excavation and earth retaining

Upload: mohamed-hisham

Post on 06-Apr-2018

217 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/3/2019 Excavation and Earth Retaining

    1/3

    11 | P a g e

    3. Excavation and retaining structure

    The excavation depth for the foundation level of the administrative building was

    about 5 m, two equipments were used which are excavator and loader. The first step

    was marking the excavation area and that was done by a surveyor using a total

    station.

    The excavator used was a hydraulic excavator (backhoe), the excavator achieved

    its work by choosing a suitable standing position and then it began digging in the soil

    of the excavation area by pulling the dipper back toward the machine and when it

    was loaded with excavated soil, the excavator boom was raised and the excavator

    body rotated while maintaining the track in its position to load the trucks if they are

    available or to collect excavated soil in one place to be loaded to the trucks using a

    loader. After excavating to a depth of 2m, the excavator changed its position and

    began digging again to a depth of 2m in its new position, and that was repeated until

    all the area was excavated to this level. After that the excavator changed its positionand stand at the new excavated level which is 2m lower than the first standing

    position, then the excavation was completed to the required level as mentioned

    before. Figure 1 shows the process of excavation using an excavator.

    A loader was used to load the trucks with the excavated soil that was collected

    by the excavator, it also made a ramp to the excavated area and assisted the

    excavator in the excavation process, it was also used for grading and leveling.

    Three offroad dump trucks were used to transport the excavated materials from

    the site to the dump area which was 10 km away from the site.

    Figure 1

  • 8/3/2019 Excavation and Earth Retaining

    2/3

    12 | P a g e

    y One side of the excavation required a retaining structure, so the areasurrounded this side was not excavated until the retaining structure was

    installed.

    Retaining structure

    Bored piles were used to support the excavation side and prevent it from failure, the

    pile length was 10m, its diameter was 0.6m, and its reinforcement was 8 25 for the

    main reinforcement and the stirrups were 7 8 /m. The steps of forming these piles

    are as follows:

    1. Site preparation and delivering equipments to site.2. Marking out the position of piles, 10 cm was left between each pile and the

    adjacent pile.

    3. Preparation and formation of the steel cage (the pile reinforcement).4. A special machine was used in drilling, it pushed a casing down to a depth of

    2m and it removed the soil within the casing, then it completed pushing the

    casing to the next 2m and removing the soil within the casing, this process

    continued until reaching the required depth.

    5. Installation of the steel cage in the borehole.6. Concrete was poured in the borehole to form the bored pile.7. Casing was removed.8. The next pile that was bored was not the adjacent pile to the finished pile

    but it was the one next to it, the piles were casted in a sequence as shown in

    figure 2 where the number written on each pile represents the order of

    casting this pile.9. A 0.6m x 0.6m beam was casted on the top of the piles to connect them

    together, the reinforcement of this beam was 6 16 in the top and in the

    bottom.

    10.The excavation process was then completed safely in this area.Figure 2

  • 8/3/2019 Excavation and Earth Retaining

    3/3

    13 | P a g e