EU DataGrid Project TestBed Status and Plans. Bob Jones EU DataGrid Technical Coordinator CERN. Project Schedule. EU contract signed on December 29th, 2000 TestBed 0 (early 2001) International test bed 0 infrastructure deployed Globus 1 only - no EDG middleware TestBed 1 ( now ) - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: EU DataGrid Project TestBed  Status and Plans

1

CERNEU DataGrid Project TestBed StatusEU DataGrid Project TestBed Statusand Plansand Plans

Bob Jones

EU DataGrid Technical Coordinator

CERN

Page 2: EU DataGrid Project TestBed  Status and Plans

EU DataGrid 2

CERN

Jan. 2002

Project ScheduleProject Schedule

EU contract signed on December 29th, 2000 TestBed 0 (early 2001)

International test bed 0 infrastructure deployedGlobus 1 only - no EDG middleware

TestBed 1 ( now )First release of EU DataGrid software based on Globus 2 to defined users

within the project:HEP experiments (WP 8)Biology applications (WP 9)Earth Observation (WP 10)

Project Review by EU (1st March 2002)External reviewers inspect deliverables & demo, partner’s contributions etc.

TestBed 2 (Sept-Oct. 2002)Builds on TestBed 1 to extend facilities of DataGrid

TestBed 3 (March 2003) & 4 (Sept 2003)

Page 3: EU DataGrid Project TestBed  Status and Plans

EU DataGrid 3

CERN

Jan. 2002

Page 4: EU DataGrid Project TestBed  Status and Plans

EU DataGrid 4

CERN

Jan. 2002

Grid aspects covered by EDG testbed 1Grid aspects covered by EDG testbed 1

VO servers LDAQ directory for mapping users (with certificates) to correct VO

Storage Element Grid-aware storage area, situated close to a CE

User Interface Submit & monitor jobs, retrieve output

Replica Manager Replicates data to one or more CEs

Job Submission Service Manages submission of jobs to Res. Broker

Replica Catalog Keeps track of multiple data files “replicated” on different CEs

Information index Provides info about grid resources via GIIS/GRIS hierarchy

Information & Monitoring

Provides info on resource utilization & performance

Resource Broker Uses Info Index to discover & select resources based on job requirements

Grid Fabric Mgmt Configure, installs & maintains grid sw packages and environ.

Logging and Bookkeeping

Collects resource usage & job status

Network performance, security and monitoring

Provides efficient network transport, security & bandwidth monitoring

Computing Element Gatekeeper to a grid computing resource

Testbed admin. Certificate auth.,user reg., usage policy etc.

Page 5: EU DataGrid Project TestBed  Status and Plans

EU DataGrid 5

CERN

Jan. 2002

TestBed 1 layout at CERNTestBed 1 layout at CERN

GateKeeperlxshare0220

Worker Nodelxshare0221

Storage Elementlxshare0219

GateKeeperlxshare0223

Worker Nodelxshare0224

Storage Elementlxshare0222

Info ServiceMDS/ftreelxshare0225

User Interfacetestbed006

Replica Catalogtestbed0226

Res. BrokerJob Sub Srvtestbed011

Logging &Bookkeepingtestbed012 LSF (initially fork)

PBS

LDAP serversFor VOsNIKHEF

Page 6: EU DataGrid Project TestBed  Status and Plans

EU DataGrid 7

CERN

Jan. 2002

Physicists from LHC experiments submitting jobs with their application software that uses: User interface (job submission language etc.) Resource Broker & Job submission service Information Service & Monitoring Data Replication

Testbed usage to dateTestbed usage to date

Add lfn/pfnto

Rep Catalog

GenerateRaw events

on local diskRaw/dst ?

Job argumentsData Type : raw/dstRun Number :xxxxxxNumber of evts :yyyyyyNumber of wds/evt:zzzzzzRep Catalog flag : 0/1Mass Storage flag : 0/1

Write logbookOn client node

raw_xxxxxx_dat.log

dst_xxxxxx_dat.log

Read raw eventsWrite dst events

Get pfnfrom

Rep Catalog

Add lfn/pfnto

Rep Catalog

MS

MS

Move toSE, MS ?

Write logbookOn client node

pfn local ? ny

raw_xxxxxx_dat.log

Copy raw data From SE toLocal disk

Generic HEP application flowchart

SEMove to SE, MS?

SE

[reale@testbed006 JDL]$ dg-job-submit gridpawCNAF.jdlConnecting to host testbed011.cern.ch, port 7771Transferring InputSandbox files...doneLogging to host testbed011.cern.ch, port 15830=========dg-job-submit Success ============ The job has been successfully submitted to the Resource Broker. Use dg-job-status command to check job current status. Your job identifier (dg_jobId) is:

https://testbed011.cern.ch:7846/137.138.181.253/185337169921026?testbed011.cern.ch:7771========================================

[reale@testbed006 JDL]$ dg-job-get-output https://testbed011.cern.ch:7846/137.138.181.253/185337169921026?testbed011.cern.ch:7771

Retrieving OutputSandbox files...done

============ dg-get-job-output Success ============

Output sandbox files for the job:

- https://testbed011.cern.ch:7846/137.138.181.253/185337169921026?testbed011.cern.ch:7771

have been successfully retrieved and stored in the directory:

/sandbox/185337169921026

First simulated ALICE event generated by using the DataGrid Job Submission Service

Page 7: EU DataGrid Project TestBed  Status and Plans

EU DataGrid 8

CERN

Jan. 2002

Groups Involved in Testbed 1Groups Involved in Testbed 1

WP8

WP8

WP9

WP9

WP10

PierGiorgio Cerello

Eric Van Herwijnen

Julian Lindford

Andrea Parrini

Yannick Legre

WP6

WP6

WP6

WP6

WP6

WP6

WP6

WP6

WP6

WP6

WP6

Brian Coghlan

Flavia Donno

Eric Fede

Fabio Hernandez

Nadia Lajili

Charles Loomis

Pietro Paolo Martucci

Andrew McNab

Sophie Nicoud

Yannik Patois

Anders Waananen

WP1

WP2

WP3

WP4

WP5

WP7

Elisabetta Ronchieri

Shahzad Muzaffar

Alex Martin

Maite Barroso Lopez

Jean Philippe Baud

Frank Bonnassieux

Integration Team VO Admin ALICE:Daniele MuraATLAS:Alessandro de SalvoCMS: Andrea SciabaLHCb: Joel ClosierEO:Yannick LegreBio-Info:John van de Vegte

ALICE: Ingo Augstin & Steve BurkeATLAS: Mario Reale & Alessia TricomiCMS & WP10: JJ BlaisingLHCb: Jeff Templon

Piergiorgio Cerello

Yves Schutz

Roberto Barbera

Predrag Buncic

Federico.Carminati

Marisa Luvisetto

Daniele Mura

Fons Rademakers

Mario Sitta

Claude CharlotDave Newbold Andrea Sciaba Claudio Grandi Igor Semeniouk Paolo Capiluppi Olga Kodolova N.Kruglov A.Kryukov L.Shamardin V.Kolosov E.Tikhonenko V.Mitsyn Marco Verlato Massimo Sgaravatto A. Edunov B.Berdnikov

Eric van HerwijnenJ ClosierG PatrickD GalliV VagnoniS KlousH van BultenG D PatelN BrookA KhanF HarrisD McPherson

Silvia Resconi Craig Tull Oxana Smirnova Stan Thompson Fairouz Ohlsson-Malek

Users

Site Admin CERN:Markus SchulzLyon:Fabio Hernandez  CNAF: A.Chierici et al.NIKHEF: Jeff Templon & David GroepRAL:B.Saunders

Page 8: EU DataGrid Project TestBed  Status and Plans

EU DataGrid 11

CERN

Jan. 2002

Security CertificatesSecurity Certificates

The project software supports 12 Certification Authorities from the various partners involved in the project

http://marianne.in2p3.fr/datagrid/ca/ca-table-ca.html

For a machine to participate as a Testbed 1 resource all the CAs must be enabled.

all CA certificates can be installed without compromising local site security

Each host running a Grid service needs to be able to authenticate users and other hosts

site manager has full control over security for local nodes

Virtual Organisation represents a community of users

6 VOs: 4 HEP (ALICE, ATLAS, CMS, LHCb), 1 EO, 1 Biology

Usage guidelines

Account Registration

Page 9: EU DataGrid Project TestBed  Status and Plans

EU DataGrid 12

CERN

Jan. 2002

EDG testbed 1 RPMS

LCFG ext pkg ext srvc globus

edg confg security middleware apps

ldxprofldxprof

GenericComponent

GenericComponent

rdxprofrdxprof

LCFG ComponentsDBM File

LCFG configuration files

mkxprof Web Server

XML Profile(one per client node)Server node

HTTP

Client nodes

Node configuration and installation toolsNode configuration and installation toolsNode configuration toolsNode configuration tools

For reference platform (Linux RedHat 6.2)

Initial installation tool using system image cloning

LCFG (Edinburgh University) for software updates and maintenance

Total of ~750 RPMsWith a 10Mbit/sec link need

just 10 mins to install anode

Page 10: EU DataGrid Project TestBed  Status and Plans

EU DataGrid 13

CERN

Jan. 2002

Lessons learnt from testbed 1Lessons learnt from testbed 1

The raw ingredients exist – we just need to be sure of the recipeSufficient expertise exists in the different institutes to cover all aspects of the project

Expertise and enthusiasm needs to be channeled using agreed framework

CERN central role underestimated and under resourced Integration and deployment is a labour intensive task

More planning & WP6 (sw integration) needs reinforcement (especially at CERN)

Better done in small steps using iterative releases

Support by and relationship with Globus developers is very important International Aspects

Already an international testbed, need to agree plans with US similar activities

Underestimated the administrative effort involved in running an international testbed Need more emphasis on testing

More unit & integration testing

Middleware WPs need to develop a test-plan (also WP6 for external packages & integration tests) and involved applications from early stage

Page 11: EU DataGrid Project TestBed  Status and Plans

EU DataGrid 14

CERN

Jan. 2002

Iterative ReleasesIterative Releases

Planned intermediate release schedule

TestBed 1: October 2001

Release 1.1: January 2002

Release 1.2: March 2002

Release 1.3: May 2002

Release 1.4: July 2002

TestBed 2: September 2002 Each release includes

feedback from use of previous release by application groups

agreed high-priority improvements/extensions

use of software infrastructure

feeds into architecture group Similar schedule will be organised for 2003

Page 12: EU DataGrid Project TestBed  Status and Plans

EU DataGrid 15

CERN

Jan. 2002

Software Release ProcedureSoftware Release Procedure

Coordination meetingGather feedback on previous releaseReview plan for next release

WP meetingTake basic plan and clarify effort/people/dependencies

Sw developmentPerformed by WPs in dispersed institutes and run unit tests

Software integrationPerformed by WP6 on frozen swIntegration tests run

Acceptance testsPerformed by Loose Cannons et al.

Roll-outPresent sw to application groupsDeploy on testbed

Coord. meeting

ReleasePlan++

Release feedback ReleasePlan

WP meetings

WP1 WP3 WP7

Component 1 Component n

Globus

EDG release

Distributed EDG release

Roll-out. meeting

testbed 1:Dec 11 2001

~100 participants

Page 13: EU DataGrid Project TestBed  Status and Plans

EU DataGrid 16

CERN

Jan. 2002

Development & Production testbedsDevelopment & Production testbeds

DevelopmentInitial set of 5 sites will keep small cluster of PCs for development purposes to

test new versions of the software, configurations etc. Production

More stable environment for use by application groupsmore sitesmore nodes per site (grow to meaningful size at major

centres)more users per VO

Usage already foreseen in Data Challenge schedules for LHC experimentsharmonize release schedules

Participating in InterGrid discussions on testbed organisationAntonia Ghiselli, Bob Jones, Francesco Prelz

Analysis of interface with US testbeds to be performed by end of April (GriPhyN/PPDG meeting)

Page 14: EU DataGrid Project TestBed  Status and Plans

EU DataGrid 17

CERN

Jan. 2002

Page 15: EU DataGrid Project TestBed  Status and Plans

EU DataGrid 18

CERN

Jan. 2002

Future PlansFuture Plans

Prepare for first project EU review 1st March 2002 (“managed panic”)

Expand testbed

More nodes per site, more sites (including US), more users

Evolve architecture and software on the basis of TestBed usage and feedback from users

Closer integration of the software components

Improve software infrastructure toolset and test suites

Look for convergence with PPDG/GriPhyN architecture

Enhance synergy with US via DataTAG-iVDGL and InterGrid

Address shortcomings in plan by collaborating with other EU projects (DataTAG, GridSTART, CrossGrid)

Promote early standards adoption with participation to GGF WGs

Final software release by end of 2003