entso-e and cim

33
ENTSO-E and CIM CIM User Group meeting, Prague, 10-13 May 2011 Chavdar Ivanov, PhD Research and Development Advisor, ENTSO-E Secretariat

Upload: adem

Post on 25-Feb-2016

82 views

Category:

Documents


3 download

DESCRIPTION

ENTSO-E and CIM. CIM User Group meeting, Prague, 10-13 May 2011. Chavdar Ivanov, PhD Research and Development Advisor, ENTSO-E Secretariat. ENTSO-E is THE European TSO platform. Founded 19 December 2008 and fully operational since 1 July 2009 Represents 41 TSOs from 34 countries - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: ENTSO-E and CIM

ENTSO-E and CIM

CIM User Group meeting, Prague, 10-13 May 2011

Chavdar Ivanov, PhDResearch and Development Advisor, ENTSO-E Secretariat

Page 2: ENTSO-E and CIM

ENTSO-E is THE European TSO platform

• Founded 19 December 2008 and fully operational since 1 July 2009

• Represents 41 TSOs from 34 countries

• 532 million citizens served• 880 GW net generation• 305,000 Km of transition lines

managed by the TSOs• 3,200 TWh/year demand• 380 TWh/year exchanges

• Replaces former TSO organisations: ATSOI, BALTSO, RTSO, NORDEL, UCTE, UKTSOA

ENTSO-E and CIM | Chavdar Ivanov | 11 May 20110 | Page 2 of 33

Page 3: ENTSO-E and CIM

Key activities set out in Regulation 714/2009 (on cross-border electricity trade, part of the 3rd Internal Energy Market Package)• Deliver network codes • Deliver network plans European / regional view of system needs (Ten-Year

Network Development Plan “TYNDP”)• Deliver crucial aspects of market integration (“market coupling”)• R&D Plan (fully included in EEGI – European Electricity

Grid Initiative, part of the SET Plan)

Through its members deliver the infrastructure to:• enable markets to function, • secure energy supply, • meet climate change objectives through connecting RES

ENTSO-E has significant role in deliveringEuropean energy and climate change objectives

ENTSO-E and CIM | Chavdar Ivanov | 11 May 20110 | Page 3 of 33

Page 4: ENTSO-E and CIM

ENTSO-E: Organised to deliver a range of services

1- Research & Development Plan2- Monitoring and Knowledge Sharing

ENTSO-E and CIM | Chavdar Ivanov | 11 May 20110 | Page 4 of 33

Page 5: ENTSO-E and CIM

Network Codes: Process + content areas defined in Reg. 714/2009

Regulation714/2009

Planning, priorities

Framework Guidelines

Draft Code(s*) ACER Comitology

Main resp. EC ACER ENTSO-E ACER EC, MS ACER, E’E

Monitoring

6 months 12 months3 months ?

Network Codes (in twelve areas)Network connection Interoperability rulesBalancing incl. network-related reserve Capacity-allocation and congestion managementNetwork security and reliability TradingOperational procedures in an emergency TransparencyThird-party access Harmonized transmission tariff structures

(incl. locational signals and TSO compensation)Data exchange and settlement Energy efficiency regarding electricity networks

ENTSO-E and CIM | Chavdar Ivanov | 11 May 20110 | Page 5 of 33

Page 6: ENTSO-E and CIM

FWGL

Electricity Grid Connection

Grid connection requirements for generators

Grid connection requirements

for DSOs

Grid connection requirements

for end customers

Grid connection requirements for HVDC links

Grid connection procedures

Network Codes

Pilot network code: ACER & ENTSO-E

ENTSO-E and CIM | Chavdar Ivanov | 11 May 20110 | Page 6 of 33

Page 7: ENTSO-E and CIM

Ten-Year Network Development Plan - TYNDP

Sustainability

Competitiveness

Security of Supply

TYNDPPolicy Action

Assessment

Monitoring

EU Strategic Goals

Inform

Assist

Coordinat

eEvaluate

“ENTSO-E shall adopt a non-binding Community-wide ten-year network development plan”• Transparency• Decision making process• Networks/scenarios/generation outlook/resilience

TYNDP = Ten-Year Network Development Plan

ENTSO-E and CIM | Chavdar Ivanov | 11 May 20110 | Page 7 of 33

Page 8: ENTSO-E and CIM

44%mid term

56%long term

78%

22%

AC > 300 kV 29600 km 83%

17%

Total projects 42100 km

DC 9600 km

AC < 300 kV 2900 km

upgrade

new

TYNDP summary

The TYNDP projects represent ~14% of existing lines

€ 23 to 28 billion for grid expansions

for the first five years

ENTSO-E and CIM | Chavdar Ivanov | 11 May 20110 | Page 8 of 33

Page 9: ENTSO-E and CIM

R&D Plan:

Cluster 1: Pan-European Grid architectureNovel approaches to develop a pan-European Grid

Cluster 2: Power technologiesAffordable technologies to make the transmission system more clever and flexible

Cluster 3: Network management and controlCritical building blocks to operate the interconnected transmission system in real-time and reliably

Cluster 4: Market rulesMarket simulation techniques to develop a single European electricity market

SMA

RT

GR

IDS

Func

tion

al le

vel

Level 1: Smart pan-European

Functional projects

T1. A toolbox for new network architecture assessment

T2. Tools to analyze the pan-European network expansion options

T14.Innovative approaches to improve the public acceptance of overhead lines

T3. Demonstrations of power technologies for more network flexibility

T4. Demonstrations of power technologies for new architectures

T5. Demonstrations of renewable integration

T6. Tools for pan-European network observability

T7. Tools for coordinated operations with stability margin evaluation

T8. Improved training tools for improved coordination

T9. Tools for pan-European network reliability assessment

SMART GRIDS MODEL

T10. Tools for pan-European balancing marketsT11. Advanced tools for congestion managementT12. Tools for renewable market integration of

active demandT13. Tools to study market integration of active

demand

Research and innovation clusters: Smart grids and cooperation with DSOs play a major part in the R&D Plan, partly because of the balancing challenge

ENTSO-E and CIM | Chavdar Ivanov | 11 May 20110 | Page 9 of 33

Page 10: ENTSO-E and CIM

European Electricity Grid Initiative: Program budget - summary

Total program cost estimation is around € 2 bn in 9 years (2010 – 2018)

The cost estimation of the priority actions that need to start in 2010-2012 is around € 1 bn

The results are beneficial for the whole European energy value chain, requiring a comprehensive funding that must involve EC, the Member States, the regulators and industry.

Roadmap

Priority projectscosts (€M)

Start 2010-12

Other projects costs (€M)

Start 2013-Total costs (€M)

Transmission/distribution coordination

68 162 230

Transmission networks 108 452 560Distribution networks 830 370 1,200

Total 1,006 984 1,990

ENTSO-E and CIM | Chavdar Ivanov | 11 May 20110 | Page 10 of 33

Page 11: ENTSO-E and CIM

ENTSO-E and CIM

ENTSO-E needs and wants to have only one data exchange

format

ENTSO-E organizes yearly Interoperability tests to ensure

right and stable development

The Roadmap for the implementation of next updates of the

ENTSO-E CIM Profile avoids frequent changes in the

ENTSO-E CIM Profile

ENTSO-E and CIM | Chavdar Ivanov | 11 May 20110 | Page 11 of 33

Page 12: ENTSO-E and CIM

Current ENTSO-E CIM/XML Profile

Current ENTSO-E Profile is the profile tested in UCTE IOP in March 2009 in Paris. THIS IS THE PROFILE THAT MUST BE IMPLEMENTED BY ENTSO-E MEMBERS. Updates of this profile should follow the approved Roadmap

Proposals for changes are welcome and will be discussed within ENTSO-E, IEC and will be tested in the ENTSO-E IOP once agreed among IOP participants.

Current ENTSO-E CIM/XML profile is published on ENTSO-E web site (CIM part: http://www.entsoe.eu/index.php?id=237)

ENTSO-E Boundary Set is available here: https://www.entsoe.eu/resources/cim/profiles/ A draft version of the 2nd edition of the ENTSO-E CIM/XML profile was

developed for the ENTSO-E interoperability test in July 2010. It is also available on the ENTSO-E web site (https://www.entsoe.eu/fileadmin/user_upload/_library/resources/CIM/Interoperability_Tests/ENTSO-E_CIM_Model_Exchange_Profile_v2_draft_7_IOPversion_12July2010.zip)

ENTSO-E and CIM | Chavdar Ivanov | 11 May 20110 | Page 12 of 33

Page 13: ENTSO-E and CIM

Roadmap for future implementation of CIM

The aim: to structure the implementation effort. No yearly implementation. An exception could be only if a change is introduced which is critical for ENTSO-E processes

The implementation process is foreseen to last one year. On regular basis the implementation effort is foreseen every three years, if

necessary. Next versions of the ENTSO-E Profile have to be approved by System

Development Committee (SDC). In case of changes that affect operational data, System Operations Committee (SOC) decision is also required.

SDC or SDC&SOC decision ensures one year implementation period. Coming into force date is fixed and mandatory for TSOs

EXAMPLE: if the updated version of the 2nd ENTSO-E Profile for IOP 2011 is OK:- Approval by SDC and SOC- 2012 implementation year- Jan 2013 ENTSO-E switches to 2nd edition of the profile for all exchanges.

ENTSO-E and CIM | Chavdar Ivanov | 11 May 20110 | Page 13 of 33

Page 14: ENTSO-E and CIM

ENTSO-E CIM Interoperability Tests – 11 July 2011 (5 days) Registered vendors

BCP Busarello + Cott + Partner AG (NEPLAN) Open Grid Systems (Cimphony) Intercompro AG (ISPEN) TIBCO (IntelliEDGE) SISCO (UIB Adapter for PI-AF and UIB Core) Siemens Power Technologies International (PSS/ODMS) GE Energy (PSLF) EKC&DMS (Transmission Network Analyzer) RTE (Convergence) FGH (INTEGRAL7) Tractebel and RTE (EUROSTAG) Ventyx/ABB (Network Manager SCADA/EMS) CESI (SPIRA; CRESO; SICRE) EPS (Power System Analyzer, PSA) PSI AG (PSIcontrol) DIgSILENT GmbH (PowerFactory 14.1) EDF R&D (GEDEON Database; CIMclipse; CIM-ENTSO-E Converters) Alstom Grid (e-terrasource) GE Energy Services (Enterprise Gateway) NexantIn addition to the above vendors, ABB (BMS CIM Explorer) requested to participate in the preparation leading up to the interoperability test. Zemiren (CimContextor) will participate in the test and will support preparation of profiles to be used in the test.

ENTSO-E and CIM | Chavdar Ivanov | 11 May 20110 | Page 14 of 33

Page 15: ENTSO-E and CIM

ENTSO-E IOP 2011 – test topics

• Interoperability using the last Unified Modeling Language (v15 + Dynamics + any modifications agreed among test participants) – new draft of the 2nd edition of the profile

• Interoperability using 1st and 2nd editions of the profile, including naming convention

• Model Authority Sets (MAS), file headers, model assembling process• Incremental exchange• Exchange of short-circuit data according to IEC 60909• Exchange of dynamic models (standard models, user-defined models,

proprietary models) – Further developments in the part of dynamics are not expected due to lack of the time

• Diagram layout – 61970-453; GIS data• Exchange “operations to planning” – The goal: detailed model to be

exported to fit to ENTSO-E profile and imported by planning applications.• ENTSO-E Equipment profile is the 452 one. “operational to operational

exchange can also be demonstrated”

ENTSO-E and CIM | Chavdar Ivanov | 11 May 20110 | Page 15 of 33

Page 16: ENTSO-E and CIM

CIM extensions needed

For the IOP 2011 • additional attributes to fully cover IEC 60909 short circuit data exchange.

Discussion with WG13 – next week

For 2012:• HVDC modelling• Extension of Dynamics package

ENTSO-E and CIM | Chavdar Ivanov | 11 May 20110 | Page 16 of 33

Page 17: ENTSO-E and CIM

Model assemblingTSO A: one MAS; set of files - zipped

TSO B: one MAS; set of files - zipped

TSO N: one MAS; set of files - zipped

Boundary MAS (equipment and topology files) - zipped

Software for power flow/simulations

1. Import – all MAS (TSOs and Boundary)2 . Set SvInjection for tie-lines to zero3 . Run power flow/simulations4 . User modifies assembled model including data in the individual MAS, if

necessary and runs power flow/simulations5 . Export of assembled model – per MAS including all modifications introduced

using the tool

2nd step -Import

Assembled power system model – one zip file; multiple MAS representing TSOs models and boundary MAS

3rd step - Export

TSO A: one MAS; equipment, topology, dynamics, diagram files

Boundary MAS – equipment and topology files

A State variables file exported by the merging MAS

TSO N: one MAS; equipment, topology, dynamics, diagram files

1st step-Import

Page 18: ENTSO-E and CIM

ENTSO-E IOP Report 2010

Finalized and published in mid August 2010

Available on the ENTSO-E web site: https://www.entsoe.eu/index.php?id=240

Identified CIM issues were listed in the final report and submitted to IEC WG13 for further discussion. CIM15 resolves most of the issues

ENTSO-E and CIM | Chavdar Ivanov | 11 May 20110 | Page 18 of 33

Page 19: ENTSO-E and CIM

ENTSO-E exchanges in CIM – migration process to CIM

Two main ENTSO-E processes are subject to CIM migration

System development • Still in migration period. • First data exchanges in CIM

started in February 2010.

DACF process• The goal is to complete migration stage

by the end of 2011• First test exchanges started on 8 June

2010 and finished in the end of August 2010

• Now the second stage of tests for DACF is running. TSOs are exchanging 6 files per day in CIM (one day in a week) . The goal is to verify the procedures and test Communication channels.

• TSOs are building their converters to CIM (operational systems to CIM)

“Planning exchanges” – required for TYNDP, regional initiatives, i.e. EU 3rd Energy Package

Day-Ahead Congestion Forecast process – stable exchange needed to support system operation

ENTSO-E and CIM | Chavdar Ivanov | 11 May 20110 | Page 19 of 33

Page 20: ENTSO-E and CIM

ENTSO-E exchanges in CIM – migration process to CIM

Why after two successful IOPs (March 2009 and November 2009) the real interoperability with 1st edition of the ENTSO-E CIM profile is still a very difficult task?

ENTSO-E and CIM | Chavdar Ivanov | 11 May 20110 | Page 20 of 33

Page 21: ENTSO-E and CIM

ENTSO-E exchanges in CIM – Lessons learned

Testing with real data is necessary. IOP test cases cannot fully represent all modelling approaches

More complex test models are needed. The role of CIMug and IEC in test models preparation is to be discussed

Some vendors introduced post IOP changes which made real interoperability not possible.

More strict rules on interoperability are needed to ensure that commercial products are really fully compliant with the Profile

Intensive communication between vendors and users is necessary to ensure right modelling and usage of right tools

Vendors should demonstrate their readiness to support ENTSO-E Profile

ENTSO-E and CIM | Chavdar Ivanov | 11 May 20110 | Page 21 of 33

Page 22: ENTSO-E and CIM

ENTSO-E exchanges in CIM – What ENTSO-E is doing .....

To reach interoperability with 1st edition of the ENTSO-E Profile:

TSOs are kept informed on the efforts to be done: ENTSO-E Committees meetings, various workshops

Actions have been taken to improve communication between TSO and vendors

ENTSO-E Secretariat is contacting involved vendors on daily basis To ensure future interoperability and improve

business process: ENTSO-E IOP 2011 will test both 1st and 2nd edition of the profile Strict validation of the naming convention will be done during IOP 2011 Vendors will be asked to export test models that they already have and

demonstrate interoperability The 2nd edition of the profile is fully based on the 452, 456, 453, 552, etc.

standards. Exchange flexibilities are improved. Open issues are clarified ENTSO-E will implement a Network Modelling Database

ENTSO-E and CIM | Chavdar Ivanov | 11 May 20110 | Page 22 of 33

Page 23: ENTSO-E and CIM

Overall concept of Power System Database

Network Modelling Database (NMD) as a part of the Power System Database concept

ENTSO-E and CIM | Chavdar Ivanov | 11 May 20110 | Page 23 of 33

Page 24: ENTSO-E and CIM

Network Modelling Database – time schedule, objectives

Preparation work and ENTSO-E decisions in 2010 EU tender started in Dec 2010; offers assessment is ongoing Contract expected in July 2011; NMD fully operational Jan 2012.

Objectives: To adapt ENTSO-E business process to an automatic CIM based data

exchange To have a system that supports the official ENTSO-E CIM profile and

supports development of next editions of the profile. In Jan 2012 NMD should support 1st and the 2nd (July 2011) editions of the profile

Provide automatic model assembling functionalities based on the ENTSO-E CIM profile, i.e. MAS, boundary sets.

Allow users to maintain TSO, regional, pan-European models; store scenarios; import/export full, partial, differential files

Allow specific queries, etc.

ENTSO-E and CIM | Chavdar Ivanov | 11 May 20110 | Page 24 of 33

Page 25: ENTSO-E and CIM

Common CIM Tools used by TSOs

CIMdesk Validation, visualization and editing tool developed by PowerInfo LLC, US Provides users with possibilities for direct editing of CIM files and

graphical visualization It is not related to the migration process. It will be used and maintained as

long as CIM /XML format is used Maintenance contact has been prolonged. A re-licensing rules were

agreed with ENTSO-E. Non ENTSO-E members can buy a license of CIMdesk. Requests should be addressed to PowerInfo LLC.

Migration converter Developed by EDF R&D, FR Converts from UCTE CIM to UCTE DEF (current version: version 02) and

vice versa To be used during the migration stage; useful only for DACF exchanges

in the RG Continental Europe Maintenance contract was prolonged until 31 Dec 2011.

ENTSO-E and CIM | Chavdar Ivanov | 11 May 20110 | Page 25 of 33

Page 26: ENTSO-E and CIM

CIM and ENTSO-E web site (www.entsoe.eu)

ENTSO-E and CIM | Chavdar Ivanov | 11 May 20110 | Page 26 of 33

Page 27: ENTSO-E and CIM

ENTSO-E CIM in the CIMug web site

ENTSO-E and CIM | Chavdar Ivanov | 11 May 20110 | Page 27 of 33

Page 28: ENTSO-E and CIM

Additional slides WG16 topics)

ENTSO-E and CIM | Chavdar Ivanov | 11 May 20110 | Page 28 of 33

Page 29: ENTSO-E and CIM

Development and Implementation of CIM in ENTSO-E

November 2007: UCTE agreed to launch an initiative for development of new UCTE XML based data exchange format that will considered as a standard for exchange of load flow and dynamic data and allows performing of all kind of analyses as follows: steady state, unbalanced short circuit and dynamic analyses.

AhG UCTE format was established. May 2008: UCTE Steering Committee approved

Cooperation of AhG “UCTE format” with international organizations aiming at inclusion of UCTE needs into international standard

UCTE participation in EPRI project (CIM for Dynamics) Summer 2008: UCTE joins the EPRI Project and creates a liaison with

IEC TC57. UCTE CIM TF is established during CIM user Group meeting in Vasteras (June 2008)

ENTSO-E and CIM | Chavdar Ivanov | 11 May 20110 | Page 29 of 33

Page 30: ENTSO-E and CIM

Development and Implementation of CIM in ENTSO-E

January 2009: UCTE Steering Committee approved Migration Policy. Priority of migration of “planning” models is given.

March 2009: UCTE IOP. Successful interoperability among IOP participants

May 2009: UCTE Profile finalized and submitted to IEC July 2009: ENTSO-E is fully operational: new work organization

related to CIM is implemented All contracts and agreements have been transferred from UCTE

to ENTSO-E. ENTSO-E has liaisons with IEC TC57 (WG13 and WG16) and it is a member of EPRI project “CIM for Dynamics”, etc.

July 2009: CIMdesk and Migration Converter provided to ENTSO-E members

Nov 2009: First IOP CIM for Dynamics. The concept is proved

ENTSO-E and CIM | Chavdar Ivanov | 11 May 20110 | Page 30 of 33

Page 31: ENTSO-E and CIM

Development and Implementation of CIM in ENTSO-E

July 2010: ENTSO-E IOP “CIM for System Development and Operations” 2010. Draft version of the second edition of the ENTSO-E CIM Profile.

ENTSO-E and CIM | Chavdar Ivanov | 11 May 20110 | Page 31 of 33

Page 32: ENTSO-E and CIM

Important ENTSO-E decisions

1 Oct 2009: System Development Committee (SDC) agreed that CIM/XML will be used in ENTSO-E data exchanges related to SDC activities (system studies, planning data exchanges)

2 Sep 2009: System Operations Committee (SOC) recommends: Regional Group Continental Europe: The change from the UCTE format to CIM

was decided by the UCTE Steering Committee. The goal is to switch to the new format before the end of 2010 at the latest (DACF exchanges)

Other Regional Groups to consider implementation of the standard with an aim of the pan-European harmonization

2 Dec 2009: SDC and SOC: Approved the roadmap for future development and implementation of updates of the CIM/XML format

11 Dec 2009: SDC, SOC and Market Committee: Approved ENTSO-E CIM Interoperability tests

Nov 2010: SDC, SOC decision on the second edition of the ENTSO-E CIM profile. Implementation postponed for after IOP 2011.

ENTSO-E and CIM | Chavdar Ivanov | 11 May 20110 | Page 32 of 33

Page 33: ENTSO-E and CIM

ENTSO-E Secretariat serves as a central function of coordination, maintenance and support of Common Information Model (CIM) related issues and therefore, it

is the interface to international organizations

- Maintenance ENTSO-E CIM tools;

- contacts with providers

Requests that concern CIM must be submitted to Secretariat

ENTSO-E Data Expert Group

System Development Committee

Operations Committee Market Committee

WGs defining needs

International organizations: IEC, EPRI, CIMug, …

- Liaisons, - Submitting ENTSO-E needs, - - Participation in the discussion, - etc

- Discussion on Committees/WGs requests;

- Information on IEC opinion; - Possible solutions - etc.

CIM toolsSecretariat

WGs defining needs

WGs defining needs

WG

NM&D WG EDI

SG NMFT in RG CE

CIMdesk; Migration Converter

ENTSO-E and CIM | Chavdar Ivanov | 11 May 20110 | Page 33 of 33