esby gymnasium and recreation center hvac … · esby gymnasium and recreation center hvac study...
TRANSCRIPT
ESBY GYMNASIUM AND ESBY GYMNASIUM AND ESBY GYMNASIUM AND ESBY GYMNASIUM AND RECREATION CENTER HVAC RECREATION CENTER HVAC RECREATION CENTER HVAC RECREATION CENTER HVAC STUDYSTUDYSTUDYSTUDY
Presented to:
MARCH 7, 2014
Presented by:
Burns Engineering, Inc.
TABLE OF CONTENTS
TABLE OF CONTENTS ................................................................................................................................ i
1.0 EXECUTIVE SUMMARY ................................................................................................................. 1
2.0 INTRODUCTION............................................................................................................................ 2
3.0 RECREATION CENTER - WORKOUT AREAS .................................................................................... 2
3.1 EXISTING CONDITIONS ............................................................................................................. 2
3.2 SYSTEM SIZING AND EVALUATION ............................................................................................ 3
3.3 RECOMMENDATIONS ............................................................................................................... 3
4.0 RECREATION CENTER - GYMNASIUM ............................................................................................ 4
4.1 EXISTING CONDITIONS ............................................................................................................. 4
4.2 SYSTEM SIZING AND EVALUATION ............................................................................................ 5
4.3 RECOMMENDATIONS ............................................................................................................... 6
5.0 ESBY GYMNASIUM ....................................................................................................................... 7
5.1 EXISTING CONDITIONS ............................................................................................................. 7
5.2 SYSTEM SIZING AND EVALUATION ............................................................................................ 7
5.3 RECOMMENDATIONS ............................................................................................................... 8
APPENDICIES
APPENDIX A – HVAC LOAD CALCULATION SUMMARY SHEETS
APPENDIX B – CONCEPTUAL HVAC EQUIPMENT CUTSHEET
APPENDIX C - CONCEPTUAL HVAC EQUIPMENT SKETCHES SKM-1 AND SKM-2
APPENDIX C – ORDER OF MAGNITUDE COST ESTIMATES
Rowan University REPORT
Esby Gymnasium and Recreation Center HVAC Study MARCH 7, 2014
1
1.0 EXECUTIVE SUMMARY
Rowan University engaged Burns Engineering to perform a study to evaluate existing temperature and
humidity control issues in the Esby and Recreation Center Gymnasiums as well as in the aerobics and
free weight rooms on the second floor of the Recreation Center.
The Aerobics Area/Free Weights Room HVAC system was determined to be undersized and has
inadequate ventilation air as does the Esby Gymnasium HVAC System. While the total capacity of the
three AHUs serving the Rec Center gymnasium are adequate, neither the Rec Center units (Unitary
Water Source Heat Pumps (WSHPs)) nor the constant volume, 2-pipe Air Handling Units (AHUs) provide
the humidity control necessary for the high latent and variable occupant loads common for health club
and gymnasium type spaces. Additional concerns regarding the existing two pipe changeover systems
were noted as a 100 gpm booster pump that was originally furnished with an incorrectly sized Heat
Exchanger is installed in series with the larger 200gpm dual temperature pumps and is currently not
energized.
To address both ventilation and humidity control problems prevalent in all three spaces we recommend
the following:
• Rec Center (Aerobics Room/Free Weights): Replace existing WSHPs with new packaged rooftop,
water cooled heat pump. Unit should include Variable Air Volume (VAV) fan control, modulating
compressors and modulating hot gas reheat as well as energy recovery. CO2 sensors should also
be included to control ventilation air amounts. Order of Magnitude Cost: $265,000
• Rec Center Gymansium: Replace (3) modular AHUs with new units of similar size. New units
should include VAV system to allow for passive dehumidification during part load conditions.
Order of Magnitude Cost: $190,000
• Esby Gymansium: Replace (2) constant volume AHUs with (1) new rooftop AHU with 2 pipe
changeover coil. New unit should include VAV to allow for passive dehumidification during part
load conditions and an energy recovery wheel. Add CO2 sensors to control ventilation air
amounts. Order of Magnitude Cost: $330,000
Refer to Appendix C for breakdown of costs. Evaluation of the roof structure, electrical capacity required
and any modifications required to the hydronic systems to accommodate the increase in load were not
evaluated as part of this study and should be investigated further.
If the two pipe changeover pumps, piping or heat exchangers are required to be replaced to
accommodate the increase in load, the University should investigate converting the system over to a
four pipe system as the current two pipe system does not allow for easy changeover from heating to
cooling during the shoulder months. A four pipe system would also allow for reheat in the Rec Center
and Gymnasium AHUs to provide active humidity control though this would require steam in the
summer months. Other methods of active dehumidification such as series dessicant wheels or recovery
of condenser water heat from the water source heat pumps for reheat could also be considered.
Rowan University REPORT
Esby Gymnasium and Recreation Center HVAC Study MARCH 7, 2014
2
2.0 INTRODUCTION
Rowan University engaged Burns Engineering to perform a study to evaluate existing temperature and
humidity control issues in the Esby and Recreation Center Gymnasiums as well in the aerobics and free
weight rooms on the second floor of the Recreation Center.
Both the Rec Center Gymnasium (1994) and Esby Gymnasium (1961) suffer from high humidity and
warmer than expected temperatures. HVAC units for both spaces are served by a two pipe, heating and
cooling changeover system. Chilled water supply serving both buildings is from a plate and frame heat
exchanger and constant speed pump located in the Rec Center basement with the cold side of the heat
exchanger supplied from the campus chilled water loop. The workout areas on the second floor are
served by Water Source Heat Pumps (WSHPs). Condenser water for the WSHPs is also supplied through
a plate and frame heat exchanger located in the basement of the Rec Center Gym with the heat rejected
to the campus chilled water loop. The cold side of the two (2) plate and frame heat exchangers are
arranged in series with incoming campus chilled water supply flowing through the first heat exchanger
serving the 2 pipe system (43EWT-48LWT) and then through the second heat exchanger to remove the
heat rejected from the WSHPs (48EWT).
The Rec Center and Esby Gymnasiums also contain Natatoriums, racquetball courts, locker rooms and
administrative spaces that are not included in the scope of this study. The findings and observations
discussed in the following sections are based on Burns visual inspection of the HVAC systems during our
site visits on 1/29/14.
3.0 RECREATION CENTER - WORKOUT AREAS
3.1 EXISTING CONDITIONS
The aerobics and free weight rooms (9,500sf) in the Rec Center contain treadmills, resistance
training machines, free weights and other equipment typical to a health club type occupancy.
Cooling is provided by seven (7) WSHPs varying from 3 to 3.5 tons of total capacity. The condenser
water loop rejects its heat to the campus chilled water system as described above. A 100% Outside
Air, Heating and Ventilating (H&V) Unit provides ventilation air to these spaces as well as the
adjacent racquetball courts. While the ventilation air is directly connected to the return ductwork of
the WSHPs serving the racquetball courts, the ventilation supply to the units serving the workout
areas is discharged into the ceiling return plenum and is not directly coupled with the units.
It is our understanding that these areas have experienced both high temperature and humidity
issues. In attempts to remedy the situation, the University has added solar reducing tint to the
windows and skylights and has recently replaced the WSHPs in kind with little result.
Rowan University REPORT
Esby Gymnasium and Recreation Center HVAC Study MARCH 7, 2014
3
3.2 SYSTEM SIZING AND EVALUATION
Burns reviewed the original building architectural and engineering drawings by Daniel F. Tulley
Associates (1991). The exterior walls were brick exterior with an air gap, 6 inches of batt insulation
and gypsum board finish on the interior. Windows appeared to be double pane insulated glass and
had since been furnished with solar reducing tint. Roof construction consists of metal deck and 3
inches of rigid insulation. Occupant Density was modeled based on data logged by the University for
maximum occupancy in the workout areas at 200 people. Based on these parameters and design
internal summer conditions of 75F/60%max RH, we calculated the following performance
requirements using Carrier’s Hourly Analysis Software (HAP) and compared the results to the
existing equipment capacities (See Appendix B for Load Calc Summary Pages):
• Aerobics/Weight Room: 13,500 cfm @ 60 Tons Total Coil Load (0.59 SHR)
o Ventilation Air Required: 4,570cfm based on 200 people (2009 IMC)
• Existing Units Total: 9,750cfm @ 23 Tons Total Coil Load
o Ventilation Air: 1,500cfm
It was determined that the existing units are undersized based on a peak occupancy during a design
cooling day. Even if sized properly, however, this type of unitary equipment is not adequate for the
variable occupancies or high latent loads of a health club environment. This is because with constant
volume units and single stage compressors, the cooling cycle is either on or off. Since HVAC
equipment predominantly operates at part load conditions most of the year, the compressors cycle
on and off and as they cycle off, they lose their ability to dehumidify the air. On a mild day with
limited sensible load from the outside but maximum occupants working out inside sweating, the
compressors would cycle on and off to maintain space temperature only, though humidity control
would still be required. Exacerbating the problem is that cooling coils are most inefficient at
dehumidification when they startup because the dewpoint temperature of the coil hasn’t dropped
low enough to effectively dehumidify the air. Frequent cycling doesn’t allow time for the cooling
coils to operate in the lower temperature range necessary for humidity control. Also, as the supply
fan continues to run, any condensation that does form on the coil is reabsorbed by the
unconditioned air and the condensed water effectively returned back to the space to be
dehumidified twice.
The ventilation air quantity is also inadequate based on the anticipated space occupancy and in
compliance with current codes (2009 International Mechanical Code (IMC)). The ventilation
effectiveness of the existing air quantity is also questionable since it is not directly coupled with the
units.
3.3 RECOMMENDATIONS
Burns determined that replacing the existing system “in kind” with larger capacity unitary heat
pumps was not appropriate for this type of occupancy for the reasons describe above. It is also our
Rowan University REPORT
Esby Gymnasium and Recreation Center HVAC Study MARCH 7, 2014
4
understanding that the existing units are already difficult to maintain above the ceiling with mimial
maintenance access to the components due to clearances with the structural steel.
Therefore we recommend a packaged rooftop heat pump to serve the workout areas of both
spaces. We recommend that the unit be Variable Air Volume(VAV), with a modulating compressor
and modulating hot gas reheat coil for humidity control. CO2 sensors and demand controlled
ventilation (DCV) is required by ASHRAE 90.1-2007 for spaces with an occupant density above 40
people/1000sf such as a health club environment.
The VAV system will help to provide passive dehumidification to the space by reducing the supply
airflow volume during part load conditions. Since the cooling coil is still active, dehumidification is
still being performed as opposed to a constant volume system with On-Off control of the
compressor. The modulating compressor keeps the compressor running at part load conditions to
avoid compressor cycling as described above. Though this approach alone would only provide
“passive” dehumidification since the unit will be running to maintain space temperature setpoint
only, a modulating hot gas reheat coil recycles waste heat from the compressor and would allow for
active humidity control by using hot refrigerant gas from the compressor to reheat the air for both
precise temperature and humidity control. Reheat is allowed by ASHRAE 90.1-2007 where system
airflows can be reduced by 50%(or to the minimum ventilation rate whichever is greater) or is
provided by site recovered energy as with the hot gas reheat approach. Due to the high latent load
of the space, a low leaving wetbulb temperature is also required (51F, refer to Appendix B load
calcs) to increase the latent capacity of the supply air. While it is not part of the scope of this report,
the condenser water heat exchanger, pumps and piping system will need to be evaluated to verify
they can accommodate the increased heat rejection load (appx. 50 gpm increase at equivalent delta
T). An energy recovery wheel was included in the preliminary equipment selections to limit the
increase to the condenser water loop.
Evaluation of the roof structure, the increased electrical capacity required for the new unit and the
adequacy of the condenser water loop was not evaluated as part of this study and should be
investigated further during preliminary design.
4.0 RECREATION CENTER - GYMNASIUM
4.1 EXISTING CONDITIONS
The Rec Center Gymnasium (24,000sf) is a 30 foot tall structure and contains multiple basketball
courts on the first floor and has a running track and concourse area for access to the racquetball
courts and adjacent spaces on the second floor. Cooling is provided by three (3) modular air
handling units hung in the ceiling of the gym with 2 pipe changeover coil for heating/cooling. Return
air for the center unit is in the ceiling of the second floor concourse area while return air for the two
end units are at the court level which is typical for air distribution with a high bay ceiling. The units
are 6,000 cfm each (1,500cfm OA) and are arranged for economizer control (free cooling). Three (3)
Rowan University REPORT
Esby Gymnasium and Recreation Center HVAC Study MARCH 7, 2014
5
6,000cfm exhaust fans in the gym roof provide exhaust during economizer control, with (1) fan
running during normal operation. The 2 pipe changeover loop is supplied by a plate and frame heat
exchanger in the summer as described above with heat supplied from a separate heat exchanger
supplied by the campus steam loop.
Heat from the Electrical Equipment Room 136 and Storage Room 134 is exhausted into the
gymnasium at 3,000cfm.
It is our understanding that these areas have experienced both high temperature and humidity
issues in the summer.
4.2 SYSTEM SIZING AND EVALUATION
Burns reviewed the original building architectural and engineering drawings by Daniel F. Tulley
Associates (1991). The exterior walls for the gymnasium are a face brick exterior with 2 inches of
rigid insulation and CMU on the interior. Windows and skylights appeared to be double pane
insulated glass with solar reducing tint. Roof construction consists of metal deck and 3 inches of rigid
insulation. Occupant Density was assumed to be approximately 50 people on the basketball courts
and 20 people on the track level above at a high activity level. Based on these parameters, including
the 3,000cfm of exhaust from adjacent equipment spaces and design internal summer conditions of
75F/60%max RH, we calculated the following performance requirements using Carrier’s Hourly
Analysis Software (HAP) and compared the results to the existing equipment capacities (See
Appendix B for Load Calc Summary Pages):
• Rec Center Gym: 18,250 cfm @ 60 Tons Total Coil Load (0.65 SHR)
o Ventilation Air Required: 7,200cfm based on 0.30cfm/sf for gym areas (2009 IMC)
• Existing Units Total: 18,000cfm @ 60 Tons Total Coil Load
o Ventilation Air: 4,500cfm
It was determined that the existing units appear to be sized adequately for the total coil load,
however, the constant volume two pipe changeover system does not provide adequate humidity
control of the space during part load conditions. As described above for the WSHPs, a constant
volume AHU with a chilled water coil will operate in much the same way during part load conditions.
The chilled water coil will begin to shutdown to match the space temperature setpoint regardless if
humidity control is still required. As chilled water flow to the coil is reduced because the space
temperature is satisfied, the leaving coil temperature increases. This increase in dewpoint of the coil
and wetbulb temperature of the supply air effects the dehumidification capacity of the system. A
two pipe changeover system can also make things difficult during the shoulder months because
once the system is turned over to heating, cooling may no longer be available but humidity control is
still required.
The ventilation air quantity would be inadequate based on current codes (2009 IMC), however, the
ventilation rates may have complied with code at the time of construction.
Rowan University REPORT
Esby Gymnasium and Recreation Center HVAC Study MARCH 7, 2014
6
It is also our understanding that when the series plate and frame heat exchangers were first
installed that the heat exchanger for the 2 pipe changeover system was undersized and did not
account for the 2 pipe changeover coils added to the Esby Gymansium H&V units. This was
confirmed by our review of the Concord Engineering drawing M-201 (2006) which had the building
chilled water flow scheduled at 110gpm/11deg delta T (56EWT-45LWT) and the primary chilled
water supply at 240gpm/5deg delta T (42EWT-47LWT). A new plate and frame heat exchanger was
furnished and installed in late 2012/early 2013 with minimal effect. We reviewed the JJ White HX
submittal (dated 10-10-12) and verified that the new HX-1 had the building chilled water flow
scheduled at 185gpm/12deg delta T (56EWT-44LWT) and the primary chilled water supply at
240gpm/11deg delta T (43EWT-54LWT). Based on our review of the original Daniel F. Tulley
Drawings H-6 and H-8 (1991), the scheduled chilled water flow required to the Rec Center and Esby
Gym 2 pipe changeover system is actually 216gpm/12 deg delta T (44EWT-56LWT), a 16%
difference between the scheduled flows of the HX-1 and the building chilled water demands.
Additionally, Concord Engineering drawing M-201 notes an 110gpm circulation pump labeled P-1
that is not noted in the Scope of Work from JJ White to be dual temperature pumps P-3 and P-4
noted on the Tulley design drawings and rated at 200gpm. Series pumping usually involves two
pumps at similar flow rates to boost the total head of the system. If the original booster pump was
sized on an incorrect flowrate, it may be limiting the system flow due to its installation in series with
the larger building pumps.
4.3 RECOMMENDATIONS
Based on our evaluation described above it appears that the air handling equipment serving the
space is sized adequetley for the space loads of the Rec Center Gymnasium at peak conditions,
however, the constant volume system provides no means for humidity control at part load
conditions. Also, various descrepancies between original design chilled water temperatures and
flows raise questions regarding the current system operation and balancing.
We recommend the following: (1) Rowan verify the system balancing and analyze the two pipe
changeover system hydraulics to verify that the existing building pumps are adequately sized for the
scheduled flow and pressure drop and if the in-line circulation pump is required or should be
resized. (2) The three (3) modular AHUs serving the Rec Center gymansium be replaced with VAV,
two pipe units. By varying the airlow in relation to space temperature instead of the chilled water
flow, the system supply air temperature remains low or even lower during partload conditions
allowing for passive dehumidification. The existing AHUs serving the space are now approximately
20 years old and nearing the end of their useful life. If the heating/cooling system was converted to
a 4 pipe system, reheat could be added for active humidity control in the space. Lowering the
supply air temperature can further increase the latent capacity of the new units but should be
reviewed with the hydronic system modifications required.
Demand controlled ventilation is not required for this gym since there is no spectator seating and
therefore not a high occupant density.
Rowan University REPORT
Esby Gymnasium and Recreation Center HVAC Study MARCH 7, 2014
7
5.0 ESBY GYMNASIUM
5.1 EXISTING CONDITIONS
The Esby Gymnasium (25,500sf) is a 30 foot tall structure and contains multiple basketball courts
similar to the Rec Center Gymansium. The gym can be divided into two separate sections: Courts
1&2(17,600sf) and Courts 3&4 (7,920sf) by a fabric moveable partition. The larger courts 1&2 also
contain fixed bleacher seating for spectators during recreational activities such as NCAA Div. III
Basketball games. Cooling is provided by two (2) Air Handling Units (AHUs) in a penthouse
mechanical room adjacent to the courts. The units appear to have been replaced in kind in 1991
with the construction of the Rec Center while the return fans are original construction. The units are
essentially replacements of the original H&V units containing steam preheat coils with 2 pipe
changeover coils for heating/cooling added in the discharge ductwork of both units. AHU-1 serves
Esby Gym courts 3&4 and is 7,500cfm. AHU-4 serves Esby Gym courts 1&2 and is 13,000cfm.
Supply air is distributed at the roof level with low return grilles to limit stratification in the high bay
space. Return air is then distributed via direct buried transite piping below the gymnasium slab and
up through a shaft to the penthouse mechanical room. Existing ventilation rates were not scheduled
for the cooling coils but based on the cooling coil selection of 80F entering air temperature, a 30%
outside air amount can be assumed (91.5F design outdoor/75F indoor). The 2 pipe changeover loop
is supplied by a plate and frame heat exchanger as described in the Section 2.0 above.
Six (6) auxiliary rooftop exhaust fans are sized for 38,400cfm (6400cfm ea.) for Courts 1&2 and four
(4) fans at 22,400cfm (5600cfm ea.) for Courts 3&4. These appear to have been sized for appx
2.5cfm/sf or 12 air changes per hour (ACH) for summer ventilation with direct makeup coming from
the outside or adjacent spaces.
It is our understanding that these areas have experienced both high temperature and humidity
issues in the summer.
5.2 SYSTEM SIZING AND EVALUATION
Burns reviewed the original building engineering drawings by Kelly and Gruzen (1961). The exterior
walls for the gymnasium are similar to the Rec Center with a face brick exterior and CMU on the
interior. No Windows or skylights are installed in this gym and the roof construction was assumed to
be consistent with the Rec Center. Occupant Density was based on the maximum number of
spectators/occupants that could occupy the fixed bleacher seating (1380people) at a seated activity
level. Ventilation requirements were calculated by dividing the court into two zones: (1) spectator
area and (2) play area for calculation of the outside air requirements in conformance with current
codes. Based on these parameters, and design internal summer conditions of 75F/60%max RH, we
calculated the following performance requirements using Carrier’s Hourly Analysis Software (HAP)
and compared the results to the existing equipment capacities (See Appendix B for Load Calcs):
Rowan University REPORT
Esby Gymnasium and Recreation Center HVAC Study MARCH 7, 2014
8
• Esby Gym: 20,100 cfm @ 100 Tons Total Coil Load(0.60 SHR)
o Ventilation Air Required: 17,000cfm based on 0.30cfm/sf for gym area and 1380
people for the spectator area (2009 IMC)
• Existing Units Total: 20, 500cfm @ 58 Tons Total Coil Load
o Ventilation Air: 6,150cfm (based on 30%OA)
It was determined that the supply air volume from the Esby Gym units appears adequate for the
space sensible loads (the increase in total load for the new unit is related to the increased load from
the higher ventilation air quantity required) but the constant volume system with two pipe
changeover coils offer no means for humidity control at part load conditions as described in
previous sections. We also noted that since the cooling coils were retrofitted into the existing
discharge ductwork that abrupt transitions prior to and after the coil may also be reducing their
effectiveness along with the potential hydronic flow concerns noted in Section 4 above.
The ventilation rate is also inadequate. When the system was originally designed the auxiliary roof
exhaust fans would run to furnish additional ventilation air in the summer or the H&V unit would
operate at 100% outside air during the winter as the heating coils are adequately sized for this
arrangement. When mechanical cooling was added, however, the ventilation requirements for the
space during the summer were never addressed and the cooling coils sized for only 30%OA as noted
above. Running the exhaust fans during the summer to increase ventilation to the space would only
increase infiltration of unconditioned and humid air leading to condensation. The gymnsium should
be maintained at a slightly positive pressure to its surrounding environment to limit infiltration from
the outdoors as well as its proximity to the Natatorium which should be maintained negative to its
surrounding environment.
5.3 RECOMMENDATIONS
We recommend that a new VAV, two pipe rooftop unit AHU be installed to replace the two existing
20 year old constant volume units. The new VAV unit will allow for passive dehumidification during
part load conditions. Due to the occupant loading on the bleachers, the system requires almost 80%
Outside Air(OA). An energy recovery wheel is required by code due to the high ventilation air
volume as is Demand Controlled Ventilation. One unit was selected in lieu of two as was originally
designed for cost savings.
The existing rooftop exhaust fans should be removed as the new AHU would provide the full
ventilation requirements to the space. Due to the increase in load, the chilled water system flow will
be required to increase by appx. 40gpm to the Esby gym. The incoming chilled water piping and
Heat Exchangers should also be evaluated to verify they can accommodate the additional load
though conversion of the system to a 4 pipe system would allow for the addition of reheat and
therefore active humdity control in the space. Lowering the supply air temperature can further
increase the latent capacity of the new unit but should be reviewed with the hydronic system
modifications required.
Rowan University REPORT
Esby Gymnasium and Recreation Center HVAC Study MARCH 7, 2014
9
APPENDIX A – HVAC LOAD CALCULATION SUMMARY SHEETS
Air System Sizing Summary for Aerobics/FreeWeights CombinedProject Name: 2014-015_Rowan_RecCenter 03/03/2014 Prepared by: Burns Engineering, Inc. 03:43PM
Air System Information Air System Name Aerobics/FreeWeights Combined Equipment Class PKG ROOF Air System Type CAV/RH
Number of zones 1Floor Area 9500.0 ft²Location Philadelphia IAP, Pennsylvania
Sizing Calculation Information Zone and Space Sizing Method: Zone CFM Sum of space airflow rates Space CFM Individual peak space loads
Calculation Months Jan to DecSizing Data Calculated
Central Cooling Coil Sizing Data Total coil load 60.9 Tons Total coil load 730.5 MBH Sensible coil load 431.4 MBH Coil CFM at Jul 1400 13306 CFM Max block CFM 13306 CFM Sum of peak zone CFM 13306 CFM Sensible heat ratio 0.591 ft²/Ton 156.1 BTU/(hr-ft²) 76.9 Water flow @ 10.0 °F rise N/A
Load occurs at Jul 1400OA DB / WB 91.5 / 74.9 °FEntering DB / WB 82.5 / 69.7 °FLeaving DB / WB 52.4 / 51.6 °FCoil ADP 49.1 °FBypass Factor 0.100Resulting RH 60 %Design supply temp. 58.0 °FZone T-stat Check 1 of 1 OKMax zone temperature deviation 0.0 °F
Central Heating Coil Sizing Data Max coil load 215.0 MBH Coil CFM at Dec 1000 13306 CFM Max coil CFM 13306 CFM Water flow @ 20.0 °F drop 21.51 gpm
Load occurs at Dec 1000BTU/(hr-ft²) 22.6Ent. DB / Lvg DB 51.0 / 65.9 °F
Supply Fan Sizing Data Actual max CFM 13306 CFM Standard CFM 13292 CFM Actual max CFM/ft² 1.40 CFM/ft²
Fan motor BHP 0.00 BHPFan motor kW 0.00 kWFan static 0.00 in wg
Outdoor Ventilation Air Data Design airflow CFM 4570 CFM CFM/ft² 0.48 CFM/ft²
CFM/person 22.85 CFM/person
Hourly Analysis Program v4.61 Page 1 of 11
Zone Sizing Summary for Aerobics/FreeWeights CombinedProject Name: 2014-015_Rowan_RecCenter 03/03/2014 Prepared by: Burns Engineering, Inc. 03:43PM
Air System Information Air System Name Aerobics/FreeWeights Combined Equipment Class PKG ROOF Air System Type CAV/RH
Number of zones 1Floor Area 9500.0 ft²Location Philadelphia IAP, Pennsylvania
Sizing Calculation Information Zone and Space Sizing Method:
Zone CFM Sum of space airflow rates Space CFM Individual peak space loads
Calculation Months Jan to DecSizing Data Calculated
Zone Sizing Data
Maximum Design Minimum Time Maximum Zone Cooling Air Air of Heating Floor
Sensible Flow Flow Peak Load Area ZoneZone Name (MBH) (CFM) (CFM) Load (MBH) (ft²) CFM/ft²
Zone 1 238.5 13040 13040 Aug 1400 109.4 9500.0 1.37
Zone Terminal Sizing Data
Reheat Zone Zone Reheat Coil Htg Htg Mixing
Coil Water Coil Water Box Fan
Load gpm Load gpm AirflowZone Name (MBH) @ 20.0 °F (MBH) @ 20.0 °F (CFM)
Zone 1 278.2 - 0.0 - 0
Space Loads and Airflows
Cooling Time Air Heating Floor Zone Name / Sensible of Flow Load Area Space Space Name Mult. (MBH) Load (CFM) (MBH) (ft²) CFM/ft²
Zone 1
Aerobics/Fitness Room 1 187.3 Aug 1400 10212 89.9 6900.0 1.48
Free Weights Room 1 51.9 Sep 1400 2828 19.5 2600.0 1.09
Hourly Analysis Program v4.61 Page 2 of 11
Ventilation Sizing Summary for Aerobics/FreeWeights CombinedProject Name: 2014-015_Rowan_RecCenter 03/03/2014 Prepared by: Burns Engineering, Inc. 03:43PM
1. Summary Ventilation Sizing Method Sum of Space OA Airflows Design Ventilation Airflow Rate 4570 CFM
2. Space Ventilation Analysis Table Floor Maximum Required Required Required Required Uncorrected Area Maximum Supply Air Outdoor Air Outdoor Air Outdoor Air Outdoor Air Outdoor Air
Zone Name / Space Name Mult. (ft²) Occupants (CFM) (CFM/person) (CFM/ft²) (CFM) (% of supply) (CFM)
Zone 1
Aerobics/Fitness Room 1 6900.0 145.0 10212.3 20.00 0.06 0.0 0.0 3314.0
Free Weights Room 1 2600.0 55.0 2827.6 20.00 0.06 0.0 0.0 1256.0
Totals (incl. Space Multipliers) 13039.9 4570.0
Hourly Analysis Program v4.61 Page 3 of 11
Air System Design Load Summary for Aerobics/FreeWeights CombinedProject Name: 2014-015_Rowan_RecCenter 03/03/2014 Prepared by: Burns Engineering, Inc. 03:43PM
DESIGN COOLING DESIGN HEATING
COOLING DATA AT Jul 1400 HEATING DATA AT DES HTG COOLING OA DB / WB 91.5 °F / 74.9 °F HEATING OA DB / WB 11.0 °F / 8.6 °F
Sensible Latent Sensible LatentZONE LOADS Details (BTU/hr) (BTU/hr) Details (BTU/hr) (BTU/hr)
Window & Skylight Solar Loads 1643 ft² 77728 - 1643 ft² - -
Wall Transmission 1727 ft² 1439 - 1727 ft² 5934 -
Roof Transmission 9175 ft² 7075 - 9175 ft² 24401 -
Window Transmission 1318 ft² 12073 - 1318 ft² 53732 -
Skylight Transmission 325 ft² 2977 - 325 ft² 13250 -
Door Loads 0 ft² 0 - 0 ft² 0 -
Floor Transmission 0 ft² 0 - 0 ft² 0 -
Partitions 900 ft² 3786 - 900 ft² 2144 -
Ceiling 0 ft² 0 - 0 ft² 0 -
Overhead Lighting 9500 W 17282 - 0 0 -
Task Lighting 0 W 0 - 0 0 -
Electric Equipment 0 W 0 - 0 0 -
People 200 99725 218000 0 0 0
Infiltration - 0 0 - 0 0
Miscellaneous - 0 0 - 0 0
Safety Factor 5% / 5% 11104 10900 10% 9946 0
>> Total Zone Loads - 233188 228900 - 109407 0
Zone Conditioning - 245476 228900 - 59240 0
Plenum Wall Load 23% 981 - 0 0 -
Plenum Roof Load 70% 16508 - 0 0 -
Plenum Lighting Load 30% 9724 - 0 0 -
Return Fan Load 13306 CFM 0 - 13306 CFM 0 -
Ventilation Load 4570 CFM 67369 70152 4570 CFM 217078 0
Supply Fan Load 13306 CFM 0 - 13306 CFM 0 -
Space Fan Coil Fans - 0 - - 0 -
Duct Heat Gain / Loss 2% 4664 - 2% 2188 -
>> Total System Loads - 344722 299052 - 278506 0
Central Cooling Coil - 431438 299053 - 0 0
Central Heating Coil - -86716 - - 0 -
Terminal Reheat Coils - 0 - - 278221 -
>> Total Conditioning - 344722 299053 - 278221 0
Key: Positive values are clg loads Positive values are htg loads Negative values are htg loads Negative values are clg loads
Hourly Analysis Program v4.61 Page 4 of 11
Air System Sizing Summary for Rec Center GymProject Name: 2014-015_Rowan_RecCenter 02/18/2014 Prepared by: Burns Engineering, Inc. 11:58AM
Air System Information Air System Name Rec Center Gym Equipment Class CW AHU Air System Type SZCAV
Number of zones 1Floor Area 24000.0 ft²Location Philadelphia IAP, Pennsylvania
Sizing Calculation Information Zone and Space Sizing Method: Zone CFM Sum of space airflow rates Space CFM Individual peak space loads
Calculation Months Jan to DecSizing Data Calculated
Central Cooling Coil Sizing Data Total coil load 58.8 Tons Total coil load 705.1 MBH Sensible coil load 460.1 MBH Coil CFM at Jul 1400 18257 CFM Max block CFM 18257 CFM Sum of peak zone CFM 18257 CFM Sensible heat ratio 0.653 ft²/Ton 408.5 BTU/(hr-ft²) 29.4 Water flow @ 10.0 °F rise 141.09 gpm
Load occurs at Jul 1400OA DB / WB 91.5 / 74.9 °FEntering DB / WB 82.1 / 69.7 °FLeaving DB / WB 58.7 / 57.7 °FCoil ADP 56.1 °FBypass Factor 0.100Resulting RH 59 %Design supply temp. 58.0 °FZone T-stat Check 1 of 1 OKMax zone temperature deviation 0.0 °F
Central Heating Coil Sizing Data Max coil load 829.4 MBH Coil CFM at Des Htg 18257 CFM Max coil CFM 18257 CFM Water flow @ 20.0 °F drop 82.99 gpm
Load occurs at Des HtgBTU/(hr-ft²) 34.6Ent. DB / Lvg DB 46.3 / 88.4 °F
Supply Fan Sizing Data Actual max CFM 18257 CFM Standard CFM 18237 CFM Actual max CFM/ft² 0.76 CFM/ft²
Fan motor BHP 0.00 BHPFan motor kW 0.00 kWFan static 0.00 in wg
Outdoor Ventilation Air Data Design airflow CFM 7200 CFM CFM/ft² 0.30 CFM/ft²
CFM/person 102.86 CFM/person
Hourly Analysis Program v4.61 Page 1 of 10
Zone Sizing Summary for Rec Center GymProject Name: 2014-015_Rowan_RecCenter 02/18/2014 Prepared by: Burns Engineering, Inc. 11:58AM
Air System Information Air System Name Rec Center Gym Equipment Class CW AHU Air System Type SZCAV
Number of zones 1Floor Area 24000.0 ft²Location Philadelphia IAP, Pennsylvania
Sizing Calculation Information Zone and Space Sizing Method:
Zone CFM Sum of space airflow rates Space CFM Individual peak space loads
Calculation Months Jan to DecSizing Data Calculated
Zone Sizing Data
Maximum Design Minimum Time Maximum Zone Cooling Air Air of Heating Floor
Sensible Flow Flow Peak Load Area ZoneZone Name (MBH) (CFM) (CFM) Load (MBH) (ft²) CFM/ft²
Zone 1 328.1 17892 17892 Jul 1400 378.1 24000.0 0.75
Zone Terminal Sizing DataNo Zone Terminal Sizing Data required for this system.
Space Loads and Airflows
Cooling Time Air Heating Floor Zone Name / Sensible of Flow Load Area Space Space Name Mult. (MBH) Load (CFM) (MBH) (ft²) CFM/ft²
Zone 1 Rec Center Gym 1 328.1 Jul 1400 17892 378.1 24000.0 0.75
Hourly Analysis Program v4.61 Page 2 of 10
Ventilation Sizing Summary for Rec Center GymProject Name: 2014-015_Rowan_RecCenter 02/18/2014 Prepared by: Burns Engineering, Inc. 11:58AM
1. Summary Ventilation Sizing Method Sum of Space OA Airflows Design Ventilation Airflow Rate 7200 CFM
2. Space Ventilation Analysis Table Floor Maximum Required Required Required Required Uncorrected Area Maximum Supply Air Outdoor Air Outdoor Air Outdoor Air Outdoor Air Outdoor Air
Zone Name / Space Name Mult. (ft²) Occupants (CFM) (CFM/person) (CFM/ft²) (CFM) (% of supply) (CFM)
Zone 1
Rec Center Gym 1 24000.0 70.0 17891.7 0.00 0.30 0.0 0.0 7200.0
Totals (incl. Space Multipliers) 17891.7 7200.0
Hourly Analysis Program v4.61 Page 3 of 10
Air System Design Load Summary for Rec Center GymProject Name: 2014-015_Rowan_RecCenter 02/18/2014 Prepared by: Burns Engineering, Inc. 11:58AM
DESIGN COOLING DESIGN HEATING
COOLING DATA AT Jul 1400 HEATING DATA AT DES HTG COOLING OA DB / WB 91.5 °F / 74.9 °F HEATING OA DB / WB 11.0 °F / 8.6 °F
Sensible Latent Sensible LatentZONE LOADS Details (BTU/hr) (BTU/hr) Details (BTU/hr) (BTU/hr)
Window & Skylight Solar Loads 955 ft² 74845 - 955 ft² - -
Wall Transmission 9533 ft² 14843 - 9533 ft² 40499 -
Roof Transmission 23232 ft² 59713 - 23232 ft² 61787 -
Window Transmission 187 ft² 1713 - 187 ft² 7623 -
Skylight Transmission 768 ft² 7035 - 768 ft² 31308 -
Door Loads 0 ft² 0 - 0 ft² 0 -
Floor Transmission 23000 ft² 0 - 23000 ft² 9435 -
Partitions 900 ft² 3786 - 900 ft² 2144 -
Ceiling 0 ft² 0 - 0 ft² 0 -
Overhead Lighting 24000 W 62371 - 0 0 -
Task Lighting 0 W 0 - 0 0 -
Electric Equipment 0 W 0 - 0 0 -
People 70 34904 76300 0 0 0
Infiltration - 53302 47492 - 190953 0
Miscellaneous - 0 0 - 0 0
Safety Factor 5% / 5% 15625 6190 10% 34375 0
>> Total Zone Loads - 328135 129982 - 378124 0
Zone Conditioning - 332971 129982 - 369567 0
Plenum Wall Load 0% 0 - 0 0 -
Plenum Roof Load 0% 0 - 0 0 -
Plenum Lighting Load 0% 0 - 0 0 -
Return Fan Load 18257 CFM 0 - 18257 CFM 0 -
Ventilation Load 7200 CFM 120530 115023 7200 CFM 452313 0
Supply Fan Load 18257 CFM 0 - 18257 CFM 0 -
Space Fan Coil Fans - 0 - - 0 -
Duct Heat Gain / Loss 2% 6563 - 2% 7562 -
>> Total System Loads - 460064 245005 - 829442 0
Central Cooling Coil - 460064 245014 - 0 0
Central Heating Coil - 0 - - 829442 -
>> Total Conditioning - 460064 245014 - 829442 0
Key: Positive values are clg loads Positive values are htg loads Negative values are htg loads Negative values are clg loads
Hourly Analysis Program v4.61 Page 4 of 10
Air System Sizing Summary for Esby Gym CombinedProject Name: 2014-015_Rowan_RecCenter 02/26/2014 Prepared by: Burns Engineering, Inc. 04:34PM
Air System Information Air System Name Esby Gym Combined Equipment Class CW AHU Air System Type SZCAV
Number of zones 1Floor Area 25545.0 ft²Location Philadelphia IAP, Pennsylvania
Sizing Calculation Information Zone and Space Sizing Method: Zone CFM Sum of space airflow rates Space CFM Individual peak space loads
Calculation Months Jan to DecSizing Data Calculated
Central Cooling Coil Sizing Data Total coil load 98.4 Tons Total coil load 1181.3 MBH Sensible coil load 702.6 MBH Coil CFM at Aug 1500 20066 CFM Max block CFM 20066 CFM Sum of peak zone CFM 20066 CFM Sensible heat ratio 0.595 ft²/Ton 259.5 BTU/(hr-ft²) 46.2 Water flow @ 10.0 °F rise 236.39 gpm
Load occurs at Aug 1500OA DB / WB 92.0 / 75.0 °FEntering DB / WB 89.5 / 73.7 °FLeaving DB / WB 57.0 / 55.9 °FCoil ADP 53.4 °FBypass Factor 0.100Resulting RH 60 %Design supply temp. 58.0 °FZone T-stat Check 1 of 1 OKMax zone temperature deviation 0.0 °F
Central Heating Coil Sizing Data Max coil load 1222.6 MBH Coil CFM at Des Htg 20066 CFM Max coil CFM 20066 CFM Water flow @ 20.0 °F drop 122.33 gpm
Load occurs at Des HtgBTU/(hr-ft²) 47.9Ent. DB / Lvg DB 20.1 / 76.6 °F
Supply Fan Sizing Data Actual max CFM 20066 CFM Standard CFM 20044 CFM Actual max CFM/ft² 0.79 CFM/ft²
Fan motor BHP 0.00 BHPFan motor kW 0.00 kWFan static 0.00 in wg
Outdoor Ventilation Air Data Design airflow CFM 16952 CFM CFM/ft² 0.66 CFM/ft²
CFM/person 11.94 CFM/person
Hourly Analysis Program v4.61 Page 1 of 12
Zone Sizing Summary for Esby Gym CombinedProject Name: 2014-015_Rowan_RecCenter 02/26/2014 Prepared by: Burns Engineering, Inc. 04:34PM
Air System Information Air System Name Esby Gym Combined Equipment Class CW AHU Air System Type SZCAV
Number of zones 1Floor Area 25545.0 ft²Location Philadelphia IAP, Pennsylvania
Sizing Calculation Information Zone and Space Sizing Method:
Zone CFM Sum of space airflow rates Space CFM Individual peak space loads
Calculation Months Jan to DecSizing Data Calculated
Zone Sizing Data
Maximum Design Minimum Time Maximum Zone Cooling Air Air of Heating Floor
Sensible Flow Flow Peak Load Area ZoneZone Name (MBH) (CFM) (CFM) Load (MBH) (ft²) CFM/ft²
Zone 1 352.8 19664 19664 Jul 1500 142.9 25545.0 0.77
Zone Terminal Sizing DataNo Zone Terminal Sizing Data required for this system.
Space Loads and Airflows
Cooling Time Air Heating Floor Zone Name / Sensible of Flow Load Area Space Space Name Mult. (MBH) Load (CFM) (MBH) (ft²) CFM/ft²
Zone 1
Esby Gym - 1&2 1 97.2 Jul 1400 5298 79.7 13200.0 0.40
Esby -1&2 Spectator Area 1 199.4 Jan 1500 10872 0.0 4425.0 2.46
Esby Gym - 3&4 1 64.1 Jul 1400 3494 63.2 7920.0 0.44
Hourly Analysis Program v4.61 Page 2 of 12
Ventilation Sizing Summary for Esby Gym CombinedProject Name: 2014-015_Rowan_RecCenter 02/26/2014 Prepared by: Burns Engineering, Inc. 04:34PM
1. Summary Ventilation Sizing Method Sum of Space OA Airflows Design Ventilation Airflow Rate 16952 CFM
2. Space Ventilation Analysis Table Floor Maximum Required Required Required Required Uncorrected Area Maximum Supply Air Outdoor Air Outdoor Air Outdoor Air Outdoor Air Outdoor Air
Zone Name / Space Name Mult. (ft²) Occupants (CFM) (CFM/person) (CFM/ft²) (CFM) (% of supply) (CFM)
Zone 1
Esby Gym - 1&2 1 13200.0 20.0 5298.3 0.00 0.30 0.0 0.0 3960.0
Esby -1&2 Spectator Area 1 4425.0 1380.0 10871.7 7.50 0.06 0.0 0.0 10615.5
Esby Gym - 3&4 1 7920.0 20.0 3494.3 0.00 0.30 0.0 0.0 2376.0
Totals (incl. Space Multipliers) 19664.4 16951.5
Hourly Analysis Program v4.61 Page 3 of 12
Air System Design Load Summary for Esby Gym CombinedProject Name: 2014-015_Rowan_RecCenter 02/26/2014 Prepared by: Burns Engineering, Inc. 04:34PM
DESIGN COOLING DESIGN HEATING
COOLING DATA AT Aug 1500 HEATING DATA AT DES HTG COOLING OA DB / WB 92.0 °F / 75.0 °F HEATING OA DB / WB 11.0 °F / 8.6 °F
Sensible Latent Sensible LatentZONE LOADS Details (BTU/hr) (BTU/hr) Details (BTU/hr) (BTU/hr)
Window & Skylight Solar Loads 0 ft² 0 - 0 ft² - -
Wall Transmission 12270 ft² 16667 - 12270 ft² 55168 -
Roof Transmission 21120 ft² 47324 - 21120 ft² 56170 -
Window Transmission 0 ft² 0 - 0 ft² 0 -
Skylight Transmission 0 ft² 0 - 0 ft² 0 -
Door Loads 0 ft² 0 - 0 ft² 0 -
Floor Transmission 21120 ft² 0 - 21120 ft² 12046 -
Partitions 2730 ft² 11668 - 2730 ft² 6504 -
Ceiling 0 ft² 0 - 0 ft² 0 -
Overhead Lighting 20691 W 58643 - 0 0 -
Task Lighting 0 W 0 - 0 0 -
Electric Equipment 0 W 0 - 0 0 -
People 1420 195818 209200 0 0 0
Infiltration - 0 0 - 0 0
Miscellaneous - 0 0 - 0 0
Safety Factor 5% / 5% 16506 10460 10% 12989 0
>> Total Zone Loads - 346625 219660 - 142877 0
Zone Conditioning - 352820 219660 - 143785 0
Plenum Wall Load 0% 0 - 0 0 -
Plenum Roof Load 0% 0 - 0 0 -
Plenum Lighting Load 0% 0 - 0 0 -
Return Fan Load 20066 CFM 0 - 20066 CFM 0 -
Ventilation Load 16952 CFM 294540 259033 16952 CFM 1076002 0
Supply Fan Load 20066 CFM 0 - 20066 CFM 0 -
Space Fan Coil Fans - 0 - - 0 -
Duct Heat Gain / Loss 2% 6933 - 2% 2858 -
>> Total System Loads - 654293 478693 - 1222645 0
Central Cooling Coil - 702634 478694 - 0 0
Central Heating Coil - -48341 - - 1222645 -
>> Total Conditioning - 654293 478694 - 1222645 0
Key: Positive values are clg loads Positive values are htg loads Negative values are htg loads Negative values are clg loads
Hourly Analysis Program v4.61 Page 4 of 12
Rowan University REPORT
Esby Gymnasium and Recreation Center HVAC Study MARCH 7, 2014
10
APPENDIX B – CONCEPTUAL HVAC EQUIPMENT CUTSHEETS
2425 South Yukon Ave - Tulsa, Oklahoma 74107-2728 - Ph. (918) 583-2266 Fax (918) 583-6094AAONEcat32 Ver. 4.212 (SN: 5728272-VE5U3BHT)
1A
1B
1C
1D
2
3
4
5A
5B
5C 6A
6B
6C
7
8
9
10
11
12
13
14A
14B
15
16
17
18
19
20
21
22
23
R N- 040-3- 0-E7 09 -000 :FGFF- Q0 B-DL L- 0BA- 0D 0B00 Z- 00-0B0 00 0MAB Tag: RTU# 1 Rev A
Job Information Unit Information
Job Name: Approx. Op./Ship Weights: Job Number: Supply CFM/ESP: Site Altitude: Refrigerant
Final-Filter FV / Qty: Exhaust CFM/ESP/TSP: Outside CFM: Ambient Temperature: Return Temperature:
Rowan University 7316 / 7316 lbs. (±5%)Job #1527 13306 / 2 in. wg.0 ftR-410A
415.81 fpm / 813306 / 1.00 / 1.96 in. wg.457095 ºF DB / 78 ºF WB75 ºF DB / 62 ºF WB
Static Pressure
External: Economizer: Evaporator: Heating: Filters Clean: Cabinet: Dirt Allowance Heatwheel: Re-Heat Coil Total:
2.00 in. wg. 0.21 in. wg.0.51 in. wg. 0.00 in. wg.0.19 in. wg. 0.13 in. wg.0.35 in. wg. 0.56 in. wg.0.08 in. wg. 3.47 in. wg.
Cooling Section Heating Section(**)
Gross Net Equivalent Total Capacity: Total Capacity: Sensible Capacity: Latent Capacity: HW Total Cooling Capacity: Mixed Air Temp: Entering Air Temp: Lv Air Temp (Coil): Lv Air Temp (Unit) Digital Comp. Capacity Ratio: Supply Air Fan: SA Fan RPM / Width: Exhaust Air Fan: EA Fan RPM / Width:
Evaporator Coil: Evaporator Face Velocity: Energy Recovery Wheel:
667.00 MBH 636.70 MBH454.66 424.36 MBH343.27 312.97 MBH111.39 MBH212.34 MBH76.35 ºF DB 63.60 ºF WB76.35 ºF DB 63.60 ºF WB52.14 ºF DB 51.40 ºF WB54.22 ºF DB 52.29 ºF WB100%1 x 300D @ 11.07 BHP1312 / 6.810"2 x RM270 @ 3.09 BHP1048 / 6.130"
32.1 ft² / 4 Rows / 14 FPI414.0 fpm2 x ERC-5245
Primary Heat Type: Total Equivalent Capacity: Total Capacity: OA Temp: RA Temp: Entering Air Temp: Leaving Air Temp:
Heat Pump852.8 MBH614.1 MBH10.0 DB / 9.0ºF WB70.0 ºF DB / 55.0 ºF WB66.0 DB / 52.5 ºF WB114.8 DB / 69.8ºF WB
Auxiliary Heat Type: Heating CFM: Fan Temp Rise:
No Heat 115712.1 ºF
Re-Heat Coil: Capacity: 257 MBH LA DB / WB: 70.00 ºF / 58.58 ºF RH: 51%
Water Side Performance: Cooling Flow Rate: Cooling PD - Heat Exchanger: Cooling PD - Pipe, Valves, etc: Cooling Ent. / Lv. Water Temp: Heating Flow Rate: Heating PD - Heat Exchanger: Heating PD - Pipe, Valves, etc: Heating Ent. / Lv. Water Temp:
Max Operating Pressure :
108 gpm8.68 ft15.36 ft85 / 95.3 ºF108 gpm8.68 ft15.36 ft68 / 58.81 ºF 125 psig
Rating Information
Application EER @ Op. Conditions: 14.8 Application COPH @ Op. Conditions: 5.11
Electrical Data
Rating: Minimum Circuit Amp: Unit FLA: Maximum Overcurrent:
460/3/60 109104 125
Qty HP VAC Phase RPM FLA RLA Compressor 1: 2 460 3 16.7 Compressor 2: 2 460 3 16.7 Supply Fan: 1 15.00 460 3 1760 21.0 Exhaust Fan: 2 5.00 460 3 1760 7.6 Heatwheel: 2 0.1667 460 1 1760 0.6
Cabinet Sound Power Levels*
Octave Bands: 63 125 250 500 1000 2000 4000 8000
Unit Rating
Date Created/Modified: 2/10/2014 11:46:10 AM Using Ver 4.212 (OSN# 5728272) Date Printed: 2/20/2014 4:05:40 PM
REC CENTER (AEROBICS/FREE WEIGHT ROOMS)
Discharge LW(dB): 93 93 96 97 94 90 86 79 Return LW(dB): 87 86 81 77 80 79 78 78 *Sound power levels are given for informational purposes only. The sound levels are not guaranteed. (**)Fan motor temperature rise is not included in the heat capacity and temps.
Unit Rating
Date Created/Modified: 2/10/2014 11:46:10 AM Using Ver 4.212 (OSN# 5728272) Date Printed: 2/20/2014 4:05:40 PM
2425 South Yukon Ave - Tulsa, Oklahoma 74107-2728 - Ph. (918) 583-2266 Fax (918) 583-6094AAONEcat32 Ver. 4.212 (SN: 5728272-VE5U3BHT)
1A
1B
1C
1D
2
3
4
5A
5B
5C 6A
6B
6C
7
8
9
10
11
12
13
14A
14B
15
16
17
18
19
20
21
22
23
R N- 040-3- 0-E7 09 -000 :FGFF- Q0 B-DL L- 0BA- 0D 0B00 Z- 00-0B0 00 0MAB Tag: RTU# 1 Rev A
Job Name Rowan University Heat Wheel Type: TotalJob Number Job #1527 Heat Wheel Model: ERC-5245Site Altitude 0' Heat Wheel Qty: 2
Summer Conditions Bypass: 0 CFM
Mixed Air Damper Supply Air HW Outside Air
13306 CFM 4570 CFM 4570 CFM76.35 ºF DB 78.93 ºF DB 78.93 ºF 95.00 ºF DB63.60 ºF WB 66.50 ºF WB 66.50 ºF 78.00 ºF WB67.71 gr/lb 77.79 gr/lb 118.01 gr/lbReturn Air From Space Exhaust Air
8736 CFM 4570 CFM
75.00 ºF DB 91.08 ºF 91.08 ºF DB62.00 ºF WB 74.55 ºF 74.55 ºF WB62.44 gr/lb 102.66 gr/lb
13306 CFM Ex Bypass: 0 CFM
Cooling/Dehumidification Heating/Humidification
Total Capacity: 212.34 MBH 0.00 MBHSensible Capacity: 81.22 MBH 0.00 MBH
Latent Capacity: 131.12 MBH 0.00 MBH
Winter Conditions Bypass: 0 CFM
Mixed Air Damper Supply Air HW Outside Air
13306 CFM 4570 CFM 4570 CFM65.96 ºF DB 58.23 ºF DB 58.23 ºF 10.00 ºF DB52.51 ºF WB 47.40 ºF WB 47.40 ºF 9.00 ºF WB37.47 gr/lb 31.41 gr/lb 7.21 gr/lbReturn Air From Space Exhaust Air
8736 CFM 4570 CFM
70.00 ºF DB 21.78 ºF 21.78 ºF DB55.00 ºF WB 21.78 ºF 21.78 ºF WB40.64 gr/lb 16.45 gr/lb
13306 CFM Ex Bypass: 0 CFM
Cooling/Dehumidification Heating/Humidification
Total Capacity: 0.00 MBH 312.54 MBHSensible Capacity: 0.00 MBH 238.72 MBH
Latent Capacity: 0.00 MBH 73.82 MBH
Energy Wheel Rating
Date Created/Modified: 2/10/2014 11:46:10 AM Using Ver 4.212 (OSN# 5728272) Date Printed: 2/20/2014 4:05:40 PM
2425 South Yukon Ave - Tulsa, Oklahoma 74107-2728 - Ph. (918) 583-2266 Fax (918) 583-6094AAONEcat32 Ver. 4.212 (SN: 5728272-VE5U3BHT)
JOB INFORMATION: WHEEL SPECIFICATION: Job Name: Max RPM: Job Tag: Diameter x Qty: Rep Firm: CFM: Date: Tip Speed:
Inertia:
Rowan University 1,600RTU# 1 Rev A 30.0 in. x 1
1330602/20/2014 10,304 FPM
35 WR²
OPERATING CONDITIONS: MOTOR SELECTION: Air Flow: Rated HP / Bypass: Static Pressure: Frame Size: Relief Dampers DP: Nominal RPM:
VAC/PH/HZ: TSP: Efficiency Site Altitude: Enclosure Type: TSP @ Sea Level: Max Inertial Load:
13,306 CFM 15 / No3.47 in. Wg. 254T0.00 in. Wg. 1760
460/3/603.47 in. Wg. Premium / 0.930.00 Ft ODP3.47 in. Wg. 149 WR²
FAN PERFORMANCE: FAN SOUND POWER (Inlet/Outlet): RPM: Octave Band: (Re 10^-12 watts) BHP: 1 2 3 4 5 6 7 8 Efficiency: In/Out Velocity: Plenum Out Velocity: SOUND POWER A-Weighted: 93 / 100 dB
Max Duct SP with Blocked Airway: 1 in. Wg. @ 1312 rpm
131211.0765.7% 88 91 90 90 89 87 83 782240/2944 FPM 93 93 96 99 97 93 90 83150 FPM
RPM
BHP
SYSTEM
Efficiency
SP Surge
CFM Min
Supply Fan Model: 300D @ 1312 RPM and 100% WidthDesign Conditions: 13306 CFM @ 3.47" SP
CFM x 10001614121086420
SP
5
4
3
2
1
0
BH
P
26
24
22
20
18
16
14
12
10
8
6
4
2
0
60%
40%
20%
0%
RPM: 1312
BHP: 11.07
EFFICIENCY: 65.70
30.0" STAR Plenum
Date Created/Modified: 2/10/2014 11:46:10 AM Using Ver 4.212 (OSN# 5728272) Date Printed: 2/20/2014 4:05:40 PM
2425 South Yukon Ave - Tulsa, Oklahoma 74107-2728 - Ph. (918) 583-2266 Fax (918) 583-6094AAONEcat32 Ver. 4.212 (SN: 5728272-VE5U3BHT)
JOB INFORMATION: WHEEL SPECIFICATION: Job Name: Max RPM: Job Tag: Diameter x Qty: Rep Firm: CFM: Date: Tip Speed:
Inertia:
Rowan University 1,800RTU# 1 Rev A 27.4 in. x 2
665302/20/2014 7,518 FPM
14 WR²
OPERATING CONDITIONS: MOTOR SELECTION: Air Flow: Rated HP / Bypass: Static Pressure: Frame Size: Relief Dampers DP: Nominal RPM:
VAC/PH/HZ: TSP: Efficiency Site Altitude: Enclosure Type: TSP @ Sea Level: Max Inertial Load:
13,306 CFM 5 x 2 / No1.50 in. Wg. 184T0.46 in. Wg. 1760
460/3/601.96 in. Wg. Premium / 0.8950.00 Ft ODP1.96 in. Wg. 52 WR²
FAN PERFORMANCE: FAN SOUND POWER x 2 Fans (In/Out): RPM: Octave Band: (Re 10^-12 watts) BHP: 1 2 3 4 5 6 7 8 Efficiency: In/Out Velocity: Plenum Out Velocity: SOUND POWER A-Weighted: 90 / 93 dB
10483.0966.4% 86 85 83 82 82 82 81 811737/1818 FPM 88 87 92 91 89 87 84 81150 FPM
RPM
BHP
SYSTEM
Efficiency
SP Surge
CFM Min
Exhaust Fan Model: RM270 @ 1048 RPM and 100% WidthDesign Conditions: 6653 CFM @ 1.96" SP
CFM x 1000987654321
SP
2
1
0
BH
P
7
6
5
4
3
2
1
0
60%
40%
20%
0%
RPM: 1048
BHP: 3.09
EFFICIENCY: 66.35
27.0" STAR Plenum
Date Created/Modified: 2/10/2014 11:46:10 AM Using Ver 4.212 (OSN# 5728272) Date Printed: 2/20/2014 4:05:40 PM
2425 South Yukon Ave - Tulsa, Oklahoma 74107-2728 - Ph. (918) 583-2266 Fax (918) 583-6094AAONEcat32 Ver. 4.212 (SN: 5728272-VE5U3BHT)
1A
1B
1C
1D
2
3
4
5A
5B
5C 6A
6B
6C
7
8
9
10
11
12
13
14A
14B
15
16
17
18
19
20
21
22
23
R N- 040-3- 0-E7 09 -000 :FGFF- Q0 B-DL L- 0BA- 0D 0B00 Z- 00-0B0 00 0MAB Tag: RTU# 1 Rev A
Job Name: Rowan University Unit Submittal For: Burns-Joe Zagorski Job Number: Job #1527 Unit Submittal Date: February 10, 2014
Base Option Description
R Series Roof Top Unit
N Generation Ninth Generation
040 Unit Size Forty
3 Voltage 460V/3Ø/60Hz
0 Interior Protection Standard
E Refrigerant Style R-410A Variable Capacity Scroll Compressor (VCC)
7 Unit Configuration Water-Source/Geothermal Heat Pump
0 Coil Coating Standard
9 Cooling/Heat Pump Staging Modulating Heat Pump + No Auxiliary Heat - 2 VCC + 2 On/Off Comp.
0 Heating Type No Heating
0 Heating Designation No Heating
0 Heating Staging No Heating
Feature Option Description
F 1A. RA/OA Section AAONAIRE® Energy Recovery Wheel - Total + Low CFM
G 1B. RA/EA Blower Configuration 2 Blowers + Premium Efficiency Motors + 2 Motors on 2 VFDs
F 1C. RA/EA Blower 27" Backward Curved Plenum
F 1D. RA/EA Blower Motor 5.0 hp - 1760 rpm
Q 2. OA Control CO2 Override + Fully Modulating Actuator - Enthalpy Limit
0 3. Heat Options Standard
B 4. Maintenance Options 115V Convenience Outlet - Factory Wired
D 5A. SA Blower Configuration 1 Blower + Premium Efficiency Motor + 1 VFD
L 5B. SA Blower 30'' Direct Drive Backward Curved Plenum - 1600 rpm Max - Aluminum Wheel
L 5C. SA Motor 15 hp - 1760 rpm
0 6A. Pre Filter Type Standard - None
B 6B. Unit Filter Type 4" Pleated - 30% Eff
A 6C. Filter Options Clogged Filter Switch
0 7. Refrigeration Control Standard - Fixed 55°F Comp. Cooling Lock Out + 3 MTDR Comp. Off - Copeland Comfort Alert + Adjustable Comp. Heating L
D 8. Refrigeration Options Modulating Hot Gas Reheat
0 9. Refrigeration Accessories Standard
B 10. Power Options Power Switch - 150 amps
0 11. Safety Options Standard
0 12. Controls Standard
Z 13. Special Controls Constant Volume (CV) Heat Pump Unit Controller - CV Cool + CV Heat
0 14A. Preheat Configuration Standard - None
0 14B. Preheat Sizing Standard - None
0 15. Glycol Percent Water or No WSHP
B 16. Interior Cabinet Options Control Panel Service Lights
0 17. Exterior Cabinet Options Standard
0 18. Customer Code Standard
0 19. Code Options Standard - ETL U.S.A. Listing
0 20. Crating Standard
M 21. Water-Cooled Cond. Balancing Valves + Water Flow Switch + Head Pressure Control
A 22. Control Vendors Wattmaster Controls
B 23. Type Standard - Includes AAON Gray Paint
Unit Submittal
Date Created/Modified: 2/10/2014 11:46:10 AM Using Ver 4.212 (OSN# 5728272) Date Printed: 2/20/2014 4:05:40 PM
2425 South Yukon Ave - Tulsa, Oklahoma 74107-2728 - Ph. (918) 583-2266 Fax (918) 583-6094AAONEcat32 Ver. 4.212 (SN: 5728272-VE5U3BHT)
1A
1B
1C
1D
2
3
4
5A
5B
5C 6A
6B
6C
7
8
9
10
11
12
13
14A
14B
15
16
17
18
19
20
21
22
23
R N- 040-3- 0-E7 09 -000 :FGFF- Q0 B-DL L- 0BA- 0D 0B00 Z- 00-0B0 00 0MAB Tag: RTU# 1 Rev A Job Name: Rowan University VCMX For: Burns-Joe Zagorski Job Number: Job #1527 VCMX Date: February 10, 2014
Hardware Included For VCMX Controller
Part # Included Parts Assigned ChannelV07140 VCMX Controller with WSHP and EBUSP94320 Space Temp Sensor - Field Installed MainController\AI1R82890 Supply Air Temp Sensor - Field Installed MainController\AI2R81550 Outside Air Temp Sensor MainController\AI4R69190 VCMX Large Expansion ModuleR37030 Building Static Pressure Sensor LargeExpansionModule\AI4R34700 Outside Air Humidity Sensor LargeExpansionModule\AI1P62520 Proof of Flow Sensor LargeExpansionModule\BI3P62520 Dirty Filter Sensor LargeExpansionModule\BI2R34690 Space Humidity Sensor - Field Installed LargeExpansionModule\AI2V18330 WSHP ModuleR28390 Suction Pressure TransducerR28390 Suction Pressure TransducerR28390 Suction Pressure TransducerR28390 Suction Pressure TransducerR32960 Water Temp SensorR32960 Water Temp SensorR70490 Water Flow SwitchR70490 Water Flow SwitchR90230 VCMX Head Pressure ModuleR22020 Head Pressure SensorR22020 Head Pressure SensorR22020 Head Pressure SensorR22020 Head Pressure Sensor
1 2 3 4 5 6 7
VCMXControllerwith WSHPand EBUS
Analog In X X XAnalog Out X XBinary InRelay Out X X X X XDigital Sensor(s)
X
1 2 3 4 5 6 7 8VCMXLarge
ExpansionModule
Analog In X X XAnalog Out XBinary In X XRelay Out X X
VCMX Components
Date Created/Modified: 2/10/2014 11:46:10 AM Using Ver 4.212 (OSN# 5728272) Date Printed: 2/20/2014 4:05:41 PM
Date Created/Modified: 2/10/2014 11:46:10 AM Using Ver 4.212 (OSN# 5728272) Date Printed: 2/20/2014 4:05:41 PM
Date Created/Modified: 2/10/2014 11:46:10 AM Using Ver 4.212 (OSN# 5728272) Date Printed: 2/20/2014 4:05:41 PM
203 Gum Springs Road - Longview, TX 75602 - Ph. (903) 236-4403 Fax (903) 236-4463AAONEcat32 Ver. 4.214 (SN: 5728272-VE5U3BHT)
M2-H-014-R-3-A-B-0-C-0Tag: AHU-2 Rev C
Job Information Unit Information Job Name: Rowan University Unit Weight: 2847 lb (±5%) Job Number: Job #1527 Supply CFM/ESP: 6000 / 1" wg. Site Altitude: 0' ft Return CFM/ESP: 6000 / 1" wg.
Outside CFM: 2400 Exhaust CFM: 2400
Static Pressure (in. wg.) External: 1 SA / 1 EA Cooling Coil: 0.46 Heating Total: 0.06 Filters Clean: 0.12 Total: 2.84 SA Dirt Allowance: 0.2
Cooling Section Summer Ambient: 95.00 DB / 75.00 WB Summer Return: 75.00 DB / 62.00 WB
Total(MBTU)
Sens.(MBTU)
Lvg. AirDB(°F)
Lvg. AirWB(°F)
Consumption Ent.Fluid(°F)
Lvg.Fluid(°F)
FluidPD.
Duct 95.00 75.00 CFM: 2400Mixing Box 83.00 67.65 CFM: 2400 + 3600Chilled Water 243.4 179.2 54.62 53.89 48.00GPM 45.00 55.10 4.61 ft 14.38 ft²/6Row/08FPI/ F
2 1/8 OD Conn.Hot Water 189.3 189.3 82.99 64.20 21.00GPM 180 160.8 1.47 ft. 14.38 ft²/1Row/08FPI/ H
1 3/8 OD Conn.Supply Fan 85.50 65.03 18 "Blower @ 5.48 BHP / 2662RPM
Heating Section Winter Ambient: 10.00 DB / 9.00 WB Winter Return: 70.00 DB / 58.00 WB
Total(MBTU)
Sens.(MBTU)
Lvg. AirDB(°F)
Lvg. AirWB(°F)
Consumption Ent.Fluid(°F)
Lvg.Fluid(°F)
FluidPD.
Duct 10.00 9.00 CFM: 2400Mixing Box 46.00 42.47 CFM: 2400 + 3600Hot Water 202.7 75.89 55.65 21.00GPM 180 159.4 1.48 ft 14.38 ft²/1Row/08FPI/ H
1 3/8 OD Conn.
EER - ARI Listing Information No ARI rating program exists for this unit
Qty HP VAC Phase RPM FLA Supply Fan: 1 8 460 3 2800 8
Electrical Data Rating: 460V/3P/60Hz Min Circuit Amp: 10 Unit FLA: 8 Max Overcurrent: 15
Date Created/Modified (OSN# 5728272): 2/10/2014 11:46:10 AM (OSN# 5728272) Date Printed: 3/3/2014 1:45:59 PM
REC CENTER - GYMNASIUM
203 Gum Springs Road - Longview, TX 75602 - Ph. (903) 236-4403 Fax (903) 236-4463AAONEcat32 Ver. 4.214 (SN: 5728272-VE5U3BHT)
M2-H-014-R-3-A-B-0-C-0Tag: AHU-2 Rev C
Job Name: Rowan University Job Number: Job #1527 Site Altitude: 0' ft
Summer Conditions
Mixed Air (Supply) Mixing Box Outside Air
6000 CFM 2400 CFM83.00 °F DB 95.00 °F DB67.65 °F WB 75.00 °F WB77.09 gr/lb 99.01 gr/lb
Recirculating Air Exhaust AirFrom Space
3600 CFM 2400 CFM75.00 °F DB62.00 °F WB62.44 gr/lb 6000 CFM
Cooling/Dehumidification Heating/Humidification
Total Capacity: 0.00 MBH 0.00 MBHSensible Capacity: 0.00 MBH 0.00 MBH
Latent Capacity: 0.00 MBH 0.00 MBH
Winter Conditions
Mixed Air (Supply) Mixing Box Outside Air
6000 CFM 2400 CFM46.00 °F DB 10.00 °F DB42.47 °F WB 9.00 °F WB34.60 gr/lb 7.21 gr/lb
Recirculating Air Exhaust Air
From Space 2400 CFM3600 CFM
70.00 °F DB58.00 °F WB52.88 gr/lb 6000 CFM
Cooling/Dehumidification Heating/Humidification
Total Capacity: 0.00 MBH 0.00 MBHSensible Capacity: 0.00 MBH 0.00 MBH
Latent Capacity: 0.00 MBH 0.00 MBH
Date Created/Modified (OSN# 5728272): 2/10/2014 11:46:10 AM (OSN# 5728272) Date Printed: 3/3/2014 1:45:59 PM
2425 South Yukon Ave - Tulsa, Oklahoma 74107-2728 - Ph. (918) 583-2266 Fax (918) 583-6094AAONEcat32 Ver. 4.214 (SN: 5728272-VE5U3BHT)
JOB INFORMATION: WHEEL SPECIFICATION: Job Name: Max RPM: Job Tag: Diameter x Qty: Rep Firm: CFM: Date: Tip Speed:
Inertia:
Rowan University 2,750AHU-2 Rev C 17.8 in. x 1
600003/03/2014 12,426 FPM
3 WR²
OPERATING CONDITIONS: MOTOR SELECTION: Air Flow: Rated HP / Bypass: Static Pressure: Frame Size: Relief Dampers DP: Nominal RPM:
VAC/PH/HZ: TSP: Efficiency Site Altitude: Enclosure Type: TSP @ Sea Level: Max Inertial Load:
6,000 CFM 8 / N2.84 in. Wg. ECM0.00 in. Wg. 2750
460/3/602.84 in. Wg. Premium / 0.8550.00 Ft TEFC2.84 in. Wg. 45 WR²
*Please Contact Factory.
FAN PERFORMANCE: FAN SOUND POWER (Inlet/Outlet): RPM: Octave Band: (Re 10^-12 watts) BHP: 1 2 3 4 5 6 7 8 Efficiency: In/Out Velocity: Plenum Out Velocity: SOUND POWER A-Weighted: 93 / 96 dB
Max Duct SP with Blocked Airway: 7.3 in. Wg. @ 2662 rpm
26625.4849.0% 72 75 91 85 83 83 86 904082/4255 FPM 75 78 89 91 95 90 90 8768 FPM
RPM
BHP
SYSTEM
Efficiency
SP Surge
CFM Min
Supply Fan Model: 450AZ @ 2662 RPM and 100% WidthDesign Conditions: 6000 CFM @ 2.84" SP
CFM x 1000654321
SP
7
6
5
4
3
2
1
0
BH
P
12
11
10
9
8
7
6
5
4
3
2
1
0
60%
40%
20%
RPM: 2662
BHP: 5.48
EFFICIENCY: 49.04
18" EBM Plenum
Date Created/Modified (OSN# 5728272): 2/10/2014 11:46:10 AM (OSN# 5728272) Date Printed: 3/3/2014 1:45:59 PM
203 Gum Springs Road - Longview, TX 75602 - Ph. (903) 236-4403 Fax (903) 236-4463AAONEcat32 Ver. 4.214 (SN: 5728272-VE5U3BHT)
M2-H-014-R-3-A-B-0-C-0Tag: AHU-2 Rev C
Job Information Job Name: Rowan University Submittal for: Burns-Joe Zagorski Job Number: Job #1527 Submittal Date: March 03, 2014
Main Section DescriptionM2 Series Series 2 Modular Air Handler
H Unit Type Horizontal
014 Unit Size 5,000 - 7,700 CFM
R Air Flow Right Hand Flow
3 Voltage 460V/3P/60Hz
A Assembly Factory Assembled
B Wiring Control Wired in Control Box
0 Cabinet Standard - No Paint
C Base Rail 6 inches High
0 Special None
Module Section Code Description Weight (lbs ±5%)MBJ-101-A-A0-00000-00000-0-0 Top H-&V- Damper / Filter
Two Position Actuator2 " 30% Pleated Filter
438
TRA-102-0-00-00000-00000-0-0 Small Control 229
CLM-103-C-00-00000-608F0-S-0 Coil(opt. CW or DX)Chilled Water CoolingCool: 6 Row/08 FPI/Full 2 1/8 OD Conn.Stainless Steel Drain Pan
557
PHB-104-B-00-108H0-00000-0-0 Heating + Dehum. Heat: 1 Row/08 FPI/Half 1 3/8 OD Conn.
215
SDB-105-U-T0-G0000-00000-0-0 Direct Drive Supply8 hp Motor18 "BlowerEC Motor
1407
Total 2847
Date Created/Modified (OSN# 5728272): 2/10/2014 11:46:10 AM (OSN# 5728272) Date Printed: 3/3/2014 1:45:59 PM
Date Created/Modified (5728272): 2/10/2014 11:46:10 AM (OSN# 5728272) Date Printed: 3/3/2014 1:46:00 PM
2425 South Yukon Ave - Tulsa, Oklahoma 74107-2728 - Ph. (918) 583-2266 Fax (918) 583-6094AAONEcat32 Ver. 4.214 (SN: 5728272-VE5U3BHT)
1A
1B
1C
1D
2
3
4
5A
5B
5C 6A
6B
6C
7
8
9
10
11
12
13
14A
14B
15
16
17
18
19
20
21
22
23
R N- 065-3- 0-0W 0H -EHJ :UGSL- Q0 B-GV T- 0BA- 00 0A00 E- 00-0B0 00 00AB Tag: RTU# 3/4 Rev B
Job Information Unit Information
Job Name: Approx. Op./Ship Weights: Job Number: Supply CFM/ESP: Site Altitude: Final-Filter FV / Qty:
Exhaust CFM/ESP/TSP: Outside CFM: Ambient Temperature: Return Temperature:
Rowan University 9837 / 9837 lbs. (±5%)Job #1527 20066 / 1 in. wg.0 ft 229.33 fpm / 35
20066 / 1.00 / 2.09 in. wg.1695295 ºF DB / 78 ºF WB75 ºF DB / 62 ºF WB
Static Pressure
External: Economizer: Coil: Heating: Filters Clean: Cabinet: Dirt Allowance Heatwheel: Total:
1.00 in. wg. 0.07 in. wg.0.34 in. wg. 0.08 in. wg.0.06 in. wg. 0.12 in. wg.0.35 in. wg. 1.01 in. wg.
3.03 in. wg.
Cooling Section Heating Section
Gross Net Equivalent Total Capacity: Total Capacity: Sensible Capacity: Latent Capacity: HW Total Cooling Capacity: Mixed Air Temp: Entering Air Temp: Lv Air Temp (Coil): Lv Air Temp (Unit) Supply Air Fan: SA Fan RPM / Width: Exhaust Air Fan: EA Fan RPM / Width:
CW Coil: CW Face Velocity: Energy Recovery Wheel:
1507.08 MBH 1462.14 MBH872.06 827.12 MBH582.03 537.09 MBH290.04 MBH635.02 MBH81.24 ºF DB 67.98 ºF WB81.24 ºF DB 67.98 ºF WB53.75 ºF DB 53.26 ºF WB55.81 ºF DB 54.11 ºF WB2 x RNE330 @ 8.10 BHP Ea.988 / 7.265"2 x RNE330 @ 5.51 BHP Ea.869 / 7.490"
58.3 ft² / 6 Rows / 8 FPI344.0 fpm2 x ERC-6488C
PreHeat Type: Std (No Preheat)
Heating Type: Heating CFM: Total Capacity: OA Temp: RA Temp: Entering Air Temp: Leaving Air Temp: Entering Water: Leaving Water: GPM / Head: Water Velocity: FA / RD / FPI / FV:
Hot Water Heat20066613.6 MBH10.0 ºF DB / 9.0 ºF WB70.0 ºF DB / 55.0 ºF WB51.3 ºF DB / 43.4 ºF WB78.6 ºF DB / 55.3 ºF WB180.0 ºF160.6 ºF65 / 1.9 ft2.45 fps19.87 ft² / 1 / 8 / 505.0
Chilled Water Coils: GPM / Water PD (HXC only): Ent. / Lv. Water Temp: Water Velocity:
156 / 11.5 ft45 / 56.2 ºF3.37 fps
Electrical Data
Rating: Minimum Circuit Amp: Unit FLA: Maximum Overcurrent:
460/3/60 7973 90
Qty HP VAC Phase RPM FLA RLA Supply Fan: 2 10.00 460 3 1170 14.5 Exhaust Fan: 2 15.00 460 3 1760 21.0 Heatwheel: 2 0.25 460 1 1760 1.2
Cabinet Sound Power Levels*
Octave Bands: 63 125 250 500 1000 2000 4000 8000 Discharge LW(dB): 91 91 94 93 90 89 88 85 Return LW(dB): 83 83 80 77 81 80 78 76 *Sound power levels are given for informational purposes only. The sound levels are not guaranteed.
Unit Rating
Date Created/Modified: 2/10/2014 11:46:10 AM Using Ver 4.214 (OSN# 5728272) Date Printed: 3/3/2014 9:16:13 AM
ESBY GYMNASIUM
2425 South Yukon Ave - Tulsa, Oklahoma 74107-2728 - Ph. (918) 583-2266 Fax (918) 583-6094AAONEcat32 Ver. 4.214 (SN: 5728272-VE5U3BHT)
1A
1B
1C
1D
2
3
4
5A
5B
5C 6A
6B
6C
7
8
9
10
11
12
13
14A
14B
15
16
17
18
19
20
21
22
23
R N- 065-3- 0-0W 0H -EHJ :UGSL- Q0 B-GV T- 0BA- 00 0A00 E- 00-0B0 00 00AB Tag: RTU# 3/4 Rev B
Job Name Rowan University Heat Wheel Type: TotalJob Number Job #1527 Heat Wheel Model: ERC-6488CSite Altitude 0' Heat Wheel Qty: 2
Summer Conditions Bypass: 0 CFM
Mixed Air Damper Supply Air HW Outside Air
20066 CFM 16952 CFM 16952 CFM81.24 ºF DB 82.38 ºF DB 82.38 ºF 95.00 ºF DB67.98 ºF WB 69.00 ºF WB 69.00 ºF 78.00 ºF WB81.66 gr/lb 85.19 gr/lb 118.01 gr/lbReturn Air From Space Exhaust Air
3114 CFM 16952 CFM
75.00 ºF DB 87.62 ºF 87.62 ºF DB62.00 ºF WB 72.35 ºF 72.35 ºF WB62.44 gr/lb 95.27 gr/lb
20066 CFM Ex Bypass: 0 CFM
Cooling/Dehumidification Heating/Humidification
Total Capacity: 635.02 MBH 0.00 MBHSensible Capacity: 236.68 MBH 0.00 MBH
Latent Capacity: 398.34 MBH 0.00 MBH
Winter Conditions Bypass: 0 CFM
Mixed Air Damper Supply Air HW Outside Air
20066 CFM 16952 CFM 16952 CFM51.29 ºF DB 47.85 ºF DB 47.85 ºF 10.00 ºF DB43.37 ºF WB 40.94 ºF WB 40.94 ºF 9.00 ºF WB29.08 gr/lb 26.96 gr/lb 7.21 gr/lbReturn Air From Space Exhaust Air
3114 CFM 16952 CFM
70.00 ºF DB 32.15 ºF 32.15 ºF DB55.00 ºF WB 30.03 ºF 30.03 ºF WB40.64 gr/lb 20.90 gr/lb
20066 CFM Ex Bypass: 0 CFM
Cooling/Dehumidification Heating/Humidification
Total Capacity: 0.00 MBH 920.75 MBHSensible Capacity: 0.00 MBH 694.59 MBH
Latent Capacity: 0.00 MBH 226.16 MBH
Energy Wheel Rating
Date Created/Modified: 2/10/2014 11:46:10 AM Using Ver 4.214 (OSN# 5728272) Date Printed: 3/3/2014 9:16:13 AM
2425 South Yukon Ave - Tulsa, Oklahoma 74107-2728 - Ph. (918) 583-2266 Fax (918) 583-6094AAONEcat32 Ver. 4.214 (SN: 5728272-VE5U3BHT)
JOB INFORMATION: WHEEL SPECIFICATION: Job Name: Max RPM: Job Tag: Diameter x Qty: Rep Firm: CFM: Date: Tip Speed:
Inertia:
Rowan University 1,800RTU# 3/4 Rev B 33.5 in. x 2
1003303/03/2014 8,665 FPM
74 WR²
OPERATING CONDITIONS: MOTOR SELECTION: Air Flow: Rated HP / Bypass: Static Pressure: Frame Size: Relief Dampers DP: Nominal RPM:
VAC/PH/HZ: TSP: Efficiency Site Altitude: Enclosure Type: TSP @ Sea Level: Max Inertial Load:
20,066 CFM 10 x 2 / No3.03 in. Wg. 256T0.00 in. Wg. 1170
460/3/603.03 in. Wg. Premium / 0.9170.00 Ft ODP3.03 in. Wg. 385 WR²
FAN PERFORMANCE: FAN SOUND POWER x 2 Fans (In/Out): RPM: Octave Band: (Re 10^-12 watts) BHP: 1 2 3 4 5 6 7 8 Efficiency: In/Out Velocity: Plenum Out Velocity: SOUND POWER A-Weighted: 91 / 98 dB
Max Duct SP with Blocked Airway: 3.2 in. Wg. @ 988 rpm
9888.1059.2% 84 86 86 85 85 85 84 821068/1541 FPM 91 91 94 94 92 92 91 88227 FPM
RPM
BHP
SYSTEM
Efficiency
SP Surge
CFM Min
Supply Fan Model: RNE330 @ 988 RPM and 97% WidthDesign Conditions: 10033 CFM @ 3.03" SP
CFM x 10001614121086420
SP
3
2
1
0
BH
P
20
19
18
17
16
15
14
13
12
11
10
9
8
7
6
5
4
3
2
1
0
40%
20%
0%
RPM: 988
BHP: 8.10
EFFICIENCY: 59.17
33.0" STAR Plenum
Date Created/Modified: 2/10/2014 11:46:10 AM Using Ver 4.214 (OSN# 5728272) Date Printed: 3/3/2014 9:16:13 AM
2425 South Yukon Ave - Tulsa, Oklahoma 74107-2728 - Ph. (918) 583-2266 Fax (918) 583-6094AAONEcat32 Ver. 4.214 (SN: 5728272-VE5U3BHT)
JOB INFORMATION: WHEEL SPECIFICATION: Job Name: Max RPM: Job Tag: Diameter x Qty: Rep Firm: CFM: Date: Tip Speed:
Inertia:
Rowan University 1,800RTU# 3/4 Rev B 33.5 in. x 2
1003303/03/2014 7,621 FPM
74 WR²
OPERATING CONDITIONS: MOTOR SELECTION: Air Flow: Rated HP / Bypass: Static Pressure: Frame Size: Relief Dampers DP: Nominal RPM:
VAC/PH/HZ: TSP: Efficiency Site Altitude: Enclosure Type: TSP @ Sea Level: Max Inertial Load:
20,066 CFM 15 x 2 / No1.90 in. Wg. 254T0.19 in. Wg. 1760
460/3/602.09 in. Wg. Premium / 0.930.00 Ft ODP2.09 in. Wg. 149 WR²
FAN PERFORMANCE: FAN SOUND POWER x 2 Fans (In/Out): RPM: Octave Band: (Re 10^-12 watts) BHP: 1 2 3 4 5 6 7 8 Efficiency: In/Out Velocity: Plenum Out Velocity: SOUND POWER A-Weighted: 89 / 95 dB
8695.5159.9% 82 83 83 84 84 83 81 791068/1541 FPM 88 88 92 93 89 89 87 84227 FPM
RPM
BHP
SYSTEM
Efficiency
SP Surge
CFM Min
Exhaust Fan Model: RNE330 @ 869 RPM and 100% WidthDesign Conditions: 10033 CFM @ 2.09" SP
CFM x 100014121086420
SP
2
1
0
BH
P
15
14
13
12
11
10
9
8
7
6
5
4
3
2
1
0
60%
40%
20%
0%
RPM: 869
BHP: 5.51
EFFICIENCY: 59.95
33.0" STAR Plenum
Date Created/Modified: 2/10/2014 11:46:10 AM Using Ver 4.214 (OSN# 5728272) Date Printed: 3/3/2014 9:16:13 AM
2425 South Yukon Ave - Tulsa, Oklahoma 74107-2728 - Ph. (918) 583-2266 Fax (918) 583-6094AAONEcat32 Ver. 4.214 (SN: 5728272-VE5U3BHT)
1A
1B
1C
1D
2
3
4
5A
5B
5C 6A
6B
6C
7
8
9
10
11
12
13
14A
14B
15
16
17
18
19
20
21
22
23
R N- 065-3- 0-0W 0H -EHJ :UGSL- Q0 B-GV T- 0BA- 00 0A00 E- 00-0B0 00 00AB Tag: RTU# 3/4 Rev B
Job Name: Rowan University Unit Submittal For: Burns-Joe Zagorski Job Number: Job #1527 Unit Submittal Date: February 10, 2014
Base Option Description
R Series Roof Top Unit
N Generation Ninth Generation
065 Unit Size Sixty Five
3 Voltage 460V/3Ø/60Hz
0 Interior Protection Standard
0 Refrigerant Style Air Handling Unit
W Unit Configuration Chilled Water Coil - 6 Row
0 Coil Coating Standard
H Cooling/Heat Pump Staging Single Serpentine 8 FPI
E Heating Type Hot Water Standard Coil
H Heating Designation 1 Row Coil
J Heating Staging Half Serpentine 8 FPI
Feature Option Description
U 1A. RA/OA Section AAONAIRE® Energy Recovery Wheel - Total + High CFM
G 1B. RA/EA Blower Configuration 2 Blowers + Premium Efficiency Motors + 2 Motors on 2 VFDs
S 1C. RA/EA Blower 33" Backward Curved Plenum
L 1D. RA/EA Blower Motor 15 hp - 1760 rpm
Q 2. OA Control CO2 Override + Fully Modulating Actuator - Enthalpy Limit
0 3. Heat Options Standard
B 4. Maintenance Options 115V Convenience Outlet - Factory Wired
G 5A. SA Blower Configuration 2 Blowers + Premium Efficiency Motors + 2 Motors on 2 VFDs
V 5B. SA Blower 33'' Direct Drive Backward Curved Plenum
T 5C. SA Motor 10 hp - 1170 rpm
0 6A. Pre Filter Type Standard - None
B 6B. Unit Filter Type 4" Pleated - 30% Eff
A 6C. Filter Options Clogged Filter Switch
0 7. Refrigeration Control Standard - Fixed 55°F Comp. Cooling Lock Out
0 8. Refrigeration Options Standard
0 9. Refrigeration Accessories Standard
A 10. Power Options Power Switch - 100 amps
0 11. Safety Options Standard
0 12. Controls Standard
E 13. Special Controls Constant Volume (CV) Unit Controller - CV Cool + CV Heat
0 14A. Preheat Configuration Standard - None
0 14B. Preheat Sizing Standard - None
0 15. Glycol Percent Water or No WSHP
B 16. Interior Cabinet Options Control Panel Service Lights
0 17. Exterior Cabinet Options Standard
0 18. Customer Code Standard
0 19. Code Options Standard - ETL U.S.A. Listing
0 20. Crating Standard
0 21. Water-Cooled Cond. Standard - None
A 22. Control Vendors Wattmaster Controls
B 23. Type Standard - Includes AAON Gray Paint
Unit Submittal
Date Created/Modified: 2/10/2014 11:46:10 AM Using Ver 4.214 (OSN# 5728272) Date Printed: 3/3/2014 9:16:13 AM
2425 South Yukon Ave - Tulsa, Oklahoma 74107-2728 - Ph. (918) 583-2266 Fax (918) 583-6094AAONEcat32 Ver. 4.214 (SN: 5728272-VE5U3BHT)
1A
1B
1C
1D
2
3
4
5A
5B
5C 6A
6B
6C
7
8
9
10
11
12
13
14A
14B
15
16
17
18
19
20
21
22
23
R N- 065-3- 0-0W 0H -EHJ :UGSL- Q0 B-GV T- 0BA- 00 0A00 E- 00-0B0 00 00AB Tag: RTU# 3/4 Rev B Job Name: Rowan University VCMX For: Burns-Joe Zagorski Job Number: Job #1527 VCMX Date: February 10, 2014
Hardware Included For VCMX Controller
Part # Included Parts Assigned ChannelV07150 VCMX Controller with EBUSP94320 Space Temp Sensor - Field Installed MainController\AI1R82890 Supply Air Temp Sensor - Field Installed MainController\AI2R81550 Outside Air Temp Sensor MainController\AI4R69190 VCMX Large Expansion ModuleR37030 Building Static Pressure Sensor LargeExpansionModule\AI4R34700 Outside Air Humidity Sensor LargeExpansionModule\AI1P62520 Proof of Flow Sensor LargeExpansionModule\BI3P62520 Dirty Filter Sensor LargeExpansionModule\BI2
1 2 3 4 5 6 7
VCMXControllerwith EBUS
Analog In X X XAnalog Out X XBinary InRelay Out X X X XDigital Sensor(s)
X
1 2 3 4 5 6 7 8VCMXLarge
ExpansionModule
Analog In X XAnalog Out X XBinary In X XRelay Out
VCMX Components
Date Created/Modified: 2/10/2014 11:46:10 AM Using Ver 4.214 (OSN# 5728272) Date Printed: 3/3/2014 9:16:14 AM
Date Created/Modified: 2/10/2014 11:46:10 AM Using Ver 4.214 (OSN# 5728272) Date Printed: 3/3/2014 9:16:14 AM
Rowan University REPORT
Esby Gymnasium and Recreation Center HVAC Study MARCH 7, 2014
11
APPENDIX C – CONCEPTUAL HVAC EQUIPMENT LAYOUT SKETCHES
SKM-1 & SKM-2
Rowan University REPORT
Esby Gymnasium and Recreation Center HVAC Study MARCH 7, 2014
12
APPENDIX D – ORDER OF MAGNITUDE COST ESTIMATES
Project Title: Rowan University - Rec Center and Esby Gym HVAC Study Discipline: ALL Sheet:
Submision: Summary Sheet Prepared by: J. Zagorski Date: 3/7/2014
Checked by: M.Walton Date: 3/7/2014
Item Description Quantity Unit Unit Price $ Total $ Total $ Assumption / Basis
# Material Labor Material Labor
SUMMARY
Rec Center - Aerobics and Weight Room $161,551 $103,520 $265,071
Rec Center - Gymnasium $81,750 $104,775 $186,525
Esby Gymnasium $181,771 $146,746 $328,517
Total $425,073 $355,040 $780,113
Notes
1
2 Costs for new power wiring/conduit or increase to electrical infrastructure required for larger units are not included in estimate.
3 Costs for supplementary steel supports and roof cutting/flashing is included in estimate. Modifications to roof structure, if required, to accommodate new equipment is not included.
Piping modifications included in estimate are to system risers on 2nd floor only. Modifications to existing condenser water or 2 pipe changeover pumps ,heat exchangers or main system piping
is not included
SUMMARY-DIV2-16 Page 1 of 1
Rowan University - Recreation Center and Esby Gym HVAC Study Discipline: ALL Sheet:
Recreation Center - Aerobics/Free Weight Room Prepared by: J. Zagorski Date: 3/7/2014
Checked by: M.Walton Date: 3/7/2014
Item Description Quantity Unit Price $ Total $ Total $ Assumption / Basis
# Material Labor Material Labor
DIVISION 15 - MECHANICAL
15050
Heat Pump and Duct Removal 3 DY 16 $85 1,360.00 - 4,080 4,080
3 DY 16 $85 1,360.00 - 4,080 4,080
2 DY 16 $85 1,360.00 - 2,720 2,720
5 DY 16 $85 5,000.00 1,360.00 25,000 6,800 31,800
1 DY 16 $85 1,000.00 1,360.00 1,000 1,360 2,360
15088 Piping Insulation
200 LF 0.094 $85 $2.56 7.99 512 1,598 2,110
15181 Hydronic Piping
200 LF 0.372 $85 $25.50 31.62 5,100 6,324 11,424
15815 Metal Ducts
3000 LB 0.087 $85 $0.66 7.40 1,980 22,185 24,165
1500 SF 0.053 $85 $0.37 4.51 555 6,758 7,313
15732
1 EA 128 $85 $80,000 10,880.00 80,000 10,880 90,880
- - -
15900
1 LS $85 1,000.00 5,000.00 1,000 5,000 6,000
15990 Testing Adjusting and Balancing
HVAC Instrumentation and
Controls
New combination Temp and Humidity
Stats with Control Wiring to AHU
Vendor Furnished Controller
Roof patching, flashing 2 man crew
1-1/2", 3" Bore; Pre-formed
Fiberglass
Ductwork (3" w.g.) incl. Fittings
$1000 point (appx. 5 points)
Insulation
Packaged Outdoor, Central Station
Air Handling Unit
13,000cfm, 60 ton Water Source Heat
Pump with Energy Recovery and Hot
Gas Reheat with Controller 4 man crew, 3 days
Basic Mechanical Materials and
Methods
2 man crew
Misc. Ceiling and Lighting Removal
and Reinstallation for Ductwork and
Piping 2 man crew
3" Supply and Condenser Water
Piping to Riser on 2nd Floor.
Modifications to CW pumps,
HX or main piping distribution
not included.
Remove 2-1/2" Condenser Water
Supply and Return Piping from HPs to
Riser on 2nd Floor. 2 man crew
Cutting, Patching and Misc
Supplementary Steel for Unit 2 man crew
Project Title:
Submision:
Unit Unit Hours Labor Rate
REC CENTER AEROBICS Page 1 of 2
Rowan University - Recreation Center and Esby Gym HVAC Study Discipline: ALL Sheet:
Recreation Center - Aerobics/Free Weight Room Prepared by: J. Zagorski Date: 3/7/2014
Checked by: M.Walton Date: 3/7/2014
Item Description Quantity Unit Price $ Total $ Total $ Assumption / Basis
# Material Labor Material Labor
Project Title:
Submision:
Unit Unit Hours Labor Rate
1 DY 8 $85 - 2,000.00 - 2,000 2,000
Subtotal 115,147 73,785 188,932
15% OH and Profit $17,272 $11,068 $28,340
Subtotal 132,419 84,852 217,271
General Conditions (2%) $2,648 $1,697 $4,345
Contingency (20%) $26,484 $16,970 $43,454
Total $161,551.24 $103,519.65 $265,070.89
Post Construction Balancing
REC CENTER AEROBICS Page 2 of 2
Rowan University - Recreation Center and Esby Gym HVAC Study Discipline: ALL Sheet:
Recreation Center - Gymnasium Prepared by: J. Zagorski Date: 3/7/2014
Checked by: M.Walton Date: 3/7/2014
Item Description Quantity Unit Price $ Total $ Total $ Assumption / Basis
# Material Labor Material Labor
DIVISION 15 - MECHANICAL
15050
AHU Removal 3 DY 32 $85 2,720.00 - 8,160 8,160
3 DY 16 $85 1,360.00 - 4,080 4,080
15088 Piping Insulation
300 LF 0.094 $85 $2.56 7.99 768 2,397 3,165
15181 Hydronic Piping
300 LF 0.444 $85 $35.00 37.74 10,500 11,322 21,822
15815 Metal Ducts
1 LS 48 $85 $1,000.00 4,080.00 1,000 4,080 5,080
15732
3 EA 128 $85 $15,000 10,880.00 45,000 32,640 77,640
- - -
15900
1 LS $85 1,000.00 10,000.00 1,000 10,000 11,000
15990
1 DY 8 $85 - 2,000.00 - 2,000 2,000
Subtotal 58,268 74,679 132,947
15% OH and Profit $8,740 $11,202 $19,942
Subtotal 67,008 85,881 152,889
General Conditions (2%) $1,340 $1,718 $3,058
Project Title:
Submision:
Unit Unit Hours Labor Rate
1-1/2", 4" Bore; Pre-formed
Fiberglass
4" Supply and Condenser Water
Piping to Riser on 2nd Floor.
Modifications to H/C pumps,
HX or main piping distribution
not included.
Basic Mechanical Materials and
Methods
4 man crew
Remove 3" Heating and Cooling
Changeover Piping from AHUs to
Riser on 2nd Floor. 2 man crew
HVAC Instrumentation and
Controls
New combination Temp and Humidity
Stats with Control Wiring to AHU
Vendor Furnished Controllers and
Existing Exhaust Fans $1000 point (appx. 10 points)
Testing Adjusting and Balancing
Post Construction Balancing
Misc Duct Modifications
Modular Indoor, Central Station
Air Handling Unit
6,000cfm, 20 ton Indoor Modular
AHU with VAV Controls 4 man crew, 3 days
REC CENTER GYM Page 1 of 2
Rowan University - Recreation Center and Esby Gym HVAC Study Discipline: ALL Sheet:
Recreation Center - Gymnasium Prepared by: J. Zagorski Date: 3/7/2014
Checked by: M.Walton Date: 3/7/2014
Item Description Quantity Unit Price $ Total $ Total $ Assumption / Basis
# Material Labor Material Labor
Project Title:
Submision:
Unit Unit Hours Labor Rate
Contingency (20%) $13,402 $17,176 $30,578
Total $81,750.00 $104,774.64 $186,524.64
REC CENTER GYM Page 2 of 2
Rowan University - Recreation Center and Esby Gym HVAC Study Discipline: ALL Sheet:
Esby Gymnasium Prepared by: J. Zagorski Date: 3/7/2014
Checked by: M.Walton Date: 3/7/2014
Item Description Quantity Unit Price $ Total $ Total $ Assumption / Basis
# Material Labor Material Labor
DIVISION 15 - MECHANICAL
15050
AHU and Duct Removal 5 DY 16 $85 1,360.00 - 6,800 6,800
3 DY 16 $85 1,360.00 - 4,080 4,080
4 DY 16 $85 1,360.00 - 5,440 5,440
5 DY 16 $85 5,000.00 1,360.00 25,000 6,800 31,800
1 DY 16 $85 1,000.00 1,360.00 1,000 1,360 2,360
15088 Piping Insulation
400 LF 0.094 $85 $2.56 7.99 1,024 3,196 4,220
15181 Hydronic Piping
400 LF 0.444 $85 $35.00 37.74 14,000 15,096 29,096
15815 Metal Ducts
3000 LB 0.087 $85 $0.66 7.40 1,980 22,185 24,165
1500 SF 0.053 $85 $0.37 4.51 555 6,758 7,313
15732
1 EA 128 $85 $85,000 10,880.00 85,000 10,880 95,880
- - -
15900
1 LS $85 1,000.00 20,000.00 1,000 20,000 21,000
15990
Project Title:
Submision:
Unit Unit Hours Labor Rate
Basic Mechanical Materials and
Methods
4 man crew
Remove 3" H/C Water Supply and
Return Piping from AHUs to Riser on
2nd Floor of Rec Center. 2 man crew
Misc. Ceiling and Lighting Removal
and Reinstallation for Ductwork and
Piping 2 man crew
Cutting, Patching and Misc
Supplementary Steel for Unit 2 man crew
Roof patching, flashing 2 man crew
1-1/2", 4" Bore; Pre-formed
Fiberglass
4" Supply and Condenser Water
Piping to Riser on 2nd Floor.
Modifications to CW pumps,
HX or main piping distribution
not included.
HVAC Instrumentation and
Controls
New combination Temp and Humidity
Stats and CO2 Sensors with Control
Wiring to AHU Vendor Furnished
Controller $1000 point (appx. 20 points)
Testing Adjusting and Balancing
Ductwork (3" w.g.) incl. Fittings
Insulation
Packaged Outdoor, Central Station
Air Handling Unit
20,000cfm, 100 ton Rooftop AHU 4 man crew, 3 days
ESBY GYM Page 1 of 2
Rowan University - Recreation Center and Esby Gym HVAC Study Discipline: ALL Sheet:
Esby Gymnasium Prepared by: J. Zagorski Date: 3/7/2014
Checked by: M.Walton Date: 3/7/2014
Item Description Quantity Unit Price $ Total $ Total $ Assumption / Basis
# Material Labor Material Labor
Project Title:
Submision:
Unit Unit Hours Labor Rate
1 DY 8 $85 - 2,000.00 - 2,000 2,000
Subtotal 129,559 104,595 234,154
15% OH and Profit $19,434 $15,689 $35,123
Subtotal 148,993 120,284 269,277
General Conditions (2%) $2,980 $2,406 $5,386
Contingency (20%) $29,799 $24,057 $53,855
Total $181,771.28 $146,746.08 $328,517.36
Post Construction Balancing
ESBY GYM Page 2 of 2