ethical disasters group 8 by dominique amos, josh seuss, alex finkelstein, mike hite, kevin hao
TRANSCRIPT
Ethical DisastersGroup 8
By Dominique Amos, Josh Seuss, Alex Finkelstein, Mike Hite, Kevin Hao
Ford Pinto
Designed and produced in the late 60s Went on sale September 11, 1970 Introduced after only 22 months of concept to
production Was conceived not to weigh an ounce over 2000 lbs
and not cost anything over $2000 Curb weight 2015-2270 lbs
The Flaw
Fuel tank placed on the underside of the car right behind the exposed bolts of the rear axle
The fuel tank would rupture in read end crash speeds of at least 25mph
Exposed bolts only cause further damage to the tank when it become pushed forward in crashes
The now leaking fuel now needed only a spark from the scraping metal of the crash to ignite
The Fatal Combination
Crashes at speeds of at least 40 mph would crumple the car in such a way that the doors would jam and be unable to open
This scenario along with the ignited fuel from meant that people would become trapped and burn to death within the vehicle
Fuel tank problem was discovered in early testing
Possible Preventions
Using the better designed tank of the Ford Capri
Not used because Lee Iacocca wanted the Pinto in showrooms by 1971
This cut down on production planning by over 18 months
This particular problem was never brought to Iacocca’s attention because any previous problems brought to him were quickly brushed aside
Another fix was a plastic shield between the tank and exposed bolts and a better designed fuel filler neck that reduced rupture rates
Ethical Violations
This negligence is a direct violation of the 1st rule of ethics in the IEEE in which engineers should accept responsibility in making decisions consistent with the safety health and welfare of the public and to disclose factors that might endanger the public or environment.
Ford decided against a last minute redesign based on a cost-benefit model
Calculated that selling as is and paying for customer damages would amount to ~$45 million
Calculated that a redesign would cost ~169 million Ford decided on the former and was hit with
lawsuits in the late 70s
Consequences
In one lawsuit in 1978 a California jury awarded $128 million in a lawsuit stemming from an auto accident
More lawsuits came after In 1978 Ford recalled 1.5 million Pintos Ford was this first company indicted in a reckless
homicide trial and acquitted Ford ceased production on the Pinto in 1980 after
the car’s reputation was destroyed
Three Mile Island
Combination of human, mechanical, and electrical failure Misconnected water hose due to poorly labelled fittings Failsafe was devised years earlier but never fully
implemented Design flaw in unit 2
Steam entered at an angle that blew water into condenser vacuum
Cased condenser to shutdown
Misread valve readings
L’Ambiance Plaza Collapse
Bridgeport Connecticut April 23, 1987 Was to be a sixteen story building with 13 floors of
apartments and 3 levels for parking. Midway through construction the plaza collapsed 28 Construction workers were killed
The Flaws
Disregard for safety standards Design flaws resulting from subcontracting Lack of accountability
The Collapse
Inadequate Design, improper building regulations, poor quality assurance Improper slab and shear design Inadequate concrete section No temporary bracing – stability problems Use of broken rock fill under footings Defective welding
Prevention
Design by single contractor
Accountability checks
Ethical Violations
IEEE and NSPE violations to public safety and high standards
ACM quality and effectiveness of work ACM professional review
Our Project – Malware Detection
Software Product No lives depend on it Ethical considerations are still important Price is not an ethical issue
Make sure the product is advertised so functionality is clear
Looking at meeting customer’s expectations through more than a business view
Our Project – Malware Detection
Make sure the product is advertised so that functionality is clear The System only detects malware; it does not
remove it. It is user initiated, so there is no continually
running process. The user must input what file/s they want scanned.
Our Project – Malware Detection
Meeting customer’s expectations through more than a business perspective Updating malware database
Newer malware will decrease the reliability of our system if it is not included in our database
To keep the product useful over the subscription period, new definitions are needed as new malware is discovered.
Customer could act against better judgement on our systems recommendation
Our Project – Malware Detection
Meeting customer’s expectations through more than a business perspectiveEnsure continued compatibility
Product works with Windows which has updates every day
Updates often cause issues with other softwareCustomer paid for a subscription to find that
the next update causes our system to no longer function