  • 7/26/2019 EoM Progrees Period March 2016 for Ao

    1/1

    Back Fill P2 :

    - G23 :12,835 LCM- G31 : 83,233 LCM- G32 : 1,911 LCM- G37 : 1,267 LCM- G38 : 153 LCM

    Total : 99,400 LCM

    P2-G.36 P2-G.37

    PIT 02 _ G31,G32,G37 & G38OB removal : 1,558.34 BCM

    Bdy area : 1,775.14 Sq.M

    Coal extracted : 8,216.39 M.Tonnes

    Bdy area : 16,415.61 Sq.M (Mine Out)

    PIT 06 _ G53_G54 & G58Coal extracted : 68,182.27 M.TonnesBdy area : 15,711 Sq.M

    Mine Out Area : 9,521 Sq.M

    PIT 06 - G39,G44 & G49

    Coal extracted : 98,497.67 M.Tonnes

    Bdy area : 15,711 Sq.MMine Out area : 9,854 SqM

    PIT 06 - G44 & G49

    Coal exposed : 17,940.92 Sq.M

    PIT 06 - G33A 7 G38A

    Coal exposed : 8,79855 Sq.M

    MINE PROGRESS SITUATION MAPPERIOD 1ST to 31TH MARCH 2016

    Prepared by : Ladjo Pammula (Mine Surveyor)

    Checked by :

    Approved by :

    MAP. Id/Date : Eom3/Surv/III/2016 / April, 3nd 2016

    D:\DEPARTEMENT SURVEY\2016 YEAR\FEBRUARY 2016\EoM Progress March 16'\final situation

    P2-G.38 P2 -G .39 P 2- G.40 P 2- G.41

    P2- G. 42 P 2-G .43 P2 -G. 44 P 2-G. 45 P2- G. 46

    P2-G.48P2-G.47 P2-G.49 P2-G.50

    P 2- G.51 P 2- G.52 P 2- G.53

    P 2-G. 32 P2- G. 33 P 2-G. 34 P2- G. 35

    LEGEND :

    : OB Removal Area

    : Coal Extracted Area

    : Coal Exposed Area

    : Mine Out Area

    : River

    : KBK Boundary

    : Mine Road

    : Loging/Village Road

    for A0

    30 M

    PIT 06 _ G17,G18,G21,G22, & G23

    OB removal : 12,796.90 BCM

    Bdy area : 22,176 Sq.MCoal exposed : 18,489 SqM