PAR 1085 – SOUTH SECONDARY IMPROVEMENTS PROJECT A 4D GIANT Eric M. Wetzel Carollo Engineers, Inc. Bentley Be Inspired Awards November 13, 2012

Upload: sharon-goy

Post on 14-Dec-2015

219 views

Category:

Documents


4 download

TRANSCRIPT

Page 1: Eric M. Wetzel Carollo Engineers, Inc. Bentley Be Inspired Awards November 13, 2012

PAR 1085 – SOUTH SECONDARY IMPROVEMENTS PROJECT

A 4D GIANT

Eric M. WetzelCarollo Engineers, Inc.

Bentley Be Inspired AwardsNovember 13, 2012

Page 2: Eric M. Wetzel Carollo Engineers, Inc. Bentley Be Inspired Awards November 13, 2012

• PAR 1085 South Secondary Improvements Project• What is 4D?• Building the 4D Model• 4D Visualization• The Benefits• Summary• Questions

South Secondary Improvements Project

Outline

Page 3: Eric M. Wetzel Carollo Engineers, Inc. Bentley Be Inspired Awards November 13, 2012

South Secondary Improvements Project

Metro Wastewater Reclamation District Robert W. Hite Treatment Facility

(The District)

Page 4: Eric M. Wetzel Carollo Engineers, Inc. Bentley Be Inspired Awards November 13, 2012

DAF & Centrate Modifications

Ammonia Facility

Stage 5, RAS Pump Stations, Secondary Clarifier Modifications

South Aeration Complex (SAC)

• $136 million w/ potential $1.8 million bonus for early completion

• Meets new wastewater discharge criteria and adds capacity

• Very tight schedule to meet permit compliance

South Secondary Improvements Project

Page 5: Eric M. Wetzel Carollo Engineers, Inc. Bentley Be Inspired Awards November 13, 2012

Carollo Engineers’ Role

• Design Engineer & Owner’s Representative during construction

• Review Contractor’s construction schedule to verify compliance with the Contract

• Responsible for 3D and 4D models

Page 6: Eric M. Wetzel Carollo Engineers, Inc. Bentley Be Inspired Awards November 13, 2012

What is 4D?

South Secondary Improvements Project

Page 7: Eric M. Wetzel Carollo Engineers, Inc. Bentley Be Inspired Awards November 13, 2012

What is 4D?

• 4D is a tool that links a 3D CAD model with a construction schedule

• The resulting 4D model allows visualization of the planned construction sequence

3D Model + Schedule = 4D Visualization

Page 8: Eric M. Wetzel Carollo Engineers, Inc. Bentley Be Inspired Awards November 13, 2012

Building the 4D Model

South Secondary Improvements Project

Page 9: Eric M. Wetzel Carollo Engineers, Inc. Bentley Be Inspired Awards November 13, 2012

3D Model

• Software Used Bentley Microstation V8 XM Bentley Architecture V8 XM Bentley Structural V8 XM PlantSpace Design Series V8 XM InRoads XM ProjectWise V8i ProjectWise InterPlot Navigator V8i

• 65 Total Models Anything above 2” pipe was modeled

• 99 Reference Files• Completed during the design phase• Finalist – Be Inspired Awards 2011

Page 10: Eric M. Wetzel Carollo Engineers, Inc. Bentley Be Inspired Awards November 13, 2012

3D Model Elements

• To achieve a 4D visualization, the 3D model must be designed into constructible elements Construction Joints Pipe Joints

• 3D model must match the depth of the construction schedule

Page 11: Eric M. Wetzel Carollo Engineers, Inc. Bentley Be Inspired Awards November 13, 2012

Construction Schedule

• Software: Primavera P6 v7.0

• Extremely detailed consisting of 12,143 activities

Structural Drawings vs. Construction Schedule

Page 12: Eric M. Wetzel Carollo Engineers, Inc. Bentley Be Inspired Awards November 13, 2012

Linking the Model and Schedule

• Import accepted Primavera P6 Schedule into Bentley Navigator V8i

• Link activities in Schedule to Item Sets in the Model Drop and Drag

• After Linking is complete: Close Navigator V8i and Open linked

model in Microstation Use Animation Producer in

Microstation to create image frames Set time frame (May ‘11 – June ‘13) Set frame duration (daily, weekly, etc.)

Import frames to Camtasia for .AVI development

Page 13: Eric M. Wetzel Carollo Engineers, Inc. Bentley Be Inspired Awards November 13, 2012

Visualizing the Visualization

• While watching the 4D visualization• Every start activity will turn

the item set within the model green

• Every finish activity will turn it to the model color. Yellow in this example

Example: Concrete – Rebar, Form, Pour, Cure

Page 14: Eric M. Wetzel Carollo Engineers, Inc. Bentley Be Inspired Awards November 13, 2012

4D Model – South West Blower Building

PAR 1085 South Secondary Improvements Project

Page 15: Eric M. Wetzel Carollo Engineers, Inc. Bentley Be Inspired Awards November 13, 2012

The BenefitsHow does this help?

South Secondary Improvements Project

Page 16: Eric M. Wetzel Carollo Engineers, Inc. Bentley Be Inspired Awards November 13, 2012

4D Benefits

• Tool for Risk Mitigation• 4D analysis validated Contractor’s realistic ability

to obtain full bonus ($1.8 million)• Detailed review and identification of issues in the

schedule

Page 17: Eric M. Wetzel Carollo Engineers, Inc. Bentley Be Inspired Awards November 13, 2012

Example 1: Concrete Pour Sequence Compliance

Schedule Bust: Wall and Slab are poured concurrently. A single bust = Potentially 14 calendar days.Schedule Bust: Wall is being poured prior to Slab

Page 18: Eric M. Wetzel Carollo Engineers, Inc. Bentley Be Inspired Awards November 13, 2012

Example 2: Missing Activities/Links or Inappropriate Logic

“A” – Schedule did not reflect updated CJs.

“B” – Threshold of two facilities. Not accounted for in schedule

AA

B B

Missing Activities/Links

Upon completion of linking the schedule to the model, linked items can be turned off to show only model items not linked to an activity

Page 19: Eric M. Wetzel Carollo Engineers, Inc. Bentley Be Inspired Awards November 13, 2012

Example 3: Visual Assessment of Actual vs. Planned

10/2/2012

Page 20: Eric M. Wetzel Carollo Engineers, Inc. Bentley Be Inspired Awards November 13, 2012

4D Benefits – Cont.

• An updated 3D model for Owner’s use

• Public Outreach• Identification of non-

conformance with Contract

• Ability to look-ahead and plan for future Work activities

Page 21: Eric M. Wetzel Carollo Engineers, Inc. Bentley Be Inspired Awards November 13, 2012

Summary

South Secondary Improvements Project

Page 22: Eric M. Wetzel Carollo Engineers, Inc. Bentley Be Inspired Awards November 13, 2012

Summary

• 4D tool mitigated significant risk associated with a complex and accelerated schedule

• Minimize logic loops, missing activities, non-conformance, etc, to account & save significant time in the schedule. Estimated at 60 working days to date

• A tool to engage stakeholders without a tangible connection to the project

• An updated 3D model that can be used for facility maintenance or modifications

• Versatile Bentley software was utilized in all facets of 3D and 4D development No hardware or software costs incurred to produce 4D

Page 23: Eric M. Wetzel Carollo Engineers, Inc. Bentley Be Inspired Awards November 13, 2012

Questions?

Eric M. Wetzel, LEED-AP BD+CProject ControlsCarollo Engineers, Inc.390 Interlocken Crescent, Broomfield, CO 80021(303) 286-3047