evm formula1
DESCRIPTION
EVM Formula1TRANSCRIPT
![Page 1: EVM Formula1](https://reader035.vdocuments.us/reader035/viewer/2022072011/55cf987f550346d033980261/html5/thumbnails/1.jpg)
EVMS
15
Five Basic Elements
BCWS Budgeted Cost for Work Scheduled“Planned Value”
BCWP Budgeted Cost for Work Performed “Earned Value”
ACWP Actual Cost of Work Performed “Actual Cost”
BAC Budget at Completion
EAC Estimate at Completion
![Page 2: EVM Formula1](https://reader035.vdocuments.us/reader035/viewer/2022072011/55cf987f550346d033980261/html5/thumbnails/2.jpg)
EVMS
25
Schedule Variance
BC WSBC WP
of the work I scheduled to have done,how much did I budget for it to cost?
of the work I actually performed,how much did I budget for it to cost?
SCHEDULE VARIANCE is the difference between work scheduled and work performed (expressed in terms of budget dollars)
formula: SV $ = BCWP - BCWS
example: SV = BCWP - BCWS = $1,000 - $2,000 SV= -$1,000 (negative = behind schedule)
SCHEDULE VARIANCE is the difference between work scheduled and work performed (expressed in terms of budget dollars)
formula: SV $ = BCWP - BCWS
example: SV = BCWP - BCWS = $1,000 - $2,000 SV= -$1,000 (negative = behind schedule)
BU
DG
ET B
ASE
D
![Page 3: EVM Formula1](https://reader035.vdocuments.us/reader035/viewer/2022072011/55cf987f550346d033980261/html5/thumbnails/3.jpg)
EVMS
28
Cost Variance
BC WPAC WP
of the work I actually performed,how much did I budget for it to cost?
of the work I actually performed,how much did it actually cost?
COST VARIANCE is the difference between budgeted costand actual cost
formula: CV $ = BCWP - ACWP
example: CV = BCWP - ACWP = $1,000 - $2,400 CV= -$1,400 (negative = cost overrun)
COST VARIANCE is the difference between budgeted costand actual cost
formula: CV $ = BCWP - ACWP
example: CV = BCWP - ACWP = $1,000 - $2,400 CV= -$1,400 (negative = cost overrun)
PER
FOR
MA
NC
E B
ASE
D
![Page 4: EVM Formula1](https://reader035.vdocuments.us/reader035/viewer/2022072011/55cf987f550346d033980261/html5/thumbnails/4.jpg)
EVMS
32
Variance at Completion (VAC)
B AC what the total job was budgeted for
E AC what the total job is projected to cost
VARIANCE AT COMPLETION is the difference between what the total job is supposed to cost and what the total job is now expected to cost.
FORMULA: VAC = BAC - EAC
Example: VAC = $5,000 - $7,500VAC = - $2,500 (negative = overrun)
VARIANCE AT COMPLETION is the difference between what the total job is supposed to cost and what the total job is now expected to cost.
FORMULA: VAC = BAC - EAC
Example: VAC = $5,000 - $7,500VAC = - $2,500 (negative = overrun)
![Page 5: EVM Formula1](https://reader035.vdocuments.us/reader035/viewer/2022072011/55cf987f550346d033980261/html5/thumbnails/5.jpg)
EVMS
34
EVM Variances
Positive Negative
SV Ahead of Schedule Behind Schedule
CV Under running costs Over running costs
VAC Projected underrun Projected overrun