experience with silicon detectors and module construction
TRANSCRIPT
13./4. July 2008 Super-Belle proto-collaboration meeting
Experience with silicon microstrip detectors and module
construction at HEPHY Vienna
Thomas BergauerInstitute for High Energy Physics (HEPHY)
of theAustrian Academy of Sciences
23./4. July 2008 Super-Belle proto-collaboration meeting
Contents
• Introduction• Silicon microstrip sensors
– Sensor design– Sensor characterization– Process monitoring– Logistics for mass production
• Module construction– Module assembly– Bonding– Testing
• Test beam experience– One example of last test beam
33./4. July 2008 Super-Belle proto-collaboration meeting
Introduction• Austrian Academy of
Sciences– Largest non-university research
organization in Austria– 70 institutes, commissions and
research units with ~1100 staff
• Institute of High Energy Physics (HEPHY)– Located in Vienna– Founded in 1966 as the
Austrian contribution to CERN– 55 persons staff plus some
students
Aus
trian
Aca
dem
y of
Sci
ence
sM
ain
Bui
ldin
gIn
stitu
te o
f Hig
h E
nerg
y P
hysi
cs
43./4. July 2008 Super-Belle proto-collaboration meeting
Institute of High Energy Physics
Participation in Experiments (Hardware & Analysis):
53./4. July 2008 Super-Belle proto-collaboration meeting
Institute of High Energy PhysicsOrganizational structure:
• Projects– BELLE Experiment (Christoph Schwanda)– CMS Analyse (Wolfgang Adam)– CMS Inner Tracker (Josef Hrubec)– CMS Trigger (Claudia-Elisabeth Wulz)– DELPHI (Wolfgang Adam)– International Linear Collider (Winfried Mitaroff)– Theory: Supersymmetry (Helmut Eberl)– Public Relations and Outreach (Wolfgang Lucha)– VCI Conference (Manfred Krammer)
• Departments– Algorithm- and Software Development (Rudolf Frühwirth)– Electronics 1 (Anton Taurok)– Electronics 2 (Markus Friedl)– Semiconductor Detectors (Thomas Bergauer)– Computing (Gerhard Walzel)– Mechanical Workshop (Anton Taurok)
63./4. July 2008 Super-Belle proto-collaboration meeting
History of Semiconductor Detector Research at HEPHY Vienna
• HEPHY Vienna participated in construction of– DELPHI Si Vertex Detector– CMS Tracker
• Moreover, we participated in different CERN R&D collaborations– RD20– RD42 (Diamond detectors)
• Therefore we have large expertise with silicon detectors and their mass production
• However: Expertise is limited to strip detectors (no pixel sensors)
73./4. July 2008 Super-Belle proto-collaboration meeting
Available manpower
• Manpower available in Semiconductor Group:– 2 FTE scientists– 1,5 FTE students– 1,5 FTE technicians
• Long term contracts with technicians have shown to be an advantage (e.g. during CMS module construction:– huge effort necessary in short time– other institutes hired people on short term basis (“hire & fire”)– Disadvantage: lack of experience caused higher failure rate)
Part of HEPHY semiconductor group staff
83./4. July 2008 Super-Belle proto-collaboration meeting
Sensor Design
• ICStation from Mentor Graphics available as Design tool
• Design is not drawn but actually “programmed”– using simple programming
language (C like)
• Therefore, it is easy to changeany parameter and re-createthe full sensor within minutes– e.g. width of metal overhang
93./4. July 2008 Super-Belle proto-collaboration meeting
Design processed at fab
• Design of test structures (based on CMS Design) was successfully fabricated by Institute for Electron Technology (Warsaw, Poland)
• They have experience with SOI and chip production, but not with fully depleted devices yet.
• Goals:– Develop improved test structures
based on CMS– Develop sensor with dual metal layer
to test in-sensor routing
• Three 4” wafers received from first processing batch, results look promising
103./4. July 2008 Super-Belle proto-collaboration meeting
Characterization = electric measurements• Performed in HEPHY cleanroomMeasurement procedure:• Sensor held by vacuum on motorized table
– Motorized table is movable in XYZ• First set of Needles are used to connect Bias
and Guard ring– Fixed in respect to the sensor
• Second set of Needles are contacting:– DC Pad (p- or n- implant of strip)– AC Pad (Aluminum strip)– By movement of the table each strip can be
contacted to these needles– Full measurement (all strips) takes approx.3 h
per sensor
• 2 „global“ measurements per detector– IV- Curve (Dark current, Breakthrough voltage)– CV- Curve (Detector capacitance, „full
depletion“-voltage)
14
Sensors Characterization
113./4. July 2008 Super-Belle proto-collaboration meeting
4 measurements per strip:
11
• Open Strip:
• Shorted Strip:
Dielectric current:
Coupling capacitance:
Poly-Silicium Bias-resistor:
Single strip current:
• “Pinhole” (short between implant and metal):
Characterization: Strip-by-Strip
123./4. July 2008 Super-Belle proto-collaboration meeting
Leakage Current at 450VSpecification: max 10µA
Full Depletion VoltageSpecification: 100 V – 300 V
Mean: 576 nA
Mean: 1865 nA
Characterization: IV and CV Results
133./4. July 2008 Super-Belle proto-collaboration meeting
Number of bad strips per sensor (pinhole, bad polyresistor, Al short,broken Al, open implant, leaky strip,….)
Number of Bad StripsSpecification: max 1% of 512/768 Channels
Percentage of bad strips: 0.018% 0.305%
Mean: 0.1 strip/sensor Mean: 1.9 strip/sensor
Characterization: Strip-Scan Results
143./4. July 2008 Super-Belle proto-collaboration meeting
TS-CAP
sheet
GCD
CAP-TS-AC CAP-TS-AC
baby diode
MOS 1
MOS 2
Process Monitoring on Test Structures
• What is Process monitoring?– Each wafer hosts additional test
structures around main detector– “standard” set of test structures is called
“half moon” (because of its shape)– Test structures used to determine one
parameter per structure– Assuming that sensor and test structures
behave identically
• Worked extremely well during CMS sensor production
– Several problems have been identified during CMS quality assurance tests
– Some parameters are not accessible on main detector (e.g. flatband voltage of MOS), but important for proper operation
153./4. July 2008 Super-Belle proto-collaboration meeting
Test Structures Measurements• TS-CAP:
– Coupling capacitance CAC to determine oxide thickness
– IV-Curve: breakthrough voltage of oxide
• Sheet:– Aluminium resistivity– p+-impant resistivity– Polysilicon resistivity
• GCD:– Gate Controlled Diode– IV-Curve to determine surface
current Isurface– Characterize Si-SiO2 interface
• CAP-TS-AC:– Inter-strip capacitance Cint
• Baby-Sensor:– IV-Curve for dark current– Bulk breakthrough voltage
• CAP-TS-DC:– Inter-strip Resistance Rint
• Diode:– CV-Curve to determine depletion
voltage Vdepletion– Calculate resistivity of silicon bulk
• MOS:– CV-Curve to extract flatband voltage
Vflatband to characterize fixed oxide charges
– For thick interstrip oxide (MOS1)– For thin readout oxide (MOS2)
TS-CAP
sheetGCD
CAP-TS-AC CAP-TS-ACbaby diode
MOS 1
MOS 2
163./4. July 2008 Super-Belle proto-collaboration meeting
Test structures Measurement Setup
• Probe-card with 40 needles contacts all pads of test structures in parallel
– Half moon fixed by vacuum– Micropositioner used for Alignment– In light-tight box with humidity and
temperature control
• Instruments– Source Measurement Unit (SMU)– Voltage Source– LCR-Meter (Capacitance)
• Heart of the system: Crosspointswitching box, used to switch instruments to different needles
• Labview and GPIB used to control instruments and switching system
173./4. July 2008 Super-Belle proto-collaboration meeting
Process Monitoring Setup
183./4. July 2008 Super-Belle proto-collaboration meeting
Yellow Fields:Limits and cuts for qualification
Blue Fields:Obtained resultsextracted from graphby linear fits (red/green lines)
Process Monitoring DAQ Software
Fully automatic measurement procedure takes approx. 30min per half moon to produce this:
193./4. July 2008 Super-Belle proto-collaboration meeting
Passed/Not Passed Lights
• After all measurements finished
• Window pops up• One light for each test
– Green: within limits– Red: out of limits
• Allows immediate judgment about quality
• Pressing “OK” button writes data directly into central database (CMS used Oracle)
20
Process Monitoring Results (1)
• Different problems of several sensor batches (production lots) have been discovered during CMS sensor QA program, e.g.:– Too high flatband voltage– Too high poly-Si resistor– Too high Al sheet resistivity– Too low inter-strip resistance– Too high bulk resistivity
• Most of the issues have been solved by the vendors after an intervention from us
3./4. July 2008 Super-Belle proto-collaboration meeting
3.5 kOhm
21
Process Monitoring Results (2)
• In fairness, I have to say that the majority of monitored parameters were pretty stable vs. time
• For example:– Coupling capacitance (top)– Breakthrough of dielectric
(bottom)
3./4. July 2008 Super-Belle proto-collaboration meeting
Specification requires > 100 V
22
Long term/Coldbox• Long term IV setup for sensor
stability tests– Used to measure dark currents of
10 sensors in parallel vs. time– Discovered corrosion of aluminum
lines on sensor– Needs air moisture and HV– Caused by Potassium
contamination of sensor production line which caused production of (non-conduction) alumina (Al2O3)
• Coldbox for aging studies– Driven by Peltier elements– Discovered issue with conductive
glue on sensor backside(Solution: Backplane bonding)
3./4. July 2008 Super-Belle proto-collaboration meeting
233./4. July 2008 Super-Belle proto-collaboration meeting
• For large scale production, an relational database system is necessary to– Keep track of each object– Store measurement results
centrally• Each action (shipment,
assembly, integration, test, repair) is recorded
• CMS Tracker Construction DB uses Oracle to manage >200.000 objects– Sensors, hybrids, modules– Cables (with cabling info)
Logistics for mass production (1)
243./4. July 2008 Super-Belle proto-collaboration meeting
Database can be used to• Store full history of each
component– Allowed us to produce nice
statistics, e.g. distribution of failures of modules (right)
• Plot histograms of measurement results– E.g. full depletion voltage of
silicon sensors as output of process monitoring tests
The logistics effort in an distributed sensor QA and module production must not be under-estimated!
Logistics for mass production (2)
25
Module Construction
• HEPHY Vienna built 650 out of 16.000 silicon detector modules for the CMS Tracker– Ring 2 of Tracker Endcaps– Two geometries: R2N and
R2S
• Production Steps:– Assembly: gluing of hybrid
and sensor to CF frame– Wire bonding– Testing
3./4. July 2008 Super-Belle proto-collaboration meeting
263./4. July 2008 Super-Belle proto-collaboration meeting
Module Assembly• Module assembly for CMS was
manual process:– CF frame was fixed with vacuum
support– Glue dispensed manually by
operator– Sensor put onto frame using
gallows– Glue curing– Using 3D coordinate
measurement machine (Mitutoyo) for measurement of assembly precision (<10 micron)
• Throughput: 4 modules per day
273./4. July 2008 Super-Belle proto-collaboration meeting
Wire bonding• Fully automatic large-area wire
bonding machine used for bonding of CMS modules– Model Delvotec 6400– Bond rate 5Hz– Takes 10 minutes for ~800 bonds
per module (if everything works well)
• Bond pull test machine– To verify bond quality– Pull strength: ~8g
• Manual wire bonding machine Kulicke & Soffa– Enhanced by motorized XY-table
for “semi-automatic” use– Bond rate 0.2 Hz– Used for quick single bonds
28
Testing/Repair• Intensive testing of modules
after assembly and bonding using dedicated setup
• Thermal Cycle to speed up aging process– Cold box
• Module repair:– Re-bonding of “touched
bonds”– Disassembly of sensor from
module with faulty hybrid– Mostly time-consuming,
manual work
3./4. July 2008 Super-Belle proto-collaboration meeting
29
Test beams
Last 5 slides
3./4. July 2008 Super-Belle proto-collaboration meeting
30
Test BeamsGoal of last testbeam (June 08):
evaluate the best strip geometry of silicon strip sensors with 50 micron pitch to determine the highest possible spatial resolution
• Using CERN’s SPS beam (120 GeV pions) [low multiple scatt.]
• Using EUDET pixel telescope as reference
• For this purpose we were using a dedicated mini sensor with different zones, each with a different strip geometry:– Different strip widths– 0, 1 or 2 intermediate strips
TESTAC:
SiLC Sensor:
31
Test Beam: SensorsDUT sensors have been intensively tested in Vienna, e.g.:• IV curves on all sensors• CV curves to determine full depletion voltages
– approx. 60V
Measurement of the inter-strip capacitance reveal different values for each zone:• Capacitance scales linearly with strip width• Different offset for region with one or two intermediate strips
0 100 200 300 400 500 600 700 800
100n
1µ
10µ
curre
nt
voltage
01 02 03 04 05 06 07 10 12 13 17 19 20 21 23 24 26 27 28 29 30 31 32 34 35 36 37 38
32
Test Beam: Modules
9 modules have been built using•Multi-geometry test sensor
•APV25 readout chip
•SVD3 readout system developed by Markus Friedl et al. in Vienna
Module Front: back:
Modules have been screwed together to form a kind of “telescope” for tracking purpose
33
Test beam results (1)
Measurement plan:• High-statistics run covering each zone
– Must have enough tracks passing through each zone
• HV scan• Angle scan
Low level data processing already done using Vienna’s testbeam software (electronics group)
• Pedestal subtraction• Common mode correction• Hit finding, Clustering• Peak time reconstruction
3./4. July 2008 Super-Belle proto-collaboration meeting
34
Test beam results (2)
3./4. July 2008 Super-Belle proto-collaboration meeting
Width -> +
Analysis started very recently using both:
• EUDET LCIO Analysis (Marlin), because telescope data is already in this format
• standard analysis chain (software developed by Prague colleagues), comprising – hit reconstruction– track identification– alignment and track fitting – calculation of detector
residuals and resolution
35
Summary
• Semiconductor group at HEPHY Vienna completed CMS Tracker construction, testing, installation and commissioning recently
• Large experience with sensor design, electric characterization; module assembly, bonding, testing, repair, logistics
• Schedule:– CMS upgrade:
small (pixel only) 2013, large (full Tracker) 2018– ILC: postponed to later future
• Therefore, we are interested in a mid-term project – Super-Belle would fit perfectly ;-)
3./4. July 2008 Super-Belle proto-collaboration meeting
36
The End.
(Backup slides follow)
3./4. July 2008 Super-Belle proto-collaboration meeting
37
Test Beam: Zone Description
3./4. July 2008 Super-Belle proto-collaboration meeting