environmental monitoring report · engineers & contractors, vijayawada. contract signed in...

35
Environmental Monitoring Report This report has been submitted to ADB by the Project Implementation Unit, Karnataka State Highways Improvement Project, PIU, Bangalore and is made publicly available in accordance with ADB’s public communications policy (2011). It does not necessarily reflect the views of ADB. This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area. Project Number: 42513-013 May 2015 Period: April 2014 December 2014 IND: Karnataka State Highway Improvement Project Submitted by Karnataka State Highways Improvement Project, PIU, Bangalore

Upload: others

Post on 22-Aug-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Environmental Monitoring Report · Engineers & Contractors, Vijayawada. Contract signed in September 2014 3 ROB 3 @km 25.92 2 27A Shelvadi-Mundar gi Gadag - M/s. KNR constructio n

Environmental Monitoring Report

This report has been submitted to ADB by the Project Implementation Unit, Karnataka State Highways Improvement Project, PIU, Bangalore and is made publicly available in accordance with ADB’s public communications policy (2011). It does not necessarily reflect the views of ADB.

This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Project Number: 42513-013 May 2015 Period: April 2014 – December 2014

IND: Karnataka State Highway Improvement Project

Submitted by

Karnataka State Highways Improvement Project, PIU, Bangalore

Page 2: Environmental Monitoring Report · Engineers & Contractors, Vijayawada. Contract signed in September 2014 3 ROB 3 @km 25.92 2 27A Shelvadi-Mundar gi Gadag - M/s. KNR constructio n
Page 3: Environmental Monitoring Report · Engineers & Contractors, Vijayawada. Contract signed in September 2014 3 ROB 3 @km 25.92 2 27A Shelvadi-Mundar gi Gadag - M/s. KNR constructio n

1

Fourth Semi -Annual Environmental Safeguards Implementation Report

of the Karnataka State Highways Improvement Project with financial

Assistance from the Asian Development Bank- Report for the Period

upto Dec-2014 (updated up to April 30th

2015)

Loan ID: 2705 IND

Introduction:

The Karnataka Public Works Department (KPWD) through the Government of

India has received financial assistance from the Asian Development Bank (ADB) for

Capacity Building of Karnataka Road Sector. Under this assistance, the KPWD through

its wing ‘Karnataka State Highways Improvement Project’ (KSHIP) has taken up

upgradation for 615 kms of existing State Highways (SH) in the State of Karnataka. The

Upgradation works include strengthening and widening of the existing State Highways

(SH) from single/intermittent lane to Two Lane Carriage Way with paved/un-paved

Shoulder. The project falls under the categroy ‘B’ as per the ADB Safeguard Policy

Statement 2009 (SPS 2009). Accordingly, Initial Environmental Examination Reports

(IEER) including Environmental Management Plan (EMP) were prepared for each sub-

project road and approval of the ADB has been received. The IEERs & EMPs have been

uploaded in KSHIP web site.

Status of Upgradation Work

The upgradation work is being carried through civil contract service. It is envisaged to

implement the project in Nine Road contracts and Four Rail Over Bridges (ROBs) .All the

nine road packages were awarded in January 2012. The ROBs are awarded in Dec

2013/Sept2014. Three contracts (AEP3, AEP6 and AEP9) were subsequently terminated

in July/Oct 2014 owing to poor progress and fresh tenders invited by splitting into seven

sub- packages (AEP3A &AEP3B, AEP6A & AEP6B and AEP9A, AEP9B & AEP 9C).

Works In the remaining six road contracts works in AEP2 and AEP 4 & AEP8 are almost

complete and in progress in three packages viz AEP1, AEP5 and AEP 7.

Contractors in all four RoBs have been mobilised and work is under progress and in

various stages.

The Road and RoB contracts are being supervised by M/s. SMEC International Pvt

ltd Australia.

Details of Roads and RoBs contrtact are given in the table below.

Page 4: Environmental Monitoring Report · Engineers & Contractors, Vijayawada. Contract signed in September 2014 3 ROB 3 @km 25.92 2 27A Shelvadi-Mundar gi Gadag - M/s. KNR constructio n

2

Table 1 Details of sub project roads and ROBs

Sl.

N

o.

Packa

ge Link ID

Road

Name

District

Covered

Tota

l

Leng

th

Kms

Name of

the

Contractor

Remarks

Roads

1 AEP-1 64C, 64D,

64E

Magadi

NH 48–

Koratag

ere

Ramanaga

ram &

Tumkur

68.2

0

KNR

Constructio

nLtd.

Work in

progress

(60%

complete)

2 AEP-2 64H

Pavagad

a to AP

Border

Tumkur 23.2

1

GVR-

RMN(JV)

Work

completed

(100%)

3 AEP-3 57A,57B,57

C

Gubbi-

Yediyur

(NH-48)

Mandya

Mandya &

Tumkur

108.

62

Being

procured

Contract

awarded to

M/s KMC-

VDB (JV) has

been

terminated

on 24th July

2014.

Now, this

package has

been divided

into two sub

packages 1)

AEP 3A:

(Gubi-Yediyur

NH48-

Kowdley) &

2) AEP 3B:

(Kowdley-

Mandya) &

tenders

invited.

4 AEP-4 T13,T17

Jagaluru

NH-

13About

5 Km

from SH-

19

(KSHIP

Road)

Davanager

e

14.3

8

GVR-

RMN(JV)

Work almost

completed.(1

00%)

5 AEP-5 48A

Padubid

ri-

Karkala

Udupi 27.8

RNS

Infrastructu

re Ltd.

Work in

progress (90

% completed)

Page 5: Environmental Monitoring Report · Engineers & Contractors, Vijayawada. Contract signed in September 2014 3 ROB 3 @km 25.92 2 27A Shelvadi-Mundar gi Gadag - M/s. KNR constructio n

3

6 AEP-6 42A,42B Davange

re-Birur

Davanager

e &

Chickamag

alur

105.

63

Being

procured

Contract

awarded to

M/s Gammon

India Ltd. has

been

terminated

on 17th

July

2014.

Now, this

package has

been divided

into two sub

packages :

1)AEP6A

(Davangere-

Channagiri) &

2)

AEP6B(Chann

agiri-Birur).

Tenders

invited.

7 AEP-7 27A,27B

Shelvadi

-

Mundagi

Dharvad

and Gadag

63.4

4

KNR

Constructio

ns Ltd.

Work in

progress

(77%

complete)

8 AEP-8 31A,31B

Mudgal-

-

Gangaw

athi

Raichur &

Koppal 74.2

KNR

Constructio

ns Ltd.

Work

complete(100

%)

9 AEP-9 21C,21D,21

E,21F

Soundat

ti-

Kamatag

i

Belgaum &

Bagalkot

130.

13

Being

procured

The contract

of Contract

awarded to

M/s. Ramky

Infrastructure

Ltd has been

terminated

on 30th

October

2014.

Now, this

package has

been divided

into three

sub packages

1)AEP 9A :

42.065 kms

(Saundatti-

Page 6: Environmental Monitoring Report · Engineers & Contractors, Vijayawada. Contract signed in September 2014 3 ROB 3 @km 25.92 2 27A Shelvadi-Mundar gi Gadag - M/s. KNR constructio n

4

Ramdurga-

Halgatti JN),

2)AEP 9B: 45

kms (Halgatti

Jn- Badami

bypass JN) &

3)AEP 9C:

43.128Kms

(Badami

bypass JN-

Pattadkallu-

Kamatgi)

Tenders

invited for all

the three sub

packages

Total 615.

61

Rail OVer Bridges

1

ROB 1

@ km

7.+69

5

42A

Davange

re –Birur

Davangere

&

-

M/s. KNR

constructio

n.

Contract

signed in

September

2014 Slow

progress

2

ROB 2

@km

44.85

5

42B Chikmagal

ur -

M/s. K.

Venkataraju

Engineers &

Contractors,

Vijayawada.

Contract

signed in

September

2014

3

ROB 3

@km

25.92

2

27A

Shelvadi

-

Mundar

gi

Gadag -

M/s. KNR

constructio

n.

Contract

signed in

December

2013. Work

in progress

(35%

complete)

4

ROB 4

@

42.21

4

21D

Soundat

ti-

Kamatgi

Bagalkot -

M/s. KNR

constructio

n.

Contract

signed in Sept

2014. Work

not

commenced

Status of EMP Implementation

The KSHIP has obtained requisite prior environmental clearance in Nov.

2008, Oct.2009 and Jan.2011 from State Environmental Impact Assessment

Page 7: Environmental Monitoring Report · Engineers & Contractors, Vijayawada. Contract signed in September 2014 3 ROB 3 @km 25.92 2 27A Shelvadi-Mundar gi Gadag - M/s. KNR constructio n

5

Authority and consent for establishment in july 2008 and Jan 2010 from the

Karnataka State Pollution Control Board for the sub project roads. The

details are given in Annex ure1.

Contractors of Road package and ROB have obtained all requisite permissions from

District Commissioner and KSPCB and Dept of Mines and Geology for quarrying and

establishing Crusher, Hot Mix Batching plant WMM plant Ready Mix Concrete Batching

Plant, DG sets Initially due to ban on crushing operations in the state owing to a writ

pertition case pending in the court of law there was some delay in obtaining these

licenses. However, the matter is settled in the court of law and almost all permissions

are in place. Details of statutory Permissions and licenses for establishing plants and

equipments by these contractors given in Annexure 2

The CSACA consultant has submitted MPR for the month of April 2015. The EMP

implementation Status as reported by the CSC for the ongoing works is given

below.

Table 3: Status of EHS under the contract packages

Activity AEP1 AEP5 AEP7 Remarks

Dust

generation and

control

Regular water

sprinkling through

tankers has been

arranged by the

Contractor to

suppress dust on

diversions

Regular water

sprinkling

through

tankers has

been arranged

by the to

Contractor

suppress dust

on diversions

Regular water

sprinkling

through

tankers has

been arranged

by the

Contractor to

suppress dust

on diversions

Satisfactory

Traffic Safety

during

construction

Moderately

Unsatisfactory.

Contractor

Satisfactory CSC has

reported as

‘Moderately

Not

Satisfactory”

AEP and AEP 7

Contractors

have has been

advised to

enhance

safety

arrangements

at all

construction

sites.

Top Soil

Management

Being laid on

Borrow Area and

embankment

slopes

Not generated Being laid on

Borrow Area

and

embankment

slopes

Satisfactory

Borrow Area Out of 18 nos of Out of 11 Out 61 All the three

Page 8: Environmental Monitoring Report · Engineers & Contractors, Vijayawada. Contract signed in September 2014 3 ROB 3 @km 25.92 2 27A Shelvadi-Mundar gi Gadag - M/s. KNR constructio n

6

Rehabilitation exhausted borrow

areas 2 borrow

areas have been

rehabilitated.

exhausted

borrow areas 4

borrow areas

have been

rehabilitated

exhausted

borrow areas

one is

rehabililtated

contractors

have been

advised to

take up

rehabilitation

works in the

remaining

borrow areas

and hand over

to the owner

Disposal of

scarified

Bitumen

Being carried as

per contract

provision

Being carried

as per contract

provision

Scarified

material is to

be removed

from work

place

Contractor

requested to

produce

request letter

from temple

authority

Environmental

Monitoring for

Ambienrt Air ,

Noise, Water

and Soil quality

Sri Krishna Aqua Engg works Hubli NABL laboratory

has carried environmenal monitoring in March 2014

Contrators

have been

advised to

carry env

monitoring

immediately

Independent

Environmental

Monitoring

M/s Sneha Test House Bangalore having NABL

Laboratory have been engaged by PIU KSHIP from

Nov 2012. The consultants have so far conducted

environmental monitoring for the 1st

and 2nd

year

and 1st

quarter of the 3rd

year (2015) during Dec.2014

Feb 2015.

No significant

pollution is

observed

Construction

Camp

Management

Maintained as per

the EMP

guidelines.

Contractr advised

to refill Fire

Extinguishers

Contractor has

been advised

to clean oil

spill attend to

leakages

Maintained as

per the EMP

guidelines.

Moderately

satisfactory in

AEP1 and

AEP7. Needs

improvement

in AEP5

Base camp Contractor

advised to

improve house

keeping and

sanitation facility

and carry health

checkup for

workers

Contractor

advised to

improve

sanitation and

solid waste

management

And conduct

health

checkups to

workers

Being carried

as per the EMP

guidelins

Moderately

Statisfactory

in AEP7.

Needs

improvement

in AEP 1 and

AEP 5

Page 9: Environmental Monitoring Report · Engineers & Contractors, Vijayawada. Contract signed in September 2014 3 ROB 3 @km 25.92 2 27A Shelvadi-Mundar gi Gadag - M/s. KNR constructio n

7

Salient of EMP Implementation Status of KSHIP during the

reporting period

• Statutory Environmneal Clearnces (EC) have been obtained by KSHIP for

the entire project from the state wing of Ministry of Environent and Forests -

SEIAA and the Consent for Establishment (CFE) from KSPCB. The details are

furnished in Annexure 1.

• Statutory Permits and licenses from District Revenue Administration and

Department of Mines and Geology and KSPCB required for establishing and

operation of Quarry , Crusher, Hot Mix Plant, Wet Mix Macadam plant, Ready

Mix Concrete Plant, DG Set and other plant and machineries have been obtained

by contractors Details are furnished in Annexure 2.

• Tree Cutting for road side trees coming under the widening is almost

completed. Out of 27,490 nos of road-side trees identified in 615 kms of

project roads 24,047 have been cut. About 3394 no. of trees saved by minor

changes in the alignment. Action is initiated to remove balance 49 trees.

Status of Tree cutting is given in Annexure 3.

• Avenue Plantation program has been initiated by KSHIP with the help from

Karnataka Forest Department. Planatation is planned for 270 kms of sub

project roads being implemented under AEP1 , AEP 2, AEP 4, AEP 5, AEP 7

and AEP 8 contracts. In 2014 monsoon 19 kms project road has been

provided with avenue planation. During 2015 monsoon about 200 kms road

length is planned for plantation. Remaining 51 kms will be covered during

May 2016 monsoon. In the reamining 345 kms (615-270) of sub project

roads under AEP 3, AEP 6 and AEP 9 where contracts have been terminated a

separate plantation program will be prepared after new contracts are signed

and mobilsied. Details of avenue plantation program are given in Annexure

4.

• Forest Land is envisaged in four links viz., 21 C, 42B, 57A and 21F for road

widening purpose. In link 21C the acquisition process is over. In the

remaining three links acquistion process is in progress. The details are

furnished in Annexure 5.

Page 10: Environmental Monitoring Report · Engineers & Contractors, Vijayawada. Contract signed in September 2014 3 ROB 3 @km 25.92 2 27A Shelvadi-Mundar gi Gadag - M/s. KNR constructio n

8

• Archeological Survey of India (ASI) permissions are required for two

monunmentas of archoelogical importance in link 42B and link 21E and F.

Permission from ASI Regional office South Bangalore has been obtained for

Musafir Khana/Honda located in 42 B under AEP6. In 21E & 21F permission is

awaited for group of temples under AEP 9 . Details furnished in Annexure 6.

• Solid Noise Barriers have been constructed by KSHIP in all sub project

roads for abatement of noise during construction and operations at

environmentally sensitive locations such as government schools, hospitals

and offices. Under this program out of a total of 248 locations solide noise

barriers have been constructed at 236 locations. Details furnished in

Annexure 7.

• Road Side Water Bodies under Environmental Enhancement programme

has been taken up. Four Water bodies in links 42B, 27D ,31B and 27B have

been taken up for improvement of which work has been completed in three

water bodies (42B,27D,31B). In link 27B improvement work is in progress.

Details furnished in Annexure 8.

• Environment and Safety Engineers have been appointed by the

Contractors. Details furnished in Annexure 9.

• Orientation Training on Environment Health and Safety was conducted

in April 2014 to Contractors’ Personnel. Various topics on EMP were

covered including a special session on procedures involved for obtaining

statutory permissions such as crusher, quarry, HMP, DG set and Wet Mix

Macadam plant and Ready Mix Concerte plant etc Details furnished in

Annexure 10.

• Independent Environmental (Pollution) Monitoring is being carriedd by

PIU for Ambient Air quality, Noise, Water and Soil in the project area.

Monitoring is being done since Jan 2012 for four years on quarterly basis

covering three seasons of the year ie,, winter, premonsson and post

monsoon seasons. Samples are collectd from on site locations such as

viiage/habitations, schools hospitals, government establishment which are

likely to be affected from construction activities and off site locations such as

crusher, quarry, campsite etc. M/s. Sneha Test House Bangalore an NABL Lab

appointed for this assingment have so far completed monitoring of all the

Page 11: Environmental Monitoring Report · Engineers & Contractors, Vijayawada. Contract signed in September 2014 3 ROB 3 @km 25.92 2 27A Shelvadi-Mundar gi Gadag - M/s. KNR constructio n

9

trhee quarters for the 1st (2012) 2nd (2013) and 3rd (2014) years and 1st

quarter of the 4th (2015) year . Resulsts and recommendations of the

consultants are being communicated to CSC and contractors to take remedial

measures. Details are furnished in Annexure 11.

• Borrow Areas are identified in non- agricultural land for embankment fill

and sub-grade construction. The exhausted borrow areas are re-habilitated

as per the requirement of land owners. The details are furnished in

Annexure 12.

• Health check-ups for contractors’ workers were conducted in AEP 6, AEP 7,

AEP 8 and AEP 9 during reporting period.

• Public Consultations were held during March 2015. Status of Public

Consultation is furnnished in Annexure 13.

• Grievance Redressal is being regularly conducted in project roads.

Complaints on dust, safety, contractors’ vehilce speed etc. are referred to

contractors through CSC to ensure redress of the grievance to the satisfaction

of complainant. The details are provided in Annexure 14.

• HIV /AIDS Awareness /Training programs were held in AEP 7 & AEP 8

during reporting period

***

Page 12: Environmental Monitoring Report · Engineers & Contractors, Vijayawada. Contract signed in September 2014 3 ROB 3 @km 25.92 2 27A Shelvadi-Mundar gi Gadag - M/s. KNR constructio n

10

Annexure 1

Statutory Environmental Clearances for the Sub Project Roads as

obtained from KSHIP (project proponent)

Sl.No Statutory Bodey SEIAA Statutory Body KSPCB

Clearance

No. Date

Link

Nos

Package Consent No.

Date

Link

No.

Package

1. No.

SEIAA:

19

IND:2010

dated 29th

Jan 2011

21C

21D

21E

21F

AEP 9 No. PCB 439-

CFE-08-

H.551dated22

July 2008

31A

31B

AEP8

2. 27A

27B

AEP7 57A

57B

57C

AEP3

3. 42A

42B

AEP6 No. PCB 05-

CNP-09-558

H.551dated

29Jan 2010

21C

21D

21E

21F

AEP9

4. 64C

64D

64E

AEP1 27A

27B

AEP7

5. No.

SEIAA: 7

IND:2009

dated 1st

Oct2009

31A

31B

AEP8 42A

42B

AEP6

6. 57A

57B

AEP3 48A AEP5

7. 57C 64C

64D

64E

AEP1

8. - - 64H AEP2

9. - - T13

T17

AEP4

Page 13: Environmental Monitoring Report · Engineers & Contractors, Vijayawada. Contract signed in September 2014 3 ROB 3 @km 25.92 2 27A Shelvadi-Mundar gi Gadag - M/s. KNR constructio n

11

Annexure 2

Statutory Permissions for Establishing Qurry, Stone Crusher, Hot

Mix Plant, Wet Mix Macadam Plant, DG set , Ready Mix Plant and

Other Plants and Machinery by Contractos (for On going Contracts)

Cont

ract

Pack

age

Quarry Crusher

Other equipments

(HMP, WMM,RMC,

DG sets

Location

EC from

SEIAA

for

quarryi

ng

KSPCB

CFE

&CFO Location

DC

License

for

establil

shment

CFE

f&CFO

from

KSPCB

Location

CFE&CF

O from

KSPCB

AEP -

1 Hodekallu Yes

Yes

Hodekall

u

Yes Yes

Bellibetta

halli

Yes

AEP 5

Nandalike

village,

KarkalTq,

Udupi Dist.

Private

Licensed

Being

procured

from

Private

licensed

quarry

Nandalik

e

Yes

Yes Nandalike

Yes

AEP -

7

Papanashi,

Lakkundi

village,

GadagTq

and Dist

Yes

Yes

Papanash

i,

Lakkundi

village

Yes

Yes

Papanashi

, Lakkundi

village

Yes

Page 14: Environmental Monitoring Report · Engineers & Contractors, Vijayawada. Contract signed in September 2014 3 ROB 3 @km 25.92 2 27A Shelvadi-Mundar gi Gadag - M/s. KNR constructio n

12

Annexure 2A

Statutory Permissions for Establishing Stone Crusher, Hot Mix

Plant, Wet Mix Macadam Plant, DG set , Ready Mix Plant and other

plants and Machinery (for all Nine contracts)

Contrac

t

Packag

e

Contractor Items Location

DC license KSPCB CFE KSPCB CFO

Approval

Date

Approval

Date

Approval

Date

AEP - 1

KNR

Construction

s Ltd.

Crusher-

1

Hodekallu

village, Sy .No.

22,

UrdigereHobli,

Tumkur Dist.

09.07.2012 08.11.2013 08.11.2013

HMP Bellibattalahalli

village Sy. No. 29

& 26 in ,

Oordigerehobli,

TumkurTq. &

Dist.

NA 08.11.2013 08.11.2013

WMP NA - -

RMC NA

08.11.2013 08.11.2013

Gasifier NA

DG Set

500

KVA

NA

AEP - 2 GVR-RMN JV

Crusher -

1 Kamadurga

village Sy. No.

343,5.1,6.4,& 6.5

in, PavgadaTq.

Tumkur Dist.

10.07.2012 25.02.2014 28.5.2014 Works

completed

HMP-1 NA 25.02.2014 28.5.2014

WMP - 1 NA - -

DG Set -1 NA - -

AEP - 3 KMC-VDB JV

Crusher-1

Bisinele village,

(Link 57 B, 5+100

RHS ) Sy. No. 55 in

Amruturhobli,

KunigalTq.

Tumkur Dist.

11.07.2012

Not Applied

Not Applied

Contract

termiated.

Crusher -

2

Hangarahalli

village Sy. No.

57/2B, 57/2C, ,

Arakere hobli,

SrirangapatnaTq.

Mandya Dist.

Awaited - -

HMP -1 NA - -

AEP - 4 GVR-RMN JV

Crusher -

1 Mustur village

Sy.

.No.203,205,221

& 227

Chitradurga

Dist.

10.07.2013 25.6.2013 21.3.2014 Works

complete

HMP -1 NA 25.6.2013 21.3.2014

WMP -1 NA 25.6.2013 07.09.2013

RMC - 1 NA 25.6.2013 07.09.2013

DG set -1 NA 25.6.2013 07.09.2013

AEP - 5

RNS

Infrastructur

e Ltd.

Crusher -

1 Nandalike

village Sy. No.

12.1,2,3,4&5 of,

KarkalTq, Udupi

Dist.

04.03.2013 24.08.2013 29.10.2013 Works

nearing

completio

n HMP -1 NA 24.08.2013 29.10.2013

WMP -1 NA 24.08.2013 29.10.2013

RMC - 1 NA 24.08.2013 29.10.2013

DG set -1 NA 24.08.2013 29.10.2013

AEP - 6

Gammon

India Ltd.

Crusher -

1 Kasturiba

village Sy.No. 59,

59. 1,71,

ChannagiriTq.

Chitradurga

03.01.2013 03.10.2013 Contract

terminate

d

HMP -1 NA 03.10.2013

WMP -1 NA 03.10.2013

RMC - 1 NA 03.10.2013

Page 15: Environmental Monitoring Report · Engineers & Contractors, Vijayawada. Contract signed in September 2014 3 ROB 3 @km 25.92 2 27A Shelvadi-Mundar gi Gadag - M/s. KNR constructio n

13

Contrac

t

Packag

e

Contractor Items Location

DC license KSPCB CFE KSPCB CFO

Approval

Date

Approval

Date

Approval

Date

DG set -1

Dist. NA - -

Crusher -

2

Kurki village,

Sy.No. 29-1 P3

(3.3 guntas)

Davangere tq &

Dist

Awaited -

-

AEP - 7

KNR

Construction

s Ltd.

Crusher -

1 Papanashi,

Lakkundi

village Sy.No.

723.7 GadagTq

& Dist.

16.08.2013 10.10.2013 Works

nearing

completio

n HMP -1 NA

-

14.08.2013

WMP -1 NA - -

RMC - 1 NA - -

DG set -1 NA 14.08.2013

AEP - 8

KNR

Construction

s Ltd.

Crusher -

1

Hulihyder

village Sy.No.

113.1 of of

GangawathiTq,

Koppal Dist.

11.03.201

3

21.02.201

3

16.03.201

3

Works

complete

HMP -1 NA 05.01.2013 04.03.2013

WMP -1 NA - -

RMC - 1

at

Thodaki

village

NA 05.10.2012 21.11.2012

RMC - 2

at

Hulihyd

er

village

NA 20.12.201

2

29.01.201

3

DG set -1 NA 05.01.2013 04.03.2013

AEP - 9

Ramky Infra

Structure

Ltd.

Crusher -

1

Batkurki village

, Sy.No. 410

Mudkavi hobli,

Ramdurg Tq.

Belgaum Dist.

28.01.201

4 02.07.2013

Contract

terminate

d

Crusher -

2

Mullur village

Sy. No. 53/1,

55/2, 55/3,

55/4, 55/5, 56

and 57/2 near,

RamdurgTq,

Belgaum Dist.

28.01.2014 - -

Crusher -

3

Kelur village Sy.

No. 197,198 &

199 (near

Tallikere village),

AmmenagadHobli

, HungundTq,

Bagalkot Dist.

17.9.2013 - -

HMP - 1 Halgatti village

Sy. No. 180

Mudkavi hobli

Ramdurga tq

Belgaum Dist

Sy. No. 62.1A+2B

NA 05.06.2012 Awaited

WMP - 1 NA - -

RMC - 1 NA 05.06.2012 Awaited

DG Set - 1 NA - -

Page 16: Environmental Monitoring Report · Engineers & Contractors, Vijayawada. Contract signed in September 2014 3 ROB 3 @km 25.92 2 27A Shelvadi-Mundar gi Gadag - M/s. KNR constructio n

14

Contrac

t

Packag

e

Contractor Items Location

DC license KSPCB CFE KSPCB CFO

Approval

Date

Approval

Date

Approval

Date

in

Kaknur village,

Bagalkot Dist.

Page 17: Environmental Monitoring Report · Engineers & Contractors, Vijayawada. Contract signed in September 2014 3 ROB 3 @km 25.92 2 27A Shelvadi-Mundar gi Gadag - M/s. KNR constructio n

15

Annexure3

Status of Tree cutting under the ADB Project roads

Sl. No Package Link No. Length

in kms

No.of

trees

identifie

d for

cutting

Total

no. of

trees

cut

Balance

No of

Trees

Saved

Remarks

1 AEP-1 64C,64D,64E 68.20 2286 2286 0

-

2 AEP-2 64H 23.21 795 795 0

-

3 AEP-3 57A,57B,57C 108.62 5223 1941 12 3270 Honoura

ble High

Court

stay

vaccated

4 AEP-4 T13,T17 14.38 1057 1057 0

-

5 AEP-5 48A 27.80 2187 2187 0

-

6 AEP-6 42A,42B 105.63 2756 2696 23

37

7 AEP-7 27A,27B 63.44 2415 2415 0

-

8 AEP-8 31A,31B 74.20 3561 3561 0

-

9 AEP-9 21C,21D,21E,

21F

130.13 7210 7112 11

87

Total 615.60 27490 24047 49

3394

Page 18: Environmental Monitoring Report · Engineers & Contractors, Vijayawada. Contract signed in September 2014 3 ROB 3 @km 25.92 2 27A Shelvadi-Mundar gi Gadag - M/s. KNR constructio n

16

Annexure 4

Status of Tree Plantation Program along Project Roads

Sl.

No

Package Length

in kms

Total No.of

Plants

required

@200 per

km

Progress

achieved during

2014 monsoon

Progam for

2015 Monsoon

Program

for 2016

Monsoon

o

Length Numbers Length

Nos Length Nos Length Km

1. AEP-1 68.20 13640 4 800

36.91 7382 27.29

2. AEP-2 23.21 4642 - -

23.21 4642 -

3. AEP-4 14.38 2876 - -

14.38 2876 -

4. AEP-5 27.80 5560 - -

27.80 5560 -

5

AEP-7 63.44 12688 15 3000

23.50 4700 24.94

6. AEP-8 74.20 14840 - -

74.20 14840 -

Sub total 271.23 54,246

19 3,800 200.00 40,000 52.23

7. AEP-3 108.62 21724

To be planned after new contracts are signed

8. AEP-6 105.63

21126

9. AEP-9 130.13

26026

Sub total 344.38 68,876

Note: AEP3, AEP 6 & AEP 9 contracts have been terminated. Fresh tenders invited for these

contract packages.

Page 19: Environmental Monitoring Report · Engineers & Contractors, Vijayawada. Contract signed in September 2014 3 ROB 3 @km 25.92 2 27A Shelvadi-Mundar gi Gadag - M/s. KNR constructio n

17

Annexure 5

Status of Forest Land Diversion

Package

No Link No Name of link Extent (Ha) Status

AEP 9 21C Soundatti-Ramadurga 5.764 Stage-II clearance received

from MOEF.

AEP 9 21F Pattadkal-Kamatagi 4.388 Stage I proposal submitted

to Karnataka Forest

Department (KFD)

AEP 6 42B Channagiri-Berur 1.9832 Stage I proposal submitted

to KFD.

AEP 3 57A Gubbi-Yediyur 0.3633 Stage I cleared by MOEF.

Stage II proposal submitted

to KFD

Page 20: Environmental Monitoring Report · Engineers & Contractors, Vijayawada. Contract signed in September 2014 3 ROB 3 @km 25.92 2 27A Shelvadi-Mundar gi Gadag - M/s. KNR constructio n

18

Annexure 6

Status of Permissions from Archeologica Survey of India (ASI)

Sl.No. Name of

Monument

Road

Link

ID

Status of permission

1. Musafir Khana

and Honda

42A Permission received from ASI Regional Directorate

(Southern Region) Bangaloe vide No.

ASI/254/CA(BC)/2012/96/dtd 13/1/2014.

Conditions of permissions communicated to

Contractor, CSC and EE KSHIP Shimoga for

adherance.

2. Group of

Temples in

Pattadakallu and

Aihole

21E

Field Visit by ASI complete. Case Recomended to

Karnataka South Regional Directorate office

Bangalore for onward submission to National

Monument Authority, New Delhi.

& 21F

Page 21: Environmental Monitoring Report · Engineers & Contractors, Vijayawada. Contract signed in September 2014 3 ROB 3 @km 25.92 2 27A Shelvadi-Mundar gi Gadag - M/s. KNR constructio n

19

Annexure 7

Status of Construction of Solid Noise Barriers under the project

Sl

No. Name of Link

Length in

Km

Pkg

No

Noise barriers

Total # Constructed % complete

1 Magadi-Koratagere 68.20 AEP1 40 40 100

2 Pavagada to AP Border

23.21 AEP-2 6 6 100.00

3 Gubbi-Mandya

108.62

AEP3 57 57 100

4 Jagaluru - NH-13

9.25

AEP-4

3 3 100.00

5 Molkalmur - SH 19 5.13 3 3 100.00

6 Padubidri - Belmane -

Karkala 27.80 AEP-5 10 10 100.00

7 Davanagere-Birur

105.63

AEP6 39 38 9704

8 Shelvadi-Mundargi

63.44

AEP7 26 26 100

9 Mudgal-Tavarekere

74.20

AEP8 27 20 74

10 Saundatti-Kamatgi

130.13

AEP 9 37 33 89.20

Total

615 248 236 95.16

Page 22: Environmental Monitoring Report · Engineers & Contractors, Vijayawada. Contract signed in September 2014 3 ROB 3 @km 25.92 2 27A Shelvadi-Mundar gi Gadag - M/s. KNR constructio n

20

Annexure 8

Status of Improvement of Roadside Water Bodies

Sl.No. Name of Pond Road Link ID Package Progress

1. Bukambudhi Kere 42B AEP6 Complete

2. Tavarekere 31A/B AEP 8 Nearing completion

3. Village Pond near Chimmankatte 21D AEP 9 Complete

4 Village pond at Baradur 42B

AEP 7 Work in progress

Page 23: Environmental Monitoring Report · Engineers & Contractors, Vijayawada. Contract signed in September 2014 3 ROB 3 @km 25.92 2 27A Shelvadi-Mundar gi Gadag - M/s. KNR constructio n

21

Annexure 9

Contractors Environment and Safety Engineers

Contract

Package Contractor

Personnel

available Name

Academic

Qualification

Project

Experience

AEP- 1

KNR

CONSTRUCTION

LTD

Environmental

Engineer

Mrs.

RenuMukunda

Masters in

Sociology, PG

in Public

Participation in

Infrastructure

Development,

Netherlands.

15 Years

Safety Officer Mr. Sajid

Pasha

Diploma in

Safety & Fire

Protection

5 Years

AEP- 5

RNS –

INFRASTRUCTURE

PVT. LTD.

Environmental

Engineer

Ratnakar

Shetty

BE –

(Transportation

Engineering)

19 Years

Safety Officer Raviraj Shetty

B.com, Safety

& Fire

Protection

Course

32 Years

AEP- 7

KNR

CONSTRUCTION

LTD

Environmental

Engineer

Bogeswar Rao Diploma in Civil

Engineering

10 Years

Safety Officer J. Santosh Intermediate

(GTL Safety

course)

5 Years

Page 24: Environmental Monitoring Report · Engineers & Contractors, Vijayawada. Contract signed in September 2014 3 ROB 3 @km 25.92 2 27A Shelvadi-Mundar gi Gadag - M/s. KNR constructio n

22

Annexure 10

Environmental Orientation Training Programme

Workshop and Orientation Training Program

on Environmental Safeguards –

Program No. 1

Contract

Package

Date Venue Timings No. of

Participant

s Class Room Training Field Study

AEP 1 & 3 08.02.2013 Base Camp, AEP 1 11.00 A.M. to 1.00 P.M. 2.00 P.M. to 5.00 P.M. 20

AEP 2 28.02.2013 Base Camp, AEP 2 11.00 A.M. to 1.00 P.M. 2.00 P.M. to 5.00 P.M. 10

AEP 5 30.01.2013 Base Camp, AEP 5 2.00 P.M. to 4.00 P.M. 11.00 A.M. to 1.00 P.M. 25

AEP 4 & 6 27.02.2013 Base Camp, AEP 6 2.00 P.M. to 4.00 P.M. 11.00 A.M. to 1.00 P.M. 20

AEP 7 23.01.2013 Base Camp, AEP 7 11.00 A.M. to 1.00 P.M. 2.00 P.M. to 4.00 P.M. 20

AEP 8 22.01.2013 Base Camp, AEP 8 6.00 PM – 8.00 P.M. 2.00 P.M. to 4.00 P.M. 15

AEP 9 24.01.2013 Base Camp, AEP 9 2.00 P.M. to 4.00 P.M. 4.00 P.M. to 6.00 P.M. 10

Workshop on Procedures for Permissions/licenses required for establishing

crushers, HMP, DG sets, quarry operationse etc. and Orientation Training

Program on Environmental Safeguards – Program No. 2

Contract

Package

Date Venue Timings No. of

Participant

s Class Room Training Field Study

AEP 1, 2 & 3 18.11.2013 Base Camp, AEP 1 11.00 A.M. to 1.00 P.M. 3.00 P.M. to 5.00 P.M. 15

AEP 4 & 6 25.10.2013 Base Camp, AEP 6 11.00 A.M. to 1.00 P.M. 2.00 P.M. to 4.00 P.M. 16

AEP 5 26.10.2013 Base Camp, AEP 5 11.00 A.M. to 1.00 P.M. 2.00 P.M. to 4.00 P.M. 22

AEP 7 24.10.2013 Base Camp, AEP 7 11.00 A.M. to 1.00 P.M. 2.00 P.M. to 4.00 P.M. 17

AEP 8 22.10.2013 Base Camp, AEP 8 6.00 PM – 8.00 P.M. - 18

23.20.2013 - - 9.00 A.M. to 11.00 P.M.

AEP 9 23.10.2013 Base Camp, AEP 9 2.00 P.M. to 4.00 P.M. 4.00 P.M. to 6.00 P.M. 08

Page 25: Environmental Monitoring Report · Engineers & Contractors, Vijayawada. Contract signed in September 2014 3 ROB 3 @km 25.92 2 27A Shelvadi-Mundar gi Gadag - M/s. KNR constructio n

23

Annexure 11

Status of Independent Environmental (Pollution) Monitoring

(Summary Report from Dec 2011- Jan 2015) Name of the

Consultant:

M/s. Sneha Test House Bangalore (NABL

accridited)

Agreement signed: Nov 2011

Start Date:

December 2011

Assignment duration

Four Years ending by Dec 2016

Environmental

Monitoring

Parameters

Ambient Air (PM2.5, PM10, SO2, No2, CO, Benzene

(c6H6), Benzo pyrene (BaP) as per NAAQS

2009.

Ambient Noise L min, L max & Leq dB(A) as per NAAQS in

respect of Noise Rules 2000 as amended in

Jan 2010.

Water Quality Physical, Chemical & Biological (BIS 10500-

2012).

Soil pH (20% suspension) , Organic Carbon, Total

Nitrogen N, Pottassium K, Phosphorous P

Year/

Quarter Period

No of Samples monitored

Nos of samples

which

exceeded limit

Remidial

measures

taken

Air Noise Water Soil

I/Q 1

Jan -

Feb

2013

49 49 18 49

A (5) N(nil)

W(nil) S (nil)

Air: Regular

sprinkling of

water on

diversion

roads ,

Covering

dust

eminating

I/Q 2

Apr -

May

2013

49 49 18 49

A (4) N(6)

W(nil) S(nil)

I/Q 3 Oct -

Dec 49 49 18 50 A(nil) N(nil)

W(nil) S(nil)

Page 26: Environmental Monitoring Report · Engineers & Contractors, Vijayawada. Contract signed in September 2014 3 ROB 3 @km 25.92 2 27A Shelvadi-Mundar gi Gadag - M/s. KNR constructio n

24

2013 locations of

crusher

including

water

sprinkling

arrangement.

Noise: Solid

Noise

Barriers

provided to

schools

hospitals and

public offices

Noise

exceeding

limits .Water:

Contractors

advised to

instal water

purifiers/use

alternate

potable water

for drinking

and cooking.

II/Q 1

Jan -

Feb

2014

49 49 18 49 A (3) N (2) W

(nil) S (nil)

II/Q 2

May -

Jun

2014

49 49 18 48 A(nil) N(nil)

W(nil) S(nil)

II/Q 3

Sept-

Oct

2014

38 38 13 37 A(2) N(2)

W(nil) S(nil)

III/Q 1

Dec

2014-

Jan

2015

39 39 14 37 A() N(4) W(2)

S(0)

III/Q 2 Programmed during May-June 2015

III/Q 3 To be programmed

IV/Q 1 To be programmed

IV/Q 2 To be programmed

IV/Q 3

To be programmed

Legend

A- Air, N-Noise, W-Water, S-Soil

Page 27: Environmental Monitoring Report · Engineers & Contractors, Vijayawada. Contract signed in September 2014 3 ROB 3 @km 25.92 2 27A Shelvadi-Mundar gi Gadag - M/s. KNR constructio n

25

Annexure 12.

Status of Borrow Area Management

Contract

Package

Total No. of

BA

identified

Nos

Exhausted

Nos

Rehabilitated

Balance out

of exhausted

AEP 1 25 18 2 16

AEP 2 16 14 9 5

AEP 3 Contract terminated

AEP 4 10 7 nil 7

AEP 5 14 11 4 7

AEP 6 Contract terminated

AEP 7 44 36 nil 36

AEP 8 65 61 1 60

AEP 9 Contract terminiated

Total

Page 28: Environmental Monitoring Report · Engineers & Contractors, Vijayawada. Contract signed in September 2014 3 ROB 3 @km 25.92 2 27A Shelvadi-Mundar gi Gadag - M/s. KNR constructio n

26

Annexure 13

Public Consultation

Contract

Package

Place Chainage Date Issues Remarks

AEP1 Honnenahalli

68+200 23.03.2015 Road

Safety

Safety

provided as

per the site

requirement Oordigere

68+200 24.03.2015

AEP 5 Padubidri

18+450 30.03.2015

Karkal

27+650 31.03.2015

AEP 7 Papanashi

24+240 27.03.2015

23+380 28.03.2015

AEP 8 Kanakagiri

22+600 25.03.2015 Satisfied

with the

work

Compliment

Herur 36+210 26.03.2015 Safety Safety

provided as

per the site

requirement

Page 29: Environmental Monitoring Report · Engineers & Contractors, Vijayawada. Contract signed in September 2014 3 ROB 3 @km 25.92 2 27A Shelvadi-Mundar gi Gadag - M/s. KNR constructio n

27

Annexure 14

Grievance Redressals

Contract

Package

Place Link

No.

Chainage Date Grievance Redressal

Action taken

by contractor

AEP 8 Kanakagiri 31B 23+100 25.03.2015 Safety at

Kanakagiri

village

Safety

Arrangements

made as per

the site

requirement

Kanakagiri 31B 23+230 26.03.2015 Control

Vehicle

speed

Counselling

done for

drivers

Page 30: Environmental Monitoring Report · Engineers & Contractors, Vijayawada. Contract signed in September 2014 3 ROB 3 @km 25.92 2 27A Shelvadi-Mundar gi Gadag - M/s. KNR constructio n

28

PHOTOS EMP IMPLEMENTATION

Page 31: Environmental Monitoring Report · Engineers & Contractors, Vijayawada. Contract signed in September 2014 3 ROB 3 @km 25.92 2 27A Shelvadi-Mundar gi Gadag - M/s. KNR constructio n

29

SE-1 Site Inspection on 13th and 28th March,

2015

Water Sprinkling Done in Link-64C

Link 64E, AEP1: Borrow Area

Redevelopment Link 64E, AEP1: Public Consultation

Link 64E,AEP 1 , Public Consultation at

ORDIGERE Village Link 64E, AEP1: Base Camp,Housekeeping

has been improved

Page 32: Environmental Monitoring Report · Engineers & Contractors, Vijayawada. Contract signed in September 2014 3 ROB 3 @km 25.92 2 27A Shelvadi-Mundar gi Gadag - M/s. KNR constructio n

30

AEP 5; Link: 48 A Flag Man is monitoring the

traffic flow AEP 5; Link: 48 A: Sign Boards in local

language are provided

AEP 5; Link 48 A Ch: 25+650 Proper PPE has

been provided for labours

AEP 5; Link 48 A Public Consultation has

been done

AEP 5; Link 48 A Diversion Boards and Crash

barrier has been provided

AEP 5; Link 48 A Ch: 27+600: Dust

Suppression carried out

Page 33: Environmental Monitoring Report · Engineers & Contractors, Vijayawada. Contract signed in September 2014 3 ROB 3 @km 25.92 2 27A Shelvadi-Mundar gi Gadag - M/s. KNR constructio n

31

AEP-5 Ch: Water Sprinkling for Dust Suppression

@ working stretch of 25+700 th km AEP5 Ch: 18+450, Safety Sign Board and

barricading has been done

AEP-7, Ch: 9+040 Air pollution monitoring has

been done

AEP-7: Sand buckets are provided to extinguish fire

at new base camp

AEP7; Public Consultation has been done

AEP7; Public Consultation has been done

Page 34: Environmental Monitoring Report · Engineers & Contractors, Vijayawada. Contract signed in September 2014 3 ROB 3 @km 25.92 2 27A Shelvadi-Mundar gi Gadag - M/s. KNR constructio n

32

AEP-7, Ch: 22+960, Dust Suppression carried out

AEP-7, Ch: 9+040 Safety Sign board and Crash

barrier is provided

Object Marker Provided at Road Divider

Barricading tape is provided near DG set

AEP-8 Right Reverse Bend Board Provided at Km.

28+050 in link 31B AEP-8, Crash Barrier Painting Provided at

Km.23+091 in link 31B

Page 35: Environmental Monitoring Report · Engineers & Contractors, Vijayawada. Contract signed in September 2014 3 ROB 3 @km 25.92 2 27A Shelvadi-Mundar gi Gadag - M/s. KNR constructio n

33

AEP-8, Ch 33+614, Public Consultation has been

done

AEP-8, Ch 33+614, Public Consultation has been

done

AEP 8: Rumble Strip Provided at Km. 36+540 in

link 31B AEP 8: Raised Pedestrian Crossing Provided at Km.

36+385 in link 31B