erosion and sediment control plan

13
Erosion and Sediment Control Plan Brizzolara Creek MNMS Erosion Consultants 1 Grand Avenue San Luis Obispo, CA 93410 Mary Hillis [email protected] Nico Navarro [email protected] Mackenzie Taggart [email protected] Sarah Treadwell [email protected]

Upload: mackenzie-taggart

Post on 14-Apr-2017

313 views

Category:

Documents


5 download

TRANSCRIPT

 Erosion  and  Sediment  Control  Plan  

Brizzolara  Creek                                

       

   

MNMS  Erosion  Consultants    1  Grand  Avenue  

San  Luis  Obispo,  CA  93410                      

Mary  Hillis    [email protected]  Nico  Navarro    [email protected]  

Mackenzie  Taggart    [email protected]  Sarah  Treadwell    [email protected]  

   

   

Table  of  Contents        1. Introduction  

1. Introduction  to  Brizzolara  Creek  Erosion  &  Sediment  Control  Plan  2. Goals  and  Objectives    3. Regulatory  Requirements  of  the  Proposed  Project  

 2. Site  Assessment    

1. Aerial  Map  of  Brizzolara  Creek  Site  2. Produced  Map  of  Brizzolara  Creek  Site  Depicting  Project  Plans  3. Site  Description    

1. Soils,  Vegetation,  Landscape  2. Sources  of  water  and  sediment  3. Site  Measurements  4. Evaluation  of  erosion    

 3. Erosion  and  Sediment  Control:  Best  Management  Practices    

1. J-­‐Hook  2. Riprap  3. Erosion  Control  Netting  4. Bioretention  Planters  

 4. Maintenance  and  Inspection  Procedures  For  Project    

1. Schedule  of  procedures  and  planned  inspections  2. Description  of  Maintenance:  J-­‐Hook  3. Description  of  Maintenance:  Riprap  4. Description  of  Maintenance:  Erosion  Control  Netting  5. Description  of  Maintenance:  Bioretention  Planters  

 5. Certifications  and  Notifications      6. Conclusion    7. References                    

1.  Introduction    1.1    Introduction  To  Brizzolara  Creek  The  purpose  of  this  project  is  to  mitigate  channel  erosion  at  the  stream  meander  north  of  Engineering  IV  building  on  the  California  Polytechnic  State  University  San  Luis  Obispo,  CA.    The  outer  bank  of  the  stream  meander  has  been  laterally  eroded,  leaving  unstable  slopes  that  threaten  the  adjacent  faculty  parking  lot  and  the  overall  channel  health.    In  addition  to  the  lateral  erosion,  additional  problems  exist  that  are  a  detriment  to  the  channel  health.    The  main  channel  problems  include:  

• Lateral  erosion  of  outer  bank  • Sedimentation  • Destruction  of  aquatic  habitat  and  terrestrial  vegetation  • Metal  scrap  waste  embedded  in  outer  bank  

1.2 Goals  &  Objectives  This  project  will  focus  on:    

• Stabilize  the  eroding  outer  bank  • Centralize  stream  flow  • Remove  scrap  metal  along  stream  bed  and  outer  bank  • Improve  overall  quality  of  channel      

1.3 Regulatory  Requirements  of  Proposed  Project    There  are  three  main  agencies  that  have  jurisdiction  over  amendments  made  in  Brizzolara  Creek.  These  agencies  and  their  jurisdiction  are  explained  below.      California  Department  of  Fish  and  Wildlife  (CDFW):  It  is  necessary  to  notify  the  (CDFW  before  undergoing  streambed  alteration.    Under  the  Fish  and  Game  Code  1602,  it  is  necessary  to  notify  the  CDFW  if  any  alterations  are  made  to  a  stream.    After  notifying  the  CDFW,  a  Streambed  Alteration  Agreement  must  be  made  to  permit  activity.    The  agreement  process  in  with  the  CDFW  must  comply  with  the  California  Environmental  Quality  Act  (CEQA).    The  lead  agency  (local  or  state  agency  with  approving  authority),  which  can  be  the  CDFW,  must  make  sure  the  alteration  complies  with  the  CEQA.    Aside  from  contacting  the  CDFW  it  is  also  important  to  determine  of  local  permits  are  necessary  and  if  the  project  is  under  the  jurisdiction  of  federal  and  state  agencies  (CDFW,  2014).  

 US  Army  Corps  of  Engineers  (USACE):  In  the  case  of  of  stream  alteration  the  movement  of  materials  within  the  streambed  requires  a  USACE  404  Nationwide  Permit  (VCPD,  2006).    This  permit  falls  under  section  404  of  the  Clean  Water  Act  (CWA),  which  regulates  discharge  of  dredged  or  fill  material  into  the  water  of  the  US  (EPA,  2014).  

Regional  Water  Quality  Control  Board  (RWQCB)  :  A  401  Certification  from  the  RWQCB  is  necessary  when  obtaining  a  USACE  404  Permit.    This  permit  falls  under  section  401  of  the  CWA  which  declares  that  each  state  must  certify  that  the  federally  permitted  activities  (in  this  case  issued  from  the  USACE)  are  in  compliance  with  all  state  water  quality  standards  (VCPD,  2006).    

 2.  Site  Assessment        

2.1 Aerial  Map  of  Brizzolara  Creek  Site      

                       

Brizzolara  Creek  Project  Site  

2.2 Produced  Map  of  Brizzolara  Creek  Site                                                                                    

       

 2.3 Site  Description    The  Brizzolara  creek  site  is  located  northeast  of  the  California  Blvd  and  Highland  Dr  intersection  on  the  Cal  Poly  campus.  The  vegetation  includes  mainly  willows  and  eucalyptus  trees  with  some  herbaceous  vegetation  sprouting  along  the  streambed  and  higher  up  on  the  banks.  The  streambed  along  the  northern  segment  of  the  site  is  exposed  bedrock,  while  the  southern  section  consists  of  mainly  cobbles  three  to  five  inches  in  width.  The  creek  is  currently  dry,  however  runoff  from  previous  events  has  caused  significant  erosion  on  the  outer  edge  of  the  stream  meander,  along  the  northern  bank.  This  past  erosion  is  evident  through  the  steep  and  mostly  unvegetated  northern  slope  adjacent  to  Highland  Dr.  In  addition,  there  is  a  high  percentage  debris  embedded  in  the  northern  bank  of  the  stream  channel.  The  southern  bank,  which  represents  the  inside  of  the  meander,  displays  a  significantly  lower  relief  than  the  northern  slope  and  is  highly  vegetated.    

2.3.1      Description  of  Soils  and  Vegetation    The  soils  at  the  Brizzolara  Creek  site  are  classified  as  silty  clay  loam,  and  are  part  of  the  Salinas  soil  series.  These  soils  formed  from  alluvial  parent  material  deposits  from  weathered  sedimentary  rock.  The  soil  is  well  drained  thanks  to  its  composition  and  is  part  of  hydrologic  soil  group  C.  The  K-­‐factor  for  this  soil  is  .32;  this  is  a  relatively  high  soil  erodibility  factor  and  is  due  to  the  high  content  of  silt,  which  is  easily  eroded.  The  average  annual  temperature  in  this  area  is  68-­‐70  degrees  Farenheit  and  the  average  annual  precipitation  is  around  23.45  inches  

 2.3.2        Sources  of  Water  and  Sediment    There  are  three  main  culverts  that  drain  into  Brizzolara  Creek  site  within  the  designated  project  area.  These  culverts  supply  water  runoff  and  sediment  from:  an  unpaved  road  running  alongside  the  creek  upland  from  the  southern  bank,  roof  drainage  from  engineering  building  192,  and  the  parking  lot  adjacent  to  the  creek.  These  culverts  funnel  sediment  and  debris  from  the  three  sources  straight  into  the  creek,  and  pose  a  problem  for  the  sensitive  habitats  of  Stenner  and  other  San  Luis  Obispo  creeks  downstream  of  Brizzolara.  Runoff  and  discharge  from  the  Horse  Canyon  Watershed  also  contribute  to  the  water  and  sediment  levels  of  Brizzoalra  Creek.    

 2.3.3      Measurements  of  Site    The  designated  watershed  area  contributing  runoff  and  erosion  at  the  Brizzolara  Creek  site  is  approximately  3.2  square  miles.  The  measured  streambed  length  at  the  project  site  is  49  feet.  The  average  width  of  the  streambed  is  10.5  feet,  and  the  average  depth  of  the  channel  is  6.5  feet,  yielding  a  cross  sectional  area  of  68.3  square  feet.    

 2.3.4        Evaluation  of  Erosion  and  Sediment  Delivery    Field  measurements  of  features  were  taken  at  the  project  site  and  used  to  calculate  BEHI  and  Shear  Stress  ratings.  The  bank  erosion  rate  for  current  and  future  conditions  was  then  calculated  based  on  these  ratings:    

 Current  Condition:  Brizzolara  Creek  is  currently  eroding  on  the  northern  slope  of  the  channel.  This  slope  exhibits  a  steep  grade,  a  low  percentage  of  surface  protection,  and  a  shallow  rooting  depth  for  vegetation.  Based  on  these  observations  and  an  assessment  of  bank  materials,  the  initial  BEHI  calculation  resulted  in  an  “extreme”  rating  for  the  hazard  of  bank  erosion.  Similarly,  

the  initial  rating  for  Shear  Stress  also  resulted  in  an  “extreme”  rating.  Based  on  both  the  initial  ratings,  the  determined  bank  erosion  rate  is  2.8  ft/yr.    

 Future  Condition  Without  BMP’s:  When  calculating  the  predicted  future  BEHI  and  Shear  Stress  ratings  for  the  area  of  interest,  it  was  determined  that  most  of  the  channel  conditions  would  remain  constant.    The  foreseeable  changes  are  a  higher  relief  on  the  northern  slope  as  it  continues  to  be  affected  by  lateral  scour      and  a  smaller  a  decrease  in  surface  cover.  Based  on  these  conclusions,  the  BEHI  and  Shear  Stress  ratings  the  are  also  rated  “extreme”.    The  continually  degrading  conditions  result  in  a  slightly  higher  bank  erosion  rate  of  2.9  ft/yr.  

 Future  Condition  With  BMP’s:  The  proper  installation  of  Best  Management  Practices  (BMP)  will  help  to  improve  channel  conditions  and  consequently  decrease  the  bank  erosion  rate.    The  BMP’s  utilized  will  reduce  the  slope  of  the  banks,  increase  surface  protection,  and  reduce  the  near  bank  maximum  depth.  These  improvements  will  reduce  both  the  bank  erosion  hazard  and  shear  stress  ratings  to  low,  resulting  in  a  bank  erosion  of  .04  ft/yr.    

   

3. Erosion  and  Sediment  Control:  Best  Management  Practices        

3.1      Overview  of  BMP’s  and  Implementation  at  Project  Site    Numerous  Best  Management  Practices  (BMPs)  will  be  used  to  divert  stream  flow,  decrease  stream  bank  erosion,  create  habitat  for  wildlife,  and  beautify  the  Brizzolara  Creek  site.  A  J-­‐hook  will  be  secured  slightly  upstream  from  the  highly  erosive  north  bank  of  the  Brizzolara  Creek  bank,  diverting  flow  away  from  the  outer  portion  of  the  stream  meander.  The  large,  inactive,  concrete  culvert  feeding  into  the  creek  will  be  taken  out  and  replaced  with  logs  and  riprap  on  the  creek  bed  to  protect  the  bank.  The  use  of  riprap  along  the  northern  bank  will  prevent  further  downward  erosion  of  the  streambed  in  this  area,  and  will  stabilize  the  slope,  preventing  scour  of  bank  materials  and  loss  of  sediment.    Excavating  the  highly  eroded  stream  bank  will  be  the  first  of  many  BMPs  applied  to  the  unstable,  highly  eroded  stream  bank.  Cutting  the  near  vertical  slope  back  to  a  grade  of  1:1,  45-­‐degree  angle  will  decrease  the  chance  of  mass  wasting  and  sediment  erosion.  While  excavation  equipment  is  in  the  creek,  the  rusting  iron  debris  will  be  removed.  Following  grade  control  on  the  north  bank,  a  series  of  BMPs  will  be  implemented  in  order  to  insure  its  stability  and  is  conducive  to  wildlife  

 Initially,  a  layer  of  compost  two  inches  thick  will  be  raked  evenly  on  the  stream  bank.  Seed  will  be  incorporated  into  this  thick,  woody  mixture  to  cut  cost  and  simplify  the  application  process.    Compost  was  chosen  because  it  improves  soil  quality,  protects  the  ground  from  splash  erosion,  and  provides  plants  with  nutrients  overtime  (Caltrans,  2014).  The  seed  mix  will  contain  native  grasses,  forbs,  and  legumes  (Caltrans,  2010).  Succeeding  the  compost,  a  layer  of  Coconut  Netting  will  blanket  the  stream  bank,  secured  with  pins.  This  rolled  erosion  control  product  is  available  in  several  strengths;  Type  B  will  be  sufficient  considering  the  weight  of  mat  and  the  amount  of  space  left  open  in  the  weave.    A  coconut  fiber  mat  was  chosen  for  its  ability  to  withstand  a  1:1  embankment,  degradable  material,  retention  of  soil  moisture  for  germination  of  seeds,  and  safeguard  soil  from  erosion  (Caltrans,  2014).  Willow  Cuttings  will  then  be  planted  systematically  

along  the  bank  through  the  open  spaces  in  the  netting.    Willows,  native  to  the  area,  thrive  in  stream  communities  providing  long-­‐term  strength  of  not  only  the  riverbank,  through  extensive  root  systems,  but  also  in  offering  animal  habitat  (WVDEP,  2014).  Plantings  of  a  variety  of  other  native  shrubs  and  grasses  within  the  willows  and  coconut  mat  structure  will  finalize  the  efforts  taken  to  assure  the  once  eroded  Brizzolara  stream  bank  is  stable  for  years  to  come.  On  the  top  of  the  bank,  bioretention  planters  will  be  utilized  to  divert,  hold,  filter,  and  infiltrate  stormwater  running  off  of  impermeable  surfaces  such  as  the  adjacent  parking  lot  all  while  creating  an  aesthetically  pleasing  environment.  

 3.2      J-­‐Hook  A  j-­‐hook  is  a  structure  used  to  redirect  stream  flow  for  urban  stream  repair  purposes.    The  j-­‐hook  is  an  upstream  directed,  gently  sloping  structure  consisting  of  natural  materials  including  but  not  limited  to  boulders,  logs,  and  root  wads  or  a  combination  of  materials.    The  structure  is  placed  at  a  20  to  30  degree  angle  on  the  outer  bend  of  the  stream  meander  where  the  highest  stream  velocity  occurs  (Rosgen,  2014).    There  are  two  sections  of  the  j-­‐hook,  the  vane  and  the  hook.    The  vane  consists  of  the  straight  section  that  covers  approximately  ⅓  of  the  banfkfull  width.    No  gaps  exist  in  the  structure  on  the  vane  section.    The  hook  section  consists  of  the  curved  section  of  the  structure.    Small  gaps  exist  in  the  hook  section.    The  j-­‐hook  helps  to  reduce  bank  erosion  along  the  stream  bank  toe  by  centralizing  flow.  Centralizing  flow  helps  to  mitigate  stream  bank  erosion  by  reducing  near-­‐bank  slope,  velocity,  and  shear  stress.  The  j-­‐hook  is  effective  to  three  times  its  length.    As  the  water  travels  downstream,  the  j-­‐hook  forces  the  flow  towards  the  center  and  allows  the  shear  stress  to  be  concentrated  in  the  center  of  the  channel.    The  vane  helps  creates  a  scour  pool  downstream.    The  hook  section  works  in  conjunction  with  the  vane  section  by  creating  a  longer,  deeper,  wider  pool.    The  gaps  within  the  hook  section  create  a  vortex  flow  pattern  that  further  helps  to  centralize  flow  and  increase  transport  of  sediment  and  debris  (Schueler  and  Brown,  2014).    The  increased  depth  helps  the  stream  accommodate  larger  floods,  increases  cross-­‐sectional  area,  and  ultimately  helps  reduces  bank  erosion.    

 3.3      Riprap  At  the  Brizzolara  Creek  site,  the  creek  takes  a  tight  right  before  continuing  downstream  of  the  area  of  interest.  This  turn  concentrates  the  energy  of  the  creek  directly  at  the  Northern  bank  before  it  can  continue  around  the  turn,  and  results  in  serious  erosion  and  instability  of  the  bank  and  the  streambed.  The  BMP  we  will  use  to  stabilize  the  streambed  and  lower  bank  from  further  erosion  is  riprap.  

 Riprap  is  the  use  of  large  stones  placed  in  a  layer  over  or  under  a  specific  area  to  prevent  soil  erosion  due  to  concentrated  runoff  (NPDES,  2014).  Riprap  can  be  effective  for  stabilization  on  slopes  as  well,  however  it  can  also  become  unstable  under  certain  conditions,  such  as  using  rounded  rocks,  or  with  slopes  steeper  than  2:1  (FHWA,  2014).  In  order  to  ensure  the  successful  implementation  of  riprap,  there  are  some  guidelines  that  must  be  followed,  these  include:  using  a  durable  stone  in  various  rock  sizes,  ensuring  your  riprap  layer  extends  deep  enough  to  two  times  the  maximum  stone  diameter,  and  placing  the  riprap  high  enough  along  banks  above  the  maximum  flow  depth  (NPDES,  2014).  At  our  site,  we  will  dig  out  an  area  about  eight  feet  in  length  and  five  in  depth  along  the  base  of  the  Northern  bank  where  the  creek  follows  the  turn;  we  will  then  fill  the  

area  with  a  layer  or  rip  rap  and  backfill  the  area  with  the  displaced  soil.  This  underlying  layer  of  riprap  will  serve  as  a  toe  protection  along  the  base  of  the  Northern  bank,  and  will  prevent  the  further  downward  erosion  of  the  streambed  by  the  creek  and  it  follows  the  sharp  turn.  The  riprap  will  be  continued  upward  two  feet  in  height  above  the  streambed  to  provide  for  extra  stabilization  of  the  bank.  Riprap  serves  as  a  cost  effective,  durable  solution  for  stabilizing  this  small  area  of  our  project.    

 3.4      Erosion  Control  Netting  

The  rolled  erosion  control  netting  product  is  made  of  100%  coconut  fiber  woven  into  a  checked  pattern.  It  is  produced  in  three  different  strengths;  Type  B,  as  defined  on  Caltrans,  will  be  sufficient  considering  the  weight  of  the  mat  (700  grams/sq.  meter)  and  the  50%  open  space  left  in  the  weave.  Type  B  netting  will  be  effective  up  to  a  1:1  slope  unlike  counter  products  such  as  Jute  or  even  Type  A  netting.  Coconut  netting  lasts  up  to  three  years,  giving  the  willows  and  plants  substantial  time  to  become  established.  A  limitation  to  rolled  erosion  control  options  is  their  expense.  However,  200  square  feet  maximum  would  be  the  needed,  rounding  out  the  cost  under  $190  (Caltrans,  2014)    Benefits  of  the  netting  include:  

• Provides  immediate  protection  of  the  soil  while  plants  are  still  young.  The  weave  is  slightly  tighter  than  many  woven  mats,  allowing  a  greater  stability  of  the  slope  at  early,  vulnerable  stages.  

• The  Natural  fibers  retain  soil  moisture,  improving  the  germination  of  seeds  and  plant  growth  (Caltrans,  2014).  This  is  a  necessity  in  the  dry  climate  of  the  Brizzolara  Creek.  

• Many  erosion  control  rolled  products  are  partial  produced  with  synthetic  material.  This  netting  is  fully  biodegradable,  a  key  in  a  self  regulating,  natural  environment.  

The  application  of  netting  follows  a  similar  process  to  other  rolled  erosion  products.  Begin  with  digging  an  anchor  trench  6  inches  deep  at  the  top  of  the  slope,  the  length  of  the  bank  wished  to  be  covered  (McCullough,  2014).  Place  the  first  4  inches  of  the  netting  in  the  trench  and  secure  with  metal  U  pins  2  feet  apart  and  cover  with  soil.  Roll  out  the  track  working  downhill  a  few  yards  at  a  time.  Catch  the  roll  using  wooden  stakes  so  adjustment  to  the  tautness  and  securing  of  the  netting  can  be  made  easily.  Drive  in  U  pins  every  3  feet  in  a  diagonal  pattern.  Once  the  roll  netting  has  covered  the  entire  slope,  make  an  anchor  trench  identical  to  the  anchor  head.  Staple  4  inches  of  excess  netting  into  the  trench  before  cutting  it  off  from  the  roll.  Finally,  burry  and  compact  the  trench  with  soil.    

 3.5      Bioretention  Planters    

The  Brizzolara  Creek  Site  Project  lies  adjacent  to  an  older  staff  parking  lot  across  Highland  Drive  from  building  192:    Engineering  IV  (see  Figure  1.  location  map).    Runoff  from  the  parking  lot  into  Brizzolara  Creek  occurs  in  the  upper  east  portion  on  the  north  bank  where  asphalt  erosion  is  evident.    Following  the  erosion  control  BMPs  executed  on  the  north  bank  of  Brizzolara  Creek  it  will  be  important  to  control  runoff  coming  onto  the  bank  from  the  parking  lot  area  in  order  to  maintain  structural  integrity.    Stormwater/bioretention  planters  utilize  soil  and  plants  to  infiltrate,  slow,  and  clean  stormwater  coming  off  of  impervious  surfaces  (Central  Coast  LIDI,  2014).    Stormwater  runoff  from  the  adjacent  staff  parking  lot  will  be  diverted  into  the  bioretention  planters  where  it  will  be  temporarily  held,  filtered,  and  infiltrated  into  the  

surrounding  substrate.    Excess  runoff  exiting  the  planters  into  the  creek  bed  will  be  slower  and  cleaner  as  a  result  (Caltrans  Erosion  Toolbox,  2014).    

 Some  general  parameter  of  parking  lot  Bioretention  Planters  include:    

• The  recommended  depth  of  soil  in  the  planters  is  24  inches  with  an  underdrain,  although  18  inches  is  the  legal  minimum.  

• Curb  height  and  gutter  width  are  also  recommended  to  be  24  inches  -­‐  providing  additional  structural  support.  

• Maintain  a  6”  wide  “bench”  of  native  soil  at  the  sides  of  the  planters  to  maintain  sidewalks  stability.  

• A  layer  of  filter  fabric  is  used  between  the  topsoil  layer  and  the  bottom  aggregate  layer.    This  allows  the  aggregate  layer  to  store  additional  stormwater  apart  from  water  stored  in  the  soil  layer  

3.6      Evaluation  of  Future  Erosion    The  current  bank  erosion  at  the  Brizzoalra  creek  site  is  2.8  ft/yr,  with  estimated  future  erosion  to  be  slightly  higher  at  2.9  ft/yr.  Through  the  use  of  the  identified  best  management  practices,  the  future  erosion  of  Brizzolara  creek  will  be  reduced  to  .04  ft/yr.  The  bank  erosion  hazard  and  shear  stress  will  also  be  significantly  decreased  after  BMP  implementation,  with  a  new  rating  of  low  for  both.      

4.      Maintenance  &  Inspection  of  BMP’s      

4.1      Maintenance  &  Inspection  of  J-­‐Hook      J-­‐hooks  are  generally  a  sturdy  BMP  and  require  low  levels  of  maintenance.  Problems  such  as  sediment  or  debris  accumulation  behind  the  hook  can  occur,  which  could  cause  damage  to  the  hook  and  reduce  its  effectiveness.  For  best  results,  the  J-­‐hook  should  be  inspected  after  heavy  rainfall  and  once  monthly.  If  accumulated  material  is  present,  they  should  be  removed,  and  any  damage  caused  should  the  j-­‐hook  should  be  remedied  right  away.      4.2      Maintenance  &  Inspection  of  Riprap  In  order  to  maintain  the  integrity  of  the  riprap,  the  area  will  be  inspected  at  minimum  once  a  year  to  survey  damages  and  necessary  management.  The  riprap  will  also  be  inspected  after  large  storms  where  excess  rainfall  may  have  caused  damage  to  the  integrity  of  the  riprap.  (NPDES,  2014)    Riprap  when  implemented  according  to  the  proper  guidelines,  is  a  relatively  sturdy  BMP  and  will  not  require  minimal  maintenance.  If  the  riprap  structure  is  damaged,  it  must  be  repaired  promptly  before  the  creek  can  cause  more  damage.  If  it  becomes  clear  the  riprap  continues  to  be  damaged  in  a  particular  spot  of  in  a  particular  way,  measurements  of  our  area  of  interest  will  be  taken  and  the  design  of  the  riprap  implementation  will  be  reevaluated.  Changes  will  be  made  in  regards  to  the  new  findings  of  inspection.  At  our  site  we  plan  to  integrate  the  use  of  other  BMP’s  such  as  Willow  stakes  and  brush  mattresses  along  with  our  implementation  of  riprap.  These  other  management  practices  will  ensure  the  stabilization  of  the  upper  bank  slopes  as  well  as  protect  the  soil  surrounding  the  riprap.    

 4.3      Maintenance  &  Inspection  of  Erosion  Control  Netting  Project  will  be  completed  around  late  summer.  This  allows  the  system  time  to  become  established  before  the  rainy  season.  In  the  weeks  following  the  development,  inspection  of  the  stream  bank  includes:  netting  is  still  secured,  seeds  are  germinating,  and  willows  and  other  vegetation  are  taking  root.  This  will  also  include  irrigation  of  the  plants  if  little  precipitation  falls,  until  they  become  more  mature.  After  heavy  rain  events  visual  checks  should  be  made  to  the  netting  to  ensure  none  has  come  loose.  After  a  few  months  of  careful  watch  and  potentially  watering,  the  vegetation  should  be  established  and  the  bank  protected  and  self  sustaining.    

 4.4      Maintenance  &  Inspection  of  Bioretention  Planters    Perennial  plants  and  trees  will  need  some  irrigation  during  the  dry  season  (June-­‐October  in  San  Luis  Obispo).    Average  watering  schedules  for  mature  established  plants  and  trees  is  approximately  weekly  with  1”  of  water  per  application.    Drip  irrigation  inspections  should  be  conducted  routinely  to  make  sure  that  water  is  being  used  efficiently  without  waste.  Reservoirs  receive  water  prior  to  infiltration  and  should  be  maintained  for  clogging.    Inspecting  for  debris  and  sediment  pre  and  post  wet  season  should  be  conducted  during  the  month  of  May,  and  again  in  October.    Sand,  gravel,  and  topsoil  allow  stormwater  to  percolate  uniformly  through  the  planter.    Inspections  and  maintenance  should  focus  on  any  holes  that  are  not  consistent  with  the  system  to  prevent  water  from  flowing  directly  through  the  planter.    Also,  litter  and  debris  shall  be  removed  during  inspections.    Inspections  should  be  conducted  prior  to  and  directly  after  the  wet  season  in  May  and  again  in  October.  Any  cracks  or  failure  spots  should  be  repaired  throughout  the  year  during  regular  inspections.  

 5.  Certifications  &  Notifications      I  certify  under  penalty  of  law  that  this  document  and  all  attachments  were  prepared  under  my  direction  or  supervision  in  accordance  with  a  system  designed  to  assure  that  qualified  personnel  properly  gathered  and  evaluated  the  information  system,  or  those  persons  directly  responsible  for  gathering  the  information,  the  information  submitted  is,  to  the  best  of  my  knowledge  and  belief,  true,  accurate,  and  complete.  I  am  aware  that  there  are  significant  penalties  for  submitting  false  information,  including  the  possibility  of  fine  imprisonment  for  knowing  violations.  

     ___________________________________                                        ____________________________________      Mary  Hillis                                                              5th  June,  2014                                              NIco  Navarro                                                        5th  June,  2014  

       

___________________________________                                        _____________________________________      Mackenzie  Taggart                                5th  June,  2014                                                Sarah  Treadwell                                              5th  June,  2014                

 6.      Conclusion    The  main  issues  of  erosion  and  sedimentation  will  be  remedied  through  the  proper  installation  of  a  riprap,  j-­‐hook,  rolled  erosion  control,  and  bioretention  planters.    Bank  erosion  is  predicted  to  decrease  from  2.8  ft/yr  to  .04  ft/yr  with  the  installation  of  these  BMP’s.    This  alteration  will  help  to  create  a  stable  channel  and  slope;  sustainable  habitat  for  aquatic  species  and  terrestrial  vegetation;  and  add  aesthetic  value.    The  alteration  will  create  a  site  that  will  enhance  the  environment  and  moreover  the  overall  channel  health.        7.      References    

Caltrans.  2010.  Key  concepts  of  sustainable  erosion  control:  technical  guide.  pp.24-­‐32.  https://polylearn.calpoly.edu/AY_20132014/pluginfile.php/439729/mod_resource/content/2/Erosion_Control_Technical_Guide_v2.pdf.  May  29,2014.    "Clean  Water  Act,  Section  404."  EPA  Regulations.  EPA,  n.d.  Web.  06  June  2014.  <http://water.epa.gov/lawsregs/guidance/wetlands/sec404.cfm>.    "EPA  -­‐  Stormwater  Menu  of  BMPs."  NPDES,  31  July  2013.  Web.  22  May  2014.  <http://cfpub.epa.gov/npdes/stormwater/menuofbmps/index.cfm?action=browse&Rbutton=detail&bmp=39>.  

 FHWA  (Federal  Highway  Administration).  1995.  Best  Management  Practices  for  Erosion  and  Sediment  Control.  FHWA-­‐SLP-­‐94-­‐005.  Federal  Highway  Administration,  Sterling,  VA    "Lake  and  Streambed  Alteration  Program."  Questions  and  Answers.  California  Department  of  Fish  and  Wildlife,  n.d.  Web.  03  June  2014.  <http://www.dfg.ca.gov/habcon/1600/qa.html>.      "Rolled  Erosion  Control  Product  (Netting)."  Erosion  Control  Netting.  Caltrans,  n.d.  Web.  06  June  2014.  <http://www.dot.ca.gov/hq/LandArch/ec/recp/ec_netting.htm>.    Rosgen,  D.L.  2014.  The  cross-­‐vane,  w-­‐weir  and  j-­‐hook  strcutures…  their  description,  design  and  application  for  stream  stabilization  and  river  restoration.    Wildland  hydrology.  Web  06  June,  2014  <  http://www.wildlandhydrology.com/assets/cross-­‐vane.pdf>    Schueler,  T.,  and  K.  Brown.  2014.  Urban  watershed  restoration  manual  no.  4:  urban  stream  repair  practices(version  1.0).  West  Virginia  Department  of  Environmental  Protection.  06  June,  2014.  <http://www.dep.wv.gov/WWE/Programs/stormwater/MS4/guidance/Documents/Manual%204%20Urban%20Stream%20Repair%20Practices%202004.pdf>