Page 1 of 25 ESTATES OFFICE – OPERATIONS DEPARTMENTAL PROCEDURE No.6 Tendering Procedures ISSUE RECORD Revision Description Updated Date Compiled by Review Date

Upload: phamkhuong

Post on 23-Mar-2018

214 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: ESTATES OFFICE OPERATIONS DEPARTMENTAL  · PDF file6. TENDERING PROCEDURE Page 2 of 25 University of Bristol Issue Date Estates Operations October 2010 6

   

Page 1 of 25

       

ESTATES OFFICE – OPERATIONS   

DEPARTMENTAL PROCEDURE No.6     

Tendering Procedures                              

ISSUE RECORD 

Revision  Description   Updated Date 

Compiled  by 

Review  Date 

         

         

Page 2: ESTATES OFFICE OPERATIONS DEPARTMENTAL  · PDF file6. TENDERING PROCEDURE Page 2 of 25 University of Bristol Issue Date Estates Operations October 2010 6

6.  TENDERING PROCEDURE 

Page 2 of 25 University of Bristol    Issue Date Estates Operations    October 2010   

6.  TENDERING PROCEDURE      The University needs to demonstrate openly that competition is brought to bear upon 

procurement processes so that value for money is obtained. The University of Bristol issues guidance in this respect and Estates Operations Department aims, by following the procedures below, to operate within those requirements. 

     Tendering processes must be considered in relation to the size of the contract to be 

placed. The following Section details the methods which must be followed for tendering works and sets down limits above which full competition must always be achieved. 

     It is important to plan sufficient time for the following processes to be carried out fully. 

Even on accelerated work a period for tender must be allowed if true value for money is to be secured. This must be borne in mind when agreeing timescales with client representatives and when closing off design requirements and changes, except in circumstances of partnering which requires authority of the Director of Estates Operations. 

     6.1  Guiding Principles     Competitive tenders are sought in order to ensure that a fair and reasonable 

price is secured for contract works that provides value for money. Tendering, therefore, is executed under a confidential and ‘”sealed” process whereby tenderers are, as far as practicable, unaware of whom they are competing against. Collusion between tenderers in the tendering process is not unknown and therefore it is important to maintain a position of complete integrity and impartiality whilst waiting for tenders to be submitted. Tenderers should be required to complete a non‐collusion declaration, see form UB/3, Appendix 6/1, when returning their tender proposal. 

         Tender proposals must always be checked for correctness before acceptance. 

Any significant errors, which are discovered, which have the effect of reducing the overall proposal must be checked with the tenderer, see qualifications below. The Department does not seek to take commercial advantage in situations since this, in the long run, can affect performance on individual contracts and on the pricing structures used by tenderers. 

       6.2  Contract Values and Tendering Methods     Tendering procedures vary according to the estimated value of work to be 

carried out. The value limits described below are not absolute; it may be that best value for money can be achieved by adopting methods other than standard procedures. 

     

Page 3: ESTATES OFFICE OPERATIONS DEPARTMENTAL  · PDF file6. TENDERING PROCEDURE Page 2 of 25 University of Bristol Issue Date Estates Operations October 2010 6

6.  TENDERING PROCEDURE 

Page 3 of 25 University of Bristol    Issue Date Estates Operations    October 2010   

    If a varied procedure is to be followed this must be approved by the Director of Operations in advance. A description of the process to be used in this eventuality must be recorded and placed on file. 

         For works projects greater than £3.9 million or goods/ services in excess of 

£156,000 cumulative over a four year period tendering processes must include advertisement throughout Europe. Refer to the Senior Surveyor ‐ Head of Capital Maintenance and Infrastructure and/or Director of Operations and/or Procurement Office for guidance in these cases.  

         Where the estimated value of works exceeds £40,000 competitive tenders shall 

always be sought unless single tender procedures are approved. See 6.3.10.  For works where estimated value exceeds £1,000,000 special insurance requirements apply, see Procedure 7.  For work where estimated value is expected to exceed £500,000 a tender board shall be convened to carry out the tender opening and review process. 

       6.3  Standard Tender Procedure     Unless specifically agreed otherwise the following requirements must be 

fulfilled when adopting standard tender procedure. Where consultants are engaged to secure competitive tenders it is permissible to vary the format of paperwork so that the consultants own documentation is utilised, the process however must match fully with the underlying requirements laid down herein. 

    6.3.1  Tender List       Prospective tenders must be selected from the University’s Approved 

List of Contractors. These contractors have already undergone a financial audit and have registered a copy of their company safety policy with the Director of Estates Operations and belong to an approved HPS Standards & Audit organisation, currently CHAS. 

             If new contactors are to be considered for eligibility to carry out work 

then pre‐approval should be sought before finalising the tender list of a project. 

             There may be special requirements, which limit the choice of 

contractors for work. The use of new contractors is to be encouraged once pre‐approval has been completed. 

             The names of companies included within a tender list must not be 

divulged outside the Department except to consultants working on the project and to the nominated client representative. The identity of any company attempting to determine names of other tenderers should be passed to the Director of Estates Operations or the University Senior 

Page 4: ESTATES OFFICE OPERATIONS DEPARTMENTAL  · PDF file6. TENDERING PROCEDURE Page 2 of 25 University of Bristol Issue Date Estates Operations October 2010 6

6.  TENDERING PROCEDURE 

Page 4 of 25 University of Bristol    Issue Date Estates Operations    October 2010   

Surveyor for action. The Senior Surveyor ‐ Head of Capital Maintenance and Infrastructure  must approve all tender lists. 

           6.3.2  Contractor Selection – Matching to Contract Value       Contractors shall only be invited to perform works equivalent in overall 

value to no more than 25% of their annual turnover. This ensures that contractors do not run into exceptional cash‐flow problems either with their own bankers or suppliers. (This information is stored on the ‘Approved Contractors’ list.) 

             Contractors wishing to have special payment provisions outside of 

standard contract payment practice should not be used as this may indicate cash flow sensitivity.  

             In the same way it is required that contractor selection is based upon 

minimum turnover it is important to consider size‐matching of the whole tender list in order to ensure value for money. Wherever possible therefore tender lists should comprise companies of similar financial size. This is especially important when inviting new contractors to tender. 

             Having formulated the tender list this must be recorded and places 

upon the project file along with the necessary approvals. See fig 6.1              It must always be presumed that if a tenderer provides the best value 

for money (see 6.3.5) at the tender review stage then the Project Manager must be happy to proceed to contract with that Company. It is not appropriate to reconsider the suitability of a contractor after the tender list has been closed unless specific new information has come to light.  

           6.3.3  Tender List Approval       All contractors who have been accepted onto the Approved List should 

receive an equal opportunity to tender for work. Therefore, when formulating a tender list consideration must be given to rotating companies and avoiding the inclusion of selected companies on all tender lists. The Senior Surveyor ‐ Head of Capital Maintenance and Infrastructure is responsible for ensuring this occurs.  

             Managing tender lists in this way prevents particular contractors from 

becoming too dependant on the University and also allows a greater breadth of experience in working on projects with us. 

       

Page 5: ESTATES OFFICE OPERATIONS DEPARTMENTAL  · PDF file6. TENDERING PROCEDURE Page 2 of 25 University of Bristol Issue Date Estates Operations October 2010 6

6.  TENDERING PROCEDURE 

Page 5 of 25 University of Bristol    Issue Date Estates Operations    October 2010   

      In approving a tender list therefore the Senior Surveyor – Head of Capital Maintenance and Infrastructure will consider overall factors relating to chosen companies and may wish to check, through cost records, how much total business a particular company has performed or is performing for the Department. 

             Management of the Approved Contract List is detailed in Procedure 9.            6.3.4  Invitation to Tender       Tenders will be invited in response to a package of work fully described 

by a specification and drawings where required.              All tenderers shall receive identical information despatched at the 

same time by 1st class post or made available for collection at the Department General Office. The tender will be distinguished by its project/job number, which will be referenced on all tender documentation. 

             Accompanying the tender package will be the following documents.       UB/1  Invitation to Tender       UB/2  Instructions to tenderers for return of tenders       UB/3  Selective Tendering – Non Collusion Declaration       UB/4  Form of Tender       UB/5  Summary of Prices       UB/6  Alternatives       UB/7  Schedule of Work Sub‐Let       UB/8  Income Tax Liability       UB/9  VAT Estimate Form       UB/10  Dayworks and Extra Works       UB/11  Contribution, levy and tax fluxations (JCT Standard Contracts 

only)       UB/12  Added Value Submission & additional documents for 

consideration.          Information which will be used/ scored to provide a ‘value’ 

judgement on tenders where VFM is evaluated rather than just price. 

             Omission of any document must be agreed/ approved by the Senior 

Surveyor – Head of Capital Maintenance and Infrastructure. A tender return date, time and place must be specified on the form of tender, UB/4, and the tender invitation UB/1.  

              

Page 6: ESTATES OFFICE OPERATIONS DEPARTMENTAL  · PDF file6. TENDERING PROCEDURE Page 2 of 25 University of Bristol Issue Date Estates Operations October 2010 6

6.  TENDERING PROCEDURE 

Page 6 of 25 University of Bristol    Issue Date Estates Operations    October 2010   

      6.3.5  Information Sought during the Tender Period       All tenderers will be allowed the opportunity to visit site accompanied 

by a member of the Project Team wherever possible. It is not unusual for questions to bring attention to problems or qualification with the design intention, which may affect the price submitted by the tenderer. The Project Manager must ensure that all such information is provided to all tenderers in writing so that all have equal chance of properly assessing the scope of the work. Project team members must offer no opinions concerning ideas that the tenderer may have about the method of doing the work. 

             Any proposals the tenderer may have must be evaluated at the tender 

review stage and opinions as to merit withheld until then. General queries relating to work content that do not alter the design intent in any way need not be communicated to other tenderers. It must be assumed that tenderers have all understood the information provided in the same way. 

           6.3.6  Tender Returns       Tenders must be received by the stipulated return date in order to be 

considered for inclusion in the review process. Any tenders received after this time will not be considered. The tender may or may not be opened depending on the circumstances applying at the time, but wherever possible the tender will be returned to the contractor unopened.  

             Tenders must be returned in the envelopes provided at invitation. 

Tenders received by post must be sent within a covering package which will be removed prior to tender opening. Any tender delivered by hand will be acknowledged by receipt if required. 

             Normally tenders should be returned at 10.00am on a normal working 

day. This may be changed if circumstances dictate, but the return time and date must be when the office is open and staff present to receive tenders. 

           6.3.7  Tender Opening and Review       All valid tenders will be opened at one sitting, in the presence of an 

independent party (see Figure 6.1) and the information contained checked for completeness. The tender offer price will be recorded manually on a review form (Figure 6.2) and a note made of any 

Page 7: ESTATES OFFICE OPERATIONS DEPARTMENTAL  · PDF file6. TENDERING PROCEDURE Page 2 of 25 University of Bristol Issue Date Estates Operations October 2010 6

6.  TENDERING PROCEDURE 

Page 7 of 25 University of Bristol    Issue Date Estates Operations    October 2010   

qualifications or omissions by the tenderer or any omissions in tender paperwork. 

             Very often information within a valid tender offer is incomplete or 

unclear and in order to be sure that best value for money is obtained some checking and analysis is required. In these circumstances a choice may exist between 2 or more tenderers depending upon the outcome of the further analysis. 

             Once all valid tender offers have been recorded the project manager or 

tender board will decide/discuss which of the tenders is appropriate to accept. If the decision is clear‐cut at this stage, i.e. there are no qualifications to consider, a recommendation for acceptance will be made at that point on the review form based solely on the best value for money for the University. 

             Should a price other than the lowest be recommended for acceptance 

this must be approved both by the Director of Estates Operations and the client representative (if this is a rechargeable project) or senior user/ project board if University funded. The budget holder is to approve any Estates funded projects. 

             Further information may be required to clarify tender offers in order to 

check validity of price, the tender review process is not complete until this information has been analysed. 

             It is permissible to seek clarification of tenders in terms of content, i.e. 

to check what is specifically included in case tenderers prices are too low. Tenderers may not reduce their price at this stage to gain commercial advantage unless items have been included in error.  

             Once the tender review is complete any other invalid tenders may be 

opened if desired. The completed tender review document will then be placed on project file. 

             After completion of the analysis process the tender review can then 

normally be successfully completed, if necessary re‐convening the tender board for this purpose. If difficulties still remain then the Director of Estates Operations should be consulted. 

           6.3.8  Confirmation of Acceptance       Upon successful completion of the tender review process the Project 

Manager will then report to the “project corporate board” (where 

Page 8: ESTATES OFFICE OPERATIONS DEPARTMENTAL  · PDF file6. TENDERING PROCEDURE Page 2 of 25 University of Bristol Issue Date Estates Operations October 2010 6

6.  TENDERING PROCEDURE 

Page 8 of 25 University of Bristol    Issue Date Estates Operations    October 2010   

existing) or Budget holder or Senior Surveyor ‐ Head of Capital Maintenance and Infrastructure, as appropriate. In the event that none of these people are available the matter should be referred to the Director of Estates Operations. 

             All contractors should be informed as quickly as possible, in writing, as 

to the result of the tender review. If requested a list of offer prices can be released, without company names, to assist tenderers in future tendering exercises. 

    6.3.10  Single Tender Action       In exceptional circumstances, for work valued at more than £40,000, it 

can be acceptable to secure only a single tender for work. Approval must be sought, in writing, from the Director of Estates Operations in all such circumstances before giving a commitment to clients that this will be the case. 

             Among possible reasons for this course of action are:              a.  Timescales imposed by The University are such that the required 

design and tender period is not possible.                b.  The work is of a very specialist nature such that only one known 

company can perform the work, time available precluding further research. 

               c.  The work is not capable of full specification and therefore pricing 

develops as the work proceeds, e.g. a job comprising of significant exploratory work prior to confirmation of scope.  

               There may be other circumstances also which could lead to the 

acceptance of a single tender being sought. These must be fully described and discussed with the Director of Estates Operations or in his absence Senior Surveyor ‐ Head of Capital Maintenance and Infrastructure prior to taking this action, all reasons and approvals must be recorded in the project file. Single Tender action for works on excess of £250,000 must be approved by the Bursar.  

             Even in single tender situations it is usually possible to demonstrate 

some element of competitiveness and options for providing this  must be included in he case for approval. 

           6.3.11  Competitive Quotations – Works Value less than £40,000       For work of value less than £40,000 it is still necessary to ensure that 

Page 9: ESTATES OFFICE OPERATIONS DEPARTMENTAL  · PDF file6. TENDERING PROCEDURE Page 2 of 25 University of Bristol Issue Date Estates Operations October 2010 6

6.  TENDERING PROCEDURE 

Page 9 of 25 University of Bristol    Issue Date Estates Operations    October 2010   

keen pricing is secured to obtain good value for money before entering into any contract commitment.  

             This will mean requesting at least three written quotations for a 

particular work item and comparing these in the same spirit as the full tender process. In this situation it is important to record all quotations in the project file along with any relevant analysis to indicate why a particular contractor was chosen. 

             The Project Manager responsible will need to determine the amount of 

time worth spending on this exercise compared to the possible commercial gain. Obviously the lower the price is below the £40,000 upper limit then the lower is the nett gain to the University when taking into account the cost if our own staff time. 

             For emergency work of a value less than £5,000 it is permissible to 

proceed on the basis of a single price only. However, whenever time allows a minimum of two quotes should be sought and recorded. 

       

Page 10: ESTATES OFFICE OPERATIONS DEPARTMENTAL  · PDF file6. TENDERING PROCEDURE Page 2 of 25 University of Bristol Issue Date Estates Operations October 2010 6

6.  TENDERING PROCEDURE 

Page 10 of 25 University of Bristol    Issue Date Estates Operations    October 2010           

 Figure 6.1 ‐ TENDER FORMULATION GUIDELINES 

Estimated Value of Work 

Standard Procedure 

Minimum Size of 

Tender List 

Approval of Tender 

List 

Minimum Tender Period Allowed (Weeks) 

Tender Opening  Works Insurance Requirements 

(See Procedure 7, Section 7.6) 

Notes 

Up to £5,000 

Preferred  1 ‐2  Project Manager  Less than 1  Project Manager     

 Less than £40,000  

 Preferred 

 3 

 Project Manager & Senior Surveyor ‐ Head of Capital Maintenance and Infrastructure 

 2 

 Project Manager & 

witness * 

 Covered by block policy 

 *Another member of UoB Estates Office staff.  See also requirements under single tender procedures 

 £40,000 to £500,000   

 Obligatory 

 3 ‐ 5 

 Project Manager & Senior Surveyor ‐ Head of Capital Maintenance and Infrastructure 

 3 

 Project Manager & Senior Surveyor ‐ Head of Capital Maintenance or 

Director of Operations 

 

 Covered by block policy 

 EU tendering requirements may apply (services). Check with Procurement Office 

 £500,000 + 

 Obligatory 

 5 

Max 6 

 Tender Board Chairman 

Or Director of Operations  

Plus Senior Surveyor – Head of Capital Maintenance and Infrastructure 

 4 

 Tender Board` (To include 

representation from budget holder and stake holders as appropriate) 

 Covered by block policy up to £1m. Individual policy above 

£1m 

The Tender Board should meet on the day that tenders are received.  Representative(s) of the budget holder should attend.  + EU tendering requirements may also apply, check with Procurement Office. 

Page 11: ESTATES OFFICE OPERATIONS DEPARTMENTAL  · PDF file6. TENDERING PROCEDURE Page 2 of 25 University of Bristol Issue Date Estates Operations October 2010 6

6.  TENDERING PROCEDURE 

Page 11 of 25 University of Bristol    Issue Date Estates Operations    October 2010           

   

Figure 6.2  

 TENDER REVIEW ‐ REPORT FORM 

 JOB/PROJECT NO:  TITLE: 

 PROJECT MANAGER: 

 

 DATE:                                                            TIME: 

Company Name  Valid Tender Rec'd  

Tender Forms 

Completed 

Tender Offer  Witnessed By 

Comments/Qualification  Qualified Offer 

Recommended for Acceptance  

             Y/N  Date 

 1  

            

   

 2  

                

 3  

                

 4  

                

 5  

                

 *Approval of Recommendation 

Approved by:  

Date:  

  

* Budget holder or Senior Surveyor ‐Head of Capital Maintenance & Infrastructure or Director of Operations or Project Corporate Board 

Page 12: ESTATES OFFICE OPERATIONS DEPARTMENTAL  · PDF file6. TENDERING PROCEDURE Page 2 of 25 University of Bristol Issue Date Estates Operations October 2010 6

6.  TENDERING PROCEDURE 

Page 12 of 25 University of Bristol    Issue Date Estates Operations    October 2010          

  

APPENDIX 1    

    Page No      UB/1  Invitation to Tender  2      UB/2  Instructions to tenderers for return of tenders  3      UB/3  Selective Tendering – Non Collusion Declaration  4      UB/4  Form of Tender  5      UB/5  Summary of Prices  6      UB/6  Alternatives  7      UB/7  Schedule of Work Sub‐Let  8      UB/8  Income Tax Liability  9      UB/9  VAT Estimate Form  10      UB/10  Dayworks and Extra Works  11      UB/11  Contribution, levy and tax fluctuations  

(JCT Standard Contracts Only) 12 

  

Page 13: ESTATES OFFICE OPERATIONS DEPARTMENTAL  · PDF file6. TENDERING PROCEDURE Page 2 of 25 University of Bristol Issue Date Estates Operations October 2010 6

6.  TENDERING PROCEDURE 

Page 13 of 25 University of Bristol    Issue Date Estates Operations    October 2010          

 

Page 14: ESTATES OFFICE OPERATIONS DEPARTMENTAL  · PDF file6. TENDERING PROCEDURE Page 2 of 25 University of Bristol Issue Date Estates Operations October 2010 6

6.  TENDERING PROCEDURE 

Page 14 of 25 University of Bristol    Issue Date Estates Operations    October 2010

         

       Dear Sirs  SPECIFICATION NO:  I enclose herewith the above Specification and associated documents and drawings and you are invited to submit your Tender for these works which should be received by this office not later than:‐  10.00AM, on THURSDAY xxTH 2010   Please note that any further details in connection with these works should be obtained from Mr xxx xxx, Project Manager (or xxx) Tel Bristol 9289000 ext xxx, and that all documents and drawings must be returned under separate cover.  Drawing No’s:   Yours Faithfully      Xxxx Xxx xxx   Encs      UB/1 

Page 15: ESTATES OFFICE OPERATIONS DEPARTMENTAL  · PDF file6. TENDERING PROCEDURE Page 2 of 25 University of Bristol Issue Date Estates Operations October 2010 6

6.  TENDERING PROCEDURE 

Page 15 of 25 University of Bristol    Issue Date Estates Operations    October 2010

         

UNIVERSITY OF BRISTOL  

   

Instructions to tenderers for return of tenders:‐  

1. Complete all forms enclosed for Tender and place in the envelope provided.  

2. The tender must be returned in the endorsed tender envelope to the appointed Contract Administrator.   

3. The tender envelope must not bear any mark or indication of the identity of the sender.  

4. Late tenders will not be accepted and any such tender will be returned in due course.  

5. No tenders or tender figures will be considered other than on the prescribed forms delivered in accordance with the foregoing instructions.  

6. If any other documents are to be returned, e.g. drawings, specifications etc, they must be sent under separate cover and must not be enclosed with the tender.  

7. The acceptance of the lowest or any tender or the nomination in the case of suppliers or subcontractors cannot be assumed and no payment will be made for tendering.  

8. Please note that the Principles of “Code for Procedure for Single Stage Selective Tendering 1989” will be observed and that if examination of the priced Bills reveals any errors or discrepancies between these prices and the tender sum, then section 6.3, Alternative 1 of the Code shall normally apply.  

9. The Contractor’s attention is drawn to the requirements stated in the preliminaries where there is a requirement to submit evidence of the existence of insurance for themselves or any sub‐contractor for the duration of the contract.  

10.  Tenders submitted by facsimile will not be accepted.  

11. The VAT Estimate Form must be completed to be returned with the tender.  

UB/2 

Page 16: ESTATES OFFICE OPERATIONS DEPARTMENTAL  · PDF file6. TENDERING PROCEDURE Page 2 of 25 University of Bristol Issue Date Estates Operations October 2010 6

6.  TENDERING PROCEDURE 

Page 16 of 25 University of Bristol    Issue Date Estates Operations    October 2010

         

UNIVERSITY OF BRISTOL  

SELECTIVE TENDERING – NON COLLUSION DECLARATION  

TENDER FOR:    RETURNABLE: 12 NOON  The essence of selective tendering is that the client shall receive bona fide competitive tenders from all firms tendering. In recognition of this principle, we certify that this is a bona fide tender, intended to be competitive, and that we have not fixed or adjusted the amount of the tender by or in accordance with any agreement with any other person. We also certify that we have not done and we undertake that we will not at any time before the returnable date for this tender any of the following acts:‐  

a. Communicate to a person other than the person calling for those tenders the amount or approximate amount of the proposed tender.  

b. Enter into any agreement or arrangement with any other person that he shall refrain from tendering or as to the amount of any tender to be submitted.  

c. Offer to pay or agree to pay or give any sum of money or valuable consideration directly or indirectly to any person for doing or having done or causing or having caused to be done in relation to any other tender or proposed tender for the said work any act or thing of the sort described above.  

In the certificate the word ‘person’ includes any persons and any body or association, corporate or unincorporate; and ‘any agreement or arrangement’ includes any such transaction, formal or informal, and whether legally binding or not.  Signed………………………………………………….  on behalf of………………………………………….  Date …………………………………………………….  UB/3 

ALL PARTS OF THIS FORM MUST BE COMPLETED SPECIFICATION NO: 

Page 17: ESTATES OFFICE OPERATIONS DEPARTMENTAL  · PDF file6. TENDERING PROCEDURE Page 2 of 25 University of Bristol Issue Date Estates Operations October 2010 6

6.  TENDERING PROCEDURE 

Page 17 of 25 University of Bristol    Issue Date Estates Operations    October 2010

         

UNIVERSITY OF BRISTOL  

FORM OF TENDER RE:  Sirs  I/Wee have read the conditions of contract, specification and schedules deliver to me/us and having examined the drawings referred to therein and visited site, do hereby offer to execute and complete the whole of the works described for the sum of:‐                  £  Works as Specified …………………………………………………………………………………………………………………………..  Specified PC Sums ……………………………………………………………………………………………………………………………  Specified Provisional Sum ………………………………………………………………………………………………………………..  Specified Contingency ……………………………………………………………………………………………………………………..          TOTAL OF TENDER   £          (EXC VAT)   We agree that the sum is a firm price Tender which shall not be affected by or adjusted in respect of any fluctuations in the price of Labour, Materials, Transport, Plant and the like and within the programme given in the conditions of contract and I/We undertake in the event of your acceptance to execute with you a form of contract embodying all the conditions and terms contained in this offer.  We further agree that, where subdivided in specific section, this Tender may be accepted in whole or in part at the discretion of the University Surveyor.  This tender shall be returned to the appointed Contract Administrator – University of Bristol on xxx 10.00am and shall be open for consideration for a period of not less than 12 weeks.  

Dated this …………………………………day of …………………………………………………20………  Name of firm ……………………………………………………………………………………………………..  Address ……………………………………………………………………………………………………………...  Signature of Director ………………………………………………………………………………………….  

THE EMPLOYERS DO NOT BIND THEMSELVES TO ACCEPT THE LOWEST OR ANY TENDER ALL PARTS OF THIS FORM MUST BE COMPLETED 

 UB/4 

Page 18: ESTATES OFFICE OPERATIONS DEPARTMENTAL  · PDF file6. TENDERING PROCEDURE Page 2 of 25 University of Bristol Issue Date Estates Operations October 2010 6

6.  TENDERING PROCEDURE 

Page 18 of 25 University of Bristol    Issue Date Estates Operations    October 2010

         

UNIVERSITY OF BRISTOL  

SUMMARY OF PRICES 

 ITEM      DESCRIPTION                      £    P               

 Total cost carried to Form of Tender (Excluding VAT) 

  Signature ………………………………………………………………………………………  Status in Company ………………………………………………………………………..  For and on Behalf of ………………………………………………………………………  Address ………………………………………………………………………………………….  Date ……………………………………………………………………………………………….      UB/5 

Page 19: ESTATES OFFICE OPERATIONS DEPARTMENTAL  · PDF file6. TENDERING PROCEDURE Page 2 of 25 University of Bristol Issue Date Estates Operations October 2010 6

6.  TENDERING PROCEDURE 

Page 19 of 25 University of Bristol    Issue Date Estates Operations    October 2010

         

UNIVERSITY OF BRISTOL  

ALTERNATIVES   

The Employer is prepared to consider Alternatives to the Materials and Manufacturers named in the Specification and to any Specialist named in the Specification. The Tenderer should state below the additional cost or saving to the Contract Sum that would result by the incorporation of such proposals.  

Item  Manufacturer of Alternative 

Increase to Tender Price 

Decrease to Tender Price 

      £                      p  £                       p                          UB/6 

Page 20: ESTATES OFFICE OPERATIONS DEPARTMENTAL  · PDF file6. TENDERING PROCEDURE Page 2 of 25 University of Bristol Issue Date Estates Operations October 2010 6

6.  TENDERING PROCEDURE 

Page 20 of 25 University of Bristol    Issue Date Estates Operations    October 2010

         

UNIVERSITY OF BRISTOL  

SCHEDULE OF WORK SUB‐LET  

The Tenderer shall complete below the name and address of the actual Sub Contractor to be employed for works sub‐let.  ………………………………………………………………………………………………………………………………………..  ………………………………………………………………………………………………………………………………………..  ………………………………………………………………………………………………………………………………………..  ………………………………………………………………………………………………………………………………………..  …………………………………………………………………………………………………………………………………………  ………………………………………………………………………………………………………………………………………..  ………………………………………………………………………………………………………………………………………..  ………………………………………………………………………………………………………………………………………..  NOTE:   The above information must be completed at the time of tendering.   Signature of Tenderer ………………………………………………………………………………..  Date ……………………………………………………………………………………………………………       

ALL PARTS OF THIS FORM MUST BE COMPLETED  

   UB/7 

Page 21: ESTATES OFFICE OPERATIONS DEPARTMENTAL  · PDF file6. TENDERING PROCEDURE Page 2 of 25 University of Bristol Issue Date Estates Operations October 2010 6

6.  TENDERING PROCEDURE 

Page 21 of 25 University of Bristol    Issue Date Estates Operations    October 2010

         

UNIVERSITY OF BRISTOL   

Notice to Tenderers Finance (No 2) Act 1975  Income Tax: Subcontractors in the Construction Industry Regulation 1975 SI No 1960    

1. Although the University of Bristol is not a ‘contractor’ under the Above Act, the University will observe the spirit of the Act.   

2. Before the tender is accepted the tenderer will be required to provide the Employer with the evidence that the contractor  is entitled to be paid without the statutory deduction unless  it has already been produced in connection with another current contract with the University.   

3. The University keeps a record of all the payments to contractors in similar form to that required under the Act for the information of the Inland Revenue.   

4. Tenderers are reminded that contractors are required to check the Tax Certificates or certifying documents of sub‐contractors they employ  (including any nominated sub‐contractors) and to deduct tax as necessary and to comply in all respects with the Act.  

            UB/8 

Page 22: ESTATES OFFICE OPERATIONS DEPARTMENTAL  · PDF file6. TENDERING PROCEDURE Page 2 of 25 University of Bristol Issue Date Estates Operations October 2010 6

6.  TENDERING PROCEDURE 

Page 22 of 25 University of Bristol    Issue Date Estates Operations    October 2010

         

UNIVERSITY OF BRISTOL  

 VAT Estimate Form   To:   The University of Bristol   We, the undersigned hereby give our provisional assessment of Value Added Tax payable on positively rated taxable supplies of goods and/or services chargeable to the University of Bristol.   

 Description of good and/or services 

Value (tax exclusive) 

£ 

Positively rated at  

Tax  £ 

            Total carried forward to Form of Tender            £ 

   Signed ………………………………………………………………….. Date …………………………………………………………………..  on behalf of ………………………………………………………………………………………………………………………………………..     UB/9 

Page 23: ESTATES OFFICE OPERATIONS DEPARTMENTAL  · PDF file6. TENDERING PROCEDURE Page 2 of 25 University of Bristol Issue Date Estates Operations October 2010 6

6.  TENDERING PROCEDURE 

Page 23 of 25 University of Bristol    Issue Date Estates Operations    October 2010

         

 UNIVERSITY OF BRISTOL  

DAYWORKS AND EXTRA WORKS  

(a) The Contractor shall complete the following schedule and return it, together with the whole specification and his tender. Failure to do so may exclude the Contractor’s tender from consideration.  i. Total percentage additions to costs of extra works and dayworks executed whilst the contract proceeds. 

 Labour ………………………………………………………………………  Materials ………………………………………………………………….  Plant Haulage ……………………………………………………………  Sub‐Contractors ………………………………………………………...  

ii. Total percentage additions to cost of extra works and dayworks executed during the maintenance period of six months following practical completion.  Labour ………………………………………………………………………  Materials ………………………………………………………………….  Plant & Haulage ……………………………………………………….  Sub‐Contractors ……………………………………………………….  

iii. Total percentages added to PC sums.  Profit ………………………………………………………………………….  Attendance ………………………………………………………………..  Special Attendance where specified ………………………….  

b. Charges and accounts for dayworks and extra work shall be made in accordance with the above mentioned percentages, added to the Contractor’s prime cost only, calculated in accordance with the “Definition of Prime Cost of Daywork carried out under a Building Contract” published by the Royal Institute of Chartered Surveyors and the National Federation of Building Trades Employers.  

c. The Contractor shall submit to the Employer, or his authorised representative, vouchers specifying the time and materials expended on dayworks or extra works and be submitted not later than seven days after the expiry of the week in which the work was done.  Signed …………………………………………………………………………..  

For and on behalf of ………………………………………………………   ALL PARTS OF THIS FORM MUST BE COMPLETED  Date ……………………………………………………………………    

UB/10   

Page 24: ESTATES OFFICE OPERATIONS DEPARTMENTAL  · PDF file6. TENDERING PROCEDURE Page 2 of 25 University of Bristol Issue Date Estates Operations October 2010 6

6.  TENDERING PROCEDURE 

Page 24 of 25 University of Bristol    Issue Date Estates Operations    October 2010           

 UNIVERSITY OF BRISTOL 

  

Contribution, levy and tax fluctuations    List of types and rates of duty and tax, referred to in Clause 38.2.1 of the Main Contract or Clause 35.2.1 of NSC/4, to be completed by the tenderer.  

 Materials, Goods, Electricity 

Type and rate of And/or tax 

       

  Signed ……………………………………………………………………    Date …………………………………………  on behalf of …………………………………………………………………………………………………………………     UB/11  

Page 25: ESTATES OFFICE OPERATIONS DEPARTMENTAL  · PDF file6. TENDERING PROCEDURE Page 2 of 25 University of Bristol Issue Date Estates Operations October 2010 6

6.  TENDERING PROCEDURE 

Page 25 of 25 University of Bristol    Issue Date Estates Operations    October 2010

         

UNIVERSITY OF BRISTOL  

ADDED VALUE SUBMISSION    

PROJECT NO: ………………………………………..        TENDER DATE: ………………………    List below Papers submitted in response to Value assessment questions included in the tender documents plus any additional supporting evidence or material included for consideration in the tender evaluation process.   LIST:                     CONTRACTOR: ………………………………………………………………………………………………………………………………….  SIGNATURE: ……………………………………     NAME: …………………………………………..  DATE: ……………………….  UB/12