evolium a9100 mbs outdoor installation manual 174173046e10
DESCRIPTION
good for BSS installation Team these book so they will enoy.TRANSCRIPT
Evolium
Evolium A9100 MBS Outdoor
Installation Manual
MBS Document
Installation Manual
3BK 17417 3046 RJZZA Ed.10
Z2EV00006-0076 Ed.10
Status RELEASED
Short title UIP 13S2
All rights reserved. Passing on and copying of this document, useand communication of its contents not permitted without writtenauthorization from Evolium.
BLANK PAGE BREAK
2 / 883BK 17417 3046 RJZZA Ed.10
Z2EV00006-0076 Ed.10
Contents
Contents
Preface . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
1 Overview . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 71.1 General Description . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8
1.1.1 Rack Presentation and Configurations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 81.1.2 Weights and Dimensions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11
1.2 Restrictions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 111.3 Prerequisite . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 111.4 Initial State . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 111.5 Final State . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 111.6 Tasks Sequences . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 121.7 Time Schedule . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 131.8 Required Information . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14
2 Preliminary Checks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15
2.1 Before Going on Site . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 162.2 Before You Start (At arrival on Site) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16
3 Delivery . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17
3.1 Rack Unpacking and Preparation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 183.2 Top Roof Removing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 193.3 Racks Dismantling (if Necessary) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20
3.3.1 Inter-Rack Cables Disconnecting (if Necessary) . . . . . . . . . . . . . . . . . . . . . . . . . . . 203.3.2 Cabinet Mechanical Disassembling (if Necessary) . . . . . . . . . . . . . . . . . . . . . . . . . 223.3.3 Batteries Dismantling (if Necessary) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23
3.4 Transportation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 263.5 Cabinet Assembling (if Dismantled on Site) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27
3.5.1 Case of Normal Operation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 273.5.2 Case of Space Constraint at Right Side of Rack . . . . . . . . . . . . . . . . . . . . . . . . . . . 27
4 Rack Positioning and Fixing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 294.1 Case of Steel Construction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 314.2 Case of Concrete Foundation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 324.3 Installation of Battery (if not Installed from Factory) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 33
4.3.1 Battery Breaker Installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 344.3.2 Battery Installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 354.3.3 Battery Assembling (if Dismantled on Site) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 374.3.4 Connect the Temperature Sensor Plug . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 37
5 Earth and Power Supply Installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 395.1 General Information . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 405.2 Installation of Cables in Site Cable Way . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 415.3 Protective Earth Cable Connection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 425.4 Mains Power Supply Connection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 43
5.4.1 AC 230 V Power Supply Connection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 435.4.2 DC - 48 V Power Supply Connection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 46
5.5 Mains Power Supply Testing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 475.5.1 AC Mains Power Supply Testing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 475.5.2 DC Mains Power Supply Testing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 48
6 PCM Cables Installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 516.1 Cable Installation in the Cable Way . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 536.2 Cable Passing at Rack Side . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 546.3 Case of 120–Ohm Cable Connection (L907/8) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 556.4 Case of 75-Ohm Coaxial Cables Connection (FLEX 3/8) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 576.5 Other Connection Possibilities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 59
6.5.1 Connection of Other Type of 120-Ohm Cables . . . . . . . . . . . . . . . . . . . . . . . . . . . . 59
3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10 3 / 88
Contents
6.5.2 Connection of Other Types of 75-Ohm Coaxial Cables . . . . . . . . . . . . . . . . . . . . . 60
7 Option: Optical Fiber Installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 617.1 Install the Optical Fiber in the Cable Way . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 627.2 Cable Passing at Rack Side . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 637.3 Connect the Optical Fibre Cable . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 64
8 Antenna Jumpers Installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 658.1 Jumpers Routing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 668.2 Connection to the Head of Feeders . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 688.3 Connection to the Rack . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 69
9 Options . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 719.1 Alarm Cable Installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 729.2 Synchronization Cables Installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 75
9.2.1 UMTS Configurations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 769.2.2 GSM Configurations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 779.2.3 Synchronization Cabling Procedure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 78
9.3 Output 48 V DC Power Cables Installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 79
10 Finishing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8110.1 Removing the Transportation Eye Bolts . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8210.2 Top Roof Closing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8210.3 Finishing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 83
Appendix A : Kits / Supplies / Documents / Tools . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 85
4 / 88 3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10
Preface
Preface
Purpose This document describes how to install an Evolium A9100 MBS Outdoor(Multistandard Base Station).
In this document, to facilitate understanding, the MBS cabinet can alsobe named:
MBO1/MBO1DC for single cabinet
MBO2/MBO2DC for twin cabinets.
Note: MBO2/MBO2DC = MBO1/MBO1DC + MBOE/MBOEDC
(MBOE/MBOEDC = Extension Cabinet on the right of equipment)
The cabinet can be equipped either with:
UMTS modules only
or GSM modules only
or UMTS and GSM modules (MBO2/MBO2DC only).
What’s New In Edition 10The section Option: Optical Fiber Installation (Section 7) was added forSTM1 connection.
The section Kits / Supplies / Documents / Tools (Section A) was updatedaccordingly.
In Edition 09The following sections were updated for Narada battery type:
Batteries Dismantling (if Necessary) (Section 3.3.3)
Battery Installation (Section 4.3.2).
Section AC 230 V Power Supply Connection (Section 5.4.1) was updated forMBOT cabinet type.
Update for bridge size in section DC - 48 V Power Supply Connection (Section5.4.2).
3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10 5 / 88
Preface
Update List of Documents (in section A) according UMTS release 4.
Audience This scenario is intended for:
Installers
Field service technicians
Site administrators
Supervisors
Project managers
Occasional users.
Assumed Knowledge The reader must have a general knowledge of:
Basic knowledge of Evolium equipments
Experience of electrical mounting cabling.
6 / 88 3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10
1 Overview
1 Overview
This chapter provides general information about the principle of the operationand requirements for the procedure.
3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10 7 / 88
1 Overview
1.1 General Description
1.1.1 Rack Presentation and Configurations
Figure 1: Evolium A9100 MBS Outdoor MBO2 cabinet, Top Cable Entry
Figure 2: Evolium A9100 MBS Outdoor MBO2 cabinet, Bottom Cable Entry
8 / 88 3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10
1 Overview
ADAM 4AC
Switch Unit radiosubrack
radio subrack
radio subrack
radio subrack
Options
AC connection
Cable gland box
Battery
SR 1
SR 2
SR 3
SR 7
OUTC
Figure 3: Evolium A9100 MBS AC Outdoor Configuration, MBO1 Cabinet
DCSwitch Unit
radio subrack
radio subrack
radio subrack
Options
GND connection
Cable gland box
SR 1
SR 2
SR 3
OUTC
DC In
Figure 4: Evolium A9100 MBS DC Outdoor Configuration, MBO1 Cabinet
3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10 9 / 88
1 Overview
options
radio subrack
radio subrack
radio subrack
OUTC
SR 4
SR 5
SR 6
ADAM 4AC
Switch Unit radiosubrack
radio subrack
radio subrack
radio subrack
Options
AC connection
Cable gland box
Battery
SR 1
SR 2
SR 3
SR 7
Figure 5: Evolium A9100 MBS AC Outdoor Configuration, MBO2 cabinet
options
radio subrack
radio subrack
radio subrack
OUTC
SR 4
SR 5
SR 6
DCSwitch Unit
radio subrack
radio subrack
radio subrack
Options
GND connection
Cable gland box
SR 1
SR 2
SR 3
DC In
Figure 6: Evolium A9100 MBS DC Outdoor Configuration, MBO2 cabinet
10 / 88 3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10
1 Overview
1.1.2 Weights and Dimensions
Dimensions (mm) Average weight (kg)
MBO1 without battery H = 1500
W = 850
D = 700
240
(max configuration)
MBO2 without battery H = 1500
W = 1500
D = 700
400 kg
(max configuration)
Battery BU 101 - 120 to 150 kg
1.2 RestrictionsNone.
1.3 PrerequisiteBefore to begin installation check that:
The site is conform to safety rules of General wiring Handbook
The site is ready to receive the rack, according to the SPP (refer to Kits /Supplies / Documents / Tools (Section A))
The equipment is delivered on site with associated installation kits (refer to
Kits / Supplies / Documents / Tools (Section A)).
Note: The site feeders are not mandatory installed before starting of operation.
1.4 Initial StateTo begin installation the following materials are delivered and packed on site:
Rack
Installation Kits
Battery BU 101 (option).
1.5 Final StateAfter installation:
Rack is fixed to the floor
Subracks are switched OFF
Equipment is ready for Commissioning.
3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10 11 / 88
1 Overview
1.6 Tasks Sequences
Preparation before going to the site
Arrival on siteDelivery Unpack the equipment
Transport the cabinets on final location
NoRack
desassemblingif necessary for transport
Cable disconnectingMechanical dismantling
Batteries dismantling (if necessary)
Run the PCM cables from the DDF to the rackConnect the PCM cables
Run the alarm cables from the site DDF to the rack Connect Alarm cables to the rack
OPTION :
Put the labels, panels, doors, roof, ...Finish the installation
Run the AC or DC power cable from the site’s power box to the rackConnect the cables to the site power box
Connect the cables to the rack
Run the GND ground cable from the site’s GND plate to the rackConnect the ground cable to the site plate
Connect the ground cable to the rack
To be done by Alcatel installation team
Can be done by the customer.If not, it isaccomplished by the installation team.
. . . . . . . . . .
OPTION: According to customerdemands, can be provided or not.
Legend
Yes
Prepare the floor
Fix the rack to the floor
Transport the rack on final location
Assemble the racksInterconnect the racks
Fit the batteries (if dismantled)
Connect the Antenna jumper cables
Run the synchronization cables from the MBS to other MBSConnect synchronization cables to the rack
OPTION :
Run the optical fiber cables from the ODF to the rackConnect the optical fiber cables
12 / 88 3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10
1 Overview
1.7 Time Schedule
In order to avoid safety problem on site, the equipment must be installedby a team of 2 installers minimum.
Task Duration1st personin mn
Duration2nd personin mn
Preliminary tasks on site 20 20
Delivery (with disassembling) 40 40
Rack positioning and fixing 30 30
Earth and power supply installation 30 30
PCM cable installation 30 30
Optical fiber cable installation 30 30
Antenna jumper installation 30 30
Finishing installation 10 10
Total without option 190 190
Option Tasks Duration1st personin mn
Duration2nd personin mn
Rack transportation on final location (1) (1)
Rack disassembling / assembling if necessaryon site
30 30
Battery removal / installation if necessary onsite
30 30
Installation of alarm cable (option) 15 -
Installation of synchronization cables (option) - 30
(1) = Transportation time to final location depending of the site. Mandatory 4people for manual transport of disassembled equipment.
3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10 13 / 88
1 Overview
1.8 Required InformationThese information are necessary to start installation:
Address and access to the site (key holder)
Grounding plate location
Customer power supply cabinet location
Fuse breakers location in customer power supply cabinet
Antenna feeders connection and information (if needed)
Rack precise location
Number of alarms to be connected (if the case)
Alarm terminal blocks location
Type of rack to be installed
Type of power supply, AC or DC
Type of rack fixing (steel construction or concrete construction)
PCM connection type (terminal blocks)
PCM cable impedance (120–ohm or 75–ohm)
Synchronization configuration (if the case).
14 / 88 3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10
2 Preliminary Checks
2 Preliminary Checks
This chapter describes the preparation of the operation in two steps:
At base
At arrival on site.
3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10 15 / 88
2 Preliminary Checks
2.1 Before Going on SiteCheck Prerequisites
Fulfillment
Refer to Prerequisite (Section 1.3) .
Check Availability of
Required Information
Refer to Required Information (Section 1.8) .
Check Availability of
Documentation
Refer to documentation list in Kits / Supplies / Documents / Tools (Section A) .
Check Availability of
Tools
Refer to tools kit list in Kits / Supplies / Documents / Tools (Section A) andrefer to the Tools Catalogue .
Check Availability of
Consumable Supplies
See consumable supplies in Kits / Supplies / Documents / Tools (Section A) .
2.2 Before You Start (At arrival on Site)Check applicable
notifications and
Operation Instructions
Refer to ITL Applicable Notifications List for checking if notifications haveto be applied during the operation.
Refer to IO Applicable Operation Instructions List for checking if OperationInstructions have to be applied.
Check that Safety
Instructions are Applied
Refer to General Wiring Handbook for checking that the safety precautionshave been taken for installation.
Fulfill Premises
Inspection Form and
Completion Check List
Fulfil the Premise Inspection Form Fulfil the Completion CheckList
The Completion Check List is completed as each instruction is carried out.
Check Availability of
Evolium Kits
Refer to Evolium kits in Kits / Supplies / Documents / Tools (Section A) .
16 / 88 3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10
3 Delivery
3 Delivery
This chapter describes how to:
Unpack the rack
Dismantle the rack (if necessary for transportation on site)
Transport the rack.
For personal safety, it is important that:
During equipment transportation, do not handle the rack by the top roof
If weather is very windy, be careful when roof opening
During battery connection, protection and insulating tools must beused.
3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10 17 / 88
3 Delivery
3.1 Rack Unpacking and Preparation
1 - Unpack the equipment 2 - Check the delivery and report any damageto the carrier delivery note
HL
1,20 0,601,20
P
AR
AV
430
H
Baie N°3Az 320°
G2_SBTS
_O_120 P
L
3 - Report on CCL:
factory serial number
cabinet serial number
4 - Locate the rack final location
18 / 88 3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10
3 Delivery
3.2 Top Roof Removing
Note: In order to remove and manipulate the roof refer also to labelling at front of roof.For safety conditions, it is preferable to manipulate with two installers.
H13
1 - Remove the four screws at front of rack 2 - Locate the two hinges at rear of rack
3 - Open the top roof about 20 4 - Push It a little to rear to engage bolt incut-out
5 - Remove the rear of roof from the bolt ofhinges
6 - Remove the top roof from the rack
3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10 19 / 88
3 Delivery
3.3 Racks Dismantling (if Necessary)Either to transport manually the rack or to pass the rack across the doors, it’spossible to disassemble the two cabinets of MBS Outdoor.
Operations :
Electrical disconnecting
Mechanical dismantling
Batteries dismantling (if necessary).
3.3.1 Inter-Rack Cables Disconnecting (if Necessary)
SR 6
SR 0
SR 5
SR 4
Door alarmHeater
Service & lightHEX/2
BUSBAR
OUTC
Flat cable
View of busbar where are connected thedifferent cables
View of OUTC board where is connected thelogic flat cable
1 - Disconnect Heater 230V cable (at bottom ofextension rack)
2 - Disconnect Heat Exchanger cable from thebusbar (HEX/2)
20 / 88 3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10
3 Delivery
3 - Disconnect “Service + light cable” 4 - Disconnect SR0, SR6, SR5, SR4 subrackpower cables from the BUSBAR
13
14
BUSBAR
DOOR SWITCH
14
13
MBO 1 MBO E
5 - Disconnect the logic flat cable from OUTCBoard
6 - Disconnect door Alarm from MBOE switch(at bottom of rack)
7 - Label , note and disconnect all cableswhich are crossing the two cabinets (examplewith UMTS modules)
3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10 21 / 88
3 Delivery
3.3.2 Cabinet Mechanical Disassembling (if Necessary)
Torxhead
2
2
H13
(on roof)
1 - Remove the right side panel 2 - Locate the four H13 assembling screws
3 - Using specific tool 3BK 08897 AA unscrewthe rack
4 - Disassemble the cabinets
22 / 88 3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10
3 Delivery
3.3.3 Batteries Dismantling (if Necessary)
Important for safety:
The weight of each element of battery is either 30 or 36 kg. Applysafety rules to carry it.
Use insulated tools during disconnecting or connecting
Batteries are delivered in fully charged status. Take precaution againstshort circuit current during batteries handling.
For Battery Type Hawker, Exide and Narada
H13
H13
H13H13
H13
H13
1 - Switch off the battery breaker 2 - Remove the battery closing plate (H13Hexagon screws)
3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10 23 / 88
3 Delivery
Battery Type Hawker Battery Type Exide and Narada
3 - Remove gas-hose from batteries (be careful, Batteries and T-connecors are fragile. Use hot airblower to soften gas-hoses)
4 - Remove the caps from the pole pins of battery
5 - On (+) terminal at the right lower battery, remove the nut/screw, disconnect the cable that goesto the circut breaker and the temperature sensor cable
24 / 88 3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10
3 Delivery
Battery Type Hawker Battery Type Exide and Narada
6 - Remove the electrical jumpers between the elements of battery
7- Remove all elements of battery
3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10 25 / 88
3 Delivery
3.4 Transportation
Example of manual transportation for a veryshort distance
Example of to avoid strap sliding duringmanual transportation
12345678901234567
Example of manual transportation using fourpeoples (single cabinet)
Example of craning using rod bar tool (forMBO2)
1740
172010 10
1x45 1x45 4.5
335 1070 335
20
MBO2 Craning tool 3BK 08804 AA Example of pallet transportation
26 / 88 3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10
3 Delivery
3.5 Cabinet Assembling (if Dismantled on Site)
3.5.1 Case of Normal Operation
To assemble the cabinet:
Follow reverse procedure as “Cabinet Disassembling”(refer to section 3.3.2)
Follow reverse procedure as “Cables Disconnecting” (refer to section 3.3.1).
3.5.2 Case of Space Constraint at Right Side of Rack
If space between right compartment and the wall is too small, it is possible touse 2 specific tools:
Ratchet + short tool 3BK 08899 AA
Long extension socket + socket 3BK 08898 AA.
Note: This tool 3BK 08898 AA can be left in the cabinet. That’s why it must beordered as other installation kits (see list of kits in appendix).
100 mm
1111111111111
1234567890123456789012345678901212121212121212121212121212123456789012345678901234567890
11111111111111
123123123
123123123
Clearanceconstraint
Guide
Rack
1234567890123456123456789012345612345678901234561234567890123456123456789012345612345678901234561234567890123456123456789012345612345678901234561234567890123456123456789012345612345678901234561234567890123456123456789012345612345678901234561234567890123456123456789012345612345678901234561234567890123456123456789012345612345678901234561234567890123456123456789012345612345678901234561234567890123456
Wall
3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10 27 / 88
3 Delivery
Cut view of screwing system inside the rack
View of long extension + socket 3BK 08898 AA
View of ratchet + short tool 3BK 08899 AA
28 / 88 3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10
4 Rack Positioning and Fixing
4 Rack Positioning and Fixing
This chapter describes how to fix the rack to the floor either on concretefoundation or on steel construction.
Be careful :
During equipment transportation, do not handle the rack by the toproof ! (it is not designed for handling)
If weather is very windy, be careful when roof opening or removing.
3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10 29 / 88
4 Rack Positioning and Fixing
Materials
Description Reference Kit
Bolt M12 x 80 1AD 00050 0123 Basic Kit
Washer 12.4 x 24 x 1.6 1AD 00236 0006 Basic Kit
Washer 13 x 24x 1.2 waved 1AD 00034 0017 Basic Kit
Nut M12 1AD 00197 0008 Basic Kit
Levelling shims 3BK 26159 AAAA Basic Kit
Expanding wall-plug 1AD 01187 0003 Basic Kit
View of installation on steel construction View of installation on concrete foundation
Torxhead
2
2
1 - Remove Torx screws of right and left sidepanels
2 - Remove right and left side panels (slide itto front)
30 / 88 3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10
4 Rack Positioning and Fixing
4.1 Case of Steel Construction
1234512345
1234567890123412345678901234
123456123456
levelingfoot
Shims Steel construction
1 - Level the rack using spanner of 19 2 - If necessary, insert shims under the rackalong entire rail
1234512345
1234567890123412345678901234
123456123456
12 Waved Washer
3 - Release the screw in order to transferweight of MBO on shims
4 - Fix the rack to the steel construction
3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10 31 / 88
4 Rack Positioning and Fixing
4.2 Case of Concrete Foundation
500 mm+/− 1mm
500 mm+/− 1mm
1460,5 +/− 1mm
839 +/− 1mm
MBO1(RS)
MBO2(RS)
85 mm
22 mm
1 - Mark the position of fixing points to thefoundation
2 - Drill the four holes to the floor
1234567890123456712345678901234567
3 - Prepare wall plug:
Insert wall-plug with screws into the holes
Tighten a little and remove the screw fromthe wall-plug
4 - Position the rack
123456123456
123456123456
Leveling foot
levelingfoot
Shims Soket rail
5 - Using spanner of 19, level the rack 6 - Fix the rack:
Position the shims under the rack
Tighten the floor fixing screws
32 / 88 3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10
4 Rack Positioning and Fixing
4.3 Installation of Battery (if not Installed from Factory)3BK 25246 ACAA
3BK 25245 ACAA
(Blue − 48V)
(Black 0V)
0 V − 48 V
3BK 25868 BAAA 3BK 25869 BAAA
Sensor cable3BK 08119 ABAA
10 mm2 black
OUTC"Sensor temp"
Stud 8 to 6 mm
Stud 8 to 6 mm
bridge
bridge
ADAM 4 module
Breakers
− 48 V
O Volt
(Blue − 48V) (Black 0V)
Figure 7: General scheme of battery connecting
3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10 33 / 88
4 Rack Positioning and Fixing
4.3.1 Battery Breaker Installation
1 - Screw the cables to the breaker 2 - Position the breaker at top of cabinet
Breakers
OFF
Torx screw d = 3 mmto fix the breaker
3 - Screw the breaker to the bracket 4 - Connect the cables to the ADAM4 module
34 / 88 3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10
4 Rack Positioning and Fixing
4.3.2 Battery Installation
Note: For battery positioning and inter-connecting, see other pictures in chapter3.3.3 “BU 101 Battery Dismantling”.
1. Put the batteries in the compartment at bottom of cabinet
2. Put spacer between the batteries
3. Install gas-hoses between batteries
4. Connect power cables between the elements of batteries
5. For Battery Type Hawker, screw the stud adapter to pole (+) and pole(–) of battery pack
6. Connect positive and negative cables to the battery pack
7. Connect the temperature sensor to the grounded pole (+) of battery pack
8. Use supplied protective covers to insulate terminals of batteries
9. Connect the temperature sensor cable to the OUTC board
10. Add or cut foam on battery closing plate and assemble it (H13 Hexagonscrews) to battery housing
M6 Terminal Stud
Upper Block Lower Block
Hawker Battery Type
REDBLUE
Spacer
5
10 5
5
10 5
Spacer
Spacer
Spacer
Spacer
Spacer
Spacer and stud positioning view Hawker Battery Type
3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10 35 / 88
4 Rack Positioning and Fixing
Upper Block Lower Block
Exide and Narada Battery Type
Spacer
5
10 5
5
10 5
Spacer
Spacer Spacer
Spacer positioning view Exide and Narada Battery Type
For Hawker Battery stud adapter must bescrewed in (+) and (–) poles of battery pack
Principle of gas-hose installation
36 / 88 3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10
4 Rack Positioning and Fixing
Depending on battery type, add or removefoam, to fix battery closing plate
The temperature sensor cable must beconnected to OUTC board
4.3.3 Battery Assembling (if Dismantled on Site)
To perform battery assembling proceed as reverse procedure as batterydismantling (refer to section 3.3.3).
4.3.4 Connect the Temperature Sensor Plug
This section must be applied only in case of Alcatel 9100 MBS DC Outdoor.
Description Reference Kit
Temperature sensor plug 3BK 26147 AAAA CMO11
To connect the temperature sensor plug:
1. Identify the X200 connector on OUTC board
2. Connect the SENSP plug to the X200 connector.
3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10 37 / 88
4 Rack Positioning and Fixing
Figure 8: SENSP on OUTC Board
38 / 88 3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10
5 Earth and Power Supply Installation
5 Earth and Power Supply Installation
This chapter describes the procedure to:
Install Personal Protective Earth cable
Install AC 230 V mains cables
Install DC - 48V mains cables
Test the power supply installation.
Before making any electrical connection to the rack, ensure that thesafety instructions are applied.
It is essential that:
The electrical power supply is disconnected. Ensure all switches orfuses devoted to the rack into the site connection box are powered off
Due to high leakage current, the protective EARTH must be connectedto the equipment before AC/DC power cable connection.
3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10 39 / 88
5 Earth and Power Supply Installation
5.1 General InformationMaterials
Description Reference Kit
Tie-wrap 1AD 00414 0006 Basic kit
Yellow/Green cable 1x50 mm2 3BK 08957 xx Kit list
AC 230 power cable 5x6 mm2 3BK 08944 AA Kit list
AC 230 V power cable 3x2.5 mm2 3BK 25561 xx Kit list
DC -48V power cable 1x25 mm2 blue 3BK 25995 xx Kit list
DC 0V power cable 1x25 mm2 black 3BK 08963 xx Kit list
Lug ring crimp 8mm/50 mm2 1AB 03205 0071 Basic kit
Lug pin crimp for power cable 25 mm2 1AB 05067 0013 Basic kit
Lug, hole ∅ 6mm for power cable 25 mm2 1AB 03205 0063 Basic kit
Wire terminal for 6 mm2 cable 1AB 05067 0004 Basic kit
Wire terminal for 2.5 mm2 cable 1AB 05067 0006 Basic kit
General view of rack fully cabled (antennajumpers, PCM cables, power cables, . . . )
AC 230 Vcable
GNDcable
View of AC 230V and Protective Earth cabling
40 / 88 3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10
5 Earth and Power Supply Installation
5.2 Installation of Cables in Site Cable Way
GND GND Power cables
1 - Install GND Yellow / Green cable in powercompartment of cable tray
2 - Install AC 230 V mains power supply inpower compartment of cable tray
1m
3 - Attach cables with plastic tie wraps 4 - Cut the cables at good length
3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10 41 / 88
5 Earth and Power Supply Installation
5.3 Protective Earth Cable Connection
1 - Crimp a 8mm terminal lug at each end ofGND cable
2 - Connect GND cable to the site Earth plateand put a label: [Node B (x) ]
12345123451234512345123451234512345123451234512345123451234512345123451234512345
GND
3 - Connect Earth cable to the GND 8mm studof rack and attach it to the rack
Cut view of GND fixing system
42 / 88 3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10
5 Earth and Power Supply Installation
5.4 Mains Power Supply Connection
5.4.1 AC 230 V Power Supply Connection
BridgeN L PE
View of 1–phase installation using 3–wire cable View of 1–phase installation using 3–wirecable on LPFMT
BridgeN PEL3 L1L2
GND
View of 1–phase installation using 5–wire cable View of 3–phase installation using 5–wirecable
3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10 43 / 88
5 Earth and Power Supply Installation
15 m
m
10 m
m
In 1–phase installation cut 5 mm from thebridge
In 1–phase installation fit the bridge to theconnector.The bridge is not used in case of MBOT.In 3–phase installation, do not fit (or remove)the bridge from the connector
Wire European Colors Standard of Wires
Earth Yellow/Green
Neutral (N) Blue
Phase 1 (L1) Black
Phase 2 (L2) Brown
Phase 3 (L3) Red
1 - Prepare head of AC power cable (exampleof cable for 1–phase installation)
2 - Put a shrink sleeve at end of the cable
44 / 88 3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10
5 Earth and Power Supply Installation
3 - Put wire terminal at end of each wire(example 1–phase installation)
4 - Connect cable to AC connector on the leftside of rack
5 - Tilt a little the bridge and close the AC cover 6 - Connect and label the AC mains cable tothe site power supply box (label [Node B (x) ]
3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10 45 / 88
5 Earth and Power Supply Installation
5.4.2 DC - 48 V Power Supply Connection
16mm
1 - Prepare head of the DC power cables 2 - Put a shrink sleeve at end of each cable
6
3 - Put wire terminal at end of each wire 4 - Run the DC -48V blue cable through therubber cap and connect it to the DC In filter
Nod
eB(x
)
5 - Connect the DC 0V black cable to thegrounding bolt
6 - Connect and label the DC mains cable tothe primary DC power supply (label [Node B(x) ]
46 / 88 3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10
5 Earth and Power Supply Installation
5.5 Mains Power Supply Testing
5.5.1 AC Mains Power Supply Testing
AC230V
N P
1 - At side power cabinet, check if fuse breakersare switched off
2 - At rack side, using an ohm-meter, check ifthere is no short-circuit between each phaseand neutral
N P
3 - At rack side, do the same test betweenprotective Earth and each 230 V phase
4 - At side power cabinet, switch on the fusebreakers
N P
V
5 - At rack side, verify if the voltage betweenphases and neutral is about 230 Volts
6 - At rack side, using phase tester, verify thatthe phase wires are connected to the wellconnection points
3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10 47 / 88
5 Earth and Power Supply Installation
7 - At site power cabinet, switch off the fusebreakers
8 - At rack side, using phase tester, verify if thephases are switched off
5.5.2 DC Mains Power Supply Testing
DC− 48V
0V − 48V
1 - At side power cabinet, check if fuse breakersare switched off
2 - At rack side, using an ohm-meter, checkif there is no short-circuit between -48V filterand 0V stud
0V − 48V
V
3 - At side power cabinet, switch on the fusebreakers
4 - At rack side, verify if the voltage between-48V filter and 0V stud is about -48 Volts DCnominal. Check carefully the polarity.
48 / 88 3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10
5 Earth and Power Supply Installation
5 - At site power cabinet, switch off the fusebreakers
6 - At rack side, using a multimeter, verify ifthe -48V is switched off.Fit the rubber cap tothe -48V terminal.
3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10 49 / 88
5 Earth and Power Supply Installation
50 / 88 3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10
6 PCM Cables Installation
6 PCM Cables Installation
This chapter describes the procedure to:
Install PCM cables in site cable tray
Connect PCM cables to the connection area of the rack.
Help: To install and connect PCM cables at site side, refer to the document:Installation Method of DDF for BSS Equipment document.
Note: In case of multistandard installation, the ports 1 and 2 are dedicated to theGSM part (Abis 1 and 2) and ports 3 and 4 are dedicated to the UMTS part(E1-1 and E1-2).
Depending on equipped SUMU board variant the following situations can occur:
For SUMU variants up to 3BK 25837 AGxx only the PCM connection
is supported and it is mandatory
From SUMU variant 3BK 25837 AHxx on, the PCM connection is optional.
3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10 51 / 88
6 PCM Cables Installation
Materials
Description Reference Kit
Tie-wrap 1AD 00414 0006 Basic kit
Label kit 3BK 08062 ACAA Basic kit
120–ohm PCM cable L907/8 3BK 08965 xx -
75–ohm PCM cable FLEX3/8 3BK 25241 xx -
SP2M adapter 3BK 08949 AA -
ST75 Heat shrink sleeve 1AC 00330 0002 -
52 / 88 3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10
6 PCM Cables Installation
6.1 Cable Installation in the Cable Way
Low power compartment 1m
1 - Install PCM cables in correspondingcompartment of cable way
2 - Attach cables with plastic tie-wrap
E1
3 - Using a marker, mark the end of cable 4 - Label the cable with supplied labels:
in UMTS fit [E1] label only
in GSM fit [ABIS 1] + [ABIS 2] labels
in GSM + UMTS fit both labels
3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10 53 / 88
6 PCM Cables Installation
6.2 Cable Passing at Rack Side
40 mm
1 - Remove the cable gland cover 2 - Strip the cable at cable gland level
123
12345678901231234567890123
123123
111
11
Tie wrap
Tie wrap
11 cover
3 - Pass the cable in the cable gland and attachit to the rack
4 - Pass the cable toward the OUTC board
KRONEconnector
View of connection on OUTC board View of cables path in cable gland
54 / 88 3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10
6 PCM Cables Installation
6.3 Case of 120–Ohm Cable Connection (L907/8)
Quad 1grey/white purple/blue
Quad 4 Quad 2
Quad 3grey/blackpurple/red
grey/green
purple/white grey/yellow
purple/brown
View of L 907/8 cable
KRONEPposition
Color of Wires Quad Signal
8 White
Grey
1 Port 1 / TX
(High level signal toward RNC)
7 Yellow
Grey
2 Port 1/ RX
(Low level signal from RNC)
6 Blue
Purple
1 Port 2 / TX
(High level signal toward RNC)
5 Brown
Purple
2 Port 2 / RX
(Low level signal from RNC)
4 Black
Grey
3 Port 3 / TX
(High level signal toward RNC)
3 Green
Grey
4 Port 3 / RX
(Low level signal from RNC)
2 Red
Purple
3 Port 4 / TX
(High level signal toward RNC)
1 White
Purple
4 Port 4 / RX
(Low level signal from RNC)
3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10 55 / 88
6 PCM Cables Installation
150 mm
1 - Remove the PCM lightening protection fromKRONE connector of OUTC board
2 - Prepare head of L907/8 cable
Sleeve
3 - Fit a sleeve to end of cable 4 - Insert the L 907/8 wires using mandatoryKRONE original tool
5 - Fit the lightening protection to the KRONEconnector
Example of KRONE finished cabling (cablebraid must be squeezed in metallic clamp)
56 / 88 3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10
6 PCM Cables Installation
6.4 Case of 75-Ohm Coaxial Cables Connection (FLEX 3/8)
KRONE position Coaxial number Core/Braid Signal
8 1 Core
Braid
Port 1 / TX
(High level signal toward RNC)
7 2 Core
Braid
Port 1/ RX
(Low level signal from RNC)
6 3 Core
Braid
Port 2 / TX
(High level signal toward RNC)
5 4 Core
Braid
Port 2 / RX
(Low level signal from RNC)
4 5 Core
Braid
Port 3 / TX
(High level signal toward RNC)
3 6 Core
Braid
Port 3 / RX
(Low level signal from RNC)
2 7 Core
Braid
Port 4 / TX
(High level signal toward RNC)
1 8 Core
Braid
Port 4 / RX
(Low level signal from RNC)
50 mm
12341234
1212
12
10 mm
1 - Remove the PCM lightening protection fromKRONE connector of OUTC board
2 - Using Hot Air Blower, fit the Heat ShrinkSleeve 1AC 00330 0002 on each coaxial. Fit arubber sleeve on head of cable
3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10 57 / 88
6 PCM Cables Installation
3 - Insert the 75–ohm coaxial using originalKRONE tool
4 - Fit 2x SP2M 75–ohm adapter at PCM sub-Dport ABIS1 and ABIS2 on OUTC board
AB
IS3
AB
IS4
11
TX
R
XT
X
RX
88 On OUTC screwblock terminal mount:
wire bridge from pin 1 to pin 2
wire bridge from pin 4 to pin 5
wire bridge from pin 6 to pin 7
5 - Connect wire bridge for use of port 3 and 4 (UMTS E1-3/E1-4, Multistandard E1-1/E1-2) onOUTC ABIS3 and ABIS4
12
34
56
78
8 coaxial cable
RX
RX
RX
RX
TX
TX
TX
TX
RX
TX 87
TX coax.
core
TX
View of 75–ohm cabling Detail of single coaxial in KRONE connector
58 / 88 3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10
6 PCM Cables Installation
6.5 Other Connection Possibilities
6.5.1 Connection of Other Type of 120-Ohm Cables
ABIS3 ABIS4
1 1TX RX TX RX
8 8
ABIS1 ABIS21 1
TX RX TX RX8 8
GSM (ABIS1, ABIS2) −−−−−−−−− Multistandard −−−−−−−−−−− UMTS (E1−1, E1−2)
UMTS only (E1−1, E1−2, E1−3, E1−4)
GSM (ABIS1, ABIS2)
Example of OUTC screwing terminals
If cables are not supplied by Evolium, then the wires must have rightspecifications for inserting in the KRONE connector. If not, the wires have to beconnected to the green screwing connectors of OUTC board.
The 3 jumpers must be removed from the connectors (they are used only for75-Ohm connection).
1 GND braid earthing clamp
2 TX
3 TX
Output signal going
toward BSC
4 GND drain wires
5 RX
6 RX
BTS input signal coming
from BSC
7 R200 (not used)
8 GND braid earthing clamp
3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10 59 / 88
6 PCM Cables Installation
6.5.2 Connection of Other Types of 75-Ohm Coaxial Cables
50 mm
10 mm123123123123
1
12
34
56
7
123412341234
12345612345671123456711234567112345671123456781234567812341234512341234123 123123 123123123
12341234561123456112345612123456123456712341234123 12123 121231212
2
Procedure 1. Prepare the cable head.
2. Connect the wires to the terminals and mount the earthing clamp.
Coaxial Connector Pin Remarks
1 ABIS 1 (TX) 2 - braid
3 - inner conductor
2 ABIS 1 (RX) 5 - braid
6 - inner conductor
3 ABIS 2 (TX) 2 - braid
3 - inner conductor
4 ABIS 2 (RX) 5 - braid
6 - inner conductor
For each connector:
wire bridge from pin 1 to pin 2
wire bridge from pin 4 to pin 5
wire bridge from pin 6 to pin 7
5 ABIS 3(TX) 2 - braid
3 - inner conductor
6 ABIS 3(RX) 5 - braid
6 - inner conductor
7 ABIS 4(TX) 2 - braid
3 - inner conductor
8 ABIS 4(RX) 5 - braid
6 - inner conductor
60 / 88 3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10
7 Option: Optical Fiber Installation
7 Option: Optical Fiber Installation
This section describes the optical fiber installation and connection.
Depending on equipped SUMU board variant the following situations can occur:
From SUMU variant 3BK 25837 AHxx on, the STM1 connection is mandatory
For SUMU variants up to 3BK 25837 AGxx only the PCM connectionis supported.
3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10 61 / 88
7 Option: Optical Fiber Installation
7.1 Install the Optical Fiber in the Cable WayThe following table lists the items required for this task.
Description Reference Kit
Label Kit 1AD 01960 0003
Tie wrap 360 x 4.6 mm 1AD 00414 0006
3BK 27700 AAAA
(OFC3SEC)
6 optical fiber cable 3BK 27554 Ax Installation kit
Low power compartment 1m
1- Install the optical fiber cables in low powercompartment of the cable tray (far from thepower supply cable).
2- Attach the optical fibre cables with plastictie wraps.
STM 1
3- Mark the optical fibre cables with a marker. 4- Label the cable with supplied labels on bothends.
62 / 88 3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10
7 Option: Optical Fiber Installation
7.2 Cable Passing at Rack Side
123
12345678901231234567890123
123123
111
11
Tie wrap
Tie wrap
11 cover
1 - Remove the cable gland cover 2 - Pass the optical fiber cable through thecable gland and attach it to the rack
3 - Pass the cable towards the splicing box.Ensure that the minimum bending radius forthe optical fibre cable is 50 mm.
3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10 63 / 88
7 Option: Optical Fiber Installation
7.3 Connect the Optical Fibre CableThe following table lists the items required for this task.
Description Reference Kit
Patch cord Lg 2m connectors LC 1AC 03809 0002
Mechnical splice 1AB 34352 0001
Tie wrap 360 x 4.6 mm 1AD 00414 0006 3BK 27700 AAAA
(OFC3SEC)
To connect the optical fiber cable:
1. Connect the optical fibre cable to the splicing box.
For details about the connection refer to the document Patching and SplicingOptical Module reference ABS 1014.
2. Insert the splicing box in a subrack
3. Fasten the splicing box with the provided screws
4. Connect the patch cords to the splicing box
5. Connect the patch cords to the SUMU board.
Figure 9: SUMU Connection
6. Connect the optical fibre cable to the optical distribution frame.
64 / 88 3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10
8 Antenna Jumpers Installation
8 Antenna Jumpers Installation
This chapter describes how to connect the antenna jumpers between feedersand top rack.
3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10 65 / 88
8 Antenna Jumpers Installation
8.1 Jumpers RoutingMaterials
Description Reference Kit
Labels 3BK 08062 xxxx Basic kit
Tie wraps 1AD 00414 0006 Basic kit
Antenna jumper cable 3BK 05360 xxxx -
Tie wrap to fix jumpers
General view of jumper installation
(example with 12 jumpers)
66 / 88 3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10
8 Antenna Jumpers Installation
Jumpers
Antenna feeders
N° Sector or
AZIMUT
N° Sector or
AZIMUT
N° Sector or
AZIMUT
Rack
Labels
UMTS
UMTSUMTS
NANT A
PANT A
NANT B
QANT B
QANT A
PANT B
NANT A
NANT A
NANT B
PANT A
PANT B
QANT A
QANT B
NANT B
PANT A
PANT B
QANT A
QANT B
Principle of antenna jumpers cabling at top of rack (example 3 sectors)
N Ant A
UMTS
UMTS
Example of customer labelson feeders
Jumper labeling
UMTS case: Label the jumper with supplied labels (do not forget UMTSlabels)
GSM case: Label the jumper with supplied labels (do not forget frequencylabels)
3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10 67 / 88
8 Antenna Jumpers Installation
8.2 Connection to the Head of Feeders
If feeders are not labeled, don’t connect the jumpers, but inform the customerand fulfill the Completion Check List (CCL).
Materials
Description Reference Kit
Vinyl electrical tape 1AC 01556 0001 Basic kit
Tie wrap 1AD 00414 0006 Basic kit
Linerless Rubber Splicing Tape 1AC 01595 0001 Basic kit
2732
1 - Screw connector male with connectorfemale (tighten the screw manually then shakecables a little)
2 - Using specific tightening tool 3BK 25050AA, tighten with firmness (refer to Toolscatalogue)
1Feeder Jumper
12123112341212311212123123
123451234512 12123 121123 12123 123123 123123 12123 12123 12123 123123123123
123123451234512 112 1112 11121212112123112312312341212312
2 1Feeder Jumper
123123123112341231211
3 - Fit the Linerless Rubber Splicing Tape 3M130C (1 in figure)
4 - Fit the Vinyl Electrical Tape (2 of figure) overthe Linerless Rubber Splicing Tape (1 in figure)
68 / 88 3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10
8 Antenna Jumpers Installation
8.3 Connection to the Rack
Qant B
Nant A
Nant B
Qant A
Pant A
Pant B
Qant A
Nant B
Pant B
Nant A
Pant A
Sant A
Tant A
Rant A
Sant B
Tant B
Rant B
Qant B
Qant A
Nant B
Nant A
Sant A
Tant A
Rant A
Sant B
Tant B
Rant B
Qant B
Qant A
Nant B
Pant B
Nant A
Pant A
Sant A
Tant A
Rant A
Sant B
Tant B
Rant B
Qant B
UMTS or
GSM
UMTS only
GSMonly
UMTS and GSM
UMTS partGSM part
Pant A
Pant B
View of rack top jumper’s cabling
3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10 69 / 88
8 Antenna Jumpers Installation
For the 1AB 18821 000x jumpers, use the bending tool and follow instructionsfrom IO 95 (3DF 00300 0095 UAZZA).
Procedure 1. Ensure that the radius of each cable is at least 3 cm
2. Refer to required information of section 1.8 for cable connections
3. Connect the cables at top of rack
4. Tighten the screw manually then shake a little the cables
5. Using tightening tool 3BK 25050 AA, tighten with firmness
When using torque wrenches to tighten the RF cables use the torquevalues given in the following table:
Connector Type Torque [Nm]
N 0.7-1.1
Bridge on ANC 0.8-1.0
7/16 25
LPQMR 35
CS25 25
Table 1: Torque Values for Different Connectors
For torque wrenches to be used see Tools Catalogue reference 3BK204580001 RJZZA.
6. Use tie wraps to bundle the jumpers together.
70 / 88 3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10
9 Options
9 Options
This chapter describes how to:
Install and connect the external alarm cables
Install and connect synchronization cables with other MBS or BTS of the site
Install and connect 48 Volts Output.
Note: To install and connect External Alarm cables at site side, refer to the document:Installation Method of DDF for BSS Equipment.
3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10 71 / 88
9 Options
9.1 Alarm Cable InstallationMaterials
Description Reference Kit
Tie-wrap 360 x 4.6 mm 1AD 00414 0006 Basic kit
Labels 3BK 08062 ACAA Basic kit
Cable L907/8 (8 pairs) 3BK 08965 xx -
Low power compartment
1 - Using marker, mark the cable 2 - Install the cable in the correspondingcompartment of the cable way
1m40 mm
3 - Using tie-wraps, attach the cable to thecable way
4 - Strip the cable at cable gland level
72 / 88 3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10
9 Options
123
12345678901231234567890123
123123
111
11
Tie wrap
Tie wrap
11 cover
70 mm
5 - Pass the cable in the cable gland and attachit to the rack
6 - Prepare the head of cable (cut the no-usedwires)
7 - Label the cable with supplied labels: [Alarm1]
8 - Unscrew and remove the jumpers fromalarm connector
9 - Connect the cable to the Connector 10 - Squeeze the cable in the earthing clamp
3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10 73 / 88
9 Options
Alarm
12
45
67
8 Alarm n°10Alarm n°13
Alarm n°14
View of OUTC board View of Alarm connector pin-out on OUTCboard
Connectorposition
Color ofwires
Quadnumber
1 None None Braid Earthing clamp
2 White 1 GND of first Alarm (customer alarm number 10)
3 Grey 1 Active pin of first Alarm (customer alarm number 10)
4 Blue 1 GND of second Alarm (customer alarm number 13)
5 Purple 1 Active pin of second Alarm (customer alarm number 13)
6 Yellow 2 GND of third Alarm (number 14)
7 Grey 2 Active pin of third Alarm (customer alarm number 14)
8 None None GND Braid earthing clamp
74 / 88 3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10
9 Options
9.2 Synchronization Cables InstallationMaterials
Description Reference Kit
Clock synchronization cable (OCC33) 3BK 08304 AA -
Clock synchronization cable (OCC23) 3BK 08303 AA -
Tie wrap 1 AD 00414 0006 Basic kit
Labels 3BK 08062 ACAA Basic kit
XCLK
View of connection on OUTC board View of synchronization cables path
3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10 75 / 88
9 Options
9.2.1 UMTS Configurations
10 m max
MBS
XCLK 1 out
Master SlaveMBS
XCLK 1 in
SlaveMBS
XCLK 1 in
XCLK 2 in /out
10 m max
Case of star configuration
MBS
XCLK 2 in /out
Master SlaveMBS
XCLK 1 in
XCLK 1 out
XCLK 1 in
MBS Slave
10 m max 10 m max
Case of daisy chain configuration
76 / 88 3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10
9 Options
9.2.2 GSM Configurations
Case of synchronization with G2 BTS
Case of synchronization between G3 and G4 BTS (1 connector must bedisassembled and assembled on site to pass cable gland)
3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10 77 / 88
9 Options
9.2.3 Synchronization Cabling Procedure
Low power compartment 1m
1 - Install the cables in the correspondingcompartment of the cable way
2 - Attach cables with plastic tie-wraps
40 mm123
12345678901231234567890123
123123
111
11
Tie wrap
Tie wrap
11 cover
3 - Strip the cable at cable gland level 4 - Pass the cable in the cable gland and attachit to the rack
5 - Label the cable with supplied labels 6 - Connect the synchronization cables to theOUTC board
78 / 88 3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10
9 Options
9.3 Output 48 V DC Power Cables Installation
Before proceeding, check that the PDU 1 and PDU 2 breakers on theBOMU busbar are in the OFF position.
The cabinet can supply 2 branches providing -48V.The maximum power for each branch is 500W.If an External Battery cabinet is attached, only one branch with -48V can beinstalled.
1 0v black2 Not used3 −48v blue
Marked 0v
For M6
EXDC cable
Nr Qty Materials Reference Kit
1 1 EXDC EXT DC Cable 3BK 26076 ABAA
2 1 Sealing Ring 3BK 26077 AAAA
3 1 Label External DC 3BK 26078 AAAA
4 2 CAP 3BK 01699 ABAA
5 1 Capacitor 1AB 043210002
6 2 Nut, hex, hex-hd M5 x 4.7mm 1AD 001970032
7 4 Washer waved 5.3mm x 10mm x 500UM/M5 1AD 009030006
8 2 Washer INT-T 5.1mm x 9.2mm 600UM/M5 1AD 000890007
3BK 26075 ABAA
This procedure
describes the
installation for 1 branch
Procedure 1. Remove 1 PG 16 gland (or cap if equipped instead) from the top of the MBOSide Compartment (see Figure )
2. Put the labels for this branch of -48V DC
3. Insert the DC capacitor (5) instead, but take care to place the sealing ring (2)in the right place and in the good position
4. Apply the tightening nut from plinth side and tighten
5. Thread up insulating caps (4)
6. Run the cables through the rubber caps (4)
7. Tighten the 48 V lugs at the M6 bolt capacitors and put the rubber caps.
3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10 79 / 88
9 Options
8. Tighten the 0 V lugs (6, 7, 8) to the 0 V stud
9. Plug the wire connector into BOMU busbar in the Side Compartment,connector PDU1 / PDU2.
PG 16 glands position
−48V DC OUT
−48V DC EXT BATT
0V DC OUT
0V DC EXT BATT
DC−OUT to external cabinet equipment
Roof area
4
3
Cable EXDC (2x)to BOMU connector PDU1/PDU2
BTS area
6, 7, 8
2
5
Take care of right location
Spring washernot used
Capacitors on top of MBO (equipped with 1 branch DC output andExternal Battery)
Figure 10: Output 48 V DC Power Cables Connection
The external equipment to supply must be connected between the filter stud(-48V) and the ground stud (0).Do not switch ON the F-PDU breaker, it will be done during commissioning.
80 / 88 3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10
10 Finishing
10 Finishing
This chapter describes:
Removing the transportation eye bolts
Top roof closing
Labelling of the rack
Cleaning up the site
Closing the rack.
3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10 81 / 88
10 Finishing
10.1 Removing the Transportation Eye Bolts
In case of Evolium A9100 MBS Outdoor installation in aggressive saltyenvironment it is recommended to remove the eye bolts from threads on thetop and to store them inside the cabinet after installation. The threads can beprotected against sand and dirt pollution by means of a standard galvanizedM12 screw.
10.2 Top Roof Closing
In order to manipulate the roof refer also to labelling at front of roof. Forsafety conditions (windy), it is preferable to manipulate with two installers.
1 - Locate the two hinges at rear of roof 2 - Insert the hinges at the bolts of rack
3 - Holding the top cover under an angle ofabout 20 , pull it to front to engage the hingesat the end of there cut-out
4 - Put the cover down
82 / 88 3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10
10 Finishing
H13
5 - Screw the roof in front 6 - Be sure that rear hinges are properlyinserted before leaving
10.3 Finishing
Torxhead
2
2
1 - Engage the two lateral side panels in thebolts
2 - Screw the lateral sides panels to the rack
STATION 4
STATION 4
3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10 83 / 88
10 Finishing
3 - Clean the site (do not put packages into thecustomer bin)
4 - Stick the “STATION” and “N ” suppliedlabels at internal head of rack
5 - Close the doors and give the key to the siteresponsible
6 - Phone to the OMC responsible to ensurethat no site alarms are activated
84 / 88 3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10
Appendix A : Kits / Supplies / Documents / Tools
Appendix A: Kits / Supplies / Documents / ToolsInstallation kits The following table is used to check, on site, the mandatory or optional delivery
item kits.
The used symbols are:
◊ = mandatory kit
# = technical choice kit
∇ = customer option kit.
Kits Mnemo Reference Qty
◊ Basic kit BKG3O 3BK 08107 xx 1
O Basic installation kit for Optical Fibre cable OFC3SEC 3BK 27700 AA 1
O Integrated Optical Fiber Distribution 1AB 34975 0001 1
◊ Antenna jumper cable (4m) BLF4 3BK 05360 EAAA 2/s
# 120–ohm PCM cable (8 pairs L907/8) CA120S8 3BK 08965 xx reel
# 75–ohm PCM Cable (8 coax FLEX3/8) CACOAX8 3BK 25241 xx reel
O Outdoor 6 optical fibers cable 3BK 27554 Ax
O Patch cord Lg 2m connectors LC 1AC 03809 0003 2
O Mechanical splice 1AB 34352 0001 6/SFPmodule
◊ GND Yellow/Green cable 1 x 50 mm2 PC50YG1D 3BK 08961 xx reel
# AC 230 volts power cable 3 x 2.5 mm2 PC03G25 3BK 25561 xx reel
# AC 230 Volts power cable 5 x 6 mm2 PC05B5 3BK 08944 xx reel
# DC -48V power cable 1x25 mm2 blue PC25BL1D 3BK 25995 xx reel
# DC 0V power cable 1x25 mm2 blue PC25B1D 3BK 08963 xx reel
∇ Clock Synchronization cable (10 m) OCC33 3BK 08304 AA 1
∇ Clock Synchronization cable (10 m) OCC23 3BK 08303 AA 2
∇ Alarm cable 8 pairs (L907/8) CA120S8 3BK 08965 xx reel
∇ Mechanical part for 24 terminal blocks MP24 1AD 02843 0001 1
∇ Labels for 24 terminal blocks LAB 1AD 02853 0001 1
∇ CAD Terminal block JS10 1AD 06634 0011 4
∇ DDF wall fixing kit FKW 1AD 02844 0001 1
3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10 85 / 88
Appendix A : Kits / Supplies / Documents / Tools
Kits Mnemo Reference Qty
# 120–ohm jumper for DDF (1 pair L904/1) CA120S 3BK 08941 xx 4m
# 75–ohm jumper for DDF (1 coax FLEX3) CACOAX1 3BK 08939 xx 4m
∇ Clearance tool part 1 (long extension + socket) DISMP 3BK 08898 AA 1
◊ Shims for levelling (1 Set for 5 racks) None 3BK 26159 AA x
86 / 88 3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10
Appendix A : Kits / Supplies / Documents / Tools
Consumable Supplies Installer or subcontractor must supply:
a set of sleeves to fit at each end of cables (PCM, Alarm, Power, ...)
a set of screws, nuts and washers to connect power cables to Site Power
Box and to Earth Plate
a set of terminal lugs for power cables.
List of Documents You need the following documents to complete this scenario:
Applicable Notification List (3DF 00462 0004 AAAGA)
Applicable Operation Instructions for GSM (3DF 00300 0004 UAZZA)
Catalogue of Instruction Operation - UMTS (3DF 00305 0000 AAAGA)
General Wiring Handbook for UMTS (3BK 17417 8099 RJZZA /
Z2EV00006-0012)
Tools Catalogue for field activity for GSM (3BK 20458 0001 RJZZA)
Tools Catalogue for field activity for UMTS (3BK 17428 0007 RJZZA /
Z2EV00006-0037)
Site Premise Inspection Form (8BL 00704 0015 DRBRA)
Completion Check List for UMTS (3BK 17428 0006 QZZZA /
Z2EV00006-0036)
Completion Check List for GSM (3BK 17200 0002 QZZZA)
SPP 50 Specification for Site Preparation (8BL 00704 0067 DRZZA)
EVOLIUM A9100 MBS Hardware Description (3BK 21013 AAAA TQZZA /
Z3EV00006-0028)
Part 17 Volume 17 CCD (3DF 00424 0021 ADBRQ)
Installation Method of DDF for RNS Equipment (3DF 00435 0033 RJZZA).
Bending Tool User Guide IO95 (3DF 00300 0095 UAZZA).
Patching and Splicing Optical Module (ABS 1014).
Installation Tools The following table is used to check, at base, the availability of the requiredtools.
refer to Tools Catalogue for content checking.
Name Reference Calibration
Basic set of tools OUT 001 No
Tightening tool for antenna jumpers 3BK 25050 AA OUT 003 No
3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10 87 / 88
Appendix A : Kits / Supplies / Documents / Tools
Name Reference Calibration
Node B Outdoor specific tools:
Craning bar 3BK 08804 AA
Long tool key 3BK 08897 AA
Short part key 3BK 08899 AA
Tent 3BK 08899 AA.
OUT 007 No
Specific bending tool for 1AB 18821 000x antennajumper
no no
88 / 88 3BK 17417 3046 RJZZA Ed.10Z2EV00006-0076 Ed.10