environmental safeguards due diligence report...wss was done using hydraulic modelling software of...

43
Environmental Safeguards Due Diligence Report Project Number 42459-014 August 2019 Sri Lanka: Local Government Enhancement Sector Project Additional Financing (LGESP-AF) ̶ Construction of Panagoda & Kruswatte Drinking Water Supply Scheme for Naththandiya Pradeshiya Sabha (NWP-AF-NAT-06) Prepared by LGESP (Pura Neguma) Project Management Unit for the Ministry of Internal & Home Affairs and Provincial Councils & Local Government (Formerly named as “Ministry of Provincial Councils, and Local Government and Sports”), Colombo, Sri Lanka and the Asian Development Bank. This environmental safeguards due diligence report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgements as to the legal or other status of any territory or area.

Upload: others

Post on 24-Mar-2021

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Environmental Safeguards Due Diligence Report...WSS was done using hydraulic modelling software of ‘EPANET’. 10. The numbers of beneficiary households in every area have been determined

Environmental Safeguards Due Diligence Report Project Number 42459-014 August 2019

Sri Lanka: Local Government Enhancement Sector

Project Additional Financing (LGESP-AF)

Construction of Panagoda & Kruswatte Drinking

Water Supply Scheme for Naththandiya

Pradeshiya Sabha

(NWP-AF-NAT-06)

Prepared by LGESP (Pura Neguma) Project Management Unit for the Ministry of Internal &

Home Affairs and Provincial Councils & Local Government (Formerly named as “Ministry of Provincial Councils, and Local Government and Sports”), Colombo, Sri Lanka and the Asian

Development Bank.

This environmental safeguards due diligence report is a document of the borrower. The views

expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature.

In preparing any country program or strategy, financing any project, or by making any

designation of or reference to a particular territory or geographic area in this document, the

Asian Development Bank does not intend to make any judgements as to the legal or other

status of any territory or area.

Page 2: Environmental Safeguards Due Diligence Report...WSS was done using hydraulic modelling software of ‘EPANET’. 10. The numbers of beneficiary households in every area have been determined

0

Ministry of Provincial Councils and Local Government

Local Government Enhancement Sector Project (Additional

Financing)

(ADB assisted – Loan 3431 SRI)

DUE DILIGENCE REPORT - ENVIRONMENT

PACKAGE NUMBER – NWP AF NAT 06

ADDITIONAL FINANCING OF LOCAL GOVERNMENT

ENHANCEMENT SECTOR PROJECT: PANANGODA AND

KURUSWATTE DRINKING WATER SUPPLY PROJECT FOR

NATHTHANDIYA PRADESHIYA SABHA

NORTH WESTERN PROVINCE, SRI LANKA

July 2019

Prepared for Local Government Enhancement Sector Project (Additional Finance)

Subproject Coordination Unit - North Western Province

Page 3: Environmental Safeguards Due Diligence Report...WSS was done using hydraulic modelling software of ‘EPANET’. 10. The numbers of beneficiary households in every area have been determined

1

Table of Contents

I. INTRODUCTION 2

A. Background ................................................................................................................ 2

B. Objective of the Subproject ......................................................................................... 3

C. Categorization and Justification .............................................................................. 4

II. PROJECT DESCRIPTION 4

A. Present Location and Environmental Status ............................................................... 4

B. Proposed Work ........................................................................................................... 5

III. POSSIBLE IMPACTS& MITIGATION…………………………………………………. 7

IV. Grievance Redress Mechanism……………………………………………………………...9

V. Environment Management Plan (EMP) and Environmental Monitoring Plan(EMoP)…………………………………………………………………………………………13

VI Conclusion and Recommendation……………………………………………………..13

List of Appendices

Appendix 1- Maps, Plans & Pictures showing existing sites & Construction related

supplementary drawings ………………………………………………………..…..…… 14

Appendix 2- Rapid Environmental Assessment (REA) -Water Supply…………………..15

Appendix 3- Environmental Management Plan & Environmental Monitoring Plan. ……22

Appendix 4- Water Quality Reports of Kuruswatte and Panangoda tube wells…………36

Page 4: Environmental Safeguards Due Diligence Report...WSS was done using hydraulic modelling software of ‘EPANET’. 10. The numbers of beneficiary households in every area have been determined

2

I. INTRODUCTION

Background

1. The Local Government Enhancement Sector Project (LGESP) was approved by ADB

on 29 September 2012 with an amount of $59 million equivalent from ADB’s Special Fund Resources. The loan became effective on 29 November 2011 and the loan closing date is 31

December 2016. Ministry of Provincial Council and Local Government (MPCLG) is the

executing agency, and subproject coordination unit (SPCU) is established in each provincial

council (total seven) to supervise and coordinate and project implementation. LGESP has

been supporting local infrastructure improvement and basic service delivery in less-developed

areas in seven provinces (excluding the Northern and Eastern Provinces), based on a bottom-

up, demand-driven approach. The additional financing is required to scale up a well-

performing project. It includes (i) improvement of water supply systems in areas affected by

chronic kidney diseases (CKD); (ii) improvement of local infrastructure and basic services

delivery; and (iii) advancing policy reform of local government and strengthening their capacity.

2. Naththandiya PS which was established in 1988 is situated in the Puttalam District in

the North Western Province of Sri Lanka. It is located East of Puttalam in Puttalam District of

North West Province and about 80 km away north east from Colombo (via Colombo Kandy

HW) and 20km away from provincial capital Kurunegala. The PS consists of 94 GN divisions,

has a population of 71,693 and is of an area of 71.94 sq.km.

3. This subproject area is primarily an agricultural area and safe drinking water is in short

supply. The drinking water requirement of the community is fulfilled through various means

and sources. Safe drinking water has been identified as a priority need of the people in the

area through public consultation meetings.

4. A community consultation meeting was held at the community hall at Mailawa in 2016

to discuss the projects to be implemented through ‘PuraNeguma’ programme. Secretary, officers of the PS, officers of the PuraNeguma and the general public attended this meeting.

The consent of the majority of those presents at the meeting has been given for balance

improvements of this sub project. As the availability of funds has considered the possibility of

carrying out both identified improvements which is also a priority request, then decided to

undertake a water supply scheme for the village of Mailawa, Kruswatte and Panangoda area.

The two projects proposed Mailawa, Kruswatte and Panangoda will be maintained by PS after

completion.

5. This due diligence report is prepared as the sub project selection was based on the

community consultation and participation criteria .Panangoda and Mailawa, Kuruswatte water

improvement project was selected as a priority sub project to be financed with the LGESP

funded by Asian Development Bank.

6. The Panangoda Kuruswatte water supply sub project will be implemented in the

Panangoda and Mailawa GN divisions of the Mahawewa and Naththandiya Divisional

Secretariats respectively. The people living there use well water for drinking and other

Page 5: Environmental Safeguards Due Diligence Report...WSS was done using hydraulic modelling software of ‘EPANET’. 10. The numbers of beneficiary households in every area have been determined

3

domestic purposes and there is severe shortage water particularly in the dry period (June to

October) during which times the quality becomes inferior. There is no drinking water supply

system provided to this community who are to be served by the subproject.

7. Through a consultation and participation process carried out with the community and

the other stake holders, and based on the sub project selection criteria, priority order of the

requirements of the public and the financial capacity of the PS to carry out the operation and

maintenance of the asset to be created by the funding, construction of a water supply project

in Panangoda and Kuruswatte to provide a better and efficient service to the community was

recommended for funding.

8. Adding more convenience for the people in the area, fulfilment of clean and safe

drinking water, supply of water continuously for the people living in the area are expected as

benefits through this water supply project.

9. The proposed scheme for Kuruswatte is expected to include the existing tube well, an

overhead water tank, filter house, and package plant and chlorination system for Kuruswatte

in PS owned land and transmission line and distribution network. For Panangoda it is

expected to include the existing tube well, an overhead tank and chlorination system in PS

owned land and transmission line and distribution network. Analyse of distribution network of

WSS was done using hydraulic modelling software of ‘EPANET’.

10. The numbers of beneficiary households in every area have been determined. Water

source is available to suit the requirements of the people and PS, giving due consideration to

the reliability and long term operating and maintaining capability of the organization that is

going to operate the scheme. Distribution network of the water supply scheme consists of pipe

lines of diameters 110, 90 and 63 mm. Total length of pipe lines in the network is about 6.5

km for Panangoda and 3.5 km for Kuruswatte. Initially, water will be issued to 196 families for

Panangoda and 75 families for Kuruswatte. Total Cost Estimate is Rs.33.10 Mn.

Objective of the Subproject

11. The objective this sub project is to supply clean and safe drinking water to people in the

Panangoda , Mailawa GN divisions of the Mahawewa and Naththandiya Divisional

Secretariats respectively, who use well water for drinking and other domestic purposes by

constructing an overhead water tank, filter house, package plant , transmission line and

distribution network in Kuruswatte and overhead tank ,transmission line and distribution

network in Panangoda ..

Page 6: Environmental Safeguards Due Diligence Report...WSS was done using hydraulic modelling software of ‘EPANET’. 10. The numbers of beneficiary households in every area have been determined

4

Categorization and Justification

12 Based on results of the Rapid Environmental Assessment ( Appendix 2), ADB SPS 2009,

and EARF the subproject is classified as environmental category C, i.e the subproject is

judged to be unlikely to have adverse environmental impacts but would have some

construction related impacts which could be mitigated/minimized to acceptable level by

adopting mitigation measures. DDR Environment report is prepared accordingly.

II. PROJECT DESCRIPTION

Present Location and Environmental Status

13. The Panangoda drinking water supply scheme’s tube well is located at 7°27'06.9"N

79°54'33.0"E and its overhead tank is located at 7°27'05.3"N and 79°54'29.2"E .Mailawa,

Kuruswatte drinking water supply scheme’s tube well is located at 7°25'12.6"N 79°52'56.9"E

and its overhead tank is located at 7°24'53.6"N 79°52'58.8"E.

14. Naththandiya PS is situated in the Puttalam District in the North Western Province of

Sri Lanka. The PS consists of 94 GN divisions, has a population of 71,693 and is of an area

of 71.94 sq.km. The elevation of the PS is 36 m from MSL.It is located about 80 km away north

east from Colombo (via Colombo Kandy HW) and 20 km away from provincial capital

Kurunegala. The boundaries of the PS are Chilaw PS from North, Indian Ocean from West,

Wennappuwa PS from South and Kurunegala District from East.

15. Naththandiya PS is a fast developing city in the North Western Province, Sri Lanka

with a well-connected road and railway network. It is situated between Puttalam and Chilaw

(in the A3 Puttalam to Peliyagoda road) town. It is one of the most populated residential parts

of the division with over 70,000 people including all religions - Buddhist, Hindu, Muslims,

Christian, living together with prosperity and harmony.

16. The main economic activity of the area is agriculture with coconut being the main

cultivations. Majority of the community depends on agriculture as their livelihood, where most

of them are engaged in paddy cultivation.

17. The proposed site for the Panangoda drinking water supply scheme is located in the

Panangoda GN division of Mahawewa DS division. The proposed land is owned by the

Pradeshoya Sabah, Naththandiya . Existing tube well (water extraction point) and overhead

tank are situated in the same land at about 130m distance apart. The proposed sites for

Mailawa, Kuruswatte scheme is also owned by the Pradeshiya Sabah, Naththandiya. Tube

well of Kuruswatte drinking water supply scheme is located in about 02 perch land while its

overhead tank will be constructed in a separate land with an area of 30 perches which is

located at about ½ km away.

18. Naththandiya falls within the low country intermediate zone, with an average annual

rainfall between 1750 - 2500 mm. The rainfall to the area is experienced in two folds. It is

around 155 mm in the months of April, May, June, October and November and reduces to

around 44 mm in the other months of the year. The rainfall is mainly affected by North East

Page 7: Environmental Safeguards Due Diligence Report...WSS was done using hydraulic modelling software of ‘EPANET’. 10. The numbers of beneficiary households in every area have been determined

5

and South West Monsoonal rains and inter monsoonal rains. The region receives an annual

average precipitation of 2064.5mm (2015). However, significant deviations in the rainfall

pattern had not been observed. The average annual temperature in the region is hot as 28.1 0C (2015). Major deviations had not been observed for the past 5 years.

19. A significant percentage of the soil in the area is a sandy soil. In addition, low humicgley

soil, Regosols on old red and yellow sand, Red Yellow Podzolic soils with soft and hard laterite

are also present.The terrain could be categorized mainly into three types, rolling, undulating

and flat. Water streams, rivers and even tributaries could be observed.

20. There are no environmentally sensitive areas such as reserved forests, protected water bodies or water channels within or in the vicinity of the project implementation area. The subproject site is not adjacent or within the area of close proximity to any environmentally protected area Eg. (i) area administered by the Department of Wild Life Conservation, (ii) Department of Coast Conservation & Coastal Resources Management, Department of Forests, (iii) the area declared as low lying and flood protection under the SLLRDC Act, and (iv) No archeologically protected monument is located in close proximity. There are areas like home gardens, paddy fields, small irrigation canals and natural water ways to receive surface drainage generated from rains. 21. The existing legislation and standards applicable for the designing projects in Sri Lanka

are mainly based on the National Environmental Act (NEA). According to the provisions under

the NEA No 47 of 1980 and the regulation on EIA which has been gazetted in 1993, this sub

project does not require an EIA or IEE prior to implementation of the sub project. As per ADB

SPS 2009 and EARF of the project, Rapid Environmental Assessment (REA) was carried out

to identify environment issues. This project is a water supply project and related environmental

impacts have been identified through this process. Accordingly developed EMP and EMoP

are shown in Appendix 3.

22. All quarry operations and mining operations connected with the project will require a valid

license issued by the Geological Survey and Mines Bureau (GSMB). All the effluents and/or

emissions shall be in compliance with the standards recommended by the National

Environmental Act (NEA).

Proposed Work

23. The Panangoda drinking water supply scheme is located in the Panangoda GN division

of Mahawewa DS division. Mailawa, Kuruswatte drinking water scheme is located in the

Mailawa GN Division of the Naththandiya DS division. The source of water for the schemes

are from two existing tube wells located at Panangoda and Kuruswatte. The Google map and

the photos annexed as Appendix 1 herewith which clearly shows the details of the subproject

areas and drawings of the pipe lines.

24. In the proposed land of Panangoda where the pump control room and overhead tank

are to be built, a community building managed by Pradhashiya Sabah is available. The water

extraction point (existing tube well) is also located in this land about 200m away.

25. There are no environmentally sensitive areas located within or adjacent to project

areas. Mainly, the land areas surrounding the location are coconut plantations and residences.

Page 8: Environmental Safeguards Due Diligence Report...WSS was done using hydraulic modelling software of ‘EPANET’. 10. The numbers of beneficiary households in every area have been determined

6

Land of the Sub Project area is generally flat. There are no prominent towns within sub project

area except for Naththandiya town. Elevation of the sub project area is approximately 36

meters above Mean Sea Level. The water quality in the tube well of Kruswatte, Mailawa is

not within the level of drinking water quality standards and therefore a Package plant will be

introduced to treat the raw water to drinking water quality standards. Water quality of

Panagoda tube well is within the level of drinking water quality. Water quality reports are given

in Appendix 4.

26. Land where the overhead water tank of Kuruswatte scheme is to be built, is located

01km away from the existing tube well. Overhead tank will be built in the highest elevation in

the area. A few trees such as Ketakala ,Kenda and Margosa are available in this land.

Yatikalana Sri Dhamma Vijayaramaya is the only religious place located in the surrounding

area.

27. The details of the total works taken up under the subproject are given below in Table

01 below.

Table 01 - Attributes of the Sub-Project

Total available capacity for WSS

For Panangoda 80 m3 For Kuruswatte 30 m3 12 m height Ferro cement overhead tank capacity

For Panangoda 40 m3 For Kuruswatte 30 m3 Distribution system For Panangoda High Lift Pumps 2 nos (Centrifugal Pump)

Length of PVC pipe line - 160 m

Diameter- 90 mm

Pump Capacity- 134 l/min

Pumping Total Head- 62 m

For Kuruswatte High Lift Pumps 2 nos (Centrifugal Pump)

Length of PVC pipe line - 700 m

Diameter- 63 mm

Pump Capacity- 50 l/min

Pumping Total Head- 30 m

Low Lift Pumps 2 nos (Submersible Pump)

Rate: 55 l/min

Diameter:<140 mm

Pump head: 60 m

Pumping Total Head- 42 m

Recommended pump installed depth 52 m below GL uPVC /GI pipes laying

For Panangoda 6.50 km For Kuruswatte 3.50 km Delivery Pipe lines 110 dia.- 655 m

90 dia.- 525 m 63 dia.- 6850 m

Ownership Naththandiya PS

Page 9: Environmental Safeguards Due Diligence Report...WSS was done using hydraulic modelling software of ‘EPANET’. 10. The numbers of beneficiary households in every area have been determined

7

28. The technical design is done in close coordination with the safeguard team of SPCU and

Design and Supervision Consultants. The due diligence process was conducted for the

proposed water supply project accordingly Local Government Enhancement Sector Project

EARF and ADB SPS 2009. Upon project implementation, the Safeguards Specialist at PMU

and the Safeguards Manager at SPCU will undertake a review of this due diligence, prepare

a confirmation report documenting any modifications for this sub-project and submit to ADB;

and receive a “no objection” confirmation from ADB prior to start of construction.

29. All technical designs and provisions are in accordance to National Standards

(ICTAD/CIDA and BS specifications) and will be constructed in close coordination with

Safeguard Team of SPCU and Design and Supervision Consultants. Related supplementary

drawings have been added in Appendix 1.

30. The environmental due diligence process has been conducted for the proposed

construction of the water supply project. This report describes details of environmental

safeguards, potential impacts, mitigation methods and monitoring parameters etc.

Safeguards staff of the SPCU, DSC, PMU and PMC are involved in developing this

environmental due diligence report in order to obtain clearances and approval from ADB prior

to initiation of any construction activity.

III. POSSIBLE IMPACTS& MITIGATION

31. Environmental screening was carried out as a part of this environmental due diligence

exercise. Rapid Environmental Assessment (Appendix2) reveals that there are some

environmental impacts and mitigation is possible during construction time and issues are

possible with the preparation and execution of the Environmental Management Plan

Environmental Management Monitoring Plan attached in this DDR .

32. The main objectives of the Rapid Environmental Assessment and the due diligence

screening are to identify the direct and indirect impacts on the physical, biological and social

or cultural heritage environment. Under the component of human risk, community/

occupational health and safety associated with the proposed construction and operations of

the subproject, particularly issues related to accident prevention, dangerous working

conditions, environment pollution and soil/ground…etc. are identified.

33. However, in consideration to the neighboring areas and the population distribution,

findings of some anticipated impacts due to the subproject activities and their management

measures can be discussed as follows;

I. Land use – There are no natural forest patches or natural streams running across the

project area. The road section selected for pipe laying has different land uses mixed with

natural environment at different locations. Along this particular road section, one can

observe quite a lot of home gardens in different scale. Livestock farming is also a popular

livelihood in this area. However, the main economic activity of the area is agriculture

specially with coconut cultivations. Majority of the community depends on agriculture as

their livelihood, where most of them are engaged in paddy cultivation. Less than half the

Page 10: Environmental Safeguards Due Diligence Report...WSS was done using hydraulic modelling software of ‘EPANET’. 10. The numbers of beneficiary households in every area have been determined

8

agricultural work is in paddy cultivation and most others in agricultural employment are

involved in cultivation of fruit crops and vegetables.

II. Ambient Air Quality – Construction activities will involve movement of vehicles carrying

construction material…etc. This will result in limited fugitive emissions on site. Spraying

of water during construction will reduce the emissions of dust fall to a great extent.

However, proper coverage shall be provided at the boundary area of the subproject site

as an environmental and safety precautionary measure before commencing the

activities.

III. Ambient Noise levels and traffic – During the construction phase, the sources of noise

pollution will primarily be limited to use of machineries and movement of vehicles

transporting construction materials and equipment to the site.

IV. Movement of traffic– The additional increase in construction related vehicles is of

concern during peak traffic hours, particularly office hours, school opening and closing

times. Its advisable to consider road safety such peak traffic hours to make sure no

accidents.

V. Waste collection and disposal facility- A system of appropriate collection (of sorted

waste) and disposal of bio-degradable and non-biodegradable solid and liquid waste will

be implemented in the subproject site. As per contract, any unusable waste shall be

disposed by the contractor to a site selected and informed by the Engineer, but with prior

approval from the Employer. Solid waste produced by the work force should be properly

disposed in agreement with the PS. Solid waste and debris generated from construction

activities should not be disposed on the sides of the road or left after construction works

is complete. Locations of sites for disposal of such waste will be selected by the

contractor in consultation with the PS. Garbage bins should be provided at all times and

they should be collected by the PS constantly.

VI. Storage of materials – Due care and separate storage shall be arranged particularly for

storage of construction materials, tools and equipment, plumbing and electrical

items...etc.

VII. Health & Safety of workers- During land clearing and construction emission of dust is

inevitable. Contractor shall distribute dusk masks to all workers to ensure protection from

dust. Dispersion of dust would be curtailed by regular watering of working areas. In

addition personal protection equipment such as helmets, gumboots, hand gloves, safety

jackets and safety belts shall be geared up accordingly. Health & safety awareness will

be provided to contractor’s workers.

VIII. Demarcation of working area, prior planning for specific work area and

dissemination of information through signage - Signage will be placed at specific

locations, which will show type and period of work. Also, work area will be demarcated

before starting of the work.

Page 11: Environmental Safeguards Due Diligence Report...WSS was done using hydraulic modelling software of ‘EPANET’. 10. The numbers of beneficiary households in every area have been determined

9

IX. Co-ordination and co-operation - Considered necessary among the staff and workers

particularly on following aspects:

Since the work has been proposed to be carried out in a rural area the contractor

shall ensure that the regular day today functioning of the area are not affected

during the construction work.

The contractor shall execute the work with prior approval of the work sequence

from the engineer.

During execution of work, materials will not be stacked in common areas and

utmost care shall be taken by the contractor to avoid any inconvenience due to

improper stacking of materials. If for any unavoidable situation, the materials

have to be stacked for a short time, prior permission from engineer shall be

obtained.

IV .GRIEVANCE REDRESS MECHANISM 34. A project-specific grievance redress mechanism (GRM) has been established to

receive, evaluate, and facilitate the resolution of affected person’s concerns, complaints and grievances about the social and environmental performance of LGESP. The GRM of the

project has been prepared and accepted by ADB and disclosed in the project website. The

GRM chart providing information on receipt of complaints and levels of redressal is displayed

in all subproject sites, local authorities’ offices, SPCU offices and other important places. The SPCU records all grievances received and address them on priority. To date all grievances

are addressed at the stage of first tier.

35. The GRM aims to provide a time-bound and transparent mechanism to voice and

resolve social and environmental concerns linked to the project. The GRM is project-specific

and not intended to bypass the government’s own redress process; rather it is intended to address affected people's concerns and complaints promptly, making it readily accessible to

all segments of the affected people and is scaled to the risks and impacts of the project.

36. The PMU and SPCUs will make the public aware of the GRM through public

awareness campaigns. Grievances can be filed in writing using the Complaint Register and

Complaint Forms or by phone with any member of the PMU or SPCU. The contact details of

the respective SPCUs will serve as a main avenue for complaints and will be publicized

through display on notice boards outside their offices and at construction sites. The safeguard

documents made available to the public in an accessible version will include information on

the GRM and will be widely disseminated throughout the corridor by the safeguards officers

in the PMU and SPCUs.

37. First tier of GRM. The SPCU is the first tier of GRM which offers the fastest and most

accessible mechanism for resolution of grievances. The Safeguards Manager – Social and

Gender in the SPCU will be designated as the key officer for grievance redress. Resolution of

complaints will be done at the earliest. Investigation of grievances will involve site visits and

Page 12: Environmental Safeguards Due Diligence Report...WSS was done using hydraulic modelling software of ‘EPANET’. 10. The numbers of beneficiary households in every area have been determined

10

consultations with relevant parties (e.g., affected persons, contractors, traffic police, etc.). The

Community Development Officer of the local authority or in the absence of Community

Development Officer, any officer who is given the responsibility of this, would coordinate with

the safeguards and gender manager of SPCU in redressing the grievances. Grievances will

be documented and personal details (name, address, date of complaint, etc.) will be included

unless anonymity is requested. A tracking number will be assigned for each grievance,

including the following elements:

• Complaint Register and Complaint Forms (including the description of the

grievance) with an acknowledgement of receipt given to the complainant when

the complaint is registered;

• Grievance monitoring sheet with actions taken (investigation, corrective

measures); and

• Closure sheet (Result of Grievance Redressal), one copy of which will be

handed to the complainant after he/she has agreed to the resolution and

signed-off.

The updated register of grievances and complaints will be available to the public at the SPCU

office, construction sites, and other key public offices. Shall the grievance remain unresolved

it will be escalated to the second tier.

38. Second Tier of GRM. The Social Safeguards and Gender Manager of SPCU will

activate the second tier of GRM1 by referring the unresolved issue (with written

documentation), The Grievance Redress Committee (GRC) will be established before

commencement of site works. A hearing will be called with the GRC, if necessary, where the

affected person can present his and/or her concern or issues. The process will facilitate

resolution through mediation. This local GRC will meet as necessary when there are

grievances to be addressed. The local GRC will suggest corrective measures at the field level

and assign clear responsibilities for implementing its decision at the earliest. The contractor

will have observer status on GRC. If unsatisfied with the decision, the existence of the GRC

will not impede the complainant’s access to the Government’s judicial or administrative remedies.

39. The safeguards and gender manager of SPCUs will be responsible for processing and

placing all papers before the GRC, maintaining database of complaints, recording decisions,

issuing minutes of the meetings and monitoring to see that formal orders are issued and the

decisions carried out.

40. Third tier of GRM. In the event that a grievance cannot be resolved directly by the

SPCUs (first tier) or GRC (second tier), the affected person can seek redress through third tier

1 The GRC will consist of the following persons (i) Commissioner of Local Government of the Province as Chairman, (ii) Divisional Secretary of the area; (iii) Chairman of the respective pradeshiya sabha; (iv) representative of nongovernment organizations and/or community based organizations working in the area as nominated by CLG; (v) Member of clergy of pradeshiya saba area; (vi) Chairman of Samathamandal; (vii) GramaNiladhari of the area; (vii) Social Safeguard and gender Manager - as Member Secretary of the GRC. The functions of the local GRC are as follows: (i) resolve problems quickly and provide support to affected persons arising from various issues including environmental and social issues.

Page 13: Environmental Safeguards Due Diligence Report...WSS was done using hydraulic modelling software of ‘EPANET’. 10. The numbers of beneficiary households in every area have been determined

11

at the central level. The third tier - Central Grievance Redressal Committee consists of (i)

Project Director as Chairman; and (ii) Legal Officer of MPCLG as member and Social

Safeguard and Gender Officer of PMU as Member Secretary.

41. In case the grievance is not solved at this level, then the complainant can refer the

same to the court of law.

42. The detailed GRM is hosted in the project website. The graphical representation of the

GRM is given at Fig 1 below.

43. The safeguard monitoring reports will include the following aspects pertaining to

progress on grievances: (i) number of cases registered with the GRC, level of jurisdiction (first,

second and third tiers), number of hearings held, decisions made, and the status of pending

cases; and (ii) lists of cases in process and already decided upon may be prepared with details

such as name, ID with unique serial number, date of notice, date of application, date of

hearing, decisions, remarks, actions taken to resolve issues, and status of grievance (i.e.

open, closed, pending).

44. All costs involved in resolving the complaints (meetings, consultations, communication

and reporting and/or information dissemination) will be borne by the executing agency.

Page 14: Environmental Safeguards Due Diligence Report...WSS was done using hydraulic modelling software of ‘EPANET’. 10. The numbers of beneficiary households in every area have been determined

12

Figure 1: Tiers of GRM

Page 15: Environmental Safeguards Due Diligence Report...WSS was done using hydraulic modelling software of ‘EPANET’. 10. The numbers of beneficiary households in every area have been determined

13

V. ENVIRONMENT MANAGEMENT PLAN (EMP) AND ENVIRONMENTAL MONITORING PLAN(EMOP)

45. Though the impacts are mostly construction related the contractors have to follow an

Environment Management Plan during construction phase of the project to mitigate those

impacts. The Environmental Management Plan(EMP) and Environmental Monitoring Plan

(EMoP)are attached vide Appendix 3. The Contractor will be required to submit

Environmental Management Action Plan ( EMAP) including the time -frame and the allocated

budget. EMAP should be prepared based on the environmental issues, migratory measures

identified in the EMP and EMoP.

VI. CONCLUSIONS AND RECOMMENDATIONS

46. The negative environmental impacts arising due to execution of the proposed water

supply scheme are minor and negligible as compared to the long term Socio-economic and

health benefits to be delivered to people of the project area. Negative impacts can be mitigated

to standard levels without difficulty through proper engineering design and the incorporation

or application of recommended mitigation measures and procedures as per EMP.

47. It is recommended that (i) DDR be made part of the bid and contract documents to

ensure mitigation measures are appropriately budgeted and legally binding to the contractors;

(ii) monitor diligently contractor/s EMP implementation by PMU, SPCU and consultants on

EMP implementation by contractors.

48. Conclusion. The subproject will not cause adverse environmental problems during

preconstruction, construction and operational stages since the identified potential adverse

impacts during environmental assessment study are manageable by implementing proposed

mitigation measures at right time and monitored through a comprehensive environment

monitoring plan as described in this DDR report. Therefore, an IEE will not be required.

Page 16: Environmental Safeguards Due Diligence Report...WSS was done using hydraulic modelling software of ‘EPANET’. 10. The numbers of beneficiary households in every area have been determined

14

APPENDICES Appendix 1: Maps, Plans & Pictures showing existing site & construction related supplementary drawings.

A) Proposed two project sites.

A-1) Kuruswatte WS scheme project site project site in the close-up Google map.

A-2) Panangoda WS scheme project site project site in the close-up Google map

Page 17: Environmental Safeguards Due Diligence Report...WSS was done using hydraulic modelling software of ‘EPANET’. 10. The numbers of beneficiary households in every area have been determined

15

Appendix 1 c) Existing landscape of the proposed site - Kuruswatte, Mailawa.

Existing Tube well – Water Extraction Point

Site selected for constructing overhead

Page 18: Environmental Safeguards Due Diligence Report...WSS was done using hydraulic modelling software of ‘EPANET’. 10. The numbers of beneficiary households in every area have been determined

16

Appendix 1 d) Landscape of the proposed site - Panangoda

Ground water extraction point – Existing Tube Well

Site selected for constructing overhead tank.

Page 19: Environmental Safeguards Due Diligence Report...WSS was done using hydraulic modelling software of ‘EPANET’. 10. The numbers of beneficiary households in every area have been determined

17

Appendix 1

Details of Pipe Lines

Pipe schedule for Panangoda WSS

SPECIALLY NOT STATED PIPES ARE PVC (PN7)

SECTION DIAMETER

(mm) LENGTH (m) SECTION

DIAMETER

(mm) LENGTH (m)

A-B 110 60 L-N 63 50

A1-B1 90 (PN11) 160 N-O 63 130

B-C 110 100 N-D 63 380

C-D 90 90 B-P 110 230

E-D 63 378 P-Q 110 270

E-F 63 340 P-T 63 305

E-H 63 77 P-X 63 130

F-G 63 80 P-Q 63 260

H-C 63 260 Q-R 63 60

C-N 63 195 Q-S 63 300

C-I 90 80 Q-T 90 190

I-N 63 120 Q-T 63 175

J-K 63 70 T-U 90 105

J-L 63 300 U-V 63 380

J-I 63 300 U-W 63 120

L-M 63 30 W-S 63 370

Pipe schedule for Kuruswatte WSS

SPECIALLY NOT STATED PIPES ARE PVC (PN7)

SECTION DIAMETER

(mm) LENGTH (m) SECTION

DIAMETER

(mm) LENGTH (m)

A-B 63 (PN11) 715 H-M 63 345

C-D 110 475 O-Q 63 135 (L)

D-F 90 96 O-Q 63 135 (R)

D-E 63 6 J-N 63 30 (L)

F-H 90 94 J-N 63 30 (R)

H-J 90 50 N-O 63 85 (L)

I-D 63 460 N-O 63 85 (R)

D-F 63 96 O-P 63 80 (L)

F-G 63 220 O-P 63 80 (R)

N-L 63 122

Page 20: Environmental Safeguards Due Diligence Report...WSS was done using hydraulic modelling software of ‘EPANET’. 10. The numbers of beneficiary households in every area have been determined

14

Appendix 1

Layout Plans For Panangoda

For Kuruswatte

Page 21: Environmental Safeguards Due Diligence Report...WSS was done using hydraulic modelling software of ‘EPANET’. 10. The numbers of beneficiary households in every area have been determined

15

APPENDIX 2:

Rapid Environmental Assessment (REA) -Water Supply

Project : Local Government Enhancement Sector Project- Additional Financing (ADB

assisted- Loan 3431 SRI) Province : North Western Province Subproject : Panangoda and Kuruswatte Drinking Water Supply Project for Naththandiya

Prdeshiya Sabah.

LA : Naththandiya PS

District : Puttalam, Sri Lanka

Screening questions Yes No Remarks A. PROJECT SITING IS THE PROJECT AREA

Densely populated? The population distribution shows that the project area is not densely populated.

Heavy with development activities?

Adjacent to or within any

environmentally sensitive areas?

No environmentally sensitive areas are located within the Project area

CULTURAL HERITAGE SITE

PROTECTED AREA

WETLAND

MANGROVE

ESTUARINE

BUFFER ZONE OF PROTECTED

AREA

SPECIAL AREA FOR PROTECTING

BIODIVERSITY

BAY

B. POTENTIAL ENVIRONMENTAL IMPACTS

Will the project cause…

Degradation of environment due to

clearing of area/ removal of vegetation

for cutting trenches.

No trees or shrub vegetation found in the pipeline trace. Already a disturbed area.

Pollution of raw water supply from

upstream wastewater discharge from

communities, industries, agriculture,

and soil erosion runoff?

Not applicable.

Impairment of historical/cultural

monuments/areas and loss/damage to

these sites?

Not applicable. There are no historical/cultural monuments/areas within or adjacent to subproject sites.

Page 22: Environmental Safeguards Due Diligence Report...WSS was done using hydraulic modelling software of ‘EPANET’. 10. The numbers of beneficiary households in every area have been determined

16

Screening questions Yes No Remarks

Hazard of land subsidence caused by

excessive ground water pumping?

Not applicable.

Social conflicts arising from

displacement of communities?

No displacements required. Subproject sites are within ROWs of public roads

Conflicts in abstraction of raw water

for water supply with other beneficial

water uses for surface and ground

waters?

Water from tube wells will be extracted below the safe extraction level as recommended by Water Resource Board(WRB) so that no conflict will arise with other beneficiaries using ground water in the surrounding area.

Unsatisfactory raw water supply (e.g.

excessive pathogens or mineral

constituents)?

Raw water is purified in a package plant where Fe and Mn will be removed and chlorination is done

Delivery of unsafe water to distribution

system?

The distributed water will be treated and ensured to comply with the National Drinking Water Quality Standards.

Inadequate protection of intake works

or wells, leading to pollution of water

supply?

Not applicable. Well-protected water sump has been established.

Over pumping of ground water,

leading to salinization and ground

subsidence?

Not applicable.

Excessive algal growth in storage

reservoir?

The water is chlorinated and there is no chance for algal growth

Increase in production of sewage

beyond capabilities of community

facilities?

Not anticipated. Community is having good sanitation facilities.

Disposal of sludge from water

treatment plants?

Sludge will be removed as specified in the EMP.

Inadequate buffer zone around

pumping and treatment plants to

alleviate noise and other possible

nuisances and protect facilities?

Residences are located away from the WTP.

Impairments associated with

transmission lines and access roads?

Not applicable.

Health hazards arising from

inadequate design of facilities for

receiving, storing, and handling of

chlorine and other hazardous

chemicals.

Well-designed office and warehouse have been built at the site of WTP.

Health and safety hazards to workers

from handling and management of

chlorine used for disinfection, other

contaminants, and biological and

physical hazards during project

construction and operation?

Well protected hazard management measures are in place at the WTP

Page 23: Environmental Safeguards Due Diligence Report...WSS was done using hydraulic modelling software of ‘EPANET’. 10. The numbers of beneficiary households in every area have been determined

17

Screening questions Yes No Remarks

Dislocation or involuntary resettlement

of people?

No involuntary resettlement impacts envisioned. Lands for the subproject are government-owned

Disproportionate impacts on the poor,

women and children, indigenous

peoples or other vulnerable groups?

Not anticipated. The contractor will be encouraged to hire local workers from the local labor force.

Noise and dust from construction

activities?

Anticipated during construction activities. Temporary increase in noise level and dusts may be caused by excavation equipment, and the transportation of equipment, materials, and people. The impacts are negative but short-term and site-specific within a relatively small area. They are also reversible through mitigation measures. Good construction practices will mitigate noise and dust, and will be specified in the EMP.

Increased road traffic due to

interference of construction activities?

Traffic management measures will be adopted along the construction sites with proper signage and traffic plans.

Continuing soil erosion/silt runoff from

construction operations?

Due to excavation and run-off from stockpiled materials. The impacts are negative but short-term and site-specific and reversible through mitigation measures. Good construction practices will mitigate soil erosion and silt runoff and will be specified in the EMP.

Delivery of unsafe water due to poor

O&M treatment processes (especially

mud accumulations in filters) and

inadequate chlorination due to lack of

adequate monitoring of chlorine

residuals in distribution systems?

Back wash operations will be adopted for every 24 hours and mud and other impurities will be removed from the sedimentation and filtration beds. Good operational and maintenance practices will minimize pollutants discharged and will be specified in the EMP.

Delivery of water to distribution

system, which is corrosive due to

inadequate attention to feeding of

corrective chemicals?

The project will include development of O&M manuals to ensure facilities are kept in working condition, including checking and maintenance of distribution network. Any distributed water must comply with the National Drinking Water Quality Standards.

Accidental leakage of chlorine gas? Not applicable as protective measures have been implemented at IWTP

Excessive abstraction of water

affecting downstream water users?

Not applicable.

Competing uses of water?

Increased sewage flow due to

increased water supply

Not applicable. Households have adequate sanitation facilities

Increased volume of sewage

(wastewater from cooking and

washing) and sludge from wastewater

treatment plant

Page 24: Environmental Safeguards Due Diligence Report...WSS was done using hydraulic modelling software of ‘EPANET’. 10. The numbers of beneficiary households in every area have been determined

18

Screening questions Yes No Remarks

Large population influx during project

construction and operation that causes

increased burden on social

infrastructure and services (such as

water supply and sanitation systems)?

Improved management systems through capacity building and institutional development will ensure reduced burden on services and infrastructure.

Social conflicts if workers from other

regions or countries are hired?

Priority in employment will be given to local residents.

Risks to community health and safety

due to the transport, storage, and use

and/or disposal of materials such as

explosives, fuel and other chemicals

during operation and construction?

Not applicable. Construction will not involve use of explosives and chemicals during the construction phase.

Community safety risks due to both

accidental and natural hazards,

especially where the structural

elements or components of the project

are accessible to members of the

affected community or where their

failure could result in injury to the

community throughout project

construction, operation and

decommissioning?

Work areas will be clearly demarcated with signage and safety barriers, and access will be controlled. Only workers and project concerned members will be allowed to visit the operational sites.

Impacts to occupational health and

safety due to the excavation of rocks

during cutting trenches.

When cutting trenches and rock excavation are carried out ,PPEs will be worn and mitigations will be taken as specified in EMP.

Impacts to community health and

safety due to the transport of

construction material.

Safety measures where required shall be taken.

Occupational and Community health

and safety risk.

When considering the scope of work, magnitude of construction activities health and safety risks are not very significant. However, PPEs will be required for some workers who works cutting trenches and construction of overhead tanks etc to avoid any accidents during the work.

Impacts to community safety caused

by construction waste and disposal of

wastes from site camps.

Construction waste generated should be disposed to a site approved by PS. Garbage bins should be provided at all times and they should be collected by the PS constantly.

Page 25: Environmental Safeguards Due Diligence Report...WSS was done using hydraulic modelling software of ‘EPANET’. 10. The numbers of beneficiary households in every area have been determined

19

APPENDIX 2:

Compliance with Sri Lanka Laws & Regulations and Basic Information of Project Site

LA :Naththandiya PS SPCU : North Western Province Subproject :Panagoda and Kruswatte Drinking Water Supply Project for Naththandiya

Prdeshiya Sabah.

Location :Panagoda and Kuruswatte

1. Compliance

The project is not located within 100 m from the boundaries of or within any area declared

under the National Heritage Wilderness Act no 4 of 1988.

The project is not located within 100 m from the boundaries of or within any area declared

under the Forest Ordinance (Chapter 451).

The project is not located within Coastal Zone as defined in the Coast Conservation Act No

57 of 1981.

The project is not located within any erodible area under the Soil Conservation Act

(Chapter 450).

The project is not located within flood prone areas declared underFlood Protection

Ordinance (Chapter 449).

The project is not located within low lying area of North Western Province which is a flood

protection area declared under the Sri Lanka Land Reclamation and Development

Corporation Act 15 of 1968 as amended by Act No 52 of 1982.

The project is not located within 60 meters from the bank of a public stream as defined in

the Crowns Lands Ordinance (Chapter 454) and having width of more than 25 meters at any

point of its course.

There are no reservations beyond the full supply level of a reservoir within the proposed

project area.

The project is not located within any archaeological reserve, ancient or protected

monument as defined or declared under the Antiquities Ordinance (Chapter 188).

The project is not located within any area declared under the Botanic Gardens Ordinance

(Chapter 446).

The project is not located within100 meters from the boundaries of, or within, any area

declared as a Sanctuary under the Fauna and Flora protection Ordinance (Chapter 454).

The project is not located within 100m from high flood level contour of a public lake as

defined by the Crown Land Ordinance (1947, 1949, and 1956) including those declared

under Section 71 of the ordinance.

The project is not located within 100m from the boundaries of or within any area declared

under the Forest Ordinance (Chapter 451)

The project is located within areas declared under the Urban Development Authority Act No.

41 of 1978 and Act No. 4 of 1982 Section 29.

2. Present ownership of the project site:

State Private Other – Specify

- - Naththandiya PS

Page 26: Environmental Safeguards Due Diligence Report...WSS was done using hydraulic modelling software of ‘EPANET’. 10. The numbers of beneficiary households in every area have been determined

20

3. Present land use:

Land Use type Land Use type

Paddy Marsh / Mangrove

Tea Scrub / Forest

Rubber Grassland / Chena

Coconut Built – up area √

Other plantations / Garden Other: Bare land

4. Does the site / Project require any:

Activity Yes No If yes give the extent

(in ha)

Reclamation of land, wetlands √

Clearing of forest √

Felling of trees √

5. Does the Project envisage any resettlement

Yes No If yes, give the number of the families to be resettled

6. Does the Project envisage laying of pipelines

Yes No If Yes, give the length of the pipeline (km)

√ Panangoda – 6.5km

Kuruswatte – 3.5km

7. Does the project involve any tunneling activities

Yes No

Page 27: Environmental Safeguards Due Diligence Report...WSS was done using hydraulic modelling software of ‘EPANET’. 10. The numbers of beneficiary households in every area have been determined

21

APPENDIX 2:

A Checklist for Preliminary Climate Risk Screening

Project Title :Local Government Enhancement Sector Project (Additional Financing)

Province :North-Western Province

Sub Project : Panagoda and Kruswatte Drinking Water Supply Project for Naththandiya Prdeshiya

Sabah.

District : Puttalam

Local Authority: Naththandiya Pradeshiya Sabha.

Screening Questions Score Rema

rks2

Location

and

Design of

project

Is siting and/or routing of the project (or its components) likely to be

affected by climate conditions including extreme weather related events

such as floods, droughts, storms, landslides?

0

Would the project design (e.g. the clearance for bridges) need to consider

any hydro-meteorological parameters (e.g., sea-level, peak river flow,

reliable water level, peak wind speed etc)?

0

Materials

and

Maintenan

ce

Would weather, current and likely future climate conditions (e.g. prevailing

humidity level, temperature contrast between hot summer days and cold

winter days, exposure to wind and humidity hydro-meteorological

parameters likely affect the selection of project inputs over the life of

project outputs (e.g. construction material)?

0

Would weather, current and likely future climate conditions, and related

extreme events likely affect the maintenance (scheduling and cost) of

project output(s)?

0

Performa

nce of

project

outputs

Would weather/climate conditions and related extreme events likely affect

the performance (e.g. annual power production) of project output(s) (e.g.

hydro-power generation facilities) throughout their design life time?

0

Options for answers and corresponding score are provided below:

Response Score

Not Likely 0

Likely 0

Very Likely 0

Responses when added that provide a score of 0 will be considered low risk project. If adding all responses will

result to a score of 1-4 and that no score of 2 was given to any single response, the project will be assigned a

medium risk category. A total score of 5 or more (which include providing a score of 1 in all responses) or a 2 in

any single response will be categorized as high risk project.

Result of Initial Screening (Low, Medium, High): Low

Page 28: Environmental Safeguards Due Diligence Report...WSS was done using hydraulic modelling software of ‘EPANET’. 10. The numbers of beneficiary households in every area have been determined

22

Appendix 3: Environmental Management Plan & Environmental Monitoring Plan

Environmental Management Plan Activity Environmental Issue Mitigation Measures Location Implementing

agency

Executing

Agency

1 Site Clearing before

starting construction.

1 Environment degradation

caused by cutting large

trees.

1 i)To avoid un –necessary tree

cutting by demarcating trees

exactly to be removed.

ii) To implement

compensatory tree planting

at 1:4 ratio.

As directed

by Engineer

Contractor Consultant/

client.

2 Site Clearing before

starting construction.

2 Environment pollution

caused by eroded soil during

rains after site clearing.

2 To provide soil conservation

bunds and maintained.

As directed

by Engineer

Contractor Consultant/

client.

3 Construction of structures

( overhead tank and

cutting trenches for pipe

laying)

3 Safety of workers at deep

excavation endangered by

embankment collapse

3 To provide embankment

protection as directed by the

Engineer.

As directed

by Engineer

Contractor Consultant/

client

4 Environment pollution

caused by material wash

away from excavated

stockpiles during rains

4 To protect material

stockpiles, wash away during

rains by covering/providing

conservation bunds or any

other arrangement

As directed

by Engineer

Contractor Consultant/

client

5 Hazardous mosquito

breeding caused by stagnant

water in excavated trenches

5 To remove stagnant water

regularly from trenches to

ensure mosquito breeding is

not taken place

As directed

by Engineer

Contractor Consultant/

client

6 Environment pollution

caused by waste water

removed from excavated

trenches.

6 To divert waste water

removed from trenches to a

drainage path with silt traps

As directed

by Engineer

Contractor Consultant/

client

Page 29: Environmental Safeguards Due Diligence Report...WSS was done using hydraulic modelling software of ‘EPANET’. 10. The numbers of beneficiary households in every area have been determined

23

Activity Environmental Issue Mitigation Measures Location Implementing

agency

Executing

Agency

by protecting downstream

environment

7 Public nuisance caused by

noise generation during

construction.

7 To provide adequate noise

barriers when and where

necessary.

As directed

by Engineer

Contractor Consultant/

client

8 Public safety endangered by

cutting trenches across

access roads.

8 To place a steel plate over

the trench for vehicles to

move and timber planks for

pedestrians where

necessary.

As directed

by Engineer

Contractor Consultant/

client

4 Rock excavation if any. 9 Health hazard of drillers and

others in the vicinity caused

by dust generation during

rock drilling/crushing

9 To provide dust control

arrangements while rock

drilling (wet gunny bags)

As directed

by Engineer

Contractor Consultant/

client

10 To provide dusk masks for

rock drillers and others in the

vicinity while

drilling/crushing

As directed

by Engineer

Contractor Consultant/

client

5 Rock blasting and

crushing in any.

10 Community and

occupational safety

endangered by insufficient

protective measures during

rock blasting

11 To arrange standard rock

blasting safety arrangements

including prior warning.

As directed

by Engineer

Contractor Consultant/

client

6 Burrowing, transporting,

placing aggregate

material (earth, gravel,

sand, metal, quarry dust

etc.)

11 Health hazard due to

windblown dust while

transporting dusty material

by uncovered trucks at dry

weather

12 To make sure that dusty

material is transported only

by covered trucks.

As directed

by Engineer

Contractor Consultant/

client

Page 30: Environmental Safeguards Due Diligence Report...WSS was done using hydraulic modelling software of ‘EPANET’. 10. The numbers of beneficiary households in every area have been determined

24

Activity Environmental Issue Mitigation Measures Location Implementing

agency

Executing

Agency

12 Community/occupational

health endangered by

windblown dust during

construction.

13 To provide regular water

spreading system or/and to

deploy sprinkler attached

water bowsers regularly

As directed

by Engineer

Contractor Consultant/

client

13 Public safety endangered by

material pieces thrown out

from overloaded moving

trucks.

14 To make sure that trucks are

not overloaded while

transporting material.

As directed

by Engineer

Contractor Consultant/

client

14 Public safety endangered by

usage of access roads

damaged due to heavy

vehicle movements

15 To reinstate access roads

regularly.

As directed

by Engineer

Contractor Consultant/

client

15 Hazardous mosquito

breeding caused by stagnant

water in burrow pits after

mining.

16 i) ) GSMB approval is

obtained for burrow pits and

burrowing material.

ii) To reinstate burrow pits as

per GSMB guidelines.

As directed

by Engineer

Contractor Consultant/

client

7 Pipe-laying, installation of

valves and hydrants,

pressure testing,

installation of service

connection and

reinstatement of trenches

16 Environment pollution by

leaving trimmed pipe scraps

at sites.

17 To collect and dispose

trimmed pipe scraps to LA

collecting Centre operated

by Naththandiya PS.

As directed

by Engineer

Contractor Consultant/

client

17 Public/occupational safety

endangered by unsafe

handling of lengthy/heavy

pipes and accessories while

laying and fixing

18 To employee trained and

experienced workers for

handling lengthy/heavy

items by taking adequate

care

As directed

by Engineer

Contractor Consultant/

client

Page 31: Environmental Safeguards Due Diligence Report...WSS was done using hydraulic modelling software of ‘EPANET’. 10. The numbers of beneficiary households in every area have been determined

25

Activity Environmental Issue Mitigation Measures Location Implementing

agency

Executing

Agency

8 Maintenance of storage

areas .

18 Environment pollution

caused by oil spills and

draining to surrounding

areas.

19 To avoid draining oil spills to

surrounding environment by

sealing leaked places or any

other means with regular

and close observation.

As directed

by Engineer

Contractor Consultant/

client

19 Polluting surrounding

environment by material

stockpiles (at open storage)

wash away during rains.

20 To protect washable material

stockpiles (at open storage)

by covering them during

rainy season and /or

providing conservation

bunds.

As directed

by Engineer

Contractor Consultant/

client

9 Occupational and public

health and safety during

construction/ excavation

of trenches.

20 Occupational health

endangered by insufficient

sanitary facilities provided

at office/camps

21 To provide adequate sanitary

facilities to office/camps and

regularly monitor the quality

and adequacy

As directed

by Engineer

Contractor Consultant/

client

21 Occupational safety

endangered by project

activities without

implementing safety

management plan

22 To prepare and implement

engineer approved safety

management plan to ensure

employees wear standard

PPEs.

As directed

by Engineer

Contractor Consultant/

client

22 Public safety endangered by

project activities without

implementing a proper

Traffic Management Plan.

23 To prepare and implement

engineer approved traffic

management plan where

safety measure to be taken

have been well described.

As directed

by Engineer

Contractor Consultant/

client

10 Construction waste

disposal

23 Occupational/public health

and safety endangered by

scattered construction

waste at sites and public

areas.

24 i) to dispose construction

waste into a site approved by

LA.

or

As directed

by Engineer

Contractor Consultant/

client

Page 32: Environmental Safeguards Due Diligence Report...WSS was done using hydraulic modelling software of ‘EPANET’. 10. The numbers of beneficiary households in every area have been determined

26

Activity Environmental Issue Mitigation Measures Location Implementing

agency

Executing

Agency

ii) to disposed to a site

operated by LA with the

consent of the LA.

11 Office/camp waste

disposal

24 Surrounding environment of

office/camp is polluted by

scattered garbage/waste.

25 To provide office/camp

waste disposal arrangements

(garbage bins) and maintain

within the premises and

regularly hand over

separated waste to LA

garbage collecting rucks.

As directed

by Engineer

Contractor Consultant/

client

Operational and Maintenance Phase

12 Over abstraction of raw

water for water supply.

25 Conflicts with other

beneficial water uses of

ground waters.

26 Ground water will be

extracted as per guidelines

and conditions imposed by

Water Resource Board.

(WRB)

Tube wells

/Panangona

and

Kruswatte

Naththandiya

Pradeshiya

Sabah.

Ministry of

Provincial and

Local

Government.

13 Generation of Sludge and

impurities.

26 Environment pollution

endangered by

sludge/impurities

generated.

27 Sludge generated will be

managed and disposed as

per the Guidelines given by

the Provincial Environmental

Authority (NWP).

Site /Package

Plant /

Kruswatte .

Naththandiya

Pradeshiya

Sabah.

Ministry of

Provincial and

Local

Government.

Page 33: Environmental Safeguards Due Diligence Report...WSS was done using hydraulic modelling software of ‘EPANET’. 10. The numbers of beneficiary households in every area have been determined

27

Environmental Monitoring Plan (EMoP)

Activity Environmental Issue Mitigation

Measures

Monitoring

Parameter

Monitoring

Methods

Location Implementin

g agency

Executing

Agency

1 Site clearing

before starting

construction.

1 Environment

degradation caused by

cutting large trees

(Removal of greenery)

1 To avoid un-necessary tree cutting by demarcating trees exactly to be removed.

Trees exactly to be removed are demarcated

Physical

observation/Photo

graphs

As

directed

by

Engineer

Contractor Consultan

t/ client

2 To implement tree re-planting program.

(i)Suitable land is selected.

(ii)Tree planting

implemented (1: 4

rate)

Physical

observation/Photo

graphs

As

directed

by

Engineer

Contractor Consultan

t/ client

2 Site clearing

before starting

construction.

2 Environment pollution

caused by eroded soil

during rains after site

clearing.

3 To provide soil

conservation

bunds and

maintain.

Well maintained soil

conservation bunds.

Physical

observation/Photo

graphs

As

directed

by

Engineer

Contractor Consultan

t/ client

3 Construction of

structures (

overhead tank,

package plant and

cutting trenches

for pipe laying

3 Safety of workers at

deep excavation

endangered by

embankment collapse

4 To provide

embankment

protection as

directed by

Engineer.

Areas where

embankment

protection done.

Physical

observation/Photo

graphs

As

directed

by

Engineer

Contractor Consultan

t/ client

4 Environment pollution

caused by material

wash away from

excavated stockpiles

during rains.

5 To provide soil

conservation

bunds and

maintain.

Areas where

conservation bunds

set up.

Physical

observation/Photo

graphs

As

directed

by

Engineer

Contractor Consultan

t/ client

Page 34: Environmental Safeguards Due Diligence Report...WSS was done using hydraulic modelling software of ‘EPANET’. 10. The numbers of beneficiary households in every area have been determined

28

Activity Environmental Issue Mitigation

Measures

Monitoring

Parameter

Monitoring

Methods

Location Implementin

g agency

Executing

Agency

5 Hazardous mosquito

breeding caused by

stagnant water in

excavated trenches

6 To remove

stagnant water

regularly and

ensure no

mosquito

breeding taken

place.

i)Area without

stagnant water.

Physical

observation/Photo

graphs

As

directed

by

Engineer

Contractor Consultan

t/ client

6 Environment pollution

caused by waste water

removed from

excavated trenches.

7 To divert waste

water removed

from trenches

to a drainage

path with silt

traps by

protecting

downstream

environment

Silt Traps and Public

complaints on waste

water discharge.

Physical

observation/Photo

graphs

As

directed

by

Engineer

Contractor Consultan

t/ client

7 Public safety

endangered by cutting

trenches across access

roads.

8 To place a steel

plate over the

trench for

vehicles to

move and for

pedestrians.

Crossing points

where facilities

provided for vehicle

movement and

pedestrians to move.

Physical

observation/Photo

graphs

As

directed

by

Engineer

Contractor Consultan

t/ client

8 Public nuisance caused

by noise generation

during construction

9 To provide

adequate noise

barriers when

and where

necessary

Adequate temporary

noise barriers are

provided as required.

Physical

observation/Photo

graphs

As

directed

by

Engineer

Contractor Consultan

t/ client

4 Rock excavation, if

any

9 Health hazard of

drillers and others in

the vicinity caused by

dust generation during

rock drilling/crushing

10 To provide dust

control

arrangements

while rock

i) Use of wet gunny

bags.

ii) Dust deposition on

the surrounding.

Physical

observation/Photo

graphs

As

directed

by

Engineer

Contractor Consultan

t/ client

Page 35: Environmental Safeguards Due Diligence Report...WSS was done using hydraulic modelling software of ‘EPANET’. 10. The numbers of beneficiary households in every area have been determined

29

Activity Environmental Issue Mitigation

Measures

Monitoring

Parameter

Monitoring

Methods

Location Implementin

g agency

Executing

Agency

drilling (wet

gunny bags)

11 To provide dusk

masks for rock

drillers and

others in the

vicinity while

drilling/crushing

i) Use of standard

dusk masks and

other relevant PPEs .

Physical

observation/Photo

graphs

As

directed

by

Engineer

Contractor Consultan

t/ client

5 Rock blasting and

crushing, if any

1

0

Community and

occupational safety

endangered by

insufficient protective

measures during rock

blasting

12 To arrange

standard rock

blasting safety

arrangements

including prior

warning.

Standard rock

blasting safety

arrangements are

provided including

prior warning.

Physical

observation/Photo

graphs

As

directed

by

Engineer

Contractor Consultan

t/ client

6 Burrowing,

transporting,

placing aggregate

material (earth,

gravel, sand,

metal, quarry dust

etc.)

1

1

Health hazard due to

windblown dust while

transporting dusty

material by uncovered

trucks at dry weather

13 To make sure

that dusty

material is

transported

only by covered

trucks.

Dusty material is

transported only by

covered trucks.

Physical

observation/Photo

graphs

As

directed

by

Engineer

Contractor Consultan

t/ client

1

2

Community/occupatio

nal health endangered

by windblown dust

during construction

14 To provide

regular water

spreading

system or/and

to deploy

sprinkler

attached water

bowsers

regularly

i)Water spreading

system or/and

sprinkler attached

water bowser use is

regularly being

carried out regularly

and to provide dust

masks for workers

ii) Construction

material dust/ dust

Physical

observation/Photo

graphs

As

directed

by

Engineer

Contractor Consultan

t/ client

Page 36: Environmental Safeguards Due Diligence Report...WSS was done using hydraulic modelling software of ‘EPANET’. 10. The numbers of beneficiary households in every area have been determined

30

Activity Environmental Issue Mitigation

Measures

Monitoring

Parameter

Monitoring

Methods

Location Implementin

g agency

Executing

Agency

from excavated soil

is not deposited over

the surrounding area.

1

3

Public safety

endangered by

material pieces thrown

out from overloaded

moving trucks.

15 To make sure

that trucks are

not overloaded

while

transporting

material

Trucks are not

overloaded while

material is

transported.

Physical

observation/Photo

graphs

As

directed

by

Engineer

Contractor Consultan

t/ client

1

4

Public safety

endangered by usage

of access roads

damaged due to heavy

vehicle movements.

16 To reinstate

access roads

regularly.

Access roads are

regularly reinstated.

Physical

observation/Photo

graphs

As

directed

by

Engineer

Contractor Consultan

t/ client

1

5

Hazardous mosquito

breeding caused by

stagnant water in

burrow pits after

mining.

17 To reinstate

burrow pits as

per GSMB

guidelines if

contractor

operates the

burrow pit.

i) GSMB approval is

obtained for burrow

pits and burrowing

material.

ii) Burrow pits are

reinstated as per

GSMB guidelines.

Documents/Physic

al observation/

/Photographs

As

directed

by

Engineer

Contractor Consultan

t/ client

Page 37: Environmental Safeguards Due Diligence Report...WSS was done using hydraulic modelling software of ‘EPANET’. 10. The numbers of beneficiary households in every area have been determined

31

Activity Environmental Issue Mitigation

Measures

Monitoring

Parameter

Monitoring

Methods

Location Implementin

g agency

Executing

Agency

7 Pipe-laying,

installation of

valves and

hydrants, pressure

testing,

installation of

service connection

and reinstatement

of trenches

1

5

Public/occupational

safety endangered by

unsafe handling of

lengthy/heavy

materials

18 To employee

trained and

experienced

workers for

handling

lengthy/heavy

items by taking

adequate care

No accidents

reported.

Physical

observation

As

directed

by

Engineer

Contractor Consultan

t/ client

1

6

Environment pollution

by leaving trimmed

pipe scraps at sites

19 To collect and

dispose

trimmed pipe

scraps to LA

collecting

Centre.

( Naththandiya)

No pipe scarps left in

the site.

Physical

observation / LA

consent letter.

As

directed

by

Engineer

Contractor Consultan

t/ client

8 Maintenance of

storage areas

1

7

Environment pollution

caused by oil spills and

draining to

surrounding areas.

20 To avoid

draining oil spills

to surrounding

environment by

sealing leaked

places or any

other means

with regular and

close

observation.

) Lubricant leaking

places are sealed,

and adequate

measures have been

taken to protect

draining lubricant to

the environment

(containers are

provided to collect

leaking oils until

repair)

Physical

observation.

As

directed

by

Engineer

Contractor Consultan

t/ client

Page 38: Environmental Safeguards Due Diligence Report...WSS was done using hydraulic modelling software of ‘EPANET’. 10. The numbers of beneficiary households in every area have been determined

32

Activity Environmental Issue Mitigation

Measures

Monitoring

Parameter

Monitoring

Methods

Location Implementin

g agency

Executing

Agency

1

8

Polluting surrounding

environment by

material stockpiles (at

open storage) wash

away during rains.

21 To protect

washable

material

stockpiles (at

open storage)

by covering

them during

rainy season

and /or

providing

conservation

bunds.

Washable material

stockpiles (at open

storage) are covered

to protect them

during rainy season.

Physical

observation

As

directed

by

Engineer

Contractor Consultan

t/ client

9 Occupational and

public health and

safety during

construction

1

9

Occupational health

endangered by

insufficient sanitary

facilities provided at

office/camps

22 To provide

adequate

sanitary

facilities to

office/camps

and regularly

monitor the

quality and

adequacy

Sanitary facilities are

provided for

office/camps and

maintained quality

and adequacy

Physical

observation

As

directed

by

Engineer

Contractor Consultan

t/ client

2

0

Occupational safety

endangered by project

activities without

implementing safety

management plan

23 To prepare and

implement

engineer

approved safety

management

plan to ensure

employees wear

standard PPEs.

i)Engineer approved

safety management

plan is available

ii)Standard PPEs (in

correct size) are

provided for all

employees

iii)Ensured all

workers are fully

equipped with PPEs

Physical

observation

As

directed

by

Engineer

Contractor Consultan

t/ client

Page 39: Environmental Safeguards Due Diligence Report...WSS was done using hydraulic modelling software of ‘EPANET’. 10. The numbers of beneficiary households in every area have been determined

33

Activity Environmental Issue Mitigation

Measures

Monitoring

Parameter

Monitoring

Methods

Location Implementin

g agency

Executing

Agency

while performing

duties

iv)Occupational and

community safety is

ensured by providing

warning boards,

barricades, luminous

stickers, night

warning lamps, safe

by-pass access roads

etc., as per approved

safety management

plan and maintained

the quality and

adequacy

2

1

Public safety

endangered by project

activities without

implementing traffic

management plan

24 To prepare and

implement

engineer

approved traffic

management

plan to ensure

public safety

Warning boards,

barricades, luminous

stickers, night

warning lamps, safe

by-pass access roads

etc., as per approved

traffic management

plan and maintained

the quality and

adequacy

Physical

observation

As

directed

by

Engineer

Contractor Consultan

t/ client

Page 40: Environmental Safeguards Due Diligence Report...WSS was done using hydraulic modelling software of ‘EPANET’. 10. The numbers of beneficiary households in every area have been determined

34

Activity Environmental Issue Mitigation

Measures

Monitoring

Parameter

Monitoring

Methods

Location Implementin

g agency

Executing

Agency

1

0

Construction

waste disposal

2

2

Occupational/public

health and safety

endangered by

scattered construction

waste at sites, yards,

and public areas.

25 To dispose

construction

waste in to a

approved

disposal site.

i) Construction waste

is disposed to

approved disposal

yards and reinstated

regularly.

ii)Ensured

construction waste is

not disposed to

unauthorized

locations whatsoever

Physical

observation

As

directed

by

Engineer

Contractor Consultan

t/ client

1

1

Office/camp waste

disposal

2

3

Surrounding

environment of

office/camp is polluted

by scattered waste

26 To provide

office/camp

waste collecting

and disposal

arrangements

and maintain

regularly.

i)Office/camp waste

collecting facilities

are adequately

provided and

regularly disposed

ii)Ensured

office/camp waste is

not scattered around

office/camp premises

and not disposed to

unauthorized

locations

Physical

observation

As

directed

by

Engineer

Contractor Consultan

t/ client

Operation/ Maintenance Phase

1

2

Over abstraction

of raw water for

water supply.

2

4

Conflicts with other

beneficial water uses

of ground waters.

27 Ground water

will be extracted

as per

guidelines and

conditions

Safe yield of ground

water extraction

recommended by

WRB.

Documents/

physical

observation.

Surround

ing dug

wells.

Naththandiya

Pradeshiya

Sabah

Ministry

of

Provincial

Council

and Local

Page 41: Environmental Safeguards Due Diligence Report...WSS was done using hydraulic modelling software of ‘EPANET’. 10. The numbers of beneficiary households in every area have been determined

35

Activity Environmental Issue Mitigation

Measures

Monitoring

Parameter

Monitoring

Methods

Location Implementin

g agency

Executing

Agency

imposed by

Water Resource

Board.

(WRB)

Governme

nt

1

3

Generation of

Sludge and

impurities.

2

5

Environment pollution

endangered by

sludge/impurities

generated.

28 Sludge generated

will be managed

and disposed as

per the Guidelines

given by the

Provincial

Environmental

Authority ( NWP)

i)Guidelines of

Provincial

Environmental

Authority(NWP)

ii) Sludge removed

not disposed to an un

authorized site.

i)Documents

ii)Physical

observation

Package

Plant

/Kuruswat

te.

Naththandiya

Pradeshiya

Sabah

Ministry of

Provincial

Council and

Local

Governme

nt.

Page 42: Environmental Safeguards Due Diligence Report...WSS was done using hydraulic modelling software of ‘EPANET’. 10. The numbers of beneficiary households in every area have been determined

35

Appendix 4- Water Quality Report – Kuruswatte , Mailawa

Page 43: Environmental Safeguards Due Diligence Report...WSS was done using hydraulic modelling software of ‘EPANET’. 10. The numbers of beneficiary households in every area have been determined

36

Appendix 4- Water Quality Report – Panangoda