environmental noise monitoring · the noise monitoring and reporting requirements for iug are...

37
ENVIRONMENTAL NOISE MONITORING Glencore Integra Underground Mine Winter 2017 FINAL November 2017

Upload: others

Post on 27-Jun-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Environmental Noise Monitoring · The noise monitoring and reporting requirements for IUG are outlined in the Integra Underground Mine Project Approval (PA 08_0101 MOD 6) and Environment

ENVIRONMENTAL NOISE MONITORING

Glencore Integra Underground Mine Winter 2017

FINAL

November 2017

Page 2: Environmental Noise Monitoring · The noise monitoring and reporting requirements for IUG are outlined in the Integra Underground Mine Project Approval (PA 08_0101 MOD 6) and Environment

Newcastle

75 York Street Teralba NSW 2284

Ph. 02 4950 5322

www.umwelt.com.au

This report was prepared using Umwelt’s ISO 9001 certified Quality Management System.

ENVIRONMENTAL NOISE MONITORING

Glencore Integra Underground Mine Winter 2017

FINAL

Prepared by

Umwelt (Australia) Pty Limited on behalf of

Glencore Integra Underground Mine

Project Director: Saul Martinez Project Manager: Dave Davis Report No. 3995/R03/FINAL Date: November 2017

Page 3: Environmental Noise Monitoring · The noise monitoring and reporting requirements for IUG are outlined in the Integra Underground Mine Project Approval (PA 08_0101 MOD 6) and Environment

Disclaimer This document has been prepared for the sole use of the authorised recipient and this document may not be used, copied or reproduced in whole or part for any purpose other than that for which it was supplied by Umwelt (Australia) Pty Ltd (Umwelt). No other party should rely on this document without the prior written consent of Umwelt.

Umwelt undertakes no duty, nor accepts any responsibility, to any third party who may rely upon or use this document. Umwelt assumes no liability to a third party for any inaccuracies in or omissions to that information. Where this document indicates that information has been provided by third parties, Umwelt has made no independent verification of this information except as expressly stated.

©Umwelt (Australia) Pty Ltd

Document Status

Rev No. Reviewer Approved for Issue

Name Date Name Date

FINAL Dave Davis 03 November 2017 Dave Davis 03 November 2017

Page 4: Environmental Noise Monitoring · The noise monitoring and reporting requirements for IUG are outlined in the Integra Underground Mine Project Approval (PA 08_0101 MOD 6) and Environment

Environmental Noise Monitoring 3995_R03_ENM_Final

Table of Contents

1.0 Introduction 1

1.1 Project Background 1

1.2 Scope 1

2.0 Assessment Criteria 5

3.0 Compliance Assessment Methodology 8

4.0 Attended Noise Monitoring 9

4.1 Attended Noise Monitoring Program 9

4.2 Attended Noise Monitoring Results for Winter 2017 11

4.3 Monitoring Results Summary 11

5.0 Statement of Compliance 12

6.0 References 13

Figures

Figure 1.1 Locality Plan 3 Figure 1.2 IUG Noise Monitoring Locations 4 Tables

Table 2.1 Noise Impact Assessment Criteria from PA 08_0101 MOD 6 for IUG, dB(A) 5 Table 2.2 Noise Impact Assessment Criteria from EPL 3390 for IUG, dB(A) 6 Table 2.3 Meteorological Exclusions 7 Table 4.1 Attended Noise Monitoring Locations 10

Appendices

Appendix 1 15 Appendix 2 3 Appendix 3 7

Glossary and Abbreviations Calibration Certificates Attended Monitoring Results

Page 5: Environmental Noise Monitoring · The noise monitoring and reporting requirements for IUG are outlined in the Integra Underground Mine Project Approval (PA 08_0101 MOD 6) and Environment

Environmental Noise Monitoring 3995_R03_ENM_Final

Introduction 1

1.0 Introduction

Glencore Integra Underground (IUG) is located in the Hunter coalfields of New South Wales (NSW), approximately 12 kilometres north-west of Singleton in the locality of Camberwell (refer to Figure 1.1). IUG is owned and managed by HV Coking Coal Pty Ltd (HVCC) which is a wholly-owned subsidiary business unit of Glencore Coal Pty Limited (Glencore).

Underground mining operations at IUG are approved at a maximum extraction rate of 4.5 million tonnes per annum (Mtpa) of run-of-mine (ROM) coal until 31 December 2035 under Project Approval PA 08_0101.

1.1 Project Background

IUG operates in an area dominated by coal mining and mining-related development. It lies immediately to the south-east of Glencore’s Mount Owen Complex while Ashton Mine operates to the west and south-west. The residential areas of Camberwell Village and Wattle Ponds are located to the west and east of the mine respectively. There are a number of residences situated in the immediate vicinity of IUG (refer to Figure 1.2).

In late 2015, HVCC acquired all assets associated with the IUG, which had been placed under care and maintenance in May 2014. During this time environmental management of the site was maintained under a care and maintenance environmental management system.

Prior to HVCC’s purchase of the mine, it formed part of the larger Integra Mine Complex. This complex comprised both underground and open cut operations and operated under a single project approval instrument which combined the project approvals for the Integra Underground (PA 08_0101) and Integra Open Cut (PA 08_0102). Following the separate sale of the underground and open cut, the combined project approval was modified to once again separate the approvals. IUG now operates under PA 08_0101 MOD 6.

HVCC recommenced underground operations early in 2017, with development resuming in February 2017 and longwall extraction resuming in May 2017.

1.2 Scope

This Noise Monitoring Report has been prepared by Umwelt (Australia) Pty Limited (Umwelt) on behalf of HVCC for IUG.

The noise monitoring and reporting requirements for IUG are outlined in the Integra Underground Mine Project Approval (PA 08_0101 MOD 6) and Environment Protection Licence (EPL) 3390, and are guided by the Integra Underground Noise Management Plan (Glencore, 2017).

Due to the underground nature of the mine, generation of noise emissions as a result of IUG’s operations will generally be limited to the following sources:

Ventilation fans, compressor and gas flares located on Forest Road;

Haulage of coal from the ROM coal stockpile to the project boundary. Bloomfield operations then transports the coal to the CHPP on their internal haul road via haul trucks; and

Page 6: Environmental Noise Monitoring · The noise monitoring and reporting requirements for IUG are outlined in the Integra Underground Mine Project Approval (PA 08_0101 MOD 6) and Environment

Environmental Noise Monitoring 3995_R03_ENM_Final

Introduction 2

Minor surface disturbance activities, including:

o Exploration activities;

o Gas drainage works;

o Minor subsidence remediation works; and

o Construction of erosion and sedimentation controls.

This report presents the results of the Winter 2017 (01 June 2017 to 31 August 2017) noise monitoring undertaken as part of the noise monitoring program for IUG. The monitoring results will be incorporated into the Annual Review required to be prepared under the relevant project approval conditions for IUG.

A glossary of terms and abbreviations used in this report is provided in Appendix 1.

Page 7: Environmental Noise Monitoring · The noise monitoring and reporting requirements for IUG are outlined in the Integra Underground Mine Project Approval (PA 08_0101 MOD 6) and Environment
Page 8: Environmental Noise Monitoring · The noise monitoring and reporting requirements for IUG are outlined in the Integra Underground Mine Project Approval (PA 08_0101 MOD 6) and Environment
Page 9: Environmental Noise Monitoring · The noise monitoring and reporting requirements for IUG are outlined in the Integra Underground Mine Project Approval (PA 08_0101 MOD 6) and Environment

Environmental Noise Monitoring 3995_R03_ENM_Final

Assessment Criteria 5

2.0 Assessment Criteria

The noise impact assessment criteria for IUG are specified in PA 08_0101 MOD 6 and EPL 3390. The noise impact assessment criteria (refer to Table 2.1 and Table 2.2) relate only to the noise contribution from IUG.

Table 2.1 Noise Impact Assessment Criteria from PA 08_0101 MOD 6 for IUG, dB(A)

Location Day/Evening/Night1

LAeq, 15 min Night time1

LA1, 1 min

NAG 1 - All privately-owned land 38 / 38 / 36 46

NAG 2 - All privately-owned land 39 / 39 / 37 47

NAG 3 – Property 87 42 / 42 / 42 49

NAG 3 – Property 106 39 / 39 / 39 49

NAG 3 - All other privately-owned land 40 / 40 / 39 49

NAG 4 – Properties 88, 91, 95, 99, 100, 105, 161 35 / 35 / 35 47

NAG 4 - All other privately-owned land 42 / 42 / 37 47

NAG 5 – Property 111 37 / 37 / 37 52

NAG 5 – Property 112 36 / 36 / 36 52

NAG 5 – Property 118 39 / 39 / 39 52

NAG 5 – Property 154 36 /36 / 36 52

NAG 5 – Properties 103, 104, 121, 139 35 / 35 / 35 52

NAG 5 - All other privately-owned land 50 / 46 / 42 52

NAG 6 – Properties 132, 133, 137 35 / 35 / 35 48

NAG 6 - All other privately-owned land 41 / 41 / 38 49

NAG 7 – Property 110 38 / 38 / 38 49

NAG 7 - All other privately-owned land 45 / 42 / 39 49

NAG 8 – Property 142 35 / 35 / 35 45

NAG 8 - All other privately-owned land 42 / 42 / 35 45

NAG 9 – Properties 2, 3, 4, 143, 144, 145, 146, 147, 48, 149, 150, 151, 152

35 / 35 / 35 48

NAG 9 - All other privately-owned land 40 / 40 / 38 48

Page 10: Environmental Noise Monitoring · The noise monitoring and reporting requirements for IUG are outlined in the Integra Underground Mine Project Approval (PA 08_0101 MOD 6) and Environment

Environmental Noise Monitoring 3995_R03_ENM_Final

Assessment Criteria 6

Location Day/Evening/Night1

LAeq, 15 min Night time1

LA1, 1 min

NAG 10 – Property 10 42 / 42 / 42 47

NAG 10 – Property 9 41 / 41 / 41 47

NAG 10 – Properties 11, 13 40 / 40 / 40 47

NAG 10 – Property 8 38 / 38 / 38 47

NAG 10 – Property 6 36 / 36 / 36 47

NAG 10 – Property 5 35 / 35 / 35 47

1 Daytime period is 7.00am to 6.00pm Monday to Saturday and 8.00am to 6.00pm Sundays and Public Holidays. Evening period is 6.00pm to 10.00pm. Night time period is 10.00pm to 7.00am Monday to Saturday and 10.00pm to 8.00am Sundays and Public Holidays.

Table 2.2 Noise Impact Assessment Criteria from EPL 3390 for IUG, dB(A)

Location Day/Evening/Night1

LAeq, 15 min Night time1

LA1, 1 min

NAG 3 - 87 42 / 42 / 42 49

NAG 3 - 106 39 / 39 / 39 49

NAG 3 - All other privately owned land 40 / 40 / 39 49

NAG 4 - 88, 91, 95, 99, 100, 105, 161 35 / 35 / 35 47

NAG 4 - All other privately owned land 42 / 42 / 37 47

NAG 5 – 111 37 / 37 / 37 52

NAG 5 - 103, 104, 121, 139 35 / 35 / 35 52

NAG 5 - All other privately owned land 50 / 46 / 42 52

NAG 6 - 132, 133,137 35 / 35 / 35 48

NAG 6 – All other privately owned land 41 / 41 / 38 48

NAG 7 - All other privately owned land 45 / 42 / 39 49

1 Daytime period is 7.00am to 6.00pm Monday to Saturday and 8.00am to 6.00pm Sundays and Public Holidays. Evening period is 6.00pm to 10.00pm. Night time period is 10.00pm to 7.00am Monday to Saturday and 10.00pm to 8.00am Sundays and Public Holidays.

The meteorological conditions under which the noise impact assessment criteria do not apply are also specified in PA 08_0101 MOD 6 and EPL 3390 (refer to Table 2.3).

Page 11: Environmental Noise Monitoring · The noise monitoring and reporting requirements for IUG are outlined in the Integra Underground Mine Project Approval (PA 08_0101 MOD 6) and Environment

Environmental Noise Monitoring 3995_R03_ENM_Final

Assessment Criteria 7

Table 2.3 Meteorological Exclusions

Parameter EPL 3390 PA 08_0101 MOD 61

Rain None specified During periods of rain or hail

Wind speed at microphone

None specified Average wind speed at microphone height exceeds 5 m/s

Wind speed at 10 m Wind speeds greater than 3 m/s measured at 10 metres above ground level

Wind speeds greater than 3 m/s measured at 10 metres above ground level

Temperature inversion2

Stability category F temperature inversion conditions and wind speeds greater than 2 m/s at 10 metres above ground level; or

Stability category G temperature inversion conditions

Temperature inversion conditions greater than 3°C/100m

1 Except for wind speed at microphone height, the data to be used for determining meteorological conditions shall be that recorded by the meteorological station located on the site (as required by condition 16 of Schedule 3 of PA 08_0101 MOD 6.

2 Temperature inversion conditions (stability category) under EPL 3390 are to be determined by the sigma-theta method referred to in Part E4 of Appendix E to the NSW Industrial Noise Policy.

Page 12: Environmental Noise Monitoring · The noise monitoring and reporting requirements for IUG are outlined in the Integra Underground Mine Project Approval (PA 08_0101 MOD 6) and Environment

Environmental Noise Monitoring 3995_R03_ENM_Final

Compliance Assessment Methodology 8

3.0 Compliance Assessment Methodology

The compliance assessment process addresses compliance with the noise impact assessment criteria (Table 2.1 and Table 2.2) and is only undertaken for periods during which the meteorological conditions are consistent with those under which the criteria apply (refer to Table 2.3). Attended noise monitoring has been used to quantify and describe the acoustic environment around IUG. The compliance assessment methodology involved the following activities:

Attended noise monitoring surveys at each of the monitoring locations during the night-time period to measure the ambient noise levels in the surrounding region and to assess IUG contributions (reported as LAeq, 15 minute) to the measured noise levels.

Comparison of the attended noise monitoring results with the relevant noise impact assessment criteria to assess compliance of IUG operations with the relevant project approvals and EPL criteria.

Comparison of the LA1, 1 minute night-time attended noise monitoring results with the night-time sleep disturbance criteria outlined in the relevant project approvals and EPL criteria.

Page 13: Environmental Noise Monitoring · The noise monitoring and reporting requirements for IUG are outlined in the Integra Underground Mine Project Approval (PA 08_0101 MOD 6) and Environment

Environmental Noise Monitoring 3995_R03_ENM_Final

Attended Noise Monitoring 9

4.0 Attended Noise Monitoring

4.1 Attended Noise Monitoring Program

Attended noise monitoring for IUG is conducted in accordance with the NSW Environment Protection Authority (EPA) Industrial Noise Policy (INP) (2000) guidelines and the Australian Standard AS1055-1997, Acoustics – Description and Measurement of Environmental Noise, Part 1 General Procedures.

In accordance with the Integra Underground Noise Management Plan (Glencore, 2017), for each measurement the following information within the raw dataset is recorded:

Operators name;

Monitoring location;

Dates and times that monitoring began and ended at each location;

Height of the microphone above the ground and, if relevant, distances to building façades or property boundaries;

Qualitative/quantitative meteorological data such as temperature, wind speed, wind direction, cloud cover, humidity, fog, rainfall etc.;

Instrument calibration details before and after measurement;

The LAeq,15 minute noise level for the measurement period;

Statistical noise level descriptors over the measurement period, LAmin, LA90, LA10, LA1 and LAmax;

LA1, 1 minute noise levels (to allow comparison with sleep disturbance criteria);

Notes that identify the noise source(s) that contribute to peak noise levels (LA1 or LAmax);

An estimate of noise contribution from operations at IUG;

An estimate of the noise contribution from other audible mines, if any;

Measurement of C-weighted and A-weighted levels to assess low frequency noise in accordance with Section 4 of the INP (a 5 dB correction is applicable if the difference between the site’s C-weighted and A-weighted level is 15 dB or more);

Data suitable for assessing the relative contribution of mine-generated noise to the overall noise being measured by using a low-pass filter (i.e. consideration of frequencies up to and including 1000 Hz); and

Recommendations and comments, where considered appropriate.

Monitoring is conducted in accordance with the provisions of Appendix 5 of PA 08_0101 MOD 6.

The purpose of attended noise surveys is to quantify and describe the ambient noise environment in the region surrounding IUG and to estimate the contribution of mining-related activities to the ambient noise levels.

Page 14: Environmental Noise Monitoring · The noise monitoring and reporting requirements for IUG are outlined in the Integra Underground Mine Project Approval (PA 08_0101 MOD 6) and Environment

Environmental Noise Monitoring 3995_R03_ENM_Final

Attended Noise Monitoring 10

Attended noise monitoring is undertaken at the locations presented in Table 4.1 and Figure 1.2 and provides the following noise-related information:

Noise data that will assist in identifying noise contributions from IUG;

Noise data that is representative of noise levels at receivers within the localised area; and

Reference noise data that will assist in determining compliance at other receiver locations.

Table 4.1 Attended Noise Monitoring Locations

Monitoring Location Description

NAG 1 Glennies Creek Road, Glennies Creek

NAG 3 Glennies Creek Road, Glennies Creek

NAG 4 Lethbridge Street, Camberwell

NAG 5 Glennie Street, Camberwell

NAG 6 Glennie Street, Camberwell

NAG 7 New England Highway, Camberwell

NAG 8 Bridgman Road, Singleton Heights

NAG 9 Bridgman Road, Obanvale

NAG 10 Bridgman Road, Bridgman

During the attended monitoring session, noise measurements are taken with a Svantek 959 noise and vibration analyser (Serial Number 12918) which is calibrated on site using a Brüel and Kjær Type 4231 Noise Meter Calibrator (Serial Number 2130702) in accordance with the requirements of AS1055-1997. Calibration certificates are included in Appendix 2. The noise meter is run using three measurement profiles (Linear, C Weighting and A Weighting) and records A-weighted 1/3 octave noise levels at 1 second intervals over a 15 minute measurement period. Raw data is available on request.

During the attended monitoring session the operator maintains a log of noise-related events that occur including various noise sources contributing to the ambient noise environment. Particular attention is paid to the contribution of the operations associated with IUG.

Meteorological data for the attended monitoring periods is collected from a Kestrel 4500 weather monitor (Serial Number 665400), positioned within 5 metres and at a corresponding height to the noise monitoring microphone (approximately 1.3 metres from the ground). Supplementary meteorological data is obtained, when required, from Mt Owen Complex’s SentineX meteorological stations.

Page 15: Environmental Noise Monitoring · The noise monitoring and reporting requirements for IUG are outlined in the Integra Underground Mine Project Approval (PA 08_0101 MOD 6) and Environment

Environmental Noise Monitoring 3995_R03_ENM_Final

Attended Noise Monitoring 11

4.2 Attended Noise Monitoring Results for Winter 2017

Attended noise monitoring sessions, comprising of night time assessment periods only, were conducted at nine locations (refer to Table 4.1 and Figure 1.2) during the winter 2017 assessment period in the region surrounding IUG.

The monitoring results are presented graphically in Appendix 3, and include:

Recorded A-weighted 1/3 octave noise levels at 1 second intervals over the 15 minute measurement period

Results of a 1000 Hz low pass filter at 1 second intervals over the 15 minute measurement period

Assessment of the maximum LA1,1minute noise level recorded over the 15 minute measurement period

LAeq, 15 minute, LA10, 15 minute and LA90, 15 minute noise levels for the 15 minute measurement period

Operator comments regarding any extraneous noise sources contributing to the ambient noise levels.

4.3 Monitoring Results Summary

The results of the winter attended noise monitoring session, presented in Appendix 3, indicate that under the meteorological conditions at the time of monitoring, IUG was compliant at all monitoring locations during the monitoring session with the relevant night time LAeq, 15 minute and LA1, 1 minute noise assessment criteria.

The noise impact assessment criteria for IUG are summarised in Table 2.1 and Table 2.2.

Page 16: Environmental Noise Monitoring · The noise monitoring and reporting requirements for IUG are outlined in the Integra Underground Mine Project Approval (PA 08_0101 MOD 6) and Environment

Environmental Noise Monitoring 3995_R03_ENM_Final

Statement of Compliance 12

5.0 Statement of Compliance

The results of the Glencore Integra Underground Mine noise monitoring program for winter 2017 have been assessed against the noise impact assessment criteria outlined in PA 08_0101 MOD 6 and EPL 3390, for meteorological conditions identified in Appendix 5 of PA 08_0101 MOD 6 and Condition L2.2 of EPL 3390.

Results of the attended noise monitoring program conducted during winter 2017 showed that Glencore Integra Underground Mine was complying with the relevant noise assessment criteria for each monitoring period, for the meteorological conditions experienced at the time of monitoring.

Page 17: Environmental Noise Monitoring · The noise monitoring and reporting requirements for IUG are outlined in the Integra Underground Mine Project Approval (PA 08_0101 MOD 6) and Environment

Environmental Noise Monitoring 3995_R03_ENM_Final

References 13

6.0 References

Australian Standard AS1055-1997. Acoustics – Description and Measurement of Environmental Noise, Part 1 General Procedures.

Glencore, 2017. Integra Underground Mine Noise Management Plan.

HV Coking Coal Pty Limited and Bloomfield Collieries Pty Limited, 2016. Application To Modify Project Approval For Integra Underground Project (MP 08_0101) And Integra Open Cut Project (MP 08_0102).

NSW Environment Protection Authority, 2000. New South Wales Industrial Noise Policy.

Page 18: Environmental Noise Monitoring · The noise monitoring and reporting requirements for IUG are outlined in the Integra Underground Mine Project Approval (PA 08_0101 MOD 6) and Environment

APPENDIX 1

Glossary and Abbreviations

Page 19: Environmental Noise Monitoring · The noise monitoring and reporting requirements for IUG are outlined in the Integra Underground Mine Project Approval (PA 08_0101 MOD 6) and Environment

Environmental Noise Monitoring 3995_R03_ENM_Final

Appendix 1 1

Appendix 1 - Glossary and Abbreviations

1/3 Octave Single octave bands divided into three parts.

Octave A division of the frequency range into bands, the upper frequency limit of each band being twice the lower frequency limit.

ABL Assessment background level – A single-figure background noise level representing each assessment period – day, evening and night (that is, three assessment background levels are determined for each 24 hour period of the monitoring period). It is determined by taking the lowest 10th percentile of the L90 level for each assessment period.

Ambient Noise The noise associated with a given environment. Typically a composite of sounds from many sources located both near and far where no particular sound is dominant.

A Weighting A standard weighting of the audible frequencies designed to reflect the response of the human ear to noise.

dB(A), dBA Decibels A-weighted.

dB(L), dB(Lin) Decibels Linear or decibels Z-weighted.

Decibel (dB) The units of sound level and noise exposure measurement where a step of 10 dB is a ten-fold increase in intensity or sound energy and actually sounds a little more than twice as loud.

Hertz (Hz) The measure of frequency of sound wave oscillations per second – one oscillation per second equals 1 hertz.

LA10 The percentile sound pressure level exceeded for 10 per cent of the measurement period with 'A' frequency weighting calculated by statistical analysis. Typically used to assess the impact of an existing operation on a receiver area and is referred to as the cumulative noise levels at the receiver attributable to the noise source.

LA90 Background Noise Level. The percentile sound pressure level exceeded for 90 per cent of the measurement period with 'A' frequency weighting calculated by statistical analysis.

LAmax The maximum of the sound pressure levels recorded over an interval of one second.

LA1,1minute The measure of the short duration high-level noises that cause sleep arousal. The noise level is measured as the percentile sound pressure level that is exceeded one per cent of measurement period with 'A' frequency weighting calculated by statistical analysis during a measurement time interval of one minute.

Page 20: Environmental Noise Monitoring · The noise monitoring and reporting requirements for IUG are outlined in the Integra Underground Mine Project Approval (PA 08_0101 MOD 6) and Environment

Environmental Noise Monitoring 3995_R03_ENM_Final

Appendix 1 2

LAeq,t Equivalent continuous sound pressure level – The value of the sound pressure level of a continuous steady noise that, a measurement interval of time (t), has the same mean square sound pressure as the sound under consideration whose level varies with time. Usually measured in dB with 'A' weighting.

LAn Percentile level – A measure of the fluctuation of the sound pressure level which is exceeded ‘n’ per cent of the observation time.

RBL Rating background level – The overall single figure background level representing each assessment period over the whole monitoring period determined by taking the median of the ABLs found for each assessment period.

SPL (dBA) Noise: Sound pressure level – The basic measure of noise loudness. The level of the root-mean-square sound pressure in decibels given by:

SPL = 10.log10 (p/p0)2

where p is the rms sound pressure in pascals and p0 is the sound reference pressure at 20 µPa. decibels.

SWL Sound power level – a measure of the energy emitted from a source as sound and is given by:

SWL = 10.log10 (W/W0)

where W is the sound power in watts and W0 is the sound reference power at 10-12 watts.

Page 21: Environmental Noise Monitoring · The noise monitoring and reporting requirements for IUG are outlined in the Integra Underground Mine Project Approval (PA 08_0101 MOD 6) and Environment

APPENDIX 2

Calibration Certificates

Page 22: Environmental Noise Monitoring · The noise monitoring and reporting requirements for IUG are outlined in the Integra Underground Mine Project Approval (PA 08_0101 MOD 6) and Environment
Page 23: Environmental Noise Monitoring · The noise monitoring and reporting requirements for IUG are outlined in the Integra Underground Mine Project Approval (PA 08_0101 MOD 6) and Environment
Page 24: Environmental Noise Monitoring · The noise monitoring and reporting requirements for IUG are outlined in the Integra Underground Mine Project Approval (PA 08_0101 MOD 6) and Environment
Page 25: Environmental Noise Monitoring · The noise monitoring and reporting requirements for IUG are outlined in the Integra Underground Mine Project Approval (PA 08_0101 MOD 6) and Environment

APPENDIX 3

Attended Monitoring Results

Page 26: Environmental Noise Monitoring · The noise monitoring and reporting requirements for IUG are outlined in the Integra Underground Mine Project Approval (PA 08_0101 MOD 6) and Environment

Environmental Noise Monitoring 3995_R03_ENM_Final

Appendix 3 1

Appendix 3 – Attended Monitoring Results

Winter - 2017

The results of the attended noise monitoring session are presented graphically as run charts in Figure A3.1 to Figure A3.9.

The results of the attended noise monitoring session are summarised in Table A3.1.

Night Period Compliance Assessment

During the night period attended noise monitoring, the results indicated that under the meteorological conditions at the time of monitoring, Integra Underground Mine was complying with the respective LAeq, 15minute and LA1, 1minute noise impact assessment criteria.

Page 27: Environmental Noise Monitoring · The noise monitoring and reporting requirements for IUG are outlined in the Integra Underground Mine Project Approval (PA 08_0101 MOD 6) and Environment

Environmental Noise Monitoring 3995_R03_ENM_Final

Appendix 3 2

Night Monitoring Results for NAG 1 Glennies Creek Road, Glennies Creek

Date and Time: 24 August 2017, 21:16 to 21:31

Local Conditions: Wind SSE at 0.6 to 0.7 m/s, gusting to 0.8 m/s; 50% cloud cover; 12°C, 74% RH

Operator Comments:

The dominant noise sources contributing to the noise environment at the monitoring location were Rixs Creek Coal Mine, rail traffic noise and an aircraft fly over. Other noise contributions included cattle and distant road traffic noise.

Glencore Integra Underground Mine was not audible during the attended monitoring period.

Figure A3.1

Night Monitoring Results for NAG 1 Glennies Creek Road, Glennies Creek

Page 28: Environmental Noise Monitoring · The noise monitoring and reporting requirements for IUG are outlined in the Integra Underground Mine Project Approval (PA 08_0101 MOD 6) and Environment

Environmental Noise Monitoring 3995_R03_ENM_Final

Appendix 3 3

Night Monitoring Results for NAG 3 Glennies Creek Road, Glennies Creek

Date and Time: 24 August 2017, 21:47 to 22:02

Local Conditions: Wind SSE at 2.5 to 2.7 m/s, gusting to 3.2 m/s; 50% cloud cover, 12°C, 70% RH

Operator Comments:

The dominant noise sources contributing to the noise environment at the monitoring location were Rixs Creek Coal Mine and New England Highway road traffic noise. Other noise contributions included an aircraft flyover, dogs barking, a distant train and occasional wind gust.

Glencore Integra Underground Mine was not audible during the attended monitoring period.

Figure A3.2 Night Monitoring Results for NAG 3 Glennies Creek Road, Glennies Creek

Page 29: Environmental Noise Monitoring · The noise monitoring and reporting requirements for IUG are outlined in the Integra Underground Mine Project Approval (PA 08_0101 MOD 6) and Environment

Environmental Noise Monitoring 3995_R03_ENM_Final

Appendix 3 4

Night Monitoring Results for NAG 4 Lethbridge Street, Camberwell

Date and Time: 24 August 2017, 23:22 to 23:37

Local Conditions: Calm, gusting ESE to 0.4 m/s; 75% cloud cover, 11°C, 69% RH

Operator Comments:

The dominant noise sources contributing to the noise environment at the monitoring location were Rixs Creek Coal Mine and New England Highway road traffic noise. Other noise contributions included dogs barking and domestic noise.

Glencore Integra Underground Mine was not audible during the attended monitoring period.

Figure A3.3 Night Monitoring Results for NAG 4 Lethbridge Street, Camberwell

Page 30: Environmental Noise Monitoring · The noise monitoring and reporting requirements for IUG are outlined in the Integra Underground Mine Project Approval (PA 08_0101 MOD 6) and Environment

Environmental Noise Monitoring 3995_R03_ENM_Final

Appendix 3 5

Night Monitoring Results for NAG 5 Glennie Street, Camberwell

Date and Time: 24 August 2017, 22:26 to 22:41

Local Conditions: Calm, gusting easterly at 0.7 m/s; partly cloudy, 12°C, 70% RH

Operator Comments:

The dominant noise sources contributing to the noise environment at the monitoring location were traffic on the New England Highway and insects. Other noise contributions included an aircraft, birds, dogs and domestic noise.

Glencore Integra Underground Mine was not audible during the attended monitoring period.

Figure A3.4 Night Monitoring Results for NAG 5 Glennie Street, Camberwell

Page 31: Environmental Noise Monitoring · The noise monitoring and reporting requirements for IUG are outlined in the Integra Underground Mine Project Approval (PA 08_0101 MOD 6) and Environment

Environmental Noise Monitoring 3995_R03_ENM_Final

Appendix 3 6

Night Monitoring Results for NAG 6 Glennie Street, Camberwell Date and Time: 14 August 2017, 23:07 to 23:22

Local Conditions: Wind NNW at 0.0 to 0.4 m/s, gusting to 1.0 m/s; clear sky, 9°C, 62% RH

Operator Comments:

The dominant noise sources contributing to the noise environment at the monitoring location were traffic on the New England Highway and Ravensworth Operations mining operational noise from the WNW. Glendell mine and Ashton mine noise was barely audible in the background. Other noise contributions included insects and frog noise.

Glencore Integra Underground Mine was not audible during the attended monitoring period.

Figure A3.5 Night Monitoring Results for NAG 6 Glennie Street, Camberwell

Page 32: Environmental Noise Monitoring · The noise monitoring and reporting requirements for IUG are outlined in the Integra Underground Mine Project Approval (PA 08_0101 MOD 6) and Environment

Environmental Noise Monitoring 3995_R03_ENM_Final

Appendix 3 7

Night Monitoring Results for NAG 7 New England Highway, Camberwell

Date and Time: 25 August 2017, 00:30 to 00:45

Local Conditions: Wind S at 0.0 to 0.7 m/s, gusting to 1.7 m/s; 50% cloud cover, 10°C, 71% RH

Operator Comments:

The dominant noise sources contributing to the noise environment at the monitoring location were traffic on the New England Highway and mining operations to the east. Other noise contributions included insects and frogs.

Glencore Integra Underground Mine was not audible during the attended monitoring period.

Figure A3.6 Night Monitoring Results for NAG 7 New England Highway, Camberwell

Page 33: Environmental Noise Monitoring · The noise monitoring and reporting requirements for IUG are outlined in the Integra Underground Mine Project Approval (PA 08_0101 MOD 6) and Environment

Environmental Noise Monitoring 3995_R03_ENM_Final

Appendix 3 8

Night Monitoring Results for NAG 8 Bridgman Road, Singleton Heights Date and Time: 25 August 2017, 01:07 to 01:22

Local Conditions: Wind SSE at 0.0 to 0.7 m/s, gusting to 1.3 m/s, few clouds, 11°C, 70% RH

Operator Comments:

The dominant noise sources contributing to the noise environment at the monitoring location were train noise, distant road traffic noise and a domestic stereo. Other noise contributions included dogs and wind in the trees.

Glencore Integra Underground Mine was not audible during the attended monitoring period.

Figure A3.7 Night Monitoring Results for NAG 8 Bridgman Road, Singleton Heights

Page 34: Environmental Noise Monitoring · The noise monitoring and reporting requirements for IUG are outlined in the Integra Underground Mine Project Approval (PA 08_0101 MOD 6) and Environment

Environmental Noise Monitoring 3995_R03_ENM_Final

Appendix 3 9

Night Monitoring Results for NAG 9 Bridgman Road, Obanvale

Date and Time: 25 August 2017, 01:35 to 01:50

Local Conditions: Wind S at 0.7 to 1.1 m/s, gusting to 2.1 m/s; partial cloud cover, 11°C, 70% RH

Operator Comments:

The dominant noise sources contributing to the noise environment at the monitoring location were mining operations to the southwest and passing cars. Other noise contributions included wind in the trees, cattle and distant road traffic noise.

Glencore Integra Underground Mine was not audible during the attended monitoring period.

Figure A3.8 Night Monitoring Results for NAG 9 Bridgman Road, Obanvale

Page 35: Environmental Noise Monitoring · The noise monitoring and reporting requirements for IUG are outlined in the Integra Underground Mine Project Approval (PA 08_0101 MOD 6) and Environment

Environmental Noise Monitoring 3995_R03_ENM_Final

Appendix 3 10

Night Monitoring Results for NAG 10 Bridgman Road, Bridgman Date and Time: 25 August 2017, 02:04 to 02:19

Local Conditions: Wind SW to WNW at 0.4 to 0.7 m/s, gusting to 1.3 m/s; overcast, 11°C, 68% RH

Operator Comments:

The dominant noise sources contributing to the noise environment at the monitoring location were mining operations to the southwest and wind in the trees. Other noise contributions included distant and local road traffic and a train.

Glencore Integra Underground Mine was not audible during the attended monitoring period.

Figure A3.9 Night Monitoring Results for NAG 10 Bridgman Road, Bridgman

Page 36: Environmental Noise Monitoring · The noise monitoring and reporting requirements for IUG are outlined in the Integra Underground Mine Project Approval (PA 08_0101 MOD 6) and Environment

Environmental Noise Monitoring 3995_R03_ENM_Final

Appendix 3 11

Table A3.1 – Summary of Attended Noise Monitoring – Night Period, 18 - 30 May 2017, dB(A)

Loca

tio

n

Start Time Measured Noise Levels Criteria

Estimated1 IUG

Contribution

Compliant

Y/N Criteria

Estimated1 IUG

Contribution

Compliant

Y/N Meteorological Assessment (1

5 m

in p

eri

od

)

LA9

0, 1

5min

LAe

q, 1

5min

LA1

, 1 m

in

LAeq, 15min LA1, 1 min Local Meteorological Conditions2

Assessable under

PA 08_0101

MOD 6;

EPL 3390

Night Period – 24 - 25 August 2017

NAG1 21:16 35.8 41.2 60.1 36 Not audible Y 46 Not audible Y Wind SSE at 0.6 to 0.7 m/s, gusting to 0.8 m/s; 50% cloud cover; 12°C, 74% RH

Y

NAG3 21:47 43.2 46.6 52.7 393 Not audible Y 49 Not audible Y Wind SSE at 2.5 to 2.7 m/s, gusting to 3.2 m/s; 50% cloud cover, 12°C, 70% RH

Y

NAG4 23:22 37.2 44.9 55.9 353 Not audible Y 47 Not audible Y Calm, gusting ESE to 0.4 m/s; 75% cloud cover, 11°C, 69% RH

Y

NAG5 22:26 43.4 51.4 58.4 353 Not audible Y 52 Not audible Y Calm, gusting easterly at 0.7 m/s; partly cloudy, 12°C, 70% RH

Y

NAG6 23:07 33.2 37.3 49.9 353 Not audible Y 48 Not audible Y Wind NNW at 0.0 to 0.4 m/s, gusting to 1.0 m/s; clear sky, 9°C, 62% RH

Y

NAG74 0:30 43.7 50.1 56.9 38 Not audible Y 483 Not audible Y Wind S at 0.0 to 0.7 m/s, gusting to 1.7 m/s; 50% cloud cover, 10°C, 71% RH

Y

NAG8 1:07 35.7 44.9 56.6 35 Not audible Y 45 Not audible Y Wind SSE at 0.0 to 0.7 m/s, gusting to 1.3 m/s, few clouds, 11°C, 70% RH

Y

NAG9 1:35 36.5 53.4 75.1 353 Not audible Y 48 Not audible Y Wind S at 0.7 to 1.1 m/s, gusting to 2.1 m/s; partial cloud cover, 11°C, 70% RH

Y

NAG10 2:04 37.5 41.6 47.4 353 Not audible Y 47 Not audible Y Wind SW to WNW at 0.4 to 0.7 m/s, gusting to 1.3 m/s; overcast, 11°C, 68% RH

Y

1 Assessed by the operator during the monitoring session.

2 Meteorological conditions are a summary of meteorological data from the attended monitoring period from a Kestrel 4500 weather monitor, Serial Number 645400, positioned within 5 metres and at a corresponding height to the noise monitoring

microphone. Determination of strength of temperature inversions (if present) is only made if a non-compliance of noise criteria is likely.

3 Assessable under PA 08_0101 MOD 6 and EPL 3390

4 Criteria listed represent the lowest criteria within this Noise Assessment Group of both PA 08_0101 MOD 6 and EPL 3390.

Page 37: Environmental Noise Monitoring · The noise monitoring and reporting requirements for IUG are outlined in the Integra Underground Mine Project Approval (PA 08_0101 MOD 6) and Environment

Newcastle

75 York Street Teralba NSW 2284

Perth

PO Box 783 West Perth WA 6872 First Floor 9 Havelock Street West Perth WA 6005

Canberra

PO Box 6135 56 Bluebell Street O’Connor ACT 2602

Sydney

50 York Street Sydney NSW 2000

Brisbane

Level 11 500 Queen Street Brisbane QLD 4000

Ph. 02 4950 5322 Ph. 08 6260 0700 Ph. 02 6262 9484 Ph. 1300 793 267 Ph. 1300 793 267

www.umwelt.com.au