epcor victoria substation e511s breaker addition v1€¦ · epcor victoria substation e511s breaker...
TRANSCRIPT
-
EPCOR Victoria Substation E511S Breaker Addition V1
Project No. 1711 AESO Functional Specification Page 2 of 13
Functional Specification Revision History
Revision Description of Revision By Date
R0B0 • For Comments Henry Ng June 21, 2016
R0B1 • For External Review Henry Ng June 29, 2016
R0 • For Issuance Henry Ng July 13, 2016
V1 • Removed SASR submission
date
• Updated Section 5.3 Henry Ng Nov 14, 2016
-
EPCOR Victoria Substation E511S Breaker Addition V1
Project No. 1711 AESO Functional Specification Page 3 of 13
TABLE OF CONTENTS
1 PURPOSE ......................................................................................... 4 2 INTERPRETATION AND VARIANCES ............................................... 4 4 FORECAST OF FUTURE DEVELOPMENT IN THE PROJECT AREA .......................................................................................................... 5 5 SCOPE OF WORK ........................................................................... 5
5.1 General ........................................................................................................... 5 5.2 Compliance with AESO Authoritative Documents .......................................... 5 5.3 Modeling Data Requirements ......................................................................... 6 5.4 Substation Equipment Specifications ............................................................. 6 5.5 Specific Scope of Work for the Legal Owner of the Transmission Facility ...... 7 5.6 Market Participant Scope of Work .................................................................. 7
6 TRANSMISSION SYSTEM OPERATING CHARACTERISTICS ....... 8 6.1 Short Circuit Current Levels ............................................................................ 8 6.2 Voltage Levels .............................................................................................. 10 6.3 Insulation Levels ........................................................................................... 11
7 APPENDICES ................................................................................. 12 7.1 Existing Transmission System and the proposed project area ..................... 12 7.2 Single Line Diagram Victoria E511S Proposed Development ...................... 13
-
EPCOR Victoria Substation E511S Breaker Addition V1
Project No. 1711 AESO Functional Specification Page 4 of 13
1 PURPOSE (1) The purpose of this document (“Functional Specification”) is to set out the technical specifications and requirements and approved variances issued by the AESO to the legal owner of the transmission facility, EPCOR Distribution & Transmission Inc.(EDTI) TFO, and the market participant, EDTI DFO, related to the design, construction, development and commissioning of certain new or modified facilities (the “Project”) that have been proposed for or are related to a physical facilities connection with the interconnected electric system (the "Purpose"). (2) This Functional Specification is issued for the Purpose only, and the legal owner of the transmission facility and the market participant must comply with the Functional Specification provisions.
(3) The AESO is not responsible for any facilities designed by or for any third party, or installed on a third party’s behalf, to accomplish the connection of the Project facilities.
(4) This Functional Specification includes: (i) certain specific engineering, technical and functional requirements for the Project; (ii) the requirements to comply with ISO rules, including OPPs, reliability standards,
technical standards, and ISO tariff provisions (collectively called the “Authoritative Documents”);
(iii) the electrical system environment in which the connecting facilities must be designed and operated; and
(iv) any approved variances from requirements set out in any applicable AESO Authoritative Documents.
2 INTERPRETATION AND VARIANCES (1) Subject to subsection (2), any revision or variance to any of the Functional Specification provisions by the legal owner of the transmission facility or the market participant is prohibited.
(2) The legal owner of the transmission facility or the market participant may make application, jointly or individually, in writing to the AESO requesting a variance to this Functional Specification, and the AESO may in writing approve of the variance after the AESO has completed an analysis of the implications to the interconnected electric system with respect to the requested variance.
3 PROJECT OVERVIEW The market participant has submitted to the AESO a System Access Service Request (SASR) for a Demand Transmission Service (Rate DTS) increase of 6.08 MW, from 133.92 MW to 140.0 MW, at existing Victoria E511S substation to support the proposed load increase around Victoria Substation. The existing Victoria Substation is located in the Edmonton area, AESO Planning Area 60.
The proposed project developments include:
• Addition of two (2) 15 kV circuit breakers at existing Victoria E511S substation.
The scheduled in-service date (ISD) for this project is March, 2017.
-
EPCOR Victoria Substation E511S Breaker Addition V1
Project No. 1711 AESO Functional Specification Page 5 of 13
4 FORECAST OF FUTURE DEVELOPMENT IN THE PROJECT AREA Refer to the AESO 2015 Long – term Transmission Plan on the AESO’s website (www.aeso.ca) for further information regarding future developments in the Edmonton area.
5 SCOPE OF WORK 5.1 General (1) The legal owner of the transmission facility and the market participant must complete all engineering, design, land or land-use acquisition, siting, public consultation, applicable regulatory approvals and permits, material procurement, construction, commissioning, and associated permitting requirements for the Project facilities.
(2) The legal owner of the transmission facility and the market participant must coordinate with each other as required on all Project facility design details, including protection and control, grounding, insulation, point of connection, site layout with proper consideration of maintenance coordination.
(3) The legal owner of the transmission facility and the market participant must develop joint operating procedures and any connection agreements as required such that all connecting transmission facilities will operate safely and reliably. (4) The legal owner of the transmission facility and the market participant must deliver to the AESO all final design and as-built Project facility information and records in the format and content required by the AESO, to enable the AESO to update and maintain its transmission technical records and system models.
(5) The legal owner of the transmission facility and the market participant must submit the Project information and records referred to in subsection (4) above, under the professional stamp and signature of a registered professional engineer in Alberta who assumes responsibility for the preparation and accuracy of the content of the information and records.
(6) The legal owner of the transmission facility and the market participant must mutually agree on each party’s roles and responsibilities regarding inspection of all facilities of the Project prior to energization of the facilities.
(7) The legal owner of the transmission facility and the market participant must ensure prior to energization of any or all of their respective Project facilities, that the facilities to be energized have been inspected by qualified personnel, so that the facilities are declared to be:
(a) safe for operation; and
(b) in compliance with this Functional Specification, Alberta Reliability Standards and any Authoritative Documents for which the Project must comply.
(8) No Project facilities are to be energized until an energization authorization has been issued by the AESO in accordance with the ISO rules.
5.2 Compliance with AESO Authoritative Documents The legal owner of the transmission facility and the market participant must comply with the Authoritative Documents provisions which are applicable to the Project and which must be incorporated into the design, construction, commissioning and operation of the connecting facilities and other connection Project work, including but not limited to these provisions contained herein:
http://www.aeso.ca/
-
EPCOR Victoria Substation E511S Breaker Addition V1
Project No. 1711 AESO Functional Specification Page 6 of 13
• AESO Operating Policies and Procedures
• Alberta Reliability Standards
• AESO Measurement System Standard Rev. 1 (dated September 18, 2007)1;
• ISO rules including: Section 502.2, Bulk Transmission Line Technical Requirements (effective January 1,
2012);
Section 502.3, Interconnected Electric System Protection Requirements (effective March 27, 2015);
Section 502.4, Automated Dispatch and Messaging System and Voice Communication Systems Requirements (effective March 27, 2015);
Section 502.8, SCADA Technical and Operating Requirements (effective March 27, 2015);
• AESO Generation and Load Interconnection Standard (dated September 19, 2006)1.
5.3 Modeling Data Requirements All modeling data shall be provided as per the Information Document ID# 2010-001R Facility Modelling Data (issued July 26, 2016).
5.4 Substation Equipment Specifications All new substation equipment2 must meet the following minimum specifications:
• Temperature rating of -50ºC for all outdoor equipment. Equipment maximum and minimum continuous voltage ratings as indicated in Table 4.
• Minimum continuous equipment current ratings as indicated in Table 1. • Equipment maximum fault duty: 30 kA for 15 kV, 40 kA for 72 kV and 240 kV.
Table1. Minimum Continuous Equipment Current Ratings (A)
Component Note 5 72 kV
Main Bus Note 1 1200
Cross Bus Note 2, 3 600
Equipment or line terminal Note 4 600 Notes for Table 1: Note 1: Main bus includes all sections of ring bus scheme or single bus of simple bus or breaker and a half
scheme except the portion of the bus connecting to a transformer. Note 2: Cross bus includes diameter sections of breaker and a half or breaker and a third schemes. Note 3: Cross bus can have higher minimum current rating based on bus configuration and equipment
connectivity.
1 The AESO considers this standard to remain in effect notwithstanding the statement in clause 1.5 of this standard. 2 Equipment includes such items as the power transformer, circuit breaker, capacitor bank, shunt reactor, high voltage current transformer, potential transformer, bus work, air break, and switchgear.
-
EPCOR Victoria Substation E511S Breaker Addition V1
Project No. 1711 AESO Functional Specification Page 7 of 13
Note 4: Line terminal includes all equipment and conductor from the transmission line to the line breakers. Note 5: Current rating of the equipment below 69 kV within the substation shall be determined by the legal owner
of the transmission facility, in consultation with market participants.
5.5 Specific Scope of Work for the Legal Owner of the Transmission Facility (1) General Requirements • Coordinate with the market participant to develop necessary connection agreements and
joint operating procedures.
• Ensure Project safety is appropriately managed from design through energization.
• Undertake all required grounding studies, testing and mitigation as required for electrical safety.
• Complete grounding studies, testing and mitigation for electrical effects on communication systems.
• Complete insulation coordination studies and coordinate with the market participant as required to establish appropriate insulation levels.
• All site preparation, fencing, foundations, grounding, support structures, termination structures, duct work, cabling, bus work, station service, control building, protection, controls, etc. as required.
(2) Victoria Substation E511S– See Appendix 7.1 Substation Equipment Install two (2) 15 kV circuit breakers.
Install all other 15 kV equipment as required for the operation and connection purposes.
Coordinate with the market participant to connect three (3) proposed new 15 kV distribution feeders.
Protection and Control Complete system protection coordination studies and coordinate with the market
participant as required to establish settings appropriate for the facility additions and Alberta Interconnected Electric System (AIES) operations.
Install all the required protection and control equipment for the facility additions.
Review and modify the protections as required at remote end substation to accommodate the new equipment additions.
Revenue Metering Provide the description of the measurement point location for the point of delivery/point
of supply, and the acceptable installation for revenue metering in order to report on the measurement point.
5.6 Market Participant Scope of Work (1) General Requirements
• Coordinate with the legal owner of the transmission facility to develop necessary connection agreements and joint operating procedures.
• Coordinate with the legal owner of the transmission facility to connect three (3) proposed new 15 kV distribution feeders.
-
EPCOR Victoria Substation E511S Breaker Addition V1
Project No. 1711 AESO Functional Specification Page 8 of 13
• Undertake all required grounding studies, testing, and mitigation to ensure the connecting distribution facilities are safe.
• Ensure distribution connection safety is appropriately managed from design through energization.
6 TRANSMISSION SYSTEM OPERATING CHARACTERISTICS The legal owner of the transmission facility and the market participant must ensure all facilities are capable of operating in the following electrical environment.
6.1 Short Circuit Current Levels (1) The short circuit current levels set out in Tables 2 to 3 have been developed by the AESO based on information provided by the legal owners of the transmission facility, any connecting generating units, and adjacent operating areas. Available fault current levels will continue to increase as generation, transmission, and system inter-ties are added to the interconnected electric system. The legal owner of the transmission facility and market participant must continue to review the fault levels and their equipment ratings for adequacy.
(2) Any future equipment upgrades or protection system setting changes required due to increasing fault levels are the responsibility of the legal owner of the transmission facility or the market participant, as applicable. (3) The following assumptions were incorporated into the AESO short circuit current models:
(i) All expected Alberta generation is dispatched. (ii) All transmission elements are in service. (iii) The proposed Project facility is connected as per this document. (iv) Vbase = Vbus, MVAbase = 100
Table 2a: Summary of Short-Circuit Current Levels – Year 2017 WP –Pre-Connection
Substation Voltage Voltage Fault Sequence Fault Thevenin Source
Name & Bus number. (kV) (kV) (kA) Thevenin Source (kA) Impedance
Impedance Castle Downs 519 240 247.5 15.5 0.003082 + J0.015254 13.9 0.003286 + J0.020632
Victoria 533 69 72.1 28.6 0.005026 + J0.028809 36.6 0.003056 + J0.009763
Victoria 25337 14.4 14.34 28.2 0.032746 +J0.138279 29.4 0.002684 + J0.127336
Victoria 25338 14.4 14.34 28.2 0.032746 +J0.138279 29.4 0.002684 + J0.127336
North Calder 137 240 248.3 16.8 0.002997 + J0.013976 14.3 0.003787 + J0.021648
Woodcraft 534 69 71.5 11.7 0.021510 + J0.067981 11.1 0.057196 + J0.065679
Kennedale 528 69 72.6 21.9 0.007928 + J0.037452 21.3 0.019202 + J0.037866
Rossdale 507 69 72.3 29.2 0.004728 + J0.028287 39.0 0.000553 + J0.007098
-
EPCOR Victoria Substation E511S Breaker Addition V1
Project No. 1711 AESO Functional Specification Page 9 of 13
Bellamy 506 240 247.1 20.8 0.002527 + J0.011304 18.3 0.002335 + J0.016098
Strathcona 532 69 71.5 7.8 0.014556 + J0.106759 6.3 0.018642 + J0.182337
Argyll Transfer Station 509 240 247.3 20.4 0.002564 + J0.011529 17.7 0.004241 + J0.016695
Argyll Transfer Station 518 240 247.2 21.1 0.002476 + J0.011134 17.8 0.004455 + J0.017278
Note: The AESO acknowledges the short circuit current levels identified in the above table which is approaching or exceed the equipment rating identified in section 5.4. The AESO will work with the market participant to address this prior to this level being reached.
Table 2b: Summary of Short-Circuit Current Levels – Year 2017 WP –Post-Connection
Substation Voltage Voltage Fault Sequence Fault Thevenin Source
Name & Bus (kV) (kV) (kA) Thevenin Source (kA) Impedance
Number Impedance (R0+jX0/PU)
(R1+jX1/PU)
Castle Downs 519 240 247.4 15.5 0.003081 + j0.015252 13.9 0.003286 + j0.020632
Victoria 533 69 72.0 28.6 0.005045 + j0.028768 36.6 0.003056 + j0.009763
Victoria 25337 14.4 14.2 28.4 0.033562 +J0.137203 29.5 0.002684 + J0.127336
Victoria 25338 14.4 14.2 28.4 0.033562 +J0.137203 29.5 0.002684 + J0.127336
North Calder 137 240 248.2 16.8 0.002996 + j0.013975 14.3 0.003787 + j0.021648
Woodcraft 534 69 71.4 11.7 0.021503 + j0.067988 11.1 0.057196 + j0.065679
Kennedale 528 69 72.5 21.9 0.007923 + j0.037456 21.3 0.019202 + j0.037866
Rossdale 507 69 72.2 29.2 0.004746 + j0.028251 39.0 0.000553 + j0.007098
Bellamy 506 240 247.0 20.8 0.002526 + j0.011301 18.3 0.002335 + j0.016098
Strathcona 532 69 71.5 7.8 0.014541 + j0.106771 6.3 0.018642 + j0.182337
Argyll Transfer Station 509 240 247.2 20.4 0.002563 + j0.022526 17.7 0.004241 + j0.016695
Argyll Transfer Station 518 240 247.1 21.1 0.002476 + j0.011132 17.8 0.004455 + j0.017278
Note: The AESO acknowledges the short circuit current levels identified in the above table which is approaching or exceeded the equipment rating identified in section 5.4. The AESO will work with the market participant to address this prior to this level being reached.
-
EPCOR Victoria Substation E511S Breaker Addition V1
Project No. 1711 AESO Functional Specification Page 10 of 13
Table 3: Summary of Short-Circuit Current Levels – Year 2025 WP
Base Pre-fault 3-Φ Positive 1-Φ Zero Sequence
Substation Voltage Voltage Fault Sequence Fault Thevenin Source
Name & Bus (kV) (kV) (kA) Thevenin Source (kA) Impedance
Impedance
Castle Downs 519 240 246.5 17.0 0.002511 + j0.013945 14.8 0.003277 + j0.020118
Victoria 533 69 72.9 29.7 0.004463 + j0.027827 37.8 0.003049 + j0.009733
Victoria 25337 14.4 14.1 28.4 0.033129 +J0.137214 29.5 0.002684 + J0.127336
Victoria 25338 14.4 14.1 28.4 0.033129 +J0.137214 29.5 0.002684 + J0.127336
North Calder 137 240 246.7 18.3 0.002531 + j0.012869 15.1 0.003779 + j0.021143
Woodcraft 534 69 72.1 11.8 0.021164 + j0.067411 11.2 0.057215 + j0.065740
Kennedale 528 69 72.0 25.6 0.006344 + j0.032097 24.2 0.016818 + j0.035061
Rossdale 507 69 73.1 30.3 0.004171 + j0.010319 40.2 0.000565 + j0.007087
Bellamy 506 240 246.3 23.4 0.001988 + j0.010082 19.9 0.002295 + j0.015458
Strathcona 532 69 71.8 7.7 0.014390 + j0.107360 6.3 0.018735 + j0.184075
Argyll Transfer Station 509 240 246.4 22.9 0.002032 + j0.010319 19.2 0.004227 + j0.016068
Argyll Transfer Station 518 240 246.5 23.8 0.001936 + j0.009908 19.3 0.004429 + j0.016630
Note: The AESO acknowledges the short circuit current levels identified in the above table which is approaching or exceeded the equipment rating identified in section 5.4. The AESO will work with the market participant to address this prior to this level being reached.
6.2 Voltage Levels Table 4 provides the steady state voltage range in the area of the proposed facility.
Table 4: Steady State Voltage Range (kV) during Normal and Contingency Events
Substation Name and Number
Nominal (kV) Extreme
Minimum (kV) Normal
Minimum (kV) Normal
Maximum (kV) Extreme
Maximum (kV)
Victoria Substation
E511S
240 216 234 252 264
Victoria Substation
E511S
72 65 68.5 75.5 79
Notes: 1. The Desired Normal Operating Minimum and Desired Normal Operating Maximum are generally associated with
Category A events and system normal. 2. The Emergency Minimum Voltage and Emergency Maximum Voltage are generally associated with Category B
and C events and system abnormal.
-
EPCOR Victoria Substation E511S Breaker Addition V1
Project No. 1711 AESO Functional Specification Page 11 of 13
3. The facilities must be capable of continuous operation at voltages up to and including the Emergency Maximum Voltage.
6.3 Insulation Levels (1) Table 5 provides the required basic insulation levels for the transmission facilities. Station equipment with lower insulation levels may be used provided that protection and coordination can be maintained with judicious insulation design and use of appropriate surge arresting equipment.
(2) For 25 kV circuit breakers where there is a grounded wye transformer and surge arrestors are installed a basic insulation level of 125 kV is acceptable.
Table 5: Basic Insulation Levels (kV)
Nominal Voltage Classification (kV rms) 15 72
Station Post Insulators and Airbreaks 95 350
Circuit Breakers 95 350
Current and Potential Transformers 95 350
Transformer Windings (Protected by Surge Arresters)) - 350
-
EPCOR Victoria Substation E511S Breaker Addition V1
Project No. 1711 AESO Functional Specification Page 12 of 13
7 APPENDICES 7.1 Existing Transmission System and the proposed project area
-
EPCOR Victoria Substation E511S Breaker Addition V1
Project No. 1711 AESO Functional Specification Page 13 of 13
7.2 Single Line Diagram Victoria E511S Proposed Development
Legend
Existing
15kV Bus 3
This SLD is based on information provided by the legal owner of the transmission facility. It is intended to identify the scope of the proposed development only.
Victoria E511S substation 15kV SwitchgearExisting and
Proposed Development
1711-VICTORIA-SLD-01
Note:5raw-out type Circuit .reaker
troposed 5evelopment
15kV Bus 4
15kV Bus 1 15kV Bus 2
V4T3
V21N
V23
V24
V23C1
To T4 15kV windings
To T3 15kV windings
To T3 15kV windings
V3T3VR34
V1T4 V2T4VR12
To T4 15kV windings
To T2 15kV windings
To T1 15kV windings
V3T2V4T1
V1T1 V2T2V22N
V23C2
V23C3
V23C4
V23C5
V25
V31N
V32N
V33
V34
V35
V14C1
V14C2
V14C3
V14C4
V14C5
V11N
V41N
V12N
V42N
V13
V14
V15
V43
V44
V45
V14C7
V14C8
V14C9
V16
V46
V17
V18
V19
V47
V48
V49
V27
V28
V26
V23C6
V23C7
V23C8
V23C9
V29
V36
V37
V38
V39
V14C6
1 PURPOSE2 INTERPRETATION AND VARIANCES4 FORECAST OF FUTURE DEVELOPMENT IN THE PROJECT AREA5 SCOPE OF WORK5.1 General5.2 Compliance with AESO Authoritative Documents5.3 Modeling Data Requirements5.4 Substation Equipment Specifications5.5 Specific Scope of Work for the Legal Owner of the Transmission Facility(1) General Requirements(2) Victoria Substation E511S– See Appendix 7.1 Install two (2) 15 kV circuit breakers. Install all other 15 kV equipment as required for the operation and connection purposes. Provide the description of the measurement point location for the point of delivery/point of supply, and the acceptable installation for revenue metering in order to report on the measurement point.
5.6 Market Participant Scope of Work(1) General Requirements
6 TRANSMISSION SYSTEM OPERATING CHARACTeRISTICS6.1 Short Circuit Current Levels6.2 Voltage Levels6.3 Insulation Levels
7 Appendices7.1 Existing Transmission System and the proposed project area7.2 Single Line Diagram Victoria E511S Proposed Development