example of repetitive project with probabilistic activity durations

12

Click here to load reader

Upload: chachrist-srisuwanrat

Post on 26-Jun-2015

80 views

Category:

Education


2 download

DESCRIPTION

Showing how the Sequence Step Algorithm, a simulation-based scheduling algorithm models and solves scheduling problem of repetitive project with probabilistic activity durations.

TRANSCRIPT

Page 1: Example of repetitive project with probabilistic activity durations

(III) Example of SQS-AL 1

EXAMPLE OF SCHEDULING

A REPETITIVE PROJECT WITH

PROBABILISTIC ACTIVITY DURATIONS

Eliminating Idle Time in Resource Utilization

Using the Sequence Step Algorithm, SQS-AL

Presented by

Chachrist Srisuwanrat

2008

Page 2: Example of repetitive project with probabilistic activity durations

(III) Example of SQS-AL 2

EXAMPLE 2

Work Amount (Work Units)

Uni

t

A B C D E F G

1 100 150 200 150 100 150 50

2 250 100 150 200 150 250 200

3 150 200 50 100 50 50 50

4 200 150 200 150 100 100 150

Productivity

(Work Units/Time Units)

Activity Mean SD

A 10 1.0

B 20 2.0

C 15 1.5

D 15 1.5

E 25 2.5

F 15 1.5

G 20 2.0

A

B

C

D

E

F

G

SQS1 SQS2 SQS3 SQS4

For example, A1 duration on average is 100/10 = 10 time units

Page 3: Example of repetitive project with probabilistic activity durations

(III) Example of SQS-AL 3

Results from sequence step 2

replication 1 (SQS2_n1)

RSM_SQS1_n1

0

1

2

3

4

0 10 20 30 40 50 60 70 80 90 100 110 120 130

Time

Un

it

A B C D E F G

Crew Idle Time of B (CITB)

Page 4: Example of repetitive project with probabilistic activity durations

(III) Example of SQS-AL 4

Collected Crew Idle Time (CIT) at

the end of SQS2

CITB

Range % Frequency

< 35 0.01

< 40 1.26

< 45 19.37

< 50 65.92

< 55 94.27

< 60 99.40

< 65 99.95

< 70 99.99

< 75 100.00

CITC

Range % Frequency

< 25 0.01

< 30 0.03

< 35 0.09

< 40 15.33

< 45 57.92

< 50 90.67

< 55 98.94

< 60 99.92

< 65 100.00

Page 5: Example of repetitive project with probabilistic activity durations

(III) Example of SQS-AL 5

Result from sequence step 3

replication 1 (SQS3_n1)

RSM_SQS2_n1

0

1

2

3

4

0 10 20 30 40 50 60 70 80 90 100 110 120 130

Time

Un

it

A B C D E F G

B starts at date 55

C starts at date 50

Page 6: Example of repetitive project with probabilistic activity durations

(III) Example of SQS-AL 6

Collected Crew Idle Time (CIT) at the

end of SQS3

CITD

Range % Frequency

< 60 0.00

< 65 62.14

< 70 99.50

< 75 99.99

< 80 100.00

CITE

Range % Frequency

< 65 0.00

< 70 1.84

< 75 74.66

< 80 99.67

< 85 99.99

< 90 100.00

CITF

Range % Frequency

< 55 0.00

< 60 0.05

< 65 63.24

< 70 99.39

< 75 99.99

< 80 100.00

CITB

Range % Frequency

< 0 0.00

< 5 99.48

< 10 99.97

< 15 100.00

CITC

Range % Frequency

< 0 0.00

< 5 98.92

< 10 99.95

< 15 100.00

Page 7: Example of repetitive project with probabilistic activity durations

(III) Example of SQS-AL 7

Result from sequence step 4

replication 1 (SQS4_n1)

RSM_SQS3_n1

0

1

2

3

4

0 10 20 30 40 50 60 70 80 90 100 110 120 130

Time

Un

it

A B C D E F G

Page 8: Example of repetitive project with probabilistic activity durations

(III) Example of SQS-AL 8

Collected Crew Idle Time (CIT)

at the end of SQS3

CITB

Range % Frequency

< 0 0.00

< 5 99.52

< 10 99.98

< 15 100.00

CITC

Range % Frequency

< 0 0.00

< 5 99.06

< 10 99.92

< 15 100.00

CITD

Range % Frequency

< 5 0.00

< 10 100.00

CITE

Range % Frequency

< 0 0.00

< 5 100.00

CITF

Range % Frequency

< 0 0.00

< 5 100.00

CITG

Range % Frequency

< 90 0.00

< 95 21.44

< 100 93.09

< 105 99.92

< 110 100.00

Page 9: Example of repetitive project with probabilistic activity durations

(III) Example of SQS-AL 9

Result from sequence step 5*

replication 1 (SQS5_n1)

RSM_SQS4_n1

0

1

2

3

4

0 10 20 30 40 50 60 70 80 90 100 110 120 130

Time

Un

it

A B C D E F G

Page 10: Example of repetitive project with probabilistic activity durations

(III) Example of SQS-AL 10

Final Crew Idle Times

CITB

Range % Frequency

< 0 0.00

< 5 99.39

< 10 99.95

< 15 100.00

CITC

Range % Frequency

< 0 0.00

< 5 99.11

< 10 99.94

< 15 100.00

CITD

Range % Frequency

< 5 0.00

< 10 100.00

CITE

Range % Frequency

< 0 0.00

< 5 100.00

CITF

Range % Frequency

< 0 0.00

< 5 100.00

CITG

Range % Frequency

< 0 0.00

< 5 99.90

< 10 100.00

Page 11: Example of repetitive project with probabilistic activity durations

(III) Example of SQS-AL 11

Results from Each Sequence Step

Average CIT

SQS A B C D E F G

2 0 48 44 54 66 54 79

3 0 0 0 64 73 64 90

4 0 0 0 0 0 0 96

5* 0 0 0 0 0 0 0

Average Sum of Lags

Between Units

(UIT)

Assigned Crew Lead Time

(CLT) Average

Project

Duration

Average

Project

Idle Time SQS B C D E F G B C D E F G

2 38 34 30 48 30 45 0 0 0 0 0 0 102 225

3 0 0 1 11 1 16 55 50 0 0 0 0 113 29

4 0 0 0 0 0 12 55 50 70 80 70 0 119 12

5* 0 0 0 0 0 0 55 50 70 80 70 100 123 0

Conclusion

At 80% confidence of continuity,

average project duration is 123 day with 0 idle time.

Page 12: Example of repetitive project with probabilistic activity durations

(III) Example of SQS-AL 12

Balancing Between

Idle Time and

Project Duration

Total Idle Time and Project Duration

0

50

100

150

200

250

100 120 140 160 180

Average Project Duration

Aver

age

Idle

Tim

e 20%

40%

60%

80%

100%

Confident Level SQS

Average

Project

Duration

Average

Project Idle

Time

100%

2 102 225

3 128 29

4 142 14

5 158 0

80%

2 102 225

3 113 29

4 119 12

5 123 0

60%

2 102 225

3 113 30

4 114 18

5 118 2

40%

2 102 226

3 108 31

4 109 18

5 113 5

20%

2 102 225

3 108 37

4 109 25

5 113 8