environmental monitoring report...environmental monitoring report annual report july 2017 sri lanka:...
TRANSCRIPT
![Page 1: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/1.jpg)
Environmental Monitoring Report
Annual Report July 2017
Sri Lanka: Southern Road Connectivity Project
Prepared by Road Development Authority for the Government of Sri Lanka and the Asian
Development Bank
This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
![Page 2: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/2.jpg)
2
Contents
1. INTRODUCTION ............................................................................................................... 6
2. PROJECT IMPLEMENTATION PROGRESS ......................................................................... 8
3. CONSTRUCTION PROGRESS .......................................................................................... 11
5. SUMMARY OF ENVIRONMENTAL MITIGATIONS AND COMPENSATION MEASURES .... 20
6. SUMMARY OF ENVIRONMENTAL MONITORING ........................................................... 32
7. PUBLIC COMPLAINTS............................................................................................. 37
8. STATUS OF COMPLIANCE TO LOAN AGREEMENT ........................................................ 39
9. CONCLUSION ................................................................................................................. 41
![Page 3: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/3.jpg)
3
ABBREVIATIONS
ADB Asian Development Bank
AIDS Acquired Immune Deficiency Syndrome
CEA Central Environmental Authority
CP Contract Package
EMAP Environmental Management Action Plan
EMOP Environmental Monitoring Plan
EMP Environmental Management Plan
EO Environmental Officer
EPL Environmental protection License
ES Environmental Specialist
GAP Gender Action Plan
GRC Graveness Redress Committee
GSMB Geological Survey and Mining Bureau
HIV Human Immunodeficiency Virus
IEE Initial Environmental Examination
IML Industrial Mining Licenses
LA Local Authority
NHSP National Highway Sector Project
PIC Project Implement Consultant
PD Project Director
PMU Project Management Unit
RDA Road development Authority
RE Resident Engineer
ROW Right-of-way
SRCP Southern Road Connectivity Project
TL Team Leader
![Page 4: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/4.jpg)
4
Figure 1. Location map of selected road sections to be developed under SRCP
CP 01- Ratmalana - Mirihana , and Moratuwa Piliyandala Road
CP 02- Kesbewa - Pokunuwita , and Kiriulapana - Godagama Road
CP 03- Matugama - Southern Expressway Road
![Page 5: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/5.jpg)
5
EXECUTIVE SUMMARY This report is the 2nd annual report on environmental safeguards compliance of the
three (3) subprojects under the Southern Road Connectivity Project (SRCP), Loan
No: 3027-SRI funded by Asian Development Bank (ADB). The reporting period is
from May 2016 to April 2017.
The three sub projects under SRCP are;
1. Ratmalana - Mirihana Road B389, and Moratuwa Piliyandala Road B295. CP
01, and total length is 4.69km
2. Kesbewa - Pokunuwita Road B084, and Kiriulapana - Godagama Road
A004. CP 02, and total length is 16.45km
3. Mathugama - Southern Expressway B157. CP 03, and total length is 12.06km
4. CINEC Junction to Ambathale Junction Link road. CP04, Total length 1.83
km
CP 01 project is nearing at its’ completion; while the construction works of CP02 and CP03 project’s had already begun recently towards the latter part of 2016 and the project works are currently being progressed. The construction works of CP04 have still not started. Due to the adverse weather conditions that prevailed, heavy showers and floods were experienced during the initial stage of the reporting period (April-May 2016). However, the weather was mostly dry throughout the latter part of the reporting period and was favourable for construction activities. The baseline sampling of the selected environment parameters were collected and reports were submitted to the PMU by CP-02 and CP 03 respectively, while only operational period sampling is planned to be collected in CP-01. Moreover, the contractors have obtained the relevant licences and approvals that were required to execute the construction activities. No major environmental impacts were observed during the reporting period, because CP 01 road works are almost completed and the works of other projects’ have just started. Nevertheless, we have observed few shortcomings on safety matters which were however rectified then there.
![Page 6: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/6.jpg)
6
1. INTRODUCTION
Sri Lanka is an island, blessed with lush green forest and year around temperate
climate. It has hilly terrain in middle and south west part with surrounding flat
law terrain. The South-West part of the country experiences more rainfall and
defined as Wet Zone, and while other parts mostly North- West and South-West
parts received less rainfall defined as Dry Zone of the country.
For administrative purposes, the island has been divided into seven administrative
divisions. The Central Government is situated in Colombo District, where the
parliament is situated in.
Considering the strength of each province in terms of economic and political, the
Southern and the Western Provinces are ranked amongst the first level of
administrative divisions of the island. These two provinces have vital economic
development compared to the other five provinces of Sri Lanka. These two
provinces contribute over 60% of the country’s GDP while other provinces
contribute the rest. The southern Province's capital is Galle, while Colombo is the
capital of the western province. Subsistence farming and fishing is the main source
of income for the vast majority of the people of the Southern region but recently
the economic activities witnessed some degree of diversification viz tourism and
related economic activities such as hotels, boutiques, villas, handicrafts, travel
guiding, and tour organizing. The majority of people are well educated and enjoy
decent healthcare facilities and other common amenities.
A vast majority of the people are keen to enter the newly created economic space
through the Southern highway network which links all the strategically important
townships along the way. These townships are poised to boost new economic
development opportunities in the area which are also situated in close proximity to
famous tourist destinations.
In view thereof, the southern road connectivity project will help improve the
connectivity between expressway network and the local transport network in
southern region. Accordingly, it is proposed to develop 33.5 km of national
highways linking with the three interchanges of the southern expressway.
![Page 7: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/7.jpg)
7
The proposed development will not only improve the expressway connectivity but
would also help manage the future traffic volumes.
Southern Road connectivity project will improve five priority national highways
which provide connectivity to three interchanges of Southern Expressway. The
priority roads are selected according to the current road condition and capacity,
traffic demands, and readiness for improvement. The road will be widened,
upgraded and realigned as necessary to meet the projected traffic demand for the
next 20 years. The pavement is designed for life up to 10 years that could be
extended to 15-20 years with proper maintenance and excess axle load control.
Bridges, drainage structures and culverts will be improved and replaced as
required. Road safety audit will be incorporated into the engineering designs and
monitored during construction period. The details of the selected roads are
furnished below;
Table 1.1 The detail of SRCP road projects
Contract Package
Road Name Route No Length (Km)
CP1 Ratmalana - Mirihana Road B389 2.14
Moratuwa Piliyandala Road B295 2.55
CP2 Kesbewa - Pokunuwita Road B084 14.38
Kiriulapana - Godagama Road A004 1.79
CP3 Matugama - Southern Expressway B157 10.37
1.1 Report Purpose The monitoring process of the environmental safeguards compliance of the project
is entrusted to Project Management Unit and Environmental & Social Development
(ESD) Unit of RDA. This Annual report is prepared by Project Management Unit to
present the situation of environmental safeguard of the ongoing projects and the
monitoring results to the ADB.
![Page 8: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/8.jpg)
8
2. PROJECT IMPLEMENTATION PROGRESS
2.1 Recruitment of Project Implementing Consultant
The MG Consultants (Pvt.) Limited has been selected as the consultancy firm for
the SRCP on 12th March 2015. The cabinet approval has also been granted, and the
consultant has mobilized on 8th June 2015 and contract is in progress. The PIC
office operates in Battaramulla, Sri Lanka and it occupies Team Leader and his
technical staff.
2.2 Project Implementing Consultants’ (PIC) role in environmental safeguards compliance
The Team Leader (TL), Residential Engineer (RE) with the Environmental
Specialist (ES) of PIC is responsible for assessment of the contractors proposed
methods in relation with the stipulated EMP. The TL will advise and assist the RE
in co-ordination and meetings with external agencies and bodies with direct
concerns in the project.
Further, the RE gives direction and instructions to the contractor to mitigate the
possible adverse effects on the environment caused by construction activities.
In the event that some sections of sub project’s roads run through the
environmentally sensitive areas, the contractors should strictly follow all the rules
and regulations laid down by various authorities governing these areas while the
construction activities are going on. The ES of PIC shall pay particular attention to
these areas and advice the RE and contractor accordingly as regards the proper
procedure to be followed and the necessary permits which need to be obtained
before commencement of work/completion of the works.
The environmental monitoring procedure/task is being carried out by the PMU
and the PIC on a monthly basis with the participation of the contractor’s
representatives. The meeting summarizes the activities done by the contractor in
each month and suggestions are made to mitigate possible adverse impacts on the
environment. The issues that cannot be resolved at the above meeting will be
![Page 9: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/9.jpg)
9
tabled at the Monthly Progress Meeting conducted by the PD of the PMU and
would be further escalated to the GRC if necessary.
2.3 The project implementing progress
Of the ongoing three road projects, CP 01 has almost been completed its major
works and other two projects ‘works are being progressed. CP-02 and CP 03
projects works have been handed over to the contractors with sectional basis due
to the land acquisition matters. The time targets are given to solve the land
acquisition matters in said two road projects and those sections will be handed
over to the contractor.
2.3.1. Rehabilitation/Improvements to sections of Moratuwa – Piliyandala Road The project has been awarded to KD Ebert & Sons Holdings (PVT) on 23rd of
October 2014.
The all major construction activities have almost been completed during the
reporting period, while considering about progress up to 31st March, 2017, the
Physical progress was 96.44%.
2.3.2.. Rehabilitation/Improvements to sections of Kesbewa – Pokunuwita and
Kirulapana – Godagama Road.
The project has been awarded to MAGA Engineering (Pvt.) Ltd, on 9th of
September 2016 and the contract should be completed within two years from the
commencement date.
The Order to Commence was issued on 17th November 2016 for the Section 1 –
B084 Km 13+800 to 16+520 (2.72km),Section 3 – B084 Km 18+600 to 21+800
(3.20km), and Section 5 (amended) – A004 Km 17+260 to 18+200 (0.94km). The rest
of area (9.33km in Sections 2, 4 and 6) will be handed over to the contractor
immediate after the land acquisition completed, that are expected to be finished on
August 2017.
2.3.3. Rehabilitation/Improvements to sections of Southern Expressway –
Matugama Road
The project has been awarded to MAGA Engineering (PVT) Ltd, on 27th June 2016.
![Page 10: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/10.jpg)
10
Road works have started at the sections 1, and 2. The construction works of section
01 are well progressing. The major culverts and bridges works have been started
while 39/5 bridge works almost has started. Considering about progress up to 31st
March, 2017, the Physical progress is 16.67%.
2.3.4. Rehabilitation/Improvements to CINEC Junction to Ambathale Junction
Link Road
The Letter of Acceptance (LOA) was issued to Olimpus Construction (Pvt)Ltd, and
the work planned to be started from June 2017. The project road hasn’t land
acquisition matters.
![Page 11: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/11.jpg)
11
3. CONSTRUCTION PROGRESS
The all project roads have started their construction works during the reporting
period except the CP04, while the CP 01 project is nearing completion. The CP-02
and CP03 project have just begun their works.
4.1 Rathmalana-Mirihana (B389) and Moratuwa-Piliyandala (B295) roads. The Contractor has finished his material sources from his crusher, quarry and
asphalt plant at Naboda which is located approx. 50 km away from the road sites.
The monthly plant visits by Client and Consultant have completed in the month of
September 2016.
The all major construction activities have been completed. Related images
pertaining to some of the project activities are given below;
1. Moratuwa-Piliyandala (B295) Road
2. Rathmalana-Mirihana (B389) Road
Figure3:1 completed pedestrian crossing at Km 2+930 road marking at Km 3+860 of B 295 and completed sections at Km 0+200 and Km 0+480 of B389
During the material sourcing period up to December 2016, the contractor has
obtained all the relevant permissions and licenses for quarry, crusher and asphalt
![Page 12: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/12.jpg)
12
plant operations. The validity periods of given licences are not necessary to extend
due to completion of road works.
Table 3.1. The summary of obtained licences and permits
Type of
Quarry/plant Location
Type of
Approval/
license
Approving
Licensing
Authority
Date of
obtaining
Approval
Date of
validity
end
1.Metal
quarry
Thudugala,
Neboda
EPL
CEA
00376(R8) 24 .06.2015 23.06. 2017
Industrial
Mining
License
GSMB
IML/A/HO/219
5/R/5
22.05.2015 21.05.2017
Explosive
License
District Explosive
controller
(A 275109)
30.06.2015 30.12.2016
2.Crusher
Plant
Thudugala, Neboda
EPL
CEA
01587(R7)04481(R
4)
16.07.2015 15.07.2017
Trade
License Dodangoda LA 18.02.2015 31.12.2017
3. Asphalt
Plant Thudugala,
Neboda
EPL
CEA
05067 (R2) 16.03.2015 31.03.2017
4.Concrete
Batching
Plant
Rukmalgama, Athurugiriya
EPL CEA 01/10/2015 31 01 2017
3.2. CP-02 Rehabilitation/Improvements to sections of Kesbewa – Pokunuwita
and Kirulapana – Godagama Road
The Order to Commence was issued on 17th November 2016 for the sections 1, 3
and 5. Other sections such as sections 2, 4 and 6 are to be granted on August 2017.
The construction works of culverts and bridges of section 01 and 03 have been
started while only clearing and grubbing works are started at section 05.
The contractor has found 06 disposal lands to dispose the waste. The approval
process is being progressed during the reporting period while; the Western
![Page 13: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/13.jpg)
13
Provincial Waste Authority is willing to accept the unsuitable at their waste
dumping premises situated close to the project road.
The material sourcing sites of the contractor, such as quarry, crusher and concrete
batching plants are operated with relevant updated licenses (See Table 3.3). The
environmental and social issues are negligible in these sites and regular inspections
have been carried out.
The contractor’s own plant sites such as Quarry, Crusher and Asphalt plants are
situated nearby areas such as follows;
Table.3.2. The materials sourcing locations and distance
Plant type Capacity Location Distance from Project Road(KM)
Asphalt 80 ton/hour Homagama 20
Quarry - Kumbuka 5
Crusher 500m3/day Millaniya 35
Concrete Batching Plant
350m3/day Kumbuka 5
The contractor is not operating his own burrow areas and sourcing his sub-base
material requirements from outside commercial base burrow areas.
Table 3:3 The summary of obtained licenses and permits
Type of
Quarry/plant Location
Type of
Approval/li
cense
Approving
Licensing
Authority
Date of
obtaining
Approval
Date of
validity
end
Remarks
1.Metal
quarry
Millaniya,
Horana
EPL
CEA
00976(R8) 10 .06.2016 09.06. 2017
Informed to
renew the
licenses
Industrial
Mining
License
GSMB
IML/A/HO
/7037/R/03
27.05.2016 26.05.2017
Apply to
renewal on
15th April
2017
Explosive
License
District
Explosive
controller
(A 280360)
10.08.2016 14.08.2017
-
2.Crusher Kumbuka, EPL CEA 28.03.2016 27.03.2018 -
![Page 14: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/14.jpg)
14
Plant Horana 08019(R2)
Trade
License Horana LA 10.0`.2017 31.12.2017
-
3. Asphalt
Plant Hoamagama EPL
CEA
01576 (R8) 07.06.2016 06.06.2017
Informed to
renew the
licenses
4.Concrete
Batching
Plant Kumbuka,
Horana
EPL CEA
13911(Ro) 24.04.2017 23.04.2018
-
Trade
License Horana LA 25.01.2017 31.01.2017
-
Culvert & Bridges
Bridges and Culverts construction activities are progressing in all three sections
while 63% progress is recorded in section 1. The relevant warning signs such as
“Men at works, Road marrows and other signs have properly been fixed.
Figure 3.2 the ongoing construction activities of Culvert (16/1) deck concreting at Km
15+298 and Bridge (17/3) base concreting at 16+321
Other Constructions
Clearing and Grubbing, Roadway Excavation, Rock Filling, and Lined drains
works are progressing in all sections while section 01 almost finished the Clearing
and Grubbing activity.
Restoration of Government properties adjoining to the road is progressing. Under
this activity, mainly boundary walls and utility facilities are considered to be
reconstructed.
![Page 15: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/15.jpg)
15
3.3. CP-03 Rehabilitation/Improvements to sections of Southern Expressway – Matugama Road.
The Order to Commence was issued on 09th September 2016 for Section 1 – from
Km 42+372 to 37+000 (5.372km). While remain section (5.0km in Section 2) was
given to the contractor on March 2017. Meanwhile the construction works of
section 01 are progressing while the major culverts and bridges works have also
been started. The bridge works of 39/5 works has just started and bypass road
including temporary bridge is constructed to carrying the traffic until new bridge
will be finished. The necessary safety precautions including night time visibility
are taken at the site.
Table 3:4 The summary of obtained licenses and permits.
Type of
Quarry/plant Location
Type of
Approval/lice
nse
Approving Licensing
Authority
Date of
obtaining
Approval
Date of
validity end Remarks
1.Metal quarry
Mr.
Wanniarchchi,
Wallatha,
Naboda
EPL CEA
04762(R5) 21 .11.2016 20.11. 2017
-
Industrial
Mining
License
GSMB
IML/B/HO/1332/LR
/08
21.03.2016 30.06.2017
The
contractor
has applied
to renewal
Explosive
License
District Explosive
controller
(A 280327)
28.12.2016 27.06.2017
Do
2.Crusher
Plant
W.K.K, Neboda
EPL CEA
02547(R7)) 25.05.2016 24.05.2017
The
contractor
has applied
to renewal
on 21st
March 2017
Trade License Dodangoda LA 08.03.2017 31.12.2017 -
3. Asphalt
Plant Danister Estate,
Welipenna
EPL CEA
12060 (R1) 04.01.2017 03.01.2018 -
Trade License Mathugama LA 07.03.2017 31.12.2017 -
![Page 16: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/16.jpg)
16
4.Concrete
Batching Plant Gabada
Junction, Welipenna
EPL CEA
WE-B 03552(R0) 28.10.2016 27.10.2019
-
![Page 17: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/17.jpg)
17
4. Completion of the Environmental Compliance
The SRCP projects have been categorized under “B” category of the ADB
environmental and safeguard policy statements in 2009. Therefore the PMU have
submitted only IEEs reports to ADB regarding the five road sections. The Basic
Information Questionnaire, which is a report that included all the significant and
anticipated impacts of the proposed project, was submitted to the CEA for each
projects, the B084 and A004 roads fall under the EIA category while other projects
(B157, B 389 and B 295) only required basic questionnaire. The status of the
government compliance details are as follows;
4.1. CP01: Rathmalana-Mirihana (B389) and Moratuwa-Piliyandala (B295)
The Initial Environmental Examination reports (IEE) had been submitted for the
Rathmalana-Mirihana and Moratuwa-Piliyandala road respectively. Those reports
were approved by the ADB.
The environmental approvals are granted by the Central Environmental Authority
(CEA) based on the Basic Information Questionaries to implement the road works
for the above two projects. The validity period of above project roads will expire in
the year 2017 and renewal is not required because the construction works of the
road have almost been completed (See Annex 01).
Road Code Name of the Road Validity Period
From To
B389 Ratmalana-Mirihana Road 13. 02. 2013 20. 09. 2017
B295 Moratuwa-Piliyandala Road 11. 03. 2013 12. 05. 2017
The contractor’s Environmental Management Action plan (EMAP) and Traffic
Management Plan have been approved on August 2015 and September 2015
respectively by the Client and Consultant.
Environmental parameter observation activity for the pre construction stage (Base
line) and construction stage were completed. The results have been submitted to
the client.
![Page 18: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/18.jpg)
18
Monthly environmental meetings have been completed on December 2016 due to
end of the major construction works.
The restoring activities such as debris cleaning at yards and office locations, stock
piling and disposal yard (Suwarapola) have been initiated. The contractor has
prepared a rehabilitation report, which is included all his restoring activities is
being reviewed.
4.2. CP02: Kirulapana-Godagama (A004) and Pamankada-Pokunuwita (B084)
The Initial Environmental Examination reports (IEE) of both road projects had
been approved by the ADB.
The environmental approvals are also granted by the Central Environmental
Authority (CEA) based on the submitted EIA to implement the road works for the
above two projects (See Annex 01).
Road Code Name of the Road Validity Period
From To
Aoo4 Kirulapona-Godagama Road 24.03. 2014 23.03.2020
B084 Kesbewa-Pokunuwita Road 25.03. 2013 24.03.2020
The contractor’s Environmental Management Action plan (EMAP) and Traffic
Management Plan have been approved on November 2016 by the Client and the
Consultant.
When the meetings are held, joint site inspections are carried out together with
client, consultant and contractor to observe the environmental and safety lapses.
During the site visits, any recorded public complains are also being followed up.
4.3: CP03: B157 Mathugama-Southern Highway
The Initial Environmental Examination report (IEE) had been submitted on May
2013 and it was approved by the ADB.
![Page 19: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/19.jpg)
19
The environmental approval has been granted by the Central Environmental
Authority (CEA) based on the Basic Questionnaire to implement the road works
(See Annex 01).
Road Code Name of the Road Validity Period
From To
B157 Mathugama-Southern Highway 24.11.2014 06.01.2018
The contractor’s Environmental Management Action plan (EMAP) and Traffic
Management Plan have been approved on November 2016 by the Client and the
Consultant.
4.4. Changes in project scope The proposed scope of the project of Southern Highway to Mathugama has been
amended as follows.
Mathugama-Southern Highway (B157), the initial approvals were granted to carry
out about the 12 km length to 32 km post from 40 km post. The two kms length has
been excluded from 30km to 32km, as 2Km length has already been developed
through an another project. Hence, there has been a reduction in the road length
from 12.37 km to 10.37km.
![Page 20: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/20.jpg)
20
5. SUMMARY OF ENVIRONMENTAL MITIGATIONS AND
COMPENSATION MEASURES
Based on the approved EMAP, the sub-project contractor has to periodically carry
out the monitoring of selected environmental parameters such as ambient air
quality, noise levels, water quality and vibration levels. The contractor should
monitor the above parameters during the pre-construction (Baseline), construction
and post- construction or operation period of each project road.
In order to prevent lowering of green cover along the road due removal of existing
tree/bushes, the contractor is obligated to implement suitable tree planting
programs along the road or within the project road area.
In additionally the contractor should rehabilitate their all material sourcing
locations, yard and disposal sites, immediate after the completion of the project
activity.
5.1. Moratuwa - Piliyandala (B295) and Ratmalana - Mirihana (B389) 4.64 km.
Collection of baseline and the construction stage data have been completed. Data
was collected by the approved sub-contractor of Industrial Technology Institute
(ITI) during 2015-2016. The results have been submitted to the PMU of the RDA.
The operation stage data will be collected as immediate after the road section
completed and handed over to the client.
During the construction period of B295 road, all the readings of water samples
found to be similar to baseline values but TSS was less and E Coli had increased
not due to construction activities. B 389 when compared with baseline values, pH
was at neutral range, TSS decreases and E coli level has increased, not due to
construction activities. It was identified that the domestic waste water discharged
into surface water body was coursed to increase E-coli in the area.
According to the noise measurement test results of B 295, allowable noise level is
75dB(A). Except at B389 in front of Mahamaya School (80dB(A) and at B295 near
Indra Traders, Piliyandala (76dB(A), noise level all the other locations were within
allowable levels.
![Page 21: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/21.jpg)
21
Except for location, Kospalana Junction, all the parameters of other locations were
well below the ambient air quality standards. TSPM level is high at Kospalana
Junction, this may due to vehicular movement of the road.
As per the given vibration data, all the measured levels (baseline data) are within
the standard level. The vibration levels have not exceeded with normal vehicle
movement of these two road sections.
A detail of observed data during the pre-construction period is given in Appendix
02.
Considering about the awareness programs, there were nine (09) programs which
are related to HIV/AIDS, Human Trafficking, and Environmental awareness held
by the project staff during the reporting period as follows.
Table 5:1 A summary of the held HIV/AIDS programs
Date & Venue Resource Persons Participated personals
Total
participants
Male Female
11/06/2017 at RE’s
office in Maharagama
National HIV/AIDS control
unit of Sri Lanka(Dr. Janaki
Pandithrathne, Dr.
N.Dissanayake and Dr.
P.Premadasa
Labours, site supervisors
and staff members
53 03
13/09/2016 at DS
office in Maharagama
Do Government officers of
surrounding areas of
project road
25 67
22/10/2016 at Rural
Hospital in Neboda,
Kaluthara
Dr.Duminda Senevirathne and
Dr.H.S.S Ruwan
Workers and contractor’s
of Plant sites and
surround communities
17 25
20/11/2016 at Rural
Hospital in Neboda,
Kaluthara
Do Do
43 19
There were four (04) programs on HIV/AIDS conducted by the National
HIV/AIDS Control Unit. The programs had been organized to improve the
awareness among the construction workers as well as community members of
![Page 22: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/22.jpg)
22
project area. These programs were keenly conducted by close supervision of Dr.
(Ms.) Janaki Panditharathne, who represents the National HIV/AIDS Control Unit
of Sri Lanka.
With regards to the environmental awareness programs, there were two programs
held under the topic of Solid Waste Management and Recycling. These programs
have been organized to improve the knowledge of project areas communities.
Meanwhile, the contractor had organized the two human trafficking programs,
two child protection programs and one income generation program as follows;
Table 5:2 The summary of conducted other programs
Program Date & Venue Resource persons participation
Female Male
Solid Waste
management and
Human
Trafficking
26th May 2016 at
RE’s office
Mr. S. Jayatissa, CEA, Sri Lanka
Mr. M.Dissanayake, Attorny at Law,
Colombo
06 42
Solid Waste
management &
Recycling
21st July 2016 at
Rukmalagama
Mrs. Shantha Dayaseeli, CEA, Sri
lanka 15 15
Road Safety and
Child protecting
14th July 2016 at
Pre-school,
Suwarapola
Ms.Kusum Punchihewa, Sri Lanka
Police. 32 8
25th August 2016 at
Agrarian Service
centre, Udahamulla
Do
18 18
Human
Trafficking and
Income
Generation
Activity
30th September 2016
at School in
Piliyandala
Mr.Lasantha Alwis
82 23
The all lectures were conducted by specialized personnel on the relevant field.
![Page 23: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/23.jpg)
23
Figure 5:1 The held Safety and Environmental awareness meetings The scheduled Gender Action Plan (GAP) and the environmental awareness programs have been conducted successfully by CP 01 project and the detail of environmental mitigation activities performed by the contractor are summarized as below in Table 5.2. Table 5.2 A summary of the major environmental mitigation activities of CP 01
EMP Requirement Compliance
Attained
Comment on Reasons for
Partial or Non-
Compliance
Issues for Further Action
and Target Dates
1 Environmental
Parameter Observation
Baseline sampling
Yes Completed -
Construction stage
Yes Completed -
Operational Stage
No To be
conducted
The activity will be
conducted Immediate after
HIV/AIDS program held on 11/06/2016 and 13/09/2016
Solid Waste Management program held on 26/05/2016 and 30/09/2016
![Page 24: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/24.jpg)
24
the road section handed over to
the RDA
2 Fauna flora survey Yes Completed -
3 Environmental
awareness Yes Completed -
4 Health & Safety
Awareness Yes Completed -
5 HIV/AIDS programs Yes
Completed -
According to the contractor’s completed compensative tree planting program, 260
saplings were planted. A tree enrichment program also carried out to replacement
of wilted trees of previously replanted areas. The following table shows the
summary of completed works.
Table: 5:3 A summary of completed tree planting program
Programme Venue/Date Number of Plant
Plant Varieties Survival rates and
action taken
Replanting Programme 01
Mirihana Police Ground & Subadrarama Temple premises on 05/05/2012
50
Mangifera indica (Mango),
Nephelium lappaceum (Rambutan), Aegle marmelos (Beli), Terminalia arjuna (Kumbuk) Artocarpus heterophyllus (Jack), Cassia fistula (Ehela) etc,
20 plants were replanted by plant enrichment program
Replanting Programme 02 For World Envi: Day
Waste Management Authority premises at Karadiyana on 07/06/2016
20
Terminalia arjuna (Kumbuk), Cassia fistula (Ehela), Aegle marmelos (Beli)
4 plants were replanted
Replanting Programme 03 Mangrove Planting
Along the Bolgoda lake at Waste Management Authority premises at Karadiyana on 16/08/2016
100
Mangrove Plants such as Rhizophora mucronata, and R. Apiculata (Maha Kadole, Rathu Kadole.).
90% plants survived and wilted plants were not replaced because the WM Authority promised to complete the task by themself
![Page 25: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/25.jpg)
25
Replanting Programme 04
Sri Siddartha Collage premises and play ground area on 26/10/2016
50
Homegarden species such as Mangifera indica (Amba), Punica granatum (Delum) Psidium guajava (Pera), Annona muricata(Katu anoda) ,Persea Americana (Aligeta pera), Cinnamomum verum(Kurudu), Citrus spp.(Dehi) and Piper nigrum(Gammiris). Forest trees such as Swietenia macrophylla (Mahogani),Tactonia grandis (Thekka), Berrya cordifolia (Halmilla) , Pongamia pinnata (Karanda)etc.
3 plants were
replanted
Replanting Programme 05
Stenly Thilakarathna School premises on 23/11/2016
40
Home-garden species such as Flacourtia Indica(Uguressa), Syzygium aqueum (Jumboo), Punica granatum (Delum), Psidium guajava (Pera), Annona muricata(Katu anoda), Persea Americana (Aligeta pera),Citrus spp. and Piper nigrum(Gammiris) Shade and forest trees such as Pongamia pinnata(Karanda) Messua ferrea (Na) etc.)
All the plants were
at good condition. It
was observed
100% survival rate
Figure 5:2 A mango sapling is planted by Project Director at Police Ground premises while
Resident Engineer is plating a mangrove plant at Bolgoda lake area
5.2. Kesbewa - Pokunuwita Road (B084) and Kirulapana - Godagama Road (A004
Collection of baseline data has been completed and this activity was done under
the approved sub-contractor. The Industrial Technology Institute (ITI) was selected
for the above purpose and it was conducted in December 2016. The results have
been submitted to the PMU of the RDA. The construction stage data will be
![Page 26: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/26.jpg)
26
collected within six month intervals and next sampling will be conducted on June
2017.
According to the test results of water quality, pH is within standard levels, while
ground water sample did not fall within the stipulated levels. pH is acidic (6.2),
standard in 6.5-8.5 range. pH acidic due to soil nature. This type of soil contains the
Humic acid. All six samples of “BoD5” levels are within standard level. However
all the locations’ day time background noise level was higher than the permissible
level of the area and total suspended particulate matter (TSPM) of air quality
monitoring was lower than the permissible level of 450µg/m3 of the all sampled
locations.
During the reporting period, there was one (01) program on HIV/AIDS conducted
by MOH office staff with coordinating of the National HIV/AIDS Control Unit of
Colombo. The program was useful to improve the knowledge of the construction
workers as well as community members of project area.
Similarly, the contractor has conducted two road safety awareness programs with
participation of Police traffic control units within the area. The details of conducted
programs are as follows,
Table 5:4 A summary of the held HIV/AIDS programs
Program Date & Venue Resource persons participation
Female Male
HIV/AIDS
prevention
programm
11/01/2017 at
Boralesgamuwa
Dr.Samanthi Wijesundara, and
Dr.Dilshan Wijerathne, MOH office,
Boralesgamuwa
20 20
Road safety
Awarenss
programm
7th March 2017 at
Guidance
international
School, Kesbewa
Mr. Madugoda, Piliyandala Police.
28 16
Mr.M.K Jagath and Mr.Indika Prasad
of Moragahahena Police, Kesbewa 70 00
Similarly, the scheduled Gender Action Plan (GAP) and the environmental
awareness programs are being progressed by CP 02 project and the detail of
![Page 27: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/27.jpg)
27
environmental mitigation activities performed by the contractor are summarized
as below in Table 5.5.
Table: 5:5 A summary of the major environmental mitigation activities of CP 02
EMP Requirement Compliance
Attained
Comment on Reasons for
Partial or Non-
Compliance
Issues for Further Action and Target
Dates
1 Environmental
Parameter Observation
Baseline sampling
Yes Completed -
Construction stage
Yes
The quotations were called to 1st sampling and it has been approved by PIC. Sampling will be taken place in June 2017.
Operational Stage
No To be
conducted
The activity will be conducted Immediate after the road section handed over to the RDA
2 Fauna flora survey Yes Completed -
3 Environmental
awareness NO
More programs to
be conducted
The contractor is advised to conduct the programs
4 Health & Safety
Awareness Yes
More programs to
be conducted -
5 HIV/AIDS programm Yes Being
progressed
The contractor is advised to expedite the activity
![Page 28: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/28.jpg)
28
Figure 5: 3 The conducted HIV/AIDS programs in Boralesgamuwa on 21/01/21
and Gonapola Temple main hall on 3/4/2017.
Having discussed about the tree planting program, a plant nursery is established
to maintain the selected saplings inside the contractor’s yard which is intended to
be used for future tree planting programs along the road. In comparison to the CP
01 project road, this road has adequate spaces within the ROW which can be used
to tree planting activity.
Figure 5:4 A nursery which is managed to replant along the ROW of the road
In addition to the above mentioned program, the contractor was requested to carry
out the plant enrichment program along the Piliyandala bypass road which was
constructed by previous project of NHSP funded by ADB. A greenery program
![Page 29: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/29.jpg)
29
was previously conducted and now it is likely to be abandoned. Therefore the
client has requested to carry out the plant enrichment program.
Figure 5:5 The weeds spread over the road side trees and the Green Islands are
abandoned.
5.3. Southern Expressway - Matugama Road (B157)- 10.37km
Initially, the collection of baseline data has been completed and the task was
carried out by Industrial Technology Institute (ITI) which is a government own
institute. The activity was conducted on December 2016. The results have been
submitted to the PMU of the RDA. The construction stage data will be collected by
six month intervals and next sampling will be conducted on June 2017.
With regards to the submitted test results of water quality, the pH, BOD and
oil/greece content were at its standard level in all locations. According to the
measured vibration levels, the maximum permissible levels of interim vibration
standards have not been exceeded with the vehicle movements of this road section.
As compared to the measured results of air quality, TSPM (03hr) average was
lower than the permissible level of 450µg/m3 at all locations.
During the reporting period, there was one (01) program on HIV/AIDS conducted
by MOH office staff with coordinating of National HIV/AIDS Control Unit of
Colombo. The program has been organized for the community in the
neighbourhood of project area and as well as for the construction workers.
![Page 30: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/30.jpg)
30
Similarly, the contractor had conducted a one road safety awareness programs
with participation of Police traffic control units within the area. The details of
conducted programs are as follows,
Table 5:6 A summary of the held HIV/AIDS programs
Program Date & Venue Resource persons participation
Female Male
HIV/AIDS
prevention
program
21/01/2017 at
School Auditorium,
Walipenna
Dr. Geethani Samaraweera and Dr.
S.A.P Nishanthi, MOH office,
Nagoda, Kaluthara
35 19
Road safety
Awareness
program
15/03/2017 at
School Auditorium,
Owitigala,
Mathugama
Mr. Rajarathne Jayasundara, Police
station, Welopenna. 42 11
In the same way, the scheduled Gender Action Plan (GAP) and the environmental
awareness programs are being progressed by CP 03 project. However an
implementation delay was observed which was due to various reasons and the
contractor was informed to expedite the work without any further delay. The
details of environmental mitigation activities done by the contractor are
summarized as below in Table 5.7.
Table 5:7 A summary of the major environmental mitigation activities of CP03
EMP Requirement Compliance
Attained
Comment on Reasons for
Partial or Non-Compliance
Issues for Further Action and Target
Dates
1 Environmental
Parameter Observation
Baseline sampling
Yes Completed -
Construction stage
Yes
The quotations were called to 1st
sampling and it has been approved by
PIC
Operational Stage
No To be conducted
The activity will be conducted
immediate after the road section
handed over to the RDA
![Page 31: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/31.jpg)
31
2 Fauna flora survey Yes Completed -
3 Environmental
awareness Yes
More programs to be conducted
-
4 Health & Safety
Awareness Yes
More programs to be conducted
-
5 HIV/AIDS program Yes Being Completed -
Figure 5:6 Conducted awareness programs of CP 03 project, Above: Road safety
awareness meeting at Owitigala School hall conducted on 15th March 2017. Below:
HIV/AIDS awareness program conducted at Welipenna School hall on 21st January 2017
The contractor has planned to implement a tree planting program along the road in
the space available in ROW immediate after road completion. The root bowling
trees will be used for this activity and community tree planting programs are also
planned to be implementation.
![Page 32: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/32.jpg)
32
6. SUMMARY OF ENVIRONMENTAL MONITORING
Based on the approved EMAP, the sub-project contractor has to periodically carry
out the monitoring of selected environmental parameters such as ambient air
quality, noise levels, water quality and vibration levels. The contractor should
monitor the above parameters during the pre-construction (Baseline), construction
and post- construction or operation period of each project road.
6.1 Moratuwa - Piliyandala (B295) and Ratmalana - Mirihana (B389) 4.64 km
Collecting of environmental parameters such as Air quality, water quality, Noise
and Vibration levels for Pre-construction (baseline data) and the construction stage
had been observed. The task was assigned by the approved sub-contractor of
government of Sri Lanka. The project road and the material sourcing locations
were also subjected to monitoring and the following table shows the data collecting
activity of the CP 01 project.
Table 6:1 The dates of environmental parameters monitoring
Parameter Baseline Construction stage I Construction stage II
Water 06/10/2015 30/06/2016 21/09/2016
Air 06/10/2015 30/06/2016 12/09/2016
Noise 13/10/2015 28/04/2016 02/08/2016
Vibration 13/10/2015 14/06/2016 04/08/2016
The detail of the observed data that was during the pre-construction period is
given in Appendix 2.
According to the observed water quality data of B295 road, it was similar to baseline
values, but TSS was low and E-coli had increased during the construction stage I and II
data. In B 389 road, when compared with baseline values, pH in neutralize range, TSS
decreased and E-coli had increased during construction stage II data. Considering about
the air quality results, baseline measurements were carried out with 8hr average but
during the construction stage I and II data measurements were carried out with 1hr
average. All locations in both roads of B295 and B 389, the TSPM (1hr) was higher than the
allowable level (500μg/m3) during the construction stage II. The noise level of B295 road,
the measured levels of two locations (Kospalana and Suwarapola) were higher than the
![Page 33: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/33.jpg)
33
baseline values during the construction stage I and II, but lower than the allowable
level(75dB(A). At Piliyandala town, measured levels were lower than baseline values and
lower than allowable level. B 389 road locations, all three locations during construction
stage I and II measured locations are lower than baseline values and lower than the
allowable level (75dB)
6.2 Kesbewa - Pokunuwita Road (B084) and Kirulapana - Godagama Road
(A004).
Baseline data collection for the pre-construction stage of the project roads, i.e. the
Ambient Air, Water, Noise and Vibration levels, were collected before
commencement of the main construction activities. The data was collected in
December 2016, and the construction stage data will be collected in June 2017.
The detail of the observed data that was during the pre-construction period is
given in Appendix 2.
Considering about the water quality results, the pH values were within the
standard for all surface water samples, but ground water samples’ pH was 6.2,
which was not within standard. All eight locations of air quality samples of B084 ,
A004 and all plant sites baseline values of TSPM (3hr average) was lower than the
permissible level of 450/μg/m3. According to noise levels, most of the locations
background level is higher than the permissible level of the area and all existing
measured noise levels are higher than the permissible levels at day times. These
may due to existing traffic nature. The results of the vibration levels of the project
area, maximum permissible levels (1.0, 2.0, or 4.0) of interim vibration standards
have not become exceeded with the vehicle movements of these road sections.
6.3 Southern Expressway - Matugama Road (B157)
Similarly, the baseline data collection of the project road was collected before
commencement of the main construction activities. The observer of the event was
Industrial Technological Institute (ITI). During the sampling, water, air, noise and
vibrations were sampled along the project road as well as selected material
sourcing location of the contractor.
![Page 34: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/34.jpg)
34
The detail of the observed data that was during the pre-construction period is
given in Appendix 2.
According to the measured water quality of all three locations pH, BOD and grease
content are within standard. All three locations of air quality samples, TSPM 3hr average
is lower than the permissible level of 450/ug/m3. The all existing measured noise levels
are higher than the permissible level of day time, this may due to traffic noise. Considering
about the vibration levels, permissible level of interim standards have not been exceeded
with vehicular movement of this road section.
6.4 Compliance Inspections
During the reporting period, road construction works were progressing in all sub-
projects while CP-01 works were nearing completion.
Monthly field inspections were carried out by Environmental Specialists of the
Employer, PIC and Contractor. Appendix 03, summarizes the activities carried out
in CP-01, CP-02 and CP-03 Sub-projects, their impacts to the environment (as
observed during each field visit mainly by the ES of PIC), suggestions given by ES
to mitigate, avoid or minimize the adverse impacts, effectiveness of the migration
measures adopted, and any further action needed.
Table 6.2 The status of the contractor’s EMP implementation
Sub Project
EMP part of
Contract
Document
(Yes/No)
EMP being
Implemented
(Yes/No)
Status of EMP
Implementation
(*)
Action Proposed
CP-01 Yes Yes Good Advised to fully Implement the EMAP
submitted by Contractor
CP-02 Yes Yes Good Advised to fully Implement the EMAP
submitted by Contractor
CP 03 Yes Yes Good Advised to fully Implement the EMAP
submitted by Contractor
(*) 1 – Very good (All required Mitigation Implemented), 2 – Good (The majority of required Mitigation
Implemented), 3- Fair (Some Mitigation Implemented), 4– Poor (Few Mitigation Implemented) ,5 – Very Poor
(Very few or No Mitigation Implemented)
![Page 35: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/35.jpg)
35
Although the contractors have been placed in good category based on the EMP
implemented, their traffic and safety measures should be upgraded further due to
high traffic congestion in the project area, especially in the morning and evening
time at CP01 and CP02. The detailed compliance to EMP is provided in Appendix
04 and their activities are separately discussed as follows.
Considering the total number of 19 mitigation actions to be complied in CP 01
project, 13 actions have been fully complied; while six (6) mitigation actions are
partly complied. The main reasons for the partly complied actions were; the
activities will be implemented after handed over the road sections. Other than
these, set of all other mitigation actions were completed by the contractor.
Because of newly started projects, all the mitigation actions that are described in
EMP should be implemented or complied by the contractors of CP02 and CP 03.
The monthly payment item for EMP requirements is provided in the contract. The
payment is released after receiving of the recommendations based on the monthly
inspections and observations by employer and the PIC Environmental Specialists
(ES) with participation of the contractor’s Environmental Officer (EO).
According to approved payment percentage of the EMP payments (Table 6.2), the
contactor has obtained 75% of average payment values base on the EMP
implementation activities done during each month.
The following table shows the monthly payment percentages that had been made
to the contractor based on the EMP implementation in the project.
Table 6.3. The approved monthly percentages for EMP implementation during the
reporting period
Months EMP implementation
Approved percentage (%)
CP01 CP 02 CP 03
May 2016 78 - -
![Page 36: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/36.jpg)
36
June 2016 83 - -
July 2016 66 - -
August 55 - -
September 2016 65 - -
October 2016 35 - -
November 2016 80 - -
December 2016 87 - 69
January 2017 - 79 69
February 2017 - 89 70
March 2017 - 88 83
April 2017 91 81
![Page 37: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/37.jpg)
37
7. PUBLIC COMPLAINTS
The Grievance Redress Committees (GRCs) have been established to look into the
public complaints regarding the social and environmental impacts during the
period of construction works for every sub project. The GRC considers the
problems that could not be solved directly by the Employer, Consultant and
Contractor. The GRC committee holds meetings with all responsible parties to
yield the best solutions for the problems.
Table 7:1 The established GRC dates and Divisional Secretariat Offices Package Road Name Divisional Secretariat GRC established date
CP 01
Rathmalana - Mirihana Road (B389) Maharagama 05. 05 .2015
Moratuwa - Piliyandala Road (B295)
Sri Jayawardenpura 01.11 .2014
CP 02
Kirulapana - Godagama Road (A004)
Homagama 05. 05 .2015
Kesbewa - Pokunuwita Road (B084) Kesbewa 05. 05 .2015
CP 03 Southern Expressway - Matugama
Road (B157 Mathugama 05. 05 .2015
The PMU and Divisional Secretary arrange the GRC meetings upon receiving of
public complaints to solve the problems. Considering the number of complaints
received so far, there were two GRC meetings conducted at Divisional Secretariat
Office in Kesbewa to discuss the received 04 complaints regarding to CP01 project
and these problems have been solved.
The above mentioned GRC meetings were conducted at Divisional Secretariats office in Kesbewa respectively on 23rd December 2016 and January 2017.
![Page 38: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/38.jpg)
38
Figure: 2.1 The GRC Committee members including chief incumbent of Buddhist temple, Project Engineer of CP01, Divisional Secretariat (Kesbewa) and Resettlement Assistant were chaired and discussing about the public complains.
Further, the employer, the consultant and the Contractor attend the public
complains which are received in written form and through the electronic media (E-
mail, Fax and Telephone). Moreover, all complains received have been listed out
and discuss in the monthly progress meetings. The summary of the received
complaints up to 31st March 2016 are given in Appendix 05. There were 99
complains have received from both B295 and B389 roads so far, most of them are
requesting of cover slabs and proper access to their hoses and business premises.
Among them 70 complains were already solved and others are being completed by
involving the related line agenesis. Some of the complaints await to insurance
claims and those cases will be completed immediately after the claim area received.
Likewise, there were 31 complaints received so far from CP 02 project, among these
complaints 15 have been solved, while 13 are pending and, 3 are progressing. In
the same way there were 44 complaints received up to 31st march 2016 from CP 03
project, while 15 complaints are already solved, 18 complaints are being
progressed and 11 complaints are pending.
In the monthly environmental meetings progress, they draw their attention and
discuss about the public complaints.
In addition, small scale Community Committee Meeting had been conducted by
CP 01 project (mainly by appointed Environmental Officer of the project) aiming
to address the public disturbances while construction activities are progressing.
It was suggested to conduct the Community Committee Based Organizations if
necessary in the project affected areas in CP02 and CP 03 (public and private
authorities and personnel) which will address the problems regarding the
constructions.
![Page 39: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/39.jpg)
39
8. STATUS OF COMPLIANCE TO LOAN AGREEMENT
Based on the information provided in the above sections the compliance of the
project to the environment safeguards related clauses in the “Loan Agreement” are
generally satisfactory. Detail of the compliance of environmental clauses is
provided in the table below.
Clause Status of Compliance 1. Schedule 4, Conditions for Award of Contract Para 6: RDA shall not award any Works contract which involves environmental impacts until: (a) CEA or the project approving agency designated by CEA has granted the final approval of the IEE; and (b) RDA has incorporated the relevant provisions from the EMP into the Works contract.
Complied. All contracts have been awarded after CEA approval of the respective project. All bidding documents included the EMP before issuance to the contractor.
2. Schedule 5, Environment, Para 4: The Borrower shall ensure or cause RDA to ensure that the preparation, design, construction, implementation, operation and decommissioning of the Project and all Project facilities comply with (a) all applicable laws and regulations of the Borrower relating to environment, health and safety; (b) the Environmental Safeguards; and (c) all measures and requirements set forth in the relevant IEE, the relevant EMP, and any corrective or preventative actions set forth in a Safeguards Monitoring Report.
Complied. All measures in the IEE and EMP are being implemented.
3. Schedule 5, Safeguards – Related Provisions in Bidding Documents and Works Contracts Para 9: The Borrower shall ensure or cause RDA to ensure that all bidding documents and contracts for Works contain provisions that require contractors to: (a) comply with the measures relevant to the contractor set forth in the IEEs, the EMPs and the RPs (to the extent they concern impacts on affected people during construction), and any corrective or preventative actions set forth in a Safeguards Monitoring Report; (b) make available a budget for all such environmental and social measures; (c) provide RDA with a written notice of any unanticipated environmental,
Complied. All bidding documents included relevant provisions from the IEE and EMP. The contractor is providing budget for implementing the EMP There have been no unanticipated environmental risks so far
![Page 40: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/40.jpg)
40
resettlement or indigenous peoples risks or impacts that arise during construction, implementation or operation of the Project that were not considered in the IEE, the EMP and the RP;
4. Schedule 5, Safeguards Monitoring and Reporting Para 10: The Borrower shall do the following or cause RDA to do the following: (a) submit semi-annual Safeguards Monitoring Reports to ADB and disclose relevant information from such reports to affected persons promptly upon submission; (b) if any unanticipated environmental and/or social risks and impacts arise during construction, implementation or operation of the Project that were not considered in the relevant IEE, EMP and/or RP, promptly inform ADB of the occurrence of such risks or impacts, with detailed description of the event and proposed corrective action plan; and (c) report any actual or potential breach of compliance with the measures and requirements set forth in an EMP or a RP promptly after becoming aware of the breach.
Being complied. Since the project is environment category B, the annual environmental monitoring report is being submitted. There have been no unanticipated environmental risks so far. There has been no breach of compliance to the EMP so far.
![Page 41: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/41.jpg)
41
9. CONCLUSION
The guidelines for Environmental protection and pollution control for construction
activities are clearly defined in the EMP for all sub-projects. In addition, the
Contractor’s EMAP provides further specific time lines & schedules to protect
project impacted areas by observing the selected environmental parameters (i.e.
Water, Air, Noise & Vibration) to ensure that the surround environment is
protected.
Firstly, the completed project road of CP 01 was successfully implemented their
proposed mitigation measures that were proposed by employer and the consultant
during their site observations. The issues at the contractor’s Asphalt plant were
satisfactorily solved, but he had taken a long period of time to rectify these issues.
Therefore, the all contractors must be taken the proposed remedial actions as soon
as possible because these impacts are irreversible. It was revealed that the
contractor’s quick response/actions are very important when addressing the
construction related environmental problems.
Secondly, the weekly site inspections are carried by the Contractor, while Monthly
Inspections are continued by the Environmental Specialists of the Employer and
PIC. The monthly environmental meetings conduct regularly and the contractor’s
participation was satisfied.
Site inspection will be regularly carried out to ensure that Environmental impacts
are being adequately mitigated and to ensure continuation of compliance with
stationary regulations as required by laws and accepted in the EMP. The
Contractor is being regularly guided and instructed to pay attention to
environmental issues and adhere to the provisions of EMP and his own EMAP.
The ongoing projects (CP02 and CP 03) environmental monitoring activities are
being progressed as proposed scheduled while final stage monitoring activity will
be completed by CP 01.
Finally, the overall status of implementation of environment safeguards under the
project is satisfactory.
![Page 42: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/42.jpg)
42
Appendix: 01
1.1 CEA approval for B295 road.
![Page 43: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/43.jpg)
43
1.2 CEA Approval for B389 road
![Page 44: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/44.jpg)
44
1.3 CEA approval for B084
![Page 45: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/45.jpg)
45
1.4. CEA approval for A004 road
![Page 46: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/46.jpg)
46
1.5 CE Approval for B157 road
![Page 47: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/47.jpg)
47
Appendix 02 The Summary of tested parameters of CP 01
Table 2.1. Water Quality results
Road Section
Sample location Date of Sampling pH
EC μs/cm
DO mg/l
TSS mg/l
BOD mg/l
Oil and grease mg/l
E.Coli Chloride mg/l
Sulphate mg/L
Baseline(6th October 2015)
B 295 Bolgoda Ela upstream
7.30 309 3.42 40 03 ND ND 34 19
B 389 Irrigation canal upstream
7.47 366 5.07 75 04 ND ND 31 20
Construction Stage-I (12th July 2016)
B 295 Bolgoda Ela upstream
7.42 1109 5 14 3 ND 20 254 40
B 389 Irrigation canal upstream
5.33 380 3 25 2 ND 110 32 17
Construction Stage-II(21st September 2016
B 295 Bolgoda Ela upstream
6.93 366 5.8 55 2 ND 2.2*104 31 13
B 389 Irrigation canal upstream
6.88 17680 6.9 15 3 ND 170 5706 750
Surface water quality standards
6-9 - - - 05 0.1 Negative 1200 -
EC=Electrical conductivity, DO=Dissolved Oxygen, TSS=Total Suspended Solid, BOD3=Biological Oxygen Demand, ND=Not Detected
![Page 48: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/48.jpg)
48
Table 2. 2 Baseline Noise levels
Road Section
Measured locations Base Line Construction Stage-I Construction Stage-II
ENL.dB(A) RBL dB(A) ENL.dB(A) RBL
dB(A) ENL.dB(A)
RBL dB(A)
B 389
Day Night Day Night Day Night Day Night
Kattiya Junction 74 73 64 63 71 NS 70 NS
Gansabha Junction 75 73 69 68 74 NS 72 NS
Front of Mahamaya School 74 73 64 63 80 NS 71 NS
B 295
Kospalana Junction 61 60 56 53 72 NS 73 NS
Suwarapola Junction 67 67 60 59 71 NS 72 NS
Indra Treaders, Piliyandala 78 72 69 63 76 NS 72 NS
ENL=Existing Noise levels(L Aeq)-dB-(A), RBL-Rating Back Ground Noise level(L A90-15min) NS=Not Sampled Standard Maximum Permissible Noise Levels at Boundaries in LAeq'T.
Areas LAeq', T
Day time Night time
Low Noise 55
45
Medium Noise
63* 50
High Noise
70 60
Silent Zone
50 45
* Provided that the noise level should not exceed 60 dB (A) inside existing houses, during day time. LAeq', T=the equivalent continuous, A- weighted sound pressure determined over a time interval T(in dB) The project area falls into the medium noise level zone
![Page 49: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/49.jpg)
49
Table 2.3 Baseline vibration levels
Road section Measured locations A(ROW) B(ROW=10m) C(ROW+20m)
B 295
Near Sri Wijerama Temple 0.572 0.199 0.371
Suwarapola Bodhi 0.265 0.092 0.142
Near Church 0.209 0.145 0.135
Near Bauddaloka Mawatha 0.157 0.140 0.134
Near School lane 0.207 0.101 0.096
B 389
Near Mirihana Junction 0.32 0.14 0.095
Subadrarama Temple 0.26 0.09 0.075
Court complex, Gangodawila
0.16 0.085 0.085
Mahamaya Girls College 0.365 0.105 0.08
Walauwatta Junction 0.09 0.072 0.072
Maximum Peak Value in Velocity mode (mm/sec) day time-one hour measurement average, Standreds-02mm/sec(type 03)
![Page 50: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/50.jpg)
50
Table 2.4 Baseline air quality results
Road Section
Mesured Locations
So2(8hr) (ug/m3)
NO2(8hr) (ug/m3)
CO(1hr) (ppm)
O3 (1hr) (ppb)
TSPM (ug/m3) 8hr
TSPM 8hr (night)
Wind Speed (ms-1)
Wind Direction
B 295
Indra traders, Piliyandala
52.0 21.0 1.8 0.01 319 48 1-2 NE
Suwarapola 30.4 12.6 1.4 0.02 236 38 1-3 NE
Kospalana Junction
30.3 8.4 1.0 0.01 455 57 2 N
B 389
Gansaba Junction
38.8 21.4 4.5 0.01 278 151 2 E
Kattiya Junction
41.0 11.8 0.8 0.01 165 91.4 2 NE
Mirihana Junction
44.7 6.8 0.9 0.01 158 111 2 NE
Maximum Permissible Level
120 150 26 100 350
![Page 51: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/51.jpg)
51
Appendix 2(A) The Summary of tested parameters of CP 02
Table 2.5 Water Quality results
Road Section
Sample location Date of Sampling pH Temperature (0C)
TSS mg/l
BoD5 (mg/l) 100ml
Oil and grease mg/l
E.Coli
B 084
Pinwala Ela, Pokunuwita at 28+000Km RHS
28th December 2016
7.20 30 44 03
ND ND
Maha Oya upstream at Gonapala Junction at 23+280 km RHS
28th December 2016
7.76 29 08 02
ND ND
Maha Oya upstream at Gonapala Junction at 22+760 km LHS
28th December 2016
6.80 28 10 02
ND 140
Kimbulkatuwa Ela upstream at18+720 km LHS
28th December 2016
6.60 30 20 05
ND 92
Maha Oya upstream at 16+320 Km LHS
28th December 2016
6.60 29 07 04
ND 220
A004 Well at Mr. Jayakody(near Army Camp in Homagama)
28th December 2016
6.20 27 - 02
ND 550
Surface Water Quality Standard 6-9 - - 05 Negative Negative
ND=Not detected Note: For all samples, pH is within standard, while ground water sample does not fall within standard. All six samples ‘ BoD5 levels are within standard
![Page 52: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/52.jpg)
52
Table 2. 6 Baseline Noise levels (measured on 08th December 2016)
Road Section Measured locations
Base Line
ENL.dB(A) RBL dB(A)
B084
Day Day
Polgasowita at 17+100 RHS 72 60
Kahathuduwa interchange at 18+540 RHS 73 67
Gonapola Junction at 23+160 km RHS 69 59
Pokunuwita Junction at 28+140km LHS 68 59
A004
Nugegoda in front of Anula School LHS 74 67
Homagama in front of Army Camp 68 63
Homagama in front of Army Camp’s Temple 74 64
Plant Sites Concrete/crusher plant at Kumbuka at 26+320 RHS 67 54
Asphalt /crusher Plant at Olaboduwa 21+850km 58 56
ENL=Existing Noise levels(L Aeq)-dB-(A), RBL-Rating Back Ground Noise level(L A90-15min) Standard Maximum Permissible Noise Levels at Boundaries in LAeq'T.
* Provided that the noise level should not exceed 60 dB (A) inside existing houses, during day time. LAeq', T=the equivalent continuous, A- weighted sound pressure determined over a time interval T(in dB) The project area falls into the medium noise level zone Note: Most of the locations’ day time background noise level is higher than the permissible level of the area.
Areas LAeq', T
Day time Night time
Low Noise 55 45
Medium Noise 63* 50
High Noise 70 60
Silent Zone 50 45
![Page 53: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/53.jpg)
53
Table 2.7 Baseline vibration levels measured on 08th December 2016
Road section
Measured locations Category of
structure Vibration Level PPV(mm/Sec.
Frequency range(Hz)
Predominant frequency)
B084
Dharamasena Artigala Girl’s school at 14+130 RHS, Kesbewa
Type 3 0.12-0.22 10-50 10.5-11.0
District Hospital at 17+920 Km RHS, Polgasowita
Type 3 0.09-0.16 10-50 13.0
Primary School at 18+940 Km LHS Type 3 0.14-0.30 10-50 10.0-12.5
Police Station at 19+080Km RHS, Polgasowita
Type 3 0.22-0.30 10 8.5-11.75
Primary School at 26+180 km LHS, Kumbuka
Type 3 0.23-0.41 10 60.5-61.5
Prashanthi Reception hall at 26+320Km LHS, Kumbuka
Type 3 0.09-0.15 10 25.5-30.0
A004
Kumara Udayam Tamil School at 0+160 LHS, Kirulapona
Type 3 0.10-0.16 10 10.75-13.0
Public Library at 0+800km RHS, Kirulapona
Type 3 0.07-0.11 10 13.0-14.5
Army Camp Entrance at 16+280 RHS, Homagama
Type 3 0.20-0.43 10 18.5-20.0
Army Camp’s temple , Homagama Type 3 0.09-031 10 12.0-15.5
**Maximum Peak Value in Velocity mode (mm/sec) day time-one hour measurement average, Standreds-02mm/sec(type 03) **According to the measured vibration levels, maximum permissible levels (2.0 or 4.0mm/sec) of interim vibration standards have not been exceeded with the vehicle movements of this two road section
![Page 54: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/54.jpg)
54
Table 2.8 Baseline air quality results
Road Section
Mesured Locations Sampling Date TSPM(µg/m3) 3hour
average)
B 084
Polgasowita at 17+100 RHS 16/12/2016 309
Kahathuduwa interchange at 18+540 RHS
16/12/2016 217
Gonapola Junction at 23+160 km RHS
16/12/2016 302
Pokunuwita Junction at 28+140km LHS
16/12/2016 259
A004
Nugegoda in front of Anula School LHS
16/12/2016 254
Homagama in front of Army Camp
16/12/2016 260
Plant Sites
Concrete/crusher plant at Kumbuka at 26+320 RHS
15/12/2016 251
Asphalt /crusher Plant at Olaboduwa 21+850km
15/12/2016 234
Note: As per the results, all eight locations of B084, A004 and plant sites, baseline level of total suspended particulate matter(TSPM) for three hour average is lower than the permissible level of 450µg/m3.
![Page 55: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/55.jpg)
55
Appendix 2(b) The Summary of tested parameters of CP 03
Table 2.9 Water Quality results
Road Section
Sample location Date of Sampling
pH EC μs/cm
Temperature (0C)
TSS mg/l
BOD mg/l
Oil and grease mg/l
E.Coli
Baseline sampling
B 157
Kadiththamankada Ela upstream(34/2 Culvert-33+610 km)
05/12/2016 7.30 45 28.6 11 02 ND 2400
Badugandola Ela upstream, (34+998Km LHS
05/12/2016 7.39 42 28.1 02 ND ND 1700
Welipenna Ela Upstream(40/1 culvert, 39+172kmLHS
05/12/2016 6.59 60 28.1 08 02 ND 790
Surface Water Quality Standard
6-9 - - - 05 0.1 1
Note: The pH ,BOD & oil/greese content at its standard level in all locations
![Page 56: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/56.jpg)
56
Table 2.10 Baseline Noise levels(measured on 21st November 2016)
Road Section Measured locations
Base Line
ENL.dB(A) RBL dB(A)
B 157
Day Night Night Day
Mathugama Town at 31+500 66 66 59 56
Horawala Junction at 36+500km 70 68 59 58
Welipenna Interchange at 42+300km
68 69 50 51
ENL=Existing Noise levels(L Aeq)-dB-(A), RBL-Rating Back Ground Noise level(L A90-15min) Standard Maximum Permissible Noise Levels at Boundaries in LAeq'T.
* Provided that the noise level should not exceed 60 dB (A) inside existing houses, during day time. LAeq', T=the equivalent continuous, A- weighted sound pressure determined over a time interval T(in dB) The project area falls into the medium noise level zone
Areas LAeq', T
Day time Night time
Low Noise 55 45
Medium Noise 63* 50
High Noise 70 60
Silent Zone 50 45
![Page 57: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/57.jpg)
57
Table 2.11 Baseline vibration levels
Road section
Mesured locations Category of
structure Vibration Level PPV(mm/Sec.
Frequency range(Hz)
Predominant frequency)
B 197
Divisional Secretariate, Mathugama at 32+120km
Type 3 0.190-0.232 10-50 10.63-12.13
Primary school-Ovitigala at 34+040 km
Type 3 0.082-0.156 10 12.13-18.38
Child Friendly School in Badugama at 35+985km
Type 3 0.129-0.362 10 11.5-13.25
Rahumania School in Welipenna at 39+320km
Type 3 0.407-0.863 10 17.0-19.5
Primary School in Lewwanduwa at 40+840km
Type 3 0.299-0322 10 49.25-51.75
**Maximum Peak Value in Velocity mode (mm/sec) day time-one hour measurement average, Standreds-02mm/sec(type 03) **According to the measured vibration levels, maximum permissible levels (2.0 or 4.0mm/sec) of interim vibration standards have not been exceeded with the vehicle movements of this road section
![Page 58: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/58.jpg)
58
Table 2.12 Baseline air quality results
Road Section
Mesured Locations Sampling Date TSPM(µg/m3) 3hour average)
B 157
Mathugama Town at 32+100 In Front of DS office
05/12/2016 269
Horawala Junction At 36+763 km RHS
05/12/2016 105
Welipenna Interchange at 42+372km
05/12/2016 41
Note: Maximum permissible level of total suspended particulate matter(TSPM) for three hour average is 450µg/m3. As per the
measured results, all three locations of B157(East) road section, TSPM (03hr)average is lower than the permissible level of 450µg/m3.
![Page 59: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/59.jpg)
59
Appendix: 03 Table 3.1 Observed Environmental Issues of the Contract Package of CP01
Issue Cause
Required Action Responsibility
Timing (Target Dates)
Description of Resolution and Timing (Actual)
Quarry-Neboda
The quarry is a commercial base one owned by out-side party
Crusher Plant
Supplying of materials have been stopped November 2016
Asphalt Plant
1.Tar barrels at open area Supplying of materials have been stopped December 2016
1. Advised to construct a roof for the tar storage area.
Plant Manager & Head Office management
Within one month During September 2016
1Construting of roof is being progressed but it was a sluggish progress. However the roof has been completed within the last quarter of 2016.
Concrete Batch Mixing Plant
Supplying of materials have been stopped December 2016
Borrow sites
Not operated
Contractor's Yard
1.Advised to regular maintains 2. Advise to handing over the collected solid waste to UC, Kesbewa 3. Advise to handed over to owner after proper cleaning of the land
Yard Manager, SO & EO
Within one week from 5th to 11th of September 2016
1.regullar maintaining observed 2.Solid waste management activities are ok 3. The contractor is still operating the yard
1.Labour Camps at Plant site, Naboda
1. the camp is maintained well
1. Dust bins, hygiene facilities, mosquito nets were provided
Plant Manager & EO
1. The said facilities are provided satisfactorily
2.Labour Camps at B389/B285 (two labour camps are under operation for both roads)
1.Sanitary problems 2.Poor labour facilities
1.Advised to improve all the conditions
Project Manager, SO & EO
Within 3 weeks From 29th August to 18th September 2016
1. The existing bad condition was uplifted.
Stock piles Not operated
![Page 60: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/60.jpg)
60
Disposal Yards
Condition is good
Advised to implement of regular maintaining such as keep the ground levelling and avoid water stagnation
Project Manager , EO & SO
Once a week
Regular maintenance observed.
Structure Construction
1. PPEs usage by workers is poor. 2. Traffic management and site safety should be improved
1. Advised to ensure of the PPEs usage by all workers while working and upgrade the site safety and traffic controlling activities especially at Kattiya Junction of B389.
Project Manager , EO & SO Site engineers, supervisors of each section and working sites
Daily rooting
1PPEs usage by workers should be further improved on or before 30th September 2016, while traffic management at the Kattiya Junction of B389 was improved.
EO=Environmental officer, SO Safety Officer
Table 3.2 Observed Environmental Issues of the Contract Package of CP02 Kesbewa-Pokunuwita(B084) and Hoamagama-Godagama(A004)
Issue Cause
Required Action Responsibility
Timing (Target Dates)
Description of Resolution and Timing (Actual)
Quarry- Millaniya
No proper PPE usage
Provide relevant PPE for all workers who engage with quarry activities.
Plant Manager Within week
Crusher Plant-Millaniya
1.Dust emission 2.Water stagnation
Install the water sprinkles and their regular maintenance. Regular levelling of the crusher area
Plant Manager Within one week 20th April 2017
The water sprinkles had been installed and dust emission also controlled well Regular levelling is being progressed
Crusher Plant-Pokunuwita
1.Water stagnation
Advised to regular levelling of the crusher area
Plant Manager Within one week Before 5th April 2017
Area has been levelled and avoid water stagnation
Asphalt Plant-Homagama
1.Plant area managed well
The plan site is well managed
Concrete Batch Mixing Plant-Pokunuwita
1.Water stagnation is observed
Advised to avoid water stagnation within the area
Plant manager Within one week
Area has been levelled and avoid water stagnation
![Page 61: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/61.jpg)
61
Before 5th April 2017
Borrow sites
Not operated
Contractor's Yard
1.Water stagnation was observed in the abandoned materials and vehicle parts
1.Advised to regular maintains
Yard Manager, SO & EO
Within one week 5th April 2017
1.regullar maintaining observed
Stock piles No proper barricades and demarcations applied
1.Advised to erect barricades and demarcating items
Project Manager, SO
Within two days 5th April 2017
Barricades and demarcation applied
Disposal Yards-Temporary disposal sites
Condition is good
Advised to implement of regular maintaining such as keep the ground levelling and avoid water stagnation
Project Manager , EO & SO
Once a week 5th April 2017
Regular maintenance observed.
Structure Construction
1.PPEs usage by sub-contract workers are poor. 2. Inadequate of the sign boards along the road. 3. Demarcation of the construction sites specially culvert locations should be improved further. 4. Danger locations of the road should be identified and install the warning signs(bent locations, road narrows etc.)
1. Advised to ensure of the PPEs usage by all workers while working. (The designated PPEs should be provided to workers such as ear plugs, mask and gum boots while activities concreting, machine operating and compaction going on). 2 & 3.. Advised to install adequate sign boards along the construction sites and culvert locations according to approved Safety Manual. 4. Advised to erect the danger warning sites along the road where necessary.
Project Manager , EO & SO Site engineers, supervisors of each section and working sites
Daily rooting
1. PPEs usage by workers should be further improved on or before 30th April 2017. 2.The sign board installation, maintenance and site demarcating are regularly observed 3. the Site Engineers are advised to install sign bords along the danger locations
![Page 62: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/62.jpg)
62
Table 3.3 Observed Environmental Issues of the Contract Package of CP03 Mathugama-Southern Expressway (B157)
Issue Cause
Required Action Responsibility
Timing (Target Dates)
Description of Resolution and Timing (Actual)
Quarry Quarries are managed by commercial base
Crusher Plant-Daniston estate, Commercial base
1.Oil leakage at backyard of the office premises 2.Dust emission was observed
1.Advised to avoid oil leakage along the pump area and put a collecting span to collect overflowing oil 2.Install the water sprinkles and regular maintenance
Plant Manager Within two weeks 26th April 2017
1. Attended to rectify said issue with cleaning the area. 2.The water sprinkles had been installed and dust emission also controlled well
Asphalt Plant
1.used polythine covers dumped at the open area 2.Oil spill-out at pump area 3.Bitumen leakage at the bitumen pumping area
1. Advised to dispose properly. 2.Advised to ovoid oil overflowing when oil pumping, and construct the concreted trays under the pump area 3. Advised to use trays while bitumen pumping and ground should be concreted to avoid tar mix(infiltration) with soil.
Plant Manager & Head Office management
Within one month 29th March 2017
1. Properly disposed 2. & 3.Taken steps to avoid oil & tar spilling out.
Concrete Batch Mixing Plant(Dry)
1.Wash water of truck mixture should be disposed in proper way
Advised to reuse the dispose water and not to dump into open
Batching Plant Manager
Immediate
A tank is constructed to re-use the waste water of truck mixtures
Borrow sites
1.Updating of licences approvals and material quantity
1.The contractor is advised to submit timely updated licenses and approvals as well as obtained quantities
Project Manager
Immediate
1.The contractor has promised to submit these detail without delay
Contractor's Yard
1. Maintaining of yard is at good level
1.Advised to regular maintains 2. Advise to handing over the collected solid waste to UC, Mathugama
Yard Manager, SO & EO
Within one week 22nd March 2017
1.Regular maintaining observed 2.Solid waste management activities are ok
1.Labour Camps at main yard
1.labour camp and kitchen maintainace area at good level
1. Advised to maintaining 2.Advise to obtain the Labour department approval
Plant Manager & EO
Within two weeks 22nd March
1. Regular maintaining observed 2.Labur dept. approval pending
![Page 63: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/63.jpg)
63
2.No Labour department’s approval
2017
Stock piles 1.Three lands are operated for store ABC, and soil.
1.advised to obtain consent letters from owaners 2.Avoid soil erosion and dust formation from stock piles
Project manager and EO
Daily rooting
1. Regular maintenance observed.
Disposal Yards
1.More than 20 lands have been selected as disposal lands
1.Advised to implement of regular maintaining such as keep the ground levelling and avoid water stagnation in the lands
Project Manager , EO & SO
Once a week
1. Regular maintenance observed.
Structure Construction
1. PPEs usage by workers is at poor level, especially sub-contractors. 2. Traffic management should improve further. Traffic controllers haven’t good awareness about their work. 3. Neatness around the working sites, especially at culverts area.
1. Advised to ensure of the PPEs usage by all workers including sub contractors. 2. Advised to increase the awareness activities (tool box meeting etc) on safety and traffic team. 3. The sites should be free with disposed soil and scattered construction materials
Project Manager , EO & SO Site engineers, supervisors of each section and working sites
Daily rooting
1PPEs usage by workers should be further improved on or before 30th April 2017. 2. Traffic controlling activities should be further improved. 3.Constrution sites neatness should be improved further
![Page 64: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/64.jpg)
64
Appendix: 04(a) Status of EMP* Compliance (Road B 295 & B 389)
(*this EMP is included in the bidding document)
Potential Environmental
Impact Mitigation Action
Indicator or Means of verifications
Complied? Yes/Not
Complied/ Partly
Complied
Explanation if compliance status is partly complied
or not complied
Further actions/Timeline
1. (a) Selection of lands for temporally use 1.(b) Solid waste disposal and sanitation
Selection of lands in accordance with local laws, regulations and in close consultation with LAs All temporary facilities should be established away from the environmental and public sensitive areas
Site visits and observations Weekly checklists Public complains No complain received.
complied The contractor has obtained the approvals for all temporary used lands and has returned the lands with proper levelling.
Disposal lands have been returned to owners with proper levelling
All relevant legal compliances should be obtained prior to the establishment of temporary facilities Minimize health hazards and environmental pollution based on CEA guidelines. Keep the all site free with environmental hazards Selection of disposal site away from public and environment sensitive areas Re-use of debris and residual spoil materials wherever possible under instruction of Engineers & CSC. Provision of proper solid waste disposal, sanitation and sewerage facilities to all sites Dumping of garbage in a hygienic manner under the inspection of PHI in the area Minimize/avoid stagnation of water around worker based camps
Do Complied Debris disposal activities have been managed without problems. Excavated materials were removed into temporary disposal lands along the road and finally disposed into permanent disposal lands (mainly at Suwarapola disposal land). PHI has periodically visited to observe the waste generated areas (labour camps and yards) of the contractor.
Completed successfully
![Page 65: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/65.jpg)
65
Potential Environmental
Impact Mitigation Action
Indicator or Means of verifications
Complied? Yes/Not
Complied/ Partly
Complied
Explanation if compliance status is partly complied
or not complied
Further actions/Timeline
Selection of local un-skilled and skilled workers for the proposed construction activities
The all skilled and unskilled workers have been selected to sites within the area as well as out sides. While female labour has paid same wages for their works.
2. Removal of public utilities
Advance notice to the public about the time and the duration of the utility disruption Recruitment of well trained and experienced machinery operators, technical officers & labours Proper coordination and consent from service providers for the removal of utilities and re-establishment
Number of complain by public & the contractor Monthly field visits Number of remaining Poles of CEB and Telecom Total remaining length of water pipe laying
Complied Water line, CEB & Telecom Poles removing activities are fully completed at both road sections of B 389 and B 295. Considering about the received complains, 3 complaints were from B 295 and 15) complains were received from B 389 Road. The most of complaints about underground telecom cable damaged and these are forwarded to insurance company to process compensation.
Shifting of utilities has been completed.
3. Extraction, transportation and storage of construction materials
Consideration of environmental requirements and guide lines issued by the CEA, GSMB and LAs If new material extraction sites need to be located, they should exclude places which are close to the public and environment sensitive
Site visits and observations Weekly checklists Public complains
Complied Bitumen Barrels were stored at open areas since the project starting time (Instructions were issued to contractor on 28th October 2015). After
The raised problems were solved satisfactorily.
![Page 66: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/66.jpg)
66
Potential Environmental
Impact Mitigation Action
Indicator or Means of verifications
Complied? Yes/Not
Complied/ Partly
Complied
Explanation if compliance status is partly complied
or not complied
Further actions/Timeline
areas Planning of construction activity to ensure that haulage of materials does not take place during night Storage of sand, rubble, mettle bitumen cement in covered areas to ensure protection from dust, emissions Storage of cement, bitumen, oil and other chemicals on an impervious surface above ground level and should be enclosed ensuring that no storm water flows in to the structure. Provision of adequate ventilation should be kept to avoid accumulation of fumes and offensive odour to storage yards.
advising to management of plant, a new roof was constructed and the barrels have been kept under the roof. A drainage path has been constructed and avoid water stagnation inside the plant area
All legal compliances for extraction, transportation and storage of construction materials should be obtained prior to the operation All drivers should follow the speed limits on roads and specific condition given by LAs or relevant authorities in given time and should have license for the category of vehicles they drive Construction materials should not exceed the carrying capacity of the trucks as well as roads when transporting provision should be made for repair and restoration, If public roads get damaged Transport loading and unloading of materials should not cause nuisance to the public Restoration of the material extraction sites
Do Do All legal documents have been obtained by the contractor for material extraction as well as transportations
Completed
![Page 67: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/67.jpg)
67
Potential Environmental
Impact Mitigation Action
Indicator or Means of verifications
Complied? Yes/Not
Complied/ Partly
Complied
Explanation if compliance status is partly complied
or not complied
Further actions/Timeline
once after borrowing.
4. Effect on local road network
provision made for repair and restoration, If project roads(B295 & B 389) get damaged
Public complains Site visits and observations Weekly checklists
Complied The contractor has repaired the project road when it damaged. No complain was received. A provision is available to do this maintenance
Completed
Obtain approvals from LAs to use local road network prior construction Construction materials should not exceed the carrying capacity of the local road network. provision should be made for repair and restoration, If public roads get damaged
Do Do Approvals (Trade licences) have been obtained from the respective Local Authorities to transport materials.
completed
5.(a) Effect on existing canals, water restoration areas and drainage paths
Restoration of water bodies to its original status once after construction Prevent storage of construction materials and disposal of debris around cross drainages. Provision of temporally drainage facilities until requires line or earth drains are provided Replacement of structurally damaged drainage structures
Site visits and observations Weekly checklists Water quality test Public complains
Complied The contractor has attended to provide temporary/permanent drainage facilities, cleaning of existing drainages So far, 10 complain for B 285 and 03 complain for B389 were received regarding the drainage problem. 04 complain of B285 road will be rectified by Kesbewa MC while others are solved.
Completed. Under the project, the existing poor quality drainages and side drainages in entire length of the road are improved.
Obtaining of proper approvals from relevant Do Complied The contractor had been Completed.
![Page 68: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/68.jpg)
68
Potential Environmental
Impact Mitigation Action
Indicator or Means of verifications
Complied? Yes/Not
Complied/ Partly
Complied
Explanation if compliance status is partly complied
or not complied
Further actions/Timeline
5.(b) Effect on water resources
authorities prior to diversion, close or blocking of water sources as well as material storage
instructed to obtain relevant permission.
Storage of toxic and hazardous construction materials away from water bodies Avoid excavation of beds of any irrigation systems or other water bodies Implement additional safety precautions to reduce the water pollution and degradation of water resources due to work
Do Complied The contractor had been advised to store toxic or hazardous away from water sources, avoid excavations close to vulnerable water sources, and avoid water pollution when his work progressing.
Do
Cleaning of upstream and lead-away channels of cross drainages to maintain a smooth water flow. Introduction of catch pits wherever possible to prevent silting of water bodies
Do Do The facilities for smooth water flow and preventing siltation were provided during the construction activities were done
Do
Awareness of employees on water conservation, pollution and minimization of water usage Prevent entering waste- water directly in to water bodies. Maintaining vehicles and equipment in good condition, to prevent leakage of oil or fuel Prevention of disrupting community water sources Restore the water resources due to any pollution or negligence done by contractor
Do Do Awareness of water conservation, prevention of pollution etc were included under the worker awareness programs
Do
6. Soil erosion Placement of erosion control measures to Do Do The contractor was Completed.
![Page 69: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/69.jpg)
69
Potential Environmental
Impact Mitigation Action
Indicator or Means of verifications
Complied? Yes/Not
Complied/ Partly
Complied
Explanation if compliance status is partly complied
or not complied
Further actions/Timeline
sedimentation and siltation
erodible areas. Covering of temporary soil dumps with thick tarpaulin sheets until remove from the site Undertake construction activities in erodible sections during dry season. Limitation of steep cuts and the reduction of slop of cuts Treatment of clearing and filling areas against flow acceleration
advised to implement his construction work during dry period along the water ways. Eg: B295 near the Kospalana Bridge area.
Re use of top soil generated from construction sites for turfing and tree planting activities.
Do Complied
7. Effect on flora, fauna and their habitats
Compensative tree planting activity with participation of project effected people and adjoining communities. Do not promote or introduction of any alien invasive plants to re-planting activity and use only native and endemic species in the area
Field visits and observations Weekly checklists
Complied Compensative tree planting programs were conducted. Due to absence of space along the ROW, vicinity areas were selected to replanting.
Three tree planting programs have been implemented. 1.Police ground and temple premises in B389 2.Ananda Samarakoon School premises 3.Karadiyana waste dumping land(mangrove species)
Awareness of workforce regarding important of fauna, flora and their habitats Display the relevant warning signs along the environmentally sensitive areas Do not use any resources that adjoining into the wildlife (specially demarcated to wildlife)
Do Complied Awareness meeting were conducted. The resource persons, who represented from CEA have participated those activities.
The contractor has conducted the awareness programs as periodical intervals
![Page 70: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/70.jpg)
70
Potential Environmental
Impact Mitigation Action
Indicator or Means of verifications
Complied? Yes/Not
Complied/ Partly
Complied
Explanation if compliance status is partly complied
or not complied
Further actions/Timeline
such as water, feeding grounds, breeding areas and habitats. Providing facilities to wild-life in the area during the environmental hazardous situation
Removal of road side trees adhering to the CEA guidelines and recommendation. Decision on tree removal based on Detailed Engineering Design Marking road side trees subjected to removal and preparation of inventory prior to start clearing. Valuable timber should be properly stacked and handed over to the DoF or rightful owners.
Do Compiled Removal of road side trees are completed
Completed
8. Biodiversity conservation and sustainable natural resource management
Rehabilitation of degraded eco-systems (such as wet land, forest ect.) adjoining into the project area or project effected area with approval of Engineer
Field visits and observations Weekly checklists
Complied It was proposed to conduct some rehabilitation activities along the Bolgoda lake in the B 285 road. But contractor couldn’t conduct these activities due to various reasons
Not completed
![Page 71: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/71.jpg)
71
Potential Environmental
Impact Mitigation Action
Indicator or Means of verifications
Complied? Yes/Not
Complied/ Partly
Complied
Explanation if compliance status is partly complied
or not complied
Further actions/Timeline
Awareness of all stakeholders regarding environmental conservation Displaying signs and warning boards about the importance of the existing fauna and flora of the area Avoid clearing of natural habitats and replacement of natural vegetation for any construction purpose except the proposed road construction. Use of natural resources in sustainable manner Rehabilitation of degraded eco-systems (such as wet land, forest ect.) adjoining into the project area or project effected area Rehabilitation (with approved and proper rehabilitation plan) of all resources extract areas and temporary used lands
Do Complied Some of the activities were implemented parallel with the tree planting campaign. Eg: During the tree planting program was conduting at the school, the awareness program was also conducting to children.
Do
9. Disruption of traffic and public inconvenience
Provide an advance notice to local communities about the schedule of construction activities Installation of traffic warning signs, temporary traffic lights or flagman at the construction sites Implementation of traffic management plans in close coordination with local police and public Schedule movement of large trucks and plant in off-peak traffic times.
Public complains Weekly checklists Site visits and observations
Complied Inadequate traffic controlling and inconvenience to public had been observed along the roads during the site observations. Public complains on house access and business access had been solved.
Monthly payments were reduced due to poor performance of traffic safety controls.
Provision of safe passage/ alternative routes Do Do Provision was provided to Completed.
![Page 72: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/72.jpg)
72
Potential Environmental
Impact Mitigation Action
Indicator or Means of verifications
Complied? Yes/Not
Complied/ Partly
Complied
Explanation if compliance status is partly complied
or not complied
Further actions/Timeline
to the vehicles and passengers make alternative passage or bypass making where necessary
10. Personal health and safety
Proper and regular awareness on health(sexually transmitted, Non-transmitted and vector born diseases ) and hygiene matters during the working period
Site observation Weekly checklists Public complain/worker’s complains
Complied Three programs on HIV/AIDS prevention had been conducted.
Scheduled all programs were completed
Provision of personal protective equipments (PPEs) and clothes to workers, based on their duty
Do Complied PPE usage was observed as weak among the workers.
Reductions of monthly payments were carried out according to the monthly observations made by RDA and the consultant.
Establishment of road engineering aspects and sign boards to reduce accidents
Do Do Temporary signs have been fixed during the construction period while permanent signs were erected/fixed after the road work finished
Completed
Proper briefing and training of workers on safety precautions, and their responsibilities Use of licensed and well trained operators for handling of machinery, equipment and material processing plants Provision of first aid facilities and emergency
Do Do Tool box meetings and awareness meetings were conducted. labour accommodations were provided Explosive materials were
Completed
![Page 73: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/73.jpg)
73
Potential Environmental
Impact Mitigation Action
Indicator or Means of verifications
Complied? Yes/Not
Complied/ Partly
Complied
Explanation if compliance status is partly complied
or not complied
Further actions/Timeline
transport to the nearest hospital Arranging regular safety checks of workers, vehicles and plants Provide proper labour facilities in labour camps, yards and accommodations for full fill their health and safety requirements. Storage of explosive materials in a secure location in a protective way
handled under supervision of nearest Police of the plant site (quarry)
11. Safety of road users
Enforcement of speed limits, traffic rules and regulations Installation of the warning signs, road markings and relevant road furniture Provision of bus bays, pedestrian crossings at the appropriate locations
Site observation Weekly checklists Public complain
Complied The signs boards had been installed throughout the road during the construction period and those were maintained regular manner.
Completed
12. Impact from dust, noise and vibration
Placement of crushers and hot mixed plants away from public and environmental sensitive areas Placement of exhaust silencers and noise reduction devices to the road side crushers, construction vehicles and hot mixed plants
Site observation Weekly checklists Air, Noise and Vibration test Public complain
Complied - -
Periodically checking of air, water, noise and vibration of the project area
Do Being complied
Baseline /construction stage monitoring activities were carried out
Monitoring activities for operation stage to be implemented immediate after the handing over the road.
Storage and transport of construction materials with proper covering, provision of
Do Complied The contractor has followed the guidelines
Actions have been followed
![Page 74: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/74.jpg)
74
Potential Environmental
Impact Mitigation Action
Indicator or Means of verifications
Complied? Yes/Not
Complied/ Partly
Complied
Explanation if compliance status is partly complied
or not complied
Further actions/Timeline
dust barriers, spraying of water and control of vehicular speed to minimize dust emission
that given to control the storage and transportation of materials.
throughout the project period
Implementation of National Emission Standards and Noise Control Regulations of CEA for project activities Implementing an effective work plan to reduce dust, noise and vibration due to construction work Regular maintenance of machinery, equipment and vehicles in a good condition Prevent bad odour and offensive smell emanating from chemicals, material processing or other construction activities Arrangement of construction activities closer to public sensitive locations coordination with the relevant authorities
Do Complied CEA approvals have been obtained.
completed
Operation stage
13. Air quality It is expected to reduce existing dust after surfacing of the roads. Proper alignment and surfacing of the road will help to reduce the vehicular emissions. Checking of differentiation of environmental parameters
Site observation Weekly checklists Public complain Air quality test
Being Complied to
The contractor has taken step to monitor the air quality. The quotation are invited and finalized
Immediate after the road handing over to the Employer
14. Drainage Congestions and maintainace of road
Regular maintenance of drainage system as well as road surface Regular maintenance of road furniture that already installed and providing an adequate requirements Avoid dumping garbage and other spoil
Site observation Weekly checklists Public complain Air quality test
Being complied to
Performance based maintainace work will be implemented.
After the road handing over to the Employer
![Page 75: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/75.jpg)
75
Potential Environmental
Impact Mitigation Action
Indicator or Means of verifications
Complied? Yes/Not
Complied/ Partly
Complied
Explanation if compliance status is partly complied
or not complied
Further actions/Timeline
material
GSMB=Geological Survey & Mining Bureau, CEB=Ceylon Electricity Board, LAs=Local Authorities, CSC=Construction supervision consultant, CEA=Central environmental Authority,
![Page 76: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/76.jpg)
76
Appendix: 04(b) Status of EMP* Compliance (Kesbewa-Pokunuwita (B084) Road)
(*this EMP is included in the bidding document)
Potential Environmental
Impact Mitigation Action
Indicator or Means of verifications
Complied? Yes/Not
Complied/ Partly
Complied
Explanation if compliance status is partly complied
or not complied
Further actions/Timeline
A. Pre construction and Construction stage
1. Removal
of public utilities
As part of the pre-construction activities, initially consultation and consent
should be taken from relevant service
providers (CEB / NWSDB / SLT) if sections
of utility lines needs to be shifted due
to design requirements or shift in alignment Obtain permission from DoI for any
proposed construction works on irrigation
canals Use of well trained and experienced
machinery operators to reduce accidental
damage to the public utilities Advance notice to be served to the affected
public about the time and the duration of
the utility disruption Substitute sources of water and other
utilities during the disruption period, and
restoration of the public utilities as soon as
possible.
Site observation Weekly checklists Public complains
Being complied to
Water lines, CEB & Telecom Poles shifting activities are being progressed. During the reporting period 1% of CEB poles and 17% Telecom poles have been shifted. Considering about the received 31 complaints, 15 complaints are solved, 3 are progressing while 13 complaints are pending about decisions.
Utility shifting activities are monitored by monthly progress meetings. The relocating activities should be expedite
2. Removal
of road side
Mark all road side trees subjected to potential felling and preparation of inventory
prior to start clearing.
Site observation Weekly checklists
Being complied to
Clearing activities are at near completion along the
![Page 77: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/77.jpg)
77
Potential Environmental
Impact Mitigation Action
Indicator or Means of verifications
Complied? Yes/Not
Complied/ Partly
Complied
Explanation if compliance status is partly complied
or not complied
Further actions/Timeline
trees Decision on tree removal should be based on
detailed engineering design. Maximum effort towards avoiding removal
of religious, cultural and aesthetic important
trees through joint field verifications and
decision taking.
Obtain permission in writing from DoF
regarding removal of trees and seek
compensatory modalities and plan for
afforestation programmes. Compensatory plantation program
at twice the number to be felled and its
cost estimation in consultation with DoF. To avoid further tree losses, the contractor
should ensure that the temporary use of land
for construction related activities will be
established w i t h o u t a n y a d d i t i o n a l
tree cutting.
handed over section (Sec.1).
3. Temporary use of lands
Construction facilities should be established at least 500 m away from water bodies, natural flow paths, important ecological habitats and residential areas. Selection of site for these facilities by
adhering to stipulated local laws and
regulations and in close consultation with
Site observation Weekly checklists
Being complied to
The contractor is using temporary stock pile yard at 16+500km and disposal land at 17+500km. The contractor’s machinery yard is also situated at 21+700km as a temporary
Monthly site visits
![Page 78: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/78.jpg)
78
Potential Environmental
Impact Mitigation Action
Indicator or Means of verifications
Complied? Yes/Not
Complied/ Partly
Complied
Explanation if compliance status is partly complied
or not complied
Further actions/Timeline
LAs. Pay compensation / rent for using the
site and get an official permit from the
agencies if any public utilities will be used
for its facilities. In establishing these facilities, the contractor
should minimize removal of trees and other
green cover vegetation to the extent possible.
basis. The contractor has obtained the consent letters from owners and has taken necessary actions regarding the environmental protection.
4.Land acquisition
and Resettlement
Compensation prior to acquisition of
property as per the RAP policy and
restoration of livelihood.
Work done records Site observations Public complain
To be complied
Land acquisition activities have almost been finished in section 01, 03 and 04, while some activities are being progressed in other sections.
5. Solid waste disposal and
sanitation
Designing and Provision of solid waste
collection, storage, disposal, sanitation and
sewage facilities at all sites for the
onstruction/labor camps, and other
construction sites. Handling and management of waste
generated from the construction/labor
camps without contaminating the
surrounding environment and not posing
any threat to the public/communities living
in and around the sites. Provide adequate facilities to manage its
wastes in consultation with CEA and PHI
Site observation Weekly checklists Public complains
To be complied
Waste collecting facilities have been provided(garbage bins) The contractor has built linkage between Municipal councils in the area to give collected solid waste from their office, yard and the labour camps in regular basis.
![Page 79: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/79.jpg)
79
Potential Environmental
Impact Mitigation Action
Indicator or Means of verifications
Complied? Yes/Not
Complied/ Partly
Complied
Explanation if compliance status is partly complied
or not complied
Further actions/Timeline
of the area. Proper drainage facilities should be designed
and developed in the workers base camp
sites to minimize stagnation of wastewater. Solid waste should not be burnt but
emphasis to be laid for their recycling,
composting and sanitary land filling.
Adequate supply of hygienic water should be provided to the urinals, toilets and wash rooms of the worker camps. Garbage bins should be provided to all
workers’ camps and construction sites, and
needs regular clearing and appropriate
disposal and if needed to be treated with
disinfectants.
6. Top soil Conservation and Disposal
of debris
The fertile top soil to a depth of 20 - 30 cm should scoop out and preserved in
a manner so that the stack is not washed
away during rainy days. The top soil
can be utilized in the future for turfing
purpose, enhancing soil quality of degraded
land patches, plantation purposes etc. All debris and residual spoil materials
including any left out earthen material
should be disposed off only at locations
approved by the relevant LAs. Spoil materials (soil, sand, rock etc,)
Site visits & observations Weekly checklist Public complains
Being complied
Approved disposal sites have been operated. The temporary disposal lands also being operated. Road side excavated materials are stock piled by contractor for future usage (at 16+500km RHS).
Sites visit/checklist updating is being conducted regular basis.
![Page 80: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/80.jpg)
80
Potential Environmental
Impact Mitigation Action
Indicator or Means of verifications
Complied? Yes/Not
Complied/ Partly
Complied
Explanation if compliance status is partly complied
or not complied
Further actions/Timeline
generated during the construction activities
should be utilised wherever found
suitable for activities like site levelling, back-
filling etc with prior approval of CSC. Suitable dumping grounds/ land fill sites
should be identified for the disposal of
surplus
excavated/surplus/discarded/demolished
materials of existing structures. The debris and spoil should be disposed in
such a manner that;
• Does not block the waterways and
drainage paths
• The disposed materials should not be
washed away by runoff
• Debris should not be disposed into
any agriculture lands, marshlands, down
slopes or any environmental sensitive
areas
• Avoid/ Minimize annoyance to general public and road users.
7. Extraction of construction materials
Suitable quarry sites and borrow areas
s h o u l d be identified at the initial stage
of the project. Utilizing the existing mines and quarry
sites available in the project influential areas,
which are approved by GSMB or LAs,
operating with EPL and IML
Site visits & observations Weekly checklist Public complains
Being complied
The contractor has obtained the materials from approved sources and submitted their approvals to the client. The periodic site visits conduct to observe the site
Sites visit/checklist updating is being conducted regular basis.
![Page 81: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/81.jpg)
81
Potential Environmental
Impact Mitigation Action
Indicator or Means of verifications
Complied? Yes/Not
Complied/ Partly
Complied
Explanation if compliance status is partly complied
or not complied
Further actions/Timeline
If new quarries and sand mines are to be
opened, prior approval should be obtained
from GSMB, CEA and LAs. Project’s quarries should not be located in
any environmentally sensitive areas, in
vicinity to archeological and cultural sites,
religious places, schools and settlements. Quarries and borrow areas should meet
aesthetic demands and have rehabilitation
plans designed and implemented. Use of alternative source for the river
sand such as screened crusher fines or sea
sand. Restoration of the borrow pits by contractor
or relevant authorities once after borrowing. Use of insecticides/disinfectants in the
camp sites/plant sites and waste collection
areas to discourage Vector breeding.
hygiene matters as well as house-keeping activities.
8. Transportation
and storage of construction
materials
Trucks carrying construction materials
should not be overloaded and covered with
tarpaulins to reduce fines getting airborne. Avoid storage of construction materials
beside the road, around water bodies,
residential or public sensitive locations.
Site visits & observations Weekly checklist Public complains
Being complied
Contractor use tar-poling covers to close the material when transporting while the vehicle conditions and loads are being observed by client and consultant in regular basis.
Sites visits and checklist updating are being conducted regular basis.
![Page 82: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/82.jpg)
82
Potential Environmental
Impact Mitigation Action
Indicator or Means of verifications
Complied? Yes/Not
Complied/ Partly
Complied
Explanation if compliance status is partly complied
or not complied
Further actions/Timeline
Materials loading and unloading should not
cause nuisance to the people by way of
noise, vibration and dust emission. Sand, rubble, metal, bitumen, cement etc
should be stored in designated areas to
ensure optimum utilization preferably on a
solid platform. Such materials should be
handled in environment friendly and
nuisance free manner.
9.Effect on local road network
Permit from LAs to use local roads prior to
using the roads for transportation of
construction materials, machinery and
equipment etc. The contractor should- ensure that
transportation of construction materials by
suppliers should not exceed the carrying
capacity of the local roads. Regular Maintenance of local roads and their
restoration which are used for hauling
activities for the construction related
activities.
Site visits & observations Weekly checklist Public complains
Being complied
The contractor is advised to get permission from relevant authorities when he using the other roads except the project road The contractor has obligated to repair the roads while using them for their activities.
Consider about the complains from the public and line authorities/agenesis
10. Soil erosion and surface runoff
Implement erosion control measures such as
fiber mats, gabions walls, rip raps and deep-
rooted grasses etc to erodible areas Seeding with a fast growing native species
and seed mix immediately after fill
placement to develop green cover to protect
Site visits & observations Weekly checklist
Being complied
The contractor is advised to take relevant actions against the soil erosion and surface runoff their construction sites as well as filling areas/materials excavation areas.
Regular site visits and checklist are being implemented
![Page 83: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/83.jpg)
83
Potential Environmental
Impact Mitigation Action
Indicator or Means of verifications
Complied? Yes/Not
Complied/ Partly
Complied
Explanation if compliance status is partly complied
or not complied
Further actions/Timeline
the earth works. Construction in erosion and flood- prone
areas should be restricted to the dry
season (excluding December – February) Stabilization of embankment slopes and road
cuts by re-vegetation and take up a turfing
work as soon as possible before rains.
Treat clearing and filling areas against flow
acceleration and construction work should
be carefully designed to minimize
obstruction or destruction to natural
drainage.
11. Effect on existing drainage pattern
Contractor should avoid storage of
construction materials and disposal of
debris around irrigation canals, cross
drainage and natural flow paths. Culverts and all other drainage paths have to
be appropriately designed by allowing
sheath flow and without any blockages. Provide temporary diverting drainage
facilities to construction sites while
repairing and replacement of obstructed
drains and structurally damaged culverts/
bridges.
Site visits & observations Weekly checklist
Being complied
The contractor has taken steps to avoid unnecessary impact to existing drainage system, further he has found the approved stock piles away from water paths as well as agrarian activities.
Regular site visits and checklist
12. Protection of Avoid tapping water from sources in Site visits & observations Being The contractor has been Regular site visits
![Page 84: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/84.jpg)
84
Potential Environmental
Impact Mitigation Action
Indicator or Means of verifications
Complied? Yes/Not
Complied/ Partly
Complied
Explanation if compliance status is partly complied
or not complied
Further actions/Timeline
water resources residential areas being used by the local
community. Contractor should not obstruct or prevent
flowing of water when working closer to
water bodies. Construction works affecting the streams and
irrigation canals have to be undertaken
during the dry season with prior permission
from the concerned Department. Minimize excavation of beds of any streams,
irrigation systems, and other water
resources so that water flow in the beds is
unaltered.
Use of silt traps and erosion control
measures where the construction is carried
out in close proximity to the water bodies to
avoid entering of cement, sand and other
particulate matters which cause turbidity
and increase sedimentations. Storage of construction materials which are toxic, hazardous and containing other fine particles would be sited at least 500 from water bodies to avoid its contamination to water resources. Trenches around the storage area to confine the flow outs .
Weekly checklist Public complains
complied advised to minimize any impact will course due to his activities. Stock piles are situated away from water sources. The contractor obtain water for his purposes mainly from main water supply(WSDB) and own dug wells in their premises(at Main Yard).
and checklist
13. Affect on flora and
fauna
Approval from DoF should be
obtained prior to start of project activities Site visits & observations Weekly checklist
Being complied
The all trees to be cut within the ROW are clearly marked by Survey
Site visits and progress meeting
![Page 85: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/85.jpg)
85
Potential Environmental
Impact Mitigation Action
Indicator or Means of verifications
Complied? Yes/Not
Complied/ Partly
Complied
Explanation if compliance status is partly complied
or not complied
Further actions/Timeline
towards felling of trees and planning
towards carrying out compensatory
afforestation.
Contractor will prevent his work force
from gathering fire wood from surrounding
habitats, disturbing to the flora, fauna
including hunting of animal and fishing in
water bodies All construction materials extraction sites,
material processing plants, storage yards
and construction vehicle service stations
will be located away from the water bodies,
environmental sensitive locations Proper awareness programs to be conducted
regarding conservation of flora, fauna
including ground vegetation to all drivers,
operators and other workers
prior to construction started. The all possible trees will be protected within ROW and re-planting program will be carried out. The contractor is maintaining a plant nursery in order to carry out the tree planting period. Provisions are provided to conduct the Environmental awareness.
14.
Disruption of
traffic
Provide and publicize advance notices to local communities about the
schedule of construction activities. Installation of traffic waning signs, signaling
system, flagman at the construction sites. Provide safe and convenient passage to
vehicles, passengers and livestock from the
approaching roads.
Site visits & observations Weekly checklist
Being complied
The contractor has submitted traffic safety plan for the project. Accordingly the contractor obligated to install relevant signs along the road Smooth traffic flow is compulsory to maintained
Monthly progress meetings and checklists
![Page 86: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/86.jpg)
86
Potential Environmental
Impact Mitigation Action
Indicator or Means of verifications
Complied? Yes/Not
Complied/ Partly
Complied
Explanation if compliance status is partly complied
or not complied
Further actions/Timeline
Traffic and safety management plan should
be implemented in close coordination with
local communities/authorities and police
department during the entire construction
period. Contractors to plan and implement diversion
roads for sensitive locations with prior
approval of the Supervision Consultant.
by the contractor throughout the project period
15. Air quality Contractors should place crushers and hot mix plants at least 500 m away
from residential areas or other social
infrastructures (school, hospital/religious
places etc)
Such establishments should strictly comply
to National Emission Standards for all
construction vehicles, equipment and
material processing plants Dust extraction/suppression systems should
be fitted to crusher units, construction
vehicles and hot mix plants
Site visits & observations Weekly checklist
Being complied
The periodical checking of air quality has been carried out (under the project’s EMP) and the contractor obligated with national emission standard that stipulated when EPL issuance for their plant operations Dust controlling activities such as sprinklers, dust barriers are installed in the crusher units/hot mix plants (at Kumbuka 26+320RHS)
Monthly progress meetings and checklists
16. Noise and vibration
Strictly implement noise control regulations
for all construction vehicles and equipments. Contractors should equip their heavy
construction equipment with acoustic
Site visits & observations Weekly checklist
Being complied
The periodical checking of noise and vibration levels have been carried out (under the project’s EMP) and the contractor
Monthly progress meetings and checklists
![Page 87: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/87.jpg)
87
Potential Environmental
Impact Mitigation Action
Indicator or Means of verifications
Complied? Yes/Not
Complied/ Partly
Complied
Explanation if compliance status is partly complied
or not complied
Further actions/Timeline
enclosures/ silencers to limit the
construction equipment not to generate
noise exceeding 75 db (compacters, loaders,
vibrators, cranes, diesel generator sets) Limit working time for activities that
create noise only between 6.00 am to 6.00
pm except for construction site near
schools, offices, religious places.
Contractors should schedule their activities
at sensitive locations in consultation with the
relevant authorities (school’s principals,
high-priest etc.) Regularly maintain all construction vehicles
and machinery to meet the National
Emission Standards.
obligated with national emission standard that stipulated when EPL issuance for their plant operations/yard operations and machineries a
17. Personal safety and health
Organize awareness programs regarding personal safety of workers and
general public during construction period. Establishment of safety provisions to
reduce the likelihood of accidents by
placing warning signs, speed limit
markings, speed breakers and signals to
particular locations. Providing appropriate PPEs such as
protective footwear, helmets, goggles, eye-
shields and clothes to the workers
Site visits & observations Weekly checklist
Being complied
The contractor is being implemented tool box meeting/awareness campaigns periodically. Safety provisions are provided to caring out the PPEs and the Traffic safety activities. The contractor has submitted a schedule about the HIV/AIDS awareness program that to
Monthly progress meetings and checklists Attending to awareness and tool box meetings
![Page 88: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/88.jpg)
88
Potential Environmental
Impact Mitigation Action
Indicator or Means of verifications
Complied? Yes/Not
Complied/ Partly
Complied
Explanation if compliance status is partly complied
or not complied
Further actions/Timeline
depending on their activities (Mixing asphalt,
blasting, handling equipments etc) and
motivating the workforce for their usage. Establishing first aid facilities and
Ambulance facilities at active working sites
to meet emergency situations. Use experienced and well trained workers
for the handling of machinery, equipment
and material processing plants. Contractor should implement STD/
HIV/AIDS awareness programs for general
public in and around project
implementation area and workers to reduce
the risk of spreading STD among them.
be conducted by him.
18. Bridge construction
Design of bridges should comply with the requirements of “Bridge
Design Manual” of RDA. Contractor should provide safe and
convenient passage or alternative access to
road users for the entire construction period
seeking approval from the Supervision
consultant. Smooth traffic flow to be ensured
during the entire construction period with
the provision of appropriate safety
measures. During piling activities, the Bentonite slurry
generated will be collected and air dried.
Site visits & observations Weekly checklist
Being complied
The contractor has taken step to implement bridge construction activities according to the approved methodology with minimum environmental damage to the nearby or vicinity areas. The consultant and the client will keenly observed their activities and guiding when he needs to dispose the slurry into open.
Monthly progress meetings and checklists
![Page 89: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/89.jpg)
89
Potential Environmental
Impact Mitigation Action
Indicator or Means of verifications
Complied? Yes/Not
Complied/ Partly
Complied
Explanation if compliance status is partly complied
or not complied
Further actions/Timeline
Then it should be disposed in disposal
yards. In no case the slurry will be
discharged to the water bodies and
agricultural land etc.
19. Access to Public utilities
Access to new public utilities should be
clearly marked within the road reservation in
consultation with the concerned
departments.
Site visits & observations Weekly checklist
Being complied
The contractor has completed the access survey to ensure the neediness of the new access along the ROW. The provisions provided to make better accesses to public parallel to road development.
Monthly progress meetings and checklists
B. Operation stage
20. Encroachment of the RoW
Routine checking to discourage
encroachments and removal of unauthorized
s t r u c t u r e s f ro m RoW in consultation
with Police Department. Popularizing and Implementation of rules
and regulations with respect to RoW and
to avoid encroachment from the RoW.
Site visits & observations To Be complied
During the performance based management, the contractor, the Executive Engineer and the PMU staff will conducting routing visits to see any encroachments along the road
Monthly progress meetings
21. Clearing of Cross Drainage Structures
Periodical clearing of Cross drains and
side drains (specially before commencing of
rainy season) to facilitate easy
discharge of
Site visits & observations To Be complied
Do Monthly progress meetings
22. Road safety Enforcement of the speed limits, traffic rules and regulations to the sensitive
locations, Installation of the warning signs,
marking of center line, pedestrian crossings,
Site visits & observations To Be complied
Do Monthly progress meetings
![Page 90: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/90.jpg)
90
Potential Environmental
Impact Mitigation Action
Indicator or Means of verifications
Complied? Yes/Not
Complied/ Partly
Complied
Explanation if compliance status is partly complied
or not complied
Further actions/Timeline
bus halts and other utilities.
23. Road
maintenance
Developing and Implementation of Periodical maintenance program.
Site visits & observations To Be complied
Do Monthly progress meetings
![Page 91: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/91.jpg)
91
Appendix: 04(c) Status of EMP* Compliance (Mathugama-Southern Expressway (B157) Road)
(*this EMP is included in the bidding document)
Potential Environmental
Impact Mitigation Action
Indicator or Means of verifications
Complied? Yes/Not
Complied/ Partly
Complied
Explanation if compliance status is partly complied
or not complied
Further actions/Timeline
A. Pre construction and Construction stage
1. Removal of public utilities
As part of the pre-construction activities, initially consultation and consent
should be taken from relevant service
providers (CEB / NWSDB / SLT) if sections
of utility lines needs to be shifted due
to design requirements or shift in alignment Obtain permission from DoI for any
proposed construction works on irrigation
canals Use of well trained and experienced
machinery operators to reduce accidental
damage to the public utilities Advance notice to be served to the affected
public about the time and the duration of
the utility disruption Substitute sources of water and other
utilities during the disruption period, and
restoration of the public utilities as soon as
possible.
Site observations Monthly Progress meetings Public complaints
Being complied to
Water lines, Telecom and Electricity poles are being removed. During the reporting period, 28% of Electricity Poles, 42% of Telecom poles were shifted. No any complaints received so far.
2. Removal
of road side
trees
Mark all road side trees subjected to potential felling and preparation of inventory
prior to start clearing.
Site observations Weekly checklists
Being complied to
Removal of road side trees is completed in section 01 and the activity has
![Page 92: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/92.jpg)
92
Potential Environmental
Impact Mitigation Action
Indicator or Means of verifications
Complied? Yes/Not
Complied/ Partly
Complied
Explanation if compliance status is partly complied
or not complied
Further actions/Timeline
Decision on tree removal should be based on
detailed engineering design. Maximum effort towards avoiding removal
of religious, cultural and aesthetic important
trees through joint field verifications and
decision taking.
Obtain permission in writing from DoF
regarding removal of trees and seek
compensatory modalities and plan for
afforestation programmes.
Compensatory plantation program
at twice the number to be felled and its
cost estimation in consultation with DoF. To avoid further tree losses, the contractor
should ensure that the temporary use of land
for construction related activities will be
established without any additional tree
cutting.
already begun in sections 02.
3. Temporary
use of lands
Construction facilities should be established at least 500 m away from
water bodies, natural flow paths,
important ecological habitats and residential
areas. Selection of site for these facilities by
adhering to stipulated local laws and
regulations and in close consultation with
LAs.
Site observations Weekly checklists Public complaints
Being complied to
The contractor uses temporary lands for his main yard at 40+010 km, stock pile at 41+280(ABC), 37+920(soil), and 36+840(soil). The permission has been obtained and rental is paid. The existing trees have
Monthly site visits
![Page 93: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/93.jpg)
93
Potential Environmental
Impact Mitigation Action
Indicator or Means of verifications
Complied? Yes/Not
Complied/ Partly
Complied
Explanation if compliance status is partly complied
or not complied
Further actions/Timeline
Pay compensation / rent for using the
site and get an official permit from the
agencies if any public utilities will be used
for its facilities. In establishing these facilities, the contractor
should minimize removal of trees and other
green cover vegetation to the extent possible.
been saved within the yard during its construction.
4.Land acquisition and Resettlement
Compensation prior to acquisition of
property as per the R& R policy and
restoration of livelihood.
Site observations Public complaints
Being complied to
Land acquisition activities have been completed in section 01 and it is being progressed in section 02.
5. Solid waste
disposal and sanitation
Designing and Provision of solid waste
collection, storage, disposal, sanitation and
sewage facilities at all sites for the
construction/labour camps, and other
construction sites. Handling and management of waste
generated from the construction/labor
camps without contaminating the
surrounding environment and not posing
any threat to the public/communities living
in and around the sites. Provide adequate facilities to manage its
wa stes in consul tat ion with CEA and
PHI of the area. Proper drainage facilities should be designed
Site observations Weekly checklist Public complaints
Being complied to
Waste collecting facilities have been provided to labour camps, yards and office. Solid Waste materials are weekly handed over to waste collecting vehicles of MC in Mathugama. Adequate toilets and wash room facilities are at the labour camps. Waste water discharging facilities have been established.
![Page 94: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/94.jpg)
94
Potential Environmental
Impact Mitigation Action
Indicator or Means of verifications
Complied? Yes/Not
Complied/ Partly
Complied
Explanation if compliance status is partly complied
or not complied
Further actions/Timeline
and developed in the workers base camp
sites to minimize stagnation of wastewater. Solid waste should not be burnt but
emphasis to be laid for their recycling,
composting and sanitary land filling.
Adequate supply of hygienic water should be provided to the urinals, toilets and wash rooms of the worker camps. Garbage bins should be provided to all
workers’ camps and construction sites, and
needs regular clearing and appropriate
disposal and if needed to be treated with
disinfectants.
6. Top soil Conservation and Disposal
of debris
The fertile top soil to a depth of 20 - 30 cm should scoop out and preserved in
a manner so that the stack is not washed
away during rainy days. The top soil
can be utilized in the future for turfing
purpose, enhancing soil quality of degraded
land patches, plantation purposes etc. All debris and residual spoil materials
including any left out earthen material
should be disposed off only at locations
approved by the relevant LAs. Spoil materials (soil, sand, rock etc,)
generated during the construction activities
should be utilised wherever found
Site observations Check lists Public complaints
Being complied to
Approved ....disposal sites are being operated and those Levelling activities are also being progressed.
![Page 95: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/95.jpg)
95
Potential Environmental
Impact Mitigation Action
Indicator or Means of verifications
Complied? Yes/Not
Complied/ Partly
Complied
Explanation if compliance status is partly complied
or not complied
Further actions/Timeline
suitable for activities like site leveling, back-
filling etc with prior approval of CSC. Suitable dumping grounds/ land fill sites
should be identified for the disposal of
surplus
excavated/surplus/discarded/demolis hed
materials of existing structures. The debris and spoil should be disposed in
such a manner that;
• Does not block the waterways and
drainage paths
• The disposed materials should not be
washed away by runoff
• Debris should not be disposed into
any agriculture lands, marshlands, down
slopes or any environmental sensitive
areas
• Avoid/ Minimize annoyance to general public and road users
7. Extraction of construction materials
Suitable quarry sites and borrow areas
should be identified at the initial stage of
the project. Utilizing the existing mines and quarry
sites available in the project influential areas,
which are approved by GSMB or LAs,
operating with EPL and IML If new quarries and sand mines are to be
Site observations Check lists Public complaints
Being complied to
The contractor is allowed only to sourcing materials from approved sites The contractor has submitted their permits and licenses about material extortion sites The monthly visits
![Page 96: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/96.jpg)
96
Potential Environmental
Impact Mitigation Action
Indicator or Means of verifications
Complied? Yes/Not
Complied/ Partly
Complied
Explanation if compliance status is partly complied
or not complied
Further actions/Timeline
opened, prior approval should be obtained
from GSMB, CEA and LAs. Project’s quarries should not be located in
any environmentally sensitive areas, in
vicinity to archeological and cultural sites,
religious places, schools and settlements. Quarries and borrow areas should meet
aesthetic demands and have rehabilitation
plans designed and implemented. Use of alternative source for the river
sand such as screened crusher fines or sea
sand. Restoration of the borrow pits by contractor
or relevant authorities once after borrowing. Use of insecticides/disinfectants in the
camp sites/plant sites and waste collection
areas to discourage Vector breeding.
conduct to observe the sites. During the visits, environmental protection activities, hygiene matters, waste disposal and related activities are observed.
8. Transportation
and storage of construction
materials
Trucks carrying construction materials
should not be overloaded and covered with
tarpaulins to reduce fines getting airborne. Avoid storage of construction materials
beside the road, around water bodies,
residential or public sensitive locations. Materials loading and unloading should not
cause nuisance to the people by way of
Site observations Check lists Public complaints
Being complied to
The contractor is advised to cover the materials when it transport to the sites, handling and its storage. When monthly site visits conducting, these activities are observed.
![Page 97: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/97.jpg)
97
Potential Environmental
Impact Mitigation Action
Indicator or Means of verifications
Complied? Yes/Not
Complied/ Partly
Complied
Explanation if compliance status is partly complied
or not complied
Further actions/Timeline
noise, vibration and dust emission. Sand, rubble, metal, bitumen, cement etc
should be stored in designated areas to
ensure optimum utilization preferably on a
solid platform. Such materials should be
handled in environment friendly and
nuisance free manner.
9.Effect on local road network
Permit from LAs to use local roads prior to
using the roads for transportation of
construction materials, machinery and
equipment etc. The contractor should- ensure that
transportation of construction materials by
suppliers should not exceed the carrying
capacity of the local roads. Regular Maintenance of local roads and their
restoration which are used for hauling
activities for the construction related
activities.
Site observations Check lists Public complaints
Being complied to
The contractor has been advised to get permissions from relevant authorities prior to use local roads for his activities mainly for material transports. If the roads get damaged due to contractor’s activities, he is obligated to repair it immediately.
10. Soil erosion and surface runoff
Implement erosion control measures such as
fiber mats, gabions walls, rip raps and deep-
rooted grasses etc to erodible areas Seeding with a fast growing native species
and seed mix immediately after fill
placement to develop green cover to protect
the earth works.
Site observations Check lists Public complaints
Being complied to
According to the EMP, the contractor is advised to take all possible remedial actions against the soil erosion takes places such as structure construction areas, material sourcing areas, and road excavation areas.
![Page 98: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/98.jpg)
98
Potential Environmental
Impact Mitigation Action
Indicator or Means of verifications
Complied? Yes/Not
Complied/ Partly
Complied
Explanation if compliance status is partly complied
or not complied
Further actions/Timeline
Construction in erosion and flood- prone
areas should be restricted to the dry
season (excluding December
– February) Stabilization of embankment slopes and road
cuts by re-vegetation and take up a turfing
work as soon as possible before rains. Treat clearing and filling areas against flow
acceleration and construction work should
be carefully designed to minimize
obstruction or destruction to natural
drainage.
11. Effect on existing drainage pattern
Contractor should avoid storage of
construction materials and disposal of
debris around irrigation canals, cross
drainage and natural flow paths. Culverts and all other drainage paths have to
be appropriately designed by allowing
sheath flow and without any blockages. Provide temporary diverting drainage
facilities to construction sites while
repairing and replacement of obstructed
drains and structurally damaged culverts/
bridges.
Site observations Check lists Public complaints
Being complied to
The contractor has taken steps to avoid blockage, make temporary diverts, and cleaning existing drainage periodically.
Regular site visits and checklist
12. Protection of water resources
Avoid tapping water from sources in
residential areas being used by the local
community.
Site observations Check lists Public complaints
Being complied to
The contractor is advised to avoid unnecessary obstructs due to his works
![Page 99: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/99.jpg)
99
Potential Environmental
Impact Mitigation Action
Indicator or Means of verifications
Complied? Yes/Not
Complied/ Partly
Complied
Explanation if compliance status is partly complied
or not complied
Further actions/Timeline
Contractor should not obstruct or prevent
flowing of water when working closer to
water bodies. Construction works affecting the streams and
irrigation canals have to be undertaken
during the dry season with prior permission
from the concerned Department. Minimize excavation of beds of any streams,
irrigation systems, and other water
resources so that water flow in the beds is
unaltered.
Use of silt traps and erosion control
measures where the construction is carried
out in close proximity to the water bodies to
avoid entering of cement, sand and other
particulate matters which cause turbidity
and increase sedimentations. Storage of construction materials which are toxic, hazardous and containing other fine particles would be sited at least 500 from water bodies to avoid its contamination to water resources. Trenches around the storage area to confine the flow outs.
to nearby water sources. The contractor has taken steps to minimize the effects from their bridge construction sites. Silt traps are located at yard, and crusher plant Stock piles are situated away from the water sources.
13. Affect
on flora and
fauna
Approval from DoF should be
obtained prior to start of project activities
towards felling of trees and planning
towards carrying out compensatory
Site observations Check lists Public complaints
Being complied to
All the trees that to be removed within the ROW are clearly marked by Survey prior to construction started.
![Page 100: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/100.jpg)
100
Potential Environmental
Impact Mitigation Action
Indicator or Means of verifications
Complied? Yes/Not
Complied/ Partly
Complied
Explanation if compliance status is partly complied
or not complied
Further actions/Timeline
afforestation.
Contractor will prevent his work force
from gathering fire wood from surrounding
habitats, disturbing tothe flora, fauna
including hunting of animal and fishing in
water bodies All construction materials extraction sites,
material processing plants, storage yards
and construction vehicle service stations
will be located away from the water bodies,
environmental sensitive locations Proper awareness programs to be conducted
regarding conservation of flora, fauna
including ground vegetation to all drivers,
operators and other workers
The trees that possible to save within ROW will be protected. A re-planting program will be carried out as a compensation to cut trees. More than 500 plants will be planted along the road Provisions are provided to conduct the Environmental awareness and the contractor has advised to carry out the programm
14.
Disruption of traffic
Provide and publicize advance notices to local communities about the
schedule of construction activities. Installation of traffic waning signs, signaling
system, flagman at the construction sites. Provide safe and convenient passage to
vehicles, passengers and livestock from the
approaching roads. Traffic and safety management plan should
be implemented in close coordination with
local communities/authorities and police
Site observations Check lists Public complaints
Being complied to
The contractor has submitted the traffic control plan and it is approved. The traffic safety plan is implemented and site safety /traffic safety activities are smoothly functioning.
Monthly observations parallel to monthly meeting
![Page 101: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/101.jpg)
101
Potential Environmental
Impact Mitigation Action
Indicator or Means of verifications
Complied? Yes/Not
Complied/ Partly
Complied
Explanation if compliance status is partly complied
or not complied
Further actions/Timeline
department during the entire construction
period. Contractors to plan and implement diversion
roads for sensitive locations with prior
approval of the Supervision Consultant.
15. Air quality Contractors should place crushers and hot mix plants at least 500 m away
from residential areas or other social
infrastructures (school, hospital/religious
places etc)
Such establishments should strictly comply
to National Emission Standards for all
construction vehicles, equipment and
material processing plants Dust extraction/suppression systems should
be fitted to crusher units, construction
vehicles and hot mix plants
Sprinkling of water to the construction
sites and haul roads which are being used for
the transportation of construction materials
in regular intervals towards dust
suppression. Placing of dust barriers nearby schools,
religious places, market etc. Use construction equipment, machinery and
Site observations Check lists Public complaints
Being complied to
The periodical cheeking of air quality is being progressed along the road as well as selected plant sites to see possible pollutions Dust controlling activities such as water sprying for road construction areas, dust barriers for plant operation are implemented
Monthly site observations parallel to monthly meeting
![Page 102: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/102.jpg)
102
Potential Environmental
Impact Mitigation Action
Indicator or Means of verifications
Complied? Yes/Not
Complied/ Partly
Complied
Explanation if compliance status is partly complied
or not complied
Further actions/Timeline
vehicles which are in good condition and
those to be regularly maintained.
16. Noise and vibration
Strictly implement noise control regulations
for all construction vehicles and equipments. Contractors should equip their heavy
construction equipment with acoustic
enclosures/ silencers to limit the
construction equipment not to generate
noise exceeding 75 db (compacters, loaders,
vibrators, cranes, diesel generator sets) Limit working time for activities that
create noise only between 6.00 am to 6.00
pm except for construction site near
schools, offices, religious places.
Contractors should schedule their activities
at sensitive locations in consultation with the
relevant authorities (school’s principals,
high-priest etc.) Regularly maintain all construction vehicles
and machinery to meet the National
Emission Standards.
Site observations Check lists Public complaints
Being complied to
The periodical cheeking of noise and vibration are being progressed along the road as well as selected plant sites to see possible impacts The contractor is obligated to maintain the national standards of noise and vibrations during his construction activities.
Monthly site observations parallel to monthly meeting
17. Personal safety and health
Organize awareness programs regarding personal safety of workers and
general public during construction period. Establishment of safety provisions to
Site observations Check lists Public complaints
Being complied to
The contractor is being implemented tool box meeting/awareness campaigns periodically.
Monthly observations, and weekly checklist observations
![Page 103: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/103.jpg)
103
Potential Environmental
Impact Mitigation Action
Indicator or Means of verifications
Complied? Yes/Not
Complied/ Partly
Complied
Explanation if compliance status is partly complied
or not complied
Further actions/Timeline
reduce the likelihood of accidents by
placing warning signs, speed limit
markings, speed breakers and signals to
particular locations. Providing appropriate PPEs such as
protective footwear, helmets, goggles, eye-
shields and clothes to the workers
depending on their activities (Mixing asphalt,
blasting, handling equipments etc) and
motivating the workforce for their usage. Establishing first aid facilities and
Ambulance facilities at active working sites
to meet emergency situations. Use experienced and well trained workers
for the handling of machinery, equipment
and material processing plants. Contractor should implement STD/
HIV/AIDS awareness programs for general
public in and around project
implementation area and workers to reduce
the risk of spreading STD among them.
Safety provisions are provided to caring out the PPEs and the Traffic safety activities. First aid facilities, and worker rest room are provided. Standstill emergency vehicle is available. The contractor has submitted a schedule about the HIV/AIDS awareness program that to be conducted and these activities are being implemented.
18. Bridge
construction
Design of bridges should comply with the requirements of “Bridge Design Manual” of RDA. Contractor should provide safe and
convenient passage or alternative access to
road users for the entire construction period
Site visits & observations Weekly checklist
Being complied
The contractor has taken step to implement bridge construction activities according to the approved methodology with minimum environmental
Monthly progress meetings and checklists
![Page 104: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/104.jpg)
104
Potential Environmental
Impact Mitigation Action
Indicator or Means of verifications
Complied? Yes/Not
Complied/ Partly
Complied
Explanation if compliance status is partly complied
or not complied
Further actions/Timeline
seeking approval from the Supervision
consultant. Smooth traffic flow to be ensured
during the entire construction period with
the provision of appropriate safety
measures. During piling activities, the Bentonite
slurry generated will be collected and air
dried. Then it should be disposed in
disposal yards. In no case the slurry will be
discharged to the water bodies and
agricultural land etc.
damage to the nearby or vicinity areas. The consultant and the client will keenly observe their activities and guiding when he needs to dispose the slurry into open.
19. Access to Public utilities
Access to new public utilities should be
clearly marked within the road reservation in
consultation with the concerned
Departments.
Site visits & observations Weekly checklist
Being complied
The contractor has completed the access survey in section 01 and is to be completed in section 02. This is for identifying the neediness of the new access along the ROW. The provisions provided to make better accesses to public parallel to road development.
Monthly progress meetings and checklists
B. Operation stage
20. Encroachment of the RoW
Routine checking to discourage
encroachments and removal of unauthorized
structures from RoW in consultation with
Police Department. Popularizing and Implementation of rules
and regulations with respect to RoW and
Site visits & observations To Be complied
During the performance based management, the contractor, the Executive Engineer and the PMU staff will conducting routing visits to see any encroachments along the
Monthly progress meetings
![Page 105: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/105.jpg)
105
Potential Environmental
Impact Mitigation Action
Indicator or Means of verifications
Complied? Yes/Not
Complied/ Partly
Complied
Explanation if compliance status is partly complied
or not complied
Further actions/Timeline
to avoid encroachment from the RoW. road
21. Clearing of Cross
Drainage Structures
Periodical clearing of Cross drains and
side drains (specially before commencing of
rainy season) to facilitate easy
discharge of
Site visits & observations To Be complied
Do Monthly progress meetings
22. Road safety Enforcement of the speed limits, traffic rules and regulations to the sensitive
locations, Installation of the warning signs,
marking of center line, pedestrian crossings,
bus halts and other utilities.
Site visits & observations To Be complied
Do Monthly progress meetings
23. Road
maintenance
Developing and Implementation of periodical maintenance program.
Site visits & observations To Be complied
Do Monthly progress meetings
![Page 106: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/106.jpg)
106
Appendix: 05 Public Complains
Table 3.1 (a)The list of complains up to 31st March 2017 for B295 ‘Moratuwa-Piliyandala’ Road # Date Complainant Nature of Complaint Action Taken Resolution
1 26-May-15 B.D.P. Kularathne (4+230 RHS) 241, Moratuwa Road, Suwarapola, Piliyandala
Not to upgrade culvert discharging to lead-away drain through their property
Employer agreed to omit culvert improvement
Contractor instructed accordingly on 09/03/2016
2 10-Aug-15 Haklis Bathlo, Piliyandala (LHS)
Remove signboard near their gate
Contractor directed to remove sign
Sign removed on 10/12/2015
3 27-Sep-15 Existing culvert at Km 3+027 unable to cope with heavy flow
Contractor cleared culvert inlet, outlet and lead-away channel to improve flow
Completed on 12/10/2015
4 28-Sep-15 N.C. Dulwala (4+560 RHS) 175/5, Moratuwa Road, Piliyandala
Objects to improving existing lead-away drain through her property
Lead-away drain improvement has been referred to Municipal Authority
Action by Municipal Authority and it is being processed
5 16-Oct-15 B.D.M.U. Kularathne (4+280 LHS) 196, Moratuwa Road, Piliyandala
i. Request for house access, ii. Retaining wall to front
boundary, and iii. Protection of water well
i. Contractor directed to provide access,
ii. PE to refer wall to GRC, and iii. Contractor directed to
construct drain to protect water well
Work completed on 08/06/2016
6 16-Oct-15 M. Kulawathi De Costa (4+840 LHS) 88/2, Moratuwa Road, Piliyandala
Request for additional compensation for land acquisition and payment delay
Referred to Employer Completed on 15/03/2016
7 16-Oct-15
H.M. Upasena (3+940 RHS) 263, Ransara Reception Hall, Moratuwa Road, Suwarapola, Piliyandala
Request to construct their two accesses one-by-one to avoid disturbing business
Contractor directed to construct accesses one-by-one
Work completed on 15/11/2015
8 16-Oct-15 Y.A. Dayarathne 142/6, Moratuwa Road, Piliyandala
Request to construct by-road access suitable for large vehicle
Contractor directed to provide sufficient cover slabs
Work completed on 20/10/2015
9 16-Oct-15 P.A.D. Rohana (3+770 RHS) 285/A, Moratuwa Road, Suwarapola,
Request to protect front door frame during construction
Structure encroaches into ROW and required demolition
Completed on 12/12/2015
![Page 107: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/107.jpg)
107
# Date Complainant Nature of Complaint Action Taken Resolution
Piliyandala
10 16-Oct-15 W.A.A.P. Gunathilaka (4+640 RHS) 126, Moratuwa Road, Piliyandala
i. Request to protect boundary wall during construction, and
ii. Provide temporary vehicle access
Contractor directed to protect boundary wall and ensure uninterrupted access
Work completed on 05/11/2015
11 16-Oct-15 I.D. Siripala Perera (3+990 LHS) 248, Moratuwa Road, Piliyandala
i. Request two access to property, and
ii. Shift CEB pole at boundary
i. Double access request referred to Employer, and
ii. Contractor directed to attend to utility relocation
Work completed on 03/03/2016
12 16-Oct-15 B.D.D.N. Kularathne (4+280 RHS) 223, Moratuwa Road, Piliyandala
i. Request 2 months to demolish shop front for construction, plus
ii. Additional resettlement compensation, plus
iii. Additional compensation for disturbance to business
(i) Contractor directed to coordinate construction with shop demolition, and
(ii) Compensation issues referred to Employer
(i) Work completed on 05/01/2016, and
(ii) Pending
13 13-Nov-15 P.G.R. Anula Gamlath 320/1, Basil Niwasa, Suwarapola, Piliyandala
Request for alternative property access location at Km 3+250 LHS
Contractor directed to provide an access suitable for the property
Work completed on 08/05/2016
14 23-Dec-15 M.P. Chandana Perera 237, Moratuwa Road, Piliyandala
Request for additional access at KM 4+180 RHS
Referred to Employer Work completed on 10/03/2016
15 15-May-15 B.D.P. Kularathne 241, Moratuwa Road, Suwarapola, Piliyandala
Request not to construct new culvert at Km 4+238
Instruction issued to alternatively open and extend existing culvert at Km 4+210
Work done on 09/03/2016
16 06-Jan-16 Muditha Chaminda Sudasinghe 320, Moratuwa Road, Suwarapola, Piliyandala
Request to slope cover slabs at Km 3+235 LHS
Site inspection determined there is no need to install sloping cover slabs
Resolved on 12/02/2016
17 Jan-16 K. Indika Thilakarathne 226/2, Moratuwa Road, Suwarapola
Request not to open existing culvert at Km 4+210
Referred to Employer for discussion with local government authority
Work completed by Municipal Authority on 25/02/2016
18 12-Jan-16 T.A. Priyarathna Suwarapola, Deniya, Piliyandala
Concern about potential flooding of access road during rainy season at Km 3+263 RHS
Referred to Employer for discussion with local government authority
Work completed by Municipal Authority on 25/02/2016
19 13-Jan-16 G.T.S. Thilakarathne 37B, Hadigama, Piliyandala 317, Moratuwa Road, Suwarapola,
Request for lead-away drain at Km 3+446 RHS
Referred to Employer for discussion with local government authority
Action by Municipal Authority to be
![Page 108: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/108.jpg)
108
# Date Complainant Nature of Complaint Action Taken Resolution
Piliyandala completed
20 14-Jan-16 C.D. Palathirathne 320/A, Moratuwa Road, Deniya, Piliyandala
Request to slope cover slabs and provide 2m paving at Km 3+172 LHS
Instruction issued to Contractor Work completed on 28/04/2016
21 15-Jan-16 Sandya Jayawardhna 321/5, Basil House, Moratuwa Road, Suwarapola, Piliyandala
Request for additional access at Km 3+153 LHS
Employer determined that existing access is sufficient
Resolved on 28/01/2016
22 20-Jan-16 K.D. Laksiri 317/B, Moratuwa Road, Suwarapola, Piliyandala
ROW at Km 3+668 RHS ROW confirmed and instruction issued to Contractor to proceed
Work completed on 20/02/2016
23 23-Jan-16 Ravina Mortes 331/1/A, Moratuwa Road, Deniya Junction
Request for cover slabs at Km 3+268 LHS
Instruction issued to Contractor to provide cover slabs for culvert catch pit
Work completed on 07/06/2016
24 25-Jan-16 Sanio Lanka Apparels 226/2, Moratuwa Road, Suwarapola, Piliyandala
Request to cover culvert opening at Km 4+210
Necessary instruction issued to Contractor on culvert design
Work in progress
25 25-Jan-16 S.D.J. Jayasinghe 320/1, Suwarapola, Piliyandala
Boundary wall at 3+140 LHS collapsed on 28-Jan-16
Contractor has advised Insurance Company and commenced reconstruction
Work completed on 14/05/2016
26 01-Mar-16 DGM NWS&DB Damage to existing water line at Km 3+137 RHS
Advised Contractor to take action with NWS&DB
Water line repaired on 03/03/2016
27 14-Mar-16 Rasanga Gamage 213/4, Gangarama Road, Werahara, Boralegamuwa
Request for more substantial cover slabs at Km 2+220 LHS
Contractor instructed to provide medium duty cover slabs
Work in progress
28 18-Mar-16 S.D. Siriyawathi No.128C, Moratuwa Road, Piliyandala
Request for suitable access arrangement at Km 4+730 LHS
Instruction issued to Contractor to accommodate access for finished road level
Work completed on 06/06/2016
29 05-Apr-16 L.A.S. Suwarna Ajantha No.64/2, Moratuwa Road, Suwarapola, Piliyandala
Drainage concern at Km 4+230 RHS
Instruction issued to Contractor to close drain opening
Work completed on 05/05/2016
30 05-Apr-16 N. Jayasundara Asala Steel Centre, No.279A Motatuwa Road, Suwarapola
Request for suitable access at Km 3+830 RHS
Instruction issued to Contractor Completed on 05/08/2016
31 26-Apr-16 P.L.A. Perera, No.307 Moratuwa Road, Suwarapola
Request for extension of provided access at Km 3+670 RHS
Sent to the PE for further advise Completed on 10/07/2016
32 04-May-16 N. Jayasundara No.108/A, Horana Road, Piliyandala
Request for cover slabs at Km 3+830 RHS
Instruction issued to Contractor for cover slabs
Completed on 05/08/2016
![Page 109: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/109.jpg)
109
# Date Complainant Nature of Complaint Action Taken Resolution
33 28-May-16 SLT Underground cable at Km 0+970 RHS damaged during construction activity
SLT and Insurance Company notified
Cable repaired on 29/05/2016 and settlement of insurance claim pending
34 31-May-16 Vishwakala Labour Camp Fire damaged operators accommodation
Insurance Company notified
Insurance claim paid and repairs carried out on 15/01/2017
35 10-Jun-16 P.A.R.P. Perera No. 302A, Moratuwa Road, Suwarapola, Piliyandala
Request for suitable access at Km 3+360 LHS
Instruction issued to Contractor Completed on 16/08/2016
36 10-Jun-16 Bodhi Bharakara Mandalaya, Purana Bodhi Rajaya, Suwarapola, Piliyandala
RDA Boundary problem at Km 3+558-3+603 LHS
Survey Department has marked RDA boundary
Boundary confirmed and work resumed on 15/09/2016
37 10-Jun-16 K. Sanath Nihal, No 259, Maratuwa Road, Suwarapola, Piliyandala
Request for suitable access at Km 3+980 - 4+000 RHS
Instruction issued Contractor to provide vehicle access
Completed on 28/02/2017
38 17-Jun-16 K. Chaya Pranandu, No. 14, Johon De Silva Mawatha, Molpe, Moratuwa
RDA Boundary problem at Km 3+558-3+603 LHS
Survey Department has marked RDA boundary
Boundary confirmed and work resumed on 15/09/2016
39 30-Jun-16 W.S. Wimala Fernando, 349/1, Moratuwa Road, Kospelana, Piliyandala
Request to provide steps for access
Contractor instructed to provide suitable steps for access
Completed on 14/01/2016
40 09-Jul-16 S.D. Srimal, 242, Moratuwa Road, Suwarapola, Piliyandala
Complaint over vibration during construction activity
Contractor directed to investigate and carry out vibration measurement
Vibration measured and found to be within allowable limit on 18/08/2016
41 11-Jul-16 V.S. Weerakkodi, 1B, Gangule Mawatha, Suwarapola, Piliyandala
Complaint about dust and disposal truck speed
Contractor directed to operate disposal yard within approved constraints
Contractor took action on 15/07/2016
42 11-Jul-16 I.A.D.U.R. Perera, 1, Gangule Mawatha, Suwarapola, Piliyandala
RDA boundary at Km 3+560 LHS Referred to PE
Boundary confirmed and work resumed on 15/09/2016
43 08-Aug-16 Ransara Reception Hall Request cattle trap cover on Referred to PE who has further Resolved
![Page 110: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/110.jpg)
110
# Date Complainant Nature of Complaint Action Taken Resolution
263, Moratuwa Road, Suwarapola, Piliyandala
concrete drain at Km 3+900 RHS referred to EE 05/03/2017
44 29-Aug-16 K.I. Thilakaratne 226/2, Moratuwa Road, Piliyandala
Request to omit culvert parapet wall to avoid blocking access at Km 4+207
Instruction issued to Contractor Completed on 10/03/2016
45 07-Sep-16 Dialog Cable damaged during construction work at Km 3+369 LHS
Contractor notified Dialog and Insurer and lodged insurance claim
Insurance claim pending
46 13-Sep-16 Wepataira Hemaloka Thero Siri Wijayaramaya Udayogi Pura, Wewala, Piliyandala
Request to construct temple road at Km 2+980
Contractor requested to submit a proposal
Work done on 15/11/2016, but Contractor proposal awaited
47 22-Sep-16 U.D. Pilyasena 148, Moratuwa Road, Piliyandala
Request to remove new parapet wall at Km 4+538
PE advised to remove parapet wall; Contractor instructed accordingly
Pending
48 17-Oct-16
Nihal Pagoda Arachchi Bodhi Bharakara Mandalaya, Purana Bodhi Rajaya, Suwarapola, Piliyandala
Request for line marking and pedestrian crossing at Km 3+560 LHS
Incorporated in line marking design
Completed on 12/01/2017
49 19-Oct-16 Hemantha U. Arachchi 238, Moratuwa Road, Suwarapola, Piliyandala
Km 4+070 LHS access road connection issue
Contractor instructed to match access road level with B295
Work in progress
50 19-Oct-16 T.A. Piyarathna Suwarapola, Deniya Road, Piliyandala
Water stagnation at Km 3+268 RHS
Lead-away drain action by Kesbewa Urban Council
Urban Council work completed 15/03/2017
51 31-Oct-16 G.H.D. Wijeesena, Piliyandala
Request for cover slabs over drains
Cover slabs instructed for electrical post area
Work in progress
52 29-Dec-16 Nuwani Construction, 128, Moratuwa Road, Piliyandala
Request for cover slabs Details submitted to PE for approval
Pending
![Page 111: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/111.jpg)
111
Table 3.1 (b)The list of complains up to 31st March 2017 for B389 ‘Ratmalana-Mirihana’ Road # Date Complainant Nature of Complaint Action Taken Resolution
1 2-Sep-15 C.L. Jayawardhana (0+210 RHS) 62A, Mirihana Road, Nugegoda
Request for temporary access during construction
Contractor directed to provide continuous access
Temporary access provided on 20/09/2015
2 7-Sep-15 H.M.D.D. Dammika (1+230LHS) 337, Amarasa Hotel, Gamsabha Junction, Nugegoda
Claim that compensation was not paid
Referred to Employer RDA have inspected and replied to the Complainant on 17/10/2015
3 17-Sep-15 Wimaladharma Ekanayaka (0+065 RHS) 73/1, Mirihana Road
Water flowing to their property
Contractor instructed to construct lined side drain
Completed on 15/03/2017
4 21-Sep-15
Palitha Wijayawardhana (1+150 LHS) 111/7, Subodarama Road, Nugegoda
Request to open drain from by-road
Contractor directed to allow storm-water to flow from by-road to main road drainage
Completed on 16/02/2016
5 23-Sep-15 Ishara Wijesinghe (0+620 LHS) 30/1, Mirihana Road, Nugegoda
Boundary wall collapsed during lined drain construction
Contractor directed to reconstruct boundary wall as soon as possible
Reconstruction completed on 10/06/2016
6 26-Oct-15 D. Kadahawala (0+520 RHS) 23, Mirihana Road, Nugegoda
Request to avoid property damage during construction
Contractor directed to liaise with resident and avoid damage
Work completed on 14/03/2016
7 11-Dec-15 D.H.H.M. Sathischandra 126D, Subadrarama Road, Nugegoda
Request to maintain drainage at Km 0+820 RHS
Contractor directed to check level at location and ensure drainage to new roadside drain
Work completed on 14/02/2016
8 Dec-15 S.D. Devasunara 107, Subadrarama Road, Nugegoda
Request to relocate telephone post at Km 1+113 LHS
Contractor directed to liaise with Telecom and property owner over post relocation
Work completed on 09/03/2016
9 Jan-16 D.R.K.V. Wijegunawardhana 51, Papiliyana Road, Gangodavila, Nugegoda
Disputing ROW land boundary at Km 1+550 LHS
Boundary checked and work cleared to proceed
Work completed on 09/03/2016
10 9-Jan-16 B.S.A.S.N. Sudasighe 22/A, Papiliyana Road, Gangodavila, Nugegoda
Boundary wall at Km 1+340 RHS collapsed during lined drain construction
Contractor directed to promptly reconstruct damaged wall and access
Contractor has submitted claim to Insurer and completed reconstruction on 20/01/2017
11 9-Jan-16 Telecom Contractor damaged buried STL wire at Km 1+820 LHS
Contractor advised SLT and Insurers
SLT repair completed but insurance claim pending
![Page 112: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/112.jpg)
112
# Date Complainant Nature of Complaint Action Taken Resolution
12 Jan-16 B.S.A.S.N. Sudasighe 22/A, Papiliyana Road, Gangodavila, Nugegoda
Request for cover slabs at Km 1+340 RHS
Contractor directed to provide cover slabs
Work completed on 05/03/2016
13 20-Jan-16 M.D.N. Daminda 10, Papiliyana Road, Nugegoda
Request for specific house access arrangement at Km 1+315 RHS
Contractor directed to provide access as requested
Work completed on 28/02/2016
14 25-Jan-16 V.A.D. Kularathne 162, Subadrarama Road, Nugegoda
Request for specific house access arrangement at Km 1+135 RHS
Contractor directed to adjust drain height to suit access
Work completed on 18/01/2017
15 29-Feb-16 SLT SLT post at Km 1+430 RHS collapsed onto three-wheeler during heavy rain
Contractor notified Insurer and lodged claim
New pole erected on 02/03/2016 but insurance claim pending
16 29-Feb-16 LECO
Underground cable Km 0+880 to 0+920 RHS damaged during construction activity
Contractor notified LECO and Insurer and lodged claim
LECO repair completed on 02/03/2016 but insurance claim pending
17 04-Mar-16
Underground cable at Km 0+078 LHS damaged during construction activity
Contractor notified LECO and Insurer and lodged claim
Cable repaired and Contractor paid compensation to SLT on 05/04/2016
18 26-Mar-16 Ananda Perera Maddumage 111/9, Subadhraramaya Road, Gangodavila, Nugegoda
Request that by-road drainage be blocked from entering lined side drain at Km 1+124 LHS
Referred to Employer as contradicts requests of other residents
Resolved on 05/04/2016
19 31-Mar-16 Bandula de Silva, No 81, Pepiliyana Road, Gangodawila, Nugegoda.
Request for house access at Km 1+810 LHS
Contractor directed to provide access as requested
Work completed on 03/05/2016
20 25-Apr-16 LECO
Underground cable at Km 0+750 LHS damaged during construction activity
Contractor notified LECO and insurer and lodged claim
Cable has been repaired on 26/04/2016 but insurance claim pending
21 29-Apr-16 LECO Electricity pole collapsed during construction at Km 0+240 RHS
Contractor notified LECO and insurer and lodged claim
New pole erected on 29/04/2016 but insurance claim pending
22 06-May-16 SLT
Underground cable at Km 0+970 LHS damaged during construction activity
Contractor notified SLT and insurer and lodged claim
Cable has been repaired on 08/05/2016 but insurance claim pending
![Page 113: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/113.jpg)
113
# Date Complainant Nature of Complaint Action Taken Resolution
23 07-May-16 LECO
Underground cable at Km 0+920 RHS damaged during construction activity
Contractor notified LECO and insurer and lodged claim
Cable has been repaired 08/05/2016 but insurance claim pending
24 11-May-16
Boundary wall at Km 0+640 LHS collapsed during construction activity
Contractor directed to promptly reconstruct damaged wall and access
Contractor has submitted claim to Insurer and is proceeding with reconstruction
25 17-May-16 A.I. Walikada No 128, Subadhrarama Road
Damage to house roof canopy during construction activity
Contractor directed to promptly repair damaged canopy
Work completed on 08/08/2016
26 28-May-16 SLT
Underground cable at Km 0+360 LHS damaged during construction activity
Contractor notified SLT and insurer and lodged claim
Cable has been repaired on 30/05/2016 but insurance claim pending
27 06-Jul-16 SLT
Underground cable at Km 0+680 LHS damaged during construction activity
Contractor notified SLT and insurer and lodged claim
Cable has been repaired on 07/07/2016 but insurance claim pending
28 08-Jul-16 LECO Electrical pole collapse while backhoe working at Km 0+250 RHS
Contractor notified LECO and insurer and lodged claim
Electrical post has been repaired on 08/07/2016 but insurance claim pending
29 09-Jul-16 D.U.R. Wijesinghe, 17B, Mirihana Road, Nugegoda
Complaint about vibration Contractor directed to investigate and
Vibration level measured and contractor directed to adjust rolling procedure on 12/07/2016
30 30-Jul-16 SLT
Underground cable at Km 0+735 LHS damaged during construction activity
Contractor notified SLT and lodged Insurance claim
Cable has been repaired on 01/08/2017, but insurance claim pending
31 30-Jul-16 SLT
Underground cable at Km 1+883 RHS damaged during construction activity
Contractor notified SLT and lodged Insurance claim
Cable has been repaired on 01/08/2017, but insurance claim pending
32 10-Aug-16 Karunasena Moramudali 13, Kattiya Junction, Mirihana Road, Nugegoda
Request for cover slabs at Km 0+647 to 0+660 RHS
Instruction issued to Contractor
Work completed on 18/01/2017
![Page 114: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/114.jpg)
114
# Date Complainant Nature of Complaint Action Taken Resolution
33 08-Sep-16 M.D.S.F. Arthakularathne 87, Papiliyana Road, Nugegoda
Request to cover slab Provided Work completed on 25/09/2016
34 11-Sep-16
Boundary wall at Km 1+330 RHS collapsed during construction activity
Contractor directed to promptly reconstruct damaged wall
Contractor has submitted claim to Insurer and reconstructed the wall on 22/01/2017
35 11-Sep-16 SLT
Underground cable at Km 1+350 LHS damaged during construction activity
Contractor notified SLT and lodged Insurance claim
Cable has been repaired on 12/09/2017, but insurance claim is pending
36 23-Sep-16 LECO
Underground cable at Km 0+890 RHS damaged during construction activity
Contractor notified LECO and lodged Insurance claim
Cable has been repaired 24/09/2017,but insurance claim is pending
37 28-Sep-16 Malika Disanayaka 75, Mirihana Road, Nugegoda
House access problem Instruction issued for steps Work in progress
38 20-Oct-16 35, Privet Lane, Mirihana Access problem Site inspected and Contractor instructed to take mitigation action
Completed on 21/12/2017
39 27-Oct-16 S.M.A. Senavirathna 17, Subadrarama Road, Gangodavilla, Nugegoda
Access problem Site inspected and Contractor instructed to take mitigation action
Completed on 28/12/2016
40 01-Nov-16 W. Ekanayake 73/1, Mirihana Road, Nugegoda
Damage to property entrance by water line construction
Contractor instructed to rectify access damage
Completed on 23/11/2016
41 03-Nov-16
Thabbowa Ananda Revatha Thero, Subadrarame, Athula Rajamaha Viharaya, Gangodavila, Nugegoda
Request for stone wall Referred to PE Awaiting Employer response
42 15-Nov-16 Police Inspector, Mirihana Request to construct by-road
By-road scope confirmed Work completed on 20/11/2016
43 01-Dec-16
Director, Agricultural & Agrarian Insurance Board, 117, Subadrarama Road, Gangodavila, Nugegoda
Access problem Contractor instructed to improve property access
Work completed on 18/12/2016
44 29-Dec-16 Amith Batugedara, 106, Old Kesbewa Road, Nugegoda
Water ponding Contractor instructed to remove pipe culvert
Work completed on 06/01/2017
45 11-Jan-17 M.A. Perera Request to construct by- By-road construction Solved on 22/01/2017
![Page 115: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/115.jpg)
115
# Date Complainant Nature of Complaint Action Taken Resolution
115, Subadrarama Road, Nugegoda
road and damaged boundary wall
completed and no boundary wall damage identified
46 06-Feb-17 M.A.R.K. Perera 77A, Mirihana Road, Nugegoda
Request for new water connection
Location inspected & approval given to excavate road
Work completed on 03/03/2017
47 20-Feb-17 W. Ekanayaka 73/1, Mirihana Road, Nugegoda
Request to add pedestrian crossing
Referred to RDA Awaiting Employer decision
![Page 116: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/116.jpg)
116
Table 3.2 The list of complains up to 31st March 2017 for B084
# Date Complainant Description Action Taken Resolution
1 21-Dec-16 Mr. A.A.D. Jagath Kumara 252, Kahathuduwa, Polgasowita B084 Km 19+680 RHS
Steep access slope due to road realignment
Survey carried out to amend alignment
Vertical alignment adjusted to improve access on 26/01/2017
2 13-Jan-17 Mr. M.D. Jayarathne 72/3, Kondurawawa, Polgasowita B084 Km 15+220 RHS
Verification of boundary
Acquired boundary demarcated on 18/01/2017
Currently subject to court case
3 16-Jan-17 Mr. P.D. Diyasiri Pannarathne 52A, Kondurawawa, Polgasowita B084 Km 15+295 RHS
Request to change lead-away due to erosion from Culvert 16/1
Referred to Local Authority as lead-away outside ROW on 17/01/2017
Awaits action by Local Authority
4 01-Feb-17 Residents near “Samagi Praja Shalawa” B084 Km 14+993 RHS
Lead-away drain near “Samagi Praja Shalawa”
Referred to Local Authority as lead-away outside ROW on 03/02/2017
Awaits action by Local Authority
5 02-Feb-17 Mr. G. Gunasoma 22, Undurugoda, Polgasowita B084 Km 18+020 RHS
Verification of boundary
Acquired boundary demarcated
Referred to RDA Land Division for check with Section 2 hand-over on 02/02/2017
6 02-Feb-17 Mr. F.P. Wickramasinghe B084 Km 25+200 RHS
Concern about erosion after road excavation
Survey being carried out to determine protection requirements
To be considered under Section 4 design on 09/02/2017
7 02-Feb-17 Mr. Amarakoon Piyasena B084 Km 21+950 RHS
Request to realign road to give space for his shop
Survey being carried out Road design checked on 09/02/2017
8 02-Feb-17 Residents near Rilawala Junction B084 Km 18+200 RHS
Request for a bus shelter
Information being assembled on 09/02/2017
Bus halt location to be considered
9 02-Feb-17 Mrs. D.L.S. Kumari B084 Km 15+710 RHS
Request for parking space and steps to residence
Necessary setting out determined on 24/03/2017
Work in progress
10 06-Feb-17 Mr. D.K. Abesinghe B084 Km 19+930 Culvert 20/6
Request to move culvert
Relocated to 19+945 to align with lead-away
Work in progress
11 13-Feb-17 B.A. Perera, 311/13, Kahathuduwa, Polgaswita B084 Km 17+380 to 18+380
Request to remark land acquisition boundary
Survey to be carried out To be done for Section 2 hand-over
![Page 117: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/117.jpg)
117
# Date Complainant Description Action Taken Resolution
12 13-Feb-17 Mr. S.J. Nawagamuwa Lot No. 4334 B084 Km 26+100 RHS
Request for house access
To be surveyed once Section 4 handed-over
Access to be provided
13 13-Feb-17 Mr. B. Ariyawansha PP No.9265/Lot No.35 B084 Km 18+890 LHS
Request to verify land acquisition boundary
Directed to RDA Land Division on 03/02/2017
Survey to be carried out
14 15-Feb-17 Mr. K.B. Chandrapala B084 Km 18+735 LHS
Request to move Culvert 19/6 lead-away
Inspected by PE & EE on 20/02/2017
Lead-away to be moved by 5m
15 15-Feb-17 Mr. D.G.L. Ramyasiri B084 Km 18+890 LHS
Request to close Culvert 18/2 and lead-away
Inspected by PE & EE on 20/02/2017
Further inspection scheduled with SDE for 09-Mar-17
16 15-Feb-17 Mr. Ranjith Fernando B084 Km 18+730 LHS (Adjacent to as 15 above)
Request to move Culvert 19/6 lead-away
Inspected by PE & EE on 20/02/2017
Lead-away to be moved by 5m
17 16-Feb-17 Mr. A.D. Leelarathna B084 Km 14+300 RHS
Request to mark land acquisition boundary
Remarked correct boundary on 16/02/2017
Boundary agreed
18 16-Feb-17 A004 Km 17+300 to 17+800 RHS, Panagoda, Homagama
Request for retaining walls
Part of government property relocation work
Work in progress from 20/02/2017
19 20-Feb-17 Residents near Kesbewa B084 Km 13+800 to 14+200
Requests to connect rain water outlets to road drainage
RDA requirements explained to shop owners
Accepted on 20/02/2017
20 21-Feb-17 Resident near Kesbewa B084 Km 17+540 LHS
Request for time to demolish house
Accepted by PE Section 2 not yet handed-over on 21/02/2017
21 22-Feb-17 Mr. R. Geekiyanage, 252/1, Kahatuduwa, Polgasowita B084 Km 19+700 RHS
Request for soil to private property
RDA considering Referred to DS on 22/02/2017
22 28-Feb-17
Mr. S.A.I. Mahendradasa, 60A, “Udula”, Honnanthara Road, Piliyandala B084 Km 14+360 LHS
Improper utility shifting
Inspected & discussed with PE
Resolved on 01/03/2017
23 03-Mar-17 Mr. W.U.R. Rodrigo 29, ‘Ratnasiri’ Market Lane, Bandaragama
Request to remark acquisition boundary
Remarking scheduled Contractor agreed to remark ROW on 07/03/2017
24 03-Mar-17 Mr. W. Atigala 14/C, Horathumbuwa, Polgasowita (Lot No.217)
Request for time to demolish house
Accepted by PE on 07/03/2017
Demolition completed on
25 09-Mar-17 Mr. M.D. Premadasa Request to widen Culvert widening agreed Wider culvert instructed
![Page 118: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/118.jpg)
118
# Date Complainant Description Action Taken Resolution
136, Old Police Road, Kahathuduwa
culvert at Kesbewa Junction
on 10/03/2017
26 09-Mar-17 Mr. W.A. Ariyasena 778, High Level Road, Panagoda, Homagama (Lot Nos. 205 & 206)
Request for house access
Accepted by PE on 09/03/2017
Access scheduled
27 15-Mar-17 Mr. D.U. Wickramage 6F-1 Wickrama Pedesa, Horana Road, Kesbewa, Piliyandala
Request for unsuitable soil
Scheduled for inspection on 17/03/2017
28 22-Mar-17 D.A. Kumawathi 277/C, Horana Road, Kahathuduwa, Polgasowita
Loss of well Inspected with PE & NWS&DB on 22/03/2017
New water connection scheduled
29 22-Mar-17 B.A. Angohami 277/A, Horana Road, Kahathuduwa, Polgasowita
Loss of well Inspected with PE & NWS&DB on 22/03/2017
New water connection scheduled
30 24-Mar-17 Upashama Kottage 26/3, Sarwodaya Road, Honnaththara, Kesbewa
Request for shop steps Agreed to provide steps on 24/03/2014
Access scheduled
31 28-Mar-17 Mr. A.K. Perera 59-B, Horana Road, Honnaththara, Piliyandala
Concern about land inundation
Inspected and provisions made
Lined drain completed on 28/03/2017
![Page 119: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/119.jpg)
119
Table 3.3 The list of complains up to 31st March 2017 for B157
# Date Complainant Nature of Complaint /
Issue Action Taken Resolution
1 19-Oct-16 Mr. O.T.M.S.E. Premarathna Km 38+940 RHS
Cracks observed in Post Office Building walls
Referred to Contractor Monitoring in progress
2 01-Nov-16 Principal of Lewwanduwa Junior School Km 41+810 LHS
Requested removal of Kottamba tree
Referred to Contractor Contractor removed
tree On 07/11/2017
3 01-Nov-16 Mrs S. Weerakoon Weera Niwasa, Lewwanduwa Km 41+950 RHS
Request for access Contractor requested to place cover slabs over
lined drain
Cover slabs installed On 02/12/2016
4 01-Nov-16 Mr. U.K.D. Asela Pallegodawatte, Lewwanduwa Km 41+980 LHS
Request for access Contractor requested to place cover slabs over
lined drain
Cover slabs installed On 02/12/2016
5 03-Nov-16 Mr. S. Kuruneru, Lewwanduwa Km 42+100 RHS
Request for retaining wall
Contractor instructed to incorporate wall in lined
drain
Construction completed on 20/12/2016
6 04-Nov-16 Mr. J.K.P.S. Jayaneththi Pallegodawatte, Lewwanduwa Km 41+810 RHS
Request for access Contractor requested to place cover slabs over
lined drain
Cover slabs installed On 02/12/2016
7 22-Nov-16 Mr. H. Perera 632, Siyathko, Lewwanduwa Km 41+750 RHS
Existing access affected by raised road profile
Contractor providing temporary access
To be finally resolved by the permanent work
8 24-Nov-16 Mr. D.U. Jayaneththi Heel House, Lewwanduwa Km 41+250 RHS
Request for access Contractor requested to place cover slabs over
lined drain
Cover slabs installed On 02/12/2016
9 24-Nov-16 Mr. M.V. Wimaladasa Lewwanduwa Km 41+160 RHS
Request for access Contractor requested to place cover slabs over
lined drain
Awaits construction of lined drain
10 25-Nov-16 Mr. K.A.D.K. Kodithuwakku Lewwanduwa Km 39+560 RHS
Existing drain temporarily blocked by
construction
New lined drain under construction
Work is in progress
11 28-Nov-16 Mrs. D.S.T. Samarakoon Shamin, Kopiwatte Km 40+530 RHS
Request for access Contractor requested to place cover slabs over
lined drain
Cover slabs installed On 21/12/2016
12 28-Nov-16 Mr. K.A.D. Sanjeewa Lewwanduwa
Request for retaining wall
Contractor instructed to incorporate wall in lined
Construction completed
![Page 120: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/120.jpg)
120
# Date Complainant Nature of Complaint /
Issue Action Taken Resolution
Km 41+800 RHS drain On 25/02/2017
13 24-Dec-16
Mr. K.M.G. Ananda Pallegodawatte, Lewwanduwa Km 41+870 RHS
House cracks Referred to Contractor Monitoring in progress
14 26-Dec-16 Mr. K.A.D.K. Kodithuwakku Lewwanduwa Km 39+560 RHS
House cracks Referred to Contractor Monitoring in progress
15 03-Jan-17 Mr. K.A.D.K. Kodithuwakku Lewwanduwa Km 39+560 RHS
Requests RFL to be raised to flood level
RFL raised to avoid frequent flooding
Work in progress
16 03-Jan-17 Mr. W. Kodithuwakku, Dippita, Welipenna Km 39+850 LHS
Request for cover slabs Referred to PE as this is
undeveloped land PE to advise whether
additional slabs needed
17 03-Jan-17
Mr. D.P. Peiris Near Telephone Exchange, Lewwanduwa Km 40+635 RHS
Request for access Referred to Contractor Access reinstated On 20/02/2017
18 03-Jan-17 Mr. D.M. Kodithuwakku 68, Main Street, Welipenna Km 39+560 RHS
Requests RFL to be raised to flood level
RFL raised to avoid frequent flooding
Work in progress
19 03-Jan-17 Mrs. P.D. Arachchigoda Pannila Km 40+000 RHS
Request for cover slabs Referred to PE as this is
undeveloped land PE to advise whether
additional slabs needed
20 05-Jan-17 Mrs. G.W. Raniani Lewwanduwa Km 41+060 RHS
House cracks Referred to Contractor Monitoring in progress
21 26-Jan-17
Mrs. S. Jinadari Pallegodawaththa, Lewwanduwa Km 41+910 LHS
House cracks Referred to Contractor Monitoring in progress
22 26-Jan-17
Mr. K.M.G. Ananda Pallegodawaththa, Lewwanduwa Km 41+970 LHS
House cracks Referred to Contractor Monitoring in progress
23 26-Jan-17 Mr. D.M. Kodithuwakku 68, Main Street, Welipenna
Requests RFL to be raised to flood level
RFL raised to avoid frequent flooding
Work in progress
![Page 121: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/121.jpg)
121
# Date Complainant Nature of Complaint /
Issue Action Taken Resolution
Km 38+750 RHS
24 26-Jan-17
Mrs. S. Jinadari Pallegodawaththa, Lewwanduwa Km 41+910 LHS
Request for cover slabs Referred to PE as this is
undeveloped land PE to advise whether
additional slabs needed
25 26-Jan-17
Mr. S.S. Manjuka Near Telephone Exchange, Lewwanduwa Km 40+635 RHS
Request for protection wall at well
Contractor instructed to raise outer wall of lined
drain Work in progress
26 26-Jan-17 Mr. P.K. Piyadasa Kopiwatta, Welipenna Km 40+290 RHS
Request for heavy duty cover slabs
Scheduled requirement confirmed to Contractor
Work in progress
27 07-Feb-17 Mr. J.K.D.S.C. Jayawardena Kopiwaththa, Welipenna Km 40+297 LHS
Request protection measure to avoid
inconvenience from culvert discharge
Request forwarded to PE for approval
Pending approval
28 08-Feb-17 Mr. W.A De Silva Dickhena, Polwatta, Welipenna Km 38+110 LHS
Request for access steps Access steps to be
provided Work in progress
29 08-Feb-17
Mr. H.M.D. Mahindapala Aluthgama Road, Horawala Junction, Welipenna Km 36+840 RHS
Dust emission
Contractor took action to minimize dust emission
Water tanker allocated to spray water to
minimize dust emission
30 09-Feb-17
Mr. T.D.S.K. Tudugala "Sithumina" near the Telephone Exchange, Lewwanduwa, Welipenna Km 41+ 890 RHS
Request to raise the lined drain wall up to
road level
Request has been forwarded to PE for
approval
Pending approval
31 09-Feb-17
Mr. D.G. ThewarapperumaNo.12, Dikhena, Welipenna Km 38+115 LHS
Request to place cover slabs
Agreed to place cover slabs
Completed On 20/03/2017
32 09-Feb-17
Mrs. T. Jayaneththi Pallegadawatte, Lewwanduwa, Welipenna Km 41+895 RHS
Request to raise the lined drain wall up to
road level
Request has been forwarded to PE for
approval Pending Approval
33 09-Feb-17 Mr. R.D. Galabadaarachchi Request to reinstate Contractor agreed to Work in progress
![Page 122: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/122.jpg)
122
# Date Complainant Nature of Complaint /
Issue Action Taken Resolution
No.170B, School Junction, Welipenna Km 39+950 RHS
damaged gate posts and fence
reinstate the damaged gate posts and fence
34 20-Feb-17
Mr. I.G. Thewarapperuma, No.12/1, Dikhena, Welipenna Km 38+240 LHS & Near 39/1 Culvert LHS
Request for vehicular access with cover slabs
Request has been forwarded to PE for
approval
Pending Approval
35 20-Feb-17
The Principal, WP/MT/Lewwand-uwa Junior School, Lewwanduwa Km 41+810 LHS
Cracks developed in building walls due to
road construction activity
Contractor to monitor cracks
Monitoring of cracks is in progress
36 07-Mar-17
Pathmendra, Gaianayaka & Malkanthi Welipenna Km 37+130 LHS
Request for lined drain from Culvert 37/5 to
38/1
Requires inspection with RDA
37 15-Mar-17 A.A.M. Nazeer 180/2, Main Street, Welipenna Km 38+880 RHS
Request for retaining wall to Bridge 39/4 lead-
away drain
To be constructed after completing bridge work
38 15-Mar-17
D.S.S. Thevarapperuma Kopiwatta Junction, Welipenna Km 41+270 RHS
Request for access to new building
Precast slabs being prepared at Maga yard
39 15-Mar-17
U.I. Sendanayaka 29, Mahawatta Junction, Welipenna Km 38+127 RHS
Request access and lined lead-away drain beyond
ROW
Contractor to reinstate access but lead-away
requires RDA decision
40 16-Mar-17 Pradeshiya Sabawa, Mathugama Km 40+380 RHS
Request to asphalt nursery access
Requires RDA consideration
41 16-Mar-17
D.C. Jayaneththi Mahawatta Junction, Welipenna Km 38+200 LHS
Request for access steps Instruction issued to
Contractor Work completed 0n 21/02/2017
42 17-Mar-17 M.B.M. Hazen 5, Nallagoda Road, Welipenna Km 39+290 LHS
Issues with stormwater Contractor instructed to
provide temporary protection
43 17-Mar-17 K.D.A.S. Gamini Request for access steps Instruction issued to Work in progress
![Page 123: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the](https://reader030.vdocuments.us/reader030/viewer/2022040910/5e82c9aac0c98e7454202f9a/html5/thumbnails/123.jpg)
123
# Date Complainant Nature of Complaint /
Issue Action Taken Resolution
Lewwanduwa, Welipenna Km 40+630 RHS
Contractor
44 17-Mar-17 P.V.S.S. Abagahawatta Lewwanduwa, Welipenna Km 41+680 RHS
Request for separate vehicle access
Requires RDA consideration