executive summary - world bankdocuments.worldbank.org/.../e28850ea0p1289012b0ea… · web viewthe...
TRANSCRIPT
Draft Environmental Management Plan (EMP)
forTuvalu Aviation Infrastructure Investment Project
(TVAIIP)
Civil Aviation Directorate / Ministryof Finance and Economic Development
Tuvalu
November 04th, 2011
Page 1 of 37
E2885
TABLE OF CONTENTSAcronyms .......................................................................................
31 Executive Summary..............................................................42 Introduction.........................................................................53 Project Description..............................................................54 Biophysical Baseline of the Project Site.................................65 Potential Environmental Issues.............................................76 Tuvalu and World Bank Safeguards Policies.........................127 Summary of Public Consultation.........................................108 Mitigation Plans.................................................................129 Monitoring Plans................................................................1610 Costs ....................................................................................
2211 Institutional Arragements ..................................................22Annex 1: Summary of the Public Consultation...............................25Annex 2: Construction Supervision Report Checklist...................35
Page 2 of 37
Acronyms
CAD Civil Aviation DirectorateEIA Environmental Impact AssessmentEMP Environmental Management PlanGOT Government of TuvaluFUN Funafuti International AirportICAO International Civil Aviation Organization MNREE Ministry of Natural Resources, Energy and EnvironmentMOT Ministry of TransportMWCT Ministry of Works Communications and TransportPDO Project Development ObjectivePIU Project Implementation UnitCAD Civil Aviation DirectorateTFSU Technical and Fiduciary Services UnitTVAIIP Tuvalu Aviation Infrastructure Investment ProjectWB World Bank
Page 3 of 37
1. Executive Summary
This Environmental Management Plan (EMP) is developed for the activities planned for funding under the Tuvalu Aviation Infrastructure Improvement Project (TVAIIP). The TVAIIP is part of the World Bank financed Pacific Aviation Investment Project (PAIP). The TVAIIP involves upgrading and construction of aviation infrastructure within the existing site of Funafuti International Airport (FUN). Proposed civil works will involve the construction of new terminal building and control tower, resurfacing the aircraft runway, replacement of outdated aviation control equipment and installation of facilities for the enhancement of airport safety. The civil works will be undertaken on the existing site of the airport. The majority of construction materials, particularly aggregates, will be imported from commercial sources in other countries.
Potential adverse impacts from the project on human heath and/or the natural environment are not expected to be significant or irreversible. Most of them are site-specific and temporary. The main adverse environmental impacts concern construction-related nuisance, disturbance to local communities from transportation of construction materials and wastes, as well as waste generation from the operation of the new or upgraded infrastructure. These impacts could be effectively avoided and mitigated by implementation of the mitigation measures identified in the EMP. The socio-economic outcome of the proposed project is overall positive. Positive results mainly include improved compliance with core safety and security obligations, creation of employment, enhanced transport accessibility, and improved social infrastructure. There will be no land acquisition for any of the project activities.
The EMP lays out the environmental responsibilities of the contractors during construction and those of the airport management entity during operation, monitoring plans for relevant authorities to check if the mitigation measures are adequately implemented and if corrective actions are needed, as well as overall institutional arrangements to ensure the implementation of the EMP.
The duties of the main entities involved in the TVAIIP include:a. The design and supervision consultant shall ensure that the design is in compliance with
applicable environmental and social legislations/regulations of Tuvalu, Safeguard Policies of the World Bank (WB), and follow IFC Environmental, Health and Safety Guidelines for Airports;
b. The contractors shall adhere to their responsibilities described in this EMP, which forms part of the contract;
c. The design and supervision consultant shall supervise the implementation of mitigation measures and report to Civil Aviation Directorate (CAD) of the Ministry of Transport, which is the principle project executing body in Tuvalu. They will include an environmental management section as part of their normal reporting to CAD
d. The CAD shall identify corrective actions needed based on records submitted by supervision consultant and the consultant’s advice;
Public consultations on the draft EMP, which was disclosed for the public access in local language, were undertaken in Funafuti on 29th and 30th September, 2011. Recommendations for sound environmental management of construction activities where provided by
Page 4 of 37
consultation participants. The draft EMP was subsequently updated based on the main recommendations provided during the consultations, which are concerned with the minimization of noise, proper disposal of construction wastes, accidently damage of assets/structures by construction contractors, and procedures required for importing materials and construction machineries. A summary of the public consultations undertaken are provided in Chapter 7.
2. IntroductionTuvalu, sitting on three reef islands and six atolls in the midway between Hawaii and Australia, is the forth smallest country in the world. With its remote location and limited capital resources, Tuvalu faces various challenges and constraints in economic development, one of which is the transport connectivity with the rest of the Pacific region.
There is an urgent need to improve the aviation transport services in Tuvalu to enhance the accessibility to the country, which ultimately benefits various parties including tourism-related services, seasonal agriculture and seafarers labor markets and commercial businesses. The only airport in Tuvalu, Funafuti International Airport (FUN), was built by United States Navy Seabee construction battalions in 1943 during World War II. Its runway and control tower are rapidly deteriorating and some aviation control equipments are lacking. Recognizing the key role of aviation transport in the country’s socio-economic growth, in 2011, the Government of Tuvalu requested the support from the WB and other regional donors (New Zealand Aid Program, AusAID and Asia Development Bank) to improve the FUN facilities and services.
The overarching objective of the TVAIIP is to enable air transport infrastructure and operations of FUN to meet International Civil Aviation Organization (ICAO) standards, and to improve sustainability of the airport and civil aviation of Tuvalu. The project is projected to be completed in 2015. The proposed physical investments are shown in Table 1. In addition, energy efficiency of the airport operation will be taken into account in the design and implementation of the investments where practical.
3. Project DescriptionThe investments on aviation infrastructures of the proposed projects are listed in Table 3.1. As indicated in the table, the activities are expected to involve issues concerning civil works and installation of safety and aviation control equipments. The construction and installation activities will be confined within the existing boundary of the FUN. No construction of access roads or worker camps will be involved.
Table 1: Proposed Aviation Investments
Equipment supply and installationAutomatic weather station (AWS)Automatic dependent surveillance-broadcast (ADS-B)Security screening equipments for both hold baggage and carry-on baggage
Page 5 of 37
Air traffic control (ATC) equipments [including provision of ceilometers, signal lamps, radios, backup generator and other ATC equipments]
Civil worksResurface of runway (1,524 meters in length)Decommission existing air traffic control tower and construct new air traffic control tower at a new locationDecommission existing terminal building and construct new terminal building at a new location
4. Biophysical Baseline of the Project SiteTuvalu is a Polynesian island nation that lies in the Central South Pacific, west of the International Dateline and 1000km north of Fiji (see Fig. 1). The three islands and six atolls1 that make up Tuvalu, which stretch for just 360miles (579km), are only 26 km2 in land area in total. The capital of Tuvalu is the entire atoll Funafuti. The terrain of Tuvalu consists of low lying, narrow coral atolls and reefs. The lowest point is the Pacific Ocean at sea level, and the highest point is on Niulakita Island at only 15 feet (4.6 meters).
Tuvalu’s climate is tropical and is moderated by easterly trade winds from March to November. It has a heavy rain season with westerly winds from November to March. With the impacts of climate change, rising sea level and soil salination has been a concern for Tuvalu. Starting from the beginning of the 21st Century, there have been increasing reports of flooding.
Figure 1: Map of Tuvalu
1 The islands and atolls include Nanumea, Niutao, Nanumanga, Nui, Vaitapu, Nukufetau, Funafuti, Nukulaelae and Nulakita.
Page 6 of 37
The Funafuti International Airport (FUN) is located on island Funafuti, the width of which ranges from 20 meters to 400 meters. The airport is surrounded by villages and a cluster of administrative buildings (see Figure 2). There are no official biological protected areas, or any sites or structures of known cultural significance near the airport. There is only one airstrip in the airport (1,524 meters). There are houses and commercial developments along the airstrip. In the area around the south west end of the airstrip, there are small livestock farms, houses and a desalination plant. The airport is unfenced. Pedestrian and vehicle traffic crosses the airstrip to the buildings along the airstrip. Being one of the few open spaces on Funafuti, the airstrip provides a breezy place to sleep on muggy nights and playground by local people. Since the air traffic is only two flights per week, the population is aware of the need to clear the strip when the fire siren announces approaching flights.
Figure 2: Satellite Image of the Funafuti International Airport (FUN)[Source: Google Earth, Imagery Date: 10/19/2007]
5. Potential Environmental Issues
The potential environmental impacts are mostly construction-related, - temporary in nature, and can be mitigated by implementing sound management of construction activities. The area of influence of the project is rather limited as the proposed civil works and the equipment replacement/installation will be undertaken on land within the existing FUN
Page 7 of 37
property boundary. The demolishing of the existing control tower, which is a two story concrete structure with wood stairs, would not generate hazardous wastes (e.g., asbestos). The off-site impacts would be associated with the delivery and disposal of construction wastes, supply and temporary storage for construction materials.
The largest amount of construction materials needed would be 10,000 m3 for resurfacing the runway. Aggregate for concrete and other works will also be required. For the supply of materials the EMP considered two alternatives, namely, excavating resources in Tuvalu and importing from other country (most likely to be Fiji due to its proximity and boat connections), It was concluded that the project construction should plan on using imported materials. This will minimize the environmental impacts on the very limited local natural resources.
Tuvalu is a small country on flat atoll and reef islands, which do not have an abundance of gravels. Indeed, it is estimated that there are a total of some 70,000 m3 of potential gravels in the entire country, only a portion of which could be extracted sustainably without influencing the environment. As a result, excavation of coral reefs would be almost inevitable if the construction is to use domestic aggregate. However, coral reefs are among the most diverse and fragile marine habitats. The living coral reefs in the sea area surrounding Tuvalu is already under threat due to infrastructure and commercial developments along the shoreline, poorly managed wastewater and solid wastes. The removal of dead reefs would also pose considerable damage to the structure of atolls and reef islands, which causes instability and erosion on the sea slopes and an impact on marine biodiversity. Given these concerns, the EMP requires the contractors to use imported construction materials, except where it can be shown that local extraction will not have a negative impact on marine biodiversity. Consequently, no natural resources of important biodiversity value, especially coral reefs, shall be used for the construction.
Potential impacts and issues of concern for each project component are summarized in Table 2.
Table 2: Potential impacts from project activities
Project Activities Potential environmental impacts and concerns
Equipment supply and installation Automatic weather station (AWS) Safety during installation
Health impacts due to exposure of x-rays during security screening equipment commissioning
Automatic dependent surveillance-broadcast (ADS-B)Security screening equipments for both hold baggage and carry-on baggageAir traffic control (ATC) equipments [including provision of ceilometers, signal lamps, radios, backup generator and other ATC equipments]
Civil worksResurface of runway (1,524 meters in length)
During Design: Collection of wastewater and solid waste from
the new terminal buildings and control tower; -
Vacating of existing terminal building, construct a new one at a new site
Page 8 of 37
Adequate drainage from tropical storms on the runway, control tower and terminal buildings
During Construction: Construction-related nuisances: noise, dust, and
exhaust emissions from construction equipments;
Land restoration at original air traffic control tower site and land preparation at new air traffic control tower/terminal site
Supply of construction materials (gravel, concrete etc.) and construction equipments: construction materials shall be imported with relevant permits obtained; dust and fall-off from delivery trucks; disturbance to communities due to poorly managed transportation schedule
Generation of construction wastes (non-hazardous );
Disturbance to local traffic; Construction workers’ and community safety; Storage and handling of fuels and oil for
construction vehicles, and emergency in case of accident spills;
Chance find of artifacts/objects of cultural or historical values during excavation works;
Accidental damage of assets, infrastructures or other structures due to construction activities;
During Operation Collection and disposal of solid wastes (non-
hazard) from new terminal buildings and control towers;
Operation and maintenance of the septic tanks; Operation of the runway drainage; Operation of x-ray equipment
Demolition of existing air traffic control tower and construct new air traffic control tower/terminal building at a new location.
6. Tuvalu and World Bank Safeguards PoliciesIn accordance with World Bank policy for Environmental Assessment (OP/BP 4.01), this project has been assigned Category “B” and an EMP was prepared during project preparation. The policy requires the borrower to undertake consultations with project-affected people and disclose relevant materials of the project, including the EMP, in a form and language that are understandable and accessible to the groups being consulted before consultations.
The Environmental Protection Act (2008 edition) is the legislation which requires that all projects in the country shall undertake environmental assessment prior or during implementation. Although the Act is yet to be formally promulgated, the items in the Act regarding environmental assessment are already under implementation. The Department of Environment has reviewed this EMP and provided its approval on November 04th, 2011. The EMP will be integrated into the technical design, and included in bidding documents for construction contractors.
Page 9 of 37
7. Summary of Public Consultation Two rounds of consultation were undertaken with various project stakeholders were
undertaken for the draft EMP, which was subsequently amended based on the recommendations and suggestions provided by consultation participants. The consultations were held at the Telecom Conference Room at the Funafuti International Airport, Funafuti on 29th and 30th September, 2011, with a total number of 40 participants. The minutes for the consultations are attached in Annex 1.
The main issues raised from the public at consultations and mitigation measures or actions that will be undertaken to address these concerns are summarized in Table 3:
Table 3 Summary of ConsultationMain concerns and recommendations from the public
Mitigation measures or actions to be undertaken to address the concerns
Waste Disposal – Apart from the involvement of the Waste Management Unit of the Government, the local Town Council need to be included.
The mitigation plan has been modified to included requirements for the contractors to have their proposed disposal sites for the solid wastes to be approved by the Engineer, as well as the local Town Council.
From the consultation, it was suggested that the World Bank to consider constructing a road on the ocean side of the runway to be included in the project. This will limit the usage of the runway for crossing or by vehicles.
The traffic safety issue will be considered in the detailed engineering design for the project.
Compensation to damages during the project implementation needs to clarify before the project kick start.
The EMP has included requirements that the contractors will need to cover the cost for fixing the accidental damage caused during construction. The EMP will form part of the bidding documents to ensure the enforceability of the mitigation measures.
Due to the shortage of water on the island, it was suggested that a proportion of the project should look at this issue since it is critical to the nation. Furthermore, the project should ensure sufficient water for the implementation of the project prior to the start of the project.
The issue will be considered and addressed to the extent that is appropriate in more detail in the engineering design for the project.
World Bank should also consider including the beautification of the runway surrounding as a contribution for tourism activities. For instance, having the same vegetation or plant surround the runway that will not infringe to the runway. This will not only serve as a part of beautifying the area but
The contractor will be required to ask for permission from the Department of Land in case of vegetation removal. Hence, significant scenic impact is not foreseen.
Page 10 of 37
indicates the restricted length and width of the runway.During the implementation of the project, a suggestion was made for locals or residents who are near to the runway to be allowed to monitor the noise level with the project equipments (noise level detector) as this may affect infants especially.
The EMP requires that construction shall only take place between the hours of 07:00 and 18:00 from Monday to Friday to minimize possible disturbance to local residents. Any off-time construction works shall be commenced only after the permission from the Engineer is obtained. In these cases, notice of construction schedule should be provided to affected people at least 24 hours prior to the off-time works start. In addition, the community can address their complaints to relevant officers in CAD.
It was highly recommended in both consultations that a temporary fence should be made to avoid any catastrophic incident.
The EMP requires the contractor to fence off dangerous locations at the construction site to ensure community safety.
Fuel supply on the island at time is usually short. Hence, the contractor should provide to the local fuel supplier the amount he would require prior to the implementation of the project.
This will be ensured during construction.
A suggestion was made for a study to be included in the project on the impact of the daily operation of aircraft. This was a concern from residents staying near the airport as they usually experience the smell of aircraft fumes.
The volume of future flights will be maintained the same. There will be no interference with the normal flight schedule as resurfacing works is carried out in portions. The increase of flights is not envisaged either. Further, the project is to resurface the runway, renew the control tower and terminal buildings. Hence, a dedicated study on this issue is out of the scope of the current project.
Should explosive permits is required, Police and Customs are the authorities to obtain the license.
No explosion operation is expected in the project. The civil works involved in these projects are mostly to be small scale.
Apart from the World Bank’s suggestion to use sea water for the new fire truck, a suggestion was made to use the pond water from the ocean side of the runway.
This consideration would be considered to assess its applicability for this project.
Contractor should be notified that import permit for sand/gravel and machineries should obtain before they are allow to be import into the country
The EMP requires that the contractors to obtain all permits needed before importing their materials or machineries.
Importation of gravel/sand and other project materials should be clean of pesticides.
The EMP requires that the imported materials to be checked and make sure that they are free of pesticides.
Page 11 of 37
8. Mitigation PlansThe mitigation measures for the potential environmental impacts summarized in Section 5 will be implemented during design (see Table 3), constructions (see Table 4), as well as during operation (see Table 5).
Table 3 Mitigation measures to be implemented during design
Environmental impact and concern Mitigating Measures Implementer
Management of wastewater and solid wastes from the new terminal building and
control tower
(a) Septic system and disposal sites for the sludge to be included in the terminal and control tower design
(b) Disposal site for solid wastes to be provided
Design consultant
Impacts from tropical storms on the runway, control tower and terminal building
The designs shall be appropriate for the storm ratings in the area with regard to water disposal, wind loading, etc. Design consultant
Table 4 Mitigation measures to be implemented during construction
Environmental impacts and concerns Mitigating Measures Implementer
Noise from construction machineries and
equipments
(a) Construction shall only take place between the hours of 07:00 and 18:00 from Monday to Friday to minimize possible disturbance to local residents. Any off-time construction works shall be commenced only after the permission from the Engineer is obtained. In these cases, notice of construction schedule should be provided to affected people at least 24 hours prior to the off-time works start;
(b) Contractor to provide contact officer to address complaints from communities due to disturbances by construction activities
(c) The CAD to assign contact personnel to accept complaints from the community due to disturbances caused by noise, if any. Surrounding communities will be notified on this information prior to the commencement of construction
(a) and (b): Contractor
(b) CAD
Page 12 of 37
Dust
(a) All delivery trucks must be covered to prevent dust generation during transport
(b) Periodically clean stagnant debris, and cover debris piles before they are transported for disposal
(c) On-site loose construction materials should be covered
Contractor
Supply of construction materials (e.g., gravel,
concrete,) and construction equipments
(a) Except with the permission of the Engineer, construction materials shall be imported. No excavation of resources in Tuvalu for construction is permitted unless it is shown this will not impact on marine biodiversity. Import permits and Quarantine certification shall be obtained from the Department of Public Works and Quarantine Department, respectively, before applying for exporting permits from the country which provides the materials;
(b) No natural resources of important biodiversity value, such as coral reefs, shall be imported as construction materials;
(c) The imported materials shall be free of pesticides;
(d) The bitumen storage and any asphalt mixing plant shall be located at the site approved by the Engineer;
(e) Access to the construction site of delivery trucks that are not covered properly and/or are loaded with materials that exceed the loading limits approved by the Engineer will be denied;
(f) Material should be delivered in accordance with traffic management plan (see section on “Traffic management” below)
Contractor
Emissions from Construction Equipment
(a) To avoid excessive emissions, equipment over 5 years of usage shall only be used with the approval by the Engineer;
(b) Replacing the equipment/machineries at request by the Engineer
(c) Quarantine certification shall be obtained for the imported equipments by the contractor prior to importing;
(a): Engineer
(b): Contractor
Land restoration at original air traffic control tower site
and land preparation/clearing at
new terminal/control tower
(a) Remove all debris and waste materials, replace topsoil and replant/re-vegetate consistent with surrounding land condition
(b) Any removal/cutting of trees shall only be undertaken after permit from the Department of Lands is obtained. The permit shall be issued after the compensation paid for the owner/use of trees2
Contractor
Page 13 of 37
site
(c) Remove any vegetative cover by manual or mechanical means, no pesticide use
(d) Excavated topsoil/vegetative cover either to be utilized on site or disposed with other non-hazardous construction wastes at a site approved by the Engineer
Management of construction wastes
(a) Unused construction materials shall be removed from the construction site after construction is finished
(b) Components or scrap materials from demolished structures (control tower) that could be reused should be identified and stored;
(c) The remaining construction wastes to be disposed at a site approved by the Engineer and local Town Council .
Contractor
Traffic Management(Equipment and
construction materials deliveries, waste
materials removal)
(a) Prepare Traffic Management Plan to minimize disruption to airport operation, daily community traffic, consistent with overall project implementation schedule. The Traffic Management Plan shall be approved by the Engineer.
(b) Implement the Traffic Management Plan
(a): Contractor, consulting with the Public Works Department
(b): Contractor
Community safety
(a) Fencing off dangerous locations at the site for general safety measures
(b) Avoid disturbance to the daily access to businesses/offices by local communities. If not avoidable, provide clear marking and directing signs to direct passengers (if applicable, such traffic management shall be specified in the contractors’ Transport Management Plan)
Contractor
Construction worker health and safety
(a) Provide personal protective equipment and clothing (goggles, gloves, respirators, dust masks, hard hats, steel-toed and shanked boots, etc.,) for construction workers and enforce their use
(b) Post signs a for each chemical present on the worksite
(c) Clearly explain the risks to construction workers and their partners
(d) During extreme weather conditions or other emergencies of any kind, suspend all work
(e) Provide brace electrical and mechanical equipments to withstand extreme weather conditions
(f) Provide basic first aid services, including medical personnel, stretcher, vehicles for transport of
(a)to (e): Contractor;(f): Contractor, in collaboration with the Ministry of Health
2 The budget to be provided by the CADPage 14 of 37
injured worker to hospital;
(g) Providing training through local NGO to workers prevention of epidemics and sexually transmitted diseases, especially HIV/AIDS. The cost of training included as a provisional sum in the contract.
Storage and handling of fuels and oil for
construction vehicles, and accident spills
(a) Fuel shall be obtained from local commercially available sources. There shall be no on site storage of fuels without the permission of the Engineer.
(b) Welding, burning activities shall be prohibited in vicinity of the fuel/oil storage facilities
(c) Drainage from bunded area with impervious base directed to oil/water separation unit. The separation unit is to be constructed if not available.
(d) Collected oil disposed at disposal site approved by the Engineer.
(e) Major spills or leaks immediately covered with sand or similar absorbent, placed in sealed containers and disposed at disposal site approved by the Engineer.
Contractor
Chance finds of artefacts/ objects of cultural or
historical values
(a) Cease work immediately and fence area to limit access
(b) Contact Ministry of Education, Sports and Culture
(c) Work is not to proceed until official approvals are providedContractor
Accidental damage of assets, infrastructures or other structures due to construction activities
(a) The damage to be reported to the CAD
(b) The damaged assets, infrastructures or other structures to be fixed at expense of contractor Contractor
Table 5 Mitigation measures to be implemented during operation
Environmental impact and concern Mitigating Measures Implementer
Page 15 of 37
Occupational Health and Safety for the operation of aviation equipments
To provide training of proper operations of equipments to airport staff Airport Management
Maintenance of runway drainage (a) Remove the sediment from drainage for the runway regularly and dispose at designated site
Airport Management
Collection and disposal of solid wastes (non-
hazard) from new terminal buildings and
control towers
(a) Trash bins to be provided;
(b) Staff provided to dispose wastes to the designated site
Airport Management
Operation and maintenance of the
septic tanks
(a) The septic tanks are cleaned regularly;
(b) Sludge from the tanks is disposed to the designated site
Airport Management
9. Monitoring Plan
The Monitoring Plan to be implemented by the design and supervision consultant (see Table 6) is essentially a check list to be used during on-site inspections at construction sites. The supervising consultant shall keep records of contractors’ performance in accordance with Annex 2 to this EMP and report to CAD every month. During operation, the CAD shall undertake monitoring for items specified in Table 7 and include in the CAD quarterly reports. The CAD shall review the records and identify corrective actions need to be taken. See also section 9.3 for details on reporting arrangements.
Table 6 Monitoring plan to be implemented by civil work supervising consultant
Page 16 of 37
Items to be monitored Whatparameter is to be monitored
Whereis the parameter to
be monitored
Howis the parameter to be monitored/
type of monitoring equipment
Whenis the parameter to be
monitored-frequency of measurement or
continuous
Noise from construction machineries and
equipments
Activities conducted during normal working hours Construction site Observation Monthly, random times
Local affected groups notified in advance of any off-hour work
Local village, schools, etc. Consultation Monthly
Noise levels should not exceed 80dB Local village, schools, etc. dB meter If there are complaints
Dust
Construction site watered Construction site Observation Mostly during dry, windy conditions
Delivery trucks are covered when carrying construction materials/debris to the construction site;
Entrances and exits of
construction site
Observation Mostly during dry, windy conditionsPiles of construction materials at storage sites are
covered
Landing sites of shipped
construction materials and storage sites
If debris are periodically cleaned, and covered if piled Construction site Observation Monthly
Supply of Construction Materials
Validity of supplier permit or licenses Landing site of construction
materials
Observation Each delivery
Page 17 of 37
Items to be monitored Whatparameter is to be monitored
Whereis the parameter to
be monitored
Howis the parameter to be monitored/
type of monitoring equipment
Whenis the parameter to be
monitored-frequency of measurement or
continuous
Validity of export permit from the export country and import permit from Tuvalu
Landing site of construction
materialsObservation Each delivery
Delivery time in accordance with Traffic Management Plan
Entrance to construction site Observation Each delivery
Delivery trucks loaded no more than what is permitted by the engineer
Entrance to construction site Observation Each delivery
Evidence of truck spillage off construction site Along delivery route Observation In case of complaints
Emissions from Construction Equipment
Equipment with excessive emissions replaced if requested by Engineer
Construction site and access roads Observation Monthly; more often if
problem persists
Land restoration at original air traffic control tower
site, and preparation/clearing at
new terminal/control tower site
All debris and wastes removed, top soil replaced and revegtation undertaken Construction site Observation
Within one month after the demolition of original
control tower
Permits obtained from the Department of Lands before removal/cutting of any trees Construction site Observation
Before land preparation/clearing is
undertaken
Page 18 of 37
Items to be monitored Whatparameter is to be monitored
Whereis the parameter to
be monitored
Howis the parameter to be monitored/
type of monitoring equipment
Whenis the parameter to be
monitored-frequency of measurement or
continuous
Management of construction wastes
Unused, non-recyclable wastes sent to government approved disposal site Disposal site
Check waste delivery records at disposal sites, and construction
site;
Monthly
Useable components properly stored Storage area Observation Monthly
Unused construction materials are all removed after construction is finished Construction site Observation At the end of
construction
Traffic Management Traffic Management Plan implementedConstruction site,
disposal sites, material supply
sites
Observation, check of truck
delivery recordsMonthly
Community safetySigns and fences are set at construction site Construction site Observation Before the
commencement of construction
Access to business/offices by locals with clear marking and directing signs provided
In vicinity of construction sites
Safety of construction workers Basic first aid services provided Construction site
Observation Before the commencement of
construction
Training to workers on prevention of epidemics and sexually transmitted diseases provided Construction site
Before the commencement of
constructionPersonal protective equipments and clothing provided for construction workers and enforce their use
Construction site Before the commencement of
constructionPage 19 of 37
Items to be monitored Whatparameter is to be monitored
Whereis the parameter to
be monitored
Howis the parameter to be monitored/
type of monitoring equipment
Whenis the parameter to be
monitored-frequency of measurement or
continuousPost signs and warning signs for chemicals Construction site Monthly
Brace electrical and mechanical equipments to withstand extreme weather conditions Construction site
Before the commencement of
construction
Storage and handling of fuels and oil for
construction vehicles, and preparation for accident
spills
Impervious base provided at oil/fuel stored in fenced and bunded area Construction site
ObservationMonthly
Materials to be used in case of accident spills properly stored Construction site
Permits obtained from the Energy Department for filling of fuels for construction equipments
Entrance of the fuel filling site
Each arrival of construction vehicle
Table 7 Monitoring plan to be implemented by the CAD
Items to be monitored Whatparameter is to be monitored
Whereis the parameter to be monitored
Howis the parameter to be monitored/
type of monitoring equipment
Whenis the parameter to be
monitored-frequency of measurement or
continuous
Collection and disposal of solid wastes (non-hazard)
from new terminal buildings and control
towers
Wastes properly disposed to the designated sites Solid waste disposal site Observation Quarterly
Page 20 of 37
Wastewater management at new air traffic control
tower and terminal buildings
Proper maintenance of the septic systemAt sewage
connector to septic system
ObservationQuarterly, more
frequently if problems are observed
Sediment from runway drainage
(a) If sediment is blocking the drainage;(b) If removed sediment properly drained and
deposited to government approved site
Water storage tanks Observation
After sediment removal activities begin, more
frequently during raining seasons
Page 21 of 37
10. Costs10.1 Mitigation and MonitoringThe cost of implementing the proposed mitigation and monitoring plans is small. This EMP will be included in the bidding document for contractors. A prospective contractor will be fully cognizant of his/her environmental management requirements and should reflect this in the bid offer. The awarded contract will also include this EMP, to further insure the requirements are legally binding to the successful bidder. Therefore, the successful contractor will cover the cost of the implementation of mitigation measures, such as provision of signs, fences, covers for piled construction materials.
10.2 EquipmentMost monitoring activities involve observational techniques, so there is no affiliated equipment cost. Noise meters have been included in the TSCP project so there is no need for additional noise monitoring equipment. Testing of X-ray equipment will be included in the initial purchase price of the radiometer as part of the acceptance test, and operational monitoring is estimated to be annually at a cost of approximately $US 1000.
10.3 Training Environmental training for Contractors, MOT/MOW/MECC has been provided in the project cost. Environmental training to CAD, the implementing agency, is anticipated to be in the general area of environmental awareness. The cost is estimated to be $US 15000.
11. Institutional Arrangements During Construction : Contractors will be responsible for implementing mitigating actions specified in the EMP. Monitoring of these actions as specified in the monitoring plan will be the responsibility of civil works design and supervision consultant. CAD will provide overall monitoring.
D uring Operation : CAD will be responsible for both mitigation and monitoring activities specified in the operational sections of their EMPs.
11.1 Reporting RequirementsDuring Construction, the civil works supervising consultant will provide monthly reports to CAD on the status of construction. The report should include an analysis of the monitoring program results, any environmental issues developed, and recommendations (including cost estimates, as necessary) for further actions. CAD in turn will share these reports with the PAIP ‘Technical and Fiduciary Services Unit (TFSU) and agree with TFSU upon implementation of any further actions as recommended in the monthly reports. Figure 3 describes the reporting arrangements.
Page 22 of 37
Fig. 3 Organogram of Communication and Reporting During Construction
During Operation, FUN Managers will include an environmental management section as part of their normal reporting to the Head of CAD. The section should include an analysis of the operational monitoring program results, any environmental issues developed, and recommendations (including cost estimates, as necessary) for further actions. Figure 4 describes the reporting arrangements.
Fig. 4 Organogram of Communication and Reporting During Operational Period
CAD will include an environment section as part of their normal progress report to the World Bank. In this section, CAD will report on: (a) overall compliance with implementation of the EMP, (b) any environmental issues developed during the report period, (c) how the issues were or will be resolved, and (d) the associated schedule for completion.
11.2 EMP ComplianceDuring Construction: The head of CAD will review the civil works design and supervision consultant’s report and recommendations and in conjunction with the TFSU Director determine: (a) what further actions are required, (b) who will be responsible for implementing the actions, (c) a schedule for completion, and (d) any costs associated with implementing the recommendations.
During Operation : The head of CAD will review the Airport Managers reports and recommendations and determine: (a) what further actions are required, (b) who will be
Page 23 of 37
Civil Works Supervisor
Head of CAD
TFSU
Decision on Actions
Reporting monthly on status of the EMP implementation.
Shares monthly reports with PIU and discusses any required actions
FUN ManagersInclude reporting on Environmental Management Section in existing monthly reports
CAD identify environmental issues and actions for inclusion in Quarterly Project Reports to WB
Head of CAD
Decision on Actions
World Bank
responsible for implementing the actions, (c) a schedule for completion, and (d) any costs associated with implementing the recommendations.
11.3 Public Participation in Monitoring The project will establish a complaints monitoring system which will facilitate the public's involvement in monitoring compliance with the EMP. At each site, signs will be installed clearly indicating that complaints or concerns can be made via phone, letter, or through the internet (e-mail). These will be received by the Project Management Unit and recorded in a database, along with follow up actions and resolution. The monthly monitoring reports will include data on complaints received, actions taken by CAD, public feedback and resolution.
Page 24 of 37
Annex 1: Summary of the Public Consultation
GOVERNMENT OF TUVALUMINISTRY OF COMMUNICATION, TRANSPORT & PUBLIC UTILITIES
DEPARTMENT OF CIVIL AVIATION
Address: Private Mail Bag, Funafuti, TUVALU. Telephone: 20153/20737. Fax: 20057/20722
Introduction:
In the preparation stage for Tuvalu Aviation Infrastructure Investment Project (TVAIIP) which is to be supported by the World Bank, the Department of Civil Aviation, the Department of Environment and the World Bank have constructed the Environmental Management Plan (EMP) for the project. The project is to be approved by late December, 2011 in which the implementation will commence straight after the approval.
The EMP was developed to identify and address the potential environmental risks of the project, and to establish appropriate mitigation measures. To support this plan, public consultations were conducted with various stakeholders to obtain their views and comment for the betterment of the plan. These consultations were conducted on the 29th
and 30th of September, 2011.
Comments, views and recommendations from the consultations were well documented, in which a list of important issues was created. The minutes, the list of issues and the lists of participants for the two days consultations are included in this report.
Page 25 of 37
Day 1 Consultation Minutes: Funafuti (FUN) – Locals/Residents Stakeholders
Location: Funafuti International Airport, Funafuti.Date and Time: Thursday 29 September 2011, 09:00 AMVenue:Telecom Conference Room
Program Outline:Opening Remarks, Mr. Uiga Paelate, Deputy Director, DCAOpening Prayer, Reverend Salanoa TinilauIntroduction and Project Description (Tuvaluan) – Mr. Vitoli Iosefa
Director, DCAQuestion and Answers – Participants and DCAClosing Remarks – Mr. Vitoli Iosefa Director, DCAClosing Prayer – Mr. Mesako
Summary of Discussion:
Mr. Iosefa thanked the participants for their effort to attend and also apologized on behalf of the Secretary for Communication & Transport whom could not formally open the consultation due to unforeseen occurrences. In addition, Mr. Iosefa stated that the Environment Department were arranged to conduct discussions but due to an adjacent workshop, were not able to present the Draft EMP. Nevertheless, further delays would only prolong project goals down the line and mentioned that the signing of the grant would be in December this year.
Mr. Iosefa briefly outlined the initial project requirements to commence with World Bank grants. He briefly stated the advantages and purpose of having an EMP in place. He also stressed out the importance of the participants’ feedback to finalizing the EMP. He also briefly described areas that Grant focused on as per the handouts and that it was of highest priority to improve Airport facilities to comply with International Standards. Capacity Development was also part of the Grant that he briefly conferred.
Mr. Iosefa also briefly discussed the history of the World Bank and its main objectives, and pointed out that this was the first ever WB infrastructure project in Tuvalu and Tuvalu’s recent membership in the WB. He concluded by thanking the participants for attending and urged them to share any ideas.
Questions and Answers:1. How long is the project for and when will it commence? (Mr.Mesako
Usufono)In improving the runway condition, will there be a possible increase in flights/or are bigger aircraft able to use the runway?
Mr. Iosefa indicated that the project was spread across a period of 5 years and hopefully commence next year and there is yet no plans to increase the number of flights or to facilitate bigger acft.
Page 26 of 37
2. In the disposal of rubbish, have you included the KAUPULE (Island Council) in this plan since they overlook this area and also own the Rubbish Dump? (Mr.Heiloa Loua – Island Council)
Mr.Iosefa responded that the successful contractor would be required to provide these details but is thankful for pointing out the involvement of the Island Council.
3. Will there be any changes to the rwy size? ( Mrs.Penieli Lotoala – Local Businesswoman) Is it possible to use the Ocean-side road for transportation during works to help with the dust issue, and also can the surfaces be sprayed wet before works begin?Also on completion of the project, would all the heavy machinery be returned?
Mr.Iosefa indicated that the rwy will have no change in size as it will only be re-surfaced and that the wetting the surfaces prior any works is in the EMP, also will take note of the possibility of using the road further away from residential areas. Regarding Heavy machinery, we will request that what is useful for further development of Tuvalu, be left behind.
4. Where will the new Terminal building be sited?(Mrs. Afasene Pese – Local Reporter) Is this project a loan from the WB and how early can the plan be formalized and sent to the World Bank?
Mr. Iosefa stated that the PWD has selected possible sites for the new Terminal building and is waiting for the successful contractor to select the best site which will have to be approved by the government. He also clarified to the attendants that this project is a Grant under the Pacific Aviation Infrastructure Investment Fund.
5. With heavy machinery/gravel/sand, there should be proper Quarantine certification be attained prior to before entering Tuvalu, due previous project experiences. (Mrs.Afasene Pese)Also to clearly point out which party was to compensate for damaged property as a result of the works!
Mr.Iosefa indicated that the issue will be raised with WB consultants/successful contractor to minimize this matter and will also look into the issue of compensation as a result of works.
6. Is there an allocation in the project budget for water? (Mr. Heiloa Loua)
Mr. Iosefa thanked Mr. Loua for raising the issue and will surely forward the query to the WB on this as it is an important issue for the nation.
7. Can a Desalination unit be included in the project? (Mrs. Afasene Pese)
It is not in the project.
Page 27 of 37
8. Since most trees within the 90mtr rwy area will be cut, is there a possibility in planting hedges along that area to mark it? (Mrs. Siemai Niko) Also could there be landscaping works on the rwy greens to better present the airport, would surely give tourist a good first impression of the country?!
Mr. Iosefa stated that he is not sure to what extend the resurfacing works would reach but acknowledged the idea for better landscaping. Regarding hedges, he indicated that later this year a survey would be carried out to point out what needs to be removed and to what heights were acceptable beyond the 90mtr restriction. He also reminded the attendants that only infringing vegetation are to be removed and will be compensated for accordingly by the government.
9. If the surveyors can carry out the survey and advise if relocation is an option? ( Mrs. Misalaima Nelesone)
Mr. Iosefa answered that the survey was only to identify all obstacles that are infringing the 1:5 transitional slope and advice on how to carry out any related activities to align the standard of our runway with international standards.
10.Since it’s stated that there are guidelines for the level of noise, I suggest that a local is available at all times to ensure that the db is within the limitations. (Mr. Mika Elisaia)
Mr. Iosefa stated that it was a good suggestion and since infants are most affected by the high levels of noise, precautions will be in place. He stated that the Department will have talks with the WB consultants/contractor on the issue.
11. Is it true that the rwy will be fenced? (Mr. Mesako Usufono)Can the contractor fix the Ocean-side road for use during construction works?
Mr. Iosefa will bring this up with the WB to be considered in the project and to look at an options of fencing the runway without interfering other uses of the runway. Also Mr Iosefa to consult with the government on this for their approval.
Page 28 of 37
Day 2 Consultation Minutes: Funafuti (FUN) - Aviation Stakeholders
Location: Funafuti International Airport, Funafuti.Date and Time: Friday 30 September 2011, 09: 30 AMVenue:Telecom Conference Room
Program Outline:Opening Remarks, Mr. Vitoli Iosefa, Director, DCAOpening Prayer, Mr. Uatea Salesa, Ag Director of Public Works
DepartmentIntro and Project Description (Tuvaluan/English) – Mr. Vitoli Iosefa Director
Question and Answers – Participants and DCAClosing Remarks – Mr. Vitoli Iosefa Director, DCAClosing Prayer – Mr. Uatea Salesa, Ag Director of Public Works
Department
Summary of Discussion:
Mr. Iosefa thanked the participants for their effort to attend and also apologized on behalf of the Secretary for Communication & Transport whom could not formally open the consultation due to unforeseen occurrences. In addition, Mr. Iosefa stated that the Environment Department were arranged to conduct discussions but due to an adjacent workshop, were not able to present the Draft EMP.
Mr. Iosefa briefly outlined the initial project requirements to commence with World Bank grants. He briefly stated the advantages and purpose of having an EMP in place and stressed out the importance of the participants’ feedback to finalizing the EMP. He also briefly described areas that the Grant focused on as per the handouts and that it was of highest priority to improve Airport facilities to comply with International standards. The Director also indicated that Capacity Development was also an area the Grant is dedicated to.
Mr. Iosefa also briefly discussed the history of the World Bank and its main objectives, and pointed out that this was the first ever WB infrastructure project in Tuvalu and Tuvalu’s recent membership in the WB. He concluded by thanking the participants for attending and urged them to share any ideas.
Questions and Answers:1. Is there a follow-up plan to this EMP? (Mr. Taeka Satupa- Tuvalu
Electricity Corporation)
Mr. Iosefa mentioned that the EMP was the only plan with regards to environment issues for the project, and he believes that there are other plans that focus on other areas of the project. The EMP is a requirement under the Environment legislation in which the project is guide by.
2. Can sand be replaced with proper absorbent mats for all oil spills? ( Mr. Uatea Salesa- PWD)
Page 29 of 37
Is there an allocation for water in the project funds, for construction that is?What is the plan regarding fuels for operation since we frequently face fuel shortages?
Mr. Iosefa stated that he will discuss the issue with the WB on the matter of proper absorbent mats for oil spills, the inclusion of water in the project. He also stated that regarding fuel, he will discuss the issue with the main supplier and WB consultants to eliminate that uncertainty.
3. Be advised that the Kaupule is the main operator for rubbish disposal + the disposal site and that the S.W.A.T also overlooks the operation? (Mrs. Suzzane Tupulaga – S.W.A.T Coordinator)
Mr. Iosefa indicated that in the previous meeting, the same issue was raised by a Kaupule official and will discuss with WB consultants on guidelines regarding rubbish disposal.
4. Would the construction works affect the normal flight schedule and has there been any study on the environmental effects of aircraft fumes? (Mr. Filemoni Panisi- Philatelic Bureau)
Mr. Iosefa indicated there will be no interference with the normal flight schedule as resurfacing works is carried out in portions. Regarding aircraft fumes, Mr. Iosefa stressed that the consultation was for the environmental impacts of construction works, but since the issue is of a serious nature, he will request to be included portion of studies in the project.
5. For explosives permits, contact the Police/Customs office for relevant actions. (Mr. Uatea Salesa) Mr. Iosefa indicated that he will consult with the WB to amend that part of the EMP, yet is not sure that any explosives will be used in project works.
6. Is there a plan to harness the Taisala by the rwy by using hydrants, or a huge water cistern for fire-fighting purposes? (Mr. Agaifo Houati – )Superintendent
Mr. Iosefa indicated that there is a current study on rwy water catchment conducted by an expert and that the Fire-Tender that we will be receiving as part of the Grant will be built to withstand the use of sea-water well as have adviced.
With reference to utilizing the Taisala (pond water) for Fire-fighting, it is a better alternative to sea-water and will further discuss it with the WB consultants/contractor.
7. Be advised that permits should be prepared and approved prior to importing quarantine items. ( Mrs. Akinesi Sianoa- Quarantine Department)
Mr. Iosefa responded that he will take note of the provided information for overseeing the importation of sand/gravel/machinery.
Page 30 of 37
8. If by chance materials (sand/gravel) is imported from Fiji, possible to setup very strict precautions due to previous project practices?(Mr. Faavae Lutelu)
Mr. Iosefa responded that at this stage it is not clear as yet to where materials (sand/gravel/soil) are to be imported from, but will ensure that the contractor is clear with the guidelines and precautions (pesticides).
9. In the new Terminal building, can there be an adequate spaced area for handling quarantine matters, since it is always crowded in the baggage claim area?(Mrs. Akinesi Sianoa)
Mr. Iosefa indicated that at this stage, design and location for the new Terminal has yet to be finalized as we a yet to select a contractor but with respect to adeqacuate spacing, it will be taken into account for discussions with the successful contractor.
10. Is there a provision for training, regarding rescue fire-fighting services? (RFFS)? (Mr. Tualua. Tepoga)
Mr. Iosefa indicated that there is a substantial provision for training over a 5 year period.
In addition to that, Mr. Iosefa concluded the meeting by thanking the participants for their views on the EMP and ideas for the smooth operations of construction work.
Page 31 of 37
Recommendations/Important Notes from the Consultations:
1. Waste Disposal – Apart from the involvement of the Waste Management Unit of the Government, the Local Town Council need to be included.
2. From the consultation, it was suggested that the World Bank to consider constructing a road on the ocean side of the runway to be included in the project. This will limit the usage of the runway for crossing or by vehicles.
3. In addition, a suggestion was raised for heavy equipments to be left back after the project has completed for Tuvalu other uses.
4. Compensation to damages during the project implementation needs to clarify before the project kick start.
5. Due to the shortage of water on the island, it was suggested that a proportion of the project should look at this issue since it is critical to the nation. Furthermore, the project should ensure sufficient water for the implementation of the project prior to the start of the project.
6. World Bank should also consider including the beautification of the runway surrounding as a contribution for tourism activities. For instance, having the same vegetation or plant surround the runway that will not infringe to the runway. This will not only serve as a part of beautifying the area but indicates the restricted length and width of the runway.
7. During the implementation of the project, a suggestion was made for locals or residents who are near to the runway to be allowed to monitor the noise level with the project equipments (noise level detector) as this may affect infants especially.
8. It was highly recommended in both consultations that a temporary fence should be made to avoid any catastrophic incident.
9. Fuel supply on the island at time is usually short. Hence, the contractor should provide to the local fuel supplier the amount he would require prior to the implementation of the project.
10. A suggestion was made for a study to be included in the project on the impact of the daily operation of aircraft. This was a concern from residents staying near the airport as they usually experience the smell of aircraft fumes.
11. Should explosive permits is required, Police and Customs are the authorities to obtain the license.
Page 32 of 37
12. Apart from the World Bank’s suggestion to use sea water for the new fire truck, a suggestion was made to use the pond water from the ocean side of the runway.
13. Contractor should be notified that import permit for sand/gravel and machineries should obtain before they are allow to be import into the country.
14. Importation of gravel/sand and other project materials should be clean of pesticides.
Page 33 of 37
Consultation Day: 1 (Thursday 29 September 2011, 09:00 AM)
Page 34 of 37
Consultation Day: 2 (Friday 30 September 2011, 09:00 AM)
Page 35 of 37
Page 36 of 37
Annex 2: Construction Supervision Report ChecklistGeneral information DD/MM/YY
Report prepared by Name of contractor/ subcontractor
Permits, agreements Permits obtained for filling of fuels of construction equipments/vehicles
Yes
No
N/A
Permits obtained for removal/cutting of treesYes
No
N/A
Management of construction sites Proper location of construction site/camp
Yes No
N/A
Availability of proper storage for fuel, oil and construction materials
Yes
No
N/A
Proper maintenance of construction machinery and equipment (prevent leakage of fuel, oil, lubricants, etc.)
Yes
No
N/A
Availability of places of preliminary accumulation of excavated and demolished materials and construction wastes
Yes
No
N/A
Timely removal of excavated and demolished materials and construction waste from the places of preliminary accumulation and disposal to planned and agreed places
Yes
No
N/A
Use covered trucks for transportation of construction materials and waste off site
Yes
No
N/A
Clean the surrounding area from dust by water sprinkling in construction zone (when necessary)
Yes
No
N/A
Clean/ wash tires of vehicles before they get to dwellings and/or drive off site (when necessary)
Yes
No
N/A
Implementation of works at the established time (e.g. work during daytime)
Yes
No
N/A
Installation of road signs in construction sites, camps
Yes
No
N/A
Ensure proper sanitary/ hygienic conditions for workers at the construction site
Yes
No
N/A
Restoration of the area of construction sites and camps when the construction works are over
Yes
No
N/A
Safety measures Workers are provided with necessary safety uniform (e.g. vests, helmets, high boots, gloves, glasses, etc.) and use them
Yes
No
N/A
Availability of fire-resistant measures on construction sites/ camps (fireproof shield, fire extinguisher, sand, etc)
Yes
No
N/A
Other Issues Observed
Page 37 of 37