evaluation of standby power system architectures

26
Evaluation of Large Standby Power System Architectures As facility power needs get very large, what’s the best design for optimum reliability?

Upload: michaeljmack

Post on 21-Jan-2017

552 views

Category:

Engineering


2 download

TRANSCRIPT

Page 1: Evaluation of standby power system architectures

Evaluation of Large Standby Power System ArchitecturesAs facility power needs get very large, what’s the best design for optimum reliability?

Page 2: Evaluation of standby power system architectures

2

Agenda

� Current Trends on Data Centers Design

� Reliability Indicators

� Overview of System Designs

� Lessons Learned

� Conclusions and Take-aways

Page 3: Evaluation of standby power system architectures

3

Data Center Power System Designs

� Huge variety of designs– Simple Systems - Single genset and transfer switches

• Bypass/Isolation and closed transition options

– Paralleling with ATS

– Paralleling with Power Transfer, Bus Ties

– Other variations (Swing generators)

� Systems becoming very large (>100MW in many sites)– 1GW in the future?

� High speed diesel gensets still most common choice: lowest cost/kW, fast starting, local fuel supply, stable, easy to service

� Tendency for Redundant and Modular Systems

Page 4: Evaluation of standby power system architectures

4

Big is not necessarily complex…

� Long Island Power Demand Response Site– 48MW, each machine individually paralleled to grid, controlled by SCADA software– Emissions compliant– No switchgear or additional controls required

Page 5: Evaluation of standby power system architectures

5

Reliability Indicators� MTBF goes up with hours of successful operation of a specific design

– New designs are hard to evaluate• New logic reliability• Hidden Flaws• Failure Mode Effects

– Common Assumptions: Avoid Single Points of Failure• But are all failure points equal?• Generator single points of failure; Redundancy

– Prototype Testing Impact (ref: NFPA110)– Number of systems in service

� Impact of Number of Components on overall reliability� PowerCommand Genset Control Example

– 150K MTBF at launch in 1994• Thousands of hours of development• Thousands of hours of testing• Hundreds of hours at seed sites

– After 15 years of service: >1 M MTBF

� Easier to be confident in a design that is proven over time

Page 6: Evaluation of standby power system architectures

6

A GOOD QUESTION

� OK, it’s easy to see that reliability is positively impacted by consistent quality control on a lot of widgits,

� but how do we deal with large, complex “one of a kind” systems?

Page 7: Evaluation of standby power system architectures

7

Simplest Designs� Genset with one or more ATS

– Best for smaller projects– Can be multiplied for larger projects

� Genset operating power transfer breaker pair– Best for larger generators, switching

near service– Lowest cost, smallest footprint– Can synchronize and ramp loads

between live sources– Breakers can trip, so need to deal

with that logically– Can be multiplied for any size

project� When used in multiples, each

genset/transfer equipment has single points of failure, but only part of system fails

��� ���

�������

������ �����

Page 8: Evaluation of standby power system architectures

8

�����

��

���

��

��������������

����

��������

���������

�������

Paralleling Applications

� Paralleling functions are the same on every project� Generator set paralleling functions commonly integrated

– No/very limited switchgear space for separate control equipment– Dedicated purpose controllers with firmware rather than PLC-based or

component functions

Page 9: Evaluation of standby power system architectures

9

Parallel Applications� Paralleling Systems Utilize Major

Control Blocks with Common Functions– Parallel Controllers (PLL)

• Start/Stop/Protect Genset• Black Start Control• Synchronize• Load Share • Bus Protection

– Transfer Controllers (ATS)• Source Availability• Transfer Logic

– System Control• System monitoring• Load Management (load add/shed)• Capacity Management (load demand)

� Distributed Logic Strategy� Design Control

– “One Throat to Choke”

Page 10: Evaluation of standby power system architectures

10

Isolated Bus Master Control Functions

� Load Management (load add & shed sequence)– Back-up for overide of automatic sequence– Controls feeder breakers, ATS, or interface to BMS

� System Capacity (load demand)– Provides means of minimizing fuel consumption in long runs

� Local Operator Interface– What do you want the operator to do? Where?

� Remote Monitor & Control

Digital Control

Page 11: Evaluation of standby power system architectures

11

Remote Monitoring & Control

������� ��

��������

�����

���

��������

�������

� ������

� ����������

� ���!�"#�$��

�����$�� ���

���

�����

���������

�%���

&�$'��()

����*��

�������

��

�������

��

��������

�����

���

��������

�������

� ������

� ����������

� ���!�"#�$��

�����$�� ���

���

�����

���������

�%���

&�$'��()

����*��

�%���

� Multiple Networks/Multiple Uses– Isolated for speed, ease of installation

� Remote Monitoring is Very Common– Tons of data and control is available

Page 12: Evaluation of standby power system architectures

12

More Complex Designs

� “Main-tie-Main” Configuration

� Service issues due to gensets on common bus with utility

� Logic Variations due to automated tie can be problematic

Page 13: Evaluation of standby power system architectures

13

More Complex Designs

�� �

��� ��� ��� ���

�%���

������

� � �

� A combination of core paralleling and power transfer control blocks

� May have many generators and many transfer pairs� Common to have multiple feeds to downstream devices� Usually includes a central monitoring system for entire

package

Page 14: Evaluation of standby power system architectures

14

Impact of Automated Ties� Automating Tie

operation complicates design

� Best accomplished with core controls, orchestrated with PLC

� Best practice is to exercise design control on PLC logic “modules”

Page 15: Evaluation of standby power system architectures

15

More Examples� Most designs use many core functions

PARALLELING

POWER TRANSFER

SUPERVISORY

Page 16: Evaluation of standby power system architectures

16

Tier 3 Data Center Design

� More duplicated functions…

PARALLELING

PWR TRANS

Page 17: Evaluation of standby power system architectures

17

Lessons Learned:Effective Use of Redundancy

� Single points of failure have a big impact on reliability

� Address by:– Design it out

– True Redundancy

– Live with it/Best Quality

� Genset Example

� MasterControl Example

Page 18: Evaluation of standby power system architectures

18

Lessons Learned:Support for Complex Systems

� Look for ability to have support local to the project site– Local support should be equipped with software necessary for

PLC and HMI (if different)

– Training is critical

� Consider ability to support the PLC and HMI and other controls’ software in the future– 30-year life is not unexpected at many sites

– Vendors’ commitment to backward compatibility• This capability varies with vendor

– Number of software sets needed for total service is a major concern over time

Page 19: Evaluation of standby power system architectures

19

Lessons Learned:Hot Standby (Vendor 1) + Hot Standby (Vendor 2)

� What does “Redundant PLC” mean?– Redundant Processor? Redundant I/O? Redundant Power

Supply? Redundant Power Supply Bus? Redundant ComsLinks?

� Hot Standby practices can significantly impact PLC operation time (responsiveness)– Impact on display responsiveness

– Operation time for critical functions

� Capabilities of each PLC/Touchscreen differ by vendor– Every system supplier standardizes on specific vendors, and has

limited flexibility to use others

Page 20: Evaluation of standby power system architectures

20

Lessons Learned:On-going Operator Instruction & Training

� Posted Manual Operation Instructions– Consider all critical operations,

• power transfer from utility to gensets and return• gensets on and off bus (if paralleled)• manual load add and shed

� Pay Attention to Operator Panel Information– What are operator capabilities? – What do you want them to do?– Where do you want them to do it?

Page 21: Evaluation of standby power system architectures

21

Conclusions

� There’s a lot of wisdom in the first rule of engineering: KISS

� BUT, we are dealing with complicated facilities and demanding performance requirements

� Use Distributed Logic Strategy

� Make sure of support plan in the long run

� Keep learning from experience

Page 22: Evaluation of standby power system architectures

22

Utility Paralleling

�����

��

���

��

��

��

���

�����

����������������

�����

���������

����

��� ������

� Connected to Utility� kW/kVar level

Page 23: Evaluation of standby power system architectures

23

Product Configurations

Cummins Caterpillar/Asco4000 Generac

� This slide shows the genset and paralleling control functions for different suppliers

� Cat/Asco/Generac all have 6-8 level load add/shed and load demand in their arrangement

– Most global control competitors use the Cat/Asco model, except SDMO

Page 24: Evaluation of standby power system architectures

24

Cummins Paralleling Topology

� Typical Isolated Bus architecture

�����

�����

Page 25: Evaluation of standby power system architectures

25

Typical Isolated Bus ArchitectureCaterpillar shown, Asco, many others similar

Others…

Page 26: Evaluation of standby power system architectures

26

CPG Interconnect Block Diagram

AC for accessories

Status to Master

Breaker Commands

Breaker Status

Power Conductors