environmental and social analysis

66
Environmental and Social Analysis Of the Construction and Operation of a Wastewater Collection, Treatment, and Disposal System for the Placencia Peninsula DRAFT Prepared by: J. C. Meerman & T. Boomsma 26 September 2010

Upload: leslie-tech

Post on 12-Mar-2016

212 views

Category:

Documents


0 download

DESCRIPTION

Of the Construction and Operation of a Wastewater Collection, Treatment, and Disposal System for the Placencia Peninsula

TRANSCRIPT

Page 1: Environmental and Social Analysis

 

Environmental and Social Analysis  

Of the Construction and Operation 

of a Wastewater Collection, Treatment,  

and Disposal System for  

the Placencia Peninsula  

 

 

 

 

 

 

 

 

 

 

 

 

 

DRAFT Prepared by: 

J. C. Meerman & T. Boomsma 

26 September 2010 

Page 2: Environmental and Social Analysis

1  Meerman & Boomsma, Environmental and Social Analysis ‐  Wastewater Collection, Treatment, and Disposal System –Placencia Peninsula – DRAFT – 26 September 2010 

    

Table of Contents 1.  Introduction .......................................................................................................................................... 3 

2.  Project description ................................................................................................................................ 3 

2.1.  Description of the planned activities ............................................................................................ 3 

2.2.  Collection of the waste water ....................................................................................................... 3 

2.3.  Treatment of the waste water ...................................................................................................... 4 

2.4.  Site selection criteria ..................................................................................................................... 5 

3.  Baseline data ......................................................................................................................................... 6 

3.1.  Physical environment including neighboring mainland ................................................................ 6 

3.1.1.  The peninsula ........................................................................................................................ 6 

3.1.2.  The mainland ........................................................................................................................ 6 

3.1.3.  The lagoon ............................................................................................................................. 7 

3.1.4.  Lagoon Bathymetry ............................................................................................................... 8 

3.1.5.  Biological environment ......................................................................................................... 9 

3.2.  Socio‐cultural environment ........................................................................................................ 10 

3.2.1.  Schools ................................................................................................................................ 11 

3.2.2.  Health clinic ......................................................................................................................... 11 

3.2.3.  Roads ................................................................................................................................... 11 

3.2.4.  Public transportation .......................................................................................................... 11 

3.2.5.  Telephone ........................................................................................................................... 11 

3.2.6.  Airstrip ................................................................................................................................. 11 

3.2.7.  Electricity ............................................................................................................................. 12 

3.2.8.  Water supply ....................................................................................................................... 12 

3.2.9.  Future water demands ........................................................................................................ 12 

3.2.10.  Sanitation ............................................................................................................................ 13 

3.2.11.  Fire service .......................................................................................................................... 13 

3.2.12.  Police stations ..................................................................................................................... 13 

3.2.13.  Economics ........................................................................................................................... 14 

3.3.  Policy, legal and administrative framework ................................................................................ 17 

4.  Impact of improved sanitation facilities on the environment ............................................................ 20 

4.1.1.  Potential impacts of activities during construction and operation phases ........................ 22 

4.2.  Description of mitigation measures ............................................................................................ 26 

4.3.  Description of a monitoring program ......................................................................................... 34 

4.3.1.  Agencies that could be incorporated in Monitoring ........................................................... 48 

4.3.2.  Monitoring agencies ........................................................................................................... 62 

Page 3: Environmental and Social Analysis

2  Meerman & Boomsma, Environmental and Social Analysis ‐  Wastewater Collection, Treatment, and Disposal System –Placencia Peninsula – DRAFT – 26 September 2010 

    

5.  Legal requirements for bidding and contract documents .................................................................. 64 

6.  Literature ............................................................................................................................................ 65 

 

 

Map 1: Placencia Lagoon with locations mentioned in the text................................................................... 5 

Map 2: Placencia Lagoon Ecosystems and Land Use .................................................................................... 6 

Map 3: Placencia Lagoon Water Catchments (From Ariola, 2003) ............................................................... 7 

Map 4: Map (2007) of developments on the Placencia Peninsula (aplaceinbelize.com) ........................... 16 

   

Page 4: Environmental and Social Analysis

3  Meerman & Boomsma, Environmental and Social Analysis ‐  Wastewater Collection, Treatment, and Disposal System –Placencia Peninsula – DRAFT – 26 September 2010 

    

1. Introduction The Inter‐American Development Bank (IDB) (in partnership with the Global Environment Facility (GEF) and United Nations Environment Programme (UNEP))  is seeking to use GEF resources to help mobilize greater  investments  in wastewater management  (including collection and  treatment  infrastructure)  in the Caribbean region. The primary objective of this initiative is to establish innovative, feasible financial instruments  through pilots  for cost effective and  sustainable  financing of wastewater management  in the Caribbean  region. One of  the  selected  initiatives  is an  inter‐municipal wastewater  system  for  the Peninsula  of  Placencia  in  Belize  (Inter‐municipal water  services)  The  IDB’s  Environmental  Safeguards Policy  requires  that  such  facility  be  subject  to  an  Environmental  and  Social  Analysis  (ESA)  and  the preparation  of  an  Environmental  and  Social Management  plan  to  ensure  its  safe  construction  and operation. The Belize Water Services Limited (BWSL) is the proposed executing agency for the operation. IDB Environmental Safeguards Policy places the responsibility for the preparation of an environmental impact assessment on the Borrower. 

Note that the current ESA is a baseline study setting the stage for a more in‐depth follow up ESA and/or possibly an Environmental Impact Assessment (EIA) which will be based on a final engineering study and design  as  well  as  on  a  feasibility  study.  Particularly  the  project  description  in  chapter  2  and  the mitigation and monitoring sections  in chapter 4, are currently “generic” and will require modifications and added detail once engineering and feasibility studies have been completed.  

 

2. Project description 

2.1. Description of the planned activities 

Some years ago, the communities of Placencia Peninsula requested assistance form Engineers Without Borders  in  the United States  (EWB‐US)  to help  them solve  their waste water problem. EWB  reviewed and approved their project proposal and the local Sacramento Valley Professional Chapter was assigned the project. The first phase of the process was for a EWB team of engineers to travel to Belize in 2006 and evaluate the problem and gather data to prepare a report. The report evaluated the socio‐economic background of the project, determined the current volume of waste water, and proposed a number of sewerage collection and treatment methods to handle the projected wastewater in the future.  

 

2.2. Collection of the waste water 

The first step in any waste water treatment system is the actual collection of the waste water. A number of alternatives exist to collect this waste water and transport it to the treatment facilities. These options include: 

Gravity collection system 

Vacuum collection system 

Pressure sewer system 

What  ultimately will  be  the  preferred  option  depends  on  existing  physical  conditions  of  the  terrain, management capacity of the proposed executing agency for the operation, the management capacity of the individual households and will need to be determined in further studies. 

Page 5: Environmental and Social Analysis

4  Meerman & Boomsma, Environmental and Social Analysis ‐  Wastewater Collection, Treatment, and Disposal System –Placencia Peninsula – DRAFT – 26 September 2010 

    

Irrespective of the collection details, a village collecting system will consist of a network of sewer pipes connecting each building with the main sewer line. The size of the sewer pipes depends on the collecting system which will be used at the peninsula, and will range between 3” and 6”. The main sewer line will collect  the  sewer  from  the  residential  connecting  pipes  and  transport  the  sewer  to  the  treatment facility.  

 

2.3. Treatment of the waste water 

Regardless the collection system, the collected waste must undergo treatment before it can be released into the environment. Several alternative treatment systems exist, and the choice of system depends on the  level of treatment required to fulfill the requirements by  law for the discharge of effluents from a sewerage  system,  the  availability of  suitable  terrain  for  the  treatment  system,  and  the management capacity of the proposed executing agency. As treatment alternatives were proposed: 

Stabilization/facultative ponds: primary and secondary treatment 

Aerated lagoons as secondary treatment in combination with a sedimentation pond for primary treatment 

Package mechanical wastewater treatment plant, in combination with a sedimentation pond for primary treatment 

Constructed wetlands as secondary  treatment,  in combination with a  sedimentation pond  for primary treatment 

Any ponds will need to be lined either using natural clays or a synthetic membrane. 

For the final disposal of the effluent, a number of alternatives were proposed: 

Disposal by irrigation at the banana plantation along the South Stann Creek (see map 1) 

Disposal by  golf  course  irrigation  at  the Ara Macao development  at  the northern end of  the peninsula 

Disposal by overland flow 

 

   

Page 6: Environmental and Social Analysis

5  Meerman & Boomsma, Environmental and Social Analysis ‐  Wastewater Collection, Treatment, and Disposal System –Placencia Peninsula – DRAFT – 26 September 2010 

    

2.4. Site selection criteria 

The  Placencia  Peninsula  does  not offer  a  suitable  site  where  the sewerage  treatment  facilities  can  be located.  There  is  insufficient  space and  the  development  density  is  too high. Consequently, this site has to be located on the mainland. There are a number  of  issues  that  have  to  be considered, namely: 

The  acreage  of  land  needed  for  the treatment  facilities  is  dependent  on the projected amounts of wastewater produced  between  2015  (when facility  becomes  operational)  and 2030  (expected  live  span  on  the facility).  

Final  destination  for  the  effluent discharge:  Suggested  solutions  such as irrigation of the banana plantation and the Ara Macao gardens (See map 1) are probably not  realistic as these developments  are  not  controlled  by the executive agent of  the  sewerage facility. 

The  preferred  option  for  sewerage treatment  facilities,  taking  into consideration  financial  and  technical sustainability: It  is assumed that with a growing economy of the peninsula, expansion  of  the  original  sewerage treatment  facility  may  happen  by more  innovative systems that do not require extensive land area. 

Land  needed  for  the  sewerage treatment  facility  has  to  be  secured by  the Government of Belize  for  this specific  purpose,  including  any  land needed  for  future  expansion  and proper overland flow discharge. 

 

 

 

Map 1: Placencia Lagoon with locations mentioned in the text

Page 7: Environmental and Social Analysis

6  Meerman & Boomsma, Environmental and Social Analysis ‐  Wastewater Collection, Treatment, and Disposal System –Placencia Peninsula – DRAFT – 26 September 2010 

    

3. Baseline data 

3.1. Physical environment including neighboring mainland 

3.1.1. The peninsula 

The Placencia Peninsula  is  located  in the  Stann  Creek  district,  Belize, between 16°30’ and 16°40’ N latitude and  88°15’  and  88°25’ W  longitude. The  peninsula  is  a  24  km  (16  mile) long  strip  of  land  in  between  the Caribbean  Sea  on  the  east  and  the Placencia  Lagoon  on  the  west.  The widest  point  of  the  peninsula  is  4.5 km  (3  mile),  the  narrowest  point  is only 50 m wide. The peninsula  is  the largest  sand  spit  along  the  Belizean coast.  

The  soils of  the peninsula are  recent deposits  consisting  of  coarse  sands along  the Caribbean Sea and silt and mangrove  peat  deposits  on  the lagoon  (west)  side.  The  whole peninsula  is  very  low  lying with  the highest levels following the Caribbean coast but barely 3 meters above sea. This  is  also  the  area  where  most developments  started.  Development of  the  lagoon  side  requires  great amounts of fill material. . 

 

3.1.2. The mainland 

The  soils of  the mainland  are  recent sediments,  consisting  of  alluvial deposits  originating  from  the  Maya Mountains.  The  soils  are  a  complex system of sandy soils and heavy clays, cross cut by numerous small streams. The  ill  drained  clay  soils  on  the coastal plain are ideal for aquaculture development  and  several  farms  are to be found near the lagoon, see map 2. 

Map 2: Placencia Lagoon Ecosystems and Land Use 

Page 8: Environmental and Social Analysis

7  Meerman & Boomsma, Environmental and Social Analysis ‐  Wastewater Collection, Treatment, and Disposal System –Placencia Peninsula – DRAFT – 26 September 2010 

    

The alluvial plains along  the major  rivers  turned out  to be perfect place  for  the development of  large scale banana plantations. Just west of the Riversdale settlement at the northern part of the peninsula is a major banana plantation is located on the alluvial plains of the South Stann Creek, see map 2. 

 

3.1.3. The lagoon 

Placencia Lagoon lies to the west of the Placencia Peninsula. It is a narrow, 3.4 km (2.2 mile) at its widest and  about  24‐km  long  estuary  that  is  mainly  shallow,  (1‐2  meters),  with  a  few  deeper  holes  and channels. The  lagoon actually consists of four wider  lagoon sections separated by three rather shallow and narrow channels. The deepest point of the lagoon is in its most southern lob and reaches a depth of 5.8 meters below MSL (Mean Sea Level).    

Map 3: Placencia Lagoon Water Catchments (From Ariola, 2003)

Page 9: Environmental and Social Analysis

8  Meerman & Boomsma, Environmental and Social Analysis ‐  Wastewater Collection, Treatment, and Disposal System –Placencia Peninsula – DRAFT – 26 September 2010 

    

3.1.4. Lagoon Bathymetry 

Three catchment areas drain  into  the  lagoon,  from  the north  to  the south  these are  the Santa Maria Creek, August Creek and Big Creek. In the south, the lagoon widens up and is in open contact with the Caribbean Sea. 

The  Santa Maria Creek watershed has  an  area of  347  km2.  The  terrain  is  relatively  low‐lying with  a maximum elevation of 500 meters on  its westernmost boundary. Part of the Santa Maria watershed  is also the Hemsley Creek, the Silver Creek and a number of several small, unnamed creeks. Some creeks flow directly  in  the  lagoon while others  flow  into wetlands  that display  connectivity  to  the Placencia Lagoon.  

The August Creek Catchment has an area of 250 km2. The  low  relief of  the  catchment makes  it very vulnerable  to  annual  flooding  events.  The major waterways  in  this watershed  are Mango  Creek  and August Creek that converge at the  lower section of the catchment before they flow  into the Placencia Lagoon.  Flour  Camp  Creek,  Jenkins  Creek  and  several minor  waterways  also  contribute  to  the  net discharge of Mango Creek.  

The Big Creek Watershed is the smallest of the three catchments adjacent to the Placencia Lagoon and has an area of 59 km2. Most of the  lands  in this basin are  less than 20 meters  in elevation. This basin exhibits  low  relief  and  a moderate  flood  risk  potential.  The  principal waterway,  Big  Creek,  is  fed  by numerous small streams and debouches at the southernmost end of the Placencia Lagoon. 

It  is worth pointing out that none of the watercourses that flow  into the Placencia Lagoon are gauged; hence there are no time series on the discharge and water  levels (Hydrology Service, 2003). However, Ariola (2003) purports that the combined low flow for August and Mango Creeks is 0.7 cubic meter per second  (CMS) which  is about 200 gallon per  second. Furthermore  the  low  flow  for  Jenkins and Flour Camp Creeks was estimated at 0.8 CMS. Silver Creek was estimated to have a low flow of 1.3 CMS. 

The  ground  water  resources  map  of  Belize  divides  the  country  into  ten  regions  based  on  water availability and quality (Buckalew et al., 1998). The terrestrial zone of influence on the Placencia Lagoon falls into two of these regions: 

(1) The Placencia Peninsula and the western margin of the  lagoon are classified as areas where small  to  large  quantities  of  brackish  to  saline water  are  available.  Also, meager  to  very  small quantities of  fresh water are available  from quaternary alluvium and coastal deposits along  the coast. Depth to water is 2 to 50 meters. 

(2) The wider extent of the terrestrial zone of influence is that part of the Central Coastal Plain composed of sandy shales, shales, claystones, mudstones, and alluvium. These deposits bear meager to moderated quantities of freshwater. Depth to water is generally less than 60 meters. 

Although  there  is  limited  information  about  the  ground  water  distribution  in  the  terrestrial  zone influencing the lagoon, it is envisaged that ground water might have some effects on the water budget of the Placencia Lagoon. (Ariola, 2003) 

The pH levels of the lagoon water generally average from 7.0 to 7.5 in the northern sections to 8.0 and 8.6  in  the more  saline  areas  in  the  south. Most marine  organisms  prefer  conditions with  pH  values ranging from 6.5‐8.5 (U.S. EPA, 1993). The observed pH values are well within the acceptable range for most marine organisms and provides for a healthy estuarine environment. 

Ariola  (2003)  studied  the  salinity  of  the water  of  the  lagoon.  Shifts  in  salinity  can  be  attributed  to evaporation,  freshwater  influx  from  the many  streams  draining  into  the  lagoon,  and  the  net water 

Page 10: Environmental and Social Analysis

9  Meerman & Boomsma, Environmental and Social Analysis ‐  Wastewater Collection, Treatment, and Disposal System –Placencia Peninsula – DRAFT – 26 September 2010 

    

exchange between the lagoon and the sea. The average salinity of the lagoon water ranged from 22.59 – 31.78 ppt  for  the  surface water and 24.94‐ 32.4 ppt  for  the bottom water. The Caribbean  Sea has a constant salinity (33‐35 parts per thousand), so the changes in salinity in the lagoon can be explained by the  very  low  flushing  rate  of  the  upper  part  of  the  lagoon  that  strongly  depends  on wind  and  tidal forces. 

The Watershed Reef Interconnectivity Scientific Study (2001) purports that water within the barrier reef lagoon  flows predominantly  from north  to south at a  rate of 0.05  to 0.15 m/s and  rarely exceeds 0.3 m/s. (Ariola, 2003). 

Tides of the Caribbean and along the Belize Barrier Reef are microtidal and of mixed semidiurnal type with a mean range of 15 cm (Kjerfve, 1981). PASCO (2002) mentions that the tidal fluctuations on the eastside  of  the  peninsula  ranges  from  0.40  to  1.5  feet.  The  tidal  fluctuations within  the  lagoon  are almost non‐existent. 

This combination of low flow and limited tidal movements within the lagoon makes the lagoon, and then specifically  its  northern  part,  very  vulnerable  to  human  impacts  through  settlement,  agriculture  and mariculture. As a result of the discharge of large volumes of untreated waste water in the upper lagoon, the water quality could rapidly decline and affect the natural ecological balance. 

Dissolved Oxygen  (DO)  levels  for  the  lagoon  ranged between 5.79 and 8.02 mg/l,  indicating a healthy environment  for  aquatic  life  (most  organism  perform  best when DO  exceeds  5 mg/l)  (Ariola,  2003). However,  the discharge of waste water with a high Biological Oxygen Demand  (BOD) can quickly turn this situation around, resulting in oxygen depleted environment that has no carrying capacity for aquatic life. 

 

3.1.5. Biological environment 

The natural vegetation of  the Placencia Peninsula, which broadly consisted of  littoral  forest along  the coast, and mangroves bordering the lagoon, has all but disappeared or at least become fragmented. The last  patches  of  natural  vegetation  will  disappear  in  the  nearby  future  when  development  of  the peninsula  keeps  following  the  current  pace. Due  to  the  loss  of  natural  vegetation  on  the  peninsula, natural wildlife has  also diminished.  Specifically, migratory birds have been hit by  the  loss of  littoral forest which provided them with natural habitat to recuperate during their migration. 

Natural  vegetation  on  the mainland  largely  consists  of  gallery  forests,  (pine)  savannah,  herbaceous swamps and mangrove swamps. The mangrove marshlands surrounding the Placencia Lagoon provide important  environmental  services  such  as  sediment  removal,  absorption  of  nutrients  and  pollutants from storm water and wastewater.  

The  alluvial  plains of  the mainland  are  considered  the most  suitable  lands  for  shrimp mariculture  in Belize.  Although  several  shrimp  farms  are  located  on  the  coastal  plain,  large  stretches  of  natural vegetation still remain on the coastal plain. Coastal plain vegetation has many plant species restricted to Belize (Belizean endemics). Yellow‐headed parrots and Aplomado falcon depend largely on coastal plain savannas for their existence. The savanna ecosystem on the west coast of the lagoon leads into gallery forests  that  provide  a  biological  corridor  to  the  Cockscomb  Jaguar  Reserve  and  the Maya Mountain Massif beyond. 

Placencia Lagoon provides a sheltered environment where adult marine mammals  like  the Bottlenose Dolphin and West Indian Manatee can care for their young. Over 70 species of fish have been identified 

Page 11: Environmental and Social Analysis

10  Meerman & Boomsma, Environmental and Social Analysis ‐  Wastewater Collection, Treatment, and Disposal System –Placencia Peninsula – DRAFT – 26 September 2010 

    

in  Placencia  Lagoon  including  Goliath  grouper  (Epinepheus  itajara),  Tarpon,  snook,  goliath  grouper, bonefish, a variety of snapper and other species. However, individual fishes tend to be very small and it has been suggested that Placencia Lagoon serves as an important nursery for juvenile fish. Studies have shown that seagrass supports the food web of fisheries in Placencia Lagoon as both a carbon source and habitat. Unique seagrass species, including Halophilla baillonii have been found in the lagoon and have been shown to be a major diet item of West Indian Manatee (Short et al. 2006).  

 The lagoon houses a remarkable biodiversity and includes several endangered and flagship species like the Jabiru Stork, Morelet's crocodile, American crocodile and West Indian manatee.  

Much of the coast is lined with mangroves whose roots are encrusted with a rich variety of sessile life ‐ shellfish, sponges, anemones and algae ‐ and provide shelter for juveniles of many commercial species of fish.  

 

3.2. Socio‐cultural environment 

For  long  two  small villages were  the only  centers of human occupation of  the peninsula. These were Placencia at the southern tip and Seine Bight about halfway the peninsula. The 2000 census noted for Placencia a mere 458 inhabitants and for Seine Bight 831 persons. In the north, the small settlement of Riversdale is located right at the point where the peninsula is connected with the mainland. Although a total population of 685 persons was tabulated during the Census 2000, Riversdale itself is rather small. Most likely residents of more southern located clusters of houses or resident staff of the nearby banana plantation were included in the count for Riversdale. 

The  last  ten years,  the peninsula has experienced an explosive growth  in development, mainly  in  the tourism sector which led to an increase of hotels, resorts and condominiums but also in permanent and semi‐permanent residential development for expatriates of pre‐dominantly North American origin. The original settlement pattern of small villages has changed and at present almost no land is un‐developed on the east coast of the peninsula. Now the availability of land along the Sea is severely limited, and the inland facing side of the lagoon is being developed piece by piece. 

The  first hotels  and  lodges were  set up  rather  spaciously but now  that  land  is becoming  scarce  and therefore expensive,  intensification of occupation  takes place.  For example,  the  lodge  Luba Hati  that offered accommodation for a maximum of 40 guests on a 40 acre property is planned to be replaced by a  high  density  development  focusing  on  the  condominium  market  with  46  hotel  suites  and  106 residences on the same land, potentially 10 fold the current maximum occupancy of the property.  

The development in the tourism industry not only resulted  in an  increase of temporary population but also  attracted  hundreds  of  Belizeans  who  sought  employment  in  the  construction  or  the  service industries. Many of these employees live in staff quarters at the lodges and hotels or reside elsewhere on the peninsula or on the mainland in Independence and Santa Cruz (Map 1). 

The last couple of years, plans have been developed to develop a 190 lot subdivision on the lagoon side of Placencia Village,  to accommodate  the  local  residents  for whom  it  is difficult  to  find houselots  for their own growing population. The Environmental Compliance Plan  for  this  sub‐division Crimson Park requires  the  provision  of  a  self‐contained  sewage  system  to  protect  the  environmentally  sensitive Placencia Lagoon from contamination.   

Page 12: Environmental and Social Analysis

11  Meerman & Boomsma, Environmental and Social Analysis ‐  Wastewater Collection, Treatment, and Disposal System –Placencia Peninsula – DRAFT – 26 September 2010 

    

The resident population on the Placencia is estimated to be about 3,000, based on the EWB report1. The report estimates the total population during the tourism high season up to 10,000 persons. The tourist peak season runs  from end December through April, which coincides with the North American winter and the time of year with the least rainfall at the peninsula. 

With  the  current  trend  of  developments,  and  the  lack  of  a  development master  plan  for  the  entire peninsula  to  determine  a  maximum  carrying  capacity  or  proper  regulations,  the  estimated  peak population of the peninsula of 10,000 in 2006 could easily be doubled or even tripled before 2020. 

 

3.2.1. Schools 

Primary schools are in Seine Bight and Placencia, but there are no high schools or junior colleges on the peninsula. The nearest secondary education facilities are in Independence and Dangriga 

 

3.2.2. Health clinic 

Seine Bight and Placencia have health clinics; Placencia has a resident doctor and a nurse, Seine Bight has a resident nurse and a nurse aid. The nearest hospital is the Southern Regional Hospital in Dangriga, about a 1.5 hour drive from Placencia. Other health facilities are in Belize City, a one hour flight from the Placencia airstrip. 

 

3.2.3. Roads 

Apart  from  some  side  roads,  there  is  basically  one  road  on  the peninsula,  stretching  from  Placencia village to the southern highway. This road has recently been improved and is now fully paved. 

 

3.2.4. Public transportation 

Several buses make a daily run to Dangriga. 

 

3.2.5. Telephone 

The peninsula has telephone services by both national telephone companies. These services also include mobile phone, and  internet services.  Internet café’s are  found  in  the villages. Most hotels and  lodges have internet services available to their guests. 

 

3.2.6. Airstrip 

In the centre of the peninsula is an airstrip which is used by local air companies for flights to and from Belize City and the south. A larger airport is being developed along the access road to the peninsula; this airport has a landing strip of more than 8000 feet, which potentially can accommodate larger airplanes from international destinations.                                                             1 Engineers without borders, 2006. Wastewater System Feasibility Study for Placencia Peninsula, Belize. 31 pp + annexes. 

Page 13: Environmental and Social Analysis

12  Meerman & Boomsma, Environmental and Social Analysis ‐  Wastewater Collection, Treatment, and Disposal System –Placencia Peninsula – DRAFT – 26 September 2010 

    

 

3.2.7. Electricity 

Electricity services are provided by the Belize Electricity Limited. The peninsula’s grid is connected with the national grid. 

 

3.2.8. Water supply 

The peninsula is supplied with water by a Rudimentary Water System (RWS) managed by local water boards. The water is derived from a well near Mango Creek on the mainland, and then piped under water to the peninsula. The system was damaged by hurricane Iris in 2001, when the underwater pipe was broken and it took several months before the system was repaired. 

At more  or  less  the  same  location  near Mango  Creek  are  two more wells which  produce water  for Independence/Mango Creek and Big Creek. Apparently all  three wells  tap  into  the same sources, and the  water  source  for  these  existing  three  wells  is  believed  to  be  an  aquifer,  but  it  has  not  been determined what the actual size and capacity of the aquifer is. 

A financial analysis of the income and expenses of RWS over the period mid 2007‐mid 2008, done in July 2008 by the Ministry of Rural Development (MRD), gave the following information: 

 

Village  No. of connections 

Water rates  Average monthly income (over a 12 month period) 

Average monthly expenses (over a 12 month period)  

Average monthly use of water, based on average monthly income 

Placencia  520  1 cent/gallon  $ 57,292.00  $ 41,021.00  5,729,200 gallon 

Seine Bight  323  1 cent/gallon  $ 24,052.00  $ 8288.00  2,490,520 gallon 

 

The total average monthly use over a 12 month period in 2007‐2008 of the two RWS was approx. 8,000,000 gallon.  

The organization Peninsula Citizens for Sustainable Development (PCSD) estimated the use of water in 2009 to 209,477,520 which is twice the amount the MRD calculated over the period mid 2007‐mid 20082. 

 

3.2.9. Future water demands 

The organization PCSD stated in their newsletter3: 

                                                            2 http://www.saveourpeninsula.org/tourism/water.html 

3 http://saveourpeninsula.org/newsletter/RnR%20April%202010%20%281%29.pdf 

Page 14: Environmental and Social Analysis

13  Meerman & Boomsma, Environmental and Social Analysis ‐  Wastewater Collection, Treatment, and Disposal System –Placencia Peninsula – DRAFT – 26 September 2010 

    

In addition, no government agency has ever addressed the capacity of the Peninsula’s water supply to support any specific level of tourism.  For example, no one knows where the water comes from, how much of it there is, whether once it’s used up, it’s gone or whether the supply gets replenished from seasonal rains – or how susceptible the water supply is to being inundated by sea water as sea levels rises. 

The increase in demand for water will be caused by a growing residential population, but mostly by an increased capacity of hotel accommodation as is sketched by PCSD: 

In 2006, the peninsula had 114 hotels, with 749 units, 1005 bedrooms and 1,450 beds.  Three years later, we have 13 more approved hotels adding 1,696 units, 3,388 bedrooms and 5,088 beds, for a total of 127 built and approved hotels, with 2,445 units, 4,393 bedrooms and 6,538 beds ‐ a four‐fold increase in bedrooms in just three years! 

For example, the proposed Placencia Marina estimated the daily use for water for its 520 guests and staff during the peak season, on 31,600 gallon which is 10 % of the present average daily consumption of the peninsula (BET, Placencia Marina EIA, 2009) 

 

3.2.10. Sanitation 

There  is no  centralized piped  sewerage  system  that  services  the  two  villages on  the peninsula.  Each household and business is responsible for its wastewater. Systems’ most used are septic systems with a form of soak‐away (soak away field, leach pit), a vaulted pit latrine, a vaulted septic system whereby the vault does not have a sealed bottom. Incidentally, sanitary waste is collected and dumped on the beach or in the sea/lagoon. 

Smaller  resorts  and  hotels  have  septic  systems,  but  the  larger  developments  are  required  by  the Department of Environment (DoE) to install so‐called package plants. A certain effort is made by DoE to monitor the effluent discharge by these package plants. 

Of  the  average  monthly  use  of  8,000,000  gallon  in  2007/2008,  80  %  of  this  volume  (6,400,000 gallon/month)  will  de  disposed  of  through  sanitation  systems,  and  ultimately  be  returned  to  the environment. 

The 2006 EWB study calculated an average monthly wastewater flow of 240,000 gallon per day which is 7.200,000 gallon wastewater per month. 

 

3.2.11. Fire service 

The peninsula does not have a fire station; Placencia has some basic fire control system. 

 

3.2.12. Police stations 

Police stations are in Seine Bight and Placencia 

 

   

Page 15: Environmental and Social Analysis

14  Meerman & Boomsma, Environmental and Social Analysis ‐  Wastewater Collection, Treatment, and Disposal System –Placencia Peninsula – DRAFT – 26 September 2010 

    

3.2.13. Economics 

Tourism 

Tourism  is  the major economic activity on  the peninsula. Placencia as a  tourism destination has been slowly  discovered  since  the  early  nineties,  but  development  at  the  moment  happens  with  an unprecedented speed. Map 3 (A Place In Belize.com, 2007)4 shows the developments, planned or under construction. The economic recession of the past years may have slowed down the speed of realization of these plans, but no doubt the industry will bounce back and continue its course if and when the world economy picks up again. As was stated under the Water Chapter, the peninsula had more than 6,500 registered hotel beds in 2009 (PCSD, 2010). With the present trend of scaling up existing establishments and planning larger and higher buildings, the number of beds will no doubt increase many fold.  

With  the  growth  in  tourism  accommodation,  comes  an  increase  in  construction  and  maintenance business. Also, there  is an  increase  in staff needed in the hotels, lodges and restaurants. Some upscale lodges in the Cayo district have a staff guest ration of one to one. On the average, a staff guest ration of 1 to 4 will  implicate a future need for more employees  in the tourism sector. It  is uncertain  in how far these  employees  will  reside  on  the  peninsula  taking  into  account  the  shortage  in  affordable houses/lodging  facilities.  Most  likely  the  employees  will  resort  to  staying  at  the  mainland  and commuting to the job on a daily basis. 

 

Caged Fish Farming5 

The Placencia area currently has no caged fish farming.  An EIA was submitted for a caged fish farm at the  Lark  Caye  Range,  but  the  developer withdrew  the  proposal  after  it was met with  exceptionally strong community opposition. 

 

Shrimp farms 

Ariola 2003,  gave  the  following description of  the  shrimpfarm operations near  the Placencia  Lagoon: Considerable attention was given to the impacts of shrimp mariculture operations in the margin of the Placencia  Lagoon.  At  the  time  of  this  study,  the  upper  portion  of  the  lagoon  was  not  affected  by aquaculture effluent. Nova Toledo has been non functional for several years (Tunich Nah, 2001). On the other hand, Belize Aquaculture Ltd. is a fully functional super intensive, closed system operation with a zero  effluent  discharge  (Boyd  et  al.,  2002).  Royal Mayan,  Tex Mar  and  Crustaceans  Ltd.  are  three operations that are  in close proximity to each other. Each of these operations meets the settling pond requirements (10% of the production area) stipulated by the Department of the Environment. Effluents discharged  from  these  operations  are  subjected  to  mangrove  wetlands  for  nutrient  and  sediment reduction prior to entry into the lower portions of the Placencia Lagoon. The fact that the lower portion of the lagoon has a much higher water exchange rate with the sea (as opposed to the upper portion) is the  reason why  there  is no  significant  impact on  the ecological  and environmental  conditions of  the lagoon. Aqua Mar is located at the southern boundary of the lagoon and its effluents are released into wetlands  in the northeastern tip of the Sennis River Catchment. Taking  into account the predominant southerly coastal currents, the impacts of this operation on the Placencia Lagoon are questionable. 

                                                            4 http://aplaceinbelize.com/map_dev.html 

5 http://saveourpeninsula.org/agriculture_aquaculture/aquaculture.html 

Page 16: Environmental and Social Analysis

15  Meerman & Boomsma, Environmental and Social Analysis ‐  Wastewater Collection, Treatment, and Disposal System –Placencia Peninsula – DRAFT – 26 September 2010 

    

According  to  the PCSD,  shrimp  farms  in  the past had  impacted  the  flora and  fauna of  the  lagoon by discharging untreated waste water that resulted in the decline of the sea grass beds which are particular important to dolphins and manatees. (Loss of sea grass beds in Placencia Lagoon linked to effluent from Belize shrimp farms.) 

During the last years, most of the shrimp farms on the Placencia Lagoon have significantly reduced their run‐off and effluent  load through voluntary efforts. To maintain a healthy  lagoon, the existence of the marsh lands and the mangroves are needed. 

Page 17: Environmental and Social Analysis

16  Meerman & Boomsma, Environmental and Social Analysis ‐  Wastewater Collection, Treatment, and Disposal System –Placencia Peninsula – DRAFT – 26 September 2010 

    

 

Map 4: Map (2007) of developments on the Placencia Peninsula (aplaceinbelize.com) 

Page 18: Environmental and Social Analysis

17  Meerman & Boomsma, Environmental and Social Analysis ‐  Wastewater Collection, Treatment, and Disposal System –Placencia Peninsula – DRAFT – 26 September 2010 

    

3.3. Policy, legal and administrative framework 

The Environmental Protection Act Chapter 328, Revised Edition 2000 

The Environmental Protection Act entrusted the Department of the Environment with a broad range of functions relating to the protection of the environment, including the assessment of water pollution, the coordination of activities relating to the discharge of wastes, the  licensing of activities that may cause water  pollution,  the  registration  of  sources  of  pollution  and  the  carrying  out  of  research  and investigations as to the causes, nature and extent of water pollution, and the necessary prevention and control measures. 

 

Environmental Impact Assessment (Amendment) Regulations, 2007. S.I. No. 24 of 2007 

Under Schedule  II projects are  listed that may require an environmental  impact assessment or  limited level environmental study depending on the location and the size of the project. Under pt. 20, d is listed: ‘a waste water treatment plant’. 

Under Schedule III are guidelines listed to be used by permitting and/or licensing agencies to determine when  a  project  is  to  be  sent  to  DoE  for  an  Environmental  Clearance.  Guidelines  applicable  to  the proposed Placencia waste water treatment facility are: 

All applications for development in coastal areas, All applications for development near or in ecologically sensitive areas  like swamps, marshes, mangrove,  lagoon, All applications for development within or  in close proximity to critical habitats for protected, threatened or endangered species of flora and fauna 

 

Pollution Regulations, 1996. S.I. No. 56 of 1996 

Under  Part  XI,  noise  abatement  is  regulated. Under  the  second  schedule maximum  noise  level  and duration of the noise is defined. 

 

Environmental Protection (Effluent Limitations)(Amendment) Regulations, 2009. S.I. 102 of 2009 

Under  the  third  schedule,  the  effluent  limits  of  the  discharge  from  domestic wastewater  treatment systems into Class I waters is determined. 

 

Table1 EFFLUENT LIMITATIONS DOMESTIC WASTE WATER TREATMENT SYSTEM 

Parameter  Effluent limits into Class I waters 

Total Suspended solids   30 mg/L (does not include algae from treatment ponds) 

Biochemical Oxygen Demand (BOD)  30 mg/L 

pH  5‐10 pH units

Fats, oil and grease  15 mg/L 

Faecal coliform  200 mpn/100 ml 

E. coli (fresh water)  126 organism/100 ml 

Enterococci (saline water)  35 mg/ 100 ml 

Floatables  Not visible 

Page 19: Environmental and Social Analysis

18  Meerman & Boomsma, Environmental and Social Analysis ‐  Wastewater Collection, Treatment, and Disposal System –Placencia Peninsula – DRAFT – 26 September 2010 

    

Water  and  Sewerage  Act,  Chapter  222,  Revised  Edition  2000‐  under  this  Act,  the  Minister  (not mentioned is of which ministry) can declare any area of the country an area of water supply and also any area  of  the  country  a  sewerage  disposal  areas.  Both  areas  fall  under  the  provisions  of  this  Act.  In sewerage disposal areas the use of the sewerage system (if any) is mandatory.  

 

The Public Utilities Commission Act, Chapter 223, Revised Edition 2000—This Act established the PUC, giving  it  authority  over  the  electricity, water,  and  telecommunications  sectors.  The Act  sets  out  the PUC’s composition, governing  rules, and general  functions.  It enables  the PUC  to  issue  regulations on rates and procedures  for  reviews, appeals, accounts, and  reports.  In  the water and  sanitation  sector, BWS is the only utility with a license from the PUC, and is the only utility regulated by the PUC  

 

The Water Industry Act, Chapter 222s, Revised Edition 2003—This Act (under the Minister responsible for water and sewerage), which has March 23, 2001 as  its  ‘appointed day’ fir the purpose of said Act, replaced the Water and Sewerage Act, Chapter 222 of the Laws of Belize. The Water Industry Act 2003 ceased the functions of the Water and Sewerage Authority (established under Section 3 of the repealed Act). The Water Industry Act gives the Minister of Natural Resources and the Environment responsibility for promoting a national policy for water, and the PUC the right to grant licenses for providing water and sewerage  services.  The Water  Industry  Act  also  sets  out  the  function  and  duties  of  the  PUC,  the responsibilities of  the  licensees, and  regulations  for water pollution  control  (including  specification of controlled areas and award of permits for discharge).  

The  act  gives detailed  information  in  regards  to  the proper design of private  sanitation  systems  like septic systems. This Act contains the following orders: 

The Belize Water Services Ltd. License (2001)—The PUC issued this 25 year license to BWS on 20 March 2001.  The  license  authorizes  BWS  to  serve  all  areas  previously  serviced  by  the WASA,  and  sets  out performance  and  safety  standards,  reporting  requirements,  and  license  fees  to  be  paid  to  the  PUC. Under  the  terms of  the  license, BWS  is  to  follow by‐laws  issued by  the PUC  for setting  tariffs, and  to request approval for  its proposed tariffs from the PUC. From the  license’s expiry  in 2026, BWS has the first right of refusal to continue to operate in the same service area under 15 year contract extensions 

 

International standards for effluent quality of sewerage systems. 

The national effluent  limitations domestic waste water, does not discriminate  in the various ways the effluent will be discharged. International standards often do have a different set of limitations in relation to the final discharge method. Table 2 compares the effluent limits as formulated in the Environmental Protection (Effluent Limitations)(Amendment) Regulations, 2009. S.I. 102 of 2009 with standards set for the Washington State, U.S.A.. The effluents limits for Belize are comparable with the limitations set for Washington State, and justifiable to be used for the proposed Placencia sewerage treatment system. 

 

 

 

 

 

Page 20: Environmental and Social Analysis

19  Meerman & Boomsma, Environmental and Social Analysis ‐  Wastewater Collection, Treatment, and Disposal System –Placencia Peninsula – DRAFT – 26 September 2010 

    

TABLE 2 EFFLUENT LIMITS BELIZE COMPARED WITH EFFLUENT LIMITS FOR WASHINGTON STATE, U.S.A. 

Parameter  Effluent limits into Class I waters (Belize) 

Discharge to surface waters http://cclme.org/collection/2‐WAC_173‐221.txt (Washington State)  

Discharge to waste stabilization ponds, less than 2 million gallon per day design http://cclme.org/collection/2‐WAC_173‐221.txt (Washington State)  

    3o day average 

Seven day average 

30 day average 

Seven day average 

Total Suspended Solids (TSS) 

30 mg/L (does not include algae from treatment ponds) 

30 mg/L    45 mg/L   30 mg/L    45 mg/L  

Biochemical Oxygen Demand (BOD) 

30 mg/L  30 mg/L  45 mg/L  30 mg/L  45 mg/L 

pH  5‐10 pH units  6.0‐9.0  6.0‐9.0  6.0‐9.0  6.0‐9.0 

Fats, oil and grease  15 mg/L  N.A.  N.A.  N.A.  N.A. 

Faecal coliform  200 mpn/100 ml  200 organism/100 ml6 

400 organism/100 ml7 

200 organism/100 ml8 

400 organism/100 ml9 

E. coli (fresh water)  126 organism/100 ml 

N.A.  N.A.  N.A.  N.A. 

Enterococci (saline water) 

35 mg/ 100 ml  N.A.  N.A.  N.A.  N.A. 

Floatables  Not visible  N.A.  N.A.  N.A.  N.A. 

           

 

 

   

                                                            6 Monthly geometric mean (The geometric mean, in mathematics, is a type of mean or average, which indicates the central tendency or typical value of a set of numbers. It is similar to the arithmetic mean, which is what most people think of with the word "average", except that the numbers are multiplied and then the nth root (where n is the count of numbers in the set) of the resulting product is taken). 

 

7 Weekly geometric mean 

8 Monthly geometric mean  

9 Weekly geometric mean 

Page 21: Environmental and Social Analysis

20  Meerman & Boomsma, Environmental and Social Analysis ‐  Wastewater Collection, Treatment, and Disposal System –Placencia Peninsula – DRAFT – 26 September 2010 

    

4. Impact of improved sanitation facilities on the environment 

Over the past two decades, the tourism development on the Placencia Peninsula resulted in an increase of the population to an estimated permanent population of around 3,000 persons, to a seasonal high of about 10,000 persons. The provision of a Rudimentary Water System  (RWS), allowed  the  residents  to improve their sanitation and hygiene standards, resulting in an increase of the average use of water per person per day. This however, has translated into a waste water problem. Basically one can assume that what comes in will go out, and regardless the sanitation facilities of the particular households, all waste water will be returned to the environment. 

The carrying capacity of the peninsula’s environment is very limited to handle waste and wastewater in an environmentally acceptable way. This is a result of the physical characteristics of the peninsula which is nothing more than a  long and narrow sand spit. Sand does not have a  large absorption complex  like clay,  and excess amounts of nutrients will pass  through and end up  in  the  shallow  fresh water  layer under  the peninsula and ultimately  flushed out  towards  the sea and  the  lagoon on either side of  the peninsula. Filtration time  is short and pathogens are not sufficiently killed off, which  is confirmed  in a recent study that showed the presence of streptococci in the lagoon water (J. Franco, 2010, unpublished data).   

The  original  sanitation method  on  the  peninsula  was  nothing more  than  collecting  the  waste  and dispose of  it on  the beach or  in  the  sea or  lagoon. This method  is prosaically  called  the  ‘honey pot’ method and it was still practiced at least until 2003 (Areola, 2003). Other sanitation facilities comprised of pit  latrines  (improved and non‐improved)  for households who had not or could not  invested  in the construction of a  flush  toilet and  septic system. As  long as  the water  table  is  low or  the pit  latrine  is elevated, this is a sanitation method that could function, as long as no wells for the collecting of water are developed nearby. But ground water table is often high, resulting in ‘flushing out’ of the contents of the latrine pit. 

Households with  flush toilets built septic  tanks  (with or without sealed bottom),  leach pits, and other constructions that for the eye function well but in real are slowly polluting the environment. Often, grey water  from  shower  units  and  kitchen  sinks  are  freely  drained  in  the  yard,  resulting  in  un‐hygienic conditions. 

The  first hotels had small to medium capacities and the most common sanitation  facility was a septic tank with a soak‐away field. The last decade, the Department of Environment does not allow septic tank system to be built for tourism accommodations; they order the use of so‐called package‐plants. Package plants are adequate solutions  for  the handling of waste water to a certain extent, but the discharged effluents still contain a high level of nutrients , and if these effluents does not receive a form of tertiary treatments, the nutrients can still be detrimental to the environment of the  lagoon and the sea where the nutrients ultimately will end up. 

Taking  the  above  into  consideration,  the  need  for  an  improved  sanitation  system  is  clear.  A  piped sewerage system that will collect all grey and black wastewater from the peninsula, and properly treat it so  it will not negatively  impact the quality of the  lagoon or the sea will benefit the environment,  local and visiting population and ultimately, the peninsula’s economy. 

First of all, proper  sanitation  facilities will  improve  the quality of  life of  the population, offer  them a dignified  way  of  using  the  bathroom  and  improve  the  hygienic  conditions  in  their  households  by resolving the problem of grey waste water that until now is usually just spilled in the yard. 

Page 22: Environmental and Social Analysis

21  Meerman & Boomsma, Environmental and Social Analysis ‐  Wastewater Collection, Treatment, and Disposal System –Placencia Peninsula – DRAFT – 26 September 2010 

    

Secondly,  an  improved way of handling human waste will offer  the people healthier  living  condition whereby the amount of water borne diseases will be reduced, resulting in considerable savings for the people. 

Tourism  will  be  positively  affected,  because  the  peninsula  can  boast  a  healthy  clean  environment without persons running the risk of ending up in contaminated waters.  

The  water  quality  of  the  lagoon  and  the  sea  will  be  safeguarded  from  excess  nutrient  levels  and potential pathogens originating  from human waste. The  lagoon  and  the  sea  are  the ultimate natural resources that are the cornerstone of local economic activities like the artisanal fishing industry and the tourism industry.  

Providing proper  sanitation  is  also  a  very  cost  effective way of providing  assistance  to  the  local  and national economy. Evaluation of the costs and benefits of water and sanitation improvements estimated that the economic return from improved sanitation is about US$ 10 for every US$ 1 invested.10 

 

 

 

                                                            10 World Business Council for Sustainable Development, http://www.wbcsd.org/ 

Page 23: Environmental and Social Analysis

22 Meerman & Boomsma, Environmental and Social Analysis ‐  Wastewater Collection, Treatment, and Disposal System – Placencia Peninsula – DRAFT – 26 September 2010 

    

4.1.1. Potential impacts of activities during construction and operation phases 

Description of impacts 

   

Project activity 

Potential Environmental Impacts Positive/ Negative 

Direct/ indirect 

Short term/ long term 

Avoidable/un‐avoidable 

Reversible/ irreversible 

Magnitude Environ‐mental costs /benefits 

Digging trenches 

Removal vegetation Negative Direct Short  Unavoidable Reversible Small Low cost

  Disturbing landscaped gardens Negative Direct Short  Unavoidable Reversible Small Low cost

  Removal fences  Negative Direct Short  Unavoidable Reversible Small Low cost

  Disturbance soil  Negative Direct Short  Unavoidable Reversible Small Low cost

  Need access to private yards Negative Direct Short  Unavoidable Reversible Small Low cost

  Dust production  Negative Direct Short  Avoidable Reversible Small Low cost

  Noise production  Negative Direct Short  Unavoidable Reversible Small Low cost

  Open trenches dangerous for traffic Negative Indirect Short  Avoidable Reversible Medium Low cost

  Blocking of traffic  Negative Indirect Short  Avoidable Reversible Medium Low cost

  Breaking of water and other utility lines 

Negative Indirect Short  Avoidable Reversible Medium/High Medium cost

  Unsightly sight after completion Negative Direct Short  Avoidable Reversible Small Low cost

Placing sub‐marine cable/  pipe depending on location 

Removal marine/coastal vegetation Negative Direct Short  Unavoidable Irreversible Small Low cost

Increase siltation  Negative Indirect Short  Unavoidable Reversible Small Low cost

Obstruction boating traffic Negative Direct Short  Unavoidable Reversible Small Low cost

Page 24: Environmental and Social Analysis

23 Meerman & Boomsma, Environmental and Social Analysis ‐  Wastewater Collection, Treatment, and Disposal System – Placencia Peninsula – DRAFT – 26 September 2010 

    

   

Project activity 

Potential Environmental Impacts Positive/ Negative 

Direct/ indirect 

Short term/ long term 

Avoidable/un‐avoidable 

Reversible/ irreversible 

Magnitude Environ‐mental costs /benefits 

Construction access road to the sewerage treatment site (dependent on final design and location) 

Private land acquisition Negative Direct Long Unavoidable Irreversible Medium Medium cost

Removal natural vegetation Negative Direct Short  Unavoidable Reversible Medium Low cost

Trucking movements to haul in road fill 

Negative Indirect Short  Unavoidable Reversible Small Low cost

Disturbance natural drainage Negative Indirect Long Avoidable Irreversible Medium Medium cost

Excavation of road fill material Negative Indirect Short  Unavoidable Irreversible Medium Medium cost

Prepare sewerage treatment site 

Private land acquisition Negative Direct Long Unavoidable Irreversible High High cost

Removal natural vegetation Negative Direct Short  Unavoidable Irreversible Medium Medium cost

Dumping of waste soil Negative Direct Short  Unavoidable Irreversible Medium Medium cost

  Increase siltation resulting from earth works 

Negative Indirect Short  Avoidable Reversible Small Low cost

  Quarrying for lining material (when applicable) 

Negative Direct Short  Unavoidable Irreversible Medium Medium cost

  Dust production  Negative Indirect Short  Avoidable Reversible Small Low cost

  Noise production  Negative Indirect Short  Unavoidable Reversible Small Low cost

Installing individual pumps  

Cost price pump units Negative Direct Short  Unavoidable Irreversible High High cost

Connecting costs  Negative Direct Short  Unavoidable Irreversible Medium Medium cost

  Operation costs pump Negative Direct Long Unavoidable Irreversible Small/medium 

Medium cost

  Maintenance schedule Negative Direct Long Unavoidable Irreversible Small Medium cost

Page 25: Environmental and Social Analysis

24 Meerman & Boomsma, Environmental and Social Analysis ‐  Wastewater Collection, Treatment, and Disposal System – Placencia Peninsula – DRAFT – 26 September 2010 

    

                                                            11 Easily mitigated following standard design and management procedures 

Project activity 

Potential Environmental Impacts Positive/ Negative 

Direct/ indirect 

Short term/  long term 

Avoidable/un‐avoidable 

Reversible/ irreversible 

Magnitude Environ‐mental costs /benefits 

Building centralized pumpstations 

Land requirements Negative Direct Short  Unavoidable Irreversible Small Low cost

  Traffic obstructions Negative Indirect Short  Avoidable Reversible Small Low cost

  Noise  Negative Indirect Short  Unavoidable Reversible Small Low cost

  Unsightly sight after completion Negative Direct Short  Avoidable Reversible Small Low cost

Operational phase sewerage system 

Costs of improving individual sanitation facilities to flush toilets 

Negative Indirect Short  Unavoidable Irreversible Medium Medium cost

  Extra costs for users system Negative Direct Long Unavoidable Irreversible Small Medium cost

  Diffuse and uncontrolled discharge of effluents changed into a controllable point release 

Positive Direct Long N.A. Reversible High High benefit

  Health benefits  Positive Direct Long N.A. N.A. High High benefit

  Improvement of living conditions Positive Direct Long N.A. N.A. High High benefit

  Economic benefits through improved tourism opportunities 

Positive Direct Long N.A. N.A. High High benefit

  Improved water quality of lagoon and sea 

Positive Direct Long N.A. Depending on project success 

High High benefit

  Miasmatic system  Negative Indirect Long Avoidable11 Reversible Low Medium cost

  System creates mosquito breeding opportunities 

Negative Indirect Long Avoidable11 Reversible Medium Medium cost

Page 26: Environmental and Social Analysis

25 Meerman & Boomsma, Environmental and Social Analysis ‐  Wastewater Collection, Treatment, and Disposal System – Placencia Peninsula – DRAFT – 26 September 2010 

    

 

  

 

   

Project activity 

Potential Environmental Impacts Positive/ Negative 

Direct/ indirect 

Short term/  long term 

Avoidable/un‐avoidable 

Reversible/ irreversible 

Magnitude Environ‐mental costs /benefits 

Failure of system: power failure 

System not working Negative Indirect Short  Avoidable Reversible Medium Low cost

Failure of system: broken pipes 

System not working Negative Indirect Short  Unavoidable Reversible Medium Low cost

  Spillage/leakage of sewerage Negative Indirect Short Avoidable Reversible Medium Low cost

Removal old sanitation systems 

Contaminated septic contents/soil Negative Indirect Short  Unavoidable NA Small Low cost

  Construction rubble  Negative Direct Short  Unavoidable Reversible Small Low cost

Page 27: Environmental and Social Analysis

26 Meerman & Boomsma, Environmental and Social Analysis ‐  Wastewater Collection, Treatment, and Disposal System – Placencia Peninsula – DRAFT – 26 September 2010 

    

4.2. Description of mitigation measures 

Note: “Developer” is that entity that ultimately takes on the responsibility for the project, will also be “manager” 

   

Project activity 

Potential Environmental Impacts Proposed mitigation measures Institutional responsibilities 

Cost estimates Comments

Digging trenches 

Removal vegetation After closing trenches, re‐distribute topsoil and replant with appropriate plants 

Contractor Part of contract 

  Disturbing landscaped gardens After closing trenches, re‐distribute topsoil and replace with ornamental plants 

Contractor Part of contract 

Cooperation with land owner 

  Removal fences  After closing trenches, restore fences  Contractor Part of contract 

Cooperation with land owner 

  Disturbance soil  After closing trenches, re‐distribute topsoil  Contractor Part of contract 

Cooperation with land owner 

  Need access to private yards Ask permission from landowner and land user to enter private yards  

All authorized employees carry identification cards 

Develop grievance mechanism 

Open hotline (telephone) 

Contractor Part of contract 

Cooperation with land owner 

  Dust production  If needed, use sprinkler system (vehicle) to wet the soil 

Contractor Part of contract 

Cooperation with land owner 

  Noise production  Use properly maintained machinery, adhere to noise pollution regulations. 

No use of heavy machinery before 7 am and after 6 pm 

Contractor Part of contract 

  Open trenches dangerous for traffic 

Demarcate open trenches, if needed with lights in the night 

Contractor Part of contract 

Page 28: Environmental and Social Analysis

27 Meerman & Boomsma, Environmental and Social Analysis ‐  Wastewater Collection, Treatment, and Disposal System – Placencia Peninsula – DRAFT – 26 September 2010 

    

   

Project activity 

Potential Environmental Impacts Proposed mitigation measures Institutional responsibilities 

Cost estimates Comments

Digging trenches 

Blocking of parcel access Guarantee access to premises by covering open trenches with steel covers for the night 

Businesses remain accessible, day and night 

Contractor Part of contract 

  Breaking of water and other utility lines 

Liaise with water board about location of the water pipes 

Liaise with BEL about standby crew for repair on power lines 

Liaise with land owners about other underground utility lines 

Have repair kit (tools and materials) available to make immediate repairs if needed 

Contractor, BWSL, BEL 

Part of contract 

  Unsightly situation after completion 

After completion of trenches, remove all construction materials, refill trenches 

One month after filling trenches, verify the level of fill, if soil has caved in, make needed fill to level ground 

Contractor Part of contract 

Placing sub‐marine pipe 

Removal marine/coastal vegetation 

Minimize amount of plants that have to be removed by good planning of activities and proper instruction of work crew about the need to minimize destruction natural habitat 

Contractor Part of contract 

  Increase siltation  Use siltation screens were appropriate  Contractor Part of contract 

  Obstruction boating traffic Place signs to regulate boat traffic

Sewer pipes should be dug in not to obstruct larger boats with deep draft  

Contractor Part of contract 

Page 29: Environmental and Social Analysis

28 Meerman & Boomsma, Environmental and Social Analysis ‐  Wastewater Collection, Treatment, and Disposal System – Placencia Peninsula – DRAFT – 26 September 2010 

    

   

                                                            12 Assumed to be BWSL 

Project activity 

Potential Environmental Impacts Proposed mitigation measures Institutional responsibilities 

Cost estimates Comments

Construction access road to the sewerage treatment site 

Private land acquisition Long term lease of private land to guarantee access to treatment site or acquisition of private land 

Government land: establish road reserve 

Developer12 Land acquisition price 

  Removal natural vegetation Determine preferred trajectory of road, taking into consideration removal of natural vegetation, presence of plant species with high conservation value, need for land fill, potential obstruction of natural drainage pattern, costs of the various trajectory options 

Developer, Contractor, 

Consultant 

Environmental Impact Assessment 

Engineering cost 

Cost estimate needs to be added to final version of this document 

  Trucking movements to haul in road fill 

The amount of fill needed to construct the access road, is one of the parameters that has to be taken into consideration when the access road trajectory is to be determined 

Developer, Contractor, 

Consultant 

Environmental Impact Assessment 

Engineering cost 

Cost estimate needs to be added to final version of this document 

  Disturbance natural drainage Hydrology study is required to understand the local drainage pattern and proper action has to be taken not to obstruct the drainage of the ‘upstream’ land 

Developer, Contractor, 

Design consultant 

Environmental Impact Assessment 

Engineering cost 

Cost estimate needs to be added to final version of this document 

  Excavation of road fill material road fill material has to be produced by existing quarries; in case new quarry sites have to be developed, licenses are needed from the Department of Geology  

Developer, Contractor, 

Consultant 

Environmental Impact Assessment 

Engineering cost 

Cost estimate needs to be added to final version of this document 

Page 30: Environmental and Social Analysis

29 Meerman & Boomsma, Environmental and Social Analysis ‐  Wastewater Collection, Treatment, and Disposal System – Placencia Peninsula – DRAFT – 26 September 2010 

    

   

Project activity 

Potential Environmental Impacts Proposed mitigation measures Institutional responsibilities 

Cost estimates Comments

Prepare sewerage treatment site 

Private land acquisition The process of land acquisition has to be finalized before development of sewage ponds can start 

Developer Land acquisition price 

  Removal natural vegetation A system has to be developed whereby plants of conservation value like orchids, Zamia’s can be rescued by appropriate entities and used in botanical gardens or similar for research or display 

Developer, Contractor, 

Consultant 

Environmental Impact Assessment 

Engineering cost 

Cost estimate needs to be added to final version of this document 

  Dumping of waste soil Excavated soil has to be characterized and a plan for re‐use of these soils has to be drafted. 

Developer, Contractor, 

Consultant 

Environmental Impact Assessment 

Engineering cost 

Cost estimate needs to be added to final version of this document 

  Increase siltation resulting from earth works 

Use siltation screens to prevent the run‐off of sediment into the water bodies 

Contractor Part of contract 

  Quarrying for lining material(when applicable) 

If local clays have to be excavated, the proper licenses have to be acquired from the Department of Geology 

Developer, Contractor 

Part of contract 

  Dust production  Wet the road surface and other surface to minimize dust production 

Contractor Part of contract 

  Noise production  Use properly maintained machinery, adhere to noise pollution regulations  

No use of heavy machinery before 7 am and after 6 pm 

Contractor Part of contract 

Page 31: Environmental and Social Analysis

30 Meerman & Boomsma, Environmental and Social Analysis ‐  Wastewater Collection, Treatment, and Disposal System – Placencia Peninsula – DRAFT – 26 September 2010 

    

   

Project activity 

Potential Environmental Impacts Proposed mitigation measures Institutional responsibilities 

Cost estimates Comments

Installing individual pumps  

Cost price pump units The cost of household pump units has to be included in the total price of the proposed project 

Developer Part of development costs 

There is a strong social component here. Can all users afford this? This needs to be addressed in a cost‐benefit analysis 

Connecting costs  Costs will be subject to PUC agreed rates. 

The connecting costs should be included in the total price of the proposed project 

For new housing developments: these costs should be included in the lot price, land developer is responsible for the connection of the houses to the sewerage system 

Developer, Land/Lot owner 

Part of development costs 

There is a strong social component here. Can all users afford this? This needs to be addressed in a cost‐benefit analysis 

Operation costs individual pump(in this and/or later stages of the project) 

The operation costs of the individual pump are often compared to the costs of a 40 Watt light bulb. With continuous use, the costs per day will thus amount to BZE$ 1.‐‐, with intermittent use the costs per day may be BZE $ 0.10 (uncertain). The user of the system is responsible to pay for each costs 

User Part of individual running costs 

There is a strong social component here. Can all users afford this? This needs to be addressed in a cost‐benefit analysis 

Page 32: Environmental and Social Analysis

31 Meerman & Boomsma, Environmental and Social Analysis ‐  Wastewater Collection, Treatment, and Disposal System – Placencia Peninsula – DRAFT – 26 September 2010 

    

Project activity 

Potential Environmental Impacts Proposed mitigation measures Institutional responsibilities 

Cost estimates Comments

Installing individual pumps 

Maintenance schedule User of the system is responsible for daily maintenance, proper use, monitoring reporting of failures of the system.  

 

User, Developer.

The ownership of individual pumps has to be agreed upon.   

Part of individual running costs.  There will be an add‐on operation cost for individual maintenance 

There is a strong social component here. Can all users afford this? This needs to be addressed in a cost‐benefit analysis 

Periodic maintenance will be the responsibility of the entity managing the system, costs should be reflected in the users fee 

Building centralized pump stations 

Land requirements First option is to locate these pump stations on national land. If national land is not available at the proper locations, land acquisition will have to take place. 

Developer, Contractor, 

Consultant 

Environmental Impact Assessment 

Engineering cost 

Cost estimate needs to be added to final version of this document 

Location of the pump houses must not conflict with other (future) developments on the peninsula 

  Traffic obstructions Construction of the central pump station is not to interfere with traffic  

Developer, Contractor, 

Consultant 

Environmental Impact Assessment 

Engineering cost 

Cost estimate needs to be added to final version of this document 

  Noise  Use properly maintained machinery, adhere to noise pollution regulations  

No use of heavy machinery before 7 am and after 6 pm 

Contractor Part of contract 

  Unsightly situation after completion 

Inspect finished pump houses to ensure proper clean up of the construction materials etc. 

Contractor Part of contract 

Landscape surrounding areas after completion of the pump house 

Page 33: Environmental and Social Analysis

32 Meerman & Boomsma, Environmental and Social Analysis ‐  Wastewater Collection, Treatment, and Disposal System – Placencia Peninsula – DRAFT – 26 September 2010 

    

Project activity 

Potential Environmental Impacts Proposed mitigation measures Institutional responsibilities 

Cost estimates Comments

Operational phase sewerage system 

Costs of improving individual sanitation facilities to flush toilets 

Outfit low income families with a pre‐fabricated  flush toilet unit, to replace pit latrines 

User, Developer Part of individual running costs 

There is a strong social component here. Can all users afford this? This needs to be addressed in a cost‐benefit analysis 

Advocate the use of water saving devices and water saving manners  

Develop technical assistance package to educate population about proper sanitation facilities 

  Extra costs for users system Develop a prop‐poor rate users fee structure 

Develop a fee structure that allows small users affordable fees 

User, Developer Part of individual running costs 

There is a strong social component here. Can all users afford this? This needs to be addressed in a cost‐benefit analysis 

  Diffuse and uncontrolled discharge of effluents changed into a controllable point release 

Connection to the sewerage system should 

be mandatory, monitor this. 

Government will need to enact legislation for mandatory connection. 

User, Developer, Government 

Part of individual running costs 

There is a strong social component here. Can all users afford this? This needs to be addressed in a cost‐benefit analysis 

  Miasmatic system   Proper design, implementation and management of the ponds 

Developer Part of operational costs 

  System creates mosquito breeding opportunities 

Use of certain fish species that prey on mosquito larvae 

Developer Part of operational costs 

Page 34: Environmental and Social Analysis

33 Meerman & Boomsma, Environmental and Social Analysis ‐  Wastewater Collection, Treatment, and Disposal System – Placencia Peninsula – DRAFT – 26 September 2010 

    

Project activity 

Potential Environmental Impacts Proposed mitigation measures Institutional responsibilities 

Cost estimates Comments

Failure of system: power failure 

System not working Back‐up generator(s) to power pump houses 

Developer Part of operational costs 

Failure of system: broken pipes 

System not working Stand by crew (24/7) to make needed repairs 

Hotline for failure reports 

 

Developer Part of operational costs 

  Spillage/leakage of sewerage Stand by crew (24/7) to make needed repairs 

Hotline for failure reports 

 

Developer Part of operational costs 

Removal old sanitation systems 

Contaminated septic contents/soil Develop a plan for cleanup campaign, decide site by site the preferred option for the de‐commissioning of the existing  sanitation facilities 

Developer Part of operational costs 

  Construction rubble  Use construction waste to fill in redundant latrine and leach pits 

Developer Part of operational costs 

Page 35: Environmental and Social Analysis

34 Meerman & Boomsma, Environmental and Social Analysis ‐  Wastewater Collection, Treatment, and Disposal System – Placencia Peninsula – DRAFT – 26 September 2010 

    

4.3. Description of a monitoring program 

   

Project activity 

Potential Environmental Impacts 

Proposed mitigation measures 

Parameters to be monitored 

Location  Methods and equipment 

Frequency  Responsibilities  Cost (B$) 

Digging trenches 

Removal vegetation  After closing trenches, re‐distribute topsoil and replant with appropriate plants 

Leveling soil, replanted with appropriate plants. Baseline will be digital pictures of yards before start of works 

Villages, peninsula 

Personal visit at the site, 

Digital camera 

Baseline before start of activities. Once: after completion of the trenching  

Baseline + final report including photographs 

Initial costs camera $ 500; $ 100 per 100 yard length of pipe 

  Disturbing landscaped gardens 

After closing trenches, re‐distribute topsoil and replace with ornamental plants 

Leveling soil, replanted with appropriate ornamental plants.  Baseline will be digital pictures of yards before start of works 

Individual houselots 

Personal visit at the site, 

Digital camera 

Baseline before start of activities. Once: after completion of the trenching  

Baseline + final report including photographs 

Initial costs camera $ 500; $ 20 per houselot 

  Removal fences  After closing trenches, restore fences 

Restoration of the fences.  Baseline will be digital pictures of yards before start of works 

Where fences where removed 

Personal visit at the site, 

Digital camera 

Once: after completion of the trenches 

Personal visit at the site, 

Digital camera 

Initial costs camera $ 500; $ 20 per houselot 

  Need access to private yards 

Ask permission from landowner and land user to enter private yards 

All authorized employees carry identification cards

Develop grievance mechanism 

Open hotline (telephone) 

Documentation of communication filed per connection 

Signed forms allowing crew access to property 

One file containing grievance documentation and follow‐up actions 

Logbook of any calls made to hotline and follow‐up actions 

Head quarters contractor 

Computer files and hard copy files 

Permission: for all privately owned land 

Contractor  Database development: $5,000  Data base management 

Page 36: Environmental and Social Analysis

35 Meerman & Boomsma, Environmental and Social Analysis ‐  Wastewater Collection, Treatment, and Disposal System – Placencia Peninsula – DRAFT – 26 September 2010 

    

   

Project activity 

Potential Environmental Impacts 

Proposed mitigation measures 

Parameters to be monitored 

Location  Methods and equipment 

Frequency  Responsibilities  Cost (B$) 

  Dust production  If needed, use sprinkler system (vehicle) to wet the soil 

Excessive dust production Dust plume higher than 5 yards 

Where excavation activities are taking place at that time 

Visual  When needed  Reporting: activity schedule of the watering truck: when and where active 

Develop activity logbook $ 500.‐‐ 

  Noise production  Use properly maintained machinery, adhere to noise pollution regulations. 

No use of heavy machinery before 7 am and after 6 pm 

Adhere to the noise levels as stipulated in Pollution regulations, 1996. S.I. 56 of 1996 

At construction sites 

Noise level measurements with dB meter 

At random  Report, including construction site activities and noise levels at certain distances 

Equipment $ 150. Monitoring $ 25/day 

  Open trenches dangerous for traffic 

Demarcate open trenches, if needed with lights in the night 

Open trenches are sign posted? 

Where appropriate 

Personal visit at the site, 

Digital camera 

When needed  Report including photographs 

Initial costs camera $ 500; $ 20 per open trench 

  Blocking of traffic  Guarantee access to premises by covering open trenches with steel covers for the night 

Businesses remain accessible, day and night 

Access to house lots remain open during evening hours 

Access to businesses remain open during the day and night 

Where appropriate 

Personal visit at the site, 

Digital camera 

When needed  Report including photographs 

Initial costs camera $ 500; $ 20 per open trench 

Page 37: Environmental and Social Analysis

36 Meerman & Boomsma, Environmental and Social Analysis ‐  Wastewater Collection, Treatment, and Disposal System – Placencia Peninsula – DRAFT – 26 September 2010 

    

   

Project activity 

Potential Environmental Impacts 

Proposed mitigation measures 

Parameters to be monitored 

Location  Methods and equipment 

Frequency  Responsibilities  Cost (B$) 

  Breaking of water and other utility lines 

Liaise with water board about location of the water pipes 

Liaise with BEL about standby crew for repair on power lines 

Liaise with land owners about other underground utility lines 

Have repair kit (tools and materials) available to make immediate repairs if needed 

Contractor has a set of blueprints outlining the water mains and other underground utility lines  

Contractor has telephone numbers of involved utility companies (BEL, water board, cable companies) 

Contractor has repair kits for water mains 

Other utility companies have repair equipment available at the peninsula 

Where needed 

Visual  When needed  One time, at the start of the project 

Liaison costs (telephone etc) 

  Unsightly situation after completion 

After completion of trenches, remove all construction materials, refill trenches 

One month after filling trenches, verify the level of fill, if soil has caved in, make needed fill to level ground 

Remove all construction materials, rubbish. Leveling soil 

Villages, peninsula 

Personal visit at the site, 

Digital camera 

Twice: first time after closing trenches, second time after closing trenches 

Report including photographs 

Initial costs camera $ 500; $ 100 per 100 yard length of pipe 

Page 38: Environmental and Social Analysis

37 Meerman & Boomsma, Environmental and Social Analysis ‐  Wastewater Collection, Treatment, and Disposal System – Placencia Peninsula – DRAFT – 26 September 2010 

    

   

Project activity 

Potential Environmental Impacts 

Proposed mitigation measures 

Parameters to be monitored 

Location  Methods and equipment 

Frequency  Responsibilities  Cost (B$) 

Placing sub‐marine cable 

Removal marine/coastal vegetation 

Minimize amount of plants that have to be removed by good planning of activities and proper instruction of work crew about the need to minimize destruction natural habitat 

Monitor the width of the trench to be dig in the lagoon bottom 

Lagoon  Measuring tape, depth sounder 

Daily during excavation activities 

reporting  $ 1000/week 

  Increase siltation  Use siltation screens were appropriate 

Turbidity level 100 yards downstream of activities 

Lagoon  Secchi disk  Daily  Reporting  Turbidity test, boat trip $ 1000/day 

  Obstruction boating traffic 

Place signs to regulate boat traffic 

Sewer pipes should be dug in not to obstruct larger boats with deep draft  

Sign posting upcoming activities 

Measure depth of channel before and after placing of the pipe(s) 

Lagoon  Measuring depth  with ‘stick',  Measuring tape, depth sounder 

3 times: first before activities start during low tide, second during construction during low tide, third after placing pipe during low tide 

Report of findings  Measuring stick, depth sounder. Three boat trips $ 200/day 

Page 39: Environmental and Social Analysis

38 Meerman & Boomsma, Environmental and Social Analysis ‐  Wastewater Collection, Treatment, and Disposal System – Placencia Peninsula – DRAFT – 26 September 2010 

    

   

Project activity 

Potential Environmental Impacts 

Proposed mitigation measures 

Parameters to be monitored 

Location  Methods and equipment 

Frequency  Responsibilities  Cost (B$) 

Construction access road to the sewerage treatment site 

Private land acquisition 

Long term lease of private land to guarantee access to treatment site or acquisition of private land 

Government land: establish road reserve 

Present private land: Lease or title to land needed for the access road has to be obtained before any construction activity starts  

Present GOB land: establish road reserve  

 

 

NA  NA  Start project  Copy of title/lease has to be submitted to the funding agency  Documentation (map) of road reserve has to be submitted to funding agency 

NA 

  Removal natural vegetation 

Determine preferred trajectory of road, taking into consideration removal of natural vegetation, presence of plant species with high conservation value, need for land fill, potential obstruction of natural drainage pattern, costs of the various trajectory options 

Scouting of proposed access  road reserve to identify sensitive micro habitats and/or plants of high biological value 

Proposed access road to sewerage treatment ponds 

Identification of sensitive micro habitats and plants of high conservation value 

One time, before construction of access roads starts 

List of names and location (GPS)of habitats and plants of high biological value 

$ 400 per mile road length excl travelling costs biologist 

Page 40: Environmental and Social Analysis

39 Meerman & Boomsma, Environmental and Social Analysis ‐  Wastewater Collection, Treatment, and Disposal System – Placencia Peninsula – DRAFT – 26 September 2010 

    

Project activity 

Potential Environmental Impacts 

Proposed mitigation measures 

Parameters to be monitored 

Location  Methods and equipment 

Frequency  Responsibilities  Cost (B$) 

  Trucking movements to haul in road fill 

The amount of fill needed to construct the access road, is one of the parameters that has to be taken into consideration when the access road trajectory is to be determined 

Evaluation of the different options for access roads 

NA  Assessment matrix with evaluation of the different options taking into account costs, traffic movements, disturbance of local vegetation, drainage pattern etc  

Once, before access road trajectory is surveyed 

Assessment matrix (part of the EIA) 

Part of the EIA 

  Disturbance natural drainage 

Hydrology study is required to understand the local drainage pattern and proper action has to be taken not to obstruct the drainage of the ‘upstream’ land 

Evaluation of the different options for access roads 

NA  Assessment matrix with evaluation of the different options taking into account costs, traffic movements, disturbance of local vegetation, drainage pattern etc  

Once, before access road trajectory is surveyed 

Assessment matrix (part of the EIA) 

Part of the EIA 

  Excavation of road fill material 

Road fill material has to be produced by existing quarries; in case new quarry sites have to be developed, licenses are needed from the Department of Geology  

Verify source of road fill material and quarry operator is in the possession of an adequate quarry license  

NA  Copy of quarry license and contract with project contractor 

Once, at the start of the project unless project is commissioned in stages 

Copy of quarry license and contract has to be submitted to funding agency 

NA 

Page 41: Environmental and Social Analysis

40 Meerman & Boomsma, Environmental and Social Analysis ‐  Wastewater Collection, Treatment, and Disposal System – Placencia Peninsula – DRAFT – 26 September 2010 

    

Project activity 

Potential Environmental Impacts 

Proposed mitigation measures 

Parameters to be monitored 

Location  Methods and equipment 

Frequency  Responsibilities  Cost (B$) 

Prepare sewerage treatment site 

Private land acquisition 

The process of land acquisition has to be finalized before development of sewage ponds can start 

Present private land: Lease or title to land needed for the treatment ponds has to be obtained before any construction activity starts  

NA  NA  Start project  Copy of title/lease has to be submitted to the funding agency   

NA 

  Removal natural vegetation 

A system has to be developed whereby plants of conservation value such as orchids, Zamia’s can be rescued by appropriate entities 

Scouting of proposed treatment ponds to identify plants of high biological value 

Liaise with established conservation organizations (Belize Botanical Gardens, Belize Zoo, Belize Tropical Forest Studies) about the potential to salvage plants with a high biological/conservation value for educational purposes 

Proposed sewerage treatment ponds 

Identification of plants of high conservation value 

Consult with conservation NGO’s 

One time, before construction of sewerage ponds starts 

List of names and location (GPS)of plants of high biological value 

$ 1000 per acre excl travelling costs biologist 

  Dumping of waste soil 

Excavated soil has to be characterized and a plan for re‐use of these soils has to be drafted. 

Properly disposal of excavated soil: or re‐used at the spot or piled up at an appropriate location and in an appropriate way 

 

Sewerage treatment ponds and elsewhere 

Visual check  Once a month  Reporting, including volume of waste soil and location of deposit, including pictures 

$ 300/month 

  Increase siltation resulting from earth works 

Use siltation screens to prevent the run‐off of sediment into the water bodies 

Assess amount of siltation in run‐off streams 

Water bodies near sewerage ponds 

Visual, secchi disk 

After heavy rain 

Reporting including GPS readings and pictures 

$ 300/time 

Page 42: Environmental and Social Analysis

41 Meerman & Boomsma, Environmental and Social Analysis ‐  Wastewater Collection, Treatment, and Disposal System – Placencia Peninsula – DRAFT – 26 September 2010 

    

 

   

Project activity 

Potential Environmental Impacts 

Proposed mitigation measures 

Parameters to be monitored 

Location  Methods and equipment 

Frequency  Responsibilities  Cost (B$) 

Prepare sewerage treatment site 

Quarrying for lining material (when applicable) 

If local clays have to be excavated, the proper licenses have to be acquired from the Department of Geology 

Provider of clays has proper quarrying license 

NA  NA  One time: before excavation of clay starts 

Copy of the permit  NA 

  Dust production  Wet the road surface and other surface to minimize dust production 

Road visibility remains at a minimum of 100 yards 

Access road  Visibility check after a truck passes 

During dry weather 

Reporting: activity schedule of the watering truck: when and where active 

$ 200/visit 

  Noise production  Use properly maintained machinery, adhere to noise pollution regulations  

No use of heavy machinery before 7 am and after 6 pm 

Adhere to the noise levels as stipulated in Pollution regulations, 1996. S.I. 56 of 1996 

Access road  dB meter  Spot checks  Reporting recorded sound levels with number plate of vehicles 

$ 200/visit 

Page 43: Environmental and Social Analysis

42 Meerman & Boomsma, Environmental and Social Analysis ‐  Wastewater Collection, Treatment, and Disposal System – Placencia Peninsula – DRAFT – 26 September 2010 

    

Project activity 

Potential Environmental Impacts 

Proposed mitigation measures 

Parameters to be monitored 

Location  Methods and equipment 

Frequency  Responsibilities  Cost (B$) 

Installing individual pumps  

Cost price pump units 

The cost of household pump units has to be discussed (inclusion in the total price of the proposed project?) 

Provision, installation of individual pump does not come at a cost of individual households 

NA  Sample survey  After delivery of the project 

reporting  $ 1000/ developing and carrying out of sample survey 

  Connecting costs  The connecting costs included in the total price of the proposed project (?) 

For new housing developments: these costs should be included in the lot price, land developer is responsible for the connection of the houses to the sewerage system 

Provision, installation of individual pump does not come at a cost of individual households 

NA  Sample survey  After delivery of the project 

reporting  $ 1000/ developing and carrying out of sample survey 

  Operation costs individual pump  

The operation costs of the individual pump are often compared to the costs of a 40 Watt light bulb. 

With continuous use, the costs per day will thus amount to BZE$ 1.‐‐, with intermittent use the costs per day may be BZE $ 0.10 (uncertain). The user of the system is responsible to pay for each costs 

NA  NA  NA  NA  NA  NA 

Page 44: Environmental and Social Analysis

43 Meerman & Boomsma, Environmental and Social Analysis ‐  Wastewater Collection, Treatment, and Disposal System – Placencia Peninsula – DRAFT – 26 September 2010 

    

Project activity 

Potential Environmental Impacts 

Proposed mitigation measures 

Parameters to be monitored 

Location  Methods and equipment 

Frequency  Responsibilities  Cost (B$) 

Installing individual pumps 

Maintenance schedule 

User of the system is responsible for daily maintenance, proper use, monitoring reporting of failures of the system.  

Head of the household has to fill out a daily/weekly/monthly maintenance schedule 

Each individual pumping unit 

Copying of the maintenance schedule 

Once a month  Collecting maintenance schedule and take appropriate action by failing proper maintenance 

$ 3,000/ month 

Periodic maintenance will be the responsibility of the entity managing the system, costs should be reflected in the users fee 

Periodic maintenance reports are filled out 

NA  Maintenance reports 

Appropriate time intervals  

Monitoring reports  NA 

Building centralized pump stations 

Land requirements  First option is to locate these pump stations on national land. If national land is not available at the proper locations, land acquisition will have to take place. 

Secure national land 

Or 

Negotiate long term lease or through land acquisition 

NA  NA  Once: before the planning phase of the project 

Copy of the title, or declaration of national land, or land acquisition procedure has been finalized 

$ 2,000 

Location of the pump houses must not conflict with other (future) developments on the peninsula and vise versa 

Consult with local authorities about landownership of lots, consult with about future development plans 

Village council, neighbours 

Development plans 

Once, before the planning phase of the project 

Report writing including copies of development plans 

$ 2,000 

Page 45: Environmental and Social Analysis

44 Meerman & Boomsma, Environmental and Social Analysis ‐  Wastewater Collection, Treatment, and Disposal System – Placencia Peninsula – DRAFT – 26 September 2010 

    

   

Project activity 

Potential Environmental Impacts 

Proposed mitigation measures 

Parameters to be monitored 

Location  Methods and equipment 

Frequency  Responsibilities  Cost (B$) 

Building centralized pump stations 

Traffic obstructions  Construction of the central pump station is not to interfere with traffic  

Use of proper traffic signs, roads and streets remain accesible 

Pump house  Visual check  Once a week  Report, including pictures 

$ 100/week 

  Noise  Use properly maintained machinery, adhere to noise pollution regulations  

No use of heavy machinery before 7 am and after 6 pm 

Adhere to the noise levels as stipulated in Pollution regulations, 1996. S.I. 56 of 1996 

Construction sites 

dB meter  Spot checks  Report   Meter $100, monitoring $ 25/day 

  Unsightly situation after completion 

Inspect finished pump houses to ensure proper clean up of the construction materials etc. 

 

Removal of all construction waste 

Pump house  Visual check  One time after completion pump house 

Report, including pictures 

$ 200/pump house 

Landscape surrounding areas after completion of the pump house 

Landscaping of the immediate surroundings of the pump house 

Pump house  Visual check  Two times: first after completion of the landscaping, second two months to monitor the survival of the plants 

Report, including pictures 

$ 400/ month 

Page 46: Environmental and Social Analysis

45 Meerman & Boomsma, Environmental and Social Analysis ‐  Wastewater Collection, Treatment, and Disposal System – Placencia Peninsula – DRAFT – 26 September 2010 

    

   

Project activity 

Potential Environmental Impacts 

Proposed mitigation measures 

Parameters to be monitored 

Location  Methods and equipment 

Frequency  Responsibilities  Cost (B$) 

Operational phase sewerage system 

Costs of improving individual sanitation facilities to flush toilets 

Research potential for assistance to low income families in order to replace pit latrines 

No more pit latrines 

 

Villages  Qualified low‐income households  

One time  Report  ? 

Advocate the use of water saving devices and water saving etiquette  

Maintain a list with households to ensure that all households have been approached 

Villages  Contact all listed households 

Several times during the construction and the first months of operational phases 

Report  $10,000 

Develop technical assistance package to educate population about proper sanitation facilities 

Maintain a list with households to ensure that all households have been approached 

Villages  Contact all listed households 

Several times during the construction and the first months of operational phases 

Report  $10,000 

  Extra costs for users system 

Develop a pro‐poor rate users fee structure 

Develop a fee structure that allows small users affordable fees 

Fee structure is staged, with an affordable fee for reasonable minimum use for low income households 

Service area  Development of the fee structure for the Placencia service area 

One time  NA  NA 

  Diffuse and uncontrolled discharge of effluents changed into a controllable point release 

Connection to the sewerage system should be mandatory, monitor this 

Monitor the presence of household sewerage connections and the disconnection of individual systems 

Each connection 

Visual check  One check for existing structures; buildings under construction when needed 

Report writing  $ 20,000 one time effort 

Page 47: Environmental and Social Analysis

46 Meerman & Boomsma, Environmental and Social Analysis ‐  Wastewater Collection, Treatment, and Disposal System – Placencia Peninsula – DRAFT – 26 September 2010 

    

Project activity 

Potential Environmental Impacts 

Proposed mitigation measures 

Parameters to be monitored 

Location  Methods and equipment 

Frequency  Responsibilities  Cost (B$) 

Operational phase sewerage system 

Miasmatic system   Respond to reports of odorous situations by applying the correct procedures of management of the system 

Occurrence of odors   Sewerage ponds 

Visual, olfactory checks 

Depends on reporting 

Grievance mechanism 

NA 

  System creates mosquito breeding opportunities 

Use of local fish species that prey on mosquito larvae 

Presence of mosquito larvae 

Sewerage ponds, drain field 

Adequate sample nets 

Rainy season, once a month 

Report writing  $ 100/month 

Discharge of effluents in class I water body (Lagoon) 

Water quality testing 

Periodically testing water quality of the lagoon near sewerage treatment ponds  

Lagoon  Testing of water samples on appropriate parameters 

Quarterly  Reporting  $ 1000/3 months 

Failure of system: power failure 

System not working  Back‐up generator(s) to power pump houses 

Monthly testing of the back‐up generator 

Check on amount of fuel, sufficient for 48 hours of operation 

Generator house(s) 

NA  Once a month  Report writing  NA 

Failure of system: broken pipes 

System not working  Stand by crew to make needed repairs 

Hotline for failure reports 

 

Time lapse between report of failure and repair 

NA  Data base  When needed  Proper reporting by the managing agency 

NA 

  Spillage/leakage of sewerage 

Stand by crew to make needed repairs 

Hotline for failure reports 

 

Time lapse between report of failure and repair 

NA  Data base  When needed  Proper reporting by the managing agency 

NA 

Page 48: Environmental and Social Analysis

47 Meerman & Boomsma, Environmental and Social Analysis ‐  Wastewater Collection, Treatment, and Disposal System – Placencia Peninsula – DRAFT – 26 September 2010 

    

 

   

Project activity 

Potential Environmental Impacts 

Proposed mitigation measures 

Parameters to be monitored 

Location  Methods and equipment 

Frequency  Responsibilities  Cost (B$) 

Removal old sanitation systems 

Contaminated septic contents/soil 

Develop a plan for cleanup campaign (separate project), decide site by site the preferred option for the de‐commissioning of the existing  sanitation facilities 

Contents septic/latrine pits not be moved but holding pits to be filled in with soil/construction waste 

Or 

Licensed sewerage waste collector collects the contents of septic and discharged at approved locations (acc to license issued by DoE) 

Villages  Visual inspection 

Per connection, when needed 

Reporting, including pictures  Or  Copy of hired waste collector 

$ 100/week 

  Construction rubble   Use construction waste to fill in redundant latrine and leach pits 

Destination of construction waste 

Villages  Visual inspection 

Weekly, for a 6 month period 

Reporting including pictures 

$ 100/week 

Page 49: Environmental and Social Analysis

48 Meerman & Boomsma, Environmental and Social Analysis ‐  Wastewater Collection, Treatment, and Disposal System – Placencia Peninsula – DRAFT – 26 September 2010 

    

4.3.1. Agencies that could be incorporated in Monitoring 

 

                                                            13 Assumed to be BWSL 

Project activity 

Potential Environmental Impacts 

Proposed mitigation measures 

Parameters to be monitored 

Entity responsible for monitoring 

Methods and equipment 

Frequency  Responsibilities  Cost (B$) 

Digging trenches 

Removal vegetation  After closing trenches, re‐distribute topsoil and replant with appropriate plants 

Leveling soil, replanted with appropriate plants. Baseline will be digital pictures of yards before start of works 

Developer13 

potentially working with a local NGO 

Personal visit at the site, 

Digital camera 

Baseline before start of activities. Once: after completion of the trenching  

Baseline + final report including photographs 

Initial costs camera $ 500; $ 100 per 100 yard length of pipe 

  Disturbing landscaped gardens 

After closing trenches, re‐distribute topsoil and replace with ornamental plants 

Leveling soil, replanted with appropriate ornamental plants.  Baseline will be digital pictures of yards before start of works 

Developerpotentially working with a local NGO 

Personal visit at the site, 

Digital camera 

Baseline before start of activities. Once: after completion of the trenching  

Baseline + final report including photographs 

Initial costs camera $ 500; $ 20 per houselot 

  Removal fences  After closing trenches, restore fences 

Restoration of the fences.  Baseline will be digital pictures of yards before start of works 

Developerpotentially working with a local NGO 

Personal visit at the site, 

Digital camera 

Once: after completion of the trenches 

Personal visit at the site, 

Digital camera 

Initial costs camera $ 500; $ 20 per houselot 

  Need access to private yards 

Ask permission from landowner and land user to enter private yards 

All authorized employees carry identification cards

Develop grievance mechanism 

Open hotline  

Documentation of communication filed per connection 

Signed forms allowing crew access to property 

File containing grievance documentation and follow‐up actions 

Logbook of calls/ follow‐up actions 

Contractor  Computer files and hard copy files 

Permission: for all privately owned land 

Contractor  Database development: $5,000  Data base management 

Page 50: Environmental and Social Analysis

49 Meerman & Boomsma, Environmental and Social Analysis ‐  Wastewater Collection, Treatment, and Disposal System – Placencia Peninsula – DRAFT – 26 September 2010 

    

 

   

Project activity 

Potential Environmental Impacts 

Proposed mitigation measures 

Parameters to be monitored 

Entity responsible for monitoring 

Methods and equipment 

Frequency  Responsibilities  Cost (B$) 

Digging trenches 

Dust production  If needed, use sprinkler system (vehicle) to wet the soil 

Excessive dust production Dust plume higher than 5 yards 

Developerpotentially working with a local NGO 

Visual  When needed  Reporting: activity schedule of the watering truck: when and where active 

Develop activity logbook $ 500.‐‐ 

  Noise production  Use properly maintained machinery, adhere to noise pollution regulations. 

No use of heavy machinery before 7 am and after 6 pm 

Adhere to the noise levels as stipulated in Pollution regulations, 1996. S.I. 56 of 1996 

Developerpotentially working with a local NGO 

Noise level measurements with dB meter 

At random  Report, including construction site activities and noise levels at certain distances 

Equipment $ 150. Monitoring $ 25/day 

  Open trenches dangerous for traffic 

Demarcate open trenches, if needed with lights in the night 

Open trenches are sign posted? 

Developerpotentially working with a local NGO 

Personal visit at the site, 

Digital camera 

When needed  Report including photographs 

Initial costs camera $ 500; $ 20 per open trench 

  Blocking of traffic  Guarantee access to premises by covering open trenches with steel covers for the night 

Businesses remain accessible, day and night 

Access to house lots remain open during evening hours 

Access to businesses remain open during the day and night 

Developerpotentially working with a local NGO 

Personal visit at the site, 

Digital camera 

When needed  Report including photographs 

Initial costs camera $ 500; $ 20 per open trench 

Page 51: Environmental and Social Analysis

50 Meerman & Boomsma, Environmental and Social Analysis ‐  Wastewater Collection, Treatment, and Disposal System – Placencia Peninsula – DRAFT – 26 September 2010 

    

Project activity 

Potential Environmental Impacts 

Proposed mitigation measures 

Parameters to be monitored 

Entity responsible for monitoring 

Methods and equipment 

Frequency  Responsibilities  Cost (B$) 

Digging trenches 

Breaking of water and other utility lines 

Liaise with water board about location of the water pipes 

Liaise with BEL about standby crew for repair on power lines 

Liaise with land owners about other underground utility lines 

Have repair kit (tools and materials) available to make immediate repairs if needed 

Contractor has a set of blueprints outlining the water mains and other underground utility lines  

Contractor has telephone numbers of involved utility companies (BEL, water board, cable companies) 

Contractor has repair kits for water mains 

Other utility companies have repair equipment available at the peninsula 

Contractor  Visual  When needed  One time, at the start of the project 

Liaison costs (telephone etc) 

  Unsightly situation after completion 

After completion of trenches, remove all construction materials, refill trenches 

One month after filling trenches, verify the level of fill, if soil has caved in, make needed fill to level ground 

Remove all construction materials, rubbish. Leveling soil 

Developerpotentially working with a local NGO 

Personal visit at the site, 

Digital camera 

Twice: first time after closing trenches, second time after closing trenches 

Report including photographs 

Initial costs camera $ 500; $ 100 per 100 yard length of pipe 

Page 52: Environmental and Social Analysis

51 Meerman & Boomsma, Environmental and Social Analysis ‐  Wastewater Collection, Treatment, and Disposal System – Placencia Peninsula – DRAFT – 26 September 2010 

    

 

   

Project activity 

Potential Environmental Impacts 

Proposed mitigation measures 

Parameters to be monitored 

Entity responsible for monitoring 

Methods and equipment 

Frequency  Responsibilities  Cost (B$) 

Placing sub‐marine cable 

Removal marine/coastal vegetation 

Minimize amount of plants that have to be removed by good planning of activities and proper instruction of work crew about the need to minimize destruction natural habitat 

Monitor the width of the trench to be dig in the lagoon bottom 

Developerpotentially working with a local NGO 

Measuring tape, depth sounder 

Daily during excavation activities 

reporting  $ 1000/week 

  Increase siltation  Use siltation screens were appropriate 

Turbidity level 100 yards downstream of activities 

Developerpotentially working with a local NGO 

Secchi disk  Daily  Reporting  Turbidity test, boat trip $ 1000/day 

  Obstruction boating traffic 

Place signs to regulate boat traffic 

Sewer pipes should be dug in not to obstruct larger boats with deep draft  

Sign posting upcoming activities 

Measure depth of channel before and after placing of the pipe(s) 

Developerpotentially working with a local NGO 

Measuring depth  with ‘stick',  Measuring tape, depth sounder 

3 times: first before activities start during low tide, second during construction during low tide, third after placing pipe during low tide 

Report of findings  Measuring stick, depth sounder. Three boat trips $ 200/day 

Page 53: Environmental and Social Analysis

52 Meerman & Boomsma, Environmental and Social Analysis ‐  Wastewater Collection, Treatment, and Disposal System – Placencia Peninsula – DRAFT – 26 September 2010 

    

   

Project activity 

Potential Environmental Impacts 

Proposed mitigation measures 

Parameters to be monitored 

Entity responsible for monitoring 

Methods and equipment 

Frequency  Responsibilities  Cost (B$) 

Construction access road to the sewerage treatment site 

Private land acquisition 

Long term lease of private land to guarantee access to treatment site or acquisition of private land 

Government land: establish road reserve 

Present private land: Lease or title to land needed for the access road has to be obtained before any construction activity starts  

Present GOB land: establish road reserve  

 

 

Funding agency  

NA  Start project  Copy of title/lease has to be submitted to the funding agency  Documentation (map) of road reserve has to be submitted to funding agency 

NA 

  Removal natural vegetation 

Determine preferred trajectory of road, taking into consideration removal of natural vegetation, presence of plant species with high conservation value, need for land fill, potential obstruction of natural drainage pattern, costs of the various trajectory options 

Scouting of proposed access  road reserve to identify sensitive micro habitats and/or plants of high biological value 

Independent consultant 

Identification of sensitive micro habitats and plants of high conservation value 

One time, before construction of access roads starts 

List of names and location (GPS)of habitats and plants of high biological value 

$ 400 per mile road length excl travelling costs biologist 

Page 54: Environmental and Social Analysis

53 Meerman & Boomsma, Environmental and Social Analysis ‐  Wastewater Collection, Treatment, and Disposal System – Placencia Peninsula – DRAFT – 26 September 2010 

    

Project activity 

Potential Environmental Impacts 

Proposed mitigation measures 

Parameters to be monitored 

Entity responsible for monitoring 

Methods and equipment 

Frequency  Responsibilities  Cost (B$) 

Construction access road to the sewerage treatment site 

Trucking movements to haul in road fill 

The amount of fill needed to construct the access road, is one of the parameters that has to be taken into consideration when the access road trajectory is to be determined 

Evaluation of the different options for access roads 

Independent consultant 

Assessment matrix with evaluation of the different options taking into account costs, traffic movements, disturbance of local veg, drainage pattern etc  

Once, before access road trajectory is surveyed 

Assessment matrix (part of the EIA) 

Part of the EIA 

  Disturbance natural drainage 

Hydrology study is required to understand the local drainage pattern and proper action has to be taken not to obstruct the drainage of the ‘upstream’ land 

Evaluation of the different options for access roads 

Independent consultant 

Assessment matrix with evaluation of the different options taking into account costs, traffic movements, disturbance of local veg, drainage pattern etc  

Once, before access road trajectory is surveyed 

Assessment matrix (part of the EIA) 

Part of the EIA 

  Excavation of road fill material 

Road fill material has to be produced by existing quarries; in case new quarry sites have to be developed, licenses are needed from the Department of Geology  

Verify source of road fill material and quarry operator is in the possession of an adequate quarry license  

Contractor  Copy of quarry license and contract with project contractor 

Once, at the start of the project unless project is commissioned in stages 

Copy of quarry license and contract has to be submitted to funding agency 

NA 

Page 55: Environmental and Social Analysis

54 Meerman & Boomsma, Environmental and Social Analysis ‐  Wastewater Collection, Treatment, and Disposal System – Placencia Peninsula – DRAFT – 26 September 2010 

    

   

Project activity 

Potential Environmental Impacts 

Proposed mitigation measures 

Parameters to be monitored 

Entity responsible for monitoring 

Methods and equipment 

Frequency  Responsibilities  Cost (B$) 

Prepare sewerage treatment site 

Private land acquisition 

The process of land acquisition has to be finalized before development of sewage ponds can start 

Present private land: Lease or title to land needed for the treatment ponds has to be obtained before any construction activity starts  

 

 

Funding agency  

NA  Start project  Copy of title/lease has to be submitted to the funding agency   

NA 

  Removal natural vegetation 

A system has to be developed whereby plants of conservation value such as orchids, Zamia’s can be rescued by appropriate entities 

Scouting of proposed treatment ponds to identify plants of high biological value 

Concur with established conservation organizations (Belize Botanical Gardens, Belize Zoo, Belize Tropical Forest Studies) about the potential to salvage plants with a high biological/conservation value for research/ educational purposes 

Independent consultant 

Identification of plants of high conservation value 

Consult with conservation NGO’s 

One time, before construction of sewerage ponds starts 

List of names and location (GPS)of plants of high biological value 

$ 1000 per acre excl travelling costs biologist 

  Dumping of waste soil 

Excavated soil has to be characterized and a plan for re‐use of these soils has to be drafted. 

Properly disposal of excavated soil: or re‐used at the spot or piled up at an appropriate location and in an appropriate way 

 

Developerpotentially working with a local NGO 

Visual check  Once a month  Reporting, including volume of waste soil and location of deposit, including pictures 

$ 300/month 

Page 56: Environmental and Social Analysis

55 Meerman & Boomsma, Environmental and Social Analysis ‐  Wastewater Collection, Treatment, and Disposal System – Placencia Peninsula – DRAFT – 26 September 2010 

    

   

Project activity 

Potential Environmental Impacts 

Proposed mitigation measures 

Parameters to be monitored 

Entity responsible for monitoring 

Methods and equipment 

Frequency  Responsibilities  Cost (B$) 

Prepare sewerage treatment site 

Increase siltation resulting from earth works 

Use siltation screens to prevent the run‐off of sediment into the water bodies 

Assess amount of siltation in run‐off streams 

Developerpotentially working with a local NGO 

Visual, secchi disk 

After heavy rain 

Reporting including GPS readings and pictures 

$ 300/time 

  Quarrying for lining material (when applicable) 

If local clays have to be excavated, the proper licenses have to be acquired from the Department of Geology 

Provider of clays has proper quarrying license 

Contractor  NA  One time: before excavation of clay starts 

Copy of the permit  NA 

  Dust production  Wet the road surface and other surface to minimize dust production 

Road visibility remains at a minimum of 100 yards 

Developerpotentially working with a local NGO 

Visibility check after a truck passes 

During dry weather 

Reporting: activity schedule of the watering truck: when and where active 

$ 200/visit 

  Noise production  Use properly maintained machinery, adhere to noise pollution regulations  

No use of heavy machinery before 7 am and after 6 pm 

Adhere to the noise levels as stipulated in Pollution regulations, 1996. S.I. 56 of 1996 

Developerpotentially working with a local NGO 

dB meter  Spot checks  Reporting recorded sound levels with number plate of vehicles 

$ 200/visit 

Page 57: Environmental and Social Analysis

56 Meerman & Boomsma, Environmental and Social Analysis ‐  Wastewater Collection, Treatment, and Disposal System – Placencia Peninsula – DRAFT – 26 September 2010 

    

Project activity 

Potential Environmental Impacts 

Proposed mitigation measures 

Parameters to be monitored 

Entity responsible for monitoring 

Methods and equipment 

Frequency  Responsibilities  Cost (B$) 

Installing individual pumps  

Cost price pump units 

The cost of household pump units has to be included in the total price of the proposed project 

Provision, installation of individual pump does not come at a cost of individual households 

Funding agency  

Sample survey  After delivery of the project 

reporting  $ 1000/ developing and carrying out of sample survey 

  Connecting costs  The connecting costs should be included in the total price of the proposed project 

For new housing developments: these costs should be included in the lot price, land developer is responsible for the connection of the houses to the sewerage system 

Provision, installation of individual pump does not come at a cost of individual households 

Funding agency  

Sample survey  After delivery of the project 

reporting  $ 1000/ developing and carrying out of sample survey 

  Operation costs individual pump  

The operation costs of the individual pump are often compared to the costs of a 40 Watt light bulb. 

With continuous use, the costs per day will thus amount to BZE$ 1.‐‐, with intermittent use the costs per day may be BZE $ 0.10 (uncertain). The user of the system is responsible to pay for each costs 

NA  Executing agency 

NA  NA  NA  NA 

Page 58: Environmental and Social Analysis

57 Meerman & Boomsma, Environmental and Social Analysis ‐  Wastewater Collection, Treatment, and Disposal System – Placencia Peninsula – DRAFT – 26 September 2010 

    

   

Project activity 

Potential Environmental Impacts 

Proposed mitigation measures 

Parameters to be monitored 

Entity responsible for monitoring 

Methods and equipment 

Frequency  Responsibilities  Cost (B$) 

Installing individual pumps 

Maintenance schedule 

User of the system is responsible for daily maintenance, proper use, monitoring reporting of failures of the system.  

 

Head of the household has to fill out a daily/weekly/monthly maintenance schedule 

Executing agency 

Copying of the maintenance schedule 

Once a month  Collecting maintenance schedule and take appropriate action by failing proper maintenance 

$ 3,000/ month 

Periodic maintenance will be the responsibility of the entity managing the system, costs should be reflected in the users fee 

Periodic maintenance reports are filled out 

Executing agency 

Maintenance reports 

Appropriate time intervals  

Monitoring reports  NA 

Building centralized pump stations 

Land requirements  First option is to locate these pump stations on national land.  

Secure national land 

Or 

Negotiate long term lease or through land acquisition 

Funding agency  

NA  Once: before the planning phase of the project 

Copy of the title, or declaration of national land, or land acquisition procedure has been finalized 

$ 2,000 

Location of the pump houses must not conflict with other (future) developments on the peninsula 

Concur with local authorities about landownership neighbouring lots, concur with neighbours about future development plans 

Executing agency 

Development plans 

Once, before the planning phase of the project 

Report writing including copies of development plans 

$ 2,000 

Page 59: Environmental and Social Analysis

58 Meerman & Boomsma, Environmental and Social Analysis ‐  Wastewater Collection, Treatment, and Disposal System – Placencia Peninsula – DRAFT – 26 September 2010 

    

Project activity 

Potential Environmental Impacts 

Proposed mitigation measures 

Parameters to be monitored 

Entity responsible for monitoring 

Methods and equipment 

Frequency  Responsibilities  Cost (B$) 

Building centralized pump stations 

Traffic obstructions  Construction of the central pump station is not to interfere with traffic  

Use of proper traffic signs, roads and streets remain accessible 

Developerpotentially working with a local NGO 

Visual check  Once a week  Report, including pictures 

$ 100/week 

  Noise  Use properly maintained machinery, adhere to noise pollution regulations  

No use of heavy machinery before 7 am and after 6 pm 

Adhere to the noise levels as stipulated in Pollution regulations, 1996. S.I. 56 of 1996 

Developerpotentially working with a local NGO 

dB meter  Spot checks  Report   Meter $100, monitoring $ 25/day 

  Unsightly situation after completion 

Inspect finished pump houses to ensure proper clean up of the construction materials etc. 

 

Removal of all construction waste 

Developerpotentially working with a local NGO 

Visual check  One time after completion pump house 

Report, including pictures 

$ 200/pump house 

Landscape surrounding areas after completion of the pump house 

Landscaping of the immediate surroundings of the pump house 

Developerpotentially working with a local NGO 

Visual check  Two times: first after completion of the landscaping, second two months to monitor the survival of the plants 

Report, including pictures 

$ 400/month 

Page 60: Environmental and Social Analysis

59 Meerman & Boomsma, Environmental and Social Analysis ‐  Wastewater Collection, Treatment, and Disposal System – Placencia Peninsula – DRAFT – 26 September 2010 

    

   

Project activity 

Potential Environmental Impacts 

Proposed mitigation measures 

Parameters to be monitored 

Entity responsible for monitoring 

Methods and equipment 

Frequency  Responsibilities  Cost (B$) 

Operational phase sewerage system 

Costs of improving individual sanitation facilities to flush toilets 

Outfit low income families with a pre‐fabricated  flush toilet unit, to replace pit latrines 

Low‐income households receive a pre‐fab toilet unit 

 

Developerpotentially working with a local NGO 

Qualified low‐income households receive a unit 

One time  Report  $ 1,500 per household 

Advocate the use of water saving devices and water saving etiquette  

Maintain a list with households to ensure that all households have been approached 

Developerpotentially working with a local NGO 

Contact all listed households 

Several times during the construction and the first months of operational phases 

Report  $10,000 

Develop technical assistance package to educate population about proper sanitation facilities 

Maintain a list with households to ensure that all households have been approached 

Developerpotentially working with a local NGO 

Contact all listed households 

Several times during the construction and the first months of operational phases 

Report  $10,000 

  Extra costs for users system 

Develop a pro‐poor rate users fee structure 

Develop a fee structure that allows small users affordable fees 

Fee structure is staged, with an affordable fee for reasonable minimum use for low income households 

Executing agency 

Development of the fee structure for the Placencia service area 

One time  NA  NA 

  Diffuse and uncontrolled discharge of effluents changed into a controllable point release 

Connection to the sewerage system should be mandatory, monitor this 

Monitor the presence of household sewerage connections and the disconnection of individual systems 

Executing agency 

Visual check  One check for existing structures; buildings under construction when needed 

Report writing  $ 20,000 one time effort 

Page 61: Environmental and Social Analysis

60 Meerman & Boomsma, Environmental and Social Analysis ‐  Wastewater Collection, Treatment, and Disposal System – Placencia Peninsula – DRAFT – 26 September 2010 

    

 

Project activity 

Potential Environmental Impacts 

Proposed mitigation measures 

Parameters to be monitored 

Entity responsible for monitoring 

Methods and equipment 

Frequency  Responsibilities  Cost (B$) 

Operational phase sewerage system 

Miasmatic system   Respond to reports of odorous situations by applying the correct procedures of management 

 

Occurrence of odors  Developerpotentially working with a local NGO 

Visual, olfactory checks 

Depends on reporting 

Grievance mechanism 

NA 

  System creates mosquito breeding opportunities 

Use of local fish species that prey on mosquito larvae 

Presence of mosquito larvae 

Developerpotentially working with a local NGO 

Adequate sample nets 

Rainy season, once a month 

Report writing  $ 100/month 

  Discharge of effluents in class I water body (Lagoon) 

Water quality testing 

Periodically testing water quality of the lagoon near sewerage treatment ponds  

DoE  

Testing of water samples on appropriate parameters 

Quarterly  Reporting  $ 1000/3 months 

Failure of system: power failure 

System not working  Back‐up generator(s) to power pump houses 

Monthly testing of the back‐up generator 

Check on amount of fuel, sufficient for 48 hours of operation 

Executing agency 

NA  Once a month  Report writing  NA 

Failure of system: broken pipes 

System not working  Stand by crew (24/7) to make needed repairs 

Hotline for failure reports 

Time lapse between report of failure and repair 

Executing agency 

Data base  When needed  Proper reporting by the managing agency 

NA 

  Spillage/leakage of sewerage 

Stand by crew (24/7) to make needed repairs 

Hotline for failure reports 

Time lapse between report of failure and repair 

Executing agency 

Data base  When needed  Proper reporting by the managing agency 

NA 

Page 62: Environmental and Social Analysis

61 Meerman & Boomsma, Environmental and Social Analysis ‐  Wastewater Collection, Treatment, and Disposal System – Placencia Peninsula – DRAFT – 26 September 2010 

    

 

 

Project activity 

Potential Environmental Impacts 

Proposed mitigation measures 

Parameters to be monitored 

Entity responsible for monitoring 

Methods and equipment 

Frequency  Responsibilities  Cost (B$) 

Removal old sanitation systems 

Contaminated septic contents/soil 

Develop a plan for cleanup campaign, decide site by site the preferred option for the de‐commissioning of the existing  sanitation facilities 

Contents septic/latrine pits not be moved but holding pits to be filled in with soil/construction waste 

Or 

Licensed sewerage waste collector collects the contents of septic and discharged at approved locations (acc to license issued by DoE) 

DoE  Visual inspection 

Per connection, when needed 

Reporting, including pictures  Or  Copy of hired waste collector 

$ 100/week 

  Construction rubble   Use construction waste to fill in redundant latrine and leach pits 

Destination of construction waste 

Developerpotentially working with a local NGO 

Visual inspection 

Weekly, for a 6 month period 

Reporting including pictures 

$ 100/week 

Page 63: Environmental and Social Analysis

62  Meerman & Boomsma, Environmental and Social Analysis ‐  Wastewater Collection, Treatment, and Disposal System –Placencia Peninsula – DRAFT – 26 September 2010 

    

4.3.2. Monitoring agencies 

Different entities will be responsible for the monitoring of the different components of the preparation, execution and operation of the proposes wastewater collection, treatment and disposal system for the Placencia Peninsula. 

By having different entities  involved  in the monitoring process,  it  is  important to create a transparent reporting system that is all information collected is according defined protocols and the outcome of the monitoring process is public. 

A total of six entities will be involved in the monitoring, namely 

Funding agency 

Local NGO 

DoE 

Independent consultant 

Contractor 

Executing agency 

 

Funding agency 

The task of the funding agency is to monitor the security of land ownership of the land needed for the construction  of  the  access  road(s)  to  the  sewerage  treatment  ponds,  the  treatment  pond  system including tertiary treatment by means of marsh land, and the centralized pump stations (if applicable). The acreage of  land needed  for the sewerage ponds must  include  future expansion of  the ponds to a treatment  capacity  of waste water  of  30,000  persons.  The  security  of  land  ownership  is  needed  to guarantee the un‐compromised functioning of the entire wastewater treatment system. 

The  funding  agency  also  is  to  perform  a  cost‐benefit  analysis which  takes  into  account  the  financial situation of the various users of the system. 

Local NGO 

It  is proposed  to have a peninsula based NGO  involved  in monitoring a number of activities  that are needed  to  execute  the  proposed works.  This  NGO  has  to  answer  to  the  responsible  party,  i.e.  the developer (BWSL). A local NGO is familiar with the local conditions and the local population. A number of  monitoring  activities  will  not  require  major  efforts  and  it  is  cost  effective  if  a  locally  based organization can take up the organization and execution of these activities. 

The proposed monitoring activities are basically activities related to the digging of the trenches and the closing of the trenches. These activities will take place in public areas but also on private properties.  

It is the responsibility of the contractor to execute the digging of the trenches from a technical point of view, but  the  local NGO has  to monitor potential disruption of  local  traffic, unsightly conditions after finishing of the works, accessibility of properties, sign posting of dangerous situations. They may become focal point for questions and complaints and may have to act as a mediator between the contractor and the general public. 

Training must be offered in the field of reporting, filing of information, conflict resolution, coordination between the different entities involved in the process. Basic equipment needed for monitoring must be supplied, including office equipment.   

Page 64: Environmental and Social Analysis

63  Meerman & Boomsma, Environmental and Social Analysis ‐  Wastewater Collection, Treatment, and Disposal System –Placencia Peninsula – DRAFT – 26 September 2010 

    

DoE 

The Department of Environment is usually the agency involved in monitoring the construction phase of a project  and  depending  on  the  character  of  the  project,  also  during  the  operational  phase.  In  the proposed monitoring schedule of the ESMP, monitoring of the activities in the field can be done by third parties,  and  DoE  can  limit  its  activities  by  reviewing  the monitoring  reports  if  DoE  agrees with  the proposed ESMP. 

DoE will be  involved  in monitoring  the quality of  the effluents discharged by  the sewerage  treatment ponds.  

Independent consultant 

Although the design of the waste water collection and treatment system  is a highly technical process, the  impact of  the project should be minimized as much as possible.  It  is unavoidable  that a  relatively large  tract of  land on  the mainland will be needed  for  the  construction of  the  treatment ponds.  It  is known (Balick et al, 2000) that the Belizean coastal savanna’s are rich in endemics, plants not occurring elsewhere  in  the world. To mitigate  the  impact of clearing a  large  tract of  land of plants with a high biological  value,  a  qualified  botanist  with  extensive  experience  in  Belize,  is  needed  to  scout  the proposed sites for access road(s) and ponds for the presence of these plants. 

If more than one site is available for the construction of the ponds, the presence of flora and sensitive microhabitats with  a  biological  value must  be  included  in  the  discussion which  location will  be  the preferred option. 

The  consultant’s  responsibility will  also  be  to monitor  the  potentially  salvaging  of  these  plants  and depositing of these plants with appropriate institutions. 

The contractor 

The contracted company that is executing the proposed project is responsible to maintain a proper data management  system  for  the documentation of all  communications between  individual house owners and the company during the construction phase. Protocols have to be developed to acquire access to private properties, and execute  the needed works. A grievance protocol must be developed.  In other words, all contacts with the community have to be documented. 

The contractor is responsible for the sub contractor(s) they hire, for instance dump trucks, boat services, excavators,  welders  for  instance.  They  can  only  contract  persons  or  companies  that  are  in  the possession of the proper  licenses and equipment.  In case fill material for the development of roads or lining material (in case of a clay liner instead of a synthetic liner) is needed for the ponds, only sources that operate under a valid quarry can be contracted. 

All  documentation  must  be  accessible  to  the  local  community,  the  funding  agency,  DoE  or  other authorities. 

Executing agency 

The executing agency will monitor the proper functioning of the system,  including timely maintenance and if needed repair of the pumping units (either individual household units or centralized pumps). They will also be responsible in negotiating a staged fee structure with the Public Utilities Commission, a fee structure  that will  include a  social  fee  for minimal use of water and  therefore minimal production of waste water. 

Page 65: Environmental and Social Analysis

64  Meerman & Boomsma, Environmental and Social Analysis ‐  Wastewater Collection, Treatment, and Disposal System –Placencia Peninsula – DRAFT – 26 September 2010 

    

They will also be  responsible  to ensure  that each  individual household  is  connected  to  the  sewerage system. For future developments, the use of the sewerage system is mandatory.  

The executing agency is responsible to have a back‐up power supply unit stationed at the peninsula and have a repair crew stand by for 24/7. All these activities will be documented and these files are open to the public to scrutinize. 

  

5. Legal requirements for bidding and contract documents 

The following is a bulleted list that summarizes legal requirements that could be included in bidding and contract  documents.  This  list  is  in  no  particular  order  and  by  no means  complete  and  still  open  for discussion. The information in this list is largely derived from the impact analysis tables. 

Contractor will only employ persons who have legal status to enter the labor force in Belize. 

Contractor will abide the Labour Laws 

Social security contributions will be paid for all employees 

Contactor will only hire sub‐contractors who employ persons who have a  legal status to enter the  labor  force  in Belize,  and  abide  the  Labour  Law  and who pay  social  security  for  all  their employees 

All  equipment  used  by  contractor  and  sub‐contractor will  be  properly  serviced  and will  not cause any nuisance (especially in regards to noise and exhaust fumes) to the employees and the general public.  

Contractor  shall  appoint  a  public  relation  officer  who  will  be  responsible  for  the  relations between the company and the general public in regards to the construction activities related to the proposed waste water treatment system. This officer or his/her deputy, have to be available 24/7, for questions, filing of complaints, disruption of services and other matters. 

Contractor will  sign post  telephone numbers where  the general public  can  contact  the public relation person within the company 24/7 

Contractor  shall  compile  information  in  regards  to households, business,  locations, names of persons  in charge, telephone numbers or other ways to contact the occupants of the premises This information shall be documented in electronic files, for each premises a separate entry 

Contractor shall document all communication, being in writing, electronic or verbal in the files.  

Contractor  shall  develop  a  standard  grievance  mechanism  to  file  all  complaints  made  by affected persons, a copy shall be give to the persons who filed a complaint, 

Contractor shall develop a standard with a minimum time frame to answer any complaint filed 

Contractor will  issue any employee who has  to enter private properties with an  identification card that will carry a photograph of the employee. 

Before entering private properties, the contractor or his authorized staff member has to contact the owner/occupant of the  lot and inform the person(s) about the need to enter the property, the character of the activities, the duration of the activities. 

Contractor shall coordinate all the activities in such a way that disruption of private and public life will be minimized as much as possible, and no hazardous conditions will remain longer than needed, and will be avoided over the weekend and holidays 

Heavy equipment will not be operated on Sundays and during the night. 

Special care must be taken  for  the use of heavy equipment near public buildings  like schools; close consultation with the teachers and possibly the Parent‐teachers association is needed 

Page 66: Environmental and Social Analysis

65  Meerman & Boomsma, Environmental and Social Analysis ‐  Wastewater Collection, Treatment, and Disposal System –Placencia Peninsula – DRAFT – 26 September 2010 

    

6. Literature http://aplaceinbelize.com/map_dev.html 

Ariola, E. 2003. Characterization of a Tropical Estuarine System: The Placencia Lagoon. Coastal Zone Management Authority and Institute. 48 pp. 

Balick, K.J., M.H. Nee and D. E. Atha. 2000. Checklist of the Vascular Plants of Belize. Memoirs of the New York Botanical Garden (85). New York Botanical Garden Press. 246 pp. 

BET, 2009. Placencia Marina EIA 

BET, 2009. Placencia Marina EIA supplement 

BET, 2010. Placnecia Marina EIA supplement 

Boyd, C. E and J.W. Clay. (2002).  Evaluation of Belize Aquaculture Ltd: A Super‐intensive Shrimp Aquaculture System. Report prepared under the World Bank, NACA, WWF and FAO Consortium Program on Shrimp Farming and the Environment. 17p.  

Buckalew et al  (1998). Water Resources Assessment for Belize. US Army Corps of Engineers District Office in Mobile, Alabama, and the U.S. Army Corps of Engineers Topographic Engineering Center in Alexandria, Virginia.  

Engineers Without Borders (2006). Wastewater Feasibility Study for Placencia Peninsula, Belize.  

Ecoworks 2007. Environmental Impact Assessment  Of  The Placencia Resort Development   On Placencia Peninsula Stann Creek District, Belize Central America To Be Undertaken By: Plexar Capital, LLC.  November 2007  

Kjerfve, B., (1981) Tides of the Caribbean Sea. Journal of Geophysical Research 86 (C5)  

PASCO (2002). An EIA Addenda for a proposed excavation of a channel at the Placencia Peninsula.  

PCSD, 2010. http://sites.google.com/site/pcsdbelize/,  

http://www.saveourpeninsula.org/tourism/water.html 

Roots and Reef, PCSD Newsletter. http://sites.google.com/site/pcsdbelize/roots‐reef 

Short, F.T; E. Fernandez, A. Vernon, J.L. Gaeckle, Occurrence of Halophila baillonii meadows in Belize, Central America, Aquatic Botany, Volume 85, Issue 3, October 2006, Pages 249‐251, 

Tunich Nah Consultants (2000).  Environmental Impact Assessment of Nova Toledo Aquaculture Venture Expansion Project.   

 Tunich Nah Consultants (2001). Environmental Impact Assessment of Nova Laguna Shrimp Mariculture Expansion Project, Stann Creek District, Belize.  

 U.S. Environmental Protection Agency (1993) Volunteer Estuary Monitoring: A Methods Manual. EPA 842‐B‐93‐004, Washington, DC.  

Watershed‐Reef Interconnectivity Scientific Study (WRIScS):1997‐2001. Lavender S. et al, 2002. 35 pp. http://www.research.plymouth.ac.uk/geomatics/wriscs/pubs/E1i_Introduction_Methods.pdf