environmental management plan empdocuments.worldbank.org/curated/pt/678501468220510692/... ·...

54
1 World Bank Loan of Jinzhou City, Yixian Urban Area Central Heating Pipe Network Expansion Project Environmental Management Plan ( EMP ) Liaoning Academy for Environmental Planning Co.,Ltd January 2014 E1714 V21 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

Upload: others

Post on 26-Jul-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Environmental Management Plan EMPdocuments.worldbank.org/curated/pt/678501468220510692/... · 2016-07-11 · 1 World Bank Loan of Jinzhou City, Yixian Urban Area Central Heating Pipe

1

World Bank Loan of Jinzhou City, Yixian

Urban Area Central Heating Pipe

Network Expansion Project

Environmental Management Plan

(EMP)

Liaoning Academy for Environmental Planning Co.,Ltd

January 2014

E1714 V21

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Page 2: Environmental Management Plan EMPdocuments.worldbank.org/curated/pt/678501468220510692/... · 2016-07-11 · 1 World Bank Loan of Jinzhou City, Yixian Urban Area Central Heating Pipe

2

Table of Contents

1 Purpose of Environmental Management Plan .......................................................................... 1 1.1 PURPOSE OF ENVIRONMENTAL MANAGEMENT PLAN ............................................... 1

1.2 PROGRAMME OF ACTION AND REQUIREMENT ............................................................ 2

1.3 INSTITUTIONAL ARRANGEMENTS ................................................................................... 2

2Basis of Compilation ..................................................................................................................... 3 2.1 EXECUTIVE STANDARD ...................................................................................................... 3

2.2 BASIS OF COMPILATION ..................................................................................................... 5

3Project Overview........................................................................................................................... 5 3.1 PROJECT BACKGROUND ..................................................................................................... 5

3.2 PROJECT NAME, NATURE AND CONSTRUCTION SITES ............................................... 6

3.3 CONSTRUCTION CONTENTS .............................................................................................. 7

3.4 POLLUTANT EMISSIONS IN THIS PROJECT ..................................................................... 8

3.5 ALTERNATIVE SOURCE ....................................................................................................... 9

3.6 HEAT PLANT ......................................................................................................................... 10

4 Environmental Impact Analysis ............................................................................................... 12 4.1 STATUS OF ENVIRONMENTAL QUALITY....................................................................... 12

4.2 ENVIRONMENTAL IMPACT ANALYSIS DURING CONSTRUCTION PERIOD ........... 13

4.3 ENVIRONMENTAL IMPACT ANALYSIS DURING OPERATION PERIOD .................... 18

5 Environmental Impact Mitigation Measures .......................................................................... 26

6 Environmental Monitoring Plan .............................................................................................. 35

7 Training Programme ................................................................................................................. 39

8 Reporting System ....................................................................................................................... 40 8.1 MONITORING REPORT ....................................................................................................... 40

8.2 RECORD AND EMP IMPLEMENTATION ANNUALS ...................................................... 42

9 Public Participation Programme .............................................................................................. 43 9.1 PUBLIC PARTICIPATION ..................................................................................................... 43

9.2 DISPUTE COMPLAINT CHANNELS .................................................................................. 51

10 Implementation Costs of Management Plan ......................................................................... 52

Page 3: Environmental Management Plan EMPdocuments.worldbank.org/curated/pt/678501468220510692/... · 2016-07-11 · 1 World Bank Loan of Jinzhou City, Yixian Urban Area Central Heating Pipe

1

1 Purpose of Environmental Management

Plan

1.1 PURPOSE OF ENVIRONMENTAL MANAGEMENT PLAN

During the construction phase of the project, the atmospheric and acoustic

environment will be impacted, and major impact on the acoustic environment will be

imposed.To elaborate the contents of the aspects of environmental impacts, mitigation

measures, environmental management, environmental supervision and environmental

monitoring, the Environmental Management Plan is hereby formulated, which is the

guidance documents for the environmental management in the project implementation

process, and its roles are listed as follows:

( 1 ) To define environmental objectives and environmental mitigation measures

Yixian EPA, environmental impact assessment unit and design unit shall conduct the

detailed verification and validation for environmental protection objectives and shall

propose effective environmental mitigation measures to incorporate into the project

design.

( 2 ) As the guiding document for environmental management

After the review of environmental management plan by the World Bank, it will be

provided for the construction supervision unit, environmental supervision unit and other

related units during construction and operation periods as the environmental protection

text.

( 3 ) To define the responsibilities and roles of related units

The responsibilities and roles of the relevant functional departments and regulatory

bodies shall be clearly defined in Environmental Management Plan, and the

communication channels and manners shall be proposed between the various departments.

( 4 ) To determine the environmental monitoring plan during construction and operation

period.

( 5 ) The environmental monitoring plan during construction period and operation

proposed in environmental management plan shall ensure the effective implementation of

environmental mitigation measures.

Page 4: Environmental Management Plan EMPdocuments.worldbank.org/curated/pt/678501468220510692/... · 2016-07-11 · 1 World Bank Loan of Jinzhou City, Yixian Urban Area Central Heating Pipe

2

1.2 PROGRAMME OF ACTION AND REQUIREMENT

In order to minimize the environmental impact of the project produced, under with

the joint efforts of the World Bank officials, international consultants, EIA units,

construction units and the relevant departments of the people's government of the Yixian

County, the overall objective of the environmental management during project

construction and operation periods is formulated: To keep the socio-economic and

environmental sustainability development in Yixian County, to improve the environmental

quality of Yixian County, to mitigate or compensate for the negative impact of the project

brought to the community and the environment until it is minimized.

The specific actions and requirements are as follows:

( 1 ) Action:

Propose and implement environmental management and monitoring plan;

Propose and implement pollution control strategies to mitigate its impact on the

ambient air.

( 2 ) Requirements:

To inspect the monitoring results of monitoring factors listed in the environmental

monitoring program of construction and operation periods.

In accordance with the procedures, all the environmental mitigation measures

proposed in the environmental impact assessment shall be implemented.

1.3 INSTITUTIONAL ARRANGEMENTS

To ensure the effectively control and mitigation of a variety of adverse environmental

impacts, the whole process of the project shall be strictly and scientifically tracked, and

the environmental management and environmental monitoring shall be carried out in a

standardized manner. Surveillance and monitoring regulatory agencies are shown in

Figure.

Page 5: Environmental Management Plan EMPdocuments.worldbank.org/curated/pt/678501468220510692/... · 2016-07-11 · 1 World Bank Loan of Jinzhou City, Yixian Urban Area Central Heating Pipe

3

2Basis of Compilation

2.1 EXECUTIVE STANDARD

2.1.1 ENVIRONMENTAL QUALITY STANDARDS

( 1 ) Ambient Air Quality Standard

For the conventional pollutants in ambient air quality, the Level II Standard in

national "Ambient Air Quality Standard" (GB3095-2012) shall be implemented. Specific

values are shown in Table 2-1.

Table 2-1 Ambient Air Quality Standard

Standard Items

pollutant concentration limits(mg/m3)

Hourly average Daily average Yearly average

GB3095-2012

SO2 0.50 0.15 0.06

TSP / 0.30 0.20

PM10 / 0.15 0.07

NO2 0.20 0.08 0.04

( 2 ) Ambient Noise Standards: the Level I and II Standard in "Environmental Quality

Standard" (GB3096-2008) of the sound environment quality of the project shall be

Lender: World Bank Loan representatives: World Bank environmental officials

Owner Representative: Jinzhou Guanda Heating Power Co., Ltd.

Environmental Monitoring Station of Yixian County (The monitoring program listed in this section shall be monitored and prepared with monitoring reports)

Environmental protection administration departments: Liaoning Provincial Environmental Protection Bureau, Environmental Protection Agency of Jinzhou City, EPA of Yixian County

Construction Unit (Implementation of pollution mitigation measures during operational period)

Environmental Management Company (Responsible for the monitoring of pollution mitigation measures of construction and operational periods)

Construction Unit (Implementation of pollution mitigation measures during construction period)

Page 6: Environmental Management Plan EMPdocuments.worldbank.org/curated/pt/678501468220510692/... · 2016-07-11 · 1 World Bank Loan of Jinzhou City, Yixian Urban Area Central Heating Pipe

4

implemented.

Table 2-2 "Environmental Quality Standard" (GB3096-2008) Unit: dB (A)

Category Number of Heat Exchange Station noise limits

Day Night

Category 1 New 8 #, New 9 #, New 15 #, New16 #, New 17 # 55 45

Category 2

new 1#, new 2#, new 3#, new 4#, new 5#, new 6#, new

7#, new 10#, new 11#, new 12#, new 13#, new 14#,

newly built 10 buildings of heat exchange stations

60 50

2.1.2 Pollutant Emission Standards

( 1 ) Wastewater

The waste water in this project is discharged into the city water supply network, and

then transfer to sewage treatment plant of Yixian County (Yixian Beikong Water Service

Limited Company) with the implementation of standard of discharging into municipal

wastewater treatment plant of "Integrated Wastewater Discharge Standard of Liaoning

Province" (DB21/1627-2008) (GB8978-1996 has also defined the effluent water quality

discharged into the municipal wastewater treatment plant, but the standards of Liaoning

provincial is stricter than national standards).

Table 2-3 comparison list of the relevant flue gas emission standards (mg/m3)

Pollutants

GB "Integrated Wastewater

Discharge Standard"

GB8978-1996 Category III

provincial standard "Integrated

Wastewater Discharge

Standard of Liaoning

Province"

(DB21/1627-2008-2003) Table

2

CODcr — 300

BOD5 — 250

SS — 300

NH3-N — 30

( 2 ) Noise

"Emission standard of environment noise for boundary of construction site" (GB12523- 2011)

shall be implemented for the noise during construction period.

( 3 ) Solid Waste

For solid waste, "Standard for pollution control on the storage and disposal site fo-

Page 7: Environmental Management Plan EMPdocuments.worldbank.org/curated/pt/678501468220510692/... · 2016-07-11 · 1 World Bank Loan of Jinzhou City, Yixian Urban Area Central Heating Pipe

5

r general industrial solid wastes" (GB18599-2001) and "Announcement On the release

of 3 National Pollutant Control standard amendments of <Standard for pollution con

-trol on the storage and disposal site for general industrial solid wastes > (GB18599-2001)

" (Announcement No. 36 in 2013).

( 4 ) Construction dust (particulate matter)

The table 2 of "Integrated emission standard of air pollutants" (GB16297-1996) shall

be implemented with the fugitive emission of monitoring the concentration limits

(1.0mg/m3).

2.2 BASIS OF COMPILATION

The Environmental Management Plan is formulated in accordance with

environmental protection laws and regulations of PRC, the World Bank security policy,

regulations and planning documents on environmental protection of Liaoning Province,

Jinzhou City and Yixian County, the project design document, the project environmental

impact assessment of technical documentation of Environmental Protection

Administration of the Ministry of Construction, international environmental agreements

signed by China.

3Project Overview

3.1 PROJECT BACKGROUND

Currently, within the urban area of Yixian, only 1 building of Jinzhou Guanda

Heating Power Co., Ltd. in the south provides the central heating heat source, 4 placess of

scattered small boiler rooms, and a total of nine hot water boilers with a total capacity of

250.5MW, total heating area of 2,445,300 m2, of which the central heating area is of

2,105,300 m2.The central heating souce Jinzhou Guanda Heating Power Co., Ltd. is

located in Houyang Village, Chengguan Township, Yixian County, which covers an area

of 35,000 m2, currently it has 43 regional heat exchange stations (including a heat

exchanger station within heating source plant), and the heating capacity is 215MW, with

two sets of 70MW (2 × 100t / h), 1 set of 46MW (65t / h), 1 set of 29MW (40t / h), where

one set of 70MW (100t / h) is used as a backup boiler currently, and the existing heating

area is of 2,105,300 m2.

Page 8: Environmental Management Plan EMPdocuments.worldbank.org/curated/pt/678501468220510692/... · 2016-07-11 · 1 World Bank Loan of Jinzhou City, Yixian Urban Area Central Heating Pipe

6

The heating pipes in urban area have quality problems.Most of the pipelines have the

problem of aging and corrosion, the pipeline leakage and blockage have seriously affected

the quality of heating; part of pipe materials are poor, and insulation materials are

damaged, and the quality problems of pipe fittings are getting increasingly serious.Due to

valve leakage, corrosion damage of compensator and the erosion of holders, failures of

heating system happened frequently, which seriously affected the heating quality.The lack

of overall planning and design of the pipe network, unreasonable pipeline laying coupled

with the significant changes occurred in heat load in recent years resulted the serious

disorders in the current pipe network hydraulic conditions and thermal condition. The

network systems of Level II lacks control facilities, which resulted in the uneven heating

and disorders of hydraulic conditions.

According the relevant issues of heating realities, the following issues are analyzed:

① The decentralized heating boiler room has low heating efficiency, big energy

consumption, poor quality and serious pollution.

② With the development of the Yixian County, the current heat source cannot meet

the needs of the heating load development.

Because of the above problems, the construction of heating pipe network expansion

project of centralized heating in Yixia County can save energy, reduce pollution and

improve the local environment.Upon completion of this project, the heating supply of

Yixian County will be undertaken by Jinzhou Guanda Heating Power Co., Ltd., which will

replace the 4 dispersing small boiler rooms in the heating area (five sets of small boilers)

to solve the problems of coal cinder dust produced by boiler room burning, the dust of

heap coal yard and boiler room noise nuisance; after the transformation of some of the

existing regional heat exchange stations, the land occupation can also be reduced.

Construction of this project brings not only economic benefits, but also the greater

environmental and social benefits.

3.2 PROJECT NAME, NATURE AND CONSTRUCTION SITES

Project Name: World Bank Loan of Jinzhou City, Yixian Urban Area Central Heating

Pipe Network Expansion Project

Construction Location: Urban District of Yixian, Jinzhou City

Page 9: Environmental Management Plan EMPdocuments.worldbank.org/curated/pt/678501468220510692/... · 2016-07-11 · 1 World Bank Loan of Jinzhou City, Yixian Urban Area Central Heating Pipe

7

Construction nature: reorganization and expansion

Project investment and construction time: a total investment of 151,166,800 yuan,

which intends to use the $ 17.1 million from World Bank loan, the remaining will be self

collected.

The project construction period: April 2014 - November 2015;

October to December of 2013: preliminary design, design documents of part of the

construction and tender documentation;

January to March of 2014: bidding and tendering;

April to October of 2014: the construction preparation, construction of some newly

built, rebuilt level one network, newly built level two network, rebuilt level two network,

heat exchange stations civil works; newly built heat exchange station, building heat

exchange station, the additional water treatment equipment installation to the original heat

transfer station;

January to September of 2014: Part of the construction drawing design and bidding

and tendering;

March to September of 2015: Newly built level one network, heat exchange stations

civil works and equipment installation;

October of 2015: Equipment commissioning and trial operation;

November of 2015: put into operation and final acceptance.

3.3 CONSTRUCTION CONTENTS

The works include the newly built level one hot water network 17.02km, level two

hot water network 18.91km, 17 regional heat exchange stations, 10 building heat

exchange stations and 54 storied building heat meter installation experimental units;

transformation of level one network 7.29km and level two network 75.046km. The 10

building heat exchange stations and 54 building heat meter installation in Junyu Huating

Community (Phase II ) of this project are both the pilot project of World Bank Loan.

After the renovation and expansion by the project, the central heating (heat load

206.18MW) of the newly built and the original heating system with a total area of

3,850,300 m2 heating can be realized, and an area of 1,220,000 m

2 for heating is still

Page 10: Environmental Management Plan EMPdocuments.worldbank.org/curated/pt/678501468220510692/... · 2016-07-11 · 1 World Bank Loan of Jinzhou City, Yixian Urban Area Central Heating Pipe

8

available for the newly built level one network.The 17 newly built area heat exchange

stations in this project are all set with softened water equipment; the building heat

exchange station of Junyu Huating is adopted with the principle of the once network for

the secondary network, so no water softening facilities and softening tanks are installed.

The newly built heat exchange station in this project has the seating capacity of 9

people, 24 people in level one network, 19 people in the newly built level two network,

and the transformation of level two network is included in the original project with a total

of 52 people added.

The composition and size of the project is shown in Table 3-1.

Table 3-1 Composition and size of the project

No. Project content scale Remark

1 Level 1 hot water network 24.31km

1-1 Newly built Level 1

network

17.02km

1-2 renovation and expansion

level 1 network

7.29km

2 Level 2 hot water network 93.956km

2-1 Newly built Level 2

network

18.91km Supporting with 782,000 m2 heating area

2-2 renovation and expansion

level 2 network

75.046km Original heating area of 1,302,600 m2

3 heat exchange station 27 buildings 17 are newly built (including the 4

transformed boiler rooms)

3-1 Newly built heat

exchange station 17 buildings

1,702,000 m2 heating area, 2 softened water

treating cylinders will be set for each heat

exchange station, one for use one for

backup

3-2 Newly built building heat

exchange station

10 buildings 43 000 m2 heating area

4 Building heat meter

experimental unit

54 areas existing area provided by 7# agricultural

machinery heat exchange station

3.4 POLLUTANT EMISSIONS IN THIS PROJECT

1. Noise

Most of the heat exchange stations drafted to be transformed and newly built in the

project are located in residential areas at noise-sensitive points, and the equipment noise

generated by heat exchange station may have some impact on the surrounding residents.

2. Wastewater

The 17 newly built heat exchange stations in the project are set with softened devices

Page 11: Environmental Management Plan EMPdocuments.worldbank.org/curated/pt/678501468220510692/... · 2016-07-11 · 1 World Bank Loan of Jinzhou City, Yixian Urban Area Central Heating Pipe

9

with the water filling quantity of 102m3/h, and will generate wastewater 15.3 m

3/h, and

the annual drainage is of 54713m3 / a, it is discharged into the Yixian urban sewage

treatment plant (Yixian Beikong Water Service Co., Ltd.) through the municipal pipe

network.

Table 3-2 Wastewater Quantity Generated during Operations Period

Emission

sources

wastewater

(m3/a)

Name of

pollutant

emission

concentration

(mg/L)

Emission load

(t/a)

Emission

behavior

Water

softening

devices

54713

CODCr 100 5.47 Discharge

into Yixian

urban

sewage

treatment

plant

through

municipal

pipe

network

ammonia

nitrogen 5 0.27

The project is added with the capacity of 52 people, and there will be domestic

sewage. Daily domestic water consumption is 5.2m3, and the sewage generated daily is

3.64m3 and the sewage is discharged into Yixian sewage treatment plant (Yixian Beikong

Water Service Limited Company) through municipal sewage pipe network.

Table 3-3 Domestic Sewage Quantity Generated during Operations Period

Emission

sources

wastewater

(m3/a)

Name of

pollutant

emission

concentration

(mg/L)

Emission load

(t/a)

Emission

behavior

Staff 1329

CODCr 240 0.32 Discharge into

Yixian urban

sewage

treatment plant

through

municipal pipe

network

BOD5 150 0.20

ammonia

nitrogen 25 0.03

3. Solid Waste

After completion of the project, the labor quota of 52 people will be increased, and

there will be garbage generation with the quantity of 19t/a.

3.5 ALTERNATIVE SOURCE

After the project is completed, five boilers and four small chimneys ( built in 2008 ~

2009 ) of four boiler rooms in Sunny Garden, Xinghua Garden, Happiness Garden and

Vocational High School will be dismantled. The heating areas of the above small boilers

Page 12: Environmental Management Plan EMPdocuments.worldbank.org/curated/pt/678501468220510692/... · 2016-07-11 · 1 World Bank Loan of Jinzhou City, Yixian Urban Area Central Heating Pipe

10

are over 0.34 million m3, if central heating via heat plant is conducted, the heating

efficiency will be increased, and thus reduce coal burning of 3596t/a. Therefore, the

reduction of 3596t/a of fuel coal can result to the reduction of emission of sulfur dioxide at

86t/a, nitrogen oxides 55t/a and fume 50t/a.Huge improvement will be rendered to the

quality of the air and environment in Yixian urban area. The land left at the location of the

original small boiler room can be used to build greenbelt of other municipal public

facilities, which can improve the regional environment, and bring a certain degree of

social benefits for the Yixian County as well.The problems of burning coal cinder dust,

waste water, coal storage yard and boiler room noise nuisance resulted from the boiler

room can all be solved. The demolition plan for the small boilers is shown in Table 5-3.

3.6 HEAT PLANT

The central heating souce Jinzhou Guanda Heating Power Co., Ltd. is located in

Houyang Village, Chengguan Township, Yixian County, which covers an area of 35,000

m2, currently it has 43 regional heat exchange stations (including a heat exchanger station

within heating source plant), and the heating capacity is 215MW, with two sets of 70MW

(2 × 100t / h), 1 set of 46MW (65t / h), 1 set of 29MW (40t / h), where one set of 70MW

(100t / h) is used as a backup boiler currently, and the existing heating area is of 2,105,300

m2.For the central heating source projects, Jinzhou Municipal Environmental Protection

Bureau issued the "On the Official Reply of Environmental Impact Statement of Central

Heating Project in JunZhou Guanda Heating Power Limited Company in Yixian County"

(Letter of Environment In Jinzhou [ 2010 ] No. 74 ) in July 2010. The main pollutant

emission indicator and environmental measures of heat plants are as follows:

The 4 boilers in the heat plant share a 65m chimney; ceramic multi-tube dust cleaner

is used, and the dust removal efficiency is 95%; the lime- calcium sulfite method tower

wet desulphurization method is used with the desulphurization efficiency ≥ 90%; dust and

SO2 concentration is controlled by the II standard time limit control in "boiler air pollution

free emission standard"(GB13271-2001) (dust emission concentration 200mg/m3; SO2

900mg/m3), ringelman emittance is less than level I, coal with ash content <25%, sulfur

content of < 0.85% should be used; fully enclosed coal yard should be used, surrounded

wind wall should be used, and top is set with the tent and mist spray system , coal

Page 13: Environmental Management Plan EMPdocuments.worldbank.org/curated/pt/678501468220510692/... · 2016-07-11 · 1 World Bank Loan of Jinzhou City, Yixian Urban Area Central Heating Pipe

11

handling system uses a fully enclosed corridor; the waste water produced by boiler river

sewage water treatment chemicals should be used in desulfurization and ash washed up

water, and domestic sewage is treated in Yixian sewage treatment plant after discharged

into septic tank treatment after processing through an urban water supply network; all the

boiler ash produced shall be subject to the comprehensive utilization by Jinzhou Yulian

building Materials Co., Ltd., a subordinate enterprise of Jinzhou Guanda Heating Power

Co., Ltd. ( production of hollow bricks ); temporary ash is stored in yard with seepage and

anti- dust measures; noise equipment must be installed in the plant with damping, isolation

sound, noise reduction measures; coal factory vehicle access is prohibited horning so that

factory noise standards can be reached.

The heat plant passed the acceptance of environmental protection for the completed

construction projects organized by administrative department of environmental protection

in March 2013.Heat plant is set with located gas-line device, and is currently applying for

environmental protection acceptance.According to the completion and acceptance contents

of heat plant environmental monitoring report, the total heat control pollutants allowable

in total plant emissions are: SO2 95.19t/a, dust 104.48t/a; actual emissions: SO2 94.01t/a,

dust 89.89t/a, which are less than total control indicators. Concentration of pollutant

emissions to the atmosphere is: SO2 177mg/m3, dust 169.9mg/m

3.

Table 3-4 comparison list of the relevant flue gas emission standards (mg/m3)

Pollutants

World Bank thermal

power plants

Environmental,

Health and Safety

Guidelines (EHS)

GB "boiler air

pollutant emission

standard"

(GB13271-2001)

Jinzhou Guanda

Heating Power Co.,

Ltd

sulfur dioxide 400 900 177

Particles (TSP) 30 200 169.9

The concentrations of SO2 and dust emissions in heat plant have both met the

requirements of national standard "boiler air pollutant emission standard"

(GB13271-2001).The concentration of SO2 emission has met the requirements of World

Bank thermal power plants Environmental, Health and Safety Guidelines (EHS), but the

dust emission concentration is higher than the requirements of World Bank thermal power

plants Environmental, Health and Safety Guidelines (EHS).Currently, the ceramic

multi-tube dust cleaner with the collection efficiency of 95 % is used in Guanda Heating

Power Plant; if dust removal system transformation is carried out as per the reference of

Page 14: Environmental Management Plan EMPdocuments.worldbank.org/curated/pt/678501468220510692/... · 2016-07-11 · 1 World Bank Loan of Jinzhou City, Yixian Urban Area Central Heating Pipe

12

EHS standards, greater investment and increased operating costs will be rendered though,

and the implementing is much more difficult considered from the economic perspective.

4 Environmental Impact Analysis The negative environmental impacts of the project are summarized in this chapter,

and the information comes mainly from the environmental impact report in this project.

4.1 STATUS OF ENVIRONMENTAL QUALITY

( 1 ) Ambient Air Quality

According to 2012 Annual Report on Environmental Quality of Yixian, Yixian urban

ambient air quality is as follows:

Annual average of sulfur dioxide in Yixian County is 0.033mg/m3, which reached the

Level 2 Standard in "Ambient Air Quality Standard" (GB3095-2012).

Annual average of nitrogen dioxide in Yixian County is 0.064mg/m3, which exceeded

the 0.6 time of Level 2 Standard in "Ambient Air Quality Standard" (GB3095-2012).

Annual average of PM10 in Yixian County is 0.098mg/m3, which exceeded the 0.4

time of Level 2 Standard in "Ambient Air Quality Standard" (GB3095-2012).

The peak concentrations of the above main atmospheric pollutants mainly appear in

winter, which has a certain relation with the scattered small heating boilers within the city,

and the relatively higher nitrogen dioxide in each month throughout the year may be

associated with the increasing of motor vehicle exhaust emissions.

( 2 ) Quality of Acoustic Environment

Sound quality of the environment was measured by Yixian environmental monitoring

stations from 22 July 2013 to 23 on the status of the noise in Yixian; the measurements

was carried out once at day and night respectively, which was 10:00 at daytime, and 22:00

at night. Noise monitoring results are shown in Table 4-1.

Status value of each noise monitoring sites can meet the standards of "Environmental

Quality Standard" (GB3096-2008).

Page 15: Environmental Management Plan EMPdocuments.worldbank.org/curated/pt/678501468220510692/... · 2016-07-11 · 1 World Bank Loan of Jinzhou City, Yixian Urban Area Central Heating Pipe

13

Table 4-1 Status of noise monitoring results

N

o.

monitoring

locations standard dB (A) noise dB (A) on July, 22 noise dB (A) on July, 23

1 Sunny Garden

Community

daytime 60,

nighttime 50

daytime 53.8, nighttime

43.9

daytime 53.6, nighttime

44.1

2 Xinghua Garden

Community

daytime 60,

nighttime 50

daytime 51.1, nighttime

42.8

daytime 52.6, nighttime

43.1

3

Happiness

Garden

Community

daytime 60,

nighttime 50

daytime 54.2, nighttime

43.5

daytime 53.9, nighttime

43.7

4 vocational high

school

daytime 55,

nighttime 45

daytime 52.7, nighttime

42.1

daytime 53.1, nighttime

41.8

5 Longteng

Garden

daytime 55,

nighttime 45

daytime 53.5, nighttime

43.2

daytime 52.1, nighttime

44.3

6 Shuxin Garden daytime 60,

nighttime 50

daytime 52.8, nighttime

40.4

daytime 50.9, nighttime

40.0

7 National Tax

Bureau

daytime 55,

nighttime 45

daytime 53.9, nighttime

43.8

daytime 51.8, nighttime

42.0

4.2 ENVIRONMENTAL IMPACT ANALYSIS DURING

CONSTRUCTION PERIOD

( 1 ) Atmospheric Environmental Impact Analysis

The dust generated in the construction is a major air pollution environmental problem,

it mainly generated in earthwork excavation, piling, material transport, road demolition,

earthwork backfilling, pavement restoration and during vehicle transport; fuel emissions

produced in the construction machinery, and the main emitted pollutants are CO, NO2.

In the construction site with the wind speed ≥ 3.5m /s and relative humidity ≤ 60%,

the dust impact strength and scope is listed in Table 4-2.

Table 4-2 Impact Degree and Scope of Construction Dust

field distance m 10 20 30 50 100

Dust concentration

in mg/m3

10.14 2.89 1.15 0.86 0.61

Construction site dust is mainly produced by transport vehicles, accounting for 60%

of total dust, and is related to the road surface and the speed of the vehicle; under normal

circumstances, the impact scope of construction site and construction of roads under the

effect of natural wind is within the range of 100m.

During the construction, the road with the vehicle driving should be sprayed with

water to suppress dust, which can reduce dust by 80 %. The dust impact after the

construction site dust suppression sprinkler is shown in Table 4-3.

Page 16: Environmental Management Plan EMPdocuments.worldbank.org/curated/pt/678501468220510692/... · 2016-07-11 · 1 World Bank Loan of Jinzhou City, Yixian Urban Area Central Heating Pipe

14

Table 4-3 Dust impact after the construction site dust suppression sprinkler

field distance m 10 20 30 50 100

Dust concentration after

watering in mg/m3

2.01 1.40 0.67 0.27 0.21

Table 4-3 shows that the watering on the construction site and roads for transport can

effectively prevent dust, and the dust concentration in the 50m is of 0.27mg/m3, which can

meet environmental standards.

Due to the shorter construction period, and under the circumstance that the

construction unit took the above measures in the construction process, the impact of

construction dust on surrounding residents is smaller. And with the end of the construction

period, dust impact will disappear.

(2)Water Environmental Impact Analysis

Sewage generated by construction workers on site is the main sources of water

pollution during the construction period of the project. For the different stages of the

construction period, the construction numbers typically ranges from dozens of people; if it

is calculated by 50L / person • d for the daily domestic water consumption of construction

workers, and the amount of sewage generated is calculated as 80% of the total water

consumption, then the average person discharge sewage is 40L / person per day. CODcr

generated by analogy was 240mg / L, BOD5 was of 150mg / L, ammonia was of 25mg / L.

During the peak construction, the project construction site sewage and pollutant emissions

per day are shown in Table 4-4.

Table 4-4 Domestic Sewage and Pollutant Emissions of Construction Staff

Construction workers

(max) (person)

water

consumption

(t/d)

wastewater

volume (t/d) CODcr(kg/d) BOD5(kg/d)

ammonia

nitrogen

(kg/d)

110 5.5 4.4 1.06 0.66 0.11

If the above domestic sewage is directly discharged, it will pollute the water

environment where the area is; therefore, construction workers should try to take

advantage of nearby health facilities, canteens sewage settling ponds of oil removal and so

on, due to the short construction period, basically no impact will be imposed to water

environment where the area is.

( 3 ) Solid Waste Environmental Impact Analysis

The solid waste generated during the construction period of the project are mainly

Page 17: Environmental Management Plan EMPdocuments.worldbank.org/curated/pt/678501468220510692/... · 2016-07-11 · 1 World Bank Loan of Jinzhou City, Yixian Urban Area Central Heating Pipe

15

domestic waste generated by construction workers, and the construction waste generated

during the construction period, such as packaging bags, construction scraps and waste heat

network cables etc.The domestic waste is processed at the urban waste yard after waste

collection. The packaging bags, construction scraps and waste heat recovery network

cables shall be recycled by the construction unit.

In this project, the excavation earthwork is 38×104m

3, and backfill earthwork is

34×104m

3 and the excess earthwork is 4×10

4m

3. Currently, many real estates in Yixian are

under construction, which demands for larger earthwork; and the excavated spoil in this

project will be used as construction fill, which will not be discharged.

The small boiler as a replacement in this project was built in from 2008 to 2009, when

asbestos is no longer used as an insulation material, but the old pipeline was built in the

1990s, as part of it still use the asbestos as the insulation materials, a series of measures

should be taken to prevent an impact on the environment caused by the asbestos removal,

as shown in Table 5-1. When asbestos materials are found in removing small boilers, it

should also process as the disposal method of asbestos in accordance with Table 5-1.

All solid waste generated during the construction period of the project can be

effectively recycled or disposed of, which causes less impact on the environment.

( 4 ) Acoustic Environmental Impact Analysis

During the construction period, the main machinery such as the excavators, rollers

and trucks will produce loud noise. The noise of main construction machinery and

equipment is shown in Table 4-5.

Table 4-5 Noise of main construction machinery and equipment

No. Name of construction equipment average noise level 10m from the equipment

[dB (A)]

1 Excavator 82

2 bulldozer 76

3 cranes 82

4 Road Rollers 82

5 heavy trucks 85

Construction noise impact on the surrounding area acoustic environment should be

evaluated by using the "Construction Site environmental noise emission standard"

Page 18: Environmental Management Plan EMPdocuments.worldbank.org/curated/pt/678501468220510692/... · 2016-07-11 · 1 World Bank Loan of Jinzhou City, Yixian Urban Area Central Heating Pipe

16

(GB12523-2011); and the standard value is daytime 70dB (A) and nighttime 55dB (A).

Take the heavy-duty trucks in Table 4-5 for example, which has the highest noise level,

the situation of its reduced operating noise after the distance is increased, as shown in

Table 4-6.

Table 4-6 Attenuation values of Construction Noise with the Distance

Distance (m) 1 10 50 100 150 200 300 400 500

Noise level [dB

(A)] 85 65 51 45 41 39 35 33 31

The noise generated by construction will have a greater impact on the first row of

buildings of residential areas, school, along the road construction pipes which are near the

heat exchange stations. To prevent construction noise impact on residents at nighttime,

construction at nighttime is prohibited at noise sensitive areas of residential areas and

hospitals etc; known from the calculation of the results in Table 4-6, the exceeding area of

daytime construction machinery noise is within 10m. In addition, the construction period

of the project is relatively shorter; the using time of various types of construction

machinery is also shorter. With the end of the construction, the impact on the environment

will disappear, therefore, the impact on the acoustic environment caused during the

construction period of the project is less.

( 5 ) Traffic Impact Analysis

The impact on traffic caused by the project during its construction period is mainly

reflected in the construction part of the pipeline, which is shown in the following three

aspects:

Broken pipeline construction road will hamper traffic;

The excavation of earth piled up and roads will hamper traffic;

The increase of transport vehicles will increase the traffic on the road.

Pipeline construction will cause some impact on road traffic, although the stage

construction methods can be adopted, some earthwork in the construction process still

needed to be temporarily piled up, which will pose impact on traffic along the road of

pipeline construction. When the pipeline pass through the road, the slotting method should

be adopted for non-main road, and it’s easy to make the vehicles on the road blocked,

Page 19: Environmental Management Plan EMPdocuments.worldbank.org/curated/pt/678501468220510692/... · 2016-07-11 · 1 World Bank Loan of Jinzhou City, Yixian Urban Area Central Heating Pipe

17

which will pose a greater impact on traffic conditions, but the average construction time of

the pipeline crossing the road is no more than seven days, so the impact of pipeline

construction on traffic should be controlled within 7 days. The pipeline laying in this

project is carried out mainly on the sidewalk with closed construction, and then no vehicle

diversion or obstruction would occur, which would not pose affect on the road traffic.

However, the construction time should be reduced, and the residents should walk

frequently on the road and residential areas as possible to prevent interference of residents

going out. For the impact on the street shops and pedestrians, the temporary access and

exit can be set with the timely public announcement of bypassing, and enclosure should be

set to protect the safety of pedestrians.

The traffic amount in this project is not big, and there’s no centralized transportation,

so little impact will be caused on city traffic.

( 6 ) Ecological Impact Analysis

The designed excavation width of pipeline is 2.5m, and pipeline construction

temporary occupation of land is about 29.5hm2, both are open space and sidewalks along

both roads. The construction process does not destroy the green space, due to the short

construction period, the land occupation is temporary, after the end of construction, the

situation of land occupation will come to an end. All pipes are laid under the ground,

without passing through the sensitive environmental goals such as the scenic spots, nature

reserves and so on.

Among the newly built 27 heat exchange stations (including 10 heat exchange

stations) in this project, 11 of which are proposed to set up in the buildings, and the other

16 heat exchange stations take a land occupation of about 2600m2, and the occupation is

mainly the unused land near the school and the newly built community.

After the completion of the project, the greening and beautification work around heat

exchange station should be done; should the vegetation is destroyed in the construction, it

should be restored to its original appearance after the end of the construction period as

soon as possible.

( 7 ) Pipeline Risk Analysis

Pipeline construction is located in one side of the city trunk roads, and municipal

pipe network are under both sides of the ground (water and drainage network).The main

Page 20: Environmental Management Plan EMPdocuments.worldbank.org/curated/pt/678501468220510692/... · 2016-07-11 · 1 World Bank Loan of Jinzhou City, Yixian Urban Area Central Heating Pipe

18

risk factors during the construction period are improper construction, resulting in breakage

of the municipal pipe network and leaks thereafter. Currently, there is no gas pipeline

network in Yixian County, so the construction will not bring the environmental risks of

gas pipeline leakage.

Prior to the construction, the construction program should be confirmed with the

municipal water and sewer pipe network management departments to ensure that the

heating pipe network construction would not affect it.

( 8 ) Impact Analysis of Pipeline Across the River

The pipeline construction project would pass through 3 sections of the artificial river,

in which one is erected along the bridge bottom, and two are adopted with the river

excavation method. Artificial river is the flood control project for the Daling River in

Yixian. The river length is 5080m, at present, the urban section is undergoing the

comprehensive management project, and the river sections through which the project will

pass is currently in the dry state. If the river way is excavated when there is water in the

river, the slurry produced will have an adverse impact on the artificial river water, but also

a certain extent on the river sediment and aquatic organisms in rivers and ecological

environment. At this time, rivers closure should be made to assure no impact would be

rendered to the water. Construction time should be selected in the winter or dry season,

which can reduce the impact of construction on the river and aquatic organisms. In

addition, the construction process time should be minimized in the river.

4.3 ENVIRONMENTAL IMPACT ANALYSIS DURING

OPERATION PERIOD

Acoustic Environmental Impact Analysis

Most of the heat exchange stations drafted to be transformed and newly built in the

project are located in residential areas at noise-sensitive points, and the equipment noise

generated by heat exchange station may have some impact on the surrounding residents.

Noise pollution control measures to be taken in heat exchange stations are listed as

follows:

Page 21: Environmental Management Plan EMPdocuments.worldbank.org/curated/pt/678501468220510692/... · 2016-07-11 · 1 World Bank Loan of Jinzhou City, Yixian Urban Area Central Heating Pipe

19

All heat exchange stations are required to select high-quality low-noise equipment,

and the noise source strength of building heat pump station shall not exceed 55dB

(A);

Noise equipment should not be connected with building body;

The damping foundation base should be done, and shock absorbers should be installed

to reduce sound transmission from vibration; pump inlet and outlet should be

connected with a rubber hose; additional concrete base should be set at the bottom of

the heat exchanger unit, and additional damper should be set between the base and the

ground and the walls to eliminate the impact of low frequency sound outside the

structure.

( 1 ) statistics of status quo of the acoustic environment around heat exchange stations

The project includes 17 newly built regional heat exchange stations and 10 building

heat exchange stations at Junyu Huating Community, which is intended to use the location

of existing four demolished boiler rooms to build 2 #, 3 #, 4 # , 17 # region heat exchange

stations.

Noise would be generated in the process of heat exchange stations running, which

would pose impact on the surrounding environment sensitive points within a certain

range.17 regional heat exchange stations and 10 building heat exchange stations of Junyu

Huating Community in this project area are planned to be built in the vicinity of

residential and office buildings, among which, 9 of the building heat exchange stations in

10 of Junyu Huating Community are set in residential buildings, one is in the integrated

building of the community (complex building includes distribution room and property

management office). For these unbuilt heat exchange stations, the EIA shall propose

control requirements concerning the distance and construction form between the heat

exchange stations and noise-sensitive buildings.

( 2 ) Noise Prediction at Heat Exchange Stations

1 ) Statistics of noise emission sources strength

According to heating area and building height of various heat exchanger stations, the

heat exchanger unit types in this project will be divided into three kinds, each heat

exchanger unit noise equipment is: 1, three circulating pumps and one constant pressure

Page 22: Environmental Management Plan EMPdocuments.worldbank.org/curated/pt/678501468220510692/... · 2016-07-11 · 1 World Bank Loan of Jinzhou City, Yixian Urban Area Central Heating Pipe

20

water pump station (Newly built 7 #, 16 #); 2, two circulating pumps and one constant

pressure water pump station (Newly built # 1 , # 2, 6 #, 9 #, 10 #, 11 #, 12 #, 13 #, 15 #,

and # 2); 3, one circulating pump and one constant pressure water-make up pump (newly

built 3#, 4#, 5 #, 8 #,14 #, and 17 # )."Cold standby" mode shall be used for both the water

circulating pump and constant pressure water make-up pump for each heat pump station,

that is the water circulating pump and constant pressure water make-up pump of the same

type will be stored in the station respectively as a backup. According to analog data

provided by equipment manufacturers, after taking damping measures, interior noise

source strength when the noise devices are operating is shown in Table 4-7, and the

outdoor noise sources strength is shown in Table 4-8.

Table 4-7 Indoor Noise Source Strength of Devices unit:dB(A)

No. main noise

equipment

measuring point

distance (m)

noise

reduction

measures

noise reduction

effect noise level

1

circulating pump

at regional heat

exchange station

1

measure of

vibration

mitigation 10~15 80

2

constant pressure

water make-up

pump at regional

heat exchange

station

1

measure of

vibration

mitigation 10~15 80

3

circulating water

pump at building

heat exchange

station

1

measure of

vibration

mitigation 10~15 55

Page 23: Environmental Management Plan EMPdocuments.worldbank.org/curated/pt/678501468220510692/... · 2016-07-11 · 1 World Bank Loan of Jinzhou City, Yixian Urban Area Central Heating Pipe

21

Table 4-8 Exterior noise source strength of devices units Unit: dB(A)

Source strength

equipment and number of

main source of noise during

operation period

Sound level at 1m

(L1) of indoor

maintenance

structure

Sound level at 1m (L2)

of outdoor maintenance

structure

heat exchanger units of

regional heat exchange

station

1 set of circulating pump

station

1 set of constant pressure

water make-up pump

station

83 63

2 sets of circulation pump

1 set of constant pressure

water make-up pump

station

85 65

3 sets of circulating pump

stations

1 set of constant pressure

water make-up pump

station

86 66

heat exchanger units of

building heat exchange

station

1 set of circulating pump

station 55 40

2 ) Prediction Method

① Sound Pressure Level (SPL) of outdoor sound source at prediction point

Loct®= Loct(r0)-20lg(r/r0)-△Loct

Where: Loct®、Loct(r0)—SPL at the distance of sound sources of r, r0, dB;

r、r0—distance of prediction point to sound source, m;

Loct—various decrement, dB.

If the octave frequency band sound power level of the known sound source is Lwoct,

and the sound source can be seen as located on the ground, then

Loct®= Lwoct-20lgr0-8

② SPL of an indoor sound source near the envelope structure

Loct,1=Lwoct+10lg(2

4 r

Q

+

R

4)

Where : Loct,1—SPL generated near the envelope structure of an indoor sound

source, dB;

Lwoct—Sound power level of a sound source, dB;

r1—the distance of an indoor sound source to the location near the envelope

Page 24: Environmental Management Plan EMPdocuments.worldbank.org/curated/pt/678501468220510692/... · 2016-07-11 · 1 World Bank Loan of Jinzhou City, Yixian Urban Area Central Heating Pipe

22

structure, m;

R—Room constant, R=

1

S;

S—Interior total surface area, m2;

—average absorption coefficient, =S

qS i;

Q—directivity factor.

③equivalent outdoor sound level

The sound level of the outdoor Loct,2(T)and acoustic transmission area is converted

into the equivalent outdoor sound cources, and the sound power level Lwoct of the

equivalent sound source can be calculated.

Lwoct=Loct, 2(T)+10lg(S)

Where: S—acoustic transmission area, m2。

④sound level generated at the prediction point of equivalent outside sound source

Loct(r)=Lwoct–20lg(r)-△Loc

Where: Loct(r)—sound level generated at the prediction point of equivalent outside

sound source, dB;

r—distance of prediction point to the sound source, m;

Loc—decrement caused by various factors, dB.

⑤formula for predicted noise value at evaluation point

)1010lg(101

1.01.0

n

i

LiLL 本

Where: L——evaluation point noise prediction point, dB(A);

Lbackground——noise background value at evaluation point, dB(A);

Li——impact value of i sound sources to the evaluation point, dB(A).

3 ) Environmental Protection Measures Taken

To reduce the noise generated by heat exchange station during operation period, all

the noise equipment of circulation pumps and water make-up pumps for 17 newly built

regional heat exchange station of the project are arranged under the ground; according to

Page 25: Environmental Management Plan EMPdocuments.worldbank.org/curated/pt/678501468220510692/... · 2016-07-11 · 1 World Bank Loan of Jinzhou City, Yixian Urban Area Central Heating Pipe

23

the analogy analysis, if the noise equipment is arranged under the ground, then the noise

source strength at heat exchange station can be reduced of 25dB (A). In addition, among

10 newly built building heat exchanger stations, one is set up in the complex building

(complex building includes distribution room and property management office) of the

community proposed to be built, heat exchange stations are set up in the position more

than 15m from residential buildings; and the heat exchanger units of the other nine

stations buildings are set up in the first floor of each residential building; according to the

current architectural design, the first floor residential building is the garage or shop to

prevent noise impact on residents; the rock wool board of the internal and external walls

of heat exchange station and the room top will be thickened one time, and

sound-absorbing composite panels of the size 2 × 15mm will be added to the top of the

room and internal walls; sound-absorbing composite panels of the size 1 × 15mm for the

external walls and insulation board of 70mm will be set outside the building with the

installation of soundproof windows and doors, and the sound level at 1m outside the

structure of the outdoor maintenance should be controlled at the level ≤ 35dB (A).。

4 ) Acoustic environmental impact analysis of heat exchange station

Under the condition that the noise source of regional heat exchange station is set

under the ground and noise reduction measures have taken for the 1 # to 9 # building heat

exchange station rooms, and the noise source strength statistics is shown in Table 4-9.

Page 26: Environmental Management Plan EMPdocuments.worldbank.org/curated/pt/678501468220510692/... · 2016-07-11 · 1 World Bank Loan of Jinzhou City, Yixian Urban Area Central Heating Pipe

24

Table 4-9 noise source strength of heat exchange station after noise reduction measures

Source strength

Main noise equipment and

number during operation

period

Sound level at 1m

(L1) of indoor

maintenance

structure

Sound level at 1m (L2)

of outdoor maintenance

structure

heat exchanger units of

regional heat exchange

station

1 set of circulating pump

station

1 set of constant pressure

water make-up pump

station

63 38

2 sets of circulating pump

stations

1 set of constant pressure

water make-up pump

station

65 40

3 sets of circulating pump

stations

1 set of constant pressure

water make-up pump

station

66 41

heat exchanger units of

building heat exchange

station

1 set of circulating pump

station 55 ≤35

Table 4-9 shows that after the noise equipment is set under the ground, the noise

contribution values at the heat exchange stations to the ambient environmentally sensitive

construction can both meet the daytime and nighttime values Class 1 standard in acoustic

environment; after the measures of thickening of walls and floor slabs, installation of

sound-absorbing materials as well as sound insulation windows and doors for the building

heat exchange station installed in 9 residential buildings, there is basically no impact on

the residents.

Table 4-8 shows that, sound level at 1m of 10 # station outdoor maintenance structure

of the building heat exchanger unit station is 35dB (A). By analogy analysis, if the

distance between the heat exchange station and residential buildings is more than 15m,

and considered from the perspective of vibration, noise etc, the impact on the residents

from the heat exchange stations are smaller.

The detailed environmental protection measures to be taken for the heat exchange

station are listed in Table 5.2.

( 3 ) Conclusion

On the basis of taking the above environmental protection measures of shock

absorption, noise reduction, the heat exchange station in this project would basically pose

Page 27: Environmental Management Plan EMPdocuments.worldbank.org/curated/pt/678501468220510692/... · 2016-07-11 · 1 World Bank Loan of Jinzhou City, Yixian Urban Area Central Heating Pipe

25

no impact on the sensitive buildings around the residential buildings during its operation

period.

2. Water Environmental Impact Analysis

The 17 newly built heat exchange stations in the project are set with softened devices

with the water filling quantity of 102m3/h, and will generate wastewater 15.3 m

3/h, and

the annual drainage is of 54713m3 / a, it is discharged into the Yixian urban sewage

treatment plant (Yixian Beikong Water Service Co., Ltd.) through the municipal pipe

network.

The project is added with the capacity of 52 people, and there will be domestic

sewage. Daily domestic water consumption is 5.2m3, and the sewage generated daily is

3.64m3 and the sewage is discharged into Yixian sewage treatment plant (Yixian Beikong

Water Service Limited Company) through municipal sewage pipe network.

Yixian urban sewage treatment plant was built in 2008, which treating mainly with

domestic sewage and industrial waste of Yixian County; the treatment scale of project in

Phase I is daily treatment of 15000m3, the factory covers an area of 54000m

2. The sewage

treatment plant passed the environmental protection acceptance in July 2010, and is

currently operating normally; Its main pollutant emissions can meet the standard limits

value of Class 1, A in national standard "Urban sewage treatment plant pollutant discharge

standard" (pH:6-9, CODcr: 50mg/m3, BOD5: 10mg/m

3, ammonia nitrogen 5mg/m

3,

SS10mg/m3). After investigation of the sewage treatment, the daily sewage treatment

capacity is 12000m3, which can achieve discharge standards and fully adapt the drainage

in this project.

3. Solid Waste Environmental Impact Analysis

After completion of the project, the labor quota of 52 people will be added, and there

will be waste generation at the amount of 19t/a; the domestic waste will be collected by

the sanitation department to the waste treatment plant for unified treatment.

Page 28: Environmental Management Plan EMPdocuments.worldbank.org/curated/pt/678501468220510692/... · 2016-07-11 · 1 World Bank Loan of Jinzhou City, Yixian Urban Area Central Heating Pipe

26

5 Environmental Impact Mitigation Measures In accordance with the environmental impact assessment documents and combined

with the characteristics of the project, and based on the analysis of pollutants emission for

the project during its construction and operation period, and based on different types of

pollutants, and environmental impact mitigation plan is made at different times as is

shown in Table 5-1 to table 5-3.

Page 29: Environmental Management Plan EMPdocuments.worldbank.org/curated/pt/678501468220510692/... · 2016-07-11 · 1 World Bank Loan of Jinzhou City, Yixian Urban Area Central Heating Pipe

27

Table 5-1 List of environmental impact mitigation measures during the construction period of the project

Stages Problems Mitigation Measures Mitigation Cost

(big or not) Responsible Unit Commencement Date

Construction

phase

noise

1. The construction plans and operations area

should be reasonably arranged, and construction at

night close to hospitals, residential areas and other

sensitive areas is prohibited.

2. Choose those low-noise construction

equipment.

3. For the nighttime construction in the business

district, it must apply to the People's Government

of Yixian and high-noise construction equipment

operating at night should be prohibited, and the

residents in the vicinity should be informed.

4. Construction equipment noise must meet the

requirements of "Construction Site Noise Limits

Value" (GB12523-2011), the requirement should

be included in the tender of construction unit.

5. Tracking and monitoring.

6. In the short distance from residential areas, the

construction segments should be effectively

blocked, such as erecting the construction fence.

7. Horns are prohibited for the transport vehicles.

150,000 Yuan

RMB

engineering

contractor

Jinzhou Guanda

Heating Power Co.,

Ltd and Yixian

Environmental

Protection Agency

dust

1. Formulate the sprinkler and dust suppression

system, in which regular watering every day

should be done to prevent dust in generation. In

dry and windy weather conditions, the watering

frequency and amount should be increased.

2. The closed fence with a height no lower than

stacking height should be set around the storage

yard of building materials.

3. At the entrances to the construction site, dirt

wheel washing facilities shall be provided to

protect vehicles from mud while driving away the

100,000 Yuan

RMB

Page 30: Environmental Management Plan EMPdocuments.worldbank.org/curated/pt/678501468220510692/... · 2016-07-11 · 1 World Bank Loan of Jinzhou City, Yixian Urban Area Central Heating Pipe

28

site.

4. For the bulk material transport, it shall be

transported in canned or covered with tarpaulin.

5. The concrete mixing station at construction site

must be equipped within the dust removing

facility.

6. At the construction site, the temporary storage

warehouse for bulk materials should be set up or

covered with dust net to eliminate bulk materials

stock in the open air.

7. The construction waste should be removed in

time, and incineration of waste at the construction

site is prohibited.

8. Fences should be set at construction site to

reduce the spread of the construction dust.

Traffic break off

The impact on the traffic due to network

construction should be controlled within 7 days.

The pipeline laying in this project is carried out

mainly on the sidewalk with closed construction.

Then, no vehicle diversion or obstruction will

occur, which does not affect road traffic.

60,000 Yuan

RMB

Passageway

construction/use

1. Interference of residents going-out: to reduce

construction time and residents should choose

those frequently walked road and residential areas

2. Impact on the street shops and pedestrians: set

up a temporary channel and exit and timely

inform the public to take the bypass; set enclosure

to protect the safety of pedestrians.

100,000 Yuan

RMB

Cultural relics

Should any cultural relics are found during

construction, then the construction should be

stopped and notify the related departments.

Moving of any artifacts is prohibited.

30,000 Yuan

RMB

Solid waste

The solid waste generated during the construction

period of the project are mainly domestic waste

generated by construction workers, and the

250,000 Yuan

RMB

Page 31: Environmental Management Plan EMPdocuments.worldbank.org/curated/pt/678501468220510692/... · 2016-07-11 · 1 World Bank Loan of Jinzhou City, Yixian Urban Area Central Heating Pipe

29

construction waste generated during the

construction period, such as packaging bags,

construction scraps and waste heat network cables

etc. The domestic waste is processed at the urban

waste yard after waste collection. The packaging

bags, construction scraps and waste heat recovery

network cables shall be recycled by the

construction unit. The earthwork construction

waste is used as the construction filling of other

projects, which will not be discharged to outside.

construction

wastewater

The wastewater sewage of construction workers

should be discharged into the city sewage

treatment plant via city underground water supply

network by making full use of the facility around.

Construction is prohibited in rainy days, and

appropriate measures shall be taken when piling

up the earthwork to prevent block the let-down

systems; oil spills should be prevented in

machinery equipment; arbitrary emission of

sewage to the outside is prohibited.

30,000 Yuan

RMB

insulation tube

The tender shall indicate that the used

pre-insulated pipe shall not contain the blowing

agent which is inconsistent with the commitment

of China in the "Montreal Protocol".

-

Affect the river

water quality and

flood discharge

capacity

Currently, there is no water in the river, if there is

water in the river way when construction is under

way, then river closure shall be conducted to

assure river water is not impacted. Construction

time should be selected in the winter or dry

season, which can reduce the impact of

construction on the river and aquatic organisms.

In addition, in the construction process, the

construction time in the river shall be minimized.

120,000 Yuan

RMB

Remove the old

small boiler pipe

120,000 Yuan RMB

1. The operator may participate in asbestos

engineering

contractor and

Page 32: Environmental Management Plan EMPdocuments.worldbank.org/curated/pt/678501468220510692/... · 2016-07-11 · 1 World Bank Loan of Jinzhou City, Yixian Urban Area Central Heating Pipe

30

network asbestos

insulation materials

removing after the inspection and meet the

protection requirements.

2. Warning signs should be set up at construction

site.

3. Watering before dismantling.

4. Before working, the removing personnel shall

wear dust proof masks and put on protective

clothing.

5. Develop specific programs and the removing

shall be conduct in the holistic demolishing

method.

6. Safety fences shall be set at operating point,

irrelevant personnel is prohibited in entering.

Professional and technical personnel shall be

designated for responsible for commanding the

site.

7. After the asbestos is removed, they should be

collected in sealed bags, and then put into the

dedicated asbestos cement sealed cans with

cement poured and cement tank sealed. And they

shall be transported to a qualified hazardous waste

landfill for permanent deep processing.

8. After the removal of asbestos, Shenyang

Zhenxing Solid Waste Disposal Co., Ltd is

responsible for collecting and processing, the

company has the qualification of disposing the

hazardous waste; should the asbestos were found

in the removal process of other projects, the

company shall also be responsible for the

collection of solid waste and treatment.

Shenyang

Zhenxing Solid

Waste disposal

Co., Ltd

ecology

Minimize the land occupation. The design should

be rational to narrow operation face width, which

will reduce the impact of vegetation and soil

structure to a minimum. During the construction

period, various construction machinery and

250,000Yuan

RMB

engineering

contractor

Page 33: Environmental Management Plan EMPdocuments.worldbank.org/curated/pt/678501468220510692/... · 2016-07-11 · 1 World Bank Loan of Jinzhou City, Yixian Urban Area Central Heating Pipe

31

equipment should be placed in strict accordance

with the design specified location without

arbitrary stacking. When digging the trench, the

excavated soil should be stacked on two sides of

the trench by surface soil (earth surface 10 ~

30cm) and subsoil, and covered to prevent water

erosion and soil erosion due to rain wash and

windy days; when the earth is backfilling, each

should be put back in its place, and the original

plant growth conditions should be kept as

possible. After construction, the greening planting

should be conducted of the surrounding areas of

heat exchange stations. Trees suitable for the

growth should be planted, and sowing and seeding

should be conducted.

others

The pipe laying should be combined with Yixian

municipal planning so as to avoid urban

environment pollution caused by the repeated

excavation; for the road sections of pipelines

laying, the burying situation of other underground

pipe network should be known in details, try to

avoid the damage to other municipal facilities due

to the construction of the project. Rainy season

should be avoided for the construction period.

50,000YuanRMB

Page 34: Environmental Management Plan EMPdocuments.worldbank.org/curated/pt/678501468220510692/... · 2016-07-11 · 1 World Bank Loan of Jinzhou City, Yixian Urban Area Central Heating Pipe

32

Table 5-2 List of environmental impact mitigation measures during the operation period of the project

Phases Problems Mitigation Measures

Mitigation

Cost

(big or not)

Responsible

Unit Monitoring unit

peration

phase

noise and

vibration of

heat exchange

station

1. All heat exchange stations are required to select high-quality

low-noise equipment, and the noise source strength of building heat

pump station shall not exceed 55dB (A);

2. Noise equipment should not be connected with building body;

3. The damping foundation base should be done, and shock absorbers

should be installed to reduce sound transmission from vibration; pump

inlet and outlet should be connected with a rubber hose; additional

concrete base should be set at the bottom of the heat exchanger unit,

and additional damper should be set between the base and the ground

and the walls to eliminate the impact of low frequency sound outside

the structure.

4. In order to prevent an impact on the nearby noise-sensitive

residential building caused by ground heat exchange station

operations, the noise equipment of circulating water pumps and water

make-up pumps for the newly built areas of 1 # to 17 # should be

placed under the ground. The noise equipment shall be arranged far

away from residential buildings and other sensitive buildings;

5. It is proposed that newly built Junyu Huating building heat

exchange station 10 # station should keep a minimum distance of 15m

with the residential areas;

6. # 1 to # 9 building heat exchange station are set up in the first floor

of residential buildings, the rock wool board of the internal and

external walls of heat exchange station and the room top will be

thickened one time, and sound-absorbing composite panels of the size

2 × 15mm will be added to the top of the room and internal walls;

sound-absorbing composite panels of the size 1 × 15mm for the

external walls and insulation board of 70mm will be set outside the

building with the installation of soundproof windows and doors;

7. The orientation and arrangement of windows and doors as well as

noise equipment of circulating pumps, water pumps should be kept

away from noise-sensitive buildings; noise equipment and building

1.97million

Yuan RMB

Jinzhou Guanda

Heating Power

Co., Ltd

Yixian

Environmental

Protection Agency

Page 35: Environmental Management Plan EMPdocuments.worldbank.org/curated/pt/678501468220510692/... · 2016-07-11 · 1 World Bank Loan of Jinzhou City, Yixian Urban Area Central Heating Pipe

33

body should not be connected , and vibration reduction measures shall

be taken to all the noise equipment of circulating pump stations and

constant pressure water make-up pumps in heat exchange station; the

vibration reduction foundation base should be done, and shock

absorbers should be installed to reduce sound transmission from

vibration; additional concrete base should be set at the bottom of the

heat exchanger unit, and additional damper should be set between the

base and the ground and the walls to eliminate the impact of low

frequency sound outside the structure.

8. The inlet and outlet of circulating pump and water make-up pump

should be connected with rubber hose to reduce noise.

9. Before the incoming of building heat exchange station pipes to the

building, the layout should be twined under the ground outside the

building to achieve the purpose of vibration reduction.

Domestic waste

of the work

staff

The domestic waste should be timely collected and sent to refuse

landfill of Yixian County.

50,000 Yuan

RMB/year

Domestic

sewage of the

work staff

It is mainly the staff domestic sewage, and the surrounding facilities

should be made full use to discharge into Yixian sewage treatment

plant through the municipal pipe network.

30,000 Yuan

RMB/year

Production

waste water

Wastewater generated by softening device of heat exchange station

should be discharged into Yixian sewage treatment plant through

municipal pipe network.

50,000 Yuan

RMB/year

Page 36: Environmental Management Plan EMPdocuments.worldbank.org/curated/pt/678501468220510692/... · 2016-07-11 · 1 World Bank Loan of Jinzhou City, Yixian Urban Area Central Heating Pipe

34

Table 5-3 Demolition plan for the small boilers

No. Name of boiler

room Place boiler capacity (t/h)

number

of units

Shut down

time

Responsible

unit

1 boiler room in

Sunny Garden

North of

Zhu Rui

Road

1×15+1×10 2 2015

People's

Government

of Yixian

2 boiler room in

Xinghua Garden

North of

Yingbing

Road

1×10 1 2015

3 boiler room in

Happiness Garden

South of

Ying Bin

Road

1×10 1 2015

4

boiler room in

Vocational High

School

East of Jin

Fu Road 1×6 1 2015

Total 296 9

Disposal methods of hazardous waste removal (asbestos-containing small boilers):

1.The operation personnel may participate in asbestos demolition after

inspection and meet the protection requirements.

2.Warning signs should be set up at construction site.

3.Watering before dismantling.

4.Before working, the removing personnel shall wear dust proof masks and put

on protective clothing.

5.Develop specific programs and the removing shall be conduct in the holistic

demolishing method.

6.Safety fences shall be set at operating point, irrelevant personnel is prohibited

in entering.Professional and technical personnel shall be designated for

responsible for commanding the site.

7.After the asbestos is removed, they should be collected in sealed bags, and

then put into the dedicated asbestos cement sealed cans with cement poured

and cement tank sealed.And they shall be transported to a qualified hazardous

waste landfill for permanent deep processing.

After the removal of asbestos, Shenyang Zhenxing Solid Waste Disposal Co., Ltd is

responsible for collecting and processing, the company has the qualification of disposing

the hazardous waste; should the asbestos were found in the removal process of other

projects, the company shall also be responsible for the collection of solid waste and

treatment.

Page 37: Environmental Management Plan EMPdocuments.worldbank.org/curated/pt/678501468220510692/... · 2016-07-11 · 1 World Bank Loan of Jinzhou City, Yixian Urban Area Central Heating Pipe

35

6 Environmental Monitoring Plan According to environmental monitoring plan, Yixian Environmental Monitoring

Station shall regularly prepare the monitoring reports and submit to the relevant

departments in order to facilitate the monitoring of the results of their audit.

1. The on-site monitoring, data analysis and statistics, monitoring reports shall be

responsible by Yixian Environmental Monitoring Station. Yixian Monitoring Station is

affiliated to Yixian Environmental Protection Agency (government agency), which is

responsible for routine monitoring of the quality of the local environment.

2. World Bank , municipal PMO, provincial PMO and external monitoring company,

owner (Jinzhou Guanda Heating Power Co., Ltd), Liaoning Provincial Environmental

Protection Bureau (government agency), Jinzhou Municipal Environmental Protection

Bureau and Yixian Environmental Protection Agency (government agency) shall be

responsible for receiving monitoring reports.

3. Jinzhou Guanda Heating Power Co., Ltd, shall be responsible for taking the

pollution mitigation measures during operation period; the construction unit shall be

responsible for the implementation of the pollution mitigation measures during

construction period, and shall be supervised by qualified environmental supervision

company (hired consulting firm).

See Table 6-1 to Table 6-2.

Page 38: Environmental Management Plan EMPdocuments.worldbank.org/curated/pt/678501468220510692/... · 2016-07-11 · 1 World Bank Loan of Jinzhou City, Yixian Urban Area Central Heating Pipe

36

Table 6-1 Heat exchange station construction environment monitoring plan

Stages Monitoring Object Monitoring Locations Monitoring

Methods Monitoring Frequency

Monitorin

g Cost

(0.01

million

Yuan)

Responsible

Unit

Monitoring

Unit

construction

phase of

newly built

heat

exchange

station

noise construction site

the nearest populated areas noise meter

monitor once a week during

the day or monitor when

received complaint

0.3

Engineering

contractors

Jinzhou

Guanda

Heating Power

Co., Ltd. and

Yixian

Environmental

Protection

Agency

dust construction site visual Monitor once a week at dry

and windy weather 0.05

Construction

workers domestic

wastes

construction site visual Once a month 0.02

Change of runoff

mode due to land

levelling

construction site visual Once a week, continuous

monitoring in rainstorm 0.05

Transportation road

construction and use

along the transportation

routes visual

Monitor once a week when

the passageway is under

construction and in use

Monitor one after the

completion of construction

0.05

Accidental

discovery of cultural

property

construction sites, along the

passageway construction-

anywhere of excavation

visual continuous

0.02

Operational

phase

noise

exterior wall if heat exchange

station or near residential

community (complaints)

noise meter Once in heating season or

receiving complaints 0.05

Jinzhou

Guanda

Heating

Power Co.,

Ltd

Yixian

Environmental

Protection

Agency Construction

workers domestic

wastes

Location of the hear

exchange station visual Once a week 0.05

Page 39: Environmental Management Plan EMPdocuments.worldbank.org/curated/pt/678501468220510692/... · 2016-07-11 · 1 World Bank Loan of Jinzhou City, Yixian Urban Area Central Heating Pipe

37

Table 6-2 Heating pipe network environment monitoring plan

Stages Monitoring Object Monitoring

Locations

Monitoring

Methods

Monitoring

Frequency

Monitoring

Cost (0.01

million

Yuan)

Responsible

Unit Monitoring Unit

Construction

phase

noise

At the road of

pipeline

the nearest

populated

areas

noise meter

Monitor each week in

the daytime , Monitor

once or after

receiving complaints

0.3

Engineering

contractor

Yixian

Environmental

Protection Agency

and Jingzhou

Guanda Heat Co.,

Ltd.

dust Pipeline

passage visual

Monitor once a week

at dry and windy

weather

0.05

Traffic break off

Pipeline

passage

Along the

commercial

network

visual weekly 0.05

Passage construction

and use

Along the

passage visual

Monitor once a week

when the passageway

is under construction

and in use Monitor

one after the

completion of

construction

0.05

vegetation deterioration Along the

pipe network visual

Monitor once each

week during

construction period

Monitor one after the

completion of

construction

0.02

Page 40: Environmental Management Plan EMPdocuments.worldbank.org/curated/pt/678501468220510692/... · 2016-07-11 · 1 World Bank Loan of Jinzhou City, Yixian Urban Area Central Heating Pipe

38

Cultural property

Pipeline

passage

Anywhere

excavated

visual

Monitor once a week

at dry and windy

weather

0.02

Removal of

non-hazardous waste

(stones, etc)

Dumping site visual

Twice or three times

during demolition

period

0.02

The chemical property

of foam foaming agent

of insulation tube

comply with China's

commitments in the

"Montreal Protocol"

When the

insulation

tubes arrived

at site

review of the

technical

specifications in

delivery

document

Conduct once when

the insulating tubes

are delivered

0.01

Construction workers

domestic wastes

construction

site visual construction site 0.02

Page 41: Environmental Management Plan EMPdocuments.worldbank.org/curated/pt/678501468220510692/... · 2016-07-11 · 1 World Bank Loan of Jinzhou City, Yixian Urban Area Central Heating Pipe

39

7 Training Programme

For the successful and effective implementation of the project, training of

environmental knowledge and skills shall be conducted for all employees, in

particular, construction personnel. In addition to the interpretation of importance of

the proposed project and the significance of implementation to all the staff, then

training with different emphases targeted for staff at different positions should also be

conducted; the training should be carried out in the methods specifically based on

different environmental management layers and the importance of environmental

protection positions, and the specific training program is shown in Table 7-1.

Table 7-1 Environmental Protection Technician Training Program

Personnel Training content Method

Number

of

People

Time

(day)

Cost (0.1

million)

Renminbi

Construction

phase

Construction

environmental

protection staff

Environment basic

theory and

monitoring

methods, preparing

monitoring reports,

position training,

and project

environmental

management plan

Domestic

Training 8 2 4

Construction

period

Environment

Supervisors

Environmental

protection

regulations,

construction

planning,

environmental

monitoring

standards and

norms, as well as

domestic project

environmental

management plan

Domestic

Training 4 2 12

Page 42: Environmental Management Plan EMPdocuments.worldbank.org/curated/pt/678501468220510692/... · 2016-07-11 · 1 World Bank Loan of Jinzhou City, Yixian Urban Area Central Heating Pipe

40

Operation

period

Environmental

Operations staff

of operation

period

environmental

protection

regulations and

project

environmental

management plan

Domestic

Training 2 1 2

Pump station

domestic noise

control and

monitoring

technology

Domestic

Training 2 1 2

Environment

domestic noise

control and

monitoring

technology

Domestic

Training 2 2 2

In total - - - - - 22

8 Reporting System

8.1 MONITORING REPORT

8.1.1 Content of Monitoring Reports and Submission Method

Monitoring report is divided into monitoring report of construction period and

operation period.

Construction period: Environmental Supervision is in its supervision report,

which should be recorded in the monthly EMP implementation, what are the

environmental protection problems and their causes, which measures shall be taken

and treatment effect, etc.

Operation period: municipal PMO or commissioned advisory body, which should

be recorded in the monthly EMP implementation, what are the environmental

protection problems and their causes, which measures shall be taken and treatment

effect, etc.

Content report:

Instructions of monitoring sites, sampling time and monitoring factors.

Page 43: Environmental Management Plan EMPdocuments.worldbank.org/curated/pt/678501468220510692/... · 2016-07-11 · 1 World Bank Loan of Jinzhou City, Yixian Urban Area Central Heating Pipe

41

According to the corresponding standards, the monitoring results of the corresponding

period of monitoring section of construction and operation period shall be analyzed

and evaluated.

According to the monitoring results, the implementation effect of environmental

mitigation measures shall be evaluated.

Discussions and consultation shall be conducted with environment supervision

institutions and environmental impact assessment group, and those ineffective

mitigation measures shall be improved or replaced.

Report submission method:

Municipal Project Management Office (PMO): responsible for submitting

Monitoring Report and information of EMP implementation to the Provincial Project

Management Office (PMO) in accordance with the submission progress of monitoring

reports in 8.1.2.

Provincial Project Management Office (PMO) and its external supervision

Company: responsible for sending the monitoring report and the implementation of

the EMP submitted by Municipal Project Management Office (PMO) to the World

Bank.

8.1.2 Submission Time and Receiving Unit of Monitoring Reports

( 1 ) Submission of monitoring reports:

For construction phase, the periodic monitoring report shall be submitted as per

the construction progress of each quarter, and submit a comprehensive report after

construction;

For operation phase, the quarterly report shall be submitted each quarter, and an

annual report shall be submited.

( 2 ) Monitoring report accepting unit:

Monitoring reports receiving units are Liaoning Provincial Environmental

Protection Office, Municipal PMO, provincial PMO and its external supervision

Page 44: Environmental Management Plan EMPdocuments.worldbank.org/curated/pt/678501468220510692/... · 2016-07-11 · 1 World Bank Loan of Jinzhou City, Yixian Urban Area Central Heating Pipe

42

company, Jinzhou Municipal Environmental Protection Bureau, Yixian Environmental

Protection Agency, Jinzhou Guanda Heating Power Co., Ltd and the World Bank.

8.1.3 Feedback Requirements fro Monitoring Report

Each receiving unit shall give feedback within one month upon the receipt of

monitoring report.

During the feedback period, the receiving unit will analyze and evaluate the

content of monitoring reports, confirm if environmental mitigation measures are

reasonable and effective and make arrangements for the next step with the provision

of the corresponding requirements.

During the feedback period, the receiving unit would also propose the

improvements suggestions and adjustment program of environmental mitigation

measures (if necessary).

8.2 RECORD AND EMP IMPLEMENTATION ANNUALS

8.2.1 Record System

In order to ensure the effective running of an environmental management system,

the owner Sea City Urban Construction Investment Co., Ltd. shall establish a sound

recording system, and keep the record of the following areas: legal and regulatory

requirements; license; environmental factors and the related environmental impact;

training; inspection, checking and maintenance activities; monitoring data;

nonconformity; effectiveness of corrective and preventive measures; information of

relevant parties; audit; assessment. In addition, necessary control shall be carried out

for the above various types of records, which includes the aspects of record

identification, collection, cataloging, archiving, storage, management, maintenance,

query, shelf life, disposal and so on.

8.2.2 EMP Executive Report

The Owner Jinzhou Heating Power Co., Ltd. shall conduct the detailed records of

EMP implementation and timely report to PMO; The project progress reports prepared

Page 45: Environmental Management Plan EMPdocuments.worldbank.org/curated/pt/678501468220510692/... · 2016-07-11 · 1 World Bank Loan of Jinzhou City, Yixian Urban Area Central Heating Pipe

43

by the PMO (e.g. monthly, quarterly, annual report etc.) must be include the content of

EMP progress, such as the implementation progress and effect of EMP; and the

annual EMP implementation report shall be completed prior to the time required by

the World Bank and submit to the World Bank.

EMP implementation report may include the following main content:

Implementation of training programs;

Project status;

whether there are public complaint, if the complaint occurred, then the main

details of the complaints, solutions and public satisfaction shall be recorded;

EMP implementation plan for next year.

9 Public Participation Programme

9.1 PUBLIC PARTICIPATION

9.1.1 Purpose

Public participation refers to the contact and communication between project

construction unit through the environmental impact assessment and the public, which

is one of the important parts of the environmental assessment work, and is also an

effective way to improve decision-making. The purpose of public participation is to

understand and master the views and requirements of the public construction projects

for public participation. By reflecting the various aspects of public participation to the

related departments, the construction projects can be fully recognized by the general

public, while a more comprehensive understanding of public construction projects can

be achieved, so as to reduce or eliminate the concerns about the impact of

construction projects. Public participation will play an important role for the

environmental protection measures and countermeasures taken by the construction

project.

Through the public participation, their environmental rights and interests can be

maintained and responsibilities and obligations of environmental protection can be

fulfilled, which further guarantees the formation of a good social atmosphere and

achieve the intended environmental objectives. The survey of public participation

Page 46: Environmental Management Plan EMPdocuments.worldbank.org/curated/pt/678501468220510692/... · 2016-07-11 · 1 World Bank Loan of Jinzhou City, Yixian Urban Area Central Heating Pipe

44

shall be carried out in strict accordance with the "Interim Measures for Public

Participation in Environmental Impact Assessment" issued by State Environmental

Protection Administration on February 14, 2006.

9.1.2Information Disclosure

Combined with the actual situation of the current project, this public

participation should be conducted in the form of disclosure of environmental

information in Jinzhou Daily and the website of environmental impact assessment unit

and post the notice in the surrounding neighborhoods of the project.

9.1.3 Public Participation Form

The evaluation of public participation is carried out in the form of publishing in

the newspaper, website publicity, posting announcements, as well as issuing public

questionnaire to ask for the comment, suggestions and requests from the general

public, especially those directly under the impact of the proposed project, and answers

difficult issues raised by the public and answer mitigation measures to solve

environmental problems.

To fully understand the opinions of the impact of projects by the public and

satisfaction of the environmental impact mitigation measures, the specific measures of

public participation taken by EIA are as follows:

( 1 ) The publicity situation of this project

In the early stage of the EIA for the report, the construction situation of the

project was published on 18 July 2013 in Jinzhou Daily. There are no phone calls and

letters received within ten working days of publicity period, the contents can be seen

in Figure 9-1.

Page 47: Environmental Management Plan EMPdocuments.worldbank.org/curated/pt/678501468220510692/... · 2016-07-11 · 1 World Bank Loan of Jinzhou City, Yixian Urban Area Central Heating Pipe

45

Figure 9-1 The first newspaper publicity information of the project

( 2 ) The second publicity situation of this project

On August 5, 2013, construction unit published the EIA situation and the method

of obtaining the environmental impact statement abridgement in the project by

Jinzhou Daily and the website of Environmental Planning Institute of Liaoning

Province, and published the environmental impact statement abridgement on the

website of Environmental Planning Institute Co., Ltd, Liaoning Province. Meanwhile,

notices are posted in the vicinity of the construction area. There are no phone calls

and letters received within ten working days of publicity period, the contents can be

seen in Figure 9-2 ~ 9-4.

Figure 9-2 The second newspaper publicity information of the project

Page 48: Environmental Management Plan EMPdocuments.worldbank.org/curated/pt/678501468220510692/... · 2016-07-11 · 1 World Bank Loan of Jinzhou City, Yixian Urban Area Central Heating Pipe

46

Figure 9-3 Website Publicity Screenshots

Page 49: Environmental Management Plan EMPdocuments.worldbank.org/curated/pt/678501468220510692/... · 2016-07-11 · 1 World Bank Loan of Jinzhou City, Yixian Urban Area Central Heating Pipe

47

Figure 9-4 Post Announcements Situation

( 3 ) Issuance of public participation questionnaire

After completion of environmental impact statement, the public participation

questionnaire was issued to the general public in the residential area and unit of the

project.

Page 50: Environmental Management Plan EMPdocuments.worldbank.org/curated/pt/678501468220510692/... · 2016-07-11 · 1 World Bank Loan of Jinzhou City, Yixian Urban Area Central Heating Pipe

48

9.1.4 Issuance Scope of Public Participation Questionnaire

The survey scope of public participation is mainly the residential area in the

vicinity of pipeline project, and the newly built heat exchange station, also includes

some residents frequently passing by along the pipeline, as well as existing residents

near the heat exchange station. In order to fully reflect the confession comments on

the project, emphasis was on the coverage of the respondents for the choice of

respondents, and various levels were covered such as the age structure of respondents,

level of education and occupation.

9.1.5 Content of Public Participation Questionnaire

First, project profiles and public participation questionnaires should be prepared.

Project profile describes the detailed overview of projects to the public, the pollution

that may arise in the course of construction and the measures taken for pollution

prevention. The education quality and profession of the respondents are taken into

account in the questionnaire; the contents are determined to facilitate the answering

and fill-out. Then take visits, surveys and fill-out of the form. Finally, the survey

results should be summarized and statistically calculated, analysis of public opinion of

participation in the survey of the project and other aspects of the views and wishes

and so on.

9.1.6 Statistics Result of Public Participation Questionnaire

It is the first time to conduct the public participation to visit the existing

residents and those around the heat exchange stations, and residents and units along

the pipe network construction; a total of 50 copies of the questionnaire were issued

and 50 valid questionnaires were collected, and the survey results of public

participation are shown in Table 9-1 and Table 9-2.

Page 51: Environmental Management Plan EMPdocuments.worldbank.org/curated/pt/678501468220510692/... · 2016-07-11 · 1 World Bank Loan of Jinzhou City, Yixian Urban Area Central Heating Pipe

49

Table 9-1 Structure statistics of public participation personnel for the first time

No. Survey content

Statistical results

Number of

people (people) Ratio (%)

1 Degree of

education

Primary school 0 0

Middle school 12 24

Universities and

above 38 76

2 Profession

Cadre 29 58

Worker 17 34

Farmer 2 4

Businessman 2 4

Students 0 0

3 Gender Male 20 40

Women 30 60

Table 9-2 Table of statistical result of public participation personnel for the first time (Unit:

Number of people)

What are your views on the

environmental quality in the area of

the project?

Ambient air good(17) acceptable(11)

average(18) poor(4 )

Water

environment

good(17) acceptable(11)

average(22) poor(0)

Acoustic

environment

good(14) acceptable(11)

average(22) poor(0)

What do you think the impact of the

emitted pollutants to the

environment in the project

construction process?

Exhaust gas serious(0) not serious(3)

slight(11) no(7)

Wastewater serious(0) not serious(32)

slight(12) no(6)

Noise serious(0) not serious(31)

slight(12) no(7)

Solid Waste serious(0) not serious(32)

slight(11) no(7)

Your relationship with construction projects:

Live in the first row of building along

the street (0) often go through this

section of the pipe laying (10)

换热站周围居民( 13 ) 其他( 27 )

其它()

Do you think the impact of heat exchange station on

the acoustic environment is serious? yes (0) no (50)

What do you think the degree of influence brought by

the heating laying project to your life:

serious(0) not serious(35)

slightly impacted (7) no impact (8)

What do you think the development trend of

environmental quality of the area after the project:

gradual deterioration of the

environmental quality of the area (0)

no change (6)

Gradual improvement of environmental

quality in the area ( 44 ) What do you think the economic benefits of the

project brought to the area:

High (7) above normal(34)

average(9) low(0)

What do you think the social benefits of the

project brought to the area: (Multiple choice)

Solve the employment problem of some

people(38)

Promote the development of other

industries (4)

Improve the quality of the heating in the

area (19)

Increase awareness of the region (3)

Page 52: Environmental Management Plan EMPdocuments.worldbank.org/curated/pt/678501468220510692/... · 2016-07-11 · 1 World Bank Loan of Jinzhou City, Yixian Urban Area Central Heating Pipe

50

Your attitude towards this project: support (48) against(0) not care (2)

9.1.7 Conclusion of Public Participation

EIA is conducted by publishing in the newspaper and website, posting

announcements, and the issuance of public participation questionnaire for public

participation. No feedback was received during the public notice. Among the 50

copies of public participation questionnaire issued, 50 valid questionnaires were

collected, of which 100% public support for the construction of the project.

During the investigation, some of the public comments and suggestions were

collected:

( 1 ) It is hoped that after running the project by the environmental protection

department, supervision and management of the enterprise's environmental protection

operation shall be strengthened to meet environmental requirements.

( 2 ) The construction units shall strengthen the management of the environment,

and set up specialized environmental agencies and personnel for the regular inspection

and maintenance of environmental protection facilities; while they shall often visit the

public around for communication and resolve of newly arisen situations and

problems.

Therefore, EIA requires that building units should, in the preparation process,

placed the work of environmental protection in an important position:

Construction units shall strictly implement the pollution control measures in

the construction period proposed in the report, and reasonably arrange for the

construction site and construction time to minimize the impact on residential

areas during the construction process.

During the project operation period, the environmental protection

departments shall strengthen the supervision and management of operation of the

enterprise's environmental protection; the construction unit shall strictly enforce

the pollution control measures proposed in the EIA report.

The construction unit shall set up specialized environmental agencies and

Page 53: Environmental Management Plan EMPdocuments.worldbank.org/curated/pt/678501468220510692/... · 2016-07-11 · 1 World Bank Loan of Jinzhou City, Yixian Urban Area Central Heating Pipe

51

personnel and conduct the regular inspection and maintenance of heat exchange

stations and pipeline; while frequently visit the relevant public to keep aware of

their views.

It is understood through statistical analysis of questionnaires and visits to

relevant public that the vast majority of the public believe that the implementation of

this project can replace the small boiler within the heating supply area, improve urban

air quality and the quality of urban heating, which should be implemented as soon as

possible.

9.2 DISPUTE COMPLAINT CHANNELS

Establishment and composition of the complaints mechanism

In order to better protect the legitimate rights of the affected people, a complaint

mechanism will be established for provision of a convenient, transparent, fair and

effective complaint channel for affected people. For this, the project leading group of

the environmental impact of complaints acceptance is established, the head is acted by

the relevant personnel of Yixian environmental Protection Agency concurrently, and

the crew members are from the PMO, Yixian environmental monitoring, and

environmental assessment units. Complaints acceptance office is set up under

environmental impact complaint handling group, which is located in Yixian

Environmental Protection Agency. The daily complaints collected by the Complaints

Acceptance Office, which will propose disposal advice after consultation with the

responsible units.

Complaint Procedures

Complaint handling leading group and office will begin receiving complaints

within a week after the project started. During the construction period, bulletin board

should be set at all construction sites to clarify the environmental safety official also

opened the complaint hotline and complaints mailboxes. The detailed complaint

procedures are as follows:

Affected people who consider their rights have been violated in any aspect of

Page 54: Environmental Management Plan EMPdocuments.worldbank.org/curated/pt/678501468220510692/... · 2016-07-11 · 1 World Bank Loan of Jinzhou City, Yixian Urban Area Central Heating Pipe

52

environmental protection, they may complain to the Complaints Acceptance Office in

writing or orally; if it is an oral complaint, the member of Complaints Acceptance

Office will conduct the detailed records and assortment, and submit disposal

comments within two weeks.

If the complainant is dissatisfied with the views of the Complaints Acceptance

Office, he may complain in writing to Liaoning Provincial Environmental Protection

Office within one month after receipt of the disposal suggestion, and Liaoning

Provincial Environmental Protection Bureau will issue disposal comments within

three weeks.

If the complainant is still dissatisfied with the views of Liaoning Provincial

Environmental Protection Office, after receiving disposal comments, he may

prosecute to the local People's Court in accordance with the "PRC Civil Procedure

Law " for the court ruling.

10 Implementation Costs of Management

Plan

Management plan implementation costs are shown in Table 10-1.

Table 10-1 Environmental Management Plan Implementation Costs

Project

Budget for 1 year

construction phase

(RMB 0.01 million

Yuan)

Budget of 3 years

operation phase

(RMB 0.01 million

Yuan)

Funding sources

Wages 12 80

domestic funds

Office expenses 6 20

Transportation costs 10 15

Monitoring costs 1.5 7

Supervising engineer

budget 10 -

total budget of

Environmental

Management Plan

39.5 122