environmental impact assessment · “environmental impact assessment (eia) is required, in one...
TRANSCRIPT
ENVIRONMENTAL IMPACTASSESSMENT
THE E7 NETWORK
O F E X P E R T I S E
FOR THE GLOBAL
E N V I R O N M E N T
A N E L E C T R I C U T I L I T Y O V E R V I E W
ENVIRONMENTAL IMPACTASSESSMENT
A N E L E C T R I C U T I L I T Y O V E R V I E W
E 7 N E T WO R K O F E X P E RT I S E F O R T H E G L O B A L E N V I R O N M E N T
June 1997
FOREWORD
This Environmental Impact Assessment (EIA) Manual was prepared by the E7 Network ofExpertise for the Global Environment, for use by electric utility planners, project developers,and decision-makers in developing and Eastern European countries. The Manual presentsan overview of the EIA process as it applies to electricity projects, and describes the role ofEIA in project decision-making and implementation. The process described is typical of EIAprocesses utilized by most major international lending agencies (e.g. the World Bank).
E7 members, in an effort to increase the capacity of developing countries to follow a sustainable development path, have developed and delivered a number of EIA seminars toincrease awareness and promote the benefits of EIA as an integral part of sound decision-making. The EIA process described in the Manual provides the organizing framework for these E7 EIA seminars. The E7 team uses this framework and augments itwith specific information and case study examples from the host country to make its EIAseminars as relevant as possible for our developing country partners.
The E7 Network is pleased to provide this EIA Manual, in which E7 members share withenergy planners and decision-makers some of the expertise they have gained in over twodecades of experience in dealing with the EIA requirements and processes for electrical utilityprojects developed worldwide. We hope that in sharing this expertise we can help movealong the path to a more sustainable energy future.
For more information on E7 or on E7’s EIA projects or seminars, please contact the E7Secretariat or one of the E7 contacts listed on the inside back cover.
Richard RonchkaChair - Steering CommitteeE7 Network of Expertise for the Global Environment
CONTENTS
INTRODUCTION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1
WHAT IS EIA? . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .4
WHY DO EIA? . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .4
EIA PROCESS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .5
Overview . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .5
Project Need . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6
Screening . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .7
Scoping . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .8
Baseline Data . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .11
Stakeholder Involvement . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .13
Effects Prediction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .14
Impact Assessment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .17
Mitigation and Residual Impacts . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .18
EIA in Decision Making . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .20
Documentation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .21
Project Implementation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .21
EIA TOOLS AND METHODS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .25
EIA PROJECT MANAGEMENT . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .27
MAXIMIZING THE VALUE OF EIA . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .29
KEY MESSAGES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .31
GLOSSARY . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .33
REFERENCES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .35
APPENDICES
APPENDIX 1: International EIA Requirements . . . . . . . . . . . . . . . . . . . .37
APPENDIX 2: Typical Environmental Effects and Mitigation Options for Hydroelectric Projects . . . . . . . . . . . . . . . . .39
APPENDIX 3: Summary of Selected EIA Tools and Methods . . . . . . . . .44
ACKNOWLEDGEMENTS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .49
1
Environmental Impact Assessment(EIA) has become one of the most effective tools we have for incorporatingenvironmental consequences into decision-making. EIA is, ideally, an inte-gral part of the overall planning processfor electricity projects. It assists, butdoes not control project planning andimplementation; ensuring that environ-mental considerations are incorporatedinto decision-making, along with techni-cal and economic factors (Figure 1). Inorder to achieve the desired goals, anEIA must begin as soon as a project isconceived, before irrevocable decisionsare made.
THE MANUAL
This EIA Manual was prepared by theE7 Network of Expertise for the GlobalEnvironment, for use by utility planners,developers and decision-makers in devel-oping countries. The Manual outlines ageneric EIA process that can assist inmeeting EIA guidelines set out by inter-national lending organizations for majorelectricity projects. It provides back-ground information on the EIA processand its application in the electricity sec-tor; summarizes the various tools andmethods used in EIA studies; and sharestechniques for managing the EIAprocess. The intent of the Manual is toshare with developing countries theapproach to EIA which has evolved, andits application in the electric utility sec-tor, so that they may benefit from thesuccesses and mistakes of the past, tomake more sustainable project decisionsin the future.
BACKGROUND ON EIA
EIA has developed in response to limita-tions in the traditional project planningprocess with regard to environmentalconsiderations, and also in response tothe growing concern about environmen-tal quality issues.
The EIA process has evolved consider-ably over the last 25 years, along withour knowledge and capacity to deal withenvironmental issues. Early EIAs tendedto be lengthy, descriptive, and not muchuse to decision-makers. They were often
Introduction“EIA must begin as soon as a project is
conceived, before irrevocable decisions
are made.”
Site selection, environmental screening, initial assessment, scoping of significantissues
Detailed assessment ofsignificant impacts, identification of mitigationneeds, input to decisionanalysis
Detailed designof mitigationand compensationmeasuresFeasibilityPre-feasibility
Design &Engineering
ImplementationMonitoring& Evaluation
ProjectConcept
Implementation of mitigationmeasures andenvironmentalmanagement strategy
Monitoring and post-auditing(lessons for future projects,EIA verification, compliance)
FIGURE 1: EIA In the Project Life CycleSource: adapted from UNEP, 1988
2
started late in the project planningprocess, after irrevocable decisions hadbeen made, therefore had little chance toinfluence project design.
With experience and study, EIAs havebecome more cost-effective and timely,focusing on issues important to stake-holders and decision-makers. We nowknow that EIAs must be initiated assoon as a project is conceived, and fullyintegrated in the overall project plan-ning process, in order to influence pro-ject design and implementation (Figure2). Public participation has become anintegral part of EIA. EIAs now aid inmaking decisions which are informedand environmentally sound.
“It is necessary to understand the linksbetween environment and develop-ment in order to make developmentchoices that will be economically effi-cient, socially equitable and responsi-ble, and environmentally sound.”
Agenda 21
THE INTERNATIONALCOMMUNITY
In recent years, the international com-munity has placed the environment atthe top of the development agenda. Asa result, international lending organiza-tions, like the World Bank, have begunto tie the provision of development
funding to a requirement to assess theenvironmental impacts of proposed projects.
Many lending institutions and interna-tional environmental agencies haveissued guidelines to ensure that pro-posed projects are designed and imple-mented in an environmentally and eco-nomically sound fashion (ADB 1992;AsDB 1990, 1993; CIDA 1994; IADB1990; UNEP 1988; World Bank 1991).
THE E7 AND EIA
In 1992, the Chairmen of the sevenlargest vertically integrated electricalutilities in the G7 countries met inJames Bay, Quebec, Canada, and agreedto cooperate and participate actively tofoster the worldwide development anduse of electricity in environmentallydesirable ways. In 1993 an eighth com-pany joined the E7. Each utility in theE7 initiative considers the prudent man-agement of environmental issues amongthe highest of corporate priorities and a key determinant to sustainable development.
“Energy issues permeate the debateover the future of our planet. And atthe very core of energy issues is the elec-tric utility industry.”
Maurice Strong
The E7 utilities believe that in addition totheir own local efforts to protect the envi-ronment, preventative measures are neces-sary at a world level in order to avoid thedeterioration of the global environment.Their common goal is “to play an activerole in protecting the global environmentand in promoting efficient generation anduse of electricity”.
To act on this goal, the E7 members havebegun to work in partnership, through aNetwork of Expertise, with utilities andgovernments in developing and EasternEuropean countries to improve their elec-trical systems and increase their capacityto follow a sustainable development path.
An important part of this capacity build-ing is ensuring that people have the skillsand training necessary to understand thelinkages between energy developmentand environmental consequences. Thisinvolves not only training to betterunderstand how power systems operate,but also how to manage the environmen-tal impacts that can occur.
People in government and business needto know how to evaluate and mitigatethe environmental impact of all
International FundingOrganizations with EIARequirements:
• African Development Bank(ADB)
• Asian Development Bank(AsDB)
• Canadian InternationalDevelopment Agency (CIDA)
• Economic Commission forEurope
• European EconomicCommunity
• European Investment Bank
• Inter-American DevelopmentBank (IADB)
• United Nations EnvironmentalProgram (UNEP)
• United States Agency forInternational Development(USAID)
• World Bank
FIGURE 2: Evolution of EIA in Relation to Project Planning
3
development projects, starting from thetime the projects are conceived. Theyneed to take a precautionary, integratedand proactive approach to protecting theenvironment. Environmental ImpactAssessment (EIA) can act as a catalyst tosustainable development by increasingenvironmental awareness and knowledge, and can serve as a startingpoint for implementing an environmen-tal management program.
“To ensure sustainability, it is neces-sary to assess the environmental impactof development and make enlightened economic choices.”
Neville V. Nicholls, PresidentCaribbean Development Bank
To help increase awareness and promotethe benefits of EIA, the E7 Network ofExpertise for the Global Environmenthas prepared this Manual describing the
EIA process and its application in theelectric utility sector, and developed anEIA training seminar. An E7 EIA semi-nar takes the information in this Manualand builds on it, adding specific infor-mation and case studies from the hostcountry, to provide greater relevance.The Manual and seminar draw on theextensive experience of E7 companies indealing with EIA requirements andprocesses for electrical utility projectsdeveloped worldwide.
4
WHAT IS EIA?
EIA is a planning process used to helpensure that environmental matters aretaken into account early in the projectplanning process, along with the moretraditional technical and economic considerations.The EIA process identi-fies, predicts, interprets and communi-cates information about impacts of aproposed project on the biophysicalenvironment (air, water, land, plants and animals) as well as on the social and economic environment of the people to be affected. It seeks ways to maximize
the societal benefits of a project, andavoid or reduce unacceptable impacts.
EIA is also a decision-making process.It examines alternative ways of carryingout a project, arriving at the selection ofa “preferred” alternative. EIA provides aframework for gathering and document-ing public and external knowledge andopinion. It therefore empowers deci-sion-makers to make informed and envi-ronmentally sound choices.
WHY DO EIA?
Today, most financial institutions andassistance agencies funding developmentprojects have a built-in requirement forEIA (Appendix 1). Some countries alsohave legislative requirements to producea satisfactory EIA before a project canproceed.
“Environmental impact assessment(EIA) is required, in one form oranother, in more than half the nationsof the world.”
Ortolano and Shepherd (1995)
EIA is intended to prevent or minimizepotentially adverse environmentalimpacts and enhance the overall qualityof a project. The EIA process allowsenvironmental issues to be addressed ina timely and cost-effective way duringproject design, preparation and imple-mentation. EIA can therefore helpreduce overall project costs, assist incompleting projects on schedule, andhelp design projects which are accept-able to stakeholders.
The main advantages and benefits ofEIA are (UNEP 1996):
• lower project costs in the long-term(fewer costly changes or add-ons atadvanced stages of the project; lowerprobability of environmental disas-ters, court cases and/or costly clean-ups);
• increased project acceptance by thepublic and key stakeholders;
• improved project design/siting;
• more informed decision-making;
• more environmentally sensitive decisions;
• increased accountability and trans-parency during the developmentprocess;
• improved integration of projects intotheir environmental and social setting;
• reduced environmental damage (mit-igation measures planned and imple-mented in time to minimize adverseimpacts on the environment).
What is EIA?Why do EIA?
“EIA is intended to prevent or
minimize potentially adverse
environmental impacts and enhance
the overall quality of a project.”
6
This section outlines the major stepsinvolved in carrying out an EIA for amajor energy project, using hydroelec-tric as an example. Figure 3 provides asummary of the process steps that arecommon to most EIA guidelines issuedby international organizations.
The approach taken to carry out an EIAcan differ somewhat, depending on therequirements and practices of the differ-ent international funding organizations(see Appendix 1); a country’s legislativeframework; and/or the type of energyproject. However, the process steps out-lined here provide a common organizingframework for all EIAs.
In addition, there are many differentEIA tools and methods that can be uti-lized at the different stages of an EIA. Certain methods, such as checklists andmatrices are widely used and useful inthe early stages of most EIAs. EIAmethods to assist with prediction andassessment of impacts are selected basedon the appropriate level of study for theproject under consideration, and theresources available for the EIA study.Although the focus of this manual is onthe EIA process, common EIA method-ologies are summarized in the EIA Toolsand Methods section, and in Appendix 3.
EIAs do not necessarily follow linearlythrough the steps outlined in Figure 3.EIA is an iterative process, and at differ-ent steps in the process it may be neces-sary to return to earlier stages to recon-sider previous findings and conclusions.New or unforeseen issues may arise,baseline studies may indicate that origi-nal predictions were inaccurate, or pre-ferred avoidance or mitigation methods
may not be feasible and new alternativesmay have to be identified.
EIA involves examining a range of pro-ject alternatives. These alternative meth-ods of carrying out a project are usuallyidentified at the scoping stage of an EIA.However, not all alternatives need to becarried through the entire EIA process.Some may drop out early if there isstrong evidence they will result in signifi-cant adverse effects that cannot be easilymitigated. Other alternatives maybecome apparent after the scoping stageand can be added into the EIA at a laterstage. The no-project alternative shouldbe carried through the process as a meansof comparison, and consideration.
In all guidelines, the term “environ-ment” is defined as including both thenatural and social environments.
OVERVIEW
The EIA process is designed to answerthe following key questions and providerationale and information to supportproject decisions:
PUBLICCONSULTATION/INTER-AGENCYCOORDINATION
EIA PROCESS
Screening
Scoping
Baseline Data
Effects Prediction
Mitigation
Impact Assessment
EIA Review
Implementation Monitoring
Need/Justification
FIGURE 3: Generic EIAProcess
EIA Process“EIA involves examining a range of
project alternatives.”
EIA distinguishes between “alterna-tives to” a project, and “alternativemethods” of carrying out a project.
“Alternatives to” a project are func-tionally different ways of achievingthe same end. For example, alterna-tives to a hydroelectric developmentcould include importing power, con-serving energy, building a nuclearstation, or obtaining the energythrough renewable resources.
“Alternative methods” of carryingout a project are methods of a similartechnical character or methods thatare functionally the same.Alternative methods with respect to ahydroelectric development, forexample, might include selecting adifferent location, choosing theappropriate number and size of tur-bines, using different operating sce-narios, etc.
“Environmental Impact Assessment isa “flexible procedure to identify, ana-lyze, and recommend steps to dealwith the potentially significant conse-quences of a proposed investment pro-ject or program.”
World Bank
7
Need/justification• What is the problem?• What options/alternatives are
available to solve the problem?• What are the environmental
implications of these options/alternatives?
• What is the preferred option/alternative? Why?
Screening• Is a full EIA required?
Scoping• What should the EIA include?
Effects Prediction• What are the environmental effects
associated with proceeding with thisproject and its alternatives?
Mitigation• Are there mitigation measures that
could reduce the overall effects of theproject and its alternatives?
Impact Assessment• What is the significance and/or
importance of the effects?• Which of the project alternatives is
the preferred alternative?Review and Decision-making
• Do the benefits of the proposed pro-ject outweigh the potential residualenvironmental effects?
Implementation• How can the project best be
implemented?Monitoring and Follow-up
• Was the project implemented in anenvironmentally acceptable fashion?
• Were effects predicted accurately?• Were there any unanticipated
effects?
Public and stakeholder consultation andinter-agency coordination are importantat all stages of the EIA process.
An EIA document is prepared, whichpresents for public and governmentinformation and review, the rationale orjustification for a proposed project, adescription of the information that wascollected, the manner in which it wasassessed, and the judgments used inselecting the preferred alternatives.
PROJECT NEED
A proponent must convince stakeholdersfirst and foremost that a project is need-ed, and that the particular project beingconsidered is justified.
The EIA process begins with the identi-fication of a problem to be solved. Thisis often referred to as the “need” for anundertaking. To satisfy this “need”,there are a number of alternatives thatmust be considered and assessed. Theassessment of alternatives is carried outin a systematic and iterative manner,considering technical, environmental,and economic criteria. UNEP refers tothis as a tiered approach to the assess-ment of alternatives to a project (Figure 4).
In some cases the definition of needcomes as a result of an “opportunity” totake advantage of certain circumstances(e.g., a funding agency willing to support a development in a certain loca-tion). An EIA study will still berequired to assess the viability andacceptability of these opportunities.
Tier 1 - Problem
In energy sector applications, a frequent“problem” is the need to supply energy-to a residential or industrial facilitywithin a limited timeframe.
The first tier of assessment wouldaddress three alternatives for solving theproblem:
• Do nothing;
• Eliminate the need for additionalenergy by saving it somewhere else inthe energy sector (energy conserva-tion, demand management);
• Supply additional energy.
The Do Nothing alternative is usuallyeasily discarded, but serves to illustratethe magnitude of the defined problem,i.e. the consequences of not providingthe required energy. It is also a usefulcheck to ensure that action is reallyrequired.
Tier 2 - Demand/Supply Options
At the second tier of assessment,demand/supply options should beassessed within the framework of what ispossible and preferred within the coun-try, as well as what the implications ofpursuing these options will be in termsof their economic, social and environ-mental impacts.
By identifying and considering the envi-ronmental and social impacts of a broadrange of functionally different energyoptions and plans at the very outset, aproponent is able to determine the mostsustainable energy solution to resolve the
Problem?
Demand/Supply Options
Electricity Options
Hydroelectric Options
Potential Sites
Proposed HydroelectricDevelopment
FIGURE 4: Tiered Approach tothe Assessment of
Alternatives to the Project
PUBLICCONSULTATION/INTER-AGENCYCOORDINATION
EIA PROCESS
Screening
Scoping
Baseline Data
Effects Prediction
Mitigation
Impact Assessment
EIA Review
Implementation Monitoring
Need/Justification
8
problem or take advantage of the oppor-tunity, and to take this step before agreat deal of time, money and resourceshave been committed.
If the predicted shortage cannot be metthrough increased conservation pro-grams (for cost or technological reasonsperhaps) then some new form of energysupply will be required. Major energysupply options may include petroleum,coal, hydroelectric or other electricityoptions. These also need to be assessedin terms of their economic, social andenvironmental impacts.
Environmental information at this stagewill relate to general, broadly definedissues rather than specific impacts,whereas detailed impact-specifictechnical information is needed later inthe EIA process.
Tier 3 - Electricity Options
If, for example, electricity is selected asthe favored mode of supplying therequired energy, the various alternativesfor producing this electrical energy arethen assessed. Options to considerinclude:
• Fossil fuel combustion (oil, naturalgas, coal)
• Hydroelectric generation• Purchases from neighbouring
countries• Nuclear• Renewable technologies (solar, wind,
biomass, geothermal, tidal, etc.)
At this stage, each option is evaluatedusing a series of technical, economic,resource use and environmental criteria.Based on this evaluation, certain optionsare rejected and others supported. Eachsituation will be unique, and should beevaluated on its own merits.
Tier 4 - Selected Generation Options
The next stage or tier is to determinepotential sites or location for a facility.If, for example, hydroelectric generationwas selected as the preferred option,then hydroelectric resources should beassessed on a broad river system basis,
and the remaining development poten-tial in each basin determined. Potentialsites within each basin are identified andconceptual designs developed.
These conceptual designs provideimportant information required to assesscertain environmental characteristics foreach proposed development, includingpotential flooded area and loss of river-ine habitat. Information on floodedareas can be used to assess in a prelimi-nary fashion the potential environmentaland social implications of proposeddevelopment schemes, e.g. the numberof people affected by flooding.
Tier 5 - Project DefinitionThe result of this site selection processwill be a ‘project’ - ie. a preferred devel-opment option (hydroelectric, in ourexample), with a potential site, in a spe-cific river basin, and using specificdesign concepts for a hydroelectricdevelopment (e.g. run-of-the river orreservoir creation).
SCREENING
Once a project is defined, it is importantto determine if a full EIA study isrequired to assess project impacts.Screening is the process by which theappropriate level and type of EIA is
determined for a given project on thebasis of its likely environmental impacts.
It is important to focus EIA studies onprojects that have potentially significantand irreversible impacts, since EIA stud-ies can be both costly and time consum-ing. A method of systematically screening potential projects is therefore critical. Other less significant projects,or those with few impacts, may not needfull EIA studies, but instead may bescreened out or assessed using less com-prehensive means such as Class EIA’s,environmental reports or environmentalfeasibility studies. These represent amore streamlined approach than a fullEIA in terms of cost and schedule.
The choice of screening method is usu-ally determined by the decision-makerswhen an EIA system is established. Allscreening methods require informationabout the project and all of them haveinvolved the use of value judgments atsome stage during their development.
Project screening can be done in a num-ber of different ways including:
• measuring against simple criteriasuch as size, location or cost;
• comparing the proposal with lists ofproject types that rarely need an EIAin other jurisdictions (e.g. minortransmission line) or that alwaysneed extensive study (e.g. major newgeneration);
• use lists of resources (e.g. rainforests), environmental problems (e.g. soil erosion, deforestation)and/or areas of special importance orsensitivity (e.g. national parks) sothat any activity that affects suchareas of concern will be judged tohave significant environmentaleffects and require an EIA;
• estimating the general impacts of aproposed project and comparingthese against set thresholds;
• doing a detailed, informal analysisusing readily available data (initialenvironmental evaluation, or envi-ronmental overview).
PUBLICCONSULTATION/INTER-AGENCYCOORDINATION
EIA PROCESS
Screening
Scoping
Baseline Data
Effects Prediction
Mitigation
Impact Assessment
EIA Review
Implementation Monitoring
Need/Justification
9
The responsibility for screeningdepends on the method adopted.Where project lists exist in legislation,proponents can screen their own pro-posals. However, where the methodinvolves discretion, the decision-maker ( e.g. government) usually likes to beinvolved or have the ability to influencethe outcome.
Screening should occur as early as possi-ble in the development of the project sothat proponents are aware of their oblig-ations before committing funding forproject design and development.
There are usually three possible out-comes (categories) of a screeningprocess:1. Where significant concerns exist or
where there is a lot that is unknownabout project impacts, a full EIAstudy is necessary.
2. If environmental impacts of a projectare known and can be easily mitigat-ed, a limited environmental studyand mitigation plan may be all thatis necessary.
3. If screening identifies no concerns,further environmental analysis isunnecessary, and the project mayproceed without an EIA study.
Most centralized new power generationfacilities are environmentally significant,and require a full EIA. Examples of pro-jects usually requiring only limited envi-ronmental study include minor modifi-cations to existing facilities, small com-bustion turbine units, or short lengths oftransmission line. The remainder of thismanual will focus on describing an EIAprocess appropriate for a major newelectricity generation project.
SCOPING
A scoping exercise is the first step in theproject assessment phase of the EIAprocess, and should be carried out soonafter the project proposal has beendefined. The primary purpose of scop-ing is to identify concerns and issueswhich are important to project deci-sions. Scoping also serves to define EIAstudy requirements and boundaries.The results of the scoping exercise formthe basis for the rest of the EIA process.
Through the use of scoping, the issuesand concerns of potential stakeholderscan be identified early in the planningprocess, so that a work program can bedesigned accordingly. Typical stakehold-ers include the project proponent, regu-latory agencies, local community leaders,project donors, scientific institutions,non-governmental organizations(NGOs), and the general public.
The objectives of scoping are:• to identify project stakeholders;
• to identify existing informationsources and local knowledge;
• to inform stakeholders of the EIAand its objectives and get input onthe EIA;
• to identify the key environmentalconcerns (community and scientific)related to a project and the relativeimportance of issues;
Class Environmental ImpactAssessmentSome countries have established a ClassEIA process. It applies to projects whichare of a similar nature and which gener-ally have a small, predictable range ofeffects (eg. short lengths of transmissionlines, minor modifications to hydroelec-tric facilities, and roadway widenings).
For projects which can be groupedtogether as a class, a single formal envi-ronmental impact assessment documentis prepared for the class. The Class EIAdocument is submitted and processedlike a full EIA. An EnvironmentalReport (ER) is typically required foreach individual project which falls with-in the class. The ER is a less detailedform of environmental impact assess-ment and does not require a full publicexamination. A Class EIA generallystreamlines the EIA process.
PUBLICCONSULTATION/INTER-AGENCYCOORDINATION
EIA PROCESS
Screening
Scoping
Baseline Data
Effects Prediction
Mitigation
Impact Assessment
EIA Review
Implementation Monitoring
Need/Justification
10
• to define the EIA work program,including a plan for public andstakeholder involvement;
• to define the range of project alter-natives to be considered;
• to obtain agreement on the methodsand techniques used in EIA studiesand document preparation;
• to determine the spatial and tempo-ral boundaries for the EIA studies.
Scoping helps to center EIA efforts onthe collection and analysis of pertinentdata and the assessment of significantenvironmental attributes. The endresult will be a work program which iswell focused and cost-effective. Failureto obtain government and public inputat the scoping stage may result in latercriticism of impact predictions and pos-sible project delays.
The benefits of scoping include:
• improves the quality of EIAinformation by focusing scientificefforts and EIA analysis on truly sig-nificant issues;
• allows environmental concerns to beidentified and incorporated early inthe project planning process, at thesame time as cost and design factorsare considered;
• reduces the magnitude and cost ofEIA studies and time required forand the size of EIA documents;
• ensures research efforts are not wast-ed on insignificant issues;
• reduces the likelihood of overlookingimportant issues;
• diminishes the chance of prolongeddelays and conflicts later in the EIAprocess by engaging stakeholders in aconstructive participatory processearly in the EIA study.
Scoping may be undertaken in stages,beginning internally, within the projectproponents company, expanding toinclude government (designated EIAreview, technical experts) and communi-ty leaders, and then the general public
and other interested parties before subse-quent plans and work programs are finalized.
Possible methods for scoping include:
• examination of EIAs for similar typesof projects in similar environments;
• EIA methods such as checklists,matrices, networks, overlays, evalua-tion techniques and adaptive meth-ods (hypotheses of effects);
• public participation methods,including: public meetings, net-working, open houses and advisorycouncils;
• group process methods, including:interactive group meetings, Delphimethod, nominal group techniques,and workshops.
Experience has shown the workshopapproach to scoping to be very effectivefor large projects. Workshops typicallybring together approximately 20 to 25people representing technical experts,managers and policy-makers, andincludes staff from regulatory agencies,community leaders, as well as the propo-nent. Workshops typically last 3-4 days
for a major generating facility. Theworkshop operates initially as a “brain-storming” session to list issues andpotential impacts, and identify availableinformation. Then priorities are set forinformation needs and study requirements.
Scoping is, in part, a negotiatingprocess. There will always be questionswithin each issue i.e. type and extent ofdata collection, significance of the data,importance of the issue, etc. These mayall be subject to debate and dispute.There are no ‘right’ answers, just a suc-cession of judgments which the
To be successful a scoping workshoprequires:
• information; effectiveness will be adirect function of the timing, leveland reliability of information pro-vided to participants; participantsneed a good description of the pro-ject and its alternatives, and descrip-tion of the study area; a pre-work-shop site visit is usually useful;
• a good workshop facilitator or organizer;
• commitment; all agencies should becommitted to the scoping processand be willing to use the results ofthese sessions in their decision-making;
• participation; opportunities must beprovided for all stakeholders to par-ticipate, and steps taken to ensure allnecessary technical resource peopleare represented (public, regulatoryagencies, proponent, academic);
• communication; the most effectivescoping processes require a two-wayflow of information, with opportu-nities for consensus building;
• flexibility; scoping methods shouldbe adapted to the project at hand;no one method is effective in all circumstances.
Typical Environmental IssuesRelating to Hydroelectric GenerationProjects:
• methane release
• disease
• water quality deterioration
• mercury contamination in fish,wildlife and people
• erosion and sediment deposition
• loss of wetlands and estuaries
• loss of environmentally sensitiveareas, endangered species, wildlife,forests, plants and wildlife habitat
• loss of or disturbance to heritageresources
• forced relocation of people living onthe land to be flooded
• access to water, land and resourcesmay be restricted
• disruption of wildlife migratory patterns
11
proponent must make to try to balancethe available resources for the study(time and money) with the legitimateconcerns of the participants.
Clearly, the workshop approach encour-ages early participation and cooperationof government staff who willundoubtedly determine the governmentposition towards approval of a project.There is also an opportunity to establisha positive, constructive relationship withstakeholders, to understand their con-cerns and begin a process of communication.
Results of the scoping exercise are pre-sented in an EIA Scope Document, orTerms of Reference, which describes theproposed work program (Table 1). TheEIA Scope Document represents anagreement with external stakeholders onthe general approach and scope of theEIA. It forms the basis for the EIAstudy and preparation of the EIA
document. The proponent may wish toprovide a draft EIA Scope Documentfor review by government and the publicbefore preparing a final.
The EIA Scope Document can becomea critical piece of process documentation
should disputes among stakeholdersdevelop during the EIA study. It can beused to bring the study back on-trackwith originally agreed to terms of refer-ence, thereby saving time and money.
Project Description should include:• rationale for the project and primary
goals;
• brief discussion of the size, scope,and phasing of activity;
• proposed location on a map, show-ing boundaries of the proposed site,major existing infrastructure, adja-cent land uses, and any importantenvironmental features;
• site plan of the project illustratinglocation of existing buildings andfacilities, proposed components ofthe project, and any infrastructurerequired to service the project;
• amount and type of labour required,over how long, and how this is to bemet;
• types and amounts of all materialswhich will go into the project, andfrom where and how these will beobtained;
• all outputs (products and wastematerials) and what will happen tothese outputs;
• expected requirements for local facil-ities and services.
TABLE OF CONTENTS
SummaryIntroductionBackground
Existing Hydroelectric FacilitiesExisting Transmission Incorporation FacilitiesRiver Basin Development Plan
The Proposed DevelopmentPurpose/JustificationDescription
System NeedAlternatives
Alternatives to the ProjectAlternative Methods of Carrying out the Project
Scope of EIA WorkStudy AreaCharacterization of the Existing EnvironmentIssue Identification and ResolutionPrediction of Environmental EffectsMitigation and Community Impact ManagementPublic Involvement ProgramConsultation with Government AgenciesPreliminary EIA Table of Contents
EIA Coordination EIA Project TeamProject Schedule
References
TABLE 1: Sample EIA Scope Document Table of Contents for aHydroelectric Development
12
BASELINE DATA
EIA guidelines typically specify that anEIA document should contain a descrip-tion of the existing environment thatwould be or might be affected directlyor indirectly by a proposed project. Theenvironment is broadly defined toinclude the natural, cultural, socio-eco-nomic systems and their interrelation-ships. The intention is not to describeall baseline conditions, but to focus thecollection and description of baselinedata on those conditions that are impor-tant to impact prediction, assessmentand decision-making.
The term “baseline” refers to conditionsexisting before development againstwhich subsequent changes can be refer-enced. Baseline studies are carried outto:
• identify environmental conditionswhich might influence project designdecisions (e.g., site layout, structuralor operational characteristics);
• identify sensitive issues or areasrequiring mitigation or compensation;
• provide input data to analyticalmodels used for predicting effects;
• provide baseline data against whichthe results of future monitoring pro-grams can be compared.
The list of issues identified in the initialscoping workshop should be furtherrefined to determine baseline informa-tion requirements for impact predictionand assessment. This is an importantstep to ensure money and time are notwasted collecting inappropriate orunnecessary data/information.
Once information needs are identified,baseline environmental information isassembled through the collection andanalysis of existing data, by carrying outspecific field studies; and/or input fromcommunity consultation programs.Before embarking on an extensive andcostly field studies program, maximumeffort should be directed at determiningwhat data already exist that will assist indescribing environmental conditions inthe proposed project study area.
Where existing information cannot ade-quately characterize the existing environ-ment, a program of field studies willgenerally be required to fill in the datagaps and/or provide more timely orfocused information. A field samplingprogram for baseline studies is designedby technical experts in the appropriatefields, with the aim of providing suffi-cient information to assist in impact
predictions, and in developing a refer-ence base to guide and test future pro-ject monitoring programs. Dependingon the nature of the proposal, the levelof detail and scope of baseline studiesare tailored towards meeting the needsof the project.
SCOPE OF TYPICALBASELINE STUDIES:
NATURAL ENVIRONMENT
• terrestrial-land use-vegetation-wildlife-physical terrain-wildlife habitat
• aquatic-water quality-aquatic life-aquatic habitat-morphology-hydrology
• atmospheric-air quality-meteorology-noise
SOCIO-ECONOMIC ENVIRONMENT
-history-economic base-labour supply/employment-demography and population-housing supply-community/social services-municipal finance/planning-social and cultural patterns-transportation-tourism
RESOURCES USES
-recreational-agricultural-fisheries-navigation-wildlife (hunting, trapping)-forestry and vegetation-mining
HERITAGE
-heritage-archaeological
PUBLICCONSULTATION/INTER-AGENCYCOORDINATION
EIA PROCESS
Screening
Scoping
Baseline Data
Effects Prediction
Mitigation
Impact Assessment
EIA Review
Implementation Monitoring
Need/Justification
Existing data sources include:• government data bases and routine
monitoring programs, other agencysources e.g. NGOs, academic com-munity;
• historical studies in study area (pub-lished and unpublished literature);
• past experience at similar projects(e.g. UNEP sponsored INFOTER-RA and the Global EnvironmentalMonitoring System (GEMS) databases);
• aerial photographs and satelliteimages (e.g. SPOT, LANDSAT,NOAA);
• traditional knowledge of native andlocal people;
• maps, census data, historicalrecords.
13
Planning for field studies can be carriedout effectively using a workshopapproach as well. Field study planningworkshops should be directed towardsthe development of hypotheses of effectwhich describe the pattern of ecologicalprocesses whereby a project action maylead to changes in one or more environ-mental component. These hypothesesof effect provide a number of links (eco-logical processes) which can be investi-gated through further studies (Figure 5).
The field study planning process shouldset the spatial and temporal boundariesfor subsequent studies. The spatialboundary should define the study areawithin which an effect is likely to bedetectable (Figure 6). For hydroelectricdevelopments, natural environment con-cerns, like water quality and fisheries,will generally be limited to within thedrainage basin while socio-economicconcerns, like migration of workers andcommunity impacts, may spill overdrainage basin boundaries into adjacentareas/ecosystems. It is important thatthe full range of potential on-site andoff-site effects be identified andassessed.The temporal boundary maydefine whether an effect will occur daily,seasonally, or after several years.
Field study terms of reference shouldlist the objective of the study and indi-cate how the results will be interpreted.When terms of reference are developed,consideration should be given to thepotential costs of the work. Some pre-liminary budgeting should always beundertaken during the study conceptu-alization phase. If studies are recom-mended as the result of a scoping work-shop involving the regulatory agencies orpublic, then a preliminary costingshould be undertaken before the propo-nent makes a commitment to do thestudy.
Study area logistical considerations suchas access and field subsistence (fieldcamps) for scientific field studies inremote areas may influence technicalfeasibility, costs and safety planning.Many future energy projects will be inrural or remote areas without properroad access. In these situations, logisticscan represent an important componentof project costs which in turn can influ-ence the technical feasibility. Wheneverpossible the proponent or their consul-tants should employ local personnel tocarry out field programs.
Due to the seasonal requirements of cer-tain field studies, e.g. fish spawning andmigration studies, scheduling is animportant consideration in the planning
FIGURE 6: Typical SpatialBoundaries for a Hydroelectric
Project
�
Changes in the pattern of flow (volume, timing, and amount of discharge)may lead to changes in resident fish populations
Changed distribution and abundance of fish
FIGURE 5:Example of a Hypothesis of Effect
14
of baseline studies. Study requirementsshould be determined in advance so thatcritical field seasons are not missed. Insome circumstances, a full year may belost by not initiating field studies earlyenough.
Proper data management is important,especially when there are large studiescovering long spans of time and costingmillions of dollars. Data collected dur-ing baseline studies is generally managedand analyzed according to the two maintypes, numerical data and spatial data.Computer databases are often used tohelp organize and manage numericaldata for use by scientists and EIA practi-tioners, while Geographic InformationSystems (GIS) are often used for thespatial data (see EIA Tools and Methodssection).
STAKEHOLDER INVOLVEMENT
Public and stakeholder involvement inthe EIA process is now widely recog-nized as being an essential component.It leads to better and more acceptabledecision-making.
The public is an important source oflocal and traditional knowledge about aproject’s physical site and likely environ-mental effects. Through public partici-pation activities, project proponents canobtain this information, better under-stand and respond to public concerns,and inform people about decisions.
Taking stakeholder viewpoints intoaccount improves project viability. TheWorld Bank (1991) has found thatwhere such views are seriously consid-ered and incorporated in the EIAprocess, projects are likely to be moresuccessful.
Public and stakeholder involvement isparticularly important during the scop-ing, impact assessment, and mitigationphases of an EIA. During scoping, pub-lic involvement is undertaken to ensurethat all the significant issues are
identified, local information about theproject is gathered and alternative waysof achieving the project objectives areconsidered. Public involvement is par-ticularly important in understanding thenature and extent of potential socio-cul-tural impacts. Further involvement ofthe public in the impact assessmentphase can help to avoid biases and canreveal local values and preferences.Public input can also assist in the con-sideration of mitigation measures whichwill be incorporated into the design andconstruction of the favored alternative.
Given its broad scope, an EIA studypotentially involves a large number ofstakeholders. The concerns and viewpoints of all parties interested inand affected by the project should betaken into account in reaching a deci-sion on the project. Informed views ofdiverse segments of the affected popula-tion are critically important to the EIAprocess because different groups use andare familiar with different parts of theenvironment and will be affected to dif-ferent degrees by the project.
The EIA coordinator and the EIA pro-ject team should be responsible for iden-tifying the concerns of all potentialstakeholders and, where reasonable, toresolve those concerns (e.g. by correctingmisunderstandings, making
commitments to further study, mitiga-tion or compensation etc.).
Where possible, a consultation programshould be coordinated by a publicinvolvement specialist. The objectives of the consultation effortshould be to:
• inform interested groups and indi-viduals about the proposed develop-ment: This will minimize misunder-standings about the scope andimpacts of the project;
• provide opportunities for timely andmeaningful input;
• ensure decisions have adequatelyconsidered the concerns and valuesof the stakeholders, particularly theaffected community(ies);
• seek approaches to problem solvingand hopefully resolve conflicts;
• obtain local and traditional knowl-edge before decision-making;
• provide better transparency andaccountability in decision-making.
Methods of public involvement are sum-marized in Appendix 3. Ideally a mix ofthese methods is used over the EIAprocess. For example, a public informa-tion center or an open communitymeeting could be used to launch a pro-ject EIA, i.e. for the public to learnabout proposals and offer comments;small workshops could be used duringscoping to discuss specific concerns andidentify opportunities to resolve thoseconcerns; and surveys, interviews orquestionnaires could be used to seekinput during impact assessment. Projectprogress reports or newsletters can beused to encourage involvement over theproject life cycle. Methods used need tosuit the social and cultural environment.
Care is required to ensure that a fair andbalanced representation of views issought and that the views of the poor orminority groups are not overwhelmedby those of the more influential orwealthy. Cultural and social patterns,and local decision-making processes,should be taken into consideration in
Potential stakeholders include:• an investor;
• regulatory authorities;
• government policy makers;
• regional planners;
• the local community and its repre-sentatives;
• public interest groups (i.e., non-government organizations orNGO’s);
• politicians
• customers
• Aboriginal Peoples
• resource users
15
designing a public involvement program (e.g. customs).
Information used in any consultationprogram (particularly for the public)should be specially prepared to minimizethe use of technical jargon and be readi-ly understandable. Written materialshould be translated into local languageswhere necessary. Where many may beunable to read, oral discussion and visualpresentations may be needed. Videosmay be particularly useful for this purpose.
It is very important to document keycomponents of the stakeholder involve-ment and consultation process. Thisdocumentation could be used as evi-dence in hearings or regulatory reviewsof the project EIA, and will help demon-strate that proper notification andinvolvement of all key stakeholdergroups has been done. Means of docu-menting the consultation processinclude, chronologies of major events ordecision points, good records of corre-spondence sent and received, copies ofquestionnaires and public survey orfeedback forms, minutes of meetingswith various stakeholder groups, andvideos of public information meetings.
Inter-agency coordination is crucial toan effective EIA process. Environmentalissues tend to cross regional, sectoral andeven international boundaries. As such,the regulatory management of theseissues can be spread throughout variouslevels and departments of governments.To be effective, an EIA study must haveaccess to and make use of or share allavailable information, specialized knowl-edge and policy direction related toimportant issues. Inter-agency coordi-nation is best achieved through meet-ings with key government agencies atkey points in the EIA process.
PREDICTION OF EFFECTS
Effects prediction is the most challeng-ing and controversial stage of the EIAprocess. Development projects can setin motion a complex chain of eventsthat can affect the environment in wayswhich are often difficult to predict inadvance (Sadar 1994). Reliable methodsare available for predicting some envi-ronmental parameters, e.g. air qualityimpacts, whereas other predictions willbe based more on professional judg-ment, e.g. impacts on wildlife populations.
Effects prediction attempts to answerthe following questions:
• How will a particular project activitygive rise to an impact?
• How likely is it that an impact willoccur?
• What will be the magnitude of eachimpact?
• What will be the spatial and tempo-ral extent of each impact?
An environmental effect is defined as areaction to a change in the environmentas a result of a project action.Distinctionis often made between direct and indi-rect effects, and normally both types ofeffects are addressed in an EIA study.
Direct effects are the immediate physi-cal effects and alterations to the environ-ment which follow as a direct cause-effect consequence of a project activity(e.g. reservoir flooding can result inbioaccumulation of methylmercury inthe aquatic food chain (Figure 7)).
Indirect effects are effects induced orstimulated by the project, and at leastone step removed from a project activityin terms of cause-effect linkages (e.g.project access road construction in aremote area can result in secondarydevelopment along the access road).
Methylmercury
Natural Water Level
Raised Water Level
Methylmercury
FIGURE 7: Transfer of Methyl Mercury After a New Reservoir is Filled
PUBLICCONSULTATION/INTER-AGENCYCOORDINATION
EIA PROCESS
Screening
Scoping
Baseline Data
Effects Prediction
Mitigation
Impact Assessment
EIA Review
Implementation Monitoring
Need/Justification
16
The cumulative effects of placing afacility in a given environment shouldalso be considered as part of effects pre-diction. An EIA should look at anycumulative effects that are likely toresult from the project in combinationwith other projects or activities that havebeen or will be carried out in the fore-seeable future.
Environmental effects are often seen asisolated or separate from one another.In reality, however, they interact overtime and space. Therefore, to addresscumulative environmental effectsrequires analysts to think “cumulative-ly”, taking into account:
• time and geographic boundaries;
• interactions between the project’senvironmental effects;
• interactions between the project’senvironmental effects and those ofother projects and activities.
It is critical to consider environmentaleffects during project construction, com-missioning and operation for each pro-ject alternative. EIAs often focus onoperation of a facility, however con-struction activities can have significanteffects as well and should not be forgotten.
Both positive and negative impactsresulting from the project should beidentified and assessed. These includeeffects on both the natural and man-made (or social) environments. A short-coming in many EIAs is that social andcultural aspects are not given muchprominence at the effects predictionstage. This is unfortunate since socio-cultural impacts are often stronglylinked to changes in the natural environ-ment and are the impacts that the localcommunity will feel most acutely in
their everyday lives (e.g. loss of a fisheryand/or food source due to methylmer-cury accumulation in fish). Therefore itis important that socio-cultural impactsbe considered, where possible, in everydiscussion and assessment of biophysicalchange. These should include:
• effects on human health;
• effects on socio-economic conditions;
• effects on physical and cultural her-itage, including effects on things ofachaeological, paleontological, orarchitectural significance;
• effects on the current use of landsand resources for traditional purpos-es by aboriginal persons.
It is important that the temporal andspatial extent of effects be carefully con-sidered in predicting impacts.Electricity project construction andoperation can have local, regional andglobal effects. For example, the con-struction of a hydroelectric generatingstation will have relatively short-term,localized impacts, while the operation ofthat station can change the water leveland flow regime of the river basin.Methane given off by reservoir floodingcan contribute to global climate change.
In order for impact predictions to beuseful to decision-makers, the predictions must generally:
• fulfill the environmental assessmentobjective of contributing to
informed decision-making (e.g. deci-sions on the evaluation of projectalternatives, need for and design ofenvironmental protection/mitigationmeasures);
• contain an estimate of the uncertain-ty expected; and
• be verifiable through a post-develop-ment monitoring program.
Predictions which are vague, generalizedspeculations are of little value to makinginformed decisions. Wherever possible,impact predictions should be statedexplicitly, and accompanied with a dis-cussion of the method used, as well asthe limitations of the analysis.
Effects prediction is carried out in twostages: First, effects are identified andpathways are determined that link pro-ject activities to environmental compo-nents; then models and other analyticalmethods are developed and applied toquantify/estimate potential environmen-tal effects.
Identification of Effects
The identification phase attempts toanswer the question - What will happenas a result of the project? At this stage,the potential sources and pathways forproject effects are identified. Figure 9shows typical activites associated withconstruction of a hydroelectric project,and Table 2 summarizes potentialimpacts associated with these activities.
Examples of cumulative environmen-tal effects include global warmingcaused by the build-up of greenhousegases in the upper atmosphere, andloss of biodiversity.
DOWNSTREAM EFFECTS
FIGURE 8: Typical Operational Concerns at a Hydroelectric Facility
17
COMPONENT POTENTIALLY AFFECTED
Atmospheric Environment Aquatic Environment Terrestrial Environment Resource Use
SOURCES OF Water Aquatic Geology HeritageEFFECTS Dust Noise Vibration Quality/ Biota Hydro- Vegetation Wildlife Aquatic Terrestrial Resources
Sediments geology Soils
Site access
Sitepreparation
Intakeconstruction
Tunnel andcanalexcavation
Materialextractiondisposal
Reservoirclearing
Constructionofpowerhouse
Cofferdamsandtemporaryflowdiversion
TABLE 2: Potential Sources of Environmental Effects During Hydoelectric Project Construction
Typical effects for hydroelectric projectsare given in Appendix 2.
Identification of key effects can beachieved by using one or all of the fol-lowing methods:
• compile a list of important impactsfrom analysis of previous projects ofa similar nature in a similar environ-mental setting;
• use checklists, networks, matrices ormap overlays to match sources ofproject impact with potential recep-tors (see EIA Tools and Methodssection);
• use hypotheses of effect to map outlinkages and potential impacts onthe environment.
Much of this identification work mayhave already been done at the scopingphase where critical issues should havebeen defined.
Broad areas of concern associated withenergy projects include effects on:
• air quality
• water quality and use
• land use
• resource use (fuels and otherresources)
• terrestrial ecosystems
• aquatic ecosystems
• social systems/community life
• human health
The level of concern for each of theseparameters will change with the type ofenergy system utilized and location ofthe project. For example, combustion-based (like wood burning) generationprocesses will result in greater concernfor air emissions while concerns related
• • • • •
• • • • • •
• • • • • • • • •
• • • • • • •
• • • • • • • • •
• • • • • • • • •
• • • • • • • • • • •
• • • • • • •
18
to hydroelectric generation will be large-ly aquatic-based.
For electricity projects, typical sources ofenvironmental effects include:
• fuel extraction and supply
• facility construction
• atmospheric emissions
• aquatic discharges and changes inflows and water levels
• land displacement
• waste production and management
• transmission corridors
• access roads and transportation
Quantification/Estimation of Effects
Having identified the key parametersrequiring assessment, a variety of analytical techniques can be used to
predict potential environmental effects.Prediction often follows an impact with-in a single environmental parameter(e.g., a toxic effluent) into its subsequenteffects on many other parameters (e.g.,reduced water quality, adverse impactson fisheries, economic effects on fishingand resulting socio-cultural changes).
A number of methods which are com-monly used in estimating/quantifyingenvironmental effects include (seeAppendix 3):
• pre-project experiments (e.g. toxicitytesting);
• hypotheses testing;
• mathematical modeling (e.g. air dis-persion, hydrology and hydrody-namics, water quality, groundwaterquality, erosion and sedimentation,
biotic habitat, oil spills, and riskanalysis);
• physical modeling (e.g. hydraulicmodels or wind tunnels);
• computer simulation (useful inassessing visual impacts of a project);
• constraint mapping (useful for predicting impacts related to land orresource use displacement, particu-larly siting and routing).
To prevent unnecessary expense, thesophistication of the prediction methodshould be properly matched with thescope of the EIA. For example, a com-plex mathematical model of atmosphericdispersion should not be used if onlysmall amounts of relatively harmless pol-lutants are expected to be emitted.Simpler models may suffice. These typeof requirements should be establishedand documented at the scoping phase.
All prediction techniques involve somedegree of uncertainty. It is important torecognize this uncertainty, and stateprobabilities and margins of errorinvolved in predicting the likely impactof a proposed project.
IMPACT ASSESSMENT
PUBLICCONSULTATION/INTER-AGENCYCOORDINATION
EIA PROCESS
Screening
Scoping
Baseline Data
Effects Prediction
Mitigation
Impact Assessment
EIA Review
Implementation Monitoring
Need/Justification
FIGURE 9: Typical Construction Activities Associated with aHydroelectric Project
19
Once predictions are made, the nextstep is to decide if these predictedchanges really “matter”, i.e. are signifi-cant or are perceived to be important.
The significance of environmentaleffects is generally evaluated in terms oftheir spatial extent (geographic distribu-tion), duration (short vs. long-term),magnitude (measured level of change ina parameter and whether thresholds arebeing exceeded), reversibility (reversibleversus irrevocable), and special sensitivi-ty (whether an impact affects a sensitivearea within the country - like a naturereserve).
Judgment of significance can be basedon one or more of the following:
• comparison with laws, regulations oraccepted standards (i.e., does theproject meet legal requirements, arestandards exceeded?);
• reference to pre-set criteria (such asthreshold limits, dose-response rela-tionships, conflicts with protectedsites, features or species, and/ormaintenance of local breeding populations);
• consistency with government policyobjectives and goals; and/or
• social acceptance (i.e., acceptabilityto the local community or the gener-al public).
The impact evaluation stage usuallyinvolves utilizing a mixture of bothquantitative comparison and qualitativejudgment.
Impact evaluation should be undertakenin a way that allows a comparison ofproject alternatives and facilitates thecommunication of results to the publicand decision-makers. It should be tiedback to issues and concerns raised dur-ing scoping exercises and issue identifi-cation. Additional stakeholder inputwill likely be required during this stageof the EIA process to help determine thesignificance and relative importance ofimpacts.
MITIGATION ANDRESIDUAL EFFECTS
If identified impacts “matter”, i.e. aresignificant and/or important, it is neces-sary to identify and implement mitiga-tion measures. Mitigation measures areselected to reduce or eliminate the sever-ity of any predicted adverse environ-mental effects and improve the overallenvironmental performance and accept-ability of the project.
Where mitigation is deemed appropri-ate, a proponent should strive to actupon effects, in the following order ofpriority, to:
1. Eliminate or avoid adverse effects,where reasonably achievable.
2. Reduce adverse effects to the lowestreasonably achievable level.
3. Regulate adverse effects to an accept-able level, or to an acceptable timeperiod.
4. Create other beneficial effects to par-tially or fully substitute for, orcounter-balance, adverse effects.
Mitigation is an integral part of impactevaluation. It looks for better ways ofdoing things so that the negativeimpacts of the proposal are eliminatedor minimized and the benefits are
PUBLICCONSULTATION/INTER-AGENCYCOORDINATION
EIA PROCESS
Screening
Scoping
Baseline Data
Effects Prediction
Mitigation
Impact Assessment
EIA Review
Implementation Monitoring
Need/Justification
Factors used in determining whether ornot environmental effects are adverseinclude (CEA A 1994):
• negative effects on the health ofbiota including plants, animals, andfish
• threat to rare or endangered species
• reductions in species diversity or dis-ruption of food webs
• loss of, or damage to, habitats,including habitat fragmentation
• discharges or release of persistentand/or toxic chemicals, microbialagents, nutrients (eg. nitrogen, phos-phorus), radiation or thermal ener-gy (eg. cooling wastewater)
• population declines, particularly intop predator, large, or long-livedspecies
• removal of resource materials (e.g.peat, coal) from the environment
• transformation of natural landscapes
• obstruction of migration, or passageof wildlife
• negative effects on the qualityand/or quantity of the biophysicalenvironment (e.g., surface water,groundwater, soil, land and air)
• negative effects on human health,well-being, or quality of life
• increase in unemployment orshrinkage in the economy
• detrimental change in the currentuse of lands and resources for tradi-tional purposes by aboriginal persons
• negative effects on historical, archae-ological, paleontological, or architec-tural resources
• loss of, or damage to, commercialspecies or resources
• foreclosure of future resource use orproduction
• decreased aesthetic appeal orchanges in visual amenities (e.g.scenic views)
20
enhanced. As soon as significant adverseimpacts are identified, discussionsshould be held to see if they can be‘designed out’ through changes in pro-ject design, location or operation. It isimportant therefore, that there is goodintegration between the EIA team andproject design engineers.
Possible mitigation options for electrici-ty projects include:
• plan alterations (e.g. changes in con-struction scheduling to avoid sensi-tive life stages of wildlife);
• design alterations (e.g., differentroutes for transmission lines, differ-ent sites for hydroelectric developments);
• provision of environmental protec-tion equipment (e.g., noise mufflers,pollution abatement equipment);
• changes in management practices(e.g., staff training, recycling wasteby-products instead of landfilling,public education);
• changes in operation (e.g. restrictionof water level fluctuations in hydro-electric reservoirs).
A summary of typical mitigation mea-sures that can be applied for hydroelec-tric projects is provided in Appendix 2.
Where residual impacts remain aftermitigation has been applied, some formof monetary or other compensation(e.g., create new fish spawning habitat,or build a new school) might be consid-ered or required to ensure the public donot bear costs which are greater than thebenefits which accrue to them from theproject.
Special financial and other assistance tocommunities affected by the operationand construction of major facilities maybe necessary. Community ImpactAgreements (CIAs) can be developedwith host communities to ensure thatassistance will be available to help localareas adjust to the possible “boom andbust” effects often associated with theconstruction and operation of majorelectricity projects. This type of agree-ment might also provide a sum ofmoney to the community to help offsetidentifiable local, social and communityeffects, and establish a monitoring pro-gram to measure the impacts on thecommunity during construction andoperation.
Resettlement Planning
Project planning should attempt toavoid or minimize involuntary
resettlement. However, when forcedresettlement is unavoidable and fullyjustified, a resettlement plan should beformulated and financed. The plan willensure that people displaced will be pro-vided with development opportunitiesto improve, or at least restore, the livingstandards they had before the project.
Mitigation and compensation measuresshould be identified early and properlycosted and incorporated in the overallcapital budget for the project to ensurethat recommended actions do get car-ried out. Mitigation/compensation costscan account for up to 10 percent of totalproject costs, but are more typically inthe 3 to 5 percent range (World Bank1991).
21
EIA IN DECISION MAKING
In order to arrive at the “preferred” pro-ject, an evaluation and comparison ofthe project alternatives in terms of theirpositive and negative effects on the envi-ronment is made. This evaluation
process involves specifying and compar-ing the trade-offs among alternatives,based on the evaluation of the predictedeffects and proposed measures to miti-gate any adverse effects of each alternative.
The public involvement program is animportant component at this stage, andshould be organized to provide inputs tothe evaluation of alternatives and theidentification of trade-offs. It must berecognized that decisions resulting froman EIA may be based as much on sub-jective judgments, involving values,opinions, beliefs, and political agendasas on the results of the scientific studies.
Various qualitative and quantitativetools are available to evaluate alterna-tives, and to arrive at a preferred project(MOE 1990, Wolfe 1987, Rau and
Wooten 1980)(see also Appendix 3 -EIA Tools and Methods). Lendingagencies and regulatory authorities donot generally specify which methodolo-gy is to be used in the evaluation ofalternatives, and selection of the pre-ferred alternative, since each project isunique in itself. All evaluation methodsresult in some form of ordering of alter-natives according to preference.
The EIA document should describe theevaluation process and the methodologyused in arriving at the recommendedproject, so that decision-makers are ableto trace each step of the process. Theassumptions and subjective judgmentsused in the evaluation should be statedin the document. As well, the issuesleading to and influencing the selectedcourse of action, and any unresolvedissues, should also be described.
PUBLICCONSULTATION/INTER-AGENCYCOORDINATION
EIA PROCESS
Screening
Scoping
Baseline Data
Effects Prediction
Mitigation
Impact Assessment
EIA Review
Implementation Monitoring
Need/Justification
A Resettlement Plan should include:• Resettlement policies and objectives
• Baseline data on affected area andpopulation; estimated capacity ofthe receiving area to sustain addi-tional population
• Environmental risks of the resettle-ment plan, eg. increased pressure onnatural resources, construction ofinfrastructure
• An Environmental ManagementPlan to address these risks to miti-gate impacts on and protect the nat-ural and human environment
• Organizations responsible for plan-ning, development, training, imple-mentation and monitoring (shortand long-term)
• Strategies for participation of affect-ed people
• Development plan for new sites anddetailed layout
• Monitoring requirements
• Cost estimate
• Financial plan, implementationschedule
FIGURE 10: Project Decision Making
22
The most acceptable alternative whichemerges from the evaluation and decision-making process is usually therecommended project to be put forwardin the EIA document by the proponentfor approval. Any residual effects whichcannot be avoided or alleviated throughmitigation or compensation measuresshould be described in the overall assess-ment section of the EIA document. It isthe job of decision-makers to assimilateall the information provided and decideif the benefits to be accrued through aproject justify the potential disruptionsthat will occur (Figure 10).
DOCUMENTATION
All pertinent information that was col-lected as part of the EIA process, as wellas the manner in which it was assessedand the judgments used in selecting thepreferred alternatives must be describedin an EIA document.
The EIA document is the main vehiclefor the project proponent to presenttheir case (i.e., rationale and justifica-tion) for proceeding with a proposeddevelopment activity. It is critical thatinformation presented in this report isclear, focused, and useful to decision-makers.
The language of the EIA documentmust be clear and concise. The infor-mation presented should be balanced,relevant, and succinct. Detailed techni-cal data should be generally confined toappendices or referenced to reports. Asthe EIA document is used for decision-making, it should focus on clarifyingissues which are important to projectdecisions, such as trade-offs, evaluationcriteria, evaluation and selection process,irreversible impacts, etc.
An EIA document should typicallyinclude:
• Executive Summary providing a con-cise discussion of significant findingsand recommended actions.
• Policy, legal and administrative
framework within which the EIA isprepared.
• Project Need/Justification.
• Description of project and its alter-natives in a geographic, ecological,social and temporal context.
• Description of existing environmentincluding a description of relevantphysical, biological, resource use andsocio-economic conditions prevail-ing before the project is developed.
• Discussion of potential environmen-tal impacts, both positive and nega-tive, that are likely to result from theproposed project - including anidentification of mitigation mea-sures, residual impacts that cannotbe mitigated, opportunities for envi-ronmental enhancement, and uncer-tainties associated with impact predictions.
• An analysis of alternatives, whichcompares design, site, technologicaland operational options systematical-ly (and quantitatively where possi-ble) in terms of potential environ-mental impacts, capital and operat-ing costs, appropriateness, and insti-tutional and monitoring requirements.
• Impact management plan includingproposals for feasible and cost-effec-tive mitigation measures that mayreduce potentially significant adverseenvironmental impacts to acceptablelevels; and compensatory measureswhere mitigation measures are notpossible.
• A summary of the EIA for the gener-al public
• Appendices - including a list of EIAcontributors, references and recordof inter-agency meetings.
Detailed data and analysis that areimportant but not critical to the EIAsfindings should be provided in a seriesof support documents to the main EIAreport.
PROJECT IMPLEMENTATION
The EIA process does not stop once aproject is approved. During implemen-tation of a project, a proponent isresponsible for ensuring that the envi-ronmental commitments made to regu-latory agencies, lending agencies andother stakeholders during the EIAprocess are met.
EIA follow-up documents, such as anImpact Management Plan, should beprepared, defining for project staff andany consultants or contractors, the envi-ronmental guidelines, regulations andcriteria to be followed in the design,construction and operation of the gener-ating station including the specific com-ments and conditions imposed by gov-ernment agencies during the EIAprocess.
Project specific environmental construc-tion guidelines should be developed.These should specify precautions andmitigation measures for constructionactivities, and include a plan for moni-toring those activities which could havea significant environmental effect (e.g.stream crossing, dredging, dewatering).
Construction monitoring, includingfield inspections and surveys, should be
PUBLICCONSULTATION/INTER-AGENCYCOORDINATION
EIA PROCESS
Screening
Scoping
Baseline Data
Effects Prediction
Mitigation
Impact Assessment
EIA Review
Implementation Monitoring
Need/Justification
23
carried out by an environmental special-ist, to ensure that environmental protec-tion requirements are being met. It isimportant to plan and budget for envi-ronmental construction monitoring aspart of the project.
If construction is to be contracted out,specific environmental requirementsduring construction should be built intoconstruction bidding documents andcontracts to ensure they are met (e.g.requirements for local hiring).
Environmental effects monitoring isused to identify environmental changesresulting from the implementation ofthe project. In the context of EIA,effects monitoring programs are carriedout to achieve the following results:
• to ensure that the facility is meetingall environmental regulatory require-ments, and that commitments madein the EIA document and/or theconditions of approval are beingmet;
• to test impact hypotheses, and toverify the predictions and assessmentof environmental effects, thus con-tributing to better assessments in thefuture;
• to evaluate the performance effec-tiveness of mitigation;
• to compare actual and predictedchanges to the environment, so thatimmediate actions can be taken tomitigate unanticipated impacts;
• to strengthen confidence by bothgovernment and the public in theEIA process, the decisions made, thestation design etc., especially when adecision is made to proceed with aproject with a high level of uncertainty.
The monitoring programs to be carriedout during the construction and opera-tion of the undertaking are normallydescribed in the EIA document.
The effects monitoring program shouldinclude several years of pre-operationalmonitoring (depending on the scope ofthe project), and continue several years
into the operation of the project. Thepre-operational phase establishes a base-line against which to measure change,while the operational phase measures thechange and trends over time. Theresults of the effects monitoring pro-gram should be summarized in an
Environmental Effects Report.It is important that information andexperience gained through the monitor-ing activities are fed back into the EIA
evaluation and analysis system toimprove the quality of future assessmentstudies. This particular element of theprocess is known as EIA verification.EIA verification, also known as EIAauditing, is that part of the EIA processwhich evaluates the accuracy or effec-tiveness of hypotheses and predictiveand assessment methods used in previ-ous project EIA documents, and drawson past experience to improve futureEIA processes. EIA verification usesaudit and other information obtainedfrom compliance monitoring, effectsmonitoring and from other relevantsources, as inputs to future projects.
The objectives of EIA verification are:
• to verify predictive models, policiesand general EIA methods for futureapplications by comparing past pre-dictions, assumptions, etc. with mea-sured and documented effects;
• to assess the effectiveness of EIAmethods, post-approval effects moni-toring, and mitigation and compen-sation measures for future applica-tions; and
• to improve EIA methods, and miti-gation and compensation measuresfor future applications.
The use of EIA verification can improvea number of EIA process components,including predictive models, studymethods, mitigation strategies, policies,scoping and early planning exercises,regulatory involvement and publicinvolvement programs. The result ofimproved EIA components will be amore cost-effective and efficient EIAprocess.
Indicators to be monitoredfor a hydroelectric projectmay include:
Water Quality -
Temperature, dissolved oxygen(reservoir, tailwater),chlorophyll asecchi disc and colour, turbidityand suspended solids
Mercury Contamination -
Fish muscle (reservoir, down-stream), human hair
Erosion and Sedimentation -
Videotaping, aerial photography &GIS, bathymetry, suspended solids
Fish Entrainment -
Acoustic assessment - high frequen-cy sonar, small mesh nets
Flow Regulation -
Stage-discharge surveys, hydraulicsurveys, substrate surveys (visual, sonar, dredges)
Population Effects -
Fish index netting, acoustic assessment, fishery results
24
The methodologies available to under-take EIA processes are numerous and arethe subject of many textbooks and pub-lished articles. Appendix 3 presents a listof selected EIA techniques, their applica-tion and relative advantages and disad-vantages. References for each techniqueare provided. Appendix 3 also providessome guidance as to what stage in theEIA process these techniques might haveapplication (e.g. scoping, screening).EIA methods are generally selected tomeet and reflect the nature of the pro-ject, its setting, and societal conditions.
Well-documented overviews of EIAmethodologies can be found in a num-ber of general references (Rau andWooten 1980, Munn 1975, MOE1990, CEARC 1986, Ross 1974, Canter1996, Warner 1973, Beanlands &Duinker 1983, Wolfe 1987, Clark1978). Some of the more commonlyused tools are summarized below.
Checklists
A checklist is a list of environmentalparameters to be investigated for possi-ble impacts. It serves as an initial refer-ence guide, for identifying relevant envi-ronmental factors for consideration inan EIA. Experience from previous pro-jects can be helpful in identifying rele-vant environmental components thatshould be included in the analysis.Checklists do not require the explicitestablishment of direct cause-effect linksto project activities. They do not inthemselves provide for the prediction orassessment of impacts.
Matrices
A matrix goes one step further than achecklist by linking a list of possibleeffects with specific actions and projectactivities. Matrices are two-dimensionaltables, with activities associated withvarious phases of the the project on oneaxis, and environmental componentslisted on the other (eg. see Table 2).The entries in the cells of the matrix can
EIA Tools & Methods
“EIA methods are generally selected to
meet and reflect the nature of the pro-
ject, its setting, and societal conditions.”
25
be either qualitative or quantitative estimates of impact. Simple matriceswill indicate only that an impact isexpected to occur, while more complexmatrices may give quantitative estimatesof impact magnitude and significance.
Networks
Networks are an extension of informa-tion found in matrices. A network dia-gram demonstrates linkages between andamong the environmental components,providing some indication of how anecosystem operates. An understandingof the interrelationships and inter-dependence in the ecological chain ofcausation is useful in identifying secondand third order effects. It also hints atprobable additive, interactive, synergisticand/or cumulative effects.
Map Overlays
Map overlay techniques rely on a set ofmaps of project effects, or environmen-tal characteristics or themes that describethe project area. These maps can beoverlain to produce a composite charac-terization of a regional environment.Thematic map overlays can aid in iden-tifying geographic areas of particularenvironmental sensitivity and can visual-
ly provide a clue as to possible incre-mental and cumulative effects (Figure11). Manual overlay techniques can beused as an effective tool for analyzingsmall projects. For large projects, geo-graphic information systems (GIS) arefavoured for map overlay analysis, dueto their capacity for handling very largedata sets incorporating many map layers.
Geographic Information SystemsGeographic Information Systems (GIS)are computer based systems to supportthe capture, management, manipulation,analysis, modeling and display of spatialdata. UNEP’s Global ResourcesInformation Database (GRID) is a glob-al environmental data system whichassembles, processes and supplies geo-referenced environmental informationto users around the world. It is intend-ed to be a world-wide GIS networkwhich is accessible from any country inthe world, and which can support indi-vidual project EIAs. The most signifi-cant uses for GIS technology in EIAs arefacility siting, modelling, change detec-tion and decision support.
The scale and scope of anticipatedimpacts will influence the type of
method selected. In general, even thelargest projects will begin with the use ofchecklists, matrices and network dia-grams to aid in the identification of per-tinent environmental components andecosystem linkages.
FIGURE 11: Sample ThematicMap Overlays
26
To ensure an EIA study is carried out inan efficient and effective manner, it isimportant that the EIA process is prop-erly managed and administered. Moreoften than not it is poor process man-agement that leads to delays in complet-ing EIA studies.
An EIA is usually carried out by thoseresponsible for a project - i.e., the pro-ject proponent. In order to perform anEIA study, it is usually desirable toassemble a multidisciplinary team(Figure 12). Typically, this EIA teamconsists of an EIA coordinator (or teamleader) and a variety of trained technical and scientific experts (in fields such asenvironmental engineering/science,process engineering, waste and pollutioncontrol, planning, geography, biology,landscape design, public involvement,and social science) who can address thefull range of issues and concerns relatedto the specific project under consideration.
It is preferable if these types of skills canbe found within the host country for theproject, in that local people will have agreater knowledge of local conditionsand issues. Where this is not possiblethese skills can generally be provided byforeign consultants. Ideally, the EIA
coordinator should be local. This coor-dinator can make decisions about whatcan be done locally by consultants, uni-versities and research organizations, andwhen to seek foreign input. The localcoordinator can also closely control thework of consultants to ensure that thework being undertaken is relevant tolocal needs and useful to potential deci-sion-makers.
The primary functions of the EIA pro-ject team of specialists are (for their par-ticular area of expertise) to:
• participate in scoping workshops todefine the work program, asrequired;
• define baseline environmental conditions;
• define all major environmentalissues;
• predict environmental impacts;
• recommend mitigative measures tominimize impacts and compensationwhere residual impacts still persist;
• identify all environmental standardsinfluencing project design and rec-ommend appropriate control/protec-tion measures;
• conduct and/or participate in pub-lic/government consultation programs;
• prepare sections of the EIA docu-ment and necessary support techni-cal studies as required.
EIA ProjectManagement
“An EIA study is very much an exercise
in issues management.”
EIA Coordinator
Public
Government�Agencies
Natural�Environment�
Disiplines
Consultants
Social�Environment�Disciplines
Project�Engineering
FIGURE 12: Multidisciplinary EIA study team
27
Functions of the EIA coordinatorshould include:
• definition of the EIA work programin relation to the overall projectplanning and decision-makingprocess;
• interpretation of the environmentallegislation compliance requirementsfor the project in question;
• breakdown (and budgeting) of theEIA work program into specificwork packages to be completed bycontributing specialists;
• scheduling of the EIA work program;
• hiring consultants and managingtheir contracts/activities;
• direct liaison with the decision-mak-ers, regulatory authorities, mediaspokesperson, public interest groups(NGOs), local community leadersand the general public;
• transmittal of design recommenda-tions, mitigation requirements,approvals requirements etc. from theEIA team to the project design team;
• monitoring progress of the workprogram;
• coordination of the final EIA documentation;
• coordination of follow-up require-ments during project implementation.
In addition to the technical/scientificspecialists performing EIA studies, cer-tain project engineering and planningstaff may also have to become involvedin the EIA study to supply engineeringand design information required to carryout the assessment. These project staffwill also have to be intimately involvedin the discussions related to project miti-gation and compensation measures.
Both the costs and lead times necessaryfor approval of EIA submissions varysubstantially from project to project.The expectations and general concernsof government and the public areimportant factors in scoping EIA studiesand ultimately the time required forapproval.
Costs related to carrying out EIA studiesfor major energy projects can vary signif-icantly, but are typically about 1-5 per-cent of overall project capital costs
(Figure 13). The largest component ofan EIA study is generally for baselineenvironmental studies, although mitiga-tion and compensation measures provid-ed during project implementation canalso be fairly significant cost items.Detailed costs are developed as part ofwork scope planning.
The time required to carry out an EIAstudy will vary with the type, size andcomplexity of the project; the character-istics of its physical, sociocultural andinstitutional setting; and the quantityand quality of environmental data that isalready available about the study area.Again, World Bank (1991) studies sug-gest that EIA studies can take between 6and 18 months, with 12 months beingtypical. An EIA for a major new gener-ating facility could take up to three yearsto complete, depending on the scope.
With respect to scheduling, one of thekey factors is the seasonal requirementsof field studies. Fisheries studies forexample may require spring and/or fall(wet and/or dry season) monitoring toassess impacts on migration and spawn-ing activities. Part of the planningprocess is to determine in advance allstudy requirements, so that field seasonsare not missed. In some circumstances,a full year may be lost by not mobilizingfor field studies early enough.
To ensure effective management of anEIA study an EIA Work Scope docu-ment should be prepared by the EIAcoordinator. This is an internal projectdocument which contains a breakdownof work packages associated with thepreparation of an EIA, specific contribu-tors assigned to the work, and a budgetsummary and schedule for each workpackage.
An EIA study is very much an exercisein issues management. Critical issuesare identified during scoping andtracked throughout the EIA process. Inmany cases, these issues evolve andchange as the EIA process progresses, inresponse to changes in project design,changes in process participants and theintroduction of study findings or otherscientific information. To ensure a suc-cessful EIA process, it is important todevelop some sort of system to track andrespond to the dynamics of issue evolu-tion throughout the EIA process. Thiswill allow the EIA team to foreseepotential problems before they becomecritical and can cause significant sched-ule delays. A record of issue dynamicsthroughout the EIA process can also bevery helpful in focusing and organizingthe final EIA documentation by ensur-ing that the document concentrates onthe key issues of concern.
An Issues Status Report can be devel-oped and maintained by the EIA teamto monitor the status and record thechronology of issues development dur-ing the EIA process. The Issues StatusReport should include the followinginformation about each major issue:
• Description - a description of theissue and how it relates to the project
• Action Taken - a discussion of anyhistorical, current or planned actionsthat relate to the issue
• Issue Status - provide the currentstatus of the issue resolution process
• Contacts - provide a list of all thestakeholders (and a key contact per-son) with an interest in the issue anda statement of their concerns relativeto this issue
• Cross-Reference - provide an indica-tion how this issue relates to othermajor issues affecting a project.
EIA
EIA
FIGURE 13: EIA Costs for a Major Generating Station with aBreakdown of Costs in the EIA
28
The following guidelines will help to getthe most out of the EIA process:
• Only do full EIAs on projects withsignificant impacts. Projects shouldbe screened carefully to focus limited
funds and resources for EIA studieson those projects that really requiredetailed assessment.
• Focus on the main issues. It isimportant that an EIA does not try
to cover too many topics in toomuch detail. Effective scoping cansave both time and money by focus-ing EIA studies on the key issues.
• EIA requires the formation of amultidisciplinary team and the lead-ership of a strong EIA coordinator.The range of effects considered inEIAs requires the skills of a broadmix of technical experts to beemployed on an assessment team,lead by an EIA coordinator.
• Involve the appropriate persons andgroups in the EIA study. It isimportant to involve the right peopleand agencies in the EIA process.Aside from the EIA team itself, peo-ple who can contribute facts, ideas orconcerns to the EIA study are needed( e.g., scientists, engineers, policymakers, government representativesand representatives of public interestgroups and the local community) aswell as people who have directauthority to permit, control or alterthe project - the decision-makers(e.g., the developer, the aid agency,regulatory authorities and politi-cians).
• Baseline studies must focus on keyenvironmental indicators. Baselinedata should not be collected simplyto describe the environment - itshould have some value for the deci-sions that need to be made. Toensure baseline studies are focusedand useful, considerable effort shouldbe directed to defining those envi-ronmental parameters that reallyneed to be sampled to assist withproject assessment. Attempts shouldbe made to select environmentalparameters that will allow testableeffects predictions to be made.
Maximizingthe Value of EIA
“An EIA should be organized so that it
directly supports the many decisions
that need to be made regarding a
proposed project”
29
• Make maximum use of existinginformation before engaging inexpensive field studies. Conductingfull-scale field investigations in sup-port of EIAs can be expensive andtime-consuming, therefore existinginformation should be used whereverpossible. Maximum use should bemade of EIA experience and infor-mation about similar projects in sim-ilar environments when scoping andassessing impacts.
• There are no set rules or proceduresfor implementing and administeringEIA studies. Given the complexityof the task of conducting EIA stud-ies, there is no ideal or standard EIAmethodology. Certain methods -like the matrix approach - have beenwidely used and despite shortcom-ings, have produced reasonableresults. When it comes to EIAmethodologies, there is plenty ofroom for experimentation. Also,there is no reason why a compositemethod, involving several tech-niques, cannot be used in an EIAstudy. What is important, is to selectan EIA method that effectively assistswith each of the tasks of predictingand assessing impacts, and is appro-priate for the level of study and themoney and manpower resourcesavailable for carrying out the EIAstudy.
• It is important to consider effectsnot only at the project site but alsoin the area surrounding a site. Acommon error in carrying out EIAstudies is that the assessment ofpotential impacts and mitigationfocuses too much on the site beingdeveloped for a project. Oftenimportant impacts occur away fromthe site as a result of activities at theproject site. These off-site and/orcumulative effects need to be careful-ly considered in project planning andin developing mitigation and com-pensation programs.
• Present clear and appropriateoptions for mitigation of impactsand for sound environmental man-agement. Mitigation is an integralpart of effects assessment.Application of appropriate mitiga-tion can eliminate or reduce adverseeffects, and improve the net overallenvironmental performance of a pro-posed project. Where residualimpacts remain after mitigation hasbeen applied, some form of mone-tary or other compensation may berequired.
• Link information to decisions aboutthe project and make EIAs useful todecision-makers. An EIA should beorganized so that it directly supportsthe many decisions that need to be
made regarding a proposed project.It should be started early enough toprovide information relevant to theselection of appropriate technologyand design and continue throughoutthe various stages of project planningand review. Environmental inputshould be incorporated by the devel-oper in assessing project concepts,selecting routes or sites, judging pro-ject feasibility, designing the project,seeking approvals and in implement-ing the project.
• Post-EIA audits and monitoringprograms are essential to ensuringthat EIA commitments are carriedout and that future EIAs improve.
• To be effective, an EIA processrequires the support of a definedinstitutional framework and com-mitment to inter-agency coopera-tion. Interagency cooperation isimportant to ensure that an EIAstudy has access to and makes use ofall available information, specializedknowledge and policy direction relat-ed to important issues. To be mosteffective, it is important that theprinciple of EIA be incorporated intolegislation governing projectapprovals.
2
3
45
1EIA allows better project plan-
ning. The objective of EIA is to
ensure that potential problems are
identified and dealt with at an
early stage in project planning,
when changes in design or siting
will have relatively low economic
impacts.
EIA promotes more informed and
environmentally sound decision-
making. To be effective, EIA must
be an integral part of project plan-
ning and implementation. Where
EIA has been seriously incorporated
in project decision-making, experi-
ence has shown that, it can have a
positive effect on project
performance.
EIA does not have to be expen-
sive. EIAs can increase the capital
costs of projects at the design stage,
but this may well prove less costly
than subsequent expenditures on
pollution control and other remedi-
al measures, if required, especially
where extensive retrofitting of
equipment is required. One of the
main reasons for undertaking an
EIA is to avoid or reduce subse-
quent damage costs.
EIA complements traditional pro-
ject planning and assessment
methods. EIA should be viewed as
a complementary exercise, the pur-
pose of which is to provide decision-
makers with a comprehensive
review of the potential environ-
mental implications of alternative
courses of action. EIA is not meant
to replace the traditional role of
decision-making. It permits deci-
sion-makers to gain a clearer indi-
cation of the likely impacts of
alternative options and clarifies the
environmental trade-offs associated
with these options.
EIA provides an important link
throughout the project life cycle.
It is important that environmental
factors be considered on an equal
basis with technical and economic
factors throughout the project plan-
ning, assessment and implementa-
tion phases (i.e., integrated life cycle
environmental management). EIA
is one of the mechanisms which
appears to offer the greatest poten-
tial for the effective integration of
environmental concerns in inte-
grated energy planning. EIA can
provide an essential bridge between
technical and economic aspects of
energy planning and a wide variety
of contemporary environmental
concerns.
30
Key Messages
“EIA must be an integral part of project
planning and implementation.”
31
assessment - refers to analyzing andevaluating the potential impacts of pro-posed actions on the environment.
baseline - existing baseline conditionsare the current conditions of an areapotentially affected by a proposed pro-ject. Existing baselines are establishedprior to construction and operation of aproposed project in order to evaluate theeffects of the project.
biodiversity - refers to the variety of lifeon earth: the number of plants and ani-mals and other organisms that exist onour planet and the variety within thesespecies and the ecosystems they inhabit.
biophysical - that part of the environ-ment that does not originate withhuman activities (e.g. biological, physi-cal and chemical processes); pertainingto the natural environment.
carrying capacity - the rate of resourceconsumption and waste discharge thatcan be sustained indefinitely in a definedimpact region without progressivelyimpairing bioproductivity and ecologicalintegrity; the maximum number ofspecies that can be supported indefinite-ly by a particular habitat withoutdegrading the environment or diminish-ing future carrying capacity.
compensation measures - monetarypayment or replacement in kind for loss-es resulting from a development project;the re-creation of lost or damaged habitat.
cumulative effects assessment - theassessment of the impact on the environ-ment which results from the incrementalimpact of an action when added to otherpast, present or reasonably foreseeableprojects, regardless of what agency orperson undertakes such actions.Cumulative impact can result from indi-vidually minor but collectively signifi-cant actions taking place over a period oftime.
decision- maker - the person(s) entrust-ed with the responsibility for allocatingresources or granting approval to a proposal.
direct impact (primary impact)(firstorder impact) - an impact which followsas a direct cause effect consequence of aproject activity.
ecological processes - processes whichplay an essential part in maintainingecosystem integrity. Four fundamentalecological processes are the cycling ofwater, the cycling of nutrients, the flowof energy and biological diversity (as anexpression of evolution).
ecosystem - a community of interdepen-dent plants, animals and other livingorganisms (including humans) togetherwith the environment which supportsthem and with which they interact.
effects/impacts (synonymous) - a reac-tion to a change in the environment as aresult of a project action. Effects can beecological (such as the effects on compo-nents of natural resources, the structure
and/or functioning of affected ecosys-tems), aesthetic, historic, cultural, eco-nomic, and social, whether direct, indi-rect or cumulative.
environment - the complex web ofinter-relationships between living andnon-living components which sustain alllife on earth, including the social/healthaspects of human group existence. Thephysical, biological, social, spiritual andcultural components which are interre-lated and affect the growth and develop-ment of living organisms.
environmental component - any of thevarious aspects of the physical or socialenvironment, at any scale, that has beenidentified as being relevant to the assess-ment process.
environmental evaluation - a structuredinvestigation and evaluation of potentialimpacts or mitigation possibilities aris-ing from a project proposal.
environmental impact - the net change(positive or negative) in human healthand well-being that results from an envi-ronmental effect, including the health ofthe ecosystems on which human survivaldepends.
environmental impact assessment (EIA)- the process of examining proposedprojects and their reasonable alternativesfor potential environmental impactsprior to making decisions onimplementation
Glossary
32
evaluation - a subjective task thatdepends on the application of humanvalues. It involves determining the sig-nificance of the potential impacts to theaffected and interested parties.
impact - the consequence of an action oractivity interacting with its surroundings.
impact management plan - a structuredmanagement plan that outlines the miti-gation, monitoring and managementrequirements arising from an environ-mental impact assessment.
indirect impact (secondary impacts)(higher order impacts) - an environmen-tal effect that is at least one stepremoved from a project activity in termsof cause-effect linkages. those caused byan action that are later in time or fartherremoved in distance, but that are stillreasonably foreseeable (e.g. developmentin undisturbed areas as a result of accessroad building.)
effects monitoring - monitoring of envi-ronmental/social/health variables, whichare expected to change after a project hasbeen constructed and is operational, totest whether any observed changes aredue to the project alone and not to anyother external influences.
interaction - a process by which achange in the condition of one compo-nent of the environment causes a changein another.
interdisciplinary team - a group of peo-ple, from a range of disciplinary back-grounds, working together to ensure theintegrated use of the natural and socialsciences in planning and decision mak-ing, which may have an impact onman’s environment.
issue - an unresolved question or con-cern regarding an environmental impact,consequence or effect.
linkages - the pathways by which indi-vidual components of the environmentinteract with each other. Pathwaysinclude the food chain, hydrologic cycle,carbon cycle, etc.
mitigation - an activity aimed at reduc-ing the severity, avoiding or controllingenvironmental impacts of a project,through design alternatives, scheduling,or other means.
monitoring - an activity involvingrepeated observation, according to a pre-determined schedule, or one or moreelements of the environment to detecttheir characteristics (status and trends).Relevant data is collected and analyzedfor the purpose of evaluating the ade-quacy of project impact predictions andmitigation measures, improving projectmanagement methods, and developingcapability for future impact assessments.
non-governmental organization (NGO)- a general term for organizations out-side of government agencies such aspublic organizations and environmentalinterest groups.
proponent - the organization, companyor institution planning to initiate a pro-ject with environmental implications.
public involvement - a range of tech-niques that can be used to inform, con-sult or interact with stakeholders affect-ed by a proposal.
residual impact - those predictedadverse impacts which remain after miti-gating measures have been applied.
resilience - the ability of a system torecover from continuous or intermittentstress, within certain limits or thresholds.
scoping - a process by which all relevantissues and concerns related to the pro-posed project or activity are identifiedand prioritized.
screening - a preliminary stage of theassessment process for determining thelevel of effort, or type of EIA, requiredfor evaluating projects.
sensitivity - the susceptibility of anecosystem or ecosystem component tochange as a result of a given level ofenvironmental stress.
significance - the relative importance ofan issue, concern or environmentalimpact, as measured by prevailing stan-dards, regulatory requirements and soci-etal values.
social impact assessment - the compo-nent of EIA concerned with changes inthe structure and functioning of socialorderings. In particular the changes thata development would create in: socialrelationships; community (population,structure, stability etc.); people’s qualityand way of life; language; ritual; politi-cal/economic processes; attitudes/values.Can sometimes include health impacts.
stakeholders - those who may be poten-tially affected by a proposal e.g. localpeople, the proponent, governmentagencies, NGOs, donors, and others.
sustainable use - ecologically sound useof natural resources that meets the needsof the present without compromisingthe ability of future generations to meettheir own needs.
tiering - addressing issues and impacts atthe appropriate level of decision-making(e.g. from the policy to project levels).
value judgment - the use of opinion orbelief in analysis or decision-making.
valued ecosystem component (VEC) -the environmental attributes or compo-nents identified as a result of a scopingexercise as having legal, scientific, cultur-al, economic or aesthetic value.
33
ADB 1992. Environmental AssessmentGuidelines. African Development Bankand African Development Fund,Abidjan. 39 pp.
AsDB 1990. Environmental Guidelinesfor Selected Industrial and PowerDevelopment Projects. AsianDevelopment Bank, Manila. 154 pp.
AsDB 1993. Environmental AssessmentRequirements and EnvironmentalReview Procedures of the AsianDevelopment Bank. AsianDevelopment Bank, Manila. 43pp.
Beanlands, G.E. and P.N. Duinker.1983. An Ecological Framework forEnvironmental Impact Assessment inCanada. Dalhousie University:Institute for Resource andEnvironmental Studies, Report ISSNO-7703-0460-S.
Bisset, R. 1987. Methods forEnvironmental Impact Assessment: aselective survey with case studies inBiswas and Geping, 1987.
Canadian Environmental AssessmentAgency (CEAA). 1994. The CanadianEnvironmental Assessment Act,Responsible Authority’s Guide.Minister of Supply and Services Canada.
Canadian Environmental AssessmentResearch Council (CEARC). 1986.Cumulative Effects: A BinationalPerspective. Federal EnvironmentalAssessment Review Office (FEARO).Hull, Canada.
Canter, L. 1996. Environmental ImpactAssessment. Second Edition. NewYork: McGraw Hill.
CIDA 1994. CIDA’s Procedural Guidefor Environmental Assessment.Environmental Assessment and
Compliance Division, CanadianInternational Development Agency,Hull, Quebec. 60 pp.
Clark, B. et al. 1978. EnvironmentalImpact Assessment in the USA: ACritical Review. DOE Research Report30. Dept. of the Environment.London.
Clark, B.D. et al. 1980. EnvironmentalImpact Assessment: a bibliography withabstracts. Mansell, London.
de Broissia, M. 1986. SelectedMathematical Models in EnvironmentalAssessment in Canada. CanadianEnvironmental Assessment ResearchCouncil, Ottawa: Ministry of Supplyand Services.
Delbecq, A.L., A.H. Vande Ven andD.H. Gustafson. 1975. GroupTechniques for Program Planning: AGuide to Nominal Group and DelphiProcesses. Scott, Foresman andCompany.
FEARO. 1988. Manual on PublicInvolvement in EnvironmentalAssessment. Ottawa.
Grieg, L.A. et al. (ESSA Ltd.). 1986.Potential Environmental Effects of theProposed Mattagami HydroelectricExtension Project. Report prepared forOntario Hydro, Toronto, Ontario,Canada.
Hobbs, B.F. 1980. A comparison ofweighting methods in power plant sit-ing. Decision Sciences. 11:725-37.
IADB 1990. Procedures for Classifyingand Evaluating Environmental Impactsof Bank Operations. Inter-AmericanDevelopment Bank, Washington D.C.5pp.
Jain, R.K. et al. 1980. EnvironmentalImpact Analysis: A New Dimension inDecision Making. Van NostrandReinhold, New York.
Leopold, L.B., et al. 1971. A Procedurefor Evaluating Environmental Impact.United States Geological SurveyCircular 645, United States Departmentof the Interior, Washington, DC.
Lichfield, N. et al. 1975. Evaluationmethodology of urban and regionalplans: A review. Regional Studies. 4:151-165.
Massam, B.H. 1980. Spatial Search:Applications to Planning Problems inthe Public Sector. Pergamon Press.
Massam, B.H. 1988. Multi CriteriaDecision Making Techniques inPlanning. Progress in Planning. 30: 1-84.
Mishan, E.J. 1976. Cost BenefitAnalysis. Praeger, New York.
MOE 1990. Evaluation Methods inEnvironmental Assessment. OntarioMinistry of the Environment.
Munn, R.E. editor. 1975.Environmental Impact Assessment:Principles and Procedures. SCOPEReport 5, Toronto, Canada.
Ontario Ministry of the Environment.1987. Guidelines and Policy on Pre-Submission Consultation in the EAProcess. Toronto.
Ortolano, L. and A. Shepherd. 1995.Environmental Impact Assessment:Challenges and Opportunities. ImpactAssessment 13:3-30.
References
34
Rau, J.G. and D.C. Wooten. 1980.Environmental Impact AnalysisHandbook. McGraw Hill, Toronto,Canada.
Ross, J.M. 1974. Quantitative Aids toEnvironmental Impact Assessment.Environment Canada, LandsDirectorate. Occasional Paper 3,Ottawa.
Ruggles, R.F. and Shopley, J.B. 1984.A comprehensive review of current envi-ronmental impact assessment methodsand techniques. Journal ofEnvironmental Management 18: 25-47.
Sadar, M.H. 1994. EnvironmentalImpact Assessment. Carleton UniversityPress. Ottawa, Canada
Saaty, T.L. 1987. Risk: Its priorityand probability: the analytic hierarchyprocess. Risk Analysis. 7(2): 159-172.
Sonntag, N.S. 1983. AdaptiveEnvironmental Assessment andManagement as a Scoping Tool. Reportprepared for the InternationalWorkshop on Environmental Planningfor Large Scale Development Projects byESSA Ltd. Whistler, B.C. Canada.
UNEP 1988. Environmental ImpactAssessment: Basic Procedures forDeveloping Countries. United NationsEnvironment Program, Nairobi. 16 pp.
UNEP 1996. Environmental ImpactAssessment: Issues, Trends and Practice.United Nations Environment Program,Nairobi, Kenya.
Warner, M.L. and E.H. Preston. 1973.A Review of Environmental ImpactAssessment Methodologies. BattelleColumbus Laboratories, prepared forthe US EPA, October 1973.
Wolfe, L.D.S. 1987. Methods forScoping Environmental ImpactAssessments - A Review of Literatureand Experience. Federal EnvironmentalAssessment Review Office (FEARO),Vancouver. January.
World Bank. 1991. EnvironmentalAssessment Sourcebook. WashingtonD.C. (3 volumes).
35
EIA PHASE ORGANIZATION AfrDB AsDB CIDA ECE EEC AIB UNEP USAID WB
NEED AND JUSTIFICATION
Proposal is initially evaluated with respect to need and justification by the organization
SCREENING
Proposal is initially evaluated according to magnitude and sensitivity of issues
SCOPING
EIA Scope Document orTerms of Reference preparedby proponent together withorganization
EIA Scope Document preparedby lending agency
BASELINE DATA
compilation of baseline data
PUBLIC/GOV’T CONSULTATION
consultation with membercountry government
consultation with NGO’sindigenous groups and theaffected public
MITIGATION
mitigation and compensationmeasures
IMPACT ASSESSMENT
analysis of alternatives
requirement to assess socialenvironmental impacts
✓ ✓ ✓ ✓ ✘ ✓ ✓ ✓ ✓
✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓
✓ ✓ ✘ ✓ ✘ ✓ ✓
✓ ✓
✓ ✘ ✘ ✓ ✓ ✘ ✓ ✓ ✓
✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓
✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓
✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓
✓ ✘ ✓ ✓ ✘ ✓ ✓ ✓ ✓
✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓
AppendicesAPPENDIX 1: Summary of EIA Guideline Provisions for Selected International Funding Organizations
36
EIA PHASE ORGANIZATION AfrDB AsDB CIDA ECE EEC AIB UNEP USAID WB
EIA REVIEW
member country government and organization
environmental commitmentsincorporated into donation/loanagreements
IMPLEMENTATION
lending agency supervisesproject implementation
monitoring program required
requirement to evaluate theaccuracy of impact predictions
requirement to evaluate the effectiveness of mitiagationmeasures
requirement to evaluatecompliance with environmentalcommitments in loan agreement
AfrDB - African Development Bank
AsDB - Asian Development Bank
CIDA - Canadian International Development Agency
ECE - Economic Commission For Europe
EEC - European Economic Community
EEC - United Nations Environmental Programme
USAID - United States Agency for International Development
WB - World Bank
✓ ✓ ✓ ✓ ✘ ✘ ✓ ✓ ✓
✓ ✓ ✓ ✘ ✘ ✓ ✘ ✓ ✓
✓ ✓ ✓ ✘ ✘ ✓ ✘ ✓ ✓
✓ ✓ ✓ ✓ ✓ ✘ ✓ ✓ ✓
✓ ✓ ✓ ✓ ✘ ✓ ✓ ✓ ✓
✓ ✓ ✓ ✓ ✘ ✓ ✓ ✓ ✓
✓ ✓ ✓ ✘ ✘ ✓ ✘ ✓ ✓
APPENDIX 1: Summary of EIA Guideline Provisions for Selected International Funding Organizations (cont’d)
LEGEND- Provision
- No Provision
✓
✘
37
APPEN
DIX
2:Typ
ical
Env
iron
men
tal Eff
ects
and
Mitig
atio
n - Con
stru
ctio
n an
d O
pera
tion
of
Hyd
roel
ectr
ic G
ener
atio
n Fac
ilities
Con
stru
ctio
n si
te c
lear
ing
and
exca
vati
on (
pow
erho
use,
and
dam
sit
e co
nstr
ucti
on c
amp)
1.Lo
ss o
f veg
etat
ion
1.R
efor
esta
tion
els
ewhe
re
2.Lo
ss o
f wild
life
habi
tat
2.H
abit
at c
reat
ion/
impr
ovem
ent
3.D
istu
rban
ce o
f wild
life
thro
ugh
nois
e an
d tr
affic
3.N
oise
con
trol
s an
d tr
affic
res
tric
tion
s
4.D
istu
rban
ce o
f rar
e an
d en
dang
ered
spe
cies
4.Si
te p
lann
ing
for
avoi
danc
e, p
rote
ctio
n (e
g. fe
ncin
g) a
nd r
eloc
atio
n
5.E
ffec
ts o
n fa
rmin
g an
d tr
adit
iona
l use
s5.
Site
pla
nnin
g fo
r av
oida
nce,
ass
ista
nce
wit
h re
loca
tion
of h
omes
, far
ms
etc.
and
com
pens
atio
n
6.E
ffec
ts o
n to
uris
m a
nd r
ecre
atio
n6.
Site
pla
nnin
g an
d ti
min
g of
act
ivit
ies
for
avoi
danc
e an
d co
mpe
nsat
ion
7.D
ust e
ffec
ts7.
Use
of d
ust s
uppr
essa
nts
8.B
last
ing
and
nois
e ef
fect
s8.
Tim
ing
of a
ctiv
itie
s, fi
sh d
eter
rent
s an
d sa
fety
pro
visi
ons
(e.g
., w
arni
ng d
evic
es),
bla
stin
g m
ats,
noi
se s
ilenc
ers)
9.Fo
rest
ry e
ffec
ts9.
Rec
over
y of
mer
chan
tabl
e ti
mbe
r an
d re
fore
stat
ion
10.N
egat
ive
envi
ronm
enta
l eff
ects
of c
onst
ruct
ion:
10.M
easu
res
to m
inim
ize
impa
cts:
•ai
r an
d w
ater
pol
luti
on fr
om c
onst
ruct
ion
and
was
te d
ispo
sal
•ai
r an
d w
ater
pol
luti
on c
ontr
ol
•so
il er
osio
n•
care
ful l
ocat
ion
of c
amps
, bui
ldin
gs, b
orro
w p
its,
qua
rrie
s, s
poil
and
disp
osal
sit
es
•de
stru
ctio
n of
veg
etat
ion
•pr
ecau
tion
s to
min
imiz
e er
osio
n
•sa
nita
ry a
nd h
ealth
pro
blem
s fr
om c
onst
ruct
ion
cam
ps•
land
rec
lam
atio
n
Res
ervo
ir P
repa
rati
on a
nd F
lood
ing
1.D
ispo
sal o
f veg
etat
ion
1.C
ontr
olle
d bu
rns,
sea
rch
for
othe
r us
es (
e.g.
, bio
mas
s pl
ant)
, mak
e av
aila
ble
to lo
cal p
opul
atio
n
2.E
xclu
sion
of f
utur
e la
nd u
ses
2.Si
te p
lann
ing
for
avoi
danc
e, a
nd c
ompe
nsat
ion
3.T
urbi
dity
and
silt
atio
n du
ring
filli
ng3.
Tim
ing
and
dura
tion
of f
ill a
nd e
rosi
on c
ontr
ol
4.Sh
orel
ine
slum
ping
and
ero
sion
4.T
imin
g an
d du
rati
on o
f fill
, sho
relin
e pr
otec
tion
, sel
ecti
ve r
eten
tion
of s
tum
ps a
nd s
hore
line
vege
tati
on
5.Lo
ss/c
reat
ion
of fi
sh h
abit
at5.
Fish
erie
s m
anag
emen
t pra
ctic
es in
clud
ing
crea
tion
of n
ew h
abit
at
6.Sh
ift to
lake
spe
cies
6.Fi
sher
ies
man
agem
ent p
ract
ices
incl
udin
g cr
eati
on o
f new
hab
itat
7.Lo
ss o
f fis
hing
opp
ortu
niti
es7.
Tim
ing
of a
ctiv
itie
s, m
inim
ize
cons
truc
tion
per
iod,
and
com
pens
atio
n
8.E
ffec
ts o
n fis
hing
and
tour
ist c
amps
8.A
ssis
t wit
h re
loca
tion
or
com
pens
atio
n
9.Lo
ss o
f oth
er to
uris
m a
nd r
ecre
atio
n op
port
unit
ies
9.T
imin
g of
act
ivit
ies,
min
imiz
e co
nstr
ucti
on p
erio
d, r
eser
voir
pla
nnin
g to
enh
ance
futu
re o
ppor
tuni
ties
for
use
10.L
oss
of a
rcha
eolo
gica
l and
cul
tura
l res
ourc
es10
.Sit
e pl
anni
ng fo
r av
oida
nce
and
prot
ecti
on o
r re
cove
ry o
f ide
ntifi
ed r
esou
rces
AC
TIV
ITY
PO
TE
NT
IAL
EN
VIR
ON
ME
NT
AL
ISSU
E/E
FFE
CT
PO
SSIB
LE M
ITIG
AT
ION
OP
TIO
NS
38
APPEN
DIX
2:Typ
ical
Env
iron
men
tal Eff
ects
and
Mitig
atio
n - Con
stru
ctio
n an
d O
pera
tion
of
Hyd
roel
ectr
ic G
ener
atio
n Fac
ilities
(co
nt’d
)
11.D
islo
cati
on o
f peo
ple
livin
g in
inun
dati
on z
one.
11.R
eloc
atio
n of
peo
ple
to s
uita
ble
area
.
Prov
isio
n of
com
pens
atio
n in
kin
d fo
r re
sour
ces
lost
.
Prov
isio
n of
ade
quat
e he
alth
ser
vice
s, in
fras
truc
ture
, and
eco
nom
ic a
nd e
mpl
oym
ent o
ppor
tuni
ties
.
12.S
ocia
l dis
rupt
ion
and
decr
ease
in s
tand
ard
of li
ving
of
12.M
aint
enan
ce o
f sta
ndar
d of
livi
ng b
y en
suri
ng a
cces
s to
res
ourc
es a
t lea
st e
qual
ling
thos
e lo
st.
rese
ttle
d pe
ople
.Pr
ovis
ion
of h
ealth
and
soc
ial s
ervi
ces.
13.E
nvir
onm
enta
l deg
rada
tion
from
incr
ease
d pr
essu
re o
n la
nd.
13.C
hoic
e of
res
ettle
men
t sit
e to
avo
id s
urpa
ssin
g ca
rryi
ng c
apac
ity
of th
e la
nd.
Incr
ease
of p
rodu
ctiv
ity
or im
prov
e m
anag
emen
t of l
and
(agr
icul
tura
l, ra
nge,
fore
stry
impr
ovem
ents
) to
ac
com
mod
ate
high
er p
opul
atio
n.
14.D
isru
ptio
n/de
stru
ctio
n of
trib
al/i
ndig
enou
s gr
oups
.14
.Avo
id d
islo
cati
on o
f una
ccul
tura
ted
peop
le a
nd w
here
not
pos
sibl
e, r
eloc
ate
in a
rea
allo
win
g th
em to
ret
ain
lifes
tyle
and
cus
tom
s.
15.L
oss
of w
ildla
nds
and
wild
life
habi
tat.
15.S
itin
g of
dam
or
decr
ease
of r
eser
voir
siz
e to
avo
id/m
inim
ize
loss
.
Est
ablis
hmen
t of c
ompe
nsat
ory
park
s or
res
erve
d ar
eas.
Ani
mal
res
cue
and
relo
cati
on.
16.C
onfli
ctin
g de
man
ds fo
r w
ater
use
.16
.Pla
nnin
g an
d m
anag
emen
t of d
am in
con
text
of r
egio
nal d
evel
opm
ent p
lans
.
Equ
itab
le a
lloca
tion
s of
wat
er b
etw
een
larg
e an
d sm
all h
olde
rs a
nd b
etw
een
geog
raph
ic r
egio
ns o
f val
ley.
Ext
ract
ion
of A
ggre
gate
s 1.T
rans
port
atio
n an
d ha
ndlin
g1.
Use
of e
xcav
ated
mat
eria
ls a
nd s
ite
plan
ning
incl
udin
g us
e of
pre
viou
sly
dist
urbe
d si
tes
Wor
ker
Influ
x
1.In
crea
sed
fishi
ng a
nd fa
rmin
g pr
essu
res
1.R
estr
icti
on o
n us
e of
sen
siti
ve a
reas
, and
env
iron
men
tal a
war
enes
s tr
aini
ng
Cof
ferd
am P
lace
men
t an
d R
emov
al
1.T
urbi
dity
incr
ease
s to
rec
eivi
ng w
ater
s1.
Silt
barr
iers
and
sel
ecti
on o
f con
stru
ctio
n m
ater
ials
Acc
ess
Roa
ds
1.D
ispl
acem
ent o
f wild
life
due
to h
abit
at lo
ss1.
Use
of e
xist
ing
road
s, a
lignm
ent s
elec
tion
and
pla
nnin
g fo
r av
oida
nce
and
rail
or w
ater
acc
ess
2.Lo
ss o
f veg
etat
ion
due
to c
lear
ing
2.U
se o
f exi
stin
g ro
ads,
alig
nmen
t sel
ecti
on a
nd p
lann
ing
and
refo
rest
atio
n
3.In
crea
sed
fishi
ng p
ress
ure
wit
h ne
w o
r im
prov
ed a
cces
s3.
Tem
pora
ry a
cces
s an
d/or
fish
ing
rest
rict
ions
4.D
istu
rban
ce o
f str
eam
s an
d la
kes
thro
ugh
cons
truc
tion
, 4.
Site
pla
nnin
g to
avo
id s
trea
m c
ross
ings
and
roa
ds a
djac
ent t
owat
er b
odie
s, a
nd u
se o
f app
ropr
iate
cul
vert
siz
es,
traf
fic, s
iltat
ion,
and
alte
rati
on in
flow
pat
tern
san
d us
e of
buf
fer
zone
s an
d se
dim
ent t
raps
.
AC
TIV
ITY
PO
TE
NT
IAL
EN
VIR
ON
ME
NT
AL
ISSU
E/E
FFE
CT
PO
SSIB
LE M
ITIG
AT
ION
OP
TIO
NS
39
APPEN
DIX
2:Typ
ical
Env
iron
men
tal Eff
ects
and
Mitig
atio
n - Con
stru
ctio
n an
d O
pera
tion
of
Hyd
roel
ectr
ic G
ener
atio
n Fac
ilities
(co
nt’d
)
5.D
ispl
acem
ent o
f fis
hing
and
tour
ist o
utpo
st c
amps
5.T
empo
rary
acc
ess,
acc
ess
rest
rict
ions
(e.
g., g
atin
g) o
r co
mpe
nsat
ion
6.U
ncon
trol
led
mig
rati
on o
f peo
ple
into
the
area
mad
e 6.
Lim
itat
ion
of a
cces
s, p
rovi
sion
of r
ural
dev
elop
men
t, an
d he
alth
ser
vice
s to
try
to m
inim
ize
impa
ct.
poss
ible
by
acce
ss r
oads
and
tran
smis
sion
line
s.
Res
ervo
ir O
pera
tion
1.Sh
orel
ine
eros
ion
1.Sh
orel
ine
prot
ecti
on (
e.g.
, rip
rap,
gab
ions
)
2.Lo
ss/c
reat
ion
of a
quat
ic h
abit
at th
roug
h:2.
Stat
ion
and
rese
rvoi
r de
sign
(e.
g., i
n-st
ep o
pera
tion
)
• W
ater
leve
l flu
ctua
tion
• C
reat
ion
of n
ew h
abit
at
• A
ltere
d th
erm
al r
egim
e•
Int
ake
desi
gn to
influ
ence
leve
l of s
trat
ifica
tion
• N
utri
ent r
elea
se•
Res
ervo
ir c
lear
ing
• O
xyge
n de
plet
ion
• I
ntak
e de
sign
and
res
ervo
ir c
lear
ing
3.M
ercu
ry tr
ansf
orm
atio
n an
d up
take
by
fish
3.R
eser
voir
cle
arin
g, s
hore
line
stab
iliza
tion
and
rem
oval
and
cov
erin
g of
org
anic
s
4.In
crea
sed
fishi
ng p
ress
ure
4.R
eser
voir
pre
para
tion
and
pla
nnin
g in
clud
ing
fish
and
wild
life
man
agem
ent (
e.g.
, hab
itat
impr
ovem
ent,
stoc
king
and
hun
ting
/fis
hing
res
tric
tion
s)
5.Im
prov
ed w
ater
fow
l and
aqu
atic
wild
life
habi
tat
5.N
one
requ
ired
6.Lo
ss o
r di
spla
cem
ent o
f aqu
atic
mam
mal
s, h
abit
at,
6.W
ildlif
e m
anag
emen
t (e.
g., c
ontr
olle
d ha
rves
ting
, hab
itat
impr
ovem
ent)
or
relo
cati
on m
easu
res
and
trad
itio
nal u
ses
asso
ciat
ed w
ith
rive
rine
sys
tem
7.Po
ssib
le in
crea
se in
rec
reat
iona
l act
ivit
y 7.
Res
ervo
ir p
repa
rati
on p
lann
ing
wit
h po
tent
ial r
esou
rce
user
s an
d ac
cess
pro
visi
ons/
cont
rols
(e.
g., b
oat r
amp)
(boa
ting
, sw
imm
ing,
fish
ing,
etc
.)
8.H
uman
hea
lth (
mer
cury
inge
stio
n) a
nd d
iet c
hang
es8.
Safe
ty p
rovi
sion
(eg
. pos
ting
res
ervo
irs)
ris
k ed
ucat
ion
and
assi
stan
ce fo
r ob
tain
ing
alte
rnat
ive
food
sou
rces
.
9.In
crea
se o
f wat
er-r
elat
ed d
isea
ses.
9.D
esig
n an
d op
erat
ion
of d
am to
dec
reas
e ha
bita
t for
vec
tor.
• V
ecto
r co
ntro
l.
• D
isea
se p
roph
ylax
is a
nd tr
eatm
ent.
10.I
ncre
ase
in h
umid
ity
and
fog
loca
lly, c
reat
ing
favo
urab
le
10.V
ecto
r co
ntro
l.ha
bita
t for
inse
ct d
isea
se v
ecto
rs (
mos
quit
os, t
sets
e).
11.M
etha
ne r
elea
se11
.Res
ervo
ir p
repa
rati
on a
nd in
take
/sta
tion
des
ign
to m
inim
ize
anox
ic c
ondi
tion
s.
12.C
arbo
n di
oxid
e re
leas
e12
.Res
ervo
ir p
repa
rati
on to
min
imiz
e pr
esen
ce o
f org
anic
s
AC
TIV
ITY
PO
TE
NT
IAL
EN
VIR
ON
ME
NT
AL
ISSU
E/E
FFE
CT
PO
SSIB
LE M
ITIG
AT
ION
OP
TIO
NS
40
APPEN
DIX
2:Typ
ical
Env
iron
men
tal Eff
ects
and
Mitig
atio
n - Con
stru
ctio
n an
d O
pera
tion
of
Hyd
roel
ectr
ic G
ener
atio
n Fac
ilities
(co
nt’d
)
Res
ervo
ir O
pera
tion
(Con
t’d)
13.P
rolif
erat
ion
of a
quat
ic w
eeds
in r
eser
voir
and
dow
nstr
eam
13
.Cle
aran
ce o
f woo
dy v
eget
atio
n fr
om in
unda
tion
zon
e pr
ior
to fl
oodi
ng (
nutr
ient
rem
oval
).im
pair
ing
dam
dis
char
ge, i
rrig
atio
n sy
stem
s, n
avig
atio
n an
d •
Wee
d co
ntro
l mea
sure
s.fis
heri
es a
nd in
crea
sing
wat
er lo
ss th
roug
h tr
ansp
irat
ion.
• H
arve
st o
f wee
ds fo
r co
mpo
st, f
odde
r or
bio
gas.
• R
egul
atio
n of
wat
er d
isch
arge
and
man
ipul
atio
n of
wat
er le
vels
to d
isco
urag
e w
eed
grow
th.O
pera
tion
Res
ervo
ir
14.D
eter
iora
tion
of w
ater
qua
lity
in r
eser
voir
.14
.Cle
aran
ce o
f woo
dy v
eget
atio
n fr
om in
unda
tion
zon
e pr
ior
to fl
oodi
ng.
Con
trol
of l
and
uses
, was
tew
ater
dis
char
ges,
and
agr
icul
tura
l che
mic
al u
se in
wat
ersh
ed.
Lim
it r
eten
tion
tim
e of
wat
er in
res
ervo
ir.
Prov
isio
n fo
r m
ulti
-lev
el r
elea
ses
to a
void
dis
char
ge o
f ano
xic
wat
er.
15.S
edim
enta
tion
of r
eser
voir
and
loss
of s
tora
ge c
apac
ity.
15.C
ontr
ol o
f lan
d us
e in
wat
ersh
ed (
espe
cial
ly p
reve
ntio
n of
con
vers
ion
of fo
rest
s to
agr
icul
ture
).
Ref
ores
tati
on a
nd/o
r so
il co
nser
vati
on a
ctiv
itie
s in
wat
ersh
eds
(lim
ited
aff
ect)
.
Hyd
raul
ic r
emov
al o
f sed
imen
ts (
flush
ing,
slu
icin
g, r
elea
se o
f den
sity
cur
rent
s).
Ope
rati
on o
f res
ervo
ir to
min
imiz
e se
dim
enta
tion
(en
tails
loss
of p
ower
ben
efit
s).
16.F
orm
atio
n of
sed
imen
t dep
osit
s at
res
ervo
ir e
ntra
nce
16.S
edim
ent f
lush
ing,
slu
icin
g.cr
eati
ng b
ackw
ater
eff
ect a
nd fl
oodi
ng a
nd w
ater
logg
ing
upst
ream
.
17.S
nagg
ing
of fi
shin
g ne
ts in
sub
mer
ged
vege
tati
on in
17
.Sel
ecti
ve c
lear
ance
of v
eget
atio
n be
fore
floo
ding
.
rese
rvoi
r.
18.E
nvir
onm
enta
l pro
blem
s ar
isin
g fr
om d
evel
opm
ent
18.B
asin
-wid
e in
tegr
ated
pla
nnin
g to
avo
id o
veru
se, m
isus
e, a
nd c
onfli
ctin
g us
es o
f wat
er a
nd la
nd r
esou
rces
.m
ade
poss
ible
by
dam
(ir
riga
ted
agri
cultu
re, i
ndus
trie
s,
mun
icip
al g
row
th).
19.P
oor
land
use
pra
ctic
es in
cat
chm
ent a
reas
abo
ve
19.L
and
use
plan
ning
eff
orts
whi
ch in
clud
e w
ater
shed
are
as a
bove
dam
.re
serv
oir
resu
lting
in in
crea
sed
silta
tion
and
cha
nges
inw
ater
qua
lity.
Stat
ion
and
Spill
way
Ope
rati
on (
dow
nstr
eam
eff
ects
)
1.E
rosi
on a
nd s
iltat
ion
effe
cts.
1.St
atio
n de
sign
, sho
relin
e pr
otec
tion
and
cha
nnel
mod
ifica
tion
s.
2.Sc
ouri
ng o
f riv
erbe
d be
low
dam
.2.
Des
ign
of tr
ap e
ffic
ienc
y an
d se
dim
ent r
elea
se (
e.g.
, sed
imen
t flu
shin
g, s
luic
ing)
to in
crea
se
salt
cont
ent o
f rel
ease
d w
ater
.
3.A
ltera
tion
in a
quat
ic h
abit
at.
3.Fl
ow r
egul
atio
n du
ring
cri
tica
l per
iods
, cha
nnel
mod
ifica
tion
s an
d cr
eati
on o
f new
hab
itat
to e
nsur
e no
net
loss
.
AC
TIV
ITY
PO
TE
NT
IAL
EN
VIR
ON
ME
NT
AL
ISSU
E/E
FFE
CT
PO
SSIB
LE M
ITIG
AT
ION
OP
TIO
NS
41
APPEN
DIX
2:Typ
ical
Env
iron
men
tal Eff
ects
and
Mitig
atio
n - Con
stru
ctio
n an
d O
pera
tion
of
Hyd
roel
ectr
ic G
ener
atio
n Fac
ilities
(co
nt’d
)
4.A
quat
ic p
rodu
ctiv
ity
effe
cts.
4.In
take
and
sta
tion
des
ign
(to
min
imiz
e ch
ange
s to
ther
mal
and
dis
solv
ed o
xyge
n re
gim
es),
flow
reg
ulat
ion
duri
ng s
paw
ning
and
egg
incu
bati
on a
nd h
abit
at c
reat
ion,
and
flow
reg
ulat
ion
or c
hann
el m
odifi
cati
on to
m
inim
ize
dew
ater
ing
of h
abit
at.
5.W
ater
qua
lity
effe
cts.
5.R
eser
voir
pre
para
tion
, int
ake
and
stat
ion
desi
gn (
e.g.
, rem
oval
of o
rgan
ics,
ero
sion
con
trol
, and
flow
m
anag
emen
t).
6.R
ecre
atio
n an
d to
uris
m e
ffec
ts.
6.St
atio
n de
sign
, flo
w r
egul
atio
n, c
hann
el m
odifi
cati
ons,
pro
visi
on o
f byp
asse
s (e
.g. p
orta
ges,
mar
ine
railw
ays)
and
sa
fety
pro
visi
ons.
7.Fi
sh p
assa
ge a
nd m
orta
lity.
7.In
take
des
ign,
fish
det
erre
nts
and/
or fi
sh p
assa
ge fa
cilit
ies
(e.g
., fis
h la
dder
s).
8.Fi
sh m
orta
lity
from
gas
bub
ble
dise
ase.
8.D
esig
n of
spi
llway
and
inta
kes
to m
inim
ize
supe
rsat
urat
ion
of g
ases
and
fish
det
erre
nts.
9.Fi
shin
g op
port
unit
y ch
ange
s.9.
Safe
ty p
rovi
sion
s, a
nd m
easu
res
to e
ncou
rage
or
disc
oura
ge fi
shin
g, a
s ap
prop
riat
e.
10.D
ecre
ase
in fl
oodp
lain
(re
cess
ion)
agr
icul
ture
.10
.Reg
ulat
ion
of d
am r
elea
ses
to p
arti
ally
rep
licat
e na
tura
l flo
odin
g re
gim
e.
11.S
alin
izat
ion
of fl
oodp
lain
land
s.11
.Reg
ulat
ion
of fl
ow to
min
imiz
e ef
fect
.
12.S
alt w
ater
intr
usio
n in
est
uary
and
ups
trea
m.
12.M
aint
enan
ce o
f at l
east
min
imum
flow
to p
reve
nt in
trus
ion.
AC
TIV
ITY
PO
TE
NT
IAL
EN
VIR
ON
ME
NT
AL
ISSU
E/E
FFE
CT
PO
SSIB
LE M
ITIG
AT
ION
OP
TIO
NS
42
Pub
lic C
onsu
ltat
ion
invo
lvem
ent o
f int
eres
ted
exte
rnal
par
ties
in th
e E
Apr
oces
s
Ad
Hoc
com
pare
s al
tern
ativ
es w
ith-
out s
peci
ficat
ion
of c
rite
ria,
rati
ngs,
or
wei
ghts
Wei
ghti
ng o
f Pre
fere
nces
tech
niqu
es u
sed
to d
eter
-m
ine
crit
eria
that
mus
t be
cons
ider
ed in
the
EA
proc
ess
focu
s gr
oups
publ
ic m
eeti
ngs
or o
penh
ouse
netw
orki
ng
ques
tion
nair
es
advi
sory
cou
ncil
refe
rend
a
grou
p in
tera
ctio
nm
etho
ds
ad h
oc
rank
ing
and
cate
go-
riza
tion
rati
ng
poin
t allo
cati
on
- th
roug
hout
the
EA
proc
ess
- th
roug
hout
the
EA
proc
ess
- th
roug
hout
the
EA
proc
ess
- th
roug
hout
the
EA
proc
ess
- sc
opin
g-
eval
uati
on
- sc
opin
g-
eval
uati
on
- sc
opin
g-
eval
uati
on
- th
roug
hout
the
EA
proc
ess
- sc
opin
g -
eval
uati
on
- sc
opin
g -
eval
uati
on
- sc
opin
g -
eval
uati
on
espe
cial
ly u
sefu
l dur
ing
scop
ing;
co
nsul
tant
s
publ
ic a
nd p
ropo
nent
mee
t and
exch
ange
info
rmat
ion
liais
on m
embe
r av
aila
ble
to e
xcha
nge
info
rmat
ion
wit
h pu
blic
used
to r
ate
eval
uati
on c
rite
ria,
sol
icit
info
rmat
ion
or c
omm
ents
on
the
alte
rnat
ives
inpu
t fro
m a
cro
ss s
ecti
on o
f a c
om-
mun
ity
- no
t onl
y th
e af
fect
ed p
ublic
voti
ng fo
llow
ing
a de
bate
cho
oses
the
alte
rnat
ive
Del
phi m
etho
d -
a se
quen
ce o
f alte
r-na
ting
que
stio
nnai
res
and
feed
back
repo
rts
nom
inal
gro
up -
gro
up m
eeti
ngs
whe
re th
e ve
rbal
inte
ract
ion
is li
mit
ed
usef
ul in
scr
eeni
ng s
tage
s no
t use
ful
for
com
plex
dec
isio
ns
scal
ing
impo
rtan
ce u
sing
nom
inal
or
ordi
nal s
cale
s
assi
gnin
g a
valu
e of
impo
rtan
ce fr
om1-
10
dist
ribu
te s
ome
(i.e
. 100
) po
ints
amon
g th
e cr
iter
ia a
ccor
ding
to th
eim
port
ance
high
er le
vel o
f com
mit
men
t;m
inim
ize
cont
rove
rsy
duri
ngim
plem
enta
tion
sta
ges
iden
tifie
s co
ncer
ns; i
nexp
en-
sive
; est
ablis
hes
two
way
com
mun
icat
ion
iden
tifie
s an
d de
term
ines
rea
-so
ns fo
r co
ncer
ns
iden
tifie
s co
ncer
ns; r
each
apo
tent
ially
larg
er a
udie
nce
repr
esen
tati
on g
uara
ntee
dfr
om th
e w
hole
com
mun
ity
high
deg
ree
of p
ublic
invo
lvem
ent
isol
ated
gen
erat
ion
of a
larg
enu
mbe
r of
hig
h qu
alit
y id
eas;
grou
p pr
essu
re a
void
ed
allo
ws
for
peri
ods
of in
tera
c-ti
on a
nd n
on-
inte
ract
ion
no tr
aini
ng r
equi
red
sim
ple
to u
se a
nd u
nder
stan
d
in d
etai
led
plan
ning
sta
ges
extr
a in
form
atio
n m
akes
deci
sion
mak
ing
tedi
ous
seen
as
publ
ic r
elat
ions
exe
r-ci
se; d
omin
ance
of o
pini
on
mor
e ex
pens
ive
- hi
ring
alia
ison
per
son
surv
ey b
ias
loya
lty to
thos
e w
hoap
poin
ted
them
(bi
as)
tim
e co
nsum
ing
sele
ctio
n of
res
pond
ent
grou
p m
ay b
ias
resu
lts;
requ
ires
mor
e ti
me
(for
cor
-re
spon
denc
e)
sele
ctio
n of
gro
up m
embe
rsm
ay b
ias
resu
lts
not t
race
able
, rep
licab
le, n
orac
coun
tabl
e
not t
heor
etic
ally
val
id -
sub
-je
ctiv
e de
cisi
ons
may
not
pro
duce
val
idre
sults
FEA
RO
, 198
8.
Wol
fe, 1
987.
O
nt. M
in. o
f Env
.,19
87.
Mas
sam
. B.H
.,19
88.
Del
becq
, A.L
., A
.HV
ande
Ven
, and
D.H
. Gus
tafs
on,
1975
.
Fugg
le, R
.F.,
and
Shop
ley,
J.B
., 19
84.
Hob
bs, B
.F.,
1980
.
CA
TE
GO
RY
/D
ESC
RIP
TIO
NM
ET
HO
DA
PP
LIC
AT
ION
AP
PR
OA
CH
AD
VA
NT
AG
ES
DIS
AD
VA
NT
AG
ES
RE
FER
EN
CE
S
APPEN
DIX
3: Sum
mar
y of
Sel
ecte
d Too
ls a
nd M
etho
ds U
sed
in t
he E
IAPro
cess
43
Wei
ghti
ng o
f Pre
fere
nces
(con
t’d)
Agg
rega
tion
of W
eigh
ts
Exa
min
atio
n of
sim
ilar
proj
ects
revi
ew o
f iss
ues
rela
ted
tosi
mila
r pr
ojec
t typ
es, o
rte
chno
logi
es, o
r in
sim
ilar
sett
ings
Che
cklis
tsco
mpa
res
alte
rnat
ives
agai
nst a
set
of c
rite
ria;
appl
icab
le d
urin
g na
rrow
-in
g pr
oces
s; u
sefu
l for
iden
-ti
fyin
g im
pact
s; li
mit
ed fo
rus
e of
eva
luat
ion
Net
wor
ks-
flow
cha
rt w
hich
trac
es p
ro-
ject
act
ions
Ove
rlay
s-
tran
spar
ent m
aps
wit
h en
vi-
ronm
enta
l and
soc
ial i
nfor
-m
atio
n
indi
ffer
ence
tra
de -
off m
etho
d
deci
sion
ana
lysi
sw
eigh
t se
lect
ion
obse
rver
der
ived
tech
niqu
es
Bor
da-K
enda
ll
Coo
k an
d Si
efor
ddi
stan
ce m
etho
ds
revi
ew
unor
dere
d lis
t of
cri
-te
ria
Sati
sfyi
ng
lexi
cogr
aphi
c or
deri
ng
syst
em d
iagr
am
cons
trai
nt m
appi
ng
- sc
opin
g-
eval
uati
on
- sc
opin
g-
eval
uati
on
- sc
opin
g-
eval
uati
on
- sc
opin
g-
eval
uati
on
- sc
reen
ing
- sc
opin
g-
pred
icti
on
- sc
reen
ing
- sc
opin
g
- sc
reen
ing
- sc
opin
g
- sc
reen
ing
- sc
opin
g
- sc
opin
g-
pred
icti
on
- sc
opin
g-
pred
icti
on
dete
rmin
es th
e am
ount
giv
en u
p fo
r on
one
attr
ibut
e to
obt
ain
mor
e of
ano
ther
wei
ghts
are
rel
ated
to p
roba
bilit
ies
ofce
rtai
n co
nseq
uenc
es
deri
ving
rat
es fr
om p
refe
renc
es a
mon
gal
tern
ativ
es
aggr
egat
es in
divi
dual
pre
fere
nces
for
a se
tof
alte
rnat
ives
into
a g
roup
con
sens
us
revi
ew r
elat
ed e
nvir
onm
enta
l im
pact
stat
emen
ts a
nd p
ost a
udit
stu
dies
part
of c
rite
ria
iden
tific
atio
n pr
oces
s
alte
rnat
ives
mus
t sat
isfy
spe
cific
con
di-
tion
s be
fore
bec
omin
g ac
cept
able
sequ
enti
al r
ejec
tion
of a
ltern
ativ
es
iden
tifie
s ac
tion
s an
d as
soci
ated
impa
cts
unac
cept
able
cha
ract
eris
tics
are
map
ped,
map
s ar
e ov
erla
id, a
reas
that
rem
ain
are
cons
ider
ed
assu
res
valid
wei
ghts
clus
ter
wei
ghts
on
a fe
wat
trib
utes
prov
ides
con
sens
us o
rder
ing
iden
tifie
s po
tent
ial i
ssue
s
elim
inat
es in
feri
or c
hoic
es;
easy
to u
se a
nd u
nder
stan
d
esta
blis
hes
min
imum
acc
ept-
able
leve
ls; e
asy
to u
se a
ndun
ders
tand
quic
kly
elim
inat
es c
hoic
es;
resu
lts r
eplic
able
; eas
y to
use
com
preh
ensi
ve; i
dent
ifies
caus
e/ef
fect
rel
atio
nshi
p
trac
eabl
e ex
plan
atio
n fo
rel
imin
ated
are
as; e
asy
to u
sean
d un
ders
tand
subj
ecti
ve
perc
eptu
al s
hort
com
ings
wei
ghts
may
not
be
prop
or-
tion
al
appe
ars
ad h
oc
mat
hem
atic
ally
com
plex
pred
icti
ons
mad
e in
one
are
am
ay n
ot b
e tr
ansf
erab
le to
othe
r ar
eas
impa
cts
no o
n lis
t may
be
igno
red
may
not
lead
to o
ne a
ltern
a-ti
ve; a
ltern
ativ
es w
ith
off-
set-
ting
ben
efit
s m
ay b
e re
ject
ed
alte
rnat
ives
wit
h of
fset
ting
bene
fits
may
be
reje
cted
diff
icul
t to
follo
w a
s th
eybe
com
e m
ore
com
plex
data
mus
t be
capa
ble
ofbe
ing
map
ped;
mul
tipl
e si
teor
no
site
sce
nari
o
Hob
bs, B
.F.,
1980
.
Mas
sam
, B.H
.,19
80.
Wol
fe, 1
987.
Bis
set,
R.,
1987
.C
lark
, B.D
., 19
80.
Jain
, R.K
., et
al.,
1980
.
Wol
fe, 1
987.
CA
TE
GO
RY
/D
ESC
RIP
TIO
NM
ET
HO
DA
PP
LIC
AT
ION
AP
PR
OA
CH
AD
VA
NT
AG
ES
DIS
AD
VA
NT
AG
ES
RE
FER
EN
CE
S
APPEN
DIX
3: Sum
mar
y of
Sel
ecte
d Too
ls a
nd M
etho
ds U
sed
in t
he E
IAPro
cess
(co
nt’d
)
44
Ove
rlay
s (c
ont’d
)
Env
iron
men
tal M
odel
ling
quan
tita
tive
rep
rese
ntat
ion
of a
n en
viro
nmen
tal s
yste
m
Mat
rix
Met
hods
- tw
o-di
men
sion
al c
heck
lists
;us
ed to
sum
mar
ize
and
dis-
play
inte
ract
ions
bet
wee
npr
ojec
t act
ion
and
envi
ron-
men
tal c
hara
cter
isti
cs
GIS
(geo
grap
hic
info
rmat
ion
syst
ems)
num
erou
s m
etho
ds
hypo
thes
is o
f eff
ect
(ada
ptiv
e en
viro
nmen
-ta
l man
agem
ent)
Leop
old
mat
rix
Ros
s’ e
nvir
onm
enta
lin
tera
ctio
n m
atri
x
SAW
(sim
ple
addi
tive
wei
ghti
ng)
SMA
RT
(sim
ple
mul
ti-
attr
ibut
e ra
ting
tech
niqu
e)
PA
TT
ER
N(p
lann
ing
assi
stan
ce th
roug
hte
chni
cal e
valu
atio
n of
rele
vanc
e nu
mbe
rs)
PR
OLI
VA
N (
prob
a-bi
listi
c lin
ear
vect
oran
alys
is)
Pet
erso
n
- sc
opin
g-
pred
icti
on
- pr
edic
tion
- sc
opin
g-
pred
icti
on
- sc
opin
g -
pred
icti
on
- sc
opin
g-
pred
icti
on
- ev
alua
tion
- ev
alua
tion
- ev
alua
tion
- ev
alua
tion
- ev
alua
tion
tran
spar
ent m
aps
wit
h en
viro
nmen
tal
and
soci
al in
form
atio
n su
peri
mpo
sed;
area
sui
tabi
lity
is in
dica
ted
by s
hadi
ngin
tens
ity
pred
icts
atm
osph
eric
, ter
rest
rial
, and
aqua
tic
effe
cts
dem
onst
rate
s lin
kage
s w
ithi
n en
viro
n-m
ent c
ausi
ng in
put
scor
ing
proc
edur
e id
enti
fies
mag
nitu
dean
d si
gnifi
canc
e of
impa
cts
on
envi
ronm
ent
first
mat
rix
iden
tifie
s en
viro
nmen
tal
depe
nden
cies
; the
sec
ond
mat
rix
trac
esim
pact
s
each
alte
rnat
ive
is g
iven
a s
core
whi
chre
pres
ents
the
utili
ty o
f the
pro
ject
rank
cri
teri
a; th
en b
egin
ning
wit
h lo
wes
tra
nked
cri
teri
on r
atio
val
ues
are
assi
gned
to p
refe
renc
es
mul
tipl
e le
vels
of c
once
rn a
re s
truc
ture
din
a `
rele
vanc
e tr
ee’
mod
ifica
tion
of S
AW
; wei
ghti
ng o
f lon
gan
d sh
ort t
erm
impa
cts;
eac
h al
tern
ativ
eha
s co
nfid
ence
lim
its
one
mat
rix
scor
es e
nvir
onm
enta
lim
pact
s, a
noth
er s
core
s so
cial
impa
ctan
d th
ey a
re m
ulti
plie
d
defin
es s
pati
al e
xten
t of
impa
cts;
doe
s no
t hav
e to
be
map
ped
- in
form
atio
n ca
ngi
ve e
xact
rat
es fo
r su
btle
vari
atio
n; m
inim
izes
co
ncer
ns
iden
tifie
s re
lati
onsh
ips
that
need
to b
e in
vest
igat
ed
indi
cate
s re
lati
onsh
ipbe
twee
n ca
use
and
effe
ct
high
ord
er d
epen
denc
ies
can
be d
eter
min
ed; c
onsi
ders
sec
-on
dary
impa
cts
mat
hem
atic
ally
sim
ple;
repl
icab
le r
esul
t
sim
ple
to u
se a
nd u
nder
stan
d
clar
ifies
issu
es o
f con
cern
asse
sses
unc
erta
inty
; ref
lect
sim
port
ance
of l
ong
and
shor
tte
rm im
pact
s
mea
sure
s se
cond
ary
impa
cts
for
map
ping
ther
e ar
e lim
its
on th
e nu
mbe
r of
ove
rlay
s(c
rite
ria)
that
can
be
used
an u
npre
dict
able
eve
nt c
anoc
cur
com
plex
for
larg
e pr
ojec
ts
num
erou
s in
tera
ctio
ns -
diff
i-cu
lt to
ass
ess
over
all i
mpa
ct
tedi
ous
for
com
plex
issu
es
impr
essi
on o
f obj
ecti
vity
,w
hich
may
not
exi
st
only
a s
mal
l num
ber
of c
rite
-ri
a ca
n be
use
d
diff
icul
t to
keep
fact
s an
dpr
efer
ence
s se
para
te
may
be
diff
icul
t to
use
addi
-ti
onal
info
rmat
ion
on c
onfi-
denc
e lim
its
subj
ecti
ve ju
dgem
ents
Bis
set,
1987
. Ja
in e
tal
., 19
80.
de B
rois
sia,
198
6.
Gre
ig, 1
986.
Sonn
tag,
198
3.
Leop
old,
L.B
., et
al.,
1971
.
Ros
s, J
.H.,
1974
.
Hob
bs, B
.F.,
1980
.
Mas
sam
, B.H
.,19
88.
CA
TE
GO
RY
/D
ESC
RIP
TIO
NM
ET
HO
DA
PP
LIC
AT
ION
AP
PR
OA
CH
AD
VA
NT
AG
ES
DIS
AD
VA
NT
AG
ES
RE
FER
EN
CE
S
APPEN
DIX
3: Sum
mar
y of
Sel
ecte
d Too
ls a
nd M
etho
ds U
sed
in t
he E
IAPro
cess
(co
nt’d
)
45
Eco
nom
ic A
ppro
ache
s re
pres
enti
ng a
ll as
pect
of a
proj
ect i
n m
onet
ary
valu
es
Pair
Wis
e C
ompa
riso
nsco
mpa
riso
n of
alte
rnat
ives
in p
airs
whi
ch a
re th
enor
dere
d us
ing
mat
hem
atic
alte
chni
ques
Opt
imiz
atio
n M
odel
ling
mat
hem
atic
al te
chni
ques
that
cho
ose
alte
rnat
ives
that
best
mee
t the
obj
ecti
ve
CB
A(c
ost b
enef
itan
alys
is)
CE
A(c
ost e
ffec
tive
anal
ysis
)
CM
A(c
ost m
ini-
miz
atio
n an
alys
is)
PB
S(p
lann
ing
bal-
ance
she
et)
Saat
y’s
anal
ytic
alhi
erar
chy
proc
edur
e
ELE
CT
RE
(co
ncor
-da
nce
and
disc
or-
danc
e an
alys
is)
TO
PSI
S
LP(l
inea
r pr
ogra
mm
ing)
DP
(dy
nam
ic
prog
ram
min
g)
GP
(goa
l pr
ogra
mm
ing)
- ev
alua
tion
- ev
alua
tion
- ev
alua
tion
- ev
alua
tion
- ev
alua
tion
- ev
alua
tion
- ev
alua
tion
- ev
alua
tion
- ev
alua
tion
- ev
alua
tion
impa
cts
are
expr
esse
d in
mon
etar
y te
rms
and
adde
d to
geth
er to
det
erm
ine
tota
lbe
nefit
s an
d to
tal c
osts
the
pref
erre
dal
tern
ativ
e ha
s th
e hi
ghes
t rat
io o
f ben
e-fit
s d
ivid
ed b
y co
sts
appl
icat
ion
of C
BA
whe
n th
ere
is a
fixe
dbu
dget
appl
icat
ion
of C
BA
whe
n ob
ject
ives
are
not c
hang
ing
appl
icat
ion
of C
BA
that
dea
ls w
ith
dis-
trib
utio
nal i
ssue
s
esti
mat
es p
refe
renc
es a
nd e
xact
val
ues
byco
mpa
ring
cri
teri
a an
d al
tern
ativ
es
com
pare
s a
smal
l num
ber
of a
ltern
ativ
es;
appl
icab
le in
the
sam
e sc
enar
io a
s SA
W
used
whe
n re
lati
onsh
ips
betw
een
two
impa
cts
are
sim
ple
allo
cate
s re
sour
ces
in a
way
that
mee
tsob
ject
ives
and
sta
ys w
ithi
n co
nstr
aint
s
opti
miz
atio
n m
etho
d
opti
miz
atio
n m
etho
d; ta
rget
s se
t for
cr
iter
ia
repr
oduc
ible
; dol
lars
and
cent
s te
rmin
olog
y
asse
sses
impa
cts
over
tim
e
obje
ctiv
es c
an b
e st
ated
inno
n-m
onet
ary
term
s
exte
rnal
itie
s ca
n be
incl
uded
in th
e an
alys
is; g
ood
repr
e-se
ntat
ion
of im
pact
di
stri
buti
on
com
bine
s co
mpl
ex a
rray
s of
data
and
judg
emen
ts in
to a
num
eric
rat
io
exte
rnal
itie
s ea
sily
incl
uded
alte
rnat
ives
can
be
rank
ed
mat
hem
atic
ally
def
ensi
ble
solu
tion
inco
rpor
ates
com
plic
ated
rela
tion
ship
s
disc
rete
alte
rnat
ives
nee
d no
tbe
spe
cifie
d
exte
rnal
itie
s m
ay b
e di
ffic
ult
to q
uant
ify; d
istr
ibut
iona
lqu
esti
ons
are
not d
ealt
wit
h(i
.e.,
who
ben
efit
s, w
hoin
curs
the
cost
)
less
com
pati
ble
wit
h th
ego
als
of E
IA th
an C
BA
no fu
rthe
r co
mpa
riso
n fo
ral
tern
ativ
es th
at m
eet t
heen
viro
nmen
tal o
bjec
tive
s
may
not
lead
to a
uni
que
solu
tion
ques
tion
able
def
ault
valu
es;
pref
eren
ce a
nd e
xact
val
ueco
nfus
ion;
rep
licat
ion
is
diff
icul
t
cum
bers
ome
whe
n th
ere
are
man
y al
tern
ativ
es
com
plex
whe
n m
any
crit
eria
are
cons
ider
ed
som
e pr
oble
ms
may
invo
lve
rela
tion
ship
s th
at a
re n
on-
linea
r
limit
ed to
pro
blem
s th
at c
anbe
seg
men
ted
diff
icul
t to
assi
gn ta
rget
s in
unit
s
Mis
han,
E.J
., 19
76.
Lich
field
, N.,
1975
.
Saat
y, T
.L.,
1987
.
CA
TE
GO
RY
/D
ESC
RIP
TIO
NM
ET
HO
DA
PP
LIC
AT
ION
AP
PR
OA
CH
AD
VA
NT
AG
ES
DIS
AD
VA
NT
AG
ES
RE
FER
EN
CE
S
APPEN
DIX
3: Sum
mar
y of
Sel
ecte
d Too
ls a
nd M
etho
ds U
sed
in t
he E
IAPro
cess
(co
nt’d
)
Sour
ce -
VH
B R
esea
rch
& C
onsu
lting
Inc
., Lo
cPla
n an
d La
wre
nce
Mac
Don
ald
and
Ass
ocia
tes.
Eva
luat
ion
Met
hods
in E
nvir
onm
enta
l Asse
ssmen
t. O
ntar
io, M
inis
try
of E
nvir
onm
ent,
Ont
ario
.a
Ref
eren
ces
othe
r th
an s
ourc
e m
ater
ial
47
AcknowledgementsThis Manual was prepared by a consultant, Marie
LeGrow, with guidance and assistance from Murray
Paterson and Stewart Sears, Ontario Hydro.
Valuable comments and suggestions were received
from Jeannette Boyer, Steve Carnegie, Steve
Hounsell, Jim Malenfant and Barb Reuber,
Ontario Hydro, and the E7-8 Project Advisory
Team members. Special thanks to John Hart and
Dana Hunter from the E7 Secretariat for their
help. Thanks also to the E7 Network Steering
Committee members for their encouragement and
support. Graphics, layout and production were pro-
vided by Charlotte Gervis, Dawn Henderson and
John Woodhouse, Ontario Hydro.
Printed on recycled paper
For more information please contact:
Secretariat,E7 Network of Expertise for the Global Environment
1010 St. Catherine Street West6th Floor, P.O. Box 6162
Montréal, QuébecCANADA, H3C 4S7
Tel: 514 392-8876Fax: 514 392-8900
E-mail: [email protected] Site: www.e7.org
E7 ContactsSECRETARIAT:E7 Network Of Expertise1010 St. Catherine Street West6th Floor, P.O. Box 6162Montréal, QuébecCANADA H3C 4S7
Phone: (514) 392-8876Fax: (514) 392-8900E-mail: [email protected]
ÉLECTRICITÉ DE FRANCE (EDF):Mr. Edouard BauerÉlectricité de France22-30, avenue de Wagram75382 Paris Cedex 08FRANCE
Phone: (33-1) 47 64 85 19Fax: (33-1) 47 64 75 01E-mail: [email protected]
ENEL:Mr. Roberto VitaliENELVia N. Bixio, 3929100 PiacenzaITALY
Phone: 39 523 525252Fax: 39 523 525519E-mail: [email protected]
HYDRO-QUEBEC:
Mr. Jean HébertHydro-Québec1010 St. Catherine Street East, 3rd FloorMontréal, QuébecCANADA H2L 2G4
Phone: (514) 840-3615Fax: (514) 840-3933E-mail: [email protected]
KANSAI ELECTRIC POWERCOMPANY:Mr. Takao ShiraishiDeputy General ManagerOffice of Corporate PlanningKansai Electric Power Co.3-22, Nakanoshima, 3-ChomeKita-Ku, Osaka 530-70JAPAN
Phone: +81-6-446-9430Fax: +81-6-441-8598E-mail: [email protected]
ONTARIO HYDRO:
Mr. Murray PatersonOntario Hydro800 Kipling Ave. KR 122Toronto, OntarioCANADA M8Z 5S4
Phone: (416) 207-6682Fax: (416) 207-5623 E-mail: [email protected]
RWE ENERGIE AG:
Mr. Hans-Georg AdamRWE EnergieKruppstrasse 54300 Essen 1GERMANY
Phone: (0201) 185-2904Fax: (0201) 185-4313E-mail: [email protected]
SOUTHERN CALIFORNIAEDISON:
Mr. Howard GollaySouthern California EdisonP.O. Box 8002244 Walnut Grove Ave.Rosemead, CaliforniaUSA 91770
Phone: 818-302-4122Fax: 818-302-9156E-mail: [email protected]
TOKYO ELECTRIC POWERCOMPANY:
Mr. Ichiro MaedaManagerInternational Affairs DepartmentTokyo Electric Power Company1-3 Uchisaiwai-Cho 1-Chome Chiyoda-KuTokyo 100 JAPAN
Phone: (03) 3501-8111Fax: (03) 3596-8438E-mail: [email protected]