ERC Recertification Summer 2014. Federal-aid Program Contracts. INDOT-LPA Contract. Stewardship & Oversight Agreement: INDOT & FHWA FHWA & INDOT are jointly responsible for how the Federal-aid program is developed and implemented. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: ERC Recertification Summer 2014

ERC Recertification

Summer 2014

Page 2: ERC Recertification Summer 2014

Federal-aid Program Contracts

Page 3: ERC Recertification Summer 2014

INDOT-LPA Contract

Stewardship & Oversight Agreement: INDOT & FHWA FHWA & INDOT are jointly responsible for how the Federal-

aid program is developed and implemented. INDOT, acting on behalf of FHWA, is expected to exercise

judgments similar to FHWA based on Federal laws, regulations and policies.

Page 4: ERC Recertification Summer 2014

INDOT-LPA Contract

INDOT-LPA Contract This contract states agreement between both parties

on: Project description LPA Responsibilities, rights & duties INDOT Responsibilities, rights & duties Project Funds Terms & Schedule General Provisions & compliance

Page 5: ERC Recertification Summer 2014

INDOT-LPA Contract When does this happen? Contract Breakdown

Sections I-VI Attachments A-D

Page 6: ERC Recertification Summer 2014

INDOT-LPA Contract Section I

Section II

Section III

Page 7: ERC Recertification Summer 2014

INDOT-LPA Contract Section IV

Section V

Page 8: ERC Recertification Summer 2014

INDOT-LPA Contract Section VI

A-T provisions outlined in contract Some highlights to be aware of:

Access to records Audits Compliance Disputes Non-discrimination (ADA, DBE)

Page 9: ERC Recertification Summer 2014

INDOT-LPA Contract Attachment A- Project

Description Attachment B- LPA’s Rights and

Duties Attachment C- INDOT’s Rights

and Duties Attachment D- Project Funds

When can I start my project?

Page 10: ERC Recertification Summer 2014

LPA-Consultant Contract

What YOU need to know!

Hiring a consultant through competitive negotiation:

Page 11: ERC Recertification Summer 2014

LPA-Consultant Contract Objectives

1. Ability to understand the various types of contracts and their elements.

2. Empower YOU to successfully negotiate a contract.

$$$ Schedule Appropriate for the project

Page 12: ERC Recertification Summer 2014

Items to cover: Contracting sequence Contract compensation methods Contract review checklist Consultant prequalification letter Profit calculation worksheet Compensation/escalation value

LPA-Consultant Contract

Page 13: ERC Recertification Summer 2014

LPA Contracting SequenceLPA-Consultant Contract

ERC reviews

the Consultant Selection Toolkit on the INDOT website.

ERC requests the

Disadvantaged Business Enterprise (DBE) goal

through email by going to the INDOT website.

ERC drafts a Request for Proposals

(RFP) using the RFP

template on the INDOT website.

When advertising is complete, ERC requests Past Performance Data for any

Letters of Interest (LOIs)

received.

District Local Program

Director reviews and advertises

RFP.

Page 14: ERC Recertification Summer 2014

LPA-Consultant Contract LPA Contracting Sequence,

cont’d.ERC

verifies that the

responding firms are

prequalified for the

work types advertised by using INDOT’s

prequalified

consultant list online.

An LPA scoring

team (3-5 individuals) evaluates and ranks

all submitted

RFPs.

LPA scoring team

completes scoring and tabulation and ERC

confirms the DBE goal is being met by the #1

ranking firm by

requesting a DBE Goal Met email

and attaching

the Affirmative

Action Certification form (AAC) submitted

with the LOI.

After receiving ‘DBE Goal Met’ email reply,

ERC completes the Consultant Contract Review Checklist and

submits to District Local Program Director

for approval.

District Local Program Director approves

Consultant Selection Review Checklist and confirms that LPA can begin negotiation with

#1 ranked firm.

Page 15: ERC Recertification Summer 2014

LPA-Consultant Contract LPA Contracting Sequence,

cont’d.After

negotiation of

scope, schedule compens

ation and fees, draft

contract is

prepared using

the boilerpla

te contract found on INDOT’s website.

ERC completes the LPA-

Consultant

Contract Review Checklist on the INDOT

website and

submits all

required documen

tation along with draft

contract to

District Local

Program Director.

District Local

Program Director reviews

LPA-Consulta

nt Contract Review Checklis

t and notifies ERC that

draft contract can be

executed.

After signing

the consulta

nt contract, the ERC maintains a copy

and sends a copy to

the District Local

Program Director.

Page 16: ERC Recertification Summer 2014

Contract Compensation Methods Lump sum Negotiated labor rate Cost Plus Fixed Fee (CPFF) Unit price Cost plus % of cost is prohibited by

Indiana Code and Federal Regulations

LPA-Consultant Contract

Page 17: ERC Recertification Summer 2014

Lump Sum Good method to use when the scope of

work is well-defined and when there is confidence in level of effort required.

Not acceptable for construction inspection.

LPA-Consultant Contract

Page 18: ERC Recertification Summer 2014

EXAMPLE #1:

See handout: “Lump Sum: Appendix D”

LPA-Consultant Contract

Page 19: ERC Recertification Summer 2014

Negotiated Labor Rate Acceptable method to use when the

scope is not well-defined, or when the consultant is not in control of the level of effort.

Typically used for construction inspection.

LPA-Consultant Contract

Page 20: ERC Recertification Summer 2014

EXAMPLE #2:

See handout: “Negotiated Labor Rate: Appendix D”

LPA-Consultant Contract

Page 21: ERC Recertification Summer 2014

Cost Plus Fixed Fee Acceptable method to use when the

scope is well-defined but there is a lower degree of confidence in the level of effort required.

Consultants must have full CPA Audit or Cognizant Audit prequalification financial approval to use this method.

LPA-Consultant Contract

Page 22: ERC Recertification Summer 2014

EXAMPLE #3:

See handout: “Cost + Fixed Fee: Appendix D”

LPA-Consultant Contract

Page 23: ERC Recertification Summer 2014

Unit Price Good method for use with repetitive

well-defined units of work. Typically used for geotechnical and

right-of-way (ROW) services. INDOT approved unit price rates for

ROW services are available on the INDOT website.

LPA-Consultant Contract

Page 24: ERC Recertification Summer 2014

EXAMPLE #4:

See handout:“Unit Price”

LPA-Consultant Contract

Page 25: ERC Recertification Summer 2014

Advice about use of multiple methods Lump sum and hourly compensation

elements should not be mixed in a contract unless the methods would be applied during different defined time periods or when there is no overlap in the staff who will be performing the work elements.

LPA-Consultant Contract

Page 26: ERC Recertification Summer 2014

Consultant Contract Review Checklist Go to: http://www.in.gov/indot/index.htm Click: Doing Business with INDOT Click: LPA & Grants Administration Click: LPA Consultant Selection Under: Forms Select: Consultant Contract Review

Checklist

LPA-Consultant Contract

Page 27: ERC Recertification Summer 2014

EXAMPLE #5:

See handout:“LPA-Consultant Contract Review Checklist”

LPA-Consultant Contract

Page 28: ERC Recertification Summer 2014

EXAMPLE #6:

See handout: “Consultant Prequalification Letter”

LPA-Consultant Contract

Page 29: ERC Recertification Summer 2014

EXAMPLE #7:

See handout:“Consultant Contracts Profit Calculation Worksheet”

LPA-Consultant Contract

Page 30: ERC Recertification Summer 2014

Escalation values for INDOT consultant contracts: Go to:

http://www.in.gov/indot/index.htm Click on: Doing Business with INDOT Highlight: Consultants/Pre-construction Click on: Proposals & Contracts Under: Contract Compensation

Information Select: Employment Cost Index (ECI)

Rates

LPA-Consultant Contract

Page 31: ERC Recertification Summer 2014

EXAMPLE #8:

See handout:“Escalation Values for INDOT Consultant Contracts”

LPA-Consultant Contract

Page 32: ERC Recertification Summer 2014

Real estate fee schedules: Go to:

http://www.in.gov/indot/index.htm Click on: Doing Business with INDOT Highlight: Consultants/Pre-construction Click on: Proposals & Contracts Under Contract Compensation

Information Select: Current Real Estate Fee

Schedules

LPA-Consultant Contract

Page 33: ERC Recertification Summer 2014

EXAMPLE #9:

See handout:“Increase in State Mileage Reimbursement Rate”

LPA-Consultant Contract

Page 34: ERC Recertification Summer 2014

EXAMPLE #10:

See handout:“Match App. D”

Common Errors

Page 35: ERC Recertification Summer 2014

Common ErrorsEXAMPLE #11:

See handout:“Appendix A”

Page 36: ERC Recertification Summer 2014

Common ErrorsEXAMPLE #12:

See handout:“Appendix B”

Page 37: ERC Recertification Summer 2014

Common ErrorsEXAMPLE #13:

See handout:“Appendix C”

Page 38: ERC Recertification Summer 2014

Common ErrorsEXAMPLE #14:

See handout:“Appendix D”

Page 39: ERC Recertification Summer 2014

How does the state negotiate consultant contracts?

If I don’t know anything about negotiating, who can I talk to?

If I include a work type on an RFP that ends up not being used, is that a problem? What if I don’t include one I end up needing?

What are some things I should be aware of in a consultant contract?

LPA-Consultant Contract FAQs

Page 40: ERC Recertification Summer 2014

Federal-Aid Program Contracts KEY TAKEAWAYS:

INDOT-LPA Contract MEETING YOUR SCHEDULE IS IMPORTANT! Attachments A-D- specific to your project

LPA-Consultant Contract Different types of contracts Following the RFP process is important-

audits WILL happen after your project You have the right to negotiate Confused? Ask for help.

Page 41: ERC Recertification Summer 2014

Local Quarterly Report (LQR)

Page 42: ERC Recertification Summer 2014

Local Quarterly Report

https://itap.indot.in.gov

Page 43: ERC Recertification Summer 2014

Local Quarterly Report

Page 44: ERC Recertification Summer 2014

Local Quarterly Report

Page 45: ERC Recertification Summer 2014

Local Quarterly Report

Page 46: ERC Recertification Summer 2014

Local Quarterly Report

Page 47: ERC Recertification Summer 2014

Local Quarterly Report

Page 48: ERC Recertification Summer 2014

Local Quarterly Report

Page 49: ERC Recertification Summer 2014

Local Quarterly Report

Page 50: ERC Recertification Summer 2014

Local Quarterly Report

Page 51: ERC Recertification Summer 2014

Local Quarterly Report

Page 52: ERC Recertification Summer 2014

LQR Main Page

Page 53: ERC Recertification Summer 2014
Page 54: ERC Recertification Summer 2014
Page 55: ERC Recertification Summer 2014

Tab Identification

Page 56: ERC Recertification Summer 2014

General Questions

Page 57: ERC Recertification Summer 2014

Comment Box

Page 58: ERC Recertification Summer 2014

Project Cost and Budget Tab

Page 59: ERC Recertification Summer 2014

Project Schedule Tab

Page 60: ERC Recertification Summer 2014

Permits Tab

Page 61: ERC Recertification Summer 2014

Tab for Post Bid Letting

Page 62: ERC Recertification Summer 2014

Comments Tab

Page 63: ERC Recertification Summer 2014

Document Upload Tab

Page 64: ERC Recertification Summer 2014

Signing & Submitting Report

Page 65: ERC Recertification Summer 2014

Review

Page 66: ERC Recertification Summer 2014

Review

Page 67: ERC Recertification Summer 2014

LQR KEY TAKEAWAYS:

1. LQR is a tool for everyone involved2. The report is only as good as the info

you put into it! (Garbage in, garbage out)

3. Technical support?