erm-soathwqst, inc. &85092* · 2020. 11. 24. · appendix f work plan for removal action -...
TRANSCRIPT
![Page 1: ERM-SoathwQst, inc. &85092* · 2020. 11. 24. · APPENDIX F WORK PLAN FOR REMOVAL ACTION - PHASE I Combustion, Inc. Denham Springs, Louisiana 6/30/92 ERM-SoathwQst, inc. &85092* 85092](https://reader035.vdocuments.us/reader035/viewer/2022071502/6121bd105d635e72a03a5767/html5/thumbnails/1.jpg)
APPENDIX FWORK PLAN FOR
REMOVAL ACTION - PHASE I
Combustion, Inc.Denham Springs, Louisiana
6/30/92
ERM-SoathwQst, inc.
![Page 2: ERM-SoathwQst, inc. &85092* · 2020. 11. 24. · APPENDIX F WORK PLAN FOR REMOVAL ACTION - PHASE I Combustion, Inc. Denham Springs, Louisiana 6/30/92 ERM-SoathwQst, inc. &85092* 85092](https://reader035.vdocuments.us/reader035/viewer/2022071502/6121bd105d635e72a03a5767/html5/thumbnails/2.jpg)
IMPLEMENTATION PLAN FOREFFLUENT TREATMENT SYSTEM
Combustion, Inc. SiteRemoval Action
May 1, 1992(Revised June 24, 1992)W. O . #85-14
Robert E, Leslie
; "5 Q-^W^Patrick J, Campbell
/fl'f^f.c^/ ^^ie^^———Michael E. Pisani, P.E.Principal
Prepared By:
ERM-SOUTHWEST, INC.3501 N. Causeway Boulevard
Suite 200Metairie, LA 70002
(504) 831-6700
![Page 3: ERM-SoathwQst, inc. &85092* · 2020. 11. 24. · APPENDIX F WORK PLAN FOR REMOVAL ACTION - PHASE I Combustion, Inc. Denham Springs, Louisiana 6/30/92 ERM-SoathwQst, inc. &85092* 85092](https://reader035.vdocuments.us/reader035/viewer/2022071502/6121bd105d635e72a03a5767/html5/thumbnails/3.jpg)
TABLE OF CONTENTS
PageSDMM&RYINTRODUCTION1,1 Background1-2 Objective and ScopePRESENT SITE CONDITIONS2.1 Existing Wastewater Inventory2.2 Existing Inventoried Wastewater
Characteristics2.3 Existing Wastewater Treatment System2.4 Existing Effluent Characteristics2.5 Existing Wastewater. Flow RatesPROPOSED TREATMENT SYSTEM UPGRADE3-1 Basic System Upgrade3.2 Anticipated Wastewater Characteristics3.3 Basic System Setup3.4 Initial System Operation3.5 Basic System Operation3 . 6 Wastewater Pretreatment and Post-
Treatment Options3.7 Air Emissions3.8 Contingency PlanEFFLUENT LIMITS, MONITORING AND REPORTING4-1 Effluent Limits4-2 Monitoring System4-3 ReportingIMPLEMENTATION SCHEDULE
1-11-11-1
2-12-1
2-12-12-92-9
3-13-13-13-63-63-63-93-123-124-14-14-14-6
5-1
SUMMARY OF ANALYTICAL-RESULTS FORTANK AND POND WATER SAMPLES
1988 POND N DISCHARGE MONITORING
ERM-SW41a(Revised,6/24/92)
![Page 4: ERM-SoathwQst, inc. &85092* · 2020. 11. 24. · APPENDIX F WORK PLAN FOR REMOVAL ACTION - PHASE I Combustion, Inc. Denham Springs, Louisiana 6/30/92 ERM-SoathwQst, inc. &85092* 85092](https://reader035.vdocuments.us/reader035/viewer/2022071502/6121bd105d635e72a03a5767/html5/thumbnails/4.jpg)
SUMMARY
This plan describes an effluent treatment system to be installed atthe Combustion, Inc. site for the duration of cleanup activities-A package biological treatment system is proposed in order tosupplement the existing pond treatment system. The purpose of thetreatment system is to safeguard existing water quality of thereceiving body - Effluent limits, monitoring and reportingrequirements are also presented in this plan.
EKM-SW41a(Revised 6/24/92)
![Page 5: ERM-SoathwQst, inc. &85092* · 2020. 11. 24. · APPENDIX F WORK PLAN FOR REMOVAL ACTION - PHASE I Combustion, Inc. Denham Springs, Louisiana 6/30/92 ERM-SoathwQst, inc. &85092* 85092](https://reader035.vdocuments.us/reader035/viewer/2022071502/6121bd105d635e72a03a5767/html5/thumbnails/5.jpg)
IMPLEMENTATION PLAN FOREFFLUENT TREATMENT SYSTEM
Combustion, Inc. SiteRemoval Action
1 - INTRODUCTION
1.1 Background
The Combustion, Inc. site is located in Livingston Parish,Louisiana about three miles northeast of Oenham Springs. The site,which operated from the 1960s until 1982, consists of a smallinactive oil reclamation plant (Process Area) and a separate areathat contains fourteen shallow ponds (Pond Area) - The generalvicinity of the site is depicted in Figure 1-1.A two-phase cleanup (Removal Action) is currently being planned forthe Combustion, Inc. site. Phase I of the cleanup will includeremoval and proper disposal of the aboveground and undergroundtanks and their contents, above ground structures, the pipelineconnecting the Process Area to the Pond Area, and the oil on thesurface of the ponds. Phase II of the cleanup will address thewater, solids and any affected soils in the Pond Area.The existing water inventory at the site, along with any wastewateror contaminated storm water generated during the cleanup processmust be treated prior to discharge. This plan characterizes thewater currently at the site, describes the existing pond stormwater treatment system, and outlines steps necessary to ensureproper treatment of the wastewater and storm water generated in thePhase I and Phase II cleanup activities.1.2 Objective and ScopeThe objective of this plan is to characterize the wastewater at theCombustion, Inc. site and to define the method for treatment -Specifically, the scope of this plan includes the following:
o Characterization of wastewater currently on siteo Description of the existing pond wastewater treatment
systemo Characterization of the existing effluent,o Specification of upgrade requirements for the existing
wastewater treatment system,
1-1 EBM-sw4la(Revised 6/24/92)
![Page 6: ERM-SoathwQst, inc. &85092* · 2020. 11. 24. · APPENDIX F WORK PLAN FOR REMOVAL ACTION - PHASE I Combustion, Inc. Denham Springs, Louisiana 6/30/92 ERM-SoathwQst, inc. &85092* 85092](https://reader035.vdocuments.us/reader035/viewer/2022071502/6121bd105d635e72a03a5767/html5/thumbnails/6.jpg)
ERM-5oothw«st. inc.MH «UMb WWfA FiaiJftCl | - I WUTOH. TIM
OENSW. ffTt VWftWrOOMBUftTMNi.IKO*
C«nn«n _^rlh8fc_LeufiMna _^..^•"•••ttoJh ' p4-M«&j|*B^———l«, hMBJaa«N t. i afl-Tn . _ ^ .
![Page 7: ERM-SoathwQst, inc. &85092* · 2020. 11. 24. · APPENDIX F WORK PLAN FOR REMOVAL ACTION - PHASE I Combustion, Inc. Denham Springs, Louisiana 6/30/92 ERM-SoathwQst, inc. &85092* 85092](https://reader035.vdocuments.us/reader035/viewer/2022071502/6121bd105d635e72a03a5767/html5/thumbnails/7.jpg)
o Definition of effluent limits and discharge monitoringrequirements, and
o Implementation plan.
1-3 - ERM-SW41a(Revised 6/24/92)
![Page 8: ERM-SoathwQst, inc. &85092* · 2020. 11. 24. · APPENDIX F WORK PLAN FOR REMOVAL ACTION - PHASE I Combustion, Inc. Denham Springs, Louisiana 6/30/92 ERM-SoathwQst, inc. &85092* 85092](https://reader035.vdocuments.us/reader035/viewer/2022071502/6121bd105d635e72a03a5767/html5/thumbnails/8.jpg)
2 - PRESENT SITE CONDITIONS2.1 Existing Wastewater InventoryThe existing wastewaters at the Combustion, Inc. site are containedin tanks at the Process Area and in tanks and ponds at the PondArea. Layouts of the Process Area and Pond Area are provided inFigures 2-1 and 2-2, respectively. Approximate Wastewaterinventories for the Process Area and Pond Area are provided inTables 2-1 and 2-2, respectively. The inventories are developedfrom data presented in the Preliminary Remedial InvestigationReport for the site*2.2 Existing Inventoried Wastewater CharacteristicsExisting waters at the site were characterized in the PreliminaryRemedial Investigation. The analytical results of individual tankand pond water samples are provided in Appendix A and summarized inTable 2-3-2.3 Existing Wastewater Treatment SystemThe wastewater treatment system currently in operation at theCombustion, Inc. site treats storm water runoff contaminated by oilor oily wastes. A schematic of the existing system is provided inFigure 2-3.Additional wastewaters are continually generated at the site as aresult of the containment of storm water runoff at the site. Rainfalling on the western half of the Process Area is contained bycontaminant dikes, sumps and/or the natural topographic relief.The contained runoff is transferred to Tank l within 24 hours viaa manually operated pump. Tank 1 allows time for oil/waterseparation, provides some equalization capacity and generally actsas a temporary storage tank until the runoff can be routinelydrained to the Pond Area. An underground pipe from Tank 1 to PondC facilitates this transfer by gravity.The Tank 1 storm water flows through Ponds C, B and A, which serveas gravity oil/water separators to a Drainage Ditch running eastthen north along the perimeter of the Pond Area. The DrainageDitch discharges to Pond M, which is connected to the final pond,Pond N. The Drainage Ditch and Ponds M and N allow facultativebiological degradation ( i . e . , by aerobic and anaerobic organisms)
2-1 EKM-SW41(Revised 5/27/92)
![Page 9: ERM-SoathwQst, inc. &85092* · 2020. 11. 24. · APPENDIX F WORK PLAN FOR REMOVAL ACTION - PHASE I Combustion, Inc. Denham Springs, Louisiana 6/30/92 ERM-SoathwQst, inc. &85092* 85092](https://reader035.vdocuments.us/reader035/viewer/2022071502/6121bd105d635e72a03a5767/html5/thumbnails/9.jpg)
WOOQ
M^
f
..„-
\r—i
|
L--..,..
p-1 r
1
\
°[\ r} v—"" t^-,^
^ J
^w
J,
———^
——J
v
—,
^rv7 n/ PARKING AREAf p-J .——J (COMBUSTION, INC.)
-LJ
«
0,-,0 Q-HWe©
„' n n^\- s ti® la<i/ suMp^uu' Qir
© / i nnnn ^^fii Q ijyuy^
———L——MIIW——
1
8
da
-^
«\-„• •..-Ll ^--
MILTON ROAC
OLDEQUIPMENT
SHEDFOUNDATION
iea,
•
^——.i.iir'r"-"*'
c
!y- <^==='
*t—i»"
«-
t.
^4*4 •»
—•>
c[
*
IN. ?
.IMPEND
———. SURPACS.WATER DRAINAGE ,
-"-— FEMCS UNEK-»fr- OATE
=^P HOUSE/BUILD1NO
^ ["1 PROCESS AREAS / 9 STORAGE TANKS
CAS/OIESB. PUMP ISLAND :
."1 fw/Q PUUPS^
" CINDER BLOCK WALL
1
0 M 1W
MftC FTZT
ERM-Soothwest. Inc.ffttAtoKMAflW* |t|AUAK t"l KUtttt TCW
M06E«« AKCA LAYOUTCOMBUSTION, WO. BI/M
»——mfn^a' '""' ^—
![Page 10: ERM-SoathwQst, inc. &85092* · 2020. 11. 24. · APPENDIX F WORK PLAN FOR REMOVAL ACTION - PHASE I Combustion, Inc. Denham Springs, Louisiana 6/30/92 ERM-SoathwQst, inc. &85092* 85092](https://reader035.vdocuments.us/reader035/viewer/2022071502/6121bd105d635e72a03a5767/html5/thumbnails/10.jpg)
\ __ -^//// ^
FIGURE 2-2APOND AREA SURFACE DRAINAGE
COMBUSTION, INC. RI/FSDENHAM SPRINGS, LOUISIANA
W . a f i a P ^ — i A • " — — — - •- -
![Page 11: ERM-SoathwQst, inc. &85092* · 2020. 11. 24. · APPENDIX F WORK PLAN FOR REMOVAL ACTION - PHASE I Combustion, Inc. Denham Springs, Louisiana 6/30/92 ERM-SoathwQst, inc. &85092* 85092](https://reader035.vdocuments.us/reader035/viewer/2022071502/6121bd105d635e72a03a5767/html5/thumbnails/11.jpg)
FIGURE 2-2BPOND AREA SURFACE DRAINAGE
COMBUSTION, INC. RI/FSDENHAM SPRINGS, LOUISIANA
feNo. ~85- 1 8 1^ I 0-30-9 I
![Page 12: ERM-SoathwQst, inc. &85092* · 2020. 11. 24. · APPENDIX F WORK PLAN FOR REMOVAL ACTION - PHASE I Combustion, Inc. Denham Springs, Louisiana 6/30/92 ERM-SoathwQst, inc. &85092* 85092](https://reader035.vdocuments.us/reader035/viewer/2022071502/6121bd105d635e72a03a5767/html5/thumbnails/12.jpg)
TABLE 2-1ESTIMATED PROCESS AREA INVENTORY
Combustion, Inc. SiteDenham Spring!, Louisiana
Unit
TanksTankiTank 2Tank 3Tank 5Tank?TankSTank 9
Tank 10Tank 11Tank 12Tank 13Tank 14Tank15Tank 16Tank 18Tank 19Tank 20
Orientation
(«)
Tanks Subtotal
VerticalVerticalVerticalVerticalVerticalVertical
HorizontalHorizontalHorizontalHorizontalHorizontalHorizontalVcrltail
HorizonialHorizontal
UndergroundUnderground
Dimensions MDiameter
(^
SO292521212110101010
10.510.1
154
9.9UnknownUnknown
881.700
Height orLengthtfu
2916/
14,814.814.814.8
303030303032166
15.2UnknownUnknown
TotalCapacityw ton426.00079400
121,00038.30038,30038.30017.60017,60017.60017^60020.70019.10021.100
6008.800
< 12.000< 12,000
In-Dl&ca Volume
OllM
29.500-•--—3,200
90014003,800
400300300600200600200
---UnknownUnknown
41,500
WalcrWraaU
Variable (c)•••--.
14.50026.800lUMO.-—1.9002^003.0005^400
11.2005,400 W—— . OJ
500UnknownUnknown
82.500 (e)
Sludge (b)(cu.ydrt
722227112662133
0£0,5
1
0,5UnknownUnknown
178
NOTBS!(a) Source: Prel!minaiy Remedial Investigation Report. March 30,1^0.(b) Assumes water conteni does not change during removal and processing.(c) Tank 1 is currently used (o store collected siornwater runoff from (he Process Area; consequently, the volume ofwaier nucluates over time.
For this estimate, any stomwater in Tank 1 Is assumed to be discharged to Pond C as part of normal operations.(d) Mcthanol/water mixture.(e) IE oil dewatering Is employed during the Phase 1 Removal Action, an additional 15,600 gallons of water may be generated^
![Page 13: ERM-SoathwQst, inc. &85092* · 2020. 11. 24. · APPENDIX F WORK PLAN FOR REMOVAL ACTION - PHASE I Combustion, Inc. Denham Springs, Louisiana 6/30/92 ERM-SoathwQst, inc. &85092* 85092](https://reader035.vdocuments.us/reader035/viewer/2022071502/6121bd105d635e72a03a5767/html5/thumbnails/13.jpg)
TABLE 2-2
ESTIMATED POND AREA INVENTORY
Combustioa. Inc. SheDenham Springs. Louisiana
Unit
PondAPoodBPondCPoadDPoodEPoodFPondGFOadHPondlPoodJPondKPondLPondMPondN
Poods Subtotal
Tanlc22(f)Tank 23(g)Tank24(h)
Area<•»*)
(•q-ft.)
1,83034X0
12.0003 70
9883.5803*410
23,00020.10010,7007,1101,7105,2607300
103.768
1331S1165
03 W^(B«L)
46,000119.000
— — — -———
6QJOOO4,000
153.000——————————————————
382,000
———1.700———
la-phcc VolumeWaterM
W
• - - - - MJOOO82JOOO
368JOOO27JOOO23JOOO
112JOOO108,00052QJOOO691.00088.000
I72JOOO- - 10JOOO
-- "120JOOO179JOOO
2.754JOOO (c)
Z5MS^OO
- 4 800
Sludge t'1*(cu.yds.)
19328251535
144376297718961228272109223347
4^699
232
Tanks Subtotal 479 1.700 15,500
NOTES:(a) Soorcc: PrcEnunaiy Remedial Investigation Report, Mareh 30.2990.(b) Calculated by Gulf Coast Aerial Mapping using planimctric techniques on a December L9S8 aerial photograph-(c) Oil volumes include free liquid oD and the waxy emulsion layer between the free oil and water.(d) Sludge refeis to the loose, UDconsoIidated solids at the bottom of the ponds, and does not include any potentially
affected sous beneath the poods. Assumcswaiercontcnl does nolchangeduringremoval and processing.(c) If oil dewaterins is employed, an additional 113,300 gallons of water may be generated.(1) Vertical tank : 13 ft. diameter x 30 ft. high: total capacity 29,800 gal!.: water and solids volumes estimated from
Tanfc 23 inventory.(g) Vertical tank: 15 ft. diameter x 15 &- high: total capacity 20,100 sail.(h) Underground tank : 11 ft. wide * S3 depth * 15 ft- length (apparently elliptical) : total capacity = 5,200 gaL
![Page 14: ERM-SoathwQst, inc. &85092* · 2020. 11. 24. · APPENDIX F WORK PLAN FOR REMOVAL ACTION - PHASE I Combustion, Inc. Denham Springs, Louisiana 6/30/92 ERM-SoathwQst, inc. &85092* 85092](https://reader035.vdocuments.us/reader035/viewer/2022071502/6121bd105d635e72a03a5767/html5/thumbnails/14.jpg)
1988M35TABLE 2-3
SUMMARY OF ANALYTICAL RESULTS FORPOND AND TANK WATER SAMPLES (a)
Combustion. Inc. SiteDenham Springs, Louisiana
Range ofUnits Values Detected
6.1->5JOOO3.9-7.2
4-600 (b)84-1490 (b)12-280 (b)86-147,000
<1.0-5.200(b)23-<60
<0.05-0.17<0.01-<0.05
12-100
Number ofSamplesParameter
BOD mg/LpH s.u,TOC m^LTDS mg/LTSS mg/LCOD mg/LOfl & Grease .. mg/LFlashpoint °CSuffidc mg/LCyanide mg/LChloride mg/L
Total MetalsAntimony mg/L <OJ005-30Arsenic mg/L <0.005-0.014Barium mg/L 0.01-142Chromium mg/L <0-01—18Cobalt mg/L _ <0.02-6Lead mg/L <0.005-275Zinc mg/L 0.64
Volatile Orgamcs1.1-Dichloroethane • mg/L 0541.2-Dichloroethane mg/L 1.7Trichloroethene mg/L <0.005-0-30Benzene mg/L <0.005-0.522-Hexanone mg/L 0^1Tomene mg/L 053Total Xylcnes mg/L <0.005-0.014Meth^ene Chloride mg/L <OJ005-1^Acetone mg/L <0.010-1.4
Semivolatiles OrganicsPhenol . mg/L <0.01-OJB62-Melhy^henol mg/L <0.01-0.0174-MeAy^henol mg/L <OJ01-0^)352,4-Dimethylhenol mg/L <0.01-0.023Naphthalene mg/L <0.01-0^)21N-Nitrosodiphenyiamine mg/L <0.01-0.015Anthiaoene mg/L <0.01-0-011
Notes:(a)Based upon data m the Preliminary Remedial Investigation Report
(revised November 7,1991).(b)Not including the methanol/water mixture in Tank 13-
32352221632343665
1717171717171
4444444
![Page 15: ERM-SoathwQst, inc. &85092* · 2020. 11. 24. · APPENDIX F WORK PLAN FOR REMOVAL ACTION - PHASE I Combustion, Inc. Denham Springs, Louisiana 6/30/92 ERM-SoathwQst, inc. &85092* 85092](https://reader035.vdocuments.us/reader035/viewer/2022071502/6121bd105d635e72a03a5767/html5/thumbnails/15.jpg)
Figure 2-3EXISTING WASTEWATER TREATMENT SYSTEM
Combustlon» Inc. SiteDenham Springs, Louisiana
RETENTIONTIME (a):
FUNCTION:
PROCES
@P^
Sump Pump
N/A
StormWater
Collection
S
»•
Equalization.Storage andOil/WaterSeparation
AREA
Tanki
19 days
| PO
Pond C Pond B Pond A
25 days 9 days 3 days
Oil/Water Separation
NDABEA
.^•Ift———l^fc. .J—rik—i^h,^ — — ^ v ^ ^^———————^V J ^ JDrainage Ditch PondM PondN 0
-Iday 6 days 13 days
Facultative Biological Treatment
.NOTES;, ;(a) Estimated flow s 16 gallons per minute.
![Page 16: ERM-SoathwQst, inc. &85092* · 2020. 11. 24. · APPENDIX F WORK PLAN FOR REMOVAL ACTION - PHASE I Combustion, Inc. Denham Springs, Louisiana 6/30/92 ERM-SoathwQst, inc. &85092* 85092](https://reader035.vdocuments.us/reader035/viewer/2022071502/6121bd105d635e72a03a5767/html5/thumbnails/16.jpg)
of -the soluble organics in -the wastewater- The -treated wastewateris discharged from Pond N to the stream located west of the site.Rain falling on the Pond Area is contained within the ponds. Theponds are interconnected and the collected water is eventuallytreated and discharged via the outfall from Pond N.As shown in Appendix A, the data collected during the 1989 RemedialInvestigation showed the BOD concentration in Pond N water to be33 Kg/L and the BOD in Pond C water to be 140 mg/L, The 76% BODremoval is indicative of biological degradation of the solubleorganics in Ponds C, B A, the Drainage Ditch and Ponds M and N.2.4 Existing Effluent CharacteristicsDuring 1988 the effluent discharged from Pond N was sampled at theoutfall to the stream west of the site for the eight months when adischarge flow occurred. The analytical results of this effluentcharacterization were reported in the Preliminary RemedialInvestigation Report. The analytical data is provided in AppendixB and is summarized in Table 2-4.2-5 Existing Wastewater Flow RatesThe average annual flow through the treatment system is estimatedto be approximately 16 gallons per minute. This estimate is basedupon the mean annual rainfall rate for Baton Rouge during theperiod 1942 to 1981 (approximately 57 inches per year). TheRational Method was used to calculate runoff assuming a runoffcoefficient of 85% and evaporative losses based up on an annuallake evaporation rate of 48 inches per year from ponds without asurface oil layer (Ponds A, D, E, I, 3, K, L, M and N ) . The basisfor the average annual wastewater flow rate is provided in Table2-5.The actual rate of outflow from Pond N is restricted by thediameter of the discharge pipe. During heavy rainfall, the inflowrate may be a greater rate than the discharge rate; therefore wateris temporarily stored in the pond system. _ The pond waterelevations rise as the water "backs up" in the system.
2-9 ERM-SW41(Revised 5/27/92)
![Page 17: ERM-SoathwQst, inc. &85092* · 2020. 11. 24. · APPENDIX F WORK PLAN FOR REMOVAL ACTION - PHASE I Combustion, Inc. Denham Springs, Louisiana 6/30/92 ERM-SoathwQst, inc. &85092* 85092](https://reader035.vdocuments.us/reader035/viewer/2022071502/6121bd105d635e72a03a5767/html5/thumbnails/17.jpg)
1977M41
TABLE 2-4
EFFLUENT DISCHARGE CONCENTRATIONS FOR1988 POND N DISCHARGE <«>
Combustion, Inc. SiteDenham Springs, Louisiana
Parameter Average^ Range Units
pHBOD.TOCOn and GreasePCBsLeadPriority Pollutants
Scmivolatile Organic CompoundsVolatile Organic Compounds (c)
BenzeneCnlorobenzeneTolueneTrichloroetheneMethyfcne ChlorideTotal Xylenes
Std. Unitsmg/Lmg/Lmg/Lmg/Lnig/L
(b)
mg/Lmg/Lmg/Lmg/Lmg/Lmg/L
5.834732.1
<OJ001<0.1
(b)
(d)(e)(d)(d)(0(0
5-5 - 6.114 - 11062-980.4-3.8
< 0.001<0.1
(b)
0.025 - 0.0290.032
0.038 - 0.0670.031 - 0.038
0.0100.031
NOTES:(a) Based upon the eight months when discharge flow occurred.(b) Below detection limits for all compounds.(c) Results below detection limits are not listed.(d) Detected in Februaly and December onfy.(e) Detected in February only.(f) Detected in December only.
![Page 18: ERM-SoathwQst, inc. &85092* · 2020. 11. 24. · APPENDIX F WORK PLAN FOR REMOVAL ACTION - PHASE I Combustion, Inc. Denham Springs, Louisiana 6/30/92 ERM-SoathwQst, inc. &85092* 85092](https://reader035.vdocuments.us/reader035/viewer/2022071502/6121bd105d635e72a03a5767/html5/thumbnails/18.jpg)
TABLE 2-5
BASIS FOR ANNUAL AVERAGE FLOWRATC
Combustion, Inc. SiteDenham Spring?, Louisiana
Average Annual Rainfall (n) = 56^ inch/year (0.156 inch/day)TotalSiteArca == 339800fi2<b)Runoff Coefficient^) = O^inchofrunoflyinchofrain
Avemge Inflow == (56^8 m V339800 fl^flISS) ( 1ft J( lyr V Idav ^ 7.48 gal ^year 12in 365 days 1440minutes ft3
Le-* QIN =: ^ gallons per minute (gpm)
Surface area of ponds with no surface oSl layer W = 58.678 ft2
Average Annual Evaporative Losses = (48 _m_)(58678 f^)( 1ft V Ivr V Idav )( 7.48 ginyear 12in 365 days 1440minutes ft3
^••QEVAP = 33 gallons per mmute
Net Annual Average Oatflow = QIN-Q^VAP
= 16.2 gallons per minute
NOTES:WReported for Baton Rouge Area in Remedial Investigation Report<*') Process Area = 63.550 fi2; Pond Area == 276.250 fl2
(c) Estimated for Total Site Area^ PondsA,D.E.I.J.K.L,MandN(e) VS. National Weather Service data tesed on period 1946-1955.
![Page 19: ERM-SoathwQst, inc. &85092* · 2020. 11. 24. · APPENDIX F WORK PLAN FOR REMOVAL ACTION - PHASE I Combustion, Inc. Denham Springs, Louisiana 6/30/92 ERM-SoathwQst, inc. &85092* 85092](https://reader035.vdocuments.us/reader035/viewer/2022071502/6121bd105d635e72a03a5767/html5/thumbnails/19.jpg)
3 - PROPOSED TREATMENT SYSTEM UPGRADE
The site cleanup may potentially result in surge flows ofrelatively high strength wastewaters. These surges would likelyoverwhelm the existing facultative pond system because of the lackof process control and the limited oxygen transfer characteristicsassociated with a pond treatment system. This section describes anupgrade of the pond system to assure consistent treatment of futuresite wastewaters.3*1 Basic System UpgradeThe core of the system upgrade will consist of adding a packagewastewater treatment system to the existing flow scheme. Aschematic of the system is provided in Figure 3-1- The retentiontimes for the system components, at an average flow rate of 16 gpm,are provided in Figure 3-1.The package system will be an extended aeration activated sludgedesign. A design data sheet for the package treatment system isprovided in Table 3-1- Preliminary process flow schematics arepresented in Figures 3-2 and 3-3- A more detailed schematic willbe available to LDEQ and EPA once a package wastewater treatmentsystem vendor has been selected-3.2 Anticipated Wastewater CharacteristicsWastewater generated during the Removal Action is not expected todiffer greatly in specific chemical composition from the wastewatercurrently present at the site. Wastewater generated from physical/chemical treatment of oily emulsions is, however, expected to havehigher organic strength as expressed by increased TOC and BODlevels.Anticipated wastewater characteristics for the Phase I RemovalAction also are provided in Table 3-1- These concentrations weredeveloped by assuming that the inventory in Ponds A, B and C werereduced sufficiently to accommodate the volume of water from theProcess Area tanks. The concentrations were then calculated froma flow weighted average of the loadings in these three ponds.The anticipated wastewater characteristics provide a design basisfor the proposed treatment system upgrade. All discharged effluentwill meet the LDEQ effluent discharge limits presented in Section4.0.
3-1 - ERM-SW41a(Revised 6/24/92)
![Page 20: ERM-SoathwQst, inc. &85092* · 2020. 11. 24. · APPENDIX F WORK PLAN FOR REMOVAL ACTION - PHASE I Combustion, Inc. Denham Springs, Louisiana 6/30/92 ERM-SoathwQst, inc. &85092* 85092](https://reader035.vdocuments.us/reader035/viewer/2022071502/6121bd105d635e72a03a5767/html5/thumbnails/20.jpg)
Figure 3-1PROPOSED WASTEWATER TREATMENT SYSTEM
Combustion, tec. SiteDenham Springs, Louisiana
PROCESS AREA
@ -T
POND AREA
Sump Pump Tank 1 Pond C Pond B Pond A Drainage Ditch Pond M Pond N OutfallRETENTION
TIME (a): N/A 19 days 25 days 9 days 3 days •I day 6 days 2 days 13 days
FUNCTION: StormWater
CollectionEqualization,Storage andOil/WaterSeparation
Oil/Water Separation BiologicalPretreatment
PackageBiologicalTreatment
System
FinalPolishing
MOBS.(a) Estimated flow as 16 gallons per minute.(b) Flow path under current conditions.
![Page 21: ERM-SoathwQst, inc. &85092* · 2020. 11. 24. · APPENDIX F WORK PLAN FOR REMOVAL ACTION - PHASE I Combustion, Inc. Denham Springs, Louisiana 6/30/92 ERM-SoathwQst, inc. &85092* 85092](https://reader035.vdocuments.us/reader035/viewer/2022071502/6121bd105d635e72a03a5767/html5/thumbnails/21.jpg)
TABLE 3-1
DESIGN DATA SHEET PACKAGE FOR BIOLOGICAL TREATMENT SYSTEMPHASE I AND n REMOVAL ACTIONS
Combustion, Inc. SiteDenham Springs, Louisiana
Preliminary Equipment SpecificationsConstructionFoundation
Nominal Flow RateMinimum Number of Air BlowersAir Delivery SystemOarmer ConfigurationTypical Operation RequirementsSludge DigestionSludge Thickemng
Anticipated Wastewater CharacteristicsBODCODOil and GreaseSuspend SolidspH
Process Control ParametersForward Flow RateDissolved Qxygpn in Aeration TankPHTarget Volatile Solids in Aeration TankSludge Return Rate (% of forward flow)Minimum Sludge AgeReactor TemperatureTotal Dissolved SolidsNutrient BalanceClarifier Overflow RateFreeboard
Welded steelWooden crane mats or
Reinforced concrete50gpm
2Diffusers
Internal or external1—4 hours daily
Not requiredPortable tank
900mg/L3500 mg/L
900 mg/L (maximum)250mg/L
7-9
Monitored continuously2.0 mg/L minimum
Maintain 7—9 range1000-2500 mg/L150% minimum
20 daysMonitor daily
5000 mg/L maximumBOD:N:P= 100:5:1
500 gal/ft2 day maximum2 feet minimum
Revised 6/24/92
![Page 22: ERM-SoathwQst, inc. &85092* · 2020. 11. 24. · APPENDIX F WORK PLAN FOR REMOVAL ACTION - PHASE I Combustion, Inc. Denham Springs, Louisiana 6/30/92 ERM-SoathwQst, inc. &85092* 85092](https://reader035.vdocuments.us/reader035/viewer/2022071502/6121bd105d635e72a03a5767/html5/thumbnails/22.jpg)
FIGURE 3-2
PRELIMINARY PROCESS FLOW SCHEMATICBIOLOGICAL PACKAGE TREATMENT SYSTEM
Combustion, Inc. SiteDenham Springs, Louisiana
Slipstream to Air Lift Sludge Return Lines
Return Activated Sludge
![Page 23: ERM-SoathwQst, inc. &85092* · 2020. 11. 24. · APPENDIX F WORK PLAN FOR REMOVAL ACTION - PHASE I Combustion, Inc. Denham Springs, Louisiana 6/30/92 ERM-SoathwQst, inc. &85092* 85092](https://reader035.vdocuments.us/reader035/viewer/2022071502/6121bd105d635e72a03a5767/html5/thumbnails/23.jpg)
FIGURE 3-3
PRELIMINARY PROCESS FLOW SCHEMATICEFFLUENT POLISHING (a)
Combustion, Inc. SiteDenham Springs, Louisiana
ClarifierWeir Box
LevelIndicator
T| Level-Controlled, FilterFeed• PumpL--(rf
Bypass Valve(Normally Closed)
Clarified EffluentGenerated During
Removal Action Activities
FinalTreatedEffluent
To Pond N
FILTER GRANULATEDACTIVATED CARBON
PACKED COLUMN
Legend: Cumulative Flow Meter
Notes:(a) Will be used as necessary.
![Page 24: ERM-SoathwQst, inc. &85092* · 2020. 11. 24. · APPENDIX F WORK PLAN FOR REMOVAL ACTION - PHASE I Combustion, Inc. Denham Springs, Louisiana 6/30/92 ERM-SoathwQst, inc. &85092* 85092](https://reader035.vdocuments.us/reader035/viewer/2022071502/6121bd105d635e72a03a5767/html5/thumbnails/24.jpg)
3.3 Basic System SetupThe package wastewater treatment system will be located in the PondArea in the vicinity of Ponds M and M. The system will be placedupon either wooden crane mats or a reinforced concrete pad. Asmall pump will be used to divert the current flow route (Pond M toPond N) through the package treatment system- Power hookups forpumps and airblowers will be made available in the Pond Area. Theinstallation of the treatment system, and any additional equipmentor surface transfer piping, will be the responsibility of vendorsupplying the package Plant-3,4 Initial System OperationUpon initiation of the Phase I cleanup, the current pond waterinventory will be reduced so that the Pond Area can accommodate adesign storm of 24 hours duration and a return frequency of 25years (equivalent to 9.5 inches rainfall). The surcharge from thisstorm is estimated to require an inventory reduction of 1.7 milliongallons. The inventory of each pond will be reduced in proportionto its current capacity. The water removed from each pond will bepumped to the package wastewater treatment system (via Pond M) fortreatment- Treatment of this volume of water over a forty-five daytime period will require a round-the-clock flow of 43 gallons perminute. The basis for this flow rate is presented in Table 3-2-The gravity flow system between ponds will be the primary measuresof achieving this volume reduction. Portable pumps and piping willbe used to permit water transfer should the water levels drop belowthose required for gravity flow. The pump and piping will also beused if there is any danger of oil carryover between ponds.3.5 Basic System OperationWater from the Process Area tanks will be transferred either toTank 1 by a portable pump and piping or directly, to Pond c via avacuum truck. Water from Tank 1 will be gravity-drained to Pond Cvia the underground pipeline currently used for storm watertransfer. The integrity of the stonnwater transfer pipeline willbe proven by low pressure testing prior to use during RemovalAction activities. (The testing procedures are provided in thePhase I Removal Action Work Plan.) Water from the ponds or tanksin the Pond Area will either drain by gravity or be pumped to PondsC, B and A. The waters in these ponds may be recirculated prior to
3-6 ERM-SW41a(Revised 6/24/92)
![Page 25: ERM-SoathwQst, inc. &85092* · 2020. 11. 24. · APPENDIX F WORK PLAN FOR REMOVAL ACTION - PHASE I Combustion, Inc. Denham Springs, Louisiana 6/30/92 ERM-SoathwQst, inc. &85092* 85092](https://reader035.vdocuments.us/reader035/viewer/2022071502/6121bd105d635e72a03a5767/html5/thumbnails/25.jpg)
TABLE 3-2
BASIS FOR STORM WATER INVENTORY REDUCTION PLOW
Combustion. Inc. SiteDenham Spring?, Louisiana
Rainfall from a design storm event of 24—hour duration, with a return faequency of 25 years, is 95 inches.
Design storm water volume is:
(9.5 in)(OJ8S mchnmoff V339800 ft2^ 1ft V 7AS_gaL ^indiiam 12 in ft3
Lc., V^JQ^^ == 1.71 million gallons (MG)
Assuming:
— the25—year storm occurs during long—term average design flow conditions, and— the surplus storm water is treated over a period of 45 days,
the maximum rate of storm water treatment is:
QAVERAGE + 1.71 MG ( Iday ^ = 16^gpm + 26.4 gpm45 days 1440 minutes
=42.6 gpm
![Page 26: ERM-SoathwQst, inc. &85092* · 2020. 11. 24. · APPENDIX F WORK PLAN FOR REMOVAL ACTION - PHASE I Combustion, Inc. Denham Springs, Louisiana 6/30/92 ERM-SoathwQst, inc. &85092* 85092](https://reader035.vdocuments.us/reader035/viewer/2022071502/6121bd105d635e72a03a5767/html5/thumbnails/26.jpg)
discharge to the Drainage Ditch if additional retention time isrequired for oil/water separation or equalization. Floatingcurtains will be placed near the discharge pipe from Ponds A and Mas an additional safeguard against the unlikely event of oilcarryover. A surface oil layer is not currently present on Pond M.
A floating curtain or rigid baffle structure will be installed inPond B to prevent the oil in Ponds B and C from being discharged toPond A and the Drainage Ditch downstream- There will be no activeflow in Ponds B and C during the removal of oil from those ponds.During the removal of oil from Ponds B and C, the Process Areastormwater will be retained and the transfer pipeline shut off orthe flow will be released offsite if the Process Area cleanup iscomplete.The Drainage Ditch and Pond M provide time for some facultativebiological-treatments prior to the package treatment system. ThepH of the water from each pond will be adjusted to within a 6,0 to9*0 range before discharge to the Drainage Ditch. This form ofbatch pH adjustment will be achieved by adding pH-adjustingchemicals to the water and recirculating the flow until the targetpH is achieved.The package system basically consists of an aeration tank followedby a clarifier unit. The clarifier unit provides control over thebiomass in the system thus giving a more reliable operation thanthe existing pond system, particularly if there is a potential forincreased loadings to the system- Mechanical air blowers will beused to introduce ambient air into the aeration tank in order toprovide the oxygen needed for the degradation of the varyingorganic loads.The average flow rate of 16 gpm (developed in Section 2.5) providesfor a hydraulic retention time of two days. The system willtypically be operated at the average flow rate. However, duringthe initial inventory reduction, described in Section 3 . 4 , a flowrate of 43 gpm will be employed- This inventory reduction flow(developed in Section 3.4) results in a hydraulic retention time of0-7 days-The package treatment system will be operated at a minimum sludgeage of approximately 20 days. This long sludge age reduces theamount of biosolids generated by the system and eliminates the needfor sludge digestion. Based upon the anticipated BOD loading,sludge generation is expected to be less than 90 Ibs/day of dry
3-8 ERM-SW41a(Revised 6/24/92)
![Page 27: ERM-SoathwQst, inc. &85092* · 2020. 11. 24. · APPENDIX F WORK PLAN FOR REMOVAL ACTION - PHASE I Combustion, Inc. Denham Springs, Louisiana 6/30/92 ERM-SoathwQst, inc. &85092* 85092](https://reader035.vdocuments.us/reader035/viewer/2022071502/6121bd105d635e72a03a5767/html5/thumbnails/27.jpg)
solids. Waste activated sludge from the package treatment systemwill be discharged to a portable tank for gravity thickening.Waste solids are expected to amount to no more than four dry tonsduring the Phase I Removal Action (assuming a 90-day projectduration). The solids will ultimately be returned to Pond M fortreatment and disposal along with the solids already present inPond M.The treated effluent from the package plant is to be discharged toPond M for final effluent polishing- A small concrete pad will besubmerged below the .package plant discharge pipe in order toprevent scouring of the pond bottom during discharge to Pond M.The water from Pond H will be discharged onsite to a small ditchrunning from Pond N to the stream located west of the site. Thesmall -ditch will be formed by removing the existing Pond Ndischarge pipe.The discharge from Pond N will occur on a batch basis during start-up and Removal Action activities and on a continuous basis duringnormal site conditions, i . e . , when no Removal Action activities areoccurring. Effluent monitoring will occur from within Pond N forbatch discharge conditions and at the discharge from Pond N to thesmall ditch for continuous discharge conditions. Initial testingwill be performed to demonstrate that leaching of constituents fromthe sludges in Pond N, if occurring, does not impact the effluentquality between the time when a batch is sampled until the time thebatch is actually discharged. The IiDEQ effluent discharge limitsare presented in Section 4.0,3 . 6 Wastewater Pretreatment and Post-Treatment OptionsThe package treatment system is designed to meet the LDEQ treatmentstandards in Section 4.0, however, optional pretreatment and post-treatment process options can be implemented, when necessary, inorder to maintain the performance of the wastewater treatmentsystem during any cleanup activities. Potential process optionsare listed in Table 3-3, The criteria and conditions by whichpotential process options will be implemented are included in Table3-3.The long retention times in the system means that any of theoptions listed .could be implemented, as appropriate. It isanticipated that these process options are available as skid-mounted units for ease of transportation and installation.
3-9 EKM-sw4la(Revised 6/24/92)
![Page 28: ERM-SoathwQst, inc. &85092* · 2020. 11. 24. · APPENDIX F WORK PLAN FOR REMOVAL ACTION - PHASE I Combustion, Inc. Denham Springs, Louisiana 6/30/92 ERM-SoathwQst, inc. &85092* 85092](https://reader035.vdocuments.us/reader035/viewer/2022071502/6121bd105d635e72a03a5767/html5/thumbnails/28.jpg)
2206M41a(Revised 6/24/92)
TABLE 3-3
ADDITIONAL PROCESS OPTIONS AVAILABLE
Combustion, Inc. SiteDenham Springs, Louisiana
Process Option Description Potential Location Purpose j^iteria for Implementation
Absorbent Pads Absoibent material typically shaped as boom.Pads collected into drums for disposal.
Fine Bubble Diffuser Porous tubingwith low horsepower air blowerSystem todeveIopa'tffllfit''offinebubblesinthewater
column.
Dissolved AirFlotation Unit
Effluent Polishing
Drainage Ditch Remove any minor oil canyover from Pond Ala order to protect the downstreambiologkaltreatment system.
Pond M Promote rough biological treatment oforganks. Enhance emulsified oil removal.
''Shipboard" Oil/ Low volume oilftivater separator typically used Between Drainage Remove any heavy oil canyovsr from Pond AWater Separator onboard ships, or offshore production Ditch and Pond M in order to protect the downstream biological
platforms, treatment system.
Low volume air flotation unit.
Lowvolume Granular Activated Carbon(GAC) fitter. •
Polymer Addition Polymer preparation and Injection system.
Between Drainage Remove any heavy or emulsified oil canyoverDitch and Pond M from Pond A In order to protect the
downstream blologkal treatment system.
Between Package Reduce high level of specific organicTreatment System constituents.and Discharge Stream
Pond M or Pond N Metals and solids precipitation in Pond M.Effluent polishing in PondN.
If minor oH canyover la Ob awed mthft DrainageDitch immediately downstream of Pond A atlevels sufficient to jeopardize the downstreambiological treatment system.
K influent or effluent testing of the batch waste-water flow Indicates that additionalblologlcaltreatment Is required in order to meet tho organkseffluentdischaigel6velsiaSectlon4.0. (Batchdischarge win notbegin until the effluentdischarge limits can be met.)
If heavy ollcanyover is observed in theDrainage Ditch immediately downstream of PondAat levels sufficient toJeopardfce the downstreambiological treatment system.
If heavy or emulsified oil canyover isobserved in tho Drainage Ditch Immediatelydownstream of Pond A at levels sufficient tojeopardize the downstream biological treatmentsystem.
If effluent testing of the batch waatewater flowIndicates that additional treatment Is requiredla order to meet the effluent discharge limitsin Section 4.0. (Batch discharge will notbegmuntil the effluent discharge limits can be met)
If Influent or effluent testing of the batch waste-water flow indicates that additional treatmentIs required in order to meet the metals effluentdischarge level* in Section 4.0. (Batch dischargewin notbegin until the effluent dischaigelimits can be met.)
![Page 29: ERM-SoathwQst, inc. &85092* · 2020. 11. 24. · APPENDIX F WORK PLAN FOR REMOVAL ACTION - PHASE I Combustion, Inc. Denham Springs, Louisiana 6/30/92 ERM-SoathwQst, inc. &85092* 85092](https://reader035.vdocuments.us/reader035/viewer/2022071502/6121bd105d635e72a03a5767/html5/thumbnails/29.jpg)
During removal action activities, the metals in the water phase inPond B may be treated by in situ precipitation, if necessary, priorto discharge to Pond A. The sludge generated as a result of thistreatment step would be managed along with the existing Pond Bsolids inventory. The remaining site water will be treated at thepackage treatment system as described in Section 3.5.3.7 Air EmissionsDuring Removal Action activities the influent wastewater to Pond Mwill be analyzed for benzene, toluene, ethylbenzene, and xylenes(BTEX) compounds. The monitoring frequency is provided in Table 4-2. Concurrent with this monitoring, daily air monitoring for BTEXcompounds will be performed in accordance with the Air -MonitoringPlan. Corrective measures will be implemented if the BTEXwastewater concentrations increase along with a correspondingincrease in BTEX air emissions above their respective actionlevels. The initial response will be to reduce the wastewater flowto the treatment system in order to reduce the potential for airemissions. If air action levels continue to be exceeded, thesource of the elevated BTEX levels will be determined and sourcecontrols evaluated and implemented, if necessary ( e . g . , activatedcarbon).3.8 Contingency PlanDuring possible process interruptions, the discharge from Pond Nwill be shut off while the process performance is evaluated- Ifnecessary, the water from Pond N will be returned to one of theponds still in service. Sufficient capacity will be available dueto the initial inventory reduction described in Section 3,4- Thelong retention times in the pond system, in addition to flowrecycling, if necessary, should provide enough time to remedy thepackage plant operation or install additional or replacementprocess options, such as those described in Section 3 . 6 .
3-11 - EBM-SW41a(Revised 6/24/92)
![Page 30: ERM-SoathwQst, inc. &85092* · 2020. 11. 24. · APPENDIX F WORK PLAN FOR REMOVAL ACTION - PHASE I Combustion, Inc. Denham Springs, Louisiana 6/30/92 ERM-SoathwQst, inc. &85092* 85092](https://reader035.vdocuments.us/reader035/viewer/2022071502/6121bd105d635e72a03a5767/html5/thumbnails/30.jpg)
4 - EFFLUENT LIMITS. MONITORING AND REPORTING
4.1 Effluent LimitsDuring the past four years of daily site inspections, there hasbeen no observable off-site impact from the discharge of Pond N tothe stream located west of the site. This discharge was sampledroutinely during 1988 and the analytical results are summarized inTable 2-4. A summary of the analytical results for the pond andtank water samples for the 1989 Remedial Investigation is presentedin Table 2-3. A comparison of the relative levels of the para-meters in Tables 2-3 and 2-4 showed that site constituents weregenerally not being discharged to the stream.The purpose of the upgraded treatment system described in Section3,0 is to ensure that the historical quality of the discharge fromthe Combustion, Inc. site is not diminished as a result of sitecleanup activities. The LDEQ effluent discharge limits areprovided in Table 4-1.4.2 Monitoring SystemThe performance of the wastewater treatment system will bemonitored to ensure that the quality of the discharge is, at aminimum, being maintained, if not improved upon. The parametersfor analysis and the frequency of monitoring are provided in Table4-2. Analyses will be performed in accordance with approved EPAmethods for wastewater analysis.
4-1 ERM-SW41a(Revised 6/24/92)
![Page 31: ERM-SoathwQst, inc. &85092* · 2020. 11. 24. · APPENDIX F WORK PLAN FOR REMOVAL ACTION - PHASE I Combustion, Inc. Denham Springs, Louisiana 6/30/92 ERM-SoathwQst, inc. &85092* 85092](https://reader035.vdocuments.us/reader035/viewer/2022071502/6121bd105d635e72a03a5767/html5/thumbnails/31.jpg)
2207M41a(Revised 6/24/92)
TABLE 4-1
LDEQ EFFLUENT DISCHARGE LIMITS
Combustion, Inc. SiteDenham Springs, Louisiana
Parameter UnitsDauy
Maximum
BODCODTOCTSSpHOn & GreaseCyanide
Total MetalsAntimonyArsenicBariumCopperChromiumLeadMercuryZinc
Semivolatile OrganicsPhenol2-Methylphenol4-MethyIphenol2,4—DimethylphenolNaphthaleneN—NitrosodiphenylamineAnthracene
Volatile OrpanicsMethyfene ChlorideAcetoneMethyl Ethyl KetoneTrichloroefheneBenzene4—Methyl—2—pentanone1,1,2 -TetrachloroethaneTolueneEthylbenzeneLl—Dichloroetfaane1,2—Dichloroethane2—HexanoneTotal Xylenes
Potychlorinated BiphenylsTotal (PCB's)
mg/Lmg/LmgflLmg/Ls.u.
ms/Lmg/L
Mg/LfxS/LfLSiL
ftgfLftSfLftS/LfLg/L
ItS/L
P^L
Mg/L{LS/Lftg/LfLgfL
fLgfL
MgflLl^/LMg/LMg/LMg/LMg/LMg/LMg/LMg/LMg/LMg/LMg/LMg/L
Mg/L
12030050
1836.0 - 9.0
1513.
549100
1000500150150
5686
2610010010059
10059
891001005410010010080
10059
21110050
![Page 32: ERM-SoathwQst, inc. &85092* · 2020. 11. 24. · APPENDIX F WORK PLAN FOR REMOVAL ACTION - PHASE I Combustion, Inc. Denham Springs, Louisiana 6/30/92 ERM-SoathwQst, inc. &85092* 85092](https://reader035.vdocuments.us/reader035/viewer/2022071502/6121bd105d635e72a03a5767/html5/thumbnails/32.jpg)
2208M41a(Re vised 6/24/92)
TABLE 4-2
MONITORING FREQUENCY
Combustion, Inc. SiteDenham Springs, Louisiana
Monitoring Frequency^
Parameter UnitsContinuous Discharge Conditions^ Batch Discharge Conditions^
Innuent Effluent Influent Effluent
pHWTemperature^FlowBOD,TSSCODTOCOfl& GreaseCyanidePCBsTotal Metals <^Volatile Organics®Semivolatilc Organics^
s.u-°Cgpmmg/Lmg/Lmg/Lmg/Lmg/Lmg/Lmg/Lmg/Lmg/Lmg/L
dailydaily
continuousI/weekI/week
- I/weekI/week
No samplingN6 samplingNo samplingNo samplingNo samplingNo sampling
dailydaily
continuousI/weekI/weekI/weekI/WeekI/monthI/monthI/monthI/monthI/month,I/month
dailydaily
continuous2/week2/week2/week2/week2/week
No samplingNo samplingNo sampling
I/week^No sampling
per batchper batchper batchper batchper batch
perbatch<11)perbatcfaO1)per batch
(e)(c)(«)(c)(c)
NOTES:
(a) 24—hour flow proportioned composite samples^ Continuous discharge wul occur during routine site activities that do not involve tike removal,
treatment and disposal ofoQ, water, sludges or sous at the site.^ Batch discharge will occur during treatment system startup and during cleanup activities that involve
the removal, treatment and disposal of on, sludges or sous at the site.w Grab sample for pH and temperature(c) Per batch during treatment system startup and until treatment process has stabilized. After five monitored
batch discharges, the monitoring frequency •will be once per five batches.® See Table 4— 1 for a list of specific compounds® Benzene, Toluene, Ethylbenzene and Xylene (BTEX) only.^ It the COD and TOC are exceptionally high (e.g. greater than 50% over the average observed values), the batch will
either be resampled or treated again in order to ensure compliance with the LDEQ effluent discharge limits.
![Page 33: ERM-SoathwQst, inc. &85092* · 2020. 11. 24. · APPENDIX F WORK PLAN FOR REMOVAL ACTION - PHASE I Combustion, Inc. Denham Springs, Louisiana 6/30/92 ERM-SoathwQst, inc. &85092* 85092](https://reader035.vdocuments.us/reader035/viewer/2022071502/6121bd105d635e72a03a5767/html5/thumbnails/33.jpg)
4.3 ReportingResults of effluent testing will be reported on a monthly basis ina format consistent with that used for Discharge Monitoring Reports(DMRs) for a standard NPDES permit. The DEQ will immediately benotified of any significant non-routine occurrences, such as asystem upset or exceedance of effluent limitations.
4-4 EKM-SW41a(Revised 6/24/92)
![Page 34: ERM-SoathwQst, inc. &85092* · 2020. 11. 24. · APPENDIX F WORK PLAN FOR REMOVAL ACTION - PHASE I Combustion, Inc. Denham Springs, Louisiana 6/30/92 ERM-SoathwQst, inc. &85092* 85092](https://reader035.vdocuments.us/reader035/viewer/2022071502/6121bd105d635e72a03a5767/html5/thumbnails/34.jpg)
Activity
5 - IMPLEMENTATION SCHEDULE
Time__ _ (Calendar Weeks
1. Plan Approval2- Preparation of bid documents for
package system vendor.3. Procure and evaluate bids.4. Preliminary vendor design for package
system.5. Package system fabrication and trans-
portation to site®.6- Installation and plant startup.7. Reduce water inventory to accommodate
design storm,TOTAL
0
10
2
6
23
NOTE:w Time may be reduced by half if a standard "off-the-shelf" unit
is available.
5-1 ERM-SW41a(Revised 6/24/92)
![Page 35: ERM-SoathwQst, inc. &85092* · 2020. 11. 24. · APPENDIX F WORK PLAN FOR REMOVAL ACTION - PHASE I Combustion, Inc. Denham Springs, Louisiana 6/30/92 ERM-SoathwQst, inc. &85092* 85092](https://reader035.vdocuments.us/reader035/viewer/2022071502/6121bd105d635e72a03a5767/html5/thumbnails/35.jpg)
APPENDIX A
SUMMARY OF ANALYTICAL RESULTS FORTANK AMD POND WATER SAMPLES
(Source: Preliminary Remedial Investigation Report,Revised November 7, 1991)
![Page 36: ERM-SoathwQst, inc. &85092* · 2020. 11. 24. · APPENDIX F WORK PLAN FOR REMOVAL ACTION - PHASE I Combustion, Inc. Denham Springs, Louisiana 6/30/92 ERM-SoathwQst, inc. &85092* 85092](https://reader035.vdocuments.us/reader035/viewer/2022071502/6121bd105d635e72a03a5767/html5/thumbnails/36.jpg)
SUMHARY OF IUMLTTICM. RESULTSTAHK UATCR SAMPLES
COffitUSTIOH, INC. RX/FS
TANKWHPLETTPESAMPLE DATE
Ail. unite in ig/l except uhere noted
ftiodhoMlcal Oxygen De—ndPH.SUTotal Organic CarbonTout Otccolved SolidsToft Suspended SolidsChericat Oxygen OecandOil andGreafieriash Point, cSulfideCyanideChloride
Total Itetalc
Volatile Orflaoics
Seqivolatile Organics
2UKIER
02/OZ/89
ited
>s«ooos-s
NT•TKT
110,000630
NTKTNTKT
3UMGR
<02/02/89
>2.SOOS-4
NTKTKT
110.00065023MTNTNT
3<«lUftTER
02/02/89
>13«0005.7
NTNTNT
U7.000600
NTNTNTNT
5UKIBt
02/01/89
4,9006.1
NTNTNT
7.6802.200
NTNTNTNT
7UUER
02/01/89
>5«<»06.2.
KTNTNT
10,0002.000
NTNTNTNT
aUKTER
02/01/89
>5.0006-6
NTNTNT
11.7005.200
NTNTNTNT
10UMER
02/01/89
>5,000<.9
NTNTNT
21,000790
NTNTNTNT
NT
NT
NT
NT
NT
NT
NT
NT
NT
NT
NT
NT
NT
NT
NT
NT
NT
NT
NT
NTNT
![Page 37: ERM-SoathwQst, inc. &85092* · 2020. 11. 24. · APPENDIX F WORK PLAN FOR REMOVAL ACTION - PHASE I Combustion, Inc. Denham Springs, Louisiana 6/30/92 ERM-SoathwQst, inc. &85092* 85092](https://reader035.vdocuments.us/reader035/viewer/2022071502/6121bd105d635e72a03a5767/html5/thumbnails/37.jpg)
SUMMARY OF AMALYT1CAL RESULTSTAMK UATER SAMPLES
COMBUSTION. INC. RI/FS
TAMKawLETWEtWLEOATE
11UATER
02/01/89
12UMCR
02/01/89
13 <b)UATER
n/18/86
13UATER
02/OVBff
14UATER
11/18/86
14UATER
02/01/89
15UATER
02/01/89
All unftc fn wo/I except uhere noted
•iocheifcal Oxygen Oecand?".«>Total Organic CarbonTotal Ofccolved SolidsTotal Suspended SoltdsCheafcal Oxygen DemandOil •nd GreaseFlach Point, CCulftdeCyanideChloride
Total ItetalsftntfffionyArcenicBariuBChnriuRCobaltLead
Volatile Organics
Senivolatile OrganTcs
3.1006.1
HT«TNT
19.80094HTNTNTNT
>2,SOT7.2t"KTHT
8,1004.200
NTHTHTNT
NTNT
135.000'69.200
NTNTNTNTKTNTNT
NTKTNTNT
13.400NT
8.20030NTNTKT
. NTNT
SBS36
NTNTNTKTNTNTNT
>S.OOO0.1
NTNTNT
8.800270
NTNTNTNT
>2.5004.1
NTNTNT
73.0004.500
NTNTNTNT
NT NT NT NT NT6.6
ND <0.2S)0.1
MO <o.onNO <0.1)ND <0-01)NO (0.02)NO (0.1>
NT
NT
2-70.48
HO <0.02)3-9
NT
NT
NT
NT
NT
NT
NT
NT
NT
MT
NT
NT
![Page 38: ERM-SoathwQst, inc. &85092* · 2020. 11. 24. · APPENDIX F WORK PLAN FOR REMOVAL ACTION - PHASE I Combustion, Inc. Denham Springs, Louisiana 6/30/92 ERM-SoathwQst, inc. &85092* 85092](https://reader035.vdocuments.us/reader035/viewer/2022071502/6121bd105d635e72a03a5767/html5/thumbnails/38.jpg)
SUWURT OF ANALYTICAL RESULTSTAKt: UATER SAHPLES
COHBUSTKM. INC. KI/FS
SAHPl£TWEMptEOKIE
HU tnlte fn no/I except Nhere
loch—teal Oxygen D«i—nda. su
Toft Organic Carbonotal Ol«colved Colfdslotal Cucpended SolidsCfwEcal Oxygen OcoiandHI and Creasel«ch Point, C
Sulftdefynide|hloride
I Total MetalsftnttaonyArcenicBartuaChroonunCobaltLead
1/olatUe OrganiccHethylene ChlorideAcetone1.1-Oiohloroethane1.2-DichloroethaneTrichtoroetheneBenzene2-ftexanoneToluene
|Seaivolatile Organics
18
UATEROZ/OT/89
noted
NT6.2
4NTMTKT13IT
KO <0.05)N0 (0.01)
12
KT—
HD <0.005)——
NO (0.025)— -—
NT— -—
0.94 (0.25) — — ———— ——————
0-52 (0.25)——
22
WTERC6/Si/S9
2405.2200320W
550S5
XO110 (C.OS)KO (0.01)
NT
MD 1:0.1)
0.16
0.040.31
1.9 (0-25)1.4 (0.50)
1.7 (0.25)0.3 (0.25)
0.91 (0.50)0-93 (0,25)
22(a)
UATER05/31/B9
2605.5190330280590350>60
HTNTKT
NO (0.1)0.009
0.2HO (0.025)
0.0410.75
NT——
——
——
23<PondArea)
UATER02/23/89
1,0005.6300
NTKT
9701»500
MT0.17 (O.OS)
110 (0.05)100
NT——————
KT—
-
- -- -
-—
23 (a)(Pond Area)
UATEK02/23/89
1,1005-6
NTITKT
3,6002,700
NTNTNT«T
NT——
-
—--
NT--
—
---.
—"
24(Pond Area)
UATER02/23/89
ai6.6
48160
NT10082NT
NO (O.OS)KO (0.01)
12
NT———
.—---
NT-
-
——
-—
24 (a)(Pond Area)
UATERC2/23/C9
226.340
170NT
1008
NTW (O.OS)MD (0.01)
12
NT—"———•"~
NT--
—
-—
-—
KT NT NT NT NT KT KT
Abbreviations
ND = Not detected at detection Limit shorn in parentheses.'NT e Not tested.
, Footnotes
(a) Delicate sample-(b) Average of two replicates, except for metals-
![Page 39: ERM-SoathwQst, inc. &85092* · 2020. 11. 24. · APPENDIX F WORK PLAN FOR REMOVAL ACTION - PHASE I Combustion, Inc. Denham Springs, Louisiana 6/30/92 ERM-SoathwQst, inc. &85092* 85092](https://reader035.vdocuments.us/reader035/viewer/2022071502/6121bd105d635e72a03a5767/html5/thumbnails/39.jpg)
SUHKARY Of AHALYTICAL RESULTSPOND HATER SAMPLES
COH8USTIOH, INC. RI/FS
CMD1WPUETWE
SNNHJEDME
Lit unite In •g/t except «4iere noted
•iocheilcal Oxygen OeMndpN,SUTatel Organic CarbonToft Ol—otved Solids[Total Suspended SolidsCheMtcal Oxygen OeiandOil «nd Grease•Flach Point. CSulflde'CyntdeChloride
Tofl MetalsAnttaony
1 AccenfcCariinChroMimCobaltLead
VoltUe Organics .
I Methylene ChlorideAcetoneTrichloroetheneBenzene
| Total Xyleocs
Seaif volatile Organlcs
1 Phenol2-Kcthylphcnol4-Hethylphcnol
1 2. -OiBCthylphenolnaphthaleneK-Nitrosodtphen/lanineAnthracene
AUlTER
01/27/89
984.2«9
WO12
ISO11NTKTMTKT
10 <0.005)W <0.005)
MO (0.05)fl-019
NO <0.02S>MD <0.006)
NT—
—. - — UD <0.010)— : --- - -- — NO <0.005>
———— NO (0.005)— — NO <O.OOS>
NT———————
BUATCR
11/17/86
KTNT
6001490
NT«TNTNTNTNTNT
30NO (0.25)
113.W6
275
NT—
NT————
-——
8WATER
01/30/89
1104.5
NTNTNT
360SOT
NTNTNTNT
NT— 0,OM (0.005?
NO <0.005)0.69 <0-C51
—— 0-052 <0.02S)—
NT—
HT——
- —= - —
- —. —
- --
CUATER
01/30/89
1404.4ISO232NT
590640
KTNTNTNT
.
0.062
1-7
NT~ — ID (0.005)
NT
—
- — -- - —
- - -
0UATER
01/237B9
254.366
loONT
1879
NTNTNTNT
NO (0.005}NO (0.005)
NO (0.05)0.045
NO (0.025)NO <0.005)
NT
NT—
-—
-,.
—-
EHATER
01/26/89
256
38160NT
2181-2NTNTNTNT
NO (0.005)NO (0.005)
O.OS90.009
NO (0.025)HO (0.005)
NO (0.02)ND (0.02)ND (0.02)NO (0.02)
— NO (0.02)NO (0.02)ND (0.02)
Note: The Pood 8 uater sample collected on November 17, 1986 contained a significant amount of solids stirred up from thebottom of the pond (see analysis of Pond B solids in Table 9 for cooparison). The Pond B water uas resampled onOctober 10. 1989 and analyzed for Total Lead. The result (average of sample and blind duplicate) was0.30 ftg/l of lead. This value uas used in the Public Health Evaluation and Endangennent Assessment rather than thevalue of 275 ng/l shoun above-
![Page 40: ERM-SoathwQst, inc. &85092* · 2020. 11. 24. · APPENDIX F WORK PLAN FOR REMOVAL ACTION - PHASE I Combustion, Inc. Denham Springs, Louisiana 6/30/92 ERM-SoathwQst, inc. &85092* 85092](https://reader035.vdocuments.us/reader035/viewer/2022071502/6121bd105d635e72a03a5767/html5/thumbnails/40.jpg)
SUMHARY OF AHALYTIOU. RESULTSPOHO UKTER SAMPLES
CDHBUSTIOH. IHC- RX/FS
POHOSAHPLETYPESAMPLE DATE
FUATEB
01/31/119
GUATER
01731/891 TO 2 FT- UATER
-01/31/W2 10 4 FT. UATEtl
01/31/89
IUATER
01/27/89
Ml unite fn a«/t except uhere noted
•tocheaiical Oxygen De—nd 130ptt CSU) 4.2Tool Organic Carbon 7Toft Ofccolved Solids ZS1Tori Suspended Solids NTCherical Oxygen Demand 261Oil and Grease 120Flach Point <C) NTSulfide KTCyanide NTChloride NT
563-981IBSNT
2S9ISONTNTNTNT
904.1«S184NT586730NTNTHTNT
480S82rsoNT
18302300NTNTNTNT
7.44.43484NT866.7NTNTNTNT
Total KetalsAntfionrArsenicBariunChrociuBCobaltLe»d
NO CO.OOS)HO <0-005)
0.0970.0130.0270.20
0.051ND <O.OOS>NO <0.05)
0.01SND <0.025)MD <0.025)
0.051(0.005)
0.270-017O.OS90.73
0.560.014
2.20.3S0.13
9
NO <O.OOS>0.007 <O.OOS>
*t0 C0.05)0.006
NO <0.02S>0.009
Volatile Organics
Semi volatile Organics
NT
NT
NT
NT
HT
NT
NT
NT
NT
NT
![Page 41: ERM-SoathwQst, inc. &85092* · 2020. 11. 24. · APPENDIX F WORK PLAN FOR REMOVAL ACTION - PHASE I Combustion, Inc. Denham Springs, Louisiana 6/30/92 ERM-SoathwQst, inc. &85092* 85092](https://reader035.vdocuments.us/reader035/viewer/2022071502/6121bd105d635e72a03a5767/html5/thumbnails/41.jpg)
SUMMARY OF ANALYTICAL RESULTSPOHO UATER SAMPLES
COMBUSTION, INC. Rl/FS
P010 J K L H HUHPLE TYPE UATER UATER UKTER UATER UATERSIMPLE DATE - 01/26/89 01/27/89 01/24/89 11/17/86 01/25/89
All unite In •o/l except uhere noted
•fochenical Oxygen Oeound 10pH. SOTotal Orsanfc CarbonTotal Olccolved SolidsTout Suspended SolidsChenfcal Oxygen DemandOil •ncf GreaseFtafh Point, CSulfideCyanideChloride
Eed
106.238
130KT90
«D 0.0)NTNTNTNT
105-55296NT
1603.5
NTNTKTNT
6.16.2 .38
130NT97
5.3KTKTNTNT
NTNT
130123NTNTNTNTNTNTNT
405.1
NTNT40
4105-7NTNTNTNT
Total MetalsAntiwonyArsenicBarimChroanuolCobaltLead
Volatile Organicc
NTND <0.005> NO (0.005> ND (0.005) NO (0.1)
0.011 NO (0.005> ND (0.005) NO <0.01?0.057 0.19 . 0.058 NO (0.1}0.013 0.006 0.009 N0 (0.01)
ND <0.025) NO (0.025) N0 (0.025) N0 (0.02)N0(0.025} HD,<0.025> 0-042 HO (0-1)
NT NT NT NT
SeRfvotatile Organics NT ' NT NT NT
NT
NT
![Page 42: ERM-SoathwQst, inc. &85092* · 2020. 11. 24. · APPENDIX F WORK PLAN FOR REMOVAL ACTION - PHASE I Combustion, Inc. Denham Springs, Louisiana 6/30/92 ERM-SoathwQst, inc. &85092* 85092](https://reader035.vdocuments.us/reader035/viewer/2022071502/6121bd105d635e72a03a5767/html5/thumbnails/42.jpg)
SUMMARY OF ANALYTICAL RESULTSPOUO WATER SAMPLES
COMBUSTION. INC. Rl/FS
PONDawiETweBWLEDATE
All unite In •s/t except tAerc noted
ftfochndcal Oxygen DemandpH.SOTotal Organic CarbonTotal Olcntved ColtdeTotal Suspended ColtdcCheancal Oxygen beundOft id GreaseFlash Polnt< CCulfideCyanideChloride
Total MetalsAntiionyArcenfcearfURChrocniunCobaltLead
Volatile OraanicsKethyicne Chloride.AcetoneTrichloroetheneBenzeneTotal Xylenes
Semi volatile OrganicsPhenol2-Hethylphenot4-Hcthytphenot2,4-OimetftylptKnolNaphthaleneN-Ni trosodiphcnylaatineAnthracene
MUATER
11/17/86
fed
MTMT
105loZ ,
KT'NTur«Tin-KTNT
0.2NO <0-01J
NO (0.1)W (0.01)KD (0.02}
NO (0.1>
NT— ——— 0-017 <O.OQ5)
— 0.13 <0.010)— 0.01 (O.OOS)-- 0-005 (0.0051
— — 0.014 (0.005}
NT0.036 (0.01)0.017 (0.01)0-035 (0.01)0-023 (0.01)0.021 (0.01>0.015 (0.01)0.011 (0.01)
K trt-V (a)UATER
01/25/119
335.3
NTMT57
130NTNTMTMTKT
NT—
— ND (0.005)—
— NO (0.025)— NO (0.025)
—
NT
tWTEft01/25/89
NTNTNTNTNTNTNTNTNTNTNT
NT---
- - -
—
NT
Off-SitePondlUATER
02^24/89
NT6.8
8NTNTNT
1.3NT
NO (0.05)NO (0.01)
15
ND (0.005)
0-07
KD (0.025)
NO (0.005)NO (0.010)UO (0.005)NO (0.005)NO (0.005)
KD (0-02)NO (0.02)N0 (0.02}N0 (0.02)N0 (0.02)N0 (0.02)N0 (0.02)
Off-SitePond 1 (b)
UATER02/24/89
NT6-7
NTNTMTNT
1.2NTNTNTNT
ND (0.005)0.0080.075
ND (0-025)ND (0.025)NO (0.005)
ND (0.005)NO (0.010)NO (0.005}NO (0.005)NO (0.005)
NO (0.01)ND (0.01)NO (0.01)HO (0.01)ND (0-01}NO (0.01)MD (0-01)
Abbreviations
ND = Not detected at detection limit shoun in parentheses.NT = Not tested.Footnotes
(a) Grab samples collected for volatile orgamcs analyses.(b) Duplicate sample.
![Page 43: ERM-SoathwQst, inc. &85092* · 2020. 11. 24. · APPENDIX F WORK PLAN FOR REMOVAL ACTION - PHASE I Combustion, Inc. Denham Springs, Louisiana 6/30/92 ERM-SoathwQst, inc. &85092* 85092](https://reader035.vdocuments.us/reader035/viewer/2022071502/6121bd105d635e72a03a5767/html5/thumbnails/43.jpg)
APPENDIX B
1988 POND N DISCHARGE MONITORING
(Sources Preliminary Remedial Investigation Report,Revised November 7, 1991)
![Page 44: ERM-SoathwQst, inc. &85092* · 2020. 11. 24. · APPENDIX F WORK PLAN FOR REMOVAL ACTION - PHASE I Combustion, Inc. Denham Springs, Louisiana 6/30/92 ERM-SoathwQst, inc. &85092* 85092](https://reader035.vdocuments.us/reader035/viewer/2022071502/6121bd105d635e72a03a5767/html5/thumbnails/44.jpg)
F Parameter JANUARY 12
1 ""
opie Date;
Cat Organic Carbon, ng/L 75
it ft Grease, ng/L 3.0
L 6-0
, ag/L ND <0-001)
ead, «g/L Pb ND (0.1)
odheaical OxygenOeaand <B>g/L 02} ' 1 4
iority Pollutants:
olatile Organic Compounds Below DetectionBenzene, igg/L • Liaits For AllChlorobenzene, ing/L CompoundsToluene, ng/LiTrichloroethene, ffig/LKethylene Chloride, ng/L
r Total Xylenes, aQ/i
Belou Detection1 Linits For Alt
Other Compounds
ise/Neutral Organic Below DetectionCompounds Limits For All
i Compounds
^cid Extractable Organic Belou Detection| Compounds Linits For All
Compounds
POND AREA DISCHARGE MOUITDRIHGCOKBUSTIOM, IKC.
1988 POND N DISCHARGE
January - June
FEBRUARY 13 WWCH 17 APRIL U HAY JUNE
67 98 62 No Flow No Flow
3-8 0.4 1-5
6.1 S-6 5.8
ND (0.001) ND (0.001) ND (0.001)
ND (0.1) NO (0.1) ND (0.1)
26 110 36
Below Detection Below Detection0.025 Liaits For All Limits For All0.032 Conpounds Compounds0.0670.038
NO (0.010)HD (0.010)
Below Detection Belou Detection Belou DetectionLimits For All Limits For All Limits For AllCompounds Compounds Conpounds
Belou Detection Below Detection Belou DetectionLimits For All Limits For All Limits For AllCompounds Compounds Compounds
![Page 45: ERM-SoathwQst, inc. &85092* · 2020. 11. 24. · APPENDIX F WORK PLAN FOR REMOVAL ACTION - PHASE I Combustion, Inc. Denham Springs, Louisiana 6/30/92 ERM-SoathwQst, inc. &85092* 85092](https://reader035.vdocuments.us/reader035/viewer/2022071502/6121bd105d635e72a03a5767/html5/thumbnails/45.jpg)
1 POHO AREA DISCHARGE HOMITORIHGCOMBUSTION, INC.
L 1988 POND N DISCHARGE
• July - Deceraber
Par—eter JULY 28 AUGUST 30 SEPTEMBER 30 OCTOBER
pie Date:
1 Organic Carbon, mg/L 70 80 66 Mo Flow
b Grease, cg/L 1.4 1.6 2.6
6.0 6-0 S-6
, ag/L NO (0.001) NO (0.001) HO <0.001)
d, •g/L Pb ND (0.1) NO <0-1) NO (0.1)
•heflncal OKygenLoand (mg/L 02} 14 29 17
Betty Pollutants:
Ltile Organic Compounds Below Detection Below Detection Below DetectionInzene, •g/L Limits For All Limits For ALL Limits For Allfnlorobenzene, •g/L Compounds Compounds Compoundsroluene, ao/i.lichloroethene, mg/Lpthytene chloride, Bag/Ltotal Xylenes, mg/L
|rL6/Netrtral Organic Belou Detection BeLow Detection Below Detection
^xnpounds Limits For All Limits For All Limits For AllConpounds CotBpounds Compounds
id Extractable Organic Belou Detection Belou Detection Below Detection|fflpounds Limits For All Limits For All Limits For All
Compounds Compounds Compounds
- - .
NOVEMBER DECEMBER 28
No Flow 64
2.3
5.5
110 (0.001)
ND (0.1)
22
0.029N0 (0-001)
0.0380.0310.0100.031
Below DetectionLimits For AllOther Compounds
Below DetectionLimits For AllCompounds
Below DetectionLimits For AllCompounds