example of repetitive project with probabilistic activity durations and work breaks

5
(IV) Work Breaks 1 Schedule work breaks in repetitive projects in order to reduce project duration Presented by Chachrist Srisuwanrat 2008 EXAMPLE OF SCHEDULING A REPETITIVE PROJECT WITH PROBABILISTIC ACTIVITY DURATIONS AND WORK BREAKS

Upload: chachrist-srisuwanrat

Post on 22-Jul-2015

28 views

Category:

Education


3 download

TRANSCRIPT

Page 1: Example of repetitive project with probabilistic activity durations and work breaks

(IV) Work Breaks 1

Schedule work breaks in repetitive projects

in order to reduce project duration

Presented by

Chachrist Srisuwanrat

2008

EXAMPLE OF SCHEDULING

A REPETITIVE PROJECT WITH

PROBABILISTIC ACTIVITY DURATIONS

AND WORK BREAKS

Page 2: Example of repetitive project with probabilistic activity durations and work breaks

(IV) Work Breaks 2

Example of a Repetitive Project with

Work Breaks

A B

C

E

D

F

G

H

J

SQS1 SQS2 SQS3 SQS4 SQS5

Page 3: Example of repetitive project with probabilistic activity durations and work breaks

(IV) Work Breaks 3

0

1

2

3

4

5

6

7

8

9

10

0 30 60 90 120 150 180 210 240 270 300 330 360 390 420 450

Time

Un

it

A B C D E F G H J

Average Total Idle Time = 1 day

Average Project Duration = 449 days

Controlling Sequence

0

1

2

3

4

5

6

7

8

9

10

0 30 60 90 120 150 180 210 240 270 300 330 360 390 420 450

Time

Un

it

A B C D E F G H J

Average Total Idle Time = 438 days

Average Project Duration = 277 days

0

1

2

3

4

5

6

7

8

9

10

0 30 60 90 120 150 180 210 240 270 300 330 360 390 420 450

Time

Un

it

A B C D E F G H J

Average Total Idle Time = 3 days

Average Project Duration = 376 days

Controlling Sequence

0

1

2

3

4

5

6

7

8

9

10

0 30 60 90 120 150 180 210 240 270 300 330 360 390 420 450

Time

Un

it

A B C D E F G H J

Average Total Idle Time = 3 days

Average Project Duration = 342 days

Controlling Sequence

Early-start schedule has project duration of 277 days but also has 438 days of idle time.

SQS-AL with no work breaks has average project duration of 449 days.

SQS-AL schedule with two work breaks has average project duration of 376 days.

SQS-AL schedule with three work breaks has average project duration of 342 days.

SQS-AL schedule with no work breaks.

SQS-AL schedule with two work breaks.

SQS-AL schedule with three work breaks.

- - 180 J

- - 84 H

254 G7-G8 174 G

- - 60 F

- - 102 E

- - 44 D

98 C4-C5 22 C

134 B5-B6 38 B

- - 0 A

Crew

Return Date

(CLT2)

Work

Break

Location

Crew

Arrival Date

(CLT1)

Activity

- - 288 J

- - 102 H

- - 282 G

- - 78 F

- - 120 E

- - 120 D

- - 68 C

- - 114 B

- - 0 A

Crew

Return Date

(CLT2)

Work

Break

Location

Crew

Arrival Date

(CLT1)

Activity

- - 214 J

- - 102 H

288 G7-G8 208 G

- - 78 F

- - 102 E

- - 78 D

- - 68 C

134 B5-B6 38 B

- - 0 A

Crew

Return Date

(CLT2)

Work

Break

Location

Crew

Arrival Date

(CLT1)

Activity

B5-B6

G7-G8

C4-C5

Improve

duration

by 73 days

Improve

duration

by 107 days

Page 4: Example of repetitive project with probabilistic activity durations and work breaks

(IV) Work Breaks 4

0

1

2

3

4

5

6

7

8

9

10

0 30 60 90 120 150 180 210 240 270 300 330 360 390 420 450

Time

Un

it

A B C D E F G H J

Average Total Idle Time = 3 days

Average Project Duration = 376 days

Controlling Sequence

0

1

2

3

4

5

6

7

8

9

10

0 30 60 90 120 150 180 210 240 270 300 330 360 390 420 450

Time

Un

it

A B C D E F G H J

Average Total Idle Time = 3 days

Average Project Duration = 342 days

Controlling Sequence

SQS-AL schedule with two work breaks has average project duration of 376 days.

SQS-AL schedule with three work breaks has average project duration of 342 days.

SQS-AL schedule with two work breaks.

SQS-AL schedule with three work breaks.

- - 180 J

- - 84 H

254 G7-G8 174 G

- - 60 F

- - 102 E

- - 44 D

98 C4-C5 22 C

134 B5-B6 38 B

- - 0 A

Crew

Return Date

(CLT2)

Work

Break

Location

Crew

Arrival Date

(CLT1)

Activity

- - 214 J

- - 102 H

288 G7-G8 208 G

- - 78 F

- - 102 E

- - 78 D

- - 68 C

134 B5-B6 38 B

- - 0 A

Crew

Return Date

(CLT2)

Work

Break

Location

Crew

Arrival Date

(CLT1)

Activity

B5-B6

G7-G8

C4-C5

Improve

duration

by 73 days

Improve

duration

by 107 days

Page 5: Example of repetitive project with probabilistic activity durations and work breaks

(IV) Work Breaks 5

Method

Work Break

Positions

Average

Project

Duration

Average

Total Idle

Time

Project Duration

plus

idle time

CPM - 277 438 715

SQS-AL - 449 1 450

SQS-AL* G7-G8 410 3 413

SQS-AL** G7-G8, B5-B6 376 3 379

SQS-AL*** G7-G8, B5-B6,C4-C5 342 3 345

Results from Introducing Work Breaks

• SQS-AL reduces idle time by 22 months, compared to

CPM.

• SQS-AL*** with 3 work breaks reduces project duration

by 5 months, compared to SQS-AL w/o work breaks.