evm formula1

5
EVMS 15 Five Basic Elements BCWS Budgeted Cost for Work Scheduled “Planned Value” BCWP Budgeted Cost for Work Performed “Earned Value” ACWP Actual Cost of Work Performed “Actual Cost” BAC Budget at Completion EAC Estimate at Completion

Upload: ashish-dahake

Post on 29-Dec-2015

2 views

Category:

Documents


0 download

DESCRIPTION

EVM Formula1

TRANSCRIPT

Page 1: EVM Formula1

EVMS

15

Five Basic Elements

BCWS Budgeted Cost for Work Scheduled“Planned Value”

BCWP Budgeted Cost for Work Performed “Earned Value”

ACWP Actual Cost of Work Performed “Actual Cost”

BAC Budget at Completion

EAC Estimate at Completion

Page 2: EVM Formula1

EVMS

25

Schedule Variance

BC WSBC WP

of the work I scheduled to have done,how much did I budget for it to cost?

of the work I actually performed,how much did I budget for it to cost?

SCHEDULE VARIANCE is the difference between work scheduled and work performed (expressed in terms of budget dollars)

formula: SV $ = BCWP - BCWS

example: SV = BCWP - BCWS = $1,000 - $2,000 SV= -$1,000 (negative = behind schedule)

SCHEDULE VARIANCE is the difference between work scheduled and work performed (expressed in terms of budget dollars)

formula: SV $ = BCWP - BCWS

example: SV = BCWP - BCWS = $1,000 - $2,000 SV= -$1,000 (negative = behind schedule)

BU

DG

ET B

ASE

D

Page 3: EVM Formula1

EVMS

28

Cost Variance

BC WPAC WP

of the work I actually performed,how much did I budget for it to cost?

of the work I actually performed,how much did it actually cost?

COST VARIANCE is the difference between budgeted costand actual cost

formula: CV $ = BCWP - ACWP

example: CV = BCWP - ACWP = $1,000 - $2,400 CV= -$1,400 (negative = cost overrun)

COST VARIANCE is the difference between budgeted costand actual cost

formula: CV $ = BCWP - ACWP

example: CV = BCWP - ACWP = $1,000 - $2,400 CV= -$1,400 (negative = cost overrun)

PER

FOR

MA

NC

E B

ASE

D

Page 4: EVM Formula1

EVMS

32

Variance at Completion (VAC)

B AC what the total job was budgeted for

E AC what the total job is projected to cost

VARIANCE AT COMPLETION is the difference between what the total job is supposed to cost and what the total job is now expected to cost.

FORMULA: VAC = BAC - EAC

Example: VAC = $5,000 - $7,500VAC = - $2,500 (negative = overrun)

VARIANCE AT COMPLETION is the difference between what the total job is supposed to cost and what the total job is now expected to cost.

FORMULA: VAC = BAC - EAC

Example: VAC = $5,000 - $7,500VAC = - $2,500 (negative = overrun)

Page 5: EVM Formula1

EVMS

34

EVM Variances

Positive Negative

SV Ahead of Schedule Behind Schedule

CV Under running costs Over running costs

VAC Projected underrun Projected overrun