executive summary - doe.gov.my · the project title for which this detailed eia report is prepared,...
TRANSCRIPT
MALAKOFF CORPORATION BERHAD
DETAILED ENVIRONMENTAL IMPACT ASSESSMENT OF A PROPOSED 2X1000MW EXTENSION AT
TANJUNG BIN COAL-FIRED POWER PLANT, MUKIM SERKAT, DAERAH PONTIAN, JOHOR DARUL
TAKZIM
Page xvi 054/80067: 00-EN-REP-0001-0 Rev 0 : 25 July 2011
EXECUTIVE SUMMARY
1 PROJECT TITLE
The Project title for which this Detailed EIA Report is prepared, is known as the “Proposed 2x1,000
MW Extension at Tanjung Bin Coal-Fired Power Plant, Mukim Serkat, Daerah Pontian, Johor Darul
Takzim” (hereinafter known as the “Project”).
The project is to be located within the existing 3x700 MW Tanjung Bin power plant land holding. The
existing power plant is located on the western bank of Sg. Pulai estuary. Road access to the power
plant is via the Federal Route 95 to Permas Kecil, and a local road Route J111 leading to the main
site access road.
The Project will occupy an area of about 235 acres (of the total 900 acres), which consist of two
power generating units of 1,000 MW each. Shared facilities with the existing plant will include the coal
unloading jetty, fly ash jetty, ash pond and main cooling water intake.
This Detailed EIA report has examined the potential environmental impacts on the extension of the
Project and assessed the cumulative impacts with the existing operation of the power plant.
2 STATEMENT OF NEED
Malakoff Corporation Berhad (MCB) is committed to providing a reliable and cost-effective electricity
supply to meet the current and future power requirements of the country. The provision of adequate,
reliable and low cost electricity is considered vital to the continuing economic success of Malaysia.
The total installed generation capacity in Peninsular Malaysia in 2010 is 21,817MW (Energy
Commission, 2010). The first-generation IPPs which have a collective generation capacity of around
3,353MW (Energy Commission, 2010) will expire in stages from 2014 to 2016. In addition, the
government has also shelved the planned 2000MW power import from Bakun to Peninsular Malaysia
in view of Sarawak’s own demand for energy to be used by heavy industries that will be built in the
state.
For the period of 2010 to 2020, the peak demand is expected to grow by 3.2% and is expected to
reach 18,000 MW by 2016. Given the cancellation of the Bakun submarine cable from East to West
Malaysia, expiration of the first generation IPPs concessions and expected increase in GDP growth,
there will be critical shortfall in Peninsular Malaysia’s power generating capacity and reserve margin
commencing from the end of 2014 onwards.
The power sector also faces a major challenge of lack of gas supply driven by depletion of domestic
gas resources. The gas supply to the power sector has been limited to 1350 mmscfd since 2002 and
further reduced to 1250 mmscfd effective March 2009 (TNB, 2010). With the rapid depletion,
Peninsular Malaysia can no longer rely heavily on domestic gas for electricity generation in the future.
MALAKOFF CORPORATION BERHAD
DETAILED ENVIRONMENTAL IMPACT ASSESSMENT OF A PROPOSED 2X1000MW EXTENSION AT
TANJUNG BIN COAL-FIRED POWER PLANT, MUKIM SERKAT, DAERAH PONTIAN, JOHOR DARUL
TAKZIM
Page xvii 054/80067: 00-EN-REP-0001-0 Rev 0 : 25 July 2011
LNG import is an alternative option for power generation, however, it poses a higher risk of price
volatility.
Considering all the above factors and the slower development in renewable energy, coal would be the
best option to meet the ever increasing power demand. In line with this, in the recently announced
10MP, the Government has identified coal-based power generation to address the shortfall in the
generation capacity.
MCB’s plan to develop the Project as an extension to the existing Tanjung Bin Coal-Fired Power Plant
is in line with the Government’s decision to reduce the country’s heavy reliance on natural gas for
electric power generation, and increasing coal’s share of electricity generation. MCB believes that
coal in particular can play a significant role in maintaining security of supply and generating capacity
in Malaysia. To this end, MCB is committed to providing a reliable and cost-effective electricity supply
to meet the current and future power requirements of the country, and to pursuing policies and
measures that aid the protection of the environment.
3 PROJECT OPTIONS
3.1 The “No Build” Option
Environmental Impacts
The “No Build” option refers to withdrawal of the Project and that the vacant land within the existing
power plant facilities would remain status quo, without any physical construction and development
activities. The existing site would remain as partially unutilised, comprises remnants of mangroves
and peat swamp forests retaining the existing undisturbed environment. The “No Build” option would
ensure the current habitats of mangroves and peat swamp forests would remain intact.
Economic Growth and National Development
Electricity demand in Peninsular Malaysia is growing at a phenomenal rate, driven largely by the
industrialisation of the nation. A strategic reserve margin shall be maintained to achieve system
stability and resilience, as one of the necessary conditions towards sustaining economic growth and
realizing Government’s Vision 2020 and Economic Transformation Programme of attaining a high
income status country.
The Government has given approval for MCB to develop an additional 1000MW within its existing Tg.
Bin site to meet this rise in demand. Sufficient generating capacity to balance the expected demand is
critical to support the Government’s Economic Transformation Programme which aims to transform
the country to become a high-income status country.
The “No Build” option is thus not an acceptable option.
MALAKOFF CORPORATION BERHAD
DETAILED ENVIRONMENTAL IMPACT ASSESSMENT OF A PROPOSED 2X1000MW EXTENSION AT
TANJUNG BIN COAL-FIRED POWER PLANT, MUKIM SERKAT, DAERAH PONTIAN, JOHOR DARUL
TAKZIM
Page xviii 054/80067: 00-EN-REP-0001-0 Rev 0 : 25 July 2011
3.2 The “Build” Option
The “Build” option assumes that the Project is constructed and operated as planned, is being viewed
as a source of pollution with the potential to adversely affect air quality, increase ambient noise levels,
degradation of marine water quality as well as causing nuisance impacts on neighbouring areas and
other environmental issues.
The “Build” option refers to the option to construct the Project and within the anticipated construction
schedule of 48 months, of which the first unit (Phase 1) of 1000 MW is to be commercially operational
by March 2016 and the consecutive unit (Phase 2) of up to 1000MW will be installed in a later phase.
Assessment of options on fuel, process technologies and air pollution controls have been considered
by MCB and are presented in Section 5.2 of the Main Report.
4 PROJECT DESCRIPTION
4.1 Introduction
This section presents the details of the technical design of the existing Tanjung Bin Unit 1, 2 and 3
and the proposed Unit 4 and 5. As the detailed design is currently unavailable, the information
presented on the Unit 4 and 5 forms an overall description of the envisaged plant and its operation,
based on the understanding and experience gained by MCB, and its consultant in the area of
supercritical boiler design. The final plant configuration will not be materially different from that
described and any changes will not have a significant impact on the environmental analysis.
4.2 Project Location
The Project comprises of two power generation units of 1,000 MW each (Unit 4 and 5), located within
its existing 3x700MW Tanjung Bin power plant land holding as well as additional land to the north of
the site for the substation extension. The existing power plant is located on the western shore of
Sungai Pulai estuary, near to the villages of Kampong Sungai Dinar and Kampong Sungai Sam,
about 25 km west of Johor Bahru. Road access to the power plant is via the Federal Route 95 to
Permas Kecil, and a local road Route J111 leading to the main site access road.
The site for the proposed new units is located immediately adjacent to the west of the main power
plant buildings, on PTD Lot 1770 and 1859, occupying an area of about 235 acres of the total area of
900 acres.
4.3 The Existing Power Plant (Unit 1, Unit 2 and Unit 3)
The existing main power plant buildings and operational areas are located generally in the eastern
area, and the coal stock yard, and the ash lagoon are located towards the west of the main plant
buildings. The land is basically low lying and flat, situated directly adjacent to the west shore of
MALAKOFF CORPORATION BERHAD
DETAILED ENVIRONMENTAL IMPACT ASSESSMENT OF A PROPOSED 2X1000MW EXTENSION AT
TANJUNG BIN COAL-FIRED POWER PLANT, MUKIM SERKAT, DAERAH PONTIAN, JOHOR DARUL
TAKZIM
Page xix 054/80067: 00-EN-REP-0001-0 Rev 0 : 25 July 2011
Sungai Pulai estuary from which the existing power plants abstract cooling water. The condenser
cooling water is subsequently discharged from the site via an outfall to Sungai Pulai. The existing
plant consists of the following key components:
• The power block, comprising of turbine buildings, steam generators with bunker bay and
subsection;
• The turbine building is executed as an enclosed steel structure. The three turbine-generators are
arranged longitudinally on concrete pedestals in parallel to the main structure of the building. The
main components of the feedwater system such as feedwater tank, boiler feed pumps, low and
high-pressure feed heater are located in a heater bay which forms an integral part of the main
structure;
• The boiler building is separated from the turbine building in order to allow the independent
construction of the two buildings and have two separate fire protection areas;
• The central switchgear building is implemented as a reinforced-concrete frame structure with
brick walls and also constitutes as an independent building in terms of fire protection regulations.
The central control room with adjacent rooms is located within this building;
• Flue gases are cleaned in the electrostatic precipitators (ESP) (to remove particulates) and flue
gas desulphurisation (FGD) (to remove sulphur compounds). Flue gases lead to a common stack
for the three units;
• The circulating water pumps are located in a separated building. The cooling water flow passes
through steel pipes to the turbine building from where it is led in steel piping to the condenser.
The return pipe is executed in steel pipes followed by concrete culverts up to the circulating water
seal pit which is part of the aeration basin of the FGD. The circulating water flows from here in an
open channel to the outfall structure;
• The chlorination building is located near the circulating water pump building;
• Coal as the main fuel is delivered by ships and unloaded at the jetty. It is transported to the coal
stockyard by means of conveyors. From there, conveyors lead to the coal bunkers in the bunker
bay;
• Bottom ash is transported to the ash pond, while fly ash is for the most part reused in cement
kilns. The switchgear and control center for the coal and the ash handling facilities is arranged
near the coal transfer tower;
• The demineralization plant with tanks and neutralization pit, the fire pump station, the fuel oil
pump station with oil unloading and transfer facilities are grouped together near the south side of
the facility;
• The administration building which includes the staff amenities facility and the workshop and
storage building are located near the intake; and
MALAKOFF CORPORATION BERHAD
DETAILED ENVIRONMENTAL IMPACT ASSESSMENT OF A PROPOSED 2X1000MW EXTENSION AT
TANJUNG BIN COAL-FIRED POWER PLANT, MUKIM SERKAT, DAERAH PONTIAN, JOHOR DARUL
TAKZIM
Page xx 054/80067: 00-EN-REP-0001-0 Rev 0 : 25 July 2011
• A coal-unloading jetty measuring 360 m in length and 30 m in width, capable of handling cape-
sized ships of up to 150,000 DWT.
The general plant layout plan is shown in Figure 6.2.1 and elevation view of the plant is shown in
Figure 6.2.2.
Existing Pollution Control Systems
The combustion process within PF-fired plant produces high levels of gaseous and solid emissions.
However, effective controls to minimise such emissions have been achieved through the application
of technologies to plant design features and downstream clean-up processes.
NOx emissions are controlled within the furnace through the use of low NOx burners, overfire air,
staged combustion and reburn. SOx and particulates are controlled by the use of low sulphur coal and
downstream clean-up processes including the Electro-Static Precipitator (ESP) and Flue Gas
Desulphurisation (FGD).The solid by-products from coal combustion are recovered mostly as fly ash
and bottom ash. Fly ash from the existing plant is reused as raw material by the cement industry.
Alternatively, it can be stored in an ash pond along with bottom ash.
In terms of wastewater management, the major source is from rain water runoff collected at the coal
yard. The runoff is stored in a collection sump for settlement of solids. Sufficient retention volume
within the sump allows settling of suspended solids prior to pumping the settled water to the Ash
Pond. All other waste waters are collected in the Pre-Retention Basin and Retention Basin of the
Waste Water Treatment Plant (WWTP). The wastewater then undergoes chemical treatment before
discharge.
4.4 The Proposed Power Plant (Units 4 and 5)
The Project comprises two power generating blocks of 1,000 MW each of similar design. Each block
will consist of one supercritical coal-fired boiler and tandem compound type turbine generator for
power generation. The Project will be executed in two phases.
The expansion will use mainly sub-bituminous coal as the primary fuel while Light Fuel Oil (LFO) as
start-up fuel. The Project will employ the most widely used method of burning coal for power
generation, i.e. Pulverised Fuel Combustion (PFC). Each coal-fired generating unit will be installed
with its respective air pollution control systems (APCs), including dust extraction system Fabric Filter
Plant (FFP) and a Flue Gas Desulphurisation (FGD) facility.
These units will be supported by auxiliary systems, a coal handling facility including a new coal jetty
(to be implemented in Phase 2), an ash handling system complete with a new ash pond (common
and to be shared with the existing plant), a once-through seawater cooling system and the
powerhouse. The Project will also share some facilities with the existing plant such as auxiliary jetty,
fly-ash jetty and raw water supply. Facilities such as coal unloading jetty, interconnection facilities and
cooling water intake will also be shared but with some upgrades to cater for the additional capacity.
MALAKOFF CORPORATION BERHAD
DETAILED ENVIRONMENTAL IMPACT ASSESSMENT OF A PROPOSED 2X1000MW EXTENSION AT
TANJUNG BIN COAL-FIRED POWER PLANT, MUKIM SERKAT, DAERAH PONTIAN, JOHOR DARUL
TAKZIM
Page xxi 054/80067: 00-EN-REP-0001-0 Rev 0 : 25 July 2011
The power generating blocks will be connected to the National Grid via the existing transmission lines
as well as a new transmission line to be constructed by Tenaga Nasional Berhad (TNB).
Major difference between the current proposed Project concept with the existing plants is in terms of
combustion technology and pollution control technology, as summarised below.
Combustion Technology
While the existing plant was built as a subcritical coal-fired power plant, the proposed Project will be
employing a supercritical coal-fired power plant technology. Supercritical steam cycles can achieve
over 4% higher total efficiency improvement compared to the more common systems and results in a
reduction of almost 10% coal consumtion to produce each kWh of electricity and consequently
translates into lower air emission intensity.
Pollution Control Technology
Similar to the existing plant, the Project will utilize seawater FGD to control SO2 and a combination of
low NOx burners, staged combustion and overfire air to control NOx formation. In contrast to the
existing plant which uses ESP, fabric filter plant has been selected to control PM emissions for the
Project. While both technologies serve the same purpose, fabric filter plant has been proven to be
able to handle higher ash resistivity and remove fly ash more effectively compared to ESP. The use of
fabric filters will enable the Project to meet the Malaysian and World Bank air emission standards.
Process Description
The electricity generation process adopted for the Project is of the same thermal technology to the
existing power plant, i.e., Pulverised Fuel Combustion (PFC). The principal process units for the
Project are described as follow:
Coal Pulveriser
The proposed pulveriser is capable of handling the expected range of coals. The type of pulveriser
utilised is of the vertical spindle mills or equivalent.
Steam Generator
The steam generator is of supercritical once-through type design, single reheat type and consisting of
water-cooled furnace, superheaters, reheaters and economizers. Its function is to produce high-
pressure steam for electricity production at the steam turbine. The firing system will be equipped with
advance low NOx vortex type coal burners with oil gun on the centreline of the burner. Staged
combustion with over-fire air supply is implemented for further NOx reduction and best burn-out of
coal particles.
Steam Turbine
The Steam Turbine (ST) proposed is of the supercritical design in the range of 25 MPa to 28 MPa and
566°C to 606°C tandem-compound reheat unit. The steam enters the HP section of turbine,
MALAKOFF CORPORATION BERHAD
DETAILED ENVIRONMENTAL IMPACT ASSESSMENT OF A PROPOSED 2X1000MW EXTENSION AT
TANJUNG BIN COAL-FIRED POWER PLANT, MUKIM SERKAT, DAERAH PONTIAN, JOHOR DARUL
TAKZIM
Page xxii 054/80067: 00-EN-REP-0001-0 Rev 0 : 25 July 2011
expanding toward the front end, exhausting to the reheater. The reheated steam re-enters the IP
cylinder and expands toward the generator and through the low pressure cylinders. Each steam
turbine will be supplied with auxiliaries including a lubricating oil system, gland steam sealing system,
turbine protection and trip system, turbine bypass system, turbine drain system, LP exhaust spray
cooling system, seal oil system, generator cooling system and gas control and distribution (H2 and
CO2).
Electrical System
The electrical generator is mechanically driven by its steam turbine, electrically excited by the static-
excitation system, and internally cooled by gaseous hydrogen. The power output by each generator is
fed mainly through the generator transformer to the 500 kV substation and from there via
transmission to the National Grid. The generator is completely enclosed and in operation uses
hydrogen as a cooling medium. The ventilation system including the fans and hydrogen coolers is
self-contained and completely enclosed to prevent ingress of dirt and moisture. The generator is
designed for continuous operation and is constructed to withstand sudden change in load and three-
phase short circuit. Various kinds of supervising and controlling instruments are provided to keep the
generator in satisfactory operation.
Power Transformer
Additional power transformer are to be constructed which includes generator transformer and unit
transformers which will be of outdoor use, three-phase, oil immersed, two or three winding type.
Substations
The Project will be connected to an extension of the existing substation for its additional power supply
to the National Grid. The 275 kV and 500 kV existing substations are of the conventional outdoor type
with a 1½ breaker scheme for the 500 kV and single breaker scheme for the 275 kV, respectively.
The existing substation shall be extended to the northern section, by two additional diameters to
accommodate the Project.
Instrumentation and Control System
The generating units are designed to be operated from the Central Control Room (CCR). A
microprocessor-based, distributed control-and –supervision system (DCS) of proven type will be used
for unit control, alarm, fault sequence printing supervision monitoring, interlock and protection. The
Project major auxiliary systems (i.e. coal-handling, ash-handling etc) will have independent control to
be performed from respective control rooms. Monitoring of the auxiliary systems which are essential
for on-line coordination will also be made possible from the plant’s CCR.
Fuel Management
Coal will be the primary fuel to be used for the Project while LFO will be used only during start-up,
shut down, mill changeover and for support firing. The simplified coal management system consists
of:
MALAKOFF CORPORATION BERHAD
DETAILED ENVIRONMENTAL IMPACT ASSESSMENT OF A PROPOSED 2X1000MW EXTENSION AT
TANJUNG BIN COAL-FIRED POWER PLANT, MUKIM SERKAT, DAERAH PONTIAN, JOHOR DARUL
TAKZIM
Page xxiii 054/80067: 00-EN-REP-0001-0 Rev 0 : 25 July 2011
(i) Coal unloading system where the coal is unloaded using two continuous bucket unloaders and
one new grab type unloader (existing jetty) and two new grab type unloaders (new jetty), and
then transferred onto the conveyor belt system;
(ii) Incoming system in which coal will be transported to the new coal yard via belt conveyor
system;
(iii) New coal storage yard, where in Phase 1, will be provided with a one bucket-wheel
stacker/reclaimer and an emergency drop-off and reclaim hopper and two bulldozers. In Phase
2, the new coal yard will be extended and provided with one additional bucket wheel
stacker/reclaimer; and
(iv) Outgoing system comprises the stacker/reclaimers, conveyer system in the coal yard and
conveyor systems leading to the coal bunker bays at the boilers.
The coal storage yard is arranged in an open-stockpile configuration, with a capacity of approximately
30 days supply.
The coal handling system will be similar to the existing plant. It is divided into two sections, namely
receiving /storage and reclaiming sections. Each section is to be controlled individually from the coal
handling control building.
The Light Fuel Oil (LFO) system will be designed to receive LFO from road tankers. The unloading
bays are used and each unloading bay is connected to the LFO unloading pump. A common
discharge manifold connects the pumps to the fuel oil storage tank. One 3,000 m3 LFO storage tank
with a bund wall is provided for start up of each unit. The bund wall will be provided around the tank
with a capacity to hold 110% of the volume of one storage tank and to ensure accidental spillage is
contained within the bunded area. The LFO forwarding system consists, for each unit, of two
forwarding pumps which pump the LFO from the tank to main boiler, two forwarding pump to feed the
emergency diesel generator, the fire fighting pump diesel and auxiliary boilers and one pump for LFO
truck vehicle filling.
Auxiliary Process Components
Water Steam Cycle
The water steam cycle essentially comprises of the super-critical steam generator, the steam turbine
with condenser, main condensate pumps, low pressure (LP) and high pressure (HP) feedwater
heaters, deaerator/feedwater storage tank, feedwater pumps and the connecting piping.Condensate
System
At the condensers, the exhausted steam from LP section will be condensed and store in condenser
hot-well. The hot-well water will be pumped up by means of 50% condensate pumps (2 units on duty
while 1 unit on standby) and be transferred to the deaerator through gland steam condenser and LP
feedwater heaters. Make-up water, for initial filing and during plant operation, will be directly supplied
from condensate reserve tank to condenser by means of make-up pumps.
MALAKOFF CORPORATION BERHAD
DETAILED ENVIRONMENTAL IMPACT ASSESSMENT OF A PROPOSED 2X1000MW EXTENSION AT
TANJUNG BIN COAL-FIRED POWER PLANT, MUKIM SERKAT, DAERAH PONTIAN, JOHOR DARUL
TAKZIM
Page xxiv 054/80067: 00-EN-REP-0001-0 Rev 0 : 25 July 2011
Feedwater System
This system serves to provide feedwater collected from the condensate system to the boiler plant.
The feedwater system consists of the deaerator and the Boiler Feedwater Pumps (BFPs) and HP
heaters.
Cooling Water System
Sg. Pulai is the source of water for plant cooling processes. The water intake, common with the
existing power plant, is located at the river mouth of Sg. Pulai. The closed cooling water system is
designed as a loop and serves to transfer the heat dissipated by components or their auxiliary cooling
water via the closed water heat exchangers. The cooling water system essentially comprises the
Circulating Seawater System (CSW), auxiliary cooling water system, Closed Cooling Water System
(CCWS) and electrochlorination plant.
The CSW is of the once-through design, which meets the cooling water requirements mainly of the
condensers, auxiliary cooling water system and supply sea water to the electrochlorination plant of
the unit. The main functions of the CSW system are to supply with cooling water by means of the
circulating water pumps to the turbine condensers and the auxiliary cooling water system. The system
discharge the warmed-up water from the condenser and auxiliary cooling water system to circulating
water seal pit and finally to the outfall.
The auxiliary cooling water system is to absorb heat transferred from the vacuum pumps and closed
cooling water system, which cools individual components of the power plant via the closed cooling
water heat exchangers, the second of these is on standby.
The CCWS will circulate demineralised water to cool components of the power plant and transfers the
heat dissipated by components to the auxiliary cooling water system. The system will be designed for
adequate supply of cooling water as required by the plant equipment, and will generally consist of
heat exchanger, pump and expansion tank. The phosphate dosing system will supply chemicals to
the CCWS.
The electrochlorination plant performs chlorination which aims to prevent slime and marine growth
build-up in the seawater system. Chlorination is performed by injection of sodium hypochlorite
solution (produced by seawater electrolysis) near the cooling water intake.
Plant Supporting Equipment
The Project will be furnished with Auxiliary Power System (APS) to supply power to all supporting
components (i.e. pumps, fans, drives, control system, lighting etc), and will be equipped with
Emergency Diesel Power Generator (EDG) to supply emergency power in case of an outage. Direct
current (DC) supplies will be maintained by batteries for a minimum safe period in the event of loss of
power supply and this is applied to emergency motors, static inverters, emergency lighting,
switchgear control and relays and instrumentation. The Project is also equipped with protection
system for electrical system (in particular HV-side) and Fire Alarm and Protection System according
to Bomba and National Fire Protection Association (NFPA) requirement.
MALAKOFF CORPORATION BERHAD
DETAILED ENVIRONMENTAL IMPACT ASSESSMENT OF A PROPOSED 2X1000MW EXTENSION AT
TANJUNG BIN COAL-FIRED POWER PLANT, MUKIM SERKAT, DAERAH PONTIAN, JOHOR DARUL
TAKZIM
Page xxv 054/80067: 00-EN-REP-0001-0 Rev 0 : 25 July 2011
Material Balance
Coal is to be primarily sourced from Indonesia as well as other countries which have similar coal
characteristics (i.e. Australia and South Africa). Approximately 428 t/hr of coal will be fed into the
boiler for one (1) power generation unit of 1,000MW. The burnt pulverised coal will produce bottom
ash (1.0 t/hr including unburned carbon) of which will be collected by the furnace hopper while a total
of 5.5 t/hr of fly ash to be captured by the fly ash system from Flue Gas Desulphurisation (FGD)
system.
The amount of raw materials required and by-products produced by each power generating block and
both is summarised in Table 6.7.2 and Figure 6.7.1 of the Main Report.
The estimated water consumption for cooling processes (seawater from Sg. Pulai) is approximately
400,000 m3/hour which includes the water usage for the seawater FGD system. The water balance
showing process water consumption of the Project is presented in Figure 6.7.2 of the Main Report.
Pollution Control System and Management
Combustion Air and Flue Gas System
The boiler facility is equipped with the required combustion air and flue gas system. The combustion
system consists of:
• 2 x 50% Forced Draft Fans (FDF) to provide combustion air in the form of secondary and
tertiary (overfire) air.
• 2 x 50% Primary Air Fans (PAF) to dry the coal in the mills and transport the pulverised coal
to the burners.
• 2 x 50% Regenerative Air Preheaters (RAPH)
• 2 x 50% Induced Draft Fans (IDF) to abstract the ensuing flue gas from the boiler via the
RAPHs and the FFPs prior to transporting the flue gas to chimney.
NOx Control Systems
There are seven oxides of nitrogen including nitrous oxide (N2O), nitric oxide (NO), dinitrogen dioxide
(N2O2), dinitrogen trioxide (N2O3), nitrogen dioxide (NO2), dinitrogen tetroxide (N2O4) and dinitrogen
pentoxide (N2O5). Of these, NO and NO2 are the most common emissions and the ones most heavily
regulated. There are three mechanisms by which NOx can be formed during combustion.
Fuel NOx is formed when nitrogen in the fuel is oxidized.
CxHyN � HCN � � CN
(HCN � � CN) + O2 � NO
MALAKOFF CORPORATION BERHAD
DETAILED ENVIRONMENTAL IMPACT ASSESSMENT OF A PROPOSED 2X1000MW EXTENSION AT
TANJUNG BIN COAL-FIRED POWER PLANT, MUKIM SERKAT, DAERAH PONTIAN, JOHOR DARUL
TAKZIM
Page xxvi 054/80067: 00-EN-REP-0001-0 Rev 0 : 25 July 2011
Prompt NOx is formed when nitrogen in the combustion air combines with fuel under fuel rich
conditions and is then oxidized along with the fuel during combustion.
CHx + N2 � HCN � � CN
(HCN � � CN) + O2 � NO
Thermal NOx is formed when the nitrogen molecules in the combustion air are oxidized at
temperatures above 760°C.
N2 + O2 � 2NO
The formation of NOx during combustion in the boilers is controlled through the use of low NOx
burners and air staging. By staging combustion over a period, much of which is sub-stoichiometric, it
prevents the formation of NOx from the N2 of the fuel. It also reduces NOx formation from nitrogen in
the combustion air without the use of chemicals.
Dust Filter Plant (DFP) Systems
Flue gases leaving boiler will pass through the regenerative air heater to the DFP. The gas shall be
drawn by the induced draught fans into the chimney and released into the environment. The function
of DFP is to remove fly ash from the flue gas stream exiting the boiler. The combustion of fossil fuels
results in residues called bottom ash and fly ash. Bottom ash consists of the heavier ash particles
which fall out the flue gas stream into the furnace bottom hopper and slag and coke deposits which
are dislodged from the furnace during soot blowing. Fly ash consists of very fine, lighter particles of
ash that are carried out of the furnace by flue gas. The flue gas stream is directed through the
precipitator where almost all of the fly ash is removed from the flue gas. There are two basic
principles for a DFP, namely an Electrostatic Precipitator (ESP) or a Fabric Filter Plant (FFP). A FFP
will be employed for this Project. In a FFP, also known as Bag Filter Plant, the particulate known as
pulverised fuel ash (PFA) is collected along long fabric bags in a tubular shape, through which the
flue gas passes from the outside to the inside. The filter bags collect the dust on the outside as the
flue gas flows into them, and the clean flue gas leaves the filter bags at the top. In order to remove
the dust from the filter bags, the bags are cleaned by a blast of compressed air from the inside, which
dislodges the dust which falls into the hoppers at the bottom of the dust filter. The fly ash would then
be conveyed to fly ash storage silos to await disposal or collected by DOE licensed recoverer.
Wastewater Treatment Plant (WWTP)
The WWTP for the Project is designed to treat the incoming industrial wastewater with potentially high
concentration of suspended solids and heavy metals. An oil separator mechanism is to be installed to
trap oily water from being discharged to outside environment. Industrial wastewater are sent to air
heater washing basin and forwarded to a retention basin (primary holding sump) both basins acting
as holding tank in case of high volume of wastewater. Mixing blowers are installed at the retention
basin at the inlet of the WWTP (primary holding sump) to equalise the incoming wastewater as well
as to prevent solid settling. The wastewater will then be pumped to the chemical treatment system
MALAKOFF CORPORATION BERHAD
DETAILED ENVIRONMENTAL IMPACT ASSESSMENT OF A PROPOSED 2X1000MW EXTENSION AT
TANJUNG BIN COAL-FIRED POWER PLANT, MUKIM SERKAT, DAERAH PONTIAN, JOHOR DARUL
TAKZIM
Page xxvii 054/80067: 00-EN-REP-0001-0 Rev 0 : 25 July 2011
consists mainly of coagulation, flocculation and chemical treatment. After the precipitation process,
the wastewater will undergo pH adjustment prior to discharge to seawater FGD open channel then to
sea.
The solids contained in the wastewater are separated in a clarifier. Sludge collected from the
underflow of the clarifier is pumped into a thickener to further concentrate the sludge which is then
transferred into a thickened sludge holding tank before lead to a belt filter press to dewater the sludge
before disposal.
Another source of wastewater is from stormwater runoff collected at the coal yard and new ash pond.
The runoff from the coal yard will be captured in a collection sump and overflow be discharged to the
new ash pond if required. Due to sufficient retention volume, settling of suspended solids will occur
prior to discharging the wastewater from ash pond to the outfall whenever required. Other source of
stormwater will be collected and discharged to sea.
Atmospheric Emission
An approximately 200 m height concrete chimney will be constructed for each of the two units of
1,000 MW each. The actual height of chimney is to be confirmed from the air modelling assessment
with approval from DOE. Continuous Emission Monitoring System (CEMS) will be provided to monitor
flue gas emission quality and to be treated to comply with the emission standards set by DOE. The
flue gas monitoring consist of a few parameters i.e. Flue gas temperature at emission point, flue gas
oxygen (O2) level, Flue gas nitrous oxygen (NO2) level, Flue gas sulphur dioxide (SO2) level and
Particulate matter (PM) level after FFP.
Wastewater Discharge
The treated effluent from WWTP will be discharged via the sea water FGD open channel then to sea.
The designed WWTP is able to treat the effluent to meet the Standard B quality of the Environmental
Quality (Industrial Effluent) Regulations, 2009. The WWTP should be regularly maintained and
inspected to minimise potential operational failures.
The sludge generated from the WWTP shall be properly stored and sealed in labelled 200 L steel
drums or 1 ton sludge bags and be transported by licensed contractors to licensed premise for
disposal. The inventory of sludge generation and disposal will be kept and sent to DOE.
Ash Handling Control System
The ash handling system consisting of scraper conveyor is used to remove bottom ash while
pneumatic transportation equipment is proposed to dispose off fly ash.
Bottom Ash Handling and Disposal System
For removal of bottom ash, an ash extractor for wet (or alternatively dry) ash extraction is installed
below the furnace hopper outlet. The system is further equipped with an ash crusher and a bottom
ash plant.
MALAKOFF CORPORATION BERHAD
DETAILED ENVIRONMENTAL IMPACT ASSESSMENT OF A PROPOSED 2X1000MW EXTENSION AT
TANJUNG BIN COAL-FIRED POWER PLANT, MUKIM SERKAT, DAERAH PONTIAN, JOHOR DARUL
TAKZIM
Page xxviii 054/80067: 00-EN-REP-0001-0 Rev 0 : 25 July 2011
The bottom ash extractor essentially consists of Submerged Chain Conveyor (SCC), which is
operating below the furnace hopper and in an enclosed water-filled housing connected to boiler by a
flexible air-tight joint. The SCC transports the furnace ash slowly using a drag link chain conveyor to
its discharge end upwards to the drop-off point at the end of the conveyor. The SCC is equipped with
basalt lining to limit friction and wear of the conveyor parts. The conveyor mainly consists of high
flexible stainless steel mesh with stainless steel plates fixated to it on which transports the ash. The
chain is advanced by sprockets to pick-up the weight of the steel belt and of the collected ash.
At the discharge end of the extractor a crusher is installed to break larger ash lumps into small pieces.
Thus, large and still very hot ash lumps can be subjected to further cooling on the post-cooler belt
conveyor. The crusher is specially adapted to crushing of hot abrasive ash lumps.
The bottom ash is then transported to the ash pond by a slurry ash handling system.
Fly Ash Handling and Disposal System
Fly ash is collected from the economiser hoppers, gas air heaters and FFP hoppers for transportation
by the fly ash system. It is then fed into fly ash transmitters via gravity. Fly ash transmitters are
vessels used to channel ash from the collection hoppers and into the ash silos. Compressors are
used to supply the air to move ash from the hoppers to the silos. Ash from the economiser and gas air
heaters is sent to the bottom ash bin while ash from the precipitators is sent to the fly ash silo. The fly
ash silo can discharge ash to fly ash trucks or to the fly ash export on the fly ash jetty, alternatively
the ash can be discharged to the ash pond.
The collected fly ash may be sold to the local cement, concrete or asphalt industry and is solely
subject to approval by DOE. As such, the MCB shall apply for special management prior to utilisation
of coal ash, which includes both bottom ash and fly ash in other industries by conforming to the
requirement stipulated under the Regulation 7 of the Environmental Quality (Scheduled Wastes)
Regulations, 2005.
Ash Pond
The projected annual ash production for the Project is approximately 100,000 tons per year. The ash
pond shall be used to store the power station’s surplus ash by-products.
The Project will share the ash pond facility with the existing plant. The existing ash pond is designed
with a space capacity of 22.5 ha and shall be able to handle approximately up to 7 years of the power
station’s ash disposal.
Due to the expansion nature of this Project, the proposed power island of Phase 2 may be sited at the
location of the existing ash pond and a new ash pond is anticipated to be constructed. The
construction of new ash pond for the Project will be divided into two phases. In the first phase, the
total area of the pond shall be 24.6 ha and designed to handle approximately 5 years of the power
station’s ash disposal. This new ash pond will be located west of the Project site, adjacent to the new
coal storage yard.
MALAKOFF CORPORATION BERHAD
DETAILED ENVIRONMENTAL IMPACT ASSESSMENT OF A PROPOSED 2X1000MW EXTENSION AT
TANJUNG BIN COAL-FIRED POWER PLANT, MUKIM SERKAT, DAERAH PONTIAN, JOHOR DARUL
TAKZIM
Page xxix 054/80067: 00-EN-REP-0001-0 Rev 0 : 25 July 2011
Depending on the possible utilisation of the ash in other industries, the need to have another ash
pond may arise. For the second phase, it is proposed that future ash pond for this Project will be
located at the mud flat area at the southern part of the project site. The construction of this ash pond
has been approved as part of the existing power plant.
All ash ponds shall be lined with impermeable material to prevent seepage of heavy metals in the coal
ash such as mercury, arsenic, etc. into the ground water. Ash ponds shall be constructed in a manner
that allows the water to be stored and returned to the plant for reuse. The ash ponds which act as
solid-liquid separator and will be designed to have a considerable area since retention time is the only
means to allow the ash to settle and separate from the conveying water.
4.5 Normal Operation
The project is expected to provide 3,000 – 4,000 jobs for locals and foreigners during the peak of its
construction period. During the operational stage, an estimated 140 personnel will be employed in
addition to the workforce for the existing plant.
4.6 Abnormal Operation
In case of power interruption or power failure, a standby diesel generator will automatically start up
and power will be supplied to critical equipment for safe shutdown of the plant. For all process
components, tripping procedures are implemented in the control programs. To ensure safe tripping,
the sequences are implemented as “de-energize to trip” in the control systems, meaning safety
conditions will be reached passively.
Coal Combustion
The coal combustion system consists of a chain of units, namely the coal feeder, the coal pulveriser
(mill), the primary air flow, burner pipes and burners as well as secondary and boundary air flows.
During normal operation, one coal pulveriser is on standby for each unit at all times, since coal
pulverisers are heavily mechanically strained and immediate compensation is vital for full operation of
the plant if one pulveriser unit has to be taken out of operation.
In the case of power interruption, if no electrical energy can be supplied to the coal pulverisers, the
units will stop to operate and the supply of pulverised coal to the boiler will end.
If the loss of the fluidising air flow through the coal pulveriser is the cause for the abnormal operation
of the unit, the mill is isolated from the air flow system and an inert internal atmosphere is created by
injecting inert gas or vapour to prevent auto-ignition of the residual fuel. Brief operation of the mill,
while isolated, will reject the coal to the pyrite removal system.
The main systems that depend on electrical energy used for the coal burners are coal pulverisers
(see above) and the primary air supply system, which is used to fluidise the pulverised coal.
MALAKOFF CORPORATION BERHAD
DETAILED ENVIRONMENTAL IMPACT ASSESSMENT OF A PROPOSED 2X1000MW EXTENSION AT
TANJUNG BIN COAL-FIRED POWER PLANT, MUKIM SERKAT, DAERAH PONTIAN, JOHOR DARUL
TAKZIM
Page xxx 054/80067: 00-EN-REP-0001-0 Rev 0 : 25 July 2011
The safety interlocks of the system are as follows:
• Failure of primary air flow trips the pulveriser system (mill);
• Failure of the pulveriser trips the coal feeder and primary air flow;
• Closing of all burner pipe valves trips the pulveriser, the feeder and the primary air flow; and
• Primary air flow below minimum trips the pulveriser.
In case of a master fuel trip (flame collapse), all fuel supply to the boiler is stopped
Steam Generator
To describe abnormal operations behaviour and precautions for the steam generator, two cases have
to be distinguished.
A blockage downstream from the boiler on the water/steam side that goes along with pressure
increase in the steam path will be handled by the overpressure relief system, bypassing the steam to
the flash tank and/or condenser. To limit steam pressure in the boiler, the boiler is equipped with
passively operating safety relief valves.
A boiler trip indicated by pressure levels exceeding the safety range will trip the fuel supply, the
pulverisers and the feeders. Air flow is provided on a constant level during tripping procedure for post
trip furnace purge.
Steam Turbine
To prevent damage from rotating speed increase due to sudden load drop at the turbine shaft, the
steam turbines are equipped with safety shutoff valves. The steam will be fed to condensers through
the HP/LP bypass systems and to the overpressure relief system (boiler safety valve) if unit was
operating above its maximum continuous rating. Since feedwater preheating depends on turbine
operation, feedwater supply is usually provided by the feed water storage tank for approximately 7
minutes of full load unit operation.
Pollution Control System
• Dust Filter Plant (DFP) - During normal operation, the efficiency of the DFP will decrease over
time due to coating of the filter bags with particulate matter. Periodic cleaning of the FFP bag
filters restores separation efficiency. Abnormal operations of the DFP will result in higher
particle emissions. To comply with particle emission limits and/or emission allowances per time
interval, the power plant has to be shut down accordingly if the DFP fails to operate.
• Fly Ash Handling System - During normal operation, the emergency fly ash handling system
which transmits fly ash to the ash pond is activated if the storage silos become overfilled due to
unloading difficulties. If the boiler trips or other emergency conditions occur with the boiler, the
fly ash system must remain activated until the ash collection hoppers under the FFP, gas air
heater and economiser are emptied of fly ash.
MALAKOFF CORPORATION BERHAD
DETAILED ENVIRONMENTAL IMPACT ASSESSMENT OF A PROPOSED 2X1000MW EXTENSION AT
TANJUNG BIN COAL-FIRED POWER PLANT, MUKIM SERKAT, DAERAH PONTIAN, JOHOR DARUL
TAKZIM
Page xxxi 054/80067: 00-EN-REP-0001-0 Rev 0 : 25 July 2011
• FGD (Flue Gas Desulphurisation) - The main material flows of the seawater FGD are flue gas
and seawater entering the process, and the treated flue gas as well as the effluent seawater
that has converted the SO2 to sulphate ions leaving the process. If there is an interruption of
seawater supply, SO2 in flue gas will most probably exceed the emission limit. To comply with
particle emission limits and/or emission allowances per time interval, the power plant has to be
shut down accordingly if the FGD fails to operate.
• WWTP (Wastewater Treatment Plant) - In case of any abnormal operation of the WWTP, waste
water in any stage of treatment is retained in the respective pits or basins and held from
uncontrolled discharge to the sea. If needs be, the fluids can be pumped and transported to a
3rd party treatment or storage system to continue plant operation. Eventually, the plant has to
be shut down if storage capacity for waste water is exceeded.
• CEMS (Continuous Emission Monitoring System) - In case of abnormal operation of the CEMS,
some local alarms are available or sent to data acquisition system in order to investigate the
reasons of the data that are out of range. In addition, mobile equipment with the same or similar
specification will be used as a replacement to monitor the emissions of the plant until normal
operation of the CEMS can be reinstated. As long as the main units of the pollution control
systems are still in normal operation mode, the power plant can continue to operate.
4.7 Project Schedule
The project will involve two phases of construction work. The tentative timeframe for completing
Phase 1 of the Project (i.e. installation of the first 1X1000MW unit) is approximately 48 months from
the kick-start of construction.
5 EXISTING ENVIRONMENT
5.1 Geology, Soil and Hydrogeology
Geology
Geology of the coastal areas is generally characterised by young alluvial deposits. The surface
geology within the proposed development area is characterised by alluvial deposits, which consists of
major cohesive components of clay and silt materials, forming horizontal bedding or strata. Non-
cohesive material is generally minor and consists of fine to very fine sand. This non-cohesive fine to
very fine sand is usually encountered as lenses in the alluvial deposits.
Soil
Soil type within the project area is of the Kranji soil series. The Kranji soil series is formed from the
original parent material of marine alluvium deposit and is characterised by cohesive (clay/silt) material
with very low sand and gravel.
MALAKOFF CORPORATION BERHAD
DETAILED ENVIRONMENTAL IMPACT ASSESSMENT OF A PROPOSED 2X1000MW EXTENSION AT
TANJUNG BIN COAL-FIRED POWER PLANT, MUKIM SERKAT, DAERAH PONTIAN, JOHOR DARUL
TAKZIM
Page xxxii 054/80067: 00-EN-REP-0001-0 Rev 0 : 25 July 2011
Groundwater
Groundwater quality has been determined through a review of Malakoff’s routine groundwater quality
data, collected between 2006 and 2010. Routine monitoring of groundwater are conducted at two
wells, GW1 and GW2. Both wells are located on the western boundary of the existing ash pond.
Based on the monitoring data between 2006 and 2010, it can be concluded that the potential for
significant impacts to the water quality from the current site use are considered low.
5.2 Water Quality
Hydrology and Coastal Characteristics
The Project site is located on the lower catchment of Sg. Pulai on the headlands of southwestern
Johor. The Project site is bounded by the Sg. Pulai Reserve, a large expansion of mangrove forest to
the north and southwest, Sg. Pulai to the east and Straits of Johor to the south. PTP is located
northeast of the Project site. Surface runoff from the Project site discharges to the sea directly or via
Sg. Sam, while surface runoff from the existing plant enters the storm drain before it discharges
directly to the sea or via Sg. Tembusu.
In terms of coastal site condition, the Project’s coastline is protected by a rock revetment. The
coastline between Tg. Piai and the western bank of Sg. Pulai estuary is embayed. A coastal bund is
present further inshore. The mangrove-fringe mudflat along the Western Johor Strait from Sg. Pulai
estuary extending until Tg. Piai has gentle gradient.
Measured current were stronger during flood flow and spring period. It was inferred from bed
sampling exercise and analysis that the surface bed material within the study area primarily consists
of clay and slit. During river gauging, the analysed TSS contribution near the river mouth was 0.05
kg/m3 during spring and neap periods. The mean temperature was 29.9°C.
Routine Water Quality Monitoring
The routine water quality data was collected on monthly basis between 2006 and 2010.
The marine water quality in the vicinity of the Project site was good with high compliance of the
Interim Marine Water Quality Standards (IMWQS) for the key parameters including DO, BOD, COD,
TSS and E. coli. Some exceedances were observed for Oil and Grease, Lead and Copper. For Sg.
Pulai, the results were mostly compliance with the limits under Class III of the Interim National Water
Quality Standard (INWQS) except for Cadmium, Lead and Dissolved Oxygen. It has to be noted that
these water sampling points are located within the vicinity of heavy vessel traffics from the Project
activities as well as from the PTP and the Bunkering Island. The other activities could also contribute
to the exceedances at the water sampling points.
The water quality for cooling water discharges, wastewater from WWTP and Ash Pond settling basin
were generally fair, with most parameters of compliance with the Standard B, Environmental Quality
(Sewage and Industrial Effluents), 1979. The outfall discharge data were in full compliance for the
MALAKOFF CORPORATION BERHAD
DETAILED ENVIRONMENTAL IMPACT ASSESSMENT OF A PROPOSED 2X1000MW EXTENSION AT
TANJUNG BIN COAL-FIRED POWER PLANT, MUKIM SERKAT, DAERAH PONTIAN, JOHOR DARUL
TAKZIM
Page xxxiii 054/80067: 00-EN-REP-0001-0 Rev 0 : 25 July 2011
Standard B limits in terms of temperature, Chlorine and Oil and Grease concentrations. The rainwater
mean pH level at the existing plant was comparable to the rainwater mean pH level recorded at the
Senai International Airport. Based on the rainfall data collected, it can be concluded that the
emissions from the existing plant has negligible impacts on the chemical characteristics of the rainfall.
Baseline River and Marine Water Quality Monitoring
The water quality conditions of the rivers in the vicinity of the Project site were satisfactory with high
compliance with the INWQS of Class III. The WQI for Sg. Dinar, Sg. Tembusu, Sg. Sam and Sg. Pulai
was between Class II and Class III. Comparatively, the water quality of Sg. Dinar downstream from
the Project site was slightly better than the upstream, attributed to the higher dilution afforded by the
seawater. The water quality for the three additional marine water points- MW6, MW7 and MW8 were
compared to the Malaysian Marine Water Quality Criteria and Standard for Class E and Interim
Marine Water Quality Standard. The results were satisfactory and in compliance to the Interim Marine
Water Quality Standard and Class E.
5.3 Marine Ecology
The study involved the collection of both primary as well as secondary data collection. Primary data
collection was based on field assessments of the aquatic environment involved the collection of water
and sediment samples at eight (8) sampling stations for plankton and macrobenthic density and
diversity assays as well as fish fauna, mangroves and seagrass assessment. Secondary data were
collected from various sources, include literature review of all existing data, reports (published and
unpublished), records and other secondary sources with respect to the study area as well as
meetings and discussion with officers from the Johor State Department of Fisheries.
Water Quality
The assessment on the water quality found out that most of the parameters in relation with the
fisheries and aquaculture were well within acceptable levels sucah as pH, BOD, TSS, mercury,
arsenic, chromium, cadmium, boron, nickel, zinc, manganese, and tin. However, there were certain
parameters that were found at deleterious levels in certain stations i.e. temperature, lead, copper, iron
and chlorine.
Phytoplankton
Phytoplankton composition at the study area consisted of two (2) major phyla i.e. Bacillariophyta and
Dinoflagellata. The Bacillariophyta were more dominant in terms of species (21 species) and density
(99.4%). Dinoflagellata, on the other hand, were represented by single species, and constitute 0.6%
of the total phytoplankton density. The range of density was from 33.22 – 131.89 cells/mL, with
average density of 83.1 cells/mL. As for the species diversity, the Shannon Weiner Diversity Index
(H’) ranged from 1.44 – 2.27, indicating a fairly moderate diversity pattern.
MALAKOFF CORPORATION BERHAD
DETAILED ENVIRONMENTAL IMPACT ASSESSMENT OF A PROPOSED 2X1000MW EXTENSION AT
TANJUNG BIN COAL-FIRED POWER PLANT, MUKIM SERKAT, DAERAH PONTIAN, JOHOR DARUL
TAKZIM
Page xxxiv 054/80067: 00-EN-REP-0001-0 Rev 0 : 25 July 2011
Zooplankton
A total of six (6) phyla of zooplankton were recorded in the study area i.e. Arthropoda, Mollusca,
Ciliophora, Chordata, Chaetognatha and Annelida. Among the phyla, Arthropoda was the most
dominant phylum, contributing a total of 91.7% of the total zooplankton density, followed by
Chaetognatha (2.2%), Chordata (1.8%), Annelida (1.8%), Mollusca (1.7%) and lastly Ciliophora
(0.8%). The density was ranged from 7.0 – 24.0 spp/L, averaged at 15.4 spp/L. In term of Shannon
Weiner Diversity Index (H’), the values ranged from 1.54 – 1.94.
Macrobenthos
Macrobenthic invertebrates at the study area indicated that four (4) major phyla were recorded i.e
Annelida, Echinodermata, Arthropoda (Crustacea) and Mollusca. The most dominant phylum
recorded was Annelida, which comprised 59.7% of the total macrobenthos density, followed by
Echinodermata (20.9%), while Arthropoda (Crustacea) and Mollusca only constitute 18.3% and 1.0%
respectively. Their densities ranged from 10 – 330 ind./m², averaged at 239 ind./m2. The Shannon
Weiner Diversity Index (H’) recorded ranged from 1.67 – 2.66, indicated that the H’ value was
moderate to high.
Fish Fauna
The fish fauna was represented by 15 individuals of fish, belonging to seven (7) families and
comprised of nine (9) species. These includes Semilang (Plotosus spp.) from Family Plotosidae; Bilis
(Stolephorus sp.), Tempurung (Setipinna taty) and Kasai Minyak (Thryssa hamiltonii) from Family
Engraulidea; Siakap (Lates calcarifer) from Family Centropomidae; Ketam Batu (Scylla serrata) from
Family Portunidae; Gosok (Monocanthus chinensis) from Family Monacanthidae; Undok - Undok
(Syngnathoides biaculeateus) from Family Syngnathidae and Kapas (Gerres abbreviatus) from
Family Gerreidae. The length was ranged from 4.0 – 24.9 cm, while the total composite weight was
651g.
Mangrove
As for the mangrove, most of them were found to be more extensive from Sg. Tembusu northward,
where it encompassed the Sg. Pulai Forest Reserve. The recent survey found mangroves in patches
at several locations surrounding the Tg. Bin Coal Fired Power Plant. A total of 12 species of
mangrove, belonging to six (6) families were recorded at the study area. Five (5) species were from
Family Rhizophoraceae and three (3) species were from Family Acanthaceae, while single species
recorded for each remaining family i.e. Sonneratiaceae, Combretaceae, Palmae and Malvaceae. The
most dominant species recorded at the study area was Bakau Minyak (Rhizophora mucronata), Api –
Api Ludat (Avicennia officinalis) and Perepat (Sonneratia alba). The girth size of mangrove trees
recorded ranged from 0.1 – 0.4 m.
MALAKOFF CORPORATION BERHAD
DETAILED ENVIRONMENTAL IMPACT ASSESSMENT OF A PROPOSED 2X1000MW EXTENSION AT
TANJUNG BIN COAL-FIRED POWER PLANT, MUKIM SERKAT, DAERAH PONTIAN, JOHOR DARUL
TAKZIM
Page xxxv 054/80067: 00-EN-REP-0001-0 Rev 0 : 25 July 2011
Seagrass
The seagrass communities were found between Sg. Tembusu and Sg. Dinar and off Tg. Pelepas
Port. The species recorded include Halophila spinulosa, Halophila ovalis, Enhalus acoroides,
Cymodocea serrulata, Thalassia hemprichii and Halodule uninervis. Seagrass between Sg. Tembusu
and Sg. Dinar was found beyond 100 – 170 m from the river bank with an estimated area of 2.3 ha,
while the seagrass area off Tg. Pelepas Port was estimated around 12ha. In terms of seagrass
health, the seagrass cover ranged from 12 – 85%.
Seagrass has been known to support a wide variety of life, and in recent study several species of fish
found off Tg. Pelepas Port includes Monocanthus chinensis, Syngnathoides biaculeateus, Chaerodon
schoenleinii, Monocanthus chinensis, Lutjanus spp., Apogon hyalosoma, Triacanthus spp., Arius
spp., Arothron spp., Batrachomeoes trispinosus and Plotosus spp. Other than the fish, the seagrass
also supports substantial invertebrate populations. A total of 20 invertebrate species recorded, where
nine (9) species belonged to Mollusca, five (5) species from Echinodermata, three (3) species from
Arthropoda, two (2) species from Cnidaria and one (1) species belonged to Annelida. The most
common invertebrate species found include Stichodactyla sp., Colochirus quadrangularis, Holothuria
scabra, Salmacis sp., Protoreaster nodosus and Cymbiola nobilis.
Seaweed
The seaweed in the study area was mostly found to be associated with the seagrass. A total of 16
species was identified, where eight (8) species from Division Chlorophyta, five (5) species from
Rhodophyta and three (3) species from Phaeophyta. The major species found were Udotea flabellum
and Gracilaria coronopifolia, where these two (2) species were recorded in both between Sg.
Tembusu and Sg. Dinar and also off Tg. Pelepas Port. Other species were only recorded in either
each study area only.
Fisheries
The project site is located in fisheries district of Pontian. There were 26 fishing villages in Pontian
district. However, only six (6) fish landing points located within the impact zone include Sg. Dinar, Sg.
Chengkeh, Sg. Karang, Belokok, Sungai Punai and Jeram Batu. A total of 92 fishermen were
recorded operating from these six (6) fish landing points. There were a total of 63 units of vessels at
the landing points, but only three (3) of them were inboard vessels, while the rest was outboard
vessels. The main fishing gears used were trammel nets, hook and line, portable traps and cast net.
Most fishing activity was conducted from the swampy mangrove areas along Sg. Pulai to the
International border (separating the west and south Johore from Indonesia and Singapore). From 20
days of fishing per month, each fishermen catch about estimated 40 - 50kg of shrimp and 5 - 6kg of
fish.
Aquaculture
In addition to capture fisheries, there is also aquaculture activity nearby to the project area. The major
systems being practiced were brackishwater cage culture (Sg. Redan) and canvas rearing (Simpang
MALAKOFF CORPORATION BERHAD
DETAILED ENVIRONMENTAL IMPACT ASSESSMENT OF A PROPOSED 2X1000MW EXTENSION AT
TANJUNG BIN COAL-FIRED POWER PLANT, MUKIM SERKAT, DAERAH PONTIAN, JOHOR DARUL
TAKZIM
Page xxxvi 054/80067: 00-EN-REP-0001-0 Rev 0 : 25 July 2011
Kiri). The main commodities reared for the cage culture were Siakap (Later calcarifer) and Kerapu
(Epinephelus sp.), while Keli (Clarius sp.) for canvas.
5.4 Meteorology and Air Quality
The climate at the Project is equatorial, warm and humid all year, and modified by two distinct
monsoonal seasons with two shorter inter-monsoon periods. Meteorological data from the Senai
Airport Meteorological Station (01°38’N, 103° 40’E) are representative of the meteorological
conditions at the Project site and are summarized as follows: mean daily temperature of 26.0°C,
mean daily humidity of 86.4%, total annual rainfall of 2,463.7mm, dominant wind from the north and
calm period 38.9% of the time.
Three rounds of baseline air quality sampling were carried out at three stations (Kg.Chengkeh, Kg.
Chokoh Besar and Sekolah Kebangsaan Tg. Adang) in the vicinity of the Project site. The parameters
tested were Total Suspended Particulates (TSP), Particulate Matter <10 micron (PM10), Sulphur
Dioxide (SO2), Nitrogen Dioxide (NO2), Carbon Monoxide (CO) and heavy metals (Arsenic, Cadmium,
Lead, and Mercury). The analysis results show that the parameters complied with the Recommended
Malaysian Air Quality Guidelines, elaborated as follows:
• TSP levels ranged from 23 to 72 µg/m3 while PM10 ranged from 3 to 24 µg/m
3;
• SO2, NO2 and CO were not detected; and
• Arsenic and mercury were undetected at all stations, while cadmium was detected at only one
station at a concentration of 0.002 µg/m3. Lead was detected at all three stations at
concentrations ranging from 0.008 µg/m3 to 0.035 µg/m
3.
5.5 Noise
Information on background noise level for the project site encompasses the routine boundary noise
monitoring data for the operation of the existing plant and baseline noise monitoring data for two
locations along the Project site boundary and two nearby settlements.
Existing project site boundary noise levels ranged from 51.4 dB(A) to 57.4 dB(A) during the day and
49.3 dB(A) to 56.8 dB(A) during the night. Noise levels were generally found to be within the
respective prescribed limits of 65 dB(A) and 55 dB(A).
Ambient noise levels recorded at the nearby settlements i.e. Kg. S. Dinar and Kg. S. Sam averaged at
52.2 dB(A) and 56.2 dB(A) during the day; 48.9 dB(A) and 52.2 dB(A) during the night. Recorded
levels at both settlements have exceeded the recommended DOE recommended noise level for
suburban residential land use in the day and night except for day time levels in Kg. S. Dinar.
Background in-plant noise was also measured and no high noise level of more than 85 dB(A) has
been identified from the noise map.
MALAKOFF CORPORATION BERHAD
DETAILED ENVIRONMENTAL IMPACT ASSESSMENT OF A PROPOSED 2X1000MW EXTENSION AT
TANJUNG BIN COAL-FIRED POWER PLANT, MUKIM SERKAT, DAERAH PONTIAN, JOHOR DARUL
TAKZIM
Page xxxvii 054/80067: 00-EN-REP-0001-0 Rev 0 : 25 July 2011
5.6 Land Use
The major land uses surrounding the Project site are agriculture, industrial and water bodies.
Agriculture usage is mainly comprised of oil palm plantations; while industrial usage is the existing
Tanjung Bin Power Plant, Hydrocarbon Storage and Distribution Terminal, and the committed
industrial development area by Seaport Worldwide Sdn. Bhd. Water bodies consist of Sungai Pulai
and Selat Johor.
5.7 Infrastructure, Utilities and Services
The Project site is connected to the south-west region of Johor via the Federal Route 5 (FR5) and
Federal Route 95 (FR95). FR95 is the main access road to the power plant which runs a distance of
20 km between Pontian Kechil and Kukup and local access to project site is via Jalan PT Haji Sayon.
The existing water supply is supplied by Syarikat Air Johor (SAJ) while electricity in the area is
provided by Tenaga Nasional Berhad (TNB). Meanwhile, telecommunication facilities and services
are served by Syarikat Telekom Malaysia. As for solid waste, the collection is conducted by local
authority and the landfill location is at Pekan Nanas, within Pontian area.
5.8 Socio-Economics
Twenty-two kampongs are located inside the 5-km impact zone, with a total of 1,675 households and
6,217 persons. About 42% of the head of households work as general workers, 33% fishermen and
12% farmers. Generally, close to 60% of the households are reported to be dependent on agriculture
and fishing. Declining fish catch over the past decade has been reported by the fishermen, and
concerns were expressed over the loss of traditional fishing grounds and breeding/spawning areas
due to loss of mangroves, declining water quality, and increase in water temperature.
Perception of the Residents
Generally, a significant percentage of respondents interviewed (67%) could not see beneficial effects
to them with respect to health, social, traffic and economy. Only 29% of those interviewed were
positive about direct and indirect employment opportunities and spin-off benefits that project would
generate. Similarly, more than 60% perceived negatively the impact the plant would have on the
environment. Their fears were towards further degradation of the air and water quality, and further
decline in fish landing.
5.9 Public Health The existing health status was determined through the health survey and a review of secondary
health surveillance data from the nearest health facility for period of five years from 2006-2010. The
potential health impacts were determined through health risk assessment methodology. In the health
survey, the prevalence rates of the sensitive receptors (children and adults) of the Project were 112.6,
38.6, 16.1 and 14.5 per 10,000 populations for the common cold/flu, fever, cough and asthmatic
MALAKOFF CORPORATION BERHAD
DETAILED ENVIRONMENTAL IMPACT ASSESSMENT OF A PROPOSED 2X1000MW EXTENSION AT
TANJUNG BIN COAL-FIRED POWER PLANT, MUKIM SERKAT, DAERAH PONTIAN, JOHOR DARUL
TAKZIM
Page xxxviii 054/80067: 00-EN-REP-0001-0 Rev 0 : 25 July 2011
attack respectively. These rates were lower than the NHMIS III, 2006. The secondary data review
found that the outpatient attendances from main air pollution related diseases in the health clinic were
URTI and asthma.
6 IMPACTS ASSESSMENT AND MITIGATION MEASURE
6.1 Soil Erosion
The potential sources of soil erosion impacts from the construction of the power plant expansion have
been identified as follow:
• Clearing of the residual mangroves and shrubs;
• Dredging and/or soil improvement of soft marine mud for seawalls;
• Earthworks for the establishment of the final platform level; and
• Piling for the substructure and superstructure and installation of the power station and other
ancillary equipment.
Impacts due to the loss of sediment during the construction of the power plant expansion and
associated facilities were assessed using the Revised Universal Soil Loss Equation (RUSLE) model
developed by Wishmeier and Smith (1962) in conjunction with a Geographical Information System
(GIS) programme to quantify the rates of soil loss.
The soil erosion assessment identified that significant impact would be experienced during the
development phase. With the installation and effective operation of silt traps and sediment control on
site, the loss of fine sediment to suspension will be minimised during the construction phase.
6.2 Water Quality
Construction Phase Impact
Assessment of construction phase has two aspects: impacts to the hydrodynamic regime and the
dispersion of fine sediment in suspension during dredging and piling activities. The assessment has
been carried out using computational modelling- MIKE 21. Other construction wastewater from land-
based activities was assessed qualitatively.
Sedimentation Transport
Based on simulation results on existing conditions, the most probable factors is re-suspension from
the bed and transport of the suspended sediments from areas with fast currents and deposition in
areas with lower currents during slack. From the results, there is a slight change in the erosion and
MALAKOFF CORPORATION BERHAD
DETAILED ENVIRONMENTAL IMPACT ASSESSMENT OF A PROPOSED 2X1000MW EXTENSION AT
TANJUNG BIN COAL-FIRED POWER PLANT, MUKIM SERKAT, DAERAH PONTIAN, JOHOR DARUL
TAKZIM
Page xxxix 054/80067: 00-EN-REP-0001-0 Rev 0 : 25 July 2011
sedimentation patterns within and around the Project site for Northeast and Southwest Monsoon
conditions.
Based on the MIKE 21 MT, a localised sedimentation of up to 0.3 m/year would probably occur within
the intake basin immediately after dredging is done. Localised erosion of up to about 0.2 m/year is
predicted to occur within the same vicinity as well as near the jetty and the new outfall location. The
changes are relatively similar for all seasonal conditions.
The initial erosion and sedimentation rates are expected to be higher upon completion of the Project
but are expected to decrease over time as the overall marine regime tries to achieve equilibrium.
Suspended Sediment Dispersion
Without appropriate mitigations in place for the dredging at the intake basin, a maximum suspended
sediment concentrations of above 5, 10 and 25 mg/l disperses as far as about 2.5, 2.2 and 0.1 km
from the source respectively. A plume with concentration above 5, 10 and 25 mg/l extends up to
about 0.2, 0.15 and 0.05 km from the source, respectively, for the same operation based on the mean
excess suspended sediment concentration plot.
For the pipeline alignment leading to the outfall, based on pure tide condition, a maximum suspended
sediment concentration of above 5, 10 and 25 mg/l disperses as far as about 1.5, 1.4 and 0.15 km
from the source, respectively. A plume with a concentration above 5, 10 and 25 mg/l extends up to
about 0.3, 0.15 and 0.05 km from the source, respectively for the same operations based on the
mean excess suspended sediment concentration plot.
Based on field measurements, an increase of 5, 10 and 25 mg/l represents an increase of 3, 6 and
14%, respectively, above the ambient mean TSS concentrations. The suspended sediment
concentrations are largest in the direct vicinity of the operation site before dropping quickly away from the
site, although the concentrations are relatively low at most times.
Other construction wastewater
It was determined that the potential negative impacts from land-based construction activities would
primarily be from contaminated surface runoff, sewage from construction site workers and vessel
discharges.
Mitigation Measures
• To construct of a precast concrete pipeline which connects the pump station located on the
mainland with the outfall structure, in line with the DID’s ‘Garispanduan 1/97: Guidelines on
Erosion Control for Development Projects in the Coastal Zone’. A trench is initially dug along
the pipeline alignment before piling is done to provide a sound foundation of the pipeline,
followed by backfilling. A 1 m cover is envisaged. Simulation results indicate that the Project
site is currently stable.
MALAKOFF CORPORATION BERHAD
DETAILED ENVIRONMENTAL IMPACT ASSESSMENT OF A PROPOSED 2X1000MW EXTENSION AT
TANJUNG BIN COAL-FIRED POWER PLANT, MUKIM SERKAT, DAERAH PONTIAN, JOHOR DARUL
TAKZIM
Page xl 054/80067: 00-EN-REP-0001-0 Rev 0 : 25 July 2011
• Use of a silt curtain to prevent or divert suspended sediment generated during dredging
operations away from environmentally sensitive areas. It should be placed extending far
enough to allow suspended sediment to settle. It is pertinent that the geo-textile fabric is firmly
held onto the seabed for it to function. If the curtain is lifted due to bed currents, suspended
sediments can pass through the gap, thus making it almost useless.
• Temporary stop dredging works during high current speeds which could occur during spring
period.
• A major contributor to suspended sediment generation when a trailer suction hopper dredger
is working arises from overflowing during loading. In general, the amount of material lost into
suspension can be reduced with careful operation and maintenance of the dredging plants.
• A continuous program to monitor TSS at various pre-determined stations to determine water
quality during construction phase.
• Periodic bathymetric and near shore topographic survey should carried out on annual basis,
preferably immediately after the passing of the Northeast Monsoon. The survey should cover
the area extending 500 m on both sides of the pipeline alignment and the water intake area.
• A number of mitigation measures were specified to minimise potential impacts from land-
based construction activities, which will be sufficient to prevent adverse impacts to water
quality. These measures include control of surface runoff, wastewater from building
construction, wastewater from site facilities, and the storage and handling of oil and other
petroleum and chemical products.
• For vessel discharges, the predicted impact is expected to insignificant during both
construction and operational phases of the Project, therefore mitigating measures are not
required.
Operational Phase Impact
The thermal plume and chlorine dispersion study was carried out to investigate and assess the impact
of cooling water discharge to the sea using the MIKE 21 modelling. Other operational wastewater was
assessed qualitatively.
Thermal plume
For existing condition, the plumes are primarily influenced by magnitude and direction of the tidal
currents. The maximum extent of mean excess temperature of greater than 0.1°C is about 5 km north
and 11 km southwest from the outfall. The maximum extent of maximum excess temperature of greater
than 0.1°C extends slightly beyond the Malaysia-Singapore border and beyond Pulau Kukup. In
comparison, the mean and maximum excess temperature of greater than 0.5°C disperses about 3
and 9 km south of the outfall. The dispersion that occurs for the monsoonal conditions is generally
MALAKOFF CORPORATION BERHAD
DETAILED ENVIRONMENTAL IMPACT ASSESSMENT OF A PROPOSED 2X1000MW EXTENSION AT
TANJUNG BIN COAL-FIRED POWER PLANT, MUKIM SERKAT, DAERAH PONTIAN, JOHOR DARUL
TAKZIM
Page xli 054/80067: 00-EN-REP-0001-0 Rev 0 : 25 July 2011
relatively lower than during the pure tide condition. The exceedance probability for 0.5°C exceeding
more than 10% at the outfall for pure tide condition can extend up to about 4.5 km from the outfall. The
exceedance probability for 1°C exceeding more than 10% would be about 0.5 km from the outfall. The
probability exceedance for 2°C exceeding more than 5% would be about 0.1 km from the outfall. It can be
inferred from the plots that the magnitude and extent of dispersion for pure tide (inter monsoon) condition
is higher compared with the monsoonal conditions.
With the new outfall, the mean excess temperature of greater than 0.1°C is about 5 km north and 15 km
southwest from the outfall. The maximum extent of maximum excess temperature of greater than 0.1°C
extends slightly beyond the Malaysia-Singapore border and beyond Pulau Kukup. The mean and
maximum excess temperature of greater than 0.5°C disperses about 8.5 and 15 km south of the outfall.
The presence of the new outfall has resulted in the maximum excess temperature of greater than 3�C to
extend about 0.2 km from the outfall. This could be due to the close proximity of the existing and the new
outfalls.
The exceedance probability for 0.5�C exceeding more than 10% of the time at the outfall would have a
spread of about 8 km. The exceedance probability for 1�C exceeding more than 10% would be about 5
km from the outfall. The probability exceedance for 2°C exceeding more than 5% would be about 0.4 km
from the outfall. It can be inferred that the magnitude and extent of dispersion for pure tide (inter
monsoon) condition is higher compared with the monsoonal conditions.
Chlorine Dispersion
For the existing condition, the maximum extent of mean and maximum residual chlorine concentration
of up to 0.05 mg/l is about 0.4 and less than 0.05 km south of the source, respectively for pure tide
condition. With the new outfall, the maximum extent of mean and maximum residual chlorine
concentration of up to 0.05 mg/l is about 1.4 and less than 0.1 km south of the source, respectively. The
maximum extent of maximum residual chlorine concentration of greater than 0.05 mg/l is about 1.3 and
1.2 km approximately south of the source, respectively for southwest and northeast monsoon condition,
respectively. The extent of mean residual chlorine concentration dispersion for monsoonal conditions is
relatively similar for pure tide condition.
The residual chlorine concentration at the intake and existing outfall is about 0.02 and 0.1 mg/l,
respectively for the existing condition. The maximum residual chlorine concentration at the intake for
‘with Project’ condition is about 0.03 mg/l.
Foam
Foam may be produced on the surface of the sea in the immediate vicinity of the cooling water
outfalls due to aeration of decaying protein from dead marine organisms resulting from the use of
chlorine and anti-fouling agents. The impact from foam generation will potentially have harmful impact
to the marine environment.
MALAKOFF CORPORATION BERHAD
DETAILED ENVIRONMENTAL IMPACT ASSESSMENT OF A PROPOSED 2X1000MW EXTENSION AT
TANJUNG BIN COAL-FIRED POWER PLANT, MUKIM SERKAT, DAERAH PONTIAN, JOHOR DARUL
TAKZIM
Page xlii 054/80067: 00-EN-REP-0001-0 Rev 0 : 25 July 2011
Other Operational Wastewater
Other operational wastewater includes seawater FGD, process wastewater, runoff from coal storage
yard and ash pond discharge, sewage generation from the workforce, stormwater and vessel
discharges.
Effluent discharge from seawater FGD is not expected to have any containment except for 3%
increased of sulphate content. However, sulphate is a natural constituent in seawater and is deemed
unlikely to cause any significant adverse impact to marine life. Process wastewater will be treated to
meet Standard B limits of the Environmental Quality (Industrial Effluent) Regulations, 2009 prior to
discharge into the receiving water body. For surface runoff from coal yard area and ash pond water
discharge, the water would be recycled for coal dust suppression system and ash pond transport.
Only excess water during heavy rainfall would be discharged to the sea after going through pH
adjustment process. Sewage will be routed and treated in the existing sewage treatment plant
designed to at least Standard B quality. The STP (250 PE) will have sufficient capacity to cater for
additional workforce. Stormwater discharge is not anticipated to contribute a significant impact on the
water quality.
Mitigation Measures
For cooling water discharge, to avoid foam generation, the Project Proponent should adopt a lower
discharge velocity to reduce turbulence at the outfalls. It is also crucial to avoid air entrainment in the
discharging water, as far as possible and to install suitable foam barrier or containment system in the
outfall vicinity to restrict any foam from escaping into the sea.
Suitable mitigation measures during the operational phase include the continuous monitoring of water
discharge, the installation of effective WWTP and water for recycling, lining of ash pond with a
permeable sheet and BMP for stormwater management. It should be noted that the efficiency of water
pollution controls is highly dependent on regular cleaning and maintenance. Therefore, it is imperative
that these installations are regularly cleaned and maintained in good working conditions and that this
be incorporated into the operational procedures.
6.3 Marine Ecology
Construction Phase Impact
During construction phase, two (2) major activities i.e. dredging and piling activity for the new outfall
construction and dredging activity at the intake basin were recognized to potentially generate negative
impacts on water quality, if not properly addressed. Dredging and piling activity would increase the
levels of suspended sediments and release biogenic and chemogenic products as well metal ions into
the water columns. High suspended sediments in the water (>80 mg/L) known to have an impact to
the aquatic organisms. From the hydraulic study, the result indicates suspended sediments dispersion
close to the intake basin and new outfall was significantly high (0.25 kg/m3 or 250 mg/L), however, it
MALAKOFF CORPORATION BERHAD
DETAILED ENVIRONMENTAL IMPACT ASSESSMENT OF A PROPOSED 2X1000MW EXTENSION AT
TANJUNG BIN COAL-FIRED POWER PLANT, MUKIM SERKAT, DAERAH PONTIAN, JOHOR DARUL
TAKZIM
Page xliii 054/80067: 00-EN-REP-0001-0 Rev 0 : 25 July 2011
can be minimised through appropriate mitigation measures. High suspended sediments in the water,
which is more than 80 mg/L, known to have a deleterious impact on aquatic organisms.
The release of biogenic and chemogenic products to the water column will exert an immediate
oxygen demand and has the potential to cause serious short-term damage to the marine ecosystem.
Disturbance of the sediments can also release metal ions to the water column. From the sediment
chemistry result, the current levels of some heavy metals recorded high in Tg. Bin area, where Cr, Ni
and Hg recorded at 32.92 - 53.23 µg/g, 192.75 - 266.62 µg/g and 11.44 -816.48 µg/g respectively.
These three (3) heavy metals exceeded the recommended level for the Sediment Criteria for Metals
according to New York State Department of Environmental Conservation of 26 µg/g for Cr, 50 µg/g for
Ni and 1.3 µg/g for Hg.
In addition, the dredging and piling works could affect the marine productivity, where significantly high
level of turbidity and suspended sediments can retard primary production, reduce crustacean
(shrimps and molluscs) abundance, suffocate sessile organisms and clog fish gill. As consequences,
food-web in the area would be disrupted thus causing imbalance to the aquatic community there.
With respect to seagrass/seaweeds, high level of sedimentations generated from the dredging works
could reduce light penetration that seagrass/seaweeds needs for photosynthesis process. However,
results from hydraulic study showed that the suspended sediments are generally low (<30 mg/L) at
the seagrass beds located between Sg. Tembusu to Sg. Dinar and the sediment plume does not
reach the seagrass area at PTP during the dredging activity for the new intake basin. As for dredging
and piling activities for the new outfall, the sediment plume does not reach the seagrass/seaweed
beds located between Sg. Tembusu to Sg. Dinar and PTP. Therefore, there is unlikely to be any
impact from the dredging and pilling activities on seagrass/seaweed beds.
Operational Phase Impact
During the operation of the new intake and outfall, the potentially major problem of water quality is
due to thermal pollution from the heated effluent. The discharge of the thermal effluent has the
potential to harm and damage marine organisms. Based on the hydraulic study, impact from the
thermal discharge is expected to be significant only at the new outfall (34.6°C) and organisms found
in the vicinity of the outfall are expected to be seriously affected.
In addition, the use of chlorine for the cleaning process of the cooling system would also give an
adverse impact to the water quality, plankton and benthic organisms as well as fish fauna. From the
hydraulic data, with the new outfall, the maximum extent of residual chlorine concentration of 0.05-0.1
mg/L is about 1.3 km and 1.2 km south of the source respectively for southwest and northeast
monsoon condition. This is based on the assumption that residual chlorine concentration of 0.2mg/L
at both existing and new marine outfall. Notwithstanding the fact that it occurs for brief intervals, this
represents a potential contamination of the marine environment given the fact that the USEPA
recommends chlorine residuals not exceeding 0.01 mg/L (USEPA, 1976).
MALAKOFF CORPORATION BERHAD
DETAILED ENVIRONMENTAL IMPACT ASSESSMENT OF A PROPOSED 2X1000MW EXTENSION AT
TANJUNG BIN COAL-FIRED POWER PLANT, MUKIM SERKAT, DAERAH PONTIAN, JOHOR DARUL
TAKZIM
Page xliv 054/80067: 00-EN-REP-0001-0 Rev 0 : 25 July 2011
As for seagrass/seaweeds, temperatures exceeding 43°C will adversely impact tropical seagrasses.
The temperature increase at seagrass beds (off PTP and between Sg. Tembusu and Sg. Dinar)
appears to be 0.5-1.5°C during pure tide and southwest and northeast moonson. As such, a
maximum increase of 1.5°C above the ambient level (30°C) may not have an adverse impact to the
seagrass beds. In addition, the residual chlorine plume is not expected to reach the seagrass beds,
therefore the impact on seagrass beds can be considered negligible.
Given the scenario above, it appears that the proposed project would potentially have a significant
degree of impact on the environment. Therefore, it is incumbent on the project proponent to ensure
that the proposed development would have minimal impact on the adjacent communities and
environments. Under these circumstances, several major mitigation measures are identified such as
use confining structures (screens, levees) to prevent the movement of suspended fines, incorporate
appropriate infrastructure for the disposal of sewage and monitor the discharges of residual chlorine
frequently.
The residual impacts that will be expected to occur include thermal pollution in the vicinity of the
discharge point as well as chlorine discharge to prevent marine growth in the cooling water system
due to the cleaning process. The primary effects of thermal pollution are direct thermal shock and
changes in dissolved oxygen, while high levels of chlorine will affect the productivity of aquatic
environment.
Mitigation Measures
An Environmental Management Plan should be set in place to guide both construction companies as
well as the subsequent operators on the environmental standards they are expected to conform to.
The main elements of such a monitoring programme include water quality (temperature, chlorine,
TSS, DO, BOD, pH, heavy metals and total phosphorus) and biological (plankton and macrobenthic
diversity and density as well as fish fauna species speciation) monitoring. The sampling point should
be located at the outer edge of the residual chlorine plume. It should be monitored quarterly during
construction and monthly during operation. The result of analyses should be submitted to the
Department of Environment.
6.4 Air Quality
Construction Phase Impact
The main potential air pollutant emission during the construction phase is fugitive dust originating
from land clearing, site preparation, and site mobilization. Site clearing and preparation create open
exposed surfaces that are prone to generate dust due to wind and vehicle movements. However, due
to their weight and size, most soil particles are expected to be carried over short distances only.
In view of the absence of residential property near the Project site, fugitive dust generated during
construction is not a significant issue of concern. The nearest residential areas are Kg. S. Dinar and
Sg. S. Sam, which are located approximately 0.5 km northwest and 0.7 km west of the Project site
MALAKOFF CORPORATION BERHAD
DETAILED ENVIRONMENTAL IMPACT ASSESSMENT OF A PROPOSED 2X1000MW EXTENSION AT
TANJUNG BIN COAL-FIRED POWER PLANT, MUKIM SERKAT, DAERAH PONTIAN, JOHOR DARUL
TAKZIM
Page xlv 054/80067: 00-EN-REP-0001-0 Rev 0 : 25 July 2011
respectively. Dust will be mitigated through control methods such as tyre washing, ground and road
watering, and adherence to the speed limit.
Operational Phase Impact
Air pollution dispersion modelling was carried out using the Industrial Source Complex Short Term
Version 3 (ISCST3) model. The parameters selected for modelling were the main pollutants emitted
by the Project, namely Total Particulate Matter (Total PM), Particulate Matter <2.5 µm (PM2.5),
Particulate Matter <10 µm (PM10), Sulphur Dioxide (SO2), Nitrogen Dioxide (NO2), Carbon Monoxide
(CO) and heavy metals – Arsenic (As), Cadmium (Cd), Lead (Pb) and Mercury (Hg).
Emission concentrations and rates for the existing stacks were obtained from the average values of
monthly stack monitoring data throughout the year 2010, while emission concentrations and rates of
the parameters for the new stacks were derived from design emission data provided by the
equipment vendor. The model receptor grid was a polar grid extending up to 6 km from the origin of
the grid. Meteorological data was obtained from the Senai Airport Meteorological Station.
Four scenarios were modelled to reflect the various possible operating scenarios at the Project
involving normal operating conditions as well as abnormal events due to failure of air pollution control
equipment, namely the bag filter and the flue gas desulphuriser (FGD). Only one air pollution control
equipment was assumed to fail at any one time. The scenarios are as follows:
i. Normal base case scenario with the new stacks (Unit 4 and Unit 5) emitting at the same
emission concentrations as the existing stacks, based on 2010 monitoring data of the existing
stacks;
ii. Normal maximum case scenario with the new stacks (Unit 4 and Unit 5) emitting at the
regulatory compliance limits for particulates, SO2, NO2 and CO;
iii. Abnormal operation scenario assuming total failure and shutdown of the flue gas
desulphurizer resulting in bypass of the FGD of one of the new stacks (Unit 4 or Unit 5); and
iv. Abnormal operation scenario assuming failure of the bag filter of one of the new stacks (Unit
4 or Unit 5).
The air dispersion model predicts Maximum Average Incremental Concentrations (MAIC), which are
ground level concentrations contributed by the stack emissions, not including background ambient
concentrations.
Overall, the predicted MAICs of all the parameters are within the respective Recommended
Malaysian Air Quality Guidelines (RMAQG) limit, due to the stack emission rates of the parameters
being generally low and well within the stack emission limits. Only SO2 and NO2 in the Normal
Maximum Case exceeded the RMAQG limits. Refined analysis of the percentile compliance for SO2
and NO2 indicates that at the 99.5 percentile level, the predicted MAIC will be below the RMAQG, thus
indicating the conservative results of the model. The conservative nature of the model is also shown
by the overall compliance of the existing plant as compared to the modelling results.
MALAKOFF CORPORATION BERHAD
DETAILED ENVIRONMENTAL IMPACT ASSESSMENT OF A PROPOSED 2X1000MW EXTENSION AT
TANJUNG BIN COAL-FIRED POWER PLANT, MUKIM SERKAT, DAERAH PONTIAN, JOHOR DARUL
TAKZIM
Page xlvi 054/80067: 00-EN-REP-0001-0 Rev 0 : 25 July 2011
The predicted dispersion patterns indicate that maximum ground level concentrations generally occur
mainly 1.5 km east (in Sg. Pulai) and 1.5 km southwest of the grid origin (along boundary of Project
site), and at areas away from sensitive receptors.
In the Normal Maximum Case scenario the 1-hour MAIC is predicted at 541.92 µg/m3, which exceeds
the RMAQG limit of 350 µg/m3. The 24-hour MAIC of 48.99 µg/m
3 is below the RMAQG limit of 105
µg/m3. However, it should be noted that the highest 1-hour MAIC occurs in the middle of Sg. Pulai
east of the Project site. Although the highest MAIC exceeds the RMAQG limit, the MAIC of SO2 at
identified sensitive receptors (villages and towns) surrounding the Project site are all below the
RMAQG limit.
During failure of the bag filter scenario, the highest 1-hour concentration of particulate matter was
predicted to be 1240 µg/m3 at Kg. S. Chengkeh, about 2.5 km northwest of the plant stack. Pollution
control equipment failures were assumed to persist for not more than one hour, as automatic
emergency shut down systems would prevent continuous uncontrolled emissions.
To ensure that air pollution control systems operate at their design performance level and to reduce
the probability of failures, it is necessary that regular monitoring and maintenance of the systems be
undertaken. An effective emergency response system is required to be in place to minimize
uncontrolled emissions.
6.5 Noise Impact
Noise impact of the Project to the study area was assessed. Noise models were built for the Unit 4
and Unit 5 construction as well as operational phases to ascertain the extent of noise impact along
the TBPP boundary and to the nearby receptors.
Construction Phase Impact
During the construction phase, no exceedance of noise levels is anticipated to extent beyond the
TBPP boundary except at Kg. S. Dinar with exceedance of 0.3 dB(A) in the day and 3.4 dB(A) at
night.
Operational Phase Impact
During full operation of Unit 4 and Unit 5, the operation noise levels at AN1 to AN3 along the TBPP
boundary are predicted to be within the respective permissible limits in the EIA Approval Conditions.
The results also concluded that the two closest settlements, Kg. S. Dinar and Kg. S. Sam will not be
potentially impacted by or subjected to noise impact from the Project.
Mitigation Measures
Mitigative measures shall be implemented in order to achieve the predicted acceptable noise levels
and to minimize potential nuisance or noise disturbances within the Project site and at the nearby
settlements.
MALAKOFF CORPORATION BERHAD
DETAILED ENVIRONMENTAL IMPACT ASSESSMENT OF A PROPOSED 2X1000MW EXTENSION AT
TANJUNG BIN COAL-FIRED POWER PLANT, MUKIM SERKAT, DAERAH PONTIAN, JOHOR DARUL
TAKZIM
Page xlvii 054/80067: 00-EN-REP-0001-0 Rev 0 : 25 July 2011
6.6 Health Risk Assessment
In health risk assessment, four air pollution emission scenarios were simulated for the project; Normal
Base Case, Normal Maximum Case, Failure of Bag Filter and Failure of Gas Desulphurizer exposure
scenarios. Under a normal and a failure of bag filter scenarios, exposure to SO2, NO2, CO, and PM2.5
at all receptors are unlikely to pose any acute and chronic health risk to the population including the
most sensitive group. However, under scenario of a failure of the bag filter, the incremental air
pollutant concentrations could be with an excess cancer risk. The exposures to toxic air pollutants are
not likely to produce any adverse health effects to community residing in the impact areas as all
hazard quotients calculated are below one for both acute and chronic effects.
6.7 Land Use
The proposed extension of the Tanjung Bin Coal-Fired Power Plant complied with the land use class
classification and conditions designated for the zone of Small Planning Block 7.1 (BPK 7.1) within
Sungai Karang Planning Block 7. Areas within this planning block have been earmarked as an
Industrial zone that allows heavy Industries such as Petrochemicals Industry, Independent Power
Plant and Bunkering Island. The Project is regarded as being compatible with the approved land use
and zoning plan and the land use of the areas in its vicinity.
Based on the potential impact form the proposed plant upon the existing and the future land use, the
impacts from noise and air modelling results would be insignificant as noise and air monitoring results
at the nearest residential areas are within DOE recommended limits.
6.8 Waste Management Implications
The waste management related issues related to dredged marine sediment, biomass waste and fill
materials, contaminated soil/ sediments, construction and demolition materials arising from the
construction works and chemical wastes, sewage, general refuse and industrial wastes from power
plant operations.
Construction Phase Impact
• Dredged marine sediment - Maintenance dredging at the cooling water intake will be required to
widen and deepen the basin. The marine sediment will be dredged and transported with care in
order to avoid leakage of sediment into the sea.
• Biomass waste and fill material - Materials generated from land clearing works such as biomass,
cut and fill materials will be confined to areas earmarked for the Project. Ground treatment may
be required and the areas will only be filled due to the low lying nature of the site. Cleared ground
cover vegetation will be used as base-fill material with no excess cut material or offsite disposal
expected.
MALAKOFF CORPORATION BERHAD
DETAILED ENVIRONMENTAL IMPACT ASSESSMENT OF A PROPOSED 2X1000MW EXTENSION AT
TANJUNG BIN COAL-FIRED POWER PLANT, MUKIM SERKAT, DAERAH PONTIAN, JOHOR DARUL
TAKZIM
Page xlviii 054/80067: 00-EN-REP-0001-0 Rev 0 : 25 July 2011
• Construction waste - Comprise of mainly of solid waste consisting of unwanted materials
generated during construction, including rejected structures and used/discarded materials.
Construction waste can be minimised through careful planning and proper execution during
construction.
• Scheduled waste - Small amounts of scheduled waste are anticipated from maintenance works
on machineries/vehicles during the construction. Scheduled wastes may pose environmental,
health and safety hazards if not stored and disposed of in an appropriate manner as specified in
the Environmental Quality (Scheduled Wastes) Regulations, 2005.
• Sewage - Sewage generated during offshore coal jetty construction is expected to be collected in
the onboard sewage rank in the case of barges/ dredgers for offsite disposal. For land-based site
workforce, sewage treatment plant or septic tank will be provided during the Unit 4 and Unit 5
construction phases.
• General refuse - Consist mainly of food waste, discarded wrappings, aluminium cans, and waste
paper which require off-site disposal.
Operational Phase Impact
• Residual process waste - Bottom ash and fly ash are produced as major coal combustion residual
waste in a power plant. The collected bottom ash is stored in an appropriate designed ash pond
whereby fly ash is disposed through licensed collector for reuse in cement industry.
• Scheduled waste - Include WWTP sludge, waste oils, used lubricants from machineries/ heavy
vehicles maintenance and spent solvent from equipment cleaning activities. The scheduled waste
generated will be managed in accordance with the Environmental Quality (Scheduled Waste)
Regulations, 2005.
Mitigation Measures
Waste shall be managed with consideration of options with the least environmental impacts and are
more sustainable in the long term. The hierarchy is as follows:
• Avoidance and reduction;
• Reuse of materials;
• Recovery and recycling; and
• Treatment and disposal.
6.9 Land and Groundwater Contamination
With proper implementation of practices and procedures, the potential for land and groundwater
contamination due to the operation of Tanjung Bin Coal-Fired Power Plant is expected to be minimal.
It is considered that the current practices and standing instructions currently used by MCB to Tanjung
MALAKOFF CORPORATION BERHAD
DETAILED ENVIRONMENTAL IMPACT ASSESSMENT OF A PROPOSED 2X1000MW EXTENSION AT
TANJUNG BIN COAL-FIRED POWER PLANT, MUKIM SERKAT, DAERAH PONTIAN, JOHOR DARUL
TAKZIM
Page xlix 054/80067: 00-EN-REP-0001-0 Rev 0 : 25 July 2011
Bin Power Plant will be adequate for the prevention of land and groundwater contamination when
applied to the Project.
6.10 Quantitative Risk Assessment
A quantitative and qualitative assessment was carried out on selected risks associated with the
proposed Project. The main risks that have impacts on the environment are mostly related to fire
hazards from LFO storage tanks and coal fires at the storage yard and mill unit.
Quantitative Assessment
The hazardous event modelled is a pool fire from LFO storage tanks. Results obtained from
frequency estimation and consequence analysis were integrated to produce risk contours for
comparison with the recommended criteria in Malaysia.
The modelled radiation zones arising from the accidental releases of identified hazards do not extend
beyond the property boundary of the plant. The iso-risk contours corresponding to the risk
acceptability criteria for the nearby industrial area (1x10-5
fatalities/person/year) and nearby
residential area (1x10-6
fatalities/person/year), have also been determined to be insignificant (i.e.
within acceptability criteria).
Qualitative Assessment
Coal Storage Yard
One of the most frequent hazards posed by coal is spontaneous combustion due to its ability to react
with oxygen in the air within the coal pile. “Hot spots” tend to develop when the coal absorbs oxygen
from the air due to the manner it is deposited or stored at a storage yard. Excessive heat build up
within the coal pile is normally the cause of a coal fire in a storage yard.
The probability of coal spontaneous combustion occuring in storage areas is very remote or does not
arise as the coal is of downstream use in power plant and not freshly mined. The deposited coal is
spread in horizontal layers and piled to ensure effective ventilation to dissipate trapped heat or
packed firmly to minimise air channels to the lower layers.
Coal Dust Hazard
The main explosion hazard associated with the coal mill unit is related to an accidental or emergency
shutdown. A shutdown of the coal mill could be attributed to power failure, system fan failure, etc.
which directly forces the coal mill to stop its operation altogether. If the coal mill unit is restarted
unaware of the fires happening inside the unit, those five explosion elements (i.e. fuel, heat, oxygen,
suspension, confinement) would be completed and an explosion is imminent when the hot burning
coal particles are suspended by the rotating movement of the confined space in the mill after the
system restarts.
MALAKOFF CORPORATION BERHAD
DETAILED ENVIRONMENTAL IMPACT ASSESSMENT OF A PROPOSED 2X1000MW EXTENSION AT
TANJUNG BIN COAL-FIRED POWER PLANT, MUKIM SERKAT, DAERAH PONTIAN, JOHOR DARUL
TAKZIM
Page l 054/80067: 00-EN-REP-0001-0 Rev 0 : 25 July 2011
A dust explosion can be prevented by elimination of one of the explosion criteria or sufficient
measures can be taken to limit the explosion magnitude to an acceptable extent by technology
adoption. Preventive strategies i.e. inerting process and CO monitoring, are primarily directed at
eliminating the explosion criteria of O2 build-up and the ignition source.
Most industrial accidents are caused by human error or negligence in plant operation and
maintenance. Preventive measures are the best means to minimise accidents. Observing strict safety
rules and regulations, implementation of prescribed safety procedures, regular and effective
maintenance, and continuous education and training are measures to be adopted for the Project.
6.11 Occupational Safety and Health
Employees’ safety and health aspects must be properly taken care of in order to avoid any untoward
incidents due to negligence as several hazardous substances are involved in the operation. During
the plant operation, workers may be exposed to hazard to their health and safety.
A copy of the MSDS is recommended to be kept close to where the hazardous substance is being
used so that workers who may be exposed can easily refer to the MSDS. The chemical
characteristics and toxicity of the element and chemicals in a waste are summarised in their
respective MSDS.
Adoption of safety procedures for all activities will be given due emphasis in the development and
operation of the plant. All employees should be trained to ensure that they are alert at all times and
able to perform their work effectively and efficiently in a safe manner, as well as be ready to respond
to any emergency. Hence, an Emergency Response Plan which outlines the procedures to be
followed has been formulated.
6.12 Socio-Economic Assessment
Generally between 5% and 10% of the locals are or will be employed at the plant during the
construction and operational phases. However, due to the special skills required for employment at
the plant, direct and indirect employment opportunities for the locals and the district might not be very
significant. Although recruitment of the locals will be prioritised, foreign workers and those from
outside Johor may be required for certain skilled work. The arrival of these workers is not expected to
impact significantly on the local residents. However, the presence of the construction workforce
during the 48-month construction period may increase pressure on public services for an interim
period.
Impacts on health and wellbeing during construction and operation will be minor provided mitigation
measures are in place to address issues such as road and marine safety, traffic management, air,
dust and noise pollution.
The loss of fishing grounds and declining fish landings is a permanent and irreversible impact.
However, the decline is not entirely due to the power plant, but is attributed to a numbers of factors at
MALAKOFF CORPORATION BERHAD
DETAILED ENVIRONMENTAL IMPACT ASSESSMENT OF A PROPOSED 2X1000MW EXTENSION AT
TANJUNG BIN COAL-FIRED POWER PLANT, MUKIM SERKAT, DAERAH PONTIAN, JOHOR DARUL
TAKZIM
Page li 054/80067: 00-EN-REP-0001-0 Rev 0 : 25 July 2011
the lower Sg Pulai region, e.g. the development of Tg Pelepas Port and its subsequent expansion,
widening of the water channel, gazetting of the water channel as the port limit and where fishing
activity is prohibited for safety reasons, reclamation works for the forthcoming petrochemical hub and
the gradual loss of mangroves due to development. Despite the three compensatory measures in the
past, there is still a residual disruption to the fishermen’s activities.
Mitigating Measures
Recommended mitigating measures to be undertaken by the Project Proponent include steps to:
i. Maximise employment of the local population through community outreach programmes,
training, education and human capital development to be initiated by the Project Proponent or
in collaboration with the relevant local and state agencies.
ii. Minimise situations where conflicts between foreign workers and the local communities could
occur.
iii. Minimise road and marine traffic risks.
iv. Expand its community outreach programme to include the fishing communities, e.g,
introduce artificial reefs in areas located outside the port limit, and expand its mangrove
replanting scheme to cover areas beyond the project site boundary.
v. Conduct more engagement/dialogue with the local communities to keep residents informed of
air and water monitoring results.
vi. Work in collaboration with the local health agency to monitor public health amongst the local
residents.
6.13 Sea Traffic
Construction Phase Impact
Construction of Unit 4 and Unit 5 will involve the transportation of 4.71 million m3 of marine sand using
589 barges over the initial 12-month construction period. 12 shipments for each unit construction is
estimated for heavy construction and plant equipment delivery.
Operational Phase Impact
During operational stage, it is estimated that an additional shipments of 61 per year is expected for
shipments of coal. However, the number of ship movements to the power plant are considered
insignificant compared to existing ship movements plying the route to the Port of Tanjung Pelepas.
Therefore mitigation measures are not required.
MALAKOFF CORPORATION BERHAD
DETAILED ENVIRONMENTAL IMPACT ASSESSMENT OF A PROPOSED 2X1000MW EXTENSION AT
TANJUNG BIN COAL-FIRED POWER PLANT, MUKIM SERKAT, DAERAH PONTIAN, JOHOR DARUL
TAKZIM
Page lii 054/80067: 00-EN-REP-0001-0 Rev 0 : 25 July 2011
7 ENVIRONMENTAL MANAGEMENT
A comprehensive Environmental Management Plan will be prepared upon approval of the DEIA
Report, prior to the implementation of the Project. The EMP will specify the various monitoring
programmes required to determine the effectiveness of mitigating measure adopted and to monitor
changes to the surrounding biological, chemical, physical and social environment, as required.
8 RESIDUAL IMPACTS
This DEIA has been conducted to evaluate the environmental effects associated with the existing
operation of the Tg. Bin Power Plant and the Project.
The key potential impacts associated with the Project have been identified and evaluated, and
mitigation measures recommended as applicable. On the basis of this assessment, it is concluded
that provided all potential impacts associated with the Project are managed appropriately and as
suggested herein, the majority of residual environmental risks will be controlled to acceptable levels.
8.1 Soil Erosion
Soil erosion during the development phase is a transient problem. However it is expected to be
gradually reduced with the progress of development and stabilisation of exposed surfaces after
development. The adoption of an ESCP and the implementation of control measures are expected to
minimise soil erosion during the development and operational phases.
Residual issues associated with soil erosion are due to failure of control measures such as
revegetation and slope stabilisation. These often relate to failure in monitoring and taking remedial
measures promptly. As such, the residual issues on soil erosion are not expected to be significant,
given that control and management measures can be taken to minimise soil loss.
8.2 Water Quality
Suspended Sedimentation
Unmitigated scenarios for marine based activities have been evaluated in Section 9.2 and most of the
impacts in terms of water quality exceedances could be mitigated by adopting effective mitigation
measures such as silt curtains and controlled dredging.
It is anticipated that no unacceptable residual impacts will arise from dredging works and land based
construction activities based on the impact assessment presented in Section 9.2 and summarised
below:
• The maximum short term elevation of SS levels is predicted to be 25 mg/l at 0.1 km and 0.15 km
from the source of intake basin dredging and pipeline alignment work, respectively. The resulting
SS concentration is thus predicted to be 45.1 mg/L, based on an average ambient SS
MALAKOFF CORPORATION BERHAD
DETAILED ENVIRONMENTAL IMPACT ASSESSMENT OF A PROPOSED 2X1000MW EXTENSION AT
TANJUNG BIN COAL-FIRED POWER PLANT, MUKIM SERKAT, DAERAH PONTIAN, JOHOR DARUL
TAKZIM
Page liii 054/80067: 00-EN-REP-0001-0 Rev 0 : 25 July 2011
concentration of 18.1 mg/L (average value for MW4 which is the nearest monitoring point to the
water intake basin). The predicted resulting concentration is still well within Marine Water Quality
and Standard for Malaysia.
• The elevation of SS will be of a short duration and the levels will return to normal after the
dredging works has stopped.
• The mixing zone is expected to be confined to the immediate vicinity of the works area.
Cooling Water Discharge
It is predicted that the maximum temperature at the existing outfall and intake is about 33.5 and 30.8�C,
respectively for the existing condition based on an ambient marine water temperature of 30�C. The
maximum temperature at the new outfall and intake is about 34.6 and 31.2�C, respectively for the existing
condition based on the same ambient marine water temperature. There is an increase of about 1% for
the maximum excess temperature at the intake due to the presence of the new outfall.
In addition to temperature, the other main environmental concern associated with cooling water
discharge is the chlorine content. However, chlorine is quickly consumed or decayed in seawater
converting mostly to chloride. Further, the dosage will be controlled to not exceed 0.2 ppm during
normal operations, which is well below the 2ppm limit stipulated under Standard B for effluent
discharge.
Given the rapid dilution of cooling water discharges from the discharge outfall, residual environmental
impacts during the operations phase are not expected.
Wastewater Discharge
Other wastewater will be treated and will be reused within the plant at the coal storage yard settling
basin, and for coal and ash transport system. No wastewater will be discharged directly from the
power plant.
Wastewater from the FGD will be treated. The absorbed SO2 is oxidised to harmless sulphate ion,
already a natural constituent of seawater, and is deemed to be insignificant impact to marine life.
Wastewater in the ash pond will be stored and circulated to the plant for reuse in the ash handling
system and will not be discharged into receiving water bodies.
It is concluded that the wastewater generated from the operation of the power plant will not cause
adverse impacts to marine water quality. Therefore, no residual impacts are anticipated provided that
the mitigating measures, described in Section 9.2, are adequately implemented and maintained.
8.3 Marine Ecology
The proposed mitigation and abatement measures as outlined above, if carried as recommended,
would have little in the way of long-term residual impacts. However, from the aquatic environment and
fisheries standpoint, there could be an impact of significance that would need to be considered i.e
MALAKOFF CORPORATION BERHAD
DETAILED ENVIRONMENTAL IMPACT ASSESSMENT OF A PROPOSED 2X1000MW EXTENSION AT
TANJUNG BIN COAL-FIRED POWER PLANT, MUKIM SERKAT, DAERAH PONTIAN, JOHOR DARUL
TAKZIM
Page liv 054/80067: 00-EN-REP-0001-0 Rev 0 : 25 July 2011
thermal pollution in the vicinity of the discharge point as well as chlorine discharge to prevent marine
growth in the cooling water system. The primary effects of thermal pollution are direct thermal shock,
changes in dissolved oxygen, and the redistribution of organisms in the local community. As for
chlorine, high levels will affect the productivity of aquatic environment.
8.4 Air Quality
Residual impacts due to air emissions are in fact the impacts due to stack emissions after flue gas
has been treated by the air pollution control equipment. As the ambient air quality monitoring for the
existing plant has indicated, the impacts from the existing plant have not adversely impacted the
surrounding environment. Air dispersion modelling for the proposed Project shows that, while
emissions of air pollutants will inevitably increase due to the increased power generating capacity of
the Project, the incremental ground level concentrations are conservatively predicted to be within
acceptable limits and thus the long term residual impacts are not significant. Proper operation and
maintenance of the power plant’s processes and air pollution control equipment will help to ensure
that emissions comply with the prescribed emission limits and thus keep residual impacts to
acceptable levels.
8.5 Noise
Based on the predicted noise levels for the Project, it can be concluded that no residual noise impact
is expected on the sensitive receptors Kg. S. Dinar and K. S. Sam. The existing workers within TBPP
may experience higher but acceptable background noise within the operational areas which require
the administration of personal protective equipment. The operational noise will be long term in nature
and mitigation measures, as described in Section 9.5.6, are crucial to be implemented to control noise
impacts to acceptable levels.
8.6 Environmental Health Risk
It was assessed that the health of the local community is unlikely to be affected by the air pollutants
emitted from the normal operation of the power plant. Under abnormal operations, such as an EP or
bag house failure, the plant will be shutdown within 60 minutes to limit uncontrolled emissions.
Therefore, no residual impact is anticipated provided that the air pollution control systems are
appropriately designed, operated and maintained and shutdown occurs within the required timeframe.
8.7 Land Use Compatibility
No residual impacts are predicted on the land use compatibility as the proposed expanded plant is
located within the existing power plant compound.
MALAKOFF CORPORATION BERHAD
DETAILED ENVIRONMENTAL IMPACT ASSESSMENT OF A PROPOSED 2X1000MW EXTENSION AT
TANJUNG BIN COAL-FIRED POWER PLANT, MUKIM SERKAT, DAERAH PONTIAN, JOHOR DARUL
TAKZIM
Page lv 054/80067: 00-EN-REP-0001-0 Rev 0 : 25 July 2011
8.8 Waste Management Implications
MCB observes strict rules on management of waste at the site. A similar system will be implemented
for the Project, hence, no residual adverse impacts are expected from the Project provided that the
mitigating measures as described in Section 9.8.4, are fully implemented, adhered to, and managed.
General refuse and construction waste are to be disposed at an approved landfill, while scheduled
waste are to be sent to prescribed premises or Kualiti Alam.
8.9 Land and Groundwater Contaminations
With proper implementation of the recommended practices and procedures, the potential for land and
groundwater contamination due to the construction and operation of the Project is expected to be
minimal. It is considered that the current procedures for handling, storage and disposal of hazardous
wastes and chemicals currently used by MCB will be adequate for the prevention of land and
groundwater contamination when applied to the Project. As such, no residual environmental impacts
are expected.
8.10 Quantitative Risk
Based on the modelling results, the cumulative quantitative risks assessed for the existing and
proposed operation will not pose any significant fire or explosion hazards to the external surrounding
population, and the potential risks involved are within acceptable levels. It is therefore concluded that
there will be no adverse residual impacts if the proposed fire fighting and mitigation measures as
recommended in Section 9.10.5 are in place and maintained in accordance to the safety regulations
stipulated by the relevant authorities.
8.11 Occupational Safety and Health
The existing power plant has recently acquired the OHSAS 18001:2007 certification, and based on
the HSE statistical data from MCB in respect to the safety performance of the existing plant, between
2006 and 2010, the effectiveness of safety management and its enforcement can be considered
adequate.
Continuous improvements in workplace safety and health management would be required in order to
provide an injury-free workplace. This can be achieved by compliance with all applicable local laws
and regulations pertaining to the management of safety and health issues, including the MCB’s HSE
performance standards. In addition, it is recommended that any education, training or initiatives to
improve safety and health include worker groups involved in non-routine activities such as plant
cleaning and contractors who are most at risk.
MALAKOFF CORPORATION BERHAD
DETAILED ENVIRONMENTAL IMPACT ASSESSMENT OF A PROPOSED 2X1000MW EXTENSION AT
TANJUNG BIN COAL-FIRED POWER PLANT, MUKIM SERKAT, DAERAH PONTIAN, JOHOR DARUL
TAKZIM
Page lvi 054/80067: 00-EN-REP-0001-0 Rev 0 : 25 July 2011
8.12 Socio-Economy
With proper mitigation and abatement measures undertaken during the construction and operational
phases, the project is not expected to have any significant lobg-term residual impacts to the
communities. However, from the aspect of increase in employment and business opportunities to the
local communities, there is a residual impact that needs to be considered. More involvement and
employment of the locals at the plant and spin-off effects to the local business community, in Daerah
Pontian and Johor state is an issue that needs the involvement and collaboration of the Project
Proponent. This residual impact cannot be resolved in the short term. Nonetheless, it is
recommended that the Project Proponent review and enlarge its existing community outreach
programme to include training, education, mentoring and capital investment of local youths to form a
potential local worker base for the plant.
8.13 Sea Traffic
The number of ship movements to the power plant both during the construction and operation phases
has been assessed to be insignificant as compared to the existing ship movements plying the route to
Port Tanjung Pelepas. However, the movement of ships/ vessels/ dredgers in the vicinity may
potentially affect the navigation of fishing boats and hindering them from reaching their fishing
grounds.
A summary of potential issues and proposed mitigation measures is given in Table ES-1.
9 CONCLUSION
This Detailed Environmental Impact Assessment has critically assessed the overall acceptability of
the environmental impacts likely to arise as a result of the construction and operation of the proposed
Project. The DEIA has demonstrated the acceptability of any residual impacts from this Project and
the protection of the population and environmentally sensitive resources. For each of the components
assessed in the DEIA report, the assessments and the residual impacts have all been shown to be
acceptable and in compliance with the relevant assessment standards/ criteria of the DOE and
industry guidelines.
Implementation of the Project will make a significant contribution to providing a reliable and cost
effective electricity supply to meet the ongoing and future power requirements, vital to the continuing
economic success of the country. Coal is acknowledged widely as a cost effective and dependable
form of fuel source. With the advances of environmental technology, the emissions of SOx and NOx
can be minimized through installation of flue gas desulphurisation plant and low NOx combustion
systems.
MA
LA
KO
FF
CO
RP
OR
AT
ION
BE
RH
AD
DE
TA
ILE
D E
NV
IRO
NM
EN
TA
L I
MP
AC
T A
SS
ES
SM
EN
T O
F A
PR
OP
OS
ED
2X
10
00
MW
EX
TE
NS
ION
AT
TA
NJ
UN
G B
IN C
OA
L-F
IRE
D P
OW
ER
PL
AN
T,
MU
KIM
SE
RK
AT
,
DA
ER
AH
PO
NT
IAN
, J
OH
OR
DA
RU
L T
AK
ZIM
P
age lvii
054
/80
06
7:
00-E
N-R
EP
-00
01
-0 R
ev 0
: 2
5 J
uly
20
11
Tab
le E
S-1
: S
um
mary
of
Ke
y I
ssu
es
an
d P
rop
osed
Mit
igati
on
Measu
res
No
K
ey I
ssu
es
P
rop
osed
Mit
igati
on
Measu
res
Refe
ren
ce in
Rep
ort
D
OE
Co
mm
en
ts
1.
So
il E
rosio
n
•
Pro
vis
ion o
f te
mpora
ry o
r p
erm
anent div
ers
ion c
ha
nne
ls
with
in t
he s
ite.
•
Eart
h b
un
d s
ho
uld
be b
uilt
near
the p
erim
ete
r of
the s
ite.
•
Pro
per
co
nstr
uctio
n o
f sedim
ent re
tentio
n p
onds.
•
Silt
tra
ps a
nd
silt
fences to b
e p
rovid
ed a
t site.
•
Topsoil
to b
e s
pre
ad a
nd
re
gra
ssin
g u
nd
ert
aken.
•
Revegeta
tion o
f bare
soil
surf
ace im
media
tely
aft
er
constr
uction.
•
Lim
it c
leari
ng t
o a
reas d
esig
nate
d f
or
the d
eve
lopm
ent
and
rela
ted f
acili
ties.
•
Min
imis
e tim
e lag b
etw
een s
ite p
repara
tion
an
d c
onstr
uction
activitie
s.
Section 9
.1
2.
Wate
r Q
uality
Constr
uction P
hase
• L
oss o
f sedim
ent to
suspe
nsio
n
• P
ollu
tants
fro
m s
ite r
unoff
ente
ring t
he r
ece
ivin
g w
ate
r
• W
aste
wate
r fr
om
tem
pora
ry s
ite
facili
ties
•
Use o
f silt
curt
ain
s to
pre
ve
nt th
e d
ispers
ion o
fsuspend
ed
sedim
ents
.
•
Tem
pora
rily
sto
p d
redgin
g o
pera
tio
ns d
uri
ng f
ast curr
ent
flow
s.
•
Care
ful sele
ctio
n, o
pera
tio
n a
nd m
ain
tena
nce o
f dre
dgin
g
pla
nts
.
•
Surf
ace r
unoff
to b
e d
irecte
d in
to a
deq
uate
ly d
esig
ned s
ilt
traps o
r sum
p p
its.
•
Open s
tockpile
s t
o b
e c
ove
red w
ith tarp
au
lin o
r sim
ilar
fabric.
Section 9
.2
MA
LA
KO
FF
CO
RP
OR
AT
ION
BE
RH
AD
DE
TA
ILE
D E
NV
IRO
NM
EN
TA
L I
MP
AC
T A
SS
ES
SM
EN
T O
F A
PR
OP
OS
ED
2X
10
00
MW
EX
TE
NS
ION
AT
TA
NJ
UN
G B
IN C
OA
L-F
IRE
D P
OW
ER
PL
AN
T,
MU
KIM
SE
RK
AT
,
DA
ER
AH
PO
NT
IAN
, J
OH
OR
DA
RU
L T
AK
ZIM
P
age lviii
054
/80
06
7:
00-E
N-R
EP
-00
01
-0 R
ev 0
: 2
5 J
uly
20
11
No
K
ey I
ssu
es
P
rop
osed
Mit
igati
on
Measu
res
Refe
ren
ce in
Rep
ort
D
OE
Co
mm
en
ts
Opera
tiona
l P
hase
• C
oolin
g w
ate
r d
ischarg
e
• O
ther
pro
cess w
ate
r dis
cha
rge
• S
torm
wate
r dis
charg
e
•
Com
ple
ted a
nd e
xposed
are
as s
hou
ld b
e r
e-v
eg
eta
ted
or
resurf
aced.
•
Pro
vis
ion o
f w
he
el w
ash
ing
ba
y a
t every
site e
xit.
•
To p
revent
foam
form
ation:
- A
do
pt a lo
w d
ischarg
e v
elo
city t
o r
ed
uce turb
ule
nce a
t
outf
all
- A
void
air e
ntr
ain
ment in
th
e d
ischarg
ed w
ate
r
- In
sta
ll a s
uita
ble
foam
barr
ier
or
conta
inm
ent syste
m in
the o
utf
all
•
Pro
cess w
aste
wa
ter
trea
ted to S
tandard
B q
ua
lity o
f th
e
En
viro
nm
enta
l Q
ua
lity (
Ind
ustr
ial E
fflu
ent)
Regu
lations 2
00
9.
•
Surf
ace r
unoff
fro
m c
oal sto
rage y
ard
will
be f
ully
recycle
d f
or
use b
y d
ust su
ppre
ssio
n s
yste
m.
•
Ash p
ond w
ill b
e lin
ed w
ith
an im
perm
eable
cla
y m
ate
rial to
avo
id s
eepa
ge o
f conta
min
ants
to g
roun
dw
ate
r.
•
All
bu
ildin
g o
r covere
d s
tru
ctu
res w
ill b
e e
quip
pe
d w
ith
rain
wate
r d
ow
n p
ipes, con
necte
d t
o th
e n
eare
st dra
in.
•
Sto
rmw
ate
r w
ill b
e p
assed t
hro
ug
h a
sum
p p
it e
qu
ippe
d w
ith
filter
befo
re b
ein
g d
ischarg
ed to
the
marine w
ate
rs.
•
All
sum
p p
its w
ill b
e r
egu
larl
y insp
ecte
d a
nd m
ain
tain
ed to
ensure
th
eir e
ffective c
apacity a
nd f
unctio
n a
t all
tim
es.
•
Sto
rmw
ate
r fr
om
work
shop a
nd lab
ora
tory
are
as w
ill p
ass
thro
ug
h a
n o
il in
terc
epto
r b
efo
re d
ischarg
e in
to t
he m
ain
dra
in.
MA
LA
KO
FF
CO
RP
OR
AT
ION
BE
RH
AD
DE
TA
ILE
D E
NV
IRO
NM
EN
TA
L I
MP
AC
T A
SS
ES
SM
EN
T O
F A
PR
OP
OS
ED
2X
10
00
MW
EX
TE
NS
ION
AT
TA
NJ
UN
G B
IN C
OA
L-F
IRE
D P
OW
ER
PL
AN
T,
MU
KIM
SE
RK
AT
,
DA
ER
AH
PO
NT
IAN
, J
OH
OR
DA
RU
L T
AK
ZIM
P
age lix
054
/80
06
7:
00-E
N-R
EP
-00
01
-0 R
ev 0
: 2
5 J
uly
20
11
No
K
ey I
ssu
es
P
rop
osed
Mit
igati
on
Measu
res
Refe
ren
ce in
Rep
ort
D
OE
Co
mm
en
ts
•
Fuel ta
nk a
nd c
hem
ical sto
rage a
reas s
ho
uld
be s
ited
on
seale
d a
reas a
nd
be s
urr
ou
nded
by b
unds w
ith a
cap
acity
equa
l to
11
0%
of
the larg
est ta
nk c
apacity to
pre
ven
t spill
age
reachin
g r
eceiv
ing
wate
rs.
•
3.
Mari
ne E
co
log
y
•
All
ne
ars
hore
dre
dg
ing a
nd
pili
ng m
ust be c
arr
ied o
ut
beh
ind
silt
curt
ain
s.
•
Appro
pria
te infr
astr
uctu
re f
or
the d
isposal and r
em
ova
l of
solid
waste
and
se
wa
ge s
hould
be
incorp
ora
ted.
•
Resid
ual ch
lori
ne t
hat
dis
ch
arg
es f
rom
the n
ew
outf
all
should
be
monitore
d f
requ
ently to
ensure
that
the
resid
ual
chlo
rine c
once
ntr
ations a
re k
ept w
ith
in a
ccep
tab
le le
ve
ls.
Section 9
.3
4.
Air
Qu
ality
Constr
uction P
hase
• F
ugitiv
e d
ust fr
om
constr
uction
activitie
s
• D
ust du
e to v
ehic
ula
r m
ove
ment
• E
xhaust
em
issio
ns f
rom
constr
uction p
lant
and
vehic
les
Opera
tiona
l P
hase
• F
ugitiv
e a
nd s
tack e
mis
sio
ns
•
Wate
r dry
ro
ad s
urf
aces, a
nd insta
ll w
ind
fences,
wash
trough a
t exit o
f th
e P
roje
ct
site.
•
Revegeta
tion o
f exposed s
urf
aces.
•
Good h
ouse k
eepin
g.
•
Contr
ol of
ve
hic
le s
pe
ed lim
it.
•
Regu
lar
serv
ice a
ndm
ain
tenance o
f constr
uction p
lant
and
veh
icle
s.
•
Pro
vis
ion o
f air p
ollu
tio
n c
ontr
ol sys
tem
s s
uch a
s f
lue g
as
desulp
huri
zation (
FG
D),
du
st filter
pla
nt,
an
d N
Ox c
ontr
ol
Section 9
.4
MA
LA
KO
FF
CO
RP
OR
AT
ION
BE
RH
AD
DE
TA
ILE
D E
NV
IRO
NM
EN
TA
L I
MP
AC
T A
SS
ES
SM
EN
T O
F A
PR
OP
OS
ED
2X
10
00
MW
EX
TE
NS
ION
AT
TA
NJ
UN
G B
IN C
OA
L-F
IRE
D P
OW
ER
PL
AN
T,
MU
KIM
SE
RK
AT
,
DA
ER
AH
PO
NT
IAN
, J
OH
OR
DA
RU
L T
AK
ZIM
P
age lx
054
/80
06
7:
00-E
N-R
EP
-00
01
-0 R
ev 0
: 2
5 J
uly
20
11
No
K
ey I
ssu
es
P
rop
osed
Mit
igati
on
Measu
res
Refe
ren
ce in
Rep
ort
D
OE
Co
mm
en
ts
sys
tem
s.
•
Perf
orm
ance m
onitoring
of
the p
ow
er
pla
nt pro
cesses.
•
Sched
ule
d a
nd p
reventive m
ain
tenance o
f equ
ipm
ent and
sys
tem
s.
•
Pollu
tio
n c
ontr
ol e
qu
ipm
ent should
be o
pera
ted a
nd
main
tain
ed b
y c
om
pete
nt
pers
onne
l.
•
Insta
llation
of
Continu
ous E
mis
sio
n M
onitorin
g S
yste
m
(CE
MS
) to
monitor
flu
e g
as e
mis
sio
n q
ua
lity.
5.
No
ise Im
pact
Constr
uction P
hase
• N
ois
e f
rom
constr
uction
equ
ipm
ent and
vehic
les
Opera
tiona
l P
hase
• N
ois
e f
rom
pro
cess a
reas
• N
ois
e f
rom
vehic
ula
r m
ove
ment
and e
qu
ipm
ent
•
Use o
f lo
w n
ois
e e
quip
ment and
turn
off
engin
e w
he
n idle
.
•
Insta
llation
of
eng
ine s
ilencers
.
•
Work
ers
to w
ear
pers
onal p
rote
ctive e
qu
ipm
ent.
•
All
constr
uction e
qu
ipm
ent
to b
e p
rop
erl
y o
pera
ted a
nd
main
tain
ed.
•
Pro
per
pla
nn
ing
an
d lo
w-n
ois
e p
lant
desig
n.
•
Routine m
ain
tena
nce a
nd inspectio
n o
n e
quip
ment.
•
Lim
it w
ork
dura
tion
in
hig
h n
ois
e a
reas.
•
Imple
menta
tio
n o
f no
ise m
onitorin
g p
rogra
mm
e.
•
Imple
menta
tio
n o
f H
eari
ng
Conserv
ation P
rogra
mm
e a
nd
aud
iom
etr
ic test fo
r w
ork
ers
.
•
Nois
e a
t e
aste
rn b
oun
dary
to m
eet D
OE
lim
its o
f 65 d
B(A
)
for
both
da
y t
ime a
nd n
ight
tim
e a
nd 6
0 d
B(A
) at
nig
ht
tim
e
Section 9
.5
MA
LA
KO
FF
CO
RP
OR
AT
ION
BE
RH
AD
DE
TA
ILE
D E
NV
IRO
NM
EN
TA
L I
MP
AC
T A
SS
ES
SM
EN
T O
F A
PR
OP
OS
ED
2X
10
00
MW
EX
TE
NS
ION
AT
TA
NJ
UN
G B
IN C
OA
L-F
IRE
D P
OW
ER
PL
AN
T,
MU
KIM
SE
RK
AT
,
DA
ER
AH
PO
NT
IAN
, J
OH
OR
DA
RU
L T
AK
ZIM
P
age lxi
054
/80
06
7:
00-E
N-R
EP
-00
01
-0 R
ev 0
: 2
5 J
uly
20
11
No
K
ey I
ssu
es
P
rop
osed
Mit
igati
on
Measu
res
Refe
ren
ce in
Rep
ort
D
OE
Co
mm
en
ts
for
nort
hern
, w
este
rn a
nd s
outh
ern
boun
dari
es.
6.
Pu
blic H
ealt
h
• N
o s
ignific
ant
impact to
com
munity h
ea
lth
•
Regu
lar
monitori
ng o
f air q
ualit
y a
t re
ce
pto
r are
as. C
ontr
ol of
air q
ualit
y w
ould
als
o e
nsure
tha
t pu
blic
he
alth r
isks a
re
min
imiz
ed.
Section 9
.6
7.
Lan
d U
se
• N
o s
ignific
ant
impact to
surr
oundin
g la
nd u
ses
•
None r
equ
ired. T
he d
evelo
pm
ent of
the P
roje
ct is
within
its
exis
tin
g T
g B
in P
ow
er
Pla
nt
lan
d h
old
ing a
nd is c
om
patible
and c
om
plie
s w
ith
the
la
nd u
se z
onin
g p
lan a
dvocate
d in t
he
Dis
tric
t Loca
l P
lan f
or
Po
ntian 2
002-2
015
. .
Section 9
.7
8.
Waste
Man
ag
em
en
t
Constr
uction P
hase
• C
onstr
uction w
aste
, g
enera
l
refu
se a
nd s
ched
ule
d w
aste
Opera
tiona
l P
hase
• M
un
icip
al so
lid w
aste
s, re
sid
ua
l
pro
cess w
aste
and s
ched
ule
d
waste
.
•
Sed
iment dre
dg
ed t
o b
e d
isposed a
t L
ong B
ank, an
appro
ve
d location,
appro
xim
ate
ly 7
7 k
m fro
m the s
ite.
•
Pro
per
dis
posal of
genera
l re
fuse a
nd c
onstr
uction w
aste
at
appro
ve
d landfill.
•
Segre
gation
an
d s
tora
ge o
f diffe
rent ty
pes o
f w
aste
in
diffe
rent conta
iners
, skip
s o
r sto
ckpile
s
•
Open b
urn
ing is s
tric
tly p
rohib
ite
d.
•
Sched
ule
d w
aste
to
be m
anage
d a
ccord
ing t
o E
nviro
nm
enta
l
Qualit
y (
Sche
dule
d W
aste
s)
Regu
lations,
200
5.
•
Sto
rage a
reas to b
e a
de
qu
ate
ly d
esig
ned
, constr
ucte
d a
nd
Section 9
.8
MA
LA
KO
FF
CO
RP
OR
AT
ION
BE
RH
AD
DE
TA
ILE
D E
NV
IRO
NM
EN
TA
L I
MP
AC
T A
SS
ES
SM
EN
T O
F A
PR
OP
OS
ED
2X
10
00
MW
EX
TE
NS
ION
AT
TA
NJ
UN
G B
IN C
OA
L-F
IRE
D P
OW
ER
PL
AN
T,
MU
KIM
SE
RK
AT
,
DA
ER
AH
PO
NT
IAN
, J
OH
OR
DA
RU
L T
AK
ZIM
P
age lxii
054
/80
06
7:
00-E
N-R
EP
-00
01
-0 R
ev 0
: 2
5 J
uly
20
11
No
K
ey I
ssu
es
P
rop
osed
Mit
igati
on
Measu
res
Refe
ren
ce in
Rep
ort
D
OE
Co
mm
en
ts
main
tain
ed to
pre
vent
spill
age o
r le
akage.
•
Resid
ual pro
cess w
aste
s w
ill b
e r
ecycle
d in t
he p
rocess lin
es
or
reused in o
ther
industr
ies (
e.g
. cem
ent in
dustr
y).
9.
Lan
d a
nd
Gro
un
dw
ate
r
Co
nta
min
ati
on
•
Lig
ht fu
el oil
tanks w
ill b
e c
onstr
ucte
d w
ithin
a b
und
ed
concre
te a
rea c
apa
ble
of
hold
ing
at
least
110
% o
f to
tal
sto
rage c
ap
acity.
•
Daily
insp
ectio
n o
f oil
inte
rcepto
rs b
y tech
nic
ians.
•
Segre
gation
, sto
rag
e a
nd h
and
ling o
f chem
icals
will
co
mply
with t
he E
nvir
onm
enta
l Q
ualit
y (
Sched
ule
d W
aste
s)
Regu
lations 2
00
5.
•
Ash p
ond w
ill b
e lin
ed w
ith
an im
perm
eable
mate
rials
to
pre
ve
nt see
pa
ge o
f he
avy m
eta
ls in the
coa
l ash into
gro
un
dw
ate
r.
Section 9
.9
10.
Qu
an
tita
tiv
e R
isk
Identified R
isks
• L
FO
Sto
rage A
rea
• C
oal S
tora
ge
Yard
•
Sto
rage t
anks m
ust be in c
om
plia
nce w
ith a
ppro
pri
ate
sta
ndard
s a
pp
lica
ble
to M
ala
ysia
.
•
Oil
sum
p, bun
d a
nd c
onta
inm
ent pits s
hall
be insta
lled
to
min
imiz
e c
onta
min
atio
n o
f spill
ag
e.
•
Pro
vis
ion o
f an inte
rna
l p
eri
mete
r dra
inag
e s
yste
m f
or
pre
ve
ntion o
f sto
rmw
ate
r conta
min
ation.
•
Coal sto
rag
e y
ard
to
be locate
d a
wa
y f
rom
heat sourc
es a
nd
Section 9
.10
MA
LA
KO
FF
CO
RP
OR
AT
ION
BE
RH
AD
DE
TA
ILE
D E
NV
IRO
NM
EN
TA
L I
MP
AC
T A
SS
ES
SM
EN
T O
F A
PR
OP
OS
ED
2X
10
00
MW
EX
TE
NS
ION
AT
TA
NJ
UN
G B
IN C
OA
L-F
IRE
D P
OW
ER
PL
AN
T,
MU
KIM
SE
RK
AT
,
DA
ER
AH
PO
NT
IAN
, J
OH
OR
DA
RU
L T
AK
ZIM
P
age lxiii
054
/80
06
7:
00-E
N-R
EP
-00
01
-0 R
ev 0
: 2
5 J
uly
20
11
No
K
ey I
ssu
es
P
rop
osed
Mit
igati
on
Measu
res
Refe
ren
ce in
Rep
ort
D
OE
Co
mm
en
ts
well
ventila
ted
.
•
Avoid
feedin
g h
ot co
als
fro
m s
tora
ge p
iles into
coa
l
pulv
eri
ser
un
it.
•
Pre
ventive a
nd r
esp
onsiv
e d
esig
n in th
e c
oa
l p
ulv
erise
r.
•
Main
tain
hig
h s
tan
dard
of
housekeepin
g a
t all
tim
es.
•
Routine e
merg
ency d
rills
.
•
Fire a
larm
and f
ire f
ighting s
yste
m s
hould
be inspecte
d a
nd
main
tain
ed r
eg
ula
rly.
•
Sto
rage t
anks s
ited w
ithin
bunds to
conta
in s
pill
age.
•
Oil
sum
p, bun
d a
nd c
onta
inm
ent pits a
re insta
lled to
min
imis
e c
onta
min
atio
n o
f spill
ag
e.
•
Pro
vis
ion o
f an inte
rna
l p
eri
mete
r dra
inag
e s
yste
m to p
reven
t
sto
rmw
ate
r co
nta
min
ation d
ue t
o s
pill
age
.
•
Peri
odic
inspectio
n a
nd m
ain
ten
ance t
o e
nsure
eq
uip
ment
is
in g
ood
work
ing c
on
ditio
ns.
11.
Occu
pati
on
al
Safe
ty a
nd
Healt
h
• W
ork
ers
’ exposure
to
safe
ty a
nd
hea
lth h
azard
s
•
Ado
ption o
f safe
ty p
rocedure
s f
or
all
activitie
s.
•
Pro
per
train
ing f
or
em
plo
ye
es to b
e a
lert
abou
t occupa
tion
al,
safe
ty a
nd h
ealth r
isks.
Section 9
.11
MA
LA
KO
FF
CO
RP
OR
AT
ION
BE
RH
AD
DE
TA
ILE
D E
NV
IRO
NM
EN
TA
L I
MP
AC
T A
SS
ES
SM
EN
T O
F A
PR
OP
OS
ED
2X
10
00
MW
EX
TE
NS
ION
AT
TA
NJ
UN
G B
IN C
OA
L-F
IRE
D P
OW
ER
PL
AN
T,
MU
KIM
SE
RK
AT
,
DA
ER
AH
PO
NT
IAN
, J
OH
OR
DA
RU
L T
AK
ZIM
P
age lxiv
054
/80
06
7:
00-E
N-R
EP
-00
01
-0 R
ev 0
: 2
5 J
uly
20
11
No
K
ey I
ssu
es
P
rop
osed
Mit
igati
on
Measu
res
Refe
ren
ce in
Rep
ort
D
OE
Co
mm
en
ts
12.
So
cio
-eco
no
my
•
Maxim
ise e
mplo
yment
of
the loca
l p
opu
latio
n thro
ug
h
com
munity o
utr
each
pro
gra
mm
es, tr
ain
ing, e
ducation a
nd
hum
an c
apita
l d
evelo
pm
ent.
•
Min
imis
e s
ituations w
here
conflic
ts b
etw
ee
n f
ore
ign w
ork
ers
and t
he loca
l com
munitie
s c
ould
occur.
•
Min
imis
e r
oad a
nd m
arine t
raff
ic r
isks.
•
Expan
d its
com
munity o
utr
each p
rogra
mm
e to inclu
de
the
fishin
g c
om
munitie
s a
nd e
xpand
its
mangro
ve r
ep
lan
ting
schem
e to c
over
are
as b
eyond t
he p
roje
ct site b
ou
nda
ry.
•
Cond
uct m
ore
engag
em
ent/dia
logue w
ith th
e local
com
munitie
s to
keep r
esid
ents
info
rmed o
f air a
nd w
ate
r
monitoring r
esu
lts.
•
Work
in c
olla
bora
tion w
ith t
he local hea
lth
ag
ency t
o m
onitor
pub
lic h
ealth a
mongst th
e local re
sid
en
ts.
Section 9
.12