ESH Program Status. Steve Hoey NSLS-II ESH Manager Conventional Facilities Advisory Committee Review November 9-10, 2009. Agenda. Best in Class Goal 9/30/09 Construction Accident ESH Program Elements Construction Risks & Controls IAO Assessment. - PowerPoint PPT PresentationTRANSCRIPT
1 BROOKHAVEN SCIENCE ASSOCIATES
ESH Program Status
Steve HoeyNSLS-II ESH Manager
Conventional Facilities Advisory Committee ReviewNovember 9-10, 2009
2 BROOKHAVEN SCIENCE ASSOCIATES
Agenda
• Best in Class Goal
• 9/30/09 Construction Accident
• ESH Program Elements
• Construction Risks & Controls
• IAO Assessment
3 BROOKHAVEN SCIENCE ASSOCIATES
Project ESH Vision – “Best in Class”• A strong ESH program is essential to the safety of the workers
and the successful completion of the project• We believe all accidents and injuries are preventable and we
strive to establish an injury free work environment • ESH is being fully integrated into the project and managed as
tightly as quality, cost, and schedule• We are committed to a strong Integrated Safety Management
System for the project• Safe working conditions and practices are an absolute
requirement for all staff and contractors
4 BROOKHAVEN SCIENCE ASSOCIATES
Plan to Achieve “Vision”• Build on successful ISM/EMS/OHSAS programs and make use of lessons
learned from recent BNL & DOE construction activities (SNS, CFN, RSB)
• Clearly establish and articulate expectations via the Project Construction ESH Plan, ESH Management Plan, Request for Proposal & daily interface with contractor
• Select contractors who have demonstrated excellent safety performance and are committed to continuous improvement
• Flow down expectations to sub-contractors
• Partner with the contractor and subs to assure success
• Hold contractor accountable for performance
• Adequately staff construction safety oversight
5 BROOKHAVEN SCIENCE ASSOCIATES
Description of Accident
On Wednesday, September 30, 2009, at approximately 8:45 AM, a contractor laborer working at the NSLS-II construction site was struck by a load of rebar steel resulting in a compound fracture of the lower right leg below the knee.
The contractor was transported to a local area hospital for treatment. The treatment of the injured party has gone well and a full recovery is anticipated. He was released from the hospital on Oct 6.
6 BROOKHAVEN SCIENCE ASSOCIATES
Immediate Actions on Day of Accident
• Stand-down of construction site to inform staff of the event• Suspension of all rebar mechanical material handling
activities involving a Lull• Management walk down of site• A post-incident fact-finding meeting was conducted• Charge written and membership identified for an
independent construction safety investigation team to perform a thorough investigation, determine causal factors, identify corrective actions, and make recommendations
7 BROOKHAVEN SCIENCE ASSOCIATES
Immediate Corrective Actions• Conducted on-site (retraining session for mechanical material handling and
instituted specific PHA’s for rebar material handling• Torcon required concrete subcontractor (Macedos) to bring a full-time field safety
superintendent• BNL senior management met with Torcon senior management on Oct 6 to discuss
expectations for safety and further corrective actions• Torcon Corporate Safety Manager is on-site full-time to support development of
Torcon corrective action plan & supplement on-site ESH Mgr until such a time that second full time field safety inspector can be identified
• Instituted daily meetings between Torcon field and safety staff and NSLS-II safety and construction management staff
• NSLS-II is accelerating the hiring an additional full-time construction safety engineer to supplement the two currently on site
• Torcon meeting with union Business Managers to convey ESH expectations and training/qualification requirements
8 BROOKHAVEN SCIENCE ASSOCIATES
Ring Building Construction ESH Program• Pro-active ESH program elements for this project
• 851 compliant Occupational Med Program (credited with saving one life thus far)
• On-site medical professional >50 workers (EMT)– The EMT was the first responder to incident and provided immediate care
• Detailed worker ESH orientation (Bi-lingual)• Worker Safety Committee – represents each sub, meets weekly• Routine tool box safety meetings• Routine third party insurance evaluations (Liberty Mutual & Zurich)• Internal & External Audit/Assessment program• Routine ESH Meeting including contractor, BHSO, Lab CSE, and SME’s• Contractor Controlled Insurance Program (CCIP)
9 BROOKHAVEN SCIENCE ASSOCIATES
Site Work Controls
• All work performed in accordance with BNL’s SBMS:• Under an approved Permit or the GC Safety Health and
Environment program– Site access permits for general access– Rad work permit for soil monitoring
• Specific SOP, e.g, equipment inspection, safety inspections• Torcon Project ESH Site Specific Program
– Meets BNL’s “model” program– Defines elements such as inspections, tool box mtgs, industrial
hygiene monitoring, Occ Med program etc– Phase Hazard Analysis developed to identify and control hazards
10 BROOKHAVEN SCIENCE ASSOCIATES
Construction ESH Plan
• The GC was required to submit a written ESH Plan for review and approval before work began. Plan consistent with the requirements established in the NSLS-II Construction Project ESH Plan (model plan)
• Plan ensures that;• Personnel possess the necessary experience, skills and training• Resources are effectively allocated to address ESH considerations• Hazards are evaluated prior to work• Engineering or administrative controls are in place• Line management responsibilities are clear• Clear and unambiguous lines of authority and responsibility for assuring ESH
compliance• Plan was reviewed and approved by Project, Lab and BHSO
Site HASP template upgraded to mimic NSLS-II model
11 BROOKHAVEN SCIENCE ASSOCIATES
ESH Management Plan for Construction
• “ESH Management Plan for Construction” has been developed to;• Define specific roles, responsibilities and reporting
mechanisms of project, contractor, DOE and Lab oversight staff.
• Establishes “call down” procedure for emergencies • Establishes reporting criteria • Identifies key procedures for construction site (i.e., daily
construction inspection, stop work etc)
12 BROOKHAVEN SCIENCE ASSOCIATES
Site Access, Security & Orientation• Contractor access is via main gate, down
Princeton Ave directly to site. (peak population 300-350)
• Analysis done in conjunction with Security to evaluate traffic flow and contingencies• Concluded main gate could handle flow and peaks• Early arrival and departure of contractors
• Site is fully fenced, access is via South end of site (some utility work beyond fence)
• CVO & Badging moved to construction site trailer eliminates 3 stops.
• Restrictive policy for authorized access• These controls have been working well
13 BROOKHAVEN SCIENCE ASSOCIATES
On-Site Safety Coverage• Continuous coverage by NSLS-II Construction Safety Engineers and Torcon
Safety Manager• Daily visits by NSLS-II ES&H Manager (increased since accident)• Weekly visits by Lab Construction Safety Engineer (increased since accident)• Periodic visits by NSLS-II Project Director, Assistant Project Director and
other NSLS-II & lab management• Weekly visits by BHSO CSE (Increased since accident)• Periodic visits by Liberty Mutual and Zurich Insurance• 2 time/week concrete sub Risk Manager site visits• Changes due to accident include;
• full time concrete sub field safety inspection and Torcon addition of full time field safety inspector
• Project is in the process of adding a third CSE
14 BROOKHAVEN SCIENCE ASSOCIATES
Emergency Response•Covered by Torcon Safety Health and Environment Program
•BNL developed Local Emergency Plan required by SBMS
•Torcon and BNL LEP are coordinated
•Assignment of Local Emergency Coordinators (BNL)
•Construction site muster points
•Shelter in place (Building 735)
•Project specific call down process to notify management and DOE
•Pre- Emergency Planning was a significant positive factor in the accident
15 BROOKHAVEN SCIENCE ASSOCIATES
Environmental ControlsEnhanced environmental controls, all equipment parked on hard surface or tarped.
Perimeter silt fencing
16 BROOKHAVEN SCIENCE ASSOCIATES
NSLS-II Specific ES&H Procedures
• Adopted from existing Plant Engineering Program:• Heavy Equipment Inspection• Rigging Inspection• Safety Inspections• Site Access for Visitors and Guests• Stop Work and Work Interruptions• Permits• Heat Stress• Reporting of Events• Construction Safety Audits (new since accident)
- Controlled documents
17 BROOKHAVEN SCIENCE ASSOCIATES
Category Description Risk Ranking ManagementESH Design
(ESH-02)
Major change driven by ESH design Oversight or changing regulation (ring bldg and tech equipment)
LOW Formal Design Reviews; SME input; Extensive use of Lessons Learned
ESH Site Prep
(ESH-Low-01)
Legacy contamination identified during excavation, protected species impacting construction
LOW Extensive site evaluation; Monitoring of protected species
ESH Construction
(ESH-01)
Minor or major injury or mishap, conventional construction, R&D Ops through technical equipment installation
HIGH ESH Construction Plan (HASP); Contractor Pre-qualification; Safety Incentive; Dedicated CSE’s, contractor qualification; work planning & control
ESH Risk Analysis & Management
18 BROOKHAVEN SCIENCE ASSOCIATES
Site Prep – Legacy Issues•Remnants of a known 1978-81 geothermal/solar experiment unearthed during excavation on 5/6.
•Glycol pumped out and cleared by NYDEC
•Undocumented (pre-BNL) tank discovered on 5/19.
•20-25 gallons pumped out (kerosene and water)
•Contaminated soil remediated approximately 20-25 yards
•NYDEC approved remediation and cleared site
Historical Artifacts discovered and preserved
19 BROOKHAVEN SCIENCE ASSOCIATES
Site Prep - Migratory BirdsKilldeer & Canadian Geese have begun nesting on site
NYS Fish and Wildlife are called in to remove Killdeer nests BNL Licensed to remove Geese nests
Eggs
20 BROOKHAVEN SCIENCE ASSOCIATES
Project Safety Record
Hours Worked
Recordable Cases
Recordable Rate
TRCTARGET
DART Cases
Dart Rate
DART TARGET
NSLS-II Pre FY09
341,101 0 0 0 0
NSLS-II FY09 Hours
320,396 1 .62 .65 0 0 .25
Contractor 60,208 3 9.96 1.5 2 6.64 .6
Total Project to Date
661,497 4 1.21 .65 2 .60 .25
Injury Data
21 BROOKHAVEN SCIENCE ASSOCIATES
Description:Sub-Contractor employee to ModSpace (Sub to Torcon the NSLS-II Ring Building Contractor) was descending from a eight foot step ladder after taking measurements to install an outside seal between two trailer sections. The worker missed the fourth step of the ladder and fell to the ground landing upright on his right foot. The worker was descending facing the ladder and not carrying any equipment, the ladder was on stable ground. He sustained a fractured right heel as a result of this fall. The contractor had recently gone through Contractor Vendor Orientation and the Torcon site specific training which both address ladder safety.
Cause: > The worker missed the fourth step on the ladder as he was descending facing the ladder
Location: NSLS-II Project Site
Injury : Fractured Right Heel
DART Case & Occurrence NSLS-II Project April 16, 2009
Accidents – April 2009
Corrective Actions: > The General Contractor conducted a tool box safety talk on this incident> CVO training and the Torcon site indoctrination will discuss this incident> Increased surveillance by Torcon of all site activities> Incident will negatively impact Torcon’s safety incentive for period one (3/09-3/10)
Contractor Injury
DART Injury
NSLS-II Project
April 16, 2009
22 BROOKHAVEN SCIENCE ASSOCIATES
Contractor Injury
Description:Sub-Contractor employee (Hink Electric) was unloading conduit elbow pieces from a supply truck. He was carrying a conduit on his right shoulder to a pallet located on the ground. As he started bending down to place the conduit on the pallet, his right foot slipped in the sandy soil causing him to lose control of conduit which slipped down lower to the ground. The piece landed on the pallet, flipped up on the elbow, and the end of the conduit struck him in the mouth. He sustained a cut lip and chipped tooth. This is an OSHA Recordable due to the chipped (fractured) tooth. Cause:> Lost footing on loose soil
Location: NSLS-II Project Site
Injury : Cut Lip & Chipped Tooth
Recordable InjuryNSLS-II Project July 16, 2009
Accidents – July 2009
Corrective Actions:> Special meeting of the project Safety Committee was held to discuss lessons learned.> The General Contractor conducted a tool box safety talk on this incident> Re-evaluated the worksite to assure that ramps and walkways are properly established
23 BROOKHAVEN SCIENCE ASSOCIATES
Construction Hazard Controls
Site 6’ Fall Projection Rule
Material handling approved lifting fixtures & tag lines
24 BROOKHAVEN SCIENCE ASSOCIATES
Construction Hazard Controls
Rebar caps or rails used on all potential impalement hazards and horizontal protrusions
Mandatory PPE, Hard Hat, Safety Glasses, Safety Shoes & high visibility shirts/vests
25 BROOKHAVEN SCIENCE ASSOCIATES
Construction Hazard Controls
Ramps and defined access into formed areas
26 BROOKHAVEN SCIENCE ASSOCIATES
Construction Hazard Controls
Defined Walkways provide safe access & egress from work areas
27 BROOKHAVEN SCIENCE ASSOCIATES
Construction Hazard Controls
Dedicated Laborer’s for improved housekeeping
28 BROOKHAVEN SCIENCE ASSOCIATES
Independent Audit & Oversight
• Laboratory Director has commissioned BNL Independent Audit and Oversight to conduct a “Construction Safety Program Review” for NSLS-II
• SME’s from IA&O, ESH Directorate, Liberty Mutual• Three Phases
• Phase One – Review of documentation and requirements - Complete• Phase Two – Field Observations of training, tool box mtgs, qualifications
etc. - Complete• Phase Three – Field Observations of work in progress and compliance
to plans and management observations - Ongoing• Phase one began 6/2009 – Phase three complete 11/09• Will continue periodic site visits by Liberty Mutual