es-14-202-19

31
Roads and Paving ES-14-202-19 Version No. 7.0 Page 1 of 31 Document last modified: 03 January 2013. Date printed: 17 January 2013. This is a Controlled Document that complies with Wesfarmers Chemicals, Energy & Fertilisers formatting and Quality Control standards. Please check that this is the latest available version before use. Title: ROADS AND PAVING Number: ES-14-202-19 Version Number: 7.0 Date Revised: 03 January 2013 Owner: Ryan Woodall Authoriser: Manoj Thakur Reasons for Creating or Amending Document Full Review of Document Actual Change Details: Control Block updated; No changes to content TABLE OF CONTENTS 1. SCOPE ....................................................................................................................................... 5 2. PURPOSE .................................................................................................................................. 5 3. DEFINITIONS .......................................................................................................................... 5 3.1 CONTRACTOR / VENDOR ................................................................................................ 5 3.2 SUB-CONTRACTOR ........................................................................................................... 5 3.3 SUPERINTENDENT ............................................................................................................ 5 3.4 WORKS................................................................................................................................. 5 3.5 ASPHALTIC CONCRETE ................................................................................................... 5 3.6 SALVIACIM™ ..................................................................................................................... 5 3.7 BASE / SUBBASE ................................................................................................................ 5 3.8 SUBGRADE ......................................................................................................................... 6 3.9 ABSOLUTE LEVEL TOLERANCE .................................................................................... 6 3.10 RELATIVE LEVEL TOLERANCE ..................................................................................... 6 4. STANDARDS ............................................................................................................................ 7 5. BASIS OF DESIGN .................................................................................................................. 8 5.1 ROAD AND PAVING MATERIAL SELECTION .............................................................. 8 5.2 ROAD BEND RADII ............................................................................................................ 9 5.3 LONGITUDINAL GRADING OF ROADS ......................................................................... 9 5.4 ROAD CROSS-SECTION .................................................................................................... 9 5.5 PAVEMENT AREAS (EXCLUDING ROADS) ................................................................ 11 5.6 SPEED HUMPS .................................................................................................................. 11

Upload: prmrao

Post on 11-May-2017

219 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: ES-14-202-19

Roads and Paving

ES-14-202-19

Version No. 7.0 Page 1 of 31

Document last modified: 03 January 2013. Date printed: 17 January 2013.

This is a Controlled Document that complies with Wesfarmers Chemicals, Energy & Fertilisers formatting and Quality Control standards.

Please check that this is the latest available version before use.

Title: ROADS AND PAVING

Number: ES-14-202-19

Version Number: 7.0

Date Revised: 03 January 2013

Owner: Ryan Woodall

Authoriser: Manoj Thakur

Reasons for Creating or Amending Document

Full Review of Document

Actual Change Details: Control Block updated; No changes to content

TABLE OF CONTENTS

1. SCOPE ....................................................................................................................................... 5

2. PURPOSE .................................................................................................................................. 5

3. DEFINITIONS .......................................................................................................................... 5

3.1 CONTRACTOR / VENDOR ................................................................................................ 5 3.2 SUB-CONTRACTOR ........................................................................................................... 5 3.3 SUPERINTENDENT ............................................................................................................ 5 3.4 WORKS................................................................................................................................. 5 3.5 ASPHALTIC CONCRETE ................................................................................................... 5 3.6 SALVIACIM™ ..................................................................................................................... 5 3.7 BASE / SUBBASE ................................................................................................................ 5 3.8 SUBGRADE ......................................................................................................................... 6 3.9 ABSOLUTE LEVEL TOLERANCE .................................................................................... 6 3.10 RELATIVE LEVEL TOLERANCE ..................................................................................... 6

4. STANDARDS ............................................................................................................................ 7

5. BASIS OF DESIGN .................................................................................................................. 8

5.1 ROAD AND PAVING MATERIAL SELECTION .............................................................. 8 5.2 ROAD BEND RADII ............................................................................................................ 9 5.3 LONGITUDINAL GRADING OF ROADS ......................................................................... 9 5.4 ROAD CROSS-SECTION .................................................................................................... 9 5.5 PAVEMENT AREAS (EXCLUDING ROADS) ................................................................ 11 5.6 SPEED HUMPS .................................................................................................................. 11

Page 2: ES-14-202-19

Roads and Paving

ES-14-202-19

Version No. 7.0 Page 2 of 31

Document last modified: 03 January 2013. Date printed: 17 January 2013.

5.7 CARPARKS ........................................................................................................................ 11 5.8 LIGHTING .......................................................................................................................... 12

6. SAFETY ................................................................................................................................... 12

7. SITE PREPARATION ........................................................................................................... 12

8. SUBBASE AND BASE ........................................................................................................... 12

8.1 MATERIALS ...................................................................................................................... 12 8.2 PLACEMENT ..................................................................................................................... 13 8.3 COMPACTION ................................................................................................................... 14 8.4 SURFACE FINISH ............................................................................................................. 14 8.5 TOLERANCES ................................................................................................................... 14

9. ASPHALTIC CONCRETE .................................................................................................... 15

9.1 GENERAL .......................................................................................................................... 15 9.2 MATERIALS ...................................................................................................................... 15 9.3 AGGREGATE PARTICLE DISTRIBUTION .................................................................... 15 9.4 PRIMER COAT .................................................................................................................. 16 9.5 TACK COAT ...................................................................................................................... 16 9.6 DELIVERY OF ASPHALT ................................................................................................ 16 9.7 SPREADING ASPHALT SURFACE ................................................................................. 16 9.8 COMPACTING ASPHALT SURFACE ............................................................................. 17 9.9 JOINT AND JUNCTIONS .................................................................................................. 17 9.10 SURFACE FINISH ............................................................................................................. 18 9.11 TOLERANCES ................................................................................................................... 18

10. SALVIACIM™ ....................................................................................................................... 19

10.1 GENERAL .......................................................................................................................... 19 10.2 ASPHALT LAYER ............................................................................................................ 20 10.3 RESIN MODIFIED GROUT .............................................................................................. 21 10.4 APPLICATION OF RESIN MODIFIED GROUT ............................................................. 22 10.5 CURING OF RESIN MODIFIED GROUT ........................................................................ 22

11. GRAVEL PAVEMENT .......................................................................................................... 23

11.1 BASE MATERIAL ............................................................................................................. 23 11.2 CONSTRUCTION .............................................................................................................. 23

12. FOOTPATHS .......................................................................................................................... 23

12.1 GENERAL .......................................................................................................................... 23 12.2 CONCRETE FOOTPATHS ................................................................................................ 24 12.3 ASPHALTIC CONCRETE FOOTPATHS ......................................................................... 24 12.4 PAVING BRICK FOOTPATHS ......................................................................................... 24 12.5 GRAVEL FOOTPATHS ..................................................................................................... 24

13. INSPECTION .......................................................................................................................... 25

14. TESTING ................................................................................................................................. 26

14.1 GENERAL .......................................................................................................................... 26 14.2 FREQUENCY OF TESTING ............................................................................................. 26 14.3 REJECT WORK .................................................................................................................. 26

15. STORM WATER AND SUB-SOIL DRAINS ....................................................................... 26

16. KERBING ................................................................................................................................ 27

Page 3: ES-14-202-19

Roads and Paving

ES-14-202-19

Version No. 7.0 Page 3 of 31

Document last modified: 03 January 2013. Date printed: 17 January 2013.

16.1 GENERAL .......................................................................................................................... 27 16.2 DESIGN AND CONSTRUCTION ..................................................................................... 27

17. SPEED HUMPS ...................................................................................................................... 28

18. ROAD MARKING .................................................................................................................. 29

19. ACCESS TO SERVICES ....................................................................................................... 29

20. ROAD SIGNS .......................................................................................................................... 30

21. GUARD RAILS AND BOLLARDS ...................................................................................... 30

22. REINSTATEMENT ................................................................................................................ 30

23. REPAIRS TO EXISTING BITUMEN .................................................................................. 30

24. RECORDS MANAGEMENT ................................................................................................ 31

24.1 AS-BUILT DRAWINGS .................................................................................................... 31 24.2 DENSITY AND COMPACTION TEST RESULTS .......................................................... 31

TABLES

Table 1 - Road and Pavement Classifications .................................................................................... 8

Table 2 - Minimum Internal Bend Road Radius ................................................................................ 9

Table 3 - Limestone Material Grading Requirements ...................................................................... 13

Table 4 - Crushed Rock Material Grading Requirements ................................................................ 13

Table 5 - Surface Tolerances ............................................................................................................ 14

Table 6 - Asphaltic Concrete Material Grading Requirements ........................................................ 15

Table 7 - Asphaltic Concrete Surface Tolerances ............................................................................ 18

Table 8 - Salviacim™ -Asphalt Aggregate Grading and Binder Content ........................................ 20

Table 9 - Curing Periods Salviacim™ Asphalt Wearing Surface .................................................... 22

Table 10 - Superintendent Approved Inspection Activities ............................................................. 25

Table 11 - Compaction Testing Frequency ...................................................................................... 26

FIGURES

Figure 1 - Typical Sealed Road Cross-Section with Shoulders 10

Figure 2 - Typical Sealed Road Cross-Section with Kerbs 11

Page 4: ES-14-202-19

Roads and Paving

ES-14-202-19

Version No. 7.0 Page 4 of 31

Document last modified: 03 January 2013. Date printed: 17 January 2013.

Figure 3 - Typical Join to an Existing Pavement 17

Figure 4 - Typical Section through Salviacim™ Layer 19

Figure 5 - Typical Pavement Section Using a Salviacim™ Surface 19

Figure 6 - Typical Kerbing Arrangement 28

Figure 7 Speed Hump Profile 29

Page 5: ES-14-202-19

Roads and Paving

ES-14-202-19

Version No. 7.0 Page 5 of 31

Document last modified: 03 January 2013. Date printed: 17 January 2013.

1. SCOPE

This Standard covers the general requirements for the design and construction of sealed and unsealed roads and pavement areas. It includes ground preparation, paving materials, placement, compaction and testing requirements, concrete kerbing, signage and repairs to bitumen pavement.

2. PURPOSE

To ensure that safe and reliable access to all locations of the site is provided to all vehicular and pedestrian traffic required at those locations during the lifetime of the plant, and that designated areas are suitably paved in accordance with their function.

3. DEFINITIONS

3.1 CONTRACTOR / VENDOR

The company that provides the equipment and services needed.

3.2 SUB-CONTRACTOR

A third party to be employed by the Contractor / Vendor, who has been approved by the Superintendent.

3.3 SUPERINTENDENT

Wesfarmers CSBP Limited, or authorised representative.

3.4 WORKS

The scope of works that a Contractor is or may be required to execute under an agreement including variations and remedial work.

3.5 ASPHALTIC CONCRETE

A dense, continuously graded mixture of coarse and fine aggregates, mineral filler and bitumen produced hot in a mixing plant. It is delivered, spread and compacted while hot to form a sealed wearing trafficable surface.

3.6 SALVIACIM™

A Semi Rigid paving material that combines the flexible characteristics of asphalt with the hard wearing properties of cement concrete. It comprises a layer of open graded asphalt whose voids are filled with a resin modified cementitious grout.

3.7 BASE / SUBBASE

One or more layers of material used where the settlement behaviour and / or the bearing capacity of the subgrade is insufficient to support the paving and traffic without excessive deformation or

Page 6: ES-14-202-19

Roads and Paving

ES-14-202-19

Version No. 7.0 Page 6 of 31

Document last modified: 03 January 2013. Date printed: 17 January 2013.

maintenance during the lifetime of the plant. Specific definition of Base and Subbase are as follows.

3.7.1 Base

A limestone layer that is placed directly onto the subgrade, compacted and trimmed to a specified shape and thickness, to provide a working surface on which a trafficable surface can be placed.

OR - IF THE DESIGN REQUIRES A SUBBASE

A crushed diorite or granite rock layer that is placed directly on the road subbase, compacted and trimmed to a specified shape and thickness on which a trafficable surface can be placed.

3.7.2 Subbase

If required by design, a limestone layer that is placed directly onto the subgrade, compacted and trimmed to a specified shape and thickness, to provide a working surface on which the base and trafficable surface can be constructed. It is used:

• to increase the pavement thickness over the sub-grade

• to prevent intrusion of the subgrade into the base

• to provide a working surface on which the remainder of the pavement can be constructed.

3.8 SUBGRADE

The trimmed or prepared portion of the formation onto which the road or pavement area is constructed.

3.9 ABSOLUTE LEVEL TOLERANCE

Maximum deviation from design levels.

3.10 RELATIVE LEVEL TOLERANCE

Maximum deviation from a three- (3) metre straightedge laid anywhere on the surface.

Page 7: ES-14-202-19

Roads and Paving

ES-14-202-19

Version No. 7.0 Page 7 of 31

Document last modified: 03 January 2013. Date printed: 17 January 2013.

4. STANDARDS

The Contractor shall perform the Works in accordance with this Standard, the latest issue of reference standards and Contractor regulations for on-site work. Should there be a conflict between the Works, Statutory Requirements, the Contractor shall notify the Superintendent in writing for resolution. In general, the most stringent requirements will prevail.

CSBP Engineering Standards

ES-14-101-02 Drawing Management ES-14-101-03 Drawing Preparation ES-14-101-04 Drawing Numbering ES-14-102-08 Safety and Information Signs ES-14-202-01 Earthworks and Site Preparation ES-14-202-10 Concrete ES-14-202-22 Road Marking ES-14-701-01 Electrical/Instrument Preferred Equipment

CSBP Guide Manuals

GM-10-090-02 Contractor’s Site Instructions GM-11-031-01 Personal Protective Equipment GM-11-035-02 Basic Safety Rules

CSBP Standard Drawings

9900-2-0600 Fencing Details 9900-2-1300/001 Bollards

Australian Standards

AS 1141 Methods for Sampling and Testing Aggregates AS 1158 Road Lighting AS 1160 Bituminous Emulsions for the Construction and Maintenance of

Pavements AS 1289 Methods of Testing Soils for Engineering Purposes AS 1348 Road and Traffic Engineering - Glossary of Terms AS 1742 Manual of Uniform Traffic Control Devices AS 1743 Road Signs - Specifications AS 2008 Residual Bitumen for Pavements AS 2150 Hot Mix Asphalt AS 2357 Mineral Filler for Asphalt AS 2734 Asphalt (hot-mixed) Paving - Guide to Good Practice AS 2758.5 Aggregates and Rock for Engineering Purposes – Asphalt Aggregates AS 2876 Concrete Kerbs and Channels (Gutters) AS 2890.1 Off-street Car Parking AS 2891 Methods for Sampling and Testing Asphalt AS 3996 Metal Access Covers, Road Grates and Frames

Page 8: ES-14-202-19

Roads and Paving

ES-14-202-19

Version No. 7.0 Page 8 of 31

Document last modified: 03 January 2013. Date printed: 17 January 2013.

5. BASIS OF DESIGN

5.1 ROAD AND PAVING MATERIAL SELECTION

Selection of road and paving materials shall be based on technical, environmental and economical considerations for each application. Traffic types, volumes, speeds and masses, texture and skid resistance requirements shall be considered when determining type of surface to be used.

Table 1 provides approved road and paving material options for use in different situations. Alternate materials shall not be used without the written approval of the Superintendent.

CLASS DESCRIPTION MINIMUM WIDTH OF PAVEMENT

PAVEMENT SURFACE

FINISH PAVING MATERIAL

1

Extra Heavy Duty Applications

• intersections, curves and turning circles subject to extreme abrasive wear

• joint-free surface resistant to oil, fuel and chemical attack

As required Sealed

40 mm minimum compacted thickness of Salviacim™ or equivalent over

• asphaltic concrete as per Class 2

• base or base/subbase as per Class 2

Refer to Sections 8 , 9 and 10 for details

2

Heavy Duty Roads

• main access roads to buildings, loading facilities and plant areas

Two way road • 7500 mm One way road • 4000 mm

Sealed

40 mm minimum compacted thickness of asphaltic concrete Grade AC14 over

• 225 mm minimum compacted depth limestone base

OR IF DESIGN REQUIRES A SUBBASE

• 100 mm minimum compacted depth crushed rock base and 200 mm min compacted depth limestone subbase

Refer to Sections 8 & 9 for details

Heavy Duty Pavement Areas

• permanent laydown areas

As required

3

Light Duty Roads

• minor access roads

Two way road • 7500 mm One way road • 4000 mm Sealed

30 mm min compacted thickness of asphaltic concrete Grade AC10 over

• 225 mm minimum compacted depth of limestone base

Refer to Sections 8 & 9 for details Light Duty Pavement Areas

• driveways and permanent carparks • permanent laydown areas

As required

4

Light Duty Roads

• minor access roads

• temporary construction roads

Two way road • 7500 mm One way road • 4000 mm Unsealed

225mm minimum compacted depth of limestone OR

150mm minimum compacted depth of gravel

Refer to Sections 8 & 11 for details Light Duty Pavement Areas

• temporary laydown areas & carparks

As required

5

Patrol Roads &Maintenance Tracks

• around perimeter fencing • access along pipelines and other

service routes

3000 mm Unsealed Cleared natural ground

6

Footpaths

Refer to Section 12 for details 1200 mm

Sealed

100 mm thick concrete on compacted sand. Refer to Section 12.2

25-mm min compacted thickness of asphaltic concrete Grade AC5 over compacted limestone. Ref. 12.3

Unsealed Paving bricks on compacted sand. Refer to Section 12.4.

Compacted gravel. Refer to Section 12.5

Table 1 - Road and Pavement Classifications

Page 9: ES-14-202-19

Roads and Paving

ES-14-202-19

Version No. 7.0 Page 9 of 31

Document last modified: 03 January 2013. Date printed: 17 January 2013.

5.2 ROAD BEND RADII

The minimum inside turning radius of roads shall be as specified in Table 2.

TURNING SPEED MINIMUM INSIDE RADIUS

0 - 5 k/hr 12.5 m

5 – 15 k/hr 15.0 m

15 – 20 k/hr 20.0 m

20 – 30 k/hr 30.0 m

The above minimum inside radii, are for guidance only. Bend radii shall be designed based on the anticipated type, length and maximum allowable turning speed of vehicles using the road. The greater value shall be used. For example:

• Minimum, safe turning inside radius for ‘B’ train vehicles is 30m - applicable for all speeds.

Table 2 - Minimum Internal Bend Road Radius

5.3 LONGITUDINAL GRADING OF ROADS

Roads shall be designed to produce acceptable drainage gradients, based on the road setout and minimum earthworks to the natural ground condition. An engineering surveyor shall establish natural ground levels to verify road design gradients.

Drainage grading shall be within the following range:

• Minimum 1in 200

• Maximum 1in 10

Note: The maximum rate in change of gradient shall be 1% in three (3) metres.

5.4 ROAD CROSS-SECTION

Crest fall both sides of the road centreline shall be 1 in 40.

Unless specified otherwise, road shoulders, where required, shall be 1500mm wide and the formation shall fall from the shoulders at a rate of 1 in 3. Where necessary, drainage sumps shall be provided to prevent water lying within six (6) metres of the road shoulder.

For typical sealed road cross-section details refer to Figures 1 and 2.

Page 10: ES-14-202-19

Roads and Paving

ES-14-202-19

Version No. 7.0 Page 10 of 31

Document last modified: 03 January 2013. Date printed: 17 January 2013.

Figure 1 - Typical Sealed Road Cross-Section with Shoulders

Page 11: ES-14-202-19

Roads and Paving

ES-14-202-19

Version No. 7.0 Page 11 of 31

Document last modified: 03 January 2013. Date printed: 17 January 2013.

Figure 2 - Typical Sealed Road Cross-Section with Kerbs

5.5 PAVEMENT AREAS (EXCLUDING ROADS)

Paved areas shall be designed to produce acceptable drainage gradients, based on access road setout and minimum earthworks to the natural ground condition. An engineering surveyor shall establish natural ground levels to verify pavement design gradients.

5.6 SPEED HUMPS

Speed humps shall be installed at locations as a warning of an approaching hazard and at location where the driver shall slow down. For further details on design and construction of speed humps refer to Section 17.

5.7 CARPARKS

Design and layout of parking facilities including access driveway, parking spaces and aisles shall be in accordance with AS 2890.1.

CSBP standard parking layout is 90-degree parking, 6m wide two-way aisles and minimum 2.9m wide and minimum 5.0m long parking bays.

Page 12: ES-14-202-19

Roads and Paving

ES-14-202-19

Version No. 7.0 Page 12 of 31

Document last modified: 03 January 2013. Date printed: 17 January 2013.

5.8 LIGHTING

Design and layout of lighting for roads and carparks, shall be in accordance with AS 1158.Light fittings shall be in accordance with CSBP Engineering Standards Electrical/Instrument Preferred Equipment (ES-14-701-01).

6. SAFETY

All equipment used by the Contractor shall be properly maintained and operated in strict accordance with any safety regulations applicable to that equipment by competent operators.

Safety precautions specified in AS 2734 Clause 7.11 shall be adhered too.

All Personal Protective Equipment (PPE) used on site shall be an approved and acceptable quality complying with CSBP Guide Manual Personal Protective Equipment (GM-11-031-01) and Basic Safety Rules (GM-11-035-02).

7. SITE PREPARATION

The extent of site clearing shall be the minimum required to complete the Works. Trees on the edge of the road reserve or areas to be paved shall only be removed with the approval of the Superintendent.

Site clearing, excavation, filling, compaction, testing and finishing of subgrade in preparation for the placement of road and pavement materials shall be in accordance with CSBP Engineering Standard Earthworks and Site Preparation (ES-14-202-01).

8. SUBBASE AND BASE

8.1 MATERIALS

8.1.1 General

Source materials shall be hard, dense durable particles of uniform quality, free from deleterious materials including clay and organic matter, and containing not more than 1% of disintegrated, weathered, discoloured, soft, fractured, friable or poorly indurated fragments.

The Contractor shall provide samples of the proposed base and subbase materials to the Superintendent for approval. Approved samples shall be safely stored on site. All subsequent material deliveries shall be of a quality appreciably the same as the relevant reference samples.

Page 13: ES-14-202-19

Roads and Paving

ES-14-202-19

Version No. 7.0 Page 13 of 31

Document last modified: 03 January 2013. Date printed: 17 January 2013.

8.1.2 Limestone

Limestone aggregate shall contain a minimum of 60% calcium carbonate by weight with particle size distribution within the limits specified in Table 3.

SIEVE APERTURE SIZE PERCENTAGE (%) PASSING (BY MASS)

80 mm 100

19 mm 50 – 70

2.36 mm 30 - 50

Table 3 - Limestone Material Grading Requirements

8.1.3 Crushed Rock

Where design requires base and subbase layers, crushed diorite or granite rock shall be used as the base material over a limestone subbase layer. Particle size distribution of crushed rock shall be within the limits specified in Table 4.

SIEVE APERTURE SIZE PERCENTAGE (%) PASSING (BY MASS)

26.5 mm 100

19.00 mm 95 – 100

4.75 mm 45 – 65

2.36 mm 30 – 50

425 µm 12 – 30

75 µm 3 - 12

Note: The ratio of the portion passing the 75 µm sieve to the portion passing the 425 µm sieve shall fall between the range of 0.4 to 0.6.

Table 4 - Crushed Rock Material Grading Requirements

8.2 PLACEMENT

Material shall be spread without segregation in uniform layers by the use of a mechanical spreader. Care shall be taken to avoid disturbing the surface beneath. After placing, the layers shall be graded and rolled to the widths, alignments, levels and gradients specified on the drawings, with degree of compaction as per Section 8.3.1, surface level finish as per Section 8.4 and tolerance as per Table 5.

Page 14: ES-14-202-19

Roads and Paving

ES-14-202-19

Version No. 7.0 Page 14 of 31

Document last modified: 03 January 2013. Date printed: 17 January 2013.

8.3 COMPACTION

8.3.1 General

In accordance with compaction tests defined in AS 1289.5.2.1, each layer of material shall be uniformly compacted to achieve full depth, modified maximum dry density as follows:

• 95% - Limestone Subbase or Base Course

• 97% - Crushed Rock Base Course

8.3.2 Moisture Control

Subject to the approval of the Superintendent, the moisture content of materials to be laid may be modified by either adding water or by allowing the materials to dry out before use. Immediately before use, the materials shall be of uniform moisture content sufficient to ensure the required degree of compaction will be achieved.

To assist in the compaction process compacted layers shall be moistened before adding the next layer. Similarly the leading edges of the existing material shall be kept moist until new material is added adjacent to it.

8.4 SURFACE FINISH

After final compaction of the base layer, the surface shall be trimmed if necessary to give a hard, tight, dense even surface, free from loose stones or a slurry of fines.

8.5 TOLERANCES

Subbase and base layers shall comply with tolerances specified in Table 5.

LAYER LEVEL TOLERANCE THICKNESS

TOLERANCE ABSOLUTE RELATIVE

Subbase surface +5 mm

-20 mm

10 mm + 20 mm

- 0 mm

Base surface +5 mm

-10 mm

10 mm + 20 mm

- 0 mm

Note: Tolerances apply to level and thickness of each layer, unless overridden by the requirement and tolerances for the surface course.

Table 5 - Surface Tolerances

Page 15: ES-14-202-19

Roads and Paving

ES-14-202-19

Version No. 7.0 Page 15 of 31

Document last modified: 03 January 2013. Date printed: 17 January 2013.

9. ASPHALTIC CONCRETE

9.1 GENERAL

The manufacture and supply of hot mix asphalt shall comply with AS 2150.

The Contractor shall take all necessary precautions to prevent bitumen or other materials used in the sealing work from entering or adhering to other works. Immediately after aggregate has been spread over the binder, the Contractor shall clean off any excess material and leave gratings, manholes, kerbing or other adjoining surfaces in a clean condition. Any damage shall be repaired to the satisfaction of the Superintendent.

9.2 MATERIALS

Asphaltic materials shall consist of the followings:

• Aggregate Crushed diorite originate to AS 2758.5

• Mineral Filler To AS 2357. Material passing the 75 µm sieve shall be non-plastic

• Bitumen To AS 2008 Class 170 for grade AC5

To AS 2008 Class 320 for grades AC10 and AC14

• Bitumen Emulsion Rapid setting to AS1160 and designated ARS/170/320 or CRS/170/320 dependant on alkalinity / acidity of base material and bitumen class.

9.3 AGGREGATE PARTICLE DISTRIBUTION

The quantity of mineral filler shall not be less than 2% by mass of the combined aggregates. The total aggregate particle size distribution (combined aggregate and mineral filler) shall comply with Table 6.

SIEVE APERTURE SIZE PERCENTAGE (%) PASSING (BY MASS)

Grade AC5 Grade AC10 Grade AC14

19.0 mm 100

13.2 mm 100 85 - 100

9.50 mm 90 - 100 70 - 85

6.70 mm 100 70 - 90 62 - 75

4.75 mm 85 - 100 58 - 76 53 - 70

2.36 mm 55 - 75 40 - 58 35 - 52

1.18 mm 38 - 57 27 - 44 24 - 40

600 µm 26 - 43 17 - 35 15 - 30

300 µm 15 - 28 11 - 24 10 - 24

150 µm 8 - 18 7 - 16 7 - 16

75 µm 4 - 11 4 - 7 4 - 7

Table 6 - Asphaltic Concrete Material Grading Requirements

Page 16: ES-14-202-19

Roads and Paving

ES-14-202-19

Version No. 7.0 Page 16 of 31

Document last modified: 03 January 2013. Date printed: 17 January 2013.

9.4 PRIMER COAT

The surface of the base course shall be swept clean of loose stones, dust, dirt and foreign matter, without dislodging the base course stones, and lightly watered if necessary. Sweeping shall be carried out immediately prior to applying the primer coat and shall extend half (½) of a metre clear of the area to be prime coated.

Bituminous emulsion shall be sprayed over the base coarse at the rate of 1.0 L/m².

9.5 TACK COAT

Loose or foreign material shall be cleaned off the primed surface with suitable power blowers or power brooms.

The tack coat shall consist of three- (3) parts bituminous emulsion to two parts of water and shall not be applied until the base course has dried out.

Note: When diluting the bituminous emulsion, add water to the emulsion NOT emulsion to the water.

Tack coat shall be applied within 30 – 120 minutes before the asphalt surface is applied. The surface is to be uniformly covered at an application rate of 0.3 L/m² residual bitumen.

9.6 DELIVERY OF ASPHALT

Asphalt shall be delivered in accordance with AS 2150, Clause 8.

Note: Loads that are outside the allowable temperature range specified in AS 2734 or become wet shall be rejected.

9.7 SPREADING ASPHALT SURFACE

Asphalt surfacing shall only be placed on a dry pavement surface whose temperature is 10 °C or higher.

The mix shall be spread in layers covering the full width of the carriageway, or if approved by the Superintendent in three- (3) metre minimum width lanes, and to the depth required by the specified compaction thickness.

A mechanical spreader, which will keep the mix in the spreader hopper at least 120°C shall be used except at locations where machine spreading is impracticable, in which case hand spreading shall be used.

Note: Care shall be taken to avoid segregation when hand spreading is used.

Page 17: ES-14-202-19

Roads and Paving

ES-14-202-19

Version No. 7.0 Page 17 of 31

Document last modified: 03 January 2013. Date printed: 17 January 2013.

9.8 COMPACTING ASPHALT SURFACE

The asphalt shall be uniformly and thoroughly rolled as soon as it will support the roller and while the temperature is above 80°C. Longitudinal rolling will commence on the lower side.

Initial rolling shall use a self-propelled vibrating smooth steel-wheeled five tonne roller, making at least five (5) passes.

Secondary rolling shall be carried out as soon as possible after initial rolling with a self-propelled pneumatic tyre roller.

Final rolling shall use a steel-wheeled non-vibrating roller to eliminate all roller marks.

In inaccessible areas small vibrating rollers or hand-operated mechanical compactors shall be used.

Note: Rollers shall not remain stationary on recently compacted work.

9.9 JOINT AND JUNCTIONS

The number of longitudinal and transverse joints shall be minimised, well bonded and sealed.

Joints between successive days work and when joining new work to existing roadways shall be carefully made in such a manner as to ensure a thorough and continuous bond between the old and new surfaces is provided and a smooth riding surface across the junction or joint is achieved.

The existing paving shall be machine / saw cut to remove any edge breaks, irregularities or edge roll and a tack coat applied to the entire length of the cut edges to ensure effective bonding. Refer to Figure 3 for a typical joint to an existing roadway.

Transverse joints shall be at right angles to the direction of spreading and cut to a straight vertical face for the full depth of the layer.

Note: Longitudinal joints in successive layers shall be offset a minimum of 150mm. Transverse joints in successive layers and between adjacent runs shall be staggered a minimum of one (1) metre.

Figure 3 - Typical Join to an Existing Pavement

Page 18: ES-14-202-19

Roads and Paving

ES-14-202-19

Version No. 7.0 Page 18 of 31

Document last modified: 03 January 2013. Date printed: 17 January 2013.

9.10 SURFACE FINISH

Final rolling of the asphaltic concrete course shall produce a surface finish that is uniform in appearance, free draining and evenly graded between level points and has no depressions in which water can lie.

9.11 TOLERANCES

Surface tolerances shall comply with Table 7.

SURFACE DIRECTION LEVEL TOLERANCE THICKNESS

TOLERANCE ABSOLUTE RELATIVE

Longitudinal ± 10 mm 5 mm + 10mm

- 0 mm Transverse ± 10 mm 10 mm

Table 7 - Asphaltic Concrete Surface Tolerances

Page 19: ES-14-202-19

Roads and Paving

ES-14-202-19

Version No. 7.0 Page 19 of 31

Document last modified: 03 January 2013. Date printed: 17 January 2013.

10. SALVIACIM™

10.1 GENERAL

Salviacim™ or equivalent shall be used on CSBP Class 1 designated pavement surfaces where:

• A joint-free surface that is resistant to oil, fuel and chemical attack is required.

• Sharply turning heavy vehicles are likely to be encountered.

• Surface is subject to excessive abrasion, static, moving and impact loads caused by heavy industrial traffic, cargo handling equipment and some tracked vehicles.

Salviacim™ is a two-stage surfacing process that involves the manufacture and laying of open graded asphalt mix, on top of normal pavement, and filling the voids with a resin modified cementitious cement as indicated in Figure 4.

Refer to Figure 5 for typical pavement section using a Salviacim* surface.

Figure 4 - Typical Section through Salviacim™ Layer

Figure 5 - Typical Pavement Section Using a Salviacim™ Surface

Page 20: ES-14-202-19

Roads and Paving

ES-14-202-19

Version No. 7.0 Page 20 of 31

Document last modified: 03 January 2013. Date printed: 17 January 2013.

10.2 ASPHALT LAYER

10.2.1 Materials

Asphalt materials shall consist of the followings:

• Aggregate Crushed diorite originate to AS 2758.5 • Mineral Filler To AS 2357 • Bitumen Binder To AS 2008 Class 320 • Bitumen Emulsion Rapid setting to AS1160.

The target grading of the combined aggregates and filler and the binder content shall conform to Table 8.

SIEVE APERTURE SIZE PERCENTAGE (%) PASSING (BY MASS)

19.0 mm 100

13.2 mm 85 - 100

9.50 mm 50 - 75

4.75 mm 10 - 30

2.36 mm 5 - 20

75 µm 0 – 6

Binder Content (% of mix) 3.5 to 6.0

Table 8 - Salviacim™ -Asphalt Aggregate Grading and Binder Content

10.2.2 Tack Coat

Tack coat shall be in accordance with Section 9.5

10.2.3 Delivery of Asphalt Mix

Delivery of asphalt shall be in accordance with Section 9.6.

10.2.4 Placement of Asphalt Mix

Spreading of asphalt shall be in accordance with Section 9.7.

Note: Paving machine shall be operated without vibrators. The Salviacim™ layer shall not be used to regulate levels or surface shape.

Page 21: ES-14-202-19

Roads and Paving

ES-14-202-19

Version No. 7.0 Page 21 of 31

Document last modified: 03 January 2013. Date printed: 17 January 2013.

10.2.5 Compacting Asphalt Surface

The mix shall be compacted immediately after paving.

Rolling shall be carried out using two static passes of the roller. Over-rolling which would close up the texture shall be avoided

Vibration shall not be used, except where necessary on the longitudinal joint and the start or end of a run in cool conditions.

Rollers shall not remain stationary on recently compacted work.

10.2.6 Joints and Junctions

Joints and junctions shall be in accordance with Section 9.9.

10.2.7 Surface Finish

Surface finish shall be in accordance with Section 9.10.

10.2.8 Tolerances

Tolerances shall be in accordance with Section 9.11.

10.3 RESIN MODIFIED GROUT

10.3.1 Materials

Mineral aggregates, cement and resin modifier shall be in accordance with the Supplier’s specification.

10.3.2 Mixing

The resin-modified grout materials shall be mixed at a suitable concrete batch plant or on site in accordance with the manufacturers’ specifications and procedures.

10.3.3 Grout Fluidity

Prior to application, the grout shall be subject to a fluidity test using a standard flow cone. Flow rate through the cone shall be between 9 and 12 seconds. If the flow rate is outside this range the grout shall be mixed further with manufacturer specified additives, if required, to improve the flow rate.

Note: If segregation is present the grout shall be further mixed.

Page 22: ES-14-202-19

Roads and Paving

ES-14-202-19

Version No. 7.0 Page 22 of 31

Document last modified: 03 January 2013. Date printed: 17 January 2013.

10.4 APPLICATION OF RESIN MODIFIED GROUT

After placement, the asphalt shall be allowed to cool to below 50°C before the resin-modified grout is applied. Normally the grout is applied the following day, or after a sufficiently large amount of surface is ready for grouting. The grout may be applied on the same day provided the temperature requirements are complied with.

Note: After the open graded asphalt layer has been placed no traffic shall be allowed over this material, except for vehicles and equipment necessary for the grout intrusion. Should the asphalt become contaminated, the contamination shall be removed prior to the grout application. If water logging of the asphalt occurs work shall not proceed until the water has been dissipated from the air voids.

The grout shall be spread evenly onto the asphalt in accordance with manufacturer’s specifications. The grout shall be vibrated using a smooth drum vibrating rollers and/or vibrating plates until no further grout is accepted into the open graded asphalt layer.

All excess resin modified grout shall be removed from the surface. Finishing shall be carried out with a soft broomed finished texture.

10.5 CURING OF RESIN MODIFIED GROUT

A curing coat shall be applied in accordance with manufacturer’s specification after the initial set of the grout to avoid surface cracks.

Note: In hot weather the surface should be watered.

To fully gain its unique properties, trafficking of the surface shall not occur until the minimum curing periods specified in Table 9 have elapsed.

TRAFFIC CURING TIMES

Pedestrians 12 hours

Cars 24 hours

Small – Medium Trucks 7 to 14 days

Heavy Vehicles 14 days

Standing Loads 21 to 28 days

Oil and Chemical Spills 21 to 28 days

Table 9 - Curing Periods Salviacim™ Asphalt Wearing Surface

Page 23: ES-14-202-19

Roads and Paving

ES-14-202-19

Version No. 7.0 Page 23 of 31

Document last modified: 03 January 2013. Date printed: 17 January 2013.

11. GRAVEL PAVEMENT

11.1 BASE MATERIAL

Base course material shall be a lateritic gravel comprising of a combination of soil binder, sand and gravel which is free of vegetable matter, lumps or balls of clay and shall not contain large quantities of pyrites or other deleterious substances.

The Contractor shall provide samples of the proposed base material to the Superintendent for approval. Approved samples shall be safely stored on site. All subsequent material deliveries shall be of a quality appreciably the same as the relevant reference sample.

Particle size distribution shall conform to the limits specified in Table 4 for road base materials.

Note: Coarse aggregate retained on the 2.36 mm sieve shall consist of hard durable particles. Materials that break up when alternatively wetted and dried shall not be used. Fine aggregate passing the 2.36 mm sieve shall consist of natural or crushed sand and fine mineral particles that would pass the 600µm sieve. The ratio of the portion passing the 75µm sieve to the portion passing the 425µm sieve shall fall between the range of 0.4 to 0.6.

11.2 CONSTRUCTION

Construction details of gravel pavement shall be similar to subbase and base materials. For details refer to the following:

Gravel Placement Section 8.2

Gravel Compaction Section 8.3

Gravel Surface Finish Section 8.4

Gravel Surface Tolerance Section 8.5

12. FOOTPATHS

12.1 GENERAL

Footpaths shall be constructed from concrete, asphaltic concrete, paving bricks or gravel as specified in the Works, to the widths, depths and in the locations shown on the drawings or as directed by the Superintendent.

All footpaths shall be constructed with a uniform cross fall of 2% towards the kerb. The width of the footpath shall be 1200 mm unless specified otherwise.

Where the path is constructed in the road reserve, the longitudinal profile of the path shall be the same as the longitudinal profile of the adjacent kerbing. Elsewhere, the path longitudinal profile will maintain a uniform grading and generally conform to the surrounding finished ground or as indicated on the drawings.

Page 24: ES-14-202-19

Roads and Paving

ES-14-202-19

Version No. 7.0 Page 24 of 31

Document last modified: 03 January 2013. Date printed: 17 January 2013.

Note: Footpaths shall not be constructed until after all drainage, major verge clearing and kerbing has been finished.

12.2 CONCRETE FOOTPATHS

Unless specified otherwise by the Superintendent, concrete footpaths shall be 100mm thick, grade N32 concrete with a 60mm slump laid on compacted, graded clean sand. Placement and curing requirements shall comply with CSBP Engineering Standard Concrete (ES-14-202-10).

Unless specified otherwise by the Superintendent, contraction joints shall be constructed at 2m maximum centres, at the sides of entry points and at tangent points of curves, and shall be at right angles to the face of the kerbing or other concrete section. Contracted joints shall be a weakened plane joint finished using a jointing tool and smooth trowel-finish for 80mm either side of the joint.

Expansion joints, in the form of a 12mm full depth gap between adjacent sections of concrete shall be constructed at 6m intervals. An approved 12mm thick bitumen impregnated filler board shall be inserted in the joint to full depth of concrete and to finish flush with the surface of the path. Expansion joints shall be marked out with an edging tool to match the appearance of the contraction joints.

The surface of the path shall be broomed finish other than joint and longitudinal edges as described above.

12.3 ASPHALTIC CONCRETE FOOTPATHS

Unless specified otherwise, footpaths shall be 25mm thick Grade AC5 asphaltic concrete, laid on a minimum compacted limestone base course thickness of 150mm. The base course shall extend 200 mm beyond the edge of the seal if kerbing is not used. Edges of asphaltic concrete shall be protected by flush kerb or timber formwork as directed by the Superintendent.

Asphaltic concrete footpaths shall be constructed in a similar manner as for asphaltic concrete roads and pavements. Refer to Section 9 for details.

12.4 PAVING BRICK FOOTPATHS

Competent personnel experienced in laying the selected materials shall carry out the work. Paving bricks shall be laid on compacted, graded clean sand and uniformly compacted in accordance with the manufacturer’s recommendations.

Bricks shall be laid evenly, with height difference between adjacent bricks being no greater than 1mm. Header courses shall be concrete bonded to ensure bricks do not move.

Any paving bricks damaged during placement or compaction shall be removed and replaced by new ones.

12.5 GRAVEL FOOTPATHS

Gravel footpaths shall be constructed from materials and in a similar manner as for gravel pavements. Refer to Section 11 for details.

Page 25: ES-14-202-19

Roads and Paving

ES-14-202-19

Version No. 7.0 Page 25 of 31

Document last modified: 03 January 2013. Date printed: 17 January 2013.

13. INSPECTION

Activities specified in Table 10 shall not commence until the Superintendent has approved the corresponding item.

ACTIVITY ITEM TO BE APPROVED REFERENCE

Testing base layer and if applicable, the subbase layer

Timing and location of tests Section 14

Prior to laying the subbase course, if specified in design drawings and documentation

Setting out, alignment, levels and gradients of roads and paved areas

CSBP Engineering Standard Earthworks and Site Preparation (ES-14-202-01)

Subgrade Compaction Test Certificates

Subbase reference sample Section 8.1.1 and 11.1

Prior to laying the base course

Subbase Compaction Test Certificates Section 8.3.1 and 14

Alignment, levels and gradients of Subbase

Section 8.2

Base reference sample Section 8.1.1 and 11.1

or

IF THERE IS NO SUBBASE COURSE

Setting out, alignment, levels and gradients of roads and paved areas

CSBP Engineering Standard Earthworks and Site Preparation (ES-14-202-01)

Subgrade Compaction Test Certificates

Base reference sample Section 8.1.1 and 11.1

Prior to priming and sealing of base course, where specified

Base Compaction Test Certificate Section 8.3.1 and 14

Alignment, gradients and levels of base course

Section 8.2

Completing the Works

Alignment, gradients, finish and levels of wearing surface

Asphalt surface: Sections 9.9, 9.10, 9.11

Gravel surface: Sections 8.4, 8.5

Table 10 - Superintendent Approved Inspection Activities

Page 26: ES-14-202-19

Roads and Paving

ES-14-202-19

Version No. 7.0 Page 26 of 31

Document last modified: 03 January 2013. Date printed: 17 January 2013.

14. TESTING

14.1 GENERAL

All sampling and in-situ density testing and other soil tests as specified shall be carried out by a suitably qualified and NATA approved testing agency.

Tests of paving materials shall conform to this Standard and shall be in accordance with Australian Standards 1141 and 1289.

Density tests shall be carried out not later than 24 hours after compaction has been completed for each layer. Where specified, results shall be verbally submitted to the Superintendent prior to the placement of the next layer. The NATA approved testing agency shall within seven (7) days of testing, confirm test results in writing to the Superintendent and the Contractor.

14.2 FREQUENCY OF TESTING

Frequency of testing for every layer shall be as shown in Table 9.

LOCATION OF TEST FREQUENCY OF TEST

Roads • One test per layer for each 150 metres of road to be constructed

Laydown areas, car parks etc. • One test for each 250 m³ or part thereof of paving material incorporated in the job, with

• Minimum three tests for each pavement area tested

Table 11 - Compaction Testing Frequency

Note: When specified by the Superintendent, random tests shall be carried out at locations where compaction limits have been defined.

14.3 REJECT WORK

Where the field density of the compacted subbase or base course, as determined by test, is less than the specified percentage compaction in Section 8.3.1, the layer shall be reworked and retested until the required compaction is achieved.

15. STORM WATER AND SUB-SOIL DRAINS

Where specified in the Works or on drawings storm water and subsoil drainage systems shall be installed in accordance with CSBP Engineering Standard Drains (ES-14-202-24).

Note: The Contractor shall ensure that pooling of water does not occur except at designated locations.

Page 27: ES-14-202-19

Roads and Paving

ES-14-202-19

Version No. 7.0 Page 27 of 31

Document last modified: 03 January 2013. Date printed: 17 January 2013.

16. KERBING

16.1 GENERAL

Concrete kerbing shall be site machine extruded unless directed otherwise by the Superintendent.

Barrier, semi-mountable, mountable, precast, cast-on-pavement and layback type kerbing shall be used where specified on the drawings or as directed by the Superintendent.

Materials, profiles, placement tolerances, surface finish, jointing, inspection, sampling and testing shall comply with AS 2876.

16.2 DESIGN AND CONSTRUCTION

The line of the kerbing shall be parallel to the centreline of the road unless shown otherwise on the drawings and laid to grades corresponding to the road grades, radius sweeps and intersections.

Kerb transitions shall be constructed between adjoining sections of kerbs of different profile. The change from one section to the other shall be made uniformly over the length shown on the drawing or as directed by the Superintendent.

Openings shall be formed or kerbing cut to form storm water drainage outlets, at locations shown on the drawings or as directed by the Superintendent. Ends of kerbing shall be chamfered at 45° and trowelled to a smooth finish to match adjacent kerbing.

For small radii or where there is a lack of clearance preventing the kerb being placed by the extrusion machine the kerbing section shall be “hand placed”. Hand placed sections shall be constructed to the satisfaction of the Superintendent, using the same concrete as the remainder of the kerb and shaped to give a profile and finish that matches the adjoining sections.

When kerbing is not to be trenched or keyed, the surface on which the kerb is to be laid must be cleaned of all foreign or loose and broken pavement material and may require dampening prior to commencing concrete extrusion. Exposed faces of extruded kerbing shall be covered with black polythene sheeting or sprayed with an approved curing compound to protect against moisture loss from the setting concrete. It is the Contractor’s responsibility to protect the kerbing using whatever measures are required during the curing period.

For typical kerbing arrangement, refer to Figure 6.

Page 28: ES-14-202-19

Roads and Paving

ES-14-202-19

Version No. 7.0 Page 28 of 31

Document last modified: 03 January 2013. Date printed: 17 January 2013.

Figure 6 - Typical Kerbing Arrangement

17. SPEED HUMPS

Speed humps shall be constructed of asphaltic concrete, same grade as the road, and installed at locations shown on the drawings. They shall be installed at right angles to the direction of traffic and extend laterally across the full width of the pavement, except where it is necessary to allow for drainage, and shall be either:

Type 1 Used as a warning when approaching a hazard e.g. carpark entrance

Type 2 Used at locations where the driver must slow down e.g. at a major intersection

Front and trailing edges of humps shall be cut into the seal to ensure edge thickness is maintained. Refer to Figure 5 for size and profile of speed humps.

On the approach side(s) of the speed hump, the surface of the hump from road level to the crest shall be painted with white paint.

Page 29: ES-14-202-19

Roads and Paving

ES-14-202-19

Version No. 7.0 Page 29 of 31

Document last modified: 03 January 2013. Date printed: 17 January 2013.

Figure 7 Speed Hump Profile

18. ROAD MARKING

The Contractor shall paint lines and other markings on the sealed surface at locations shown on the drawings or as directed by the Superintendent in accordance with CSBP Engineering Standard Road Marking (ES-14-202-22).

19. ACCESS TO SERVICES

Where required, the Contractor shall install ‘Gatic” trafficable pits and lids at locations shown on the drawings or as directed by the Superintendent. The trafficable lids shall be suitably sized to allow access to the services below, sealed to prevent ingress of water, dirt etc and be capable of withstanding the intended loading in accordance with AS 3996.

Page 30: ES-14-202-19

Roads and Paving

ES-14-202-19

Version No. 7.0 Page 30 of 31

Document last modified: 03 January 2013. Date printed: 17 January 2013.

20. ROAD SIGNS

The Contractor shall supply and install traffic directional and warning signs at locations shown on the drawings or as directed by the Superintendent in accordance with CSBP Engineering Standard Safety and Information Signs (ES-14-102-08) and Australian Standards 1742 and 1743.

21. GUARD RAILS AND BOLLARDS

Where required, the Contractor shall install bollards and ‘Armco’ type or other approved equivalent guardrails in the locations shown on the drawings or as directed by the Superintendent. Refer to CSBP Standard Drawing 9900-2-1300/001 for standard bollard details.

22. REINSTATEMENT

Existing ground surfaces including paving, roadwork, lawn and natural vegetation areas, that was removed, disturbed or damaged by the Works activities, shall be reinstated by the Contractor to match existing and adjacent ground, to the satisfaction of the Superintendent.

Fences that were removed or damaged during the Works shall be reinstated in accordance with CSBP Standard Drawing 9900-2-0600.

23. REPAIRS TO EXISTING BITUMEN

Repairs to bitumen paving shall be carried out in accordance with the following:

a. All loose material shall be brushed out of the crack or pothole.

b. Very fine cracks shall be filled with bitumen emulsion diluted in accordance with manufacture’s instructions.

c. Intermediate and wider cracks shall be filled with bitumen emulsion and sand filler if required, in accordance with manufacture’s instructions.

d. Potholes shall be saw cut back to form a regular shape in the bitumen, the existing limestone base compacted and a tack coat applied to the edges of existing pavement prior to patching with asphalt to ensure effective bonding.

Note: Cracked hot–mix paving must be attended too as water will penetrate to the base course and rapid deterioration will result. Applying another layer of asphalt over the top of the crack will not solve the problem, as the crack will propagate up through the new layer.

Page 31: ES-14-202-19

Roads and Paving

ES-14-202-19

Version No. 7.0 Page 31 of 31

Document last modified: 03 January 2013. Date printed: 17 January 2013.

24. RECORDS MANAGEMENT

24.1 AS-BUILT DRAWINGS

On completion of the Works the Contractor shall prepare an as-built paving survey for approval by the Superintendent.

Drawings shall be upgraded in accordance with approved survey results. Responsibility for revising the drawings shall be specified in the Works.

Drawings recording the as-built details, shall be prepared / revised, numbered, approved and handed over in accordance with CSBP Engineering Standards:

ES-14-101-02 Drawing Management

ES-14-101-03 Drawing Preparation

ES-14-101-04 Drawing Numbering

24.2 DENSITY AND COMPACTION TEST RESULTS

Density and compaction test results issued by the NATA approved testing agency shall be retained in the engineering project file.