ExcavationExcavation activity involves use of manual
and mechanical means and interaction of both. Hence, safety aspect to plan involvement and inter action of the same:
Individual ExcavationDeep ExcavationExcavation of TrenchesCannal Excavation
![Page 3: EXCAVATION. Excavation 1Excavation activity involves use of manual and mechanical means and interaction of both. Hence, safety aspect to plan involvement](https://reader036.vdocuments.us/reader036/viewer/2022062518/56649e175503460f94b02e60/html5/thumbnails/3.jpg)
Topic that will be dealt with
Hazards of ExcavationRemedial measuresInspectionsEmergency Response
![Page 4: EXCAVATION. Excavation 1Excavation activity involves use of manual and mechanical means and interaction of both. Hence, safety aspect to plan involvement](https://reader036.vdocuments.us/reader036/viewer/2022062518/56649e175503460f94b02e60/html5/thumbnails/4.jpg)
Collapse of shoring
Falling loads
Excavation hazards
![Page 5: EXCAVATION. Excavation 1Excavation activity involves use of manual and mechanical means and interaction of both. Hence, safety aspect to plan involvement](https://reader036.vdocuments.us/reader036/viewer/2022062518/56649e175503460f94b02e60/html5/thumbnails/5.jpg)
Slip & fall of workmen
Underground utilities
…..Excavation hazards
![Page 6: EXCAVATION. Excavation 1Excavation activity involves use of manual and mechanical means and interaction of both. Hence, safety aspect to plan involvement](https://reader036.vdocuments.us/reader036/viewer/2022062518/56649e175503460f94b02e60/html5/thumbnails/6.jpg)
Vehicular traffic
Adjacent structures
…..Excavation hazards
![Page 7: EXCAVATION. Excavation 1Excavation activity involves use of manual and mechanical means and interaction of both. Hence, safety aspect to plan involvement](https://reader036.vdocuments.us/reader036/viewer/2022062518/56649e175503460f94b02e60/html5/thumbnails/7.jpg)
Access / Egress
Mobile equipment.
…..Excavation hazards
![Page 8: EXCAVATION. Excavation 1Excavation activity involves use of manual and mechanical means and interaction of both. Hence, safety aspect to plan involvement](https://reader036.vdocuments.us/reader036/viewer/2022062518/56649e175503460f94b02e60/html5/thumbnails/8.jpg)
Cave-in / Soil collapse
Improper shoring.
…..Excavation hazards
![Page 9: EXCAVATION. Excavation 1Excavation activity involves use of manual and mechanical means and interaction of both. Hence, safety aspect to plan involvement](https://reader036.vdocuments.us/reader036/viewer/2022062518/56649e175503460f94b02e60/html5/thumbnails/9.jpg)
Excavation HazardsTo sum it up …….
• Cave -in / Soil Collapse•Utilities•Hazardous atmospheres•Adjacent structures•Falling loads•Access/Egress•Vehicle traffic•Mobile equipment
![Page 10: EXCAVATION. Excavation 1Excavation activity involves use of manual and mechanical means and interaction of both. Hence, safety aspect to plan involvement](https://reader036.vdocuments.us/reader036/viewer/2022062518/56649e175503460f94b02e60/html5/thumbnails/10.jpg)
Before going down, check & sides are properly shored.
Inspect for proper shoring
Remedial measures
![Page 11: EXCAVATION. Excavation 1Excavation activity involves use of manual and mechanical means and interaction of both. Hence, safety aspect to plan involvement](https://reader036.vdocuments.us/reader036/viewer/2022062518/56649e175503460f94b02e60/html5/thumbnails/11.jpg)
When working inside trench, location of safe exit to be ascertained.
If you notice any shift in position,stop and investigate.
…..Remedial measures
![Page 12: EXCAVATION. Excavation 1Excavation activity involves use of manual and mechanical means and interaction of both. Hence, safety aspect to plan involvement](https://reader036.vdocuments.us/reader036/viewer/2022062518/56649e175503460f94b02e60/html5/thumbnails/12.jpg)
Use a proper means of access to cross a trench
Barricade the opening
…..Remedial measures
![Page 13: EXCAVATION. Excavation 1Excavation activity involves use of manual and mechanical means and interaction of both. Hence, safety aspect to plan involvement](https://reader036.vdocuments.us/reader036/viewer/2022062518/56649e175503460f94b02e60/html5/thumbnails/13.jpg)
Proper shoring / Benching
During excavation ladder shallbe provided for access / egress.
…..Remedial measures
![Page 14: EXCAVATION. Excavation 1Excavation activity involves use of manual and mechanical means and interaction of both. Hence, safety aspect to plan involvement](https://reader036.vdocuments.us/reader036/viewer/2022062518/56649e175503460f94b02e60/html5/thumbnails/14.jpg)
Use Gumboot while workinginside a trench
…..Remedial measures
Usage of stop blocks to prevent vehicle fall inside a trench
![Page 15: EXCAVATION. Excavation 1Excavation activity involves use of manual and mechanical means and interaction of both. Hence, safety aspect to plan involvement](https://reader036.vdocuments.us/reader036/viewer/2022062518/56649e175503460f94b02e60/html5/thumbnails/15.jpg)
So what should be done prior to Excavation
Check for…..
Soil type & Ground condition
Ground / Surface Water / Water table
Under ground / Overhead utilities
Adjacent buildings
Dynamic (Traffic) load
![Page 16: EXCAVATION. Excavation 1Excavation activity involves use of manual and mechanical means and interaction of both. Hence, safety aspect to plan involvement](https://reader036.vdocuments.us/reader036/viewer/2022062518/56649e175503460f94b02e60/html5/thumbnails/16.jpg)
Preventing Soil Collapse• Soil Classification determines construction
of protective system:
Sloping or benchingShoring
•Timber / Aluminum shoring•Sheet piling
Placing shield between the side of the excavation & the work area.Underpinning
![Page 17: EXCAVATION. Excavation 1Excavation activity involves use of manual and mechanical means and interaction of both. Hence, safety aspect to plan involvement](https://reader036.vdocuments.us/reader036/viewer/2022062518/56649e175503460f94b02e60/html5/thumbnails/17.jpg)
Water Accumulation
• Ground water
• Surface water
• Water table
![Page 18: EXCAVATION. Excavation 1Excavation activity involves use of manual and mechanical means and interaction of both. Hence, safety aspect to plan involvement](https://reader036.vdocuments.us/reader036/viewer/2022062518/56649e175503460f94b02e60/html5/thumbnails/18.jpg)
Soil classification
• Type A - Cohesive soils– Clay, Sandy clay, silty clay, clay loam
• Type B - Cohesionless soils– Silt, Sandy loam, silt loam
• Type C - Water is freely seeping– Gravel, sand,
![Page 19: EXCAVATION. Excavation 1Excavation activity involves use of manual and mechanical means and interaction of both. Hence, safety aspect to plan involvement](https://reader036.vdocuments.us/reader036/viewer/2022062518/56649e175503460f94b02e60/html5/thumbnails/19.jpg)
Types of Soil
• Loose soil like black cotton and sandy soil
• Stiff soil like murrum
• Rock Excavation
![Page 20: EXCAVATION. Excavation 1Excavation activity involves use of manual and mechanical means and interaction of both. Hence, safety aspect to plan involvement](https://reader036.vdocuments.us/reader036/viewer/2022062518/56649e175503460f94b02e60/html5/thumbnails/20.jpg)
ANGLE OF REPOSE
Minimum angle of inclination for free standing soil face for stability
![Page 21: EXCAVATION. Excavation 1Excavation activity involves use of manual and mechanical means and interaction of both. Hence, safety aspect to plan involvement](https://reader036.vdocuments.us/reader036/viewer/2022062518/56649e175503460f94b02e60/html5/thumbnails/21.jpg)
Simple Sloping -Type A Soil
Unsupported Vertically-Sided Lower Portion <12 ft
Unsupported Vertically-Sided Lower Portion <8 ft
![Page 22: EXCAVATION. Excavation 1Excavation activity involves use of manual and mechanical means and interaction of both. Hence, safety aspect to plan involvement](https://reader036.vdocuments.us/reader036/viewer/2022062518/56649e175503460f94b02e60/html5/thumbnails/22.jpg)
Simple Sloping -Type A Soil
Supported or Shielded Vertically-Sided Lower Portion
![Page 23: EXCAVATION. Excavation 1Excavation activity involves use of manual and mechanical means and interaction of both. Hence, safety aspect to plan involvement](https://reader036.vdocuments.us/reader036/viewer/2022062518/56649e175503460f94b02e60/html5/thumbnails/23.jpg)
Simple Sloping
• Type A - 3/4:1 530
• Type B - 1:1 450
• Type C - 1½ :1 340
Greater than 20 feet deep shall be designed
by a registered professional engineer.
![Page 24: EXCAVATION. Excavation 1Excavation activity involves use of manual and mechanical means and interaction of both. Hence, safety aspect to plan involvement](https://reader036.vdocuments.us/reader036/viewer/2022062518/56649e175503460f94b02e60/html5/thumbnails/24.jpg)
Benching
![Page 25: EXCAVATION. Excavation 1Excavation activity involves use of manual and mechanical means and interaction of both. Hence, safety aspect to plan involvement](https://reader036.vdocuments.us/reader036/viewer/2022062518/56649e175503460f94b02e60/html5/thumbnails/25.jpg)
Preventing Soil Collapse
SLOPE / SHORING
Above 5 ft. depth.
1M3 SOIL WEIGHS APP. 1.3 MT
![Page 26: EXCAVATION. Excavation 1Excavation activity involves use of manual and mechanical means and interaction of both. Hence, safety aspect to plan involvement](https://reader036.vdocuments.us/reader036/viewer/2022062518/56649e175503460f94b02e60/html5/thumbnails/26.jpg)
Timber Shoring Installations
Refer to Design Engr.
![Page 27: EXCAVATION. Excavation 1Excavation activity involves use of manual and mechanical means and interaction of both. Hence, safety aspect to plan involvement](https://reader036.vdocuments.us/reader036/viewer/2022062518/56649e175503460f94b02e60/html5/thumbnails/27.jpg)
UtilitiesUnderground Above ground
PERMIT SYSTEM
![Page 28: EXCAVATION. Excavation 1Excavation activity involves use of manual and mechanical means and interaction of both. Hence, safety aspect to plan involvement](https://reader036.vdocuments.us/reader036/viewer/2022062518/56649e175503460f94b02e60/html5/thumbnails/28.jpg)
Hazardous Atmospheres
• Oxygen• CO
• H2S
• Petroleum• Other toxics
![Page 29: EXCAVATION. Excavation 1Excavation activity involves use of manual and mechanical means and interaction of both. Hence, safety aspect to plan involvement](https://reader036.vdocuments.us/reader036/viewer/2022062518/56649e175503460f94b02e60/html5/thumbnails/29.jpg)
Access / Egress
– Ladders - @ every
30mts.
– Ramps
– Stairs cut on earth
![Page 30: EXCAVATION. Excavation 1Excavation activity involves use of manual and mechanical means and interaction of both. Hence, safety aspect to plan involvement](https://reader036.vdocuments.us/reader036/viewer/2022062518/56649e175503460f94b02e60/html5/thumbnails/30.jpg)
STACKING OF MATERIAL ETC.
![Page 31: EXCAVATION. Excavation 1Excavation activity involves use of manual and mechanical means and interaction of both. Hence, safety aspect to plan involvement](https://reader036.vdocuments.us/reader036/viewer/2022062518/56649e175503460f94b02e60/html5/thumbnails/31.jpg)
Other parameters……..
BARRICATION FENCINGILLUMINATION
![Page 32: EXCAVATION. Excavation 1Excavation activity involves use of manual and mechanical means and interaction of both. Hence, safety aspect to plan involvement](https://reader036.vdocuments.us/reader036/viewer/2022062518/56649e175503460f94b02e60/html5/thumbnails/32.jpg)
Mobile Equipment
![Page 33: EXCAVATION. Excavation 1Excavation activity involves use of manual and mechanical means and interaction of both. Hence, safety aspect to plan involvement](https://reader036.vdocuments.us/reader036/viewer/2022062518/56649e175503460f94b02e60/html5/thumbnails/33.jpg)
Vehicle Traffic
»Traffic Control»Traffic Safety Vests
![Page 34: EXCAVATION. Excavation 1Excavation activity involves use of manual and mechanical means and interaction of both. Hence, safety aspect to plan involvement](https://reader036.vdocuments.us/reader036/viewer/2022062518/56649e175503460f94b02e60/html5/thumbnails/34.jpg)
Adjacent Structures
• Ensure structure stability– Shoring– Bracing– Evaluation by
Professional
![Page 35: EXCAVATION. Excavation 1Excavation activity involves use of manual and mechanical means and interaction of both. Hence, safety aspect to plan involvement](https://reader036.vdocuments.us/reader036/viewer/2022062518/56649e175503460f94b02e60/html5/thumbnails/35.jpg)
Excavation Inspections
• Daily Inspections by Competent Person – Start of shift, as needed, following
rainstorms or other hazard-increasing event
• Possible cave-ins• Protective system failure• Water accumulation• Hazardous atmospheres
![Page 36: EXCAVATION. Excavation 1Excavation activity involves use of manual and mechanical means and interaction of both. Hence, safety aspect to plan involvement](https://reader036.vdocuments.us/reader036/viewer/2022062518/56649e175503460f94b02e60/html5/thumbnails/36.jpg)
Excavation Rescue
• Initial Size-up – Type of incident?
• Cave-in, flooding, medical, fire, spill
– Injuries?• Number and type
– Missing personnel?– Chemical (or sewage)
exposures?– Safety of excavation for
rescuers?
![Page 37: EXCAVATION. Excavation 1Excavation activity involves use of manual and mechanical means and interaction of both. Hence, safety aspect to plan involvement](https://reader036.vdocuments.us/reader036/viewer/2022062518/56649e175503460f94b02e60/html5/thumbnails/37.jpg)
Excavation Rescue
• Notify:– Field personnel– SSC = Emergency Coordinator– Fire Department– Police Department– Emergency Medical Services
(EMS)/Hospital
![Page 38: EXCAVATION. Excavation 1Excavation activity involves use of manual and mechanical means and interaction of both. Hence, safety aspect to plan involvement](https://reader036.vdocuments.us/reader036/viewer/2022062518/56649e175503460f94b02e60/html5/thumbnails/38.jpg)
Excavation Rescue
• Stabilize cave-in• Control flooding• Hazardous
Atmospheres?– Ventilate– SCBA– Safety harness and
line– Basket stretcher
![Page 39: EXCAVATION. Excavation 1Excavation activity involves use of manual and mechanical means and interaction of both. Hence, safety aspect to plan involvement](https://reader036.vdocuments.us/reader036/viewer/2022062518/56649e175503460f94b02e60/html5/thumbnails/39.jpg)
Excavation Rescue
![Page 40: EXCAVATION. Excavation 1Excavation activity involves use of manual and mechanical means and interaction of both. Hence, safety aspect to plan involvement](https://reader036.vdocuments.us/reader036/viewer/2022062518/56649e175503460f94b02e60/html5/thumbnails/40.jpg)
DON’T ROLL THE DICE!!!
Excavation Rescues
• The best rescue is the one you never have to make!– Practice proper procedures
• Make sure everything is safe before anybody goes in!
![Page 41: EXCAVATION. Excavation 1Excavation activity involves use of manual and mechanical means and interaction of both. Hence, safety aspect to plan involvement](https://reader036.vdocuments.us/reader036/viewer/2022062518/56649e175503460f94b02e60/html5/thumbnails/41.jpg)
ACCIDENT SUMMARY
Accident Type : Cave-inWeather Conditions : Cloudy and DryType of Operation : ExcavationWas the worksite Inspected Regularly : YesTraining and Education Provided : NoAge & Sex : 32-MaleExperience at this Type of Work : 9 MonthsTime on Project : 2 Weeks
![Page 42: EXCAVATION. Excavation 1Excavation activity involves use of manual and mechanical means and interaction of both. Hence, safety aspect to plan involvement](https://reader036.vdocuments.us/reader036/viewer/2022062518/56649e175503460f94b02e60/html5/thumbnails/42.jpg)
BRIEF DESCRIPTION OF ACCIDENTWorkmen were laying sewer pipe in a trench 15 feet deep. The sides of the trench, 4 feetwide at the bottom and 15 feet wide at the top, were not shored or protected. Soil in thelower portion of the trench was mostly sand and gravel and the upper portion was clay andloam. The trench was not protected from vibration caused by heavy vehicle traffic on the
road nearby. To leave the trench, employees had to exit by climbing over the backfill. Asthey attempted to leave the trench, there was a small cave-in covering one employee to hisankles. When the other employee went to his co-worker's aid another cave-in occurredcovering him to his waist. The first employee died of a rupture of the right ventricle of hisheart at the scene of the cave-in. The other employee suffered a hip injury.