excavation layout (kurd towers)
TRANSCRIPT
-
8/10/2019 Excavation Layout (Kurd Towers)...
1/2
From site discussions regarding the coming work for excavation, piles, piles caps and raft work
we have come to some suggestions to facilitate those works. To get us all up to date to those
changes and have everyones input for the coming works, we have put together the attached
drawing. Please review the drawing carefully with the aid of the following points. :
1. All piles have a number(as shown in the attached drawing), so that when we have
discussions we can mention them by name. beside each pile cap is a tag with threeelements, name of the pile cap, the pile cap type, and the originalcut of level of the piles
in that pile cap (add 7.5 cm you get the lean concrete level, add 19.5 cm (7.5+12 for lean)
you get to the excavation level). These levels are from the final design, according to our
modifications some of those levels will change.
2.
The drawing is based on the pile cap layout we got before the final changes in the pile cap
sizes (since the new set does not have a pile cap layout coming with it). I have copied the
new piles into this drawing, I have kept the original for your reference, the correct piles
are the ones that have a tag at their center with their corresponding names (and they are
always closer to the inner side of the building, or smaller when only their sizes have
changed).
3. Excavation levels for the zones:
a. Zone 1: Excavation level -23.02. (Location of pile caps C1,C2, and C5 will be
excavated from this level to their required levels. (Dear Engineer Anil. Do you
have any suggestion/objection on this issue???? If it is O.K. we will adopt it)
b. Zone 2: Excavation Level -24.42 (corresponding to -24.225 cut off level) for al
except the core @ -28.27 (-28.075 cut off level).. The core piles will be dig from -
24.42 levels, later the areas around the piles have to be excavated to get to the -
28.27 level. The cut off level of the piles in the following pile caps will change to -
24.225 (corresponding to excavation level of -24.42)
C27,C28,C29,C30,C31,C32,C36. (Dear Engineer Anil Please update the pile caps
for those mentioned abovewe will increase the thickness of those pile caps and
for the basement foundation also.).
c.
Zone 3 (The water tank area): General excavation level will be at -25.42(corresponding to 25.225 cut off level of piles). Pile cap locations for C8, C13, C14,
C15, and C17 will be excavated from that level to get to the -26.02 excavation
level (corresponding to -25.825 cut off level of piles). The rest of piles that are
higher than the designated levels will be lowered to -25.42 (-25.225 level). (Dear
Engineer Anil.. can you please update those pile caps for us.).
d. Zone 4: Excavation Level -24.42 (corresponding to -24.225 cut off level) for al
except the core @ -28.27 (-28.075 cut off level). The core piles will be dig from -
-
8/10/2019 Excavation Layout (Kurd Towers)...
2/2
24.42 levels, later the areas around the piles have to be excavated to get to the -
28.27 level. The cut off level of the piles in the following pile caps will change to -
24.225 (corresponding to excavation level of -24.42)
C67,C22,C24,C25,C81,C71,C72. (Dear Engineer Anil Please update the pile caps
for those mentioned abovewe will increase the thickness of those pile caps and
for the basement foundation also.).
e. The remaining areas have generally piles at cut off level of -22.825 (excavation leve
of -23.02). we will try to excavate the pile caps for these to the -23.02 level and the
dig the pile at their exact levels (the pile machine should stand at a higher level of -
21.7)
4. Dear Engineer Anil:We noticed that the location and/ or shape of the following pile caps
have been affected by the changes in pile sizes. So, can you review and revise those pile
caps and any other they find. The pile caps are (C1, C13, C15, C23, C25, C37, C41, C42,
C45, C76, C77, C78, C79 and C80)