i 2015 ENVIRONMENTAL MANAGEMENT PLAN FOR THE PROPOSED CONSTRUCTION OF NINE MINI CELLULAR STRUCTURES IN WINDHOEK

Upload: vuliem

Post on 31-Jan-2018

224 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: ENVIRONMENTAL MANAGEMENT PLAN FOR THE · PDF fileBillboard 3 x Kathrein 742265 (65 ... Proposed Construction of nine mini cellular structures in Windhoek ... Proposed Construction

i

2015

ENVIRONMENTAL MANAGEMENT PLAN FOR THE

PROPOSED CONSTRUCTION OF NINE MINI CELLULAR

STRUCTURES IN WINDHOEK

Page 2: ENVIRONMENTAL MANAGEMENT PLAN FOR THE · PDF fileBillboard 3 x Kathrein 742265 (65 ... Proposed Construction of nine mini cellular structures in Windhoek ... Proposed Construction

1

Table of Contents

LIST OF TABLES AND FIGURES ....................................................................................................2

ABBREVIATIONS .........................................................................................................................2

1 INTRODUCTION...................................................................................................................3

2 RESPONSIBILITIES .................................................................................................................8

2.1 EMPLOYERS REPRESENTATIVE (ER) ..............................................................................8

2.2 ENVIRONMENTAL CONTROL OFFICER (ECO) ............................................................9

2.3 CONTRACTOR ...........................................................................................................10

3 MANAGEMENT REQUIREMENTS .......................................................................................10

4 PERMIT REQUIREMENTS.....................................................................................................11

5 PLANNING AND DESIGN PHASE ......................................................................................12

6 CONSTRUCTION MITIGATION DETAILS.............................................................................13

7 OPERATIONAL PHASE .......................................................................................................20

8 DECOMMISSIONING PHASE ............................................................................................20

Page 3: ENVIRONMENTAL MANAGEMENT PLAN FOR THE · PDF fileBillboard 3 x Kathrein 742265 (65 ... Proposed Construction of nine mini cellular structures in Windhoek ... Proposed Construction

2

Proposed Construction of nine mini cellular structures in Windhoek Appendix C – Environmental Management Plan (EMP)

March 2015

LIST OF TABLES AND FIGURES

Table 1: Relevant legislated permit requirements ...........................................................11

Table 2: Management requirements for the Planning and Design phase ...................12

Table 3: Generic and site-specific environmental management actions for the construction phase...............................................................................................13

Table 4: Operational phase mitigation measures ............................................................20

Table 5: Decommissioning phase mitigation measures..................................................20

Figure 1: The proposed locality of the project site. ..........................................................3

Figure 2: Site specifications ................................................................................................5

ABBREVIATIONS

DEA Directorate of Environmental Affairs

ECC Environmental Clearance Certificate

ECO Environmental Control Officer

EA Environmental Assessment

EIA Environmental Impact Assessment

EMP Environmental Management Plan

ER Employer’s Representative

GG Government Gazette

GN Government Notice

MHz Mega Hertz

Page 4: ENVIRONMENTAL MANAGEMENT PLAN FOR THE · PDF fileBillboard 3 x Kathrein 742265 (65 ... Proposed Construction of nine mini cellular structures in Windhoek ... Proposed Construction

3

Proposed Construction of nine mini cellular structures in Windhoek Appendix C – Environmental Management Plan (EMP)

March 2015

1 INTRODUCTION

Due to the constant growth in the use of mobile voice and data services in Windhoek, service providers such as Mobile Telecommunications (Ltd) (MTC) are under pressure to continuously expand their communications network.

Figure 1: The proposed locality of the project sites.

Page 5: ENVIRONMENTAL MANAGEMENT PLAN FOR THE · PDF fileBillboard 3 x Kathrein 742265 (65 ... Proposed Construction of nine mini cellular structures in Windhoek ... Proposed Construction

4

Proposed Construction of nine mini cellular structures in Windhoek Appendix C – Environmental Management Plan (EMP)

March 2015

By adding new infrastructures, cellphone reception and accessibility to mobile voice and data services can be assured. The quality of the mobile services provided by MTC to their customers is greatly improved.

Page 6: ENVIRONMENTAL MANAGEMENT PLAN FOR THE · PDF fileBillboard 3 x Kathrein 742265 (65 ... Proposed Construction of nine mini cellular structures in Windhoek ... Proposed Construction

5

The proposed 9 mini BTS structures have the following specifications:

Figure 2: Site specifications

Project site Site location Structure type

Structure design (Example) Type of Antenna

Power output (Watts)

Radio Frequency

Roman Catholic Existing billboard on the northern boundary of the property

Billboard

Integrated Antennas

5 1920 - 2170 MHz

Ausspanplatz Circle

Existing billboard at the centre of the circle

Billboard 2 x Kathrein 736350 (8dBi Omni)

5 1920 - 2170 MHz

Concordia Existing billboard on the southern boundary of the Concordia College

Billboard 3 x Kathrein 742265 (65 degree, dual band)

20 880 - 960 MHz / 1920 - 2170 MHz

KFC Building On top of the KFC building, corner of Mandume Ndemufayo Avenue and Tal street.

Rooftop Integrated Antennas

5 1920 - 2170 MHz

Arebbusch Supermarket

On top of Supermarket building, Arebbush street in Cimbebasia

Rooftop 2 x Kathrein 736350 (8dBi Omni)

5 1920 - 2170 MHz

Equipment Box

Page 7: ENVIRONMENTAL MANAGEMENT PLAN FOR THE · PDF fileBillboard 3 x Kathrein 742265 (65 ... Proposed Construction of nine mini cellular structures in Windhoek ... Proposed Construction

6

Proposed Construction of nine mini cellular structures in Windhoek Appendix C – Environmental Management Plan (EMP)

March 2015

Project site Site location Structure type

Structure design (Example) Type of Antenna

Power output (Watts)

Radio Frequency

Maerua Mall On top of Maerua Mall

Rooftop

Grove Mall On top of Grove Mall

Rooftop

IUM (School of Management)

On top of the entrance gate at the School of Management

Rooftop Integrated Antennas

5 1920 - 2170 MHz

Satcom On top of an existing structure on the Satcom building in Suiderhof

Rooftop

Integrated Antennas

5 1920 - 2170 MHz

Page 8: ENVIRONMENTAL MANAGEMENT PLAN FOR THE · PDF fileBillboard 3 x Kathrein 742265 (65 ... Proposed Construction of nine mini cellular structures in Windhoek ... Proposed Construction

7

An EMP is one of the most important outcomes of an Environmental Assessment (EA) process. It combines all recommended mitigation and monitoring measures, laid out according to the various stages of a project life cycle, with clearly defined follow-up actions and responsibility assigned to specific actors. This EMP is a legally binding document and has been drafted in accordance with the Namibian Environmental Management Act (No. 7 of 2007) and its Environmental Impact Assessment Regulations (2012).

This plan describes the mitigation and monitoring measures to be implemented during the following phases of the site establishment:

• Planning and Design;

• Construction; and

• Operation and Decommissioning

Although decommissioning of the sites are not foreseen mitigation measures have been provided nonetheless (Table 5).

Page 9: ENVIRONMENTAL MANAGEMENT PLAN FOR THE · PDF fileBillboard 3 x Kathrein 742265 (65 ... Proposed Construction of nine mini cellular structures in Windhoek ... Proposed Construction

8

Proposed Construction of nine mini cellular structures in Windhoek Appendix C – Environmental Management Plan (EMP)

March 2015

2 RESPONSIBILITIES

The responsibility for the implementation of the EMP ultimately lies with MTC (the Proponent), who is also responsible for the eventual operation of the site. The implementation of this EMP requires the involvement of several stakeholders, each fulfilling a different but vital role to ensure comprehensive environmental management during each phase of this project.

The proponent should appoint an Employer’s Representative (ER) to oversee all aspects of this project (including all contracts for sub-contractor work outsourced). The ER will in turn appoint an Environmental Control Officer (ECO) to oversee the implementation of the whole EMP (if no ECO is appointed this responsibility remains with the ER). The following positions and their respective responsibilities will be outlined below:

• Employer’s Representative;

• Environmental Control Officer; and

• Contractor (Construction and Operations).

2.1 EMPLOYERS REPRESENTATIVE (ER)

The ER is appointed by the contractor to manage all contracts for work/services that are outsourced during the construction phase. Any official communication regarding work agreements is delivered through this person. The ER should with the commencement of the project appoint a competent ECO who will represent the Proponent on-site.

The ER shall assist the ECO where necessary and will have the following responsibilities regarding the implementation of this EMP:

• Ensuring that the necessary legal authorisations and permits (see Table 1) have been obtained by the Contractor;

• Assisting the Contractor in finding environmentally responsible solutions to problems with input from the ECO where necessary;

• Ordering the removal of individuals and/or equipment not complying with the EMP;

• Issuing fines for transgression of site rules and penalties for contravention of the EMP; and

• Providing input into the ECO's ongoing internal review of the EMP. This review report should be submitted on a monthly basis to the Proponent.

Page 10: ENVIRONMENTAL MANAGEMENT PLAN FOR THE · PDF fileBillboard 3 x Kathrein 742265 (65 ... Proposed Construction of nine mini cellular structures in Windhoek ... Proposed Construction

9

Proposed Construction of nine mini cellular structures in Windhoek Appendix C – Environmental Management Plan (EMP)

March 2015

2.2 ENVIRONMENTAL CONTROL OFFICER (ECO)

The ECO should be a competent person appointed by the ER. The ECO is the Proponent’s on-site representative primarily responsible for the monitoring and review of on-site environmental management and implementation of the EMP by the Contractor. If no ECO is appointed the duties of the ECO fall upon the ER.

The ECO’s duties include the following:

• Assisting the ER in ensuring that the necessary legal authorisations have been obtained;

• Maintaining open and direct lines of communication between the ER, Proponent, and Interested and Affected Parties (I&APs) with regard to this EMP and matters incidental thereto;

• Monthly site inspection of all construction areas with regard to compliance with this EMP;

• Monitor and verify adherence to the EMP (audit the implementation of the EMP) and verify that environmental impacts are kept to a minimum;

• Taking appropriate action if the specifications of the EMP are not adhered to;

• Assisting the contractor in finding environmentally responsible solutions to problems;

• Advising on the removal of person(s) and/or equipment not complying with the specifications of the EMP in consultation with the ER;

• Recommending the issuing of fines for transgressions of site rules and penalties for contraventions of the EMP; and

• Undertaking an annual review of the EMP and recommending additions and/or changes to the document.

Page 11: ENVIRONMENTAL MANAGEMENT PLAN FOR THE · PDF fileBillboard 3 x Kathrein 742265 (65 ... Proposed Construction of nine mini cellular structures in Windhoek ... Proposed Construction

10

Proposed Construction of nine mini cellular structures in Windhoek Appendix C – Environmental Management Plan (EMP)

March 2015

2.3 CONTRACTOR

The Contractor is responsible for the implementation of the EMP, on-site monitoring and evaluation of the EMP. It is envisaged that only one contractor might be appointed during the construction phase of this project. In order to ensure sound environmental management, the relevant sections of this EMP should be included in all contracts of work outsourced, thus legally binding the contractor. All contractors shall ensure that adequate environmental awareness training (see Section D) of senior site personnel takes place and that all construction workers and newcomers receive an induction presentation on the importance and implications of this EMP. The presentation shall be conducted, as far as is possible, in the employees’ language of choice.

The Contractor should keep records of all environmental training sessions, including names, dates and the information presented.

3 MANAGEMENT REQUIREMENTS

This EMP has been structured to provide its various intended recipients (Proponent, ER, Contractor and ECO) with mitigation measures immediately applicable to their respective scopes of work. The management requirements for the various recipients carrying out work for this project are divided according to the main project phases:

• Permit and relevant legal requirements (Table 1);

• Planning and Design Phase requirements (Table 2);

• Construction Phase mitigation requirements (Table 3); and

• Decommissioning phase requirements (Table 5)

Page 12: ENVIRONMENTAL MANAGEMENT PLAN FOR THE · PDF fileBillboard 3 x Kathrein 742265 (65 ... Proposed Construction of nine mini cellular structures in Windhoek ... Proposed Construction

11

Proposed Construction of nine mini cellular structures in Windhoek Appendix C – Environmental Management Plan (EMP)

March 2015

4 PERMIT REQUIREMENTS

Table 1 below outlines the relevant permit acquisitions that have to be obtained in order to render this project legally compliant.

Table 1: Relevant legislated permit requirements

THEME LEGISLATION INSTRUMENT

MANAGEMENT REQUIREMENTS CONTACT PERSON

Environmental Environmental Management Act 7 of 2007

EIA Regulations (EIAR) GN 57/2007 (GG 3812)

The amendment, transfer or renewal of the Environmental Clearance Certificate (EIAR s19 & 20) after every three year approval period.

Dr Freddy Sikabongo/ Ms Saima Angula

Tel: 061 284 2751

Labour Labour Act 11 of 2007

Health and Safety Regulations (HSR) GN 156/1997 (GG 1617).

Adhere to all applicable provisions of the Labour Act and the Health and Safety regulations.

Labour Law office: Legal Advice;

Tel: 061 309 957

The following section illustrates the planning and design management parameters that must be considered and implemented before construction can begin on site.

Page 13: ENVIRONMENTAL MANAGEMENT PLAN FOR THE · PDF fileBillboard 3 x Kathrein 742265 (65 ... Proposed Construction of nine mini cellular structures in Windhoek ... Proposed Construction

12

Proposed Construction of nine mini cellular structures in Windhoek Appendix C – Environmental Management Plan (EMP)

March 2015

5 PLANNING AND DESIGN PHASE

The following Management requirements for this phase should be noted and implemented.

Table 2: Management requirements for the Planning and Design phase

ASPECT MANAGEMENT REQUIREMENT

Recruitment of construction personnel

• The recruitment process should be a formalised process that gives preference to local inhabitants of Windhoek to fill all positions available to complete the construction phase.

• All unskilled jobs must be availed to local residents residing in Windhoek (if available).

General provisions • A provision for the facilitation of an induction programme for senior, casual construction personnel as well as subcontractors and associated personnel should be made to implement before and during construction.

Page 14: ENVIRONMENTAL MANAGEMENT PLAN FOR THE · PDF fileBillboard 3 x Kathrein 742265 (65 ... Proposed Construction of nine mini cellular structures in Windhoek ... Proposed Construction

13

Proposed Construction of nine mini cellular structures in Windhoek Appendix C – Environmental Management Plan (EMP)

March 2015

6 CONSTRUCTION MITIGATION DETAILS

The following table provides a large-scale overview of all the major environmental management themes pertaining to both generic and site-specific construction mitigation details. This table serves to act as quick reference, for the detailed mitigation details that follow below, for the implementation of the construction component of this EMP.

Table 3: Generic and site-specific environmental management actions for the construction phase

THEME OBJECTIVE MITIGATION DETAIL

GENERIC SITE-SPECIFIC

Waste management Avoid and where not possible minimise all pollution associated with construction.

Section A N/A

Health and safety Safeguard health and safety of laborers and general public.

Section B N/A

Environmental training and awareness

Awareness creation regarding the provisions of the EMP as well as importance of safeguarding environmental resources.

Section C N/A

Environmental conservation

Minimise construction activity footprint and safeguard biodiversity.

Section D N/A

Employment/ Recruitment Minimise negative conflict through legal and fair recruitment practices.

Section E N/A

Stakeholder communication

Provide a platform for stakeholders to raise grievances and receive feedback and hence minimise negative conflict

Section F N/A

Page 15: ENVIRONMENTAL MANAGEMENT PLAN FOR THE · PDF fileBillboard 3 x Kathrein 742265 (65 ... Proposed Construction of nine mini cellular structures in Windhoek ... Proposed Construction

14

Proposed Construction of nine mini cellular structures in Windhoek Appendix C – Environmental Management Plan (EMP)

March 2015

SECTION A: WASTE MANAGEMENT

ASPECT MITIGATION MEASURE

GENERIC MITIGATION DETAILS

General waste • The construction site should be kept tidy at all times. All domestic and general construction waste produced on a daily basis should be contained and the site cleaned daily.

• No waste may be buried or burned. • Waste containers (bins) must be emptied regularly and removed from site to a

recognised (municipal) waste disposal site. All recyclable waste needs to be taken to the nearest recycling depot.

• A sufficient number of separate waste containers (bins) for hazardous and domestic/general waste must be provided on site. These should be clearly marked as such and properly secured.

• Construction labourers should be sensitised to dispose of waste in a responsible manner and not to litter.

• No waste may remain on site after the completion of the project.

MONITORING DETAILS

The ECO should compile a checklist to use on site daily. This checklist must record compliance to the waste management measures prescribed in this section. All non-compliances must be dealt with sternly and promptly.

Page 16: ENVIRONMENTAL MANAGEMENT PLAN FOR THE · PDF fileBillboard 3 x Kathrein 742265 (65 ... Proposed Construction of nine mini cellular structures in Windhoek ... Proposed Construction

15

Proposed Construction of nine mini cellular structures in Windhoek Appendix C – Environmental Management Plan (EMP)

March 2015

SECTION B: HEALTH AND SAFETY

ASPECT MITIGATION MEASURE

GENERIC MITIGATION MEASURES

Road Safety • All vehicles that transport materials to and from the site must be road worthy.

• Drivers that transport materials should have a valid driver’s license and should adhere to all traffic rules.

• Loads upon vehicles should be properly secured to avoid items falling off the vehicle.

Safety Around Work Areas

• All building materials and equipment are to be stored only within set out and demarcated work areas, if on-site.

• Only construction personnel will be allowed within work areas.

• Two fire extinguishers should be available on site.

• Comply with all mitigation measures laid out in Section A (Waste Management mitigation details)

Ablutions • Separate ablutions (toilets) should be available for men and women and should clearly be indicated as such.

• Portable toilets (i.e. easily transportable) should be available at the construction site:

o Sewage waste needs to be removed on a regular basis by the supplier company to an approved (municipal) sewage disposal site.

Open fires • No open fires may be made anywhere on site.

General • Sufficient potable water should be provided to workers (5 litres per person per day).

• No person should be allowed to smoke close to portable toilets (if toilets are chemical toilets – the chemicals are flammable).

• No workers should be allowed to drink alcohol during work hours.

• No workers should be allowed on site if under the influence of alcohol.

Page 17: ENVIRONMENTAL MANAGEMENT PLAN FOR THE · PDF fileBillboard 3 x Kathrein 742265 (65 ... Proposed Construction of nine mini cellular structures in Windhoek ... Proposed Construction

16

Proposed Construction of nine mini cellular structures in Windhoek Appendix C – Environmental Management Plan (EMP)

March 2015

SECTION C: ENVIRONMENTAL TRAINING AND AWARENESS

ASPECT MITIGATION MEASURE

GENERIC MITIGATION DETAILS

Environmental Induction (Training)

All construction workers are to undergo environmental induction (training) which should include as a minimum the following:

• Explanation of the importance of complying with the EMP.

• Discussion of the potential environmental impacts of construction activities.

• Employees’ roles and responsibilities, including emergency preparedness.

• Explanation of the mitigation measures that must be implemented when particular work groups carry out their respective activities.

• Explanation of the specific mitigation measures within this EMP especially unfamiliar provisions.

MONITORING DETAILS

A training register should be kept by the ECO. The following should be recorded in it:

• The approved training material provided.

• A signed record of the attendees present at each training session.

Page 18: ENVIRONMENTAL MANAGEMENT PLAN FOR THE · PDF fileBillboard 3 x Kathrein 742265 (65 ... Proposed Construction of nine mini cellular structures in Windhoek ... Proposed Construction

17

Proposed Construction of nine mini cellular structures in Windhoek Appendix C – Environmental Management Plan (EMP)

March 2015

SECTION D: ENVIRONMENTAL CONSERVATION

ASPECT MITIGATION MEASURE

GENERIC MITIGATION DETAILS

Materials camp and lay-down areas

Suitable locations for the materials camp and lay-down areas should be identified with the assistance of the ER and the following should be considered in selecting these sites:

• The areas designated for the proposed services infrastructure should be used as far possible. Degraded land should preferably be used.

Page 19: ENVIRONMENTAL MANAGEMENT PLAN FOR THE · PDF fileBillboard 3 x Kathrein 742265 (65 ... Proposed Construction of nine mini cellular structures in Windhoek ... Proposed Construction

18

Proposed Construction of nine mini cellular structures in Windhoek Appendix C – Environmental Management Plan (EMP)

March 2015

SECTION E: EMPLOYMENT/RECRUITMENT

ASPECT MITIGATION MEASURE

GENERIC MITIGATION DETAILS

Legislation Adhere to the legal provisions in the Labour Act (see Table 1) for the recruitment of labour (target percentages for gender balance, optimal use of local labour and SME’s, etc) in the Contract.

Page 20: ENVIRONMENTAL MANAGEMENT PLAN FOR THE · PDF fileBillboard 3 x Kathrein 742265 (65 ... Proposed Construction of nine mini cellular structures in Windhoek ... Proposed Construction

19

Proposed Construction of nine mini cellular structures in Windhoek Appendix C – Environmental Management Plan (EMP)

March 2015

SECTION F: STAKEHOLDER COMMUNICATION

ASPECT MITIGATION MEASURE

GENERIC MITIGATION DETAILS

Communication plan • How stakeholders, who require ongoing communication for the duration of the construction period, will be identified and recorded and who will manage and update these records;

• How these stakeholders will be consulted on an ongoing basis;

• Make provision for grievance mechanisms – i.e. how concerns can/ will be lodged/ recorded and how feedback will be delivered as well as further steps of arbitration in the even feedback is deemed unsatisfactory.

General communication matters

• The ECO must liaise between the Proponent, stakeholders, and consultants.

• All communication with the stakeholders must take place through the ECO.

• A copy of the EMP must be available at the site office and should be accessible to all stakeholders

• The ECO should liaise with the Proponent regarding all issues related to community consultation and negotiation before construction commences.

• A procedure should be put in place to ensure that concerns raised have been followed-up and addressed.

• All people on the stakeholders list should be informed about the availability of the complaints register in writing by the ECO prior to the commencement of construction activities.

Page 21: ENVIRONMENTAL MANAGEMENT PLAN FOR THE · PDF fileBillboard 3 x Kathrein 742265 (65 ... Proposed Construction of nine mini cellular structures in Windhoek ... Proposed Construction

20

Proposed Construction of nine mini cellular structures in Windhoek Appendix C – Environmental Management Plan (EMP)

March 2015

7 OPERATIONAL PHASE

Table 4: Operational phase mitigation measures

ASPECT MITIGATION MEASURE

Radiation • MTC should regularly review the radiation output of the BTS to ensure that it complies with ICNIRP standards, or other nationally or internationally accepted standards.

• Should new Radio Frequency emission standards be approved either by Communications Regulatory Authority of Namibia (CRAN), the National Radiation Protection Authority(NRPA) or by the World Health Organisation (WHO), MTC will need to revise their output levels to ensure that they comply with the new standards.

8 DECOMMISSIONING PHASE

Table 5: Decommissioning phase mitigation measures

ASPECT MITIGATION MEASURE

EMP implementation

If any construction is to be conducted as part of decommissioning works for the services infrastructure within the project area please refer to the construction mitigation measures of this EMP (Section 8).

Post-construction environmental training and awareness

All contractors appointed for maintenance work on the respective services infrastructure must ensure that all personnel are aware of necessary health, safety and environmental considerations applicable to their respective work.