estimating ii

Upload: kentdemeterio

Post on 02-Jun-2018

213 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/10/2019 Estimating II

    1/34

    COST MANAGEMENT 642

    Paper 10

    ESTIMATING II

    GENERAL

  • 8/10/2019 Estimating II

    2/34

    Paper 10 - ESTIMATING II

    1.0. COST ESTIMATING - ACCURACY

    2.0 COST ESTIMATING - ASPECTS

    3.0. COST ESTIMATING - COST ESCALATION

    4.0. COST ESTIMATING - CONTINGENCY

  • 8/10/2019 Estimating II

    3/34

    COST ESTIMATING

    QUESTIONS

    1. What factors determine the accuracyof a cost

    estimate?

    2. What are the specific difficulties of estimating

    the costs of projects?

  • 8/10/2019 Estimating II

    4/34

    COST ESTIMATING -ACCURACY

    estimating is not an exact science: it is much an art as a

    science, and involves intuition and expertjudgement

    cost estimates should be as accurate as possible.

    Accuracy expressed as+/-% range around point estimate

    Factors which determine the level of accuracy include:

    project definition

    quality of cost database

    quality of estimator

    estimating method

    level of effort

    project characteristics

  • 8/10/2019 Estimating II

    5/34

    ACCURACY:PROJECT DEFINITION - PLC Link: growth of information during PLC & estimating accuracy

    project definition increases, expected accuracy improves

    Earlier in PLC, problems of estimate accuracy

    Quality of info. increases through PLC, accuracy range narrows

    CONCEPT PHASE

    Estimates used for economic viability of project reasonably accurate estimates essential for go/no-go decision

    but minimal information, so concerted effort required

    Estimates - 'order-of-magnitude' based on parametric estimating

    "early estimates have wide variability ... most often notoriously low.

    DEVELOPMENT PHASE

    Scope developed - allows more accurate estimates

    As more inform, estimate continually updated & accuracy improved.

  • 8/10/2019 Estimating II

    6/34

    ACCURACY:PROJECT DEFINITION - PLC

  • 8/10/2019 Estimating II

    7/34

    ACCURACY:PROJECT DEFINITION - PLC

  • 8/10/2019 Estimating II

    8/34

    ACCURACY: COST DATABASE

    Accuracy dependent on quality of reference cost data

    Accuracy better when verified data used rather than

    assumptions

    So comprehensive, relevant, up-to-date database of cost

    information required for accurate cost estimating

  • 8/10/2019 Estimating II

    9/34

    ACCURACY: QUALITY OF ESTIMATOR

    1 major cause of poor estimation in that the people making

    the estimates dont know what they are doing.

    Greater accuracy if estimator is capable, unbiased,

    experienced, knowledgeable, methodical,

    Estimator should:

    be able to forecast and interpret trends;

    work intuitively where information is limited;

    motivated & enthusiastic

    most significant human factor is estimators knowledge ofgeneral price levels, acquired through experience

  • 8/10/2019 Estimating II

    10/34

    ACCURACY: QUALITY OF ESTIMATOR

    Desirable qualities in good estimator :

    basic numerate education;

    ability to communicate;

    ability to understand & interpret project information;

    patience;

    curiosity;

    confidence;

    ability to question the basis of assumptions

  • 8/10/2019 Estimating II

    11/34

    ACCURACY: Estimating Methods

    several estimating methods - some inherently more

    accurate

    EG parametric typically less accurate than bottom-up

    But, choice & accuracy of estimating method is

    fundamentally affected by quality of information available.

  • 8/10/2019 Estimating II

    12/34

    ACCURACY: Level of Effort

    it costs money to estimate costs

    Accuracy depends time & effort devoted to estimating greater accuracy, greater the cost of producing estimates

    Beyond certain level of effort, only modest improvement in

    accuracy

    Research - significant obstacle to accurate estimates =

    unwilling to invest resources to develop better estimating

    practice Type of Estimate Accuracy (%) level of effort, % of project cost*

    Proposal +/- 30 to +/- 50 0.02 - 0.1

    Budget +/- 20 to +/- 35 0.1 - 0.3

    Sanction +/- 10 to +/- 25 0.4 - 0.8

    Control +/- 5 to +/- 15 1 - 3

    Tender +/- 2 to +/- 5 5 - 10

  • 8/10/2019 Estimating II

    13/34

    ACCURACY: Project Characteristics

    Technical uniqueness & complexity of a project affects

    estimate accuracy

    first-of-a-kind project more difficult to estimate accuracy

    compared to a project that repeats past practices.

  • 8/10/2019 Estimating II

    14/34

    Accuracy - Classification Systems

    Awareness of Accuracy

    Important - those using estimates are aware of accuracy. Reasons:

    Feasibility Studies

    If known accuracy = +/-10%, sensitivity analysis can be

    applied to feasibility study.

    Management Attitude

    Management appreciate why earlier estimate to be too low

  • 8/10/2019 Estimating II

    15/34

    Accuracy - Classification Systems

    Classification Systems

    1 way to indicate accuracy - classification system. Benefits:

    highlights missing information required for more accurate

    estimate

    good means of communicating estimate quality

    Action by management which uses estimate done in full

    understanding of its accuracy

    management aware of degree of reliance that should be

    placed on it when making decisions.

  • 8/10/2019 Estimating II

    16/34

    Accuracy - Classification Systems

    Concept Develop Design Execution

    Unclassified Class B or AClass E

    Class C

    Class D

    Class B

  • 8/10/2019 Estimating II

    17/34

  • 8/10/2019 Estimating II

    18/34

    Project Cost Estimating - Problems

    Project = uniqueness = lack of suitable precedents.

    project changes due to scope changes & new knowledge

    poorly defined scope = incorrect estimates. Often due to

    time pressure

    long projects - further project extends from original

    estimating base, less accurate original estimates likely tobe

  • 8/10/2019 Estimating II

    19/34

    Project Cost Estimating - Problems

    Problems in estimating for software development :

    Priority of Project Objectives- Historically, strong focus of

    meeting deadlines & quality.

    Task-Orientated Environment- emphasis on creativity and

    technical excellence. Less effort on cost estimation

    Lack of Managerial Expertise- favour young specialists asPMs, technically expert but perhaps poor PM & cost

    estimators

    Lack of Cost Data- SD firms do not keep comprehensive,accurate and detailed time sheets from previous projects

    Technological Change.-past cost data, however good, is of

    little use for preparing cost estimates of present SD

    projects

  • 8/10/2019 Estimating II

    20/34

    COST ESTIMATING

    QUESTION

    3. What would be the typical sectionsin a cost estimate

    REPORT ?

    C

  • 8/10/2019 Estimating II

    21/34

    Cost Estimating - Documentation

    estimate should always include written documentation on

    how it was developed, and what is included and excluded

    Written document should include

    The Purpose of the Estimate

    The Scope of the Estimate

    Assumptions & Exclusions

    Source of Cost Information

    Escalation Allowances

    Contingency Allowances

    Significant Findings

    COST ESTIMATING COST ESCALATION

  • 8/10/2019 Estimating II

    22/34

    COST ESTIMATING - COST ESCALATION

    Escalation = "provision in estimated costs for continuing

    price level increase over time"

    Oftenreceives less attention than other smaller items"

    Escalation a result of two factors:

    general inflation in costs, invariably upwards.

    specific market factors.

    COST ESTIMATING

  • 8/10/2019 Estimating II

    23/34

    COST ESTIMATING

    QUESTION

    4. ost ontingency

    i. Definecontingency

    ii. What type of items is it meantto cater for?

    iii. What type of items is it notmeant to cater for

    iii. By what methodsmight it be calculated?

    COST CONTINGENCY INTRODUCTION

  • 8/10/2019 Estimating II

    24/34

    COST CONTINGENCY- INTRODUCTION

    3 basic types of C - tolerance in specification, float in

    schedule, money in budget.

    C= mostmisunderstood, misinterpreted, misapplied word

    in projects. C means different things to different people

    C is highly subjective, inconsistently interpreted,

    inadequately estimated

    imperative to have a policy regarding C definition that is

    understood and accepted by all project participants

    COST CONTINGENCY DEFINITION

  • 8/10/2019 Estimating II

    25/34

    COST CONTINGENCY- DEFINITION

    "amount of money added to the estimate to allow for

    changes that experience shows will likely be required"

    allowances added to an estimate to represent the bestjudgement of undefined or uncertain items of work which it

    is considered should be provided for. ... They are 'areas of

    space' in an estimate which help a PM to meet the projectcost objectives, as they face exposure to project risk and

    uncertainty"

    ATTRIBUTES OF COST CONTINGENCY

  • 8/10/2019 Estimating II

    26/34

    ATTRIBUTES OF COST CONTINGENCY It is a reserve of a sum of money.

    It is part of the project cost estimating process

    Its necessity & amount is linked to the existence of risk - caters for

    events unknown, undefined, uncertain, or unforeseeable.

    It is a risk management tool - reduces impact if risks eventuate

    Inclusion means estimate represents total financial commitment:

    estimatewithout contingency is simply not a complete estimate

    increases probability that final cost will not exceed our estimate

    Can have major impact on decision-making:

    Client - if too high, encourages sloppy cost management or causeproject to be uneconomic & aborted; if too low, too rigid & set

    unrealistic financial environment unsatisfactory outcomes.

    Contractor, balance risk of overrunning costs against probability

    of winning contract

    C ti C

  • 8/10/2019 Estimating II

    27/34

    Contingency - Coverage Incomplete Scope Definition

    Allows for incomplete scope definition.

    Order-of-magnitude & budget estimates developed early in PLC. With

    more scope definition, estimate invariably increases.

    C caters for increases in costs due to present incomplete definition

    Inaccuracy of Estimating Methods & Data

    no method or data is perfect, & historically result in low estimate

    C added to the estimate to cover for these inadequacies.

    But C should not be an excuse for poor estimating

    C ti C

  • 8/10/2019 Estimating II

    28/34

    Contingency - Coverage

    Identified risks

    C may be created for specifically identified risks. Eg contractor

    tendering, allow C for:

    scope error interpretations,

    minor design changes,

    inaccuracy in quantification,

    abnormal construction problems,

    liabilities in the contract,

    unforeseen regulations,

    safety requirements, equipment breakdowns,

    weather interruptions,

    labour productivity,

    technological change

    Contingency Coverage

  • 8/10/2019 Estimating II

    29/34

    Contingency - Coverage Unknown Unknowns

    C set up to allow for unidentified risks:

    "It is important to identify contingency allowances associated

    with all significant individual risks, plus a residual allowance for

    other unidentified risks"

    This excludes unforeseeable major events (see below).

    Items not part of contingencies

    C should cover for scope development but not scope changes. Other items not considered appropriate for inclusion in C:

    escalation,

    unforeseeable major events - extreme weather, earthquakes, riots,

    acts of war, new government regulations, economic collapse

    Contingency Calculation PERCENTAGE ADD ON

  • 8/10/2019 Estimating II

    30/34

    Contingency - Calculation: PERCENTAGE ADD-ON C calculated as % on base estimate, based on from experience &

    historical data. For example:

    incomplete scope definition in early estimates, 30%- 50%; oncescope fully developed 3% to 5%"

    inaccuracy of estimating method &/or data 5%-10%,

    Level of contingencies will depend on:

    organisation and the type of business

    type of estimate. (eg. order-of-magnitude estimate demands a

    high C to cover for the inherent inaccuracies of this method)

    PLC phase (eg estimate at concept phase = high C to allow for

    limited information used to prepare an estimate)

    type of project. (eg new/unproven technology High C

    type of work - eg underground work = uncertainty = High C

    Variation to single % additional to base estimate - apply different %to each major component of the estimate.

    Contingency Calculation Risk Analysis

  • 8/10/2019 Estimating II

    31/34

    Contingency - Calculation Risk Analysis contingencies by % mark-up not recommended:

    "all too often risk is either ignored or dealt with in an arbitrary

    way: simply adding a 10% 'contingency' onto the estimated cost ofa project is typical. This is virtually certain to be inadequate and

    cause expensive delay, litigation, and perhaps bankruptcy"

    contingency should definitely be based on an experienced

    review of uncertainties of estimate details. An arbitrary bottompercentage is not good enough.

    Allocating % insufficient unless linked to a confidence level. i.e. level

    of probability that final cost will be within estimate (including C).

    Nowadays, more rigorous & defendable approaches for calculation

    ofC , typically derived from probability analysis, eg Central Limit

    Theorem and Monte Carlo simulation.

    Contingency Management

  • 8/10/2019 Estimating II

    32/34

    Contingency - Management Level of C constantly monitored & reassessed through PLC

    Success of contingency management:

    establish procedures for proper use of C

    establish information system showing each responsible manager

    & C under their control, C used, trends, when possible to transfer

    balances to other less successful areas or general reserve

    2 basic ways to manage C

    Single account - single line item account. Disadvantages:

    tendency to use C first-come, first-serve basis with potential

    exhaustion well before project is over

    control likely to be responsibility of PM - but other commitments

    are intense and may lead to neglect of contingency management.

    Individual Allocations - & responsibility assigned for their control. If

    expenditure exceedsC, negative variance reported. Unexpended C

    can be transferred to a general contingency account.

    ALLOWANCES

  • 8/10/2019 Estimating II

    33/34

    ALLOWANCES Contingency = unforeseeable and undefined items

    Allowance - = for known and undefined items, foreseen to be spent

    Redefined each time an estimate is revised

    allowance should only be made if "there is a better than 50% chance

    of it happening"

    Allowance added to estimate, identified with documented basis

    Allowances - Exclusions:

    major scope changes

    weather extremes, earthquakes

    accidents acts of God

    strikes

    because "these items are unpredictable, both in terms of

    probability magnitude of cost impact if they do occur".

    Paper 10 ESTIMATING II

  • 8/10/2019 Estimating II

    34/34

    Paper 10 - ESTIMATING II 1.0. COST ESTIMATING - ACCURACY

    1.1. Factors affecting Accuracy

    1.2. Accuracy - Classification Systems 2.0 COST ESTIMATING - ASPECTS

    2.1. Cost Estimating - Problems

    2.2. Cost Estimating - Do's and Don'ts

    2.3. Cost Estimating - Documentation

    3.0. COST ESTIMATING - COST ESCALATION

    3.1. Cost Escalation - Introduction

    3.2. Cost Escalation - Process

    3.3. Cost Escalation - Cost Indices

    4.0. COST ESTIMATING - CONTINGENCY 4.1. Contingency - Definition

    4.2. Contingency - Coverage

    4.3. Contingency - Calculation Methods

    4 4 Contingency Management