EN/STI investigations during LS1in TDC2 and TCC2

TDC2:-TCSC (collimator) to be replaced if …

TCC2:-Targets Stations T2-T4-T6

*Monitors and Target equipment*Cabling*Flow meters

Annual maintenance

To keep in mind for each operation: waste, contamination

Page 2: EN/STI investigations during LS1 in TDC2 and TCC2 TDC2: -TCSC (collimator) to be replaced if … TCC2: -Targets Stations T2-T4-T6 *Monitors and Target equipment

TCSC in TDC2To be replaced only if budget is allocated and dripping acid is stopped from falling onto the TCSC!!

Needs:-RP-Transport-VSC-STI

Conflicts:-Large radioactive vessel to transport

Page 3: EN/STI investigations during LS1 in TDC2 and TCC2 TDC2: -TCSC (collimator) to be replaced if … TCC2: -Targets Stations T2-T4-T6 *Monitors and Target equipment

TARGET Stations T2-4-6 in TCC2Moniteur TBIU BAC Moniteur TBID

Moteur blindage mobile

Patch Panel

Ventilateur

Switchs Blindage mobile

Page 4: EN/STI investigations during LS1 in TDC2 and TCC2 TDC2: -TCSC (collimator) to be replaced if … TCC2: -Targets Stations T2-T4-T6 *Monitors and Target equipment

Monitors and Target to replace

Needs:-RP-Transport-STI

Conflicts:-Large amount of radioactive assemblies to transport (x9)

Only if BI budget accepted!

Page 5: EN/STI investigations during LS1 in TDC2 and TCC2 TDC2: -TCSC (collimator) to be replaced if … TCC2: -Targets Stations T2-T4-T6 *Monitors and Target equipment

Cabling on Targets to replace

Needs:-RP-BI-VSC-STI

To replace

To remove

To keep

Page 6: EN/STI investigations during LS1 in TDC2 and TCC2 TDC2: -TCSC (collimator) to be replaced if … TCC2: -Targets Stations T2-T4-T6 *Monitors and Target equipment

Flow meters to replace on T2-4-6T2-T4

T6

Needs:-RP-CV-STI

Page 7: EN/STI investigations during LS1 in TDC2 and TCC2 TDC2: -TCSC (collimator) to be replaced if … TCC2: -Targets Stations T2-T4-T6 *Monitors and Target equipment

Annual maintenanceAccès Ligne Direc. Elec. Equipement Déplacement Fin de course Refroidissement Vide Remarques Hor. Vert. Hor. Vert. Débit Temper. BA 80 TCC2 D BA 80 BAC T2 / / / / / TBIU T2 / / / / TBID T2 / / / / Eau T2 / / / / / Ventilateur T2 / / / / / / Blindage D T2 / / / / / Blindage G T2 / / / / /

BA 80 TCC2 D BA 80 BAC T4 / / / / / TBIU T4 / / / / TBID T4 / / / / Eau T4 / / / / / Ventilateur T4 / / / / / / Blindage D T4 / / / / / Blindage G T4 / / / / / BA 80 TCC2 D BA 80 BAC T6 / / / / / TBIU T6 / / / / TBID T6 / / / / Eau T6 / / / / / Ventilateur T6 / / / / / / Blindage D T6 / / / / / Blindage G T6 / / / / / Palan pont / / / / / TDC2 G TCSC 211708 / / / / / / TDC2 G TCSC 220436 / / / / / /