas” means the Centre for Environment, Fisheries and Aquaculture Science or any replacement
body or successor to its functions;
“commence” means beginning to carry out any material operation (as defined in section 56(4) of the
1990 Act) other than operations consisting of archaeological investigations, investigations for
the purpose of assessing ground conditions, remedial work in respect of any contamination or
other adverse ground conditions and "commencement" is to be construed accordingly;
“enforcement officer” means a marine enforcement officer within the meaning of section 235 of the
2009 Act;
“English Heritage” means the Historic Buildings and Monuments Commission for England or any
successor to its statutory functions;
“the English inshore region” has the same meaning as that given in section 322 (interpretation) of
the 2009 Act;
“the Environment Agency” means the body established under the Environment Act 1995(c) or any
successor to its statutory functions;
“the environmental statement” means the document certified as the environmental statement by the
Secretary of State for the purposes of the Order;
“the Health and Safety Executive” or “HSE” means the body established under section 10 of
the Health and Safety at Work etc. Act 1974(d) or any successor to its statutory functions or other
authority performing, carrying out or having the same regulatory functions as the HSE has at
the date of the Order;
“the intertidal area” means the area between mean high water spring tide and mean low water spring
tide;
“the Kingfisher Fortnightly Bulletin” means the bulletin published by the Humber Seafood Institute
or such other alternative publication approved in writing by the MMO for the purposes of this
Schedule;
“the licence conditions” means the conditions set out in Part 2 of this Schedule;
“licensed activity” means a licensable marine activity listed in paragraph 2 of Part 1 of this
Schedule;
___________________________________________________________________________________________
_
(c) 1995 c.25.
(d) 1974 c.37; section 10 of the Health and Safety at Work Act is substituted by S.I. 2008/960.
“licensed location” means the area set out at paragraphs 2(3)(a) and 2(3)(b) of Part 1 of this
Schedule;
“licensed works” means any works constructed in the course of a licensed activity;
“the Marine Management Organisation” or “the MMO” means the body of that name created
under the 2009 Act which is responsible for the monitoring and enforcement of this licence or
any successor to its functions;
“the Maritime and Coastguard Agency” or “MCA” means the executive agency of the
Department for Transport or any successor to its functions;
“mean high water spring tide” or “MHWS” means the highest level which spring tides reach on
average over a period of time;
“mean low water spring tide” or “MLWS” means the lowest level which spring tides reach on
average over a period of time;
“Natural England” means the body established by section 1 of the Natural Environment and
Rural Communities Act 2006 or any successor to its statutory functions;
“notice to mariners” includes any notice to mariners which may be issued by the Admiralty,
Trinity House, Queen's harbourmasters, government departments and harbour and pilotage
authorities;
“the Order” means the Yorkshire and Humber (Carbon Capture and Storage Cross Country
Pipeline) Order 201[●];
“the project design statement” means the document certified as the project design statement by
the Secretary of State for the purposes of the Order;
“regulatory authorities” means any government department, public, local or regulatory or any
other authority or institution having regulatory functions, powers, duties and obligations having
the full force of law;
“sea” has the same meaning as that given at section 42(3) of the 2009 Act;
“Trinity House” means the Corporation of Trinity House of Deptford Strond or any successor to
its functions;
“the UK Hydrographic Office” means the Hydrographic Office of the Ministry of Defence,
Taunton, Somerset TA1 2DN or any replacement body or successor to its functions;
“the undertaker” has the same meaning as that given in article 2 (interpretation) of the Order;
“vessel” means every description of vessel, however propelled or moved, and includes a
non-displacement craft, a personal watercraft, a barge, a jack up barge, a seaplane on the
surface of the water, a hydrofoil vessel, a hovercraft or any other amphibious vehicle and any
other thing constructed or adapted for movement through, in, on or over water and which is at
the time in, on or over water;
“VHF” means very high frequency; and
“working day” means a day which is not a Saturday, Sunday, Bank Holiday or other public
holiday.
Unless otherwise indicated all geographical co-ordinates contained within this licence are in (1)
latitude and longitude degrees and minutes to three decimal places and the datum used for such
co-ordinates is WGS84.
Except where otherwise notified in writing by the relevant organization, the primary point of (2)
contact with the organisations listed below and the address for returns and correspondence is
Marine Licensing Team(a)
Marine Management Organisation
Lancaster House
Hampshire Court
Newcastle upon Tyne NE4 7YH
Tel: 0300 123 1032
Email: [email protected]
119
Northern Marine Area(b)
Marine Management Organisation
Unit 2a
Newchase Court
Hopper Hill Road
Eastfield
Scarborough
North Yorks YO11 3YS
Tel: 01723 580040
Email: [email protected]
Trinity House(c)
Tower Hill
London EC3N 4DH
Tel: 020 7481 6900
The United Kingdom Hydrographic Office Admiralty Way(d)
Taunton
Somerset TA1 2DN
Tel: 01823 337 900
Maritime and Coastguard Agency Navigation Safety Branch(e)
Bay 2/04
Spring Place
105 Commercial Road
Southampton S015 lEG
Tel: 023 8032 9191
Centre of Environment, Fisheries and Aquaculture Science(f)
Pakefield Road
Lowestoft
Suffolk NR33 OHT
Tel: 01502 562 244
The Environment Agency (g)
8 City Walk
Leeds
West Yorkshire LS11 9AT
0370 8506506
Natural England(h)
Foundary House
3 Millsands
Riverside Exchange
Sheffield S3 8NH
Tel: 0845 600 3078
English Heritage(i)
Eastgate Court
195-205 High Street
Guildford GU1 3EH
120
Details of licensed marine activities
—a) Subject to the licence conditions this licence authorises the undertaker (and any agent 2.
or contractor acting on their behalf) to carry out the following licensable marine activities
pursuant to section 66(1) of the 2009 Act—
the deposit at sea of the substances and articles specified in sub-paragraph (5);(a)
the construction of works in, under or over the intertidal area;(b)
the inspection and maintenance of works in, under or over the intertidal area; (c)
the construction of works under the River Ouse;(d)
the inspection and maintenance of works under the River Ouse; and(e)
sampling or investigative works required in connection with paragraphs (a) and (e). (f)
The activities set out in sub-paragraph (1) are authorised in relation to the construction and (1)
operation of those elements of Work No.5C and Work No. 15B of the Schedule 1 (authorised
development) of this Order, and any further associated development listed in items (a) to (o) in
Schedule 1 in connection with those Work Nos., which fall within the English inshore region.
The undertaker (and any agent, contractor or subcontractor acting on its behalf) may engage in (2)
the licensed activities in—
the area bounded by the coordinates set out in this sub-paragraph; and(a)
any area within the Order limits (as defined in article 2 (interpretation) of this Order) (b)
which falls outwith the area bounded by the coordinates set out in this sub-paragraph but
which falls below mean high water spring tide when the licensed activities are carried out.
Latitude (DMS) Longitude
Work No. 15B at the intertidal
54:01:44.049N 0:12:58.516W
54:01:44.455N 0:12:48.824W
54:01:31.310N 0:12:48.398W
54:01:31.374N 0:12:57.079W
Latitude Longitude
Work No. 5C at the river Ouse
53:44:10.693N 0:57:06.533W
53:44:07.840N 0:56:58.581W
53:44:05.786N 0:57:04.199W
53:44:7.501N 0:57:15.290W
53:44:05:031N 0:56:51:938W
53:44:04:800N 0:56:51:398W
53:44:04:542N 0:56:51:514W
53:44:04:741N 0:56:52:000W
For the avoidance of doubt, the licence in this Schedule does not authorise the decommissioning (3)
of the licensed works for which a separate marine licence may be required.
The substances or articles authorised for deposit at sea are—(4)
metal;(a)
121
gravel;(b)
concrete;(c)
sand; and(d)
bentonite and grout.(e)
In the application of section 72 of the 2009 Act to this licence, subsection 72(8) of the 2009 Act (5)
does not apply to a transfer made in accordance with article 9 (transfer of benefit of Order) of this
Order.
122
PART 2
LICENCE CONDITIONS
Application of Licence Conditions
This Part does not apply to any part of Work No. 5C and Work No. 15B of Schedule 1 1.
(authorised development) which falls outside the English inshore region.
Licensed location
The licensed works must be located within the licensed location.2.
Notifications and inspections
—a) The undertaker must ensure that a copy of this Schedule and any subsequent 3.
amendments or revisions to it are provided prior to commencement of the licensed activities to—
all agents and contractors notified to the MMO in accordance with the licence conditions; (a)
and
the masters and transport managers responsible for the vessels notified to the MMO in (b)
accordance with the licence conditions.
Only those persons and vessels notified to the MMO in accordance with the licence conditions (1)
are permitted to carry out the licensed activities.
Copies of this Schedule must also be available for inspection by an enforcement officer at all (2)
times during construction of the licensed works at the following locations—
the undertaker's registered address;(a)
any site office located at or adjacent to the construction site and used by the undertaker or (b)
its agents and contractors responsible for the loading, transportation or deposit of the
authorised deposits and works; and
on board each vessel or at the office of any transport manager with responsibility for (c)
vessels from which authorised deposits are to be made or authorised works undertaken.
The undertaker must provide access to the construction site for licensed activities or any other (3)
associated works or vessels to facilitate any inspection that the MMO considers necessary to inspect
the works during the carrying out of the licensed activities.
The undertaker must inform the MMO in writing of the commencement of the licensed activities (4)
at least five working days in advance of those activities.
At least seven days prior to the commencement of the licensed activities the undertaker must (5)
publish in the Kingfisher Fortnightly Bulletin details of the vessel routes, timings and locations
relating to the carrying out of licensed activities.
The undertaker must ensure that—(6)
a notice to mariners is issued at least ten days prior to the commencement of the licensed (a)
activities advising of the commencement of licensed activities within the licensed location;
and
a second notice to mariners is issued advising of the commencement of licensed activities (b)
within the licensed location.
The notices to mariners must be updated and reissued not less frequently than weekly during (7)
construction of the licensed works.
The undertaker must notify—(8)
the UK Hydrographic Office within ten days of the completion of the licensed works in (a)
order that all necessary amendments to nautical charts are made;
123
the MMO of completion of the licensed works within ten days of completion of those (b)
works; and
the MMO of any marking of the route of the licensed works (if any) within ten days of (c)
completion of the licensed works.
The undertaker must ensure that prior to the commencement of the licensed activities the (9)
following suitably qualified and experienced liaison officers are appointed and their identity and
credentials notified to the MMO as part of the project environmental management plan required by
licence condition 6(1)(c) (pre-construction plans and documentation)—
a Fisheries Liaison Officer or Officers; and(a)
an Environmental Liaison Officer or Officers.(b)
The responsibilities of the Fisheries and Environmental Liaison Officer(s) must be provided to (10)
the MMO no later than twelve weeks prior to the commencement of licensed activities for comment.
Chemicals, drilling and debris
—a) All chemicals used in the construction of the licensed works, including any chemical 4.
agents placed within the void comprised in the construction of Work No. 5C and Work No. 15B,
must be selected from the List of Notified Chemicals approved for use by the offshore oil and gas
industry under the Offshore Chemicals Regulations 2002(a) unless otherwise agreed in writing
by the MMO.
The undertaker must ensure that any coatings and/or treatments are suitable for use in the marine (1)
environment and are used in accordance with relevant Pollution Prevention Guidelines issued by the
Environment Agency and/or relevant guidelines issued by the Health and Safety Executive; and any
accidental spillages of such coatings and/or treatments in the marine environment must be reported to
the MMO marine pollution response team within six hours of such spillage.
The storage, handling, transport and use of fuels, lubricants, chemicals and other substances (2)
must be undertaken so as to prevent releases into the marine environment including bunding of 110%
of the total volume of all reservoirs and containers.
Where drilling works are proposed as the trenchless crossing technique for the purposes of a (3)
licensed activity, and any system other than water-based mud is proposed for such drilling works, the
MMO's written approval in relation to the proposed disposal of any arisings from such drilling works
must be obtained prior to the commencement of such drilling works; and if the disposal of the arisings
at sea does not fall within the scope of the environmental statement a separate marine licence for such
drilling is required.
The undertaker must ensure that any—(4)
waste and/or debris arising from construction of the licensed activities;(a)
equipment used for the purposes of carrying out the licensed activities; and(b)
works placed below MHWS temporarily for the purposes of carrying out the licensed (c)
activities,
are removed within four weeks of completion of the licensed activities.
Force majeure
If, due to stress of weather or any other cause the master of a vessel determines that it is 5.
necessary to deposit the authorised deposits outside of the licensed location because the safety of
human life and/or of the vessel is threatened, full details of the circumstances of the deposit must
be notified to the MMO within 48 hours; and such deposits must later be removed by the
undertaker following the approval of the MMO for such removal.
Pre-construction plans and documentation
—a) At least four months prior to the commencement of licensed activities (unless such 6.longer period is agreed in writing by the MMO) the undertaker must submit for the approval of
124
the MMO—
a construction and monitoring programme to include details of— (a)
the proposed construction start date for the licensed works;(i)
timings for mobilisation of plant, delivery of materials and installation works; and(ii)
the methodologies for, and timings for preparing and submitting, survey (iii)
specifications, data collection and analysis to the MMO in accordance with licence
conditions 9 to 11 (pre-construction baseline and post construction),
and where compliance with the construction and monitoring programme agreed under
this paragraph (a) is not possible, the undertaker must notify the MMO in writing and
submit a revised programme for approval; and, in circumstances where the revised
programme affects other plans or documents agreed by the MMO under this
paragraph, the MMO may require construction works to cease until it has approved
the revised programme;
a construction method statement which is in accordance with the project design statement (b)
and environmental statement and which includes details of—
reception pit construction;(i)
trenchless crossing method(s);(ii)
pipeline installation;(iii)
works associated with sub-paragraphs (b)(i), (b)(ii) and (b)(iii) above;(iv)
contractors; and(v)
vessels.(vi)
a project environmental management plan to include details of— (c)
a marine pollution contingency plan to address the risks, methods and procedures to (i)
deal with any spills and collision incidents during construction and operation of the
licensed works in relation to all licensed activities carried out between mean low
water springs and mean high water springs;
a chemical risk analysis to include information regarding how and when chemicals (ii)
are to be used, stored and transported;
waste management and disposal arrangements;(iii)
the appointment and responsibilities of any officers required in connection with the (iv)
carrying out of the licensed activities; and
locations of any archaeological exclusion zones agreed as part of the written scheme (v)
of investigation approved under paragraph (e) of this licence condition;
a written scheme of archaeological investigation to include— (d)
details of responsibilities of the undertaker, archaeological consultant and contractor;(i)
a methodology for any site investigation including any specifications for geophysical (ii)
and geotechnical;
analysis and reporting of survey data to be submitted to the MMO within three (iii)
months of survey completion and to be agreed in writing with the MMO following
consultation with English Heritage;
delivery of any mitigation including, where necessary, archaeological exclusion (iv)
zones;
monitoring during and post construction, including a conservation programme for (v)
finds;
archiving of archaeological material with a public archive in accordance with the (vi)
Online AccesS to the Index of archaeological investigationS (OASIS) system; and
a reporting and recording protocol, including reporting of any wreck or wreck (vii)
material during construction, operation and decommissioning of the authorised
development.
125
No licensed activity is to commence until the MMO has approved in writing the relevant (1)
programme, statement, plan, protocol or scheme required to be approved for that licensed activity
under this paragraph; and a licensed activity must be carried out in accordance with the plans,
protocols, statements, schemes and details approved in relation to it under this paragraph, unless
otherwise agreed in writing by the MMO.
Reporting of engaged agents, contractors and vessels
—a) The undertaker must provide to the MMO— 7.
the name and function of any agent or contractor appointed to engage in a licensed activity (a)
at least five working days before that agent or contractor engages in that licensed activity;
and
a listing of the vessels currently and to be used in relation to the licensed activities (b)
each week during the carrying out of the licensed activities.
Any changes to the details supplied to the MMO under this paragraph must be notified to and (1)
agreed with the MMO in writing prior to the agent, contractor or vessel in question engaging in the
licensed activities.
Equipment and operation of vessels engaged in licensed activities
—a) All vessels employed to perform the licensed activities must be constructed and 8.
equipped to be capable of the proper performance of such activities in accordance with the
licence conditions and must comply with sub-paragraphs (2) and (3).
Subject to sub-paragraph (3) all motor powered vessels must be fitted with—(1)
electronic positioning aid to provide navigational data;(a)
radar;(b)
echo sounder; and(c)
multi-channel VHF.(d)
No vessel is to engage in the licensed activities unless all the equipment specified in (2)
sub-paragraph (2) is fully operational.
Pre-construction baseline
—a) Any pre-construction baseline report must take account of any existing environmental 9.
data, assessments and reports prepared by or on behalf of the undertaker and relevant to the
licensed location.
Prior to the commencement of the licensed activities the undertaker must submit a (1)
pre-construction baseline report to the MMO for written approval. No licensed activities are to
commence until the MMO has approved in writing the pre-construction baseline report. The form and
content of the report, including any environmental monitoring, must be agreed in writing by the MMO
The pre-construction baseline report must include—(2)
a Phase l survey of the intertidal area(a)
data concerning existing marine fish and shellfish populations and marine spawning (b)
activity within five kilometres of that part of the licensed location comprising the
intertidal area;
data concerning existing marine ornithological activity within five kilometres of that part (c)
of the licensed location comprising the intertidal area; and
a desk based assessment of known and predicted archaeology and paleo-archaeological (d)
deposits.
In the event that the pre-construction baseline report contains sufficient information regarding (3)
the effects of the licensed activities on individual matters listed at sub-paragraphs (3)(a) to (3)(d) the
126
licensed activities may be commenced (subject to any ongoing monitoring requirements notified by the
MMO to the undertaker in writing).
Construction monitoring
—a) During construction of the licensed works the undertaker must submit environmental 10.
monitoring reports to the MMO in accordance with the construction and monitoring programme
approved under licence condition 6(1)(a) (pre-construction plans and documentation) which
must include—
the monitoring of suspended sediment concentrations in seawater within the jetting (a)
area and at a suitable control location, should jetting be used for pipeline
installation;
measurements of noise and vibration generated by the installation of any piled pits and (b)
trenchless crossing;
In the event that the reception pit comprised in Work No. 15B of Schedule 1 (authorised (1)
development) is located seaward of MLWS, the undertaker must provide the results of any initial
noise measurements (required under sub-paragraph (1)(b)) to the MMO within six weeks of such
results being obtained; and the MMO may determine whether any further noise monitoring is required
pursuant to sub-paragraph (1)(b) on the basis of those preliminary results.
Post construction
Following construction of the licensed works the undertaker must submit environmental 11.
monitoring reports to the MMO in accordance with the construction and monitoring timetable
approved under 6(1)(a) (pre-construction plans and documentation).
Amendments to approved details
With respect to any condition of this Schedule which requires the licensed activities to be 12.
carried out in accordance with plans, programmes and reports approved by the MMO, the
approved plans, programmes and reports include any amendments that may subsequently be
approved in writing by the MMO to the extent that the MMO may lawfully do so.
127
SCHEDULE 11 Article 48
PROTECTIVE PROVISIONS
PART 1
FOR THE PROTECTION OF ELECTRICITY, GAS, WATER AND SEWERAGE
UNDERTAKERS
Application
For the protection of the undertakers referred to in this Part of this Schedule the following 1.
provisions, unless otherwise agreed in writing at any time between the promoter and the
undertaker concerned, have effect.
Interpretation
In this Part of this Schedule—2.
“alternative apparatus” means alternative apparatus adequate to enable the undertaker in
question to fulfil its statutory functions in a manner not less efficient than previously;
“apparatus” means—
in the case of an electricity undertaker, electric lines or electrical plant (as defined in the (a)
Electricity Act 1989(jj)), belonging to or maintained by that electricity undertaker for the
purposes of electricity supply;
in the case of a gas undertaker, any mains, pipes or other apparatus belonging to or (b)
maintained by that gas transporter for the purposes of gas supply;
in the case of a water undertaker, mains, pipes or other apparatus belonging to or (c)
maintained by that water undertaker for the purposes of water supply; and
in the case of a sewerage undertaker—(d)
any drain or works vested in the undertaker under the Water Industry Act 1991(kk) (i)
and Water Industry (Schemes for Adoption of Private Sewers) Regulations 2011(ll);
and
any sewer which is so vested or is the subject of a notice of intention to adopt given (ii)
under section 102(4) of that Act or an agreement to adopt made under section 104 of
that Act,
and in each case includes a sludge main, disposal main (within the meaning of (iii)
section 219 of that Act) or sewer outfall and any manholes, ventilating shafts, pumps
or other accessories forming part of any such sewer, drain or works,
and includes any structure in which apparatus is or is to be lodged or which gives or
will give access to apparatus;
“commence” has the same meaning as in paragraph 1 of Schedule 3 (requirements);
“functions” includes powers and duties;
“in” in a context referring to apparatus or alternative apparatus in land includes a reference to
apparatus or alternative apparatus under, over or upon land;
(jj) 1989 c. 29.
(kk) 1991 c. 56.
(ll) S.I. 2011/1566.
128
“pipeline” means the whole or any part of a pipeline belonging to or maintained by an
undertaker and includes any ancillary works and apparatus;
“plan” includes a section and description of the works to be executed;
“promoter” means the undertaker as defined in article 2 (interpretation) of this Order;
“undertaker” means—
any licence holder within the meaning of Part 1 of the Electricity Act 1989;(a)
a gas transporter within the meaning of Part 1 of the Gas Act 1986(mm);(b)
a water undertaker within the meaning of the Water Industry Act 1991; and(c)
a sewerage undertaker within the meaning of Part 1 of the Water Industry Act 1991,(d)
for the area of the authorised development, and in relation to any apparatus, means the
undertaker to whom it belongs or by whom it is maintained.
On-street apparatus
This Part of this Schedule does not apply to apparatus in respect of which the relations 3.
between the promoter and the undertaker are regulated by the provisions of Part 3 of the 1991
Act.
Acquisition of apparatus
Regardless of any provision in this Order or anything shown on the land plans, the promoter 4.
must not acquire any apparatus otherwise than by agreement.
Removal of apparatus
—a) If, in the exercise of the powers conferred by this Order, the promoter acquires any 5.
interest in any land in which any apparatus is placed, that apparatus must not be removed under
this Part of this Schedule and any right of an undertaker to maintain that apparatus in that land
must not be extinguished until alternative apparatus has been constructed and is in operation to
the reasonable satisfaction of the undertaker in question.
If, for the purpose of executing any works in, on or under any land purchased, held, appropriated (1)
or used under this Order, the promoter requires the removal of any apparatus placed in that land, it
must give the undertaker in question written notice of that requirement, together with a plan of the
work proposed.
If alternative apparatus or any part of such apparatus is to be constructed as a consequence of (2)
the removal of apparatus placed on the land referred to in sub-paragraph (2), the undertaker in
question must, on receipt of a written notice to that effect from the promoter, as soon as reasonably
possible use its best endeavours to obtain the necessary facilities and rights in other land in which the
alternative apparatus is to be constructed.
The undertaker in question must, after the alternative apparatus to be provided or constructed (3)
has been agreed or settled by arbitration in accordance with article 51 (arbitration), and after the
grant to the undertaker of any such facilities and rights as are referred to in sub-paragraph (3),
proceed without unnecessary delay to construct and bring into operation the alternative apparatus and
subsequently to remove any apparatus required by the promoter to be removed under the provisions of
this Part of this Schedule.
Regardless of anything in sub-paragraph (4), if the promoter gives notice in writing to the (4)
undertaker in question that it desires itself to execute any work, or part of any work in connection with
the construction or removal of apparatus, that work, instead of being executed by the undertaker, must
be executed by the promoter without unnecessary delay under the superintendence, if given, and to the
reasonable satisfaction of the undertaker.
(mm) 1986 c.44.
129
Retained apparatus: protection
—a) Not less than 28 days before starting the execution of any works of the type referred to 6.
in sub-paragraph 5(2) that are near to, or will or may affect, any apparatus the removal of which
has not been required by the promoter under sub-paragraph 5(2), the promoter must submit to the
undertaker in question a plan of the works to be executed.
Those works are to be executed only in accordance with the plan submitted under sub-paragraph (1)
(1) and in accordance with such reasonable requirements as may be made in accordance with
sub-paragraph (3) by the undertaker for the alteration or otherwise for the protection of the apparatus,
or for securing access to it; and the undertaker is entitled to watch and inspect the execution of those
works.
Any requirements made by an undertaker under sub-paragraph (2) must be made within a period (2)
of 21 days beginning with the date on which a plan under sub-paragraph (1) is submitted to it.
If an undertaker in accordance with sub-paragraph (2) and in consequence of the works (3)
proposed by the promoter, reasonably requires the removal of any apparatus and gives written notice
to the promoter of that requirement, paragraphs 1 to 5 apply as if the removal of the apparatus had
been required by the promoter under sub-paragraph 5(2).
Nothing in this paragraph precludes the promoter from submitting at any time or from time to (4)
time, but in no case less than 28 days before commencing the execution of any works, a new plan,
instead of the plan previously submitted, and having done so the provisions of this paragraph apply to
and in respect of the new plan.
The promoter is not required to comply with sub-paragraph (1) in a case of emergency but in (5)
that case it must give to the undertaker in question notice as soon as is reasonably practicable and a
plan of those works as soon as reasonably practicable subsequently and must comply with
sub-paragraph (2) in so far as is reasonably practicable in the circumstances.
Cathodic protection testing
Where in the reasonable opinion of the promoter—7.
the authorised development might interfere with the existing cathodic protection forming (a)
part of a pipeline; or
a pipeline might interfere with the proposed or existing cathodic protection forming part of (b)
the authorised development,
the undertaker to whom the pipeline belongs, or who maintains that pipeline, and the promoter
must co-operate in undertaking the tests which the promoter considers reasonably necessary for
ascertaining the nature and extent of such interference and measures for providing or preserving
cathodic protection.
Expenses
—a) Subject to the following provisions of this paragraph, the promoter must repay to an 8.
undertaker the reasonable expenses reasonably incurred by that undertaker in, or in connection
with—
the inspection, removal, alteration or protection of any apparatus; or(a)
the construction of any new apparatus,(b)
which may be required in consequence of the execution of any such works as are required
under this Part of this Schedule.
The value of any apparatus removed under the provisions of this Part of this Schedule is to be (1)
deducted from any sum payable under sub-paragraph (1), that value being calculated after removal.
If in accordance with the provisions of this Part of this Schedule—(2)
130
apparatus of better type, of greater capacity or of greater dimensions is placed in (a)
substitution for existing apparatus of worse type, of smaller capacity or of smaller
dimensions; or
apparatus (whether existing apparatus or apparatus substituted for existing apparatus) is (b)
placed at a depth greater than the depth at which the existing apparatus was situated,
and the placing of apparatus of that type or capacity or of those dimensions or the placing of
apparatus at that depth, as the case may be, is not agreed by the promoter or, in default of
agreement, is not determined by arbitration in accordance with article 51 (arbitration) to be
necessary, then, if such placing involves cost in the construction of works under this Part of this
Schedule exceeding that which would have been involved if the apparatus placed had been of the
existing type, capacity or dimensions, or at the existing depth, as the case may be, the amount which
apart from this sub-paragraph would be payable to the undertaker in question by virtue of
sub-paragraph (1) is to be reduced by the amount of that excess.
For the purposes of sub-paragraph (3)—(3)
an extension of apparatus to a length greater than the length of existing apparatus must not (a)
be treated as a placing of apparatus of greater dimensions than those of the existing
apparatus; and
where the provision of a joint in a pipe or cable is agreed, or is determined to be necessary, (b)
the consequential provision of a jointing chamber or of a manhole must be treated as if it
also had been agreed or had been so determined.
An amount which apart from this sub-paragraph would be payable to an undertaker in respect of (4)
works by virtue of sub-paragraph (1) must, if the works include the placing of apparatus provided in
substitution for apparatus placed more than 7 years and 6 months earlier so as to confer on the
undertaker any financial benefit by deferment of the time for renewal of the apparatus in the ordinary
course, be reduced by the amount which represents that benefit.
Co-operation
Where in consequence of the proposed construction of any of the authorised development, 9.
the promoter requires the removal of apparatus under sub-paragraph 5(2)) or an undertaker
makes requirements for the protection or alteration of apparatus under paragraph 6(2), the
promoter must use its reasonable endeavours to co-ordinate the execution of the works in the
interests of safety and the efficient and economic execution of the authorised development; and
each undertaker must use its reasonable endeavours to co-operate with the promoter for that
purpose.
Arbitration
Any difference or dispute arising between the promoter and an undertaker under this 10.
Schedule is, unless otherwise agreed in writing between the promoter and that undertaker, to be
determined by arbitration in accordance with article 51 (arbitration).
PART 2
FOR THE PROTECTION OF OPERATORS OF ELECTRONIC
COMMUNICATIONS CODE NETWORKS
Effect
For the protection of any operator, the following provisions, unless otherwise agreed in 1.
writing between the promoter (as defined in Part 1 of this Schedule) and the operator, have
effect.
131
Interpretation
In this part of this Schedule—2.
“the 2003 Act” means the Communications Act 2003(nn);
“conduit system” has the same meaning as in the electronic communications code and
references to providing a conduit system is to be construed in accordance with paragraph 1(3A)
of that code;
“electronic communications apparatus” has the same meaning as in the electronic
communications code;
“the electronic communications code” has the same meaning as in Chapter 1 of Part 2 of the 2003
Act(oo);
“electronic communications code network” means—
(a) so much of an electronic communications network or conduit system provided by an
electronic communications code operator as is not excluded from the application of the
electronic communications code by a direction under section 106 of the 2003 Act; and
(b) an electronic communications network which the Secretary of State is providing or
proposing to provide;
“electronic communications code operator” means a person in whose case the electronic
communications code is applied by a direction under section 106 of the 2003 Act; and
“operator” means the operator of an electronic communications code network.
On-street apparatus
The exercise of the powers of article 34 (statutory undertakers) are subject to paragraph 3.
23 of Schedule 2 to the Telecommunication Act 1984(pp) as if the promoter were a “relevant
undertaker” for the purposes of that paragraph.
Enactments and agreements in respect of apparatus in the promoter’s land
Nothing in this Part of this Schedule affects the provisions of any enactment or agreement 4.
regulating the relations between the promoter and an undertaker in respect of any apparatus laid
or erected in land belonging to the promoter on the date on which this Order is made.
Arbitration
Any difference or dispute arising between the promoter and an operator under this Part of 5.
this Schedule is, unless otherwise agreed in writing between the promoter and that operator, to be
referred to and settled by arbitration under article 51 (arbitration).
(nn) 2003 c.21.
(oo) See section 106.
(pp) 1984 c.12.
132
SCHEDULE 12 Article 3
MISCELLANEOUS CONTROLS
PART 1
PUBLIC GENERAL LEGISLATION
Introduction
This Part 1 of this Schedule applies, modifies and excludes statutory provisions which 1.
relate to matters for which provision may be made in this Order.
—a) This Order—2.
fulfils the condition specified in section 28E(3)(a) (duties in relation to sites of special (a)
scientific interest) of the 1981 Act; and
is a permission for the purposes of section 28I (statutory undertakers, etc: duty in relation (b)
to authorising operations) of the 1981 Act,
in respect of an operation or operations referred to in sections 28E and 28I(2) of the 1981 Act
which are carried out pursuant to this Order and, including the requirements in Schedule 3
(requirements), subject to its provisions.
In this paragraph “the 1981 Act” means the Wildlife and Countryside Act 1981(qq).(1)
—a) To the extent provided in sub-paragraph (2) but subject to sub-paragraphs (3) and (4), 3.
the authorised development is to be treated as a major accident hazard pipeline as if carbon
dioxide were a dangerous fluid under Part III (Major Accident Hazard Pipelines) of the
Regulations.
The following Regulations and Schedules of the Regulations apply to the authorised (1)
development—
Regulation 20 (Notification before construction);(a)
Regulation 21 (Notification before use);(b)
Regulation 22 (Notification in other cases);(c)
Regulation 23 (Major accident prevention document);(d)
Regulation 24 (Emergency procedures); (e)
Schedule 4 (Particulars to be Included in Notification Relating to Construction of a (f)
Major Accident Hazard Pipeline); and
Schedule 5 (Particulars to be Notified Before Certain Events Relating to Major Accident (g)
Hazard Pipelines).
The following Regulations and Schedule of the Regulations do not apply to the authorised (2)
development—
Regulation 19 (Emergency shut-down valves);(a)
Regulation 25 (Emergency plans in case of major accidents);(b)
Regulation 26 (Charge by a local authority for a plan); and(c)
Regulation 27 (Transitional provision);(d)
Schedule 3 (Requirements for Emergency Shut-down Valves on Certain Major Accident (e)
Hazard Pipelines Connected to Offshore Installations).
(qq) 1981 c.69.
133
The following sections and schedule of the Health and Safety at Work etc. Act 1974 do not (3)
apply to any breach of Part III (Major Accident Hazard Pipelines) of the Regulations by the
undertaker as a result of the application of Part III (Major Accident Hazard Pipelines) of the
Regulations by this paragraph—
Sections 18 (Authorities responsible for enforcement of the relevant statutory provisions) (a)
to 28 (Restrictions on disclosure of information) (inclusive);
Sections 33 (Offences) to 42 (Power of court to order cause of offence to be remedied or, (b)
in certain cases, forfeiture) (inclusive); and
Schedule 3A (Offences: Mode of Trial and Maximum Penalty).(c)
In this paragraph “the Regulations” mean the Pipeline Safety Regulations 1996(rr) and, subject (4)
to the provisions of this paragraph, “major accident hazard pipeline” and “dangerous fluid” have the
same meanings as those given in the Regulations.
PART 2
LOCAL LEGISLATION
Year Byelaws Short Title
1980 5, 6, 10, 15 Yorkshire Land Drainage Byelaws
1999 4, 7, 9, 11, 14, 15, 23,
24
Selby Area Internal Drainage Board Byelaws
2011 4, 7, 10, 12, 15, 16, 19,
25, 26
Ouse and Humber Drainage Board Byelaws
[●] 4, 7, 9, 11, 14, 15, 24,
25
Beverley and North Holderness Internal Drainage Board
Byelaws
(rr) S.I. 1996/825.
134
SCHEDULE 13 Article 22
MODIFICATION OF COMPENSATION AND COMPULSORY
PURCHASE ENACTMENTS FOR CREATION OF NEW RIGHTS
Compensation enactments
The enactments for the time being in force with respect to compensation for the compulsory 1.
purchase of land apply, with the necessary modifications as respects compensation, in the case of
a compulsory acquisition under this Order of a right by the creation of a new right as they apply
as respects compensation on the compulsory purchase of land and interests in land.
—a) Without prejudice to the generality of paragraph 1, the Land Compensation Act 2.
1973(ss) has effect subject to the modifications set out in sub-paragraphs (2) and (3).
In section 44(1) (compensation for injurious affection), as it applies to compensation for (1)
injurious affection under section 7 of the 1965 Act as substituted by paragraph 4—
for the words “land is acquired or taken” there are substituted the words “a right or (a)
restrictive covenant over land is purchased from or imposed on”; and
for the words “acquired or taken from him” there are substituted the words “over which the (b)
right is exercisable or the restrictive covenant enforceable”.
In section 58(1) (determination of material detriment where part of house etc. proposed for (2)
compulsory acquisition), as it applies to determinations under section 8 of the 1965 Act as substituted
by paragraph 5—
for the word “part” in paragraphs (a) and (b) there are substituted the words “a right over (a)
or restrictive covenant affecting land consisting”;
for the word “severance” there is substituted the words “right or restrictive covenant over (b)
or affecting the whole of the house, building or manufactory or of the house and the park or
garden”;
for the words “part proposed” there are substituted the words “right or restrictive covenant (c)
proposed”; and
for the words “part is” there are substituted the words “right or restrictive covenant is”.(d)
Application of the 1965 Act
—a) The 1965 Act has effect with the modifications necessary to make it apply to the 3.
compulsory acquisition under this Order of a right by the creation of a new right, or to the
imposition under this Order of a restrictive covenant, as it applies to the compulsory acquisition
under this Order of land, so that, in appropriate contexts, references in that Act to land are read
(according to the requirements of the particular context) as referring to, or as including
references to—
the right acquired or to be acquired; or(a)
the land over which the right is or is to be exercisable.(b)
Without prejudice to the generality of sub-paragraph (1), Part 1 of the 1965 Act applies in (1)
relation to the compulsory acquisition under this Order of a right by the creation of a new right with
the modifications specified in the following provisions of this Schedule.
For section 7 of the 1965 Act (measure of compensation) there is substituted the following 4.
section—
“7. In assessing the compensation to be paid by the acquiring authority under this Act,
regard must be had not only to the extent (if any) to which the value of the land over which
(ss) 1973 c. 26.
135
the right is to be acquired or the restrictive covenant is to be imposed is depreciated by the
acquisition of the right or the imposition of the covenant but also to the damage (if any) to be
sustained by the owner of the land by reason of its severance from other land of the owner, or
injuriously affecting that other land by the exercise of the powers conferred by this or the
special Act.”.
The following provisions of the 1965 Act (which state the effect of a deed poll executed in 5.
various circumstances where there is no conveyance by persons with interests in the land), that is
to say—
section 9(4) (failure by owners to convey);(a)
paragraph 10(3) of Schedule 1 (owners under incapacity);(b)
paragraph 2(3) of Schedule 2 (absent and untraced owners); and(c)
paragraphs 2(3) and 7(2) of Schedule 4 (common land),(d)
are modified to secure that, as against persons with interests in the land which are expressed to be
overridden by the deed, the right which is to be compulsorily acquired or the restrictive covenant
which is to be imposed is vested absolutely in the acquiring authority.
Section 11 of the 1965 Act (powers of entry) is modified to secure that, as from the date on 6.
which the acquiring authority has served notice to treat in respect of any right, it has power,
exercisable in equivalent circumstances and subject to equivalent conditions, to enter for the
purpose of exercising that right or enforcing that restrictive covenant (which is deemed for this
purpose to have been created on the date of service of the notice); and sections 12 (penalty for
unauthorised entry) and 13 (entry on warrant in the event of obstruction) of the 1965 Act are
modified correspondingly.
Section 20 of the 1965 Act (protection for interests of tenants at will, etc.) applies with the 7.
modifications necessary to secure that persons with such interests in land as are mentioned in that
section are compensated in a manner corresponding to that in which they would be compensated
on a compulsory acquisition under this Order of that land, but taking into account only the extent
(if any) of such interference with such an interest as is actually caused, or likely to be caused, by
the exercise of the right or the enforcement of the restrictive covenant in question.
Section 22 of the 1965 Act (protection of acquiring authority’s possession where by 8.
inadvertence an estate, right or interest has not been got in) is modified as to enable the
acquiring authority, in circumstances corresponding to those referred to in that section, to
continue to be entitled to exercise the right acquired, subject to compliance with that section as
respects compensation.
136
SCHEDULE 14 Article 53
PROCEDURE IN RELATION TO CERTAIN APPROVALS ETC.
Determination of applications for specified consents
—a) Where an application has been made to the discharging authority for any specified 1.
consent, the discharging authority must give notice to the undertaker of its decision on the
application within a period of 8 weeks (or in respect of a COPA application 28 days) beginning
with—
where no further information is requested under sub-paragraph (2), the day immediately (a)
following that on which the application is received by the discharging authority;
where further information is requested under sub-paragraph (2), the day immediately (b)
following that on which further information has been supplied by the undertaker; or
such longer period as may be agreed in writing by the undertaker and the discharging (c)
authority.
Where an application has been made under sub-paragraph (1) the discharging authority may (2)
request such reasonable further information from the undertaker as it considers is necessary to enable
it to consider the application.
If the discharging authority considers further information is necessary and this Order does not (3)
specify that consultation with a consultee is required, the discharging authority must, within 7
business days of receipt of the application, notify the undertaker in writing specifying the further
information required.
If a provision of this Order relating to a specified consent specifies that consultation with a (4)
consultee is required, the discharging authority must issue the consultation to the consultee within 1
business day of receipt of the application and must notify the undertaker in writing specifying any
further information requested by the consultee within 1 business day of receipt of such a request and
in any event within 21 business days of receipt of the application.
If the discharging authority does not give the notification mentioned in sub-paragraph (3) or (4) (5)
it is deemed to have sufficient information to consider the application and is not thereafter entitled to
request further information without the prior agreement of the undertaker.
Fees
Where an application is made to a relevant planning authority for any consent, agreement or (6)
approval required by a requirement listed in Schedule 3 (requirements) to this Order, a fee of £97 (or
such other fee as may be prescribed in regulations made pursuant to sections 303 (fees for planning
applications etc.) and 333(2A) (regulations and orders) of the 1990 Act for the confirmation by a
local planning authority of compliance with a condition attached to a planning permission) must be
paid to the discharging authority.
Any fee paid under this Schedule must be refunded to the undertaker within 4 weeks of—(7)
the application being rejected as invalidly made; or(a)
the discharging authority failing to determine the application within 8 weeks from the date (b)
on which it is received,
unless within that period the undertaker agrees in writing that the fee may be retained by the
discharging authority and credited in respect of a future application.
Appeals
—a) The undertaker may appeal if—2.
the discharging authority refuses an application for any specified consent or grants it (a)
subject to conditions (or in respect of a COPA application limits or qualifies it in any way);
137
the discharging authority does not give notice of its decision to the undertaker within the (b)
period specified in sub-paragraph 1(1);
having received a request for further information under paragraph 1(3) the undertaker (c)
considers that either the whole or part of the specified information requested by the
discharging authority is not necessary for consideration of the application;
having received any further information requested, the discharging authority notifies the (d)
undertaker that the information provided is inadequate and requests additional information
which the undertaker considers is not necessary for consideration of the application; or
the discharging authority serves a COPA notice.(e)
The procedure for appeals is as follows—(1)
the undertaker must submit to the Secretary of State a copy of the application submitted to (a)
the discharging authority (or where a COPA notice has been served a copy of that notice)
and any supporting documents which the undertaker may wish to provide (“the appeal
documents”);
the undertaker must on the same day provide copies of the appeal documents to the (b)
discharging authority and (if applicable) the consultee (if applicable);
as soon as is practicable after receiving the appeals documents the Secretary of State must (c)
appoint a person to determine the appeal (“the appointed person”) and notify the appeal
parties of the identity of the appointed person and the address to which all correspondence
for the appointed person should be sent;
the discharging authority and (if applicable) the consultee (if applicable) may submit any (d)
written representations in respect of the appeal to the appointed person within 10 business
days beginning with the first day immediately following the date on which the appeal
parties are notified of the appointment of the appointed person and must ensure that copies
of their written representations are sent to each other and to the undertaker on the day on
which they are submitted to the appointed person;
the appeal parties may make any counter-submissions to the appointed person within 10 (e)
business days beginning with the first day immediately following the date of receipt of
written representations pursuant to paragraph (d) above; and
the appointed person must make a decision and notify it to the appeal parties, with reasons, (f)
as soon as reasonably practicable.
If the appointed person considers that further information is necessary to consider the appeal, the (2)
appointed person must as soon as practicable notify the appeal parties in writing specifying the further
information required, the appeal party from whom the information is sought, and the date by which the
information must be submitted.
Any further information required pursuant to sub-paragraph (3) must be provided by the party (3)
from whom the information is sought to the appointed person and to other appeal parties by the date
specified by the appointed person.
The appeal parties may submit written representations to the appointed person concerning (4)
matters contained in the further information.
Any such representations must be submitted to the appointed person and made available to all (5)
appeal parties within 10 business days of the date mentioned in sub-paragraph (3).
Outcome of appeals
—a) On an appeal under paragraph 2, the appointed person may—3.
allow or dismiss the appeal; or(a)
reverse or vary any part of the decision of the discharging authority (whether the appeal (b)
relates to that part of it or not),
and may deal with the application as if it had been made to the appointed person in the first instance.
138
The appointed person may proceed to a decision on an appeal taking into account only such (1)
written representations as have been sent within the time limits prescribed or set by the appointed
person under this paragraph.
The appointed person may proceed to a decision even though no written representations have (2)
been made within those time limits if it appears to the appointed person that there is sufficient material
to enable a decision to be made on the merits of the case.
The decision of the appointed person on an appeal is final and binding on the parties, and a court (3)
may entertain proceedings for questioning the decision only if the proceedings are brought by a claim
for judicial review within 6 weeks of the date of the decision.
Any approval given by the appointed person pursuant to this Schedule is deemed to be an (4)
approval for the purposes of this Order and any other enactment which required the specified consent
as if it had been given by the discharging authority.
The discharging authority may confirm any determination given by the appointed person in (5)
identical form in writing but a failure to give such confirmation (or a failure to give it in identical
form) does not affect or invalidate the effect of the appointed person’s determination.
Except where a direction is given pursuant to sub-paragraph 8 requiring the costs of the (6)
appointed person to be paid by the discharging authority, the reasonable costs of the appointed person
must be met by the undertaker.
On application by the discharging authority or the undertaker, the appointed person may give (7)
directions as to the costs of the appeal parties and as to the parties by whom the costs of the appeal are
to be paid.
In considering whether to make any such direction and the terms on which it is made, the (8)
appointed person must have regard to Communities and Local Government Circular 03/2009 or any
circular or guidance which may from time to time replace it.
Where the undertaker appeals under paragraph 2—(9)
this Schedule applies instead of article 51 (arbitration); and(a)
in respect of any specified consent required pursuant to sections 54 to 106 of the 1991 act, (b)
this Schedule applies instead of section 99 (arbitration) of that Act;
in respect of any COPA notice or COPA application this Schedule applies instead of (c)
sections 60(7) or 61(7) of the 1974 Act.
Interpretation of this Schedule
In this Schedule—4.
“1974 Act” means the Control of Pollution Act 1974(tt);
“the appeal parties” means the discharging authority, the consultee and the undertaker;
“business day” means Monday to Friday excluding bank holidays;
“consultee” means any body named in a provision of this Order relating to a specified consent
which is the subject of an appeal as a body to be consulted by the discharging authority in
determining that specified consent;
“COPA application” means an application made pursuant to section 61 (prior consent for work
on construction sites) of the 1974 Act;
“COPA notice” means a notice served pursuant to section 60 (control of noise on construction
sites) of the 1974 Act;
“discharging authority” means the body responsible for determining whether a specified consent
should be given or the local authority in the exercise of functions set out in sections 60 or 61 of
the 1974 Act;
“specified consent” means any—
agreement, certificate, consent, permission, expression of satisfaction or other approval (a)
required by—
(tt) 1974 c.40.
139
a requirement listed in Schedule 3 (requirements) of this Order;(i)
a document referred to in any requirement listed in Schedule 3 of this Order; (ii)
a licence condition in the deemed marine licence listed in Schedule 10 (deemed (iii)
marine licence) under Part 4 (marine licensing) of the Marine and Coastal Access
Act 2009); or
article 44(3)(b) (felling or lopping of trees or shrubs); or(iv)
agreement, certificate, consent, permission, expression of satisfaction or other approval of (b)
the highway authority, street authority (where it is also the highway authority for the same
area) or traffic authority required pursuant to articles—
10 (street works) (including pursuant to sections 54 to 106 of the 1991 Act as (i)
applied by article 11(3));
11 (power to alter layout, etc. of streets);(ii)
12 (construction and maintenance of new, altered or diverted streets);(iii)
14 (temporary stopping up of streets and public rights of way);(iv)
13 (permanent stopping up of streets);(v)
17 (traffic regulation); or(vi)
21 (authority to survey and investigate the land); or(vii)
a consent pursuant to a COPA application.(c)
140
EXPLANATORY NOTE
(This note is not part of the Order)
The Order
This Order authorises National Grid Carbon Limited (referred to as “the undertaker”) to construct
and operate a pipeline transportation network and associated infrastructure to support the provision
of carbon capture and storage technology in the Yorkshire and Humber region.
The Order permits the undertaker to acquire, compulsorily or by agreement, land and rights in
land and to use land for this purpose. The Order also makes provision in connection with the
maintenance of the network.
A copy of the Order plans and the book of reference mentioned in this Order and certified in
accordance with article 49 of this Order (certification of plans, etc.) may be inspected free of
charge during working hours at the [Planning Reception Desk], of East Riding of Yorkshire Council
[insert address] and Selby District Council [insert address].
141
S T A T U T O R Y I N S T R U M E N T S
201[●] No. [●]
INFRASTRUCTURE PLANNING
ENERGY
The [Draft] Yorkshire and Humber (Carbon Capture and
Storage Cross Country Pipeline) Order 201[●]
BERWIN LEIGHTON PAISNER LLP
Adelaide House
London Bridge
London EC4R 9HA
Solicitors
142