estimating ii
TRANSCRIPT
-
8/10/2019 Estimating II
1/34
COST MANAGEMENT 642
Paper 10
ESTIMATING II
GENERAL
-
8/10/2019 Estimating II
2/34
Paper 10 - ESTIMATING II
1.0. COST ESTIMATING - ACCURACY
2.0 COST ESTIMATING - ASPECTS
3.0. COST ESTIMATING - COST ESCALATION
4.0. COST ESTIMATING - CONTINGENCY
-
8/10/2019 Estimating II
3/34
COST ESTIMATING
QUESTIONS
1. What factors determine the accuracyof a cost
estimate?
2. What are the specific difficulties of estimating
the costs of projects?
-
8/10/2019 Estimating II
4/34
COST ESTIMATING -ACCURACY
estimating is not an exact science: it is much an art as a
science, and involves intuition and expertjudgement
cost estimates should be as accurate as possible.
Accuracy expressed as+/-% range around point estimate
Factors which determine the level of accuracy include:
project definition
quality of cost database
quality of estimator
estimating method
level of effort
project characteristics
-
8/10/2019 Estimating II
5/34
ACCURACY:PROJECT DEFINITION - PLC Link: growth of information during PLC & estimating accuracy
project definition increases, expected accuracy improves
Earlier in PLC, problems of estimate accuracy
Quality of info. increases through PLC, accuracy range narrows
CONCEPT PHASE
Estimates used for economic viability of project reasonably accurate estimates essential for go/no-go decision
but minimal information, so concerted effort required
Estimates - 'order-of-magnitude' based on parametric estimating
"early estimates have wide variability ... most often notoriously low.
DEVELOPMENT PHASE
Scope developed - allows more accurate estimates
As more inform, estimate continually updated & accuracy improved.
-
8/10/2019 Estimating II
6/34
ACCURACY:PROJECT DEFINITION - PLC
-
8/10/2019 Estimating II
7/34
ACCURACY:PROJECT DEFINITION - PLC
-
8/10/2019 Estimating II
8/34
ACCURACY: COST DATABASE
Accuracy dependent on quality of reference cost data
Accuracy better when verified data used rather than
assumptions
So comprehensive, relevant, up-to-date database of cost
information required for accurate cost estimating
-
8/10/2019 Estimating II
9/34
ACCURACY: QUALITY OF ESTIMATOR
1 major cause of poor estimation in that the people making
the estimates dont know what they are doing.
Greater accuracy if estimator is capable, unbiased,
experienced, knowledgeable, methodical,
Estimator should:
be able to forecast and interpret trends;
work intuitively where information is limited;
motivated & enthusiastic
most significant human factor is estimators knowledge ofgeneral price levels, acquired through experience
-
8/10/2019 Estimating II
10/34
ACCURACY: QUALITY OF ESTIMATOR
Desirable qualities in good estimator :
basic numerate education;
ability to communicate;
ability to understand & interpret project information;
patience;
curiosity;
confidence;
ability to question the basis of assumptions
-
8/10/2019 Estimating II
11/34
ACCURACY: Estimating Methods
several estimating methods - some inherently more
accurate
EG parametric typically less accurate than bottom-up
But, choice & accuracy of estimating method is
fundamentally affected by quality of information available.
-
8/10/2019 Estimating II
12/34
ACCURACY: Level of Effort
it costs money to estimate costs
Accuracy depends time & effort devoted to estimating greater accuracy, greater the cost of producing estimates
Beyond certain level of effort, only modest improvement in
accuracy
Research - significant obstacle to accurate estimates =
unwilling to invest resources to develop better estimating
practice Type of Estimate Accuracy (%) level of effort, % of project cost*
Proposal +/- 30 to +/- 50 0.02 - 0.1
Budget +/- 20 to +/- 35 0.1 - 0.3
Sanction +/- 10 to +/- 25 0.4 - 0.8
Control +/- 5 to +/- 15 1 - 3
Tender +/- 2 to +/- 5 5 - 10
-
8/10/2019 Estimating II
13/34
ACCURACY: Project Characteristics
Technical uniqueness & complexity of a project affects
estimate accuracy
first-of-a-kind project more difficult to estimate accuracy
compared to a project that repeats past practices.
-
8/10/2019 Estimating II
14/34
Accuracy - Classification Systems
Awareness of Accuracy
Important - those using estimates are aware of accuracy. Reasons:
Feasibility Studies
If known accuracy = +/-10%, sensitivity analysis can be
applied to feasibility study.
Management Attitude
Management appreciate why earlier estimate to be too low
-
8/10/2019 Estimating II
15/34
Accuracy - Classification Systems
Classification Systems
1 way to indicate accuracy - classification system. Benefits:
highlights missing information required for more accurate
estimate
good means of communicating estimate quality
Action by management which uses estimate done in full
understanding of its accuracy
management aware of degree of reliance that should be
placed on it when making decisions.
-
8/10/2019 Estimating II
16/34
Accuracy - Classification Systems
Concept Develop Design Execution
Unclassified Class B or AClass E
Class C
Class D
Class B
-
8/10/2019 Estimating II
17/34
-
8/10/2019 Estimating II
18/34
Project Cost Estimating - Problems
Project = uniqueness = lack of suitable precedents.
project changes due to scope changes & new knowledge
poorly defined scope = incorrect estimates. Often due to
time pressure
long projects - further project extends from original
estimating base, less accurate original estimates likely tobe
-
8/10/2019 Estimating II
19/34
Project Cost Estimating - Problems
Problems in estimating for software development :
Priority of Project Objectives- Historically, strong focus of
meeting deadlines & quality.
Task-Orientated Environment- emphasis on creativity and
technical excellence. Less effort on cost estimation
Lack of Managerial Expertise- favour young specialists asPMs, technically expert but perhaps poor PM & cost
estimators
Lack of Cost Data- SD firms do not keep comprehensive,accurate and detailed time sheets from previous projects
Technological Change.-past cost data, however good, is of
little use for preparing cost estimates of present SD
projects
-
8/10/2019 Estimating II
20/34
COST ESTIMATING
QUESTION
3. What would be the typical sectionsin a cost estimate
REPORT ?
C
-
8/10/2019 Estimating II
21/34
Cost Estimating - Documentation
estimate should always include written documentation on
how it was developed, and what is included and excluded
Written document should include
The Purpose of the Estimate
The Scope of the Estimate
Assumptions & Exclusions
Source of Cost Information
Escalation Allowances
Contingency Allowances
Significant Findings
COST ESTIMATING COST ESCALATION
-
8/10/2019 Estimating II
22/34
COST ESTIMATING - COST ESCALATION
Escalation = "provision in estimated costs for continuing
price level increase over time"
Oftenreceives less attention than other smaller items"
Escalation a result of two factors:
general inflation in costs, invariably upwards.
specific market factors.
COST ESTIMATING
-
8/10/2019 Estimating II
23/34
COST ESTIMATING
QUESTION
4. ost ontingency
i. Definecontingency
ii. What type of items is it meantto cater for?
iii. What type of items is it notmeant to cater for
iii. By what methodsmight it be calculated?
COST CONTINGENCY INTRODUCTION
-
8/10/2019 Estimating II
24/34
COST CONTINGENCY- INTRODUCTION
3 basic types of C - tolerance in specification, float in
schedule, money in budget.
C= mostmisunderstood, misinterpreted, misapplied word
in projects. C means different things to different people
C is highly subjective, inconsistently interpreted,
inadequately estimated
imperative to have a policy regarding C definition that is
understood and accepted by all project participants
COST CONTINGENCY DEFINITION
-
8/10/2019 Estimating II
25/34
COST CONTINGENCY- DEFINITION
"amount of money added to the estimate to allow for
changes that experience shows will likely be required"
allowances added to an estimate to represent the bestjudgement of undefined or uncertain items of work which it
is considered should be provided for. ... They are 'areas of
space' in an estimate which help a PM to meet the projectcost objectives, as they face exposure to project risk and
uncertainty"
ATTRIBUTES OF COST CONTINGENCY
-
8/10/2019 Estimating II
26/34
ATTRIBUTES OF COST CONTINGENCY It is a reserve of a sum of money.
It is part of the project cost estimating process
Its necessity & amount is linked to the existence of risk - caters for
events unknown, undefined, uncertain, or unforeseeable.
It is a risk management tool - reduces impact if risks eventuate
Inclusion means estimate represents total financial commitment:
estimatewithout contingency is simply not a complete estimate
increases probability that final cost will not exceed our estimate
Can have major impact on decision-making:
Client - if too high, encourages sloppy cost management or causeproject to be uneconomic & aborted; if too low, too rigid & set
unrealistic financial environment unsatisfactory outcomes.
Contractor, balance risk of overrunning costs against probability
of winning contract
C ti C
-
8/10/2019 Estimating II
27/34
Contingency - Coverage Incomplete Scope Definition
Allows for incomplete scope definition.
Order-of-magnitude & budget estimates developed early in PLC. With
more scope definition, estimate invariably increases.
C caters for increases in costs due to present incomplete definition
Inaccuracy of Estimating Methods & Data
no method or data is perfect, & historically result in low estimate
C added to the estimate to cover for these inadequacies.
But C should not be an excuse for poor estimating
C ti C
-
8/10/2019 Estimating II
28/34
Contingency - Coverage
Identified risks
C may be created for specifically identified risks. Eg contractor
tendering, allow C for:
scope error interpretations,
minor design changes,
inaccuracy in quantification,
abnormal construction problems,
liabilities in the contract,
unforeseen regulations,
safety requirements, equipment breakdowns,
weather interruptions,
labour productivity,
technological change
Contingency Coverage
-
8/10/2019 Estimating II
29/34
Contingency - Coverage Unknown Unknowns
C set up to allow for unidentified risks:
"It is important to identify contingency allowances associated
with all significant individual risks, plus a residual allowance for
other unidentified risks"
This excludes unforeseeable major events (see below).
Items not part of contingencies
C should cover for scope development but not scope changes. Other items not considered appropriate for inclusion in C:
escalation,
unforeseeable major events - extreme weather, earthquakes, riots,
acts of war, new government regulations, economic collapse
Contingency Calculation PERCENTAGE ADD ON
-
8/10/2019 Estimating II
30/34
Contingency - Calculation: PERCENTAGE ADD-ON C calculated as % on base estimate, based on from experience &
historical data. For example:
incomplete scope definition in early estimates, 30%- 50%; oncescope fully developed 3% to 5%"
inaccuracy of estimating method &/or data 5%-10%,
Level of contingencies will depend on:
organisation and the type of business
type of estimate. (eg. order-of-magnitude estimate demands a
high C to cover for the inherent inaccuracies of this method)
PLC phase (eg estimate at concept phase = high C to allow for
limited information used to prepare an estimate)
type of project. (eg new/unproven technology High C
type of work - eg underground work = uncertainty = High C
Variation to single % additional to base estimate - apply different %to each major component of the estimate.
Contingency Calculation Risk Analysis
-
8/10/2019 Estimating II
31/34
Contingency - Calculation Risk Analysis contingencies by % mark-up not recommended:
"all too often risk is either ignored or dealt with in an arbitrary
way: simply adding a 10% 'contingency' onto the estimated cost ofa project is typical. This is virtually certain to be inadequate and
cause expensive delay, litigation, and perhaps bankruptcy"
contingency should definitely be based on an experienced
review of uncertainties of estimate details. An arbitrary bottompercentage is not good enough.
Allocating % insufficient unless linked to a confidence level. i.e. level
of probability that final cost will be within estimate (including C).
Nowadays, more rigorous & defendable approaches for calculation
ofC , typically derived from probability analysis, eg Central Limit
Theorem and Monte Carlo simulation.
Contingency Management
-
8/10/2019 Estimating II
32/34
Contingency - Management Level of C constantly monitored & reassessed through PLC
Success of contingency management:
establish procedures for proper use of C
establish information system showing each responsible manager
& C under their control, C used, trends, when possible to transfer
balances to other less successful areas or general reserve
2 basic ways to manage C
Single account - single line item account. Disadvantages:
tendency to use C first-come, first-serve basis with potential
exhaustion well before project is over
control likely to be responsibility of PM - but other commitments
are intense and may lead to neglect of contingency management.
Individual Allocations - & responsibility assigned for their control. If
expenditure exceedsC, negative variance reported. Unexpended C
can be transferred to a general contingency account.
ALLOWANCES
-
8/10/2019 Estimating II
33/34
ALLOWANCES Contingency = unforeseeable and undefined items
Allowance - = for known and undefined items, foreseen to be spent
Redefined each time an estimate is revised
allowance should only be made if "there is a better than 50% chance
of it happening"
Allowance added to estimate, identified with documented basis
Allowances - Exclusions:
major scope changes
weather extremes, earthquakes
accidents acts of God
strikes
because "these items are unpredictable, both in terms of
probability magnitude of cost impact if they do occur".
Paper 10 ESTIMATING II
-
8/10/2019 Estimating II
34/34
Paper 10 - ESTIMATING II 1.0. COST ESTIMATING - ACCURACY
1.1. Factors affecting Accuracy
1.2. Accuracy - Classification Systems 2.0 COST ESTIMATING - ASPECTS
2.1. Cost Estimating - Problems
2.2. Cost Estimating - Do's and Don'ts
2.3. Cost Estimating - Documentation
3.0. COST ESTIMATING - COST ESCALATION
3.1. Cost Escalation - Introduction
3.2. Cost Escalation - Process
3.3. Cost Escalation - Cost Indices
4.0. COST ESTIMATING - CONTINGENCY 4.1. Contingency - Definition
4.2. Contingency - Coverage
4.3. Contingency - Calculation Methods
4 4 Contingency Management