ERCOT Planning Go-Live Update. Jay Teixeira Manager, Seasonal Planning. ERCOT Concerns regarding Planning Go-Live. Topology Processor is in production for CRR Data, such as connectivity node groups (CNG) must be maintained by ERCOT and TSPs - PowerPoint PPT PresentationTRANSCRIPT
November 11, 2010
ROS
ERCOT Planning Go-Live Update
Jay TeixeiraManager, Seasonal Planning
2 ROSNovember 11, 2010
ERCOT Concerns regarding Planning Go-Live
• Topology Processor is in production for CRR– Data, such as connectivity node groups (CNG) must be
maintained by ERCOT and TSPs– Equipment IDs and Circuit IDs for all equipment must be
populated and unique and are dependent on correct CNG definition
• TSPs will need to commit to Go-Live barring unforeseen major problems– SCR needs commitment
• No reflection on current TSP efforts, but TSPs will need to commit necessary resources to complete testing in an expeditious manner– 2012 Base Case testing– SCR testing, testing timelines will be tight– Building base cases while testing system has stressed workload
3 ROSNovember 11, 2010
ERCOT Concerns regarding Planning Go-Live
• June PLWG discussion on no longer creating Data Set A cases because TSPs do not use them
• Delay affects Data Set A cases which where shown to be mainly used by ERCOT– Big effect on Near Term congestion analysis and studies to
support ERCOT Operations– Studies simulate planned outages, manual process to map to
SSWG cases
4 ROSNovember 11, 2010
Data Set A Uses from June PLWG meeting
ERCOT Use DS A Case Used
Determining Flat load for Near Term congestion and 5 year plan cases
Uses all 8 cases for range of load level.
SPS Reviews Can use any of all 8 cases depending on SPS under study and time frame
RMR Analysis Can use any of all 8 cases depending on RMR unit under study and time frame
Transmission Loss Factor Calculations Uses generation, load, losses from all 8 cases
Near term congestion analysis Uses summer peak topology
ERCOT Operations requested studies Can use any of all 8 cases
Dynamic Data Set (wind and no wind) Currently use summer peak, DWG proposal to use peak and off-peak case
Stability Screening Studies (Dynamic and Voltage)
PV and TS for summer, PV for winter peak and TS for winter off-peak
NERC Compliance Studies Summer peak and one off-peak
Voltage Profile Studies Peak(Sum, Win) and Off peak (Spg, Fal) cases
5
Current Process – Separate System for Planning
ROS November 11, 2010
ERCOTManual Process
TSP Review
Case complete
?
Case Posted
Yes
NoTSPs submitChanges via IDEV, other
NMMS db
ERCOT Topology
Processor for ODMS
ERCOT/TSP Network Model
update via NOMCR
CRR Top Output
Planning Case
Creation
ERCOT Dispatch
TSPs submit RAWD files for their area
containingTopology,
Load, Voltage Control
6
Topology Processor/Model on Demand Integrated System
ROS November 11, 2010
TSPProfiles
Planning Topology
Output
TSP Review
Case complete
?
Case Posted
Yes
NoTSPs submitChange via MOD
NMMS db
ERCOT Topology
Processor for ODMS
ERCOT/TSP Network Model
update via NOMCR
CRR Topology Output
Planning Case Output
ERCOTModel on Demand
TSP Standard PMCR
TSP Future PMCR
ERCOT DispatchProfile
7
Model on Demand Separated System
ROS November 11, 2010
TSPProfiles
Topology from Existing
Planning Case
TSP Review
Case complete
?
Case Posted
Yes
NoTSPs submitChange via MOD
NMMS db
ERCOT Topology
Processor for ODMS
ERCOT/TSP Network Model
update via NOMCR
CRR Top Output
Planning Case Output
ERCOTModel on DemandTSP
Future PMCR
ERCOT DispatchProfile
8
MOD Standard PMCR Count by TSP as of 11/8/10
ROS November 11, 2010
Bus Branch Load GenSwiched Shunt XF FACT
Mult-Section Lines Area Owner Totals
Total of DSB Submission
%Size of DSB submission
AEN Add 1 14 1 7 1 24Delete 2 23 3 1 29Modify 2 14 16
3 37 6 1 0 21 1 0 0 0 69 263 26.24%AEP Add 8 1 133 8 1 9 1 3 164
Delete 3 5 7 1 1 17Modify 7 2 5 2 16
18 6 133 17 2 10 0 0 6 5 197 2638 7.47%CNP Add 38 165 97 9 26 7 151 493
Delete 93 251 125 9 21 5 504Modify 10 7 6 86 109
141 423 228 18 47 98 0 151 0 0 1106 1833 60.34%CPS Add 13 13
Delete 13 6 19Modify 22 22
0 26 6 0 22 0 0 0 0 0 54 349 15.47%GPL Add 6
Delete 6Modify 2 1 3
0 2 0 13 0 0 0 0 0 0 3 273 1.10%LCRA Add 383 383
Delete 324 324Modify 1 1
0 0 708 0 0 0 0 0 0 0 708 1043 67.88%Oncor Add 253 253
Delete 2 2Modify 0
0 0 0 0 255 0 0 0 0 0 255 5087 5.01%STEC Add 6 3 3 12
Delete 6 16 3 25Modify 4 4
0 12 23 0 0 6 0 0 0 0 41 5087 0.81%AEN deleted Gen is Statcom, added back as new bus and FACTDSB case used was 12Sum1 of pass9 11DSB. Only Busses, Branches, and Transformers were included in count.
Topology Processor Results from the 2010 Test case as of 11-08-2010
9
SCR Resolution Methodology (Preliminary)
ROS November 11, 2010
Deficiency Number
Deficiency Description
Requested
Functionality currently
exists in MOD
Changes required if SCR is
Implemented
CIM Modification
Topology Processor
Code Change
Potential Impact to
other Nodal Systems
1 Topology Processor Upgrade to output PSS/E v32
Y Y Y Y
2 Distribution Cap Banks
Y Y Y Y
3 Zero Impedance line ratings
Y N Y N
4 Associate Loads and Caps with the correct CNG
Y Y Y Y
5 Additional Autotransformer data for Planning
Y Y Y Y
6 FACTS Devices
Y Y Y Y
7 Assign valid PSSE IDs to Breakers/Switches/Series Devices
Y N Y N
8 Phase shift of Autos for short circuit studies
Y Y Y Y
10
SCR Resolution Timeline (Preliminary)
ROS November 11, 2010
Month/Yr Action Required
Nov 10 SCR760 submitted, begin Nodal Project stabilization prioritization, include SCR759
Dec 10 Impact Analysis on SCR760
Jan 11 Finalize stabilization projects priority, SCR760 to Board of Directors
Feb 11
Mar 11 SCR760 items involving only Topology Processor code fixes possible
Apr 11 Begin Data Set A build with Integrated or MOD Separated System
May 11 Remaining SCR760 items deadline for Annual Planning Model
Jun 11
Jul 11 Begin Annual Planning Model Updates using Integrated System (pass 0)
Aug 11
Sep 11 Annual Planning Model Updates Due September 1 (equiv pass 4)
Oct 11 Annual Planning Models Released October 15th
11
ERCOT Request
ROS November 11, 2010
• SSWG commitment to Go-Live barring unforeseen major problems
• TSPs commitment to provide resources to complete testing in an expeditious manner
• Decide Model on Demand Separated System Go-Live for 2012 Data Set A case build first
• Then decide for 2012 Data Set A whether to move to Topology Processor/Model on Demand Integrated System
12
Other Issues
November 11, 2010 ROS
13
Protocol 3.10.2 – Which Five Years?
ROS November 11, 2010
3.10.2 Annual Planning Model (1)For each of the next five years, ERCOT shall develop models for annual planning purposes that contain, as much as practicable, information consistent with the Network Operations Model. The “Annual Planning Model” for each of the next five years is a model of the ERCOT power system (created, approved, posted, and updated regularly by ERCOT) as it is expected to operate during peak Load conditions for the corresponding future year.(2).(3).(4).
(5)ERCOT shall coordinate updates to the Annual Planning Model with the Network Operations Model to ensure consistency of data within and between the Annual Planning Model and Network Operations Model to the extent practicable.
14 ROSNovember 11, 2010
Topology Processor/SSWG Case Comparison
Difference In 8/30/2010 10/5/2010 Delta %Impedances Both R&X 789 382 -51.6%
R 53 21 -60.4%X 68 53 -22.1%
Total 910 456 -49.9%Line Ratings Both Rate A and B 370 67 -81.9%
Rate A 28 10 -64.3%Rate B 89 87 -2.2%
Total 487 164 -66.3%
• Case Comparison between Topology Processor and 10FAL1 case– Limited to those differences greater than 5%
– Limited to Branches that exist in both cases (From Bus, To Bus, Circuit ID exactly the same)
Branches in Compare list 7965Branches in Both Cases 5142
64.6%
Questions?
November 11, 2010 ROS