Page 1: EP-DRR Quarterly Report Oct-Dec 2013 MA HS KS 1€¦ · 3 AIFDR Project Update GENERAL INFORMATION Reporting Period 1 October – 31 December 2013 Title Enhancing Policy and Planning
Page 2: EP-DRR Quarterly Report Oct-Dec 2013 MA HS KS 1€¦ · 3 AIFDR Project Update GENERAL INFORMATION Reporting Period 1 October – 31 December 2013 Title Enhancing Policy and Planning
Page 3: EP-DRR Quarterly Report Oct-Dec 2013 MA HS KS 1€¦ · 3 AIFDR Project Update GENERAL INFORMATION Reporting Period 1 October – 31 December 2013 Title Enhancing Policy and Planning

  1

 

United  Nations  Development  Programme    

And  

National  Disaster  Management  Agency  

Enhancing  Policy  and  Planning  for  Disaster  Risk  Reduction    

(EP-­‐DRR)  

Quarterly  Progress  Report  

01  October  –  31  December  2013  

Prepared  For  

Department  of  Foreign  Affair  and  Trade  -­‐  The  Government  of  Australia  

Australia-­‐Indonesia  Facility  for  Disaster  Reduction  (AIFDR)  

 

February  2014  

 

Page 4: EP-DRR Quarterly Report Oct-Dec 2013 MA HS KS 1€¦ · 3 AIFDR Project Update GENERAL INFORMATION Reporting Period 1 October – 31 December 2013 Title Enhancing Policy and Planning

  2

Contents

AIFDR PROJECT UPDATE ....................................................................................................... 3  

ACRONYMS ............................................................................................................................ 6  

EXECUTIVE SUMMARY .......................................................................................................... 7  

EVALUATION OF PROGRESS DURING THE REPORTING PERIOD ........................................ 9  

Output 1: Policy guidance developed to support better integration of disaster risk reduction in planning and budgeting  ........................................................................................................................  9  

Output 2: DM Plan improved and DRR fiscal tracking criteria developed  .........................................  12  

CROSS CUTTING ISSUES ...................................................................................................... 14  

Gender Mainstreaming  .......................................................................................................................  14  

Partnerships  ........................................................................................................................................  15  

Lessons Learned  ..................................................................................................................................  15  

CHALLENGES/ISSUES AND RESPONSES ............................................................................ 16  

ANNEXES: ............................................................................................................................. 17  

Annex 1: EP-DRR project components and respective roles of project partners  ..............................  17  

Annex 2: Risk profiles and priority groups  ..........................................................................................  18  

Annex 3: Financial Report  ...................................................................................................................  19  

           

Page 5: EP-DRR Quarterly Report Oct-Dec 2013 MA HS KS 1€¦ · 3 AIFDR Project Update GENERAL INFORMATION Reporting Period 1 October – 31 December 2013 Title Enhancing Policy and Planning

  3

AIFDR Project Update GENERAL INFORMATION Reporting Period 1 October – 31 December 2013 Title Enhancing Policy and Planning for Disaster Risk Reduction (EP-DRR) Person in Charge Malikah Amril, DRR Programme Manager, CPRU-UNDP Indonesia Date of Submission

6 March 2014

PROGRESS REPORT Project Description The project is designed to influence strategic policy guidance on

disaster management, and support the improvement of planning and budgeting for disaster risk reduction. The period for implementation is 23 April 2013 – 30 June 2014 with a budget of AUD 800,000. The project has received all committed funding in December 2013.

Summary of key achievements/results/outcomes to date

EP-DRR support to the National Development Planning Agency (Bappenas) resulted in the submission of a draft background study on disaster management. The study, which received input from government and non-government actors, will inform the preparation of the technocratic draft of the next National Mid-term Development (RPJMN) 2015-2019. Disaster management issues and priorities will likely be taken up in different sections of the RPJMN. EP-DRR is supporting BNPB in the formulation of the next National Disaster Management Plan (Renas PB). In this quarter, a framework for the Disaster Risk Reduction Action Plan, a subsidiary to the Renas PB, was drafted. This, along with the other sections of the Renas PB, will guide and help monitor the next five years of programmatic work in disaster management undertaken by government and non-government actors. Initiatives to incorporate climate change issues in the next five-year disaster management plan (Renas PB) and in the provincial risk assessment methodology of the National Disaster Management Agency (BNPB) kicked off this quarter. Experts have been engaged to provide recommendations for the improvement of methodological practices and programmatic planning, helping to create better linkages between the climate change and disaster management fields.

What have been the key outputs of the project and how are they being used?

In this quarter, the following outputs were produced: Bappenas:

1. Draft recommendations on improving existing provincial spatial planning guidelines with disaster risk reduction considerations were formally submitted to the BKPRN. A carefully selected candidate will formulate the technical paper required for presentation to the Ministry of Public Works.

2. A draft of the background study for the inclusion of disaster management in the RPJMN 2015-2019 has been produced. A second round of consultations was undertaken with in mid-December with 12 directorates of Bappenas, 15 line ministries and government agencies, three academic institutions, DRR forms and international agencies. Feedback

Page 6: EP-DRR Quarterly Report Oct-Dec 2013 MA HS KS 1€¦ · 3 AIFDR Project Update GENERAL INFORMATION Reporting Period 1 October – 31 December 2013 Title Enhancing Policy and Planning

  4

and inputs are being incorporated and a final draft will be available in the next quarter

3. A methodology for undertaking the study on fiscal tracking of DRR has been drafted in discussion with Bappenas. The consultant has been recruited and will be on board in January.

MoHA:

1. Draft conceptual framework of policy guideline for DRR planning and budgeting prepared through technical consultation with Ditjen PUM and Ditjen Bangda.

BNPB:

1. Consultant recruited to undertake the analysis of risk assessment methodology with climate related factors. Initial discussions have taken place with between the climate expert and BNPB on risk assessment methodology. A workplan is in place.

2. Analysis for the inclusion of CCA in DM Plan was initiated with the collection of data and through an FGD conducted with non-governmental development partners.

3. A draft programmatic framework for the NAP DRR has been prepared.

4. Consultant recruited to develop the monitoring, reporting and evaluation of DM Plan. Work plan prepared in coordination with BNPB.

What is the current situation: Progress towards sustained outcomes?

Progress against planned outputs has been slower than expected. Similarly to the previous quarter, government ministries focused on the delivery of their own work plans and budgets as 2013 came to a close. In addition, the policy and planning inputs provided by the EP-DRR need to be adjust to the government pace. Nonetheless, the EP-DRR team has stepped up efforts to initiate consultations and lay the ground work for the implementation of activities.

Future Outputs/Deliverables Bappenas: 1. Preparation of technical paper for proposing revision of the

guideline on provincial spatial plan to Public Works. 2. Background study for inclusion of disaster management into

RPJMN 2015-2019 is finalized. 3. Data on local government budgeting collected from MoHA

and MoF and analyzed to develop the criteria and indicators for tracking fiscal allocation for DRR.

MoHA: 1. Consultation with other line ministries undertaken to gain

feedback on the conceptual framework and strategy of local DRR planning and budgeting.

2. Applicability of the concept tested in the provinces of Yogyakarta and Southeast Sulawesi, and one district under each respective province.

BNPB: 1. Academic paper and recommendations for inclusion of CCA

in the Renas PB prepared. 2. NAP DRR programme matrix elaborated through

consultation with government and non-government partners.

3. Data on government key performance indicators and best practices in the area of monitoring collected to help define the monitoring and evaluation framework of Renas PB.

4. Agreement on approach and methodology for improved

Page 7: EP-DRR Quarterly Report Oct-Dec 2013 MA HS KS 1€¦ · 3 AIFDR Project Update GENERAL INFORMATION Reporting Period 1 October – 31 December 2013 Title Enhancing Policy and Planning

  5

provincial disaster risk assessment. Gaps/Issues/Lessons learned The key lessons learned in this quarter are as follows:

1. Engagement of very senior officials in line ministries is critical to obtaining ownership and accelerating implementation.

2. Identifying relevant government priorities and interests when designing development initiatives and formulating government planning documents is advantageous for securing ownership and commitment.

3. In the future, BNPB may want to consider putting in place a senior level task force or advisory group that engages high-level officials and possibly ministerial levels in the formulation of the Renas PB.

Project Expenditure In agreement with AIFDR, the fund commitment was reduced in December from AUD 1,000,000 to AUD 800,000 due to internal changes within AIFDR and DFAT. Project expenditure in this period: Please see Annex 1 for more details.

Page 8: EP-DRR Quarterly Report Oct-Dec 2013 MA HS KS 1€¦ · 3 AIFDR Project Update GENERAL INFORMATION Reporting Period 1 October – 31 December 2013 Title Enhancing Policy and Planning

  6

Acronyms AIFDR Australia-Indonesia Facility for Disaster Reduction APBN Anggaran Pendapatan Belanja Negara (State Budget) Bappenas Badan Perencanaan Pembangunan Nasional (National Development Planning Agency) BIG Badan Informasi Geospatial (Geospatial Information Agency) BKPRN Badan Koordinasi Penataan Ruang Nasional (National Spatial Planning Coordinating Board) BNPB Badan Nasional Penanggulangan Bencana (National Disaster Management Agency) CCA Climate change adaptation CCROM Center for Climate Change Risk and Opportunity Management CDSP Capacity Development Support Programme DFAT Department of Foreign Affairs and Trade (Australian Government) Ditjen PUM Direktorat Jenderal Pemerintahan Umum (Directorate General for Public Administration) DNPI Dewan Nasional Perubahan Iklim (National Council on Climate Change) DRR Disaster risk reduction EP-DRR Enhancing Policy and Planning for Disaster Risk Reduction GoI Government of Indonesia HFA Hyogo Framework for Action IP Implementing Partner IPB Institut Pertanian Bogor (Bogor Institute of Agriculture) Jabodetabekpunjur Jakarta-Bogor-Depok-Tangerang-Puncuk-Ciajnjur Kemendagri Kementerian Dalam Negeri (Ministry of Home Affairs) Kemenkeu Kementerian Keuangan (Ministry of Finance) KemenPPPA Kementrian Pemberdayaan Perempuan and Perlindungan Anak (Ministry of Women’s

Empowerment and Child Protection) KemPU Kementerian Pekerjaan Umum (Ministry of Public Works) KSN Kawasan Strategis Nasional (National Strategic Area) NAP-DRR National Action Plan for Disaster Risk Reduction NAR National Assessment Result Permendagri Peraturan Menteri Dalam Negeri (Ministry of Home Affairs Regulation) RAN-API Rencana Aksi Nasional Adaptasi Perubahan Iklim (National Action Plan for Climate Change

Adaptation) RAN-PRB Rencana Aksi Nasional Pengurangan Risiko Bencana (National Action Plan for

Disaster Risk Reduction) Renas PB Rencana Nasional Penanggulangan Bencana (National Disaster Management Plan) Renstra-KL Rencana Strategis Kementerian Lembaga (Strategic Plan of Line Ministries) RDTR Rencana Detail Tata Ruang (Detailed Spatial Plan) RKP Rencana Kerja Pemerintah (Annual Government Work Plan) RPKD Rencana Kerja Pemerintah Daerah (Regional Government Annual Work Plan) RP Responsible party RPJMD Rencana Pembangunan Jangka Menengah Daerah (Regional Mid-term Development Plan) RPJMN Rencana Pembangunan Jangka Menengah (National Mid-term Development Plan) RPJPN Rencana Pembangunan Jangka Panjang Nasiona (National Long-term Development Plan) RTR Rencana Tata Ruang (Spatial Plan) RTRW Rencana Tata Ruang Wilayah (Regional Spatial Plan) SC-DRR Safer Communities through Disaster Risk Reduction in Development SPPN Sistem Perencanaan Pembangunan Nasional (National Development Planning System) TRP Tata Ruang dan Pertanahan (Spatial Planning and Land Affairs) UNDP United Nations Development Programme UNWOMEN United Nations Entity for Gender Equality and the Empowerment of Women  

 

Page 9: EP-DRR Quarterly Report Oct-Dec 2013 MA HS KS 1€¦ · 3 AIFDR Project Update GENERAL INFORMATION Reporting Period 1 October – 31 December 2013 Title Enhancing Policy and Planning

  7

Executive Summary In fourth quarter 2013, a background study was drafted to inform the integration of disaster management into the National Mid-term Development Plan/Rencana Pembangunan Jangka Menengah (RPJMN) 2015-2109. The study analyzed and identified opportunities and strategic issues to be address in the next RPJMN. The comprehensive analysis has brought to light important considerations for Bappenas to take into account in formulating the RPJMN. This is a critical for securing a place for disaster management in the development plans and priorities of the next regime. EP-DRR continued to provide technical assistance to BNPB that are helping to advance their efforts in formulating the 2015-2019 Disaster Management Plan (Renas PB). Specifically, climate experts are collaborating with BNPB to develop an analysis for integrating climate change adaptation (CCA) programmes into Renas PB. Valuable inputs have been gained from stakeholders working on CCA, which will inform the formulation of policy documents necessary to integrate CCA in the Renas PB. A programme matrix for the National Action Plan (NAP) on DRR was drafted in this quarter and consulted with non-government partners. Preparations are also underway to develop a monitoring, reporting and evaluation framework for the Renas PB. Both the action plan and monitoring framework are critical sections of the Renas PB. EP-DRR support is contributing to inclusive engagement of non-government partners on the NAP DRR and better results-oriented planning. Despite some delays in the early implementation period, overall EP-DRR is on the right track and anticipates an accelerated implementation in the coming quarter. During the last quarter of 2013, government-funded activities took precedence over jointly implemented activities under EP-DRR. Nevertheless, the drafting of both the RPJMN and Renas PB 2015-2019 are key priorities of the government. EP-DRR support in these areas remains critical and propitious.

Page 10: EP-DRR Quarterly Report Oct-Dec 2013 MA HS KS 1€¦ · 3 AIFDR Project Update GENERAL INFORMATION Reporting Period 1 October – 31 December 2013 Title Enhancing Policy and Planning

  8

Situational Background The Enhancing Policy and Planning for Disaster Risk Reduction (EP-DRR) is part of the second phase of the Safer Communities through Disaster Risk Reduction (SC-DRR) project. EP-DRR focuses on supporting the national government with inputs and assistance in the formulation of a number of policies and planning documents relevant to disaster risk reduction and disaster management. EP-DRR is structured under two main outputs: policy guidance, and planning and coordination support (See Annex 1). EP-DRR is responding to imminent policy needs, such as the preparation of the next National Mid-term Development Plan (Rencana Pembangunan Jangka Menengah/RPJMN) and the National Disaster Management Plan (Rencana Nasional Penanggulangan Bencana/Renas PB). These two planning documents serve as important entry points for influencing and shaping Indonesia’s development agenda. The RPJMN forms the basis for ministries and government agencies to formulate respective sectoral plans over a five-year period. EP-DRR is providing technical assistance to the National Development Planning Agency (Badan Perencanaan Pembangunan Nasional/Bappenas) to help set forth a continued prioritization of disaster management in the next RPJMN. The Renas PB, which will cover same period as the RPJMN, will set out strategies and priorities for disaster management and disaster risk reduction to guide both governmental and non-governmental agencies in disaster management. Support is provided through EP-DRR to the National Disaster Management Agency (Badan Nasional Penanggulangan Bencana/BNPB) to prepare sections of the plan, including the disaster risk reduction (DRR) Action Plan, and incorporating a climate perspective. In addition, input and recommendations will be given to improve the consideration of future climate-related factors in the existing provincial risk assessment methodology. EP-DRR also intends to influence current practices in critical development sectors. Spatial planning is a critical area through which to promote the adoption of disaster risk reduction as a means to induce transformative change. To promote disaster risk reduction considerations, EP-DRR is working with the National Spatial Planning Coordinating Board to provide recommendations on how to improve the existing guideline for provincial spatial planning. In parallel, EP-DRR is encouraging the improvement of investments for risk reduction. This is being done through the provision of technical and financial support to the Ministry of Home Affairs (Kemendagri) to draft a national guideline on subnational DRR planning and budgeting. EP-DRR is working with Bappenas to set up indicators and criteria to track annual work plans and budget allocations of relevant line ministries for disaster risk reduction.

Page 11: EP-DRR Quarterly Report Oct-Dec 2013 MA HS KS 1€¦ · 3 AIFDR Project Update GENERAL INFORMATION Reporting Period 1 October – 31 December 2013 Title Enhancing Policy and Planning

  9

Evaluation of Progress during the Reporting Period

Output 1: Policy guidance developed to support better integration of disaster risk reduction in planning and budgeting

Key achievements: Draft recommendations formally submitted to the BKPRN on improving existing

provincial spatial planning guidelines with disaster risk reduction considerations. Technical discussions undertaken to discuss methodological and data requirements

to integrate climate factors in provincial risk assessment methodology. Conceptual framework for DRR planning and budgeting has been prepared and

discussed with the Ministry of Home Affairs. A draft of the background study for the inclusion of disaster management in the

RPJMN 2015-2019 has been produced and shared with Bappenas.

Spatial Planning As reported in the third quarter, recommendations for the improvement of the existing guideline on provincial spatial planning have been drafted and shared with Bappenas. A final report containing recommendations for spatial planning and the Jakarta-Bogor-Depok-Tangerang-Puncuk-Cianjur (Jabodetabekpunjur) case study was submitted formally to Bappenas’ Directorate for Spatial Planning and Land Affairs (TRP), as the secretariat of BKPRN. Bappenas identified the need to present the recommendations in the form of a technical paper for the Ministry of Public Works as the chair of BKPRN. EP-DRR will assign an expert to develop this technical paper under the guidance of the Directorate TRP, Bappenas. Individual experts with the specific skills required have been identified and approached in advance by Bappenas in December. Directorate TRP will make the final selection decision in January 2014. Risk assessment methodology Activities to improve BNPB’s provincial risk assessment methodology with climate change parameters kicked off this quarter. In December 2013, initial meetings were convened between the climate change risk expert from the Centre for Climate Change Risk and Opportunity Management in Southeast Asia Pacific (CCROM-SEAP) in Bogor and the technical team from BNPB. Methodological issues and risk assessment practices were discussed. From the discussion, it was decided that an additional consultant from CCROM-SEAP would be recruited to provide support at a technical level.

Entering into the last quarter of 2013, a number of strategic priorities, including the formulation of the disaster management plan, have kept BNPB occupied. Further technical work on the risk assessment methodology and in depth consultation will take place in the first quarter of 2014.

Page 12: EP-DRR Quarterly Report Oct-Dec 2013 MA HS KS 1€¦ · 3 AIFDR Project Update GENERAL INFORMATION Reporting Period 1 October – 31 December 2013 Title Enhancing Policy and Planning

  10

DRR planning & budgeting sub-national level In this quarter, the EP-DRR policy analyst drafted the conceptual framework for the DRR planning and budgeting guideline. The framework has been prepared on the basis of an analysis of relevant policies and consultation with technical staff from the Directorate Generals of Public Administration (Ditjen PUM) and Local Development Administration (Ditjen Bangda), Ministry of Home Affairs. The guideline will encompass mechanisms for integrating DRR into Regional Government Work Plans (RKPD), local disaster management plans, and Mid-term Development Plans. In January the conceptual framework will be shared with other relevant line ministries to solicit their input. The next step is to test the applicability of the concept within current budget planning practices of local government. The provinces of Yogyakarta and Southeast Sulawesi, and one district under each respective province, have been selected for this exercise. RPJMN In the fourth quarter a preliminary draft background study on disaster management was completed. The study aims to inform the inclusion of disaster management in the next RPJMN. Strategic issues for consideration over the next five years have been identified based on an analysis of the current disaster management context1 and the identification of challenges in the field. The strategic issues, which cover the three phases of the disaster management cycle (pre-disaster, emergency and post-disaster), can be summarized as follows:

1. Legal framework: linkage of planning documents (Renas PB, RPJMN, etc); authority and coordination for national response & recovery framework, and; agreed tools/methods risk assessment, etc.

2. Institutional capacity: personnel, technical capacity, operational funding, clarity of roles and responsibilities

3. Planning and budgeting: funding gaps, risk transfer mechanisms, financial contributions from local governments, monitoring and evaluation

The strategic issues were presented in a workshop organized in December. Participants included 12 Directorates of Bappenas, 15 line ministries and government agencies, three academic institutions, international development partners and DRR forums. Several recommendations were made, namely: 1) integrate disaster risk reduction, climate change adaptation and poverty reduction; 2) put in place a clear monitoring and evaluation framework; 3) standardize risk mapping and strengthen the sharing of information among BNPB, BIG, BPPT and Kemenristek, and; 4) promote the participation of academic institutions and non-governmental organizations in local government planning and budgeting.

                                                                                                                         1 The contextual analysis looks at the accomplishments under the 2010-2014 RPJMN (including progress against ten main indicators), the National Long-term Development Plan (Rencana Pembangunan Jangka Panjang Nasional/RPJPN) 2005-2025, progress in achieving priorities under the Hyogo Framework for Action (HFA), cross-sectoral linkages, and regional disaster profiles.

Page 13: EP-DRR Quarterly Report Oct-Dec 2013 MA HS KS 1€¦ · 3 AIFDR Project Update GENERAL INFORMATION Reporting Period 1 October – 31 December 2013 Title Enhancing Policy and Planning

  11

The background study also recommends better cross-sectoral coordination and the need to apply minimum standards in the area of disaster management. Geographical prioritization is also suggested. The provinces of West Sumatra, Bengkulu, West Java, Central Java, Yogyakarta, East Java and South Sulawesi are exposed to the most to natural hazards (See Annex). Given current trends in development and economic growth, urban areas are likely to experience more disasters in the coming years. Rural areas, especially those in Eastern Indonesia, are still underdeveloped and have higher percentages of vulnerable, poor people. Disaster management is intrinsically linked to broader programmes of poverty reduction, green economy, climate change, small island management, and child protection. The background study is to be used by Bappenas as a reference in consultations with other ministries and in formulating the technocratic draft of RPJMN 2015-2019. Bappenas plans to present the background study to the Vice Minister in charge of the Deputy for Regional Planning and Local Autonomy where this work is anchored. Table 1. Progress achieved against milestones and targets Output 1 Output Indicator

Annual Milestone (2013) Output Target (by end of EP-DRR)

Number/type of policy recommendations produced

Planned Recommendations for revision of existing guideline on provincial spatial planning produced

Recommendations for improved risk assessment methodology that integrates climate related factors produced

3 policy recommendations produced on spatial planning, risk assessment and DM inclusion in RPJMN

1 draft policy on local planning and budgeting

Progress to date

Input and recommendations for improvement of provincial spatial planning guideline produced and submitted to BKPRN. Technical paper to be produced.

Draft background study and analysis for inclusion of disaster management into RPJMN 2015-2019 available and proposed to Bappenas

Number/type of stakeholders involved in formulation

Planned Discussions between BNPB and BKPRN initiated

Ministry of Environment consulted in producing recommendations for improved risk assessment methodology

MoHA consults regional governments on guideline for planning and budgeting

Inter-ministerial and agency discussions held to gather inputs on DM inclusion into RPJMN

At least 5 line ministries involved in formulation of policy recommendations

Progress to date

Discussions between BNPB and BKPRN, undertaken throughout 2013

Second round consultaltation with key line ministries and development partners to solicit feedback and input

So far, 28 government ministries/agencies have been engaged/consulted. Spatial planning: KemenSDM, KLH,

Page 14: EP-DRR Quarterly Report Oct-Dec 2013 MA HS KS 1€¦ · 3 AIFDR Project Update GENERAL INFORMATION Reporting Period 1 October – 31 December 2013 Title Enhancing Policy and Planning

  12

on strategic issuses for DM inclusion in RPJMN.

KKP, KemHan, Kemendagri, BNPB, BIG, BPPT, BPN, KemPU, Bappenas, LAPAN, KemenHub, Kemenko EKON, Kemenperin, LIPI, BPBDs of DKI & Banten, KemenHut, & Cabinet Secretary (sub-total of 20)

DM inclusion RPJMN: BNPB, Kem PU, KKP, Bappenas, Kemsos, Kemkes, Menkokesra, KPDT, Basarnas, LAPAN, Kemdikbud, BMKG, Kemendagri, BPPT, KemenSesneg, LIPI (sub-total of 16) Non-governmental agencies engaged/consulted: 6 universities, AIFDR, UN Agencies, LPBI-NU, Planas PB

Extent to which recommendations are accepted and followed up

Planned N/A BNPB adopts at least 1 policy recommendation

Inputs provided by the project are used by Bappenas in the RPJMN planning process

Progress to date

BKPRN is now considering engaging BNPB in a thematic working group, which gives BNPB an opportunity to mainstream a risk perspective in spatial planning.

BKPRN accepted recommendations on spatial planning, which will be followed up with a technical paper to be presented to KemenPU

Output 2: DM Plan improved and DRR fiscal tracking criteria developed

Key achievements: Consultants for inclusion CCA into DRR in Renas PB recruited and are undertaking

an analysis of relevant policies and data initiated. Programme matrix for the DRR Action Plan is drafted and consulted with non-

government partners. Collection of data from strategic government plans, key performance indicators,

and information on government roles and functions underway to be used in developing the monitoring, reporting and evaluation framework of the Renas PB.

DM Plan & DRR Action Plan EP-DRR continued to provide technical assistance to BNPB in preparing the National Disaster Management Plan (Rencana Nasional Penanggulangan Bencana/Renas PB) 2015-2019. EP-DRR is supporting four areas: 1) a study and analysis of climate change adaptation (CCA) related programmes for the inclusion in the plan; 2) formulation of the

Page 15: EP-DRR Quarterly Report Oct-Dec 2013 MA HS KS 1€¦ · 3 AIFDR Project Update GENERAL INFORMATION Reporting Period 1 October – 31 December 2013 Title Enhancing Policy and Planning

  13

National Action Plan (NAP) DRR (Chapter 6 & Annex C of the plan), and; 3 monitoring, reporting and evaluation framework (Chapter 8). Since October, a team of two experts has begun the CCA analysis. The team has reviewed papers prepared by universities on 12 prevalent hazards and other relevant documents, such as the National Action Plan for CCA (RAN API) and disaster risk maps. A focus group discussion was conducted on 19 December with climate stakeholders from government agencies (Bappenas, BMKG, BNPB, DNPI, Menkokesra, KKP), international organizations (IMACS/IFACS – USAID, GIZ, Wetlands International, Mercy Corps), national NGOs and forums (Planas PB). Inputs and recommendations were provided on CCA programming and the linkages with DRR, particularly regarding the impacts of climate-related hazards on sectoral development and community vulnerability. A final document outlining key recommendations will be available in the first quarter of 2014. In this quarter, a preliminary draft NAP DRR programming matrix was produced. On the 10th of December a public consultation with non-governmental partners was organized by BNPB to disseminate the matrix. This exercise is essential for integrating a non-government perspective into the NAP DRR and for building synergy with government plans. Partners were requested to provide relevant information on their DRR initiatives in the matrix as a follow up to the consultation. Thus far, only five organizations have provided inputs. More discussions and consultations will be organized in the next quarter to ensure non-governmental contributions. Ideally the NAP DRR, as a subsidiary planning document, is formulated after a draft of the main Renas PB document is available. However, discussions on the framework and substance of the Renas PB are still ongoing. BNPB has set March as the deadline for the completion of the entire Renas PB document. Consequently, all the other sections of the document are being written in parallel, rather than being carried out in series. An iterative approach is being applied to develop the NAP DRR, with regular discussions and analysis of the draft. EP-DRR also coordinated closely with the BNPB team in charge of the Renas PB and other consultants assigned to support the formulation process. Similar to the NAP DRR, the preparation of a monitoring, reporting and evaluation framework for the Renas PB is dependent on a clear framework in the main document. Nonetheless, work was initiated in November 2013 with the collection of data from strategic government plans, key performance indicators, and information on roles and functions (Tupoksi) from line ministries and government agencies. By seeking alignment with the National Development Planning System (Sistem Perencanaan Pembangunan Nasional/SPPN), it is expected that this Renas PB will have a more comprehensive monitoring framework than the previous plan. This will enable the GoI to review and evaluate the progress of implementing the plan and the contributions to the RPJMN targets. Consultation with selected sub-national government (DI Yogyakarta and West Sumatera) will be organized in the next quarter. DRR fiscal tracking EP-DRR is supporting Bappenas to conduct a study and analysis of the current practices of the national government in allocating resources for DRR. In this quarter the recruitment

Page 16: EP-DRR Quarterly Report Oct-Dec 2013 MA HS KS 1€¦ · 3 AIFDR Project Update GENERAL INFORMATION Reporting Period 1 October – 31 December 2013 Title Enhancing Policy and Planning

  14

process was completed, and the consultant team will be on board in the first quarter of 2014 – later than originally planned. To accelerate the process, the EP-DRR policy analyst assigned to Bappenas has conducted initiate discussions, prepared a detailed work plan and identifying data collection needs. However, given the reduction in EP-DRR funding, some minor adjustments will be required. Data collection in selected provinces will not take place, rather criteria to track fiscal allocations will be developed on the basis of secondary data from the Ministries of Home Affair and Finance. Table 2. Progress achieved against milestones and targets Output 2 Output Indicator

Annual Milestone (2013) Output Target (by end of EP-DRR)

Number of sections/chapters of DM Plan produced and approved

Planned Analysis and recommendations for the inclusion of CCA in DM Plan 2015-2019 produced

3 draft sections/chapters of DM plan prepared: - Chapter 6: Executive Summary of

NAP DRR Action Plan - Chapter 8: Monitoring, Evaluation

and Reporting - Annex C: Detailed NAP DRR

3 sections/chapters drafted and endorsed to be included in DM Plan 2015-2019

Progress to date

Study to prepare academic paper for inclusion of CCA into DM Plan is ongoing and consultation with CCA stakeholders organized

Analysis and data collection has been started for developing Monitoring, evaluation and reporting of Renas PB

Initial consultation with non-government partners for matrix of NAP DRR facilitated

N/A

Extent to which recommended criteria/indicators for fiscal monitoring are accepted and followed up

Planned Data collection undertaken by consultants

Recommended criteria/indicators for fiscal tracking are submitted by Bappenas to Kemenkeu

Progress to date

Consultant recruited, workplan prepared and target areas for data collection selected.

N/A

Cross Cutting Issues Gender Mainstreaming The Ministry for Women’s Empowerment and Child Protection and UN Women were invited by BNPB to public consultations on the Renas PB. However, their presence at these consultations has been limited. Although it may be beyond the scope of EP-DRR, future initiatives may need to invest in building better collaboration between BNPB and entities like the Women’s Empowerment Ministry.

Page 17: EP-DRR Quarterly Report Oct-Dec 2013 MA HS KS 1€¦ · 3 AIFDR Project Update GENERAL INFORMATION Reporting Period 1 October – 31 December 2013 Title Enhancing Policy and Planning

  15

Work on integrating CCA into the Renas PB has included data collection and analysis on adaptive capacities of vulnerable groups, such as women, children, difable, and elderly. This is significant for identifying specific programmes and monitoring indicators within the plan. Partnerships EP-DRR continues its support to maintain, foster partnership and improve coordination on disaster-risk sensitive spatial planning. This has indicated promising progress with eagerness of the Directorate TRP under Bappenas to proceed with the formulation of a technical paper to be presented to the Ministry of Public Works. This line ministry is the chair of BKPRN and owner of the national guideline on spatial planning. With EP-DRR support, disaster management experts from BNPB are engaging with climate experts from CCROM. Collaboration across disciplinary perspectives should contribute to the identification of mutually shared concepts in the area of climate and disaster risk management. EP-DRR will also engage the Ministry of Environment in discussions on this topic. Although just an initial step in a long-term agenda, it is anticipated that discussions on policies, methodologies and practices will bring decision-makers closer together in their efforts to reduce the risks of climate-induced disasters. Coordination between EP-DRR and CDSP (Capacity Development Support Programme), AIFDR direct support of technical assistance to BNPB, started with identification of common areas of intervention and results. A matrix of convergence for synergy of EP-DRR and CDSP was produced (see Annex 4) to guide respective teams in enhancing the partnership among them. Lessons Learned  Some line ministries have a top-down management structure, under which the authority and direction of high-level officials is strongly respected. The engagement of very senior officials, especially when working with line ministries that possess strict hierarchies like MoHA, is strategic to gaining full commitment to implement activities and deliver expected results. The nature of each ministry should shape the approach taken on by development initiatives. Within this reporting period, EP-DRR had to undergo an adjustment of resources. The fund had to be reduced down to 80 percent of its original budget. The targets have been kept, but the intensity and scope of some activities had to be consequently reduced. In this circumscribed context, it is essential to gain the commitment from responsible ministries (BNPB, Bappenas and MoHA) so that project results can be taken to the next level, especially in gaining official endorsement of improved policies.

Page 18: EP-DRR Quarterly Report Oct-Dec 2013 MA HS KS 1€¦ · 3 AIFDR Project Update GENERAL INFORMATION Reporting Period 1 October – 31 December 2013 Title Enhancing Policy and Planning

  16

Currently, the Directorate for Disaster Risk Reduction under BNPB’s Deputy for Prevention and Preparedness has been tasked to lead the formulation of the Renas PB. With support from development partners including EP-DRR, AIFDR and local NGOs, the Directorate is doing what it can to incorporate a holistic approach within the plan. However, the jurisdiction of the Directorate is limited. In the future, BNPB may want to consider putting in place a senior level task force or advisory group that engages high-level officials and possibly ministerial levels. This would allow for more intensive consultative relationships among deputies and help make the Renas PB more influential at a senior level. Challenges/Issues and Responses As explained in the previous report, EP-DRR faced initial challenges in commencing work on DRR planning and budgeting with MoHA. Since this challenge emerged, the policy analyst has been analyzing relevant policy documents, consulting with MoHA staff and experts, and has initiated the drafting of the guideline. Consultants hired to draft the NAP DRR and Renas PB monitoring framework will likely face delays in completing their work. The NAP DRR and monitoring framework need to make reference to the main sections of the Renas PB, which has not been completed. To anticipate this challenge, EP-DRR in consultation with BNPB, is taking an iterative approach to produce the results. The reduced funding commitment has affected the implementation and scope of planned activities. The scope in terms of deliverables and outputs could not be adjusted due to commitments made to implementing and responsible parties. It should be noted that at the time the budget cut was announced, contracts had already been issued for the majority of the consultants and staff, making it unfeasible for EP-DRR to reduce human resources. Planned consultations with sub-national governments will be taking place at a limited scale. Ultimately, the results may not reach the maturity expected. An internal mid-term review of EP-DRR commenced this quarter. The review, focusing on examining effectiveness and efficiency, will provide recommendations to improve the implementation of EP-DRR. An initial draft has been produced. Due to the schedules of government partners the draft could not be shared with the project board to obtain feedback and input in this quarter. Overall, the review found EP-DRR to be relevant with current government needs and priorities, but noted that targets were ambitious considering the time and resources available. The final report will be completed following consultation with the project board and stakeholders in first quarter of 2014.

Page 19: EP-DRR Quarterly Report Oct-Dec 2013 MA HS KS 1€¦ · 3 AIFDR Project Update GENERAL INFORMATION Reporting Period 1 October – 31 December 2013 Title Enhancing Policy and Planning

  17

Annexes:

Annex 1: EP-DRR project components and respective roles of project partners

Output/Activity BNPB MoHA Bappenas Output 1: Policy guidance

Activity 1.1 Spatial planning ✓

Activity 1.2 Risk assessment methodology ✓

Activity 1.3 DRR planning & budgeting sub-national level

Activity 1.4 Input for RPJMN ✓

Output 2: Planning & Coordination Activity 2.1 DM Plan ✓

Activity 2.2 DRR Action Plan ✓

Activity 2.3 Monitoring, Evaluation and Reporting on DM Plan

Activity 2.4 DRR fiscal tracking ✓ *  Note:  The  activities  above  have  been  generalized  to  reflect  the  main  area  of  intervention  and  are  not  the  activity  statements  as  reflected  in  the  RRF.    

   

Page 20: EP-DRR Quarterly Report Oct-Dec 2013 MA HS KS 1€¦ · 3 AIFDR Project Update GENERAL INFORMATION Reporting Period 1 October – 31 December 2013 Title Enhancing Policy and Planning

  18

 

Annex 2: Risk profiles and priority groups No Priority Group 1 :

Provinces with high risk profiles (all hazards)

Priority Group 2: Provinces with high risk profiles for 8 hazards

Priority Group 3: Provinces with risk profiles for 7 hazards

Priority Group 4: Provinces with risk profiles for less than 7 hazards

1. West Sumatera North Sumatera Bangka Belitung Aceh

2. Bengkulu Jambi Riau Islands West Kalimantan

3. West Java South Sumatera Riau Central Kalimantan

4. Central Java Lampung DKI Jakarta South Kalimantan

5. DI Yogyakarta Banten Bali East Kalimantan

6. East Java NTB Maluku

7. South Sulawesi NTT North Maluku

8. Central Sulawesi West Papua

9. South Sulawesi Papua

10. South-East Sulawesi

11. Gorontalo

12. West Sulawesi

Page 21: EP-DRR Quarterly Report Oct-Dec 2013 MA HS KS 1€¦ · 3 AIFDR Project Update GENERAL INFORMATION Reporting Period 1 October – 31 December 2013 Title Enhancing Policy and Planning

Annex 3: Financial Report

United  Nations  Development  Programme  -­‐  Indonesia Safer  Communities  through  Disaster  Risk  Reduction  Phase  II  (SCDRR  Phase  II)  

Provisional  Statement  of  Revenue  and  Expenses  period  1  April  2013  -­‐  31  December  2013  

Prepared  for  The  Government  of  Australia  (Department  of  Foreign  Affairs  and  Trade)  

Tranches  of  Payment    

(AUD)    Fund  Received    

(USD)   Utilization     %    

250,000.00              258,264.47      258,264.47                    100.00    

   

550,000.00              499,092.56            81,124.58                              16.25    

       

   800,000.00     757,357.03      339,389.05     45%  

       

                   

Expected  Output     Planned  Activities    

Contribution    Received  (USD)    

2013  Plan     Expenditure     Commitment   Utilization    Available  Resources  

%  Budget  Plan  vs  

Utilization    

 

Output  1:    Policy  guidance  is  developed  to  support  the  better  integration  of  disaster  risk  reduction  in  planning  and  budgeting  

1.1   Draft  National  Guideline  on  mainstreaming  DRR  into  spatial  plans    

         117,142.56            74,930.98              45,357.27     14,549.71     59,906.98     57,235.58     80%      

1.2   Improved  risk  assesment  methodology  with  climate  related  factors  

               64,079.21                    

53,035.23              24,374.43                                    

7,640.64                

32,015.07                      

32,064.14     60%                       1.3   Draft  national  guideline  on  

local  DRR  planning  and  budgeting    

         114,095.97                    

54,195.04              16,658.79                                    

6,917.60                

23,576.39                      

90,519.58     44%                       1.4   Analysis  and  preparatory  work  

for  next  cycle  RPJMN  for  DRR  inclusion  

               64,079.21                    

48,857.81              54,032.49                                    

8,971.66                

63,004.15                          

1,075.06     129%                           GMS                  26,855.14              16,171.33                  9,832.38              9,832.38      17,022.76     61%   Total  Output  1            386,252.09      247,190.39     150,255.36                38,079.61     188,334.97     197,917.12     76%  

Page 22: EP-DRR Quarterly Report Oct-Dec 2013 MA HS KS 1€¦ · 3 AIFDR Project Update GENERAL INFORMATION Reporting Period 1 October – 31 December 2013 Title Enhancing Policy and Planning

Output  2:        DM  Plan  improved  and  DRR  fiscal  tracking  monitoring  criteria  developed  

2.1   Analysis  and  preparatory  work  for  next  cycle  DM  Plans  with  Considerations  to  CCA  related  programmes  

         102,853.18        

               54,554.55              39,440.31    

   

                         13,785.46    

           53,225.77    

                 49,627.41     98%  

 

                    2.2   Draft  of  NAP  2013-­‐2015  which  

connected  and  synchronized  with  DM  Plan    

               77,264.83     44,960.80              28,344.71     11,169.10     39,513.81     37,751.02     88%       2.3   Analysis  and  recommendation  

for  improving  DM  Plan  coordination  and  Monitoring    

         104,289.22                    

43,455.78        

         16,226.54                              

10,825.23        

           27,051.77    

   

                 77,237.45    

   62%  

   

2.4  Analysis  and  recommendation  for  improving  fiscal  allocation  for  DRR  

59,783.41   48,037.22   12,348.34   12,165.36   24,513.70   35,269.71   51%  

  GMS   26,914.29     13,370.58     6,749.03         6,749.03     20,165.26     50%  

Total  Output  2            371,104.94     204,378.93          103,108.93                  47,945.15     151,054.08     220,050.86     74%  

Grand  Total            757,357.03          451,569.32          253,364.29                    86,024.76     339,389.05     417,967.98     75%  

             (run  date  as  of  5  March  2014)  

Note:                    

This  is  to  certify  that  the  above  statement  of  revenues  and  expenses  is  correct  and  that  the  expenses  was  incurred  in  connection  with  the  approved  projects  for  which  the  contributions    have  been  received.  

               

Please  note  that  2013  expenditures  included  in  this  financial  report  are  provisional  pending  issuance  of  the  certified  financial  statement  for  2013  by  the  Comptroller's  Office  in  UNDP    

Headquarter  on  or  before  30  June  2014.  

             

 

 

 

 

Page 23: EP-DRR Quarterly Report Oct-Dec 2013 MA HS KS 1€¦ · 3 AIFDR Project Update GENERAL INFORMATION Reporting Period 1 October – 31 December 2013 Title Enhancing Policy and Planning

Annex 4: Matrix Synergy EP-DRR and CDSP

Programme  Components

Partners  /  Beneficiaries Objectives Outputs/Outcomes Personnel Personnel Activities Partners  /  

Beneficiaries Outputs

Improving  the  quality  of  socialization  and  simulation  of  BNPB  Head  Regulation  No.  22  of  

2010;

3  Consultants  recruited  (Lusina,  Peni,  Handoko)  /  Khairullah

Support  to  formulate  recommendation  for  revision  of  existing  guideline  on  provincial  spatial  planning

Bappenas

Staff  of  BNPB  &  Provincial  BPBD  master  basic  techniques  for  Formulation  of  Public  Policy  &  Legal  

Drafting;Nanang  

2  Consultant  recruited  (Rizaldi  Boer,  Adi  Rahman)  /  Ridwan  Yunus  /  Arezka  /  Irawan

Support  to  improvement  of  risk  assessment  methodology    with  climate  risks  factors BNPB

Irawan  /  Saleh  Jasape Support  to  draft  national  guideline  on  local  DRR  planning  and  budgeting Kemdagri

2  Consultants  recuited  (May,  Dea)/  Khairullah

Support  to  produce  recommendation    and  input  for  inclusion  DM  into  next  cycle  RPJMN   Bappenas

2  Consultants  recruited  (Dian,  Ninil)  /  Arezka

Support  to  analysis  and  preparatory  work  for  next  cycle  DM  Plan   BNPB

3  Consultants  recruited  (Bayudono,  Hening,  Dian)  /  Arezka

Support  to    draft  DRR  NAP    as  part  of  DM  Plan  2015-­‐2019 BNPB

1  Consultant  recruited  (Rahman)  /  Arezka

Support  to  formulation  of    indicators  for  monitoring  and  evaluation  for  DM  Plan   BNPB

3  Consultants  recruited  (Heri  Sudarwanto,  Yanita,  Suyantoro)/  Khoirullah

Support  to    formulation  of  recommendation  for    fiscal  tracking  criteria/indicators     Bappenas

Staff  of  BNPB  &  Provincial  BPBD  master  basic  techniques  /  methods  of  SOP  drafting;

Staff  of  BNPB  &  Provincial  BPBD  are  able  to  prepare  and  develop  SOP  of  work; Nanang  

BNPB  and  Provincial  BPBD  are  able  to  apply  SOP  into  the  work  management  of  institutions Nanang  

BNPB  &  Provincial  BPBD  have  a  standard  of  clear  and  measurable  work  processes. Nanang  

Staff  of  BNPB  and  Provincial  BPBD  master  basic  techniques  /  methods  of  Personnel  Competency  

Standards  drafting;

Indra  Nurpatria

Staff  of  BNPB  and  Provincial  BPBD  are  able  to  prepare  a  draft  of  Disaster  Management  Personnel  

Competency  Standards.

Indra  Nurpatria

2  Consultant  recruited  (Rizaldi  Boer,  Adi  Rahman)  /  Ridwan  Yunus  /  Arezka  /  Irawan

Support  to  improvement  of  risk  assessment  methodology    with  climate  risks  factors BNPB

Policy  guidance  developed  to  support  better  integration  of  

disaster  risk  reduction  in  planning  and  budgeting

3  Consultants  recruited  (Bayudono,  Hening,  Dian)  /  Arezka

Support  to    draft  DRR  NAP    as  part  of  DM  Plan  2015-­‐2019 BNPB DM  Plan  improved  and  DRR  fiscal  

tracking  criteria  developed.  

2  Consultant  recruited  (Rizaldi  Boer,  Adi  Rahman)  /  Ridwan  Yunus  /  Arezka  /  Irawan

Support  to  improvement  of  risk  assessment  methodology    with  climate  risks  factors BNPB

Policy  guidance  developed  to  support  better  integration  of  

disaster  risk  reduction  in  planning  and  budgeting

3  Consultants  recruited  (Bayudono,  Hening,  Dian)  /  Arezka

Support  to    draft  DRR  NAP    as  part  of  DM  Plan  2015-­‐2019 BNPB DM  Plan  improved  and  DRR  fiscal  

tracking  criteria  developed.  

Increased  knowledge  and  skills  to  utilize  ICT  asset Noel

DM  Plan  improved  and  DRR  fiscal  tracking  criteria  developed

Support  to  increased  theoretical  knowledge  of  staff  

in  Disaster  Management

Increased  theoretical  knowledge  of  staff  in  Disaster  Management

Better  program  planning  and  synchronizationSupport  to  increased  

theoretical  knowledge  of  staff  in  Disaster  Management

Improving  Busines  Process

Staff  of  BNPB  &  Provincial  BPBD  are  able  to  formulate  regulation  /  policy  drafts  correctly.

Nanang  &  Domi

Support  to  development  of  policy,  guidelines,  planning,  

and  budgeting  on  DRR

Improving  Policy  (regulation)  Quality

ENHANCING  POLICY  AND  PLANNING  FOR  DISASTER  RISK  REDUCTION

Policy  guidance  developed  to  support  better  integration  of  

disaster  risk  reduction  in  planning  and  budgeting

POSSIBLE  SYNERGYCAPACITY  DEVELOPMENT  SUPPORT  PROGRAMME

Development  of  Human  Resource  Management

To  increase  capacity  in  the  dissemination  of  information  

and  collaboration,  management  ICT  

           

Capacity  Development  of  

Institution  Government

BNPBICT  Capacity  

BNPB  &  BPBD

Page 24: EP-DRR Quarterly Report Oct-Dec 2013 MA HS KS 1€¦ · 3 AIFDR Project Update GENERAL INFORMATION Reporting Period 1 October – 31 December 2013 Title Enhancing Policy and Planning

Programme  Components

Partners  /  Beneficiaries Objectives Outputs/Outcomes Personnel Personnel Activities Partners  /  

Beneficiaries Outputs

                   

     

ENHANCING  POLICY  AND  PLANNING  FOR  DISASTER  RISK  REDUCTIONPOSSIBLE SYNERGY

CAPACITY  DEVELOPMENT  SUPPORT  PROGRAMME

Thorough  monitoring  and  analysis  of  PUSDALOPS NoelIncreased  maintenance  and  accountability  of  ICT  

asset Noel

Increased  disaster  preparedness  and  response Robert

Dissemination  and  control  capability Support  to  data  and  information  sharing

1  Consultant  being  recruited  /  Arezka

Support  to  formulate  recommendation  for  revision  of  existing  guideline  on  provincial  spatial  planning

Bappenas

Policy  guidance  developed  to  support  better  integration  of  

disaster  risk  reduction  in  planning  and  budgeting

BNPB  needs  assessment  in  disaster  studies  to  support  the  development  of  BNPB  policies,  

guidelines  and  strategies

3  Consultants  recruited  (Lusina,  Peni,  Handoko)  /  Khairullah

Support  to  formulate  recommendation  for  revision  of  existing  guideline  on  provincial  spatial  planning

Bappenas

2  Consultant  recruited  (Rizaldi  Boer,  Adi  Rahman)  /  Ridwan  Yunus  /  Arezka  /  Irawan

Support  to  improvement  of  risk  assessment  methodology    with  climate  risks  factors BNPB

3  Consultants  recruited  (Bayudono,  Hening,  Dian)  /  Arezka

Support  to    draft  DRR  NAP    as  part  of  DM  Plan  2015-­‐2019 BNPB DM  Plan  improved  and  DRR  fiscal  

tracking  criteria  developed

BNPB  staff  are  able  to  develop  a  protocol  that  is  integrated  with  humanitarian  international  

partnerships;  →  One  draft  of  BNPB  Humanitarian  duties  Handbook  is  generated

International  Partnership  in  Humanitarian ArwinIncreased  Good  Governance  through  Internal  

Reporting  Tool1  Consultant  recruited  (Rahman)  /  Arezka

Support  to  formulation  of    indicators  for  monitoring  and  evaluation  for  DM  Plan   BNPB DM  Plan  improved  and  DRR  fiscal  

tracking  criteria  developedBNPB  staff  create  and  operate  the  short-­‐term  international  partnership  tool;  →  Program  kit,  

ranging  from  guidelines  for  registration,  concept  notes,  implementation,  M  &  E  and  exit  strategy  for  

each  international  NGO  and  donor  to  specific  disasters.

Arwin 1  Consultant  recruited  (Rahman)  /  Arezka

Support  to  formulation  of    indicators  for  monitoring  and  evaluation  for  DM  Plan   BNPB DM  Plan  improved  and  DRR  fiscal  

tracking  criteria  developed

BNPB  staff  are  able  to  create  long-­‐term  international  partnership  mechanisms  and  

procedures  ;  →  SOP  to  be  used  to  establish  long-­‐term  partnerships  at  bilateral,  regional  and  

multilateral  levels

Arwin

BNPB  staff  have  a  capacity  of  coordinating  international  donors  and  NGOs;  →  Donor  

Coordination  Forum  Arwin

BNPB  staff  are  able  to  produce  an  internal  reporting  tool;  →  One  SOP  for  Internal  Reporting  is  

generated

Support  to  skill  development  in  monitoring,  evaluation,  and  

reporting

1  Consultant  recruited  (Rahman)  /  Arezka

Support  to  formulation  of    indicators  for  monitoring  and  evaluation  for  DM  Plan   BNPB DM  Plan  improved  and  DRR  fiscal  

tracking  criteria  developed

Directorate  for  Community  Empowerment  is  able  to  build  a  database  as  a  basis  of  planning Chasan

Directorate  for  Community  Empowerment  has  concepts  of  programs,  monitoring  &  evaluation  tools,  and  a  plan  draft  of  resilient  village  /  sub-­‐

district  program  development  in  2013-­‐2014

ChasanSupport  to  skill  development  in  monitoring,  evaluation,  and  

reporting

1  Consultant  recruited  (Rahman)  /  Arezka

Support  to  formulation  of    indicators  for  monitoring  and  evaluation  for  DM  Plan   BNPB DM  Plan  improved  and  DRR  fiscal  

tracking  criteria  developed

Policy  guidance  developed  to  support  better  integration  of  

disaster  risk  reduction  in  planning  and  budgeting

Support  to  skill  development  in  research  and  methodology

                   

management,  ICT  infrastructure,  and  technical  preparedness  for  emergency  

response

The  Directorate  for  Community  Empowerment  

has  increased  capacity  for  the  implementation  and  

development  of  more  effective  programs  and  

         

   

BNPB    Development

BNPB

BNPB  staff  have  increased  capacity  in  the  management  of  international  partnerships  

based  on  mastery  of  humanitarian  protocol  

supported  by  good  governance.

Policy  Making  Capacity  

Development  /  Scientific  Study  

Framework  -­‐  Based  Planning

Capacity  Development  of  Humanitarian  Protocol  and  International  

relations

BNPB

Capacity  Development  of  

Community  Empowerment

Support  to  skill  development  in  monitoring,  evaluation,  and  

reporting

BNPB

To  accompany  BNPB  policy  pattern  to  be  more  evidence-­‐based  policy,  through  capacity  

building  in  the  pattern  of  planning,  strategy  development  and  

implementation  of  programs  based  on  analyses  of  disaster  scientific  studies  at  Deputy  for  Prevention  and  Preparedness,  particularly  at  Directorate  for  

Disaster  Risk  Reduction

Skill  development  for  BNPB  staff  that  is  relevant  in  research  and  methodology  skills  

Page 25: EP-DRR Quarterly Report Oct-Dec 2013 MA HS KS 1€¦ · 3 AIFDR Project Update GENERAL INFORMATION Reporting Period 1 October – 31 December 2013 Title Enhancing Policy and Planning

Programme  Components

Partners  /  Beneficiaries Objectives Outputs/Outcomes Personnel Personnel Activities Partners  /  

Beneficiaries Outputs

                   

     

ENHANCING  POLICY  AND  PLANNING  FOR  DISASTER  RISK  REDUCTIONPOSSIBLE SYNERGY

CAPACITY  DEVELOPMENT  SUPPORT  PROGRAMME

Directorate  for  Community  Empowerment  has  and  introduces  the  concept  of  business  institution  

involvement  in  disaster  riskChasan

2  Consultant  being  recruited  /  Ridwan  Yunus  /  Arezka  /  Irawan  /  Yusniar

Support  to  improvement  of  risk  assessment  methodology    with  climate  risks  factors BNPB

Policy  guidance  developed  to  support  better  integration  of  

disaster  risk  reduction  in  planning  and  budgeting

3  Consultants  recruited  (Bayudono,  Hening,  Dian)  /  Arezka

Support  to    draft  DRR  NAP    as  part  of  DM  Plan  2015-­‐2019 BNPB DM  Plan  improved  and  DRR  fiscal  

tracking  criteria  developed.  

Increased  Number  of  Budgeting  Plans  approved  by  Local  Parliament Irawan  /  Saleh  Jasape Support  to  draft  national  guideline  on  local  

DRR  planning  and  budgeting Kemdagri

Policy  guidance  developed  to  support  better  integration  of  

disaster  risk  reduction  in  planning  and  budgeting

Increased  knowledge  of  BPBD  staff  about  M-­‐E  process  and  method

1  Consultant  recruited  (Rahman)  /  Arezka

Support  to  formulation  of    indicators  for  monitoring  and  evaluation  for  DM  Plan   BNPB DM  Plan  improved  and  DRR  fiscal  

tracking  criteria  developedA  clear  division  of  roles  among  BPBDs  on  Who,  

Does  What  during  a  Disaster

2  Consultant  recruited  (Rizaldi  Boer,  Adi  Rahman)  /  Ridwan  Yunus  /  Arezka  /  Irawan

Support  to  improvement  of  risk  assessment  methodology    with  climate  risks  factors BNPB

Policy  guidance  developed  to  support  better  integration  of  

disaster  risk  reduction  in  planning  and  budgeting

3  Consultants  recruited  (Bayudono,  Hening,  Dian)  /  Arezka

Support  to    draft  DRR  NAP    as  part  of  DM  Plan  2015-­‐2019 BNPB DM  Plan  improved  and  DRR  fiscal  

tracking  criteria  developed.  

East  Java  BPBD  is  able  to  prepare  regulations  of  DM  Plan

Didik  S  Mulyono

East  Java  BPBD  has  a  database  for  planning  and  monitoring  and  evaluation  of  DM  program

Didik  S  Mulyono

1  Consultant  recruited  (Rahman)  /  Arezka

Support  to  formulation  of    indicators  for  monitoring  and  evaluation  for  DM  Plan   BNPB DM  Plan  improved  and  DRR  fiscal  

tracking  criteria  developed

East  Java  Province  BPBD    is  able  to  plan  specific  derivative  plans

Didik  S  Mulyono Irawan  /  Saleh  Jasape Support  to  draft  national  guideline  on  local  

DRR  planning  and  budgeting Kemdagri

Policy  guidance  developed  to  support  better  integration  of  

disaster  risk  reduction  in  planning  and  budgeting

Increased  knowledge  and  skills  of  BPBD  Staff  and  stakeholders  involved  in  the  preparation  of  disaster  

risk  assessmentButtu  Ma'dika

2  Consultant  recruited  (Rizaldi  Boer,  Adi  Rahman)  /  Ridwan  Yunus  /  Arezka  /  Irawan

Support  to  improvement  of  risk  assessment  methodology    with  climate  risks  factors BNPB

Policy  guidance  developed  to  support  better  integration  of  

disaster  risk  reduction  in  planning  and  budgeting

Meningkatnya  kemampuan  BPBD  Sulawesi  Selatan  dan  parapihak  dalam  penyusunan  kajian  risiko  

bencana

3  Consultants  recruited  (Bayudono,  Hening,  Dian)  /  Arezka

Support  to    draft  DRR  NAP    as  part  of  DM  Plan  2015-­‐2019 BNPB DM  Plan  improved  and  DRR  fiscal  

tracking  criteria  developed.  

Increased  coordination  and  cooperation  of  stakeholders  in  development  planning  and  

implementation  of  disaster  risk  reduction  program  in  South  Sulawesi

Buttu  Ma'dika Irawan  /  Saleh  Jasape Support  to  draft  national  guideline  on  local  DRR  planning  and  budgeting Kemdagri

Policy  guidance  developed  to  support  better  integration  of  

disaster  risk  reduction  in  planning  and  budgeting

Meningkatnya  kemampuan  BPBD  dan  parapihak  dalam  penyusunan    dokumen  perencanaan    terkait  

Penanggulangan  Bencana

3  Consultants  recruited  (Bayudono,  Hening,  Dian)  /  Arezka

Support  to    draft  DRR  NAP    as  part  of  DM  Plan  2015-­‐2019 BNPB DM  Plan  improved  and  DRR  fiscal  

tracking  criteria  developed.  

Increased  technical  knowledge  and  capability  of  South  Sulawesi  province  BPBD  Staff  in  DM  /  DRM Buttu  Ma'dika

2  Consultant  recruited  (Rizaldi  Boer,  Adi  Rahman)  /  Ridwan  Yunus  /  Arezka  /  Irawan

Support  to  improvement  of  risk  assessment  methodology    with  climate  risks  factors BNPB

Policy  guidance  developed  to  support  better  integration  of  

disaster  risk  reduction  in  planning  and  budgeting

Meningkatnya    jaringan  kerja  para  pemangku  kepentingan  dalam  membangun  ketangguhan  

masyarakat  terhadap  bencana  di  Sulawesi  Selatan

         

             

           

coordinate  community  development  actors  in  disaster  risk  reduction

Increased  capacity  of  WEST  SUMATRA  BPBD  in  realizing  

ALERT,  RESPONSIVE,  RESILIENT  AND  TAWAKAL  

West  Sumatra  in  the  face  of  disaster

To  increase  capacity  of  East  Java  BPBD  in  Developing  and  

Implementing  Disaster  Management  Plan  of  East  Java  

Province  in  2012  –  2016  

To  contribute  to  the  reinforcement  of  South  

Sulawesi  BPBD  to  be  able  to  lead  the  implementation  of  

Disaster  Management  in  South  Sulawesi  in  an  effective,  

efficient  and  integrated  manner  to  realize  a  disaster  

resilient  community  of  South  Sulawesi  /  BPBD  Sulawesi  

Selatan  memiliki  kemampuan  dalam  menyusun  kajian  risiko  

bencana  dan  perencanaan  terkait  PB  bersama  para  pihak

East  Java  Province  BPBD    is  able  to  develop  DM  Plan Didik  S  Mulyono

       

Empowerment

4  BPBDsCapacity  

Development  of  BPBDs

Support  to  capacity  development  in  DRM  at  sub-­‐

natinal  level

An  increase  in  BPBD  knowledge  in  DRM

Page 26: EP-DRR Quarterly Report Oct-Dec 2013 MA HS KS 1€¦ · 3 AIFDR Project Update GENERAL INFORMATION Reporting Period 1 October – 31 December 2013 Title Enhancing Policy and Planning

Programme  Components

Partners  /  Beneficiaries Objectives Outputs/Outcomes Personnel Personnel Activities Partners  /  

Beneficiaries Outputs

                   

     

ENHANCING  POLICY  AND  PLANNING  FOR  DISASTER  RISK  REDUCTIONPOSSIBLE SYNERGY

CAPACITY  DEVELOPMENT  SUPPORT  PROGRAMME

Increased  capacity  of  BPBD  in  planning  preparation Josua

2  Consultant  recruited  (Rizaldi  Boer,  Adi  Rahman)  /  Ridwan  Yunus  /  Arezka  /  Irawan

Support  to  improvement  of  risk  assessment  methodology    with  climate  risks  factors BNPB

Policy  guidance  developed  to  support  better  integration  of  

disaster  risk  reduction  in  planning  and  budgeting

Increased  capacity  of  BPBD  in  institutional  management Josua

3  Consultants  recruited  (Bayudono,  Hening,  Dian)  /  Arezka

Support  to    draft  DRR  NAP    as  part  of  DM  Plan  2015-­‐2019 BNPB DM  Plan  improved  and  DRR  fiscal  

tracking  criteria  developed.  

 BPBD  have  an  overview  of  financial  resources  to  support  Disaster  Management Josua Irawan  /  Saleh  Jasape Support  to  draft  national  guideline  on  local  

DRR  planning  and  budgeting Kemdagri

Policy  guidance  developed  to  support  better  integration  of  

disaster  risk  reduction  in  planning  and  budgeting

Working  Groups: Thematic  sectors:

Community  Empowerment Monitoring  and  Evaluation  of  DM  Plan

Risk  Assessment  DRR  Action  Plan

Risk  AssessmentSpatial  PlanningDRR  Action  PlanBack  ground  study  -­‐  DM  inclusion  in  RPJMN

International  Partneship Monitoring  and  Evaluation  of  DM  Plan

Risk  AssessmentDRR  Action  PlanLocal  Planning  and  BudgetingMonitoring  and  Evaluation  of  DM  Plan

Strengthening  Local  Government

ICT

Increased  capacity  of  BPBD  (East  Nusa  Tenggara)  in  Disaster  Management  

according  to  the  Main  Duties  and  Functions

   

   

Evidence/Research  Based  Policy