environment management plan for the addition of...
TRANSCRIPT
ENVIRONMENT MANAGEMENT PLAN FOR THE ADDITION OF EASTERN CONNECTIVITY TUNNEL AT
KEMPEGOWDA INTERNATIONAL AIRPORT, DEVANAHALLI, BENGALURU, KARNATAKA
VIMTA Labs Limited, Hyderabad 1
1.0 INTRODUCTION
Bangalore International Airport Limited (BIAL) is the owner and developer of
Kempegowda International Airport located at Devanahalli, Bengaluru, Karnataka.
It is a public limited company and is a consortium of FIH Mauritius Investments
Ltd, Siemens project ventures GmbH, Government of Karnataka & Government of
India).
1.1 BACKGROUND
The primary access and circulation roadway for Kempegowda International
Airport (KIA) is the main access roadway (MAR) connecting the NH7 to the
terminal area facilities. Traffic leading to the airport and leaving the airport use
this road.
Robust growth in the passenger traffic to airport is noted over last few years
leading to congestion on NH-7. In-order to de-congest the traffic on NH-7, Office
of Commissioner of Police, Traffic Bangalore vide letter dated 23rd August 2016
advised Bangalore International Airport Limited (BIAL) to evaluate alternate
connectivity option to the Terminal Forecourt of Kempegowda International
Airport. Additionally, from uninterrupted operational requirements for airport of
size of KIA, alternate additional access are required.
It may be noted that in the Detail Project Report (DPR), submitted for the KIA
expansion program, (DPR, 6.6.2 Roadways & Kerbside proposals, page no149.)
connectivity to the eastern plot of the airport for of Cargo, MRO and commercial
development is being proposed. Based on the requirement of GOK, this cargo,
MRO, commercial connectivity is now planned to be extended to the Terminal
facilities for passengers.
BIAL has developed a South West Connectivity Road from BK Halli road to Main
Access road as an alternate access to airport (operational from Mar’18).
BIAL has also carried out studies to identify alternate connectivity to the terminal.
Following options were evaluated.
Option 1: Underground connectivity from south crossing the proposed NSPR as a
tunnel connectivity.
Option 2: Underground connectivity from Eastern side (Option2) of below
proposed airfield taxiway connecting SH-104 and terminal.
Based on pros and cons, Eastern access road is found to be a better and feasible
option given the reduction in traffic load it brings to the other airport access roads
The State of Karnataka plans to develop a second highway providing access to
the Airport to relieve anticipated congestion on NH-7. Access to BIA from Eastern
side through SH-104 (Eastern Access) catering to the eastern developments of
BIA comprising of Cargo, MRO and commercial developments proposed in that
area. This will be proposed as a six lane divided road with possibility of up
gradation to a 10 lane road in the future. This entry will help in segregating the
passenger traffic and the cargo traffic by providing separate access for them to
ENVIRONMENT MANAGEMENT PLAN FOR THE ADDITION OF EASTERN CONNECTIVITY TUNNEL AT
KEMPEGOWDA INTERNATIONAL AIRPORT, DEVANAHALLI, BENGALURU, KARNATAKA
VIMTA Labs Limited, Hyderabad 2
the airport, thus dividing the load on any particular road. This will also be a major
road for the cargo traffic originating or destined to the KIADB.
BIAL has explored all the possible options and decided to build an access tunnel
of length approximately 2,500 m and a link road of length approximately 1280 m.
Approximately 300 m of tunnel portion falls within the boundary of the NSPR
which needs to be constructed along Second stage of expansion (ongoing project)
to avoid any construction in the cross field taxiway in the future once it is
operationalized. The tunnel is proposed with 5.5 m clear height with 4 lane twin
box tunnel connecting the access road of the tunnel to the State Highway-104 via
a new approach road being constructed by PWD.
It is expected that the proposed alternate road connectivity will reduce
approximately 20% of traffic load on NH-7.
2.0 PURPOSE OF REPORT
This report is prepared for seeking amendment in Environmental
Clearance (F.no: 10-24/2012-IA.III dated 22nd August, 2014) for the
addition of Eastern Connectivity Tunnel at Kempegowda International
Airport at Devanahalli, Bengaluru, Karnataka.
As per Environmental Impact Assessment Notification dated 14th September,
2006 and 01.12.2009, the proposed project falls under category ‘A’ under project type 7(a) and requires Environmental Clearance (EC) from Ministry of
Environment, Forest and Climate Change (MoEF&CC) before the commencement
of any ground activity. Which requires Form-I along with Environment
Management Plan to be prepared and submitted to MOEF&CC for obtaining
amendment in Environmental Clearance.
3.0 ENVIRONMENTAL SETTING OF THE PROJECT
The location map is given in Figure-1. The study area representing 10 km radius
is shown in Figure-2. The environmental setting of the project is given in Table-
1.
TABLE-1
ENVIRONMENTAL SETTING AROUND THE PROJECT SITE
Sr. No. Particulars Details
1 Coordinates of airport boundary Latitude & Longitudes of Extreme Coordinates A: 130 12’35" N and 770 40’38" E B: 130 12’36" N and 770 43’03" E C: 130 12’22" N and 770 44’16" E D: 130 10’58" N and 770 44’13" E E: 130 11’10" N and 770 40’53" E
2 General Elevation above MSL About 899.2 m
3 Climatic conditions (IMD, Bengaluru)
A] Annual Max. Temp: 35.2 oC B] Annual Min. Temp: 13.8 oC C] Average Annual total rainfall: 980 mm D] Predominant Annual wind directions : West and East
4 Nearest Highways NH-7 connecting Bengaluru with Hyderabad (0.4 km, WNW) State Highway-207 (1.5 km, NE) State highway – 104 (adjacent towards S)
5 Nearest Railway Station Devanhalli Railway Station (4.0 km, N)
ENVIRONMENT MANAGEMENT PLAN FOR THE ADDITION OF EASTERN CONNECTIVITY TUNNEL AT
KEMPEGOWDA INTERNATIONAL AIRPORT, DEVANAHALLI, BENGALURU, KARNATAKA
VIMTA Labs Limited, Hyderabad 3
Sr. No. Particulars Details
Doddajala Railway Station (4.4 km, WSW)
6 Nearest other airports Airforce Station Yelahanka (10.7 km, SW) Jakkur Aerodrome (16.5 km, SW) HAL Airport, Bengaluru (27.1 km, S)
7 Nearest Village/City Devanhalli (4.0 km, N) Bengaluru (25 km, SSW)
8 Ecologically sensitive zones Nil within 10 km radius
9 Forest areas in 10 km radius Rayasandra RF (1.0 km, NE) RF Near Buvanahalli (1.0 km, NNW) Akkupel SF (3.8 km, N) Koramangala SF (6.4 km, NNE)
Mutsandra SF (7.2 km, SE) Marasandra SF (7.9 km, S) Mandibele RF (9.9 km, NE) Note: RF: Reserve Forest; SF: State Forest
10 Notified Historical/ Archaeological/ Tourist Places
Nil within 10 km radius
11 Defense and other related Establishments
Nil within 10 km radius
12 Major Water Bodies Bettakote Kere (adjacent to the BIAL complex in NE direction) Bandakodiganahalli Kere (0.5 km, SW) Dodda Sanne Kere (1.0 km, N) Chikka Sanne Kere (2.5 km, NNW) Doddaja Amani Kere (3.4 km, SW) Budigere Amani Kere (3.6 km, SE) Dakshina Pinakini River ( 5.5 km, E)
Hoskote Kere (5.6 km, SE)
Note: all distances mentioned above in ( ) are aerial distances
ENVIRONMENT MANAGEMENT PLAN FOR THE ADDITION OF EASTERN CONNECTIVITY TUNNEL AT
KEMPEGOWDA INTERNATIONAL AIRPORT, DEVANAHALLI, BENGALURU, KARNATAKA
VIMTA Labs Limited, Hyderabad 4
FIGURE- 1
INDEX MAP
Project
Site
STATE MAP
ENVIRONMENT MANAGEMENT PLAN FOR THE ADDITION OF EASTERN CONNECTIVITY TUNNEL AT
KEMPEGOWDA INTERNATIONAL AIRPORT, DEVANAHALLI, BENGALURU, KARNATAKA
VIMTA Labs Limited, Hyderabad 5
FIGURE-2
STUDY AREA MAP
ENVIRONMENT MANAGEMENT PLAN FOR THE ADDITION OF EASTERN CONNECTIVITY TUNNEL AT
KEMPEGOWDA INTERNATIONAL AIRPORT, DEVANAHALLI, BENGALURU, KARNATAKA
VIMTA Labs Limited, Hyderabad 6
4.0 PROJECT JUSTIFICATION & DESCRIPTION
Eastern Connectivity Tunnel
Kempegowda International Airport (KIA) proposes addition of a 4-lane tunnel to
cater as an alternative access to the Terminal Forecourt from the Eastern part of
the city. Connecting the under-construction Secondary Access Road (SAR) and
the new Eastern Connectivity Road being constructed by the PWD on the Eastern
Boundary of KIAB from KSRDCL road, this proposed tunnel is about 2.5 km long
with approach road of about 1.28 km and passes under the aprons and the cross
taxiway of the proposed Airside development. This section describes the factors
which influence site selection for the proposed development, infrastructure and
utilities available, water requirement and power requirement etc. The layout map
is given in Figure-3 & 3A
4.1 Land-use
The notified site area of Kempegowda International Airport (KIA) is 1622 ha
(4009 acres). The existing land use details are given in Table-2.
TABLE-2
SUMMARY OF EXISTING LAND USE
Sr. No.
Land Use Category
Developed
Area (Ha)
Developed
Area (acres)
(%)
1
Airfield
676
1670
41.72
2
Vacant
648
1601
40.00
3
Non Aeronautical development
188
465
11.61
4
Passenger Terminal
40
99
2.47
5
Ground transportation and parking
31
77
1.92
6
Air cargo
16
40
0.98
7
Airport and airline support
14
35
0.86
8
Utilities
9
23
0.43
Total Area
1622
4009
100
Land for ECT:
Proposed ECT construction will be taken up within the airport premises.
ENVIRONMENT MANAGEMENT PLAN FOR THE ADDITION OF EASTERN CONNECTIVITY TUNNEL AT
KEMPEGOWDA INTERNATIONAL AIRPORT, DEVANAHALLI, BENGALURU, KARNATAKA
VIMTA Labs Limited, Hyderabad 7
FIGURE-3
MASTER PLAN- OVERALL LAYOUT PLAN
ENVIRONMENT MANAGEMENT PLAN FOR THE ADDITION OF EASTERN CONNECTIVITY TUNNEL AT
KEMPEGOWDA INTERNATIONAL AIRPORT, DEVANAHALLI, BENGALURU, KARNATAKA
VIMTA Labs Limited, Hyderabad 8
FIGURE-3(A)
LAYOUT SHOWING EASTERN TUNNEL CONNECTIVITY
ENVIRONMENT MANAGEMENT PLAN FOR THE ADDITION OF EASTERN CONNECTIVITY TUNNEL AT
KEMPEGOWDA INTERNATIONAL AIRPORT, DEVANAHALLI, BENGALURU, KARNATAKA
VIMTA Labs Limited, Hyderabad 9
4.2 Water Requirement
Existing Airport:
The total water demand for Kempegowda International Airport (KIA) by the year
2030 is estimated to be 52.80 MLD, inclusive of aeronautical & non-
aeronautical uses. Aeronautical use water demand is projected to be 18.00 MLD,
while water demand for non-aeronautical uses is estimated to be 34.8 MLD. The
fresh water requirement for aeronautical is 7.20 MLD and for non- aeronautical is
20.88 MLD. The total fresh water requirement is 28.08 MLD. The water demand
for non-potable use will be generated through waste water recycling and rain
water harvesting initiatives proposed. The details are given in Table-3.
TABLE-3
Sr.No Particulars Aeronautical
Development
Non-
Aeronautical
development
Total
(MLD)
1 Potable Water Demand 7.20 20.88 28.08
2 Non-Potable Water
Demand
10.80 13.92 24.72
Total 18.00 34.8 52.80
Proposed ECT:
During construction phase of the tunnel, the water requirement will be about
2,25,000 m3 which will be supplied by BWSSB.
The present water requirement will be met from Bangalore Water Supply and
Sewerage Board (BWSSB) (19 MLD) Water requirement is envisaged for
firefighting during operational phase.
4.3 Power Requirement
The total power requirement for KIA by 2030 is projected to be 325 MVA. The
power shall be supplied by Bengaluru Electricity Supply Company (BESCOM).
DG sets have been provided with inbuilt and buried fuel (HSD) storage tanks.
The required fuel is sourced from the nearest oil depots. It is proposed to install
five power houses of approximately 2500 m2 and 70 MVA each. The power
requirement for existing airport facilities is about 25.8 MVA which is being met
from the power supply of BESCOM to the airport. The backup power supply
available for the airport is about 10.9 MVA and shall be further augmented as
required. The demand estimation for aeronautical zone and non aeronautical
zone is given in Table-4.
TABLE-4
DEMAND ESTIMATION
Zone MVA
Aeronautical development 100
Non Aeronautical Development 225
Total 325
ENVIRONMENT MANAGEMENT PLAN FOR THE ADDITION OF EASTERN CONNECTIVITY TUNNEL AT
KEMPEGOWDA INTERNATIONAL AIRPORT, DEVANAHALLI, BENGALURU, KARNATAKA
VIMTA Labs Limited, Hyderabad 10
Proposed ECT:
The power requirement for the proposed ECT will be about 1500 kv which will be
met from existing source. Temporary DG power is used for construction.
4.4 Employment
Existing Airport:
The total employment potential of KIA by 2030 would be 2.35 lakhs. As all
facilities and functions at KIA (like any other international airport) shall operate
on 24X7 basis, Average no. of employees at airport at any one point of time shall
be 2.35 lakhs/3=Approx. 78000, as all staff and employees shall be working in 3
shifts of 8 hours each. The details are given in Table-5. The expansion of KIA will
have a pronounced imprint on the local and regional economy. The above forecast
confirms the importance of KIA as an employer in the region and Karnataka state
and is expected to infuse regional development and economic growth of the
region. There is likely to be a large manpower for skilled personnel to helm with
the growth at KIA.
TABLE-5
EMPLOYEE DETAILS
Employment Employees
Direct (60,000 aeronautical + 1.75 lakhs non-
aeronautical)
2,35,000
Indirect 7,050
Induced 8,225
Total 2,50,275
Proposed ECT:
For the construction and operation of the tunnel the approximate manpower
requirement will be about 150 and 50 persons respectively.
5.0 TRANSPORTATION NETWORK & NODES
The proposed transportation network shall include central nodes, serving as
public transportation centers & multi-modal hubs for KIA. Primary aim of the
nodes is to establish multi-modal public transportation interface and network to
increase accessibility and mobility of all users, within KIA and to the surrounding
airport catchment including the city of Bengaluru, surrounding region, all major
places of tourist, business and cultural interest. The nodes will offer increased
accessibility by providing modes/system of transportation at all the Zones of KIA,
City at a Regional Level. It will provide an efficient system by making traveling
more scheduled and hassle free. Proposed transportation network shall include
the world class stations on Metro Rail and on area adjoining it to provide
seamless, obstacle free transport connectivity to the KIA, City and the Region,
integrated with surface transport nodes and parking areas. This landuse category
will include uses like all roads, and parking areas, Metro Rail Stations, PRT, Bus
Stops (for Airport Express Buses/ Shuttle Buses), MLCPs for Terminal Parking
(for Passengers), MLCPs for Taxi Staging, MLCPs for city side Users, pedestrian
walkways, under passes and skywalks, etc.
ENVIRONMENT MANAGEMENT PLAN FOR THE ADDITION OF EASTERN CONNECTIVITY TUNNEL AT
KEMPEGOWDA INTERNATIONAL AIRPORT, DEVANAHALLI, BENGALURU, KARNATAKA
VIMTA Labs Limited, Hyderabad 11
6.0 BASELINE ENVIRONMENT MONITORING STATUS
6.1 Study on Ambient Air Quality & Noise Levels at the Existing Airport
Ambient Air Quality Monitoring is being carried out at 10 locations at the site as per
the instruction of KSPCB. Monitoring is carried out once in a month at all 10
locations. Location map showing the monitoring locations is given below in Figure-
4 & 4A. The noise monitoring is being carried out in 4 locations. The waterwater
quality analysis is being carried out at inlet and outlet of STP and report attached
as Annexure-I. The range of observation of all the monitoring locations of air
quality and noise levels are given in Annexure-I.
FIGURE-4
AMBIENT AIR QUALITY MONITORING LOCATIONS
ENVIRONMENT MANAGEMENT PLAN FOR THE ADDITION OF EASTERN CONNECTIVITY TUNNEL AT
KEMPEGOWDA INTERNATIONAL AIRPORT, DEVANAHALLI, BENGALURU, KARNATAKA
VIMTA Labs Limited, Hyderabad 12
FIGURE-4(A)
PHOTOGRAPHS SHOWING AMBIENT AIR MONITORING STATIONS
7.0 ENVIRONMENT MANAGEMENT PLAN
The Environment Management Plan (EMP) is required to ensure sustainable
development. Hence it needs to be an all encompassing plan for which the project
authorities, Government, Regulating agencies like Pollution Control Board etc.
working in the region and more importantly the affected population of the study
area need to extend their cooperation and contribution.
The Management Action Plan aims at controlling pollution at the source level to
the maximum extent possible, with the available technology, followed by
treatment measures before they are discharged. Specifically, the EMP lays stress
on key environmental aspects and issues of the project during operation phase
by:
Identifying potential environmental impacts;
Recommending mitigation measures for the negative impacts;
Identifying opportunities for enhancement measures;
Formulating Environmental Action Plans (EAPs) which specify mitigation,
activities during project implementation and operation.
The potential environmental impacts to be regulated from the proposed project
are summarized below:
ENVIRONMENT MANAGEMENT PLAN FOR THE ADDITION OF EASTERN CONNECTIVITY TUNNEL AT
KEMPEGOWDA INTERNATIONAL AIRPORT, DEVANAHALLI, BENGALURU, KARNATAKA
VIMTA Labs Limited, Hyderabad 13
Air pollution due to the emissions from various activities;
Noise pollution due to various noise generating equipment;
Wastewater generation from domestic activities; and
Solid waste (STP sludge) disposal.
In order to minimize these adverse impacts and to ensure that the environment
in and around the project site as well as the neighbouring population is well
protected, an effective Environment Management Plan is developed for
construction phase as well as operational phase.
7.1 Environment Management Measures during Construction & Operation
Phase
The construction phase involves site preparation, transportation of construction
materials, equipment and construction of the infrastructure. During this phase it
is imminent that workers/labourers would be staying on site till the completion of
construction. However, this is not a long term impact as this is a temporary
phase. It is envisaged that there would be some effect on the existing
environment. The project proponents, in order to minimize these impacts, would
undertake the required preventive and remedial measures which are outlined
hereunder.
7.1.1 Land use and Topography
There will not be any change in land use within the project area. As the
construction of the proposed eastern tunnel will be within the airport premises.
Hence, no additional land acquisition involved. The land is already categorized
under public utility zone and there will not be any change in land use pattern. The
proposed project does not involve neither tree felling nor disturbance in
vegetation cover.
7.1.2 Soil Management
The excavation for underground tunnel will be to the tune of 10,00,000 m3.
Excavated soil from the construction area will be partly used for back filling, for
reclamation of low laying areas and green belt development in the site. This
excess volume if any for green belt development will be treated as a contingency
to cover any additional losses that may occur during construction such as losses
during clearing & grubbing, settlement and consolidation of native soils
underlying proposed embankment areas and for any removal & disposal of
unsuitable or unstable materials encountered (wet areas, organics, buried debris,
etc.).
The dripping of oil from construction vehicles might cause soil contamination. In
order to prevent soil contamination likely to result from the oil spill and dripping
from vehicles, drip pans shall be placed at the parking places of vehicles and the
dripped oil shall be collected and subsequently sent to the authorized recycling
agencies.
The hazardous materials used during the construction may include petrol, diesel,
welding gas and paints. These materials shall be stored and handled according to
the guidelines specified under Manufacture, Storage and Import of Hazardous
Chemical Rules (MSHIC) and Hazardous Wastes Storage, Handling and
ENVIRONMENT MANAGEMENT PLAN FOR THE ADDITION OF EASTERN CONNECTIVITY TUNNEL AT
KEMPEGOWDA INTERNATIONAL AIRPORT, DEVANAHALLI, BENGALURU, KARNATAKA
VIMTA Labs Limited, Hyderabad 14
Transportation Rules of MoEF&CC. Some of the precautions of storage and
handling of hazardous materials and waste includes the following:
Dyked enclosures shall be provided which can contain complete contents of
the largest tank;
Diesel and other fuels shall be stored in separate dyke enclosures;
Wherever possible, hazardous raw materials to be substituted by non-
hazardous materials, e.g. cleaning solvents can be replaced with film-free bio-
degradable cleaners, usage of non-chlorinated strippers instead of strippers
containing methylene chloride and substitution of water based paints for oil-
based ones;
Separate storage of waste paints and thinners, contaminated rags and
brushes to facilitate recycling and reuse. Rags could be laundered for reuse;
Installation of on-site recycling equipment to be considered by large painting
sub-contractors;
Vehicle maintenance area will be designed to prevent contamination of ground
water by accidental spillage of oil; and
Maintaining appropriate inventory control.
Apart from localized constructional impacts within airport site, no adverse impact
on the soil in the surrounding area is anticipated.
7.1.3 Air Quality Management
Anticipated Impact
Construction phase would involve site clearances and preparation, infrastructure
development and other related activities and Operational phase would involve
emissions from vehicular movement and diesel generators and negligible
emissions from sewage and solid waste handling and disposal.
In order to control emission of pollutants during operation of the DG sets,
adequate stack height will be provided for wider dispersion into the atmosphere.
The stack height for DG sets will be as per CBCB/MOEF&CC prescribed norms.
Green belt and green cover will also be provided to absorb the dust and gaseous
emissions due to the traffic within the campus.
Mitigation Measures for Fugitive Emission Control
Adopting techniques like, air extraction equipment, and covering scaffolding,
hosing down road surfaces and cleaning of vehicles can reduce dust and vapour
emissions. Measures include appropriate containment around storage tanks and
materials stores to prevent spillages entering watercourses.
The other measures to reduce the air pollution on site are:
Sprinkling of water and fine spray from nozzles to suppress the dust.
On-Road- Inspection should be done for black smoke generating machinery.
Promotion of use of cleaner fuel should be done.
All DG sets should comply emission norms notified by MoEF&CC.
Use of covering sheet to prevent dust dispersion at buildings and
infrastructure sites, which are being constructed.
ENVIRONMENT MANAGEMENT PLAN FOR THE ADDITION OF EASTERN CONNECTIVITY TUNNEL AT
KEMPEGOWDA INTERNATIONAL AIRPORT, DEVANAHALLI, BENGALURU, KARNATAKA
VIMTA Labs Limited, Hyderabad 15
Material storages / warehouses –should be taken to keep all material storages
adequately covered and contained so that they are not exposed to situations
where winds on site could lead to dust / particulate emissions. Fabrics and
plastics for covering piles of soils and debris is an effective means to reduce
fugitive dust.
Management of Dust Emission due to Transportation
Construction area consists of large open area;
To reduce dust emission due to vehicle movement, vehicle access area is
limited through designated pathway;
Speed limit of 30 km/hr is fixed for vehicles, and speed monitoring is done;
All aggregate transporting vehicles are covered on top to prevent emission of
dust;
Use of covering sheets will be done for trucks to prevent dust dispersion from
the trucks;
Paving is a more permanent solution to dust control, suitable for longer
duration projects;
Speed bumps are commonly used to ensure speed reduction. In cases where
speed reduction cannot effectively reduce fugitive dust, it may be necessary
to divert traffic to nearby paved areas.
Dust emission control measures are shown in Figure-5 &5A.
ENVIRONMENT MANAGEMENT PLAN FOR THE ADDITION OF EASTERN CONNECTIVITY TUNNEL AT
KEMPEGOWDA INTERNATIONAL AIRPORT, DEVANAHALLI, BENGALURU, KARNATAKA
VIMTA Labs Limited, Hyderabad 16
Red line indicated the main access to site and yellow is the temporary access in
the site
FIGURE-5
LAYOUT OF DESIGNATED VEHICLE ACCESS ROAD
ENVIRONMENT MANAGEMENT PLAN FOR THE ADDITION OF EASTERN CONNECTIVITY TUNNEL AT
KEMPEGOWDA INTERNATIONAL AIRPORT, DEVANAHALLI, BENGALURU, KARNATAKA
VIMTA Labs Limited, Hyderabad 17
Aggregate transporting vehicles covered on top to prevent emission of
dust
FIGURE-5(A)
EMISSION MANAGEMENT DUE TO TRANSPORATION
Demarcated vehicle access route Speed monitoring of vehicle
ENVIRONMENT MANAGEMENT PLAN FOR THE ADDITION OF EASTERN CONNECTIVITY TUNNEL AT
KEMPEGOWDA INTERNATIONAL AIRPORT, DEVANAHALLI, BENGALURU, KARNATAKA
VIMTA Labs Limited, Hyderabad 18
WATER SPRINKLING TO SUPPRESS THE DUST
Water tankers are engaged for water sprinkling to suppress the dust
Sprinkling is done along access roads, runways, taxiways, plant areas, site
peripheries etc
Photographs showing the water sprinkling to suppress the dust are given in
Figure-6.
FIGURE-6
WATER SPRINKLING TO SUPPRESS THE DUST
ENVIRONMENT MANAGEMENT PLAN FOR THE ADDITION OF EASTERN CONNECTIVITY TUNNEL AT
KEMPEGOWDA INTERNATIONAL AIRPORT, DEVANAHALLI, BENGALURU, KARNATAKA
VIMTA Labs Limited, Hyderabad 19
Work area green cloth barricading to prevent dust emission
FIGURE-6(A)
DUST CONTROL MEASURES
Sand heap covered by tarpaulin to prevent dust emission
ENVIRONMENT MANAGEMENT PLAN FOR THE ADDITION OF EASTERN CONNECTIVITY TUNNEL AT
KEMPEGOWDA INTERNATIONAL AIRPORT, DEVANAHALLI, BENGALURU, KARNATAKA
VIMTA Labs Limited, Hyderabad 20
Dust Control Measures At Batching Plant Area:
DUST CONTROL MEASURES
EAST FENCING Total length covered – 1.5 Km
SOUTH FENCING Total length covered – 2.6 Km
Aggregate Feeding Bins Covered By
Green Cloth To Prevent Dust
Emission
Regular Cleaning Of Silo Bottom Filter
ENVIRONMENT MANAGEMENT PLAN FOR THE ADDITION OF EASTERN CONNECTIVITY TUNNEL AT
KEMPEGOWDA INTERNATIONAL AIRPORT, DEVANAHALLI, BENGALURU, KARNATAKA
VIMTA Labs Limited, Hyderabad 21
M-Sand Stock Pile Covered By Green Cloth To Prevent Dust Emission
Nearly 5000 m2 Green Cloth Is Used Till Now For Covering
Covering Conveyor Belt And Hoppers With Gi Sheets
ENVIRONMENT MANAGEMENT PLAN FOR THE ADDITION OF EASTERN CONNECTIVITY TUNNEL AT
KEMPEGOWDA INTERNATIONAL AIRPORT, DEVANAHALLI, BENGALURU, KARNATAKA
VIMTA Labs Limited, Hyderabad 22
Dust Control Measures At Hot Mix Plant Area:
Wind Break Wall Construction In Progress Proposed Fog Canon System
The Filtered Dusty Material Will Be Mixed With Water And Made Into Slurry To Prevent Dust Emission
ENVIRONMENT MANAGEMENT PLAN FOR THE ADDITION OF EASTERN CONNECTIVITY TUNNEL AT
KEMPEGOWDA INTERNATIONAL AIRPORT, DEVANAHALLI, BENGALURU, KARNATAKA
VIMTA Labs Limited, Hyderabad 23
Impact on Traffic and Road Network
The proposed project of expansion (ultimate capacity) of passenger handling
capacity will lead to an increase in road traffic due to increase in aviation activity.
BIAL has conducted extensive traffic study for a period of one week to know the
existing traffic volume. Landside traffic survey has been conducted at the seven
locations by BIAL in existing airport complex at trumpet flyover, secondary access
road and main access road (inbound and outbound). The observed landside traffic
details are given in the Table-6.
TABLE-6
DETAILS OF EXISTING LANDSIDE TRAFFIC
Survey Point Location and Direction Daily Total (in Vehicles)
Daily Total (in PCU)
VI VI-A At Trumpet & Airport Entry – From Bengaluru
19118 20669
VI-B At Trumpet & Airport Entry – From Hyderabad
2934 3309
VI-C At Trumpet & Airport Exit to Bengaluru 18521 19893
VI-D At Trumpet & Airport Exit to Hyderabad 2331 2561
V2 V2-A Secondary Access Road Trumpet- Airport 2512 4281
V2-B Secondary Access Road Airport-Trumpet 2160 3584
V3 V3-A Major Access road East of the Eastern Roundabout (inbound)
19410 20893
V3-B Major Access road East of the Eastern Roundabout (outbound)
20075 23886
V4 Inner Curb 4736 4729
V5 Outer Curb 15917 16019
V6 Terminal Curbside Exit 30420 31267
V7 Parking Access Road 9561 9652
Source: Earlier EIA Report, 2014
Traffic due to Proposed Project (estimated to ultimate capacity)
The forecast of increase in landside traffic has been done by international consulting
company M/s Landrum & Brown (source: Earlier EIA report).
Transport Mode Share
The modal share assumed in the traffic forecast is based on the current modal share
pattern of air travellers and employees at BIA, proposals of future public transit
facilities and the accessibility to the same, trip length, purpose and frequency of
travel and income level of users. Model share for traffic assignment is given in
Table-7. TABLE-7
MODEL SHARE
Trip Category Cars (%) Two Wheelers (%) Buses
(%) Trains (%)
Air Passengers 71 0 20 9
Airport
Employees
5 23 56 16
APC Employees 12 22 51 15
APC Visitors 21 26 45 8 Source: DPR
ENVIRONMENT MANAGEMENT PLAN FOR THE ADDITION OF EASTERN CONNECTIVITY TUNNEL AT
KEMPEGOWDA INTERNATIONAL AIRPORT, DEVANAHALLI, BENGALURU, KARNATAKA
VIMTA Labs Limited, Hyderabad 24
Note that the figures above represent overall mode shares for the total trips
generated in each category of development. Mass Transit share of upto 20% and
upto 50% has been allocated to the airport passengers and employees respectively
only for zones that have close access to the mass transit corridor.
There will be considerable shift of trips to the HSRL/Metro system (from the road
based system) assumed to be functional by 2029-30. Under this scenario, 50% of
trips produced at the residential zones near the HSRL stations are assumed to shift
from road to HSRL/Metro systems. The peak hour traffic and the corresponding lane
requirements in the major arterials leading to KIA are given in Table-8.
TABLE-8
REQUIREMENTS OF MAJOR ARTERIAL ROADS
Sr. No. Inbound Peak Hour Traffic - One
Direction Traffic Volume (PCU)
No of Lanes per Direction
1 Traffic Entering KIA(West) 11283 10
KIA(West) via Trumpet 6800 6
KIA (West) via South West Access
Road 4483 4
2 Traffic Entering APC W 6005 5
3 Terminal Traffic 5278 5
4 APC East 1777 2
Source: EIA, 2014
Proposed ECT:
The proposed Eastern Connectivity tunnel will divert the traffic of landside and
prevents from traffic congestion in landside.
Management
Height of the stack for DG sets will be kept as per CPCB guidelines;
Measures for vehicles and equipment with internal combustion engines will be
taken in the operational phase also;
Providing adequate buffer zones where pollution concentrations is highest to
reduce the impact of emissions;
Appropriate design of access roads to avoid traffic jams to reduce air
pollution;
Providing suitable green belt / green cover to reduce the impact of air
pollution; and
Vehicles moving within the airport will be maintained and emission checks will
be carried out on regular interval.
7.1.4 Water Quality Management
Construction Phase
The construction phase would involve water requirements for the following
activities:
Site preparation: Involves levelling for infrastructure development.
ENVIRONMENT MANAGEMENT PLAN FOR THE ADDITION OF EASTERN CONNECTIVITY TUNNEL AT
KEMPEGOWDA INTERNATIONAL AIRPORT, DEVANAHALLI, BENGALURU, KARNATAKA
VIMTA Labs Limited, Hyderabad 25
Water is required for dust settlement, consolidation, compaction and curing.
Construction of building infrastructure involves water for construction
activities and domestic and other water requirements for labour and staff
onsite.
Wastewater Generation and Utilization of Treated Wastewater
Total wastewater generation will be about 58.618 KLD for the entire airport
operations. The domestic wastewater generated labour colony will be treated in a
Sewage Treatment plant (STP) of 100 KLD capacity. Treated wastewater received
from the STP will be utilized within the project premises for gardening and
flushing. The remaining treated wastewater will be utilized for flushing purpose
and thus, no wastewater will be discharged outside the premises. The treated
wastewater utilization details are given in the Table-9. The schematic diagram of
sewage treatment plant is shown in Figure-7.
TABLE-9
TREATED WASTE WATER UTILIZATION DETAILS
Sr. No. Particular Water Requirement
(KLD)
1 Water required for gardening 18.6
2 Water available for flushing 40.0
Total 58.618
Wastewater Management
o At Labour Camp
Wastewater Management
Domestic sewage from labour colony is treated in Sewage Treatment Plant
and recycled for water sprinkling to suppress the dust;
Nearly 50 KL wastewater is recycled daily;
Municipal solid waste from labour camp and office areas is disposed off on
daily basis to authorized agencies; and
Separate storage area are identified for other waste materials generated and
will be disposed through authorized dealers.
The photograph showing the sewage treatment plant is given in Figure-7.
ENVIRONMENT MANAGEMENT PLAN FOR THE ADDITION OF EASTERN CONNECTIVITY TUNNEL AT
KEMPEGOWDA INTERNATIONAL AIRPORT, DEVANAHALLI, BENGALURU, KARNATAKA
VIMTA Labs Limited, Hyderabad 26
FIGURE-15
FIGURE-7
SEWAGE TREATMENT PLANT FOR WORKMEN CAMP
Storm Water Drainage System
In general, the rainwater from terraces and other elevated open areas shall be
collected through rainwater down-take pipes and connected to catch basins. The
rain water from hard courts and landscaped area shall be collected by catch
basins through a RCC pipe network/or open drains with gratings and connected to
the storm water manholes/channels in the complex. The collected water from the
catch basins will be diverted to rain water harvesting pits. Provision shall be made
for rain water harvesting as required by the Codes. Drainage system is under
execution to prevent accumulation of water inside the labour colony.
Layout showing proposed drainage system at labour camp are given in
Figure-8.
Wastewater Generation from proposed ECT: (Operational Phase)
There will be only domestic wastewater generation during the operational phase
of ECT. Which will be diverted to existing STP and reutilized.
ENVIRONMENT MANAGEMENT PLAN FOR THE ADDITION OF EASTERN CONNECTIVITY TUNNEL AT
KEMPEGOWDA INTERNATIONAL AIRPORT, DEVANAHALLI, BENGALURU, KARNATAKA
VIMTA Labs Limited, Hyderabad 27
FIGURE-7
LAYOUT SHOWING DRAINAGE SYSTEM AT LABOUR CAMP
ENVIRONMENT MANAGEMENT PLAN FOR THE ADDITION OF EASTERN CONNECTIVITY TUNNEL AT
KEMPEGOWDA INTERNATIONAL AIRPORT, DEVANAHALLI, BENGALURU, KARNATAKA
VIMTA Labs Limited, Hyderabad 28
Water Conservation Initiatives:
Rain Water Harvesting:
Water harvesting refers to the collection and storage of rain-water and also
harvesting surface and ground water, prevention of loss through evaporation and
seepage, and other hydrological and engineering interventions aimed at
conserving water.
The advantages of using rain water harvesting structures are as follows:
o Water harvesting recharges ground water and is an ideal solution to water
problems in areas with inadequate water resources.
o Increase in ground water aquifer level due to methods of enhancing
infiltration
o Mitigation of the effect of drought
o Reduction of storm water runoff into the public drainage system
o Reduction of flooding of the roads during monsoons
o Removal of pollutants and soil from the storm water runoff
o Reduction of soil erosion
Planning to collect the storm water from camp roof gutters for ground water
recharge. As an initiative of Rain water harvesting construction of ponds are in
progress (Pond 3 and pond 6).
The photographs of the ponds are shown in Figure-9.
Approximate water holding capacity of these ponds after excavation will be
Pond 3 - 290,000 m3 Pond 6 - 150,000 m3
FIGURE- 9 PROGRESS OF CONSTRUCTION PONDS
ENVIRONMENT MANAGEMENT PLAN FOR THE ADDITION OF EASTERN CONNECTIVITY TUNNEL AT
KEMPEGOWDA INTERNATIONAL AIRPORT, DEVANAHALLI, BENGALURU, KARNATAKA
VIMTA Labs Limited, Hyderabad 29
Noise Level Management
Anticipated Impact
During the construction phase, the following source of noise pollution is expected
Construction equipment – Movement of Vehicles, DG sets operation.
During operational phase the following sources of noise pollution is expected:
Diesel generator operations
Increase in transport noise from within the site due to the movement of
vehicles
Mitigation Measures
It is important that no new development is carried out within areas where
expected noise levels will cause mental and physical fatigue or permanent loss of
hearing. In case development in such areas is essential, adequate sound
insulation should be provided for the building. There are two ways of applying
controls or measures. The first is to plan so as to keep the noise at a distance.
Under this aspect comes the separation of housing from traffic noise by
interposing buffer zones, and the protection of schools and hospitals by green
belts, public gardens, etc. The second is the principle of shading or screening. Use
of noise deflectors can also help in reducing the noise. This consists of
deliberately interposing a less vulnerable building to screen a more vulnerable
one or by providing a solid barrier such as a wall between the source and the
location to be protected and the protection of schools and hospitals by green
belts, public gardens, etc. The second is the principle of shading or screening. Use
of noise deflectors can also help in reducing the noise. This consists of
deliberately interposing a less vulnerable building to screen a more vulnerable
one or by providing a solid barrier such as a wall between the source and the
location to be protected.
Control of noise from road traffic: Tree plantation will be carried out on both
sides of carriage way help to muffle the noise provided.
Management Measures during Phase:
Maintenance of vehicles to reduce noise levels;
Personnel working in noisy areas will be provided with ear plugs/mufflers to
reduce the noise impacts;
The DG set will be provided with acoustic enclosures and exhaust mufflers for
effective noise reduction of 25 dB(A) each;
Sources of intermittent noise generating equipment such as compressors will
be provided with appropriate acoustic barriers so that the noise level within
100 m of these facilities when in operation will be less than 70 dB(A); and
Noise attenuating green belt / green cover shall be developed for effective
reduction in noise wherever feasible.
ENVIRONMENT MANAGEMENT PLAN FOR THE ADDITION OF EASTERN CONNECTIVITY TUNNEL AT
KEMPEGOWDA INTERNATIONAL AIRPORT, DEVANAHALLI, BENGALURU, KARNATAKA
VIMTA Labs Limited, Hyderabad 30
7.1.5 Waste and Hazardous Material Handling
Existing Airport
Air Side
Solid waste will be generated from different facilities i.e. PTB, flight catering,
cargo handling areas, aircraft maintenance, GSE, medical facility, STP etc. The
estimation is done for different planning years and the solid waste generation will
be approximately 0.35 tonne/day for the ultimate capacity (2029-2030). Waste
will be disposed through authorized agents. Recyclable is segregated & given to
recyclers.
City Side
Based on the data of solid waste generation from cityside land uses, detailed
estimation has been carried out for solid waste generation quantity from different
facilities i.e. hospitality, commercial/office spaces, retail and F&B, entertainment,
health care and educational institutions, MICE, cultural & event spaces,
pedestrian plaza, transport facilities. Based on the present scenario, it has been
estimated that about 60 tonnes/day of waste from airside and 122.6 tonnes/day
from cityside would be generated during the ultimate phase i.e 2029-30.
ECT Construction Phase
The construction phase waste will comprise of excavated and demolition material.
The different types of wastes need to be handled as per their needs and
regulatory requirements. It is not possible to dispose off all type of wastes onto
the land and has to be dealt with depending upon their type and characteristics.
Building construction leads to generation of sand, gravel, concrete, stone, bricks,
wood, metal, glass, polythene sheets plastic, paper etc. as waste.
Hazardous materials such as diesel, fuel oil, lubricating oil during construction
phase should be stored properly as per the safety regulations. Combustible
wastes should be burnt in a controlled manner and other category of wastes
should be disposed off at identified dump site. Accidental spillages of oil from
construction equipment and storage sites should be prevented.
Major solid waste generation from the premises is mostly municipal solid waste.
Municipal solid waste from labour camp and office area are disposed on daily
basis. Separate storage areas are identified for other waste materials generated
and will be disposed through authorized agencies.
The sludge generated from the Sewage Treatment Plant will be used as manure
for greenbelt development.
Used Oil from DG Sets
The used oil generated from the DG sets will be stored in separate tank as per
Hazardous Waste management Rules, 2008 and sent to the authorized agencies
recognized by SPCB.
ENVIRONMENT MANAGEMENT PLAN FOR THE ADDITION OF EASTERN CONNECTIVITY TUNNEL AT
KEMPEGOWDA INTERNATIONAL AIRPORT, DEVANAHALLI, BENGALURU, KARNATAKA
VIMTA Labs Limited, Hyderabad 31
Other Solid Waste Generation
(i) Municipal or domestic waste;
(ii) Landscape waste; and
(iii) Waste DG set oil.
An effective solid waste management system will be followed. Measures to be
taken to minimize the adverse impact due the said waste are given below:
Municipal Solid Waste
Adequate number of collection bins separate for biodegradable and non-
biodegradable waste shall be provided as per The Municipal Solid Waste
(Management and Handling) Rules. Waste form such bin shall be collected
separately on daily bases. All the collection bins shall be properly maintained on
regular bases. Arrangements will be made for providing a central garbage station
or transfer point, from where all waste collected from collection bin shall be
disposed off to the authorized agencies.
Landscape Waste
Landscape waste comprises of fallen leaves and other vegetative material shall be
collected at the secured location such that it shall not hindered daily activity
schedule or washed away by the surface run off causing choking of drains, etc.
For such waste also, adequate arrangement shall be worked out with municipal
authority to collect and disposed in appropriate manner.
Waste Oil from DG Sets
The waste oil generated due to usage of DG sets will be stored and subsequently
given to the authorized hazardous waste management agencies recognized by
Pollution Control Board (PCB). The hazardous waste generated from the facility
will be stored and disposed off as required by the Hazardous Wastes Management
and Handling Act Amendment Rules (MoEF&CC, 2008).
Solid Waste During Operational Phase
Adequate provision should be made for storage of solid waste and for easy access
to the dustbins;
for labours from source to the place of storage, and
from the place of storage to a collection point specified by the waste collection
authority and/or contractor
Three colours of wheeled bins: - dark grey for inert waste, green for wood and
ply waste and blue for hazardous waste can be used.
The photographs showing waste management are given in Figure-10 & 10A.
Solid waste Generation – During operational phase of ECT:
During operational phase of Eastern Connectivity tunnel the generation of solid
waste will be minimal being a route for transport of passengers.
ENVIRONMENT MANAGEMENT PLAN FOR THE ADDITION OF EASTERN CONNECTIVITY TUNNEL AT
KEMPEGOWDA INTERNATIONAL AIRPORT, DEVANAHALLI, BENGALURU, KARNATAKA
VIMTA Labs Limited, Hyderabad 32
FIGURE-10
COLOUR CODED WASTE BINS PROVIDED FOR SEGREGATION OF WASTE
ENVIRONMENT MANAGEMENT PLAN FOR THE ADDITION OF EASTERN CONNECTIVITY TUNNEL AT
KEMPEGOWDA INTERNATIONAL AIRPORT, DEVANAHALLI, BENGALURU, KARNATAKA
VIMTA Labs Limited, Hyderabad 33
FIGURE-10(A)
WASTE COLLECTED ON DAILY BASIS
REGISTER MAINTAINED ON WASTE DISPOSAL
ENVIRONMENT MANAGEMENT PLAN FOR THE ADDITION OF EASTERN CONNECTIVITY TUNNEL AT
KEMPEGOWDA INTERNATIONAL AIRPORT, DEVANAHALLI, BENGALURU, KARNATAKA
VIMTA Labs Limited, Hyderabad 34
7.1.6 Ecological Management
Primarily the land required for setting up of proposed project activity is within the
existing airport premises and there is not much of green cover. Thus, the floral
significance at the proposed plant site is negligible and impact of construction on
flora will be negligible.
Green Cover: Tree plantation should be undertaken at the time of preparation of
site so that they would grow to considerable size by time of commissioning of the
proposed project. Ecological management given in Figure-11.
Tree Plantation Proposed:
• Total of 70 tree saplings are planted so far at labour camp.
• Survival ratio of 91% is obtained
• From construction site, so far 5 trees are relocated/transplanted
FIGURE-11
TREE PLANTATION
ENVIRONMENT MANAGEMENT PLAN FOR THE ADDITION OF EASTERN CONNECTIVITY TUNNEL AT
KEMPEGOWDA INTERNATIONAL AIRPORT, DEVANAHALLI, BENGALURU, KARNATAKA
VIMTA Labs Limited, Hyderabad 35
7.1.7 Socio-Economic Environment
Provision of wage employment to the local public during construction period of
the project will contribute to un-employed public and might reduce the
dependency on main workers of the surrounding families. This initiative will
promote the income levels of the construction laborers and lead for their socio-
economic well-being during the construction phase, which will be a positive
impact due to the project. The existing airport provides employment to people of
different skills and trades. The local population is the largest beneficiary among
these employees. The employment potential ameliorate the economic conditions
of these families directly and provide revenue generation opportunities to many
other families indirectly who are involved in business and service oriented
activities. This in turn will improve the socio-economic conditions of the region.
7.1.8 Health and Safety
Medical care is provided for the laborers in the camps. Awareness programs will
also be conducted on communicable diseases and their spread. The movement of
heavy equipment should be done with proper precaution to prevent any accidents
on the road. Occupational risk should be minimized at the project site through
implementation of a full proof safety system. Speed limit set for movement of
vehicles will be 30 km/hr on village roads to reduce risk of accidents or injuries.
Safety training should be provided to all construction workers on operation of
equipment. Security should also be extended during non-working hours to ensure
there is controlled access to the machinery and equipment. The measures taken
for workman welfare are given below:
Pre deployment medical checkup is done for all workmen. Well-equipped
medical center is functioning inside the camp with scheduled doctor visit
Well facilitated rooms are provided for workmen at labour camp with beds,
cots, drinking water and other arrangements
Adequate toilet and washing facilities are provided
A canteen is set up inside the camp for workmen
Potable water is supplied to workmen through RO plant
LABOUR CAMP WITH ADEQUATE CIVIC AMENITIES
ENVIRONMENT MANAGEMENT PLAN FOR THE ADDITION OF EASTERN CONNECTIVITY TUNNEL AT
KEMPEGOWDA INTERNATIONAL AIRPORT, DEVANAHALLI, BENGALURU, KARNATAKA
VIMTA Labs Limited, Hyderabad 36
8.0 TUNNEL OPERATIONS SAFETY MEASURES – SPECIFIC TO PROPOSED EASTERN
CONNECTIVITY TUNNEL
Infrastructure supporting tunnel operation will include, traffic monitoring &
management systems, in-tunnel safety systems (fire protection and monitoring
systems), tunnel ventilation system, cross passages for vehicle diversion, in-tunnel
communication system and emergency exit points for the users.
Traffic Operations System (TOS):
Traffic monitoring & management system shall comprise of cameras along the
length of the tunnel including the approach ramps and backend analysis system for
recording & storing the type of vehicles entering/exiting the tunnel, generating
warning pop-ups for slowing or stopping vehicles inside the tunnel. Traffic lights
controlling and regulating the traffic passing through the tunnel including the use of
the cross passages will be connected to the TOM (Tunnel Operations Management).
This will also in turn will be connected to the Environment Control System
controlling the tunnel ventilation, fresh air supply and exhaust fume extraction
system. This will also provide the required inputs for incident detection inside the
tunnel.
MEDICAL CENTER WITH 24X7 AMBULANCE
FACILITY
POTABLE WATER SUPPLIED THROUGH RO PLANT MEDICAL CHECK-UP BY DOCTOR
ENVIRONMENT MANAGEMENT PLAN FOR THE ADDITION OF EASTERN CONNECTIVITY TUNNEL AT
KEMPEGOWDA INTERNATIONAL AIRPORT, DEVANAHALLI, BENGALURU, KARNATAKA
VIMTA Labs Limited, Hyderabad 37
Environment Control System (ECS):
Environment Control System will comprise of monitoring units for detection of
various parameters like exhaust fumes (SOx, NOx, CO etc) which will in turn trigger
the operation of the foul air extraction fans and fresh air supply fans to maintain the
desired air quality & environment in the tunnel. Extraction fans are proposed along
the tunnel to facilitate this. Tunnel lighting and Fire Protection System (FPS) shall be
a part of this. The tunnel ventilation system is to be designed to maintain in-tunnel
air quality through the operation of a ventilation system linked to an automatic
control system receiving information from visibility, air speed and gas monitors (for
CO and NO/NO2).
Fire Protection System (FPS):
Fire hydrant system is proposed along the length of the tunnel to cater to fire
fighting needs of the tunnel arising due to any vehicle or other fire inside the tunnel.
There will be thermal cameras providing with temperatures inside the tunnel for
monitoring and generating alert trigger when it exceeds desired values. Some
extraction system shall be part of the ECS System. A fire rated central
walkway/passage between the roads will be used for evacuation of users by foot.
There will be fire rated staircases at intermittent points connecting the central
walkway to a refuge area in the upper level above the tunnel box to take the users
up to the surface during a fire or in an emergency. The refuge area will be normally
closed and will be provided panic doors for opening during emergency and fire.
Communication System (CS):
A communication will be provided for communication between various areas of the
tunnel and also the control room during an emergency.
Security Systems:
Security systems shall be a combination of the TOM systems, driver cameras,
vehicle checking systems like underbody cameras & portable vehicle scanners and
tyre killers which will be deployed before the tunnel entry and will be used as per
the requirement & threat perception. There will be control barriers and median cuts
for controlling and sending off undesired vehicles before the entry of the tunnel.
Tunnel Operations & Management Centre (TOM):
All the above systems shall be integrated and a tunnel control and management unit
shall be established either as a standalone building or integrated with the SOCC
(Security Operations Control System). This will enable tunnel managers and
emergency response agencies to manage operations and emergency incidents
flexibly. An Incident Management Response Sub-Plan of the Operations EMP is to be
prepared and critically appraised with emergency response agencies by means of
simulation exercises prior to the commencement of operation of the tunnel. The
overall traffic management will be also be conducted from TOM, which will collect
and process all data from in-tunnel monitoring systems and control all services
connected with safe tunnel operations. The KIA proposes phasing of lights on
intersections at either end of the tunnel will be managed by TOM to control traffic
ENVIRONMENT MANAGEMENT PLAN FOR THE ADDITION OF EASTERN CONNECTIVITY TUNNEL AT
KEMPEGOWDA INTERNATIONAL AIRPORT, DEVANAHALLI, BENGALURU, KARNATAKA
VIMTA Labs Limited, Hyderabad 38
flow into and out of the tunnel, having regard to conditions in tunnel and on the
surface road network.
While it is intended to exclude dangerous goods vehicles from the tunnel by
Regulation, this cannot guarantee the total exclusion of these types of vehicles from
the tunnels. Monitoring and reporting procedures will need to be established, and
the procedures and capacity for dealing with incidents involving these vehicles will
need to be adequate.
9.0 GREEN BELT/ GREENERY DEVELOPMENT
The principal airport level green space/ open area in the form of central linear
green is located along the airport access road. Secondary open areas shall be
planned in various locations in different landuse zones. The total area under this
zone shall be approximately 24.95 ha (61.64 acres).
Green Area/Green Belt Development In The Context Of Airport
Development
Green Development as part of Airport Development Project needs to be considered
in view of typical airport related constraints, such as –
A. Height Restriction -Development of green areas and planting of trees including
their types (as per height at maturity) is guided by the height restrictions imposed
by Airport Authority of India & DGCA Guidelines, hence any type of dense
vegetation with bigger height trees cannot be developed in the vicinity of Airport
operational area. Green Area development at BIAL is being done accordingly.
B. Bird Menace- Trees attract insects and birds which have potential to cause
maximum damage to aircraft. This requires a careful restricted selection of trees to
be planted on an airport premise, as a part of Airport Safety measures. Green Area
development at BIAL is being done accordingly.
C. Restriction In Operational Area - As part of Airport Operational
requirements, typically almost 70% of total Airport land area is defined as
Operational Area (Airside) where in the regular movement of flight movement
demands clear and clean area, without any form of vegetation (except
grass), which may affect the flight operations due to plants leading to bird nuisance.
Green Area development at BIAL is being done accordingly.
GREEN AREA/GREEN BELT DEVELOPMENT AT KIA
Bengaluru Airport Development is a greenfield project developed on vacant,
mostly rocky land outside Bengaluru city, with limited water supply resources.
Green Area development at BIAL is being planned and implemented in this
context. The percentage of the Green Belt Development in terms of the
overall Airport Development Area [4009 acres] is about 32 % including
turfed area on the airside between the runway, taxiway and apron.
First Phase of Green Area/Green Belt Development using indigenous species of
plants. The areas in this phase on the landside include,
ENVIRONMENT MANAGEMENT PLAN FOR THE ADDITION OF EASTERN CONNECTIVITY TUNNEL AT
KEMPEGOWDA INTERNATIONAL AIRPORT, DEVANAHALLI, BENGALURU, KARNATAKA
VIMTA Labs Limited, Hyderabad 39
Green area along the entrance road;
Tree plantation on peripheral areas of north and south slopes along with
Median planting on the Main Access Road;
Slope stabilization through grassed embankment along the swale;
Landscape area near ATC;
Landscape in Forecourt area; and
Landscape area adjacent to trumpet cloverleaf
BIAL has prepared over all Master Plan for Green Area / Landscape
Development for implementation in phases. Phase 1 of this is currently under
progress. The total plan shall be implemented in next 4-5 years. Green area
towards land side and airside are shown in Figure-12 & Figure-13.
ENVIRONMENT MANAGEMENT PLAN FOR THE ADDITION OF EASTERN CONNECTIVITY TUNNEL AT
KEMPEGOWDA INTERNATIONAL AIRPORT, DEVANAHALLI, BENGALURU, KARNATAKA
VIMTA Labs Limited, Hyderabad 40
FIGURE-12
GREEN AREA DEVELOPMENT PLAN ON THE LANDSIDE
ENVIRONMENT MANAGEMENT PLAN FOR THE ADDITION OF EASTERN CONNECTIVITY TUNNEL AT
KEMPEGOWDA INTERNATIONAL AIRPORT, DEVANAHALLI, BENGALURU, KARNATAKA
VIMTA Labs Limited, Hyderabad 41
FIGURE-13
GREEN AREA DEVELOPMENT PLAN ON THE AIRSIDE
ENVIRONMENT MANAGEMENT PLAN FOR THE ADDITION OF EASTERN CONNECTIVITY TUNNEL AT
KEMPEGOWDA INTERNATIONAL AIRPORT, DEVANAHALLI, BENGALURU, KARNATAKA
VIMTA Labs Limited, Hyderabad 42
FIGURE-13(A)
LANDSCAPE DEVELOPMENT AT TERMINAL FORECOURT
ENVIRONMENT MANAGEMENT PLAN FOR THE ADDITION OF EASTERN CONNECTIVITY TUNNEL AT
KEMPEGOWDA INTERNATIONAL AIRPORT, DEVANAHALLI, BENGALURU, KARNATAKA
VIMTA Labs Limited, Hyderabad 43
PRIORTY IMPLEMENTATION PROJECT-PHASE-1 ALONG MAIN
ACCESSROAD
ENVIRONMENT MANAGEMENT PLAN FOR THE ADDITION OF EASTERN CONNECTIVITY TUNNEL AT
KEMPEGOWDA INTERNATIONAL AIRPORT, DEVANAHALLI, BENGALURU, KARNATAKA
VIMTA Labs Limited, Hyderabad 44
10.0 EXPENDITURE ON ENVIRONMENT MANAGEMENT PRACTICES
The expenditure on environment management practices is given in Table-10.
TABLE-10
ENVIRONMENT EXPENDITURE FOR O&M
Sr.No Activities Expenditure INR
(Annual)
1 Operation and Maintenance of STP 1,06,28,000
2 Scientific disposal of municipal solid waste 5,000,000
3 Aviation noise monitoring 39,33,294
4 Monitoring of environmental parameters 4,71,995
Total 20,033,289
ENVIRONMENT MANAGEMENT PLAN FOR THE ADDITION OF EASTERN CONNECTIVITY TUNNEL AT
KEMPEGOWDA INTERNATIONAL AIRPORT, DEVANAHALLI, BENGALURU, KARNATAKA
VIMTA Labs Limited, Hyderabad 45
ANNEXURE-I
WASTEWATER ANALSIS REPORT
Sr.
No. Parameters
KSPCB
Limits
July, 2018
(Untreated
Water
Sample)
July,
2018
(Treated
Water
Sample)
1 pH 6.0 — 8.5 5.6 7.21
2 Oil & Grease, mg/l Max 10 4.0 BDL
3 BOD 3 days at 27°C, mg/l ≤10 92 7.0
4 COD, mg/l Max 250 450 48.0
5 Total Dissolved Solids,
mg/l Max 2100 2700 774.0
6 Residual Chlorine, mg/l >1.0 0.6 1.1
7 Turbidity, NTU <2 3.0 0.8
8 Total Suspended solids,
mg/l ≤10 28 6.0
ENVIRONMENT MANAGEMENT PLAN FOR THE ADDITION OF EASTERN CONNECTIVITY TUNNEL AT
KEMPEGOWDA INTERNATIONAL AIRPORT, DEVANAHALLI, BENGALURU, KARNATAKA
VIMTA Labs Limited, Hyderabad 46
AIR QUALITY MONITORING OBSERVATIONS
Date Location PM10
(µg/m3 PM2.5
(µg/m3) SO2
(µg/m3) NO2
(µg/m3) CO
(µg/m3)
6, 7 July, 2018 L & T Office (AAQM Station 1)
60
22
4.1
16
0.25
6, 7 July, 2018 South Gate (AAQM Station 4)
74
32
4.1
17
0.22
6, 7 July, 2018 Aster Gate (AAQM Station 8)
75
40
4.1
16
0.18
13, 14 July, 2018 Center of NSPR, South-East
end (AAQM Station 2)
71
24
4.3
12
0.18
13, 14 July, 2018 South Boundary, near factory
(AAQM Station 3)
84
46
4.1
14
0.25
13, 14 July, 2018 South Boundary, Dummanur
(AAQM Station 5)
68
30
4.3
16
0.21
20, 21 July, 2018 South Boundary, Mylanahalli
(AAQM Station 6)
74
38
4.5
15
0.21
20, 21 July, 2018 Near Pond 6 (AAQM Station
7)
64
33
4.2
14
0.26
30, 31 July, 2018 Alpha 2 (AAQM Station 9)
68
29
4.5
19
0.26
30, 31 July, 2018 BIAL STP (AAQM Station 10)
66
27
4.1
17
0.23
ENVIRONMENT MANAGEMENT PLAN FOR THE ADDITION OF EASTERN CONNECTIVITY TUNNEL AT
KEMPEGOWDA INTERNATIONAL AIRPORT, DEVANAHALLI, BENGALURU, KARNATAKA
VIMTA Labs Limited, Hyderabad 47
NOISE MONITORING OBSERVATIONS
AAI Begaluru, Noise Level Data
Month & Year Location Avg. Noise Level, dB (A) Leq
Day Time Night Time
July, 2018
a). East Gate 50.5 42.7
b). West Side 61.7 40.5
c). South Gate 48.2 41.3
d). Aster Gate 55.9 44.0