experience with 25ns beams in the lhc and future perspectives

31
G. Rumolo, G. Iadarola, H. Bartosik, G. Arduini for CMAC#6, 16 August 2012 Many thanks to: V. Baglin, G. Bregliozzi, S. Claudet, O. Dominguez, J. Esteban-Müller, B. Goddard, W. Höfle, V. Kain, F. Roncarolo, E. Shaposhnikova, L. Tavian, F. Zimmermann Experience with 25ns beams in the LHC and future perspectives

Upload: mada

Post on 14-Feb-2016

34 views

Category:

Documents


0 download

DESCRIPTION

Experience with 25ns beams in the LHC and future perspectives. G. Rumolo, G. Iadarola , H. Bartosik , G. Arduini for CMAC#6 , 16 August 2012 Many thanks to: - PowerPoint PPT Presentation

TRANSCRIPT

Experience with 25ns beams in the LHC and future perspectives

G. Rumolo, G. Iadarola, H. Bartosik, G. Arduinifor CMAC#6, 16 August 2012

Many thanks to: V. Baglin, G. Bregliozzi, S. Claudet, O. Dominguez, J. Esteban-Mller, B. Goddard, W. Hfle, V. Kain, F. Roncarolo, E. Shaposhnikova, L. Tavian, F. ZimmermannExperience with 25ns beams in the LHC and future perspectives

Focus of the talk Review our present knowledge on electron cloud in the LHC with 25ns beam & anticipate future operation

25ns tests in the LHC in 2012SEY evolution Scrubbing runs and operation after LS1Required yearly scrubbing time

2

Commissioning with beam03/0414/03Physics run 50ns11/12201216/083

Commissioning with beam13/0305/0475ns physics run (nominal)12/0421/02Scrubbing run 50nsPhysics run 50ns30/1029/0626/0807-14-24/1025ns MDs (nominal)

Milestones of 25ns beam in the LHC201110/0725ns MDs (nominal)Scrubbing run 25ns08-12+25/10 25/0927/0912-16/12 25ns TESTS in 2012 and SEY EVOLUTION

Beam 1Beam 22012 injection tests (10 July 2012)Bunch-by-bunch intensityBeam 1Bunch-by-bunch intensityBeam 2

6Some electron cloud observables during the injection tests on 10 July 2012

Dynamic pressure riseBad lifetime and degrading transverse emittances towards the tail(s) of the batchesHeat load in the arcs

Use beam observables to double check that they are consistent with the picture we have built so far!! 67Some electron cloud observables during the injection tests on 10 July 2012

Dynamic pressure riseMainly in common areas and never above the interlock value of 4e-7 mbar Bad lifetime and degrading transverse emittances towards the tail(s) of the batchesHeat load in the arcs

Use beam observables to double check that they are consistent with the picture we have built so far!! 78Some electron cloud observables during the injection tests on 10 July 2012

Dynamic pressure riseBad lifetime and degrading transverse emittances towards the tail(s) of the batchesHeat load in the arcs

Use beam observables to double check that they are consistent with the picture we have built so far!! 8

10/07/12 12h55

Beam 1Beam 2

Beam 1Beam 2Beam evolution and emittancesBSRT SnapshotsUp to 4x emittance growth for both beamsAffecting last bunches of batchesAffecting especially the vertical plane10Some electron cloud observables during the injection tests on 10 July 2012

Dynamic pressure riseBad lifetime and degrading transverse emittances towards the tail(s) of the batchesHeat load in the arcs

Use beam observables to double check that they are consistent with the picture we have built so far!! 10

Simulation points10/07/12 12h00-12h1510/07/12 12h45-13:00A clear increase in the heat load was measured in the arcsThis is due to Electron Cloud + Synchrotron Radiation + Image Currents

Heat load

1229/0607/1024-25/1014/10Six snapshots from the 25ns MDs to reproduce the measured heat load by PyECLOUD simulations!

Flashback on 2011 (see Chamonix 2012)Beam 1Beam 2EnergyHeat load averaged sector by sector [x 10 mW/m/beam]

dmax decreased from the initial 2.1 to 1.52 in the arcs after approximately 50h machine time with 25ns beams in 2011 (injected nominal and degraded)It was found to be slightly higher (1.65) in 2012, but it has already decreased to 1.55 at the end the injection tests (4h beam time, 1h between measurements) Scrubbing history of LHC arcs

25ns threshold @450 GeV25ns threshold @3.5 TeV29/0607/1024-25/1014/1050ns

10/07/20123w p operation (50ns) 2011 + ions + Winter shut-down + 3m operation (50ns) 2012

4 hoursdmaxBeam 1Beam 2 Deterioration in SEY confirmed by worse beam lifetimeJuly 10, 2012 Beam 2 - October 24, 2011Beam observations

14SCRUBBING RUNS in 2012 and AFTER LS1Scrubbing run in 2012 + MDs16 Need to further lower the SEY in the arcs from the presently estimated value of 1.55 Effect of the filling pattern on scrubbing efficiencyEffect of bunch intensityScrubbing doseBeam stabilityMDs: Ramping a stable beam configuration to high energyPhotoelectronsLower SEY thresholds for (significant) e-cloud build up

25 Sep26 Sep27 SepThe 2012 scrubbing run is scheduled on 2527 September 2012Continue scrubbing of the machine for 25ns beams and enable MDs using these beams before LS1Validate the scrubbing procedure and establish a strategy for operation with 25ns beams after LS1

~1.45~1.55~1.37@injection

Effect of filling scheme

Trains of 72Trains of 144Trains of 216Trains of 28817

Ideal bunchesEffect of filling scheme Scan in SEY at nominal bunch intensity

Degraded bunches (as from last fill)

18

Effect of bunch intensity Scan in bunch intensity at SEYmax=1.55Max scrubbing dose @about 8 x 1010 ppb(however, only 10% larger than at 1.3 x 1011 ppb)Threshold value for electron cloud build up

Heat load 20% lower than at 1.3 x 1011 ppb 19

Effect of bunch intensity Scan in bunch intensity at SEYmax=1.55Electron distribution in the dipole chamber:The central density is higher for lower intensitiesThe two stripes move further out with higher intensitiesLower intensity beams also tend to be more unstable due to larger central densities they generateAll in all, it seems better to use higher intensities and move the beam radially to better scrub the central part

Electron distribution20

Effect of beam energy Ramping to 4 TeV during MDsA few concurrent effects at top energy:More production of photoelectrons causes higher electron densities (lower SEY threshold, ~1.37) and larger heat loads Due to the shorter bunches, the central peak in the electron distribution is less pronouncedThe beam is more rigid and generally more stable against coherent mechanisms (even with low chromaticity)

Scrubbing the LHC at injection energy with filling patterns based on long bunch trains should give enough margin to ramp up a non-degraded beam with shorter trains

Then the scrubbing process will continue thanks to photoelectrons

21Scrubbing runs after LS122Rough time estimate for first scrubbing run after LS1 (2014)~50h = 2 days machine time, as was needed in 2011, to lower dmax from 2.1 to 1.55 (including set up of all injection steps, 72-144-216-288 bunches)An additional 20h net beam time with 2100 bunches to get to 1.45 (scrubbing limit at flat bottom), estimated with a simple model (Chamonix 2012) = 6 days machine time (applying scrubbing factor from 2011 = 0.14)At least 4 days machine time for operation & further scrubbing at 7 TeV with increasing number of bunches (perhaps gradually including ramps at intermediate energies?)Total of 12 days with very good machine availability and no contingency Scrubbing scenarios could also foresee a staged approachFirst, light scrubbing with 25ns beams (few trains @injection) to allow a period of electron cloud free operation with 50ns and intensity ramp up. Then, full scrubbing for 25ns operation

In subsequent years, scrubbing should go much faster because, in absence of venting, de-conditioning is weak and re-conditioning much faster

Much to be yet validated with the 2012 scrubbing run + MDs with ramp to 4TeV2 days6 days4 days

Effect of beam energy Ramping to 7 TeV after LS1 with different filling patternsDue to photoelectrons:Threshold behaviour much less sharp than at injectionEffect of filling pattern only visible due to the different number of bunches (memory between batches is irrelevant) The absolute value of the scrubbing efficiency and heat load strongly depend on the reliability of our photoemission model

Still relatively high scrubbing efficiency and heat load well below 200 W/hcellScrubbing efficiency23

Effect of beam energy Ramping to 7 TeV after LS1Differences with injection energy:Strong peak where the SR hits directlyLower SEY threshold value for stripe formationMuch less pronounced central spike (effect of bunch length)Stripes in the same position benefits from scrubbing @injection + more scrubbing possibleBeam is more stable (low central density, higher energy)

Electron distribution@7 TeV@450 GeV24Summary and conclusions25The electron cloud still affects 25ns beams in the LHCSEY has come down to 1.55 and needs further loweringThere is a slight effect of de-conditioning between runs, but re-conditioning appears to be faster

Scrubbing runs are needed to be able to run LHC with 25ns beams for possible future operation (after LS1)2012Scrubbing run (3d) important to continue acquiring experience on operation with 25ns and scrubbing procedures (@injection)MDs with ramps to 4 TeV important to learn experimentally how the electron cloud effects behave with energy (and validate our models for extrapolation to 7 TeV)After LS1First scrubbing run might have to be long to recover acceptable SEY conditions (~12d)Future scrubbing runs should be shorter in absence of venting

SPARE SLIDES

25ns experience in 2011

DATESHORT DESCRIPTION29 JuneInjections of 9 x 24b trains per beam with different spacings between them26 AugustTwo attempts to inject a 48b train with damper on and off: fast instability dumps the beam within 500 turns in both cases (SBI and CBI)7 OctoberHigh chromaticity (Qx,y 15): Injection tests with trains of 72-144-216-288 bunches from the SPS + ramp to 3.5 TeV & 5h store with 60b (12+24+24) per beam 14 OctoberHigh chromaticity: injection of up to 1020 bunches per beam in 72b trains (decreasing spacings between trains at each fill: 6.33.21 ms)24-25 OctoberInjection of up to 2100 bunches in Beam 1 and 1020 in Beam 2 (1ms train spacing)Scrubbing29/0607/1024-25/1014/10Beam 1Beam 2Energy

28Measured heat loadTotal simulated heat loadfastBCT + bunch-by-bunch b-length (B1)fastBCT + bunch-by-bunch b-length (B2)Simulator PyECLOUD

dmax in the arcs: estimation technique

R0=0.7, scan in dmaxEmax=330 eV

28Commissioning with beam03/0414/03Physics run 50ns30/11201216/0829

Commissioning with beam13/0305/0475ns physics run (nominal)12/0421/02Scrubbing run 50nsPhysics run 50ns30/10Nominal:1.1 x 1011 ppb2.5 mm29/0626/0807-14-24/1025ns MDs (nominal)

Milestones of 25ns beam in the LHC201110/0725ns MDs (nominal)Scrubbing run 25ns09-15-25/10 ??25/0927/09

10/07/12 11h49-12h00

Beam 1

Beam 2

Scrubbing run in 201231The 2012 scrubbing run is scheduled on 2729 September 2012Continue scrubbing of the machine for 25ns beams and enable MDs using these beams before LS1Validate the scrubbing procedure and establish a strategy for operation with 25ns beams after LS1 Need to further lower the SEY in the arcs from the presently estimated value of 1.55 Effect of the filling pattern on scrubbing efficiencyEffect of bunch intensityScrubbing doseBeam stabilityRamping to high energy (probably to be done in MDs after the scrubbing run)PhotoelectronsLower SEY thresholds for e-cloud build up After 2012 scrubbing + 25ns studies in MDs, we will have collected enough data to predict the evolution of the LHC performance with 25ns beams.

0 500 1000 1500 2000 2500

11:30

12:00

12:30

13:00

Bunch #

Tim

e

LHC.BCTFR.A6R4.B1 July 10, 2012

N/N0

0.4

0.6

0.8

1

0 100 200 300 400

11:30

12:00

12:30

13:00

Bunch #

Tim

e

LHC.BCTFR.A6R4.B2 July 10, 2012

N/N0

0.4

0.6

0.8

1

0 100 200 300 400

22:00

23:00

Bunch #

Tim

e

LHC.BCTFR.A6R4.B2 October 24, 2011

N/N0

0.4

0.6

0.8

1

0 500 1000 1500 2000 2500

11:30

12:00

12:30

13:00

Bunch #

Tim

e

LHC.BCTFR.A6R4.B2 July 10, 2012

N/N0

0.4

0.6

0.8

1

max

Wtot(max)

Eb [mJ/turn]

Eb1(max)

Eb2(max)

Wmeas

Wsim1(max)

Wsim2(max)