EPR Flamanville 3 project
Robert PAYSDeputy Director - EDF Nuclear Engineering Division
© 2011 Electricité de France (EDF). All rights reserved
Project Management (schedule, cost, quality, interfacemanagement, Risk analysis …)Licensing process Definition of general technical codes and specificationsContract allotment and contract managementTechnical specifications and surveillance of main contracts (NSSS, I&C, TG, BNI design, nuclear fuel)In factory manufacturing surveillanceConstruction on site and commissioning test managementPreparation of commissioning test and operation
documentation
EDF Architect Engineer for FA3 project
Architect EngineerLevel 1
Detailed DesignLevel 2
SuppliersLevel 3
SUPPLY CONTRACTS
AREVA NP
ANP
NSSS + I&C BNI
EDF
BOP/BCI
Engineering sub-contractors
-
CALLS FOR BID
SOFINEL
DESIGN CONTRACTS
TG and Auxiliaries
ALSTOM
EDF
55% EDF,45% ANP
EDF Architect Engineer for FA3 construction
Contract management
150 main contracts
The 20 biggest lots represent about 80% of the construction budget
Contracts for equipment supply and erection on site
Competition for all the lots except for NSSS
Quality and Safety management
EDF, as architect Engineer, is in charge to perform the surveillance of suppliers activities to check the quality
Each supplier provides its own quality programme approved by EDF
EDF surveillance is based on surveillance programmes with check and hold points for design, manufacturing and site activities
The Safety Authority (ASN) control is based on Nuclear French regulation for the activities linked to safety. ASN performs inspections in the design offices, factories and on site (2 inspections per month)
Licensing application
• The start-up authorization file has to be sent to the French Safety Authority (ASN) one year before fuel loading at the latest. This file includes the Final Safety Report (FSAR) and the general operation rules (GOR)
• Anticipated issuance of FSAR files to ASN :• to secure the acceptability by ASN
• to anticipate the ASN assessment
• to mitigate the risks of late modifications further to ASN assessment
• Documentation already issued• Accident studies
• Most of the FSAR chapters
Full scope simulatorMCR replica is erected in simulator building on site
Full scope simulator implemented in engineering teams offices and in Flamanville for the operation teams training
Nuclear Steam Supply System - AREVA
NSSS components manufacturing :
Reactor Vessel ready for hydro-test
Vessel head ; welding defects on adapters under reparation
Steam Generators, Main coolant lines, Main coolant pumps : normal progress. Available beginning 2012
CI : ALSTOM
All the main equipmentmanufactured and deliveredon site
HMP barrel
HMP cylinder
LP cylinder
General progress of FA3 (End of September)
Electro mechanical activities
~18% Progress
Civil work activities
~85% progress
Total manpower on site (end of Sept. 2011): 2995
~ 15 million worked hours since the opening of the site
Main steps of Flamanville 3 project
2007
Gridconnection
Electromechanical erection
2008 2009 2010 2011 2012 2013 2015
Decree for authorizationto proceed
Preparatoryworks
Commissioning tests
2014 2016
Civil work
Reactor & fuel BuildingsHR
- Inner containment : 10th level completed- 19.50m slab partially concreted - IRWST wall liner in progress
HK- Pools concreted up to 14,80m- Top edge transfer pool welding in progress- Beginning of piping erection- Southern area below 0.00m: Reactor Boron Tank liner in
progress,
HL1-4HL2-3
Safeguard BuildingsHL1 & HL4
- Level between +21.00 and +24.70 civil construction in progress- Emergency feedwater 1&4 tank liners in progress- Piping and cable trays erection in progress
HL2 & 3- Level between +21.00 and 26.80 civil construction in progress- HV/LV transformers implemented in HL3- Piping and cable trays erection in progress- Beginning of Control Room insulation- Emergency feedwater 2 tank liners in progress
HN
HD1-2
Auxiliary Buildings
Auxiliary nuclear building- Construction of slab +19.50 in progress- Rooms in levels >10,50m available for erection
Diesel building 1-2- Roof concreted – parapets in progress- Secondary structural steelwork in progress below 8.10m- Start of electrical works
Waste treatment building-Building waterproofed- Painting below level 0.00m completed
HQ
Turbine hall Building
- Turbine and generator shaft line : erection in progress- Start of erection of HMP casing, HMP rotor installed at level 16m- Alstom piping and cable trays in progress- Main feedwater pump motors installed
Power Transmission Platform
Step down-transformer zoneEnd of erection tests in progressCable pulling
Substation zoneErection progress: 95% (inside building + roof)LV cable routing in progress
Main transformer zoneTransformers equipped, cooling erection under finalization Bunkers are closedLV cable routing in progress
Erection of HV cap
End of Civil Works – Painting in progressCirculating water pit: end of painting, rail erection in progressUltimate Heat Sink pit: pipes support erection in progressStart of erection of emergency cool down pumps and filters
Pumping Station and discharge structure
• End of Civil Works• 5T crane in operation• Pipes support erection in progress
25t crane in HCB
23 - Présentation_fa3_30091023 - Présentation_fa3_300910
Flamanville 3 : an EPR first of kind for EDF group
Flamanville 3 is a first of kind which has requested :
The development of a complete set of detailed design, manufacturing procedures and construction methods
A learning curve for the suppliers and EDF after a 20 years without nuclear construction
Lessons learnt from Flamanville 3
Some positive pointsThe complete use of 3D mock up in order to manage all the layout interfaces (civil, piping, cabling, ducts,...)The development of a simulator for validation of the process and the operation documentationThe in factory surveillance for the manufacturing activitiesThe involvement of the local companies and the recruitment of local workers
Some points to be improvedLack of experience and competences in the nuclear field (knowledge of codes and standards)Beyond the selection of the suppliers, a need to agree on the subcontracting chainCompletion of basic design and a significant part of detailed design before the beginning of constructionSome construction methods to be improved (liner erection, anchor plates, ...)
A dedicated EPR feedback experience project
EDF has created a dedicated feedback project from Flamanville 3 with the following objectives :
- Analysis of the difficulties encountered during the detailed design, the manufacturing and the construction
- Issue of feedback sheets providing information on situation for FA3 and proposed solutions for the future project
- Modifications assessed to simplify the EPR design and improve the construction methods
A specific EDF feedback organisation : the EPR family
EDF Group is involved, alone or with partners, in 8 EPR projects as a future licensee and as an architect engineer :
France: Flamanville 3 + Penly 3 China: Taishan 1&2 UK: Hinkley Point C 1&2, Sizewell B 1&2
EDF has set up a specific organisation “ EPR family” with all its owner partners in order to facilitate the exchanges between the projects and to set up an organisation enabling each one to benefit from the feedback experience of the other projects
Conclusion
The performance of EPR Flamanville 3 construction should be evaluated as is a First of kind. The updated schedule takes into account this point for the electromechanical erection and commissioning tests
The EDF feedback process from Flamanville 3 is now under operation and good results are already obtained from the feedback experience for the construction of Taishan (China)
All the future projects with Flamanville 3 reference will reduce their risks for delay, cost and quality thanks to this feedback experience