environmental management plan - world bank...46 dong tan 47 thang long 48 nguyen xa 49 an chau 8...

89
1 NORTH POWER CORPORATION POWER NETWORK PROJECT MANAGEMENT BOARD ----------------------------- WB credit VN - 4576 ENVIRONMENTAL MANAGEMENT PLAN Vietnam Rural Energy II Project Additional Financing phase 3- Thai Binh province Hanoi, August 2012 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

Upload: others

Post on 29-Jan-2021

6 views

Category:

Documents


0 download

TRANSCRIPT

  • 1

    NORTH POWER CORPORATION

    POWER NETWORK PROJECT MANAGEMENT BOARD

    -----------------------------

    WB credit VN - 4576

    ENVIRONMENTAL MANAGEMENT PLAN

    Vietnam Rural Energy II Project

    Additional Financing – phase 3- Thai Binh province

    Hanoi, August 2012

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    wb231615Typewritten Text

    wb231615Typewritten TextE2105v37

  • 2

    TABLE OF CONTENTS

    1. INTRODUCTION AND SCOPE OF WORK ............................................................ 5

    1.1. OBJECTIVES OF THE SUBPROJECT .............................................................................. 5

    1.2. NEED FOR SUBPROJECT INVESTMENT ........................................................... 5

    1.3. COMMUNE SELECTION CRITERIA ............................................................................... 5

    2. SUBPROJECT DESCRIPTION ................................................................................. 9

    2.1. SUBPROJECT SCALE ................................................................................................. 9

    2.2. SUBPROJECT SCHEDULE .......................................................................................... 9

    2.3. SOME OF MAIN TECHNICAL SPECIFICATIONS FOR THE SUBPROJECT ....................... 9

    2.4. SOME OF MAIN ACTIVITES FOR CONSTRUCTION AND INSTALLATION ..................... 10

    2.5. BRIEF DESTCRIPTION OF NATURAL AND SOCIAL CONDISTION OF THE

    SUBPROJECT’S PROVINCES ................................................................................... 12

    2.6. INVESTMENT STRUCTURE OF THE SUBPROJECT ...................................................... 13

    3. LEGAL FRAMEWORK FOR SUBPROJECT’S ENVIRONMENTAL IMPACT

    ASSESSMENT ................................................................................................................ 14

    3.1. VIETNAM REGULATIONS AND LAWS ........................................................... 14

    3.2. WORLD BANK SAFEGUARD POLICIES .......................................................... 14

    4. ASSESSMENT OF ENVIRONMENTAL IMPACTS ............................................. 16

    4.1. CLASSIFICATION OF IMPACTS .................................................................................. 16

    4.2. IDENTIFICATION OF POTENTIAL IMPACTS OF THE SUBPROJECT .............................. 17

    5. ENVIRONMENTAL MANAGEMENT PLAN ....................................................... 23

    6 ENVIRONMENTAL MONITORING....................................................................... 27

    7. ARRANGEMENT FOR ENVIROMENTAL MANAGEMENT PLAN

    IMPLEMENTATION .................................................................................................... 29

    7.1 ARRANGEMENT FOR EMP’S IMPLEMENTATION ........................................................ 29

    7.2 REPORTING PROCESS ................................................................................................ 30

    8. COST ESTIMATION FOR IMPLEMENTATION OF EMP................................ 32

    9. PUBLIC CONSULTATION AND DISCLOSURE ................................................. 33

    9.1 PUBLIC CONSULTATION ........................................................................................... 33

    9.2 DISCLOSURE ............................................................................................................. 36

  • 3

    LIST OF TABLE

    Table 1.1. Subproject communes

    Table 2. 1. The investment structure of the Subproject (VND)

    Table 2.2. Subproject implementation schedule

    Table 4.1. The assessment of Subproject's impacts

    Table. 5.1. Mitigation measures applied for the Subproject

    Table 6.1. Monitoring of mitigation measures

    Table 6.2: Monitoring of environmental quality

    Table 7.1. Arrangement for EMP’s implementation

    Table 7.2 The environmental reporting requirement

    Table 8.1. The cost estimation for future trainings

    Table 8.2: Estimated costs for implementation of the EMP (VND)

    APPENDIX

    Appendix 1: List of EIA preparers

    Appendix 2: Subproject's environmental permit

    Appendix 3: Example of public consultation for environment impact assessment record

    Appendix 4: Map of Subproject in Thai Binh

    Appendix 5: Example commune-level data report format

    Appendix 6: Example of site environmental management monitoring report (applied for

    contractor’s report)

    Appendix 7: Example of environmental performance monitoring report

    Appendix 8: Summary of Impacted Assets by Subproject

  • 4

    Abbreviations

    CPC Commune People’s Committee

    CRC Compensation and Resettlement Committee

    D/L Distribution Line

    DMS Detailed Measurement Survey

    DONRE Department of Natural Resources and Environment

    DOC Department of Construction

    DOF Department of Finance

    DOIT Department of Industry and Trade

    DPC District People’s Committee

    DP Displaced Persons

    GOV Government of Vietnam

    HH Household

    IDA International Development Association

    IMA Independent Monitoring Agency

    LURC Land Use Right Certificate

    NPC North Power Company

    PMU Project Management Unit

    PPC Provincial People’s Committee

    PPP Project Provincial Power

    ROW Right-of-Way

    USD US Dollar

    VND Viet Nam Dong

  • 5

    1. INTRODUCTION AND SCOPE OF WORK

    1.1. OBJECTIVES OF THE PROJECT

    The development objectives of the proposed Rural Energy II Project are to assist the

    Government of Vietnam to alleviate poverty in the rural areas by providing basic

    infrastructure service such as electricity and access to general services, for improving living

    conditions and productivity. The Project will assist the Government of Vietnam to implement

    its national objective of providing electricity to about 12 million rural households through:

    - An effective strategy for rural electrification with special focus on provision of energy to the remote mountainous areas;

    - Rehabilitating, upgrading and expanding the rural power system in order to meet the demand for power supply for future socio-economic development;

    - Strengthening reliability and quality of power networks, reduce voltage and electricity losses on the grid, lower rural consumption price, improve businesses efficiency and

    rural power management ability of local power management boards;

    - Refurbishment of the existing rural power network to increase reliability and quality of supply, including reduction of technical and non-technical losses; this Project

    incorporates 65 communes in 8 districts (Thai Binh city, Kien Xuong, Tien Hai, Vu

    Thu, Hung Ha, Thai Thuy, Dong Hung and Quynh Phu) of Thai Binh province.

    - Extension of existing power networks to supply additional households; - Assisting local District and Commune committees to improve power system

    management processes and improve business efficiency, to provide electricity

    reliably, safely and at reasonably cost;

    - Review rural power management models, to establish power management units of legal standing, with economic independence and the managerial/technical skills to

    operate effectively and profitably, repaying loaned funds;

    - Expanding the use of renewable energy for the off-grid systems to serve the rural load in the remote and isolated areas, where feasible and economically practicable;

    1.2. NEED FOR SUBPROJECT INVESTMENT

    Based on the forecast data on economic development, power demand and the current

    situation of the existing power distribution network of the Subproject’s commune. The

    existing distribution network is degraded, not synchronous. Power losses are very high. The

    alignment of power lines were not well designed. Many types of poles are existed in the

    network. There are also many types of electricity meters. In the past in order to save money,

    the distribution lies were created to go across gardens, ponds etc. The conductor was

    overhead type and not covered by any insulating materials, so it causes a lot of risk on safety

    to local people. The Subproject is planned to implement in order to:

    - Improve the quality of the existing distribution network in the Subproject’s communes.

    - Increase the safety management of the distribution network; - Reduce power losses; - Increase electricity supply for the Subproject’s communes; - Change the form for management model of rural power network; - Gradually modernize the distribution power network.

    1.3. COMMUNE SELECTION CRITERIA

    1.3.1. General criteria

  • 6

    To be voluntary participants in the Subproject and understand requirements and regulations of World Bank and the Government of Vietnam to carry out RE II Project;

    To be willing to convert the communes power management model to legal local distribution units to control LV networks;

    To have potential for economic development;

    To have an acceptable capital recovery rate;

    Revenue from power business can cover management, operation and funding costs.

    1.3.2. Criteria for selection of communes for rehabilitation

    Power losses exceeds 20%; aged power networks degraded and require refurbishment;

    Power demand is substantial (over 500 households);

    Power demand for industrial production is substantial (over 20%);

    Number of electrified communes over 80%;

    Average power consumption rate power household in substantial; estimated annually 500 kWh/household.

    1.3.3. Criteria for communes to be connected

    Number of households connected to power network is Provincial communes is below the average (60%);

    Customers are able to pay cost of connection and subsequent power bills;

    Communes have potential for development in agriculture, forestry and handicraft, which would be enhanced if electrified;

    Communes in the poorest communes list;

    Communes in the assistance program of World Bank.

    Communes are ready to adopt the management model of power network.

    Table 1.1: Subproject communes

    Sr.No District/commune

    I THAI BINH City

    1 Vu Phuc

    2 Vu Dong

    3 Dong My

    4 Phu Xuan

    II KIEN XUONG

    5 Vu Le

    6 An Binh

    7 Vu Hoa

    8 Quyet Tien

    9 Vu An

    10 Quang Hung

    III TIEN HAI

    11 Dong Xuyen

    12 An Ninh

    13 Dong Hoang

    14 Dong Trung

  • 7

    Sr.No District/commune

    15 Dong Lam

    16 Tay Son

    IV VU THU

    17 Minh Quang

    18 Hong Phong

    19 Hiep Hoa

    20 Trung An

    21 Dung Nghia

    22 Viet Thuan

    23 Tam Quang

    24 Dong Thanh

    25 Minh Lang

    26 Tu Tan

    V HUNG HA

    27 Minh Tan

    28 Kim Trung

    29 Duyen Hai

    30 Van Cam

    31 Phuc Khanh

    32 Doan Hung

    33 Van Lang

    34 Hung Dung

    35 Hoa Binh

    VI THAI THUY

    36 Thuy Dan

    37 My Loc

    38 Thuy Binh

    39 Thuy Luong

    40 Thai Xuyen

    41 Thai Hong

    42 Thuy Lien

    43 Thuy Dung

    VII ĐONG HUNG

    44 Dong Cac

    45 Dong Quang

    46 Dong Tan

    47 Thang Long

    48 Nguyen Xa

    49 An Chau

  • 8

    Sr.No District/commune

    50 Dong Ha

    51 Dong Hop

    52 Dong Son

    53 Dong Linh

    VIII QUYNH PHU

    54 An Thanh

    55 An Duc

    56 An Dong

    57 An Bai

    58 An Vinh

    59 An Quy

    60 Dong Hai

    61 Quynh Xa

    62 Quynh My

    63 Quynh Hoang

    64 Quynh Trang

    65 Quynh Minh

  • 9

    2. SUBPROJECT DESCRIPTION

    Name of Project: Vietnam rural Energy II project for the Additional Financing

    Location: Thai Binh

    2.1. SUBPROJECT SCALE

    The Subproject is consisted two parts: Low voltage (0.4kV) line and energy meter

    system

    Low voltage part of the Project is consisted of 1,122.531 km low voltage transmission

    line, from which:

    - Rehabilitation line: 433.504km

    - Reusing line: 566.145 km

    - New construction: 122.882km

    Total number of energy meters is 107,788 sets.

    NPC will be the Owner for the Subproject.

    2.2. SUBPROJECT SCHEDULE

    Table 2.2. Subproject implementation schedule

    Investment preparation 2/2011-6/2011

    Construction preparation 07/2011-05/2012

    Bid of procurement equipment 6/2012-8/2012

    Bid of procurement civil works 7/2012-10/2012

    Implementation 11/2012-10/2013

    Completion 12/2013

    2.3. SOME OF MAIN TECHNICAL SPECIFICATIONS FOR THE SUBPROJECT

    Electricity pole

    Concrete poles for most lines are H-section type, cast in workshops.

    For 3 phase lines and branches along inter-District, inter-commune roads: 7.5m, 8.5m pole

    sizes.

    For two wire branches to communes: 6.5m, 7.5m pole sizes.

    For 1 phase lines into household groups: 6.5m pole size.

    A-B-C type poles according to bearing requirements of each position; manufactured to the

    standard DNT-QDKT-44/2006.

    For poles near vehicle transport areas: use 10 m, 12 m centrifugal concrete poles to ensure

    safe clearances.

    For MV, LV line co-sharing positions: use MV line concrete poles.

    Most concrete poles are A and B-type poles, manufactured to standard DNT-QDKT-44/2006.

  • 10

    Square concrete poles and circular concrete poles are used at the following positions:

    Straight, corner positions of 3 phase trunk lines: single poles; and

    Corner anchor, straight anchor, end anchor: double poles.

    If poles are installed near households, trafficable roads, double poles should be used at corner

    anchoring, straight anchoring, end anchoring positions; stayed tension poles are used only at

    such high bearing positions that double poles could not solve and tension poles are

    conveniently placed;

    Utilize existing poles which are of good quality and satisfy the standard when installing new

    conductors.

    Poles under 7.5m size are not used for 3 phase trunk lines.

    Poles recovered from lines are to be returned to localities to allow people to re-use poles to

    support supply lines to houses.

    Pole foundation

    To support line poles, cast in-situ M100 concrete block foundations are used:

    For single poles: use MV1, MV2

    H double poles: use MV3.

    The depth of foundations is in proportion to pole heights and is shown in the overall layout of

    LV pole, cross-arm and foundation.

    2.4. SOME OF MAIN ACTIVITES FOR CONSTRUCTION AND INSTALLATION

    Site clearance

    - Site clearance for Subproject is undertaken by the local Compensation and Site

    Clearance Board based on ROW handover by the Consultant.

    - Compensation and site clearance shall be developed right in the bid process to ensure

    the schedule.

    - Site clearance must duly follow the Decree on safe protection of high voltage power

    grids.

    Transportation

    a, Long distance transportation

    For electric equipment and materials supplied by Investor:

    + Long distance transportation from the delivery place to store of the Investor is

    implemented by specialized vehicle on road. Specialized vehicle is selected suitable to the

    packing of goods specified in contracts.

    + Long distance transportation from the Investors’ store to construction site is

    implemented by 5 7.5-ton vehicle, loading and unloading by 5 ton crane.

    With respect to materials provided by the Contractor:

    + Pole is transported by Kawaz vans, loaded and unloaded by 5 ton crane.

  • 11

    + Structures of cross-arms and beams, auxiliaries are transported by 5 ton van,

    loaded and unloaded by handicraft.

    + Cement, iron and steel are transported by 5 ton vehicle, and loaded and

    unloaded by hand.

    + Stone, sand, rock, etc. are transported by 5-ton dumper truck..

    b, Intermediate Transportation:

    All goods must be stored at site, such as: conductors, insulators, fittings, switchgear

    equipment, capacitors, meters and cement must be laid on site by primitive vehicle in

    combination with handicraft method.

    c, Handicraft transportation:

    - All materials should be laid at site by handicraft. The laying distance of each work

    item and in each locality depends on specific conditions, in general, from 30m to 1000m.

    Construction and Installation work

    a. Soil digging and backfill

    - Digging and backfilling soil for pole foundations and anchors, earthling system by

    handicraft.

    - Constructing foundation hole by tamping at base in combination with layer-by-layer

    tamping.

    - Foundation holes are opened wit slope roof, appropriate to depth and soil kind in

    accordance with regulations to ensure safety.

    b. Making concrete

    - All concrete of foundations and anchors is mixed by 500 liter mixer. Foundation

    concrete could be mixed by hand.

    - Pouring concrete by hand in combination with vibrator and crowbar.

    - Maintaining concrete by watering, in dry and sunny season combined with covering

    sacks to keep moisture.

    c. Pole erection:

    - Erecting round and square concrete poles by handicraft in combination with winch,

    bracket, etc.

    - With respect to the line along roads, it’s possible to use crane at once when pole is

    transport to construction site.

    - Installation of cross-arms, insulators, guy wires is implemented absolutely by

    handicraft after erecting pole.

    - Laying, stringing conductor, taking sag is implemented by handicraft in combination

    with winches. When laying or stringing conductor across other lines, it needs to

    arrange scaffold in accordance with regulation.

    - Installing transformer by 5-ton crane in combination with handicraft when

    transporting transformer to construction site.

    - Installing equipment of substation and meters by handicraft.

    Some machines in work sit

    - 5-ton crane for installing transformer

  • 12

    - 5-ton vehicle for transporting cement, iron and steel

    - 5-ton dumper truck stone, sand, rock

    - 5÷7ton vehicle electric equipment and materials

    - Kawaz vans for transporting pole

    - 5 ton van for transporting cross-arm and beams, auxiliaries

    2.5. BRIEF DESTCRIPTION OF NATURAL AND SOCIAL CONDISTION OF THE

    SUBPROJECT’S PROVINCES

    Geographical position and topography

    Thai Binh locates in the Hong (Red) river delta. The province is close to the northern focus

    economic triangle Hanoi - Hai Phong - Quang Ninh and it is also a commercial exchange gate

    between Hai Phong, Quang Ninh and coastal provinces across the country.

    Covering an area of 1,542.24 km2, Thai Binh makes up 0.5 percent of total area of Vietnam.

    The province borders on the Gulf of Tonkin in the east, Nam Dinh and Ha Nam provinces in

    the west and southwest and Hai Duong, Hung Yen and Hai Phong City in the north.

    The province is surrounded by a close system of seas and rivers with coastal line of more

    than 50 km long, which is an advantageous environment for the development of trade on sea

    and tourism.

    Thai Binh has 1 city and 7 districts divided into 284 communes, wards and towns.

    Climate

    Locating on the edge of the tropical climatic zone, Thai Binh has annual average temperature

    of 23 - 240C, average rainfall of between 1,400 mm and 1,800 mm and humidity of about 85-

    90 percent. From May to the end of October, it is always rainy and hot while the weather

    from November to April next year is dry.

    Land resource

    Thai Binh possesses fertile land. The convenient irrigational system has partly helped build

    up paddy fields yielding 14-15 tons/ha.

    Total natural land across the province is 153,596 ha, of which 94,187 ha is under cultivation.

    Farmers can cultivate 3-4 crops in one year. Soil in Thai Binh is also good for the plantation

    of foodstuff and industrial plants of short life, tropical fruit trees, flowers, etc.

    Possessing three kinds of water, namely salty water (covering 17 km2), brackish water

    (covering about 20,705 ha) and fresh water (covering 9,256 ha), Thai Binh has high potential

    for aquatic products.

    Minerals:

    In Thai Binh exists Tien Hai Gas Mine reaching annual average exploitation output of tens

    millions of cubic meters used to make porcelain products, glass-wear, tile, white cement, etc.

    In 2003, the state-run oil and gas corporation Petro Vietnam exploded offshore in

    preparations for exploitation of gas offshore Gulf of Tonkin.

  • 13

    Tien Hai mineral water mine is at the depth of 450 meters with reserve of about 12 million

    m3. Tien Hai mineral water is highly appreciated by both domestic and foreign consumers.

    Recently, a mine of hot water was discovered in Duyen Hai commune, Hung Ha district at

    the depth of 50 meters (hot water of 570C) and at the depth of 178 meters (hot water of 72

    0C).

    Transport

    The system of roads and waterway in Thai Binh has long established and developed faster

    than the whole country. The province possesses a total of 5,614 km of roads, including 98 km

    of national roads and 312 km of provincial roads. The rest is rural roads.

    Thai Binh has the Diem Dien National Seaport from which 600 tonnage ships can enter and

    depart. In the second stage of the project, the seaport will be expanded and improved

    Electricity

    Thai Binh is among provinces and cites ranking first in the development of electricity system.

    100 percent of communes in Thai Binh is provided with electricity and 98 percent of rural

    households are accessed to electricity. The improved system of electricity in Thai Binh

    province can satisfy demand for electricity in years ahead.

    Agricultural and husbandry: rice cultivation, industrial trees, dry crop, fruits.

    2.6. INVESTMENT STRUCTURE OF THE SUBPROJECT

    Table 2.1: The investment structure of the Subproject (VND)

    Items Amount

    1 Construction cost 102,377,290,822

    2 Equipment cost 3,990,665,539

    3 Compensation cost 165,000,000

    4 Management cost 1,755,548,763

    5 Consultant cost 11,940,611,837

    6 Other cost 1,835,313,934

    7 Contingencies 9,765,154,472

    Total 131,829,585,366

  • 14

    3. LEGAL FRAMEWORK FOR SUBPROJECT’S ENVIRONMENTAL IMPACT

    ASSESSMENT

    3.1. VIETNAM REGULATIONS AND LAWS

    The following laws and regulations are applied for subproject:

    - Law on Protection of the Environment No. 52/2005/QH11 passed by the National

    Assembly, dated 29 November, 2005 regulating the responsibilities of individuals,

    organizations regarding environmental protection.

    - Decree of Vietnamese Government No.80/2006/ND-CP dated 9 August, 2006 on

    detail regulations and guidance on the implementation of some Articles of the

    Environment Protection Law.

    - Decree of Government No.21/2008/ND-CP dated 28 February, 2008 on revision and

    addition of some Articles of Decree 80/2006/ND-CP dated 09 August 2006

    - Decree of Vietnamese Government No.29/2011/ND-CP dated 18 April, 2006

    regarding regulations on strategic environmental assessment, environmental impact

    assessment and environment protection commitments.

    - Circular No.26/2011/TT-BTNMT dated 18 July, 2011 detailing some articles of

    Decree No.29/2011/ND-CP dated 18 April, 2011 regarding regulations on strategic

    environmental assessment, environmental impact assessment and environment

    protection commitments

    - Decree of Government No.106/2005/ND-CP dated 17 August, 2005 on detailed

    regulations and guidance on implementation of some Articles of the Law on

    Electricity related to safe protection of high voltage networks.

    - Decree of Government No.81/2009/ND-CP dated 12 October, 2009 on revision and

    addition of some Articles of Decree 106/2005/ND-CP dated 17th August 2005 on

    detailed regulations and guidance on implementation of some Articles of the Law on

    Electricity related to safe protection of high voltage networks.

    - Circular No.12/2011/TT-BTNMT dated 14 April, 2011 regarding the management of

    hazardous wastes.

    - National Technical Regulations: QCVN05: 2009/BTNMT – Air quality – Standard

    for ambient air quality; QCVN 26:2010 – National technical regulation on noise

    3.2. WORLD BANK SAFEGUARD POLICIES

    - OP/BP 4.01 Environmental Assessment;

    - OP/BP 4.12 Involuntary Resettlement;

    - The World Bank policy on access to information

  • 15

    Detailed guidance on assessment methodologies and common impacts associated with

    transmission subprojects are found in:

    World Bank, 1991. Environmental Assessment Sourcebook, Volume 3.

    IFC, 2007 Environmental, Health, and Safety Guidelines on Electric Power Transmission and Distribution.

    Framework for Applying Environment Safeguards to Rural Energy II Project and Rural Energy II Project extension.

  • 16

    4. ASSESSMENT OF ENVIRONMENTAL IMPACTS

    4.1. CLASSIFICATION OF IMPACTS

    The Environmental Impact Assessment focuses on the major environmental issues of

    the Project’s Most Favoured Alternative. The potential impacts of the Project’s pre-

    construction, construction, and operation phases were assessed as being in one of four

    categories:

    i. NO IMPACT. The potential impact of the Project activity is assessed as NO IMPACT if the project activity is physically removed in space or time from the

    environmental component.

    ii. MAJOR IMPACT. An impact is said to be MAJOR if the project activity has potential to affect an environmental component. Major impacts could be “Major

    Negative” or “Major Positive.” The following criteria were used to determine whether

    a given impact is MAJOR:

    a) Spatial scale of the impact (site, local, regional, or national/ international);

    b) Time horizon of the impact (short, medium, or long term);

    c) Magnitude of the change in the environmental component brought about by the Project activities (small, moderate, large);

    d) Importance to local human populations;

    e) Compliance with national, provincial, or district environmental protection laws, standards, and regulations

    f) Compliance with Vietnam’s international commitments. These include the Convention on Wetlands of International Importance especially as Waterfowl

    Habitat (RAMSAR), the Convention Concerning the Protection of the World

    Cultural and Natural Heritage (World Heritage Convention), and the

    Convention on International Trade in Endangered Species of Wild Fauna and

    Flora (CITES); and

    g) Compliance with World Bank guidelines, policies, and regulations.

    iii. MINOR IMPACT. If an impact occurs but does not meet the criteria for a Major Impact it is assigned the category MINOR. Minor impacts could be “Minor negative”

    or “Minor Positive.”

    iv. MITIGABLE IMPACT. The potential impact of a project activity on an environmental component is said to be MITIGABLE if there is potential for a major

    negative impact and the proposed mitigation measure will prevent the impact or

    reduce the impact to acceptable levels.

  • 17

    4.2. IDENTIFICATION OF POTENTIAL IMPACTS OF THE SUBPROJECT

    The Subproject will play an important role in the electrification program and in

    implementation of the policy of poverty alleviation of 65 communes within 8 districts of Thai

    Binh province. It will also promote the policy of industrialization and modernization of the

    Government of Vietnam as well as create a great opportunity for overall socio-economic

    development of the poor area.

    When the distribution lines are constructed, there is a trend of local people to move to

    live near the lines. The local people committee will have a proper planning accordingly to

    support the development of the areas. These planning are included: road, residential area,

    industrial development and farming etc. The communes/districts will move toward its

    planning.

    Beside the significant beneficial impacts, the Subproject may cause different adverse

    impacts on the environment and local socio-economy. By using Environmental Screening

    Data Checklist and Environmental baseline Checklist as guided in Framework for Applying

    Environment Safeguards to Rural Energy II Project, The potential impacts of the Subproject

    are described in Table 4.1.

  • 18

    Table 4.1: The assessment of Subproject's impacts

    No Impact Location Description of the impacts

    Pre-construction phase

    1 Permanent and temporary land

    acquisition

    Along the

    route, inside

    the ROW

    - 838 m2 Agricultural land will be permanently

    - Average area lost is less than 2m2 per HH, it is not signification for total land holding of

    HHs (about over 1000m2 per HH).

    - 15,626 m2

    of productive land temporarily occupied for LV distribution line.

    - Refer to Appendix 8 for more information and supporting – data;

    - There is no HHs affected more than 10% of their total productive land holding.

    - This impact is not significant in consideration with wide range of the Project: 65

    communes in 7 districts.

    2 Impact on Subproject affected

    household

    HHs have

    land inside

    the ROW

    - 243 HHs will lose their land permanently;

    - Refer to Appendix 8 for supporting data;

    - During designing of the Subproject, the alignment has been carefully considered in order

    to avoid crossing houses and other structures; wrong positioning of poles; minimizing

    temporary and minimizing land acquisition.

    3 Impacts associated with clearing

    the ROW

    Along the

    route and

    inside the

    ROW

    - All of parts of trees that are higher than 4m need to be cut. The trees are still remained.

    - The lines are not going through any forested areas.

    - Acquired lands are mainly un-used land along the existing road, crossing agricultural

    fields with very low ecological values.

    - See Appendix 8 for information on number of trees to be cut. These trees have value in

    economics (fruit trees) rather than environmental.

    4 Health risk due to explosives,

    chemical hazard

    Subproject

    area

    - The area is very intensively used by local government and people. There is no risk of

    explosives;

  • 19

    No Impact Location Description of the impacts

    - No hazardous chemicals are used in the Subproject.

    5 Loss of historical and cultural

    properties

    Subproject

    area

    - The routes are designed to avoid temples, churches and other cultural, historical properties

    in the areas, so the Subproject will not effect any cultural heritages

    - During construction if there is any valuable historical or cultural properties are found

    underground, the Contractor and Subproject owner will report to local Department of

    Culture and information for further consideration.

    Construction phase

    6 Change of surface water quality

    or water flows

    At new

    pole’s

    foundation,

    Worker’s

    camp

    - The water can be more turbid due to the soil residue from excavation of the pole's

    foundation will enter to the water bodies by water run-off.

    7 Noise and vibration Subproject

    area, work

    site

    - Noise levels during construction will be required to comply with Vietnamese standard

    QCVN 26:2010/BTNMT and QCVN 27:2010/BNTMT. Use of construction machinery

    will be limited due to the small scale of the Subproject (distribution as opposed to

    transmission lines), and the very short period of time involved in construction activities.

    - Noise and vibration are caused by: equipment, material transportation, Subproject's

    vehicles, pole's erection and cable's pulling, generators (if there is any)

    8 Excavated Soil New pole’s

    foundation

    - Soil excavation for pole's foundation;

    - Vegetation cover is reduced due to ROW clearance and access roads’ construction.

    - Subproject’s sites are in plain areas or in plain position, so the risk of soil erosion is not

    high.

    - In terms of soil erosion, the impact is considered to be minor due to the small scale of the

    activities involved, the limited period over which they will occur, and the spatially small

    areas to be affected. Furthermore, these impacts could be reduced to less than minor with

    implementation of mitigation measures

  • 20

    No Impact Location Description of the impacts

    9 Dust generation Subproject

    area, work

    site, local

    roads

    - Dust generated from soil excavation, especially during dry seasons.

    - Dust caused by movement of vehicles transporting material and equipment for Subproject

    construction.

    10 Agricultural production due to

    temporary acquisition of

    productive land

    Along the

    route, inside

    the ROW

    - Some of productive land will be required for a short period for construction.

    - Refer to Appendix 8 for supporting data

    11 Traffic disturbance Subproject

    area, local

    roads

    - Transportation of material and equipment, soil excavation and cable pulling activities will

    disturb the normal traffic in the areas during short period of time;

    - Equipment will be transported from receiving port to warehouses of the Subproject

    owners by special trucks;

    - From warehouses to construction the goods are transported by truck 5 to 7.5 tons and

    unloaded by 5 tones cranes;

    - Construction materials will be transported by 10 to 12 tones trucks; unloaded by 5 tones

    cranes;

    - Steel constructions are transported by 5 tones trucks; unloaded by man power;

    - Road system in Thai Binh is quite good so transportation will be very convenient and will

    cause less impact to local traffic;

    - Construction work will be mainly carried out along the rural roads with high gathering of

    poles, construction materials. It will cause disturbance to traffic in rural areas as well. But

    this disturbance in quite minor since the construction duration at each site is short, rural

    transportation is not very intensive and mainly by rudimentary vehicles like bicycles,

    motorbikes, etc.

    - Cable pulling crossing the roads can cause disturbance to transportation also. But

    scaffolds are required in these crossing sections and will reduce the traffic disturbance.

  • 21

    No Impact Location Description of the impacts

    12 Road degradation Local roads - Heavy loaded vehicles might degrade the existing roads, which usually are not very good

    in rural areas.

    13 Biological environment impacts Along the

    route, inside

    the ROW

    - Some of trees will need to be cut. But these trees are common planted species like

    agricultural or fruit trees.

    - Some of insects are small animals will lose their habitat but the insects and animals are

    common species. Area of loose habitats is small in comparison with entire affected

    ecosystem. Main ecosystems that are affected by the Subproject is agricultural, shrub trees

    along the roads etc.

    - The trees that will be cut by the subproject is mainly fruit trees, trees along the roads, they

    have economic value rather than environmental value.

    14 Solid waste generation New pole’s

    foundation,

    work site

    - The soil and construction materials can remain in the site;

    - Contractors need to commit to return the working sites to the original conditions and clean

    up the construction sites.

    15 Environmental impacts caused

    by construction worker

    Subproject

    area,

    worker

    camps

    - Solid waste, wastewater disposal and hygiene condition.

    - Possible dissemination of certain diseases from construction workers to local people and

    vice versa.

    16 Conflict between construction

    worker and local people

    Subproject

    communes

    - The conflicts might cause by difference in incomes, cultures, behaviors;

    - Duration of construction work is very limited (about 6 months); local people will be hired

    for simple work, only skill staff from other locations are hired to do professional work; it

    estimated that the group of 15 persons will be formed for each working team; so all of these

    figures reveals that the risk of conflict is not very high and serious.

    17 Health and Safety Work site,

    Subproject

    area

    - Accidents might happen during construction if the safety issues are not well considered.

    - Electric shock and accidents occurring if the proper safety issues are not paid proper

    attention.

    Operation phase

  • 22

    No Impact Location Description of the impacts

    18 Development and poverty

    alleviation

    Subproject

    area

    - Increase the quality of life for local peoples.

    - Support agricultural production and other services including health and education

    19 Habitat fragmentation and

    increase access to wild lands

    Subproject

    area

    - No new road or access roads are constructed

    - No line crossing the forest, wetland or other natural habitats.

    20 Health and safety Subproject

    area

    - Electric shock and accidents occurring if the proper safety issues are not paid proper

    attention

    21 EMF Subproject

    area

    - With voltage just up to 35 kV, the EMF is not a problem.

    22 Impacts on aircrafts Subproject

    area

    - The height of pole is less than 50 m. There will not be any problem with avian and

    aircrafts

    23 Oil hazardous waste

    contamination

    Subproject

    area

    - The Subproject has the potential to cause oil contamination from leakage from

    transformers. The transformers used are small, with a 20 liter or less capacity. Operation

    records for similar transformers show that the chance of container breakage that could

    cause an oil spill is almost zero. Therefore, a risk of oil contamination caused by the

    Subproject from either of these two sources is extremely low, if not negligible.

    - No PCBs containing oil and other hazardous chemicals will be used.

    - Oil refilling should be done in workshop

  • 23

    5. ENVIRONMENTAL MANAGEMENT PLAN

    Table 5.1: Mitigation measures applied for the Subproject

    No Environmental and social

    impacts

    Mitigation measures

    Pre-construction phase

    1 Permanent and temporary land

    acquisition

    - Careful site survey, consult with local peoples for optimum route selection.

    - Avoid ecologically high value areas (forest, reserve area, wetland etc.).

    - Proper compensate the impacts.

    2 Impact on subproject affected

    household

    - Routes should be selected to minimize the need to relocate houses

    - Increase the span between towers, increase the tower height, use hanging substation etc. to minimize the

    impacts on Subproject affected households.

    - Compensate for the impacts.

    3 Impacts associated with clearing

    the ROW

    - Work with Subproject affected households during clearance of ROWs to minimize impacts to

    surrounding trees and other constructions;

    - Not allow using any herbicides and defoliant to clear the trees within ROWs.

    - Not allow burning the wooden residue after tree cutting.

    4 Health risk due to explosives,

    chemical hazard

    - Not necessary to apply any mitigation measure

    Construction phase

    5 Surface water contamination - Soil excavation is managed to carry out in the shortest period.

    - Construction material will be kept in the store with cover to protect from rain.

    - Select a right place for concrete mixing.

    - Residue from earthwork should be removed from the site to proper places (soil residue can use for

    garden filling; concrete residues are removed by contractor to the permitted places).

  • 24

    No Environmental and social

    impacts

    Mitigation measures

    6 Noise and vibration - Use the construction machines that have noise level under permitted limits.

    - Carefully consider night work. No night work is permitted to carry out in populated and sensitive areas

    like hospital, residential, student camp.

    7 Soil erosion - Excavate and earth-moving activities in erosion prone areas will be schedule in the dry seasons, after the

    harvest time and during the shortest duration of time.

    - Land surface recovery after the pole erection.

    8 Air pollution - Minimize the construction time in each site. Spray water regularly on dirt piles and any other areas that

    could create dust

    - Use wind fences in case of strong wind.

    - Minimize use of diesel generators.

    9 Agricultural production due to

    temporary acquisition of

    productive land

    - Carry out the construction work after harvest time.

    - Compensate for the loss of agricultural productivity

    - Return the construction areas to the useful state after the work.

    10 Traffic disturbance - Minimize the construction work (excavation, cable pulling) in traffic intensive sites.

    - Use warning signs in construction sites.

    - Cooperate with local authority for traffic arrangement.

    - Avoid high-traffic areas

    11 Damaging the existing road

    system

    - Construction Contractor needs to commit to not use heavy vehicles that might cause damage to the

    existing road system in the area.

    - Not allow vehicles with heavy load of construction material and equipment to enter the road system. The

    load should be separated to acceptable levels that the road can resist for.

    - Repair the road when there is any damage occurred.

  • 25

    No Environmental and social

    impacts

    Mitigation measures

    12 Solid waste generated from soil

    excavation

    - Construction contractor need to commit to clean the site and disposal solid waste in the permitted places.

    - Reuse as much as possible an excavated soil for refilling foundation.

    13 Environmental impacts caused by

    construction worker

    - Minimize the impact of solid waste: Solid waste should be disposed properly by local collecting system

    or dumping in permitted areas of communes.

    - Arrange hygiene toilets for workers;

    - Provide clean water for camping areas. Control discharge of waste water from camping sites. Not allow

    discharge waste water directly to clean water sources such as rivers, stream, which is supplying water for

    residential areas.

    14 Conflict between construction

    worker and local people

    - Hire as much as possible local citizens for the simple construction work to avoid the influx of migrants.

    - In cases where the worker camps are near the communes, the Employer could request that the Contractor

    provide accurate, timely and regular information about the construction team to the People’s Committees

    in affected areas. With open communication and information, the People’s Committee and Contractor will

    be able to make a joint informed decision about the management of construction team accommodation.

    - Rectify the impact: The general conditions of Contract should state: after the Subproject finished, all

    camps will be completed removed and the campsites will be rectified to their original conditions.

    15 Health and Safety - Organize the health care service in each group of workers.

    - Inform workers the safety regulations and procedures, do not hire any local people who are not trained

    in working safety

    - Equip safety facilities for the workers, prohibit unauthorized persons entering construction sites,

    especially dangerous areas.

    Operation phase

    16 Development and poverty

    alleviation

    - Not necessary to apply any mitigation measure

    17 Health and safety - Disseminate the information on electricity safety regulations to the users.

  • 26

    No Environmental and social

    impacts

    Mitigation measures

    - Follow the regulation of Government on network protection.

    - Regular training for local technicians and people on safety issues.

    - Not allow burning the woody residues after ROW clearing.

    19 Reduction of air pollutants

    generated by diesel generators

    - Not necessary to apply any mitigation measure

    20 EMF - Not necessary to apply any mitigation measure

    21 Impacts on avian and aircrafts - Not necessary to apply any mitigation measure

    22 Oil hazardous waste contamination - Oil refilling of transformers should be done in the Workshop.

    - No PCBs will be used.

    Table 5.2: The Measures applied for managing the social impacts

    TT Contents Measures

    1

    Information and media programs

    This program must be informed to local authorities and local people at the time subproject started through

    the public consultation meeting or the public media During construction phase, information of subproject,

    Contractor, construction plan and hot line to resolve all complains of environment and social will be

    published at the work site or commune office

    2 Compensation and complain

    policies.

    Compensation and complain policies will be implemented under WB’s policy and Regulation of Viet

    Nam

    Pls. see RP report for detail

    3 Monitoring and evaluation system

    The implementation of EMP and RP will be monitored and evaluated day to day by NPC and local

    authorities. Inside, an agency of independent monitoring will be hire to external monitoring during the

    implementation of EMP and RP.

  • 27

    6. ENVIRONMENTAL MONITORING

    Table 6.1: Monitoring of mitigation measures

    Issues Location Methods

    Construction phase

    1. Dust generation mitigation Work site, material dump site, material transportation Observing

    2. Air pollution mitigation Transportation and construction machine at work site such as

    machine of mixing cement ...

    Observing

    3. Noise mitigation Work site, local roads through residential and/or sensitive

    areas

    Observing and Consultation with

    local residents

    4. Wastewater mitigation Work site, worker camp Observing

    5. Erosion and sedimentation mitigation Work site, material warehouse, worker camp and river,

    stream, lake near the work site

    Observing

    6. Managing material warehouses and

    borrow areas

    Contractor warehouse, pole’s foundation Observing

    7. Solid wastes and hazardous wastes

    mitigation

    ROW, Worker camp, work site, construction machine Observing

    8. Vegetation clearance mitigation Along the route inside the ROW Observing

    9. Traffic congestion mitigation Rural roads in the subproject area Observing, consulting the local

    residents

    10. Disruption of regular activities and

    services

    Residential areas Consulting the local Authorities and

    residents

  • 28

    11. Restoration of the affected areas Waste disposal areas, worker camp, warehouse, work site,

    rural roads and borrow pits

    Observing and Consulting the local

    Authorities and residents

    12. Labor and public safety Work sites Observing, Consulting the worker,

    base on provisions of Vietnam’s

    labor safety.

    13. Information and communication Subproject communes Consulting the local Authorities and

    residents

    14. Chance finds Work site Observing

    Operation phase

    1. Health and safety with operation workers

    and local resident

    Subproject area Consulting the worker and local

    residents

    2. Risk of incidents, fire Subproject area Consulting the worker and local

    residents

    Table 6.2: Monitoring of environmental quality (if necessary)

    Determination Parameter Location Methods The timing/frequency

    1. Ambient Air quality

    - PM10, CO, SO2, and NOx Construction sites and

    transportation routes near

    residential areas (to be

    determined)

    Use of specialized

    equipment

    During construction phase

    when it is large wind

    2. Noise Leq (dBA) Residential areas near construction sites (to be

    determined)

    Use of sonometer Complaints by local

    residents during

    construction phase

  • 29

    7. ARRANGEMENT FOR ENVIROMENTAL MANAGEMENT PLAN

    IMPLEMENTATION

    7.1 ARRANGEMENT FOR EMP’S IMPLEMENTATION

    The responsibilities for implementing Environmental Management Plan as following:

    Table 7.1: Arrangement for EMP’s implementation

    UNIT RESPONSIBILITIES

    Subproject Owner (NPC

    through PMU)

    Ultimately responsible for overall subproject management,

    including environmental management.

    Coordination and management of overall subproject

    implementation,

    Preparing, guiding and supervising implementation of the EMP.

    Responsible for operation of the Subproject including operation

    stage environmental management and monitoring activities.

    Resolving grievances from affected communities

    Civil Works Contractor Responsible for compliance and implementing of mitigation

    measures in the EMP. This includes:

    + Applying mitigation measures for potential negative impacts

    as described in the EMP

    + To actively communicate with local resident and to

    prevent disturbances for social and environment during the

    construction phase.

    + Reporting on problems and solutions to the PMU.

    + Reporting to local government and the PMU if the

    environmental accidents occur and coordinate with

    other agencies and parties to resolve.

    Offering changes of the mitigation measures when they are

    unsuitable to the subproject

    Local Authority Review, appraise and approve the EMP for this subproject

    Supervise compliance with environmental protection measures

    as indicated in the EMP report

    Receive grievances related to the subproject implementation

    from local communities and work with the subproject owner to

    resolve these grievances

    Affected Community Monitor compliance with mitigation measures conducted by

    civil contractors

  • 30

    UNIT RESPONSIBILITIES

    Provide information about environmental and social issues

    related to the subproject implementation that need to be further

    addressed for PMU

    Feedback to local authorities/Subproject owner about EMP

    report and non-complying mitigation measures by Contractors

    7.2 REPORTING PROCESS

    Reporting responsibilities and frequency for the EMP implementation described in the table

    below:

    Table 7.2: The environmental reporting requirement

    No. Item Reported by Submitted to Frequency

    1 Implementation of

    mitigation measures

    and site

    environmental

    management

    Contractors NPC’s PMU Once before starting

    construction and then

    once a month.

    2 Monitoring of

    implementing

    mitigation measures

    and environmental

    management

    NPC’s PMU NPC’s and

    WB

    Every six months

    7.3 Capacity development and training

    The following training has been conducted to date:

    1) May 2002: Training Workshop on preparation of EIA reports for power transmission and

    distribution projects

    2) August 2003: Hands-on learning-by doing training for improving environmental reports.

    3) September 2003: Hands-on workshop for environmental assessment of transmission and

    distribution projects.

    4) May 2004: Training on preparation of EMP according to newly environmental templates

    developed by WB experts.

    5) November 2004: Launch workshop for RE 2 projects. One important section of the

    workshop is implementation of EMP for Rural Energy projects.

  • 31

    6) July 2005: Training on social assessment and resettlement issue in transmission and

    distribution projects under the WB loans.

    Future training includes the following:

    1) Workshop on sharing experience of EMP implementation for PMU staffs and contractors.

    This training is planned to carry out before implementing construction by NPC’s PMU.

    2) Training on Monitoring EMP implementation for project commune authorities and

    Affected Community according to WB requirement by NPC’s PMU before implementing

    construction.

    3) Annual regular training of NPC’s PMU on safety issue for staff

    4) Annual regular information dissemination for local people on electricity safety by local

    Power.

  • 32

    8. COST ESTIMATION FOR IMPLEMENTATION OF EMP

    Table 8.1: The cost estimation for future trainings

    No Training Cost (VND)

    1 Workshop on sharing

    experience of EMP

    implementation for PMU

    staffs and contractors

    18 persons x 1 day x 1,000,000 VND/person =

    18,000,000 VND

    (including 5 PMU staffs and about 13 staffs of

    Contractors)

    2 Training on Monitoring EMP

    implementation for subproject

    commune authorities and

    affected communities

    1 persons/commune x 1 day x 500,000 VND/person x 65

    communes = 32,500,000 VND

    TOTAL 50,500,000 VND

    Table 8.2: Estimated costs for implementation of the EMP (VND)

    No Item Amount

    1 Mitigation measures Included in construction cost

    2 Monitoring costs Included in construction cost

    3 Training costs 50,500,000

    TOTAL 50,500,000

  • 33

    9. PUBLIC CONSULTATION AND DISCLOSURE

    9.1 PUBLIC CONSULTATION

    9.1.1 Consultation Measure and information consultation

    During preparation stage of the Subproject from earlier September 2009, 65 meetings

    with local authorities and local residents at 65 subproject communes were carried out in order to

    consult public on subproject and EMP.

    The contents of the meetings include:

    - General information about Subproject: Name, Subproject owner, scale of Subproject, Subproject districts and communes;

    - Potential environmental impacts that may cause by the Subproject; - Mitigation measures that will be applied in order to minimize environmental impact; - Time schedule for Subproject implementation. - Contact address for receiving of public comments on environmental concerns of the

    Subproject.

    9.1.2 Time and Place of the meetings

    No

    Name of

    Commune and

    District

    Place Timing

    THAI BINH

    1 Vu Phuc Office of Commune People Committee 03/9/2009

    2 Vu Dong Office of Commune People Committee 03/9/2009

    3 Dong My Office of Commune People Committee 04/9/2009

    4 Phu Xuan Office of Commune People Committee 04/9/2009

    KIEN

    XUONG

    5 Vu Le Office of Commune People Committee 07/9/2009

    6 An Binh Office of Commune People Committee 07/9/2009

    7 Vu Hoa Office of Commune People Committee 07/9/2009

    8 Quyet Tien Office of Commune People Committee 14/9/2009

    9 Vu An Office of Commune People Committee 14/9/2009

    10 Quang Hung Office of Commune People Committee 14/9/2009

    TIEN HAI

    11 Dong Xuyen Office of Commune People Committee 25/9/2009

    12 An Ninh Office of Commune People Committee 24/9/2009

    13 Dong Hoang Office of Commune People Committee 25/9/2009

    14 Dong Trung Office of Commune People Committee 27/9/2009

    15 Dong Lam Office of Commune People Committee 25/9/2009

    16 Tay Son Office of Commune People Committee

    VU THU

    17 Minh Quang Office of Commune People Committee 10/9/2009

  • 34

    No

    Name of

    Commune and

    District

    Place Timing

    18 Hong Phong Office of Commune People Committee 10/9/2009

    19 Hiep Hoa Office of Commune People Committee 10/9/2009

    20 Trung An Office of Commune People Committee 11/9/2009

    21 Dung Nghia Office of Commune People Committee 13/9/2009

    22 Viet Thuan Office of Commune People Committee 13/9/2009

    23 Tam Quang Office of Commune People Committee 12/9/2009

    24 Dong Thanh Office of Commune People Committee 10/9/2009

    25 Minh Lang Office of Commune People Committee 11/9/2009

    26 Tu Tan Office of Commune People Committee 11/9/2009

    HUNG HA

    27 Minh Tan Office of Commune People Committee 17/9/2009

    28 Kim Trung Office of Commune People Committee 19/9/2009

    29 Duyen Hai Office of Commune People Committee 17/9/2009

    30 Van Cam Office of Commune People Committee 17/9/2009

    31 Phuc Khanh Office of Commune People Committee 19/9/2009

    32 Doan Hung Office of Commune People Committee 17/9/2009

    33 Van Lang Office of Commune People Committee 19/9/2009

    34 Hung Dung Office of Commune People Committee 18/9/2009

    35 Hoa Binh Office of Commune People Committee 18/9/2009

    THAI THUY

    36 Thuy Dan Office of Commune People Committee 20/9/2009

    37 My Loc Office of Commune People Committee 21/9/2009

    38 Thuy Binh Office of Commune People Committee 20/9/2009

    39 Thuy Luong Office of Commune People Committee 21/9/2009

    40 Thai Xuyen Office of Commune People Committee 22/9/2009

    41 Thai Hong Office of Commune People Committee 20/9/2009

    42 Thuy Lien Office of Commune People Committee 21/9/2009

    43 Thuy Dung Office of Commune People Committee 22/9/2009

    44 ĐONG HUNG

    45 Dong Cac Office of Commune People Committee 21/9/2009

    46 Dong Quang Office of Commune People Committee 22/9/2009

    47 Dong Tan Office of Commune People Committee 20/9/2009

    48 Thang Long Office of Commune People Committee 22/9/2009

    49 Nguyen Xa Office of Commune People Committee 21/9/2009

    50 An Chau Office of Commune People Committee 21/9/2009

    51 Dong Ha Office of Commune People Committee 20/9/2009

    52 Dong Hop Office of Commune People Committee 22/9/2009

    53 Dong Son Office of Commune People Committee 22/9/2009

    Dong Linh

    54 QUYNH PHU Office of Commune People Committee 25/9/2009

  • 35

    No

    Name of

    Commune and

    District

    Place Timing

    55 An Thanh Office of Commune People Committee 27/9/2009

    56 An Duc Office of Commune People Committee 25/9/2009

    57 An Dong Office of Commune People Committee 27/9/2009

    58 An Bai Office of Commune People Committee 28/9/2009

    59 An Vinh Office of Commune People Committee 28/9/2009

    60 An Quy Office of Commune People Committee 25/9/2009

    61 Dong Hai Office of Commune People Committee 26/9/2009

    62 Quynh Xa Office of Commune People Committee 29/9/2009

    63 Quynh My Office of Commune People Committee 28/9/2009

    64 Quynh Hoang Office of Commune People Committee 25/9/2009

    65 Quynh Trang Office of Commune People Committee 27/9/2009

    9.1.3 Participants

    The Participants of the meetings include representatives of the Commune People Committee,

    Farmer Association, Women Association , and other public organizations, hamlet chiefs,

    representatives of Subproject’s affected households, and consulting agency

    9.1.4 Comments from the Participants

    All of the concerns, comments of local people were recorded and considered by

    consultants and subproject's owner during designing of the subproject and development of EMP

    for the subproject.

    Main comments received from participants are summarized as bellows:

    - Local authorities and local people are willing to implement the subproject;

    - Construction work should carry out in dry season, after harvesting;

    - Contractor should clean and return construction sites to the previous condition;

    - Consultant should inform local about construction work as soon as they can so people can have a plan to harvest agricultural products in their affected lands.

    - Warning sign for power pole system should be hang on

    - Consultants should carefully consider the pole’s position; avoid erecting the pole inside garden, near houses, or residential areas.

    - Head and responsible people of the villages should convince people to release the land on time for Contractor;

    - Compensation should be done equally and clearly

    - There is a need to support households that are heavily affected by the Subproject - Construction work should be planned to carry out in the shortest time to avoid losses in

    agricultural production.

    9.1.5 PMU’s Feedback

  • 36

    The environmental impact of subproject is not serious due to the nature of the impact is small

    and the scope is reasonable

    The mitigation measures will be presented in the EMP as part of this report. The mitigation

    measures will be incorporated in the tender documents that the contractor must comply and the

    contractor shall submit an organizational chart of the construction site, construction methods and

    mitigation measures for investors to approve the bidding results

    The construction contractors will have to report the organizational chart of construction site,

    make the temporary residence statement for workers and coordinate with local government to

    administer these workers

    The Subproject team will complete all procedures for preparing the Subproject investment and

    require the investor to arrange capital for the subproject

    9.2 DISCLOSURE

    The Vietnamese copies of EMP report, RP and the subproject summary will be sent to the local

    authorities (district level and commune level) for disclosure at the subproject area. The expected

    time will be in the end of July, 2012

    The English and Vietnamese copies of EMP report will also be sent to the World Bank for

    disclosure in the VDIC and InfoShop. The time for disclosure is estimated in July, 2012.

  • 37

    REFERENCES

    1 Draft of Resettlement Action Plan of the Project, 2009

    2 Environmental Status Report of Thai Binh province in 2008 - DoNRE

    3 World Bank Environmental Assessment Source Book

    4 Statistical Yearbook 2008 – Statistical Publisher

    5 Sourcebook of Protected Areas in Viet Nam – Bird Life International

    6 Subproject's feasibility study

    7 Framework for Applying Environment Safeguards to Rural Energy II Project- WB 2003.

  • 38

    APPENDIX 1

    --------------------

    LIST OF EIA PREPARERS

    1 Mai Xuan Thanh Director

    2 Le Duc Thien Staff

    3 Dang Minh Tuan Staff

    4 Hoong Van Hieu Staff

    5 Nguyen Tai Trung Staff

  • 39

  • 40

    APPENDIX 1: Sample Reports

    Appendix 1.1. Sample data collected from communal authority

    -----------------------------------------------------------------------------------------------------------

    SAMPLE DATA COLLECTED FROM COMMUNAL REPORT

    Name of Project Commune:

    Evaluation phase:

    Environmental impacts:

    Impacts/ Mitigation Measures Acknowledgement of

    the local authority

    Acknowledgement of

    the community

    Vehicles and project activities cause

    dust in the area

    Vehicles and project activities cause

    noise in the area

    Project activities cause river and lake

    water pollution in the area

    Cutting trees of the project affects

    environment

    Project activities cause impacts on

    agricultural and residential land

    Project activities cause impacts on

    cultural and historical relics

    The Project’s construction site affects

    local traffic

    Solid or liquid waste is discharged into

    environment

    The Project’s workers lay impacts on

    socio-economic and health aspect in the

    area

    Accidents

    Dust mitigation measures

  • 41

    Impacts/ Mitigation Measures Acknowledgement of

    the local authority

    Acknowledgement of

    the community

    Erosion and sediment mitigation

    measures

    Construction material collection place,

    etc, to avoid consequences due to

    waterlog or chemical pollution, etc

    Waste management measures

    Project activities affect birds, animals or

    rare plants

    Trucks transporting raw materials

    damage road system

    Others

    Recommendations

    Construction activities near the hospital must be limited with working hours from 07:00 to 11:00 in the morning and from 14:00- 17:00 in the afternoon. The period from 11:00 to 14:00

    is the tea break of officials and patients to be kept quiet.

    More attention should be made when clearing construction camps

    The Contractor must ensure to store columns and construction waste at required places

    It is required to fully provide the safety equipment and training programs to workers to minimize labor accidents, etc, especially for local workers because they neglect about labor

    safety.

    Signature of representatives of community supervision board:

    Title:

    Date:

    ---------------------------------------------------------------------------------------------------

  • 42

    Appendix 1.2. Sample Report on Site Environmental Management Observation

    (Applied for Contractor)

    Project Title: Project site:

    Contractor's name:

    Project commencement report or monthly report:

    Date of Report:

    No. Impacts Implemented

    mitigation measures Remarks

    Construction phase

    1 Water surface pollution

    2 Noise and vibration

    3 Soil erosion

    4 Air pollution

    5 Impacts on agricultural production due to

    temporary occupancy of production land

    6 Impacts on traffic

    7 Damages on local road system

    8 Solid waste from excavation

    9 Impacts on environment caused by construction

    workers

    10 Conflict between construction workers and local

    people

    11 Labor health and safety

    Prepared by:

    Title:

    Address: Telephone:

  • 43

    Appendix 1.3. Sample Report on Site Environmental Observation Parameters

    (This Form is applied for Environmental Observation Report of the Construction

    Supervision Consultant)

    Project Title:

    Project site:

    Province:

    District:

    Commune:

    Type of Report:

    Monthly report (Yes/No):

    Quarterly report submitted to EVN (Yes/No):

    Quarterly report submitted to WB (Yes/No):

    Report by independent consultant (Yes/No):

    Date of Report:

    No. Parameters

    Evaluation on

    feedback of

    supervisor and

    community

    Remarks/

    Recommendations

    During construction:

    1 Water impurity and erosion phenomenon

    2 Noise surrounding site and neighboring

    residential areas

    3 Dust

    4 Management and control of cutting trees down

    and temporary road for construction

    5 Solid waste and sanitation clearance after

    construction

    6 Sanitation and labor safety equipment for

    workers

    7 Impacts on traffic

    8 Road damages

    9 Situation of implementing labor safety

  • 44

    No. Parameters

    Evaluation on

    feedback of

    supervisor and

    community

    Remarks/

    Recommendations

    protection measures

    10 Construction materials management

    11 Impacts on wild animas and natural resources

    12 Bio-diversification loosing signs (if any)

    13 Signs of encroaching cultural and historical

    relics

    14 Others environmental issues (if any)

    During operation:

    15 ROW protection

    16 Impacts on wild animas and natural resources

  • 45

    Appendix 1.4. Sample Report on Site Environment Management Plan

    Construction Contractor

    The Construction Contractor shall submit a monthly report on progress of

    implementing the Site Environmental Management Plan to the Power Company in project

    provinces. This Site Environment Management Plan Report must contain contents as follows:

    Cover page

    Table of Contents

    Introduction

    - A paragraph introduces about purposes of the Report

    Updates of changes in preferences against the Final Report

    - List preference issues of the Final Report

    - List progress of settling each issue implemented by the Contractor

    - List all unsolved issues and give out recommendations for such issues. If such issues

    are not solved, reasons should be specified.

    Results of environmental management activities in reporting phase

    - Report mitigation measures in Site Environmental Management Plan (SEMP).

    - Are set objectives satisfied by these mitigation measures? If not, why? Explanations

    should be clear and complete.

    Implemented by: Title:

    Appendix 1. 5. Procedures on supervision report submission

    No. Issues to be

    reported

    The first reporting

    level

    The second

    reporting level

    The third reporting

    level (Some copies

    submitted to

    Department of

    Natural Resources

    and Environment)

    Construction

    phase

    1 Implementing

    mitigation

    measures and site

    environment

    management plan

    By: Contractor

    Frequency: Monthly

    Submitted to:

    PMUs

    By: PMU

    Frequency: Semi-

    annual

    Submitted to:

    Provincial

    People’s

    By: Provincial

    People’s Committees

    Frequency: Semi-

    annual

    Submitted to: WB

  • 46

    No. Issues to be

    reported

    The first reporting

    level

    The second

    reporting level

    The third reporting

    level (Some copies

    submitted to

    Department of

    Natural Resources

    and Environment)

    Committees

    2 Environmental

    monitoring

    By: Technical

    supervisor of PMU

    Frequency: Monthly

    Submitted to: PMU

    By: PMU

    Frequency: Semi-

    annual

    Submitted to:

    Provincial

    People’s

    Committees

    By: Provincial

    People’s Committees

    Frequency: Semi-

    annual

    Submitted to: WB

    Frequency: Twice

    during project

    performance. One

    during construction,

    one after finishing

    construction

    Submitted to: WB

    and PMUs of the

    Project Owner

    Operation phase

    1 Environmental

    monitoring

    including safety

    issues

    By: District power

    companies

    Frequency: Semi-

    annual

    Submitted to: Local

    PC (province)

    By: PMU

    Frequency: Semi-

    annual

    Submitted to:

    Provincial

    People’s

    Committees

    By: Provincial

    People’s Committees

    Frequency: Annual

    Submitted to: WB

  • 47

    APPENDIX 2

    --------------------

    SUBPROJECT'S ENVIRONMENTAL PERMIT

  • 48

    APPENDIX 3

    --------------------

    EXEMPLE OF PUBLIC CONSULATION

    FOR ENVIRONMENT IMPACT ASSESSMENT RECORD

  • 49

  • 50

  • 51

  • 52

  • 53

  • 54

  • 55

  • 56

  • 57

  • 58

  • 59

  • 60

  • 61

  • 62

  • 63

  • 64

  • 65

  • 66

  • 67

  • 68

  • 69

  • 70

  • 71

  • 72

  • 73

  • 74

  • 75

  • 76

  • 77

    APPENDIX 4

    --------------------

    MAP OF SUBPROJECT IN THAI BINH

  • 78

  • 79

    APPENDIX 5

    COMMUNE-LEVEL DATA REPORT

    Project’s Commune

    Reporting Period

    Environmental Impacts:

    Impact / Mitigation

    Measure

    Commune

    Representative

    Comments

    Community Comments

    Project vehicles or activities

    increased ambient dust

    levels

    Project vehicles or activities

    increased ambient noise

    levels

    Project activities polluted

    local rivers or lakes

    Project cleared vegetation

    and this caused

    environmental impacts

    Project activities created

    impacts on agricultural

    and/or residential land

    Project activities impacted

    cultural property

    Project construction caused

    traffic impacts

    Project caused solid waste

    or liquid waste impacts

    Project caused Social and

    health impacts of workers

    Accidents

    Dust suppression measures

    Erosion and sediment

    controls

    Sitting of materials etc. to

    avoid exacerbation of flood

    effects, chemical pollution

    etc.

    Waste management

    practices

    Project activities caused any

    impact on birds, animals

    and rare flora

    Project vehicles damaged

    the roads

    Other

  • 80

    Recommendations

    ..........................................................................................................................................

    Signature of Commune Representative:

    Title of Commune Representative:

    Date: ---------------------------------------------------------------------------------------------------

  • 81

    APPENDIX 6

    Site Environmental Management Monitoring Report

    (Applied for Contractor’s Report)

    Project name: Project location:

    Name of Contractor:

    Commencement of Project report or monthly report:

    Date of report:

    No Impact Mitigation measures implemented Comment

    Construction phase

    1 Surface water contamination

    2 Noise and vibration

    3 Soil erosion

    4 Air pollution

    5 Agricultural production due to

    temporary acquisition of

    productive land

    6 Traffic disturbance

    7 Damaging the existing road

    system

    8 Solid waste generated from

    soil excavation

    9 Environmental impacts caused

    by construction worker

    10 Conflict between construction

    worker and local people

    11 Health and Safety

    Name of person prepared this Report:

    Title:

    Address: Telephone:

  • 82

    APPENDIX 7

    Environmental Performance Monitoring Report

    (This Example can be used for environmental monitoring report of Technical

    supervisor consultant, SMIC)

    Project name:

    Project location:

    Type of Report:

    Monthly report (Yes/No): Quarterly Report to PMU (Yes/No):

    Quarterly Report to the WB (Yes/No): SMIC report (Yes/No):

    Date of report:

    No Parameter Assessment of Consultant/

    community complaints

    Comments/Recommenda

    tions

    During Construction

    1 Surface water turbidity and

    soil erosion

    2 Noise level around

    construction sites and

    adjacent residential areas

    3 Dust

    4 Tree cutting and access roads

    management and control

    5 Solid waste and site cleaning

    up after the construction

    6 Workers' sanitation facilities

    and safety management

    7 Transportation disturbance

    8 Road degradation

    9 Status of application of safety

    measures

    10 Construction material

    management

    11 Management of redundant

    soil

    12 Impact on wild life and

    natural resources

    13 Evidence of biodiversity loss

    (if there is any)

    14 Evidence of loss of historical

    and cultural properties

    15 Other environment related

    issue (if there is any)

  • 83

    No Parameter Assessment of Consultant/

    community complaints

    Comments/Recommenda

    tions

    During operation

    16 Maintaining of ROW

    17 Impact on wild life and

    natural resource

    Report prepared by: Position:

  • 84

    APPENDIX 8

    SUMMARY OF SUBPROJECT IMPACTS

    1. Summary of Land acquisition by the Project

    Sr.

    No District/Commune

    Number

    of HHs

    Land Categories

    Total Agricultural

    land

    Garden

    Land

    Other

    land

    Grand Total 243 838 - 2,521 3,359

    THAI BINH

    1 Vu Phuc 1 5 - 15 20

    2 Vu Dong 3 18 - 55 73

    3 Dong My 1 5 - 15 20

    4 Phu Xuan 5 16 - 48 64

    KIEN XUONG

    5 Vu Le 1 5 - 15 20

    6 An Binh 3 11 - 34 45

    7 Vu Hoa 2 10 - 31 41

    8 Quyet Tien 4 10 - 31 41

    9 Vu An 3 7 - 21 28

    10 Quang Hung 4 11 - 33 44

    TIEN HAI

    11 Dong Xuyen 5 18 - 54 72

    12 An Ninh 4 10 - 31 41

    13 Dong Hoang 5 12 - 35 47

    14 Dong Trung 5 12 - 37 49

    15 Dong Lam 4 11 - 33 44

    16 Tay Son 2 4 - 12 16

    VU THU

    17 Minh Quang 4 17 - 50 67

    18 Hong Phong 3 12 - 36 48

    19 Hiep Hoa 5 12 - 36 48

    20 Trung An 1 4 - 12 16

    21 Dung Nghia 3 12 - 36 48

    22 Viet Thuan 4 14 - 43 57

    23 Tam Quang 2 3 - 9 12

    24 Dong Thanh 3 9 - 27 36

    25 Minh Lang 4 15 - 45 60

    26 Tu Tan 4 11 - 32 43

    HUNG HA

    27 Minh Tan 1 3 - 9 12

    28 Kim Trung 3 10 - 30 40

    29 Duyen Hai 1 6 - 17 23

    30 Van Cam 3 9 - 26 35

    31 Phuc Khanh 4 11 - 34 45

    32 Doan Hung 2 7 - 22 29

    33 Van Lang 5 15 - 45 60

    34 Hung Dung 4 12 - 35 47

    35 Hoa Binh 7 24 - 72 96

  • 85

    Sr.

    No District/Commune

    Number

    of HHs

    Land Categories

    Total Agricultural

    land

    Garden

    Land

    Other

    land

    THAI THUY

    36 Thuy Dan 3 7 - 20 27

    37 My Loc 5 16 - 47 63

    38 Thuy Binh 8 27 - 82 109

    39 Thuy Luong 4 13 - 40 53

    40 Thai Xuyen 3 13 - 40 53

    41 Thai Hong 5 18 - 55 73

    42 Thuy Lien 5 17 - 50 67

    43 Thuy Dung 7 23 - 69 92

    ĐONG HUNG

    44 Dong Cac 3 14 - 41 55

    45 Dong Quang 4 12 - 36 48

    46 Dong Tan 2 3 - 10 13

    47 Thang Long 1 7 - 20 27

    48 Nguyen Xa 7 20 - 60 80

    49 An Chau 4 12 - 36 48

    50 Dong Ha 3 8 - 25 33

    51 Dong Hop 4 16 - 47 63

    52 Dong Son 3 13 - 39 52

    53 Dong Linh 2 16 - 48 64

    QUYNH PHU

    54 An Thanh 5 15 - 46 61

    55 An Duc 4 13 - 40 53

    56 An Dong 7 23 - 70 93

    57 An Bai 5 18 - 53 71

    58 An Vinh 6 17 - 50 67

    59 An Quy 4 16 - 47 63

    60 Dong Hai 1 21 - 63 84

    61 Quynh Xa 4 14 - 43 57

    62 Quynh My 5 18 - 53 71

    63 Quynh Hoang 6 22 - 65 87

    64 Quynh Trang 5 16 - 48 64

    65 Quynh Minh 3 21 - 62 83

  • 86

    2. Summary of Affected Crop by the Project

    Sr.

    No District/Commune

    Type of crop Total

    Rice Vegetables

    Grand Total 3,559 2,056 5,615

    THAI BINH CITY

    1 Vu Phuc 115 0 115

    2 Vu Dong 66 54 120

    3 Dong My 20 13 33

    4 Phu Xuan 86 20 106

    KIEN XUONG

    5 Vu Le 33 0 33

    6 An Binh 20 55 75

    7 Vu Hoa 35 33 68

    8 Quyet Tien 32 37 69

    9 Vu An 31 16 47

    10 Quang Hung 33 40 73

    TIEN HAI

    11 Dong Xuyen 73 46 119

    12 An Ninh 33 34 67

    13 Dong Hoang 54 24 78

    14 Dong Trung 46 34 80

    15 Dong Lam 47 26 73

    16 Tay Son 13 13 26

    VU THU

    17 Minh Quang 53 56 109

    18 Hong Phong 53 27 80

    19 Hiep Hoa 79 0 79

    20 Trung An 27 0 27

    21 Dung Nghia 66 13 79

    22 Viet Thuan 75 20 95

    23 Tam Quang 20 0 20

    24 Dong Thanh 60 0 60

    25 Minh Lang 53 47 100

    26 Tu Tan 51 20 71

    HUNG HA

    27 Minh Tan 20 0 20

    28 Kim Trung 33 33 66

    29 Duyen Hai 13 23 36

    30 Van Cam 20 36 56

    31 Phuc Khanh 47 28 75

    32 Doan Hung 22 27 49

    33 Van Lang 56 44 100

    34 Hung Dung 46 30 76

    35 Hoa Binh 33 125 158

    THAI THUY

    36 Thuy Dan 34 10 44

    37 My Loc 72 32 104

    38 Thuy Binh 106 73 179

  • 87

    Sr.

    No District/Commune

    Type of crop Total

    Rice Vegetables

    39 Thuy Luong 39 47 86

    40 Thai Xuyen 48 39 87

    41 Thai Hong 72 49 121

    42 Thuy Lien 79 30 109

    43 Thuy Dung 92 60 152

    ĐONG HUNG

    44 Dong Cac 26 53 79

    45 Dong Quang 52 37 89

    46 Dong Tan 8 13 21

    47 Thang Long 22 22 44

    48 Nguyen Xa 81 52 133

    49 An Chau 55 24 79

    50 Dong Ha 21 34 55

    51 Dong Hop 66 36 102

    52 Dong Son 73 13 86

    53 Dong Linh 60 46 106

    QUYNH PHU

    54 An Thanh 75 26 101

    55 An Duc 61 26 87

    56 An Dong 102 51 153

    57 An Bai 79 36 115

    58 An Vinh 74 36 110

    59 An Quy 66 36 102

    60 Dong Hai 98 41 139

    61 Quynh Xa 68 26 94

    62 Quynh My 79 36 115

    63 Quynh Hoang 107 36 143

    64 Quynh Trang 80 26 106

    65 Quynh Minh 100 36 136

  • 88

    3. Number of trees to be cut

    Sr.

    No District/Commune

    Type of tree Total

    Banana Coconut Guava Mango Bamboo

    Grand Total 592 2 70 41 516 1,221

    THAI BINH

    1 Vu Phuc 10 - 1 1 6 18

    2 Vu Dong 20 - 3 - - 23

    3 Dong My 8 - - - - 8

    4 Phu Xuan 12 - 1 - 1 14

    KIEN XUONG

    5 Vu Le 6 - 1 - 1 8

    6 An Binh 5 - 2 - 2 9

    7 Vu Hoa 6 - - - 8 14

    8 Quyet Tien 8 - 1 - 7 16

    9 Vu An 12 - - - 6 18

    10 Quang Hung 18 - - 2 5 25

    TIEN HAI

    11 Dong Xuyen 8 - 1 - 7 16

    12 An Ninh 14 - 1 - 8 23

    13 Dong Hoang 8 - 3 - 3 14

    14 Dong Trung 12 - 3 - 9 24

    15 Dong Lam 6 - 2 - 7 15

    16 Tay Son 7 - 1 1 3 12

    VU THU

    17 Minh Quang 9 - 2 2 4 17

    18 Hong Phong 5 - 1 1 4 11

    19 Hiep Hoa 12 - 2 - 12 26

    20 Trung An 6 - 1 - 5 12

    21 Dung Nghia 5 - 2 - 5 12

    22 Viet Thuan 8 - 3 - 9 20

    23 Tam Quang 10 - - 1 4 15

    24 Dong Thanh 7 - 1 - 7 15

    25 Minh Lang 9 - 1 - 11 21

    26 Tu Tan 10 - 1 - 8 19

    HUNG HA

    27 Minh Tan 3 - 1 - 1 5

    28 Kim Trung 5 - - 1 7 13

    29 Duyen Hai 5 - 1 - 4 10

    30 Van Cam 6 - 1 1 2 10

    31 Phuc Khanh 9 - 1 - 5 15

    32 Doan Hung 4 - - 2 5 11

    33 Van Lang 11 - 2 - 9 22

    34 Hung Dung 6 - 1 - 8 15

    35 Hoa Binh 15 - 1 2 18 36

    THAI THUY

    36 Thuy Dan 9 - - 1 6 16

    37 My Loc 12 - 1 - 7 20

    38 Thuy Binh 16 - 1 1 13 31

  • 89

    Sr.

    No District/Commune

    Type of tree Total

    Banana Coconut Guava Mango Bamboo

    39 Thuy Luong 9 - 1 1 10 21

    40 Thai Xuyen 4 - 1 - 10 15

    41 Thai Hong 10 - 1 1 13 25

    42 Thuy Lien 11 - 2 - 9 22

    43 Thuy Dung 12 - 1 1 22 36

    ĐONG HUNG

    44 Dong Cac 5 - 1 - 4 10

    45 Dong Quang 10 - - 1 10 21

    46 Dong Tan 6 - - 1 3 10

    47 Thang Long 5 - 1 - 4 10

    48 Nguyen Xa 7 - 1 1 13 22

    49 An Chau 7 - 1 1 11 20

    50 Dong Ha 9 - - 1 7 17

    51 Dong Hop 13 - 1 1 13 28

    52 Dong Son 10 - 1 - 11 22

    53 Dong Linh 6 - 1 - 8 15

    QUYNH PHU

    54 An Thanh 10 - 1 1 6 18

    55 An Duc 8 - - 1 13 22

    56 An Dong 14 - 1 1 15 31

    57 An Bai 9 - 1 - 14 24

    58 An Vinh 12 - 1 2 14 29

    59 An Quy 6 - 1 1 7 15

    60 Dong Hai 14 - 2 1 15 32

    61 Quynh Xa 10 - 1 1 10 22

    62 Quynh My 12 - 1 2 16 31

    63 Quynh Hoang 11 1 2 2 10 26

    64 Quynh Trang 10 1 1 2 11 25

    65 Quynh Minh 10 - 1 2 10 23