environmental monitoring report...environmental monitoring report annual report july 2017 sri lanka:...

123
Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the Government of Sri Lanka and the Asian Development Bank This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Upload: others

Post on 23-Mar-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

Environmental Monitoring Report

Annual Report July 2017

Sri Lanka: Southern Road Connectivity Project

Prepared by Road Development Authority for the Government of Sri Lanka and the Asian

Development Bank

This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Page 2: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

2

Contents

1. INTRODUCTION ............................................................................................................... 6

2. PROJECT IMPLEMENTATION PROGRESS ......................................................................... 8

3. CONSTRUCTION PROGRESS .......................................................................................... 11

5. SUMMARY OF ENVIRONMENTAL MITIGATIONS AND COMPENSATION MEASURES .... 20

6. SUMMARY OF ENVIRONMENTAL MONITORING ........................................................... 32

7. PUBLIC COMPLAINTS............................................................................................. 37

8. STATUS OF COMPLIANCE TO LOAN AGREEMENT ........................................................ 39

9. CONCLUSION ................................................................................................................. 41

Page 3: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

3

ABBREVIATIONS

ADB Asian Development Bank

AIDS Acquired Immune Deficiency Syndrome

CEA Central Environmental Authority

CP Contract Package

EMAP Environmental Management Action Plan

EMOP Environmental Monitoring Plan

EMP Environmental Management Plan

EO Environmental Officer

EPL Environmental protection License

ES Environmental Specialist

GAP Gender Action Plan

GRC Graveness Redress Committee

GSMB Geological Survey and Mining Bureau

HIV Human Immunodeficiency Virus

IEE Initial Environmental Examination

IML Industrial Mining Licenses

LA Local Authority

NHSP National Highway Sector Project

PIC Project Implement Consultant

PD Project Director

PMU Project Management Unit

RDA Road development Authority

RE Resident Engineer

ROW Right-of-way

SRCP Southern Road Connectivity Project

TL Team Leader

Page 4: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

4

Figure 1. Location map of selected road sections to be developed under SRCP

CP 01- Ratmalana - Mirihana , and Moratuwa Piliyandala Road

CP 02- Kesbewa - Pokunuwita , and Kiriulapana - Godagama Road

CP 03- Matugama - Southern Expressway Road

Page 5: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

5

EXECUTIVE SUMMARY This report is the 2nd annual report on environmental safeguards compliance of the

three (3) subprojects under the Southern Road Connectivity Project (SRCP), Loan

No: 3027-SRI funded by Asian Development Bank (ADB). The reporting period is

from May 2016 to April 2017.

The three sub projects under SRCP are;

1. Ratmalana - Mirihana Road B389, and Moratuwa Piliyandala Road B295. CP

01, and total length is 4.69km

2. Kesbewa - Pokunuwita Road B084, and Kiriulapana - Godagama Road

A004. CP 02, and total length is 16.45km

3. Mathugama - Southern Expressway B157. CP 03, and total length is 12.06km

4. CINEC Junction to Ambathale Junction Link road. CP04, Total length 1.83

km

CP 01 project is nearing at its’ completion; while the construction works of CP02 and CP03 project’s had already begun recently towards the latter part of 2016 and the project works are currently being progressed. The construction works of CP04 have still not started. Due to the adverse weather conditions that prevailed, heavy showers and floods were experienced during the initial stage of the reporting period (April-May 2016). However, the weather was mostly dry throughout the latter part of the reporting period and was favourable for construction activities. The baseline sampling of the selected environment parameters were collected and reports were submitted to the PMU by CP-02 and CP 03 respectively, while only operational period sampling is planned to be collected in CP-01. Moreover, the contractors have obtained the relevant licences and approvals that were required to execute the construction activities. No major environmental impacts were observed during the reporting period, because CP 01 road works are almost completed and the works of other projects’ have just started. Nevertheless, we have observed few shortcomings on safety matters which were however rectified then there.

Page 6: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

6

1. INTRODUCTION

Sri Lanka is an island, blessed with lush green forest and year around temperate

climate. It has hilly terrain in middle and south west part with surrounding flat

law terrain. The South-West part of the country experiences more rainfall and

defined as Wet Zone, and while other parts mostly North- West and South-West

parts received less rainfall defined as Dry Zone of the country.

For administrative purposes, the island has been divided into seven administrative

divisions. The Central Government is situated in Colombo District, where the

parliament is situated in.

Considering the strength of each province in terms of economic and political, the

Southern and the Western Provinces are ranked amongst the first level of

administrative divisions of the island. These two provinces have vital economic

development compared to the other five provinces of Sri Lanka. These two

provinces contribute over 60% of the country’s GDP while other provinces

contribute the rest. The southern Province's capital is Galle, while Colombo is the

capital of the western province. Subsistence farming and fishing is the main source

of income for the vast majority of the people of the Southern region but recently

the economic activities witnessed some degree of diversification viz tourism and

related economic activities such as hotels, boutiques, villas, handicrafts, travel

guiding, and tour organizing. The majority of people are well educated and enjoy

decent healthcare facilities and other common amenities.

A vast majority of the people are keen to enter the newly created economic space

through the Southern highway network which links all the strategically important

townships along the way. These townships are poised to boost new economic

development opportunities in the area which are also situated in close proximity to

famous tourist destinations.

In view thereof, the southern road connectivity project will help improve the

connectivity between expressway network and the local transport network in

southern region. Accordingly, it is proposed to develop 33.5 km of national

highways linking with the three interchanges of the southern expressway.

Page 7: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

7

The proposed development will not only improve the expressway connectivity but

would also help manage the future traffic volumes.

Southern Road connectivity project will improve five priority national highways

which provide connectivity to three interchanges of Southern Expressway. The

priority roads are selected according to the current road condition and capacity,

traffic demands, and readiness for improvement. The road will be widened,

upgraded and realigned as necessary to meet the projected traffic demand for the

next 20 years. The pavement is designed for life up to 10 years that could be

extended to 15-20 years with proper maintenance and excess axle load control.

Bridges, drainage structures and culverts will be improved and replaced as

required. Road safety audit will be incorporated into the engineering designs and

monitored during construction period. The details of the selected roads are

furnished below;

Table 1.1 The detail of SRCP road projects

Contract Package

Road Name Route No Length (Km)

CP1 Ratmalana - Mirihana Road B389 2.14

Moratuwa Piliyandala Road B295 2.55

CP2 Kesbewa - Pokunuwita Road B084 14.38

Kiriulapana - Godagama Road A004 1.79

CP3 Matugama - Southern Expressway B157 10.37

1.1 Report Purpose The monitoring process of the environmental safeguards compliance of the project

is entrusted to Project Management Unit and Environmental & Social Development

(ESD) Unit of RDA. This Annual report is prepared by Project Management Unit to

present the situation of environmental safeguard of the ongoing projects and the

monitoring results to the ADB.

Page 8: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

8

2. PROJECT IMPLEMENTATION PROGRESS

2.1 Recruitment of Project Implementing Consultant

The MG Consultants (Pvt.) Limited has been selected as the consultancy firm for

the SRCP on 12th March 2015. The cabinet approval has also been granted, and the

consultant has mobilized on 8th June 2015 and contract is in progress. The PIC

office operates in Battaramulla, Sri Lanka and it occupies Team Leader and his

technical staff.

2.2 Project Implementing Consultants’ (PIC) role in environmental safeguards compliance

The Team Leader (TL), Residential Engineer (RE) with the Environmental

Specialist (ES) of PIC is responsible for assessment of the contractors proposed

methods in relation with the stipulated EMP. The TL will advise and assist the RE

in co-ordination and meetings with external agencies and bodies with direct

concerns in the project.

Further, the RE gives direction and instructions to the contractor to mitigate the

possible adverse effects on the environment caused by construction activities.

In the event that some sections of sub project’s roads run through the

environmentally sensitive areas, the contractors should strictly follow all the rules

and regulations laid down by various authorities governing these areas while the

construction activities are going on. The ES of PIC shall pay particular attention to

these areas and advice the RE and contractor accordingly as regards the proper

procedure to be followed and the necessary permits which need to be obtained

before commencement of work/completion of the works.

The environmental monitoring procedure/task is being carried out by the PMU

and the PIC on a monthly basis with the participation of the contractor’s

representatives. The meeting summarizes the activities done by the contractor in

each month and suggestions are made to mitigate possible adverse impacts on the

environment. The issues that cannot be resolved at the above meeting will be

Page 9: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

9

tabled at the Monthly Progress Meeting conducted by the PD of the PMU and

would be further escalated to the GRC if necessary.

2.3 The project implementing progress

Of the ongoing three road projects, CP 01 has almost been completed its major

works and other two projects ‘works are being progressed. CP-02 and CP 03

projects works have been handed over to the contractors with sectional basis due

to the land acquisition matters. The time targets are given to solve the land

acquisition matters in said two road projects and those sections will be handed

over to the contractor.

2.3.1. Rehabilitation/Improvements to sections of Moratuwa – Piliyandala Road The project has been awarded to KD Ebert & Sons Holdings (PVT) on 23rd of

October 2014.

The all major construction activities have almost been completed during the

reporting period, while considering about progress up to 31st March, 2017, the

Physical progress was 96.44%.

2.3.2.. Rehabilitation/Improvements to sections of Kesbewa – Pokunuwita and

Kirulapana – Godagama Road.

The project has been awarded to MAGA Engineering (Pvt.) Ltd, on 9th of

September 2016 and the contract should be completed within two years from the

commencement date.

The Order to Commence was issued on 17th November 2016 for the Section 1 –

B084 Km 13+800 to 16+520 (2.72km),Section 3 – B084 Km 18+600 to 21+800

(3.20km), and Section 5 (amended) – A004 Km 17+260 to 18+200 (0.94km). The rest

of area (9.33km in Sections 2, 4 and 6) will be handed over to the contractor

immediate after the land acquisition completed, that are expected to be finished on

August 2017.

2.3.3. Rehabilitation/Improvements to sections of Southern Expressway –

Matugama Road

The project has been awarded to MAGA Engineering (PVT) Ltd, on 27th June 2016.

Page 10: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

10

Road works have started at the sections 1, and 2. The construction works of section

01 are well progressing. The major culverts and bridges works have been started

while 39/5 bridge works almost has started. Considering about progress up to 31st

March, 2017, the Physical progress is 16.67%.

2.3.4. Rehabilitation/Improvements to CINEC Junction to Ambathale Junction

Link Road

The Letter of Acceptance (LOA) was issued to Olimpus Construction (Pvt)Ltd, and

the work planned to be started from June 2017. The project road hasn’t land

acquisition matters.

Page 11: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

11

3. CONSTRUCTION PROGRESS

The all project roads have started their construction works during the reporting

period except the CP04, while the CP 01 project is nearing completion. The CP-02

and CP03 project have just begun their works.

4.1 Rathmalana-Mirihana (B389) and Moratuwa-Piliyandala (B295) roads. The Contractor has finished his material sources from his crusher, quarry and

asphalt plant at Naboda which is located approx. 50 km away from the road sites.

The monthly plant visits by Client and Consultant have completed in the month of

September 2016.

The all major construction activities have been completed. Related images

pertaining to some of the project activities are given below;

1. Moratuwa-Piliyandala (B295) Road

2. Rathmalana-Mirihana (B389) Road

Figure3:1 completed pedestrian crossing at Km 2+930 road marking at Km 3+860 of B 295 and completed sections at Km 0+200 and Km 0+480 of B389

During the material sourcing period up to December 2016, the contractor has

obtained all the relevant permissions and licenses for quarry, crusher and asphalt

Page 12: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

12

plant operations. The validity periods of given licences are not necessary to extend

due to completion of road works.

Table 3.1. The summary of obtained licences and permits

Type of

Quarry/plant Location

Type of

Approval/

license

Approving

Licensing

Authority

Date of

obtaining

Approval

Date of

validity

end

1.Metal

quarry

Thudugala,

Neboda

EPL

CEA

00376(R8) 24 .06.2015 23.06. 2017

Industrial

Mining

License

GSMB

IML/A/HO/219

5/R/5

22.05.2015 21.05.2017

Explosive

License

District Explosive

controller

(A 275109)

30.06.2015 30.12.2016

2.Crusher

Plant

Thudugala, Neboda

EPL

CEA

01587(R7)04481(R

4)

16.07.2015 15.07.2017

Trade

License Dodangoda LA 18.02.2015 31.12.2017

3. Asphalt

Plant Thudugala,

Neboda

EPL

CEA

05067 (R2) 16.03.2015 31.03.2017

4.Concrete

Batching

Plant

Rukmalgama, Athurugiriya

EPL CEA 01/10/2015 31 01 2017

3.2. CP-02 Rehabilitation/Improvements to sections of Kesbewa – Pokunuwita

and Kirulapana – Godagama Road

The Order to Commence was issued on 17th November 2016 for the sections 1, 3

and 5. Other sections such as sections 2, 4 and 6 are to be granted on August 2017.

The construction works of culverts and bridges of section 01 and 03 have been

started while only clearing and grubbing works are started at section 05.

The contractor has found 06 disposal lands to dispose the waste. The approval

process is being progressed during the reporting period while; the Western

Page 13: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

13

Provincial Waste Authority is willing to accept the unsuitable at their waste

dumping premises situated close to the project road.

The material sourcing sites of the contractor, such as quarry, crusher and concrete

batching plants are operated with relevant updated licenses (See Table 3.3). The

environmental and social issues are negligible in these sites and regular inspections

have been carried out.

The contractor’s own plant sites such as Quarry, Crusher and Asphalt plants are

situated nearby areas such as follows;

Table.3.2. The materials sourcing locations and distance

Plant type Capacity Location Distance from Project Road(KM)

Asphalt 80 ton/hour Homagama 20

Quarry - Kumbuka 5

Crusher 500m3/day Millaniya 35

Concrete Batching Plant

350m3/day Kumbuka 5

The contractor is not operating his own burrow areas and sourcing his sub-base

material requirements from outside commercial base burrow areas.

Table 3:3 The summary of obtained licenses and permits

Type of

Quarry/plant Location

Type of

Approval/li

cense

Approving

Licensing

Authority

Date of

obtaining

Approval

Date of

validity

end

Remarks

1.Metal

quarry

Millaniya,

Horana

EPL

CEA

00976(R8) 10 .06.2016 09.06. 2017

Informed to

renew the

licenses

Industrial

Mining

License

GSMB

IML/A/HO

/7037/R/03

27.05.2016 26.05.2017

Apply to

renewal on

15th April

2017

Explosive

License

District

Explosive

controller

(A 280360)

10.08.2016 14.08.2017

-

2.Crusher Kumbuka, EPL CEA 28.03.2016 27.03.2018 -

Page 14: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

14

Plant Horana 08019(R2)

Trade

License Horana LA 10.0`.2017 31.12.2017

-

3. Asphalt

Plant Hoamagama EPL

CEA

01576 (R8) 07.06.2016 06.06.2017

Informed to

renew the

licenses

4.Concrete

Batching

Plant Kumbuka,

Horana

EPL CEA

13911(Ro) 24.04.2017 23.04.2018

-

Trade

License Horana LA 25.01.2017 31.01.2017

-

Culvert & Bridges

Bridges and Culverts construction activities are progressing in all three sections

while 63% progress is recorded in section 1. The relevant warning signs such as

“Men at works, Road marrows and other signs have properly been fixed.

Figure 3.2 the ongoing construction activities of Culvert (16/1) deck concreting at Km

15+298 and Bridge (17/3) base concreting at 16+321

Other Constructions

Clearing and Grubbing, Roadway Excavation, Rock Filling, and Lined drains

works are progressing in all sections while section 01 almost finished the Clearing

and Grubbing activity.

Restoration of Government properties adjoining to the road is progressing. Under

this activity, mainly boundary walls and utility facilities are considered to be

reconstructed.

Page 15: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

15

3.3. CP-03 Rehabilitation/Improvements to sections of Southern Expressway – Matugama Road.

The Order to Commence was issued on 09th September 2016 for Section 1 – from

Km 42+372 to 37+000 (5.372km). While remain section (5.0km in Section 2) was

given to the contractor on March 2017. Meanwhile the construction works of

section 01 are progressing while the major culverts and bridges works have also

been started. The bridge works of 39/5 works has just started and bypass road

including temporary bridge is constructed to carrying the traffic until new bridge

will be finished. The necessary safety precautions including night time visibility

are taken at the site.

Table 3:4 The summary of obtained licenses and permits.

Type of

Quarry/plant Location

Type of

Approval/lice

nse

Approving Licensing

Authority

Date of

obtaining

Approval

Date of

validity end Remarks

1.Metal quarry

Mr.

Wanniarchchi,

Wallatha,

Naboda

EPL CEA

04762(R5) 21 .11.2016 20.11. 2017

-

Industrial

Mining

License

GSMB

IML/B/HO/1332/LR

/08

21.03.2016 30.06.2017

The

contractor

has applied

to renewal

Explosive

License

District Explosive

controller

(A 280327)

28.12.2016 27.06.2017

Do

2.Crusher

Plant

W.K.K, Neboda

EPL CEA

02547(R7)) 25.05.2016 24.05.2017

The

contractor

has applied

to renewal

on 21st

March 2017

Trade License Dodangoda LA 08.03.2017 31.12.2017 -

3. Asphalt

Plant Danister Estate,

Welipenna

EPL CEA

12060 (R1) 04.01.2017 03.01.2018 -

Trade License Mathugama LA 07.03.2017 31.12.2017 -

Page 16: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

16

4.Concrete

Batching Plant Gabada

Junction, Welipenna

EPL CEA

WE-B 03552(R0) 28.10.2016 27.10.2019

-

Page 17: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

17

4. Completion of the Environmental Compliance

The SRCP projects have been categorized under “B” category of the ADB

environmental and safeguard policy statements in 2009. Therefore the PMU have

submitted only IEEs reports to ADB regarding the five road sections. The Basic

Information Questionnaire, which is a report that included all the significant and

anticipated impacts of the proposed project, was submitted to the CEA for each

projects, the B084 and A004 roads fall under the EIA category while other projects

(B157, B 389 and B 295) only required basic questionnaire. The status of the

government compliance details are as follows;

4.1. CP01: Rathmalana-Mirihana (B389) and Moratuwa-Piliyandala (B295)

The Initial Environmental Examination reports (IEE) had been submitted for the

Rathmalana-Mirihana and Moratuwa-Piliyandala road respectively. Those reports

were approved by the ADB.

The environmental approvals are granted by the Central Environmental Authority

(CEA) based on the Basic Information Questionaries to implement the road works

for the above two projects. The validity period of above project roads will expire in

the year 2017 and renewal is not required because the construction works of the

road have almost been completed (See Annex 01).

Road Code Name of the Road Validity Period

From To

B389 Ratmalana-Mirihana Road 13. 02. 2013 20. 09. 2017

B295 Moratuwa-Piliyandala Road 11. 03. 2013 12. 05. 2017

The contractor’s Environmental Management Action plan (EMAP) and Traffic

Management Plan have been approved on August 2015 and September 2015

respectively by the Client and Consultant.

Environmental parameter observation activity for the pre construction stage (Base

line) and construction stage were completed. The results have been submitted to

the client.

Page 18: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

18

Monthly environmental meetings have been completed on December 2016 due to

end of the major construction works.

The restoring activities such as debris cleaning at yards and office locations, stock

piling and disposal yard (Suwarapola) have been initiated. The contractor has

prepared a rehabilitation report, which is included all his restoring activities is

being reviewed.

4.2. CP02: Kirulapana-Godagama (A004) and Pamankada-Pokunuwita (B084)

The Initial Environmental Examination reports (IEE) of both road projects had

been approved by the ADB.

The environmental approvals are also granted by the Central Environmental

Authority (CEA) based on the submitted EIA to implement the road works for the

above two projects (See Annex 01).

Road Code Name of the Road Validity Period

From To

Aoo4 Kirulapona-Godagama Road 24.03. 2014 23.03.2020

B084 Kesbewa-Pokunuwita Road 25.03. 2013 24.03.2020

The contractor’s Environmental Management Action plan (EMAP) and Traffic

Management Plan have been approved on November 2016 by the Client and the

Consultant.

When the meetings are held, joint site inspections are carried out together with

client, consultant and contractor to observe the environmental and safety lapses.

During the site visits, any recorded public complains are also being followed up.

4.3: CP03: B157 Mathugama-Southern Highway

The Initial Environmental Examination report (IEE) had been submitted on May

2013 and it was approved by the ADB.

Page 19: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

19

The environmental approval has been granted by the Central Environmental

Authority (CEA) based on the Basic Questionnaire to implement the road works

(See Annex 01).

Road Code Name of the Road Validity Period

From To

B157 Mathugama-Southern Highway 24.11.2014 06.01.2018

The contractor’s Environmental Management Action plan (EMAP) and Traffic

Management Plan have been approved on November 2016 by the Client and the

Consultant.

4.4. Changes in project scope The proposed scope of the project of Southern Highway to Mathugama has been

amended as follows.

Mathugama-Southern Highway (B157), the initial approvals were granted to carry

out about the 12 km length to 32 km post from 40 km post. The two kms length has

been excluded from 30km to 32km, as 2Km length has already been developed

through an another project. Hence, there has been a reduction in the road length

from 12.37 km to 10.37km.

Page 20: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

20

5. SUMMARY OF ENVIRONMENTAL MITIGATIONS AND

COMPENSATION MEASURES

Based on the approved EMAP, the sub-project contractor has to periodically carry

out the monitoring of selected environmental parameters such as ambient air

quality, noise levels, water quality and vibration levels. The contractor should

monitor the above parameters during the pre-construction (Baseline), construction

and post- construction or operation period of each project road.

In order to prevent lowering of green cover along the road due removal of existing

tree/bushes, the contractor is obligated to implement suitable tree planting

programs along the road or within the project road area.

In additionally the contractor should rehabilitate their all material sourcing

locations, yard and disposal sites, immediate after the completion of the project

activity.

5.1. Moratuwa - Piliyandala (B295) and Ratmalana - Mirihana (B389) 4.64 km.

Collection of baseline and the construction stage data have been completed. Data

was collected by the approved sub-contractor of Industrial Technology Institute

(ITI) during 2015-2016. The results have been submitted to the PMU of the RDA.

The operation stage data will be collected as immediate after the road section

completed and handed over to the client.

During the construction period of B295 road, all the readings of water samples

found to be similar to baseline values but TSS was less and E Coli had increased

not due to construction activities. B 389 when compared with baseline values, pH

was at neutral range, TSS decreases and E coli level has increased, not due to

construction activities. It was identified that the domestic waste water discharged

into surface water body was coursed to increase E-coli in the area.

According to the noise measurement test results of B 295, allowable noise level is

75dB(A). Except at B389 in front of Mahamaya School (80dB(A) and at B295 near

Indra Traders, Piliyandala (76dB(A), noise level all the other locations were within

allowable levels.

Page 21: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

21

Except for location, Kospalana Junction, all the parameters of other locations were

well below the ambient air quality standards. TSPM level is high at Kospalana

Junction, this may due to vehicular movement of the road.

As per the given vibration data, all the measured levels (baseline data) are within

the standard level. The vibration levels have not exceeded with normal vehicle

movement of these two road sections.

A detail of observed data during the pre-construction period is given in Appendix

02.

Considering about the awareness programs, there were nine (09) programs which

are related to HIV/AIDS, Human Trafficking, and Environmental awareness held

by the project staff during the reporting period as follows.

Table 5:1 A summary of the held HIV/AIDS programs

Date & Venue Resource Persons Participated personals

Total

participants

Male Female

11/06/2017 at RE’s

office in Maharagama

National HIV/AIDS control

unit of Sri Lanka(Dr. Janaki

Pandithrathne, Dr.

N.Dissanayake and Dr.

P.Premadasa

Labours, site supervisors

and staff members

53 03

13/09/2016 at DS

office in Maharagama

Do Government officers of

surrounding areas of

project road

25 67

22/10/2016 at Rural

Hospital in Neboda,

Kaluthara

Dr.Duminda Senevirathne and

Dr.H.S.S Ruwan

Workers and contractor’s

of Plant sites and

surround communities

17 25

20/11/2016 at Rural

Hospital in Neboda,

Kaluthara

Do Do

43 19

There were four (04) programs on HIV/AIDS conducted by the National

HIV/AIDS Control Unit. The programs had been organized to improve the

awareness among the construction workers as well as community members of

Page 22: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

22

project area. These programs were keenly conducted by close supervision of Dr.

(Ms.) Janaki Panditharathne, who represents the National HIV/AIDS Control Unit

of Sri Lanka.

With regards to the environmental awareness programs, there were two programs

held under the topic of Solid Waste Management and Recycling. These programs

have been organized to improve the knowledge of project areas communities.

Meanwhile, the contractor had organized the two human trafficking programs,

two child protection programs and one income generation program as follows;

Table 5:2 The summary of conducted other programs

Program Date & Venue Resource persons participation

Female Male

Solid Waste

management and

Human

Trafficking

26th May 2016 at

RE’s office

Mr. S. Jayatissa, CEA, Sri Lanka

Mr. M.Dissanayake, Attorny at Law,

Colombo

06 42

Solid Waste

management &

Recycling

21st July 2016 at

Rukmalagama

Mrs. Shantha Dayaseeli, CEA, Sri

lanka 15 15

Road Safety and

Child protecting

14th July 2016 at

Pre-school,

Suwarapola

Ms.Kusum Punchihewa, Sri Lanka

Police. 32 8

25th August 2016 at

Agrarian Service

centre, Udahamulla

Do

18 18

Human

Trafficking and

Income

Generation

Activity

30th September 2016

at School in

Piliyandala

Mr.Lasantha Alwis

82 23

The all lectures were conducted by specialized personnel on the relevant field.

Page 23: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

23

Figure 5:1 The held Safety and Environmental awareness meetings The scheduled Gender Action Plan (GAP) and the environmental awareness programs have been conducted successfully by CP 01 project and the detail of environmental mitigation activities performed by the contractor are summarized as below in Table 5.2. Table 5.2 A summary of the major environmental mitigation activities of CP 01

EMP Requirement Compliance

Attained

Comment on Reasons for

Partial or Non-

Compliance

Issues for Further Action

and Target Dates

1 Environmental

Parameter Observation

Baseline sampling

Yes Completed -

Construction stage

Yes Completed -

Operational Stage

No To be

conducted

The activity will be

conducted Immediate after

HIV/AIDS program held on 11/06/2016 and 13/09/2016

Solid Waste Management program held on 26/05/2016 and 30/09/2016

Page 24: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

24

the road section handed over to

the RDA

2 Fauna flora survey Yes Completed -

3 Environmental

awareness Yes Completed -

4 Health & Safety

Awareness Yes Completed -

5 HIV/AIDS programs Yes

Completed -

According to the contractor’s completed compensative tree planting program, 260

saplings were planted. A tree enrichment program also carried out to replacement

of wilted trees of previously replanted areas. The following table shows the

summary of completed works.

Table: 5:3 A summary of completed tree planting program

Programme Venue/Date Number of Plant

Plant Varieties Survival rates and

action taken

Replanting Programme 01

Mirihana Police Ground & Subadrarama Temple premises on 05/05/2012

50

Mangifera indica (Mango),

Nephelium lappaceum (Rambutan), Aegle marmelos (Beli), Terminalia arjuna (Kumbuk) Artocarpus heterophyllus (Jack), Cassia fistula (Ehela) etc,

20 plants were replanted by plant enrichment program

Replanting Programme 02 For World Envi: Day

Waste Management Authority premises at Karadiyana on 07/06/2016

20

Terminalia arjuna (Kumbuk), Cassia fistula (Ehela), Aegle marmelos (Beli)

4 plants were replanted

Replanting Programme 03 Mangrove Planting

Along the Bolgoda lake at Waste Management Authority premises at Karadiyana on 16/08/2016

100

Mangrove Plants such as Rhizophora mucronata, and R. Apiculata (Maha Kadole, Rathu Kadole.).

90% plants survived and wilted plants were not replaced because the WM Authority promised to complete the task by themself

Page 25: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

25

Replanting Programme 04

Sri Siddartha Collage premises and play ground area on 26/10/2016

50

Homegarden species such as Mangifera indica (Amba), Punica granatum (Delum) Psidium guajava (Pera), Annona muricata(Katu anoda) ,Persea Americana (Aligeta pera), Cinnamomum verum(Kurudu), Citrus spp.(Dehi) and Piper nigrum(Gammiris). Forest trees such as Swietenia macrophylla (Mahogani),Tactonia grandis (Thekka), Berrya cordifolia (Halmilla) , Pongamia pinnata (Karanda)etc.

3 plants were

replanted

Replanting Programme 05

Stenly Thilakarathna School premises on 23/11/2016

40

Home-garden species such as Flacourtia Indica(Uguressa), Syzygium aqueum (Jumboo), Punica granatum (Delum), Psidium guajava (Pera), Annona muricata(Katu anoda), Persea Americana (Aligeta pera),Citrus spp. and Piper nigrum(Gammiris) Shade and forest trees such as Pongamia pinnata(Karanda) Messua ferrea (Na) etc.)

All the plants were

at good condition. It

was observed

100% survival rate

Figure 5:2 A mango sapling is planted by Project Director at Police Ground premises while

Resident Engineer is plating a mangrove plant at Bolgoda lake area

5.2. Kesbewa - Pokunuwita Road (B084) and Kirulapana - Godagama Road (A004

Collection of baseline data has been completed and this activity was done under

the approved sub-contractor. The Industrial Technology Institute (ITI) was selected

for the above purpose and it was conducted in December 2016. The results have

been submitted to the PMU of the RDA. The construction stage data will be

Page 26: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

26

collected within six month intervals and next sampling will be conducted on June

2017.

According to the test results of water quality, pH is within standard levels, while

ground water sample did not fall within the stipulated levels. pH is acidic (6.2),

standard in 6.5-8.5 range. pH acidic due to soil nature. This type of soil contains the

Humic acid. All six samples of “BoD5” levels are within standard level. However

all the locations’ day time background noise level was higher than the permissible

level of the area and total suspended particulate matter (TSPM) of air quality

monitoring was lower than the permissible level of 450µg/m3 of the all sampled

locations.

During the reporting period, there was one (01) program on HIV/AIDS conducted

by MOH office staff with coordinating of the National HIV/AIDS Control Unit of

Colombo. The program was useful to improve the knowledge of the construction

workers as well as community members of project area.

Similarly, the contractor has conducted two road safety awareness programs with

participation of Police traffic control units within the area. The details of conducted

programs are as follows,

Table 5:4 A summary of the held HIV/AIDS programs

Program Date & Venue Resource persons participation

Female Male

HIV/AIDS

prevention

programm

11/01/2017 at

Boralesgamuwa

Dr.Samanthi Wijesundara, and

Dr.Dilshan Wijerathne, MOH office,

Boralesgamuwa

20 20

Road safety

Awarenss

programm

7th March 2017 at

Guidance

international

School, Kesbewa

Mr. Madugoda, Piliyandala Police.

28 16

Mr.M.K Jagath and Mr.Indika Prasad

of Moragahahena Police, Kesbewa 70 00

Similarly, the scheduled Gender Action Plan (GAP) and the environmental

awareness programs are being progressed by CP 02 project and the detail of

Page 27: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

27

environmental mitigation activities performed by the contractor are summarized

as below in Table 5.5.

Table: 5:5 A summary of the major environmental mitigation activities of CP 02

EMP Requirement Compliance

Attained

Comment on Reasons for

Partial or Non-

Compliance

Issues for Further Action and Target

Dates

1 Environmental

Parameter Observation

Baseline sampling

Yes Completed -

Construction stage

Yes

The quotations were called to 1st sampling and it has been approved by PIC. Sampling will be taken place in June 2017.

Operational Stage

No To be

conducted

The activity will be conducted Immediate after the road section handed over to the RDA

2 Fauna flora survey Yes Completed -

3 Environmental

awareness NO

More programs to

be conducted

The contractor is advised to conduct the programs

4 Health & Safety

Awareness Yes

More programs to

be conducted -

5 HIV/AIDS programm Yes Being

progressed

The contractor is advised to expedite the activity

Page 28: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

28

Figure 5: 3 The conducted HIV/AIDS programs in Boralesgamuwa on 21/01/21

and Gonapola Temple main hall on 3/4/2017.

Having discussed about the tree planting program, a plant nursery is established

to maintain the selected saplings inside the contractor’s yard which is intended to

be used for future tree planting programs along the road. In comparison to the CP

01 project road, this road has adequate spaces within the ROW which can be used

to tree planting activity.

Figure 5:4 A nursery which is managed to replant along the ROW of the road

In addition to the above mentioned program, the contractor was requested to carry

out the plant enrichment program along the Piliyandala bypass road which was

constructed by previous project of NHSP funded by ADB. A greenery program

Page 29: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

29

was previously conducted and now it is likely to be abandoned. Therefore the

client has requested to carry out the plant enrichment program.

Figure 5:5 The weeds spread over the road side trees and the Green Islands are

abandoned.

5.3. Southern Expressway - Matugama Road (B157)- 10.37km

Initially, the collection of baseline data has been completed and the task was

carried out by Industrial Technology Institute (ITI) which is a government own

institute. The activity was conducted on December 2016. The results have been

submitted to the PMU of the RDA. The construction stage data will be collected by

six month intervals and next sampling will be conducted on June 2017.

With regards to the submitted test results of water quality, the pH, BOD and

oil/greece content were at its standard level in all locations. According to the

measured vibration levels, the maximum permissible levels of interim vibration

standards have not been exceeded with the vehicle movements of this road section.

As compared to the measured results of air quality, TSPM (03hr) average was

lower than the permissible level of 450µg/m3 at all locations.

During the reporting period, there was one (01) program on HIV/AIDS conducted

by MOH office staff with coordinating of National HIV/AIDS Control Unit of

Colombo. The program has been organized for the community in the

neighbourhood of project area and as well as for the construction workers.

Page 30: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

30

Similarly, the contractor had conducted a one road safety awareness programs

with participation of Police traffic control units within the area. The details of

conducted programs are as follows,

Table 5:6 A summary of the held HIV/AIDS programs

Program Date & Venue Resource persons participation

Female Male

HIV/AIDS

prevention

program

21/01/2017 at

School Auditorium,

Walipenna

Dr. Geethani Samaraweera and Dr.

S.A.P Nishanthi, MOH office,

Nagoda, Kaluthara

35 19

Road safety

Awareness

program

15/03/2017 at

School Auditorium,

Owitigala,

Mathugama

Mr. Rajarathne Jayasundara, Police

station, Welopenna. 42 11

In the same way, the scheduled Gender Action Plan (GAP) and the environmental

awareness programs are being progressed by CP 03 project. However an

implementation delay was observed which was due to various reasons and the

contractor was informed to expedite the work without any further delay. The

details of environmental mitigation activities done by the contractor are

summarized as below in Table 5.7.

Table 5:7 A summary of the major environmental mitigation activities of CP03

EMP Requirement Compliance

Attained

Comment on Reasons for

Partial or Non-Compliance

Issues for Further Action and Target

Dates

1 Environmental

Parameter Observation

Baseline sampling

Yes Completed -

Construction stage

Yes

The quotations were called to 1st

sampling and it has been approved by

PIC

Operational Stage

No To be conducted

The activity will be conducted

immediate after the road section

handed over to the RDA

Page 31: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

31

2 Fauna flora survey Yes Completed -

3 Environmental

awareness Yes

More programs to be conducted

-

4 Health & Safety

Awareness Yes

More programs to be conducted

-

5 HIV/AIDS program Yes Being Completed -

Figure 5:6 Conducted awareness programs of CP 03 project, Above: Road safety

awareness meeting at Owitigala School hall conducted on 15th March 2017. Below:

HIV/AIDS awareness program conducted at Welipenna School hall on 21st January 2017

The contractor has planned to implement a tree planting program along the road in

the space available in ROW immediate after road completion. The root bowling

trees will be used for this activity and community tree planting programs are also

planned to be implementation.

Page 32: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

32

6. SUMMARY OF ENVIRONMENTAL MONITORING

Based on the approved EMAP, the sub-project contractor has to periodically carry

out the monitoring of selected environmental parameters such as ambient air

quality, noise levels, water quality and vibration levels. The contractor should

monitor the above parameters during the pre-construction (Baseline), construction

and post- construction or operation period of each project road.

6.1 Moratuwa - Piliyandala (B295) and Ratmalana - Mirihana (B389) 4.64 km

Collecting of environmental parameters such as Air quality, water quality, Noise

and Vibration levels for Pre-construction (baseline data) and the construction stage

had been observed. The task was assigned by the approved sub-contractor of

government of Sri Lanka. The project road and the material sourcing locations

were also subjected to monitoring and the following table shows the data collecting

activity of the CP 01 project.

Table 6:1 The dates of environmental parameters monitoring

Parameter Baseline Construction stage I Construction stage II

Water 06/10/2015 30/06/2016 21/09/2016

Air 06/10/2015 30/06/2016 12/09/2016

Noise 13/10/2015 28/04/2016 02/08/2016

Vibration 13/10/2015 14/06/2016 04/08/2016

The detail of the observed data that was during the pre-construction period is

given in Appendix 2.

According to the observed water quality data of B295 road, it was similar to baseline

values, but TSS was low and E-coli had increased during the construction stage I and II

data. In B 389 road, when compared with baseline values, pH in neutralize range, TSS

decreased and E-coli had increased during construction stage II data. Considering about

the air quality results, baseline measurements were carried out with 8hr average but

during the construction stage I and II data measurements were carried out with 1hr

average. All locations in both roads of B295 and B 389, the TSPM (1hr) was higher than the

allowable level (500μg/m3) during the construction stage II. The noise level of B295 road,

the measured levels of two locations (Kospalana and Suwarapola) were higher than the

Page 33: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

33

baseline values during the construction stage I and II, but lower than the allowable

level(75dB(A). At Piliyandala town, measured levels were lower than baseline values and

lower than allowable level. B 389 road locations, all three locations during construction

stage I and II measured locations are lower than baseline values and lower than the

allowable level (75dB)

6.2 Kesbewa - Pokunuwita Road (B084) and Kirulapana - Godagama Road

(A004).

Baseline data collection for the pre-construction stage of the project roads, i.e. the

Ambient Air, Water, Noise and Vibration levels, were collected before

commencement of the main construction activities. The data was collected in

December 2016, and the construction stage data will be collected in June 2017.

The detail of the observed data that was during the pre-construction period is

given in Appendix 2.

Considering about the water quality results, the pH values were within the

standard for all surface water samples, but ground water samples’ pH was 6.2,

which was not within standard. All eight locations of air quality samples of B084 ,

A004 and all plant sites baseline values of TSPM (3hr average) was lower than the

permissible level of 450/μg/m3. According to noise levels, most of the locations

background level is higher than the permissible level of the area and all existing

measured noise levels are higher than the permissible levels at day times. These

may due to existing traffic nature. The results of the vibration levels of the project

area, maximum permissible levels (1.0, 2.0, or 4.0) of interim vibration standards

have not become exceeded with the vehicle movements of these road sections.

6.3 Southern Expressway - Matugama Road (B157)

Similarly, the baseline data collection of the project road was collected before

commencement of the main construction activities. The observer of the event was

Industrial Technological Institute (ITI). During the sampling, water, air, noise and

vibrations were sampled along the project road as well as selected material

sourcing location of the contractor.

Page 34: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

34

The detail of the observed data that was during the pre-construction period is

given in Appendix 2.

According to the measured water quality of all three locations pH, BOD and grease

content are within standard. All three locations of air quality samples, TSPM 3hr average

is lower than the permissible level of 450/ug/m3. The all existing measured noise levels

are higher than the permissible level of day time, this may due to traffic noise. Considering

about the vibration levels, permissible level of interim standards have not been exceeded

with vehicular movement of this road section.

6.4 Compliance Inspections

During the reporting period, road construction works were progressing in all sub-

projects while CP-01 works were nearing completion.

Monthly field inspections were carried out by Environmental Specialists of the

Employer, PIC and Contractor. Appendix 03, summarizes the activities carried out

in CP-01, CP-02 and CP-03 Sub-projects, their impacts to the environment (as

observed during each field visit mainly by the ES of PIC), suggestions given by ES

to mitigate, avoid or minimize the adverse impacts, effectiveness of the migration

measures adopted, and any further action needed.

Table 6.2 The status of the contractor’s EMP implementation

Sub Project

EMP part of

Contract

Document

(Yes/No)

EMP being

Implemented

(Yes/No)

Status of EMP

Implementation

(*)

Action Proposed

CP-01 Yes Yes Good Advised to fully Implement the EMAP

submitted by Contractor

CP-02 Yes Yes Good Advised to fully Implement the EMAP

submitted by Contractor

CP 03 Yes Yes Good Advised to fully Implement the EMAP

submitted by Contractor

(*) 1 – Very good (All required Mitigation Implemented), 2 – Good (The majority of required Mitigation

Implemented), 3- Fair (Some Mitigation Implemented), 4– Poor (Few Mitigation Implemented) ,5 – Very Poor

(Very few or No Mitigation Implemented)

Page 35: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

35

Although the contractors have been placed in good category based on the EMP

implemented, their traffic and safety measures should be upgraded further due to

high traffic congestion in the project area, especially in the morning and evening

time at CP01 and CP02. The detailed compliance to EMP is provided in Appendix

04 and their activities are separately discussed as follows.

Considering the total number of 19 mitigation actions to be complied in CP 01

project, 13 actions have been fully complied; while six (6) mitigation actions are

partly complied. The main reasons for the partly complied actions were; the

activities will be implemented after handed over the road sections. Other than

these, set of all other mitigation actions were completed by the contractor.

Because of newly started projects, all the mitigation actions that are described in

EMP should be implemented or complied by the contractors of CP02 and CP 03.

The monthly payment item for EMP requirements is provided in the contract. The

payment is released after receiving of the recommendations based on the monthly

inspections and observations by employer and the PIC Environmental Specialists

(ES) with participation of the contractor’s Environmental Officer (EO).

According to approved payment percentage of the EMP payments (Table 6.2), the

contactor has obtained 75% of average payment values base on the EMP

implementation activities done during each month.

The following table shows the monthly payment percentages that had been made

to the contractor based on the EMP implementation in the project.

Table 6.3. The approved monthly percentages for EMP implementation during the

reporting period

Months EMP implementation

Approved percentage (%)

CP01 CP 02 CP 03

May 2016 78 - -

Page 36: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

36

June 2016 83 - -

July 2016 66 - -

August 55 - -

September 2016 65 - -

October 2016 35 - -

November 2016 80 - -

December 2016 87 - 69

January 2017 - 79 69

February 2017 - 89 70

March 2017 - 88 83

April 2017 91 81

Page 37: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

37

7. PUBLIC COMPLAINTS

The Grievance Redress Committees (GRCs) have been established to look into the

public complaints regarding the social and environmental impacts during the

period of construction works for every sub project. The GRC considers the

problems that could not be solved directly by the Employer, Consultant and

Contractor. The GRC committee holds meetings with all responsible parties to

yield the best solutions for the problems.

Table 7:1 The established GRC dates and Divisional Secretariat Offices Package Road Name Divisional Secretariat GRC established date

CP 01

Rathmalana - Mirihana Road (B389) Maharagama 05. 05 .2015

Moratuwa - Piliyandala Road (B295)

Sri Jayawardenpura 01.11 .2014

CP 02

Kirulapana - Godagama Road (A004)

Homagama 05. 05 .2015

Kesbewa - Pokunuwita Road (B084) Kesbewa 05. 05 .2015

CP 03 Southern Expressway - Matugama

Road (B157 Mathugama 05. 05 .2015

The PMU and Divisional Secretary arrange the GRC meetings upon receiving of

public complaints to solve the problems. Considering the number of complaints

received so far, there were two GRC meetings conducted at Divisional Secretariat

Office in Kesbewa to discuss the received 04 complaints regarding to CP01 project

and these problems have been solved.

The above mentioned GRC meetings were conducted at Divisional Secretariats office in Kesbewa respectively on 23rd December 2016 and January 2017.

Page 38: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

38

Figure: 2.1 The GRC Committee members including chief incumbent of Buddhist temple, Project Engineer of CP01, Divisional Secretariat (Kesbewa) and Resettlement Assistant were chaired and discussing about the public complains.

Further, the employer, the consultant and the Contractor attend the public

complains which are received in written form and through the electronic media (E-

mail, Fax and Telephone). Moreover, all complains received have been listed out

and discuss in the monthly progress meetings. The summary of the received

complaints up to 31st March 2016 are given in Appendix 05. There were 99

complains have received from both B295 and B389 roads so far, most of them are

requesting of cover slabs and proper access to their hoses and business premises.

Among them 70 complains were already solved and others are being completed by

involving the related line agenesis. Some of the complaints await to insurance

claims and those cases will be completed immediately after the claim area received.

Likewise, there were 31 complaints received so far from CP 02 project, among these

complaints 15 have been solved, while 13 are pending and, 3 are progressing. In

the same way there were 44 complaints received up to 31st march 2016 from CP 03

project, while 15 complaints are already solved, 18 complaints are being

progressed and 11 complaints are pending.

In the monthly environmental meetings progress, they draw their attention and

discuss about the public complaints.

In addition, small scale Community Committee Meeting had been conducted by

CP 01 project (mainly by appointed Environmental Officer of the project) aiming

to address the public disturbances while construction activities are progressing.

It was suggested to conduct the Community Committee Based Organizations if

necessary in the project affected areas in CP02 and CP 03 (public and private

authorities and personnel) which will address the problems regarding the

constructions.

Page 39: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

39

8. STATUS OF COMPLIANCE TO LOAN AGREEMENT

Based on the information provided in the above sections the compliance of the

project to the environment safeguards related clauses in the “Loan Agreement” are

generally satisfactory. Detail of the compliance of environmental clauses is

provided in the table below.

Clause Status of Compliance 1. Schedule 4, Conditions for Award of Contract Para 6: RDA shall not award any Works contract which involves environmental impacts until: (a) CEA or the project approving agency designated by CEA has granted the final approval of the IEE; and (b) RDA has incorporated the relevant provisions from the EMP into the Works contract.

Complied. All contracts have been awarded after CEA approval of the respective project. All bidding documents included the EMP before issuance to the contractor.

2. Schedule 5, Environment, Para 4: The Borrower shall ensure or cause RDA to ensure that the preparation, design, construction, implementation, operation and decommissioning of the Project and all Project facilities comply with (a) all applicable laws and regulations of the Borrower relating to environment, health and safety; (b) the Environmental Safeguards; and (c) all measures and requirements set forth in the relevant IEE, the relevant EMP, and any corrective or preventative actions set forth in a Safeguards Monitoring Report.

Complied. All measures in the IEE and EMP are being implemented.

3. Schedule 5, Safeguards – Related Provisions in Bidding Documents and Works Contracts Para 9: The Borrower shall ensure or cause RDA to ensure that all bidding documents and contracts for Works contain provisions that require contractors to: (a) comply with the measures relevant to the contractor set forth in the IEEs, the EMPs and the RPs (to the extent they concern impacts on affected people during construction), and any corrective or preventative actions set forth in a Safeguards Monitoring Report; (b) make available a budget for all such environmental and social measures; (c) provide RDA with a written notice of any unanticipated environmental,

Complied. All bidding documents included relevant provisions from the IEE and EMP. The contractor is providing budget for implementing the EMP There have been no unanticipated environmental risks so far

Page 40: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

40

resettlement or indigenous peoples risks or impacts that arise during construction, implementation or operation of the Project that were not considered in the IEE, the EMP and the RP;

4. Schedule 5, Safeguards Monitoring and Reporting Para 10: The Borrower shall do the following or cause RDA to do the following: (a) submit semi-annual Safeguards Monitoring Reports to ADB and disclose relevant information from such reports to affected persons promptly upon submission; (b) if any unanticipated environmental and/or social risks and impacts arise during construction, implementation or operation of the Project that were not considered in the relevant IEE, EMP and/or RP, promptly inform ADB of the occurrence of such risks or impacts, with detailed description of the event and proposed corrective action plan; and (c) report any actual or potential breach of compliance with the measures and requirements set forth in an EMP or a RP promptly after becoming aware of the breach.

Being complied. Since the project is environment category B, the annual environmental monitoring report is being submitted. There have been no unanticipated environmental risks so far. There has been no breach of compliance to the EMP so far.

Page 41: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

41

9. CONCLUSION

The guidelines for Environmental protection and pollution control for construction

activities are clearly defined in the EMP for all sub-projects. In addition, the

Contractor’s EMAP provides further specific time lines & schedules to protect

project impacted areas by observing the selected environmental parameters (i.e.

Water, Air, Noise & Vibration) to ensure that the surround environment is

protected.

Firstly, the completed project road of CP 01 was successfully implemented their

proposed mitigation measures that were proposed by employer and the consultant

during their site observations. The issues at the contractor’s Asphalt plant were

satisfactorily solved, but he had taken a long period of time to rectify these issues.

Therefore, the all contractors must be taken the proposed remedial actions as soon

as possible because these impacts are irreversible. It was revealed that the

contractor’s quick response/actions are very important when addressing the

construction related environmental problems.

Secondly, the weekly site inspections are carried by the Contractor, while Monthly

Inspections are continued by the Environmental Specialists of the Employer and

PIC. The monthly environmental meetings conduct regularly and the contractor’s

participation was satisfied.

Site inspection will be regularly carried out to ensure that Environmental impacts

are being adequately mitigated and to ensure continuation of compliance with

stationary regulations as required by laws and accepted in the EMP. The

Contractor is being regularly guided and instructed to pay attention to

environmental issues and adhere to the provisions of EMP and his own EMAP.

The ongoing projects (CP02 and CP 03) environmental monitoring activities are

being progressed as proposed scheduled while final stage monitoring activity will

be completed by CP 01.

Finally, the overall status of implementation of environment safeguards under the

project is satisfactory.

Page 42: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

42

Appendix: 01

1.1 CEA approval for B295 road.

Page 43: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

43

1.2 CEA Approval for B389 road

Page 44: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

44

1.3 CEA approval for B084

Page 45: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

45

1.4. CEA approval for A004 road

Page 46: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

46

1.5 CE Approval for B157 road

Page 47: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

47

Appendix 02 The Summary of tested parameters of CP 01

Table 2.1. Water Quality results

Road Section

Sample location Date of Sampling pH

EC μs/cm

DO mg/l

TSS mg/l

BOD mg/l

Oil and grease mg/l

E.Coli Chloride mg/l

Sulphate mg/L

Baseline(6th October 2015)

B 295 Bolgoda Ela upstream

7.30 309 3.42 40 03 ND ND 34 19

B 389 Irrigation canal upstream

7.47 366 5.07 75 04 ND ND 31 20

Construction Stage-I (12th July 2016)

B 295 Bolgoda Ela upstream

7.42 1109 5 14 3 ND 20 254 40

B 389 Irrigation canal upstream

5.33 380 3 25 2 ND 110 32 17

Construction Stage-II(21st September 2016

B 295 Bolgoda Ela upstream

6.93 366 5.8 55 2 ND 2.2*104 31 13

B 389 Irrigation canal upstream

6.88 17680 6.9 15 3 ND 170 5706 750

Surface water quality standards

6-9 - - - 05 0.1 Negative 1200 -

EC=Electrical conductivity, DO=Dissolved Oxygen, TSS=Total Suspended Solid, BOD3=Biological Oxygen Demand, ND=Not Detected

Page 48: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

48

Table 2. 2 Baseline Noise levels

Road Section

Measured locations Base Line Construction Stage-I Construction Stage-II

ENL.dB(A) RBL dB(A) ENL.dB(A) RBL

dB(A) ENL.dB(A)

RBL dB(A)

B 389

Day Night Day Night Day Night Day Night

Kattiya Junction 74 73 64 63 71 NS 70 NS

Gansabha Junction 75 73 69 68 74 NS 72 NS

Front of Mahamaya School 74 73 64 63 80 NS 71 NS

B 295

Kospalana Junction 61 60 56 53 72 NS 73 NS

Suwarapola Junction 67 67 60 59 71 NS 72 NS

Indra Treaders, Piliyandala 78 72 69 63 76 NS 72 NS

ENL=Existing Noise levels(L Aeq)-dB-(A), RBL-Rating Back Ground Noise level(L A90-15min) NS=Not Sampled Standard Maximum Permissible Noise Levels at Boundaries in LAeq'T.

Areas LAeq', T

Day time Night time

Low Noise 55

45

Medium Noise

63* 50

High Noise

70 60

Silent Zone

50 45

* Provided that the noise level should not exceed 60 dB (A) inside existing houses, during day time. LAeq', T=the equivalent continuous, A- weighted sound pressure determined over a time interval T(in dB) The project area falls into the medium noise level zone

Page 49: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

49

Table 2.3 Baseline vibration levels

Road section Measured locations A(ROW) B(ROW=10m) C(ROW+20m)

B 295

Near Sri Wijerama Temple 0.572 0.199 0.371

Suwarapola Bodhi 0.265 0.092 0.142

Near Church 0.209 0.145 0.135

Near Bauddaloka Mawatha 0.157 0.140 0.134

Near School lane 0.207 0.101 0.096

B 389

Near Mirihana Junction 0.32 0.14 0.095

Subadrarama Temple 0.26 0.09 0.075

Court complex, Gangodawila

0.16 0.085 0.085

Mahamaya Girls College 0.365 0.105 0.08

Walauwatta Junction 0.09 0.072 0.072

Maximum Peak Value in Velocity mode (mm/sec) day time-one hour measurement average, Standreds-02mm/sec(type 03)

Page 50: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

50

Table 2.4 Baseline air quality results

Road Section

Mesured Locations

So2(8hr) (ug/m3)

NO2(8hr) (ug/m3)

CO(1hr) (ppm)

O3 (1hr) (ppb)

TSPM (ug/m3) 8hr

TSPM 8hr (night)

Wind Speed (ms-1)

Wind Direction

B 295

Indra traders, Piliyandala

52.0 21.0 1.8 0.01 319 48 1-2 NE

Suwarapola 30.4 12.6 1.4 0.02 236 38 1-3 NE

Kospalana Junction

30.3 8.4 1.0 0.01 455 57 2 N

B 389

Gansaba Junction

38.8 21.4 4.5 0.01 278 151 2 E

Kattiya Junction

41.0 11.8 0.8 0.01 165 91.4 2 NE

Mirihana Junction

44.7 6.8 0.9 0.01 158 111 2 NE

Maximum Permissible Level

120 150 26 100 350

Page 51: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

51

Appendix 2(A) The Summary of tested parameters of CP 02

Table 2.5 Water Quality results

Road Section

Sample location Date of Sampling pH Temperature (0C)

TSS mg/l

BoD5 (mg/l) 100ml

Oil and grease mg/l

E.Coli

B 084

Pinwala Ela, Pokunuwita at 28+000Km RHS

28th December 2016

7.20 30 44 03

ND ND

Maha Oya upstream at Gonapala Junction at 23+280 km RHS

28th December 2016

7.76 29 08 02

ND ND

Maha Oya upstream at Gonapala Junction at 22+760 km LHS

28th December 2016

6.80 28 10 02

ND 140

Kimbulkatuwa Ela upstream at18+720 km LHS

28th December 2016

6.60 30 20 05

ND 92

Maha Oya upstream at 16+320 Km LHS

28th December 2016

6.60 29 07 04

ND 220

A004 Well at Mr. Jayakody(near Army Camp in Homagama)

28th December 2016

6.20 27 - 02

ND 550

Surface Water Quality Standard 6-9 - - 05 Negative Negative

ND=Not detected Note: For all samples, pH is within standard, while ground water sample does not fall within standard. All six samples ‘ BoD5 levels are within standard

Page 52: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

52

Table 2. 6 Baseline Noise levels (measured on 08th December 2016)

Road Section Measured locations

Base Line

ENL.dB(A) RBL dB(A)

B084

Day Day

Polgasowita at 17+100 RHS 72 60

Kahathuduwa interchange at 18+540 RHS 73 67

Gonapola Junction at 23+160 km RHS 69 59

Pokunuwita Junction at 28+140km LHS 68 59

A004

Nugegoda in front of Anula School LHS 74 67

Homagama in front of Army Camp 68 63

Homagama in front of Army Camp’s Temple 74 64

Plant Sites Concrete/crusher plant at Kumbuka at 26+320 RHS 67 54

Asphalt /crusher Plant at Olaboduwa 21+850km 58 56

ENL=Existing Noise levels(L Aeq)-dB-(A), RBL-Rating Back Ground Noise level(L A90-15min) Standard Maximum Permissible Noise Levels at Boundaries in LAeq'T.

* Provided that the noise level should not exceed 60 dB (A) inside existing houses, during day time. LAeq', T=the equivalent continuous, A- weighted sound pressure determined over a time interval T(in dB) The project area falls into the medium noise level zone Note: Most of the locations’ day time background noise level is higher than the permissible level of the area.

Areas LAeq', T

Day time Night time

Low Noise 55 45

Medium Noise 63* 50

High Noise 70 60

Silent Zone 50 45

Page 53: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

53

Table 2.7 Baseline vibration levels measured on 08th December 2016

Road section

Measured locations Category of

structure Vibration Level PPV(mm/Sec.

Frequency range(Hz)

Predominant frequency)

B084

Dharamasena Artigala Girl’s school at 14+130 RHS, Kesbewa

Type 3 0.12-0.22 10-50 10.5-11.0

District Hospital at 17+920 Km RHS, Polgasowita

Type 3 0.09-0.16 10-50 13.0

Primary School at 18+940 Km LHS Type 3 0.14-0.30 10-50 10.0-12.5

Police Station at 19+080Km RHS, Polgasowita

Type 3 0.22-0.30 10 8.5-11.75

Primary School at 26+180 km LHS, Kumbuka

Type 3 0.23-0.41 10 60.5-61.5

Prashanthi Reception hall at 26+320Km LHS, Kumbuka

Type 3 0.09-0.15 10 25.5-30.0

A004

Kumara Udayam Tamil School at 0+160 LHS, Kirulapona

Type 3 0.10-0.16 10 10.75-13.0

Public Library at 0+800km RHS, Kirulapona

Type 3 0.07-0.11 10 13.0-14.5

Army Camp Entrance at 16+280 RHS, Homagama

Type 3 0.20-0.43 10 18.5-20.0

Army Camp’s temple , Homagama Type 3 0.09-031 10 12.0-15.5

**Maximum Peak Value in Velocity mode (mm/sec) day time-one hour measurement average, Standreds-02mm/sec(type 03) **According to the measured vibration levels, maximum permissible levels (2.0 or 4.0mm/sec) of interim vibration standards have not been exceeded with the vehicle movements of this two road section

Page 54: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

54

Table 2.8 Baseline air quality results

Road Section

Mesured Locations Sampling Date TSPM(µg/m3) 3hour

average)

B 084

Polgasowita at 17+100 RHS 16/12/2016 309

Kahathuduwa interchange at 18+540 RHS

16/12/2016 217

Gonapola Junction at 23+160 km RHS

16/12/2016 302

Pokunuwita Junction at 28+140km LHS

16/12/2016 259

A004

Nugegoda in front of Anula School LHS

16/12/2016 254

Homagama in front of Army Camp

16/12/2016 260

Plant Sites

Concrete/crusher plant at Kumbuka at 26+320 RHS

15/12/2016 251

Asphalt /crusher Plant at Olaboduwa 21+850km

15/12/2016 234

Note: As per the results, all eight locations of B084, A004 and plant sites, baseline level of total suspended particulate matter(TSPM) for three hour average is lower than the permissible level of 450µg/m3.

Page 55: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

55

Appendix 2(b) The Summary of tested parameters of CP 03

Table 2.9 Water Quality results

Road Section

Sample location Date of Sampling

pH EC μs/cm

Temperature (0C)

TSS mg/l

BOD mg/l

Oil and grease mg/l

E.Coli

Baseline sampling

B 157

Kadiththamankada Ela upstream(34/2 Culvert-33+610 km)

05/12/2016 7.30 45 28.6 11 02 ND 2400

Badugandola Ela upstream, (34+998Km LHS

05/12/2016 7.39 42 28.1 02 ND ND 1700

Welipenna Ela Upstream(40/1 culvert, 39+172kmLHS

05/12/2016 6.59 60 28.1 08 02 ND 790

Surface Water Quality Standard

6-9 - - - 05 0.1 1

Note: The pH ,BOD & oil/greese content at its standard level in all locations

Page 56: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

56

Table 2.10 Baseline Noise levels(measured on 21st November 2016)

Road Section Measured locations

Base Line

ENL.dB(A) RBL dB(A)

B 157

Day Night Night Day

Mathugama Town at 31+500 66 66 59 56

Horawala Junction at 36+500km 70 68 59 58

Welipenna Interchange at 42+300km

68 69 50 51

ENL=Existing Noise levels(L Aeq)-dB-(A), RBL-Rating Back Ground Noise level(L A90-15min) Standard Maximum Permissible Noise Levels at Boundaries in LAeq'T.

* Provided that the noise level should not exceed 60 dB (A) inside existing houses, during day time. LAeq', T=the equivalent continuous, A- weighted sound pressure determined over a time interval T(in dB) The project area falls into the medium noise level zone

Areas LAeq', T

Day time Night time

Low Noise 55 45

Medium Noise 63* 50

High Noise 70 60

Silent Zone 50 45

Page 57: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

57

Table 2.11 Baseline vibration levels

Road section

Mesured locations Category of

structure Vibration Level PPV(mm/Sec.

Frequency range(Hz)

Predominant frequency)

B 197

Divisional Secretariate, Mathugama at 32+120km

Type 3 0.190-0.232 10-50 10.63-12.13

Primary school-Ovitigala at 34+040 km

Type 3 0.082-0.156 10 12.13-18.38

Child Friendly School in Badugama at 35+985km

Type 3 0.129-0.362 10 11.5-13.25

Rahumania School in Welipenna at 39+320km

Type 3 0.407-0.863 10 17.0-19.5

Primary School in Lewwanduwa at 40+840km

Type 3 0.299-0322 10 49.25-51.75

**Maximum Peak Value in Velocity mode (mm/sec) day time-one hour measurement average, Standreds-02mm/sec(type 03) **According to the measured vibration levels, maximum permissible levels (2.0 or 4.0mm/sec) of interim vibration standards have not been exceeded with the vehicle movements of this road section

Page 58: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

58

Table 2.12 Baseline air quality results

Road Section

Mesured Locations Sampling Date TSPM(µg/m3) 3hour average)

B 157

Mathugama Town at 32+100 In Front of DS office

05/12/2016 269

Horawala Junction At 36+763 km RHS

05/12/2016 105

Welipenna Interchange at 42+372km

05/12/2016 41

Note: Maximum permissible level of total suspended particulate matter(TSPM) for three hour average is 450µg/m3. As per the

measured results, all three locations of B157(East) road section, TSPM (03hr)average is lower than the permissible level of 450µg/m3.

Page 59: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

59

Appendix: 03 Table 3.1 Observed Environmental Issues of the Contract Package of CP01

Issue Cause

Required Action Responsibility

Timing (Target Dates)

Description of Resolution and Timing (Actual)

Quarry-Neboda

The quarry is a commercial base one owned by out-side party

Crusher Plant

Supplying of materials have been stopped November 2016

Asphalt Plant

1.Tar barrels at open area Supplying of materials have been stopped December 2016

1. Advised to construct a roof for the tar storage area.

Plant Manager & Head Office management

Within one month During September 2016

1Construting of roof is being progressed but it was a sluggish progress. However the roof has been completed within the last quarter of 2016.

Concrete Batch Mixing Plant

Supplying of materials have been stopped December 2016

Borrow sites

Not operated

Contractor's Yard

1.Advised to regular maintains 2. Advise to handing over the collected solid waste to UC, Kesbewa 3. Advise to handed over to owner after proper cleaning of the land

Yard Manager, SO & EO

Within one week from 5th to 11th of September 2016

1.regullar maintaining observed 2.Solid waste management activities are ok 3. The contractor is still operating the yard

1.Labour Camps at Plant site, Naboda

1. the camp is maintained well

1. Dust bins, hygiene facilities, mosquito nets were provided

Plant Manager & EO

1. The said facilities are provided satisfactorily

2.Labour Camps at B389/B285 (two labour camps are under operation for both roads)

1.Sanitary problems 2.Poor labour facilities

1.Advised to improve all the conditions

Project Manager, SO & EO

Within 3 weeks From 29th August to 18th September 2016

1. The existing bad condition was uplifted.

Stock piles Not operated

Page 60: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

60

Disposal Yards

Condition is good

Advised to implement of regular maintaining such as keep the ground levelling and avoid water stagnation

Project Manager , EO & SO

Once a week

Regular maintenance observed.

Structure Construction

1. PPEs usage by workers is poor. 2. Traffic management and site safety should be improved

1. Advised to ensure of the PPEs usage by all workers while working and upgrade the site safety and traffic controlling activities especially at Kattiya Junction of B389.

Project Manager , EO & SO Site engineers, supervisors of each section and working sites

Daily rooting

1PPEs usage by workers should be further improved on or before 30th September 2016, while traffic management at the Kattiya Junction of B389 was improved.

EO=Environmental officer, SO Safety Officer

Table 3.2 Observed Environmental Issues of the Contract Package of CP02 Kesbewa-Pokunuwita(B084) and Hoamagama-Godagama(A004)

Issue Cause

Required Action Responsibility

Timing (Target Dates)

Description of Resolution and Timing (Actual)

Quarry- Millaniya

No proper PPE usage

Provide relevant PPE for all workers who engage with quarry activities.

Plant Manager Within week

Crusher Plant-Millaniya

1.Dust emission 2.Water stagnation

Install the water sprinkles and their regular maintenance. Regular levelling of the crusher area

Plant Manager Within one week 20th April 2017

The water sprinkles had been installed and dust emission also controlled well Regular levelling is being progressed

Crusher Plant-Pokunuwita

1.Water stagnation

Advised to regular levelling of the crusher area

Plant Manager Within one week Before 5th April 2017

Area has been levelled and avoid water stagnation

Asphalt Plant-Homagama

1.Plant area managed well

The plan site is well managed

Concrete Batch Mixing Plant-Pokunuwita

1.Water stagnation is observed

Advised to avoid water stagnation within the area

Plant manager Within one week

Area has been levelled and avoid water stagnation

Page 61: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

61

Before 5th April 2017

Borrow sites

Not operated

Contractor's Yard

1.Water stagnation was observed in the abandoned materials and vehicle parts

1.Advised to regular maintains

Yard Manager, SO & EO

Within one week 5th April 2017

1.regullar maintaining observed

Stock piles No proper barricades and demarcations applied

1.Advised to erect barricades and demarcating items

Project Manager, SO

Within two days 5th April 2017

Barricades and demarcation applied

Disposal Yards-Temporary disposal sites

Condition is good

Advised to implement of regular maintaining such as keep the ground levelling and avoid water stagnation

Project Manager , EO & SO

Once a week 5th April 2017

Regular maintenance observed.

Structure Construction

1.PPEs usage by sub-contract workers are poor. 2. Inadequate of the sign boards along the road. 3. Demarcation of the construction sites specially culvert locations should be improved further. 4. Danger locations of the road should be identified and install the warning signs(bent locations, road narrows etc.)

1. Advised to ensure of the PPEs usage by all workers while working. (The designated PPEs should be provided to workers such as ear plugs, mask and gum boots while activities concreting, machine operating and compaction going on). 2 & 3.. Advised to install adequate sign boards along the construction sites and culvert locations according to approved Safety Manual. 4. Advised to erect the danger warning sites along the road where necessary.

Project Manager , EO & SO Site engineers, supervisors of each section and working sites

Daily rooting

1. PPEs usage by workers should be further improved on or before 30th April 2017. 2.The sign board installation, maintenance and site demarcating are regularly observed 3. the Site Engineers are advised to install sign bords along the danger locations

Page 62: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

62

Table 3.3 Observed Environmental Issues of the Contract Package of CP03 Mathugama-Southern Expressway (B157)

Issue Cause

Required Action Responsibility

Timing (Target Dates)

Description of Resolution and Timing (Actual)

Quarry Quarries are managed by commercial base

Crusher Plant-Daniston estate, Commercial base

1.Oil leakage at backyard of the office premises 2.Dust emission was observed

1.Advised to avoid oil leakage along the pump area and put a collecting span to collect overflowing oil 2.Install the water sprinkles and regular maintenance

Plant Manager Within two weeks 26th April 2017

1. Attended to rectify said issue with cleaning the area. 2.The water sprinkles had been installed and dust emission also controlled well

Asphalt Plant

1.used polythine covers dumped at the open area 2.Oil spill-out at pump area 3.Bitumen leakage at the bitumen pumping area

1. Advised to dispose properly. 2.Advised to ovoid oil overflowing when oil pumping, and construct the concreted trays under the pump area 3. Advised to use trays while bitumen pumping and ground should be concreted to avoid tar mix(infiltration) with soil.

Plant Manager & Head Office management

Within one month 29th March 2017

1. Properly disposed 2. & 3.Taken steps to avoid oil & tar spilling out.

Concrete Batch Mixing Plant(Dry)

1.Wash water of truck mixture should be disposed in proper way

Advised to reuse the dispose water and not to dump into open

Batching Plant Manager

Immediate

A tank is constructed to re-use the waste water of truck mixtures

Borrow sites

1.Updating of licences approvals and material quantity

1.The contractor is advised to submit timely updated licenses and approvals as well as obtained quantities

Project Manager

Immediate

1.The contractor has promised to submit these detail without delay

Contractor's Yard

1. Maintaining of yard is at good level

1.Advised to regular maintains 2. Advise to handing over the collected solid waste to UC, Mathugama

Yard Manager, SO & EO

Within one week 22nd March 2017

1.Regular maintaining observed 2.Solid waste management activities are ok

1.Labour Camps at main yard

1.labour camp and kitchen maintainace area at good level

1. Advised to maintaining 2.Advise to obtain the Labour department approval

Plant Manager & EO

Within two weeks 22nd March

1. Regular maintaining observed 2.Labur dept. approval pending

Page 63: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

63

2.No Labour department’s approval

2017

Stock piles 1.Three lands are operated for store ABC, and soil.

1.advised to obtain consent letters from owaners 2.Avoid soil erosion and dust formation from stock piles

Project manager and EO

Daily rooting

1. Regular maintenance observed.

Disposal Yards

1.More than 20 lands have been selected as disposal lands

1.Advised to implement of regular maintaining such as keep the ground levelling and avoid water stagnation in the lands

Project Manager , EO & SO

Once a week

1. Regular maintenance observed.

Structure Construction

1. PPEs usage by workers is at poor level, especially sub-contractors. 2. Traffic management should improve further. Traffic controllers haven’t good awareness about their work. 3. Neatness around the working sites, especially at culverts area.

1. Advised to ensure of the PPEs usage by all workers including sub contractors. 2. Advised to increase the awareness activities (tool box meeting etc) on safety and traffic team. 3. The sites should be free with disposed soil and scattered construction materials

Project Manager , EO & SO Site engineers, supervisors of each section and working sites

Daily rooting

1PPEs usage by workers should be further improved on or before 30th April 2017. 2. Traffic controlling activities should be further improved. 3.Constrution sites neatness should be improved further

Page 64: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

64

Appendix: 04(a) Status of EMP* Compliance (Road B 295 & B 389)

(*this EMP is included in the bidding document)

Potential Environmental

Impact Mitigation Action

Indicator or Means of verifications

Complied? Yes/Not

Complied/ Partly

Complied

Explanation if compliance status is partly complied

or not complied

Further actions/Timeline

1. (a) Selection of lands for temporally use 1.(b) Solid waste disposal and sanitation

Selection of lands in accordance with local laws, regulations and in close consultation with LAs All temporary facilities should be established away from the environmental and public sensitive areas

Site visits and observations Weekly checklists Public complains No complain received.

complied The contractor has obtained the approvals for all temporary used lands and has returned the lands with proper levelling.

Disposal lands have been returned to owners with proper levelling

All relevant legal compliances should be obtained prior to the establishment of temporary facilities Minimize health hazards and environmental pollution based on CEA guidelines. Keep the all site free with environmental hazards Selection of disposal site away from public and environment sensitive areas Re-use of debris and residual spoil materials wherever possible under instruction of Engineers & CSC. Provision of proper solid waste disposal, sanitation and sewerage facilities to all sites Dumping of garbage in a hygienic manner under the inspection of PHI in the area Minimize/avoid stagnation of water around worker based camps

Do Complied Debris disposal activities have been managed without problems. Excavated materials were removed into temporary disposal lands along the road and finally disposed into permanent disposal lands (mainly at Suwarapola disposal land). PHI has periodically visited to observe the waste generated areas (labour camps and yards) of the contractor.

Completed successfully

Page 65: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

65

Potential Environmental

Impact Mitigation Action

Indicator or Means of verifications

Complied? Yes/Not

Complied/ Partly

Complied

Explanation if compliance status is partly complied

or not complied

Further actions/Timeline

Selection of local un-skilled and skilled workers for the proposed construction activities

The all skilled and unskilled workers have been selected to sites within the area as well as out sides. While female labour has paid same wages for their works.

2. Removal of public utilities

Advance notice to the public about the time and the duration of the utility disruption Recruitment of well trained and experienced machinery operators, technical officers & labours Proper coordination and consent from service providers for the removal of utilities and re-establishment

Number of complain by public & the contractor Monthly field visits Number of remaining Poles of CEB and Telecom Total remaining length of water pipe laying

Complied Water line, CEB & Telecom Poles removing activities are fully completed at both road sections of B 389 and B 295. Considering about the received complains, 3 complaints were from B 295 and 15) complains were received from B 389 Road. The most of complaints about underground telecom cable damaged and these are forwarded to insurance company to process compensation.

Shifting of utilities has been completed.

3. Extraction, transportation and storage of construction materials

Consideration of environmental requirements and guide lines issued by the CEA, GSMB and LAs If new material extraction sites need to be located, they should exclude places which are close to the public and environment sensitive

Site visits and observations Weekly checklists Public complains

Complied Bitumen Barrels were stored at open areas since the project starting time (Instructions were issued to contractor on 28th October 2015). After

The raised problems were solved satisfactorily.

Page 66: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

66

Potential Environmental

Impact Mitigation Action

Indicator or Means of verifications

Complied? Yes/Not

Complied/ Partly

Complied

Explanation if compliance status is partly complied

or not complied

Further actions/Timeline

areas Planning of construction activity to ensure that haulage of materials does not take place during night Storage of sand, rubble, mettle bitumen cement in covered areas to ensure protection from dust, emissions Storage of cement, bitumen, oil and other chemicals on an impervious surface above ground level and should be enclosed ensuring that no storm water flows in to the structure. Provision of adequate ventilation should be kept to avoid accumulation of fumes and offensive odour to storage yards.

advising to management of plant, a new roof was constructed and the barrels have been kept under the roof. A drainage path has been constructed and avoid water stagnation inside the plant area

All legal compliances for extraction, transportation and storage of construction materials should be obtained prior to the operation All drivers should follow the speed limits on roads and specific condition given by LAs or relevant authorities in given time and should have license for the category of vehicles they drive Construction materials should not exceed the carrying capacity of the trucks as well as roads when transporting provision should be made for repair and restoration, If public roads get damaged Transport loading and unloading of materials should not cause nuisance to the public Restoration of the material extraction sites

Do Do All legal documents have been obtained by the contractor for material extraction as well as transportations

Completed

Page 67: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

67

Potential Environmental

Impact Mitigation Action

Indicator or Means of verifications

Complied? Yes/Not

Complied/ Partly

Complied

Explanation if compliance status is partly complied

or not complied

Further actions/Timeline

once after borrowing.

4. Effect on local road network

provision made for repair and restoration, If project roads(B295 & B 389) get damaged

Public complains Site visits and observations Weekly checklists

Complied The contractor has repaired the project road when it damaged. No complain was received. A provision is available to do this maintenance

Completed

Obtain approvals from LAs to use local road network prior construction Construction materials should not exceed the carrying capacity of the local road network. provision should be made for repair and restoration, If public roads get damaged

Do Do Approvals (Trade licences) have been obtained from the respective Local Authorities to transport materials.

completed

5.(a) Effect on existing canals, water restoration areas and drainage paths

Restoration of water bodies to its original status once after construction Prevent storage of construction materials and disposal of debris around cross drainages. Provision of temporally drainage facilities until requires line or earth drains are provided Replacement of structurally damaged drainage structures

Site visits and observations Weekly checklists Water quality test Public complains

Complied The contractor has attended to provide temporary/permanent drainage facilities, cleaning of existing drainages So far, 10 complain for B 285 and 03 complain for B389 were received regarding the drainage problem. 04 complain of B285 road will be rectified by Kesbewa MC while others are solved.

Completed. Under the project, the existing poor quality drainages and side drainages in entire length of the road are improved.

Obtaining of proper approvals from relevant Do Complied The contractor had been Completed.

Page 68: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

68

Potential Environmental

Impact Mitigation Action

Indicator or Means of verifications

Complied? Yes/Not

Complied/ Partly

Complied

Explanation if compliance status is partly complied

or not complied

Further actions/Timeline

5.(b) Effect on water resources

authorities prior to diversion, close or blocking of water sources as well as material storage

instructed to obtain relevant permission.

Storage of toxic and hazardous construction materials away from water bodies Avoid excavation of beds of any irrigation systems or other water bodies Implement additional safety precautions to reduce the water pollution and degradation of water resources due to work

Do Complied The contractor had been advised to store toxic or hazardous away from water sources, avoid excavations close to vulnerable water sources, and avoid water pollution when his work progressing.

Do

Cleaning of upstream and lead-away channels of cross drainages to maintain a smooth water flow. Introduction of catch pits wherever possible to prevent silting of water bodies

Do Do The facilities for smooth water flow and preventing siltation were provided during the construction activities were done

Do

Awareness of employees on water conservation, pollution and minimization of water usage Prevent entering waste- water directly in to water bodies. Maintaining vehicles and equipment in good condition, to prevent leakage of oil or fuel Prevention of disrupting community water sources Restore the water resources due to any pollution or negligence done by contractor

Do Do Awareness of water conservation, prevention of pollution etc were included under the worker awareness programs

Do

6. Soil erosion Placement of erosion control measures to Do Do The contractor was Completed.

Page 69: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

69

Potential Environmental

Impact Mitigation Action

Indicator or Means of verifications

Complied? Yes/Not

Complied/ Partly

Complied

Explanation if compliance status is partly complied

or not complied

Further actions/Timeline

sedimentation and siltation

erodible areas. Covering of temporary soil dumps with thick tarpaulin sheets until remove from the site Undertake construction activities in erodible sections during dry season. Limitation of steep cuts and the reduction of slop of cuts Treatment of clearing and filling areas against flow acceleration

advised to implement his construction work during dry period along the water ways. Eg: B295 near the Kospalana Bridge area.

Re use of top soil generated from construction sites for turfing and tree planting activities.

Do Complied

7. Effect on flora, fauna and their habitats

Compensative tree planting activity with participation of project effected people and adjoining communities. Do not promote or introduction of any alien invasive plants to re-planting activity and use only native and endemic species in the area

Field visits and observations Weekly checklists

Complied Compensative tree planting programs were conducted. Due to absence of space along the ROW, vicinity areas were selected to replanting.

Three tree planting programs have been implemented. 1.Police ground and temple premises in B389 2.Ananda Samarakoon School premises 3.Karadiyana waste dumping land(mangrove species)

Awareness of workforce regarding important of fauna, flora and their habitats Display the relevant warning signs along the environmentally sensitive areas Do not use any resources that adjoining into the wildlife (specially demarcated to wildlife)

Do Complied Awareness meeting were conducted. The resource persons, who represented from CEA have participated those activities.

The contractor has conducted the awareness programs as periodical intervals

Page 70: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

70

Potential Environmental

Impact Mitigation Action

Indicator or Means of verifications

Complied? Yes/Not

Complied/ Partly

Complied

Explanation if compliance status is partly complied

or not complied

Further actions/Timeline

such as water, feeding grounds, breeding areas and habitats. Providing facilities to wild-life in the area during the environmental hazardous situation

Removal of road side trees adhering to the CEA guidelines and recommendation. Decision on tree removal based on Detailed Engineering Design Marking road side trees subjected to removal and preparation of inventory prior to start clearing. Valuable timber should be properly stacked and handed over to the DoF or rightful owners.

Do Compiled Removal of road side trees are completed

Completed

8. Biodiversity conservation and sustainable natural resource management

Rehabilitation of degraded eco-systems (such as wet land, forest ect.) adjoining into the project area or project effected area with approval of Engineer

Field visits and observations Weekly checklists

Complied It was proposed to conduct some rehabilitation activities along the Bolgoda lake in the B 285 road. But contractor couldn’t conduct these activities due to various reasons

Not completed

Page 71: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

71

Potential Environmental

Impact Mitigation Action

Indicator or Means of verifications

Complied? Yes/Not

Complied/ Partly

Complied

Explanation if compliance status is partly complied

or not complied

Further actions/Timeline

Awareness of all stakeholders regarding environmental conservation Displaying signs and warning boards about the importance of the existing fauna and flora of the area Avoid clearing of natural habitats and replacement of natural vegetation for any construction purpose except the proposed road construction. Use of natural resources in sustainable manner Rehabilitation of degraded eco-systems (such as wet land, forest ect.) adjoining into the project area or project effected area Rehabilitation (with approved and proper rehabilitation plan) of all resources extract areas and temporary used lands

Do Complied Some of the activities were implemented parallel with the tree planting campaign. Eg: During the tree planting program was conduting at the school, the awareness program was also conducting to children.

Do

9. Disruption of traffic and public inconvenience

Provide an advance notice to local communities about the schedule of construction activities Installation of traffic warning signs, temporary traffic lights or flagman at the construction sites Implementation of traffic management plans in close coordination with local police and public Schedule movement of large trucks and plant in off-peak traffic times.

Public complains Weekly checklists Site visits and observations

Complied Inadequate traffic controlling and inconvenience to public had been observed along the roads during the site observations. Public complains on house access and business access had been solved.

Monthly payments were reduced due to poor performance of traffic safety controls.

Provision of safe passage/ alternative routes Do Do Provision was provided to Completed.

Page 72: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

72

Potential Environmental

Impact Mitigation Action

Indicator or Means of verifications

Complied? Yes/Not

Complied/ Partly

Complied

Explanation if compliance status is partly complied

or not complied

Further actions/Timeline

to the vehicles and passengers make alternative passage or bypass making where necessary

10. Personal health and safety

Proper and regular awareness on health(sexually transmitted, Non-transmitted and vector born diseases ) and hygiene matters during the working period

Site observation Weekly checklists Public complain/worker’s complains

Complied Three programs on HIV/AIDS prevention had been conducted.

Scheduled all programs were completed

Provision of personal protective equipments (PPEs) and clothes to workers, based on their duty

Do Complied PPE usage was observed as weak among the workers.

Reductions of monthly payments were carried out according to the monthly observations made by RDA and the consultant.

Establishment of road engineering aspects and sign boards to reduce accidents

Do Do Temporary signs have been fixed during the construction period while permanent signs were erected/fixed after the road work finished

Completed

Proper briefing and training of workers on safety precautions, and their responsibilities Use of licensed and well trained operators for handling of machinery, equipment and material processing plants Provision of first aid facilities and emergency

Do Do Tool box meetings and awareness meetings were conducted. labour accommodations were provided Explosive materials were

Completed

Page 73: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

73

Potential Environmental

Impact Mitigation Action

Indicator or Means of verifications

Complied? Yes/Not

Complied/ Partly

Complied

Explanation if compliance status is partly complied

or not complied

Further actions/Timeline

transport to the nearest hospital Arranging regular safety checks of workers, vehicles and plants Provide proper labour facilities in labour camps, yards and accommodations for full fill their health and safety requirements. Storage of explosive materials in a secure location in a protective way

handled under supervision of nearest Police of the plant site (quarry)

11. Safety of road users

Enforcement of speed limits, traffic rules and regulations Installation of the warning signs, road markings and relevant road furniture Provision of bus bays, pedestrian crossings at the appropriate locations

Site observation Weekly checklists Public complain

Complied The signs boards had been installed throughout the road during the construction period and those were maintained regular manner.

Completed

12. Impact from dust, noise and vibration

Placement of crushers and hot mixed plants away from public and environmental sensitive areas Placement of exhaust silencers and noise reduction devices to the road side crushers, construction vehicles and hot mixed plants

Site observation Weekly checklists Air, Noise and Vibration test Public complain

Complied - -

Periodically checking of air, water, noise and vibration of the project area

Do Being complied

Baseline /construction stage monitoring activities were carried out

Monitoring activities for operation stage to be implemented immediate after the handing over the road.

Storage and transport of construction materials with proper covering, provision of

Do Complied The contractor has followed the guidelines

Actions have been followed

Page 74: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

74

Potential Environmental

Impact Mitigation Action

Indicator or Means of verifications

Complied? Yes/Not

Complied/ Partly

Complied

Explanation if compliance status is partly complied

or not complied

Further actions/Timeline

dust barriers, spraying of water and control of vehicular speed to minimize dust emission

that given to control the storage and transportation of materials.

throughout the project period

Implementation of National Emission Standards and Noise Control Regulations of CEA for project activities Implementing an effective work plan to reduce dust, noise and vibration due to construction work Regular maintenance of machinery, equipment and vehicles in a good condition Prevent bad odour and offensive smell emanating from chemicals, material processing or other construction activities Arrangement of construction activities closer to public sensitive locations coordination with the relevant authorities

Do Complied CEA approvals have been obtained.

completed

Operation stage

13. Air quality It is expected to reduce existing dust after surfacing of the roads. Proper alignment and surfacing of the road will help to reduce the vehicular emissions. Checking of differentiation of environmental parameters

Site observation Weekly checklists Public complain Air quality test

Being Complied to

The contractor has taken step to monitor the air quality. The quotation are invited and finalized

Immediate after the road handing over to the Employer

14. Drainage Congestions and maintainace of road

Regular maintenance of drainage system as well as road surface Regular maintenance of road furniture that already installed and providing an adequate requirements Avoid dumping garbage and other spoil

Site observation Weekly checklists Public complain Air quality test

Being complied to

Performance based maintainace work will be implemented.

After the road handing over to the Employer

Page 75: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

75

Potential Environmental

Impact Mitigation Action

Indicator or Means of verifications

Complied? Yes/Not

Complied/ Partly

Complied

Explanation if compliance status is partly complied

or not complied

Further actions/Timeline

material

GSMB=Geological Survey & Mining Bureau, CEB=Ceylon Electricity Board, LAs=Local Authorities, CSC=Construction supervision consultant, CEA=Central environmental Authority,

Page 76: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

76

Appendix: 04(b) Status of EMP* Compliance (Kesbewa-Pokunuwita (B084) Road)

(*this EMP is included in the bidding document)

Potential Environmental

Impact Mitigation Action

Indicator or Means of verifications

Complied? Yes/Not

Complied/ Partly

Complied

Explanation if compliance status is partly complied

or not complied

Further actions/Timeline

A. Pre construction and Construction stage

1. Removal

of public utilities

As part of the pre-construction activities, initially consultation and consent

should be taken from relevant service

providers (CEB / NWSDB / SLT) if sections

of utility lines needs to be shifted due

to design requirements or shift in alignment Obtain permission from DoI for any

proposed construction works on irrigation

canals Use of well trained and experienced

machinery operators to reduce accidental

damage to the public utilities Advance notice to be served to the affected

public about the time and the duration of

the utility disruption Substitute sources of water and other

utilities during the disruption period, and

restoration of the public utilities as soon as

possible.

Site observation Weekly checklists Public complains

Being complied to

Water lines, CEB & Telecom Poles shifting activities are being progressed. During the reporting period 1% of CEB poles and 17% Telecom poles have been shifted. Considering about the received 31 complaints, 15 complaints are solved, 3 are progressing while 13 complaints are pending about decisions.

Utility shifting activities are monitored by monthly progress meetings. The relocating activities should be expedite

2. Removal

of road side

Mark all road side trees subjected to potential felling and preparation of inventory

prior to start clearing.

Site observation Weekly checklists

Being complied to

Clearing activities are at near completion along the

Page 77: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

77

Potential Environmental

Impact Mitigation Action

Indicator or Means of verifications

Complied? Yes/Not

Complied/ Partly

Complied

Explanation if compliance status is partly complied

or not complied

Further actions/Timeline

trees Decision on tree removal should be based on

detailed engineering design. Maximum effort towards avoiding removal

of religious, cultural and aesthetic important

trees through joint field verifications and

decision taking.

Obtain permission in writing from DoF

regarding removal of trees and seek

compensatory modalities and plan for

afforestation programmes. Compensatory plantation program

at twice the number to be felled and its

cost estimation in consultation with DoF. To avoid further tree losses, the contractor

should ensure that the temporary use of land

for construction related activities will be

established w i t h o u t a n y a d d i t i o n a l

tree cutting.

handed over section (Sec.1).

3. Temporary use of lands

Construction facilities should be established at least 500 m away from water bodies, natural flow paths, important ecological habitats and residential areas. Selection of site for these facilities by

adhering to stipulated local laws and

regulations and in close consultation with

Site observation Weekly checklists

Being complied to

The contractor is using temporary stock pile yard at 16+500km and disposal land at 17+500km. The contractor’s machinery yard is also situated at 21+700km as a temporary

Monthly site visits

Page 78: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

78

Potential Environmental

Impact Mitigation Action

Indicator or Means of verifications

Complied? Yes/Not

Complied/ Partly

Complied

Explanation if compliance status is partly complied

or not complied

Further actions/Timeline

LAs. Pay compensation / rent for using the

site and get an official permit from the

agencies if any public utilities will be used

for its facilities. In establishing these facilities, the contractor

should minimize removal of trees and other

green cover vegetation to the extent possible.

basis. The contractor has obtained the consent letters from owners and has taken necessary actions regarding the environmental protection.

4.Land acquisition

and Resettlement

Compensation prior to acquisition of

property as per the RAP policy and

restoration of livelihood.

Work done records Site observations Public complain

To be complied

Land acquisition activities have almost been finished in section 01, 03 and 04, while some activities are being progressed in other sections.

5. Solid waste disposal and

sanitation

Designing and Provision of solid waste

collection, storage, disposal, sanitation and

sewage facilities at all sites for the

onstruction/labor camps, and other

construction sites. Handling and management of waste

generated from the construction/labor

camps without contaminating the

surrounding environment and not posing

any threat to the public/communities living

in and around the sites. Provide adequate facilities to manage its

wastes in consultation with CEA and PHI

Site observation Weekly checklists Public complains

To be complied

Waste collecting facilities have been provided(garbage bins) The contractor has built linkage between Municipal councils in the area to give collected solid waste from their office, yard and the labour camps in regular basis.

Page 79: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

79

Potential Environmental

Impact Mitigation Action

Indicator or Means of verifications

Complied? Yes/Not

Complied/ Partly

Complied

Explanation if compliance status is partly complied

or not complied

Further actions/Timeline

of the area. Proper drainage facilities should be designed

and developed in the workers base camp

sites to minimize stagnation of wastewater. Solid waste should not be burnt but

emphasis to be laid for their recycling,

composting and sanitary land filling.

Adequate supply of hygienic water should be provided to the urinals, toilets and wash rooms of the worker camps. Garbage bins should be provided to all

workers’ camps and construction sites, and

needs regular clearing and appropriate

disposal and if needed to be treated with

disinfectants.

6. Top soil Conservation and Disposal

of debris

The fertile top soil to a depth of 20 - 30 cm should scoop out and preserved in

a manner so that the stack is not washed

away during rainy days. The top soil

can be utilized in the future for turfing

purpose, enhancing soil quality of degraded

land patches, plantation purposes etc. All debris and residual spoil materials

including any left out earthen material

should be disposed off only at locations

approved by the relevant LAs. Spoil materials (soil, sand, rock etc,)

Site visits & observations Weekly checklist Public complains

Being complied

Approved disposal sites have been operated. The temporary disposal lands also being operated. Road side excavated materials are stock piled by contractor for future usage (at 16+500km RHS).

Sites visit/checklist updating is being conducted regular basis.

Page 80: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

80

Potential Environmental

Impact Mitigation Action

Indicator or Means of verifications

Complied? Yes/Not

Complied/ Partly

Complied

Explanation if compliance status is partly complied

or not complied

Further actions/Timeline

generated during the construction activities

should be utilised wherever found

suitable for activities like site levelling, back-

filling etc with prior approval of CSC. Suitable dumping grounds/ land fill sites

should be identified for the disposal of

surplus

excavated/surplus/discarded/demolished

materials of existing structures. The debris and spoil should be disposed in

such a manner that;

• Does not block the waterways and

drainage paths

• The disposed materials should not be

washed away by runoff

• Debris should not be disposed into

any agriculture lands, marshlands, down

slopes or any environmental sensitive

areas

• Avoid/ Minimize annoyance to general public and road users.

7. Extraction of construction materials

Suitable quarry sites and borrow areas

s h o u l d be identified at the initial stage

of the project. Utilizing the existing mines and quarry

sites available in the project influential areas,

which are approved by GSMB or LAs,

operating with EPL and IML

Site visits & observations Weekly checklist Public complains

Being complied

The contractor has obtained the materials from approved sources and submitted their approvals to the client. The periodic site visits conduct to observe the site

Sites visit/checklist updating is being conducted regular basis.

Page 81: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

81

Potential Environmental

Impact Mitigation Action

Indicator or Means of verifications

Complied? Yes/Not

Complied/ Partly

Complied

Explanation if compliance status is partly complied

or not complied

Further actions/Timeline

If new quarries and sand mines are to be

opened, prior approval should be obtained

from GSMB, CEA and LAs. Project’s quarries should not be located in

any environmentally sensitive areas, in

vicinity to archeological and cultural sites,

religious places, schools and settlements. Quarries and borrow areas should meet

aesthetic demands and have rehabilitation

plans designed and implemented. Use of alternative source for the river

sand such as screened crusher fines or sea

sand. Restoration of the borrow pits by contractor

or relevant authorities once after borrowing. Use of insecticides/disinfectants in the

camp sites/plant sites and waste collection

areas to discourage Vector breeding.

hygiene matters as well as house-keeping activities.

8. Transportation

and storage of construction

materials

Trucks carrying construction materials

should not be overloaded and covered with

tarpaulins to reduce fines getting airborne. Avoid storage of construction materials

beside the road, around water bodies,

residential or public sensitive locations.

Site visits & observations Weekly checklist Public complains

Being complied

Contractor use tar-poling covers to close the material when transporting while the vehicle conditions and loads are being observed by client and consultant in regular basis.

Sites visits and checklist updating are being conducted regular basis.

Page 82: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

82

Potential Environmental

Impact Mitigation Action

Indicator or Means of verifications

Complied? Yes/Not

Complied/ Partly

Complied

Explanation if compliance status is partly complied

or not complied

Further actions/Timeline

Materials loading and unloading should not

cause nuisance to the people by way of

noise, vibration and dust emission. Sand, rubble, metal, bitumen, cement etc

should be stored in designated areas to

ensure optimum utilization preferably on a

solid platform. Such materials should be

handled in environment friendly and

nuisance free manner.

9.Effect on local road network

Permit from LAs to use local roads prior to

using the roads for transportation of

construction materials, machinery and

equipment etc. The contractor should- ensure that

transportation of construction materials by

suppliers should not exceed the carrying

capacity of the local roads. Regular Maintenance of local roads and their

restoration which are used for hauling

activities for the construction related

activities.

Site visits & observations Weekly checklist Public complains

Being complied

The contractor is advised to get permission from relevant authorities when he using the other roads except the project road The contractor has obligated to repair the roads while using them for their activities.

Consider about the complains from the public and line authorities/agenesis

10. Soil erosion and surface runoff

Implement erosion control measures such as

fiber mats, gabions walls, rip raps and deep-

rooted grasses etc to erodible areas Seeding with a fast growing native species

and seed mix immediately after fill

placement to develop green cover to protect

Site visits & observations Weekly checklist

Being complied

The contractor is advised to take relevant actions against the soil erosion and surface runoff their construction sites as well as filling areas/materials excavation areas.

Regular site visits and checklist are being implemented

Page 83: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

83

Potential Environmental

Impact Mitigation Action

Indicator or Means of verifications

Complied? Yes/Not

Complied/ Partly

Complied

Explanation if compliance status is partly complied

or not complied

Further actions/Timeline

the earth works. Construction in erosion and flood- prone

areas should be restricted to the dry

season (excluding December – February) Stabilization of embankment slopes and road

cuts by re-vegetation and take up a turfing

work as soon as possible before rains.

Treat clearing and filling areas against flow

acceleration and construction work should

be carefully designed to minimize

obstruction or destruction to natural

drainage.

11. Effect on existing drainage pattern

Contractor should avoid storage of

construction materials and disposal of

debris around irrigation canals, cross

drainage and natural flow paths. Culverts and all other drainage paths have to

be appropriately designed by allowing

sheath flow and without any blockages. Provide temporary diverting drainage

facilities to construction sites while

repairing and replacement of obstructed

drains and structurally damaged culverts/

bridges.

Site visits & observations Weekly checklist

Being complied

The contractor has taken steps to avoid unnecessary impact to existing drainage system, further he has found the approved stock piles away from water paths as well as agrarian activities.

Regular site visits and checklist

12. Protection of Avoid tapping water from sources in Site visits & observations Being The contractor has been Regular site visits

Page 84: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

84

Potential Environmental

Impact Mitigation Action

Indicator or Means of verifications

Complied? Yes/Not

Complied/ Partly

Complied

Explanation if compliance status is partly complied

or not complied

Further actions/Timeline

water resources residential areas being used by the local

community. Contractor should not obstruct or prevent

flowing of water when working closer to

water bodies. Construction works affecting the streams and

irrigation canals have to be undertaken

during the dry season with prior permission

from the concerned Department. Minimize excavation of beds of any streams,

irrigation systems, and other water

resources so that water flow in the beds is

unaltered.

Use of silt traps and erosion control

measures where the construction is carried

out in close proximity to the water bodies to

avoid entering of cement, sand and other

particulate matters which cause turbidity

and increase sedimentations. Storage of construction materials which are toxic, hazardous and containing other fine particles would be sited at least 500 from water bodies to avoid its contamination to water resources. Trenches around the storage area to confine the flow outs .

Weekly checklist Public complains

complied advised to minimize any impact will course due to his activities. Stock piles are situated away from water sources. The contractor obtain water for his purposes mainly from main water supply(WSDB) and own dug wells in their premises(at Main Yard).

and checklist

13. Affect on flora and

fauna

Approval from DoF should be

obtained prior to start of project activities Site visits & observations Weekly checklist

Being complied

The all trees to be cut within the ROW are clearly marked by Survey

Site visits and progress meeting

Page 85: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

85

Potential Environmental

Impact Mitigation Action

Indicator or Means of verifications

Complied? Yes/Not

Complied/ Partly

Complied

Explanation if compliance status is partly complied

or not complied

Further actions/Timeline

towards felling of trees and planning

towards carrying out compensatory

afforestation.

Contractor will prevent his work force

from gathering fire wood from surrounding

habitats, disturbing to the flora, fauna

including hunting of animal and fishing in

water bodies All construction materials extraction sites,

material processing plants, storage yards

and construction vehicle service stations

will be located away from the water bodies,

environmental sensitive locations Proper awareness programs to be conducted

regarding conservation of flora, fauna

including ground vegetation to all drivers,

operators and other workers

prior to construction started. The all possible trees will be protected within ROW and re-planting program will be carried out. The contractor is maintaining a plant nursery in order to carry out the tree planting period. Provisions are provided to conduct the Environmental awareness.

14.

Disruption of

traffic

Provide and publicize advance notices to local communities about the

schedule of construction activities. Installation of traffic waning signs, signaling

system, flagman at the construction sites. Provide safe and convenient passage to

vehicles, passengers and livestock from the

approaching roads.

Site visits & observations Weekly checklist

Being complied

The contractor has submitted traffic safety plan for the project. Accordingly the contractor obligated to install relevant signs along the road Smooth traffic flow is compulsory to maintained

Monthly progress meetings and checklists

Page 86: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

86

Potential Environmental

Impact Mitigation Action

Indicator or Means of verifications

Complied? Yes/Not

Complied/ Partly

Complied

Explanation if compliance status is partly complied

or not complied

Further actions/Timeline

Traffic and safety management plan should

be implemented in close coordination with

local communities/authorities and police

department during the entire construction

period. Contractors to plan and implement diversion

roads for sensitive locations with prior

approval of the Supervision Consultant.

by the contractor throughout the project period

15. Air quality Contractors should place crushers and hot mix plants at least 500 m away

from residential areas or other social

infrastructures (school, hospital/religious

places etc)

Such establishments should strictly comply

to National Emission Standards for all

construction vehicles, equipment and

material processing plants Dust extraction/suppression systems should

be fitted to crusher units, construction

vehicles and hot mix plants

Site visits & observations Weekly checklist

Being complied

The periodical checking of air quality has been carried out (under the project’s EMP) and the contractor obligated with national emission standard that stipulated when EPL issuance for their plant operations Dust controlling activities such as sprinklers, dust barriers are installed in the crusher units/hot mix plants (at Kumbuka 26+320RHS)

Monthly progress meetings and checklists

16. Noise and vibration

Strictly implement noise control regulations

for all construction vehicles and equipments. Contractors should equip their heavy

construction equipment with acoustic

Site visits & observations Weekly checklist

Being complied

The periodical checking of noise and vibration levels have been carried out (under the project’s EMP) and the contractor

Monthly progress meetings and checklists

Page 87: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

87

Potential Environmental

Impact Mitigation Action

Indicator or Means of verifications

Complied? Yes/Not

Complied/ Partly

Complied

Explanation if compliance status is partly complied

or not complied

Further actions/Timeline

enclosures/ silencers to limit the

construction equipment not to generate

noise exceeding 75 db (compacters, loaders,

vibrators, cranes, diesel generator sets) Limit working time for activities that

create noise only between 6.00 am to 6.00

pm except for construction site near

schools, offices, religious places.

Contractors should schedule their activities

at sensitive locations in consultation with the

relevant authorities (school’s principals,

high-priest etc.) Regularly maintain all construction vehicles

and machinery to meet the National

Emission Standards.

obligated with national emission standard that stipulated when EPL issuance for their plant operations/yard operations and machineries a

17. Personal safety and health

Organize awareness programs regarding personal safety of workers and

general public during construction period. Establishment of safety provisions to

reduce the likelihood of accidents by

placing warning signs, speed limit

markings, speed breakers and signals to

particular locations. Providing appropriate PPEs such as

protective footwear, helmets, goggles, eye-

shields and clothes to the workers

Site visits & observations Weekly checklist

Being complied

The contractor is being implemented tool box meeting/awareness campaigns periodically. Safety provisions are provided to caring out the PPEs and the Traffic safety activities. The contractor has submitted a schedule about the HIV/AIDS awareness program that to

Monthly progress meetings and checklists Attending to awareness and tool box meetings

Page 88: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

88

Potential Environmental

Impact Mitigation Action

Indicator or Means of verifications

Complied? Yes/Not

Complied/ Partly

Complied

Explanation if compliance status is partly complied

or not complied

Further actions/Timeline

depending on their activities (Mixing asphalt,

blasting, handling equipments etc) and

motivating the workforce for their usage. Establishing first aid facilities and

Ambulance facilities at active working sites

to meet emergency situations. Use experienced and well trained workers

for the handling of machinery, equipment

and material processing plants. Contractor should implement STD/

HIV/AIDS awareness programs for general

public in and around project

implementation area and workers to reduce

the risk of spreading STD among them.

be conducted by him.

18. Bridge construction

Design of bridges should comply with the requirements of “Bridge

Design Manual” of RDA. Contractor should provide safe and

convenient passage or alternative access to

road users for the entire construction period

seeking approval from the Supervision

consultant. Smooth traffic flow to be ensured

during the entire construction period with

the provision of appropriate safety

measures. During piling activities, the Bentonite slurry

generated will be collected and air dried.

Site visits & observations Weekly checklist

Being complied

The contractor has taken step to implement bridge construction activities according to the approved methodology with minimum environmental damage to the nearby or vicinity areas. The consultant and the client will keenly observed their activities and guiding when he needs to dispose the slurry into open.

Monthly progress meetings and checklists

Page 89: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

89

Potential Environmental

Impact Mitigation Action

Indicator or Means of verifications

Complied? Yes/Not

Complied/ Partly

Complied

Explanation if compliance status is partly complied

or not complied

Further actions/Timeline

Then it should be disposed in disposal

yards. In no case the slurry will be

discharged to the water bodies and

agricultural land etc.

19. Access to Public utilities

Access to new public utilities should be

clearly marked within the road reservation in

consultation with the concerned

departments.

Site visits & observations Weekly checklist

Being complied

The contractor has completed the access survey to ensure the neediness of the new access along the ROW. The provisions provided to make better accesses to public parallel to road development.

Monthly progress meetings and checklists

B. Operation stage

20. Encroachment of the RoW

Routine checking to discourage

encroachments and removal of unauthorized

s t r u c t u r e s f ro m RoW in consultation

with Police Department. Popularizing and Implementation of rules

and regulations with respect to RoW and

to avoid encroachment from the RoW.

Site visits & observations To Be complied

During the performance based management, the contractor, the Executive Engineer and the PMU staff will conducting routing visits to see any encroachments along the road

Monthly progress meetings

21. Clearing of Cross Drainage Structures

Periodical clearing of Cross drains and

side drains (specially before commencing of

rainy season) to facilitate easy

discharge of

Site visits & observations To Be complied

Do Monthly progress meetings

22. Road safety Enforcement of the speed limits, traffic rules and regulations to the sensitive

locations, Installation of the warning signs,

marking of center line, pedestrian crossings,

Site visits & observations To Be complied

Do Monthly progress meetings

Page 90: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

90

Potential Environmental

Impact Mitigation Action

Indicator or Means of verifications

Complied? Yes/Not

Complied/ Partly

Complied

Explanation if compliance status is partly complied

or not complied

Further actions/Timeline

bus halts and other utilities.

23. Road

maintenance

Developing and Implementation of Periodical maintenance program.

Site visits & observations To Be complied

Do Monthly progress meetings

Page 91: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

91

Appendix: 04(c) Status of EMP* Compliance (Mathugama-Southern Expressway (B157) Road)

(*this EMP is included in the bidding document)

Potential Environmental

Impact Mitigation Action

Indicator or Means of verifications

Complied? Yes/Not

Complied/ Partly

Complied

Explanation if compliance status is partly complied

or not complied

Further actions/Timeline

A. Pre construction and Construction stage

1. Removal of public utilities

As part of the pre-construction activities, initially consultation and consent

should be taken from relevant service

providers (CEB / NWSDB / SLT) if sections

of utility lines needs to be shifted due

to design requirements or shift in alignment Obtain permission from DoI for any

proposed construction works on irrigation

canals Use of well trained and experienced

machinery operators to reduce accidental

damage to the public utilities Advance notice to be served to the affected

public about the time and the duration of

the utility disruption Substitute sources of water and other

utilities during the disruption period, and

restoration of the public utilities as soon as

possible.

Site observations Monthly Progress meetings Public complaints

Being complied to

Water lines, Telecom and Electricity poles are being removed. During the reporting period, 28% of Electricity Poles, 42% of Telecom poles were shifted. No any complaints received so far.

2. Removal

of road side

trees

Mark all road side trees subjected to potential felling and preparation of inventory

prior to start clearing.

Site observations Weekly checklists

Being complied to

Removal of road side trees is completed in section 01 and the activity has

Page 92: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

92

Potential Environmental

Impact Mitigation Action

Indicator or Means of verifications

Complied? Yes/Not

Complied/ Partly

Complied

Explanation if compliance status is partly complied

or not complied

Further actions/Timeline

Decision on tree removal should be based on

detailed engineering design. Maximum effort towards avoiding removal

of religious, cultural and aesthetic important

trees through joint field verifications and

decision taking.

Obtain permission in writing from DoF

regarding removal of trees and seek

compensatory modalities and plan for

afforestation programmes.

Compensatory plantation program

at twice the number to be felled and its

cost estimation in consultation with DoF. To avoid further tree losses, the contractor

should ensure that the temporary use of land

for construction related activities will be

established without any additional tree

cutting.

already begun in sections 02.

3. Temporary

use of lands

Construction facilities should be established at least 500 m away from

water bodies, natural flow paths,

important ecological habitats and residential

areas. Selection of site for these facilities by

adhering to stipulated local laws and

regulations and in close consultation with

LAs.

Site observations Weekly checklists Public complaints

Being complied to

The contractor uses temporary lands for his main yard at 40+010 km, stock pile at 41+280(ABC), 37+920(soil), and 36+840(soil). The permission has been obtained and rental is paid. The existing trees have

Monthly site visits

Page 93: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

93

Potential Environmental

Impact Mitigation Action

Indicator or Means of verifications

Complied? Yes/Not

Complied/ Partly

Complied

Explanation if compliance status is partly complied

or not complied

Further actions/Timeline

Pay compensation / rent for using the

site and get an official permit from the

agencies if any public utilities will be used

for its facilities. In establishing these facilities, the contractor

should minimize removal of trees and other

green cover vegetation to the extent possible.

been saved within the yard during its construction.

4.Land acquisition and Resettlement

Compensation prior to acquisition of

property as per the R& R policy and

restoration of livelihood.

Site observations Public complaints

Being complied to

Land acquisition activities have been completed in section 01 and it is being progressed in section 02.

5. Solid waste

disposal and sanitation

Designing and Provision of solid waste

collection, storage, disposal, sanitation and

sewage facilities at all sites for the

construction/labour camps, and other

construction sites. Handling and management of waste

generated from the construction/labor

camps without contaminating the

surrounding environment and not posing

any threat to the public/communities living

in and around the sites. Provide adequate facilities to manage its

wa stes in consul tat ion with CEA and

PHI of the area. Proper drainage facilities should be designed

Site observations Weekly checklist Public complaints

Being complied to

Waste collecting facilities have been provided to labour camps, yards and office. Solid Waste materials are weekly handed over to waste collecting vehicles of MC in Mathugama. Adequate toilets and wash room facilities are at the labour camps. Waste water discharging facilities have been established.

Page 94: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

94

Potential Environmental

Impact Mitigation Action

Indicator or Means of verifications

Complied? Yes/Not

Complied/ Partly

Complied

Explanation if compliance status is partly complied

or not complied

Further actions/Timeline

and developed in the workers base camp

sites to minimize stagnation of wastewater. Solid waste should not be burnt but

emphasis to be laid for their recycling,

composting and sanitary land filling.

Adequate supply of hygienic water should be provided to the urinals, toilets and wash rooms of the worker camps. Garbage bins should be provided to all

workers’ camps and construction sites, and

needs regular clearing and appropriate

disposal and if needed to be treated with

disinfectants.

6. Top soil Conservation and Disposal

of debris

The fertile top soil to a depth of 20 - 30 cm should scoop out and preserved in

a manner so that the stack is not washed

away during rainy days. The top soil

can be utilized in the future for turfing

purpose, enhancing soil quality of degraded

land patches, plantation purposes etc. All debris and residual spoil materials

including any left out earthen material

should be disposed off only at locations

approved by the relevant LAs. Spoil materials (soil, sand, rock etc,)

generated during the construction activities

should be utilised wherever found

Site observations Check lists Public complaints

Being complied to

Approved ....disposal sites are being operated and those Levelling activities are also being progressed.

Page 95: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

95

Potential Environmental

Impact Mitigation Action

Indicator or Means of verifications

Complied? Yes/Not

Complied/ Partly

Complied

Explanation if compliance status is partly complied

or not complied

Further actions/Timeline

suitable for activities like site leveling, back-

filling etc with prior approval of CSC. Suitable dumping grounds/ land fill sites

should be identified for the disposal of

surplus

excavated/surplus/discarded/demolis hed

materials of existing structures. The debris and spoil should be disposed in

such a manner that;

• Does not block the waterways and

drainage paths

• The disposed materials should not be

washed away by runoff

• Debris should not be disposed into

any agriculture lands, marshlands, down

slopes or any environmental sensitive

areas

• Avoid/ Minimize annoyance to general public and road users

7. Extraction of construction materials

Suitable quarry sites and borrow areas

should be identified at the initial stage of

the project. Utilizing the existing mines and quarry

sites available in the project influential areas,

which are approved by GSMB or LAs,

operating with EPL and IML If new quarries and sand mines are to be

Site observations Check lists Public complaints

Being complied to

The contractor is allowed only to sourcing materials from approved sites The contractor has submitted their permits and licenses about material extortion sites The monthly visits

Page 96: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

96

Potential Environmental

Impact Mitigation Action

Indicator or Means of verifications

Complied? Yes/Not

Complied/ Partly

Complied

Explanation if compliance status is partly complied

or not complied

Further actions/Timeline

opened, prior approval should be obtained

from GSMB, CEA and LAs. Project’s quarries should not be located in

any environmentally sensitive areas, in

vicinity to archeological and cultural sites,

religious places, schools and settlements. Quarries and borrow areas should meet

aesthetic demands and have rehabilitation

plans designed and implemented. Use of alternative source for the river

sand such as screened crusher fines or sea

sand. Restoration of the borrow pits by contractor

or relevant authorities once after borrowing. Use of insecticides/disinfectants in the

camp sites/plant sites and waste collection

areas to discourage Vector breeding.

conduct to observe the sites. During the visits, environmental protection activities, hygiene matters, waste disposal and related activities are observed.

8. Transportation

and storage of construction

materials

Trucks carrying construction materials

should not be overloaded and covered with

tarpaulins to reduce fines getting airborne. Avoid storage of construction materials

beside the road, around water bodies,

residential or public sensitive locations. Materials loading and unloading should not

cause nuisance to the people by way of

Site observations Check lists Public complaints

Being complied to

The contractor is advised to cover the materials when it transport to the sites, handling and its storage. When monthly site visits conducting, these activities are observed.

Page 97: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

97

Potential Environmental

Impact Mitigation Action

Indicator or Means of verifications

Complied? Yes/Not

Complied/ Partly

Complied

Explanation if compliance status is partly complied

or not complied

Further actions/Timeline

noise, vibration and dust emission. Sand, rubble, metal, bitumen, cement etc

should be stored in designated areas to

ensure optimum utilization preferably on a

solid platform. Such materials should be

handled in environment friendly and

nuisance free manner.

9.Effect on local road network

Permit from LAs to use local roads prior to

using the roads for transportation of

construction materials, machinery and

equipment etc. The contractor should- ensure that

transportation of construction materials by

suppliers should not exceed the carrying

capacity of the local roads. Regular Maintenance of local roads and their

restoration which are used for hauling

activities for the construction related

activities.

Site observations Check lists Public complaints

Being complied to

The contractor has been advised to get permissions from relevant authorities prior to use local roads for his activities mainly for material transports. If the roads get damaged due to contractor’s activities, he is obligated to repair it immediately.

10. Soil erosion and surface runoff

Implement erosion control measures such as

fiber mats, gabions walls, rip raps and deep-

rooted grasses etc to erodible areas Seeding with a fast growing native species

and seed mix immediately after fill

placement to develop green cover to protect

the earth works.

Site observations Check lists Public complaints

Being complied to

According to the EMP, the contractor is advised to take all possible remedial actions against the soil erosion takes places such as structure construction areas, material sourcing areas, and road excavation areas.

Page 98: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

98

Potential Environmental

Impact Mitigation Action

Indicator or Means of verifications

Complied? Yes/Not

Complied/ Partly

Complied

Explanation if compliance status is partly complied

or not complied

Further actions/Timeline

Construction in erosion and flood- prone

areas should be restricted to the dry

season (excluding December

– February) Stabilization of embankment slopes and road

cuts by re-vegetation and take up a turfing

work as soon as possible before rains. Treat clearing and filling areas against flow

acceleration and construction work should

be carefully designed to minimize

obstruction or destruction to natural

drainage.

11. Effect on existing drainage pattern

Contractor should avoid storage of

construction materials and disposal of

debris around irrigation canals, cross

drainage and natural flow paths. Culverts and all other drainage paths have to

be appropriately designed by allowing

sheath flow and without any blockages. Provide temporary diverting drainage

facilities to construction sites while

repairing and replacement of obstructed

drains and structurally damaged culverts/

bridges.

Site observations Check lists Public complaints

Being complied to

The contractor has taken steps to avoid blockage, make temporary diverts, and cleaning existing drainage periodically.

Regular site visits and checklist

12. Protection of water resources

Avoid tapping water from sources in

residential areas being used by the local

community.

Site observations Check lists Public complaints

Being complied to

The contractor is advised to avoid unnecessary obstructs due to his works

Page 99: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

99

Potential Environmental

Impact Mitigation Action

Indicator or Means of verifications

Complied? Yes/Not

Complied/ Partly

Complied

Explanation if compliance status is partly complied

or not complied

Further actions/Timeline

Contractor should not obstruct or prevent

flowing of water when working closer to

water bodies. Construction works affecting the streams and

irrigation canals have to be undertaken

during the dry season with prior permission

from the concerned Department. Minimize excavation of beds of any streams,

irrigation systems, and other water

resources so that water flow in the beds is

unaltered.

Use of silt traps and erosion control

measures where the construction is carried

out in close proximity to the water bodies to

avoid entering of cement, sand and other

particulate matters which cause turbidity

and increase sedimentations. Storage of construction materials which are toxic, hazardous and containing other fine particles would be sited at least 500 from water bodies to avoid its contamination to water resources. Trenches around the storage area to confine the flow outs.

to nearby water sources. The contractor has taken steps to minimize the effects from their bridge construction sites. Silt traps are located at yard, and crusher plant Stock piles are situated away from the water sources.

13. Affect

on flora and

fauna

Approval from DoF should be

obtained prior to start of project activities

towards felling of trees and planning

towards carrying out compensatory

Site observations Check lists Public complaints

Being complied to

All the trees that to be removed within the ROW are clearly marked by Survey prior to construction started.

Page 100: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

100

Potential Environmental

Impact Mitigation Action

Indicator or Means of verifications

Complied? Yes/Not

Complied/ Partly

Complied

Explanation if compliance status is partly complied

or not complied

Further actions/Timeline

afforestation.

Contractor will prevent his work force

from gathering fire wood from surrounding

habitats, disturbing tothe flora, fauna

including hunting of animal and fishing in

water bodies All construction materials extraction sites,

material processing plants, storage yards

and construction vehicle service stations

will be located away from the water bodies,

environmental sensitive locations Proper awareness programs to be conducted

regarding conservation of flora, fauna

including ground vegetation to all drivers,

operators and other workers

The trees that possible to save within ROW will be protected. A re-planting program will be carried out as a compensation to cut trees. More than 500 plants will be planted along the road Provisions are provided to conduct the Environmental awareness and the contractor has advised to carry out the programm

14.

Disruption of traffic

Provide and publicize advance notices to local communities about the

schedule of construction activities. Installation of traffic waning signs, signaling

system, flagman at the construction sites. Provide safe and convenient passage to

vehicles, passengers and livestock from the

approaching roads. Traffic and safety management plan should

be implemented in close coordination with

local communities/authorities and police

Site observations Check lists Public complaints

Being complied to

The contractor has submitted the traffic control plan and it is approved. The traffic safety plan is implemented and site safety /traffic safety activities are smoothly functioning.

Monthly observations parallel to monthly meeting

Page 101: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

101

Potential Environmental

Impact Mitigation Action

Indicator or Means of verifications

Complied? Yes/Not

Complied/ Partly

Complied

Explanation if compliance status is partly complied

or not complied

Further actions/Timeline

department during the entire construction

period. Contractors to plan and implement diversion

roads for sensitive locations with prior

approval of the Supervision Consultant.

15. Air quality Contractors should place crushers and hot mix plants at least 500 m away

from residential areas or other social

infrastructures (school, hospital/religious

places etc)

Such establishments should strictly comply

to National Emission Standards for all

construction vehicles, equipment and

material processing plants Dust extraction/suppression systems should

be fitted to crusher units, construction

vehicles and hot mix plants

Sprinkling of water to the construction

sites and haul roads which are being used for

the transportation of construction materials

in regular intervals towards dust

suppression. Placing of dust barriers nearby schools,

religious places, market etc. Use construction equipment, machinery and

Site observations Check lists Public complaints

Being complied to

The periodical cheeking of air quality is being progressed along the road as well as selected plant sites to see possible pollutions Dust controlling activities such as water sprying for road construction areas, dust barriers for plant operation are implemented

Monthly site observations parallel to monthly meeting

Page 102: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

102

Potential Environmental

Impact Mitigation Action

Indicator or Means of verifications

Complied? Yes/Not

Complied/ Partly

Complied

Explanation if compliance status is partly complied

or not complied

Further actions/Timeline

vehicles which are in good condition and

those to be regularly maintained.

16. Noise and vibration

Strictly implement noise control regulations

for all construction vehicles and equipments. Contractors should equip their heavy

construction equipment with acoustic

enclosures/ silencers to limit the

construction equipment not to generate

noise exceeding 75 db (compacters, loaders,

vibrators, cranes, diesel generator sets) Limit working time for activities that

create noise only between 6.00 am to 6.00

pm except for construction site near

schools, offices, religious places.

Contractors should schedule their activities

at sensitive locations in consultation with the

relevant authorities (school’s principals,

high-priest etc.) Regularly maintain all construction vehicles

and machinery to meet the National

Emission Standards.

Site observations Check lists Public complaints

Being complied to

The periodical cheeking of noise and vibration are being progressed along the road as well as selected plant sites to see possible impacts The contractor is obligated to maintain the national standards of noise and vibrations during his construction activities.

Monthly site observations parallel to monthly meeting

17. Personal safety and health

Organize awareness programs regarding personal safety of workers and

general public during construction period. Establishment of safety provisions to

Site observations Check lists Public complaints

Being complied to

The contractor is being implemented tool box meeting/awareness campaigns periodically.

Monthly observations, and weekly checklist observations

Page 103: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

103

Potential Environmental

Impact Mitigation Action

Indicator or Means of verifications

Complied? Yes/Not

Complied/ Partly

Complied

Explanation if compliance status is partly complied

or not complied

Further actions/Timeline

reduce the likelihood of accidents by

placing warning signs, speed limit

markings, speed breakers and signals to

particular locations. Providing appropriate PPEs such as

protective footwear, helmets, goggles, eye-

shields and clothes to the workers

depending on their activities (Mixing asphalt,

blasting, handling equipments etc) and

motivating the workforce for their usage. Establishing first aid facilities and

Ambulance facilities at active working sites

to meet emergency situations. Use experienced and well trained workers

for the handling of machinery, equipment

and material processing plants. Contractor should implement STD/

HIV/AIDS awareness programs for general

public in and around project

implementation area and workers to reduce

the risk of spreading STD among them.

Safety provisions are provided to caring out the PPEs and the Traffic safety activities. First aid facilities, and worker rest room are provided. Standstill emergency vehicle is available. The contractor has submitted a schedule about the HIV/AIDS awareness program that to be conducted and these activities are being implemented.

18. Bridge

construction

Design of bridges should comply with the requirements of “Bridge Design Manual” of RDA. Contractor should provide safe and

convenient passage or alternative access to

road users for the entire construction period

Site visits & observations Weekly checklist

Being complied

The contractor has taken step to implement bridge construction activities according to the approved methodology with minimum environmental

Monthly progress meetings and checklists

Page 104: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

104

Potential Environmental

Impact Mitigation Action

Indicator or Means of verifications

Complied? Yes/Not

Complied/ Partly

Complied

Explanation if compliance status is partly complied

or not complied

Further actions/Timeline

seeking approval from the Supervision

consultant. Smooth traffic flow to be ensured

during the entire construction period with

the provision of appropriate safety

measures. During piling activities, the Bentonite

slurry generated will be collected and air

dried. Then it should be disposed in

disposal yards. In no case the slurry will be

discharged to the water bodies and

agricultural land etc.

damage to the nearby or vicinity areas. The consultant and the client will keenly observe their activities and guiding when he needs to dispose the slurry into open.

19. Access to Public utilities

Access to new public utilities should be

clearly marked within the road reservation in

consultation with the concerned

Departments.

Site visits & observations Weekly checklist

Being complied

The contractor has completed the access survey in section 01 and is to be completed in section 02. This is for identifying the neediness of the new access along the ROW. The provisions provided to make better accesses to public parallel to road development.

Monthly progress meetings and checklists

B. Operation stage

20. Encroachment of the RoW

Routine checking to discourage

encroachments and removal of unauthorized

structures from RoW in consultation with

Police Department. Popularizing and Implementation of rules

and regulations with respect to RoW and

Site visits & observations To Be complied

During the performance based management, the contractor, the Executive Engineer and the PMU staff will conducting routing visits to see any encroachments along the

Monthly progress meetings

Page 105: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

105

Potential Environmental

Impact Mitigation Action

Indicator or Means of verifications

Complied? Yes/Not

Complied/ Partly

Complied

Explanation if compliance status is partly complied

or not complied

Further actions/Timeline

to avoid encroachment from the RoW. road

21. Clearing of Cross

Drainage Structures

Periodical clearing of Cross drains and

side drains (specially before commencing of

rainy season) to facilitate easy

discharge of

Site visits & observations To Be complied

Do Monthly progress meetings

22. Road safety Enforcement of the speed limits, traffic rules and regulations to the sensitive

locations, Installation of the warning signs,

marking of center line, pedestrian crossings,

bus halts and other utilities.

Site visits & observations To Be complied

Do Monthly progress meetings

23. Road

maintenance

Developing and Implementation of periodical maintenance program.

Site visits & observations To Be complied

Do Monthly progress meetings

Page 106: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

106

Appendix: 05 Public Complains

Table 3.1 (a)The list of complains up to 31st March 2017 for B295 ‘Moratuwa-Piliyandala’ Road # Date Complainant Nature of Complaint Action Taken Resolution

1 26-May-15 B.D.P. Kularathne (4+230 RHS) 241, Moratuwa Road, Suwarapola, Piliyandala

Not to upgrade culvert discharging to lead-away drain through their property

Employer agreed to omit culvert improvement

Contractor instructed accordingly on 09/03/2016

2 10-Aug-15 Haklis Bathlo, Piliyandala (LHS)

Remove signboard near their gate

Contractor directed to remove sign

Sign removed on 10/12/2015

3 27-Sep-15 Existing culvert at Km 3+027 unable to cope with heavy flow

Contractor cleared culvert inlet, outlet and lead-away channel to improve flow

Completed on 12/10/2015

4 28-Sep-15 N.C. Dulwala (4+560 RHS) 175/5, Moratuwa Road, Piliyandala

Objects to improving existing lead-away drain through her property

Lead-away drain improvement has been referred to Municipal Authority

Action by Municipal Authority and it is being processed

5 16-Oct-15 B.D.M.U. Kularathne (4+280 LHS) 196, Moratuwa Road, Piliyandala

i. Request for house access, ii. Retaining wall to front

boundary, and iii. Protection of water well

i. Contractor directed to provide access,

ii. PE to refer wall to GRC, and iii. Contractor directed to

construct drain to protect water well

Work completed on 08/06/2016

6 16-Oct-15 M. Kulawathi De Costa (4+840 LHS) 88/2, Moratuwa Road, Piliyandala

Request for additional compensation for land acquisition and payment delay

Referred to Employer Completed on 15/03/2016

7 16-Oct-15

H.M. Upasena (3+940 RHS) 263, Ransara Reception Hall, Moratuwa Road, Suwarapola, Piliyandala

Request to construct their two accesses one-by-one to avoid disturbing business

Contractor directed to construct accesses one-by-one

Work completed on 15/11/2015

8 16-Oct-15 Y.A. Dayarathne 142/6, Moratuwa Road, Piliyandala

Request to construct by-road access suitable for large vehicle

Contractor directed to provide sufficient cover slabs

Work completed on 20/10/2015

9 16-Oct-15 P.A.D. Rohana (3+770 RHS) 285/A, Moratuwa Road, Suwarapola,

Request to protect front door frame during construction

Structure encroaches into ROW and required demolition

Completed on 12/12/2015

Page 107: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

107

# Date Complainant Nature of Complaint Action Taken Resolution

Piliyandala

10 16-Oct-15 W.A.A.P. Gunathilaka (4+640 RHS) 126, Moratuwa Road, Piliyandala

i. Request to protect boundary wall during construction, and

ii. Provide temporary vehicle access

Contractor directed to protect boundary wall and ensure uninterrupted access

Work completed on 05/11/2015

11 16-Oct-15 I.D. Siripala Perera (3+990 LHS) 248, Moratuwa Road, Piliyandala

i. Request two access to property, and

ii. Shift CEB pole at boundary

i. Double access request referred to Employer, and

ii. Contractor directed to attend to utility relocation

Work completed on 03/03/2016

12 16-Oct-15 B.D.D.N. Kularathne (4+280 RHS) 223, Moratuwa Road, Piliyandala

i. Request 2 months to demolish shop front for construction, plus

ii. Additional resettlement compensation, plus

iii. Additional compensation for disturbance to business

(i) Contractor directed to coordinate construction with shop demolition, and

(ii) Compensation issues referred to Employer

(i) Work completed on 05/01/2016, and

(ii) Pending

13 13-Nov-15 P.G.R. Anula Gamlath 320/1, Basil Niwasa, Suwarapola, Piliyandala

Request for alternative property access location at Km 3+250 LHS

Contractor directed to provide an access suitable for the property

Work completed on 08/05/2016

14 23-Dec-15 M.P. Chandana Perera 237, Moratuwa Road, Piliyandala

Request for additional access at KM 4+180 RHS

Referred to Employer Work completed on 10/03/2016

15 15-May-15 B.D.P. Kularathne 241, Moratuwa Road, Suwarapola, Piliyandala

Request not to construct new culvert at Km 4+238

Instruction issued to alternatively open and extend existing culvert at Km 4+210

Work done on 09/03/2016

16 06-Jan-16 Muditha Chaminda Sudasinghe 320, Moratuwa Road, Suwarapola, Piliyandala

Request to slope cover slabs at Km 3+235 LHS

Site inspection determined there is no need to install sloping cover slabs

Resolved on 12/02/2016

17 Jan-16 K. Indika Thilakarathne 226/2, Moratuwa Road, Suwarapola

Request not to open existing culvert at Km 4+210

Referred to Employer for discussion with local government authority

Work completed by Municipal Authority on 25/02/2016

18 12-Jan-16 T.A. Priyarathna Suwarapola, Deniya, Piliyandala

Concern about potential flooding of access road during rainy season at Km 3+263 RHS

Referred to Employer for discussion with local government authority

Work completed by Municipal Authority on 25/02/2016

19 13-Jan-16 G.T.S. Thilakarathne 37B, Hadigama, Piliyandala 317, Moratuwa Road, Suwarapola,

Request for lead-away drain at Km 3+446 RHS

Referred to Employer for discussion with local government authority

Action by Municipal Authority to be

Page 108: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

108

# Date Complainant Nature of Complaint Action Taken Resolution

Piliyandala completed

20 14-Jan-16 C.D. Palathirathne 320/A, Moratuwa Road, Deniya, Piliyandala

Request to slope cover slabs and provide 2m paving at Km 3+172 LHS

Instruction issued to Contractor Work completed on 28/04/2016

21 15-Jan-16 Sandya Jayawardhna 321/5, Basil House, Moratuwa Road, Suwarapola, Piliyandala

Request for additional access at Km 3+153 LHS

Employer determined that existing access is sufficient

Resolved on 28/01/2016

22 20-Jan-16 K.D. Laksiri 317/B, Moratuwa Road, Suwarapola, Piliyandala

ROW at Km 3+668 RHS ROW confirmed and instruction issued to Contractor to proceed

Work completed on 20/02/2016

23 23-Jan-16 Ravina Mortes 331/1/A, Moratuwa Road, Deniya Junction

Request for cover slabs at Km 3+268 LHS

Instruction issued to Contractor to provide cover slabs for culvert catch pit

Work completed on 07/06/2016

24 25-Jan-16 Sanio Lanka Apparels 226/2, Moratuwa Road, Suwarapola, Piliyandala

Request to cover culvert opening at Km 4+210

Necessary instruction issued to Contractor on culvert design

Work in progress

25 25-Jan-16 S.D.J. Jayasinghe 320/1, Suwarapola, Piliyandala

Boundary wall at 3+140 LHS collapsed on 28-Jan-16

Contractor has advised Insurance Company and commenced reconstruction

Work completed on 14/05/2016

26 01-Mar-16 DGM NWS&DB Damage to existing water line at Km 3+137 RHS

Advised Contractor to take action with NWS&DB

Water line repaired on 03/03/2016

27 14-Mar-16 Rasanga Gamage 213/4, Gangarama Road, Werahara, Boralegamuwa

Request for more substantial cover slabs at Km 2+220 LHS

Contractor instructed to provide medium duty cover slabs

Work in progress

28 18-Mar-16 S.D. Siriyawathi No.128C, Moratuwa Road, Piliyandala

Request for suitable access arrangement at Km 4+730 LHS

Instruction issued to Contractor to accommodate access for finished road level

Work completed on 06/06/2016

29 05-Apr-16 L.A.S. Suwarna Ajantha No.64/2, Moratuwa Road, Suwarapola, Piliyandala

Drainage concern at Km 4+230 RHS

Instruction issued to Contractor to close drain opening

Work completed on 05/05/2016

30 05-Apr-16 N. Jayasundara Asala Steel Centre, No.279A Motatuwa Road, Suwarapola

Request for suitable access at Km 3+830 RHS

Instruction issued to Contractor Completed on 05/08/2016

31 26-Apr-16 P.L.A. Perera, No.307 Moratuwa Road, Suwarapola

Request for extension of provided access at Km 3+670 RHS

Sent to the PE for further advise Completed on 10/07/2016

32 04-May-16 N. Jayasundara No.108/A, Horana Road, Piliyandala

Request for cover slabs at Km 3+830 RHS

Instruction issued to Contractor for cover slabs

Completed on 05/08/2016

Page 109: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

109

# Date Complainant Nature of Complaint Action Taken Resolution

33 28-May-16 SLT Underground cable at Km 0+970 RHS damaged during construction activity

SLT and Insurance Company notified

Cable repaired on 29/05/2016 and settlement of insurance claim pending

34 31-May-16 Vishwakala Labour Camp Fire damaged operators accommodation

Insurance Company notified

Insurance claim paid and repairs carried out on 15/01/2017

35 10-Jun-16 P.A.R.P. Perera No. 302A, Moratuwa Road, Suwarapola, Piliyandala

Request for suitable access at Km 3+360 LHS

Instruction issued to Contractor Completed on 16/08/2016

36 10-Jun-16 Bodhi Bharakara Mandalaya, Purana Bodhi Rajaya, Suwarapola, Piliyandala

RDA Boundary problem at Km 3+558-3+603 LHS

Survey Department has marked RDA boundary

Boundary confirmed and work resumed on 15/09/2016

37 10-Jun-16 K. Sanath Nihal, No 259, Maratuwa Road, Suwarapola, Piliyandala

Request for suitable access at Km 3+980 - 4+000 RHS

Instruction issued Contractor to provide vehicle access

Completed on 28/02/2017

38 17-Jun-16 K. Chaya Pranandu, No. 14, Johon De Silva Mawatha, Molpe, Moratuwa

RDA Boundary problem at Km 3+558-3+603 LHS

Survey Department has marked RDA boundary

Boundary confirmed and work resumed on 15/09/2016

39 30-Jun-16 W.S. Wimala Fernando, 349/1, Moratuwa Road, Kospelana, Piliyandala

Request to provide steps for access

Contractor instructed to provide suitable steps for access

Completed on 14/01/2016

40 09-Jul-16 S.D. Srimal, 242, Moratuwa Road, Suwarapola, Piliyandala

Complaint over vibration during construction activity

Contractor directed to investigate and carry out vibration measurement

Vibration measured and found to be within allowable limit on 18/08/2016

41 11-Jul-16 V.S. Weerakkodi, 1B, Gangule Mawatha, Suwarapola, Piliyandala

Complaint about dust and disposal truck speed

Contractor directed to operate disposal yard within approved constraints

Contractor took action on 15/07/2016

42 11-Jul-16 I.A.D.U.R. Perera, 1, Gangule Mawatha, Suwarapola, Piliyandala

RDA boundary at Km 3+560 LHS Referred to PE

Boundary confirmed and work resumed on 15/09/2016

43 08-Aug-16 Ransara Reception Hall Request cattle trap cover on Referred to PE who has further Resolved

Page 110: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

110

# Date Complainant Nature of Complaint Action Taken Resolution

263, Moratuwa Road, Suwarapola, Piliyandala

concrete drain at Km 3+900 RHS referred to EE 05/03/2017

44 29-Aug-16 K.I. Thilakaratne 226/2, Moratuwa Road, Piliyandala

Request to omit culvert parapet wall to avoid blocking access at Km 4+207

Instruction issued to Contractor Completed on 10/03/2016

45 07-Sep-16 Dialog Cable damaged during construction work at Km 3+369 LHS

Contractor notified Dialog and Insurer and lodged insurance claim

Insurance claim pending

46 13-Sep-16 Wepataira Hemaloka Thero Siri Wijayaramaya Udayogi Pura, Wewala, Piliyandala

Request to construct temple road at Km 2+980

Contractor requested to submit a proposal

Work done on 15/11/2016, but Contractor proposal awaited

47 22-Sep-16 U.D. Pilyasena 148, Moratuwa Road, Piliyandala

Request to remove new parapet wall at Km 4+538

PE advised to remove parapet wall; Contractor instructed accordingly

Pending

48 17-Oct-16

Nihal Pagoda Arachchi Bodhi Bharakara Mandalaya, Purana Bodhi Rajaya, Suwarapola, Piliyandala

Request for line marking and pedestrian crossing at Km 3+560 LHS

Incorporated in line marking design

Completed on 12/01/2017

49 19-Oct-16 Hemantha U. Arachchi 238, Moratuwa Road, Suwarapola, Piliyandala

Km 4+070 LHS access road connection issue

Contractor instructed to match access road level with B295

Work in progress

50 19-Oct-16 T.A. Piyarathna Suwarapola, Deniya Road, Piliyandala

Water stagnation at Km 3+268 RHS

Lead-away drain action by Kesbewa Urban Council

Urban Council work completed 15/03/2017

51 31-Oct-16 G.H.D. Wijeesena, Piliyandala

Request for cover slabs over drains

Cover slabs instructed for electrical post area

Work in progress

52 29-Dec-16 Nuwani Construction, 128, Moratuwa Road, Piliyandala

Request for cover slabs Details submitted to PE for approval

Pending

Page 111: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

111

Table 3.1 (b)The list of complains up to 31st March 2017 for B389 ‘Ratmalana-Mirihana’ Road # Date Complainant Nature of Complaint Action Taken Resolution

1 2-Sep-15 C.L. Jayawardhana (0+210 RHS) 62A, Mirihana Road, Nugegoda

Request for temporary access during construction

Contractor directed to provide continuous access

Temporary access provided on 20/09/2015

2 7-Sep-15 H.M.D.D. Dammika (1+230LHS) 337, Amarasa Hotel, Gamsabha Junction, Nugegoda

Claim that compensation was not paid

Referred to Employer RDA have inspected and replied to the Complainant on 17/10/2015

3 17-Sep-15 Wimaladharma Ekanayaka (0+065 RHS) 73/1, Mirihana Road

Water flowing to their property

Contractor instructed to construct lined side drain

Completed on 15/03/2017

4 21-Sep-15

Palitha Wijayawardhana (1+150 LHS) 111/7, Subodarama Road, Nugegoda

Request to open drain from by-road

Contractor directed to allow storm-water to flow from by-road to main road drainage

Completed on 16/02/2016

5 23-Sep-15 Ishara Wijesinghe (0+620 LHS) 30/1, Mirihana Road, Nugegoda

Boundary wall collapsed during lined drain construction

Contractor directed to reconstruct boundary wall as soon as possible

Reconstruction completed on 10/06/2016

6 26-Oct-15 D. Kadahawala (0+520 RHS) 23, Mirihana Road, Nugegoda

Request to avoid property damage during construction

Contractor directed to liaise with resident and avoid damage

Work completed on 14/03/2016

7 11-Dec-15 D.H.H.M. Sathischandra 126D, Subadrarama Road, Nugegoda

Request to maintain drainage at Km 0+820 RHS

Contractor directed to check level at location and ensure drainage to new roadside drain

Work completed on 14/02/2016

8 Dec-15 S.D. Devasunara 107, Subadrarama Road, Nugegoda

Request to relocate telephone post at Km 1+113 LHS

Contractor directed to liaise with Telecom and property owner over post relocation

Work completed on 09/03/2016

9 Jan-16 D.R.K.V. Wijegunawardhana 51, Papiliyana Road, Gangodavila, Nugegoda

Disputing ROW land boundary at Km 1+550 LHS

Boundary checked and work cleared to proceed

Work completed on 09/03/2016

10 9-Jan-16 B.S.A.S.N. Sudasighe 22/A, Papiliyana Road, Gangodavila, Nugegoda

Boundary wall at Km 1+340 RHS collapsed during lined drain construction

Contractor directed to promptly reconstruct damaged wall and access

Contractor has submitted claim to Insurer and completed reconstruction on 20/01/2017

11 9-Jan-16 Telecom Contractor damaged buried STL wire at Km 1+820 LHS

Contractor advised SLT and Insurers

SLT repair completed but insurance claim pending

Page 112: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

112

# Date Complainant Nature of Complaint Action Taken Resolution

12 Jan-16 B.S.A.S.N. Sudasighe 22/A, Papiliyana Road, Gangodavila, Nugegoda

Request for cover slabs at Km 1+340 RHS

Contractor directed to provide cover slabs

Work completed on 05/03/2016

13 20-Jan-16 M.D.N. Daminda 10, Papiliyana Road, Nugegoda

Request for specific house access arrangement at Km 1+315 RHS

Contractor directed to provide access as requested

Work completed on 28/02/2016

14 25-Jan-16 V.A.D. Kularathne 162, Subadrarama Road, Nugegoda

Request for specific house access arrangement at Km 1+135 RHS

Contractor directed to adjust drain height to suit access

Work completed on 18/01/2017

15 29-Feb-16 SLT SLT post at Km 1+430 RHS collapsed onto three-wheeler during heavy rain

Contractor notified Insurer and lodged claim

New pole erected on 02/03/2016 but insurance claim pending

16 29-Feb-16 LECO

Underground cable Km 0+880 to 0+920 RHS damaged during construction activity

Contractor notified LECO and Insurer and lodged claim

LECO repair completed on 02/03/2016 but insurance claim pending

17 04-Mar-16

Underground cable at Km 0+078 LHS damaged during construction activity

Contractor notified LECO and Insurer and lodged claim

Cable repaired and Contractor paid compensation to SLT on 05/04/2016

18 26-Mar-16 Ananda Perera Maddumage 111/9, Subadhraramaya Road, Gangodavila, Nugegoda

Request that by-road drainage be blocked from entering lined side drain at Km 1+124 LHS

Referred to Employer as contradicts requests of other residents

Resolved on 05/04/2016

19 31-Mar-16 Bandula de Silva, No 81, Pepiliyana Road, Gangodawila, Nugegoda.

Request for house access at Km 1+810 LHS

Contractor directed to provide access as requested

Work completed on 03/05/2016

20 25-Apr-16 LECO

Underground cable at Km 0+750 LHS damaged during construction activity

Contractor notified LECO and insurer and lodged claim

Cable has been repaired on 26/04/2016 but insurance claim pending

21 29-Apr-16 LECO Electricity pole collapsed during construction at Km 0+240 RHS

Contractor notified LECO and insurer and lodged claim

New pole erected on 29/04/2016 but insurance claim pending

22 06-May-16 SLT

Underground cable at Km 0+970 LHS damaged during construction activity

Contractor notified SLT and insurer and lodged claim

Cable has been repaired on 08/05/2016 but insurance claim pending

Page 113: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

113

# Date Complainant Nature of Complaint Action Taken Resolution

23 07-May-16 LECO

Underground cable at Km 0+920 RHS damaged during construction activity

Contractor notified LECO and insurer and lodged claim

Cable has been repaired 08/05/2016 but insurance claim pending

24 11-May-16

Boundary wall at Km 0+640 LHS collapsed during construction activity

Contractor directed to promptly reconstruct damaged wall and access

Contractor has submitted claim to Insurer and is proceeding with reconstruction

25 17-May-16 A.I. Walikada No 128, Subadhrarama Road

Damage to house roof canopy during construction activity

Contractor directed to promptly repair damaged canopy

Work completed on 08/08/2016

26 28-May-16 SLT

Underground cable at Km 0+360 LHS damaged during construction activity

Contractor notified SLT and insurer and lodged claim

Cable has been repaired on 30/05/2016 but insurance claim pending

27 06-Jul-16 SLT

Underground cable at Km 0+680 LHS damaged during construction activity

Contractor notified SLT and insurer and lodged claim

Cable has been repaired on 07/07/2016 but insurance claim pending

28 08-Jul-16 LECO Electrical pole collapse while backhoe working at Km 0+250 RHS

Contractor notified LECO and insurer and lodged claim

Electrical post has been repaired on 08/07/2016 but insurance claim pending

29 09-Jul-16 D.U.R. Wijesinghe, 17B, Mirihana Road, Nugegoda

Complaint about vibration Contractor directed to investigate and

Vibration level measured and contractor directed to adjust rolling procedure on 12/07/2016

30 30-Jul-16 SLT

Underground cable at Km 0+735 LHS damaged during construction activity

Contractor notified SLT and lodged Insurance claim

Cable has been repaired on 01/08/2017, but insurance claim pending

31 30-Jul-16 SLT

Underground cable at Km 1+883 RHS damaged during construction activity

Contractor notified SLT and lodged Insurance claim

Cable has been repaired on 01/08/2017, but insurance claim pending

32 10-Aug-16 Karunasena Moramudali 13, Kattiya Junction, Mirihana Road, Nugegoda

Request for cover slabs at Km 0+647 to 0+660 RHS

Instruction issued to Contractor

Work completed on 18/01/2017

Page 114: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

114

# Date Complainant Nature of Complaint Action Taken Resolution

33 08-Sep-16 M.D.S.F. Arthakularathne 87, Papiliyana Road, Nugegoda

Request to cover slab Provided Work completed on 25/09/2016

34 11-Sep-16

Boundary wall at Km 1+330 RHS collapsed during construction activity

Contractor directed to promptly reconstruct damaged wall

Contractor has submitted claim to Insurer and reconstructed the wall on 22/01/2017

35 11-Sep-16 SLT

Underground cable at Km 1+350 LHS damaged during construction activity

Contractor notified SLT and lodged Insurance claim

Cable has been repaired on 12/09/2017, but insurance claim is pending

36 23-Sep-16 LECO

Underground cable at Km 0+890 RHS damaged during construction activity

Contractor notified LECO and lodged Insurance claim

Cable has been repaired 24/09/2017,but insurance claim is pending

37 28-Sep-16 Malika Disanayaka 75, Mirihana Road, Nugegoda

House access problem Instruction issued for steps Work in progress

38 20-Oct-16 35, Privet Lane, Mirihana Access problem Site inspected and Contractor instructed to take mitigation action

Completed on 21/12/2017

39 27-Oct-16 S.M.A. Senavirathna 17, Subadrarama Road, Gangodavilla, Nugegoda

Access problem Site inspected and Contractor instructed to take mitigation action

Completed on 28/12/2016

40 01-Nov-16 W. Ekanayake 73/1, Mirihana Road, Nugegoda

Damage to property entrance by water line construction

Contractor instructed to rectify access damage

Completed on 23/11/2016

41 03-Nov-16

Thabbowa Ananda Revatha Thero, Subadrarame, Athula Rajamaha Viharaya, Gangodavila, Nugegoda

Request for stone wall Referred to PE Awaiting Employer response

42 15-Nov-16 Police Inspector, Mirihana Request to construct by-road

By-road scope confirmed Work completed on 20/11/2016

43 01-Dec-16

Director, Agricultural & Agrarian Insurance Board, 117, Subadrarama Road, Gangodavila, Nugegoda

Access problem Contractor instructed to improve property access

Work completed on 18/12/2016

44 29-Dec-16 Amith Batugedara, 106, Old Kesbewa Road, Nugegoda

Water ponding Contractor instructed to remove pipe culvert

Work completed on 06/01/2017

45 11-Jan-17 M.A. Perera Request to construct by- By-road construction Solved on 22/01/2017

Page 115: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

115

# Date Complainant Nature of Complaint Action Taken Resolution

115, Subadrarama Road, Nugegoda

road and damaged boundary wall

completed and no boundary wall damage identified

46 06-Feb-17 M.A.R.K. Perera 77A, Mirihana Road, Nugegoda

Request for new water connection

Location inspected & approval given to excavate road

Work completed on 03/03/2017

47 20-Feb-17 W. Ekanayaka 73/1, Mirihana Road, Nugegoda

Request to add pedestrian crossing

Referred to RDA Awaiting Employer decision

Page 116: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

116

Table 3.2 The list of complains up to 31st March 2017 for B084

# Date Complainant Description Action Taken Resolution

1 21-Dec-16 Mr. A.A.D. Jagath Kumara 252, Kahathuduwa, Polgasowita B084 Km 19+680 RHS

Steep access slope due to road realignment

Survey carried out to amend alignment

Vertical alignment adjusted to improve access on 26/01/2017

2 13-Jan-17 Mr. M.D. Jayarathne 72/3, Kondurawawa, Polgasowita B084 Km 15+220 RHS

Verification of boundary

Acquired boundary demarcated on 18/01/2017

Currently subject to court case

3 16-Jan-17 Mr. P.D. Diyasiri Pannarathne 52A, Kondurawawa, Polgasowita B084 Km 15+295 RHS

Request to change lead-away due to erosion from Culvert 16/1

Referred to Local Authority as lead-away outside ROW on 17/01/2017

Awaits action by Local Authority

4 01-Feb-17 Residents near “Samagi Praja Shalawa” B084 Km 14+993 RHS

Lead-away drain near “Samagi Praja Shalawa”

Referred to Local Authority as lead-away outside ROW on 03/02/2017

Awaits action by Local Authority

5 02-Feb-17 Mr. G. Gunasoma 22, Undurugoda, Polgasowita B084 Km 18+020 RHS

Verification of boundary

Acquired boundary demarcated

Referred to RDA Land Division for check with Section 2 hand-over on 02/02/2017

6 02-Feb-17 Mr. F.P. Wickramasinghe B084 Km 25+200 RHS

Concern about erosion after road excavation

Survey being carried out to determine protection requirements

To be considered under Section 4 design on 09/02/2017

7 02-Feb-17 Mr. Amarakoon Piyasena B084 Km 21+950 RHS

Request to realign road to give space for his shop

Survey being carried out Road design checked on 09/02/2017

8 02-Feb-17 Residents near Rilawala Junction B084 Km 18+200 RHS

Request for a bus shelter

Information being assembled on 09/02/2017

Bus halt location to be considered

9 02-Feb-17 Mrs. D.L.S. Kumari B084 Km 15+710 RHS

Request for parking space and steps to residence

Necessary setting out determined on 24/03/2017

Work in progress

10 06-Feb-17 Mr. D.K. Abesinghe B084 Km 19+930 Culvert 20/6

Request to move culvert

Relocated to 19+945 to align with lead-away

Work in progress

11 13-Feb-17 B.A. Perera, 311/13, Kahathuduwa, Polgaswita B084 Km 17+380 to 18+380

Request to remark land acquisition boundary

Survey to be carried out To be done for Section 2 hand-over

Page 117: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

117

# Date Complainant Description Action Taken Resolution

12 13-Feb-17 Mr. S.J. Nawagamuwa Lot No. 4334 B084 Km 26+100 RHS

Request for house access

To be surveyed once Section 4 handed-over

Access to be provided

13 13-Feb-17 Mr. B. Ariyawansha PP No.9265/Lot No.35 B084 Km 18+890 LHS

Request to verify land acquisition boundary

Directed to RDA Land Division on 03/02/2017

Survey to be carried out

14 15-Feb-17 Mr. K.B. Chandrapala B084 Km 18+735 LHS

Request to move Culvert 19/6 lead-away

Inspected by PE & EE on 20/02/2017

Lead-away to be moved by 5m

15 15-Feb-17 Mr. D.G.L. Ramyasiri B084 Km 18+890 LHS

Request to close Culvert 18/2 and lead-away

Inspected by PE & EE on 20/02/2017

Further inspection scheduled with SDE for 09-Mar-17

16 15-Feb-17 Mr. Ranjith Fernando B084 Km 18+730 LHS (Adjacent to as 15 above)

Request to move Culvert 19/6 lead-away

Inspected by PE & EE on 20/02/2017

Lead-away to be moved by 5m

17 16-Feb-17 Mr. A.D. Leelarathna B084 Km 14+300 RHS

Request to mark land acquisition boundary

Remarked correct boundary on 16/02/2017

Boundary agreed

18 16-Feb-17 A004 Km 17+300 to 17+800 RHS, Panagoda, Homagama

Request for retaining walls

Part of government property relocation work

Work in progress from 20/02/2017

19 20-Feb-17 Residents near Kesbewa B084 Km 13+800 to 14+200

Requests to connect rain water outlets to road drainage

RDA requirements explained to shop owners

Accepted on 20/02/2017

20 21-Feb-17 Resident near Kesbewa B084 Km 17+540 LHS

Request for time to demolish house

Accepted by PE Section 2 not yet handed-over on 21/02/2017

21 22-Feb-17 Mr. R. Geekiyanage, 252/1, Kahatuduwa, Polgasowita B084 Km 19+700 RHS

Request for soil to private property

RDA considering Referred to DS on 22/02/2017

22 28-Feb-17

Mr. S.A.I. Mahendradasa, 60A, “Udula”, Honnanthara Road, Piliyandala B084 Km 14+360 LHS

Improper utility shifting

Inspected & discussed with PE

Resolved on 01/03/2017

23 03-Mar-17 Mr. W.U.R. Rodrigo 29, ‘Ratnasiri’ Market Lane, Bandaragama

Request to remark acquisition boundary

Remarking scheduled Contractor agreed to remark ROW on 07/03/2017

24 03-Mar-17 Mr. W. Atigala 14/C, Horathumbuwa, Polgasowita (Lot No.217)

Request for time to demolish house

Accepted by PE on 07/03/2017

Demolition completed on

25 09-Mar-17 Mr. M.D. Premadasa Request to widen Culvert widening agreed Wider culvert instructed

Page 118: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

118

# Date Complainant Description Action Taken Resolution

136, Old Police Road, Kahathuduwa

culvert at Kesbewa Junction

on 10/03/2017

26 09-Mar-17 Mr. W.A. Ariyasena 778, High Level Road, Panagoda, Homagama (Lot Nos. 205 & 206)

Request for house access

Accepted by PE on 09/03/2017

Access scheduled

27 15-Mar-17 Mr. D.U. Wickramage 6F-1 Wickrama Pedesa, Horana Road, Kesbewa, Piliyandala

Request for unsuitable soil

Scheduled for inspection on 17/03/2017

28 22-Mar-17 D.A. Kumawathi 277/C, Horana Road, Kahathuduwa, Polgasowita

Loss of well Inspected with PE & NWS&DB on 22/03/2017

New water connection scheduled

29 22-Mar-17 B.A. Angohami 277/A, Horana Road, Kahathuduwa, Polgasowita

Loss of well Inspected with PE & NWS&DB on 22/03/2017

New water connection scheduled

30 24-Mar-17 Upashama Kottage 26/3, Sarwodaya Road, Honnaththara, Kesbewa

Request for shop steps Agreed to provide steps on 24/03/2014

Access scheduled

31 28-Mar-17 Mr. A.K. Perera 59-B, Horana Road, Honnaththara, Piliyandala

Concern about land inundation

Inspected and provisions made

Lined drain completed on 28/03/2017

Page 119: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

119

Table 3.3 The list of complains up to 31st March 2017 for B157

# Date Complainant Nature of Complaint /

Issue Action Taken Resolution

1 19-Oct-16 Mr. O.T.M.S.E. Premarathna Km 38+940 RHS

Cracks observed in Post Office Building walls

Referred to Contractor Monitoring in progress

2 01-Nov-16 Principal of Lewwanduwa Junior School Km 41+810 LHS

Requested removal of Kottamba tree

Referred to Contractor Contractor removed

tree On 07/11/2017

3 01-Nov-16 Mrs S. Weerakoon Weera Niwasa, Lewwanduwa Km 41+950 RHS

Request for access Contractor requested to place cover slabs over

lined drain

Cover slabs installed On 02/12/2016

4 01-Nov-16 Mr. U.K.D. Asela Pallegodawatte, Lewwanduwa Km 41+980 LHS

Request for access Contractor requested to place cover slabs over

lined drain

Cover slabs installed On 02/12/2016

5 03-Nov-16 Mr. S. Kuruneru, Lewwanduwa Km 42+100 RHS

Request for retaining wall

Contractor instructed to incorporate wall in lined

drain

Construction completed on 20/12/2016

6 04-Nov-16 Mr. J.K.P.S. Jayaneththi Pallegodawatte, Lewwanduwa Km 41+810 RHS

Request for access Contractor requested to place cover slabs over

lined drain

Cover slabs installed On 02/12/2016

7 22-Nov-16 Mr. H. Perera 632, Siyathko, Lewwanduwa Km 41+750 RHS

Existing access affected by raised road profile

Contractor providing temporary access

To be finally resolved by the permanent work

8 24-Nov-16 Mr. D.U. Jayaneththi Heel House, Lewwanduwa Km 41+250 RHS

Request for access Contractor requested to place cover slabs over

lined drain

Cover slabs installed On 02/12/2016

9 24-Nov-16 Mr. M.V. Wimaladasa Lewwanduwa Km 41+160 RHS

Request for access Contractor requested to place cover slabs over

lined drain

Awaits construction of lined drain

10 25-Nov-16 Mr. K.A.D.K. Kodithuwakku Lewwanduwa Km 39+560 RHS

Existing drain temporarily blocked by

construction

New lined drain under construction

Work is in progress

11 28-Nov-16 Mrs. D.S.T. Samarakoon Shamin, Kopiwatte Km 40+530 RHS

Request for access Contractor requested to place cover slabs over

lined drain

Cover slabs installed On 21/12/2016

12 28-Nov-16 Mr. K.A.D. Sanjeewa Lewwanduwa

Request for retaining wall

Contractor instructed to incorporate wall in lined

Construction completed

Page 120: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

120

# Date Complainant Nature of Complaint /

Issue Action Taken Resolution

Km 41+800 RHS drain On 25/02/2017

13 24-Dec-16

Mr. K.M.G. Ananda Pallegodawatte, Lewwanduwa Km 41+870 RHS

House cracks Referred to Contractor Monitoring in progress

14 26-Dec-16 Mr. K.A.D.K. Kodithuwakku Lewwanduwa Km 39+560 RHS

House cracks Referred to Contractor Monitoring in progress

15 03-Jan-17 Mr. K.A.D.K. Kodithuwakku Lewwanduwa Km 39+560 RHS

Requests RFL to be raised to flood level

RFL raised to avoid frequent flooding

Work in progress

16 03-Jan-17 Mr. W. Kodithuwakku, Dippita, Welipenna Km 39+850 LHS

Request for cover slabs Referred to PE as this is

undeveloped land PE to advise whether

additional slabs needed

17 03-Jan-17

Mr. D.P. Peiris Near Telephone Exchange, Lewwanduwa Km 40+635 RHS

Request for access Referred to Contractor Access reinstated On 20/02/2017

18 03-Jan-17 Mr. D.M. Kodithuwakku 68, Main Street, Welipenna Km 39+560 RHS

Requests RFL to be raised to flood level

RFL raised to avoid frequent flooding

Work in progress

19 03-Jan-17 Mrs. P.D. Arachchigoda Pannila Km 40+000 RHS

Request for cover slabs Referred to PE as this is

undeveloped land PE to advise whether

additional slabs needed

20 05-Jan-17 Mrs. G.W. Raniani Lewwanduwa Km 41+060 RHS

House cracks Referred to Contractor Monitoring in progress

21 26-Jan-17

Mrs. S. Jinadari Pallegodawaththa, Lewwanduwa Km 41+910 LHS

House cracks Referred to Contractor Monitoring in progress

22 26-Jan-17

Mr. K.M.G. Ananda Pallegodawaththa, Lewwanduwa Km 41+970 LHS

House cracks Referred to Contractor Monitoring in progress

23 26-Jan-17 Mr. D.M. Kodithuwakku 68, Main Street, Welipenna

Requests RFL to be raised to flood level

RFL raised to avoid frequent flooding

Work in progress

Page 121: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

121

# Date Complainant Nature of Complaint /

Issue Action Taken Resolution

Km 38+750 RHS

24 26-Jan-17

Mrs. S. Jinadari Pallegodawaththa, Lewwanduwa Km 41+910 LHS

Request for cover slabs Referred to PE as this is

undeveloped land PE to advise whether

additional slabs needed

25 26-Jan-17

Mr. S.S. Manjuka Near Telephone Exchange, Lewwanduwa Km 40+635 RHS

Request for protection wall at well

Contractor instructed to raise outer wall of lined

drain Work in progress

26 26-Jan-17 Mr. P.K. Piyadasa Kopiwatta, Welipenna Km 40+290 RHS

Request for heavy duty cover slabs

Scheduled requirement confirmed to Contractor

Work in progress

27 07-Feb-17 Mr. J.K.D.S.C. Jayawardena Kopiwaththa, Welipenna Km 40+297 LHS

Request protection measure to avoid

inconvenience from culvert discharge

Request forwarded to PE for approval

Pending approval

28 08-Feb-17 Mr. W.A De Silva Dickhena, Polwatta, Welipenna Km 38+110 LHS

Request for access steps Access steps to be

provided Work in progress

29 08-Feb-17

Mr. H.M.D. Mahindapala Aluthgama Road, Horawala Junction, Welipenna Km 36+840 RHS

Dust emission

Contractor took action to minimize dust emission

Water tanker allocated to spray water to

minimize dust emission

30 09-Feb-17

Mr. T.D.S.K. Tudugala "Sithumina" near the Telephone Exchange, Lewwanduwa, Welipenna Km 41+ 890 RHS

Request to raise the lined drain wall up to

road level

Request has been forwarded to PE for

approval

Pending approval

31 09-Feb-17

Mr. D.G. ThewarapperumaNo.12, Dikhena, Welipenna Km 38+115 LHS

Request to place cover slabs

Agreed to place cover slabs

Completed On 20/03/2017

32 09-Feb-17

Mrs. T. Jayaneththi Pallegadawatte, Lewwanduwa, Welipenna Km 41+895 RHS

Request to raise the lined drain wall up to

road level

Request has been forwarded to PE for

approval Pending Approval

33 09-Feb-17 Mr. R.D. Galabadaarachchi Request to reinstate Contractor agreed to Work in progress

Page 122: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

122

# Date Complainant Nature of Complaint /

Issue Action Taken Resolution

No.170B, School Junction, Welipenna Km 39+950 RHS

damaged gate posts and fence

reinstate the damaged gate posts and fence

34 20-Feb-17

Mr. I.G. Thewarapperuma, No.12/1, Dikhena, Welipenna Km 38+240 LHS & Near 39/1 Culvert LHS

Request for vehicular access with cover slabs

Request has been forwarded to PE for

approval

Pending Approval

35 20-Feb-17

The Principal, WP/MT/Lewwand-uwa Junior School, Lewwanduwa Km 41+810 LHS

Cracks developed in building walls due to

road construction activity

Contractor to monitor cracks

Monitoring of cracks is in progress

36 07-Mar-17

Pathmendra, Gaianayaka & Malkanthi Welipenna Km 37+130 LHS

Request for lined drain from Culvert 37/5 to

38/1

Requires inspection with RDA

37 15-Mar-17 A.A.M. Nazeer 180/2, Main Street, Welipenna Km 38+880 RHS

Request for retaining wall to Bridge 39/4 lead-

away drain

To be constructed after completing bridge work

38 15-Mar-17

D.S.S. Thevarapperuma Kopiwatta Junction, Welipenna Km 41+270 RHS

Request for access to new building

Precast slabs being prepared at Maga yard

39 15-Mar-17

U.I. Sendanayaka 29, Mahawatta Junction, Welipenna Km 38+127 RHS

Request access and lined lead-away drain beyond

ROW

Contractor to reinstate access but lead-away

requires RDA decision

40 16-Mar-17 Pradeshiya Sabawa, Mathugama Km 40+380 RHS

Request to asphalt nursery access

Requires RDA consideration

41 16-Mar-17

D.C. Jayaneththi Mahawatta Junction, Welipenna Km 38+200 LHS

Request for access steps Instruction issued to

Contractor Work completed 0n 21/02/2017

42 17-Mar-17 M.B.M. Hazen 5, Nallagoda Road, Welipenna Km 39+290 LHS

Issues with stormwater Contractor instructed to

provide temporary protection

43 17-Mar-17 K.D.A.S. Gamini Request for access steps Instruction issued to Work in progress

Page 123: Environmental Monitoring Report...Environmental Monitoring Report Annual Report July 2017 Sri Lanka: Southern Road Connectivity Project Prepared by Road Development Authority for the

123

# Date Complainant Nature of Complaint /

Issue Action Taken Resolution

Lewwanduwa, Welipenna Km 40+630 RHS

Contractor

44 17-Mar-17 P.V.S.S. Abagahawatta Lewwanduwa, Welipenna Km 41+680 RHS

Request for separate vehicle access

Requires RDA consideration