environmental safeguards due diligence report...wss was done using hydraulic modelling software of...
TRANSCRIPT
Environmental Safeguards Due Diligence Report Project Number 42459-014 August 2019
Sri Lanka: Local Government Enhancement Sector
Project Additional Financing (LGESP-AF)
Construction of Panagoda & Kruswatte Drinking
Water Supply Scheme for Naththandiya
Pradeshiya Sabha
(NWP-AF-NAT-06)
Prepared by LGESP (Pura Neguma) Project Management Unit for the Ministry of Internal &
Home Affairs and Provincial Councils & Local Government (Formerly named as “Ministry of Provincial Councils, and Local Government and Sports”), Colombo, Sri Lanka and the Asian
Development Bank.
This environmental safeguards due diligence report is a document of the borrower. The views
expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature.
In preparing any country program or strategy, financing any project, or by making any
designation of or reference to a particular territory or geographic area in this document, the
Asian Development Bank does not intend to make any judgements as to the legal or other
status of any territory or area.
0
Ministry of Provincial Councils and Local Government
Local Government Enhancement Sector Project (Additional
Financing)
(ADB assisted – Loan 3431 SRI)
DUE DILIGENCE REPORT - ENVIRONMENT
PACKAGE NUMBER – NWP AF NAT 06
ADDITIONAL FINANCING OF LOCAL GOVERNMENT
ENHANCEMENT SECTOR PROJECT: PANANGODA AND
KURUSWATTE DRINKING WATER SUPPLY PROJECT FOR
NATHTHANDIYA PRADESHIYA SABHA
NORTH WESTERN PROVINCE, SRI LANKA
July 2019
Prepared for Local Government Enhancement Sector Project (Additional Finance)
Subproject Coordination Unit - North Western Province
1
Table of Contents
I. INTRODUCTION 2
A. Background ................................................................................................................ 2
B. Objective of the Subproject ......................................................................................... 3
C. Categorization and Justification .............................................................................. 4
II. PROJECT DESCRIPTION 4
A. Present Location and Environmental Status ............................................................... 4
B. Proposed Work ........................................................................................................... 5
III. POSSIBLE IMPACTS& MITIGATION…………………………………………………. 7
IV. Grievance Redress Mechanism……………………………………………………………...9
V. Environment Management Plan (EMP) and Environmental Monitoring Plan(EMoP)…………………………………………………………………………………………13
VI Conclusion and Recommendation……………………………………………………..13
List of Appendices
Appendix 1- Maps, Plans & Pictures showing existing sites & Construction related
supplementary drawings ………………………………………………………..…..…… 14
Appendix 2- Rapid Environmental Assessment (REA) -Water Supply…………………..15
Appendix 3- Environmental Management Plan & Environmental Monitoring Plan. ……22
Appendix 4- Water Quality Reports of Kuruswatte and Panangoda tube wells…………36
2
I. INTRODUCTION
Background
1. The Local Government Enhancement Sector Project (LGESP) was approved by ADB
on 29 September 2012 with an amount of $59 million equivalent from ADB’s Special Fund Resources. The loan became effective on 29 November 2011 and the loan closing date is 31
December 2016. Ministry of Provincial Council and Local Government (MPCLG) is the
executing agency, and subproject coordination unit (SPCU) is established in each provincial
council (total seven) to supervise and coordinate and project implementation. LGESP has
been supporting local infrastructure improvement and basic service delivery in less-developed
areas in seven provinces (excluding the Northern and Eastern Provinces), based on a bottom-
up, demand-driven approach. The additional financing is required to scale up a well-
performing project. It includes (i) improvement of water supply systems in areas affected by
chronic kidney diseases (CKD); (ii) improvement of local infrastructure and basic services
delivery; and (iii) advancing policy reform of local government and strengthening their capacity.
2. Naththandiya PS which was established in 1988 is situated in the Puttalam District in
the North Western Province of Sri Lanka. It is located East of Puttalam in Puttalam District of
North West Province and about 80 km away north east from Colombo (via Colombo Kandy
HW) and 20km away from provincial capital Kurunegala. The PS consists of 94 GN divisions,
has a population of 71,693 and is of an area of 71.94 sq.km.
3. This subproject area is primarily an agricultural area and safe drinking water is in short
supply. The drinking water requirement of the community is fulfilled through various means
and sources. Safe drinking water has been identified as a priority need of the people in the
area through public consultation meetings.
4. A community consultation meeting was held at the community hall at Mailawa in 2016
to discuss the projects to be implemented through ‘PuraNeguma’ programme. Secretary, officers of the PS, officers of the PuraNeguma and the general public attended this meeting.
The consent of the majority of those presents at the meeting has been given for balance
improvements of this sub project. As the availability of funds has considered the possibility of
carrying out both identified improvements which is also a priority request, then decided to
undertake a water supply scheme for the village of Mailawa, Kruswatte and Panangoda area.
The two projects proposed Mailawa, Kruswatte and Panangoda will be maintained by PS after
completion.
5. This due diligence report is prepared as the sub project selection was based on the
community consultation and participation criteria .Panangoda and Mailawa, Kuruswatte water
improvement project was selected as a priority sub project to be financed with the LGESP
funded by Asian Development Bank.
6. The Panangoda Kuruswatte water supply sub project will be implemented in the
Panangoda and Mailawa GN divisions of the Mahawewa and Naththandiya Divisional
Secretariats respectively. The people living there use well water for drinking and other
3
domestic purposes and there is severe shortage water particularly in the dry period (June to
October) during which times the quality becomes inferior. There is no drinking water supply
system provided to this community who are to be served by the subproject.
7. Through a consultation and participation process carried out with the community and
the other stake holders, and based on the sub project selection criteria, priority order of the
requirements of the public and the financial capacity of the PS to carry out the operation and
maintenance of the asset to be created by the funding, construction of a water supply project
in Panangoda and Kuruswatte to provide a better and efficient service to the community was
recommended for funding.
8. Adding more convenience for the people in the area, fulfilment of clean and safe
drinking water, supply of water continuously for the people living in the area are expected as
benefits through this water supply project.
9. The proposed scheme for Kuruswatte is expected to include the existing tube well, an
overhead water tank, filter house, and package plant and chlorination system for Kuruswatte
in PS owned land and transmission line and distribution network. For Panangoda it is
expected to include the existing tube well, an overhead tank and chlorination system in PS
owned land and transmission line and distribution network. Analyse of distribution network of
WSS was done using hydraulic modelling software of ‘EPANET’.
10. The numbers of beneficiary households in every area have been determined. Water
source is available to suit the requirements of the people and PS, giving due consideration to
the reliability and long term operating and maintaining capability of the organization that is
going to operate the scheme. Distribution network of the water supply scheme consists of pipe
lines of diameters 110, 90 and 63 mm. Total length of pipe lines in the network is about 6.5
km for Panangoda and 3.5 km for Kuruswatte. Initially, water will be issued to 196 families for
Panangoda and 75 families for Kuruswatte. Total Cost Estimate is Rs.33.10 Mn.
Objective of the Subproject
11. The objective this sub project is to supply clean and safe drinking water to people in the
Panangoda , Mailawa GN divisions of the Mahawewa and Naththandiya Divisional
Secretariats respectively, who use well water for drinking and other domestic purposes by
constructing an overhead water tank, filter house, package plant , transmission line and
distribution network in Kuruswatte and overhead tank ,transmission line and distribution
network in Panangoda ..
4
Categorization and Justification
12 Based on results of the Rapid Environmental Assessment ( Appendix 2), ADB SPS 2009,
and EARF the subproject is classified as environmental category C, i.e the subproject is
judged to be unlikely to have adverse environmental impacts but would have some
construction related impacts which could be mitigated/minimized to acceptable level by
adopting mitigation measures. DDR Environment report is prepared accordingly.
II. PROJECT DESCRIPTION
Present Location and Environmental Status
13. The Panangoda drinking water supply scheme’s tube well is located at 7°27'06.9"N
79°54'33.0"E and its overhead tank is located at 7°27'05.3"N and 79°54'29.2"E .Mailawa,
Kuruswatte drinking water supply scheme’s tube well is located at 7°25'12.6"N 79°52'56.9"E
and its overhead tank is located at 7°24'53.6"N 79°52'58.8"E.
14. Naththandiya PS is situated in the Puttalam District in the North Western Province of
Sri Lanka. The PS consists of 94 GN divisions, has a population of 71,693 and is of an area
of 71.94 sq.km. The elevation of the PS is 36 m from MSL.It is located about 80 km away north
east from Colombo (via Colombo Kandy HW) and 20 km away from provincial capital
Kurunegala. The boundaries of the PS are Chilaw PS from North, Indian Ocean from West,
Wennappuwa PS from South and Kurunegala District from East.
15. Naththandiya PS is a fast developing city in the North Western Province, Sri Lanka
with a well-connected road and railway network. It is situated between Puttalam and Chilaw
(in the A3 Puttalam to Peliyagoda road) town. It is one of the most populated residential parts
of the division with over 70,000 people including all religions - Buddhist, Hindu, Muslims,
Christian, living together with prosperity and harmony.
16. The main economic activity of the area is agriculture with coconut being the main
cultivations. Majority of the community depends on agriculture as their livelihood, where most
of them are engaged in paddy cultivation.
17. The proposed site for the Panangoda drinking water supply scheme is located in the
Panangoda GN division of Mahawewa DS division. The proposed land is owned by the
Pradeshoya Sabah, Naththandiya . Existing tube well (water extraction point) and overhead
tank are situated in the same land at about 130m distance apart. The proposed sites for
Mailawa, Kuruswatte scheme is also owned by the Pradeshiya Sabah, Naththandiya. Tube
well of Kuruswatte drinking water supply scheme is located in about 02 perch land while its
overhead tank will be constructed in a separate land with an area of 30 perches which is
located at about ½ km away.
18. Naththandiya falls within the low country intermediate zone, with an average annual
rainfall between 1750 - 2500 mm. The rainfall to the area is experienced in two folds. It is
around 155 mm in the months of April, May, June, October and November and reduces to
around 44 mm in the other months of the year. The rainfall is mainly affected by North East
5
and South West Monsoonal rains and inter monsoonal rains. The region receives an annual
average precipitation of 2064.5mm (2015). However, significant deviations in the rainfall
pattern had not been observed. The average annual temperature in the region is hot as 28.1 0C (2015). Major deviations had not been observed for the past 5 years.
19. A significant percentage of the soil in the area is a sandy soil. In addition, low humicgley
soil, Regosols on old red and yellow sand, Red Yellow Podzolic soils with soft and hard laterite
are also present.The terrain could be categorized mainly into three types, rolling, undulating
and flat. Water streams, rivers and even tributaries could be observed.
20. There are no environmentally sensitive areas such as reserved forests, protected water bodies or water channels within or in the vicinity of the project implementation area. The subproject site is not adjacent or within the area of close proximity to any environmentally protected area Eg. (i) area administered by the Department of Wild Life Conservation, (ii) Department of Coast Conservation & Coastal Resources Management, Department of Forests, (iii) the area declared as low lying and flood protection under the SLLRDC Act, and (iv) No archeologically protected monument is located in close proximity. There are areas like home gardens, paddy fields, small irrigation canals and natural water ways to receive surface drainage generated from rains. 21. The existing legislation and standards applicable for the designing projects in Sri Lanka
are mainly based on the National Environmental Act (NEA). According to the provisions under
the NEA No 47 of 1980 and the regulation on EIA which has been gazetted in 1993, this sub
project does not require an EIA or IEE prior to implementation of the sub project. As per ADB
SPS 2009 and EARF of the project, Rapid Environmental Assessment (REA) was carried out
to identify environment issues. This project is a water supply project and related environmental
impacts have been identified through this process. Accordingly developed EMP and EMoP
are shown in Appendix 3.
22. All quarry operations and mining operations connected with the project will require a valid
license issued by the Geological Survey and Mines Bureau (GSMB). All the effluents and/or
emissions shall be in compliance with the standards recommended by the National
Environmental Act (NEA).
Proposed Work
23. The Panangoda drinking water supply scheme is located in the Panangoda GN division
of Mahawewa DS division. Mailawa, Kuruswatte drinking water scheme is located in the
Mailawa GN Division of the Naththandiya DS division. The source of water for the schemes
are from two existing tube wells located at Panangoda and Kuruswatte. The Google map and
the photos annexed as Appendix 1 herewith which clearly shows the details of the subproject
areas and drawings of the pipe lines.
24. In the proposed land of Panangoda where the pump control room and overhead tank
are to be built, a community building managed by Pradhashiya Sabah is available. The water
extraction point (existing tube well) is also located in this land about 200m away.
25. There are no environmentally sensitive areas located within or adjacent to project
areas. Mainly, the land areas surrounding the location are coconut plantations and residences.
6
Land of the Sub Project area is generally flat. There are no prominent towns within sub project
area except for Naththandiya town. Elevation of the sub project area is approximately 36
meters above Mean Sea Level. The water quality in the tube well of Kruswatte, Mailawa is
not within the level of drinking water quality standards and therefore a Package plant will be
introduced to treat the raw water to drinking water quality standards. Water quality of
Panagoda tube well is within the level of drinking water quality. Water quality reports are given
in Appendix 4.
26. Land where the overhead water tank of Kuruswatte scheme is to be built, is located
01km away from the existing tube well. Overhead tank will be built in the highest elevation in
the area. A few trees such as Ketakala ,Kenda and Margosa are available in this land.
Yatikalana Sri Dhamma Vijayaramaya is the only religious place located in the surrounding
area.
27. The details of the total works taken up under the subproject are given below in Table
01 below.
Table 01 - Attributes of the Sub-Project
Total available capacity for WSS
For Panangoda 80 m3 For Kuruswatte 30 m3 12 m height Ferro cement overhead tank capacity
For Panangoda 40 m3 For Kuruswatte 30 m3 Distribution system For Panangoda High Lift Pumps 2 nos (Centrifugal Pump)
Length of PVC pipe line - 160 m
Diameter- 90 mm
Pump Capacity- 134 l/min
Pumping Total Head- 62 m
For Kuruswatte High Lift Pumps 2 nos (Centrifugal Pump)
Length of PVC pipe line - 700 m
Diameter- 63 mm
Pump Capacity- 50 l/min
Pumping Total Head- 30 m
Low Lift Pumps 2 nos (Submersible Pump)
Rate: 55 l/min
Diameter:<140 mm
Pump head: 60 m
Pumping Total Head- 42 m
Recommended pump installed depth 52 m below GL uPVC /GI pipes laying
For Panangoda 6.50 km For Kuruswatte 3.50 km Delivery Pipe lines 110 dia.- 655 m
90 dia.- 525 m 63 dia.- 6850 m
Ownership Naththandiya PS
7
28. The technical design is done in close coordination with the safeguard team of SPCU and
Design and Supervision Consultants. The due diligence process was conducted for the
proposed water supply project accordingly Local Government Enhancement Sector Project
EARF and ADB SPS 2009. Upon project implementation, the Safeguards Specialist at PMU
and the Safeguards Manager at SPCU will undertake a review of this due diligence, prepare
a confirmation report documenting any modifications for this sub-project and submit to ADB;
and receive a “no objection” confirmation from ADB prior to start of construction.
29. All technical designs and provisions are in accordance to National Standards
(ICTAD/CIDA and BS specifications) and will be constructed in close coordination with
Safeguard Team of SPCU and Design and Supervision Consultants. Related supplementary
drawings have been added in Appendix 1.
30. The environmental due diligence process has been conducted for the proposed
construction of the water supply project. This report describes details of environmental
safeguards, potential impacts, mitigation methods and monitoring parameters etc.
Safeguards staff of the SPCU, DSC, PMU and PMC are involved in developing this
environmental due diligence report in order to obtain clearances and approval from ADB prior
to initiation of any construction activity.
III. POSSIBLE IMPACTS& MITIGATION
31. Environmental screening was carried out as a part of this environmental due diligence
exercise. Rapid Environmental Assessment (Appendix2) reveals that there are some
environmental impacts and mitigation is possible during construction time and issues are
possible with the preparation and execution of the Environmental Management Plan
Environmental Management Monitoring Plan attached in this DDR .
32. The main objectives of the Rapid Environmental Assessment and the due diligence
screening are to identify the direct and indirect impacts on the physical, biological and social
or cultural heritage environment. Under the component of human risk, community/
occupational health and safety associated with the proposed construction and operations of
the subproject, particularly issues related to accident prevention, dangerous working
conditions, environment pollution and soil/ground…etc. are identified.
33. However, in consideration to the neighboring areas and the population distribution,
findings of some anticipated impacts due to the subproject activities and their management
measures can be discussed as follows;
I. Land use – There are no natural forest patches or natural streams running across the
project area. The road section selected for pipe laying has different land uses mixed with
natural environment at different locations. Along this particular road section, one can
observe quite a lot of home gardens in different scale. Livestock farming is also a popular
livelihood in this area. However, the main economic activity of the area is agriculture
specially with coconut cultivations. Majority of the community depends on agriculture as
their livelihood, where most of them are engaged in paddy cultivation. Less than half the
8
agricultural work is in paddy cultivation and most others in agricultural employment are
involved in cultivation of fruit crops and vegetables.
II. Ambient Air Quality – Construction activities will involve movement of vehicles carrying
construction material…etc. This will result in limited fugitive emissions on site. Spraying
of water during construction will reduce the emissions of dust fall to a great extent.
However, proper coverage shall be provided at the boundary area of the subproject site
as an environmental and safety precautionary measure before commencing the
activities.
III. Ambient Noise levels and traffic – During the construction phase, the sources of noise
pollution will primarily be limited to use of machineries and movement of vehicles
transporting construction materials and equipment to the site.
IV. Movement of traffic– The additional increase in construction related vehicles is of
concern during peak traffic hours, particularly office hours, school opening and closing
times. Its advisable to consider road safety such peak traffic hours to make sure no
accidents.
V. Waste collection and disposal facility- A system of appropriate collection (of sorted
waste) and disposal of bio-degradable and non-biodegradable solid and liquid waste will
be implemented in the subproject site. As per contract, any unusable waste shall be
disposed by the contractor to a site selected and informed by the Engineer, but with prior
approval from the Employer. Solid waste produced by the work force should be properly
disposed in agreement with the PS. Solid waste and debris generated from construction
activities should not be disposed on the sides of the road or left after construction works
is complete. Locations of sites for disposal of such waste will be selected by the
contractor in consultation with the PS. Garbage bins should be provided at all times and
they should be collected by the PS constantly.
VI. Storage of materials – Due care and separate storage shall be arranged particularly for
storage of construction materials, tools and equipment, plumbing and electrical
items...etc.
VII. Health & Safety of workers- During land clearing and construction emission of dust is
inevitable. Contractor shall distribute dusk masks to all workers to ensure protection from
dust. Dispersion of dust would be curtailed by regular watering of working areas. In
addition personal protection equipment such as helmets, gumboots, hand gloves, safety
jackets and safety belts shall be geared up accordingly. Health & safety awareness will
be provided to contractor’s workers.
VIII. Demarcation of working area, prior planning for specific work area and
dissemination of information through signage - Signage will be placed at specific
locations, which will show type and period of work. Also, work area will be demarcated
before starting of the work.
9
IX. Co-ordination and co-operation - Considered necessary among the staff and workers
particularly on following aspects:
Since the work has been proposed to be carried out in a rural area the contractor
shall ensure that the regular day today functioning of the area are not affected
during the construction work.
The contractor shall execute the work with prior approval of the work sequence
from the engineer.
During execution of work, materials will not be stacked in common areas and
utmost care shall be taken by the contractor to avoid any inconvenience due to
improper stacking of materials. If for any unavoidable situation, the materials
have to be stacked for a short time, prior permission from engineer shall be
obtained.
IV .GRIEVANCE REDRESS MECHANISM 34. A project-specific grievance redress mechanism (GRM) has been established to
receive, evaluate, and facilitate the resolution of affected person’s concerns, complaints and grievances about the social and environmental performance of LGESP. The GRM of the
project has been prepared and accepted by ADB and disclosed in the project website. The
GRM chart providing information on receipt of complaints and levels of redressal is displayed
in all subproject sites, local authorities’ offices, SPCU offices and other important places. The SPCU records all grievances received and address them on priority. To date all grievances
are addressed at the stage of first tier.
35. The GRM aims to provide a time-bound and transparent mechanism to voice and
resolve social and environmental concerns linked to the project. The GRM is project-specific
and not intended to bypass the government’s own redress process; rather it is intended to address affected people's concerns and complaints promptly, making it readily accessible to
all segments of the affected people and is scaled to the risks and impacts of the project.
36. The PMU and SPCUs will make the public aware of the GRM through public
awareness campaigns. Grievances can be filed in writing using the Complaint Register and
Complaint Forms or by phone with any member of the PMU or SPCU. The contact details of
the respective SPCUs will serve as a main avenue for complaints and will be publicized
through display on notice boards outside their offices and at construction sites. The safeguard
documents made available to the public in an accessible version will include information on
the GRM and will be widely disseminated throughout the corridor by the safeguards officers
in the PMU and SPCUs.
37. First tier of GRM. The SPCU is the first tier of GRM which offers the fastest and most
accessible mechanism for resolution of grievances. The Safeguards Manager – Social and
Gender in the SPCU will be designated as the key officer for grievance redress. Resolution of
complaints will be done at the earliest. Investigation of grievances will involve site visits and
10
consultations with relevant parties (e.g., affected persons, contractors, traffic police, etc.). The
Community Development Officer of the local authority or in the absence of Community
Development Officer, any officer who is given the responsibility of this, would coordinate with
the safeguards and gender manager of SPCU in redressing the grievances. Grievances will
be documented and personal details (name, address, date of complaint, etc.) will be included
unless anonymity is requested. A tracking number will be assigned for each grievance,
including the following elements:
• Complaint Register and Complaint Forms (including the description of the
grievance) with an acknowledgement of receipt given to the complainant when
the complaint is registered;
• Grievance monitoring sheet with actions taken (investigation, corrective
measures); and
• Closure sheet (Result of Grievance Redressal), one copy of which will be
handed to the complainant after he/she has agreed to the resolution and
signed-off.
The updated register of grievances and complaints will be available to the public at the SPCU
office, construction sites, and other key public offices. Shall the grievance remain unresolved
it will be escalated to the second tier.
38. Second Tier of GRM. The Social Safeguards and Gender Manager of SPCU will
activate the second tier of GRM1 by referring the unresolved issue (with written
documentation), The Grievance Redress Committee (GRC) will be established before
commencement of site works. A hearing will be called with the GRC, if necessary, where the
affected person can present his and/or her concern or issues. The process will facilitate
resolution through mediation. This local GRC will meet as necessary when there are
grievances to be addressed. The local GRC will suggest corrective measures at the field level
and assign clear responsibilities for implementing its decision at the earliest. The contractor
will have observer status on GRC. If unsatisfied with the decision, the existence of the GRC
will not impede the complainant’s access to the Government’s judicial or administrative remedies.
39. The safeguards and gender manager of SPCUs will be responsible for processing and
placing all papers before the GRC, maintaining database of complaints, recording decisions,
issuing minutes of the meetings and monitoring to see that formal orders are issued and the
decisions carried out.
40. Third tier of GRM. In the event that a grievance cannot be resolved directly by the
SPCUs (first tier) or GRC (second tier), the affected person can seek redress through third tier
1 The GRC will consist of the following persons (i) Commissioner of Local Government of the Province as Chairman, (ii) Divisional Secretary of the area; (iii) Chairman of the respective pradeshiya sabha; (iv) representative of nongovernment organizations and/or community based organizations working in the area as nominated by CLG; (v) Member of clergy of pradeshiya saba area; (vi) Chairman of Samathamandal; (vii) GramaNiladhari of the area; (vii) Social Safeguard and gender Manager - as Member Secretary of the GRC. The functions of the local GRC are as follows: (i) resolve problems quickly and provide support to affected persons arising from various issues including environmental and social issues.
11
at the central level. The third tier - Central Grievance Redressal Committee consists of (i)
Project Director as Chairman; and (ii) Legal Officer of MPCLG as member and Social
Safeguard and Gender Officer of PMU as Member Secretary.
41. In case the grievance is not solved at this level, then the complainant can refer the
same to the court of law.
42. The detailed GRM is hosted in the project website. The graphical representation of the
GRM is given at Fig 1 below.
43. The safeguard monitoring reports will include the following aspects pertaining to
progress on grievances: (i) number of cases registered with the GRC, level of jurisdiction (first,
second and third tiers), number of hearings held, decisions made, and the status of pending
cases; and (ii) lists of cases in process and already decided upon may be prepared with details
such as name, ID with unique serial number, date of notice, date of application, date of
hearing, decisions, remarks, actions taken to resolve issues, and status of grievance (i.e.
open, closed, pending).
44. All costs involved in resolving the complaints (meetings, consultations, communication
and reporting and/or information dissemination) will be borne by the executing agency.
12
Figure 1: Tiers of GRM
13
V. ENVIRONMENT MANAGEMENT PLAN (EMP) AND ENVIRONMENTAL MONITORING PLAN(EMOP)
45. Though the impacts are mostly construction related the contractors have to follow an
Environment Management Plan during construction phase of the project to mitigate those
impacts. The Environmental Management Plan(EMP) and Environmental Monitoring Plan
(EMoP)are attached vide Appendix 3. The Contractor will be required to submit
Environmental Management Action Plan ( EMAP) including the time -frame and the allocated
budget. EMAP should be prepared based on the environmental issues, migratory measures
identified in the EMP and EMoP.
VI. CONCLUSIONS AND RECOMMENDATIONS
46. The negative environmental impacts arising due to execution of the proposed water
supply scheme are minor and negligible as compared to the long term Socio-economic and
health benefits to be delivered to people of the project area. Negative impacts can be mitigated
to standard levels without difficulty through proper engineering design and the incorporation
or application of recommended mitigation measures and procedures as per EMP.
47. It is recommended that (i) DDR be made part of the bid and contract documents to
ensure mitigation measures are appropriately budgeted and legally binding to the contractors;
(ii) monitor diligently contractor/s EMP implementation by PMU, SPCU and consultants on
EMP implementation by contractors.
48. Conclusion. The subproject will not cause adverse environmental problems during
preconstruction, construction and operational stages since the identified potential adverse
impacts during environmental assessment study are manageable by implementing proposed
mitigation measures at right time and monitored through a comprehensive environment
monitoring plan as described in this DDR report. Therefore, an IEE will not be required.
14
APPENDICES Appendix 1: Maps, Plans & Pictures showing existing site & construction related supplementary drawings.
A) Proposed two project sites.
A-1) Kuruswatte WS scheme project site project site in the close-up Google map.
A-2) Panangoda WS scheme project site project site in the close-up Google map
15
Appendix 1 c) Existing landscape of the proposed site - Kuruswatte, Mailawa.
Existing Tube well – Water Extraction Point
Site selected for constructing overhead
16
Appendix 1 d) Landscape of the proposed site - Panangoda
Ground water extraction point – Existing Tube Well
Site selected for constructing overhead tank.
17
Appendix 1
Details of Pipe Lines
Pipe schedule for Panangoda WSS
SPECIALLY NOT STATED PIPES ARE PVC (PN7)
SECTION DIAMETER
(mm) LENGTH (m) SECTION
DIAMETER
(mm) LENGTH (m)
A-B 110 60 L-N 63 50
A1-B1 90 (PN11) 160 N-O 63 130
B-C 110 100 N-D 63 380
C-D 90 90 B-P 110 230
E-D 63 378 P-Q 110 270
E-F 63 340 P-T 63 305
E-H 63 77 P-X 63 130
F-G 63 80 P-Q 63 260
H-C 63 260 Q-R 63 60
C-N 63 195 Q-S 63 300
C-I 90 80 Q-T 90 190
I-N 63 120 Q-T 63 175
J-K 63 70 T-U 90 105
J-L 63 300 U-V 63 380
J-I 63 300 U-W 63 120
L-M 63 30 W-S 63 370
Pipe schedule for Kuruswatte WSS
SPECIALLY NOT STATED PIPES ARE PVC (PN7)
SECTION DIAMETER
(mm) LENGTH (m) SECTION
DIAMETER
(mm) LENGTH (m)
A-B 63 (PN11) 715 H-M 63 345
C-D 110 475 O-Q 63 135 (L)
D-F 90 96 O-Q 63 135 (R)
D-E 63 6 J-N 63 30 (L)
F-H 90 94 J-N 63 30 (R)
H-J 90 50 N-O 63 85 (L)
I-D 63 460 N-O 63 85 (R)
D-F 63 96 O-P 63 80 (L)
F-G 63 220 O-P 63 80 (R)
N-L 63 122
14
Appendix 1
Layout Plans For Panangoda
For Kuruswatte
15
APPENDIX 2:
Rapid Environmental Assessment (REA) -Water Supply
Project : Local Government Enhancement Sector Project- Additional Financing (ADB
assisted- Loan 3431 SRI) Province : North Western Province Subproject : Panangoda and Kuruswatte Drinking Water Supply Project for Naththandiya
Prdeshiya Sabah.
LA : Naththandiya PS
District : Puttalam, Sri Lanka
Screening questions Yes No Remarks A. PROJECT SITING IS THE PROJECT AREA
Densely populated? The population distribution shows that the project area is not densely populated.
Heavy with development activities?
Adjacent to or within any
environmentally sensitive areas?
No environmentally sensitive areas are located within the Project area
CULTURAL HERITAGE SITE
PROTECTED AREA
WETLAND
MANGROVE
ESTUARINE
BUFFER ZONE OF PROTECTED
AREA
SPECIAL AREA FOR PROTECTING
BIODIVERSITY
BAY
B. POTENTIAL ENVIRONMENTAL IMPACTS
Will the project cause…
Degradation of environment due to
clearing of area/ removal of vegetation
for cutting trenches.
No trees or shrub vegetation found in the pipeline trace. Already a disturbed area.
Pollution of raw water supply from
upstream wastewater discharge from
communities, industries, agriculture,
and soil erosion runoff?
Not applicable.
Impairment of historical/cultural
monuments/areas and loss/damage to
these sites?
Not applicable. There are no historical/cultural monuments/areas within or adjacent to subproject sites.
16
Screening questions Yes No Remarks
Hazard of land subsidence caused by
excessive ground water pumping?
Not applicable.
Social conflicts arising from
displacement of communities?
No displacements required. Subproject sites are within ROWs of public roads
Conflicts in abstraction of raw water
for water supply with other beneficial
water uses for surface and ground
waters?
Water from tube wells will be extracted below the safe extraction level as recommended by Water Resource Board(WRB) so that no conflict will arise with other beneficiaries using ground water in the surrounding area.
Unsatisfactory raw water supply (e.g.
excessive pathogens or mineral
constituents)?
Raw water is purified in a package plant where Fe and Mn will be removed and chlorination is done
Delivery of unsafe water to distribution
system?
The distributed water will be treated and ensured to comply with the National Drinking Water Quality Standards.
Inadequate protection of intake works
or wells, leading to pollution of water
supply?
Not applicable. Well-protected water sump has been established.
Over pumping of ground water,
leading to salinization and ground
subsidence?
Not applicable.
Excessive algal growth in storage
reservoir?
The water is chlorinated and there is no chance for algal growth
Increase in production of sewage
beyond capabilities of community
facilities?
Not anticipated. Community is having good sanitation facilities.
Disposal of sludge from water
treatment plants?
Sludge will be removed as specified in the EMP.
Inadequate buffer zone around
pumping and treatment plants to
alleviate noise and other possible
nuisances and protect facilities?
Residences are located away from the WTP.
Impairments associated with
transmission lines and access roads?
Not applicable.
Health hazards arising from
inadequate design of facilities for
receiving, storing, and handling of
chlorine and other hazardous
chemicals.
Well-designed office and warehouse have been built at the site of WTP.
Health and safety hazards to workers
from handling and management of
chlorine used for disinfection, other
contaminants, and biological and
physical hazards during project
construction and operation?
Well protected hazard management measures are in place at the WTP
17
Screening questions Yes No Remarks
Dislocation or involuntary resettlement
of people?
No involuntary resettlement impacts envisioned. Lands for the subproject are government-owned
Disproportionate impacts on the poor,
women and children, indigenous
peoples or other vulnerable groups?
Not anticipated. The contractor will be encouraged to hire local workers from the local labor force.
Noise and dust from construction
activities?
Anticipated during construction activities. Temporary increase in noise level and dusts may be caused by excavation equipment, and the transportation of equipment, materials, and people. The impacts are negative but short-term and site-specific within a relatively small area. They are also reversible through mitigation measures. Good construction practices will mitigate noise and dust, and will be specified in the EMP.
Increased road traffic due to
interference of construction activities?
Traffic management measures will be adopted along the construction sites with proper signage and traffic plans.
Continuing soil erosion/silt runoff from
construction operations?
Due to excavation and run-off from stockpiled materials. The impacts are negative but short-term and site-specific and reversible through mitigation measures. Good construction practices will mitigate soil erosion and silt runoff and will be specified in the EMP.
Delivery of unsafe water due to poor
O&M treatment processes (especially
mud accumulations in filters) and
inadequate chlorination due to lack of
adequate monitoring of chlorine
residuals in distribution systems?
Back wash operations will be adopted for every 24 hours and mud and other impurities will be removed from the sedimentation and filtration beds. Good operational and maintenance practices will minimize pollutants discharged and will be specified in the EMP.
Delivery of water to distribution
system, which is corrosive due to
inadequate attention to feeding of
corrective chemicals?
The project will include development of O&M manuals to ensure facilities are kept in working condition, including checking and maintenance of distribution network. Any distributed water must comply with the National Drinking Water Quality Standards.
Accidental leakage of chlorine gas? Not applicable as protective measures have been implemented at IWTP
Excessive abstraction of water
affecting downstream water users?
Not applicable.
Competing uses of water?
Increased sewage flow due to
increased water supply
Not applicable. Households have adequate sanitation facilities
Increased volume of sewage
(wastewater from cooking and
washing) and sludge from wastewater
treatment plant
18
Screening questions Yes No Remarks
Large population influx during project
construction and operation that causes
increased burden on social
infrastructure and services (such as
water supply and sanitation systems)?
Improved management systems through capacity building and institutional development will ensure reduced burden on services and infrastructure.
Social conflicts if workers from other
regions or countries are hired?
Priority in employment will be given to local residents.
Risks to community health and safety
due to the transport, storage, and use
and/or disposal of materials such as
explosives, fuel and other chemicals
during operation and construction?
Not applicable. Construction will not involve use of explosives and chemicals during the construction phase.
Community safety risks due to both
accidental and natural hazards,
especially where the structural
elements or components of the project
are accessible to members of the
affected community or where their
failure could result in injury to the
community throughout project
construction, operation and
decommissioning?
Work areas will be clearly demarcated with signage and safety barriers, and access will be controlled. Only workers and project concerned members will be allowed to visit the operational sites.
Impacts to occupational health and
safety due to the excavation of rocks
during cutting trenches.
When cutting trenches and rock excavation are carried out ,PPEs will be worn and mitigations will be taken as specified in EMP.
Impacts to community health and
safety due to the transport of
construction material.
Safety measures where required shall be taken.
Occupational and Community health
and safety risk.
When considering the scope of work, magnitude of construction activities health and safety risks are not very significant. However, PPEs will be required for some workers who works cutting trenches and construction of overhead tanks etc to avoid any accidents during the work.
Impacts to community safety caused
by construction waste and disposal of
wastes from site camps.
Construction waste generated should be disposed to a site approved by PS. Garbage bins should be provided at all times and they should be collected by the PS constantly.
19
APPENDIX 2:
Compliance with Sri Lanka Laws & Regulations and Basic Information of Project Site
LA :Naththandiya PS SPCU : North Western Province Subproject :Panagoda and Kruswatte Drinking Water Supply Project for Naththandiya
Prdeshiya Sabah.
Location :Panagoda and Kuruswatte
1. Compliance
The project is not located within 100 m from the boundaries of or within any area declared
under the National Heritage Wilderness Act no 4 of 1988.
The project is not located within 100 m from the boundaries of or within any area declared
under the Forest Ordinance (Chapter 451).
The project is not located within Coastal Zone as defined in the Coast Conservation Act No
57 of 1981.
The project is not located within any erodible area under the Soil Conservation Act
(Chapter 450).
The project is not located within flood prone areas declared underFlood Protection
Ordinance (Chapter 449).
The project is not located within low lying area of North Western Province which is a flood
protection area declared under the Sri Lanka Land Reclamation and Development
Corporation Act 15 of 1968 as amended by Act No 52 of 1982.
The project is not located within 60 meters from the bank of a public stream as defined in
the Crowns Lands Ordinance (Chapter 454) and having width of more than 25 meters at any
point of its course.
There are no reservations beyond the full supply level of a reservoir within the proposed
project area.
The project is not located within any archaeological reserve, ancient or protected
monument as defined or declared under the Antiquities Ordinance (Chapter 188).
The project is not located within any area declared under the Botanic Gardens Ordinance
(Chapter 446).
The project is not located within100 meters from the boundaries of, or within, any area
declared as a Sanctuary under the Fauna and Flora protection Ordinance (Chapter 454).
The project is not located within 100m from high flood level contour of a public lake as
defined by the Crown Land Ordinance (1947, 1949, and 1956) including those declared
under Section 71 of the ordinance.
The project is not located within 100m from the boundaries of or within any area declared
under the Forest Ordinance (Chapter 451)
The project is located within areas declared under the Urban Development Authority Act No.
41 of 1978 and Act No. 4 of 1982 Section 29.
2. Present ownership of the project site:
State Private Other – Specify
- - Naththandiya PS
20
3. Present land use:
Land Use type Land Use type
Paddy Marsh / Mangrove
Tea Scrub / Forest
Rubber Grassland / Chena
Coconut Built – up area √
Other plantations / Garden Other: Bare land
4. Does the site / Project require any:
Activity Yes No If yes give the extent
(in ha)
Reclamation of land, wetlands √
Clearing of forest √
Felling of trees √
5. Does the Project envisage any resettlement
Yes No If yes, give the number of the families to be resettled
√
6. Does the Project envisage laying of pipelines
Yes No If Yes, give the length of the pipeline (km)
√ Panangoda – 6.5km
Kuruswatte – 3.5km
7. Does the project involve any tunneling activities
Yes No
√
21
APPENDIX 2:
A Checklist for Preliminary Climate Risk Screening
Project Title :Local Government Enhancement Sector Project (Additional Financing)
Province :North-Western Province
Sub Project : Panagoda and Kruswatte Drinking Water Supply Project for Naththandiya Prdeshiya
Sabah.
District : Puttalam
Local Authority: Naththandiya Pradeshiya Sabha.
Screening Questions Score Rema
rks2
Location
and
Design of
project
Is siting and/or routing of the project (or its components) likely to be
affected by climate conditions including extreme weather related events
such as floods, droughts, storms, landslides?
0
Would the project design (e.g. the clearance for bridges) need to consider
any hydro-meteorological parameters (e.g., sea-level, peak river flow,
reliable water level, peak wind speed etc)?
0
Materials
and
Maintenan
ce
Would weather, current and likely future climate conditions (e.g. prevailing
humidity level, temperature contrast between hot summer days and cold
winter days, exposure to wind and humidity hydro-meteorological
parameters likely affect the selection of project inputs over the life of
project outputs (e.g. construction material)?
0
Would weather, current and likely future climate conditions, and related
extreme events likely affect the maintenance (scheduling and cost) of
project output(s)?
0
Performa
nce of
project
outputs
Would weather/climate conditions and related extreme events likely affect
the performance (e.g. annual power production) of project output(s) (e.g.
hydro-power generation facilities) throughout their design life time?
0
Options for answers and corresponding score are provided below:
Response Score
Not Likely 0
Likely 0
Very Likely 0
Responses when added that provide a score of 0 will be considered low risk project. If adding all responses will
result to a score of 1-4 and that no score of 2 was given to any single response, the project will be assigned a
medium risk category. A total score of 5 or more (which include providing a score of 1 in all responses) or a 2 in
any single response will be categorized as high risk project.
Result of Initial Screening (Low, Medium, High): Low
22
Appendix 3: Environmental Management Plan & Environmental Monitoring Plan
Environmental Management Plan Activity Environmental Issue Mitigation Measures Location Implementing
agency
Executing
Agency
1 Site Clearing before
starting construction.
1 Environment degradation
caused by cutting large
trees.
1 i)To avoid un –necessary tree
cutting by demarcating trees
exactly to be removed.
ii) To implement
compensatory tree planting
at 1:4 ratio.
As directed
by Engineer
Contractor Consultant/
client.
2 Site Clearing before
starting construction.
2 Environment pollution
caused by eroded soil during
rains after site clearing.
2 To provide soil conservation
bunds and maintained.
As directed
by Engineer
Contractor Consultant/
client.
3 Construction of structures
( overhead tank and
cutting trenches for pipe
laying)
3 Safety of workers at deep
excavation endangered by
embankment collapse
3 To provide embankment
protection as directed by the
Engineer.
As directed
by Engineer
Contractor Consultant/
client
4 Environment pollution
caused by material wash
away from excavated
stockpiles during rains
4 To protect material
stockpiles, wash away during
rains by covering/providing
conservation bunds or any
other arrangement
As directed
by Engineer
Contractor Consultant/
client
5 Hazardous mosquito
breeding caused by stagnant
water in excavated trenches
5 To remove stagnant water
regularly from trenches to
ensure mosquito breeding is
not taken place
As directed
by Engineer
Contractor Consultant/
client
6 Environment pollution
caused by waste water
removed from excavated
trenches.
6 To divert waste water
removed from trenches to a
drainage path with silt traps
As directed
by Engineer
Contractor Consultant/
client
23
Activity Environmental Issue Mitigation Measures Location Implementing
agency
Executing
Agency
by protecting downstream
environment
7 Public nuisance caused by
noise generation during
construction.
7 To provide adequate noise
barriers when and where
necessary.
As directed
by Engineer
Contractor Consultant/
client
8 Public safety endangered by
cutting trenches across
access roads.
8 To place a steel plate over
the trench for vehicles to
move and timber planks for
pedestrians where
necessary.
As directed
by Engineer
Contractor Consultant/
client
4 Rock excavation if any. 9 Health hazard of drillers and
others in the vicinity caused
by dust generation during
rock drilling/crushing
9 To provide dust control
arrangements while rock
drilling (wet gunny bags)
As directed
by Engineer
Contractor Consultant/
client
10 To provide dusk masks for
rock drillers and others in the
vicinity while
drilling/crushing
As directed
by Engineer
Contractor Consultant/
client
5 Rock blasting and
crushing in any.
10 Community and
occupational safety
endangered by insufficient
protective measures during
rock blasting
11 To arrange standard rock
blasting safety arrangements
including prior warning.
As directed
by Engineer
Contractor Consultant/
client
6 Burrowing, transporting,
placing aggregate
material (earth, gravel,
sand, metal, quarry dust
etc.)
11 Health hazard due to
windblown dust while
transporting dusty material
by uncovered trucks at dry
weather
12 To make sure that dusty
material is transported only
by covered trucks.
As directed
by Engineer
Contractor Consultant/
client
24
Activity Environmental Issue Mitigation Measures Location Implementing
agency
Executing
Agency
12 Community/occupational
health endangered by
windblown dust during
construction.
13 To provide regular water
spreading system or/and to
deploy sprinkler attached
water bowsers regularly
As directed
by Engineer
Contractor Consultant/
client
13 Public safety endangered by
material pieces thrown out
from overloaded moving
trucks.
14 To make sure that trucks are
not overloaded while
transporting material.
As directed
by Engineer
Contractor Consultant/
client
14 Public safety endangered by
usage of access roads
damaged due to heavy
vehicle movements
15 To reinstate access roads
regularly.
As directed
by Engineer
Contractor Consultant/
client
15 Hazardous mosquito
breeding caused by stagnant
water in burrow pits after
mining.
16 i) ) GSMB approval is
obtained for burrow pits and
burrowing material.
ii) To reinstate burrow pits as
per GSMB guidelines.
As directed
by Engineer
Contractor Consultant/
client
7 Pipe-laying, installation of
valves and hydrants,
pressure testing,
installation of service
connection and
reinstatement of trenches
16 Environment pollution by
leaving trimmed pipe scraps
at sites.
17 To collect and dispose
trimmed pipe scraps to LA
collecting Centre operated
by Naththandiya PS.
As directed
by Engineer
Contractor Consultant/
client
17 Public/occupational safety
endangered by unsafe
handling of lengthy/heavy
pipes and accessories while
laying and fixing
18 To employee trained and
experienced workers for
handling lengthy/heavy
items by taking adequate
care
As directed
by Engineer
Contractor Consultant/
client
25
Activity Environmental Issue Mitigation Measures Location Implementing
agency
Executing
Agency
8 Maintenance of storage
areas .
18 Environment pollution
caused by oil spills and
draining to surrounding
areas.
19 To avoid draining oil spills to
surrounding environment by
sealing leaked places or any
other means with regular
and close observation.
As directed
by Engineer
Contractor Consultant/
client
19 Polluting surrounding
environment by material
stockpiles (at open storage)
wash away during rains.
20 To protect washable material
stockpiles (at open storage)
by covering them during
rainy season and /or
providing conservation
bunds.
As directed
by Engineer
Contractor Consultant/
client
9 Occupational and public
health and safety during
construction/ excavation
of trenches.
20 Occupational health
endangered by insufficient
sanitary facilities provided
at office/camps
21 To provide adequate sanitary
facilities to office/camps and
regularly monitor the quality
and adequacy
As directed
by Engineer
Contractor Consultant/
client
21 Occupational safety
endangered by project
activities without
implementing safety
management plan
22 To prepare and implement
engineer approved safety
management plan to ensure
employees wear standard
PPEs.
As directed
by Engineer
Contractor Consultant/
client
22 Public safety endangered by
project activities without
implementing a proper
Traffic Management Plan.
23 To prepare and implement
engineer approved traffic
management plan where
safety measure to be taken
have been well described.
As directed
by Engineer
Contractor Consultant/
client
10 Construction waste
disposal
23 Occupational/public health
and safety endangered by
scattered construction
waste at sites and public
areas.
24 i) to dispose construction
waste into a site approved by
LA.
or
As directed
by Engineer
Contractor Consultant/
client
26
Activity Environmental Issue Mitigation Measures Location Implementing
agency
Executing
Agency
ii) to disposed to a site
operated by LA with the
consent of the LA.
11 Office/camp waste
disposal
24 Surrounding environment of
office/camp is polluted by
scattered garbage/waste.
25 To provide office/camp
waste disposal arrangements
(garbage bins) and maintain
within the premises and
regularly hand over
separated waste to LA
garbage collecting rucks.
As directed
by Engineer
Contractor Consultant/
client
Operational and Maintenance Phase
12 Over abstraction of raw
water for water supply.
25 Conflicts with other
beneficial water uses of
ground waters.
26 Ground water will be
extracted as per guidelines
and conditions imposed by
Water Resource Board.
(WRB)
Tube wells
/Panangona
and
Kruswatte
Naththandiya
Pradeshiya
Sabah.
Ministry of
Provincial and
Local
Government.
13 Generation of Sludge and
impurities.
26 Environment pollution
endangered by
sludge/impurities
generated.
27 Sludge generated will be
managed and disposed as
per the Guidelines given by
the Provincial Environmental
Authority (NWP).
Site /Package
Plant /
Kruswatte .
Naththandiya
Pradeshiya
Sabah.
Ministry of
Provincial and
Local
Government.
27
Environmental Monitoring Plan (EMoP)
Activity Environmental Issue Mitigation
Measures
Monitoring
Parameter
Monitoring
Methods
Location Implementin
g agency
Executing
Agency
1 Site clearing
before starting
construction.
1 Environment
degradation caused by
cutting large trees
(Removal of greenery)
1 To avoid un-necessary tree cutting by demarcating trees exactly to be removed.
Trees exactly to be removed are demarcated
Physical
observation/Photo
graphs
As
directed
by
Engineer
Contractor Consultan
t/ client
2 To implement tree re-planting program.
(i)Suitable land is selected.
(ii)Tree planting
implemented (1: 4
rate)
Physical
observation/Photo
graphs
As
directed
by
Engineer
Contractor Consultan
t/ client
2 Site clearing
before starting
construction.
2 Environment pollution
caused by eroded soil
during rains after site
clearing.
3 To provide soil
conservation
bunds and
maintain.
Well maintained soil
conservation bunds.
Physical
observation/Photo
graphs
As
directed
by
Engineer
Contractor Consultan
t/ client
3 Construction of
structures (
overhead tank,
package plant and
cutting trenches
for pipe laying
3 Safety of workers at
deep excavation
endangered by
embankment collapse
4 To provide
embankment
protection as
directed by
Engineer.
Areas where
embankment
protection done.
Physical
observation/Photo
graphs
As
directed
by
Engineer
Contractor Consultan
t/ client
4 Environment pollution
caused by material
wash away from
excavated stockpiles
during rains.
5 To provide soil
conservation
bunds and
maintain.
Areas where
conservation bunds
set up.
Physical
observation/Photo
graphs
As
directed
by
Engineer
Contractor Consultan
t/ client
28
Activity Environmental Issue Mitigation
Measures
Monitoring
Parameter
Monitoring
Methods
Location Implementin
g agency
Executing
Agency
5 Hazardous mosquito
breeding caused by
stagnant water in
excavated trenches
6 To remove
stagnant water
regularly and
ensure no
mosquito
breeding taken
place.
i)Area without
stagnant water.
Physical
observation/Photo
graphs
As
directed
by
Engineer
Contractor Consultan
t/ client
6 Environment pollution
caused by waste water
removed from
excavated trenches.
7 To divert waste
water removed
from trenches
to a drainage
path with silt
traps by
protecting
downstream
environment
Silt Traps and Public
complaints on waste
water discharge.
Physical
observation/Photo
graphs
As
directed
by
Engineer
Contractor Consultan
t/ client
7 Public safety
endangered by cutting
trenches across access
roads.
8 To place a steel
plate over the
trench for
vehicles to
move and for
pedestrians.
Crossing points
where facilities
provided for vehicle
movement and
pedestrians to move.
Physical
observation/Photo
graphs
As
directed
by
Engineer
Contractor Consultan
t/ client
8 Public nuisance caused
by noise generation
during construction
9 To provide
adequate noise
barriers when
and where
necessary
Adequate temporary
noise barriers are
provided as required.
Physical
observation/Photo
graphs
As
directed
by
Engineer
Contractor Consultan
t/ client
4 Rock excavation, if
any
9 Health hazard of
drillers and others in
the vicinity caused by
dust generation during
rock drilling/crushing
10 To provide dust
control
arrangements
while rock
i) Use of wet gunny
bags.
ii) Dust deposition on
the surrounding.
Physical
observation/Photo
graphs
As
directed
by
Engineer
Contractor Consultan
t/ client
29
Activity Environmental Issue Mitigation
Measures
Monitoring
Parameter
Monitoring
Methods
Location Implementin
g agency
Executing
Agency
drilling (wet
gunny bags)
11 To provide dusk
masks for rock
drillers and
others in the
vicinity while
drilling/crushing
i) Use of standard
dusk masks and
other relevant PPEs .
Physical
observation/Photo
graphs
As
directed
by
Engineer
Contractor Consultan
t/ client
5 Rock blasting and
crushing, if any
1
0
Community and
occupational safety
endangered by
insufficient protective
measures during rock
blasting
12 To arrange
standard rock
blasting safety
arrangements
including prior
warning.
Standard rock
blasting safety
arrangements are
provided including
prior warning.
Physical
observation/Photo
graphs
As
directed
by
Engineer
Contractor Consultan
t/ client
6 Burrowing,
transporting,
placing aggregate
material (earth,
gravel, sand,
metal, quarry dust
etc.)
1
1
Health hazard due to
windblown dust while
transporting dusty
material by uncovered
trucks at dry weather
13 To make sure
that dusty
material is
transported
only by covered
trucks.
Dusty material is
transported only by
covered trucks.
Physical
observation/Photo
graphs
As
directed
by
Engineer
Contractor Consultan
t/ client
1
2
Community/occupatio
nal health endangered
by windblown dust
during construction
14 To provide
regular water
spreading
system or/and
to deploy
sprinkler
attached water
bowsers
regularly
i)Water spreading
system or/and
sprinkler attached
water bowser use is
regularly being
carried out regularly
and to provide dust
masks for workers
ii) Construction
material dust/ dust
Physical
observation/Photo
graphs
As
directed
by
Engineer
Contractor Consultan
t/ client
30
Activity Environmental Issue Mitigation
Measures
Monitoring
Parameter
Monitoring
Methods
Location Implementin
g agency
Executing
Agency
from excavated soil
is not deposited over
the surrounding area.
1
3
Public safety
endangered by
material pieces thrown
out from overloaded
moving trucks.
15 To make sure
that trucks are
not overloaded
while
transporting
material
Trucks are not
overloaded while
material is
transported.
Physical
observation/Photo
graphs
As
directed
by
Engineer
Contractor Consultan
t/ client
1
4
Public safety
endangered by usage
of access roads
damaged due to heavy
vehicle movements.
16 To reinstate
access roads
regularly.
Access roads are
regularly reinstated.
Physical
observation/Photo
graphs
As
directed
by
Engineer
Contractor Consultan
t/ client
1
5
Hazardous mosquito
breeding caused by
stagnant water in
burrow pits after
mining.
17 To reinstate
burrow pits as
per GSMB
guidelines if
contractor
operates the
burrow pit.
i) GSMB approval is
obtained for burrow
pits and burrowing
material.
ii) Burrow pits are
reinstated as per
GSMB guidelines.
Documents/Physic
al observation/
/Photographs
As
directed
by
Engineer
Contractor Consultan
t/ client
31
Activity Environmental Issue Mitigation
Measures
Monitoring
Parameter
Monitoring
Methods
Location Implementin
g agency
Executing
Agency
7 Pipe-laying,
installation of
valves and
hydrants, pressure
testing,
installation of
service connection
and reinstatement
of trenches
1
5
Public/occupational
safety endangered by
unsafe handling of
lengthy/heavy
materials
18 To employee
trained and
experienced
workers for
handling
lengthy/heavy
items by taking
adequate care
No accidents
reported.
Physical
observation
As
directed
by
Engineer
Contractor Consultan
t/ client
1
6
Environment pollution
by leaving trimmed
pipe scraps at sites
19 To collect and
dispose
trimmed pipe
scraps to LA
collecting
Centre.
( Naththandiya)
No pipe scarps left in
the site.
Physical
observation / LA
consent letter.
As
directed
by
Engineer
Contractor Consultan
t/ client
8 Maintenance of
storage areas
1
7
Environment pollution
caused by oil spills and
draining to
surrounding areas.
20 To avoid
draining oil spills
to surrounding
environment by
sealing leaked
places or any
other means
with regular and
close
observation.
) Lubricant leaking
places are sealed,
and adequate
measures have been
taken to protect
draining lubricant to
the environment
(containers are
provided to collect
leaking oils until
repair)
Physical
observation.
As
directed
by
Engineer
Contractor Consultan
t/ client
32
Activity Environmental Issue Mitigation
Measures
Monitoring
Parameter
Monitoring
Methods
Location Implementin
g agency
Executing
Agency
1
8
Polluting surrounding
environment by
material stockpiles (at
open storage) wash
away during rains.
21 To protect
washable
material
stockpiles (at
open storage)
by covering
them during
rainy season
and /or
providing
conservation
bunds.
Washable material
stockpiles (at open
storage) are covered
to protect them
during rainy season.
Physical
observation
As
directed
by
Engineer
Contractor Consultan
t/ client
9 Occupational and
public health and
safety during
construction
1
9
Occupational health
endangered by
insufficient sanitary
facilities provided at
office/camps
22 To provide
adequate
sanitary
facilities to
office/camps
and regularly
monitor the
quality and
adequacy
Sanitary facilities are
provided for
office/camps and
maintained quality
and adequacy
Physical
observation
As
directed
by
Engineer
Contractor Consultan
t/ client
2
0
Occupational safety
endangered by project
activities without
implementing safety
management plan
23 To prepare and
implement
engineer
approved safety
management
plan to ensure
employees wear
standard PPEs.
i)Engineer approved
safety management
plan is available
ii)Standard PPEs (in
correct size) are
provided for all
employees
iii)Ensured all
workers are fully
equipped with PPEs
Physical
observation
As
directed
by
Engineer
Contractor Consultan
t/ client
33
Activity Environmental Issue Mitigation
Measures
Monitoring
Parameter
Monitoring
Methods
Location Implementin
g agency
Executing
Agency
while performing
duties
iv)Occupational and
community safety is
ensured by providing
warning boards,
barricades, luminous
stickers, night
warning lamps, safe
by-pass access roads
etc., as per approved
safety management
plan and maintained
the quality and
adequacy
2
1
Public safety
endangered by project
activities without
implementing traffic
management plan
24 To prepare and
implement
engineer
approved traffic
management
plan to ensure
public safety
Warning boards,
barricades, luminous
stickers, night
warning lamps, safe
by-pass access roads
etc., as per approved
traffic management
plan and maintained
the quality and
adequacy
Physical
observation
As
directed
by
Engineer
Contractor Consultan
t/ client
34
Activity Environmental Issue Mitigation
Measures
Monitoring
Parameter
Monitoring
Methods
Location Implementin
g agency
Executing
Agency
1
0
Construction
waste disposal
2
2
Occupational/public
health and safety
endangered by
scattered construction
waste at sites, yards,
and public areas.
25 To dispose
construction
waste in to a
approved
disposal site.
i) Construction waste
is disposed to
approved disposal
yards and reinstated
regularly.
ii)Ensured
construction waste is
not disposed to
unauthorized
locations whatsoever
Physical
observation
As
directed
by
Engineer
Contractor Consultan
t/ client
1
1
Office/camp waste
disposal
2
3
Surrounding
environment of
office/camp is polluted
by scattered waste
26 To provide
office/camp
waste collecting
and disposal
arrangements
and maintain
regularly.
i)Office/camp waste
collecting facilities
are adequately
provided and
regularly disposed
ii)Ensured
office/camp waste is
not scattered around
office/camp premises
and not disposed to
unauthorized
locations
Physical
observation
As
directed
by
Engineer
Contractor Consultan
t/ client
Operation/ Maintenance Phase
1
2
Over abstraction
of raw water for
water supply.
2
4
Conflicts with other
beneficial water uses
of ground waters.
27 Ground water
will be extracted
as per
guidelines and
conditions
Safe yield of ground
water extraction
recommended by
WRB.
Documents/
physical
observation.
Surround
ing dug
wells.
Naththandiya
Pradeshiya
Sabah
Ministry
of
Provincial
Council
and Local
35
Activity Environmental Issue Mitigation
Measures
Monitoring
Parameter
Monitoring
Methods
Location Implementin
g agency
Executing
Agency
imposed by
Water Resource
Board.
(WRB)
Governme
nt
1
3
Generation of
Sludge and
impurities.
2
5
Environment pollution
endangered by
sludge/impurities
generated.
28 Sludge generated
will be managed
and disposed as
per the Guidelines
given by the
Provincial
Environmental
Authority ( NWP)
i)Guidelines of
Provincial
Environmental
Authority(NWP)
ii) Sludge removed
not disposed to an un
authorized site.
i)Documents
ii)Physical
observation
Package
Plant
/Kuruswat
te.
Naththandiya
Pradeshiya
Sabah
Ministry of
Provincial
Council and
Local
Governme
nt.
35
Appendix 4- Water Quality Report – Kuruswatte , Mailawa
36
Appendix 4- Water Quality Report – Panangoda