executive summary of draft eia report

19
EXECUTIVE SUMMARY OF DRAFT EIA REPORT FOR PROPOSED EXPANSION FOR PRODUCTION OF M.S. INGOTS/BILLETS By M/s North East Ferro Alloys Co. (P) Ltd. At Plot No.: 846/847, Village : Suboljote, P.O- Nemai, via Matigara, P.S Matigara, Dist.- Darjeeling, West Bengal- 734010 ENVIRONMENTAL CONSULTANT M/s. ULTRA-TECH ENVIRONMENTAL LABORATORY AND CONSULTANCY Unit No. 206, 224, 225 Jai Commercial Complex, Eastern Express Highway, Opp Cadbury Factory, Khopat, Thane (West) 400 061 Tel: 022-2534 2776, Fax: 022-25429650, Email: [email protected] Website: www.ultratech.in September, 2020

Upload: others

Post on 28-Jan-2022

10 views

Category:

Documents


0 download

TRANSCRIPT

EXECUTIVE SUMMARY OF DRAFT EIA REPORT

FOR

PROPOSED EXPANSION FOR PRODUCTION OF

M.S. INGOTS/BILLETS

By

M/s North East Ferro Alloys Co. (P) Ltd. At

Plot No.: 846/847, Village : Suboljote, P.O- Nemai, via

Matigara, P.S –Matigara, Dist.- Darjeeling, West Bengal-

734010

ENVIRONMENTAL CONSULTANT

M/s. ULTRA-TECH ENVIRONMENTAL LABORATORY AND CONSULTANCY

Unit No. 206, 224, 225 Jai Commercial Complex, Eastern Express Highway,

Opp Cadbury Factory, Khopat, Thane (West) – 400 061

Tel: 022-2534 2776, Fax: 022-25429650, Email: [email protected]

Website: www.ultratech.in

September, 2020

TABLE OF CONTENTS

EXECUTIVE SUMMARY .......................................................................................................................... 1

1.0 Introduction .......................................................................................................................... 1

2.0 Project Description ................................................................................................................ 5

3.0 Description of Environment .................................................................................................. 9

4.0 Anticipated Environment Impacts and Environment Management Plan ............................ 12

6.0 Environmental Monitoring Program ................................................................................... 14

7.0 Additional Studies ............................................................................................................... 15

8.0 Project Benefits ................................................................................................................... 15

9.0 Environmental Cost Benefit Analysis ................................................................................... 16

10.0 Environment Management Plan ......................................................................................... 16

11.0 Disclosure of Consultants Engaged ............................................................................................. 17

LIST OF FIGURES

Figure E-1: Location map of the Project Site ............................................................................ 2

Figure E-2: Study Area Map of 10 KM radius .......................................................................... 3

Figure E-3: Water balance diagram ........................................................................................... 7

Figure E-4: Process Flowchart of M.S Billets/M.S Ingots ........................................................ 9

LIST OF TABLES

Table E.1: Environmental Setting around Project Site .............................................................. 3

Table E.2: Details of Production Capacity ................................................................................ 5

1

EXECUTIVE SUMMARY

1.0 Introduction

M/s North East Ferro Alloys’ Co. (P) Ltd., is a private limited company, limited by shares,

incorporated on 16.-07-2008 under the Indian Companies Act, 1956, having its registered

office at Vill.- Suboljote, P.O.- Nemai, P.S.- Matigara , Dt.- Darjeeling, in the state of west

Bengal. The Board of directors, comprising of presently, two female Directors, namely, Smt.

Minu Goyal & Smt. Krishna Devi Agarwal, are at the top of the management of the

company. The Administrative office of the company is however, located at 2nd

floor, PCM

Tower, Sevoke road, Siliguri. The proposed industrial unit has already been provisionally

registered as SSI unit, bearing E.M. No-19/001/12/10108, dated-08-08-2008.A plot of land,

measuring 6757.67 Sq.m (1.67 acres) has already been purchased for the set up of industrial

unit at the above location in the name of the company for production of 28,800TPA MS

Billets / Ingots using 1 x 8T Induction Furnace

With the favourable change in the industrial climate, the directors have decided for an

expansion of production capacity from 28,800 MTPA to 1,36,800 MTPA by installing

2x15MT Induction Furnace. Additionally they are also proposing to install a 2 strand 7/4m

radius Continious Casting Machine in the same premises.

The company will aim for efficient management of the unit, which will require judicious

manpower planning, selection of qualified and experienced personnel and also appropriate

organizational structure, clearly defining the functions and responsibilities of the managerial

and supervising staff.

As per the Environmental Impact Assessment Notification dated 14th September 2006, the

proposed expansion project falls under the Schedule No.3 (a) [Metallurgical Industries

Ferrous and Non-ferrous] and categorized as “Category B1” for which the Environmental

Clearance (EC) from the State level Environmental Impact Assessment Authority (SEIAA) is

required.

In line with EIA notification, a TOR meeting was held for determining Terms of Reference

(TOR) on 27.12.2019 (185th

meeting) and received TOR vide letter No. 08-2N-72/2019(E)

Dated 07.01.2020 and the EIA report has been prepared in line with the TOR conditions

obtained.

1.1 Project Location

The proposed expansion will be done inside the existing steel plant of M/s. North East Ferro

Alloys‟ Co. (P) Ltd. which is located at Plot No.: 846/847, Village : Suboljote, P.O- Nemai,

via Matigara, P.S –Matigara, Dist.- Darjeeling, West Bengal-734010. Therefore, no

additional land will be acquired for the proposed expansion.

2

The location map of the existing plant site is shown in Figure-E.1. The study area map of 10

km radius is shown in Figure E-.2. The details of environmental setting are given in Table-

1.1.

Figure E-1: Location map of the Project Site

3

Figure E-2: Study Area Map of 10 KM radius

The details of environmental setting are given below.

Table E.1: Environmental Setting around Project Site

SN Component Description

Plant Location Plot No.: 846/847, Village : Suboljote, P.O-

Nemai, via Matigara, P.S –Matigara, Dist.-

Darjeeling, West Bengal-734010

Approx Site Centre Point

Coordinates

Centre Point: 26°44'41.09"N, 88°21'55.97"E

Point Latitude Longitude

A 26°44'42.33"N 88°21'57.84"E

B 26°44'40.35"N 88°21'58.68"E

C 26°44'39.86"N 88°21'53.94"E

D 26°44'41.84"N 88°21'53.79“E

Village/District/State Suboljote/ Darjeeling / West Bengal

Maximum temperature 17.8oC (Annual Average)

Minimum temperature 6.6oC (Annual Average)

Annual rainfall (Average) 2800 mm

Plant site elevation above MSL 138 m

Present land use at the site Land use pattern is industrial

Nearest highway NH-55

4

SN Component Description

Aerial Distance – 1.5 Kms W

Road Distance – 2.3 Kms

Nearest Railway Station Siliguri Railway Station

Aerial distance – 5.36 km, ESE

Road distance- 7.9 Km

Nearest Airport

Bagdogra International Airport

Aerial Distance – 7.88 kms WSW

Road Distance – 12.8 km

Nearest major water bodies Mahananda River – 3.2 km towards E

Nearest town/City Siliguri- 3.5 Km, E

Nearest village Suboljote, Matigara

Nearest Dispensary and Govt.

Hospital, Educational facility

Hospital and all other facilities available at

Matigara 1.5 Km, E of Project Site.

Interstate boundary None within 10 km

Archaeologically important

places

None within 10 km

Protected areas as per Wildlife

Protection Act, 1972 (Tiger

reserve, Elephant reserve,

Biospheres, National parks,

Wildlife Sanctuaries, Community

Reserves and Conservation

Reserves)

No Tiger reserve, Elephant reserve, Biospheres,

National parks, Wildlife sanctuaries, community

reserves and conservation reserves within 10 km

of project site.

Mahananda Wildlife Sanctuary- 22.5 Kms (NE)

Jore Pokhri Wildlife Sanctuary- 10.91 Kms (W)

Forests Nearby Forests are-

Sukna Forest- 6.5 Kms (N)

Mohanadi Forest- 6 Kms (N)

Panta Pari Forest- 6.5 Kms (E)

Dalkajhar Forest – 9.5 Km (E)

Defence Installations Not Available within 10 km

Seismicity As per the 2002 Bureau of Indian Standards

(BIS) seismic zone map of India, categorized as

Seismic Zone-IV.

Industries 1 Nebula Marketing Private Limited- Adjacent

towards N

2 Fabulous Commercial Pvt. Ltd.- Adjacent towards

W

3 M/s Sensitive Vanijya Pvt. Ltd Adjacent towards S

4 Hindmake Industries and Infrastructures

Commodities India (P) Ltd (HICL)- 6.55 kms NE

5 Peak Chemical Industries Limited- 7.4 Kms ESE

6 KTL Industries- 6.5 Kms SE

7 Ceasefire Industries Limited- 6.8Kms SE

8 M/s Deepak Industries- 7.08Kms SE

9 S.P. Industries- 4.15Kms S

5

2.0 Project Description

North East Ferro Alloys’ Co. (P) Ltd., is having its registered office at Vill.- Suboljote,

P.O.- Nemai, P.S.- Matigara , Dist.- Darjeeling, in the state of West Bengal. With the

favourable change in the industrial climate, the directors have decided for an expansion of

production capacity at their plant at Village: Suboljote, P.O- Nemai, via Matigara, P.S –

Matigara, Dist.- Darjeeling, West Bengal-734010 on a plot of land, measuring 6757.67 Sq.m

(1.67 acres).

The details of production capacity of existing and after expansion are listed in Table E-2.

Table E.2: Details of Production Capacity

Product Capacity Existing Proposed Total After Expansion

MS Billets/ Ingot 28800 TPA 1,08,000 TPA 1,36,800 TPA

2.1 Land Requirement

The total land available under the ownership of North East Ferro Alloys‟ Co. (P) Ltd is 6757.67

Sq. m (1.67 Acres). The proposed expansion activities will be carried out within the existing

industrial premises itself. Hence no additional land will be required for the proposed expansion.

The details of land-use breakup of the existing plant and after the proposed expansion are given

in Table-E-3.

Table E.3: Details of Land use Break-Up

S. No. Land Use

Area (SQM)

Percentage

(%)

Area

(SQM) Percentage (%)

Existing Proposed

1

Total Land

Area 6757.67 100 6757.67 100.00

2

Main factory

Shed Area 1890.805 27.98 1890.805 27.98

3

Office Block

Area 97.5 1.44 97.5 1.44

4 Green Area 621.71 9.2 1000* 14.80

5 Parking Area 125 1.84 125 1.85

6

Other shades &

Structures 1135 16.8 1135 16.80

7

Road & Paved

area 450.36 6.66 450.36 6.66

8 Vacant Land 2437.3 36.08 2059.005 30.47

*Compensatory Plantation: The project proponent will develop a green area in an adjacent

area to the project site on a land measuring 1298 Sq.m as compensatory plantation. Hence

total green area developed after proposed expansion will be 1000 Sq.M + 1298 Sq.M= 2298

sq.m which will be 34% of the total land area 6757. 67Sq.M. The adjacent land belongs to the

director of the company.

6

2.2 Raw Material Requirement

The details of requirement of raw materials, sources and their mode of transport are given in

Table E.4.

Table E.4: Details of Raw Material for Ms Ingots/Billets

S.

No.

Raw

Material

Existing Proposed Total Source

Mode of

transport Consumption

1 Sponge Iron 25,200 94,500 1,19,700 Odhisa,

Jharkhand

Durgapur

Truck

2 M.S. Scrap 6,480 24,300 30,780 Local Truck

3 Ferro Silicon 14.4 54.00 68.4 Kolkata Truck

4 Ferro

Manganese 334 1205 1,539 Kolkata Truck

5 CPC Coke 180 675 855 Durgapur,

Dhanbad

Truck

Power and Fuel Requirement

The details of power and fuel requirement for existing and after expansion are shown in

Table E.5 & Table E.6 respectively.

Table E.5 Details of Power Requirement

Phase Demand Source

Existing 3.4 MW West Bengal State Electricity Distribution

Company (WBSEDCL) Proposed 6 MW

Back up 125 kVA x1 D.G Set (Proposed)

Table E.6 Details of Fuel Requirement

Fuel Name Point of use Source Quantity

Diesel 1 x 125 KVA DG set

(Proposed)

Local Suppliers 20 lit/Hr

2.3 Water Requirement

For industrial cooling purpose, around 380 KL water will be required from where around 342

KL water will be recycled. Another 5 KLD water will be required for plantation and

sprinkling purpose. Total fresh water requirement will be 47 KLD. The source of water is

Ground water. The water balance is given in Figure E-3.

7

Figure E-3: Water balance diagram

2.4 Manpower Requirement

The project has an existing employment of around 95 people where the local workforce has

been given preference. No additional manpower employment is expected after the proposed

expansion.

2.5 Manufacturing Process Description

M.S. ingots are manufactured by melting of M.S scraps in induction Furnaces and casted in

cast iron moulds to get ingots. The raw material required for the manufacture of M.S ingots

are M.S scrap obtained from the open market. Required quantities of M.S scraps from the

stock yard are transported through trucks into the furnace yard by the electro magnet and

crane fed into furnace. A minimum manual shovelling is required. The molten metal in the

induction Furnaces is poured into the cast iron moulds. The ingots are cooled and separated from

the Moulds.

INDUCTION FURNACE:

It is like a transformer with induction coil acting as primary and the charge acting as secondary.

In order to improve the power factor, capacitor banks are incorporated in the circuit. The greatest

Total Water Requirement

389 KLD

[Fresh Water 47 KLD

Recycled Water 342 KLD]

Industrial Cooling

380 KLD

Clean Water Tank

342KLD

Evaporation

Loss

38 KLD

Plantation & Sprinkling

5 KLD

Domestic Usage

4 KLD

Sewage Water

2.75 KLD

Septic Tank

Soak Pit Recycle

8

advantage of the induction furnace is its low capital cost compared with other types of meeting

units.

Its installation is relatively easier and its operation is simpler. Among other advantages, there is

very little heat loss due to rotation from the furnace as the bath is constantly covered and there is

practically no noise attending its operation. The molten metal in an induction furnace is circulated

automatically by electro-magnetic action so that when alloy additions are made, a homogeneous

product is ensured in minimum time. While making mild or carbon steel in an induction furnace,

the primary consideration is the optimum utilization of the furnace as well as elimination of

delays.

THE CHARGE:

Scrap constitutes the major raw material for steelmaking in the induction furnace. The charge

should be compact and should consist of a number of small pieces of steel selected steel scrap

mixed with clean turnings, borings, and a moderate amount of heavy melting of commercial

grade. This is to provide the initial conditions of a high flux path through the charge for

facilitation generation of heat and commencement of melting. As soon as the furnace is charged,

the switches admitting current to the induction coil are closed.

MELTING THE CHARGE:

The furnace is turned on, current starts flowing at a high rate producing an induced magnetic

field inside the central space of the coils where the crucible is located. The induced magnetic flux

thus generated cuts through the highly resistive path of the scrap mix, generates tremendous

amount of heat and melting of scrap starts. The magnetic flux can be controlled by varying input

of power to the furnace. Soon, pool of molten metal forms at the bottom causing the charge to

sink. Any remaining charges are added at this point gradually.

The scrap charged into the furnace gets heated and melted at a temperature of about 1200˚C to

1670 ˚C. As soon as the charge has melted clearly, any objectionable slag is skimmed off, and the

necessary alloying elements are added. When these additives also melt, temperature is increased

by increasing the power input to bring it up to the point most desirable for pouring. The current is

then turned off and molten material is poured, the furnace crucible is tilted by means of hydraulic

system and the molten material is poured into iron moulds. This gets cooled to form the finished

product - M.S. ingots. The moulded material is rolled with roller machine thereafter.

9

The manufacturing process flowchart of MS Billets is shown in Figure E-4.

Figure E-4: Process Flowchart of M.S Billets/M.S Ingots

3.0 Description of Environment

The 10 km radial distance from the existing plant boundary has been considered as study area for

Environmental Impact Assessment (EIA) baseline studies. Environmental monitoring for various

attributes like meteorology, ambient air quality, surface and ground water quality, soil

characteristics, noise levels and flora & fauna have been conducted at specified locations and the

secondary data collected from various Government and Semi-Government organizations.

Baseline Environmental monitoring studies for the various environmental attributes were carried

out during 1st December 2019 to 29

th February 2020. The details of the baseline study are

presented as follows:

3.1 Meteorology

Preparation of Charge, C.I. Scrap, Sponge Iron etc

Charging in Induction Furnace

Melting Refine Smoke to Air through

APCD system

Slag

Adding to Ferro Alloy

Temperature Control 1600 ±20 ºC

CCM

Billet/Ingot

Physical Testing

Checked

10

The meteorological parameters were recorded on hourly basis during the study period near

proposed project site and the summary of meteorological data generated at site is presented in

following Table E.7.

Table E.7: Summary of the Meteorological Data generated at Site

Period Wind Speed (m/s) Temp (°C) Relative Humidity (%) Rainfall

(mm) Max Min Max Min Max Min

December 2019 3.6 0.8 28 13 80 9 0

January 2020 4.4 0.3 25 12 82 25 0.1

February 2020 4.7 0.6 31 13 79 20 0.1

3.2 Air Environment

8 ambient air quality monitoring stations were selected in and around the project site and

studies were carried out as per CPCB standards.

PM10: The maximum value for PM10 is observed at AAQ4, as 110.5 µg/m3, while the

minimum value observed at AAQ2, as 77.7 µg/m3 during the study period.

PM2.5: The maximum value for PM2.5 is observed at AAQ8, as 49.4 µg/m3 with the minimum

value observed at AAQ6, as 24.6 µg/m3 during the study period.

SO2: The maximum value for SO2 is observed at AAQ1, as 8.7 µg/m3 with the minimum

value observed at AAQ6, as 5 µg/m3 during the study period.

NO2: The maximum value for NO2 is observed at AAQ7, as 45.2 µg/m3 with the minimum

value observed at AAQ6, as 21.3 µg/m3 during the study period.

O3: The maximum value for O3 is observed at AAQ4, as 39.8 µg/m3 with the minimum value

observed at AAQ6, as 23.4 µg/m3 during the study period.

NH3: The maximum value for NH3 is observed at AAQ7, as 29.5 µg/m3 with the minimum

value observed at AAQ3, as 17.6 µg/m3 during the study period.

3.3 Noise Environment

The noise monitoring has been conducted for determination of noise levels at 8 locations in

the study area. Noise level of the study area varied from 59.4 to 72.2 dB (A) in day time and

from 37.4 to 55.4 dB (A) in the night time, which are well within the limits as per ambient

noise standards.

3.4 Water Environment

Ground Water Quality

11

The analysis results indicate that the pH ranges in between 6.73 to 8.07, which is well

within the specified standard of 6.5 to 8.5. The minimum pH value was observed at

GW4; the maximum pH value was observed at GW2.

Total hardness was observed to be ranging from 50.2 to 105.4 mg/l. The minimum

hardness was recorded at GW4 and the maximum was recorded at GW1.

Chlorides were found to be in the range of 21.4 to 51.6 mg/l, the minimum

concentration of chlorides was observed at GW5, whereas the maximum value was

observed at GW2.

Sulphates were found to be in the range of <5.0 to 19.7 mg/l. The minimum value

observed at GW3, 4, 5 whereas the maximum value observed at GW2.

The Total Dissolved Solids (TDS) concentrations were found to be ranging in between

60.4 to 186.9 mg/l, the minimum TDS observed at GW4 and maximum concentration

of TDS observed at GW2.

Surface Water Quality

The analysis results indicate that the pH values in the range of 6.18 to 7.82, the minimum

value was observed at SW8 and maximum value was observed at SW7

DO was observed to be in the range of 2.2 to 6.6 mg/l. The minimum DO value was

observed at SW8 and maximum DO was observed at SW3.

The TDS was observed to be in the range of 50.2 to 81.7 mg/l. The minimum DO value

was observed at SW2 and maximum DO was observed at SW8.

Sulphates were found to be in the range of 6 to 9.5 mg/l.

Total hardness expressed as CaCO3 ranges between 26.3 to 46.2 mg/l.

The calcium & magnesium were found to be in the range of 6 to 11.6 mg/l and 3.3 to 8

mg/l, respectively.

Surface Water quality is in accordance with Class A: SW1, SW2, SW4, SW6, Class B:

SW3, SW5, SW7 ans SW8 will fall into Class D as per CPCB classification.

3.5 Soil Quality

A total of 8 samples within the study area were collected and analysed.

It has been observed that the pH of the soil in the study area varied from 6.98 to 8.44. The

minimum pH value was observed at S5 where as the maximum value was observed at S2.

The electrical conductivity was observed to range from 740 to 1840 μ mhos/cm, with the

maximum observed at S7 with the minimum observed in S2.

The nitrogen value was found between the range of 0.024 to 0.114 mg/kg

3.6 Ecology and Biodiversity

On the basis of field studies, records of Botanical Survey of India and Forest department,

West Bengal state did not indicate the presence of any endangered and/or vulnerable species

in this area and there are no reserved, protected or village forests at a distance of 10-km from

the existing plant boundary. No species in the study area belongs to Schedule I, of Wildlife

12

Protection Act, 1972 and there are no endangered, threatened wild animal species in study

area.

3.7 Socio Economics

The total population of the study area as per the Census of 2011 is 513264 persons. There are

about 115957 households in the study area and the average size of household is 4 members

per household. The sex ratio of the area is 946 (females) per 1000 (Males). In the study area

the average literacy rate is 77.1%, whereas 22.9 % population is Illiterate. Out of total literate

population the male literacy is 41.2% and female literacy is 35.8% in the study area.

4.0 Anticipated Environment Impacts and Environment Management Plan

Impact on Soil

The soil quality remains the same as the proposed expansion does not involve a change in

land use pattern. The airborne fugitive dust from the plant is likely to be deposited on the

topsoil in the immediate vicinity of the plant boundary. However, the fugitive emissions are

likely to be controlled to a great extent through pollution control measures like water

sprinkling and the greenbelt development

Impact on Air Quality

Particulate Matter (PM), Sulphur dioxide (SO2) and Oxides of Nitrogen (NOx) will be the

major pollutants emitting from the proposed expansion. In order to control the emissions of

particulates, the pollution control equipment is proposed. Adequate stack height and APC

system has been provided to disperse gaseous emissions over a wider area.

Gaseous Emission Control Measures: A 360° swing suction hood is provided just above

crucible at required height to have effective suction of gases and fumes. Flue gases from the

furnace will be passed through hood into duct and through duct to spark arrestor.

Impact on Water Quality & Management

The total water requirement will be around 389 KL per day, out of which 4 KL will be used

for domestic purpose from where around 2.75 KL sewage water will be generated which will

be flowed to septic tank followed by soak pit.

For industrial cooling purpose, around 380 KL water will be required from where around

342KL water will be recycled. Another5 KLD water will be required for plantation and

sprinkling purpose. For the cooling makeup water and other purpose, total fresh water

requirement will be 47 KLD.

The source of water is Ground water.

Impact due to Solid Waste Generation

In order to avoid problems associated with solid waste disposal, an effective solid waste

management system will be followed. Hence, the impact due to solid waste generation during

13

the plant operation is not envisaged. The sources, quantity of the solid waste generation and

waste management measures for existing and after the proposed expansion are presented in

Table E.8.

Table E.8: Details of Solid Waste Generation

Particulars Waste Quantity Treatment/ disposal

Type of Waste Total Quantity

Industrial Solid

Waste (TPM)

Iron Slag from

Billet

932 MT/Month Slag will be crushed and metal part

will be recovered by magnetic

separator and rest part will be used

for road construction

Dust from air

APC system

135 MT/Month Dust will be packed in HDPE bags

and stored in Godown and the same

is transported to Fly Ash brick

manufacturing unit

Municipal Solid

Waste (kg/ day)

Wet Garbage 7 kg/day As per MSW Rules

Dry Garbage 17 kg/ day

Impact on Noise levels

The major noise generating sources are from cooling tower, Air Compressors, Transformer,

DG sets, loading & unloading operation.

Noise Attenuation Measures

The following control measures will be implemented for the proposed expansion project:

All the design/installation precautions as specified by the manufacturers with respect to

noise control will be strictly adhered to;

High noise generating sources will be insulated adequately by providing suitable

enclosures;

All the necessary noise protective equipment will be supplied to workmen operating near

high noise generating sources.

The air compressor, DG sets, transformer will be provided with acoustic enclosure;

Other than the regular maintenance of the various equipment, ear plugs/muffs will be

recommended for the personnel working close to the noise generating units;

Furnace operators will be protected by enclosing the source of noise with sound

deadening material or by providing sound-proofed shelters.

Construction of noise protection wall at the scrap yard; and

Adequate greenbelt is also being developed in the plant boundary of the steel plant.

14

Impact on Ecology

The proposed expantion will be done in the existing premises. So no tree cuttion will be

required. The impacts on aquatic ecology due to the proposed expansion activity would be

negligible as the treated water will be properly reused and no waste water is discharged

outside the plant premise. The proposed expansion does not create any significant impact on

aquatic bodies also.

Impact on Public Health

The discharge of waste materials (stack emission, wastewater and solid wastes) from process

operations could have some adverse impact on public safety and health in the surrounding

area, if appropriate treatment procedures are not followed. As the plant pollution control

equipments will be designed as per the modern available technology for controlling the

impacts, no adverse impacts on public health in the area are anticipated.

5.0 Analysis of Alternative Sites and Technology

The proposed expansion will take place within the existing plant premises itself. Therefore,

no additional land will be acquired for the proposed expansion. The technologies mentioned

for production of MS Ingots very well proven technology for over a period of time all over

the world. In view of the above no technological failures are anticipated. Hence no alternative

technologies are considered.

6.0 Environmental Monitoring Program

The environmental monitoring program is important in terms of evaluating the performance

of pollution control equipment‟s installed in the project. The sampling and analysis of the

environmental attributes will be as per the guidelines of CPCB/WBPCB. The frequency of

air, noise, surface water and ground water sampling and location of sampling will be as per

the directives of West Bengal Pollution Control Board.

Budgetary Allocation for Environmental Protection

The total project cost for the proposed expansion project is about Rs. 1637 Lakhs. An initial

budget of Rs.33.0 Lacs to be made on the following heads as included in the project cost in

the proposed project. The recurring cost is estimated to be around Rs. 5.8 lakhs per annum.

Table E.9: Expenditure Proposed for Environmental Protection Activities

S. No. Particulars Capital Cost Lacs Recurring Cost in Lacs

1. Air Pollution Control equipments 14.0 1.25

2 Rain water harvesting system 2.0 0.25

3. Plantation 2.0 0.25

4. Miscellaneous safety including fire

fighting purpose

1.5 0.25

5 Environmental Monitoring & 5.5 3

15

S. No. Particulars Capital Cost Lacs Recurring Cost in Lacs

Management

6 Occupational Health 8.0 0.8

Total 33.00 5.8

7.0 Additional Studies

To tackle the consequences of a major emergency inside the project premises or its

immediate vicinity, a Disaster Management Plan has been formulated and this planned

emergency document is called “Disaster Management Plan”. The objective of the Disaster

Management Plan is to make use of the combined resources of the steel melting plant and the

outside services, to achieve the following:

Effect the rescue and medical treatment of casualties;

Safeguard other people;

Minimize damage to property and the environment;

Initially contain and ultimately bring the incident under control;

Identify any dead;

Provide for needs of relatives;

Provide authoritative information to the media;

Secure the safe rehabilitation of affected area; and

Preserve relevant records and equipment for the subsequent inquiry into the cause and

circumstance of the Emergency.

Occupational Health & Safety Measures

Large projects where multifarious activities are involved during construction, erection,

testing, commissioning, operation and maintenance, the men, materials and machines are the

basic inputs. Along with the benefits, the industrialization generally brings several problems

like occupational health and safety. The industrial planner therefore has to take steps to

minimize the impacts and to ensure appropriate occupational health and safety in the steel

melting plant and rolling mill. The following measures are proposed:

Conducting awareness programs at regular intervals to the employees

Providing safety kits and prevention kits

Provision of Clinic at the project site to handle emergency situations that may arise

8.0 Project Benefits

The Proposed expansion project will have indirect positive impact on surrounding area which

is as mentioned below:

The proposed expansion project will be carried out on the existing land of M/s North East Ferro Alloys‟ Co. (P) Ltd., .; hence no displacement of people is required

Substantial Socio-economic benefits

Good Techno-commercial viability

Around the project site semi-skilled and unskilled workmen are expected to be available from local population in these areas to meet the manpower requirement during

construction phase.

16

Infrastructural facilities will be improved due to the project

Secondary employment will be generated thereby benefiting locals

Thus a significant benefit to the socio-economic environment is likely to be created due to the

project.

North East Ferro Alloys‟ Co. (P) Ltd. not only carries out business but also understands the

obligations towards the society. The unit is aware of the obligations towards the society and

to fulfill the social obligations unit will employ semi-skilled and unskilled labor from the

nearby villages for the proposed augmentation project as far as possible. Unit will also try to

generate maximum indirect employment in the nearby villages by appointing local

contractors during construction phase as well as during operation phase. The Project

Proponents will contribute reasonably as part of their Corporate Environmental

Responsibility (CER) in and will carry out various activities in nearby villages.

The total estimated cost of the proposed expansion is 1637 Lakhs. The project Proponent will

allot 1% of the project cost i.e. around 16.37 Lakhs (~16.4 Lakhs) towards the CER activity.

9.0 Environmental Cost Benefit Analysis

According to Appendix III of the EIA Notification 2006 and its subsequent amendments,

„Environment Cost Benefit Analysis‟ is applicable, if recommended at the Scoping stage. As

per the TOR approved by State Environmental Impact Assessment Authority, West Bengal

for the project Proposed Expansion for Production of M.S. Ingots/Billets by installation of

Induction Furnace at Village: Suboljote, P.O Nemai, Via Matigara, P.S –Matigara,

Darjeeling, by North East Ferro Alloys‟ Co. Pvt. Ltdl the Environmental Cost Benefit

Analysis is not applicable and hence not prepared.

10.0 Environment Management Plan

Environmental pollution during construction stage will be limited and for a temporary period

during the construction activity. Construction shall be planned in such a way that excavated

material shall be disposed safely. Directly or indirectly all the environmental components get

affected due to the construction activity. In order to mitigate the impacts due to capacity

expansion of facility on various environmental components, suitable environmental

management measures are recommended.

An Environment Management Cell will be earmarked for monitoring of pollutants and

development of greenbelt as per Environmental Management Plan. The Project proponent

will develop the environment cell, consisting of officers from various disciplines to

coordinate the activities concerned with the management and implementation of the

environmental control measures during construction and operation phase of the plant. They

will also develop a well-documented system to monitor and control pollution. Environmental

Management Cell (EMC) will meet at least once a month to assess the progress and analyse

the data collected for the month. Any deviation/variation noticed shall be immediately taken

17

into consideration for improvement of the same. Yearly action plan of EMP will be updated

with respect to results achieved and proposed activities for next year.

11.0 Disclosure of Consultants Engaged

This EIA report is prepared on behalf of the proponents, taking inputs from proponent‟s office

staff, their R and D wing, Architects, Project Management Professionals etc. by

Environmental Consultants M/s. Ultra-Tech Environmental Consultancy and Laboratory,

Thane.