enya ational ighways uthority - kpric folder/nairobi-thika investor...please note that this...
TRANSCRIPT
KENYA NATIONAL HIGHWAYS AUTHORITY
INTERCONTINENTAL
CONSULTANTS AND
TECHNOCRATS PVT. LTD.
GRANT
THORNTON
INDIA LLP.
CHITALE & CHITALE
PARTNERS
GEODEV (K) LTD.
KENYA PPP ROADS INVESTOR CONFERENCE15TH NOVEMBER 2016
OPERATION AND MAINTENANCE OF
THE NAIROBI-THIKA HIGHWAY (A2) ON PPP
Please note that this presentation is for informational purposes only. Any comments orstatements made herein do not necessarily reflect the views of KeNHA nor IntercontinentalConsultants and Technocrats Pvt. Ltd (ICT). The information is intended for the recipient's useonly and should not be cited, reproduced or distributed to any third party without the priorconsent of the authors. Although great care is taken to ensure accuracy of information neitherIntercontinental Consultants and Technocrats Pvt. Ltd (ICT), nor KeNHA can be held responsiblefor any decision made on the basis of the information cited.
1
Disclaimer
PROJECT ROAD
50 Km highway connecting
Nariobi city and satellite town
Thika including
3 Nairobi city connectors
27 major structures
Popularly known as “Thika Super-
Highway (A2)” - 6/8 lanes with
service lanes/cycle tracks
Passes through highly urbanized
and semi-urban regions
Already operational, currently
under maintenance contract
9
TRAFFIC PROFILE
65000 to 83000PCU
65000 to 83000PCU
35000PCU
35000PCU
65000 to 82000PCU
65000 to 82000PCU
110000 to 150000PCU
110000 to 150000PCU
LANES TRAFFIC
55000 to 60000PCU
55000 to 60000PCU
TRAFFIC COMPOSITION
67.34%
3.35%
15.67%
5.49%7.23%
0.17%0.49% 0.20%
0.07%
Car/Taxi/Auto
2-W/Boda boda
Matatu/Mini Bus
Medium and Large Bus
LGV
2 Axle
3 Axle
MAV
NMT (Cycle/H. Cart/ADV)
10
PROJECT SCOPE
Primary objective is Operation & Maintenance of the Project
Road, including initial capex on provision/installation of
Construction of new foot over bridges*
Street Lighting on Main Carriageway / Service Roads
HTMS for the entire project road
including Emergency Response System
Spot Improvements at intersections
Concession Period -10 years
* Thika Superhighway speed-breakers, zebra crossings to be removed11
ILLUSTRATIONS
HIGHWAY TRAFFIC MANAGEMENT SYSTEM
EMERGENCY RESPONSE SYSTEM
13
PPP STRUCTURE
KeNHA
Project Company
Investors
Lenders
Project Agreement
TollOperator
Dedicated Funding Facility
Government
Backstopping in case of revenue shortfall
ServicePayments
Users
Toll
14
KEY RISK ALLOCATION
Rights, Responsibilities, Risks Project Company Contracting Authority
ROW
Design
Necessary Approvals
Construction
Financing
Force Majeure
Axle overloading
Revenue
Operations & Maintenance
Performance
Local Currency Inflation
USD:KSH Exchange Rate
Local Currency Interest Rate
Political
15
PAYMENT MECHANISM
Form of payment to Project Company
Performance-linked Service Payments, largely linked to ProjectRoad Availability
Deductions
Service Payments will be deducted for not meeting the
Performance Standards
Cumulative deductions leads to Event of Default / Termination
Indexation of Service Payments
Forex Local currency interest rate Inflation
The provisions of the Project Agreement – in accordance with the
‘International Practices’
Force Majeure
Termination Payments
Lenders Direct Agreement
Dispute Resolution
Change in Law, etc.
16
KEY TERMS OF THE PROJECT AGREEMENT
Nov ‘16
Publication of RFQ Notice
4th week, Jan ‘17
RFQ Evaluation and short-listing of pre-qualified
bidders
1st week, Feb ‘17
Issuance of RFP documents
including DCA
4th week, Jun. ‘17
Selection of Preferred Bidder
2nd week, Sep. ‘17
Signing of PA
Dec ‘17
Financial Closure
IMPLEMENTATION PLAN
17