Environmental Monitoring Report
Quarterly Report April 2011
VIE: Greater Mekong Subregion Kunming–Hai
Phong Transport Corridor Noi Bai–Lao Cai Highway
Project
Prepared by Vietnam Expressway Corporation for the Ministry of Transport and the Asian
Development Bank.
CURRENCY EQUIVALENTS (as of 30 April 2011)
Currency unit – dong (D)
D1.00 = $0.000048 $1.00 = D20,550
ABBREVIATIONS
ADB – Asian Development Bank EIA – environmental impact assessment EQR – environmental quarterly report km – kilometer L – liter m – meter mg – milligram ml – milliliter m3 – cubic meter MONRE – Ministry of Natural Resources and Environment MOT – Ministry of Transport NAN – non-accordance notification NB–LC – Noi Bai–Lao Cai PMU – project management unit PSC – project supervision consultants TSP – total suspended particles TSS – total suspended solids VEC – Vietnam Expressway Corporation
NOTE
In this report, "$" refers to US dollars unless otherwise stated. This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
Hanoi office : 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da District Vinh Phuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Dist, Vinh Phuc Province Madrid Spain head office: C/ Ramón de Aguinaga No 8, 28028 Madrid, Spain/ Web Page: www.getinsa.com
QUARTERLY ENVIRONMENTAL MONITORING REPORT
APRIL 2011
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
1 | P a g e
INDEX
ABBREVIATIONS……………………………………………………………...……………3
1. INTRODUCTION. REPORT’S FRAMEWORK ............................................................. 4
2. CONSTRUCTION WORKS PROGRESS DURING THE PERIOD ............................... 7
2.1 PACKAGE A1 ................................................................................................................. 7
2.2 PACKAGE A2 ................................................................................................................. 9
2.3 PACKAGE A3 ............................................................................................................... 11
2.4 PACKAGE A4 ............................................................................................................... 12
2.5 PACKAGE A5 ............................................................................................................... 13
2.6 PACKAGE A6 ............................................................................................................... 14
2.7 PACKAGE A7 ............................................................................................................... 17
2.8 PACKAGE A8 ............................................................................................................... 18
3. CARRIED OUT TASKS DURING THE PERIOD ........................................................ 20
3.1 PACKAGE A1 ............................................................................................................... 20
3.2 PACKAGE A2 ............................................................................................................... 21
3.3 PACKAGE A3 ............................................................................................................... 23
3.4 PACKAGE A4 ............................................................................................................... 24
3.5 PACKAGE A5 ............................................................................................................... 25
3.6 PACKAGE A6 ............................................................................................................... 26
3.7 PACKAGE A7 ............................................................................................................... 27
3.8 PACKAGE A8 ............................................................................................................... 29
4. ENVIRONMENTAL MONITORING RESULTS. COMPLEMENTARY MEASURES TO
BE APPLIED ............................................................................................................... 31
4.1 PROBLEMS AND RECOMMENDATIONS. SUMMARY TABLE .............................. 31
4.3 WATER QUALITY ........................................................................................................ 60
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
2 | P a g e
4.4 SOILS QUALITY ........................................................................................................... 75
4.5 NOISE AND VIBRATION LEVELS ............................................................................. 82
4.6 STREAMS AND RIVERSIDES MAINTENANCE ....................................................... 98
4.7 EROSION RISKS AND STABILITY IN SLOPES ..................................................... 106
4.8 HAZARDOUS SUBSTANCES MANAGEMENT ...................................................... 112
4.9 UNSUITABLE MATERIAL DISPOSALS AND BORROW PITS ............................. 119
4.10 WORKER’S CAMPS CONDITIONS .......................................................................... 128
4.11 WASTE AND CLEANLINESS IN SITE ..................................................................... 137
4.12 BIODIVERSITY PRESERVATION ............................................................................ 143
5. REFERENCE DOCUMENTS RELATIVE TO ENVIRONMENT ................................ 150
5.1 PACKAGE A1 ............................................................................................................. 150
5.2 PACKAGE A2 ............................................................................................................. 150
5.3 PACKAGE A3 ............................................................................................................. 151
5.4 PACKAGE A4 ............................................................................................................. 152
5.5 PACKAGE A5 ............................................................................................................. 153
5.6 PACKAGE A6 ............................................................................................................. 153
5.7 PACKAGE A7 ............................................................................................................. 155
5.8 PACKAGE A8 ............................................................................................................. 156
ANNEX 1: PHOTOGRAPHIC REPORT ............................................................................. 157
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
3 | P a g e
ABBREVIATIONS
ADB Asian Development Bank
EIA Environmental Impact Assessment
EQR Environmental Quarterly Report
MONRE Ministry of Natural Resources and Environment
MOT Ministry of Transport
NAN Non Accordance Notification
NB-LC Noi Bai - Lao Cai
PSC Project Supervision Consultants
VEC Vietnam Expressway Corporation
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
4 | P a g e
1. INTRODUCTION. REPORT’S FRAMEWORK
Within the framework of the Environmental Control Plans proposed by the contractors and
the duties of the Consultant in this matter contained in the Consulting Services Contract, the
environmental team of specialists in charge of inspecting the environmental conditions of the
works for the new highway, have done weekly inspections along the sites and surroundings
of all the Packages which nowadays have already begun their construction activities,
checking the environmental measures applied by the constructors and detecting any impacts
that could be generated by the building works during the period of reference of this report,
that means, January, February and March 2011. So, this document is defined as a Quarterly
Environmental Monitoring Report (hereinafter called EQR).
Noi Bai - Lao Cai highway is a part of Kunming - Hai Phong Transport Corridor, which has
been studied with a total length of 865 km passing Yunnan province of China and Lao Cai,
Yen Bai, Phu Tho, Vinh Phuc, Ha Noi, Bac Ninh, Hai Duong, Quang Ninh and Hai Phong
provinces of Vietnam.
Viet Nam Express Corporation (VEC), which is a state owner company, is the proposer of
this project. The executing agency of it, is the Ministry of Transport (MOT), and it’s being
financed by Asian Development Bank (ADB) an the Government of VietNam.
According to original design, Noi Bai - Lao Cai highway has a total length of about 262.4 km,
passing through 72 communes and 18 districts of provinces and cities as Ha Noi, Vinh Phuc,
Vinh Yen, Yen Bai, Phu Tho, and Lao Cai.
The construction of project is divided into two phases, in which the first phase will construct
244 km with 4 lanes from Ha Noi to Yen Bai and 2 lanes from Yen Bai to Lao Cai. The
second phase will be the widen section of the former with 6 lanes from Ha Noi to Yen Bai
and 4 lanes from Yen Bai to Lao Cai (Chinese border, 262 km).
Construction of the whole project, first phase, is divided into 8 packages including A1, A2,
A3, A4, A5, A6, A7 and A8. All of them have already begun their construction activities. The
length, location and the status of works in each package are described in the following
paragraphs.
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
5 | P a g e
- Package A1 is about 26,60km of length with start point at station Km 0+070 and finish
at station Km 26+700. Package A1 goes through the Soc Son district of Hanoi City
and Vinh Phuc province. Working.
- Package A2 is about 22.120km of length and goes through the Vinh Phuc province
and a little of Phu Tho province. Package A2 has start point at station Km 26+700
and finish at station Km 48+820. It must cross Lo River, with a long bridge. Working.
- Package A3 is about 32.240km of length with start point at station Km48+360 and
end point at station km80+00. Package A3 goes through the Phu Tho province. The
Contractor divided Package A3 into 7 sections and 17 big and small bridges. The
most significative is the bridge to cross over Red River. Working.
- Package A4 has beginning point at km 80+000 of Cam Khe district, Phu Tho province
and ending point at Km109+750 of Tran Yen district, Yen Bai province. Total length is
29.750 m. Working.
- Package A5 has beginning point at Km109+750 of Tran Yen district, Yen Bai
province and ending point at Km150+900 of Van Yen district, Yen Bai province. Total
length is 41.150 m. Working.
- Package A6 lengthens from beginning point Km150+900 of Van Yen district, Yen Bai
province to Km190+420 of Van Ban district, Lao Cai province. Total length is 39.520
m. Almost alignment goes in through high mountains of Yen Bai and Lao Cai
province and overcome natural streams by 18 bridges. This section also includes 1
tunnel under range of mountain at Km186+500. Working.
- Package A7 lengthens from beginning point Km190+420 of Van Ban district, Lao Cai
province to Km 218+040 of Bao Thang district, Lao Cai province. Almost alignment
also goes in through high mountains and 18 bridges are needed. Khe Sang bridge is
the biggest one with a length of 287m. Working.
- Package A8 begins in station Km 218+040 of Bao Thang district, Lao Cai province
and finishes in Km 244+155 of Bao Thang district, Lao Cai province. 6 bridges
overcome streams and natural valleys. Suoi Trat bridge is the biggest one with the
length of 374,8m. Working.
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
6 | P a g e
The environmental monitoring program is carried out in compliance with regulations of
Vietnam Government and ADB safeguard policy in order to control environmental impacts
and ensure the environment is well preserved. The VEC proponent should perform
environmental protection measures stated in the EIA report as well as requirements written in
the approval decision made by MONRE. In accordance with article 23 of the Environmental
Protection Law and article 15 of Decree 80/2006/ND-CP, MONRE will organize, direct, and
monitor the environmental protection measures performed by VEC as stated in the EIA
report approved.
At present, this environmental monitoring program is being undertaken by Environmental
specialists of Getinsa hired by Vietnam Expressway Corporation (VEC). EPMU, the Project
Manager, monitors the environmental protection measures for the contractors carrying on
their works incompliance with the environmental control and protection plan in the contract.
In addition to that, during monitoring process, the environmental specialists and contractors
will try to find out and mitigate unanticipated environmental impacts arising from the project
construction process.
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
7 | P a g e
2. CONSTRUCTION WORKS PROGRESS DURING THE PERIOD
In this chapter, they are included all the works already done or in process during the period,
in each package and detailing the section where the works are developed.
2.1 PACKAGE A1
January
Sec 1: Km 0+900 ~ Km 4+350 Site clearing, Excavation and
Embankment work
Sec 2: Km 0+080 ~ Km 1+000 & Km
4+350 ~ Km 7+661 Site clearing and Embankment work
Sec 3: Km 7+661 ~ Km 10+771 Site clearing and Embankment work
Sec 4: Km 10+771 ~ Km15+030 Site clearing and Embankment work
Sec 5: Km 15+030 ~ Km 18+400 Site clearing and Embankment work
Sec 6: Km 18+400 ~ Km 21+900 Site clearing and Embankment work
Sec 7: Km 21+900 ~ Km 23+900 Site clearing and Embankment work
Sec 8: Km 23+900 ~ Km 26+700 Site clearing and Embankment work
Underpass QL2 Eearth work
Tan Loi bridge Bored pile work
Xuan Phuong bridge (Km 7+660.05) Mobilizing equipment and man power
NTT bridge (Km 7 + 854.7) Pier and PIC girder
Ba Thien bridge (Km 14+026)
I.C 3 bridge (Km 14+590) Pier and PCI girder
Bon bridge (Km 15+107) Bored pile work
TL302B bridge (Km 15+825) Foundation and pier work
TL-TK bridge (Km 19+120.05) Pier and PCI girder work
Cam I bridge (Km 21+910.05) Foundation and Pier work
Cam II bridge Bored pile work
TL302CII bridge (Km 22+480.05) PCI girder work
Army I bridge Bored pile work
NH2B bridge (Km 24+946) PCI girder work
February
Sec 1: Km 0+900 ~ Km 4+350 Site clearing and embankment work
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
8 | P a g e
Sec 2: Km 0+080 ~ Km 1+000 & Km
4+350 ~ Km 7+661 Site clearing and Embankment work
Sec 3: Km 7+661 ~ Km 10+771 Embankment work
Sec 4: Km 10+771 ~ Km15+030 Embankment work
Sec 5: Km 15+030 ~ Km 18+400 Embankment work
Sec 6: Km 18+400 ~ Km 21+900 Embankment work
Sec 7: Km 21+900 ~ Km 23+900 Site clearing and Embankment work
Sec 8: Km 23+900 ~ Km 26+700 Embankment work
Underpass QL2 Excavation work
TL402 bridge (Km 3+053.55) Structure work
Trung Kien bridge (Km 4+491) Bored pile and abutment
Dai Duong bridge (Km 7+392.65) Bored pile and abutment
Xuan Phuong bridge (Km 7+660.05) No activities
NTT bridge (Km 7 + 854.7) Pier and PIC girder
Ba Thien bridge (Km 14+026) Substructure work
I.C 3 bridge (Km 14+590) Pier and PCI girder
Bon bridge (Km 15+107) Bored pile work
TL302B bridge (Km 15+825) Detour road work
TL-TK bridge (Km 19+120.05) Pier and PCI girder work
Cam I bridge (Km 21+910.05) Substructure work
Cam II bridge Substructure work
TL302CII bridge (Km 22+480.05) PC voided Slab
Army I bridge Substructure work
NH2B bridge (Km 24+946) PCI girder work
March
Sec 1: Km 0+900 ~ Km 4+350 Site clearing and embankment work
Sec 2: Km 0+080 ~ Km 1+000 & Km
4+350 ~ Km 7+661 Site clearing and Embankment work
Sec 3: Km 7+661 ~ Km 10+771 Embankment work
Sec 4: Km 10+771 ~ Km15+030 Embankment work
Sec 5: Km 15+030 ~ Km 18+400 Embankment work
Sec 6: Km 18+400 ~ Km 21+900 Embankment work
Sec 7: Km 21+900 ~ Km 23+900 Site clearing and Embankment work
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
9 | P a g e
Sec 8: Km 23+900 ~ Km 26+700 Embankment work
Underpass QL2 Excavation work
TL402 bridge (Km 3+053.55) Structure work
Trung Kien bridge (Km 4+491) Bored pile and abutment
Dai Duong bridge (Km 7+392.65) Bored pile and abutment
Xuan Phuong bridge (Km 7+660.05) Substructure work
NTT bridge (Km 7 + 854.7) Pier and PIC girder
Ba Thien bridge (Km 14+026) Substructure work
I.C 3 bridge (Km 14+590) Pier and PCI girder
Bon bridge (Km 15+107) Bored pile work
TL302B bridge (Km 15+825) Substructure work
TL-TK bridge (Km 19+120.05) Pier and PCI girder work
Cam I bridge (Km 21+910.05) Substructure work
Cam II bridge Substructure work
TL302CII bridge (Km 22+480.05) PC voided Slab & launching girders
Army I bridge Substructure work
NH2B bridge (Km 24+946) PCI girder work
2.2 PACKAGE A2
January
Sec 1: Km 26+700~Km 32+700 Site clearing, embankment and backfill
Sec 2: Km 32+700~Km 35+300 Site clearing and embankment
Sec 3: Km 35+300~Km36+910 Site clearing and embankment
Sec 4: Km 36+910~Km 39+850 Site clearing and embankment
Sec 5: Km 39+580~Km 40+690 Site clearing and earthworks
Sec 6: Km 40+690~Km 45+300 Site clearing and earthworks
Sec 7: Km 43+400~Km 45+300 Site clearing and earthworks
Sec 8: Km 45+300~Km 47+660 Site clearing and earthworks
TL310 bridge (~Km 29+200) Bored pile works
Army II bridge (Km 27+015) Bored pile works
Army III bridge (Km 28+010)
Phung Nguyen bridge (Km 39+188) Pier works
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
10 | P a g e
Lo river bridge (Km 48+000) Equipment mobilization and bored pile works
February
Sec 1: Km 26+700~Km 32+700 Site clearing; embankment; remove unsuitable
material
Sec 2: Km 32+700~Km 35+300 Site clearing; embankment
Sec 3: Km 35+300~Km36+910 Embankment
Sec 4: Km 36+910~Km 39+850 Embankment
Sec 5: Km 39+580~Km 40+690 Embankment
Sec 6: Km 40+690~Km 45+300 Site clearing and embankment
Sec 7: Km 43+400~Km 45+300 Embankment
Sec 8: Km 45+300~Km 47+660 No activities
Army II bridge (Km 27+015) Framework mobilization
Army III bridge (Km 28+010) Framework mobilization
TL310 bridge (~Km 29+200) Bored pile and foundation work
Tan Dung bridge Bored pile work
Ben Gao bridge Bored pile work
Song Dao bridge Bored pile work
Phung Nguyen bridge (Km 39+188) Sub-structure work and PCI girder
Lo river bridge (Km 48+000) Bored pile work
March
Sec 1: Km 26+700~Km 32+700 Site clearing; embankment; remove unsuitable
material
Sec 2: Km 32+700~Km 35+300 Site clearing; embankment
Sec 3: Km 35+300~Km36+910 Embankment
Sec 4: Km 36+910~Km 39+850 Embankment
Sec 5: Km 39+580~Km 40+690 Embankment
Sec 6: Km 40+690~Km 45+300 Site clearing and embankment
Sec 7: Km 43+400~Km 45+300 Embankment
Sec 8: Km 45+300~Km 47+660 No activities
Army II bridge (Km 27+015) Substructure work
Army III bridge (Km 28+010) Substructure work
TL310 bridge (~Km 29+200) Bored pile and substructure work
Ben Tre bridge (Km 31+068) Bored pile work
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
11 | P a g e
Tan Dung bridge (Km 31+245.05) Bored pile work
Ben Gao bridge (Km 35+211.05) Bored pile work
TL305 bridge (Km 37+951.55) Bored pile work
Song Dao bridge (Km 38+450.05) Bored pile work
Phung Nguyen bridge (Km 39+188) Sub-structure work and void slap girder
Lo river bridge (Km 48+181.30) Bored pile work
2.3 PACKAGE A3
January
TL323B Bridge – Km 51 Sub - structure
Bai Bang railway Flyover - Km60+967.05 Finished: 70 bored piles(left 35 bored piles)
IC8 - Km54+640 Preparation of bore pile space
Red river Bridge – km77+800 Drilling the first bore pile
National railway flyover – Km77+246 Finished: 60 bored piles (stop work)
Section 1: Km48+360-Km54+000 Site clearing and excavation&filling work
Section 2: Km54+000-Km59+600 Site clearing and excavation&filling work
Section 3: Km59+600-Km65+390 Embankment work and topsoil remove
Section 4: Km65+390-Km69+070 Site clearing and excavation&filling work
Section 5: Km69+070-Km73+070 Site clearing and excavation&filling work
Section 6: Km73+070-Km77+620 Embankment work and topsoil remove
Section 7: Km77+620-Km80+000 Not yet active (Obstruction)
February
TL323B Bridge – Km 51 Sub – structure
Bai Bang railway Flyover - Km60+967.05 Finished: 75 bored piles(left 30 bored piles)
IC8 - Km54+640 Finished: 34 bored piles ( preparation to sub-
structure)
Red river Bridge – km77+800 Finished: 7 bored piles
National railway flyover – Km77+246 Sub - structure
Section 1: Km48+360-Km54+000 Site clearing and excavation&filling work
Section 2: Km54+000-Km59+600 Site clearing and excavation&filling work
Section 3: Km59+600-Km65+390 Embankment work and topsoil remove
Section 4: Km65+390-Km69+070 Site clearing and excavation&filling work
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
12 | P a g e
Section 5: Km69+070-Km73+070 Site clearing and excavation&filling work
Section 6: Km73+070-Km77+620 Embankment work and topsoil remove
Section 7: Km77+620-Km80+000 Not yet active (Obstruction)
March
TL323B Bridge – Km 51 Execute sub-structure
BaiBang railway Flyover - Km60+967.05 Finished: 75 bored piles (stop work because rain)
IC8 - Km54+640 Execute sub-structure (stop work because rain)
Red river Bridge – km77+800 Finished: 11 bored piles
National railway flyover – Km77+246 Execute sub-structure
Ho Chi Minh IC- Km65+540 Finished: 2 bore piles
Section 1: Km48+360-Km54+000 Excavation & filling work
Section 2: Km54+000-Km59+600 Earth work and Implement box culvert
Section 3: Km59+600-Km65+390 Embankment work and Implement box and pipe
culvert
Section 4: Km65+390-Km69+070 Excavation & filling work
Section 5: Km69+070-Km73+070 Excavation & filling work
Section 6: Km73+070-Km77+620 Excavation & filling work and Implement pipe
and box culvert
Section 7: Km77+620-Km80+000 Not yet active (Obstruction)
2.4 PACKAGE A4
January
Ngoi Lao Bridge - Km77+200 Topographic drilling
Ngoi Van bridge – Km108+960 Topographic drilling
Dam Nang Bridge – Km108+227 Topographic drilling
Section 1: Km80+00-Km85+000 Not yet worked
Section 2: Km85+000-Km89+600 Not yet worked
Section 3: Km89+600-Km96+200 Site clearing
Section 4: Km96+200-Km100+000 Site clearing
Section 5: Km100+000-Km105+000 Not yet worked
Section 6: Km105+000-Km109+750 Site clearing
February
Ngoi Lao Bridge - Km77+200 Topographic drilling
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
13 | P a g e
Ngoi Van bridge – Km108+960 Topographic drilling
Dam Nang Bridge – Km108+227 Topographic drilling
Section 1: Km80+00-Km85+000 Not yet working
Section 2: Km85+000-Km89+600 Not yet working
Section 3: Km89+600-Km96+200 Site clearing
Section 4: Km96+200-Km100+000 Site clearing
Section 5: Km100+000-Km105+000 Not yet working
Section 6: Km105+000-Km109+750 Site clearing
March
Ngoi Lao bridge Km97+100 Preparation place for drilling bore pile
Ngoi Gianh bridge Km88+700 Not yet work
Ngoi Van bridge Km108+960 Preparation place for drilling bore pile
Section 1: Km80+000-Km85+000 Site clearing
Section 2: Km85+000-Km89+600 Site clearing
Section 3: Km89+600-Km96+200 Site clearing and top soil remove
Section 4: Km96+200-Km100+000 Site clearing
Section 5: Km100+000-Km105+000 Site clearing
Section 6: Km105+000-Km109+750 Site clearing
2.5 PACKAGE A5
February
Section 1: Km109+750 - Km115+800 Site clearing work
Section 2: Km115+800 - Km120+000 Site clearing work
Section 3: Km120+000 - Km125+000 Site clearing work
Section 4: Km125+000 - Km130+000 Not yet active
Section 5: Km130+000 - Km136+400 Checking existing ground
Section 6: Km136+400 - Km142+000 Site clearing work
Section 7: Km142+000 - Km148+000 Not yet active
Section 8: Km148+000 - Km150+900 Checking existing ground
March
Section 1: Km109+750 - Km115+800 Site clearing and excavation & filling work
Section 2: Km115+800 - Km120+000 Site clearing work
Section 3: Km120+000 - Km125+000 Site clearing work
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
14 | P a g e
Section 4: Km125+000 - Km130+000 Checking existing ground
Section 5: Km130+000 - Km136+400 Checking existing ground
Section 6: Km136+400 - Km142+000 Site clearing work
Section 7: Km142+000 - Km148+000 Site clearing work
Section 8: Km148+000 - Km150+900 Checking existing ground
2.6 PACKAGE A6
January
Ngoi That bridge Access road
Ngoi Rom bridge Excavation of Foundation and inspection
Ngoi Cong bridge Excavation of Foundation, Bored Pile
preparation
Ngoi Giam I bridge Excavation of Foundation, Board pile
preparation
Ngoi Giam II bridge Assembly of footing rebar and formwork
Ngoi Hut bridge Excavation of Foundation
Ngoi Chac bridge Existing ground elevation inspection
Ngoi Pha bridge Existing ground elevation inspection
Ngoi Nhuoc bridge Excavation of Foundation (A1, A2), temporary
access road
Lang Nhay bridge Excavation of Foundation
Ngoi Don bridge Excavation of Foundation
Suoi Nau bridge Excavation of Foundation
Suoi Quan bridge Excavation of Foundation
Section 1: Km150+900 -
Km156+000
Site clearing and excavation & filling work
Section 2: Km156+000 -
Km162+000
Site clearing and excavation & filling work
Section 3: Km162+000 -
Km165+000
Site clearing and excavation & filling work
Section 4: Km165+000 -
Km168+000
Site clearing and excavation & filling work
Section 5: Km168+000 - Site clearing and excavation work
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
15 | P a g e
Km172+000
Section 6: Km172+000 -
Km176+713
Site clearing and excavation & filling work
Section 7: Km176+713 -
Km182+214
Site clearing and excavation & filling work
Section 8: Km182+214 -
Km186+200
Site clearing and excavation work
Section 9: Km186+730 -
Km190+420
Site clearing and excavation & filling work
February
Ngoi That bridge Structural Excavation without cofferdam
Ngoi Rom bridge Excavation of Foundation and inspection
Ngoi Cong bridge Excavation of Foundation, Bored Pile
preparation
Ngoi Giam I bridge Structural Excavation without cofferdam
Ngoi Giam II bridge Structural Excavation without cofferdam
Ngoi Hut bridge Structural Excavation without cofferdam
Ngoi Chac bridge Existing ground elevation inspection
Ngoi Pha bridge Existing ground elevation inspection
Ngoi Nhuoc bridge Structural Excavation without cofferdam
Lang Nhay bridge Structural Excavation without cofferdam
Ngoi Don bridge Structural Excavation without cofferdam
Suoi Nau bridge Excavation of Foundation
Suoi Quan bridge Structural Excavation without cofferdam
Lang Lau bridge Structural Excavation without cofferdam
Section 1: Km150+900 -
Km156+000
Site clearing and excavation & filling work
Section 2: Km156+000 -
Km162+000
Site clearing and excavation & filling work
Section 3: Km162+000 -
Km165+000
Site clearing and excavation & filling work
Section 4: Km165+000 -
Km168+000
Site clearing and excavation & filling work
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
16 | P a g e
Section 5: Km168+000 -
Km172+000
Site clearing and excavation & filling work
Section 6: Km172+000 -
Km176+713
Site clearing and excavation & filling work
Section 7: Km176+713 -
Km182+214
Site clearing and excavation & filling work
Section 8: Km182+214 -
Km186+200
Site clearing and excavation & filling work
Section 9: Km186+730 -
Km190+420
Site clearing and excavation & filling work
March
Ngoi That bridge Structural Excavation without cofferdam
Ngoi Rom bridge Structural Excavation without cofferdam
Ngoi Cong bridge Structural Excavation without cofferdam
Ngoi Giam I bridge Structural Excavation without cofferdam
Ngoi Giam II bridge Structural Excavation without cofferdam
Ngoi Hut bridge Structural Excavation without cofferdam
Ngoi Chac bridge Existing ground elevation inspection
Ngoi Pha bridge Existing ground elevation inspection
Ngoi Nhuoc bridge Structural Excavation without cofferdam
Lang Nhay bridge Structural Excavation without cofferdam
Ngoi Don bridge Structural Excavation without cofferdam
Suoi Nau bridge Excavation of Foundation
Suoi Quan bridge Structural Excavation without cofferdam
Lang Lau bridge Structural Excavation without cofferdam
Dai Viet bridge Structural Excavation without cofferdam
Section 1: Km150+900 - Km156+000 Site clearing and excavation & filling work
Section 2: Km156+000 - Km162+000 Site clearing and excavation & filling work
Section 3: Km162+000 - Km165+000 Site clearing and excavation & filling work
Section 4: Km165+000 - Km168+000 Site clearing and excavation & filling work
Section 5: Km168+000 - Km172+000 Site clearing and excavation & filling work
Section 6: Km172+000 - Km176+713 Site clearing and excavation & filling work
Section 7: Km176+713 - Km182+214 Site clearing and excavation & filling work
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
17 | P a g e
Section 8: Km182+214 - Km186+200 Site clearing and excavation & filling work
Section 9: Km186+730 - Km190+420 Site clearing and excavation & filling work
2.7 PACKAGE A7
January
Khe Sang bridge Bore pile by manpower, 3 hole
Casting Abutment A1 (Class 2)
Khe U bridge Casting Abutment A1 (Class 2)
Tan An Bridge Structure excavation without cofferdam
Khe Can bridge Spread foundation P1
Khe Dai bridge Casting Abutment A1
Section 1: Km190+420-Km201+000 Rock excavation to fill; common excavation
and unsuitable material
Section 2: Km201+000-Km207+000 Rock excavation to fill; common excavation
and unsuitable material
Section 3: Km207+000- Km218+040 Common excavation and unsuitable material
February
Khe Sang bridge Casting Pier P2
Tan An Bridge Reinforcing steel bar
Section1: Km190+420-Km201+000
Rock excavation to fill
Unsuitable material
Common excavation
Section2: Km201+000-Km207+000 Rock excavation to fill and unsuitable
material
Section3: Km207+000-Km218+040
Rock excavation to fill
Unsuitable material
Common excavation
March
Section1: Km190+420-Km201+000 Unsuitable material and common excavation
Section2: Km201+000-Km207+000
Rock excavation to fill
Unsuitable material
Common excavation
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
18 | P a g e
Section3: Km207+000-Km218+040 Unsuitable material and common excavation
Khe Sang bridge Reinforcing steel bar
Khe U bridge Reinforcing steel bar
Khe Can bridge Spread foundation P1
Chau Que Thuong bridge Bored pile works
Xom Danh bridge Spread foundation P1
2.8 PACKAGE A8
January
IC18 Ram A1 bridge Km 244+ 570 Bored pile works – Pier P1 and P2
Suoi Trat bridge Bored pile works – Pier P6
Ngoi Bo bridge Bored pile works – Pier P2
Section 1: Km218+300-Km225+000 Unsuitable material and common excavation
Section 2: Km225+000-Km229+000 Unsuitable material and common excavation
Section 3: Km229+000-Km232+000 Unsuitable material and common excavation
Section 4: Km232+000-Km235+000 Unsuitable material and common excavation
Section 5: Km235+000-Km238+000 Unsuitable material
Section 6: Km238+000-Km244+000 Excavation and embankment
Section 7: Km238+000-Km241+000 Excavation and embankment
Section 8: Km241+000-Km243+000 Excavation and embankment
February
Section 1: Km218+080-Km223+000 Common excavation
Section 2: Km223+000-Km225+000 Unsuitable material
Section 3: Km225+000-Km229+000 Unsuitable material and common excavation
Section 4: Km229+000-Km232+000 Common excavation
Section 5: Km232+000-Km235+000 Embankment
Section 6: Km235+000-Km238+000 Embankment
Section 7: Km238+000-Km241+000 Embankment
Suoi Trat bridge Bored pile work
Ngoi Bo bridge Bored pile work
March
Section 1: Km218+080-Km223+000 Unsuitable material and common excavation
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
19 | P a g e
Section 2: Km223+000-Km225+000 Unsuitable material and common excavation
Section 3: Km225+000-Km229+000 Common excavation
Section 4: Km229+000-Km232+000 Unsuitable material and common excavation
Section 5: Km232+000-Km235+000 Embankment
Section 6: Km235+000-Km238+000 Embankment
Section 7: Km238+000-Km241+000 Excavation and embankment
Suoi Trat bridge Bored pile work
Ngoi Bo bridge Bored pile work
IC18 Ram A1 Km 244+ 570 Bored pile work
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
20 | P a g e
3. CARRIED OUT TASKS DURING THE PERIOD
During the period of reference for this quarterly report, the environmental tasks carried out by the specialists were the following. The Weekly
Reports have been included in the corresponding Monthly Reports. So, it’s considered not necessary or useful to include again in this report.
3.1 PACKAGE A1
January
TASK 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
General Inspection in site
Punctual Inspection in site
Submitted Weekly Report
Submitted letters/notifications
Weekly/Monthly meetings
February
TASK 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
General Inspection in site
Punctual Inspection in site
Submitted Weekly Report
Submitted letters/notifications
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
21 | P a g e
Weekly/Monthly meetings
March
TASK 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
General Inspection in site
Punctual Inspection in site
Submitted Weekly Report
Submitted letters/notifications
Weekly/Monthly meetings
3.2 PACKAGE A2
January
TASK 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
General Inspection in site
Punctual Inspection in site
Submitted Weekly Report
Submitted letters/notifications
Weekly/Monthly meetings
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
22 | P a g e
February
TASK 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
General Inspection in site
Punctual Inspection in site
Submitted Weekly Report
Submitted letters/notifications
Weekly/Monthly meetings
March
TASK 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
General Inspection in site
Punctual Inspection in site
Submitted Weekly Report
Submitted letters/notifications
Weekly/Monthly meetings
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
23 | P a g e
3.3 PACKAGE A3
January
TASK 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
General Inspection in site
Punctual Inspection in site
Submitted Weekly Report
Submitted letters/notifications
Weekly/Monthly meetings
February
TASK 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
General Inspection in site
Punctual Inspection in site
Submitted Weekly Report
Submitted letters/notifications
Weekly/Monthly meetings
March
TASK 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
General Inspection in site
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
24 | P a g e
Punctual Inspection in site
Submitted Weekly Report
Submitted letters/notifications
Weekly/Monthly meetings
3.4 PACKAGE A4
January
TASK 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
General Inspection in site
Punctual Inspection in site
Submitted Weekly Report
Submitted letters/notifications
Weekly/Monthly meetings
February
TASK 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
General Inspection in site
Punctual Inspection in site
Submitted Weekly Report
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
25 | P a g e
Submitted letters/notifications
Weekly/Monthly meetings
March
TASK 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
General Inspection in site
Punctual Inspection in site
Submitted Weekly Report
Submitted letters/notifications
Weekly/Monthly meetings
3.5 PACKAGE A5
February
TASK 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
General Inspection in site
Punctual Inspection in site
Submitted Weekly Report
Submitted letters/notifications
Weekly/Monthly meetings
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
26 | P a g e
March
TASK 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
General Inspection in site
Punctual Inspection in site
Submitted Weekly Report
Submitted letters/notifications
Weekly/Monthly meetings
3.6 PACKAGE A6
January
TASK 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
General Inspection in site
Punctual Inspection in site
Submitted Weekly Report
Submitted letters/notifications
Weekly/Monthly meetings
February
TASK 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
27 | P a g e
General Inspection in site
Punctual Inspection in site
Submitted Weekly Report
Submitted letters/notifications
Weekly/Monthly meetings
March
TASK 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
General Inspection in site
Punctual Inspection in site
Submitted Weekly Report
Submitted letters/notifications
Weekly/Monthly meetings
3.7 PACKAGE A7
January
TASK 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
General Inspection in site
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
28 | P a g e
Punctual Inspection in site
Submitted Weekly Report
Submitted letters/notifications
Weekly/Monthly meetings
February
TASK 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
General Inspection in site
Punctual Inspection in site
Submitted Weekly Report
Submitted letters/notifications
Weekly/Monthly meetings
March
TASK 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
General Inspection in site
Punctual Inspection in site
Submitted Weekly Report
Submitted letters/notifications
Weekly/Monthly meetings
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
29 | P a g e
3.8 PACKAGE A8
January
TASK 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
General Inspection in site
Punctual Inspection in site
Submitted Weekly Report
Submitted letters/notifications
Weekly/Monthly meetings
February
TASK 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
General Inspection in site
Punctual Inspection in site
Submitted Weekly Report
Submitted letters/notifications
Weekly/Monthly meetings
March
TASK 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
General Inspection in site
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
30 | P a g e
Punctual Inspection in site
Submitted Weekly Report
Submitted letters/notifications
Weekly/Monthly meetings
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
31 | P a g e
4. ENVIRONMENTAL MONITORING RESULTS. COMPLEMENTARY MEASURES TO
BE APPLIED
4.1 PROBLEMS AND RECOMMENDATIONS. SUMMARY TABLE
4.1.1 Package A1
JANUARY
No Description Location Solution Responsible
1
Untidy and Unclean
sites and worker’s
camps
NH2B bridge
Collect debris,
rearrange site and
camp; implement
safety housekeeping
work every day
POSCO
2 Worker’s camps are
without septic tanks
TL302CII
bridge
Install the backhouse
with septic tanks for
workers
POSCO
3 Backhouses are not
suitable
I.C3 and NH2B
bridge
Install the suitable
backhouse with septic
tanks for workers
POSCO
4
Mud after recycling
bentonite spilled into
river
Bon bridge
Collect mud and
dispose of it properly;
install sediment trap to
prevent spill/leak of this
material onsite/offsite;
remove sediment
periodically
POSCO
FEBRUARY
No Description Location Solution Responsible
1 Oil leaked on sites
Trung Kien
bridge; Km
17+100; Km
19+300
Place oil tray under
equipment during
maintenance
POSCO
2 Mud after recycling
bentonite spilled into
Trung Kien
bridge
Install sediment basin
with enough capacity POSCO
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
32 | P a g e
river and remove mud
periodically
3 Riverside is eroded Xuan Phuong
bridge
Install temporary pile
culverts with enough
capacity and
appropriate with high
velocity
POSCO
4 Backhouses are not
suitable
I.C3 and NH2B
bridge
Install the suitable
backhouses with septic
tanks for workers;
always keep septic
tank in cleanliness and
sanitary condition
POSCO
5 Concrete waste was
discharged on site TL402 bridge
Collect discharged
concrete waste and
dispose of it properly;
only discharged
concrete waste in
designated areas
POSCO
6 Worker’s camp without
septic tank
TL302CII
bridge
Provide enough
sanitary facilities for
workers
POSCO
MARCH
No Description Location Solution Responsible
1 Drilling mud spilled into
river
Tan Loi bridge
(abutment 2)
Use sediment trap to
temporarily store mud POSCO
2 Oil leaked on site Tan Loi bridge
(abutment 2)
Collect contaminate soil
and check equipment
before work
POSCO
3
Washout concrete
vehicle out of
designated area
Tan Loi bridge
(abutment 2)
Collect disposed
concrete and dispose of
it properly; only washout
equipment and vehicle in
designated area
POSCO
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
33 | P a g e
4
Untidy and Unclean
sites and worker’s
camps
NTT bridge
and NH2B
bridge
Collect debris, rearrange
site and camp;
implement safety
housekeeping work
every day
POSCO
5 Worker’s camps are
without septic tanks
I.C3 and
TL302CII bridge
Install the backhouse
with septic tanks for
workers
POSCO
4.1.2 Package A2
JANUARY
No Description Location Solution Responsible
1 Channel was block by
erosion
Tan Dung
bridge
Dredge channel,
stabilize slopes, inlet
and outlet of culvert
POSCO
2 Mud spilled into river Ben Gao
bridge
Dredge the river, apply
the sediment and
erosion control
measures
POSCO
3 Bentonite leaked offsite Ben Gao
bridge
Check and repair
leaking point, collect
leaked bentonite, apply
the sediment control
measures
POSCO
4
Site was dirty with
debris and leftover
material
Tan Dung
bridge
Clean the site and
implement the safety
housekeeping work
often
POSCO
5
Fueling areas are not
applied the
environmental
protection measure well
An Phat 1
section; Ben
Bao bridge
Apply the
environmental
protection measure at
fueling areas
POSCO
FEBRUARY
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
34 | P a g e
No Description Location Solution Responsible
1 Casing was put in the
stream
Tan Dung
bridge
Remove the casing out
of water body when
workers back to work
POSCO
2 Small leak of oil Ben Gao
bridge
Always place the drip
pan under fuel pile
during fueling
equipment
POSCO
3 Mud after recycling
bentonite leaked offsite
Lo river bridge
– abutment 1
Collect the leaked mud
and repair the silt fence POSCO
4 Bentonite slurry leaked
in river
Lo river bridge
– pier 4
Patching holed points
and usually check for
and repair leak points
POSCO
5 Construction site is kept
in untidy condition
Lo river bridge
– abutment 2
Rearrange the site
when the workers back
to work
POSCO
6
Septic tanks were
obstructed and not
available for use
Lo river bridge
- worker’s
camp –
abutment 2
Empty and clean septic
tank POSCO
7 Water flow was blocked Song Dao
bridge
Reinstall new
temporary stream
crossing with suitable
pipe culverts
POSCO
MARCH
No Description Location Solution Responsible
1
There no septic tank
was installed for
workers
TL402 bridge Provide enough sanitary
facilities for workers POSCO
2
Mud after recycling
bentonite leaked offsite
and to be discharge into
adjacent paddy field
Trung Kien
bridge
Install sediment basin
with enough capacity
and remove mud
periodically
POSCO
3 Mud and bentonite Bon bridge Install sediment trap; POSCO
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
35 | P a g e
slurry were discharged
into watercourse
store mud in sediment
trap and it must be
removed periodically;
ensure all the mud and
bentonite will be not
discharged or leak offsite
4
Temporary stream
crossing with not
enough capacity pipe
culvert
Riverside is eroded
Xuan Phuong
bridge
Install temporary pipe
culverts with enough
capacity and appropriate
with high velocity
Stabilize the inlets and
outlets of pipe culverts
POSCO
5 There was small leak of
oil Bon bridge
Apply the measures to
prevent leak of oil such
as place drip pan under
nuzzle; check and repair
leaked points
POSCO
6
Temporary pipe culverts
are not enough capacity
and easy to be blocked
by erosion and
sedimentation
Km 0+775; Km
2+280 ~ Km
2+960
Reinstall temporary pipe
culverts with suitable
capacities; stabilize
inlets and outlets of
temporary pipe culverts
to prevent erosion and
sedimentation blocking
water flow
POSCO
4.1.3 Package A3
JANUARY
No. Problem description Location Solution Responsible
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
36 | P a g e
1
Many superfluous
material are thrown
away in site.(fragment
of iron and bentonite
sacks)
Km60+900,
Km77+800
The Contractor must
control their worker and
clean site immediately.
POSCO
2
Oil tank is need to
installed safety
measure before using
in site
IC8-
Km54+640
The contractor must install
safety measure for oil
tanks follow the
Consultant's letter
regarding "instruct to fuel
in site"
POSCO
3 Waste Bentonite were
pour into surrounding. Km60+900
Contractor must make a
sediment control pond to
collect all mud Bentonite
POSCO
4 Many rubbish in site
Km51,
Km60+900,
Km73
The Contractor must
collect all rubbish in site
every day strictly follow
ECP.
POSCO
5 Oil is leaked out
ground Km54+600
Contractor must collect all
oil on ground by dry sand
then thrown away with
waste in site.
POSCO
6
Drainage canal is
prepared to build pipe
culvert.
Km51
The Contractor must pay
attention to maintenance
irrgation and drainage
POSCO
FEBRUARY
No. Problem description Location Solution Responsible
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
37 | P a g e
1
Dump trucks are over
load and don't cover
when they transport
material from borrow
pit to construction site.
Km71
The Contractor must cover
dump trucks and never
over load.
POSCO
2 Bentonite pour into
ground. Km77+700
The Contractor must
collect all fallen bentonite
on ground and control it
carefully.
POSCO
3 Much rubbish is near
worker's camp Km74+300
The Contractor must
collect all rubbish in site or
near worker's camps.
POSCO
4 Bridge construction site
is not cleaned Km54+600
The Contractor must
remove all mud bentonite
after few days when it's
dryer.
POSCO
5
The access road need
to be reinforced. It's too
much mud on surface.
Therefore, it's much
dust on dry days and
equipment can not
tranfer on rainy days.
Km77+700
(Red River
bridge),
Km54+600
(IC8)
The Contractor is
requested to spread stone
on surface of access
roads to improve it.
POSCO
MARCH
No. Problem description Location Solution Responsible
1
Dump trucks are over
load and don't cover
when they transport
material from borrow
pit to construction site.
Km71
The Contractor must cover
dump trucks and never
over load.
POSCO
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
38 | P a g e
2
Unsuitable material
was piled up in site.
Km68,
Km77+200
The Contractor has to
complete all legal
documents for disposal
and transport unsuitable
material to disposal area
after it stop rain.
POSCO
4.1.4 Package A4
JANUARY
No. Problem description Location Solution Responsible
1
Existing roads need to
be watered on dry days
by contractor. Dust is
much in the air.
Km93+260,
Km92+460
The Contractor must
water these existing
roads appropriatly on dry
days.
KEANGNAM
2
Drainage canal was
broken by excavator of
project.
Km102+250
The Contractor must give
their whole mind to
maintenance irrgation
and drainage follow
approval ECP.
KEANGNAM
FEBRUARY
No. Problem description Location Solution Responsible
1 Dump trucks are not
covered. Km89+800
The Contractor is
requested to cover and
never over load all dump
trucks.
KEANGNAM
2
Worker's camps
weren't installed
hygiene toilet and
waste bin.
General
The Contractor must
install hygiene toilet and
waste bin at all worker's
camps follow approval
ECP.
KEANGNAM
MARCH
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
39 | P a g e
No. Problem description Location Solution Responsible
1
Worker's camps
weren't installed
hygiene toilet and
waste bin.
General
The Contractor must
install hygiene toilet and
waste bin at all worker's
camps follow approval
ECP.
KEANGNAM
2
Earth is fallen to
drainage canal. It will
be blocked in near
future
Km108+965
The Contractor must
dredge all fallen earth in
drainage canal bed and
reinforce side of this
access road to avoid fall
solid substance into
drainage canal.
KEANGNAM
3
The dump trucks do
not cover and over load
when it transports
material from borrow
pit to the construction
site.
Km105+600
The Contractor must
cover all dump truck and
never load.
KEANGNAM
4
The surface of existing
road has much fallen
earth.
Km105+600
The Contractor has to
clean fallen earth on
existing road and water
appropriately on dry
days.
KEANGNAM
4.1.5 Package A5
FEBRUARY
No. Problem description Location Solution Responsible
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
40 | P a g e
1
During construction,
The unsuitable soil
prevented the water
flow of some the
ditches
Km119+000 –
Km119+700
Conducting and
instruction of Engineer
in the letter,
GET3/KEANGNAM/A5/
110 dated on 16th
February 2011
KEANGNAM
2
The Contractor has not
been Submit
Environmental
Monitoring Plan to the
Consultant for review
General
The Contractor must
submit Environmental
Monitoring Plan to the
Consultant and
implement to monitoring
environmental indicator
KEANGNAM
MARCH
No. Problem description Location Solution Responsible
1
At station Km118+930
during material
transportation, there is
much soil falling down
on provincial road.
Km118+930
Conducting the
instructions of Engineer
in letter,
GET3-KEANGNAM-11-
A5-002 dated on 3rd
March 2011.
KEANGNAM
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
41 | P a g e
2
At station Km122+030:
when it rains heavily, if
the Contractor don’t
take care and organize
the protection methods,
soil erosion might
happen leading to
erosion of Access
Road, which affects
safety of the Project.
Km122+030
Conducting the
instructions of Engineer
in letter,
GET3-KEANGNAM-11-
A5-023 dated on 17th
March 2011
KEANGNAM
4.1.6 Package A6
JANUARY
No. Problem description Location Solution Responsible
1
When transporting
materials, many trucks are
not covered with canvas.
Some section
of package
A6 Implement the
instructions of Engineer
in letter
GET3/DOOSAN/A6/394
dated on 30th
December 2010
DOOSAN
2
Soil was disposed into the
stream, which prevents the
water flow.
Km162+900
(Ngoi Giam
bridge);
Km 159+200
(Ngoi Cong
bridge):
3
There is much soil falling
down on the road during
material transportation.
Km155;
Km157;
Km159;
Km161;
Km172+600;
Km173;
Implement the
instructions of Engineer
in letter
GET3/DOOSAN/A6/412
dated 7th January 2011
DOOSAN
4
Unsuitable materials were
disposed near the Red
River.
Km187+500
Implement the
instructions of Engineer
in letter
DOOSAN
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
42 | P a g e
5
There is much unsuitable
material had been
disposed into the area that
the Contractor did not
submit as disposal area.
Km171+900
GET3/DOOSAN/A6/435
dated on 18th January
2011
6 Approval of disposal areas
for unsuitable material.
Km188+200;
Km190+110;
Implement the
instructions of Engineer
in letter
GET3/DOOSAN/A6/460
dated on 24th January
2011
DOOSAN
FEBRUARY
No. Problem description Location Solution Responsible
1 Unsuitable soil disposed
near the river bank
Km161+100;
Km185+600;
Km165+050;
Conducting and
instruction of Engineer
in the letter,
GET3/DOOSAN/A6/518
dated on 23rd Feb 2011
DOOSAN
2
During construction
material transportation,
many the trucks are not
covered with canvas.
Km186+740
Conducting and
instruction of Engineer
in the letter,
GET3/DOOSAN/A6/518
dated on 23rd Feb 2011
DOOSAN
3 The waste water disposed
directly into the river.
Batching plant
at Km165
(Stone White
VINA
Subcontractor
Conducting and
instruction of Engineer
in the letter,
GET3/DOOSAN/A6/518
dated on 23rd Feb 2011
DOOSAN
4
Environmental Monitoring
Plan has not been
submitted yet to Engineer
for review
General
Conducting and
instruction of Engineer
in the letter,
GET3/DOOSAN/A6/519
dated on 23rd Feb 2011
DOOSAN
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
43 | P a g e
MARCH
No. Problem description Location Solution Responsible
1
The living conditions of
workers at their camp, who
are working at station
Km190+100 are bad. The
worker’s camp here has
not toilet, no sewage
treatment system
Km190+100
Conducting the
instructions of Engineer
in letter,
GET3-DOOSAN-11-A6-
033 dated on 12th
March 2011.
DOOSAN
2
There are many errors in
the Contractor’s
Environmental Monitoring
Plan
General
Conducting the
instructions of Engineer
in letter,
GET3-DOOSAN-11-A6-
050 dated on 21st
March 2011.
DOOSAN
3
At station Km172+300: this
station is near a pound,
when it rains heavily, if the
Contractor don’t take care
and organize the
protection methods, soil
erosion might happen
leading to erosion of pond
edge, which affects safety
of the Project
Km172+300
Conducting the
instructions of Engineer
in letter,
GET3-DOOSAN-11-A6-
034 dated on 14th
March 2011.
DOOSAN
4.1.7 Package A7
JANUARY
No. Problem description Location Solution Responsible
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
44 | P a g e
1 Fire on the construction site.
Km191+353
Contractor must warn the workers about the dangers of fires on the works. In addition, it causes environmental pollution and the risks of explosion.
GRBCC
2
Dangerous roads can cause accidents to traffic participants.
Km194+200;
Required construction urgently installs advertising sign at the above locations.
GRBCC
3 The construction site is very indiscriminately unhygienic.
Km209+300;
Km191+353
Contractor should install garbage bins and transport to the prescribed treatment.
GRBCC
4 Electrical safety. Km207+935
Contractor has to train and direct workers the way of using electricity safety.
GRBCC
5 Safety for gas and oxygen tanks.
Km204+581;
The Contractor shall warn workers about the risks, dangers to workers have preventive measures.
GRBCC
6
Some landfills have been planted grass under the Consultant's guidance.
Km195+800
Requiring Contractor continue to planting grass at the remained locations under Consultant's guidance.
GRBCC
7
Unsuitable material disposals are resolved completely under the direction of the Environmental Police Lao Cai and supervision consultant.
Km194+200;
Km195+800;
Km199+500;
Km207+000
The location of landfill containing unsuitable material disposals is excavated. The soil which was dropped into the riverbed has transported and a grass has been planted to avoid, returned landscape to environment.
GRBCC
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
45 | P a g e
8
The contractor installed warning signs for traffic safety at the construction location of the cross-roads.
Km194+200
The Contractor recorded and implemented timely the Supervision Consultant's directions.
GRBCC
9
Rocks and soil fell into river-bed to obstruct the flow and polluted water environment.
Km204+581
Requiring the Contractor to dredge a river's flow, prevent water pollution of the rivers and streams
GRBCC
FEBRUARY
No. Problem description Location Solution Responsible
1
Rubbish and soil flew into the stream and obstruct the follow and cause water pollution.
Km191+353
Km204+581
Require the contractor to fish waste out of the stream, clear and return natural flow to the stream.
GRBCC
MARCH
No. Problem description Location Solution Responsible
1
Rubbish is untidily discharged into the works near worker's camps
The caste culvert No1 at Km194+670
Require the subcontractor to collect rubbish and transported to the approved wasteland areas.
GRBCC
2
Some landfills are requested to plant trees and grass in order to protect from eroding and land sliding into Red River.
Km190+400; Km195+800; Km199+500
Require the contractor to have plan for re-planting grasses in March because this time is good for trees and grasses to grow.
GRBCC
3 The flow is blocked while executing.
Km194+765
Km209+329
Require the subcontract to implement measure to dredge and clear the flow
GRBCC
4
There is no toilet and the garbage collection bins for worker at the worker's camps.
Km190+487
Require the subcontract to build the toilet and install garbage collection bins for workers.
GRBCC
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
46 | P a g e
4.1.8 Package A8
JANUARY
No. Problem description Location Solution Responsible
1
At the construction site of Suoi Trat bridge, bentonite outflow to stream.
Km 232+890
Requiring Contractor to have waste bentonite tank during the process of drilling borrow piles.
VINACONEX
2
At worker's camps of Viet Dung Co.,ltd and Tuan Tu Co.,ltd, the waste oil outflow to the ground.
Km232+900;
Km237+060
Requiring contractor to have trays for prevention of waste oil from out flowing to the ground during the maintained process.
VINACONEX
3
At the construction site of Ngoi Bo bridge, material disposals of borrow piles is not being transported to the landfill.
Km238+265
Contractor must have tray for containing material disposal of borrow piles and transport it to the approval wasteland area.
VINACONEX
4
There were not sandbags at the foot of surrounding wall at the location of IC18 bridge as consultant's guidance.
Km244+570
Contractor must seriously perform this problem follow consultant’s guidance.
VINACONEX
5
Domestic waste is not being collected and transported to the place of prescribed treatment.
Km232+900
Requiring contractor to install 02 rubbish bins at least for each worker's camp.
VINACONEX
6
At the construction site of Suoi Trat bridge has collected holes of bentonite. However, in the process of collecting, bentonite outflow to stream.
Km 231+890
Requiring Contractor to have measure for managing and collecting strictly waste bentonite, and preventing it from overflowing.
VINACONEX
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
47 | P a g e
7
According to Consultant's guidance, contractor use sand bags at the wall's foot.
Km244+570 VINACONEX
8 Labour safety while during the process of construction.
Km231+890;
The casting station of Tuan Tu Co., Ltd
Contractor is required to equip labour protection for workers. Contractor reminds workers to wear labour protections during the process of construction.
VINACONEX
9
At construction site of Suoi Trat bridge, Bentonite overflows into the stream and polluted water resource.
Km 231+890
Requiring the contractor have to manager and collect bentonite strictly to avoid overflowing out.
VINACONEX
10
At location of IC18 bridge, waste water and mud are overflows into the construction site and road.
Km244+570
The contractor must have measure of collecting waste water and mud during the process of construction.
VINACONEX
11
At the location of Suoi Trat bridge, electrical wires and circuit breaker are not safe.
Km231+890
The contractor is required to hang up at least 3 meter above the ground and the circuit breaker must be placed in secure location.
VINACONEX
FEBRUARY
No. Problem description Location Solution Responsible
1
Soil and benite overflow into the stream to obstruct the flow and cause water pollution.
Km 231+890
Require the contractor to collect and transport the above soil and bentonite to the approved wasteland area and return a natural flow to the stream.
VINACONEX
2
Unsuitable materials is not transported to the approved wasteland area
Km238+265
Require the contractor to transport total unsuitable disposal materials to the approved wasteland area.
VINACONEX
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
48 | P a g e
3
Waste is discharged untidily at the worker’s camps of Vinaconex 34
Km241+000
Require the contractor to collect and transport soild waste to the place of treatment prescribed.
VINACONEX
MARCH
No. Problem description Location Solution Responsible
1
The subcontractor has transported soil and bentonite to dredge the flow and return natural flow to this stream.
Km 231+890 VINACONEX
2
Total unsuitable materila disposals are transported to the approved wasteland area.
Km238+265 VINACONEX
During the digging process of the bridge's post, waste land is not transported but left them near the river's side.
Km218+040
Require the contractor to transport the mentioned waste soils to the approved wasteland area.
VINACONEX
Waste land is provisionally collecting at the execution place.
Km238+265
Km244+570
Require the subcontractor to transport waste land away after completing every bored pile.
VINACONEX
The canal cut through the road-bed of the construction project
Km221+480
Require the subcontractor to maintain the flow of canals for production of the people before breaking away to do again the drainage system as designed.
VINACONEX
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
49 | P a g e
The canals are in site limited of construction areas
Km221+500- Km221+700
Require the subcontractor to work with People Committee to find solutions to maintain the irrigation system of the people and ensuring the progress of construction of the contractor.
VINACONEX
3
Bentonite is overflow into the stream while recovering
Km232+890
Require the contractor to dredge the entire quantity of bentonite that spilled down the stream and commit not to relapse this situation. If the contractor continues to violate, the Consultant will to stop giving payment related items.
VINACONEX
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
50 | P a g e
4.2 AIR QUALITY
4.2.1 Package A1
January
By observation during the month, we perceived that there is no significant impact on ambient
air quality detected. The weather is wet and many drizzling days in the month so the dust in
the air is reduced considerably. Besides, at the sensitive areas the Contractor has watered the
surface of existing roads suitably so the dust also is reduced.
Besides, the equipment and machineries have been checked before operation and at the
sensitive areas, the quantity of operation equipment are small so the air quality at these areas
are quite good.
At the I.C3, the backhouse is unsuitable so the fresh fecal matter is let in directly the
environment and this makes smell at this area although it is far away from the sensitive areas.
The PSC has requested the Contractor to remove this backhouse and install the new one
which meets standard with septic tanks to make sure the sanitary condition for workers and
protect the ambient environment.
February
During the month, the weather is wet with almost days of drizzle and after the New Year
holiday the quantity of construction work on the sites was small so the air at the sensitive areas
was not impacted by dust and exhaust fumes from equipment.
Besides, the PSC has inspected I.C3 and NH2B bridge construction sites in third week to
check the report of Contractor, however we didn’t see any improvement at these sections. The
fresh fecal matter is still let directly in channel and cause environmental pollution and bad
smell. The PSC has issued the letter and suspended the procedure of payment progress of
these sections.
In the fourth week, during the site inspection we found that the Contractor had removed the
unsuitable backhouses and fresh fecal matter together and the septic tank at I.C3 construction
site is being built. In addition, the septic tank at the NH2B bridge construction site was cleaned,
too. The PSC also recommended the Contractor to provide enough the sanitary facilities as
well as keep them in cleanliness condition for workers.
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
51 | P a g e
March
By observations during the month, we perceived that the construction activities of project did
not impacted adversely on ambient air quality, especially at the sensitive areas.
At the Km 4+220 (pagoda) and Km 19+650 (elementary school and resident area) there was
no construction work this month. At the Km 13+100 (resident area) the Contractor has watered
suitably the embankment surface and at QL2B bridge construction site the main construction
activity is launching PCI girders, therefore the level of dust in the air at these sections is
reduced.
4.2.2 Package A2
January
By observation during the month, we perceived that there is no significant impact on ambient
air quality detected. The weather is wet and many drizzling days in the month so the dust in
the air is reduced considerably. Besides, at the sensitive areas the Contractor has watered the
surface of existing roads suitably so the dust also is reduced.
Besides, the equipment and machineries have been checked before operation and at the
sensitive areas, the quantity of operation equipment are small so the air quality at these areas
are quite good.
February
During site inspections in month, we didn’t detect the adverse impact on ambient air quality
from the construction activities at the sensitive areas. Almost days of this month were drizzle
so the weather was wet and the quantity of construction work in this month was also small.
At the some interchange with existing roads such as TL305 bridge, TL309 bridge, Km 34+780,
we perceived that these section were clean and there was no sign of dirt or mud tracked onto
public roads during the site inspections.
The PSC has also recommended the Contractor to tightly control the construction sites to
make sure the negative impacts could be well mitigated.
March
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
52 | P a g e
During site inspection on March 23rd 2011, we detected that the level of dust in the air at the
detour road, TL305 bridge construction site was high. The PSC has requested the Contractor
to resolve this problem by watering suitably this stretch of detour road. Besides, the Contractor
was also requested to apply the measures to prevent tracking of dirt onto public road at this
section.
At other sections such as Km 34+780 (pagoda), Km 34+408.05 (TL309 bridge) we didn’t
detected the adverse impact on ambient air quality during site inspections in month.
In addition, we also recommended the Contractor to manage the construction sites well to
prevent negative impact on ambient environment.
4.2.3 Package A3
January
During recent January, Contractor has maintained fairly well surface of outside routing
assignment road (Km51, Km68, Km74+400...). Earth was scattered during tranport of materials
from mine to contruction site or inappropriate materials carried to dumping ground were
cleared. Besides, Contractor wetted road surface on dry days so dust was not much scattred in
the air.
February
In the first week (from 7th- 12th February), dust is much on access road from borrow pit to
construction site at Km71. Because the Contractor has not managed their sub-Contractor. All
dump trucks are over load and do not cover when they transport material from borrow pit to
construction site. The Contractor is warned to solve this violation matter immediately. They
must cover dump trucks and never over load. In the next week, when the Consultant inspected
on site, we have found that this matter is improved by Contractor.
In inspection tour on the third week (from 21st -26th February), the Consultant has found that
the access road at Km77+700 (Red river bridge) and Km54+600 (IC8) have much mud on
surface. That is a reason why in the dry days that road has much dust in the air. The
Consultant warned the Contractor of above matter and will recheck after 1 week.
March
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
53 | P a g e
Almost days in March, it was rain much. Therefore, there is no dust in the air. According result
of Environmental monitoring all the environmental pollutant ambient air arising from
construction activities in site is within the limits by Viet Nam standard (QCVN05:2009/BTNMT;
QCVN 06:2009/BTNMT; QCVN 27:2010/BTNMT). Detail of analysing for reference in Report
on Environmental monitoring March, 2011.
4.2.4 Package A4
January
Pursuant inspection tour from 17th to 21th January, 2011, the Consultant has found that there
were many fallen earth on surface of the road at stations Km96+400, Km92+280 – Km92+760,
Km93+260 which is the result of transport material or unsuitable material. The situation of this
road is particularly serious. The Consultant has warned the Contractor has to water
appropriately and recheck in next time.
February
The situation of air quality in February has not much changed against in January. The access
road or existing road are path way (Km92+280, Km93+260, Km89+800). Therefore the
Contractor is requested to water appropriately in dry days to avoid dust in the air.
In inspection tour on 21st -26th February, the Consultant has detected some dump trucks were
not covered. Earth was fallen on access road. The Contractor is requested to cover dump
trucks carefully and never over load. We will recheck in next week if this situation is still
continuous the Consultant will make site minutes.
March
It was rain in many days during March. Therefore, it is no dust in the air. But in inspection tour
on March 21st-26th, 2011, the Consultant has detected some dump trucks was not covered
and over load at Km105+600. Earth was fallen much on the surface of existing road. The
Contractor is requested to cover all dump truck and never over load when it transfers on
existing road. In dry days, the Contractor must water appropriately and collect all fallen earth
often.
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
54 | P a g e
4.2.5 Package A5
February
In this period, just several items of package A5 were in progress, air quality was generally
good. In February there were many rainy days, so the dust generated during transportation of
construction materials and excavation and fill works was reduced by natural factor.
In site inspections, the Consultant has frequently requested the Contractor to implement
measures to reduce air pollution in project area.
March
In weekly site inspections, the Consultant has frequently reminded the Contractor to implement
measures to prevent and minimize air pollution due to activities of the Project.
However, at stations Km118+930, the intersection area with provincial road, there was a much
soil dropped on the road during material transportation that can affect the air environment and
area safety. The Consultant has required the Contractor to collect dropped soil and clear the
road in order to ensure traffic as well as regional environment (Refer to the Consultant’s letter
No. GET3-KEANGNAM-11-A5-002 on 2nd March 2011 ).
This month, in weekly site inspections of the Consultant, air quality was generally maintained
in good conditions, the construction works haven’t affected seriously the regional air
environment. In March there were many rainy days, so the dust generated during
transportation of construction materials, excavation and fill works was reduced by natural
factor.
4.2.6 Package A6
January
In this period, air quality was generally good. Because of many rainy days in January, the dust
generated during transportation of construction materials and excavation and fill works was
reduced by natural factor. However, due to bad control of the Contractor at some stations,
many trucks weren’t equipped with canvas during material transportation at several stations
such as Km157, Km159. This created dust and affected the air environment, especially on
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
55 | P a g e
sunny and windy days. The Consultant has reminded the Contractor on this issue in letter
No.GET3/DOOSAN/A6/394 on 30th December 2010.
In site inspections, the Consultant has frequently requested the Contractor to implement
measures to reduce air pollution in project area.
February
In this period, air quality was generally good. At some stations, the Contractor has watered to
minimize dust during material transportation like at Km 163, Km 159…
However, due to bad control of the Contractor at some stations, many trucks weren’t equipped
with canvas during material transportation at station Km 186+740. This created dust and
affected the air environment. The Consultant has reminded the Contractor on this issue in
letter ref.GET3/DOOSAN/A6/519 on 23rd February 2011.
In site inspections, the Consultant has frequently requested the Contractor to implement
measures to reduce air pollution in project area.
March
At this stage, the construction activities of the project haven’t affected the regional air quality
much. At some stations such as Km183-Km184, Km171-Km172, Km157-Km158,… the
material transporting works were carried out within the site. Beside, in March there were many
rainy days, so the dust was reduced by natural factor.
However, due to bad environment management, on some hot days in this month, at some
stations such as Km174+340, Km165+340,… there was much soil dropped on the road during
material transportation that can affect the air environment. The Consultant has required the
Contractor to implement some measures such as: collecting dropped soil on the transportation
roads, watering on the site and on the transportation roads.
In weekly site inspections, the Consultant has frequently reminded the Contractor to implement
measures to prevent and minimize air pollution due in the Project area.
4.2.7 Package A7
January
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
56 | P a g e
In January 2011, cold days interspersed with drizzly days so construction activities of the
contractor did not cause any adverse impact on air quality inside and outside the scope of the
construction side. Also due to the high humidity of the air plus the drizzling days so land should
always is in the wet state, so the digging activities and land transportation without causing
dust.
In addition, the results of air quality monitoring four quarter - December 2010 of the contractor
indicated that the construction activities didn’t cause negatively affect on air quality in the
region. Here are the results of monitoring air quality of the contractors was made in December
2010.
Results of air quality analysis are compared with QCVN 05:2009 / BTNMT: National Technical
Regulation on ambient air quality and QCVN 06:2009 / BTNMT: The national standards on a
number of toxic substances in ambient air, and are measured as follows:
No
Sample
Monitoring parameters
TSP (mg/m3) CO (mg/m3) SO2 (mg/m3) NO2 (mg/m3)
1 KK01 0.053 0.031 0.011 0.013
2 KK02 0.107 0.996 0.031 0.025
3 KK03 0.059 0.027 0.010 0.014
4 KK04 0.061 0.025 0.007 0.016
5 KK05 0.033 0.014 0.010 0.011
6 KK06 0.031 0.017 0.015 0.012
7 KK07 0.030 0.030 0.030 0.030
8 KK08 0.007 0.017 0.013 0.015
9 KK09 0.030 0.010 0.007 0.006
10 KK10 0.085 0.033 0.010 0.006
11 KK11 0.031 0.023 0.014 0.007
12 KK12 0.028 0.020 0.014 0.008
13 KK13 0.030 0.024 0.009 0.005
14 KK14 0.009 0.013 0.012 0.004
QCVN 05: 2009/BTNMT
QCVN 06: 2009/BTNMT
0.30 30 0.35 0.20
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
57 | P a g e
Note:
KK01: Xuan Sang 1 Primary School, Xuan Sang 1 Hamlet, Tan An Commune, Van ban District
(coordinates X: 2447621; Y: 437656)
KK02: Concrete mixing plant No.1, Ngam Thin Hamlet, Tan Thuong Commune, Van Ban
District (coordinates X: 2450769; Y: 431840)
KK03: Concrete mixing plant No.2, Dap Tran Hamlet, Tan Thuong Commune, Van Ban District
(coordinates X: 2450128; Y: 432378)
KK04: Bridge girder casting yard, Xuan Sang 2 Hamlet, Tan An Commune, Van Ban District
(coordinates X: 2446740; Y: 437982)
KK05: Equipment gathering yard, worker’s living area, Khe U Hamlet, Tan Thuong Commune,
Van Ban District (coordinates X:2454378; Y:430097)
KK06: Cam Con Primary School, Khe Mai Hamlet, Cam Con Commune, Bao Yen District
(coordinates X:2455549; Y:428569)
KK07: Cam Con Health Center, Tan Tien Commune, Bao Yen District (coordinates X:2459218;
Y:425187)
KK08: Drainage casting yard No.1, Khe Quat Hamlet, Tan An Commune, Van Ban District
(coordinates X:2448896; Y:435403)
KK09: Khe U Primary School, Khe U Hamlet, Tan Thuong Commune, Van Ban District
(coordinates X:2454480; Y:430171)
KK10: Residential areas at the right side of project road, Ban Ly Hamlet, Cam Con Commune,
Bao Yen District (coordinates X:2455100; Y:429124)
KK11: Tan Thuong Secondary School, Khe Tep Hamlet, Tan Thuong Commune, Van Ban
District (coordinates X:2451577; Y:431693)
KK12: Drainage casting yard No.2, Bong 1 Hamlet, Cam Con Commune, Bao Yen District
(coordinates X:2458097; Y:425895)
KK13: Cam Con Secondary School, Hamlet 2, Cam Con Commune, Bao Yen District
(coordinates X:2461778; Y:422467)
KK14: Tan An Kinder Garden, Tan Duong Hamlet, Tan An Commune, Van Ban District
(coordinates X:2450626; Y:434435)
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
58 | P a g e
The results of air quality environmental monitoring in the above table are compared with the
limit values in the standards. It shows that most of the observation results are lower than the
prescribed limit values and ranges:
+ Dust concentration: Between 0.007 – 0.107 mg/m3.
+ CO concentration: Between 0.010 - 0.996 mg/m3.
+ SO2 concentration: Between 0.007 – 0.031mg/m3.
+ NO2 concentration: Between 0.004 – 0.030 mg/m3.
February
The Contractor resumed the work from Feb 21st, 2011 and Consultant did not detect any
activity of adverse impact on air quality.
March
At the present, the construction activities of the contractor has not caused adversely affect on
air quality in the region. The coordination activities of land are carried out on routes, vehicles of
transporting land so hardly move out of the resident area, so these present activities didn't
increased the concentration of dust in the air.
In addition, in March because of the weather of drizzly weather and high humidity so the road-
beds are wet. Therefore, the movement of machinery, construction equipment and
transportation of raw materials hasn't caused dust pollution.
4.2.8 Package A8
January
In January 2011, cold drizzle alternating days so the construction actives of the contractor
does not cause adverse impacts on air quality inside and outside the scope of the construction
site. In addition, due to the high humidity of the air plus the drizzling days lead to the land
always be in the wet state, so the digging activities and land transportation without causing
dust.
February
In February, the Contractor began the construction only from February 21, Consultant did not
detect any activity of any adverse impacts of the contractor on air quality in this time.
March
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
59 | P a g e
At the present, the construction activities of the contractor hasn't caused adversely affect on air
quality in the region. The coordination activities of land are carried out on routes, vehicles of
transporting land so hardly move out of the resident area, so these present activities didn't
increased the concentration of dust in the air.
In addition, in March because of the weather of drizzly weather and high humidity so the road-
beds are wet. Therefore, the movement of machinery, construction equipment and
transportation of raw materials has not caused dust pollution.
Result of the Contractor air quality monitoring (carried out by Green Environment Engineering
Joint Stock Company in February 2011) showed that construction works not effected to
ambient air quality.
No
Sampling Site
Air substances
Dust (TSP)
(g/m3)
CO
(g/m3)
SO2
(g/m3)
NOx (g/m3)
HC
(g/m3)
1 KK01 105 1850 34 12 510
2 KK02 112 1970 35 10 630
3 KK03 204 1910 32 11 750
4 KK04 298 2750 54 22 1550
5 KK05 213 1900 31 10 850
6 KK06 160 1720 30 7 700
7 KK07 212 1640 32 9 720
8 KK08 234 1770 38 13 940
QCVN 05: 2009/BTNMT
QCVN 06: 2009/BTNMT
300 30000 350 200 5000
Note:
KK-01: Near the starting point of project, Sonha primary School -No 2, Anthang branch
(GPS: E:48418960; N:2465164);
KK-02: Sonha primary School -No 2, Sonha commune (GPS: E:48416909; N:2467052);
KK-03: Near Nangsom pre-school, near gate of Kheden village, Sonha commune
(GPS: E:48415439; N:2468285);
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
60 | P a g e
KK-04: Xuangiao road junction (GPS: E:48408457; N:2471454);
KK-05: Mixing concrete station - Near Xuangiao High school - Langpheo branch
(GPS: E:48409086; N:2470910 );
KK-06: Giaphu primary School -No 3 (GPS: E:48403182; N:2474612);
KK-07: Point of intersection with Binhminh road (IC 18) near petrol station
(GPS: E:48439948; N:2478869);
KK-08: Section of covering drain of precasting concrete (GPS: E:48404272; N:2472996).
Comparing the results of environmental monitoring of air quality in the table above with the
limit values showed that most of the observation results are lower than the prescribed limit,
except for a fall in third position with Spring Communications Dust concentration approximately
limits and ranges are as follows:
+ Dust concentration: Between 105 – 298 µg/m3.
+ CO concentration: Between 1640 – 2750 µg/m3.
+ SO2 concentrations: In about 30 – 54 µg/m3.
+ NOx concentration: Between 7 – 22 µg/m3.
+ HC concentrations (CxHy): In about 510 – 1550 µg/m3.
Causes dust concentration limits of approximately 3 Spring Communications is at the cross by
the traffic volume at this position is quite high in the early years, especially trucks carrying ore
from the Tang Loong industrial park and Coach back.
4.3 WATER QUALITY
4.3.1 Package A1
January
At the Bon bridge construction site, a little of mud spilled into adjacent river due to the
Contractor didn’t apply the sediment control measures to detain sediment on construction site
or prevent spill of it offsite. The PSC has requested as well as instructed the Contractor to
resolve this problem. We will recheck this area in the next site inspection.
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
61 | P a g e
At the Xuan Phuong bridge and Tan Loi bridge construction sites, the Contractor narrowed the
water bodies of the stretches of adjacent rivers for construction works and temporary stream
crossings because the sites are close the rivers. The PSC has found the risks of erosion and
requested the Contractor to apply the measures to stabilize the slopes and control erosion to
prevent polluting the surface water quality or blocking water flows at these sections. Up to this
time, with the site inspections, we perceived that the surface water qualities in these areas are
not affected from the construction activities of project.
At the other sensitive areas, the surface water qualities are being kept in good condition.
Besides, the PSC has not found any adverse impact on underground water quality from the
construction activities of project.
February
At the Bon bridge construction site, during the site inspection in section week, we found that
the Contractor has dredged the river and there was no sign of bentonite/or mud spilled in
adjacent river.
At Trung Kien bridge, in second week we found that a little of mud after recycling bentonite
slurry spilled in the water course because the Contractor didn’t apply the sediment control
measures. The PSC has recommended the Contractor to apply the sediment control measure
to prevent spill of this material offsite. However, in the third week, during the site inspection we
perceived that the sediment control measure applied was not suitable (sediment basin is too
small) and the mud still leaked in water course. We have immediately requested the Contractor
to resolve this problem and in the weekly meeting, we repeated this problem again and request
the Contractor to control tightly the construction sites.
At the Xuan Phuong bridge, the Contractor has installed the unsuitable temporary pile culverts
with not enough capacity and it blocked the drift of waste and adrift plants such as water-fern.
This matter probably causes water pollution at this area. The PSC has issued the letter in the
third week to instruct the Contractor to install the appropriate culverts at this area to make sure
the water flow as well as ensure the safety. The PSC will recheck this problem in the next site
inspection on Tuesday, March 01st 2011.
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
62 | P a g e
At the other sensitive areas such as Tam Long – Thien Ke bridge and Km 19+150 ~ Km
19+400, we didn’t detect any adverse impact on surface water quality during site inspections in
month.
Besides, there is no negative impact on ground water quality detected, too.
March
At Xuan Phuong bridge construction site, during the site inspection on March 08th 2011, we
perceived that the Contractor had installed more 2 pipe culverts and the adrift plants and waste
were no longer blocked. However, the PSC has recommended the Contractor to calculate the
highest level of water flow, especially in the coming rainy season as well as mobilize more pipe
culverts to make sure the water flow and safety for temporary stream crossing at this area.
Besides, we also detected that the Contractor discharged the waste water directly into river,
the PSC has warned the Contractor to avoid this action in the future.
At the Trung Kien bridge construction site, we detected that the Contractor had installed the
sediment basin to temporary stored mud before removing and prevent the leak of mud offsite.
However, the leaked mud has not been removed still. Besides, during the site inspection on
March 15th 2011, we detected that the mud after recycling bentonite had discharged offsite
and spilled into adjacent paddy field due to the negligence/unawareness of workers. The PSC
has requested the Contractor to immediately remove discharged mud as well as negotiate with
land owner for compensation. The Contractor was also requested to submit the report of this
problem settlement to Engineer in the end of this month.
During the site inspection on March 07th 2011, we detected that the Contractor had installed
the new bentonite slurry flow line but there was no sediment basin installed at Bon bridge
construction site. Besides, we also detected that the mud after recycling bentonite had been
discharged into watercourse. The PSC has requested the Contractor to immediately stop
construction work at this area temporarily till the sediment basin is installed. Besides, the
Contractor was also requested to check bentonite flow line to patch the leaked points to
prevent the leak of bentonite slurry offsite. And up to present, the construction activity at this
area is still being stopped due to the equipment has broken down.
Besides, there is no negative impact on ground water quality detected, too.
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
63 | P a g e
4.3.2 Package A2
January
At the Ben Gao bridge construction site, the Contractor narrowed the water body of the stretch
of river for construction activities (bored pile work) and we found that there was a little of mud
spilled into river due to the Contractor didn’t apply the erosion and sediment control measures
to retain the sediment on construction site.
Besides, at the Tan Dung bridge construction site, the small erosion happened and blocked
the inlet of culvert of temporary stream crossing.
The PSC has requested the Contractor to solve these problems. With the Contractor’s report
and site inspection of PSC, we perceived that the Contractor has implemented the requests of
Engineer and made sure the water flows at these areas.
February
At Lo river bridge – Pier 4 construction site, we detected that the bentonite slurry was leaked in
river during the site inspections in the third week and fourth week. The PSC has requested the
workers to immediately revise the bentonite slurry flow line and patch the holed points. We
also recommended the site engineer and site inspector to control this problem tightly and will
recheck this area on the next site inspection on March 01st 2011.
At the other sections, we didn’t find the adverse impact on water quality embraced surface
water and underground water qualities.
March
During site inspections, we didn’t realize the serious problem which impacts on surface water
quality such as bentonite slurry leakage, hazardous substances leakage in river. However, on
March 16th 2011, we detected that the workers were discharging the drilling mud into river at
Pier 4, Lo river bridge construction site. The PSC has requested the Contractor to immediately
temporary stop the work at this site and remove the drilling mud to approved disposal place.
At the other sections such as Tan Dung bridge (Km 31+245.05), Ben Tre bridge (Km
31+075.65), section 7 (Km 43+400~Km 45+300 – reservoir), we didn’t find the adverse impact
on water quality embraced surface water and underground water qualities.
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
64 | P a g e
4.3.3 Package A3
January
At Km77+700, Red River Bridge is currently executing the first bored pile. 700m was the
distance between Executed position and river bank. And now Consultant has not found any
harmful influence on water surface.
February
Until now, there is no construction activity which is implemented near 500m of Red river blanks
or a branch of Red river (Km67+000). The Consultant usually inspects these sensitive points
on February. However, we have not found any impact from construction work to water quality
of rive, stream or ponds in the scope of this project.
March
Dated March 23rd, 2011 the Contractor mobilize barge to execute on Red river. They lay stone
to reinforce access road in river blank and gather equipment and material to prepare drilling
bore pile on river. The Consultant has still inspected all construction activities in site, but until
now, we have found any impact from construction work to surface water quality of Red river.
Detail of analysing for reference in Report on Environmental monitoring March, 2011.
At Km67+000, the construction work is far 700m from branch of Red river. Therefore, no
construction activities effect to water quality here.
4.3.4 Package A4
January
Currently, bridge construction has not worked yet. However, Consultant warned Contractor to
pay attention to environmental protection and maintenance flow of canal or river. Contractor is
not allowed to pour waste or mud into stream, canal, pond or river.
February
At present, the Contractor is preparing place for drilling bore pile at Ngoi Gianh stream
(Km88+800), Ngoi Van stream (km108+960) and Ngoi Lao stream (Km97+200),. The
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
65 | P a g e
Consultant has inspected these stations but we have not found any impact for water quality: no
waste, no fallen earth on flow, no leaking oil…
Beside, at Km 92+200 the Contractor is removing topsoil and embankment next to a big pond.
Although the Contractor made a bank of earth between construction site and this pond but
earth still easy scatter into pond. Therefore, the Consultant require the Contractor must
carefully when work to avoid polluted surface water here.
March
The Contractor has not executed bridge on Ngoi Gianh (km88+700), Ngoi Van (km108+960),
Ngoi Lao (Km97+100) and Dam Nang (Km108+250) which are valley zone in package A4. In
inspection tour on March 21st-26th, 2011 the Consultant has found that Ngoi Gianh stream is
full of mud by other project. We remind the Contractor should remark it and we will recheck
careful when the Contractor execute bridge on Ngoi Gianh stream.
4.3.5 Package A5
February
Up to now, construction activities of the project haven’t affected seriously the quality of surface
water and the quality of underground water hasn’t been affected.
However, due to weak environment management of the Contractor, at stations Km119+000-
Km119+700, during construction process, unsuitable soil has stopped the water flow of some
gutters. The Consultant has required the Contractor to install immediately temporary culverts in
these areas in letter ref.GET3/KEANGNAM/A5/110 on 15th February 2011.
March
Up to now, the construction activities of the Project haven’t affect seriously the quality of
regional surface and underground water. However, at some stations and routes of the project
which go through some lakes such as: Km121+600 (Nuoc Mat lake); Km126+000 (Ykan lake)
the water quality of these lakes could be affected. The Consultant has requested the
Contractor to have measures to protect and control the environment at these stations so that
the environment and the surface water quality are ensured during construction process.
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
66 | P a g e
In weekly site inspections, the Consultant has frequently reminded the Contractor to manage
strictly the waste, especially the harmful waste to prevent bad effects on environmental quality,
especially in areas near water sources.
4.3.6 Package A6
January
Up to now, contraction activities of the project haven’t affected seriously the quality of surface
water and the quality of underground water hasn’t been affected.
In this period, several bridges of the package A6 were in progress and some round culverts
were installed, this didn’t affect seriously the surface water quality of the streams and rivers
because no toxicants were discharged into the water.
Unsuitable soil was disposed and stored at some stations which were not accepted by the
Consultant, that could affect the water such as at stations Km162+900 (Ngoi Giam bridge);
Km159+200 (Ngoi Cong bridge); Km175+020; Km186+140; Km187+500; Km188+800 (Suoi
Nau bridge). But these effects are just local and temporary. The Consultant has requested the
Contractor to deal with them in letter No. GET3/DOOSAN/A6/394 on 30th December 2010;
No.GET3/DOOSAN/A6/435 on 18th January 2011; No.GET3/DOOSAN/A6/458 on 22nd
January 2011; GET3/DOOSAN/A6/471 on 25th January 2011.
February
Up to now, contraction activities of the project haven’t affected seriously the quality of surface
water and the quality of underground water hasn’t been affected.
In this period, many bridges of the package A6 were in progress and some round culverts were
installed, this didn’t affect seriously the surface water quality of the streams and rivers because
no toxicants were discharged into the water. But at station Concrete mixing plant Km165
(Stone White Vina Co.), waste water follows drainage, run into river Ngoi Hut but not through
any waste water treatment system. The Consultant has requested the Contractor to install
waste water treatment system for this plant in letter ref.GET3/DOOSAN/A6/518 on 23rd
February 2011.
Besides, due to bad environment control and protection of the Contractor, unsuitable soil was
disposed near Red river at some stations such as Km161+100; Km165+050, that can affect
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
67 | P a g e
Red river’s corridors as well as quality of river water. The Consultant has required the
Contractor to stop disposing unsuitable soil at these stations and promptly move them to
disposal area which is approved by the Consultant.
March
Construction activities of the project this month haven’t affected seriously the quality of surface
water and underground water.
In this period, many bridges of the package A6 were in progress and some RC pipe culverts
were installed, this didn’t affect seriously the surface water quality of the streams and rivers
because no toxicants were discharged into the water.
But due to bad environment control and protection of the Contractor, unsuitable soil was
disposed near Red river at some stations such as Km190+140; Km187+300; Km171;
Km161+100, that can affect Red river’s corridors as well as quality of river water. The
Consultant has required the Contractor to stop disposing unsuitable soil at these stations and
promptly move them to disposal area which is approved by the Consultant.
4.3.7 Package A7
January
At the location of Khe U bridge, consultant found that during the construction process, soil and
sand were flew into the stream and intercepted the flow & effected on the water quality of the
above stream. Consultant has requested the contractor to resolve the above problem
immediately and contractor has mobilized machinery and manpower to recover it.
The locations of bridge’s cross-section through the streams are Khe U, Khe Sang, Ngoi Bong
Bridge. The construction activities of these construction sites still doesn't cause any adverse
impacts on water quality of these streams because the Contractors have implemented
measures as installation of culverts through construction sites, mud protection from
overflowing into streams and garbage collection at construction sites.
However, during the late construction process, consultant has to remind the contractors keep
construction sanitation to minimize adverse impacts on water quality of these streams.
No Parameters Unit NM-1A NM-1B NM-2A NM-2B NM-3A NM-3B QCVN
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
68 | P a g e
08:2008/
BTNMT(A2)
1 pH - 7.4 7.65 7.8 7.56 8.0 7.65 6-8.5
2 Temperature oC 21.5 21.5 20.9 20.8 21.7 21.65 -
3 DO mg/L 8.8 8.05 7.6 7.58 7.5 8.05 ≥5
4 TSS mg/L 67 23 44 22 10 19.8 30
5 COD mg O2/L
4.8 6.8 7.7 5.6 2.0 16.0 15
6 BOD5 mg/L 2 6.57 5 5.62 1 6.1 6
7 Coliform MPN/ 100mL
93 90 230 195 90 95 5000
8 Grease and oil
mg/L 0.10 0.12 0.11 0.11 0.11 0.15 0.02
9 NO3- mg/L 0.31 0.143 0.54 0.174 0.25 1.434 5
10 NH4+
- N mg/L 0.93 0.92 1.04 0.99 0.85 0.92 0.2
11 SO42- mg/L 3.07 2.98 3.06 2.95 1.65 1.72 -
12 PO43- mg/L 0.01 0.14 0.01 0.10 <0.01 0.08 0.2
13 Total Nitrogen mg/L 1.57 1.046 1.82 3.179 1.26 2.964 -
14 Total Phosphorous
mg/L 0.13 0.036 1.10 0.002 0.10 0.058 -
15 Fe mg/L 1.620 0.231 1.320 <0.2 0.478 0.205 1.0
16 Cd mg/L <0.0002
<0.0002
<0.0002
<0.0002 <0.0002 <0.000
2 0.005
17 As mg/L 0.001 0.001 0.001 0.001 0.001 0.001 0.02
18 Mn mg/L 0.150 0.161 0.200 0.192 0.053 0.075 -
19 Pb mg/L 0.003 0.003 0.003 0.003 0.001 0.002 0.02
20 Zn mg/L 0.009 0.006 0.049 0.058 0.012 0.025 1.0
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
69 | P a g e
Note:
NM-1A: 100m upstream of Com Stream (Coordinates X: 2446740, Y: 437982)
NM-1B: 100m downstream of Com Stream (Coordinates X: 2446740, Y: 437982)
NM-2A: 100m upstream of Khe Sang Stream (Coordinates X: 2446740, Y: 437982)
NM-2B: 100m downstream of Khe Sang Stream (Coordinates X: 2446740, Y: 437982)
NM-3A: 100m upstream of Khe Quat Stream (Coordinates X: 2448055, Y: 436942)
NM-3B: 100m downstream of Khe Quat Stream (Coordinates X: 2448055, Y: 436942)
No Parameters Unit NM-4A NM-4B NM-5A NM-5B NM-6A NM-6B
QCVN 08:2008/
BTNMT(A2)
1 pH - 6.9 7.2 7.4 7.59 6.2 6.92 6-8.5
2 Temperature oC 24.1 24.1 23.9 23.9 18 18 -
3 DO mg/L 6.3 6.73 8.0 7.2 6.23 7.0 ≥5
4 TSS mg/L 43 25 12 21 20 24 30
5 COD mg O2/L 5.2 6.4 3.4 5.6 5.8 16.8 15
6 BOD5 mg/L 2 6.78 1 4.92 3 5.72 6
7 Coliform MPN/100mL
230 237 2 5 230 228 5000
8 Grease and oil
mg/L 0.12 0.12 0.12 0.14 0.10 0.13 0.02
9 NO3- mg/L 0.29 0.284 0.43 1.001 0.37 1.383 5
10 NH4+
- N mg/L 0.74 0.79 1.08 1.02 1.02 0.98 0.2
11 SO42- mg/L 4.33 4.25 2.95 3.02 2.94 3.01 -
12 PO43- mg/L <0.01 0.03 <0.01 0.25 <0.01 0.07 0.2
13 Total Nitrogen
mg/L 1.94 1.445 1.55 1.841 1.47 2.061 -
14 Total Phosphorous
mg/L 0.12 0.023 0.08 0.031 0.09 0.016 -
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
70 | P a g e
15 Fe mg/L 1.330 0.221 0.545 0.254 1.980 <0.2 1.0
16 Cd mg/L <0.0002
<0.0002
<0.0002
<0.0002
<0.0002
<0.0002
0.005
17 As mg/L 0.001 0.001 0.001 0.001 0.001 0.001 0.02
18 Mn mg/L 0.266 0.305 0.062 0.085 0.300 0.298 -
19 Pb mg/L 0.001 0.002 0.001 0.001 0.001 0.001 0.02
20 Zn mg/L 0.010 0.023 0.003 0.004 0.009 0.011 1.0
Note:
NM-4A: 100m upstream of Khe U Stream (Coordinates X: 2454378, Y: 430097)
NM-4B: 100m downstream of Khe U Stream (Coordinates X: 2454378, Y: 430097)
NM-5A: 100m upstream of Bong Stream (Coordinates X: 2457976, Y: 425879)
NM-5B: 100m downstream of Bong Stream (Coordinates X: 2457976, Y: 425879)
NM-6A: 100m upstream of Cam 4 Stream (Coordinates X: 2452027, Y: 431655)
NM-6B: 100m downstream of Cam 4 Stream (Coordinates X: 2452027, Y: 431655)
No Parameters Unit NM-7A NM-7B NM-8A NM-8B
QCVN 08:2008/
BTNMT(A2)
1 pH - 7.7 7.56 6.1 6.8 6-8.5
2 Temperature oC 20.9 20.8 21.5 21.5 -
3 DO mg/L 7.4 7.58 8.9 8.1 ≥5
4 TSS mg/L 44 23 22 18 30
5 COD mg O2/L 7.9 10.4 3.2 8.0 15
6 BOD5 mg/L 5.0 5.52 1 6.0 6
7 Coliform MPN/100mL 230 243 230 232 5000
8 Grease and oil mg/L 0.12 0.14 0.13 0.11 0.02
9 NO3- mg/L 0.55 1.110 0.48 0.361 5
10 NH4+
- N mg/L 0.98 0.88 0.85 0.93 0.2
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
71 | P a g e
11 SO42- mg/L 3.03 2.95 5.09 4.93 -
12 PO43- mg/L 0.01 0.09 0.01 0.03 0.2
13 Total Nitrogen mg/L 1.79 2.007 1.46 1.616 -
14 Total Phosphorous mg/L 0.10 0.027 0.37 0.037 -
15 Fe mg/L 1.23 0.210 1.200 0.230 1.0
16 Cd mg/L <0.0002 <0.0002 <0.0002 <0.0002 0.005
17 As mg/L 0.001 0.001 0.001 0.001 0.02
18 Mn mg/L 0.18 0.135 0.131 0.145 -
19 Pb mg/L 0.002 0.002 0.001 0.001 0.02
20 Zn mg/L 0.045 0.013 0.009 0.008 1.0
Note:
NM-7A: 100m upstream of Mai Hong Stream (Coordinates X: 2448160, Y: 436866)
NM-7B: 100m downstream of Mai Hong Stream (Coordinates X: 2448160, Y: 436866)
NM-8A: 100m upstream of Ban Ly 1 Stream
NM-8B: 100m downstream of Ban Ly 1 Stream
The analytical results of 16 surface water sample showed that: almost all of parameters are
lower than allowable limit values of Standard QCVN 08:2008/BTNMT (A2). However, the
concentration of grease and oil, NH4+, TSS and Fe in some samples are over the allowable
limit values.
February
At the position of Khe Sang Bridge at Km191 + 353 and Khe U Bridge at Km204+581, rubbish
and soil flew into the stream. The Consultant required the Subcontractor to pick waste and
dredge off the flow to return natural flow for these streams.
March
On March 11th, at the construction site of Tan An bridge of Km194+765 and Tan Tien bridge of
Km209+329, during the process of digging abutment piers, the Subcontractor hasn't
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
72 | P a g e
transported waste land and temporarily left them on the construction site so this waste land
has been landslide down the stream to obstruct the stream's flow and increase the
concentration of suspended solids. This affects on the water quality of the river and stream.
Consultant has asked the subcontractor to dredge and clear the flow at the above places
before March 17th, 2011.
On March 22sd, at the location of Tan An Bridge ofKm194 +765 the Subcontractor didn't have
measures is dredged and clear the flow of streams through the construction location.
Consultant asked the Subcontractor to seriously implement and compose the warning letter
Ref: GET4 GRBCC-334 dated on March 23rd, 2011.
4.3.8 Package A8
January
At the construction site of Suoi Trat Bridge, the process of bore piles of the contractor there is
currently no collection tanks of bentonite. Bentonites overflow into Suoi Trat stream to cause
water pollution and affect on the people's life at downstream. Consultant issued an official
warning letter and required the contractor to install collection tanks of bentonite before Jan 5,
2011
At the construction site of Ngoi Bo Bridge, duirng bore pile process a large amount of waste
soil is not transported. Consultant has asked the contractor to install collection tanks and
transport waste soil before Jan 5, 2011 in case when water rises or when it rain heavily, will
sweep away this waste soil to downstream, causing water pollution.
On Jan 5, 2011, the Consultant inspects and found that collection tank of bentonite has
installed in Suoi Trat Bridge, but in the recovery process bentonite spill out and flow downs the
stream. Consultant has requested the contractor to immediately overcome the above
problems. At the construction site Ngoi Bo, the construction activities of contractors is pausing
so the contractor has not transport the amount of waste soil away. Consultant required the
contractor transfered this waste soil as soon as the contractor resume the construction
progresses.
February
On February 21st, 2011, in the execution of Suoi Trat bridge bentonite is overflown during
recovery. Consultant required the Contractor to recovery the overflowing bentonite and repair
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
73 | P a g e
the path of recovered bentonite in order to ensure the bentonite is not overflown while
recovering. This work must be completed before February 28th, 2011.
March
On February 21st at the construction site of Suoi Trat bridge, while constructing the
Subcontractor left soil and rock and betonite spill down the stream affecting water quality.
Consultant has requested the Contractor to dredge and clear the river to ensure the circulation
flow and does not affect on water quality according to the content of Ref. GET4-Vinaconex -
264 dated on February 24th, 2011. To the date of February 28th, the two Subcontractors have
overcome this above problem under the direction of Consultant.
On March 21st, while construction process, the subcontractor let bentonite to spill over the
collection area and affect on the water quality of Suoi Trat stream. Consultant has made a
report on the scene and issue the warning letter that required the contractor to overcome
seriously the problem before March 31st, 2011.
Result of the Contractor water quality monitoring (carried out by Green Environment
Engineering Joint Stock Company in February 2011) showed in following table.
Results of surface water quality analysis are compared with QCVN 08:2008 / BTNMT -
National Technical Regulations on surface water quality as follows:
No
Parameters
Unit
NM-1A
NM-1B
NM-2A
NM-2B
NM-3A
NM-3B
QCVN 08:2008/
BTNMT(A2)
1 pH - 6.73 7.12 6.91 6.74 6.77 7.52 6.5-8.5
2 Temperature oC 17.9 18.1 22.7 22.0 19.1 20.2 -
3 DO mg/l 7.55 7.20 7.40 8.20 7.30 7.50 >5
4 TDS mg/l 622 654 611 788 641 665 -
5 TSS mg/l 16.8 18.1 19.5 29.9 17.9 19.3 30
6 COD mg/l 7.5 8.1 9.4 12.2 10.8 12.5 15
7 BOD5 mg/l 2.5 2.8 2.9 3.4 3.1 3.3 6
8 Coliform MPN/ 550 680 720 840 770 780 5000
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
74 | P a g e
No
Parameters
Unit
NM-1A
NM-1B
NM-2A
NM-2B
NM-3A
NM-3B
QCVN 08:2008/
BTNMT(A2)
100ml
9 Oils & grease
mg/l 0.007 0.008 0.006 0.014 0.008 0.010 0.02
10 NO2- mg/l 0.008 0.008 0.009 0.009 0.008 0.009 0.02
11 NO3- mg/l 3.60 3.71 3.65 3.67 3.20 3.44 5
12 NH4 – N mg/l 0.125 0.132 0.146 0.215 0.154 0.158 0.2
13 PO43- mg/l 0.128 0.131 0.122 0.136 0.115 0.128 0.2
14 Ni mg/l <0.002 <0.002 <0.002 <0.002 <0.002 <0.002 0.1
15 Fe mg/l 0.213 0.226 0.205 0.314 0.237 0.545 1.0
16 Cd mg/l <0.002 <0.002 <0.002 <0.002 <0.002 <0.002 0.005
17 Hg mg/l <0.0002 <0.0002 <0.0002 <0.0002 <0.0002 <0.0002 0.001
18 As mg/l 0.007 0.007 0.007 0.008 0.007 0.008 0.02
19 Cu mg/l 0.011 0.012 0.014 0.014 0.015 0.016 0.2
20 Pb mg/l <0.002 <0.002 <0.002 0.005 0.008 0.008 0.02
21 Zn mg/l 0.006 0.006 0.008 0.016 0.011 0.012 1.0
Note:
NM-1A: Upstream bridge across Nhu stream (100m) (GPS :48420023E; 2463882N);
NM-1B: Downstream bridge across Nhu stream (100m) (GPS: 48419964E; 2464573N);
NM-2A: Upstream bridge across Trat stream (100m) (GPS: 48409292E; 2470972N);
NM-2B: Downstream bridge across Trat stream (100m) (GPS: 48409215E; 2471061N);
NM-3A: Upstream bridge across Ngoi Bo river (100m) (GPS: 48404733E; 247586N);
NM-3B: Downstream bridge across Ngoi Bo river (100m) (GPS: 48404840E; 2474631N).
The result of surface water quality analysis showed that most parameters are located below
the level prescribed for that surface water quality at monitoring sites no sign of pollution.
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
75 | P a g e
4.4 SOILS QUALITY
4.4.1 Package A1
January
At present, the Contractor is implementing the construction work in compliance with the site
limit and the PSC didn’t find any negative impact on soil quality, specially the productive soil in
the agriculture areas surrounding the sites. However, the PSC always recommend the
Contractor to manage tightly material especially liquid and hazardous materials to prevent
potential adverse impact on ambient environment including soil.
February
At the sections Km 17+100 and Km 19+300 and Trung Kien bridge, during the site inspection
in the third week we found there were little of oils leaked on site because the workers didn’t
place drip pans under equipment during maintenance. The PSC requested the Contractor to
collect leaked oil and contaminated soil as well as comply with Engineer’s instruction for
Vehicle and Equipment maintenance. Besides, in this site inspection, at TL402 bridge
construction site we also found that the concrete waste was discharged on undesignated area
(on embankment area) and we has requested the Contractor to collect this material and
dispose it in designated places.
During the next site inspection in the fourth week, we perceived that the Contractor had
collected leaked oil and contaminated soil at mentioned sections and collected concrete waste
at TL402 bridge construction site.
In addition, we also didn’t find the adverse impacts on productive soil during site inspections in
month.
March
At the fueling area in Bon bridge construction site, we detected that there was a small leak of
oil during site inspection on March 01st 2011. The PSC has requested the Contractor to apply
the measures to prevent leak of oil such as place drip pan under nuzzle, fuel tank; checking
and repair leak point as well as must be attended at all times during fueling.
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
76 | P a g e
In addition, we also detected that at Trung Kien bridge construction site, due to the negligence
of workers, the mud after recycling bentonite slurry had discharged offsite and spilled into
adjacent paddy filed during site inspection on march 07th 2011. This problem impacted
adversely on productive soil and probably poisons the plants at this area. The PSC has
requested the Contractor to resolve this problem as well as dealing with land owner for
compensation. The report of this problem settlement must be submitted to the Engineer in the
end of this month.
4.4.2 Package A2
January
At the Ben Gao bridge construction site, due to the Contractor didn’t apply the sediment control
measures and didn’t check the leak of bentonite flow line so the little of bentonite slurry leaked
in productive soil which is next to the site. The PSC has requested the Contractor to check and
repair the leaking point of bentonite flow line; collect leaked bentonite and disposed of it
properly. The Contractor has submitted the report with attached pictures of this matter
resolving to Engineer. We will recheck this problem on site in the next site inspection.
At the other areas, there is no impact on soil quality from construction activities of project
detected.
February
By observation during the site inspection in the third week, we detected that there was a little
of oil leaked in fueling area at Ben Gao bridge construction site because the Contractor did’t
use automatic shut-off nozzle but also didn’t place the drip pan under during fueling
equipment. The PSC has requested the Contractor to use drip pan and control fueling activity
tightly to prevent the leak of oil onsite and in the next site inspection on February 23rd 2011,
we perceived that leaked oil and contaminated soil were removed.
At the Lo river bridge – abutment 1 construction area, during the site inspection on February
18th 2011, we found that there was a little of mud after recycling bentonite slurry spilled offsite
in productive soil because the silt fence was broken. In the next site inspection in fourth week,
we found that the Contractor has collected leaked mud and stop bentonite slurry flow line at
this area.
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
77 | P a g e
At the other areas, there is no impact on soil quality from construction activities of project
detected.
March
We didn’t find any serious problem which impacts adversely on soil quality during the site
inspections this month.
At the Lo river bridge, pier 2 construction site, although the leaked mud was removed from
productive soil, however the silt fence has not been repaired despite many requirements of the
Engineer. During the site inspection on March 23rd 2011, the PSC has warned the site
manager and requested the Contractor to immediately resolve this matter and we found that
the Contractor has complied with request of the PSC.
Besides, the PSC has also requested the Contractor to tightly control hazardous substances
management usually such as oil, grease… to prevent leakage of these substances causing
soil pollution, especially productive soil.
4.4.3 Package A3
January
The last week of December (from 27th to 31st December 2010),Bentonite discharged was still
poured uncontrolledly onto soil-bed in contruction site of Bai Bang railway overpass
(Km60+900). Bentonite flowed into field area which was near contruction site, after long time, it
could impact harmfully on quality of farmland and crop. Consultant already noted this warning
in Contractor contruction site diary and would compose warning letter if Contractor still
postponed not to solve above issue. The first week of January (from 3rd to 7th January 2011)
Consultant rechecked contruction site and the result was that more mud in contruction site was
dredged; Contractor digged a furrow drain and blocked stream flow of Bentonite not to
overflow into below field area.
According to the result of second investigation ( from 10th to 14th January 2011), Consultant
found that there were so much oil available on the soil-bed, Contractor was required to clear
them immediately.
February
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
78 | P a g e
In February, Soil quality has not much changed compare with it in January. Except, the first
week, the Consultant has detected bentonite is poured uncontrolled on ground at Km77+700
(Red river bridge construction). The first reason is the Contractor does not observe
Environmental control plan. And the second is they can not manage their sub-Contractor. The
Contractor is requested to collect all fallen bentonite on ground and control it carefully to avoid
damage to soil quality. After that, in the inspection tour in the second week, the Consultant
inspected in this station and has not found fallen bentonite in site.
March
During March, fuel, oil, bentonite… were managed closer by the Contractor and strictly
inspection by the Consultant. The oil or bentonite spill risks were not detected in site. Beside,
the worker collected rubbish or domestic waste in site and near worker’s camps. Therefore,
soil quality was not affected by construction activities in this month. The Consultant still remind
the Contractor pay attention to maintenance control well all hazardous substance in site to
avoid risk and damage to soil quality.
4.4.4 Package A4
January
During January, the Consultant has not found any serious impact for soil quality. However,
during construction progress, it would have many impacts for soil environment so the
Consultant still strictly warning the Contractor must specially concentrate to controlling and
management fuel in site, avoid to leaking, overflowing oil on ground.
February
There are some differences between February and January. In inspection tours in February,
the Consultant has not detected leaking oil on ground.
The Contractor has just installed a mixing concrete station at Km91+000. If concrete is poured
into ground, it will effect to soil quality. Therefore, the Consultant will pay attention to this point
when we inspect in site.
March
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
79 | P a g e
The construction site quasi-stop execute all month because it was rain almost days of March.
Machine and fuel ungrouped in site. Beside, the worker collected rubbish or domestic waste in
site and near worker’s camps. The Consultant has not found any impact from construction
activities to soil quality.
4.4.5 Package A5
February
To date, the Contractor has executed construction activities on the site within project term that
did’t affect negatively the soil quality, especially agricultural land of local people around the
site.
In environment inspections, the Consultant has always required the Contractor to control tightly
the wastes, especially the harmful waste to prevent bad effects on soil quality.
March
To date, the Contractor still executes the construction activities on the site within the limits of
the project and therefore they have not affected negatively the soil quality, especially
agricultural land of local people around the site.
At some fuel stations of the Contractor, the Consultant has requested the Contractor to check
regularly the equipments which store fuel in order to avoid leakage of material which affects
soil quality.
Besides, in weekly site inspections, the Consultant has required the Contractor to control
disposal areas which store unsuitable soil and promptly move them to treatment areas which is
approved by the Consultant to ensure the environment as well as the soil quality.
4.4.6 Package A6
January
In this period, the site clearing activities, excavation and fill have been carried out on the entire
route of Package A6. To date, the Contractor still executes the construction activities on the
site within the limits of the project and therefore they have not affected negatively the soil
quality, especially agricultural land of local people around the site.
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
80 | P a g e
However, a large amount of unsuitable soil was disposed at some stations such as
Km171+900; Km175+020 which had not been submitted as disposal area by the Contractor.
This can affect the soil quality due to the mix of different soil types. The Consultant has
requested the Contractor to deal with this promptly in letter No.GET3/DOOSAN/A6/435 on
18th January 2011 and No. GET3/DOOSAN/A6/471 on 25th January 2011;
In environment inspections, the Consultant has always required the Contractor to control tightly
the wastes, especially the harmful waste to prevent bad effects on soil quality. Besides, the
Consultant has requested the Contractor to finish the documents of unsuitable disposal areas
as soon as possible and to submit them to the Consultant promptly so that they can be
considered and accepted.
February
To date, the Contractor still executes the construction activities on the site within the limits of
the project and therefore they have not affected negatively the soil quality, especially
agricultural land of local people around the site.
However, unsuitable soil was disposed at some stations such as Km161+100; Km165+050
which had not been submitted as disposal area by the Contractor. This can affect the soil
quality due to the mix of different soil types. The Consultant has requested the Contractor to
deal with this promptly in letter No. GET3/DOOSAN/A6/518 on 23rd February 2011.
In environment inspections, the Consultant has always required the Contractor to control tightly
the wastes, especially the harmful waste to prevent bad effects on soil quality.
March
This month, the Contractor still executes the construction activities on the site within the limits
of the project and therefore they have not affected negatively the soil quality, especially
agricultural land of local people around the site.
The Consultant has required the Contractor to control tightly the wastes and to consolidate the
equipments for preventing material leaking at fuel stations of the Contractor in order not to
affect the environment as well as the soil quality.
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
81 | P a g e
4.4.7 Package A7
January
Current construction activities of the Contractor in this month do not cause harmful effects to
soil quality. The layers of organic soils and unsuitable material disposals was transported to
the fixed and temporary landfills to can be re-used later for growing grass of talus.
The Contractor should pay more attention to other activities such as oil and waste oil tanks to
avoid oil and waste oils from spilling on the ground in the long time can lead to soil and
groundwater pollution.
February
In the inspection of construction on Feb 25th, 2011 at Khe Sang, Khe U and Khe Dai bridges,
Consultant did not detect any activity of the Sub contractor adversely impacts on soil quality in
the surrounding areas of their construction.
March
Current construction activities of the Contractor in this month did not cause harmful effects to
soil organic quality. The layers of organic soils and unsuitable material disposals were
transporte to the defined and temporary landfills in order to be reused later for growing grass of
slope.
The Contractor should pay more attention to other activities such as oil and waste oil tanks
management to avoid oil and waste oils from spilling on the ground because in the long time
they can be the cause of soil and groundwater pollution.
4.4.8 Package A8
January
During the periodic inspection on December 31, 2010, Consultant found that the waste oil form
Tuan Tu Company at Km237+060 and Viet Dung Company Km232+900 spill over on the
ground and polluted the soil environment. The Consultant has requested the Contractor to
overcome the above problems before Jan 5, 2011.
Worker's camps of Viet Dung Co. ltd at Km232 +900, oil waste spill into the ground and this
situation have been overcome under the opinion of the Consultant. However, oil waste spill
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
82 | P a g e
over on the ground of Tuan Tu Company at Km237+060 and still has not been overcome
throughly so the Contractor is required immediately to handle this problem.
February
In February, the Contractor began the construction only from February 21st, 2011 but
Consultant did not detect any activity of any adverse impacts of the Contractor on soil quality.
March
Current construction activities of the contractor in this month did not cause harmful effects to
soil organic quality. The layers of organic soils and unsuitable material disposals were
transported to the defined and temporary landfills in order to be reused later for growing grass
of slope.
The Contractor should pay more attention to other activities such as oil and waste oil tanks
management to avoid oil and waste oils from spilling on the ground because in the long time
they can be the cause of soil and groundwater pollution.
4.5 NOISE AND VIBRATION LEVELS
4.5.1 Package A1
January
During the month with the site inspection, we perceive that the sensitive areas such as temple,
pagoda, schools and resident areas are not affected by noise from construction activities of
project. Besides, these also no construction activity made the considerable vibration affect
these sensitive areas.
February
At the sensitive areas such as section Km 4+220 (pagoda), Km 13+100 (resident area), Km
19+650 (school) there was no construction work carried out during the month, therefore these
areas were not affected by noise or vibration from construction activities of project this month.
March
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
83 | P a g e
At Km 13+100, the construction quantity this month is very small and the main construction
activity is material transport so the noise and vibration rising from construction work of project
was no considerable.
At the sensitive areas such as section Km 4+220 (pagoda), Km 19+650 (school) there was no
construction work carried out during the month, therefore these areas were not affected by
noise or vibration from construction activities of project this month.
4.5.2 Package A2
January
During the month with the site inspections, we perceive that the sensitive areas such as
temple, pagoda, schools and resident areas are not affected by noise from construction
activities of project. Besides, these also no construction activity made the considerable
vibration affect these sensitive areas.
February
At the sensitive areas such as Km 34+780 (Hoang Van pagoda and resident area) we didn’t
detect the adverse impact of noise of vibration from the construction activities of project.
Besides, the quantity of construction work at this area is small so there were not many
equipment operated here.
March
During site inspections this month we didn’t detected the negative impact of noise and
vibration which raise from construction activities of project on sensitive areas (Km 34+780 –
pagoda; Km 34+480 – resident area). In addition, the quantity of construction work at this area
is small so there were not many equipment operated here.
4.5.3 Package A3
January
Construction sites near resident areas as Km48+360, Km55+500, Km67+800, Km78+900
have not worked yet. At Km52-Km54+400; Km58-Km59; Km61-Km67; Km70-Km76+400,
Km77+200+-Km77+800, Km60+900… almost current construction areas are far from resident
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
84 | P a g e
areas. At present, the Consultant has not found any serious effect by noise or vibration to
sensitive points along package A3.
February
According Noise monitoring result when the Consultant take it in site we have some conclusion
as bellow:
Location Monitoring value (dBA)
Standard Value (dBA)
TCVN 5949:1998 (LAeq) Remark
6h -18h 18- 22h 22h- 6h 6h -18h 18- 22h 22h- 6h
Km 48+500
(resident area)
59 51 42 60 55 50 Not yet work
Km 55+550
(resident area)
53 48 37 60 55 50 Not yet work
Km 67+700
(resident area)
58 53 42 60 55 50 Not yet work
Km 78+900 (resident area intermix trading, service).
48 44 39 75 70 50 Not yet work
At monitoring points, construction work is not implemented so above monitoring value is Noise
base data for Package A3. The current construction areas which are operating far from
resident areas as Km52-Km54+400; Km58-Km59; Km61-Km67; Km70-Km76+400,
Km77+200+-Km77+800, Km60+900…
March
According Noise monitoring result when the Consultant takes it in site we have some
conclusion as bellow:
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
85 | P a g e
Location Monitoring value (dBA)
Standard Value (dBA)
QCVN 27:2010/BTNMT
6h -12h 12- 15h 15h- 18h 6h-18h
Km48+500 (resident area) 51 57 58 60
Km55+550 (resident area) 53 60 59 60
Km67+700 (resident area) 50 58 57 60
Km78+900 (resident area
intermix trading, service). 52 58 56 60
Noise monitoring results at the positions are in the Standard Value. The Contractor is
requested to maintain control of construction activities to noise arising from the allowed limit.
4.5.4 Package A4
January
Almost construction site which are working , are far from resident areas. Except construction
area at Km92+800 in section 3, there are about ten households scattered along left side.
Therefore, in order to controlling disadvantage impacts of noise to sensitive areas near site,
the Consultant requested Contractor Keangnam to submit noise report if they has plan for any
work carried out at night next to sensitive points (resident areas, school, pogoda ...).
February
The Construction work is still not executed at Km91+150 (school), Km106+700(school),
Km95+100 (residential area), Km108+227(residential area) which is sensitive areas along
package A4. The Consultant has not found any impact of noise and vibration from the
construction activities to sensitive areas.
The Construction sites are working now at Km81-Km82, Km89+800, km92-km94, km97-km98,
km103-km104, km105-km108… almost are far from residential areas.
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
86 | P a g e
March
The Construction work is still not executed at Km91+150 (school), Km106+700(school),
Km95+100 (residential area), Km108+227(residential area) which is sensitive areas along
package A4. The Consultant has not found any impact of noise and vibration from the
construction activities to sensitive areas.
The Construction sites are working now at Km81-Km82, Km89+800, km92-km94, km97-km98,
km103-km104, km105-km108… almost are far from residential areas.
4.5.5 Package A5
February
During this period, noise and vibration have not seriously affected the construction areas on
the site and residential areas, schools, temples, churches, hospitals ....
In February, the Consultant has measured the noise level in some areas with the sound meter
SC-2c.
No Location Date Time Noise level (dBA)
Max Min Average
1 Km112+500 11/02/2011 09h45 AM 57 43 50.0
2 Km118+930 15/02/2011 15h45 PM 59 52 55.5
All of the noise observation areas above are near residential areas (with maximum permitted
noise level of 60 dBA from 6h00 AM to 18h00 PM). This noise level does not exceed TCVN
(Vietnamese Standards) 5949-1998 (Acoustics – Noise in public and residential areas
maximum permitted noise level)
The Consultant has also advised the Contractor to reduce construction at night in the sensitive
and residential areas.
In coming months, the Consultant will regularly test noise level in the sensitive areas and
residential areas with the sound meter SC-2c to timely detect the areas with the noise levels
over permitted TCVN in order to advise the Contractor to implement the noise minimization
measures that are appropriate in those areas.
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
87 | P a g e
March
During this period, noise and vibration have not seriously affected the construction areas on
the site and residential areas, schools, temples, churches, hospitals ....
In March, the Consultant has measured the noise level in some areas with the sound meter
SC-2c.
No Location Date Time Noise level (dBA)
Max Min Average
1 Km117+050 10/03/2011 10h00 AM 58 46 52.0
2 Km118+820 10/03/2011 16h15 AM 60 53 56.5
3 Km121+433 23/03/2011 09h30 AM 59 50 54.5
All of the noise observation areas above are near residential areas (with maximum permitted
noise level of 60 dBA from 6h00 AM to 18h00 PM). This noise level does not exceed TCVN
(Vietnamese Standards) 5949-1998 (Acoustics – Noise in public and residential areas
maximum permitted noise level)
The Consultant has also advised the Contractor to reduce construction at night in the sensitive
and residential areas.
In coming months, the Consultant will regularly test noise level in the sensitive areas and
residential areas with the sound meter SC-2c to timely detect the areas with the noise levels
over permitted TCVN in order to advise the Contractor to implement the noise minimization
measures that are appropriate in those areas.
4.5.6 Package A6
January
The package A6 goes through the mountainous region of Yen Bai province, and through
residential areas and other sensitive areas not much. During this period, noise and vibration
have not seriously affected the construction areas on the site and residential areas, schools,
temples, churches, hospitals....
In January, the Consultant has measured the noise level in some areas with the sound meter
SC-2c.
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
88 | P a g e
No Location Date Time Noise level (dBA)
Max Min Medium
1 Km157+500 12/01/2011 09h30 AM 58 47 52.5
2 Km163+200 12/01/2011 14h00 AM 60 53 56.5
3 Km165+350 21/01/2011 10h00 AM 61 51 56.0
4 Km176+500 21/01/2011 14h15 PM 58 45 51.5
5 Km184+500 21/01/2011 15h45 PM 59 49 54.0
All of the noise observation areas above are near residential areas (with maximum permitted
noise level of 60 dBA from 6h00 AM to 18h00 PM). This noise level does not exceed TCVN
5949-1998 (Acoustics – Noise in public and residential areas maximum permitted noise level)
The Consultant has also advised the Contractor to reduce construction at night in the sensitive
and residential areas.
In coming months, the Consultant will regularly test noise level in the sensitive areas and
residential areas with the sound meter SC-2c to timely detect the areas with the noise levels
over permitted TCVN (Vietnamese Standards) in order to advise the Contractor to implement
the noise minimization measures that are appropriate in that area.
February
The package A6 goes through the mountainous region of Yen Bai province, and less through
residential areas and other sensitive areas. During this period, noise and vibration have not
seriously affected the construction areas on the site and residential areas, schools, temples,
churches, hospitals, ....
In February, the Consultant has measured the noise level in some areas with the sound meter
SC-2c.
No Location Date Time Noise level (dBA)
Max Min Average
1 Km157+500 12/02/2011 10h00 AM 59 45 52.0
2 Km163+200 12/02/2011 15h15 PM 61 51 56.0
3 Km165+350 14/02/2011 09h00 AM 56 49 52.5
4 Km176+500 14/02/2011 14h30 PM 59 47 53.0
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
89 | P a g e
5 Km184+500 14/02/2011 16h00 PM 57 50 53.5
All of the noise observation areas above are near residential areas (with maximum permitted
noise level of 60 dBA from 6h00 AM to 18h00 PM). This noise level does not exceed
TCVN(Vietnamese Standards) 5949-1998 (Acoustics – Noise in public and residential areas
maximum permitted noise level)
The Consultant has also advised the Contractor to reduce construction at night in the sensitive
and residential areas.
In coming months, the Consultant will regularly test noise level in the sensitive areas and
residential areas with the sound meter SC-2c to timely detect the areas with the noise levels
over permitted TCVN in order to advise the Contractor to implement the noise minimization
measures that are appropriate in that area.
March
The package A6 goes through the mountainous region of Yen Bai province, and less through
residential areas and other sensitive areas. During this period, noise and vibration have not
seriously affected the construction areas on the site and residential areas, schools, temples,
churches, hospitals, ....
In March, the Consultant has measured the noise level in some areas with the sound meter
SC-2c.
No Location Date Time Noise level (dBA)
Max Min Average
1 Km155+360 04/03/2011 10h30 AM 57 51 54.0
2 Km163+200 04/03/2011 14h45 AM 59 50 54.5
3 Km165+350 24/02/2011 09h45 AM 60 56 58.0
4 Km176+500 24/02/2011 16h15 PM 58 56 57.0
All of the noise observation areas above are near residential areas (with maximum permitted
noise level of 60 dBA from 6h00 AM to 18h00 PM). This noise level does not exceed
TCVN(Vietnamese Standards) 5949-1998 (Acoustics – Noise in public and residential areas
maximum permitted noise level)
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
90 | P a g e
The Consultant has also advised the Contractor to reduce construction at night in the sensitive
and residential areas.
In coming months, the Consultant will regularly test noise level in the sensitive areas and
residential areas with the sound meter SC-2c to timely detect the areas with the noise levels
over permitted TCVN in order to advise the Contractor to implement the noise minimization
measures that are appropriate in that area.
4.5.7 Package A7
January
At the present, the construction sites of bridges such as Khe Sang at Km191+353, Tan An
bridge at Km194+756, Khe Can bridge Km195+360, Khe U bridge at Km204+581, Ngoi Bong
bridge at Km207+935 also are far away from residential and sensitive areas like schools and
hospitals. Therefore, the contractor's activities are drillers, air compressors; diesel engines
didn’t cause adverse impact on noisy and vibration to these areas.
In addition, the construction of road base operations, transportation of materials can also
cause impacts on noisy and vibration but the impacts is appraised to be acceptable and in
accordance with limited noise and vibration levels .
Noise measuring results are compared with TCVN 5949:1998: Acoustics-noise in public and
residential areas. Maximum allowable noise level is shown in the following table:
Sample
Noise level (dBA)
Leq Lmax L50
L1 L2 L3 TB L1 L2 L3 TB L1 L2 L3 TB
N01 52.5 48.6 49.5 50.2 82.2 71.8 84.5 80.5 38.4 39.5 49.5 42.5
N02 58 55.7 57.4 57.0 72.5 72.8 72.9 72.7 49.7 49.8 49.5 49.7
N03 51.1 51.7 38.2 47.0 63.5 62.7 54.9 60.4 41.9 42 36 40.0
N04 47 60.7 46.5 51.4 72.5 81.9 72.8 75.7 29.1 37.2 33.5 33.3
N05 47.3 55.0 50.1 50.8 72.8 77.9 75.3 75.3 41.9 39.7 40.2 40.6
N06 46.5 47.3 50.5 48.1 62.3 66.9 58.1 62.4 39.3 37.3 38.1 38.2
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
91 | P a g e
N07 46.2 42.2 46.8 45.1 72.6 73.5 74.9 73.7 31.8 38.2 37.1 35.7
N08 46.5 42.5 50.7 46.6 64.4 64.0 65.7 64.7 40.6 36.3 48.1 41.7
N09 50.1 32.3 30.7 37.7 72.8 72.6 74.0 73.1 49.7 48.7 34.1 44.2
N10 57 59.7 59.8 58.8 79.9 82.7 83 81.9 41.3 32 45 39.4
N11 47.8 46.9 47.4 47.4 72.3 72.0 74.4 72.9 36 34.8 36.4 35.7
N12 50.4 60.2 55.5 55.4 72.2 71.5 70.0 71.2 35.5 40.3 45.6 40.5
N13 49.3 46.5 52.0 49.3 72.9 73.2 73.6 73.2 36.3 38.9 35.5 36.9
N14 50.1 47.2 48.3 48.5 65.6 64.8 67.6 66.0 40.6 43.3 42.1 42.0
TCVN 5949:1998
75 - -
Note:
N01: Xuan Sang 1 Primary School, Xuan Sang 1 Hamlet, Tan An Commune, Van ban District (coordinates X: 2447621; Y: 437656)
N02: Concrete mixing plant No.1, Ngam Thin Hamlet, Tan Thuong Commune, Van Ban District (coordinates X: 2450769; Y: 431840)
N03: Concrete mixing plant No.2, Dap Tran Hamlet, Tan Thuong Commune, Van Ban District (coordinates X: 2450128; Y: 432378)
N04: Bridge girder casting yard, Xuan Sang 2 Hamlet, Tan An Commune, Van Ban District (coordinates X: 2446740; Y: 437982)
N05: Equipment gathering yard, worker’s living area, Khe U Hamlet, Tan Thuong Commune, Van Ban District (coordinates X:2454378; Y:430097)
N06: Cam Con Primary School, Khe Mai Hamlet, Cam Con Commune, Bao Yen District (coordinates X:2455549; Y:428569)
N07: Cam Con Health Center, Tan Tien Commune, Bao Yen District (coordinates X:2459218; Y:425187)
N08: Drainage casting yard No.1, Khe Quat Hamlet, Tan An Commune, Van Ban District (coordinates X:2448896; Y:435403)
N09: Khe U Primary School, Khe U Hamlet, Tan Thuong Commune, Van Ban District (coordinates X:2454480; Y:430171)
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
92 | P a g e
N10: Residential areas at the right side of project road, Ban Ly Hamlet, Cam Con Commune, Bao Yen District (coordinates X:2455100; Y:429124)
N11: Tan Thuong Secondary School, Khe Tep Hamlet, Tan Thuong Commune, Van Ban District (coordinates X:2451577; Y:431693)
N12: Drainage casting yard No.2, Bong 1 Hamlet, Cam Con Commune, Bao Yen District (coordinates X:2458097; Y:425895)
N13: Cam Con Secondary School, Hamlet 2, Cam Con Commune, Bao Yen District (coordinates X:2461778; Y:422467)
N14: Tan An Kinder Garden, Tan Duong Hamlet, Tan An Commune, Van Ban District (coordinates X:2450626; Y:434435)
As mentioned above, all the noise monitoring results are compared with Vietnam standard
TCVN 5949-1998 for the region that mixing between production and residential areas. Most of
the measured data are approximately or lower than the prescribed level in ISO 5949-1998, and
the ranges of measured results are as follows:
Leq noise levels ranged from 37.7 dBA to 58.8 dBA. The highest value was found in residential
areas that located on the right side of project, in Ban Ly Hamlet, Cam Con Commune, Bao Yen
District
As the same as noise monitoring, the results of vibration monitoring will be compared with
TCVN 6962:2001: Vibration and shock-Vibration emitted by construction activities and
industrial production. Maximum allowable level for environment in public and residential areas
are as follows
SampleLaeq (m/s2) Lveq (m/s) Frequ
ency (Hz) L1 L2 L3 TB L1 L2 L3 TB
V01 0.00155 0.00170 0.00162 0.00162 0.000309 0.000339 0.000323 0.000324 8Hz
V02 0.000945 0.00118 0.00114 0.00109 0.000190 0.000235 0.000227 0.000217 8Hz
V03 0.00128 0.00139 0.00127 0.00131 0.000255 0.000277 0.000253 0.000262 8Hz
V04 0.00148 0.00196 0.00183 0.00176 0.000294 0.000390 0.000365 0.000350 8Hz
V05 0.00106 0.00139 0.00114 0.00120 0.000210 0.000277 0.000227 0.000238 8Hz
V06 0.00154 0.00129 0.00133 0.00139 0.000306 0.000256 0.000265 0.000276 8Hz
V07 0.00143 0.00156 0.00164 0.00154 0.000284 0.000311 0.000326 0.000307 8Hz
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
93 | P a g e
SampleLaeq (m/s2) Lveq (m/s) Frequ
ency (Hz) L1 L2 L3 TB L1 L2 L3 TB
V08 0.00140 0.00113 0.00121 0.00125 0.000278 0.000224 0.000240 0.000247 8Hz
V09 0.00138 0.00164 0.00132 0.00145 0.000274 0.000326 0.000262 0.000287 8Hz
V10 0.00182 0.00167 0.00179 0.00176 0.000361 0.000333 0.000356 0.000350 8Hz
V11 0.00141 0.00157 0.00141 0.00146 0.000281 0.000313 0.000281 0.000292 8Hz
V12 0.00188 0.00167 0.00165 0.00175 0.000375 0.000332 0.000328 0.000345 8Hz
V13 0.00180 0.00172 0.00183 0.00178 0.000357 0.000342 0.000363 0.000354 8Hz
V14 0.00118 0.00139 0.00122 0.00126 0.000234 0.000277 0.000243 0.000251 8Hz
TCVN 6962: 2001
0.055
Note:
V01: Xuan Sang 1 Primary School, Xuan Sang 1 Hamlet, Tan An Commune, Van ban District (coordinates X: 2447621; Y: 437656)
V02: Concrete mixing plant No.1, Ngam Thin Hamlet, Tan Thuong Commune, Van Ban District (coordinates X: 2450769; Y: 431840)
V03: Concrete mixing plant No.2, Dap Tran Hamlet, Tan Thuong Commune, Van Ban District (coordinates X: 2450128; Y: 432378)
V04: Bridge girder casting yard, Xuan Sang 2 Hamlet, Tan An Commune, Van Ban District (coordinates X: 2446740; Y: 437982)
V05: Equipment gathering yard, worker’s living area, Khe U Hamlet, Tan Thuong Commune, Van Ban District (coordinates X:2454378; Y:430097)
V06: Cam Con Primary School, Khe Mai Hamlet, Cam Con Commune, Bao Yen District (coordinates X:2455549; Y:428569)
V07: Cam Con Health Center, Tan Tien Commune, Bao Yen District (coordinates X:2459218; Y:425187)
V08: Drainage casting yard No.1, Khe Quat Hamlet, Tan An Commune, Van Ban District (coordinates X:2448896; Y:435403)
V09: Khe U Primary School, Khe U Hamlet, Tan Thuong Commune, Van Ban District (coordinates X:2454480; Y:430171)
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
94 | P a g e
V10: Residential areas at the right side of project road, Ban Ly Hamlet, Cam Con Commune, Bao Yen District (coordinates X:2455100; Y:429124)
V11: Tan Thuong Secondary School, Khe Tep Hamlet, Tan Thuong Commune, Van Ban District (coordinates X:2451577; Y:431693)
V12: Drainage casting yard No.2, Bong 1 Hamlet, Cam Con Commune, Bao Yen District (coordinates X:2458097; Y:425895)
V13: Cam Con Secondary School, Hamlet 2, Cam Con Commune, Bao Yen District (coordinates X:2461778; Y:422467)
V14: Tan An Kinder Garden, Tan Duong Hamlet, Tan An Commune, Van Ban District (coordinates X:2450626; Y:434435)
As a rule, the vibration acceleration should not exceed 0.055 m/s2 from 7h to 19h. According
to table 12, the average vibration values range from 0.00109 to 0.00178 m/s2 and below the
prescribed level.
February
At the present, the Contractor has installed two cement stations at Khe Sang Bridge at
Km191+ 353 and Xom Danh Bridge at Km198+400. However, the two cement stations were
located far away from the residential and sensitive areas. They are not be operated now so
haven't caused any effect of noise and vibration levels.
In addition, the construction of road base operations, transportation of materials can also
cause impacts on noise and vibration but the impacts are appraised to be acceptable and in
accordance with standards noise and vibration levels .
March
At the present, the Contractor has installed two cement stations at Khe Sang Bridge at
Km191+ 353 and Xom Danh Bridge at Km198+400. However, the two cement stations were
located far away from the residential and sensitive areas. They are not be operated now so
haven't caused any effect of noise and vibration levels.
In addition, the construction of road base operations, transportation of materials can also
cause impacts on noise and vibration but the impacts are appraised to be acceptable and in
accordance with standards noise and vibration levels .
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
95 | P a g e
4.5.8 Package A8
January
Currently the construction site of Ngoi Bo bridge , Suoi Nhu Bridge are located away from
residential and sensitive areas so the impact of construction equipment such as bored pile
machine, air compressor, concrete drill do not affect the level of noisy and vibration to people
here.
In addition to the construction site of IC18 Bridge, Suoi Trat Bridge is located near highways
and houses. However, during the construction process of IC 18 Bridge has definitely stopped
wall around to minimize the noise and vibration impacts. Proposed the unit constructing Suoi
Trat to give measures to minize the impacts of noisy and vibration.
February
Currently a number of constructions such as Suoi Nhu, IC 18 and Ngoi Bo Bridges did not
cause impacts on noisy and vibration because the location of construction of the bridge away
from residential areas and sensitive areas .
In addition, the construction of road base operations, transportation of materials can also
cause impacts on noise and vibration but the impacts are appraised to be acceptable and in
accordance with standards noise and vibration levels.
March
Currently a number of constructions such as Suoi Nhu, IC 18 and Ngoi Bo Bridges did not
cause impacts on noisy and vibration because the location of construction of the bridge away
from residential areas and sensitive areas .
In addition, the construction of road base operations, transportation of materials can also
cause impacts on noise and vibration but the impacts are appraised to be acceptable and in
accordance with standards noise and vibration levels .
Result of the Contractor noise and vibration level monitoring (carried out by Green
Environment Engineering Joint Stock Company in February 2011) shown in the following
tables.
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
96 | P a g e
Sampling site
Noise level (dBA)
Leq Lmax L50
L1 L2 L3 Average L1 L2 L3 Average L1 L2 L3 Average
N01 47.7 52.1 45.6 48.5 58.6 61.4 55.7 58.6 52.4 56.5 48.7 52.5
N02 50.7 54.6 53.3 52.9 64.1 65.2 61.8 63.7 56.2 58.7 57.2 57.4
N03 67.3 63.3 64.7 65.1 87.1 76.4 71.3 78.2 69.5 68.8 66.8 68.4
N04 70.7 61.4 66.3 66.1 87.1 75.1 72.6 78.3 73.2 66.5 68.1 69.3
N05 46.5 64.5 52.4 54.5 58.8 76.8 63.1 66.2 49.8 68.4 55.7 58.0
N06 51.4 52.5 54.4 52.8 68.7 64.7 61.9 65.1 63.2 57.8 57.4 59.5
N07 66.8 60.7 68.4 65.3 78.4 71.9 74.6 75.0 69.3 65.8 70.3 68.5
N08 59.2 48.8 61.5 56.5 70.6 60.5 68.3 66.5 62.6 55.4 64.1 60.7
QCVN 26:2010 / BTNMT
70 - -
Note:
L1, L2, L3: Times measuring during 01 hour, 10 minutes measured each time.
N-01: Near the starting point of project, Sonha primary School -No 2, Anthang branch
(GPS: E:48418960; N:2465164);
N-02: Sonha primary School -No 2, Sonha commune (GPS: E:48416909; N:2467052);
N-03: Near Nangsom pre-school, near gate of Kheden village, Sonha commune
(GPS: E:48415439; N:2468285);
N-04: Xuangiao road junction (GPS: E:48408457; N:2471454);
N-05: Mixing concrete station - Near Xuangiao High school - Langpheo branch
(GPS: E:48409086; N:2470910 );
N-06: Giaphu primary School -No 3 (GPS: E:48403182; N:2474612);
N-07: Point of intersection with Binhminh road (IC 18) near petrol station
(GPS: E:48439948; N:2478869);
N-08: Section of covering drain of precasting concrete (GPS: E:48404272; N:2472996).
As mentioned, all the noise monitoring results are compared with Vietnam standard QCVN
26:2010 / BTNMT - National Technical Regulations on noise. Most of the measured data to or
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
97 | P a g e
lower than the prescribed level of approximately QCVN 26:2010/BTNMT and the following
changes:
Leq noise levels ranged from 48.5 dBA to 66.3 dBA and the highest in Giao Xuan Nga Ba
position and the position of Communications for the road Dawn (IC18) near gas stations.
Similar observation noise, vibration measuring results are compared with QCVN 27:2010 /
BTNMT - National Technical Regulations on vibration, shown in the following table:
Sampling site
Lva (m/s2) Lv (m/s) Frequency
(Hz) L1 L2 L3 Average L1 L2 L3 Average
V01 0.0039 0.0054 0.0038 0.0044 0.0028 0.0027 0.0031 0.0029 1-10
V02 0.0043 0.0067 0.0039 0.0050 0.0035 0.0032 0.0032 0.0033 1-10
V03 0.0055 0.0022 0.0061 0.0046 0.0033 0.0034 0.0026 0.0031 1-10
V04 0.0141 0.0186 0.0135 0.0154 0.0024 0.0028 0.0030 0.0027 1-10
V05 0.0033 0.0047 0.0024 0.0035 0.0026 0.0026 0.0019 0.0024 1-10
V06 0.0039 0.0057 0.0025 0.0040 0.0025 0.0026 0.0028 0.0026 1-10
V07 0.0150 0.0168 0.0134 0.0151 0.0031 0.0033 0.0020 0.0028 1-10
V08 0.0052 0.0088 0.0071 0.0070 0.0028 0.0033 0.0026 0.0029 1-10
QCVN 27:2010/ BTNMT
0.055
Note:
L1, L2, L3: Times measuring during 01 hour, 10 minutes measured each time.
V-01: Near the starting point of project, Sonha primary School -No 2, Anthang branch
(GPS: E:48418960; N:2465164);
V-02: Sonha primary School -No 2, Sonha commune (GPS: E:48416909; N:2467052);
V-03: Near Nangsom pre-school, near gate of Kheden village, Sonha commune
(GPS: E:48415439; N:2468285);
V-04: Xuangiao road junction (GPS: E:48408457; N:2471454);
V-05: Mixing concrete station - Near Xuangiao High school - Langpheo branch
(GPS: E:48409086; N:2470910 );
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
98 | P a g e
V-06: Giaphu primary School -No 3 (GPS: E:48403182; N:2474612);
V-07: Point of intersection with Binhminh road (IC 18) near petrol station
(GPS: E:48439948; N:2478869);
V-08: Section of covering drain of precasting concrete (GPS: E:48404272; N:2472996).
As a rule, the vibration acceleration should not exceed 0.055 m/s2 from 7h to 19h. According
to table 12, the average vibration values range from 0.0035 to 0.0154 m/s2 m/s2 and below
the prescribed level.
4.6 STREAMS AND RIVERSIDES MAINTENANCE
4.6.1 Package A1
January
At the Xuan Phuong bridge and Tan Loi bridge construction sites, the Contractor narrowed the
water bodies for construction works and temporary stream crossings. The PSC has found the
risks of erosion and requested the Contractor to apply the measures to stabilize the bed, inlets
and outlets of temporary culverts as well as control erosion to prevent blocking water flows at
these sections. Up to now, the water flows at these sections are still maintained.
At the other sections, the construction activities don’t affect the stream or riversides.
February
At Xuan Phuong bridge construction site, during site inspection in the third week we perceived
that the capacity of temporary pile culverts is not enough and unsuitable with velocity of water
flow when the water level rose high due to the local authority provides water for new crop. The
left side of stream in this area is also eroded because the Contractor didn’t apply the measure
to stabilize the outlet of temporary pipe culvert and the side of stream as the instructions of
Engineer (we had issued the instruction letter of temporary stream crossing in the third week –
see in the annex 3). The PSC has instructed and request the Contractor to mobilize more pipe
culverts to ensure the water flow as well as safety for workers in the weekly meeting in the
fourth week. The Contractor promised to resolve this problem by the Monday, February 28th
2011. The PSC will recheck this area during the next site inspection on Tuesday, March 01st
2011.
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
99 | P a g e
The erosion happened will be mitigated, at the end of the works in this area, with the
application of corrective measures to restore the affected riverside.
Besides, we didn’t find the adverse impact on stream and riversides at the other sections.
March
During site inspection on March 08th 2011, we perceived that the Contractor had installed
more two pipe culverts for temporary stream crossing at Xuan Phuong bridge construction site.
However, the PSC reckoned that only two pipe culverts have been installed more is not
enough, besides, the outlets and inlets of temporary pipe culverts have not stabilized so the
temporary stream crossing at this section can be broken easily when the water level here
rises, especially in the coming rainy season. The PSC has also recommended the Contractor
to pay attention to this opinion to apply the suitable measures to make sure the water flow as
well as safety and the solid of structure.
In addition, we also realized that the left riverside at this area has been no longer eroded.
At section Km 2+218 ~ Km 2+960, during site inspection on March 15th 2011 we detected that
temporary pipe culverts are not enough capacities and easy to be blocked by erosion and
sedimentation in the rain. The PSC has requested the Contractor to install new others to make
sure the water flow at this section. From March 16th 2011 till March 17th 2011, the weather
was drizzle rain, the PSC rechecked this area and detected that the Contractor had not
replaced unsuitable temporary pipe culverts and the water flows has been blocked by erosion
and sedimentation. The PSC has issued the warning letter to request the
Contractor to resolve this problem and will recheck this area on March 29th 2011.
Temporary drainage at section Km 0+775 is considered not enough capacity and the PSC has
also requested the Contractor replace with another in the site inspection on March 24th 2011.
4.6.2 Package A2
January
At the Ben Gao bridge construction site, the Contractor has narrowed the water body of the
stretch of river for construction activities (bored pile work) and we found that there was a little
of mud spilled into river due to the Contractor didn’t apply the erosion and sediment control
measures to retain the sediment on construction site.
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
100 | P a g e
Besides, at the Tan Dung bridge construction site, the small erosion happened and blocked
the inlet of culvert of temporary stream crossing.
The PSC has requested the Contractor to solve these problems and with the Contractor’s
report and site inspection of PSC, we perceived that the Contractor has implemented the
requests of Engineer and made sure the water flows at these areas.
February
At Tan Dung bridge, during the site inspection on February 09th 2011, we found that the
casing was put on the bank of irrigational canal and in water flow. The PSC has requested the
Contractor to remove this casing to the material storage area right after the workers come back
site to work. In the next site inspection on February 16th 2011, we perceived that the casing
was removed from water flow.
At Song Dao bridge, the Contractor had installed the temporary stream crossing with
unsuitable pipe culverts so the water flow was blocked. During the site inspection on February
21st 2011, the PSC has request the Contractor to demobilize the temporary stream crossing to
ensure the water flow to prevent the flood on upstream. Besides, the Contractor also has to
reinstall temporary stream crossing with suitable pipe culverts to ensure the water flow and
tally with high water level and flow velocity in rainy season coming and/or during the local
authorities provide water for cultivated crops.
The PSC will recheck this section in the next site inspection on March 01st 2011.
March
At Song Dao bridge construction site, during the site inspection on March 02nd 2011 we
detected that the Contractor has not implemented requirements of PSC regarding to water flow
protection here. We had requested again the Contractor to comply with our requirement as
statement last month to make sure the water flow as well as protect the irrigation work.
On March 16th 2011, we perceived that the Contractor had demobilized the temporary pipe
culvert and restored the water flow at this area.
At other sections, we didn’t detect the serious problem impacts on streams and riversides
maintenance during site inspections.
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
101 | P a g e
4.6.3 Package A3
January
At Km 51 Bridge TL323B, Contractor digged and enlarged irrigation canal in project area. And
circulate drain was placed in this position to maintain stream flow to serve irrigation for
surrouding areas.
At Km74+500, Contractor currently transported discharged earth out of buiding site, the ditch
crossing over contruction site would be enlarged in the nearest future.
February
At Km51, Km74+500, Km73+600, Km72+300 the Contractor built pile culvert to maintenance
irrigation flow in February.
There is a canal across at Km68+300 but it is not set up pile culvert because drawing is not
approved. Therefore, the Contractor has dredged this canal to unblock it since 2 weeks ago
(14th- 19th February).
March
In order to maintenance flow of drainage canal, the pile culvert is executed in many points
along package A3 in March, ex: Km73+210, Km73+670, Km73+769, Km73+940. In this month,
the Consultant has not found any impact of construction works to block the drainage canal.
4.6.4 Package A4
January
In package A4, almost construction activities are site clearing and top soil remove. At present,
the Consultant has not found any impact from construction work to block river, stream, canal
flow in project area.
February
In February, the construction work has not executed near river or stream in package A4. Up to
now, the Consultant has not detected any canal is blocked or river, stream are impacted.
March
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
102 | P a g e
The Contractor has not executed near river or stream in package A4. But in inspection tour on
March 21st-26th, 2011 the Consultant has found that mud take one-third of Ngoi Gianh stream
bed. But the Contractor undertook that is the result of other project of Cam Khe district
because the Contractor still has not implement yet in this point. We confirm the Contractor still
has not implement in Ngoi Gianh (Km88+700) yet.
At Km108+965, the Consultant detected that Earth is fallen to drainage canal in inspection tour
on March 21st-26th, 2011. It will be blocked in near future. The Contractor is requested to
dredge all fallen earth in drainage canal bed and reinforce side of this access road to avoid fall
solid substance into drainage canal. We will recheck in next week
4.6.5 Package A5
February
In this period, there was no item of building bridges and culverts. Streams and riversides are
still maintained in good conditions.
However, during construction process at stations Km119+000-Km119+700, unsuitable soil has
stopped the water flow of some gutters. The Consultant has required the Contractor to install
temporary culverts at these stations immediately in letter ref.GET3/KEANGNAM/A5/110 on
15th February 2011.
In weekly site inspections, the Consultant has always reminded the Contractor to ensure the
natural water flow of streams and river corridors
March
This month, streams and riversides are maintained in good conditions. In weekly site
inspections, the Consultant has frequently reminded the Contractor to ensure natural water
flow of streams and river. Besides, the Consultant has required the Contractor to transport all
unsuitable soil to disposal area which is approved by the Consultant to ensure that unsuitable
soil can’t affect Stream and River in project area.
In coming months, the Consultant will regularly inspect the situation of River and Stream in
order to discover negative effects on Stream and River due to construction activities of the
project and remind the Contractor to deal with it.
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
103 | P a g e
4.6.6 Package A6
January
On the entire route of package A6 there are many locations that require building bridges over
rivers, streams and many culverts. At present, in some areas like Ngoi Rom bridge, Ngoi Giam
bridge, Ngoi Nhuoc bridge, Lang Nhay bridge, temporary paths cross the streams were in
progress, however, the Contractor has installed culverts to ensure natural water flow in these
areas.
In this period, unsuitable soil was disposed and stored at some unaccepted positions, that can
affect the water flow of streams and rivers.
At some other stations, the construction activities didn’t affect the streams and river sides.
February
At present, streams and riversides are maintained in good conditions. The construction of Ngoi
Rom bridge, Ngoi Giam bridge, Ngoi Nhuoc bridge,… goes through small rivers and streams,
however, the Contractor has installed temporary culverts to ensure natural water flow in these
areas.
In this period, at some stations such as Km161+100; Km165+050, waste soil was disposed in
Red river area that affects river corridors and risks spilling into Red river. The Consultant has
requested the Contractor to deal with this promptly in letter No. GET3/DOOSAN/A6/518 on
23th February 2011.
In weekly site inspections, the Consultant has frequently reminded the Contractor to ensure
natural water flow of streams and river corridors.
March
This month, the construction activities of the project haven’t affect seriously the situation of the
Stream and River. However, the package A6 is near to Red river and goes through many small
streams and rivers. Therefore, unsuitable soil was disposed or stored near rivers and streams
at some stations such as Km190+140; Km187+300; Km171; Km165+050; Km173
Km161+100,…, that can affect river’s corridors as well as quality of river water. The
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
104 | P a g e
Consultant has required the Contractor to move them promptly to disposal area which is
approved by the Consultant to ensure the water quality of streams and rivers in project area.
In weekly site inspections, the Consultant has frequently reminded the Contractor to ensure
the natural water flow of the streams and the river corridors.
4.6.7 Package A7
January
At the construction side of Khe U Bridge, on Jan 14, 2011 during the construction process soil
and rocks flew into the stream and intercepted the flow. Consultant has required the Contractor
resolve the above problem immediately and Contractor has mobilized machinery and
manpower to clear the flow and return natural flow to this stream.
At construction sites of Khe U, Khe Sang, Ngoi Bong bridges are the construction sites of
bridges crossing streams and the Contractor has installed sullage pits to ensure flow
circulation and not interfere and cause water pollution, ensuring good maintenance problems
embankments and canals during construction process.
However, during the later process construction, consultant also remind contractor to take
measures to minimize adverse impacts on erosion of embankments and canals of these
streams.
February
At the present, the embankments of these streams at the position of Khe Sang and Khe U
bridges are remained well without having erosion and landsides although the subcontractor let
rubbish and soil to fall into the stream and caused obstruct and changed the flow at some
positions (on Feb 25th, 2011). However, because of the low flow and resolution of the
Subcontractor timely so it did not cause any erosion and landside in both sides of the stream.
March
Currently all of the bridges over the streams are under in the construction process by
contractor such as Khe Sang Bridge at Km191+353, Khe U Bridge at Km204+581, Ngoi Bong
Bridge at Km207+936 have been installed drainage to ensure the flow and no erosion and
landside for the stream. However, On March 11th, 2011, in the construction process at Tan An
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
105 | P a g e
Bridge at Km 194+765, Tan Tien Bridge at Km 209+329, the Subcontractor let land and rock
fall into the stream and obstruct the flow. Consultant ordered the Subcontractor to dredge and
clear the flow at the above location before March 17th, 2011.
However, until March 22nd, at the location of Tan An Bridge of Km194 +765, the flow has not
been dredge and Consultant asked the Subcontractor to seriously implement this measure.
4.6.8 Package A8
January
The construction site of Suoi Trat bridge , the Contractor place the muzzle of rocks in the
stream-bed and then covered with soil and major aim to create a path to move machinery
across the stream without affecting the flow and water quality of the stream. The Consultant
also remind the Contractor picked up garbage at the muzzle of rocks to clear and maintain the
flow, avoid clogging when heavy rain.
Current water level of Bo Ngoi is very low so the construction under the riverbed does not
reduce the flow and effect to the water quality of rivers but the Consultant also remind the
Contractor must have a plan to shield minimize the impact of construction site to the water
quality of the river in case water levels are high or when it rains.
February
In the location of Suoi Trat , the Contractor has installed a temporary bridge for ease of moving
machinery and construction equipment to the other side, however, the rate flow and
maintained embankments and canals are still guaranteed in good condition.
In the location of Suoi Trat, the Contractor has covered a road near the river to facilitate the
construction, which has changed the flow of river. But the water level is low so the changed of
flow doesn cause erosion and landside of both riversides.
March
At the construction site of Suoi Nhu stream, the Contractor has built a temporary bridge near
the middle river to be convenient for moving the machinery and equipment to the other side.
However, the circulation flow and maintain embankment of canal are still guaranteed well.
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
106 | P a g e
At the construction site of Suoi Nhu Bridge, the Contractor has built a road near the middle
river to be convenient for the construction that changed the river's flow. However, the current
water level of river is lover so the changed flow has cause erosion and riverbank landside
4.7 EROSION RISKS AND STABILITY IN SLOPES
4.7.1 Package A1
January
At this time, the weather is in dry season and the route is on the plain area with the low
embankment so the risk of erosion is low. However, at the temporary stream crossings, the
erosion risks are visible so the PSC has requested the Contractor to pay attention and apply
the measures of erosion control and stabilize the bed, inlets and outlets of temporary culverts
to prevent erosion blocking the water flows at these areas.
At the Tan Loi bridge, TL320B bridge and TL402 bridge construction sites, the landslide risks
are visible because the slopes of foundations are upright and close existing road. The PSC
has requested and instructed the Contractor to apply the measures to stabilize the walls of
foundations to prevent landslide breaking existing structures. We will check the implementation
of Contractor in the next site inspections.
February
At the Xuan Phuong bridge construction site, during the site inspection in the third week, we
detected that the temporary stream crossing with unsuitable pipe culverts made high velocity
of water flow at outlet and cause erosion on left riverside toe. This problem can make landslide
on left riverside. The PSC has requested the Contractor to resolve this problem with the
instructions in letter GET1/POS/A1/788 dated February 15th 2011 – Temporary Road Plan.
However, in the site inspection in the fourth week, we found that the problem has not been
solved and it made landslide on left riverside. In the weekly meeting on February 24th 2011,
the PSC has repeated the request of solving this problem. The Contractor promised that they
will mobilize and install 4 more culverts at least in five days to resolve this matter. The PSC,
who considers this matter as a very serious impact, will recheck this section in the next site
inspection on March 01st 2011.
At the embankment sections, we didn’t detect the erosion risk because this time is in the dry
season and the embankment is short. However, the PSC also recommended the Contractor to
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
107 | P a g e
pay attention to the erosion risk and apply the measure to prevent erosion in the coming rainy
season.
At TL302B bridge construction site, the Contractor is building the detour road to prevent the
vibrations from the vehicles that can make landslide on the walls of foundations. This detour
road will be finished on February 28th 2011. At Tan Loi bridge construction site, the Contractor
has set the stakes in the ground close to the wall of foundation to prevent landslide.
March
At Xuan Phuong bridge construction site (Ca Lo river), by observation during site inspection on
March 01st 2011, we realized that the riverside was no longer eroded after the Contractor
installs two pipe culverts more.
At section Km 2+218 ~ Km 2+960, the erosion blocked the temporary pipe culverts here and at
the section Km 0+775, the temporary drainage also could be blocked by erosion. The PSC has
requested the Contractor to resolve these problems by replace with suitable pipe culverts and
stabilize outlets and inlets of temporary culverts to prevent erosion blocking flows. The PSC
will recheck these sections in next site inspection on March 29th 2011.
4.7.2 Package A2
January
At this time, the weather is in dry season and the route is on the plain area with the low
embankment so the risk of erosion is low. However, at the temporary stream crossings such as
Tan Dung bridge construction site, the erosion risks are visible so the PSC has requested the
Contractor to pay attention and apply the measures of erosion control and stabilize the bed,
inlets and outlets of temporary culverts to prevent erosion blocking the water flows at these
areas.
February
The outlet of temporary pipe culvert and banks in downstream of irrigation canal at Tan Dung
bridge construction site were stabilized so the erosion risk at this area is reduced. Besides, at
the embankment sections, the PSC didn’t find the erosion during the site inspection because
this time is in the dry season and for the most part of embankment is low.
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
108 | P a g e
At section Km 43+400 ~ Km 43+500, the embankment is high and close to the productive soil
and the erosion risk here is high. The PSC has requested the Contractor to apply the measure
to stabilize the slope to prevent erosion into productive soil during the site inspection and in
meeting between PSC, EPMU, Contractor and People’s Committee of Cao Phong commune.
The Contractor has promised that he will implement this requirement before the end of March,
2011.
March
At Song Dao bridge construction site, the Contractor had installed the temporary stream
crossing with unsuitable pipe culvert. The inlet and outlet of this pipe culvert were not stabilized
so the water flow is probably blocked by high erosion risk and sedimentation.
The PSC requested the Contractor to resolve this problem to ensure the water flow as well as
prevent the flood on upstream at this section, and during the site inspection on March 16th
2011, we perceived that the Contractor had dealt this matter by demobilizing the temporary
stream crossing with pipe culvert and restoring the water flow.
4.7.3 Package A3
January
In the construction progress, the soil environment will be affected by the earthworks that
results in erosion and landslide. Erosion and landslide occur in these positions might cause the
removal of vegetation (Ex: Km50-km51; Km73-km76 ...). Currently, there is no report or
findings related to these problems based on these points of view. However, the Consultant has
warned the Contractors to pay attention to regularly monitor and record on the issue.
February
In this period, there is no report or findings related to erosion and landslides. However, the
Consultant has warned the Contractors to pay attention to regularly monitor and record on the
issue.
March
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
109 | P a g e
There was no problem detected related erosion and landslides in this month. However, the
Consultant has warned the Contractors to pay attention to regularly monitor and record on the
issue.
4.7.4 Package A4
January
In the construction progress, the soil environment will be affected by the earthworks that
results in erosion and landslide. Currently, there is no report or findings related to these
problems based on these points of view. However, the Consultant has warned the Contractors
to pay attention to regularly monitor and record on the issue.
February
In the construction progress, the soil environment will be affected by the earthworks that
results in erosion and landslide. Currently, there is no report or findings related to these
problems based on these points of view. However, the Consultant has warned the Contractors
to pay attention to regularly monitor and record on the issue.
March
Currently, there is no report or findings related to these problems based on these points of
view. However, the Consultant has warned the Contractors to pay attention to regularly
monitor and record on the issue.
4.7.5 Package A5
February
To date, no problem of erosion and landslides has occurred in areas of package A5. In site
inspections, the Consultant has frequently remind the Contractor on erosion risks and stability
in slopes in order to ensure safety during construction process for workers as well as local
people and travelers.
March
To date, no problem of erosion and landslides has occurred in areas of package A5. However,
at some access roads such as Km 122+030, when there is heavy rain, soil erosion might
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
110 | P a g e
happen, it leading to erosion of the access road. Therefore, the Consultant has requested the
Contractor to remedy this in letter ref.GET3-KEANGNAM-11-A5-023 on 17th March 2011.
In site inspections, the Consultant has frequently remind the Contractor on erosion risks and
stability in slopes in order to ensure safety during construction process for workers as well as
local people and travelers.
4.7.6 Package A6
January
Package A6 is in the strong separated terrain, with relative slope, narrow folded river-bed in V-
shape and many falls. The alignment section of this area includes terrains as follows:
Medium and high mountains, folded complex block mountains, denudative terrain in Yen Bai
province, valley terrain in the Tectonics - the mountains with erosion agglomeration activities.
For this terrain, beside occurred erosion and agglomeration activities, there is surface runoff
process.
This month, package A6 has developed many construction items on the site. But so far, no
problems of erosion and landslides have occurred in the area of project package A6.
In weekly tests on the site, the Consultant frequently reminded the contractor on erosion risks
and stability in slopes.
February
At this stage, package A6 has developed many construction items on the site. But so far, no
problem of erosion and landslides has occurred in the area of project package A6.
Package A6 is in the strong separated terrain, with relative slope, narrow folded river-bed in V-
shape and many falls. So in weekly tests on the site, the Consultant frequently reminded the
contractor on erosion risks and stability in slopes in order to ensure safety during executing
construction works for workers as well as local people and travelers.
March
At this stage, no problem of erosion and landslides has occurred in the area of project package
A6. However, at station Km172+300, the constructing area is near a pond, when there is heavy
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
111 | P a g e
rain, landslide situation can occur leading to erosion of the pond edge, which affects the safety
of the project. The Consultant has reminded the Contractor on this issue in letter Ref.GET3-
DOOSAN-11-A6-034 14th March 2011.
Package A6 is in the strong separated terrain, with relative slope, narrow folded river-bed in V-
shape and many falls. So in weekly inspections on the site, the Consultant has frequently
reminded the Contractor on erosion risks and stability in slopes in order to ensure safety during
executing construction works for workers as well as local people and travelers.
4.7.7 Package A7
January
Now this time is dry season so the amount of water quantity is very little and is lightly rain and
doesn't cause erosion risks and stability in slope. In addition, although hilly terrain, but in the
process of excavation and embankment construction's taluy, the contractor carried out training
and flexed up grading to stabilize roof's slope and until this time has not happened the erosion
and runoff serious.
In addition, the Contractor also dug gutters to avoid water from assembling to soil erosion,
partial runoff.
February
There was no any erosion risk and stability in the construction process in February.
March
In many construction locations, the Contractor had dug up the positive slop and negative slop ,
but until this time has not happened problem about erosion and landslide. However,
Consultant and Client also remind the Contractor to quickly finish top of the drainage of slop to
ensure drainage and prevent erosion, landside when the rainy season is coming.
4.7.8 Package A8
January
Now this time is dry season so the amount of water quantity is very little and is lightly rain and
doesn't cause erosion risks and stability in slope. In addition, although hilly terrain, but in the
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
112 | P a g e
process of excavation and embankment construction's taluy, the contractor carried out training
and flexed up grading to stabilize roof's slope and until this time has not happened the erosion
and runoff serious.
In addition, the Contractor also dug gutters to avoid water from assembling to soil erosion,
partial runoff.
February
In February, the Consultant did not detect erosion risks and stability in slop in the construction
process.
March
In many construction locations, the Contractor had dug up the positive slop and negative slop ,
but until this time has not happened problem about erosion and landslide. However,
Consultant and Client also remind the Contractor to quickly finish top of the drainage of slop to
ensure drainage and prevent erosion, landside when the rainy season is coming.
4.8 HAZARDOUS SUBSTANCES MANAGEMENT
4.8.1 Package A1
January
With the site inspections during the month, we didn’t detect any problem of hazardous
substance management of Contractor. The Contractor has managed the fueling areas better
and there is no leak of oil detected on site. Besides, at the sites, which are under equipment
mobilization such as Bon bridge and Trung Kien bridge, the PSC has recommended the
Contractor to comply with the material and fuel management regulations.
February
By observation during the site inspections, we perceived that the hazardous substances such
as hydrocarbon (acetylene), gas are managed suitably (containers are tight, in good condition
and kept in steel cages with lock for authority).
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
113 | P a g e
The fueling areas is also managed tighter and we didn’t detect the leak of oil in these areas
such as Trung Kien bridge (Km 4+491), Dai Duong bridge (Km 7+392.65) construction sites,
subcontractor PPI’s section (Km 19+300), subcontractor Tan Minh’s section (Km 22+800).
However, during the site inspection in the third week, we detected that the Contractor had not
complied with equipment and vehicle maintenance instructions of Engineer and let oil leaks on
site. The PSC has requested the Contractor to resolve this problem and in the next site
inspection on February 22nd 2011 we perceived that the Contractor had collected the oil and
contaminate soil and disposed of them properly.
March
During the site inspections in month, there was only small leak of oil detected at Bon bridge
construction site. The PSC has requested the Contractor to apply the measure to prevent leak
of oil such as place drip pan under nuzzle, fuel tank; checking and repair leak point as well as
must be attended at all times during fueling.
At other section such as Bon bridge, Xuan Phuong bridge construction sites, the pipes of gas
and oxygen compressed box were tied with unsuitable ties. This problem causes high risk of
leak of gas and explosion. The PSC has requested the Contractor to tightly manage these
material and use suitable clamp to tie pipe of gas and oxygen compressed box.
The PSC will pay attention to these problems to anticipate the risk in hazardous substance
management of Contractor to minimize the risks.
4.8.2 Package A2
January
During the site inspections in month, we didn’t found the leaking of oil or other hazardous
materials. However, we perceived that the fuelling areas at the An Phat sub-contractor’s
section and Ben Gao bridge construction site don’t meet safety codes and be not applied the
environmental protection measures.
The PSC has requested the Contractor to resolve these problems to make sure the safety on
the site as well as ensure that the environmental impact will be mitigated well.
February
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
114 | P a g e
During the site inspection on February 18th 2011, we detected that at the Ben Gao bridge –
abutment 2 construction site there was a little of oil leaked on site because the Contractor did’t
use automatic shut-off nozzle but also didn’t place the drip pan under during fueling
equipment.
The PSC has requested the Contractor to use drip pan and control fueling activity tightly to
prevent the leak of oil onsite.
In the next site inspection on February 23rd 2011, we didn’t detect the leak of oil at this
construction site.
Besides, by observation during the site inspections, we perceived that the hazardous
substances such as hydrocarbon (acetylene), gas are managed suitably (containers are tight,
in good condition and kept in steel cages with lock for authority).
March
During the site inspection this month, there was no serious problem regarding to hazardous
substances management detected.
At the Ben Gao bridge, the fueling area was moved to the level grade area and there was no
oil leakage found.
At other places, the equipment and vehicle maintenance was carried out offsite and there was
no serious sign of oil/or and grease leakage also.
Besides, the PSC also recommended the Contractor to always control tightly the other
hazardous substances management such as hydrocarbon (acetylene), LPG (gas) are
managed suitably (containers are tight, in good condition and kept in steel cages with lock for
authority).
4.8.3 Package A3
January
At stations Km59, Km62, Km60+900, Km77+200, oil tank capacity is 1100m3, it is put on
ground and have any safety measure and prevention overflowing oil risk as approval
Environmental control plan. After many time remind and warning, the Consultant submitted the
Client (letter no GET2-EPMU2-A3-107 dated 1st December, 2010) to stop work in site until the
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
115 | P a g e
Contractor will show treatment appropriately (letter no GET2-POS-A3-295 dated 27th October,
2010 regarding “instruct to storage fuels in site”). However, the Contractor had some explain
(letter no POS321-2010/A3 dated 13th December, 2010) as bellow:
“Prevention measures against oil spills and leaks have been adopted for oil tanks on site, for
example: The tank is made of two steel layers with the bypass pressure valve in order to avoid
of overflow; the supply location has been sprayed with concrete to prevent oil leaks. The tanks
which do not meet the safety and environment standards have been moved out of construction
area (Km59) or are not allowed to use (Km70)”
At Km54+640, oil tank was put on concrete ground and fight fire equipment was installed in
site.
At Km 77+800, in inspection tour on january 3rd 2011, the Consultant has found one oxygen
vessel which use to weld or cut iron, steel in site, its valve is uncovered. The Contractor was
request to stop relate work and overcome this risk immediately before start using this oxygen
vessel.
February
The Contractor store oil by steel big tank or drum in construction site. With the big oil tanks the
Contractor have prevention measures against oil spills and leaks have been adopted for oil
tanks on site, for example: The tank is made of two steel layers with the bypass pressure valve
in order to avoid of overflow; the supply location has been sprayed with concrete to prevent oil
leaks. The tanks which do not meet the safety and environment standards have been moved
out of construction area (Km59) or are not allowed to use (Km70)”. Beside the big oil tanks
which capacity are 1100m3, many oil drums lying about disorderly in site. The Contractor is
reminded to manage and mark the boundaries of hazardous substances store area. They must
install some sand drums in this area to against oil spills, leaks or fire risk.
March
The Contractor store oil by steel big tank or drum in construction site. With the big oil tanks the
Contractor have prevention measures against oil spills and leaks have been adopted for oil
tanks on site, for example: The tank is made of two steel layers with the bypass pressure valve
in order to avoid of overflow; the supply location has been sprayed with concrete to prevent oil
leaks. The tanks which do not meet the safety and environment standards have been moved
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
116 | P a g e
out of construction area (Km59) or are not allowed to use (Km70). Beside the big oil tanks
which capacity are 1100m3, many oil drums lying about disorderly in site. The Contractor is
reminded to manage and mark the boundaries of hazardous substances store area. They must
install some sand drums in this area to against oil spills, leaks or fire risk.
4.8.4 Package A4
January
Up to now, the Contractor regroup oil tanks in site to attend to construction work (Km 92+200,
Km104+200...). These oil tanks were put on ground without any safety or prevention fire or
overflow oil measure. It is very dangerous if fire risk would happen or oil tank is holed or leak
out oil which will pollute seriously local water and soil environment. This matter, the Consultant
had instruction letter to ensure safety for storage fuel in site.
February
In some inspection tours (from 14th- 26th February) the Consultant has detected all oil drums
was lying about disorderly in site without safety method (km92+200, Km105+300…). Namely,
there is not having safety fence around fuel tanks and reinforce foundation by concrete to
avoid oil or fuel overflow risk, fire fighting equipment. The Consultant requested the Contractor
to resolve this matter and recheck carefully.
March
Oil drums were ungrouped in site because it was rain almost day in March. Therefore the
Contractor can not implement in March. The Consultant has not detected any problem about
hazardous substance in site along package A4.
4.8.5 Package A5
February
Up to now, there is no serious problem due to hazardous substances within project area. Most
fuel stations are equipped with fire prevention and fighting equipments. So far, there is no
problem of serious effects by hazardous substances in the project area.In weekly site
inspections, the Consultant has advised the Contractor to manage effectively the hazardous
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
117 | P a g e
substances in order not to affect the environment and to ensure safety for workers, local
people and travelers.
March
Up to now, there is no serious problem due to hazardous substances within project area. Most
fuel stations are equipped with safety fences, fire prevention and fighting equipments and
signs.
In order to emphasize hazardous substances management, the Consultant has requested the
Contractor to hold meetings on safety to raise the awareness of hazardous substances
management of the workers and the project staff.
In weekly site inspections, the Consultant has advised the Contractor to manage effectively the
hazardous substances in order not to affect the environment and to ensure safety for workers,
local people and travelers.
4.8.6 Package A6
January
At present, package A6 has a laboratory at the Doosan office (Km 165) and the fuel stations of
the subcontractors. Most fuel stations and laboratories are equipped with fire prevention and
fighting equipments. So far, there is no problem of serious effects by hazardous substances in
the project area.
However, in some areas such Km185+200 (Ngoi Don bridge), because of low awareness of
the workers, empty oil tanks were put out on the ground without collecting. The Consultant has
reminded the Contractor on this issue in weekly site inspections.
February
In this period, most fuel stations and laboratories are equipped with fire prevention and fighting
equipments. So far, there is no problem of serious effects by hazardous substances in the
project area.
In weekly site inspections, the Consultant has frequently reminded the Contractor to manage
hazardous substances effectively to ensure safety for workers as well as local people and
travelers.
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
118 | P a g e
March
In this period, most fuel stations and laboratories are equipped with fire prevention and fighting
equipments. So far, there is no problem of serious effects by hazardous substances in the
project area.
In weekly site inspections, the Consultant has frequently reminded the Contractor to manage
hazardous substances effectively, consolidate the safety mechanism and the equipments for
preventing material leaking in order not to affect the environment and ensure safety for
workers as well as local people and travelers.
4.8.7 Package A7
January
In January 2011 consultant confirmed that management activities of hazardous substances
management complied with regulations. Therefore, it did not cause adverse impacts to the
environment. Oil and waste oil tanks are now far away from water sources, this position will
have risks of flooding banned sign of fire and fire extinguisher.
Because of the borrow pile process is conducted by man and did not use bentonite therefore it
did care about management issues of bentonite during the drilling process of borrow pile.
However, consultant also reminded the contractor to pay attention to the construction process
later if using bentonite and especially in management issues of oil and waste oil.
February
In February, the Consultant did not detect violations of a harmful waste management in the
construction process.
March
In March, Consultant did not detect violations of a harmful waste management in the
construction process.
4.8.8 Package A8
January
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
119 | P a g e
Unsuitable material disposals such as waste oil from worker's camps of Tuan Tu Co.,ltd at
Km237+060 and Viet Dung Co.,ltd Km232+900 is not be collected in tanks and spilled over to
the ground. The Consultant issued a warning letter and required the Contractor to overcome
before January 5th, 2011.
In the construction Suoi Trat and IC18 bridge, bentonite is not be collected for re-use or
transported to the landfill as prescribed bentonite of place as recovery bentonite has high
concentrations of alkali ( pH = 8-11), if not well managed will greatly affect productivity of crop
yields and livestock when using contaminated water sources by recovery bentonite.
After the Consultant reminded and given an warning messages to overcome it, the Contractor
has installed the barrel bentonite for re-use and avoid environmental pollution at construction
sites of bridges like Suoi Trat and Ngoi Bo.
February
On February 24th, 2011, Vinaconex 34 Company of a number of oil barrels and cans at Km 238
– Km 241 were not stored in the approved place that indiscriminately threw near the worker's
camps. Consultant asked the subcontractor to move them to the required storage location.
Also, the Consultant did not detect any violation of the contractor for hazardous waste
management during construction.
March
In March, Consultant did not detect violations of a harmful waste management in the
construction process.
4.9 UNSUITABLE MATERIAL DISPOSALS AND BORROW PITS
4.9.1 Package A1
January
The Contractor has submitted the disposal place for unsuitable material of underpass QL2B
construction site. With the checking and assessment onsite, the PSC didn’t have any
opposition because the disposal place is a borrowed pit and after excavating, the top soil and
excavated soil in underpass QL2 construction site will be disposed there for planting purpose.
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
120 | P a g e
However, the PSC has also requested the Contractor to have enough permission certificated
of local authority before implementing the disposal activity.
February
During the month, there was no disposal place submitted by Contractor. The unsuitable
material for embankment such as top/or organic soil is stored along the sites and in the sites
limits for planting purpose in the future and the quantity of this material is small.
The borrow pits, which were approved by Geological and Material Engineer, are almost
material planting hills with for the most past of eucalyptus and acacia mangium/and or acacia
auriculiformis. In addition, there are some borrow pits were used in the previous project and
there is no tree or animal growing on.
March
At Trung Kien bridge construction site, we detected that the mud after recycling bentonite
slurry had discharged offsite and spilled into adjacent paddy filed during site inspection on
March 07th 2011, due to the negligence of workers. The PSC has requested the Contractor to
manage tightly the unsuitable material disposal activity. The discharged mud must be removed
to the approved disposal place. Besides, the Contractor has to contact with land owner to
negotiate for compensation.
In this month, the Contractor had submitted the borrow pit 21 at Dong Mo hill, Nam Son
commune, Soc Son district, Hanoi. This area is material planting hills with the most of
eucalyptus. The PSC has approved this borrow pit.
4.9.2 Package A2
January
The Contractor had submitted the disposal places for unsuitable material of package A2 and
the PSC has checked and don’t have any opposition. However, the Contractor has to have
enough the permission certificates from local authorities before doing disposal activities and
the PSC also recommended the Contractor about this.
February
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
121 | P a g e
In this month, the Contractor has not submitted more any disposal area. The unsuitable
material for embankment such as top/or organic soil is stored along the sites and in the sites
limits for planting purpose in the future and the quantity of this material is small.
The borrow pits, which were approved by Geological and Material Engineer, are almost
material planting hills with for the most past of eucalyptus and acacia mangium/and or acacia
auriculiformis. In addition, there are some borrow pits were used in the previous project and
they are treeless hills.
March
There was no disposal place or borrow pit submitted this month. During site inspections, we
perceived that the quantity of unsuitable materials (spoil and mud) is very small (approximate
0) so there was no disposal activity of Contractor this month.
4.9.3 Package A3
January
The contractor already submitted discharging areas record for section 1, section 2, section3,
section 4, section 5 and section 6. Pursuant to item 2; article 10, section 1, chapter II of Decree
59/2007/ND-CP, the planning of solid waste management at local level issued and approved
by the Chairman of provincial People’s Committee. Currently, the Contractor is requested to
determine co-ordinates (X, Y) of all disposal areas in package A3 to ensure the management
of disposal area closely (letter no GET2-POS-A3-366 dated 15th December, 2010). The
Consultant approved disposal area at section 1, section 5 and section 6 to implement after the
Contractor promised would addendum all information about discharging area’s co-ordinates.
February
The Contractor has submitted disposal areas record for section 1, section 2, section3, section
4, section 5 and section 6. The Consultant approved disposal area at section 1, section 3,
section 5 and section 6 to implement after the Contractor promised would addendum all
information about discharging area’s co-ordinates. The disposal area document of section 2
and 4 are lacked approved by the Chairman of provincial People’s Committee pursuant to item
2; article 10, section 1, chapter II of Decree 59/2007/ND-CP. Therefore, to ensure plan for
construction work and environmental protection, the Contractor is requested to complete all
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
122 | P a g e
legal document of disposal areas for 2 above section to activate these disposal areas. Ref.
GET2-POS-A3-451 dated February 25th, 2011.
March
The Contractor has submitted disposal areas record for section 1, section 2, section3, section
4, section 5 and section 6. The Consultant approved disposal area at section 1, section 3,
section4, section 5 and section 6 to implement after the Contractor promised would addendum
all information about discharging area’s co-ordinates. The document of disposal area of
section 2 is lacked approved by the Chairman of provincial People’s Committee pursuant to
item 2; article 10, section 1, chapter II of Decree 59/2007/ND-CP. Therefore, to ensure plan for
construction work and environmental protection, the Contractor is requested to complete all
legal document of disposal areas for above section to activate these disposal areas. Ref.
GET2-POS-A3-451 dated February 25th, 2011 and ref. GET2-POS-A3-482 dated March 14th,
2011.
4.9.4 Package A4
January
The Contractor submitted disposal area document of Cam Khe district. But this legal document
is lacked of landlord's cadastral register was notarized and co-ordinate(X,Y) of disposal area.
February
The Contractor submitted disposal areas record for Cam Khe (section 1, 2) district and Ha Hoa
district (section 3, 4, 5, 6). Pursuant to item 2; article 10, section 1, chapter II of Decree
59/2007/ND-CP, the Consultant approved all disposal areas for package A4 to implement after
the Contractor promised would addendum all information about discharging area’s co-
ordinates and drive in a stake and stretch a wire at the angles to fix the boundaries of disposal
areas. The Contractor is moving unsuitable material out of site to these disposal areas.
March
The Contractor submitted disposal areas record for Cam Khe (section 1, 2) district and Ha Hoa
district (section 3, 4, 5, 6). Pursuant to item 2; article 10, section 1, chapter II of Decree
59/2007/ND-CP, the Consultant approved all disposal areas for package A4 to implement. The
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
123 | P a g e
Contractor was addendum all information about discharging area’s co-ordinates and they will
drive stake and stretch a wire at the angles to fix the boundaries of disposal areas.
4.9.5 Package A5
February
At present, 8 unsuitable material disposals of package A5 has been approved by the
Consultant. Some other disposal areas have submitted but have not been approved by the
Consultant:
No Location Approval
Capacity (m3) Note Yes No
1 Km113+050-Km113+150 (No.5-A) X 5641.111
2 Km113+050-Km113+150 (No.5-B) X 6808.732
3 Km113+050-Km113+150 (No.5-C) X 2101.210
4 Km113+050-Km113+150 (No.5-D) X 3860.360
5 Km113+050-Km113+150 (No.4) X 10946.510
6 Km116+500 X 1045.000
7 Km118+800 X 24990.000
8 Km119+680-Km119+700 X 16441.000
9 Km116+223 X 5000.000
In this period, the disposal areas haven’t affected environment and safety. The Consultant has
requested the Contractor to finish the documents of unsuitable disposal areas promptly with
authorities according to the rules of Social Republic of Vietnam and then submit to the
Consultant so that they can be considered and accepted.
In coming months, the Consultant will continue inspecting unsuitable disposal areas to ensure
the environment of the project.
March
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
124 | P a g e
At present, 8 unsuitable material disposals of package A5 has been approved by the
Consultant. Some other disposal areas have submitted but have not been approved by the
Consultant.
In this period, the disposal areas haven’t affected environment and safety. The Consultant has
requested the Contractor to finish the documents of unsuitable disposal areas promptly with
authorities according to the rules of Social Republic of Vietnam and then submit to the
Consultant so that they can be considered and accepted.
In coming months, the Consultant will continue to inspect unsuitable disposal areas to ensure
the environment of the project.
4.9.6 Package A6
January
At present, 16 unsuitable material disposals of package A6 has been approved by the
Consultant. Some other disposal areas have submitted but have not been approved by the
Consultant:
No Location Approval
Capacity Note Yes No
1 Km 166+600 X 3,258 m3 Check again the capacity (m3)
2 Km 167+300 X 5,380 m3 Check again the capacity (m3)
3 168+700 X 24,318 m3 Check again the capacity (m3)
4 168+000 X 11,882 m3 Check again the capacity (m3)
5 168+050 X 2,819 m3 Check again the capacity (m3)
6 Km 175+240 X 6938.96 m2 Submit the capacity (m3)
7 Km 175+460 X 2383.487 m2 Submit the capacity (m3)
8+9 Km 175+720(2); X
346.554 m2
541.624 m2 Submit the capacity (m3)
10 Km 176+200 X 2514.76 m2 Submit the capacity (m3)
11 Km 167+560 X 784.524 m2 Submit the capacity (m3)
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
125 | P a g e
12 Km 177+340 X 1096.366 m2 Submit the capacity (m3)
13 Km 177+440 X 964.502 m2 Submit the capacity (m3)
14 Km184+900 X 4646 m2 Submit the capacity (m3)
15 Km188+200 X 162582 m3
16 Km190+110 X 17032 m3
17 Km186+140 X 7231 m2 Submit the capacity (m3)
18-22
Km153+392-Km153+870
(5 pits) X
(1) 1500 m2
(2) 3000 m2
(3) 3000 m2
(4) 1200 m2
(5) 3000 m2
Submit the capacity (m3)
23-28
156+073-159+157
(6 pits) X
1) 2077 m2
(2) 2171 m2
(3) 6466 m2
(4) 7526 m2
(5) 3422 m2
(7) 6877 m2
Submit the capacity (m3)
Package A6 goes through hilly areas, so it has a large amount of surplus land. Presently, in
some areas such as Km162+900 (Ngoi Giam bridge); Km159+200 (Ngoi Cong bridge);
Km175+020; Km186+140; Km187+500; Km188+800 (Suoi Nau bridge); Km171+900;
Km175+020, unsuitable soil was disposed at the positions which had not accepted by the
Consultant. The Consultant has requested the Contractor to deal with this situation promptly,
to finish the documents of unsuitable disposal areas as soon as possible and then submit to
the Consultant so that they can be considered and accepted.
In coming months, the Consultant will continue inspecting unsuitable disposal areas to ensure
the environment of the project.
February
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
126 | P a g e
At present, 17 unsuitable material disposal areas of package A6 have been approved by the
Consultant. Some other disposal areas have submitted but have not been approved by the
Consultant.
Package A6 goes through hilly areas, so it has a large amount of surplus land. Presently, in
some areas such as Km161+100; Km165+050, unsuitable soil was disposed at the positions
which had not accepted by the Consultant. The Consultant has requested the Contractor to
deal with this situation promptly, to finish the documents of unsuitable disposal areas as soon
as possible and then submit to the Consultant so that they can be considered and accepted.
In coming months, the Consultant will continue to inspect unsuitable disposal areas to ensure
the environment of the project.
March
At present, 16 unsuitable material disposal areas of package A6 have been approved by the
Consultant. Some other disposal areas have submitted but have not been approved by the
Consultant.
Package A6 goes through hilly areas, so it has a large amount of surplus land. The Consultant
has requested the Contractor to deal with this situation promptly, to finish the documents of
unsuitable disposal areas as soon as possible and then submit to the Consultant so that they
can be considered and accepted.
In coming months, the Consultant will continue to inspect unsuitable disposal areas to ensure
the environment of the project.
4.9.7 Package A7
January
Currently the legal procedure for the landfills of unsuitable material disposals is not completed.
Consultant issued a remind letter and required the Contractor to carry out this work before
January 28, 2011.
Some landfills of unsuitable material disposals which were processed according to the request
of the Environmental Police of Lao Cai province and the consultant & investor. However, the
planting of grasses to avoid erosion has not carried out. After repeatedly been reminded by
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
127 | P a g e
consultant, the contractor planted grasses on some location of landfill at Km195+800 on Jan
7th, 2011. Consultant required the contractor continue to grow grasses at the remained
landfill.
On January 14th, 2011 at the landfills of unsuitable material disposals at Km194 +200; Km195
+800; Km199+500 and Km207 +000 have been grown grasses to avoid erosion and return the
environment landscape under the order of Police Department's environmental crime prevention
in Lao Cai province and Supervision Consultant's direct.
February
The landfills of unsuitable material disposals at KmKm190+400; Km191+600; Km195+800;
Km194+200; Km199+500 been planting and greening grass to keep soil from being washed
down the Red River. However, due to bad weather conditions and therefore some kinds of
trees have been died at waste disposal Km190+400; Km195+800; Km199+500. Consultant
has requested the contractor to take measures to replant the entire greening position on these
landfills in March 2011
In addition, Consultant also reminded the Contractor to complete legal procedures related to
the landfills of unsuitable material disposals. But so far the Contractor has not been completed.
Consultant has requested the Contractor to complete this before Feb 31st, 2011
March
The landfill of unsuitable material disposals at Km190 +420 is planted corn to cover green and
limit soil erosion into the Red River, however Consultant required the Subcontractor continue
to grow grasses, trees for the location of plain side and the remained vacant position. Time for
completion is before March 31st, 2011.
In addition, Consultant also reminded the Contractor to complete legal procedures related to
the landfills of unsuitable material disposals. But so far the Contractor has not been completed.
Consultant has requested the contractor to complete this before March 31st, 2011.
4.9.8 Package A8
January
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
128 | P a g e
Currently the Contractor has completed the legal procedures for the landfills of unsuitable
material disposals at the stage 1 with 19 locations of landfills is approved by the People's
Committee of Bao Thang district. However, now some newly landfills have not approved by
the People's Committee of Bao Thang district. The Consultant has issued letter on December
6th, 2010 on this matter and as well as suggested the Contractor should complete the above
legal procedures for submission to the Consultant and Client in the earliest time.
February
Currently the Contractor has completed the legal procedures for the landfills of unsuitable
material a disposal at the stage 1 with 19 locations of landfills is approved by the People's
Committee of Bao Thang district. However, now some newly landfills have not approved by the
People's Committee of Bao Thang district. The consultant has issued letter on Dec 6, 2010 on
this matter and as well as suggested the Contractor should complete the above legal
procedures for submission to the Consultant and Client in the earliest time.
March
Currently the Contractor has completed legal procedure for the landfill of unsuitable material
disposals at the stage 1 with 19 locations of landfills that have been approved by Bao Thang
district People's Committee. But now some landfill of unsuitable material disposal such as
Km218+500; Km218+700; Km219+500; Km222+200; Km222+800; Km224+020; Km227+900;
Km231+000 have not finished legal procedure to submit to the Consultant for approval.
Consultant has reminded many times and composed the warming letter on December 6th,
2010 to request the Contractor to complete them before April 23rd , 2011.
4.10 WORKER’S CAMPS CONDITIONS
4.10.1 Package A1
January
At the NH2B bridge construction site, the domestic solid waste still is disposed surrounding
worker’s camp. The PSC has recommended and requested the Contractor clean the site,
camp and collect wastes and dispose of them properly many times but till now there is nothing
changed. The PSC once again requested the Contractor to resolve this problem and in the site
inspection on January 25th, 2011 we perceived that the Contractor was cleaning worker’s
camps. However, the unsuitable backhouse is still used so the fresh fecal matter is being let in
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
129 | P a g e
directly ambient environment and makes pollution. The PSC has requested the Contractor to
remove the unsuitable backhouse and collect fresh fecal matter and dispose of it properly. We
will recheck this matter in the next site inspection.
At the I.C3 construction site, the backhouse was installed but unsuitable (the same case of
NH2B construction site) and it lets fresh fecal matter in directly environment and makes
pollution. Besides, at the TL302CII bridge construction site, the Contractor has not installed
backhouse with septic tank for worker. The PSC has applied the stronger measures to request
the Contractor to comply with the requirements as stated in the contract with VEC and the
Contractor promised that they will install the suitable backhouses for the workers in February,
2011. We will check the implementation of Contractor in the next site inspections.
February
During the site inspection dated February 11th 2011, we perceived that the domestic solid
waste surrounding worker’s camp at NH2B bridge construction site was collected. Besides, the
unsuitable backhouse has been removed and the septic tank also has been cleaned in the
third week (on February 17th 2011) after the PSC had applied the measure of suspending the
procedure of payment progress to this section.
At the Interchange 3 construction site, we found that the unsuitable back house has not been
removed and there was no septic tank installed during the site inspection on February 10th
2011. The PSC has requested the Contractor to resolve these problems and applied the
measure of suspending the procedure of payment progress to this section until the Contractor
corrects the matters. On February 21st 2011, the Contractor submitted the report of Engineer’s
request implementation. Having review and checked the site on February 22nd 2011, we
perceived that the Contractor removed unsuitable backhouse and the septic tank is being built.
The workers who are working in TL302CII bridge construction site have been renting the
house of local people with enough sanitary facilities.
March
During the site inspection on March 01st 2011, we detected that the Contractor had not
installed the backhouse with septic tank for worker at worker’s camp in TL402 bridge
construction site. The PSC has requested the Contractor to urgently install enough sanitary
facilities to make sure the living condition for workers. On March 15th 2011, we perceived that
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
130 | P a g e
the Contractor has rented the house of local people near the site with enough sanitary facilities
for workers.
At TL302CII bridge construction site, the Contractor had removed the worker’s camp and has
rented the house of local people with enough sanitary facilities for workers.
At the Cam1 bridge, Cam2 bridge and Army1 bridge construction sites, the Contractor has
been building camps for workers and we also recommended the Contractor to provide enough
sanitary facilities to ensure living condition for workers. The PSC will recheck these sections in
the next site inspection on March 29th 2011.
4.10.2 Package A2
January
At the worker’s camp of sub-contractor An Phat 1 (Km 35+300), we found that the Contractor
didn’t provide the sanitary facilities such as garbage bin so the domestic solid waste was
disposed surrounding the camp. This matter made the camp dirty and probably affects the
health of workers. The PSC has requested the Contractor to provide the sanitary facilities for
workers as well as clean the camp to make sure their health and living condition. In the last
site inspection, we perceived that the Contractor has implemented the requirements of
Engineer.
At the other sections such as Lo river bridge, Tan Minh section, Tasco section etc, the worker’s
camps are being kept in tidy, cleanliness and sanitary condition.
February
The subcontractor An Phat 1 (section 3: Km 35+300 ~ Km 36+910) has already rented the
house of local people for workers with sanitary facilities. Besides, during the site inspections in
the third week and fourth week, we perceived that at the sections of Tan Minh, Tasco
subcontractors and at the Lo river bridge construction sites the worker’s camps were kept in
tidy, cleanliness and sanitary condition.
At other sections such as section 2 of subcontractor ICON4 (Km 32+700 ~ Km 35+300),
section 4 and 5 of subcontractor Phuoc An (Km 36+910 ~ Km 40+960), the subcontractors has
also rented the house with enough sanitary facilities for workers.
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
131 | P a g e
March
By observation during this month, we perceived that the Contractor still maintain the worker’s
camps in cleanliness and sanitary condition. The worker’s camp of subcontractor 465 (Lo river
bridge) is being built and the PSC has recommended the Contractor to provide enough
sanitary facilities for workers to ensure the living condition of them.
4.10.3 Package A3
January
Tents were still maintained hygienically, all garbages were collected, Toilets were installed …
February
The Consultant has detected much rubbish near worker’s camp at Km74+300 in the second
week (14th-19th February). The main reason is the Contractor does not pay much attention to
preserve environmental sanitation. And they are uncontrollable their sub-contractor. In
addition, worker consciousness is poor in environmental protection field. Therefore, the
Contractor is requested to propagandize for their worker to improve their consciousness.
This situation is improved in the second week (21st – 26th February). The Contractor collected
all rubbish near worker’s camps.
All worker’s camps in package were installed hygiene toilet, ambulance box, fire fighting
equipment but no waste bin (Km74+300). The Consultant request the Contractor must install
waste bin in every camps pursuant to approval Environmental Control Plan.
March
All worker’s camps in package were installed hygiene toilet, ambulance box, fire fighting
equipment and waste bin. After the Consultant warned in the last month, the Contractor
reminded their worker and cleaned all camp. Therefore, in inspection tours the Consultant has
not detected rubbish near worker’s camp.
4.10.4 Package A4
January
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
132 | P a g e
At present, the Constructor is clearing site and removing topsoil. After inspection tours in
January, the Consultant has not found many rubbish in site. But the Contractor was warned
clean site often following approval ECP.
Beside, unsuitable material which is arised from site clearing and topsoil removing activities,
was piled up many in site. The Contractor plan to transport all unsuitable material out of site
when they complete all legal document of disposal zone of Ha Hoa and Cam Khe districts.
February
All worker’s camps in package A4 are not installed hygiene toilet, waste bin and ambulance
box, fire fighting equipment. To ensure safety and conditions of worker’s health, the Consultant
request the Contractor must install all above equipment in every camps pursuant to approval
Environmental Control Plan.
March
All worker’s camps in package A4 are not installed hygiene toilet, waste bin and ambulance
box, fire fighting equipment. To ensure safety and conditions of worker’s health, the Consultant
request the Contractor must install all above equipment in every camps pursuant to approval
Environmental Control Plan.
4.10.5 Package A5
February
In weekly environment and safety inspections of the Consultant, worker’s camps were well
maintained, most of worker’s camps have equipment to prevent fire, garbage container’s (
trash) and septic toilets and cleaned daily by workers.
The Consultant will continue to pay attention to worker’s camp conditions in coming months in
order to detect timely and request the Contractor to have measures to ensure the living
conditions for the worker in camps.
March
In weekly environment and safety inspections of the Consultant, worker’s camps were well
maintained, most of worker’s camps have fire prevention and fighting equipments, garbage
container’s ( trash) and septic toilets and cleaned daily by workers.
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
133 | P a g e
However, at worker’s camps of the Subcontractor Locogi 15, there was no fire prevention
equipment and first aid box, the Consultant has requested the Contractor to supply these
equipments to ensure safety of the project.
The Consultant will continue to pay attention to worker’s camp conditions in coming months in
oder to detect timely and request the Contractor to have measures to ensure the living
conditions for the worker in camps.
4.10.6 Package A6
January
Up to now, package A6 has about 16 subcontractors with about 23 worker’s camps.
No. Name of Subcontractor Location Length
(Km)
Workers’
camps
1 Quang Trung Trading &
Construction JSC
Km150+900-Km153+318 2.42 2
2 Truong Loc Trading &
Construction JSC
Km153+392-Km155+870 2.48 1
3 LICOGI 13 Km156+073-Km159+157 3.08 1
4 An Sinh JSC Km159+259-Km163+192 3.80 1
5 JS Vina Km163+192-Km169+387 6.05 1
6 CAVICO VIETNAM Km169+437-Km171+000 1.56 1
7 CITECHCOM JSC Km171+000-Km172+000 1.00 1
8 AVICO VIETNAM Km172+000-Km173+405 1.41 2
9 An Sinh JSC Km173+463-Km176+713 3.15 1
10 WEICOVINA Km176+713-Km182+114 5.40 4
11 Mien Trung Tranding &
Construction JSC
Km182+214-Km186+200 3.99 1
12 Nghe An Trade Building
JSC
Km186+730-Km190+420 3.70 2
13 VIETBUIL Bridges on the site 2
14 CAVICO II VIETNAM The tunnel (Km186+200 –
Km186+730)
1
15 VINASAN Batching plant (Km163) 1
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
134 | P a g e
16 Stone White Batching plant (Km180) 1
In this stage, Package A6 has carried out construction activities on the entire route, so a
relatively large of labour force has been mobilized. Therefore, some contractors have hired
local people’s houses to become worker’s camps or pitch camps, most of worker’s camps
have equipment to prevent fire, garbage container’s ( trash) and septic toilets. Most camps are
cleaned daily by workers. They collect garbage and treat by manual methods such as burning
or burying. Up to now, worker’s camp conditions are well maintained. The Consultant will
continue pay attention to worker’s camp conditions in coming months in order to detect timely
and request the Contractor to have measures to ensure the living condition for the worker in
camps.
February
Up to now, package A6 has about 16 subcontractors with about 23 worker’s camps.
No. Name of Subcontractor Location Length (Km)
Workers’
camps
1 Quang Trung Trading & Construction JSC
Km150+900-Km153+318 2.42 2
2 Truong Loc Trading & Construction JSC
Km153+392-Km155+870 2.48 1
3 LICOGI 13 Km156+073-Km159+157 3.08 1
4 An Sinh JSC Km159+259-Km163+192 3.80 1
5 JS Vina Km163+192-Km169+387 6.05 1
6 CAVICO VIETNAM Km169+437-Km171+000 1.56 1
7 CITECHCOM JSC Km171+000-Km172+000 1.00 1
8 AVICO VIETNAM Km172+000-Km173+405 1.41 2
9 An Sinh JSC Km173+463-Km176+713 3.15 1
10 WEICOVINA Km176+713-Km182+114 5.40 4
11 Mien Trung Tranding & Construction JSC
Km182+214-Km186+200 3.99 1
12 Nghe An Trade Building JSC
Km186+730-Km190+420 3.70 2
13 VIETBUIL Bridges on the site 2
14 CAVICO II VIETNAM The tunnel (Km186+200 – Km186+730)
1
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
135 | P a g e
15 VINASAN Batching plant (Km163) 1
16 Stone White Batching plant (Km180) 1
In this stage, package A6 has carried out construction activities on the entire route, so a
relatively large of labour force has been mobilized. Therefore, some contractors have hired
local people’s houses to become worker’s camps or pitch camps, most of worker’s camps
have equipment to prevent fire, garbage container’s ( trash) and septic toilets. Most camps are
cleaned daily by workers. They collect garbage and treat by manual methods such as burning
or burying. Up to now, worker’s camp conditions are well maintained. The Consultant will
continue to pay attention to worker’s camp conditions in coming months in order to detect
timely and request the Contractor to have measures to ensure the living conditions for the
worker in camps.
March
Up to now, worker’s camps were well maintained, most of worker’s camps have fire
prevention and fighting equipments, garbage container’s (trash) and septic toilets and cleaned
daily by workers, they collect garbage and treat by manual methods such as burning or
burying.
However, because the Contractor hasn’t paid enough attention to worker’s camp conditions, at
some stations like Km 190+100, the living conditions of the workers in camps were not
ensured, there was no septic toilets and wastewater treatment system.
The Consultant has requested the Contractor to promptly improve and ensure the living
conditions of the workers at this station in letter No. GET3-DOOSAN-11-A6-033 on 12th March
2011.
The Consultant will continue to pay attention to worker’s camp conditions in coming months in
order to detect timely and request the Contractor to have measures to ensure the living
conditions for the worker in camps.
4.10.7 Package A7
January
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
136 | P a g e
Worker's camps at the casting culverts of Km194 +670, waste cement packaging was not
collected in approved places and discharge indiscriminately at construction site. Consultant
has requested the Contractor to immediately collected and taken to a place where treatment
prescribed.
Also at worker's camps of the casting culverts Km194+670 Consultants found that the
Contractor has collected waste cement packaging and burn next to the worker's camps.
Consultant asked to stop and remind the Contractor warned about the above acts as well as
remind the Contractor of safety rules and sanitation at worker's camps.
February
When checking worker's camps at Khe Sang, Khe Dai and Khe U bridges at February 25th , all
worker's camps have septic tanks workers as prescribed, rubbish are collected and
transported to the place of treatment prescribed by the local's requirement.
March
At the present, the worker's camp of Chau Que Thuong Bridge does not have toilet for workers
and wastebasket existing. The Contractor gave the reason why that is the volume of work is
not much and workers move from the worker's camps of Khe Sang bridge to work so they don't
live and sleep directly but only the security guard stays here. Consultant asked the Contractor
to build toilet and install garbage bin before taking workers to the worker's camps. The
construction of toilet and installation of garbage bin must be complete before March 17th, 2011.
However, to the date of March 22sd, the Subcontractor still has not implement to build toilets
for workers and install garbage bins at the workers' camps of Chau Que Thuong Bridge.
Consultant had warned the Contractor by the letter Ref: GET4 GRBCC-334 dated on March
23rd, 2011.
At the cast site of culvert at Km194 + 670, some cement bags and waste are discharge
indiscriminately into the construction site near the worker's camps. Consultant has required the
Subcontractor to immediately collect and transport them to the place of prescribed treatment.
4.10.8 Package A8
January
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
137 | P a g e
At worker's camps of Viet Dung Co.,Ltd at Km232+900, garbage is not collected and taken to
where the prescribed treatment place. The Consultant warmed and reminded the Contractor to
install collection garbage bins and transport to the place of prescribed treatment before
January 5th , 2011.
Date January 5th, 2011 the Contractor has collected garbage and transported to the prescribed
treatment place according to the guidance of Consultant.
February
February 24th, 2011 there are a lot of the barrels and cans of oil of Vinaconex 34 Km238-
Km241 indiscriminately threw near worker's camps workers. Consultant asked the
Subcontractors to remove them to the stored place as prescribed.
Also, in February, worker’s camps of the construction units are guaranteed well such as
worker's camps of Suoi Trat, Ngoi Bo, IC 18 bridges. These worker's camps have septic tanks;
waste was collected and transported according to local regulations.
March
The workder's camp of Lang Tra Bridge, the Subcontractor is currently constructing and
preparing to start constructing Lang Tra Bridge. Current worker's camps of Lang Tra Bridge
haven't installed toilets for workers and no garbage bins. The Consultant required the
Subcontractor to build toilet and install tanks to collect garbage for the workers before taking
the workers to the construction site.
4.11 WASTE AND CLEANLINESS IN SITE
4.11.1 Package A1
January
During the site inspections, we perceived that the Contractor managed the site better. The
construction solid waste and surplus materials were collected and disposed properly. The PSC
has recommended the Contractor to maintain the tighten management on sites to keep the
sites in tidy, cleanliness and sanitary condition as well as make sure the safety to workers.
February
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
138 | P a g e
We perceived that the construction sites are kept in tidy and cleanliness condition during the
site inspections. Besides, we also usually recommend the Contractor to tightly manage and
control the construction sites such as implementing the safety housekeeping work often to
keep the site in tidy and sanitary condition and ensure the safety as well as healthy
environment for workers.
March
During the site inspections in month, we perceived that the sites were kept in sanitary
condition. The PSC has also recommended the Contractor to manage site tightly to maintain
tidy and cleanliness condition and safety as well as healthy environmental for workers.
4.11.2 Package A2
January
With site inspection during the month, we perceived that the Tan Dung bridge construction site
was dirty with debris and leftover materials. The PSC has requested the Contractor to
implement the safety housekeeping work often in this site to keep the site in tidy, cleanliness
and sanitary condition. In the last site inspection in month, we perceived that the Contractor
has cleaned the site.
At the other sections, the Contractor kept the sites in good condition and the PSC also
recommended the Contractor to maintain this situation always.
February
During the site inspection on February 09th 2011, we found that the construction site at Lo
river bridge construction area was untidy because the site had not been rearranged before the
workers came back home to enjoy Tet holiday.
The PSC has requested the Contractor to rearrange and clean the site right after the workers
come back to work and in the next site inspection in the third week, we perceived that the
Contractor had cleaned and rearranged the site.
At other sites, by observation during site inspections in month, we perceived that the sites
were kept in cleanliness and sanitary condition.
March
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
139 | P a g e
During inspecting the construction sites this month, we perceived that they almost were kept in
tidy, cleanliness and sanitary condition.
On March 16th 2011, during site inspection we detected that there were some empty oxygen
compressed boxes put on the ground in disorder waiting for change of others at the Lo river
bridge, abutment 1. The PSC requested the Contractor to immediately keep them in the
regulated place and keep the site in tidy and cleanliness condition.
4.11.3 Package A3
January
There were so many life garbages, scrap iron, Bentonite sacks uncontrolledly thrown without
any collections (KM60+900, Km51, Km73). Consultant requested Contractor to collect all kinds
of rubbishes and tranport them to stipulated area.
February
In inspection tour on the second and third week (14th – 26th February), the Bridge construction
site at Km54+600 (IC8), Km77+700 (Red river bridge), Km60+900 (Bai Bang railway flyover)
are not cleaned. In February, it is rain much. So the Contractor can not transport unsuitable
material which is wet pile up much in site. They must wait some day later to transport waste
out to site when it is drier.
March
There is not much rubbish in site. But unsuitable material is piled up much in site because it
was rain many days in March (Km68+000, Km63+200, Km77+200…). It is very hard to remove
unsuitable material out of site to the disposal areas. The Consultant issue instruct letter
regarding this matter Ref GET2-POS-A3-487. And the Contractor promised they will transport
all unsuitable material to the disposal areas when it stops raining.
4.11.4 Package A4
January
At present, the Contractor is deploying site clearing and topsoil remove. After inspection tour in
December, the Consultant has found that there is not many rubbish in site, except at station
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
140 | P a g e
Km 92+200. The Contractor is reminded to clean site follow Environmental control plan was
approved by the Consultant.
However, waste soil from site clearing and topsoil remove was piled up much in site. The
Contractor is planning to transport all unsuitable material out of construction area when
disposal area legal document complete.
February
There is not much rubbish in site. Almost, there is unsuitable material from site clearing or
topsoil. But the Contractor is transporting it to the approval disposal areas.
March
There is no rubbish in site. The worker cleaned all domestic waste out of site and worker’s
camp.
4.11.5 Package A5
February
In this period, cleanliness on site was still ensured. The main waste in this period is unsuitable
soil transported to disposal areas or disposed on the site. The Consultant has frequently
advised the Contractor to implement measures to ensure the environment on the site and
within the project area.
March
In this period, cleanliness on site was still ensured. The main waste in this period is unsuitable
soil transported to disposal areas or disposed on the site.
However, at stations Km118+930, the intersection area with provincial road, there was much
soil dropped on the road during material transportation. The Consultant has required the
Contractor to deal with this in letter No. GET3-KEANGNAM-11-A5-002 on 2th March 2011.
In weekly site inspections, the Consultant has frequently advised the Contractor to implement
measures to ensure the environment on the site and within the project area.
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
141 | P a g e
4.11.6 Package A6
January
Currently, the main waste on the site is unsuitable soil. In some areas such as: Km162+900
(Ngoi Giam bridge); Km159+200 (Ngoi Cong bridge); Km175+020; Km186+140; Km187+500;
Km188+800 (Suoi Nau bridge); Km171+900; Km175+020 unsuitable soil was disposed in
areas which had not been accepted by the Consultant. The Consultant has requested the
Contractor to deal with this promptly.
In addition, the worker’s consciousness in many areas isn’t good and the Contractor has not
controlled the environment actively. Thus, it has arisen some problems such as: the empty oil
tanks were dropped on the ground without collected as at station Km185+200 (Ngoi Don
bridge). However, these arisen problems are local, temporary. The Consultant has requested
the Contractor to propagandise to improve awareness of environmental protection for workers
and transport waste and excessive material out of the site when the work is progressing.
February
In this period, cleanliness on site is still ensured. The main waste in this period is unsuitable
soil transported to disposal areas or disposed on the site. The Consultant has frequently
advised the Contractor to implement measures to ensure the environment on the site and
within the project area.
However, due to bad awareness of workers and bad environment management, concrete was
spilled on the ground at station Ngoi Hut bridge (Km 165+100). The Consultant has frequently
reminded the Contractor on this issue in weekly site inspections.
March
In this period, cleanliness on site is still ensured. The main waste in this period is unsuitable
soil transported to disposal areas or disposed on the site.
In weekly site inspections, the Consultant has frequently reminded the Contractor to clean the
site and implement measures to ensure the environment on the site and in the project area.
4.11.7 Package A7
January
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
142 | P a g e
January 14th, 2011 at the location of Tan An Bridge Construction, Consultant found that
household waste on site. Consultant have warned and requested the Contractor to
immediately overcome the above problems. At the same time reminding the contractor
installing bins for refuse collection workers camps and field sanitation during construction.
Also in the 01 month in 2011 without consulting, detect garbage and other waste at the
positions of other candidates of the Contractor.
February
At the position of Khe Sang, Khe U and Khe Dai bridges, due to start constructing after Lunar
New Year therefore this construction site are so neat and relatively clean.
March
At the cast site No. 1 of culvert at km194+670, a number of cement packaging and rubbish are
discharge indiscriminately on the construction site and near the worker's camps. The
Consultant has asked the Subcontractor to immediately collect and transport them to the
prescribed treatment place.
4.11.8 Package A8
January
At the construction site of IC18 Bridge Km244+570, waste bentonite and water spills into the
street causing muddy and difficult for traffic participants. But after being reminded and issued
letter by Consultant on dated January 5th, 2011, the Contractor has to shield the sandbag wall
to prevent waste bentonite and minimize waste water overflowing in the streets.
February
On February 24th, 2011 at the construction of Ngoi Bo Bridge, while the process boredplies
construction, rock and bentonite spill over and were not transported to the approved wasteland
areas. Consultant required the Subcontractor to transport this rock and bentonite to the landfill
was approved on March 3rd, 2011.
At the construction of Suoi Trat, Suoi Nhu, IC 18 bridges, the roadworks are relatively neat and
clean at the acceptable level.
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
143 | P a g e
March
Current at the construction sites of Suoi Trat bridge, Ngoi Bo bridge, IC 18 are neatly arranged
and cleaned the space clearly.
The Consultant has not detected any violations of the Contractor on the issue of waste and
hygiene of the construction site.
4.12 BIODIVERSITY PRESERVATION
4.12.1 Package A1
January
Construction activities are seen not to cause negative impacts on the fauna and flora system.
However, the PSC always recommended the Contractor to control the construction activities to
prevent as well as avoid the negative impacts on ambient environmental and enhance the
sense of workers in environmental protection and biodiversity preservation.
February
With site inspections during the month we didn’t detect any adverse impact on biodiversity
preservation from the construction activities of project. There were only some small leaks of oil
however these problems didn’t threaten biodiversity surrounding because the leaked oil is too
small and didn’t leak offsite.
March
There was no serious adverse impact on biodiversity preservation from the construction
activities of project detected during site inspections. At Trung Kien bridge and Bon bridge
construction sites the mud and bentonite were leaked offsite as mentioned above, however
these problems were not considered as a serious threaten on biodiversity preservation due to
they happened in small areas and has been solved timely. Besides, the PSC also requested
the Contractor to manage the site and construction activities tightly to avoid these problems in
the future.
4.12.2 Package A2
January
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
144 | P a g e
Construction activities are seen not to cause negative impacts on the fauna and flora system.
However, the PSC always recommended the Contractor to control the construction activities to
prevent as well as avoid the negative impacts on ambient environmental and enhance the
sense of workers in environmental protection and biodiversity preservation.
February
The blocking water flow of channel at Song Dao bridge construction site probably affects the
agricultural biodiversity at this section because this problem also blocks the movement of
aquatic creature here. The PSC has requested the Contractor to remove the unsuitable pipe
culvert and reinstall new temporary stream crossing with appropriate pipe culverts to make
sure the water flow as well as movement of aquatic creature here.
March
During the site inspection on March 16th, 2011, we perceived that the Contractor had
demobilized the temporary stream crossing with unsuitable pipe culvert and restored the water
flow at Song Dao bridge construction site, so the water flow and the movement of aquatic
creature here are no longer blocked.
4.12.3 Package A3
January
Areas surrounding construction sites are almost paddy fields, gardens and plantations.
Construction activities are considered as factors not to cause negative impacts on the flora
system except for the dust coverage onto leaves that would affect harmfully photosynthesis
process and this would lead to reduction in biomass and oxygen production. No animals were
died by machinery or vehicle operation. Until now, we have no report about plants out of the
site limits which was unnecessary to be cut.
February
Areas surrounding construction sites are almost paddy fields, gardens and plantations.
Construction activities are considered as factors not to cause negative impacts on the flora
system except for the dust coverage onto leaves that would affect harmfully photosynthesis
process and this would lead to reduction in biomass and oxygen production. No significant
animals were died by machinery or vehicle operations, as far as Consultant knows and based
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
145 | P a g e
on the available information. Until now, we have no report about plants, specially trees, out of
the site limits which were unnecessary cut.
March
Areas surrounding construction sites are almost paddy fields, gardens and plantations.
Construction activities are considered as factors not to cause negative impacts on the flora
system except for the dust coverage onto leaves that would affect harmfully photosynthesis
process and this would lead to reduction in biomass and oxygen production. No significant
animals were died by machinery or vehicle operations, as far as Consultant knows and based
on the available information. Until now, we have no report about plants, special trees, out of
the site limits which were unnecessary cut.
4.12.4 Package A4
January
Along package A4, where the expressway of project across from station Km92+900 to
Km93+850 has forest. Construction activities are considered as factors not to cause negative
impacts on the flora system except for the dust coverage onto leaves that would affect
harmfully photosynthesis process and this would lead to reduction in biomass and oxygen
production. No animals were died by machinery or vehicle operation. Until now, we have no
report about plants or animal out of the site limits which was unnecessary to be damaged.
February
Areas surrounding construction sites are almost paddy fields, gardens and plantations.
Construction activities are considered as factors not to cause negative impacts on the flora
system except for the dust coverage onto leaves that would affect harmfully photosynthesis
process and this would lead to reduction in biomass and oxygen production. No significant
animals were died by machinery or vehicle operations, as far as Consultant knows and based
on the available information. Until now, we have no report about plants, special trees, out of
the site limits which were unnecessary cut.
March
Areas surrounding construction sites are almost paddy fields, gardens and plantations.
Construction activities are considered as factors not to cause negative impacts on the flora
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
146 | P a g e
system except for the dust coverage onto leaves that would affect harmfully photosynthesis
process and this would lead to reduction in biomass and oxygen production. No significant
animals were died by machinery or vehicle operations, as far as Consultant knows and based
on the available information. Until now, we have no report about plants, special trees, out of
the site limits which were unnecessary cut.
4.12.5 Package A5
February
According to the assessment of the diversity’s level of flora and fauna along package A5 route
(The assessment report of environment’s impact in Noi bai – Lao cai highway project) there
isn’t any kind of conservational creatures that is affected. At present, the construction activities
in this period haven’t affected negatively the flora and fauna.
In site inspections, the Consultant has always reminded the Contractor on biodiversity
protection and preservation and in coming months, the Consultant will continue to pay
attention to biodiversity of the package A5.
March
According to the assessment of the diversity’s level of flora and fauna along package A5 route
(The report of Environment Impact Assessment in Noi Bai – Lao Cai highway project) there
isn’t any kind of conservational creatures that is affected. At present, the construction activities
in this period haven’t affected negatively the flora and fauna.
In site inspections, the Consultant has always reminded the Contractor on biodiversity
protection and preservation and in coming months, the Consultant will continue to pay
attention to biodiversity of Package A5.
4.12.6 Package A6
January
Package A6 is a project which has direction along Red river and one site of package A6 is hilly
terrain with an average height over 120m. Clearing a large area of forest land, garden land and
agricultural land will affect the life of fauna and flora in project area. However, according to the
assessment of the diversity’s level of flora and fauna along package A6 route (The assessment
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
147 | P a g e
report of environment’s impact in Noi bai – Lao cai highway project) there isn’t any kind of
conservational creatures that is affected. The species that are affected, are common local
species, the flora are mainly agricultural crops and forestal trees used for purpose of
exploitation such as: cinnamon, eucalyptus, (mangium) acacia, bamboo, neohouzeaua…
The construction activities in this period haven’t affected negatively the flora and fauna.
However, the Consultant has always recommended the Contractor to control the construction
activities in order to prevent and avoid bad effects on the environment.
February
The construction activities in this period haven’t affected negatively the flora and fauna.
However, because of bad environment management of the Contractor, at some stations such
as Km186+740, many trucks weren’t equipped with canvas that created dust affecting the
flora, for example: reducing photosynthesis ability of plants. However, this is only temporary,
the Consultant has required the Contractor to water the transportation routes, equip canvas for
trucks and clean transportation roads.
In coming months, the Consultant will continue to pay attention to biodiversity preservation of
package A6.
March
The construction activities in this period haven’t affected negatively the flora and fauna.
However, because of bad environment management of the Contractor, on some hot days in
this month, at some stations such as Km174+340, Km165+340,…, dust was created during
transportation, affecting the flora, for example: reducing photosynthesis ability of plants.
However, this is only locally, the Consultant has required the Contractor to water the
transportation routes, equip canvas for trucks and clean transportation roads to ensure the
environment of the project.
In coming months, the Consultant will continue to pay attention to biodiversity preservation of
Package A6.
4.12.7 Package A7
January
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
148 | P a g e
Until the present time the construction activities of the Contractor does not cause adverse
impacts to plant and animal populations around the region. There are no animals were injured
or killed by the construction activities of the Contractor caused.
At Km198+400; Km202+200 are the positions of provincial roads were cut off by the
construction of the Contractor. The contractor is required to measures to slow vehicles as they
pass through these areas to prevent accidents caused to animals crossing the street.
In addition, Consultant also reminded the main Contractor and Sub contractors always pay
attention on barrier, shielding the cross-sectional area of construction site near the provincial
road or provincial road to avoid accidents happen to the creatures (buffalo, cows, dogs,
horses) when crossing the street.
February
Until the present time the construction activities of the contractor have not caused adverse
impacts to plant and animal populations around the region. There are no animals were injured
or killed by the construction activities of the Contractor.
However, th Consultant also reminded the main Contractor and Sub contractors are always
paying attention barrier, shielding the cross-sectional area of construction near the provincial
road or provincial road to avoid accidents happen to the creatures (buffalo, cows, dogs,
horses) when crossing the street.
March
Until the present time the construction activities of the contractor have not caused adverse
impacts to plant and animal populations around the region. There are no animals were injured
or killed by the construction activities of the contractor.
However, the Consultant also reminded the main Contractor and Subcontractors are always
paying attention barrier, shielding the cross-sectional area of construction near the provincial
road or provincial road to avoid accidents happen to the creatures (buffalo, cows, dogs,
horses) when crossing the street.
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
149 | P a g e
4.12.8 Package A8
January
Until the present time the construction activities of the Contractor have not caused adverse
impacts to plant and animal populations around the region. There are no animals were injured
or killed by the construction activities of the Contractor.
However, Consultant also reminded the principal Contractor and Sub contractors are always
paying attention barrier, shielding the cross-sectional area of construction near the provincial
road or provincial road to avoid accidents happen to the creatures (buffalo, cows, dogs,
horses) when crossing the street.
February
Until the present time the construction activities of the Contractor have not caused adverse
impacts to plant and animal populations around the region. There are no animals were injured
or killed by the construction activities of the Contractor.
However, the Consultant also reminded the main Contractor and Sub contractors are always
paying attention barrier, shielding the cross-sectional area of construction near the provincial
road or provincial road to avoid accidents happen to the creatures (buffalo, cows, dogs,
horses) when crossing the street.
March
Until the present time the construction activities of the contractor have not caused adverse
impacts to plant and animal populations around the region. There are no animals were injured
or killed by the construction activities of the Contractor.
However, the Consultant also reminded the main Contractor and Subcontractors are always
paying attention barrier, shielding the cross-sectional area of construction near the provincial
road or provincial road to avoid accidents happen to the creatures (buffalo, cows, dogs,
horses) when crossing the street.
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
150 | P a g e
5. REFERENCE DOCUMENTS RELATIVE TO ENVIRONMENT
The documents and letters sent and received to or from the Client and Contractors, have been
included in the Monthly Reports corresponding with the period of this Quarterly Report, so they
can be checked in those reports. In this chapter it’s only included a list of all of them.
5.1 PACKAGE A1
No Document reference Date Remark
1
GET1/POS/A1/750 Jan 17th, 2011
Report on Environmental Monitoring
and Observation Service – Dec, 2010
2
GET1/POS/A1/760 Jan 21st, 2011
Request to apply the environmental
protection measures
3 GET1/POS/A1/785 Feb 14th, 2011 Request to apply the EPMs
4 GET1/POS/A1/788 Feb 15th, 2011 Temporary Road Plan
5 REF-A1-GET1-MOM-38
Feb 24th, 2011 Minutes of Weekly Meeting (has not
been returned from EPMU)
6 GET1/POS/A1/802 Mar 02nd, 2011
Request to apply the Environmental
Protection Measures
7 GET1/POS/A1/803 Mar 04th, 2011 Environmental Protection Measures
8 GET1/POS/A1/820 Mar 18th, 2011 Request to implement the
Environmental Protection Measures
9 REF-A1-GET1-MOM-
38 Mar 17th, 2011 Minutes of Weekly Meeting
10
Site minutes between
EPMU, PSC
GETINSA and
Contractor POSCO
Mar 24th, 2011
Request to check and ensure
irrigation/drainage/temporary pipe
culverts/sanitary condition for workers
5.2 PACKAGE A2
No Document reference Date Remark
1 GET1/POS/A2/497 Jan 17th, 2011 Request to apply the environmental
protection measures
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
151 | P a g e
2 GET1/POS/A2/500 Jan 17th, 2011 Report on Environmental Monitoring and
Observation
3 REF–A2–GET1–MOM-
26 Feb 24th, 2011
Minutes of Weekly Meeting (has not
been returned from EMPU)
4 Site Minutes Feb 18th, 2011
Site minutes between PSC, EPMU and
Contractor POSCO (has not been
returned from EPMU)
5 REF–A2–GET1–MOM-
27 Mar 17th, 2011
Minutes of Weekly Meeting (has not
been returned from EMPU)
6 GET1/POS/A2/592 Mar 04th, 2011 Request to apply the irrigational works
protection measures
5.3 PACKAGE A3
No Document reference Date Remark
1 GET2-EPMU2-A3-139 Jan 26th, 2011 Approval of Plan of using and maintaining
the existing road for construction work
2 GET2-POS-A3-403 Jan 14th, 2011 Approval of first aid support on site from
hospital
3 Site minutes Jan 19th, 2011 Plan of using and maintaining the existing
road for construction work
4 GET2-POS-A3-432 Feb 12th 2011 Request to submit Environment monitoring
report of December 2010
5
GET2-POS-A3-451 Feb 25th 2011 Request to supplement the document of
disposal areas of section 2 and 4 Package
A3.
6 GET2-POS-A3-456 Feb 25th 2011 Approval of disposal area for section 3-
Package A3.
7 Site minutes Feb 24th 2011 Violation of Environment and safety at Red
river bridge construction.
8 GET2-POS-A3-484 Mar 14th 2011 Approval of environmental monitoring report
in December 2011 for Package A3.
9 GET2-POS-A3-487 Mar 16th 2011 Transportation of unsuitable material by the
Contractor, A3
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
152 | P a g e
10 GET2-POS-A3-492 Mar 22nd 2011 Approval for disposal area of section 4 - A3
11 Site minutes Mar 3rd 2011 Safety and Environment violation in section
6, Package A3.
5.4 PACKAGE A4
No Document reference Date Remark
1 GET2-KEA-A4-123 Jan 12th, 2011 Request on weekly environmental inspection
and environmental monitoring.
2 GET2-KEA-A4-117 Jan 3rd, 2011 Request to install signpost on site
3 GET2-KEA-A4-149 Feb 12th, 2011 Request to monitor Environment quality for
package A4.
4 GET2-KEA-A4-152 Feb 15th, 2011 Approval of Plan of using and maintaining
existing roads for construction package A4.
5 GET2-KEA-A4-162 Feb 21st, 2011 Approval of disposal areas of Cam Khe
district (section 1,2) package A4.
6 Site minutes Feb 18th, 2011 Inspect existing road package A4 (sec
1,2,3,4)
7 Site minutes Feb 22th, 2011 Inspect environment quality monitoring
Package A4
8 Site minutes Feb 15th, 2011 Checking disposal area in Cam Khe district
9 Site minutes Feb 16th, 2011 Inspect existing road package A4 (sec 5. 6)
10 GET2-KEA-A4-196 Mar 22nd, 2011 Request to additional legal document for
disposal areas of Ha Hoa district- package
A4 (second time)
11 GET2-KEA-A4-198 Mar 29th, 2011 Approval of addendum to proposal for
disposal area of Ha Hoa district- package A4.
12 GET2-KEA-A4-201 Mar 30th, 2011 Meeting invitation about Environment and
Safety of Package A4.
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
153 | P a g e
5.5 PACKAGE A5
No Document reference Date Remark
1 GET3-KEA-A5-109 16th Feb 2011 Approval of disposal areas
2 GET3-KEA-A5-110 16th Feb 2011
Reminding Contractor on Environmental and
safety at station Km119+000 – Km119+700
3 GET3-KEA-A5-114 18th Feb 2011
Approval of disposal areas for unsuitable
materials
4 GET3-KEA-A5-109 16th Feb 2011 Approval of disposal areas
5 GET3-KEA-11-A5-002 3rd Mar 2011
Reminding Contractor on Environmental and
safety issues
6 GET3-KEA-11-A5-003 3rd Mar 2011
Request for monitoring environmental
indicators – Package A5
7 GET3-KEA-11-A5-007 8th Mar 2011
Notice on approve the disposal areas for
unsuitable material – Package A5
8 GET3-KEA-11-A5-011 8th Mar 2011
Comments on Environmental Monitoring
Plan – Package A5
9 GET3-KEA-11-A5-023 17th Mar 2011
Reminding Contractor on Environmental and
safety issues
10 GET3-KEA-11-A5-032 23rd Mar 2011
Notice on documental of disposal areas for
unsuitable material
5.6 PACKAGE A6
No Document reference Date Remark
1 GET3/DOOSAN/A6/394 30th Dec
2010
Reminding Contractor on
environmental issues
2 GET3/DOOSAN/A6/399 03rd Jan 2011Non – approval of disposal areas for
unsuitable material
3 GET3/DOOSAN/A6/412 07th Jan 2011Reminding Contractor on
Environmental and traffic issue
4 GET3/DOOSAN/A6/420 12th Jan 2011Reminding Contractor on First Aid
Base establishment – Package A6
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
154 | P a g e
No Document reference Date Remark
5 GET3-DOOSAN-A6-427 14th Jan 2011Request for checking disposal areas
for unsuitable materials
6 GET3-DOOSAN-A6-435 18th Jan 2011Reminding Contractor on
Environmental and safety issues
7 GET3-DOOSAN-A6-458 22nd Jan 2011Reminding Contractor on
Environmental and safety issues
8 GET3-DOOSAN-A6-460 24th Jan 2011Approval of disposal areas for
unsuitable material
9 GET3-DOOSAN-A6-461 24th Jan 2011Comments on Re-submission of
Disposal Area at Tunnel South Portal
10 GET3-DOOSAN-A6-469 25th Jan 2011Reminding Contractor on number
plates of the cars
11 GET3-DOOSAN-A6-471 25th Jan 2011
Request for remove all unsuitable soil
at station Km175+020 to the disposal
area approved by Engineer
12 GET3-DOOSAN-A6-472 25th Jan 2011
Reminding Contractor on ensure
environmental and safety on Lunar
New Year holiday
13 GET3/DOOSAN/A6/500 17th Feb 2011Approval of disposal area at Tunnel
South Portal Km186+140
14 GET3/DOOSAN/A6/518 23rd Feb 2011Reminding Contractor on
Environmental and Safety issue
15 GET3-DOOSAN-A6-519 23rd Feb 2011Request for monitoring environmental
indicators – Package A6
16 GET3-DOOSAN-11-A6-010 7th Mar 2011 Notice on approve the disposal areas
for unsuitable material – package A6
17 GET3-DOOSAN-11-A6-024 10th Mar 2011 Reply to your letter, ref DHIC-11-PT-
040
18 GET3-DOOSAN-11-A6-033 12th Mar 2011 Request Contractor to ensure the living
conditions of workers
19 GET3-DOOSAN-11-A6-032 12th Mar 2011 Notice on Environmental and Safety
Meeting
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
155 | P a g e
No Document reference Date Remark
20 GET3-DOOSAN-11-A6-050 21st Mar 2011 Comments on Environmental
Monitoring Plan – Package A6
21 GET3-DOOSAN-11-A6-054 22nd Mar 2011 Reply to your letter, ref DHIC-11-PT-
050
22 GET3-DOOSAN-11-A6-065 25th Mar 2011
Request Contractor to submit CV of
Safety Manager and Environmental
Manager
5.7 PACKAGE A7
No Document reference Date Remark
1
GET4- GRBCC-295 Jan 12th, 2011
Slowly Submit the Report on the
Environment Monitoring Result – Stage 1-
December, 2010
2
GET4- GRBCC-297 Jan 18th, 2011
Delay in Completing the Procedure to Ask
the Confirmation of Social Committee at
District Level related to Using the Waste Pit
3 GRBCC-GET- A7-556 Jan 17th, 2011 Submitting Environmental monitoring report
on Construction stage (first time)
4
GET4- GRBCC-298 Jan 19th, 2011 Approve the Environment Monitoring Report
at Construction Stage (phase 1- December
2010) - Package A7
5 GET4-GRBCC-326 Mar 4th, 2011 Delay in complete the legal related to using
unsuitable material waste pits
6 GET4-EPMU4-304 Mar 4th, 2011 Officially Approved position of
Environmental Engineer - Package A7
7 GET4- GRBCC- 334 Mar 23rd, 2011 Require to overcome Environmental and
Safety problems of Package A7
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
156 | P a g e
5.8 PACKAGE A8
No Document reference Date Remark
1 GET4 – VINACONEX - 224 Dec 28th, 2010 Require to overcome the Environment
and safety problem of Package A8
2 GET4 – EPMU4-223 Jan 10th, 2011 Propose to Approve the Environment
and Safety Specialist - Package A8.
3
GET4 – VINACONEX - 239 Jan 19th, 2011 Require You to Overcome the
Environment and Safety Issue –
Package A8
4
A8/LC/110120-18 Jan 20th, 2011 Submit the curriculum of Mai Xuan Lap -
key personnel for position of Safety
officer
5
GET4 – VINACONEX - 244 Jan 25th, 2011 Not Approve the CV of Mr. Mai Xuan
Lap – Proposed for Safety Specialist
Position.
6 GET4-VINACONEX-264 Feb 24th, 2011 Require to overcome Environmental
and Safety problems of Package A8
7 GET4- EPMU4- A8-317 Mar 18th, 2011 Propose to approved Safety engineer of
Package A8
8 GET4- VINACONEX- 270 Mar 18th, 2011 Approved the Report environmental
monitoring on construction stage (phase
2- February 2011) – Package A8.
9 GET4- VINACONEX- 273 Mar 23rd, 2011 Require to overcome Environmental
problems of Package A8
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
157 | P a g e
ANNEX 1: PHOTOGRAPHIC REPORT
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
158 | P a g e
PACKAGE A1
Landslide risk (TL402 bridge)
Temporary Stream Crossing
(Xuan Phuong bridge)
Concrete waste was discharged on site.
15/02/2011 (TL402 bridge)
Mud after recycling bentonite spilled offsite.
15/02/2011 (Trung Kien bridge)
Riverside is eroded. 01/03/2011 (Xuan Phuong bridge)
Wastewater is discharged directly into river. 02/03/2011 (Xuan Phuong bridge)
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
159 | P a g e
PACKAGE A2
Channel is blocked by erosion
(Tan Dung bridge)
Drilling mud spilled into river
(Ben Gao bridge)
Worker’s camp is kept in sanitary condition. 18/02/2011 (Lo river bridge)
Mud after recycling bentonite spilled offsite. 16/02/2011 (Lo river bridge)
High level of dust in the air. 23/03/2011 (TL305 bridge)
Mud was discharged into river. 16/03/2011 (Pier 4 – Lo river bridge)
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
160 | P a g e
PACKAGE A3
Unsuitable material is pile up in site many
days (Km74+500)
Oil is leaked out ground (Km54+600)
Dump truck is not covered (km71) (dated: 11th February, 2011)
Bridge construction site is not cleaned
(Km54+600) (dated: 18th February, 2011)
unsuitable material is not moved out site to disposal areas. Km54+640 (dated: 24th
March, 2011)
Access road is muddy. It need to clean Km77+800 (Dated 17th March, 2011)
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
161 | P a g e
PACKAGE A4
Existing road at Km 81. It isn't cleaned and
watered appropriately.
Existing road at Km 92+200. It isn't cleaned
and watered appropriately.
Dump truck is not covered (Km 89+800) Oil drums is stored without safety method (Km 92+200)
Earth is fallen to drainage canal (Km108+965)
(dated: 23rd March, 2011)
Mud take one-third of Ngoi Gianh stream bed
(Km 88+700) (dated: 23rd March, 2011)
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
162 | P a g e
PACKAGE A5
The water flow is blocked by unsuitable soil at Km119+400. 14/2/2011.
The water flow is blocked by unsuitable soil at Km119+400. 14/2/2011.
There is much soil falls down on province road at Km118+930. 2/3/2011.
The construction location near the lake at Km121+600. 17/3/2011.
Erosion of access road at Km122+030 17/3/2011.
Monthly Safety and Environment Meeting of Package A5. 31/3/2011.
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
163 | P a g e
PACKAGE A6
Soil spilled into and blocked the channel, Km159+200 (Ngoi Cong bridge). 30/3/2010.
Unsuitable soil was poured near by the Red river. Km187+500. 15/1/2011.
Unsuitable soil disposed at unapproved area. Km171+900. 25/1/2011.
The truck without back cover. 15/2/2011.
The unsuitable soil was stored on the site at Km153+300. 24/3/2011.
The Contractor installed drainage pile at
Km186+730. 11/3/2011.
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
164 | P a g e
PACKAGE A7
The diposal place has been planted grass at Km195+800. 7/1/2011
Rocks and soil fell into the river at Km204+581 14/1/2011.
Rubbish and soil fall into the stream at Km191+353. 25/2/2011.
Rubbish and soil fall into the stream at
Km204+581. 25/2/2011.
Muddy road is very difficult for people to travel at Km194+200. 22/3/2011.
The flow is blocked during construction Km209 +329. 11/3/2011
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
165 | P a g e
PACKAGE A8
Bentonite flew in to the river. Suoi Trat Bridge. 28/12/2011
The revoking hole of bentonite at Suoi Trat
Bridge. 5/1/2011
Unsuitable soil is not transported to
disposal area. 24/2/2011
Bentonite flew into the stream at Km231+890
21/2/2011
Waste land is provisionally collected at the execution place at Km238+265. 8/3/2011.
Waste land is provisionally collected at the execution place at Km244+570. 8/3/2011.
Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project
166 | P a g e