25
Experience with short notice (SNRI) and unannounced (UI) inspections in Sweden Elisabeth André Turlind And Göran Dahlin Section of Nuclear Non-Proliferation Swedish Radiation Safety Authority (SSM)

Upload: others

Post on 30-Aug-2019

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Experience with short notice (SNRI) and unannounced (UI ... · SO informs SSM of inspector arrival SSM contacts IAEA HQ for confirmation Elisabeth André Turlind and Göran Dahlin,

Experience with short notice (SNRI) and unannounced (UI) inspections in Sweden

Elisabeth André TurlindAnd

Göran DahlinSection of Nuclear Non-Proliferation

Swedish Radiation Safety Authority (SSM)

Page 2: Experience with short notice (SNRI) and unannounced (UI ... · SO informs SSM of inspector arrival SSM contacts IAEA HQ for confirmation Elisabeth André Turlind and Göran Dahlin,

ContentsSwedish facilities and fuel cycleAdditional Protocol in SwedenIntegrated Safeguards in SwedenExperiencesSummaryElisabeth André Turlind and Göran Dahlin, SSM, ESARDA/INMM Oct 20112

Page 3: Experience with short notice (SNRI) and unannounced (UI ... · SO informs SSM of inspector arrival SSM contacts IAEA HQ for confirmation Elisabeth André Turlind and Göran Dahlin,

Swedish RadiationSafety Authority,SSM.

270 employee,9 in safeguards.

DG Ministry of Environment

Elisabeth André Turlind and Göran Dahlin, SSM, ESARDA/INMM Oct 20113

Page 4: Experience with short notice (SNRI) and unannounced (UI ... · SO informs SSM of inspector arrival SSM contacts IAEA HQ for confirmation Elisabeth André Turlind and Göran Dahlin,

Facilities and Material in Sweden10 NPP (LWR)1 central intermediate storage for spent fuel, (25 000 FA), Clab

1 LEU Fuel fabrication plant (900 t/year), Westinghouse1 research facility, Studsvik1 uranium recovery facility, Ranstad

Elisabeth André Turlind and Göran Dahlin, SSM, ESARDA/INMM Oct 20114

Page 5: Experience with short notice (SNRI) and unannounced (UI ... · SO informs SSM of inspector arrival SSM contacts IAEA HQ for confirmation Elisabeth André Turlind and Göran Dahlin,

Facilities and Material (cont.)~25 minor facilities1 control rod fabrication facility, Westinghouse1 Zr-tube fabrication facility, Sandviken2 closed down NPP, Barsebäck 1-2Encapsulation plant, Clink ~year 2027Geological repository, Forsmark ~year 2027Depleted, Natural, LEU, HEU (~1 kg),Pu (~3 kg) and Th (~2,5 t)Elisabeth André Turlind and Göran Dahlin, SSM, ESARDA/INMM Oct 20115

Page 6: Experience with short notice (SNRI) and unannounced (UI ... · SO informs SSM of inspector arrival SSM contacts IAEA HQ for confirmation Elisabeth André Turlind and Göran Dahlin,

Elisabeth André Turlind and Göran Dahlin, SSM, ESARDA/INMM Oct 20116

Page 7: Experience with short notice (SNRI) and unannounced (UI ... · SO informs SSM of inspector arrival SSM contacts IAEA HQ for confirmation Elisabeth André Turlind and Göran Dahlin,

Fuel cycle in Sweden

Elisabeth André Turlind and Göran Dahlin, SSM, ESARDA/INMM Oct 20117

Import UF6, FA

Export FA, rodsControl rodsZr-tubesGraphite

FINAL REPOSITORY

Page 8: Experience with short notice (SNRI) and unannounced (UI ... · SO informs SSM of inspector arrival SSM contacts IAEA HQ for confirmation Elisabeth André Turlind and Göran Dahlin,

Safeguards history in Sweden1972 Trilateral agreement IAEA – US – Sweden

-May 1972 first IAEA inspection in Sweden

1974 SKI responsible for Swedish SSAC1975 IAEA Agreement (INFCIRC/234)1995 Sweden joins EU – Euratom Treaty

IAEA Agreement INFCIRC/234 => INFCIRC/193

1994-6 Field trials under 93+2

Elisabeth André Turlind and Göran Dahlin, SSM, ESARDA/INMM Oct 20118

Page 9: Experience with short notice (SNRI) and unannounced (UI ... · SO informs SSM of inspector arrival SSM contacts IAEA HQ for confirmation Elisabeth André Turlind and Göran Dahlin,

Elisabeth André Turlind and Göran Dahlin, SSM, ESARDA/INMM Oct 2011

Sweden during the SSS and 93+2Increased use of SSAC– Inspections by national inspectors– Exchange of surveillance media– Common review at SKI HQ with IAEA inspectors

Expanded declarationIncreased information flow– Weekly ICRs– Weekly production plans for the FFP

Unannounced inspectionsRemote monitoringEnvironmental sampling

9

Page 10: Experience with short notice (SNRI) and unannounced (UI ... · SO informs SSM of inspector arrival SSM contacts IAEA HQ for confirmation Elisabeth André Turlind and Göran Dahlin,

Safeguards history (cont.)

1998 The Additional Protocol (AP) signed2004 AP enters into force2005 The new Euratom safeguards regulation2008 New SKI regulation (SKIFS 2008:1, now SSMFS 2008:3)2009 Integrated Safeguards (IS) in Sweden

Elisabeth André Turlind and Göran Dahlin, SSM, ESARDA/INMM Oct 201110

Page 11: Experience with short notice (SNRI) and unannounced (UI ... · SO informs SSM of inspector arrival SSM contacts IAEA HQ for confirmation Elisabeth André Turlind and Göran Dahlin,

IS approach in Sweden

NPP - SNRI with 24 h notice (at least 2-3 per year for 10 NPP tot)- PIV (pre- and post-PIV)

Clab and Research facility (Studsvik)- UI (at least 1 per facility and year)- PIV

Elisabeth André Turlind and Göran Dahlin, SSM, ESARDA/INMM Oct 201111

Page 12: Experience with short notice (SNRI) and unannounced (UI ... · SO informs SSM of inspector arrival SSM contacts IAEA HQ for confirmation Elisabeth André Turlind and Göran Dahlin,

IS appraoch (cont.)

LEU Fuel Fabrication facility (Westinghouse)- SNRI with 24 h notice (at least 1 per year ,48 h retention

time)- COM at least 3 SNRI per year- Mailbox system- PIV

Elisabeth André Turlind and Göran Dahlin, SSM, ESARDA/INMM Oct 201112

Page 13: Experience with short notice (SNRI) and unannounced (UI ... · SO informs SSM of inspector arrival SSM contacts IAEA HQ for confirmation Elisabeth André Turlind and Göran Dahlin,

IS approach (cont.)

Barsebäck and Uranium recovery facility (Ranstad)- PIV (DIV)

Minor facilities- 1 PIV (at 1 facility every 4-6 years)

Also:CA when necessary – 2 h or 24 h notice

Elisabeth André Turlind and Göran Dahlin, SSM, ESARDA/INMM Oct 201113

Page 14: Experience with short notice (SNRI) and unannounced (UI ... · SO informs SSM of inspector arrival SSM contacts IAEA HQ for confirmation Elisabeth André Turlind and Göran Dahlin,

Preparations for ISMeetings with IAEA and European CommissionInformation to the facilitiesMeeting with the Ministry of EnvironmentSetting up the SSM organisation

Elisabeth André Turlind and Göran Dahlin, SSM, ESARDA/INMM Oct 201114

Page 15: Experience with short notice (SNRI) and unannounced (UI ... · SO informs SSM of inspector arrival SSM contacts IAEA HQ for confirmation Elisabeth André Turlind and Göran Dahlin,

IS organisationSSM participates in all IAEA inspections/CAsSSM Point of ContactSSM Site representative– SSM receives all information necessesary– SSM compiles the information in AP format– SSM forwards declarations to IAEA and/or EU-COM

Elisabeth André Turlind and Göran Dahlin, SSM, ESARDA/INMM Oct 201115

Page 16: Experience with short notice (SNRI) and unannounced (UI ... · SO informs SSM of inspector arrival SSM contacts IAEA HQ for confirmation Elisabeth André Turlind and Göran Dahlin,

Elisabeth André Turlind and Göran Dahlin, SSM, ESARDA/INMM Oct 2011

IS organisation at SSMOne communication line for all inspection/CA noticesNotice received in two mobiles, a dedicated email address and a faxOne inspector on alert every week

16

Page 17: Experience with short notice (SNRI) and unannounced (UI ... · SO informs SSM of inspector arrival SSM contacts IAEA HQ for confirmation Elisabeth André Turlind and Göran Dahlin,

IS organisation for UI at Clab and Studsvik

IAEA inspectors informs IAEA HQ before entering the security gateIAEA HQ sends urgent fax to SSMIAEA arrives at security gateGuard checks IAEA documentation and contacts the facility Safeguard Office, SOSO informs SSM of inspector arrival

SSM contacts IAEA HQ for confirmationElisabeth André Turlind and Göran Dahlin, SSM, ESARDA/INMM Oct 201117

Page 18: Experience with short notice (SNRI) and unannounced (UI ... · SO informs SSM of inspector arrival SSM contacts IAEA HQ for confirmation Elisabeth André Turlind and Göran Dahlin,

IS organisation for UI at Clab and Studsvik (cont’d)

SSM inspector leaves immediately– Time to Studsvik ~ 2 hours– Time to Clab ~ 4-5 hours

Clab have two prepared blank access cards for use by IAEA for smooth accessIAEA enters the facility within 2 hoursIAEA gets requested documentationIf needed IAEA can freeze the situation by applying sealsVerification activities can start when SSM arrivesElisabeth André Turlind and Göran Dahlin, SSM, ESARDA/INMM Oct 201118

Page 19: Experience with short notice (SNRI) and unannounced (UI ... · SO informs SSM of inspector arrival SSM contacts IAEA HQ for confirmation Elisabeth André Turlind and Göran Dahlin,

Elisabeth André Turlind and Göran Dahlin, SSM, ESARDA/INMM Oct 201119

Page 20: Experience with short notice (SNRI) and unannounced (UI ... · SO informs SSM of inspector arrival SSM contacts IAEA HQ for confirmation Elisabeth André Turlind and Göran Dahlin,

Elisabeth André Turlind and Göran Dahlin, SSM, ESARDA/INMM Oct 201120

Page 21: Experience with short notice (SNRI) and unannounced (UI ... · SO informs SSM of inspector arrival SSM contacts IAEA HQ for confirmation Elisabeth André Turlind and Göran Dahlin,

Elisabeth André Turlind and Göran Dahlin, SSM, ESARDA/INMM Oct 201121

Page 22: Experience with short notice (SNRI) and unannounced (UI ... · SO informs SSM of inspector arrival SSM contacts IAEA HQ for confirmation Elisabeth André Turlind and Göran Dahlin,

Experiences34 CA/SNRI/UI so farGood (on the whole, improving as more experience is gained)Facilities well informedSite definition for Clab had to be changedSSM organize prepardeness for UI/SNRI- one week at a time, ~6 month ahead- dedicated telephone/number, fax and e-mail- SSM participates in all IAEA inspections/CAs

Elisabeth André Turlind and Göran Dahlin, SSM, ESARDA/INMM Oct 201122

Page 23: Experience with short notice (SNRI) and unannounced (UI ... · SO informs SSM of inspector arrival SSM contacts IAEA HQ for confirmation Elisabeth André Turlind and Göran Dahlin,

Experiences (cntd)Some details failed- Training- Information/Communication- Procedures not clear- Inspector competence in the beginning- Access problems(new areas, people and snow)- Sometimes to optimistic plan by IAEA for CA- Fuel fabrication - Mailbox problems- UI on a national holiday- SNRI during core loading = problems

Elisabeth André Turlind and Göran Dahlin, SSM, ESARDA/INMM Oct 201123

Page 24: Experience with short notice (SNRI) and unannounced (UI ... · SO informs SSM of inspector arrival SSM contacts IAEA HQ for confirmation Elisabeth André Turlind and Göran Dahlin,

Summary

Good preparations/information/training necessaryImportant with inspector knowledge on ISVital with a proper organization – preparednessSite definition importantCommunication/information vitalFewer inspections can be a risk

Elisabeth André Turlind and Göran Dahlin, SSM, ESARDA/INMM Oct 201124

Page 25: Experience with short notice (SNRI) and unannounced (UI ... · SO informs SSM of inspector arrival SSM contacts IAEA HQ for confirmation Elisabeth André Turlind and Göran Dahlin,

Thank you for your attention!